Sunty Development Co., Ltd 2018 Investor Conference

==> picture [721 x 136] intentionally omitted <==

Disclaimer Statement

  • This presentation contains forward looking statements which are estimated based on the current status of Sunty Development Co., LTD and general economic conditions. The forward looking statements involve certain risks and uncertainties that could cause actual results to differ materially from those contained in the forward looking statements. Potential risks and uncertainties include such factors as general economic conditions, foreign exchange fluctuations, rising costs of raw materials, competitive products and pricing pressures and regulatory developments.

  • Forward-looking statements involve significant risks and uncertainties, should not be read as guarantees of future performance or results, and will not necessarily be accurate indications of whether or not such results will be achieved.

  • Sunty Development Co., LTD expressly disclaims any obligation to review, update or correct these materials after the date thereof. Sunty Development Co., LTD may update, amend, supplement or otherwise alter the information contained in such materials or other

  • any by subsequent presentations, reports, filings, means without notice. This presentation may not be stored, copied, distributed, transmitted.

==> picture [721 x 136] intentionally omitted <==

Sunty Development Co., Ltd

==> picture [261 x 180] intentionally omitted <==

Major business Construction Industry Date of Company March 1993 Establishment December 2014 Date of Listing (Co. Code 3266) Capital NT$3.52 Billion Chairman Kuan-Chen Mai General Manager Pou-Ying Chien Employees 69

==> picture [261 x 179] intentionally omitted <==

Unit: Thousands of NT$

==> picture [721 x 393] intentionally omitted <==

----- Start of picture text -----

Year 2018
2016 2017
Item (Up to Sep 30, 2018)
Sales Revenue 1,481,603 1,461,374 2,061,964
Gross Profit 230,597 132,042 417,677
Operating Income(Loss) (14,931) (125,518) 188,232
Net Income(Loss) (49,811) (44,865) 150,405
Earnings Per Share(NT) 0.12 0.08 0.49
----- End of picture text -----

==> picture [721 x 136] intentionally omitted <==

Taipei City New Taipei City Taoyuan City

Focus on the Greater Taipei area Exquisite Construction

==> picture [721 x 136] intentionally omitted <==

Projects on line

==> picture [721 x 457] intentionally omitted <==

----- Start of picture text -----

Sunt Li-Fan
y g
2.2 billion
28-39 in
p g
Pre-sale
Sunt Pen - Chen
y g g
1.12 billion
17-56 in
p g
Guanghuan
New Sale after-
Era
construction
1.5 billion
27-88 in
p g Sunt Chen -Jun
y g g
Sale after-
2 billion
construction
19-28 in
p g
New Sale after-
construction
----- End of picture text -----

Project pipelines

==> picture [721 x 457] intentionally omitted <==

----- Start of picture text -----

Sunty Kuo-Yung
2.8 billion
18-45 ping Sunty Hao-Hao
Pre-sale 2.2 billion
18-29 ping
Pre-sale
Sunty Wen-Hui
0.8 billion
Yixian Project
25-49 ping
6 billion
New Sale after-
26-89 ping
construction
Pre-sale
----- End of picture text -----

Sunty Wen-Hui Sunty Wen-Hui
Project Sunty Wen-Hui
Site Location Banqiao Dist.
New Taipei City
The Lin’s Family Man
sion and Garden
Selling Mechanism New Sale after-constr
uction
t Ridtil ditit
Product
Planning
ype esena src
size 25~63 ping
unit 77 (all 129)
floor B4-15F
Launch Date Jan. 2019
Construction

Commencement Date
Mar. 2016
Completion Date Nov. 2018
Sunty Kuo-Yung Sunty Kuo-Yung
Project Sunty Kuo-Yung
Site Location Yonghe Dist.
New Taipei City
MRT Dingxi Station
Selling Mechanism Pre-sale
type Residential district
Product
Planning
size about 24~49、15~33 ping
unit about 97、54(all)
floor B4-15、B4-18
Launch Date Mar. 2019
Construction
Commencement Date
Dec. 2019
Completion Date Aug. 2023
Sunty Hao-Hao Sunty Hao-Hao
Project Sunty Hao-Hao
Site Location Zhongshan Dist.,
Taipei City
MRT Xingtian Temple
Station
Selling Mechanism Pre-sale
type Market
Product
Planning
size about 18~29 ping
unit about 99 (all 102)
floor B4-15
Launch Date Jun. 2019
Construction Feb 2020
Commencement Date .
Completion Date Jul. 2023
Yixian
Urban Renewal Project
Yixian
Urban Renewal Project
Project Yixian
Urban Renewal Project
Site Location Xinyi Dist., Taipei City
Taipei City Hall
Selling Mechanism Pre-sale
type Commercial district、
Product
Planning
Residential district
size about 26~89 ping
unit about 50 (all 170)
floor B7-31
Launch Date Jun. 2019
Construction
Commencement Date
May 2020
Completion Date Sep. 2024

==> picture [721 x 541] intentionally omitted <==

----- Start of picture text -----

Jinlong Rd. Project
0.5 billion
Oct. 2017
start construction
Songjiang
Changchun Project
0.7 billion
Oct. 2017
start construction
----- End of picture text -----

==> picture [721 x 541] intentionally omitted <==

----- Start of picture text -----

Dexing E. Rd.
Project
4 billion
Yongji Rd.
Project
6 billion
----- End of picture text -----

Developing Project

==> picture [721 x 412] intentionally omitted <==

----- Start of picture text -----

Zhongli Project
1.2 billion
Jul. 2021
start construction
----- End of picture text -----

==> picture [721 x 541] intentionally omitted <==

----- Start of picture text -----

The End