20 March 2014
Heemskirk Tin Diamond Drilling Commences
Stellar Resources is pleased to announce the commencement of diamond drilling at the Heemskirk Tin Project.
- Two diamond drilling contractors have been engaged to complete a combined program of 17 holes totalling 4,740 metres.
- One rig has commenced drilling at Heemskirk and the other at St Dizier.
- The overall objective is to improve project economics following on from a positive PFS.
- Drilling milestones are shown in Table 1 with targets identified in long-section in Figures 1, 2 and 3.
- Specific objectives of each phase of the drilling program are:
Heemskirk
- Increase the size of the high grade zone to the east of Lower Queen Hill;
- Explore the Golf Course target 300m to the south of Severn;
- Expand the high grade zone along the upper edge of Severn;
- Extensional drilling of Severn at depth;
plans to become Australia's second largest producer of tin.
St Dizier
Expand the known St Dizier Mineral Resource of 2.26mt @0.61% tin, 0.04% tungsten and 23.0% iron (released to the market on 12 March 2014);
Stellar Resources (SRZ) is an exploration and development company with assets in Tasmania and South Australia. The company is rapidly advancing its high-grade Heemskirk Tin Project, located near Zeehan in Tasmania, and
Explore the skarn zone 2.5 km to the east of St Dizier.
ASX Code: SRZ
About Stellar:
ABN 96 108 758 961 Level 17, 530 Collins Street Melbourne Victoria 3000 Australia
Telephone +61 3 9618 2540 Facsimile +61 3 9649 7200

| Site | Drill Holes | Metreage | Drilling | Assay |
|---|---|---|---|---|
| Completion | Completion | |||
| St Dizier | 7 | 1240 | 30-May | 27-Jun |
| Queen Hill Lower | 3 | 1200 | 30-May | 27-Jun |
| Golf Course | 2 | 400 | 27-Jun | 31-Jul |
| Severn Upper | 3 | 900 | 29-Aug | 26-Sep |
| Severn Lower | 2 | 1000 | 31-Oct | 21-Nov |
| Totals | 17 | 4740 | 31-Oct | 21-Nov |
Table 1: Estimated Drilling Schedule

Figure 1: Queen Hill Long-Section Showing Planned Diamond Drilling Targets (Mine Grid)
140031SRL.doc
2


Figure 2: Severn Long-Section Showing Planned Diamond Drilling Targets (Mine Grid)

Figure 3: St Dizier Long-Section Showing Planned Diamond Drilling Targets (GDA94)

Competent Person Statement
The drill and exploration results reported herein are based on information compiled by Mr R K Hazeldene (Member of the Australasian Institute of Mining and Metallurgy and Member of the Australian Institute of Geoscientists) who is a Consultant of the Company. Mr Hazeldene has sufficient experience relevant to the style of mineralisation and type of deposits being considered to qualify as a Competent Person as defined by the 2012 Edition of the Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves (the JORC Code, 20012 Edition). Mr Hazeldene consents to the inclusion in the report of the matters based on his information in the form and context in which it appears.