Luka Koper Group
Business performance 2010 – 2017 and key investments from 2014 to present

Luka Koper Group
Market position and cargo throughput

MARKET POSITION AND THROUGHPUT
- Record achievements related to maritime throughput.
- Top container terminal in Adriatic.
- Among top three largest car terminals in the Mediterranean.
- The first port for Austria.
- The first container port for Hungary and Slovakia.
- Achievement of new reference businesses which bring further opportunities for new business.

Luka Koper Group
Financial indicators

Net sales revenues (EUR)


EBIT (EUR)

EBITDA (EUR)



EBITDA margin


ROE


Net profit (EUR)


Investments (EUR)

Key investments from 2014 - present Luka Koper – Port of Koper

Luka Koper – Port of Koper Accomplished investments


Luka Koper
Container terminal investments
Dredging to -15 meters

Investment value: 5,8 M EUR Duration: 3 years


Stacking areas behind 7.c berth (realization in 2013/2014)
6.840 m2 of new stacking areas Investment valuee: 8,62 M EUR Duration: 8 months
Stacking areas behind 7.c berth – embankment (realization in 2014/2015)
Investment value: 0,56 M EUR Duration: 3 months

Depot for empty containers, phase A: consolidation of storing and handling areas (2015)
Investment value: 1,66 M EUR Duration: 5 months


Arrangement of areas for full containers (2015/2016)
Investment value: 0,3 M EUR Duration: 2 months
Extension of full containers block B5 (2016)
Investment value: 0,47 M EUR Duration: 2 months

Construction of rail tracks 21a,b,c and railway bridge (2015)
Investment value: 3,68 M EUR Duration: 7 months

Construction of RMG rails, 740 meters of length (2016)
Investment value: 4 M EUR Duration: 9 months



Two super post-panamax STS cranes
24 rows of outreach Delivery in april 2017 Investment value: 18,1 M EUR Duration: 1,5 years

Two new RMG cranes for wagon loading/unloading
Investment value: 6,1 M EUR Duration: 1,5 years

Seven new E-RTG cranes
Investment value: 12 MIO EUR Duration: 1,5 year

Reconstruction and enlargement of existing main port gate
Moving of parking place gate: Investment value: 65.000 EUR Duration: 3 months
Enlargement of the gate and offices: Investment value: 200.000 EUR Duration: 3 months




Luka Koper
Liquid bulk terminal investments
Shore tanks for fuels on Pier II, total capacity 60.000 m3 (3 x 20.000 m3), accomplished in 2016
Investment value: 12,7 M EUR Duration: 1,5 years

Truck loading station no. 2
Investment value: 1,6 M EUR Duration: 5 months




Luka Koper
Car terminal investments
Asphalted landfills at front of Pier II, total 33.270 m2 of storing areas

throughput in 2016
22 million tons
Investment value: 2 M EUR Duration: 1 year



Luka Koper
Environmental permit for Ankaran reclamation area
Environmental permit for Ankaran reclamation area

Investment value: 64.000 EUR Duration: 2 years

Luka Koper – Port of Koper PENDING INVESTMENTS


Luka Koper
Contianuation of investments in the Container terminal
Reorganization of container blocks, phase 1 and 2 (2016/2017) Investment value: 3,75 M EUR
Depot for empty containers including sevice facility (2016/2017) Investment value: 2,8 M EUR


Extenstion of Pier I
- 1st phase: quayside extension (98,5 m) and southern part of stacking areas (24.830 m2)
- 2nd phase, after 2020: new quayside (341 m and stacking areas 53.185
Estimated investment value of phase 1: 35 - 40 M EUR



Luka Koper
Water management arrangements of Ankaran margin canal
Project documentation ofr the 1st phase of the arrangement of the Ankaran's margin canal Investment value: 61.000 EUR
Duration: 110 days


Luka Koper
Dry Bulk terminal investments
Warehouse for cereals/grains, 16.000 m2 total capacity
Investment value: 9,3 M EUR Duration: 1 year


Luka Koper
Strategic corporate documents

Strategic documents
- Strategic Business Plan 2016 2020
- Business Strategy until 2030
- Strategic Business Plan 2020 with orientations until 2030 (Masterplan)
- Strategic environment development until 2030
- IT strategy
- Purchase policy

Luka Koper – Port of Koper
Other achievements

Other corporate management achievements
- Revised risk management system in 2015 and expanded to the level of the Group's subsidiaries in 2016
- successful external assessment of internal audit in 2015
- 2016: adopted Strategy of corporate integrity and revised Code of ethics,
- the management and employees sign the declaration to the provisions of the Code of Ethics
- Guidance on acceptance of gifts adopted in 2016
- adopted Rules of procedure of proxy for corporate integrity,
- Established a system for violation of corporate integrity reporting,
- Benchmarking analysis.

Other achievements on the enviroment protection and work safety areas
- European Seaport Organization (ESPO) Award 2014 for the most innovative environment projects »No waste, just resources!«.
- 2014: organized first environment conference together with the local community an effective and transparent presentation of present and future environment-related projects.
- In November 2015, the European Commission awarded Luka Koper, d.d. a special recognition in the field of environmental management. As a national pioneer in this field we have maintained the EMAS certificate for the seventh year.
- New heating/cooling systems for buildings based on renewable sources (biomass from the Timber terminal, heat pumps).
- Extension of EMAS registration in 2016 for another 3 years.

Other achievements on the enviroment protection and work safety areas
- 2016: bronze award of the Chamber of commerce and industry of Slovenia for the innovative project of transforming marine sediments to bricks.
- Replacement of existing lighting with modern and energy efficient LED lighting.
- Delivery of first e-RTG cranes (Electrifies Rubber Tired Gantries) to decrease energy costs and dust/noise emissions.
- Established SCADA energy consumption management system within the framework of the EU project GreenBerth.
- Creation of a permanent working body with representatives of the Municipality of Koper and Ankaran Municipality aiming to support the development plans of the company.
- Installation of the best available technology to improve safety at work.

EU projects
- 8,44 millions EUR of granted fund, of which 6,28 million EUR were obtain during 2014 – 2016 period (3,13 million EUR in 2016 alone).
- According to the 8 already approved projects in progress and 4 in the final stages of reporting, the company is still able to draw additional 7,94 million EUR of funds,
- 3 new projects approved in 2015 2016 with the anticipated value of 11,81 million EUR (possibility to draw 3,63 million EUR of funds) for facilities related to containers and cars segment.
- A new EU project was approved in January 2017, the 42nd for Luka Koper, d.d.

Other achievements
- 2014: signed contract for a long-term loan of 36 million EUR with the European Investment,
- 2016: signed contract for a long-term loan of 28 million EUR with the Banka Koper,
- 2016: Dun & Bradstreet credit rating 5A1