Aker Solutions Wins Bid for Ormen Lange Onshore Scope

Aker Solutions Wins Bid for Ormen Lange Onshore Scope

December 21, 2020 - Aker Solutions has been awarded a letter of intent from

Norske Shell for the Ormen Lange Phase 3 (OLP3) onshore project. The scope is to

integrate the wet gas subsea compression system with the Nyhamna onshore gas

plant in Norway. Subsea compression will enable increased recovery from the

Shell-operated Ormen Lange field. Aker Solutions' scope includes a 500-metric

-ton module which will be fabricated at the company's yard in Egersund, Norway.

The contract will have a value of approximately NOK 600 million.

The delivery will include both engineering, procurement, construction and

installation (EPCI). The awarded contract is a continuation of the front-end

engineering and design (FEED) delivered by Aker Solutions. The contract is

called off under an established long-term frame agreement for Nyhamna brownfield

modifications. Aker Solutions has been present at Nyhamna since start of the

development in 2004 and the award is a testimony to the relationship between

Aker Solutions and Norske Shell.

The Nyhamna plant outside Molde in Mid-Norway receives gas via underwater

pipelines from several offshore gas fields, including Ormen Lange. Nyhamna is

operated by Gassco, with Shell as the technical service provider.

"Aker Solutions has a global business with supporting customers in maintenance

and modifications of offshore installations and onshore industrial facilities.

For the new scope, we will combine our expertise on what is best practice for

safe and cost-effective project execution with our extensive knowledge of the

plant at Nyhamna," said Linda Litlekalsøy Aase, executive vice president,

electrification, maintenance and modifications at Aker Solutions.

Pre-execution work will start during first half of 2021. Pending final

investment decision for the OLP3 project and confirmation from Norske Shell

later in 2021, the work will progress into the execution phase. The engineering,

procurement and project management will mostly be executed from Aker Solutions'

offices in Stavanger and Kristiansund, Norway. The module will be delivered from

the company's Egersund yard. The contract also involves civil construction and

construction of new facilities at the site, which will be managed by a dedicated

site team from Aker Solutions with support from partners. The work is expected

to be completed in 2024.

The contract will be booked as order intake in the fourth quarter of 2020 in the

Electrification, Maintenance and Modifications segment.

ENDS

Media Contact:

Torbjørn Andersen, mob: +47 928 85 542, email:

[email protected]

Investor Contact:

Fredrik Berge, mob: +47 450 32 090, email: [email protected]

Aker Solutions helps the world meet its energy needs. We engineer the products,

systems and services required to unlock energy. Our goal is to maximize recovery

and efficiency of oil and gas assets, while using our expertise to develop the

sustainable solutions of the future. Aker Solutions employs approximately 15,000

people in more than 20 countries.

Visit akersolutions.com and connect with us on

Facebook (https://www.facebook.com/AkerSolutions/),

Instagram (https://instagram.com/akersolutions/),

LinkedIn (https://www.linkedin.com/company/aker-solutions),

Twitter (https://twitter.com/akersolutions) and

YouTube (https://www.youtube.com/akersolutions).

This press release may include forward-looking information or statements and is

subject to our disclaimer, see https://akersolutions.com

This information is subject of the disclosure requirements pursuant to section 5

-12 of the Norwegian Securities Trading Act.