AERIS RESOURCES LIMITED Capital/Financing Update 2012

Dec 20, 2012

64347_rns_2012-12-20_5ac767ac-883d-4c41-a57c-416023753df5.pdf

Capital/Financing Update

Open in viewer

Opens in your device viewer

==> picture [67 x 67] intentionally omitted <==

----- Start of picture text ----- +----- End of picture text -----

Straits

20 December 2012

ASX/MEDIA RELEASE

STRAITS RESOURCES LIMITED (ASX: SRQ)

STRAITS PRODUCTION UPDATE

Straits is pleased to update the market on production from both its operations, which form two of the company’s five key objectives.

Key Objective

  • On-time and on-budget ramp up of the Mt Muro gold mine to full production in March 2013 in order to achieve production of 100,000oz AuEq in the current financial year.

Production & Guidance

For the period of July 2012 to November 2012 Mt Muro has produced 25,700 AuEqoz. Updated guidance for the current quarter and the full year are given in the table below.

Mt Muro Expectation FY13 Mt Muro Expectation FY13 Mt Muro Expectation FY13
Period Previous Guidance (AuEqoz) Current Guidance (AuEqoz)
Current Quarter 15,000 – 17,000 12,000 – 13,000
Full Year 100,000 95,000 – 100,000

The mining operations have been impacted by recent rain events. The waste movements are expected to recover during the second half.

Key Objective

  • Achieve 25,000t of Copper production from Tritton in the current financial year post a period of significant cost reduction and on-site management change.

Production & Guidance

For the period of July 2012 to November 2012 Tritton has produced 9,900 Cu tonnes. Updated guidance for the current quarter and the full year are given in the table below.

Tritton Expectation FY13 Tritton Expectation FY13 Tritton Expectation FY13
Period Previous Guidance (Cu t) Current Guidance (Cu t)
Current Quarter 6,000 – 6,500 5,000 – 5,500
Full Year 25,000 24,500 – 25,500

The current quarter is lower than the previous due to delays in the paste filling and stoping sequence. These have been worked through and Tritton remains on target for the full year.

For further information, please contact: Mr. Mathew Smith – Company Secretary Tel: +61 8 9480-0500, or visit our website at www.straits.com.au