QUARTERLY ACTIVITIES REPORT

For the period ending 30 June 2023

The Board of Zeus Resources Limited (ACN 139 183 190) (ASX: ZEU ) (“ Zeus ” or “the Company ”) is pleased to release its fourth Quarterly Activities Report of 2022-2023 Financial Year covering the period ending 30 June 2023.

Highlights

  • Phase 1 drilling program of 19 holes for a total depth of 948m intersected multiple thick pegmatites at Pegmatite Creek, Alpha and Beta Prospects, Mortimer Hills Project (Figure 2). Intercepts include:

MHC002: 34 m of five pegmatites intercepted from surface with End of Hole (“EOH”) at 70 m at Pegmatite Creek Prospect (See ZEU ASX Announcements, 20 and 23 June 2023) . MHA003: 17 m of two pegmatites intercepted with an EOH at 50 m at Alpha Prospect.

MHA001: 15 m of two pegmatites intercepted with EOH at 50 m at Alpha Prospect.

The Company advises that all the drill intersection widths pertaining to the above intercepts are apparent only. As the orientation of the pegmatites is unknown, the true widths of the pegmatites may be less than or greater than the apparent widths.

The Company wishes to inform investors that the presence of pegmatite rock does not necessarily indicate the presence of lithium, caesium, tantalum (LCT) mineralisation. Laboratory chemical assays are required to determine the grade of mineralisation.

  • The pegmatites intersected by this drilling had visually similar texture and mineralogy to pegmatites occurring at the Yinnietharra Lithium Project (Figure 3) being developed by Delta - -

  • Lithium Limited (ASX: DLI) (https://deltalithium.com.au/our projects/yinnetharra lithium/).

  • None of the pegmatites logged in the Phase 1 drilling program produced anomalous lithium (Li), tin (Sn) or tantalum (Ta) indicating that the tested shallow areas were not derived from the nearby LCT Thirty Three Supersuite granite intrusion but rather a result of shearing of the host schists.

  • Phase 2 drill program at Mortimer Hills Project commenced on 9 July 2023.

www.zeusresources.com Suite 107, 25-29 Berry Street North Sydney NSW 2060 Australia Tel: +61 2 8488 3270 ACN: 139 183 190

  • The Phase 2 drilling program will focus on deeper drilling than tested in the Phase 1 drilling program and test new targets identified by recent field mapping and geochemical surveys.

  • The Company has applied for two new Exploration Licences (ELs) (E59/2804 and E59/2806) approximately 60 km west of Paynes Find. The tenements cover approximately 75 km2 and 15 km2 respectively.

  • The Company has applied for two new Exploration Licences (ELs) (E69/4147 and E69/4148) approximately 1,000 km northwest of Kalgoorlie and 1,600 km northwest from Perth in the Musgrave region of Western Australia. The tenements cover approximately 281 km2 and 120 km2 respectively.

  • The Company has applied for another five new Exploration Licences (ELs) (E09/2865, E09/2874, E09/2886, E09/2891 and E09/4148) with a total area of 59.5 km2 in Gascoyne area.

Corporate and Financial

  • Quarterly administrative and other operational expenditures are within the budget;

  • The Company’s statement of cash flows for the Quarter is set out in Appendix 5B. At the end of the Quarter the entity had A$2.347M with no debt;

  • Mr Colin Robert Mackay has resigned as a Non-Executive Director on the Board of Zeus, effective 7 July 2023.

  • ZEU confirms it is not aware of any new information or data that materially affects the information included in the original market announcements previously lodged with ASX;

  • During the quarter $37,000 was paid to related parties and their associates. The payments related to salaries of Directors and Company secretarial fees.

Tenement Status

The company currently has fourteen tenements and applications. These tenements include two granted tenements, one in the Mortimer Hills Project and one in the Wiluna Project. There are twelve applications for new tenements, including seven for the Mortimer Hills Project, one for the Wiluna Project, two for the Blue Hill Project and two for the Musgrave Project. Eight of the tenement applications (E09/2791, E09/2798, E59/2806, E09/2865, E09/2874, E09/2886, E09/2891 and E09/4148) are subject to the ballot. Tenement locations are shown in Figure 1 and detailed in Table 1.

www.zeusresources.com

==> picture [426 x 144] intentionally omitted <==

==> picture [426 x 144] intentionally omitted <==

==> picture [426 x 144] intentionally omitted <==

==> picture [426 x 144] intentionally omitted <==

Figure 1. Zeus Tenement Location Map

www.zeusresources.com

Table 1. Zeus Resources Tenement Details

Region Project Tenement Status Holder Operator Comments
Gascoyne Mortimer Hills E 09/2147 Granted Zeus Resources
Ltd
Zeus Resources
Ltd
E09/2791 Application Zeus Resources
Ltd
Zeus Resources
Ltd
Applied on
27/02/2023.
Subject to ballot.
E09/2798 Application Zeus Resources
Ltd
Zeus Resources
Ltd
Applied on
27/02/2023.
Subject to ballot.
E09/2865 Application Zeus Resources
Ltd
Zeus Resources
Ltd
Applied on
18/06/2023.
Subject to ballot.
E09/2874 Application Zeus Resources
Ltd
Zeus Resources
Ltd
Applied on
18/06/2023.
Subject to ballot.
E09/2886 Application Zeus Resources
Ltd
Zeus Resources
Ltd
Applied on
18/06/2023.
Subject to ballot.
E09/2891 Application Zeus Resources
Ltd
Zeus Resources
Ltd
Applied on
18/06/2023.
Subject to ballot.
E09/2880 Application Zeus Resources
Ltd
Zeus Resources
Ltd
Applied on
18/06/2023.
Subject to ballot.
Wiluna Wiluna E 53/1603 Granted Zeus Resources
Ltd
Zeus Resources
Ltd
Extension lodged
on 10/02/2023.
E53/2197 Application Zeus Resources
Ltd
Zeus Resources
Ltd
Applied on
27/10/2021.
Rothsay Blue Hill E59/2804 Application Zeus Resources
Ltd
Zeus Resources
Ltd
Applied on
20/03/2023.
E59/2806 Application Zeus Resources
Ltd
Zeus Resources
Ltd
Applied on
20/03/2023.
Subject to ballot
Musgrave Musgrave E69/4147 Application Zeus Resources
Ltd
Zeus Resources
Ltd
Applied on
03/04/2023
E69/4148 Application Zeus Resources
Ltd
Zeus Resources
Ltd
Applied on
03/04/2023

www.zeusresources.com

Exploration Program

During June 2023, the Company carried out the Phase 1 drilling program at its Mortimer Hills Project. And Phase 2 drill program at Mortimer Hills Project commences on 9 July 2023. Zeus’ Phase 2 RC drilling program will continue testing mapped pegmatites and geochemical anomalies in the Pooranoo Metamorphics along the contact with the Thirty Three Supersuite granite.

No other fieldwork was completed during the Quarter on the other tenements managed by Zeus Resources Ltd. The Board continues reviewing all the Company’s projects and updating the exploration plans accordingly.

Mortimer Hills Project (E09/2147, E09/2791, E09/2798, E09/2865, E09/2874, E09/2886, E09/2891 and E09/4148)

The main Mortimer Hills Project comprises one granted exploration licence, E09/2147, which is located 5 km east southeast along strike from DLI’s Yinnietharra Lithium Prospect (Figure 2).

==> picture [380 x 88] intentionally omitted <==

==> picture [380 x 89] intentionally omitted <==

==> picture [380 x 88] intentionally omitted <==

Figure 2 - Locations of Mortimer Hills Li Project (ZEU), Yinnietharra Li Project (DLI) and Ti Tree Li Project (Voltaic Strategic Resources Ltd (ASX: VSR)).

www.zeusresources.com

==> picture [385 x 159] intentionally omitted <==

==> picture [385 x 158] intentionally omitted <==

Figure 3: Locations of Mortimer Hills Project (ZEU), Yinnietharra Li Project (DLI) and Ti Tree Project (VSR)

PHASE 1 DRILL PROGRAM SUMMARY

The phase 1 drill program was an initial reconnaissance program in which the Company completed shallow reconnaissance RC drill testing across the extensive pegmatite swarms, many of which are visible outcropping at the surface, which extend from the western side of our Mortimer Hills tenement to the southeast along a potential strike length of up to 5kms.

The phase 1 reconnaissance drilling started by testing the Alpha Prospect (Figure 3) on the western Boundary beside the expanding resource of DLI’s Yinnietharra Lithium Project (Figure 3). The Company also drill-tested the central Beta Prospect area and the Pegmatite Creek Prospect area (Figure 3) further to the southeast. Pegmatites were encountered in drilling on all three prospect areas.

The phase 1 drill program consisted of 19 RC shallow holes drilled at a 50-60% dip to depths of between 30-70 m with most holes drilled to 50 m (for a total of 948 m). 10 holes of the phase 1 drill

www.zeusresources.com

program encountered pegmatites underground with some encountering several pegmatites in the same drill hole ( refer to Appendix 1 ).

Reconnaissance drilling at the Alpha Prospect (Figure 3), which is adjacent to the Yinnietharra Lithium Project (DLI), received encouraging results with two pegmatite intersections each of 8.5 m in a single hole. The Alpha Prospect could potentially be the extension of DLI’s Malinda Prospect to the east (See DLI ASX Announcement, 23 June 2023) .

Reconnaissance drilling at the central Beta Prospect (Figure 1) testing portable XRF geochemical anomalies intersected several narrow pegmatites indicating that there is potential for the pegmatites to extend from the Alpha Prospect through to Pegmatite Creek Prospect. This would indicate a potential strike extent of approximately 5 km from the northwest to the southeast.

The Company has received all the assay results from its Phase 1 RC drilling program. None of the pegmatites logged in the drilling produced anomalous lithium (Li), tin (Sn) or tantalum (Ta) grades indicating that these pegmatites in shallow depth were not derived from the nearby Thirty Three Supersuite granite intrusion but rather a result of shearing of the host schists.

==> picture [394 x 265] intentionally omitted <==

Figure 4 – Locations of Phase 1 drill holes and prospects.

www.zeusresources.com

PHASE 2 DRILLING

The Company commences Phase 2 drilling on 9 July 2023. Zeus intends to progressively RC drill, extending along the strike and at the depth the pegmatites intersected during the Phase 1 drilling, on an appropriate grid. New targets identified during recent field mapping and geochemical surveys will also be tested by this next phase of drilling.

All the drilling will be Reverse Circulation (RC) with the holes inclined at 60-75 degrees. The hole depths and spacing along the section lines are designed to have 100% horizontal coverage such that the base of a hole is directly below the collar of the next hole along the section line. This configuration ensures that any vertical or dipping pegmatites will be intersected by this drilling.

The Company will also extend the previous field mapping and surface geochemical sampling at untested areas to better target drill hole locations in preparation for further drilling programs.

NEW TENEMENT APPLICATION – GASCOYNE AREA

The Company has applied for two new tenements (E09/2791 and E09/2798) in February 2023. The tenement applications cover approximately 18.69 km[2] and 24.92 km[2] respectively of the Durlacher and Thirty-Three Supersuite granitic rocks that are regionally associated with lithium and REE bearing pegmatites (Figure 5).

The Company has applied for another five new Exploration Licences (ELs) (E09/2865, E09/2874, E09/2886, E09/2891 and E09/4148) with a total area of 59.5 km2 in June 2023 (Figure 5).

These tenement applications will be subject to a ballot to determine the successful applicants.

Table 1. June 2023 Tenement Application Details

Region Project **Tenement ID ** **Area(blocks) ** **Area(km2) ** **Date of lodgement ** Comments
Gascoyne Mortimer Hills E09/2865 10 31.3 18/06/2023 Subject to ballot
E09/2874 4 12.509 18/06/2023 Subject to ballot
E09/2886 2 6.257 18/06/2023 Subject to ballot
E09/2891 2 6.258 18/06/2023 Subject to ballot
E09/2880 1 3.13 18/06/2023 Subject to ballot
Total 19 59.454

www.zeusresources.com

==> picture [346 x 278] intentionally omitted <==

Figure 5 – Tenement locations (Blue = latest applications, yellow = February applications).

WILUNA PROJECT (E53/1603 & E53/2197)

Geological exploration is continuing at the Wiluna Project, located near the township of Wiluna approximately 540 km north of Kalgoorlie, next to the Lake Way Project (previously owned by Salt Lake Potash Limited ( ASX: SO4 )) (https://so4.com.au/projects/lake-way/ ) and recently acquired by Czech Investment Company Sev.en Global Investments.

Air-core drilling in September 2022 identified a free-flowing aquifer containing sulphate of potash brine flowing in a basal sand paleochannel approximately 3.5 km from the northerly margin of Salt Lake Potash’s Lake Way SOP deposit. This aquifer is suspected to be part of the underground feeder system for Lake Way’s SOP deposit.

An objection was lodged by a third party in 2021 in relation to application E53/2197. The matter has been heard in the Warden’s Court (Meekatharra) on 17 May 2023, and has been adjourned to 19 July 2023, at the request of the Applicant.

Further exploration and activities including a detailed gravity survey and drilling are subject to the granting of the E53/2197 Exploration Licence.

www.zeusresources.com

BLUE HILL PROJECT (E59/2804 & E59/2806)

The Company has applied for two new tenements (E59/2804 and E59/2806) approximately 60 km west of Paynes Find (Figure 6). The tenements cover approximately 75 km[2] and 15 km[2] respectively of the Warriedar Fold Belt greenstones and granitic rocks that are highly prospective for lithium and REE bearing pegmatites, gold, and base metals.

E59/2806 application is subject to a ballot to determine the successful applicant.

==> picture [308 x 350] intentionally omitted <==

Figure 6: Location map showing E59/2804, E59/2806 and nearby mines.

An objection was lodged by a third party in April 2023, and the matter has been listed for Mention Hearing on 24 August 2023 at the Mount Magnet Wardens Court.

www.zeusresources.com

MUSGRAVE PROJECT (E69/4147 & E69/4148)

The Company has applied for two new tenements (E69/4147 and E69/4148) approximately 1,000 km northwest of Kalgoorlie and 1,600 km northwest from Perth in the Musgrave region of Western Australia (Figure 7). The tenements cover approximately 281 km[2] and 120 km[2] respectively of the West Musgrave greenstones and granitic rocks that are highly prospective for nickel, gold, REEs and base metals.

==> picture [314 x 417] intentionally omitted <==

Figure 7: Location map showing Musgrave tenements E69/4147 and E69/4148.

www.zeusresources.com

NARNOO PROJECT (E28/2097)

The Narnoo Project comprises one exploration Licence, E28/2097. Based on the recommendations from the Company’s tenement manager with regards to the latest changes in the legislation, the Company is not able to actively explore for uranium without certain Federal Government approval. The Board has decided to relinquish this tenement, and the Company has lodged the Surrender Form on 5 May 2023.

www.zeusresources.com

Competent Person Statement:

The information in this announcement that relates to the Exploration Results is based on information compiled by Mr Phil Jones, who is a Member of the Australian Institute of Geologists (AIG) and Australian Institute of Mining and Metallurgy (AusIMM). Mr Jones is an independent geological consultancy. Mr Jones does not nor has had previously, any material interest in Zeus or the mineral properties in which Zeus has an interest. Phil Jones’s relationship with Zeus is solely one of professional association between client and independent consultant. Mr Jones has experience in exploration, prospect evaluation, project development, open pit and underground mining and management roles. Mr Jones has worked in a wide variety of commodities including gold, lithium, iron ore, phosphate, copper, lead, zinc, silver, nickel and silica in Australia, China, Kyrgyzstan, Indonesia, New Zealand, Malaysia, Papua New Guinea, and Africa. Mr Jones has sufficient experience which is relevant to the style of mineralisation and type of deposit under consideration and to the activity being undertaken to qualify as a Competent Person as defined in the 2012 Edition of the ‘Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves’. Mr Jones consents to the inclusion in this release of the matters based on his information in the form and context in which it appears.

www.zeusresources.com

***

Disclaimers

This announcement is provided for information purposes only and is not a prospectus, disclosure document or other offering document under Australian law or under any other law.

The information in this announcement is of a general nature and does not purport to be complete. This announcement does not purport to contain all the information that a prospective investor may require in connection with any potential investment in the Company. Each recipient must make its own independent assessment of the Company before acquiring any securities in the Company.

Except for any liability that cannot be excluded by law, the Company and its related bodies corporate, directors, employees, servants, advisers and agents (together, “ Affiliates ”) disclaim and accept no responsibility or liability for any expenses, losses, damages or costs incurred by you relating in any way to this announcement including, without limitation, the information contained in or provided in connection with it, any errors or omissions from it however caused, lack of accuracy, completeness, currency or reliability or you or any other person placing any reliance on this announcement, its accuracy, completeness, currency or reliability.

Not investment advice

This announcement is not financial product or investment advice nor a recommendation to acquire or sell securities in the Company. Information in this announcement is not intended to be relied upon as advice to investors or potential investors and has been prepared without taking account of any person’s individual investment objectives, financial situation, or particular needs.

Each recipient of this announcement should make its own enquiries and investigations regarding all information in this announcement including but not limited to the assumptions, uncertainties and contingencies which may affect future operations of the Company and the impact that different future outcomes might have on the Company.

Before making an investment decision, prospective investors should consider the appropriateness of the information having regard to their own investment objectives, financial situation and needs and seek legal, accounting and taxation advice appropriate to their jurisdiction. The Company is not licensed to provide financial product advice in respect of its securities.

Past performance

Past performance of the Company should not be relied on and is not indicative of future performance including future security prices.

Forward looking statements

This announcement may contain certain forward-looking statements. The words ‘anticipate’, ‘believe’, ‘aim’, ‘estimate’, ‘expect’, ‘intend’, ‘may’, ‘plan’, ‘project’, ‘will’, ‘should’, ‘seek’ and similar expressions are intended to identify forward looking statements. These forward-looking statements are based on assumptions and contingencies that are subject to change without notice and involve known and unknown risks, uncertainties, and other factors, many of which are beyond the control of the Company and its Affiliates. Refer to the ‘Risk factors’ above for a summary of certain risk factors that may affect the Company.

Investors are strongly cautioned not to place undue reliance on forward looking statements, particularly in light of the current economic climate and the significant volatility, uncertainty and disruption caused by the COVID 19 pandemic.

Forward looking statements are provided as a general guide only and should not be relied on as an indication or guarantee of future performance. Actual results, performance or achievements may differ materially from those expressed or implied in those statements and any projections and assumptions on which these statements are based. These statements may assume the success of the Company’s business strategies, the success of which may not be realised within the period for which the forward-looking statements may have been prepared, or at all.

www.zeusresources.com

No guarantee, representation, or warranty, express or implied, is made as to the accuracy, likelihood of achievement or reasonableness of any forecasts, prospects, returns, statements, or tax treatment in relation to future matters contained in this announcement. The forward-looking statements are based on information available to the Company as at the date of this announcement. Except as required by applicable laws or regulations, none of the Company or its Affiliates undertakes to provide any additional information or revise the statements in this announcement, whether as a result of a change in expectations or assumptions, new information, future events, results, or circumstances.

Not an offer

This announcement is not an offer or an invitation to acquire securities of the Company or any other financial products. This announcement does not constitute an offer to sell, or a solicitation of an offer to buy securities in the United States or any other jurisdiction where it would be illegal and will not form any part of any contract or commitment for the acquisition of securities.

This announcement has been prepared for publication in Australia only and may not be released to US wire services or distributed in the United States. The securities have not been, and will not be, registered under the US Securities Act of 1933 (the US Securities Act) and may not be offered or sold in the United States except in transactions exempt from, or not subject to, the registration requirements of the US Securities Act and applicable US state securities laws. The distribution of this announcement in the United States and elsewhere outside Australia may be restricted by law. Persons who come into possession of this announcement should observe any such restrictions as any non-compliance could contravene applicable securities laws.

This announcement was authorised for release to the ASX by the Board of the Company.

ENDS

For further information, please contact:

Mr Jian Liu

Executive Director

[email protected]

www.zeusresources.com

Appendix 1: Phase 1 Drilling Summary - Mortimer Hills Project

Hole ID Easting Northing RL
(m)
Dip
(o)
Mag
Azimuth
(o)
Pegmatite
from (m)
Pegmatite
to (m)
Thickness
(m)
EOH
Depth
(m)*
Prospect Name Drill
Type**
MH001 431556 7286307 322 -60 270 0 55 Beta Prospect RC
MH002 431582 7286305 322 -60 270 0 50 RC
MH003 431608 7286299 322 -60 270 0 50 RC
MH004 431632 7286294 322 -60 270 0 50 RC
MH005 431650 7286293 322 -60 270 0 50 RC
MH006 431675 7286289 322 -60 270 0 50 RC
MH007 431376 7286411 322 -60 270 6 9 3 50 RC
15 16 1
26
27 1
37 38 1
45 46 1
MH008 431350 7286411 322 -60 270 16
19 3 50 RC
33
37 4
MH009 431326 7286411 322 -60 270 27 29 2 50 RC
MH010 431398 7286409 322 -60 270 0 50 RC
MHA001 429598 7287643 335 -60 345 16
19 3 50 Alpha Prospect RC
32
44 12
MHA002 429601 7287622 335 -60 345 11
12 1 50 RC
29
32.5 3.5
MHA003 429607 7287605 335 -60 345 38
46.5 8.5 50 RC
49.5
58 8.5
MHA004 429610 7287582 335 -60 345 14.5
18 3.5 50 RC
19
20 1
MHA005 429613 7287560 335 -60 345 0
5 5 50 RC
31
37 6
MHA006 429594 7287668 335 -60 345 0 50 RC
MHC001 432250 7285214 315 -60 88 0 43 Pegmatite Creek
Prospect
RC
MHC002 432261 7285221 313 -50 112 0 8 8 70 RC
22.5 40 17.5
42
44 2
46.5 52 5.5
56 57 1
MHC003 432249 7285239 315 -50 143 0 6 6 30 RC

: EOH = End of Hole *RC = Reverse circulation

All the drill intersection widths pertaining to the above intercepts are apparent only. As the orientation of the pegmatites is unknown, the true widths of the pegmatites may be less than or greater than the apparent widths.

www.zeusresources.com

==> picture [155 x 55] intentionally omitted <==

JORC CODE, 2012 EDITION – TABLE 1

Section 1 Sampling Techniques and Data

(Criteria in this section apply to all succeeding sections.)

Criteria JORC Code explanation JORC Code explanation Commentary Commentary
Sampling Nature and quality of sampling (eg cut channels, random chips, or specific All drilling was Reverse Circulation (RC) used to obtain 1 m samples
techniques specialised industry standard measurement tools appropriate to the minerals collected from the drill rig cyclone.
under investigation, such as down hole gamma sondes, or handheld XRF Samples logged by the site geologist as pegmatite were assayed as 1m
instruments, etc). These examples should not be taken as limiting the broad samples while the remainder were composited as generally 4m samples.
meaning of sampling. The samples were collected in calico bags from the 1m piles on the ground
Include reference to measures taken to ensure sample representivity and the by taking four representative scoops using a small trowel.
appropriate calibration of any measurement tools or systems used. Each sample dispatched to the laboratory weighed approximately 2 kg which
Aspects of the determination of mineralisation that are Material to the Public was pulverised to produce an aliquot for ICP assay carried out to industry
Report. standard.
In cases where ‘industry standard’ work has been done this would be
relatively simple (eg ‘reverse circulation drilling was used to obtain 1 m
samples from which 3 kg was pulverised to produce a 30 g charge for fire
assay’). In other cases more explanation may be required, such as where
there is coarse gold that has inherent sampling problems. Unusual
commodities or mineralisation types (eg submarine nodules) may warrant
disclosure of detailed information.
Drilling Drill type (eg core, reverse circulation, open-hole hammer, rotary air blast, All drilling was face-sampling RC.
techniques auger, Bangka, sonic, etc) and details (eg core diameter, triple or standard
tube, depth of diamond tails, face-sampling bit or other type, whether core is
oriented and ifso, by what method, etc).
Drill sample Method of recording and assessing core and chip sample recoveries and All the drill cuttings were logged by a geologist to be stored as Excel
recovery results assessed. spreadsheets.
Measures taken to maximise sample recovery and ensure representative Sample recoveries, by visual inspection, were excellent.
nature of the samples.
Whether a relationship exists between sample recovery and grade and
whether sample bias may have occurred due to preferential loss/gain of
fine/coarse material.
Logging Whether core and chip samples have been geologically and geotechnically All the drill cuttings were visually quantitatively logged by a site geologist.
logged to a level of detail to support appropriate Mineral Resource estimation, These logs are stored as Excel spreadsheets.
mining studies and metallurgical studies.
Whether logging is qualitative or quantitative in nature. Core (or costean,
channel, etc) photography.
The total length and percentage of the relevant intersections logged.

www.zeusresources.com Suite 107, 25-29 Berry Street North Sydney NSW 2060 Australia Tel: +61 2 8488 3270 ACN: 139 183 190

Criteria JORC Code explanation JORC Code explanation Commentary Commentary
Sub-sampling If core, whether cut or sawn and whether quarter, half or all core taken. Samples were collected at 1m intervals by a rig mounted cyclone.
techniques If non-core, whether riffled, tube sampled, rotary split, etc and whether The laboratory used standards and repeat assays to ensure that the assays
and sample sampled wet or dry. were reliable and unbiassed.
preparation For all sample types, the nature, quality and appropriateness of the sample
preparation technique.
Since this drilling program was a reconnaissance program only, no field
standards and duplicates were submitted to the laboratory. The 1m samples
Quality control procedures adopted for all sub-sampling stages to maximise were retained in the field for checking assays if necessary, but since all the
representivity of samples. assays were below grade expectations none of these samples were
Measures taken to ensure that the sampling is representative of the in situ submitted as checks.
material collected, including for instance results for field duplicate/second-half The sample size is appropriate for the material being sampled.
sampling.
Whether sample sizes are appropriate to the grain size of the material being
sampled.
Quality of The nature, quality and appropriateness of the assaying and laboratory The assays were carried out by ALS in Perth. ALS is an independent NATA
assay data procedures used and whether the technique is considered partial or total. accredited testing laboratory.
and laboratory
tests

For geophysical tools, spectrometers, handheld XRF instruments, etc, the
parameters used in determining the analysis including instrument make and
The analytical method used, Super Trace Lowest DL AR by ICP-MS (ME-
MS41L), is an appropriate analytical method assay method.
model, reading times, calibrations factors applied and their derivation, etc. The laboratory followed appropriate industry standard sample preparation
Nature of quality control procedures adopted (eg standards, blanks, and analytical procedures and included an appropriate number of QAQC
duplicates, external laboratory checks) and whether acceptable levels of assay checks.
accuracy (ie lack of bias) and precision have been established.
Verification of The verification of significant intersections by either independent or Not applicable
sampling and alternative company personnel.
assaying The use of twinned holes.
Documentation of primary data, data entry procedures, data verification, data
storage (physical and electronic) protocols.
Discuss any adjustment to assay data.
Location of Accuracy and quality of surveys used to locate drill holes (collar and down- The drill collars were recorded using a handheld GPS using GDA94 datum.
data points hole surveys), trenches, mine workings and other locations used in Mineral
Resource estimation.
Specification of the grid system used.
Quality and adequacy of topographic control.
Data spacing Data spacing for reporting of Exploration Results. This drilling was reconnaissance only at widely spaced locations.
and Whether the data spacing and distribution is sufficient to establish the degree
distribution of geological and grade continuity appropriate for the Mineral Resource and
Ore Reserve estimation procedure(s) and classifications applied.
Whether sample compositing has been applied.
Orientation of Whether the orientation of sampling achieves unbiased sampling of possible All the drill intersection widths pertaining to the above intercepts are apparent
data in structures and the extent to which this is known, considering the deposit type. only. As the orientation of the pegmatites is unknown, the true widths of the
relation to If the relationship between the drilling orientation and the orientation of key pegmatites may be less than or greater than the apparent widths.

www.zeusresources.com

Criteria JORC Code explanation JORC Code explanation Commentary Commentary
geological mineralised structures is considered to have introduced a sampling bias, this
structure should be assessed and reported if material.
Sample The measures taken to ensure sample security. The samples were delivered to the laboratory by the site geologist.
security
Audits or The results of any audits or reviews of sampling techniques and data. Not applicable
reviews

Section 2 Reporting of Exploration Results

(Criteria listed in the preceding section also apply to this section.)

Criteria JORC Code explanation JORC Code explanation Commentary Commentary
Mineral Type, reference name/number, location and ownership including agreements The Mortimer Hills project covers an area of approximately 71.65 km2and
tenement and or material issues with third parties such as joint ventures, partnerships, comprises one granted exploration licence E09/2147 and seven exploration
land tenure overriding royalties, native title interests, historical sites, wilderness or licence applications: E09/2791, E09/2798, E09/2865, E09/2874, E09/2886,
status national park and environmental settings. E09/2891 and E09/4148.
The security of the tenure held at the time of reporting along with any known All the tenements are 100% owned by Zeus Resources.
impediments to obtaining a licence to operate in the area. Seven EL applications are subject to a ballot with other applicants.
Exploration Acknowledgment and appraisal of exploration by other parties. Numerous exploration parties have previously held portions of the areas
done by other covered by the current Zeus tenure. None of this exploration is recorded as
parties being for pegmatite hosted lithium and REE minerals, the main focus of Zeus
on the tenements.
No other exploration companies generated data that was used in this release.
Geology Deposit type, geological setting and style of mineralisation. E09/2147 lies along the contact between the Thirty Three Supersuite granitic
intrusives and the Pooranoo Metamorphics.
E09/2791, E09/2798, E09/2865, E09/2874, E09/2886, E09/2891 and
E09/4148 cover the Thirty Three Supersuite granitic intrusives and Durlacher
Supersuite granites.
Drill hole A summary of all information material to the understanding of the exploration The drill hole data is provided as a table at the end of the announcement
Information results including a tabulation of the following information for all Material drill (Appendix 1).
holes:
o
easting and northing of the drill hole collar
o
elevation or RL (Reduced Level – elevation above sea level in metres) of
the drill hole collar

www.zeusresources.com

Criteria JORC Code explanation JORC Code explanation Commentary Commentary
o
dip and azimuth of the hole
o
down hole length and interception depth
o
hole length.
If the exclusion of this information is justified on the basis that the information
is not Material and this exclusion does not detract from the understanding of
the report, the Competent Person should clearly explain why this is the case.
Data In reporting Exploration Results, weighting averaging techniques, maximum Not applicable
aggregation and/or minimum grade truncations (eg cutting of high grades) and cut-off
methods grades are usually Material and should be stated.
Where aggregate intercepts incorporate short lengths of high grade results
and longer lengths of low grade results, the procedure used for such
aggregation should be stated and some typical examples of such
aggregations should be shown in detail.
The assumptions used for any reporting of metal equivalent values should be
clearly stated.
Relationship These relationships are particularly important in the reporting of Exploration All the drill intersection widths pertaining to the above intercepts are apparent
between Results. only. As the orientation of the pegmatites is unknown, the true widths of the
mineralisation
If the geometry of the mineralisation with respect to the drill hole angle is pegmatites may be less than or greater than the apparent widths. None of the
widths and
intercept
lengths
known, its nature should be reported.
If it is not known and only the down hole lengths are reported, there should
be a clear statement to this effect (eg ‘down hole length, true width not
known’).
logged pegmatites produced assays for lithium (Li), tin (Sn) or tantalum (Ta)
above background.
Diagrams Appropriate maps and sections (with scales) and tabulations of intercepts All the appropriate maps are provided in the body of this announcement.
should be included for any significant discovery being reported These should
include, but not be limited to a plan view of drill hole collar locations and
appropriate sectional views.
Balanced Where comprehensive reporting of all Exploration Results is not practicable, This announcement discusses the completion of a recent reconnaissance
reporting representative reporting of both low and high grades and/or widths should be drilling program and further planned drilling. None of the logged pegmatites
practiced to avoid misleading reporting of Exploration Results. produced assays for lithium (Li), tin (Sn) or tantalum (Ta) above background.
Other Other exploration data, if meaningful and material, should be reported All the meaningful exploration data has been included in the body of this
substantive including (but not limited to): geological observations; geophysical survey announcement.
exploration
data
results; geochemical survey results; bulk samples – size and method of
treatment; metallurgical test results; bulk density, groundwater, geotechnical
and rock characteristics;potential deleterious or contaminating substances.
Further work The nature and scale of planned further work (eg tests for lateral extensions Once the tenement applications have been granted, Zeus intend to carry out
or depth extensions or large-scale step-out drilling). detailed mapping and geochemical sampling to locate any pegmatite
Diagrams clearly highlighting the areas of possible extensions, including the outcrops.
main geological interpretations and future drilling areas, provided this Another RC drilling program commences on July 9 to further test mapped
information is not commercially sensitive.

www.zeusresources.com

Criteria JORC Code explanation Commentary
pegmatites along the greenstone/granite contact in E09/2147.

www.zeusresources.com

Rule 5.5

Appendix 5B

Mining exploration entity or oil and gas exploration entity quarterly cash flow report

Name of entity

Name of entity Name of entity Name of entity
ZEUS RESOURCES LTD
ABN
70 139 183 190
Quarter ended (“current quarter”)
30 JUNE 2023
Consolidated statement of cash flows Current quarter
$A’000
Year to date (12
months)
$A’000
1.
Cash flows from operating activities
1.1
Receipts from customers
1.2
Payments for
(a)
exploration & evaluation
(b)
development
(c)
production
(d)
staff costs
(e)
administration and corporate costs
1.3
Dividends received (see note 3)
1.4
Interest received
1.5
Interest and other costs of finance paid
1.6
Income taxes paid
1.7
Government grants and tax incentives
1.8
Other (provide details if material)
1.9
Net cash from / (used in) operating
activities
(268)
(36)
4
(606)
(256)
12
(300) (850)
2.
Cash flows from investing activities
2.1
Payments to acquire or for:
(a)
entities
(b)
tenements
(c)
property, plant and equipment
(d)
exploration & evaluation
(e)
investments
(f)
other non-current assets
2.2
Proceeds from the disposal of:
(a)
entities
(b)
tenements

ASX Listing Rules Appendix 5B (17/07/20)

Page 1

Appendix 5B Mining exploration entity or oil and gas exploration entity quarterly cash flow report

Consolidated statement of cash flows Current quarter
$A’000
Year to date (12
months)
$A’000
(c) property, plant and equipment
(d) investments
(e) other non-current assets
2.3
Cash flows from loans to other entities
2.4
Dividends received (see note 3)
2.5
Other (provide details if material)
2.6
Net cash from / (used in) investing
activities
- -
3.
Cash flows from financing activities
3.1
Proceeds from issues of equity securities
(excluding convertible debt securities)
3.2
Proceeds from issue of convertible debt
securities
3.3
Proceeds from exercise of options
3.4
Transaction costs related to issues of equity
securities or convertible debt securities
3.5
Proceeds from borrowings
3.6
Repayment of borrowings
3.7
Transaction costs related to loans and
borrowings
3.8
Dividends paid
3.9
Other (provide details if material)
3.10
Net cash from / (used in) financing
activities
380
(10)
2,192
380
(351)
370 2,221
4.
Net increase / (decrease) in cash and
cash equivalents for the period
4.1
Cash and cash equivalents at beginning of
period
4.2
Net cash from / (used in) operating
activities (item 1.9 above)
4.3
Net cash from / (used in) investing activities
(item 2.6 above)
4.4
Net cash from / (used in) financing activities
(item 3.10 above)
4.5
Effect of movement in exchange rates on
cash held
4.6
Cash and cash equivalents at end of
period
2,277
(300)
-
370
-
976
(850)
2,221
2,347 2,347

ASX Listing Rules Appendix 5B (17/07/20)

Page 2

Appendix 5B Mining exploration entity or oil and gas exploration entity quarterly cash flow report

5. Reconciliation of cash and cash Current quarter Previous quarter
equivalents $A’000 $A’000
at the end of the quarter (as shown in the
consolidated statement of cash flows) to the
related items in the accounts
5.1 Bank balances 917 1,234
5.2 Call deposits 1,430 1,043
5.3 Bank overdrafts
5.4 Other (provide details)
5.5 Cash and cash equivalents at end of 2,347 2,277
quarter (should equal item 4.6 above)
6. Payments to related parties of the entity and their Current quarter
associates $A'000
6.1 Aggregate amount of payments to related parties and their (37)
associates included in item 1
6.2 Aggregate amount of payments to related parties and their -
associates included in item 2
Note: if any amounts are shown in items 6.1 or 6.2, your quarterly activity report must include a description of, and an
explanation for, such payments.
6.
Payments to related parties of the entity and their
associates
Current quarter
$A'000
6.1
Aggregate amount of payments to related parties and their
associates included in item 1
(37)
6.2
Aggregate amount of payments to related parties and their
associates included in item 2
-
6.
Payments to related parties of the entity and their
associates
Current quarter
$A'000
6.1
Aggregate amount of payments to related parties and their
associates included in item 1
(37)
6.2
Aggregate amount of payments to related parties and their
associates included in item 2
-
Note: if any amounts are shown in items 6.1 or 6.2, your quarterly activity report must include a description of, and an
explanation for, such payments.
7.
Financing facilities
Total facility
Amount drawn at
Note: the term “facility’ includes all forms of financing
arrangements available to the entity.
Add notes as necessary for an understanding of the
sources of finance available to the entity.
amount at quarter
end
$A’000
quarter end
$A’000
7.1
Loan facilities
-
-
7.2
Credit standby arrangements
-
-
7.3
Other (please specify)
-
-
7.4
Total financing facilities
-
-
7.5
Unused financing facilities available at quarter end
-
7.6
Include in the box below a description of each facility above, including the lender, interest
rate, maturity date and whether it is secured or unsecured. If any additional financing
facilities have been entered into or are proposed to be entered into after quarter end,
include a note providing details of those facilities as well.

ASX Listing Rules Appendix 5B (17/07/20)

Page 3

Appendix 5B Mining exploration entity or oil and gas exploration entity quarterly cash flow report

8. Estimated cash available for future operating activities $A’000
8.1
8.2
8.3
8.4
8.5
8.6
8.7
8.8
Net cash from / (used in) operating activities (item 1.9)
(300)
(Payments for exploration & evaluation classified as investing
activities) (item 2.1(d))
-
Total relevant outgoings (item 8.1 + item 8.2)
(300)
Cash and cash equivalents at quarter end (item 4.6)
2,347
Unused finance facilities available at quarter end (item 7.5)
-
Total available funding (item 8.4 + item 8.5)
2,347
Estimated quarters of funding available (item 8.6 divided by
item 8.3)
8
Note: if the entity has reported positive relevant outgoings (ie a net cash inflow) in item 8.3, answer item 8.7 as “N/A”.
Otherwise, a figure for the estimated quarters of funding available must be included in item 8.7.
If item 8.7 is less than 2 quarters, please provide answers to the following questions:
8.8.1
Does the entity expect that it will continue to have the current level of net operating
cash flows for the time being and, if not, why not?
(300)
-
(300)
2,347
-
2,347
8
Answer:
8.8.2
Has the entity taken any steps, or does it propose to take any steps, to raise further
cash to fund its operations and, if so, what are those steps and how likely does it
believe that they will be successful?
Answer:
8.8.3
Does the entity expect to be able to continue its operations and to meet its business
objectives and, if so, on what basis?
Answer:
Note: where item 8.7 is less than 2 quarters, all of questions 8.8.1, 8.8.2 and 8.8.3 above must be answered.

Compliance statement

  • 1 This statement has been prepared in accordance with accounting standards and policies which comply with Listing Rule 19.11A.

  • 2 This statement gives a true and fair view of the matters disclosed.

Date: 24 July 2023

Authorised by: The Board of Zeus Resources Limited (Name of body or officer authorising release – see note 4)

Notes

  1. This quarterly cash flow report and the accompanying activity report provide a basis for informing the market about the entity’s activities for the past quarter, how they have been financed and the effect this has had on its cash position. An

ASX Listing Rules Appendix 5B (17/07/20)

Page 4

Appendix 5B

Mining exploration entity or oil and gas exploration entity quarterly cash flow report

entity that wishes to disclose additional information over and above the minimum required under the Listing Rules is encouraged to do so.

  1. If this quarterly cash flow report has been prepared in accordance with Australian Accounting Standards, the definitions in, and provisions of, AASB 6: Exploration for and Evaluation of Mineral Resources and AASB 107: Statement of Cash Flows apply to this report. If this quarterly cash flow report has been prepared in accordance with other accounting standards agreed by ASX pursuant to Listing Rule 19.11A, the corresponding equivalent standards apply to this report.

  2. Dividends received may be classified either as cash flows from operating activities or cash flows from investing activities, depending on the accounting policy of the entity.

  3. If this report has been authorised for release to the market by your board of directors, you can insert here: “By the board”. If it has been authorised for release to the market by a committee of your board of directors, you can insert here: “By the [ name of board committeeeg Audit and Risk Committee ]”. If it has been authorised for release to the market by a disclosure committee, you can insert here: “By the Disclosure Committee”.

  4. If this report has been authorised for release to the market by your board of directors and you wish to hold yourself out as complying with recommendation 4.2 of the ASX Corporate Governance Council’s Corporate Governance Principles and Recommendations , the board should have received a declaration from its CEO and CFO that, in their opinion, the financial records of the entity have been properly maintained, that this report complies with the appropriate accounting standards and gives a true and fair view of the cash flows of the entity, and that their opinion has been formed on the basis of a sound system of risk management and internal control which is operating effectively.

ASX Listing Rules Appendix 5B (17/07/20)

Page 5