AI assistant
WEST WITS MINING LIMITED — Capital/Financing Update 2017
Mar 8, 2017
66091_rns_2017-03-08_e53cb116-5150-4e08-a4d7-bfd86da060d2.pdf
Capital/Financing Update
Open in viewerOpens in your device viewer
ASX: WWI
ASX Announcement and Media Release Thursday, 9 March 2017
www.westwitsmining.com
==> picture [100 x 73] intentionally omitted <==
Fast Facts @ 9 Mar 2017 Capital Structure: Shares on issue 456 million Options 52 million Market Cap A$11 million Cash in Bank A$0.3 million Debt Nil Enterprise Value (EV) A$11.1 million EV/oz A$8.07/oz
| Company Directors & | Management |
|---|---|
| Michael Quinert | Chairman |
| Vin Savage | Executive Director |
| Neil Pretorius | Non-Exec Director |
| Hulme Scholes | Non-Exec Director |
| Top Shareholders ≈ | |
| Twynam Ag | 19.9% |
| DRD Gold Ltd | 11% |
| Top 40 Shareholders | 74% |
Company Highlights
• South Africa
o near surface and underground targets o 1.374m oz JORC resource - Measures: 302,300 - Indicated: 592,500 - Inferred: 489,000 o Historic estimate of 12.8m oz at 4.6g/t o 31.8m ozs Au produced historically
==> picture [154 x 109] intentionally omitted <==
• Indonesia
-
High grade placer deposit
-
oProject show early stage similarities with discoveries inc; Porgera, Edie Creek, Wau
o Independent geologists believe source of nuggets likely to be local, based on the size and shape of the nuggets discovered
==> picture [145 x 118] intentionally omitted <==
Contact Details West Wits Mining Limited ACN 124 894 060 Suite 1, 1233 High Street Armadale VIC 3143 T: +61 3 8692 9049 F: +61 3 8692 9040 E: [email protected] W: www.westwitsmining.com
Sol Plaatje Project Update
Highlights
-
Definitive agreement close with one remaining issue delaying finalisation
-
Production is continuing
-
Discussions with alternative operating contractors are underway
-
West Wits received a further 550,000 rand (~A$55,000) as partial payments from the mining contractor for December/January production at SPP in addition to 1.75m rand previously received in December
-
West Wits has received a further 800,000 rand (A$80,000) payment from the freehold landowner of the SPP area as part of its development agreement
West Wits Mining Limited (“West Wits” or “the Company”) wishes to provide a further update on the progress at its Sol Plaatje Project (“SPP”). The definitive agreement for SPP has yet to be completed with the current mining contractor. Negotiations have successfully resolved all the key issues except one.
Under the original Term Sheet West Wits was to receive a rate of 0.6 g/t for each tonne of ore extracted from SPP. Since that agreement was entered SPP has evolved into a larger project albeit with lower targeted grades. These current project parameters however have made the original arrangement uncommercial for the operating contractor. As such the parties have in good faith been discussing alternative terms for the project. The parties mutual intention is now to operate SPP as a 50:50 joint venture with all operational responsibilities including subcontractors, processing ore, community and government interaction and working capital requirements to be managed by the contractor. Gold royalties are to the account of West Wits as the rights holder. Such an arrangement covers all costs and processes so that West Wits has no operational responsibilities.
However, despite in principle consensus being reached on virtually all points there has been an ongoing impasse over the imposition by the contractor of what West Wits considers to be an excessive Plant Call Factor (“PCF”) reduction on gold produced. West Wits has insisted on setting the PCF at a fixed rate whereas the contractor has persisted in applying variable rates dependent on overall production outcomes and its “in house” allocation reconciliations. The relevant plants processing recoveries are being detrimentally affected because the plant is also processing third party ore which is often contaminated with organic carbon. For this reason West Wits has sought to establish a fixed PCF which reflects the consistently good recoveries produced by its own clean ore. This issue has delayed the signing of a definitive contract.
In the interim operations are continuing and distributions are being made on the basis of the proposed agreement: i.e. 50:50 basis but with the contractor applying a variable PCF. The Company has reserved its rights to challenge the PCF reduction being applied. The current arrangement only relates to pits 1 and 2 of SPP. Although discussions are continuing the Company is considering all options including replacing the contractor for not only the remaining pits 3, 4 and 5 for the SPP but potentially also Pits 1 and 2. In addition to the SPP the Company is advancing a second surface project and is now in active discussions with other potential operators. West Wits will update the market further in the coming days on its second surface project.
SPP is the first of a pipeline of 5-6 surface opportunities across the Soweto Cluster Gold Project, Gauteng Province, South Africa. The development of SPP forms part of the Company’s broader strategy to develop a number of surface opportunities providing cashflow to allow the Company to further expand its JORC statement from 1.374 Mozs au as well as develop a larger mine plan with the aim of sustaining the production of 100,000 ozs per annum for a minimum 10 years.
Production at the SPP continues to progress. In January circa 7,500 tonnes of ore were extracted which was below the scheduled rate due to the impact of the holiday period as well as grade recoveries being slightly below expectations. In February production was also below expectations as a result of weather related stoppages and equipment failures. Since payments commenced in December the Company has received some $230,000 in distributions from SPP together with a recovery of $80,000 from an agreement with the landowner for contribution to exploration costs.
Michael Quinert, Chairman commented “We are disappointed with the delays in getting SPP running to its full potential. However, the project despite these issues, is operating profitably and surplus cash is being generated. Whilst we are working hard to resolve the current issues with the operating contractor we have also developed alternative strategies which can be implemented, if required. We remain confident in SPP delivering on its potential in the coming months”.
For And On Behalf Of The Board
==> picture [156 x 60] intentionally omitted <==
Michael Quinert Chairman West Wits Mining Limited
For further information visit www.westwitsmining.com
Or Contact
Tim Chapman Telephone: +61 3 8692 9049