AI assistant
VOLTAIC STRATEGIC RESOURCES LTD — Capital/Financing Update 2012
Oct 16, 2012
66024_rns_2012-10-16_3ec6c25d-e806-491c-83b7-312d9cfc333b.pdf
Capital/Financing Update
Open in viewerOpens in your device viewer
==> picture [253 x 57] intentionally omitted <==
ABN 66 138 145 114 16 Phillimore Street Fremantle, WA Tel: 08 94317306
17th October 2012
The Manager Companies Company Announcements Australian Securities Exchange 20 Bridge Street SYDNEY NSW 2000
By: e-lodgement (ASX code: IOG)
Dear Sir/Madam
Operations Update
Incremental Oil and Gas (IOG) is pleased to provide the following operational update:
ROUND MOUNTAIN, CALIFORNIA
SMOOT 8 is expected to spud in the next few weeks. The well is planned as a development well and should intersect the prospective Walker Formation about 70’ high to Smoot 7, which is still producing in excess of 50 bopd after six weeks production. Smoot 7 has been an outstanding result for a well that was completed for only $370k. Incremental has a 100% working interest in the Round Mountain project.
VENTURA, CALIFORNIA
C & H 18 is IOG’s first well in the West Mountain Field, near Ventura in California. It is expected to spud shortly. This well is planned to a measured depth of 6900’, making it the deepest IOG has drilled to date. Itis expected to take 17 days to drill and cost $1.04million with an additional $462k completion cost. The West Mountain Field is characterized by an original hydrocarbon column as thick as 1500’.
C & H 18 will be the first well drilled in the IOG lease since the 1940’s. Many of the earlier wells had initial production rates in excess of 200 bopd. Incremental now holds a 25% working interest in this well and the West Mountain Project, having sold down from its initial 75% interest which decreased the companies risk exposure to this project.
Page | 1
CRP02 2012-10-17 Operations update Oct 2012
FLORENCE, COLORADO
As previously announced, a two well drilling programme is expected to start in Florence in mid November. Both wells will be planned as inclined wells targeting the naturally fractured Pierre Shale, with total measured depths between 3530’ and 4486’. IOG holds a 100% working interest in the Florence project in Colorado.
Yours sincerely
Gerry McGann Managing Director
Page | 2
CRP02 2012-10-17 Operations update Oct 2012