TIVAN LIMITED Investor Presentation 2017

May 9, 2017

65967_rns_2017-05-09_e93a3e94-0d99-49ef-99ed-18a873847f82.pdf

Investor Presentation

Open in viewer

Opens in your device viewer

1

Disclaimer

FORWARD LOOKING STATEMENTS

  • This presentation has been prepared by TNG Ltd. This document contains background information about TNG Ltd current at the date of this presentation. The presentation is in summary form and does not purport to be all inclusive or complete. Recipients should conduct their own investigations and perform their own analysis in order to satisfy themselves as to the accuracy and completeness of the information, statements and opinions contained in this presentation.

  • This presentation is for information purposes only. Neither this presentation nor the information contained in it constitutes an offer, invitation, solicitation or recommendation in relation to the purchase or sale of TNG Ltd shares in any jurisdiction. This presentation may not be distributed in any jurisdiction except in accordance with the legal requirements applicable in such jurisdiction. Recipients should inform themselves of the restrictions that apply in their own jurisdiction. A failure to do so may result in a violation of securities laws in such jurisdiction.

  • This presentation does not constitute investment advice and has been prepared without taking into account the recipient's investment objectives, financial circumstances or particular needs and the opinions and recommendations in this presentation are not intended to represent recommendations of particular investments to particular persons. Recipients should seek professional advice when deciding if an investment is appropriate. All securities transactions involve risks, which include (among others) the risk of adverse or unanticipated market, financial or political developments. To the fullest extent permitted by law, TNG Ltd, its officers, employees, agents and advisers do not make any representation or warranty, express or implied, as to the currency, accuracy, reliability or completeness of any information, statements, opinions, estimates, forecasts or other representations contained in this presentation. No responsibility for any errors or omissions from this presentation arising out of negligence or otherwise is accepted. This presentation may include forward looking statements. Forward looking statements are only predictions and are subject to risks, uncertainties and assumptions which are outside the control of TNG Ltd. Actual values, results or events may be materially different to those expressed or implied in this presentation.

COMPETENT PERSON’S STATEMENTS

  • The information in this report that relates to the Mount Peake Mineral Resource estimates is extracted from an ASX Announcement dated 26 March 2013, (see ASX Announcement – 26 March 2013, “Additional Information on the Mount Peake Resource”, www.tngltd.com.au and www.asx.com.au ), and was completed in accordance with the guidelines of the JORC Code (2012). Initial mining and financial assessment work, based on the Mineral Resource, followed (see ASX Announcement – 15 July 2013, “TNG Considers Two-Stage Development Option for Mount Peake Project, NT ”, www.tngltd.com.au and www.asx.com.au). The Company confirms that it is not aware of any new information or data that materially affects the information included in the original market announcement and that all material assumptions and technical parameters underpinning the Mineral Resource estimates in the relevant market announcement continue to apply and have not materially changed. The Company confirms that the form and context in which the Competent Person’s findings are represented have not been materially modified from the original market announcement.

  • The information in this report that relates to the Mount Peake Ore Reserve estimates is extracted from an ASX Announcement dated 31 July 2015, (see ASX Announcement – 31 July 2015, “Mount Peake Feasibility Study Confirms a World-Class Project”, www.tngltd.com.au and www.asc.com.au) and was completed in accordance with the guidelines of the JORC Code (2012). The Company confirms that it is not aware of any new information or data that materially affects the information included in the original market announcement and that all material assumptions and technical parameters underpinning the Ore Reserve estimates in the relevant market announcement continue to apply and have not materially changed. The Company confirms that the form and context in which the Competent Person’s findings are represented have not been materially modified from the original market announcement.

  • The information in this report that relates to Exploration Results for Mount Peake and Mt Hardy projects are based on information compiled by Exploration Manager Mr Kim Grey B.Sc. and M. Econ. Geol. Mr Grey is also a member of the Australian Institute of Geoscientists and a full time employee of TNG Limited. Mr Grey has sufficient experience relevant to the style of mineralisation and type of deposit under consideration and to the activity which he is undertaking to qualify as a Competent Person as defined in the 2012 Edition of the ‘Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves’. Mr Grey consents to the inclusion in the report of the matters based on his information in the form and context in which it appear.

PRODUCTION TARGETS AND FINANCIAL INFORMATION

  • Information in relation to the Mount Peake Definitive Feasibility, including production targets and financial information, included in this report is extracted from an ASX Announcement dated 31 July 2015, (see ASX Announcement – 31 July 2015, “Mount Peake Feasibility Study Confirms a World-Class Project”, www.tngltd.com.au and www.asx.com.au). The Company confirms that all material assumptions underpinning the production target and financial information set out in the announcement released on 31 July 2015 continue to apply and have not materially changed.

2

TNG: Corporate Overview

Key Corporate and Financial Data

ASX code: TNG
Market capitalisation (at 15c): $121M
Shares on issue: 804M
Cash (at 15 April 2017): $7.3M
Auditors: KPMG
Lawyers: Clifford Chance
Board of Directors
Paul Burton Managing Director
Stuart Crow Non-executive Director
Rex Turkington Non-executive Director
John Davidson Non-executive Director
Major Shareholders
WWB Investments P/L 9.94%
Aosu Investment & Development Co 6.99%
Ao-Zhong International Mineral Resources 3.85%
SMS Investments SA 1.81%
(Directors and their related companies hold approximately 4% of issued capital)
12-month share price– as at 27 April 2017

3

Mount Peake: Project Layout

==> picture [801 x 444] intentionally omitted <==

4

TNG: Mount Peake Highlights

► A Vanadium-Iron-Titanium Project, located in northern Australia’s development hub

► World-scale project with 17 year mine life: circa A$27.3b

► Project Facilitation Agreement (PFA) signed with Northern Territory Government ► TIVAN™metals refinery to produce high-purity products for export including:

► 17,560t V2O5,

► 236,000t TiO2 pigment

► 637,000t pig iron

► Binding Heads of Agreement with SMS Group for design of TIVAN™refinery

► MOU for mine/refinery construction and operation

► Development ready: feasibility study completed in 2015, final approvals due this quarter

► Robust economics: A$4.9b NPV, 41% IRR

► Advanced financing discussions and binding offtake agreements in place

5

Mount Peake Feasibility Study: Key Metrics

Project life 17 years
Mining rate 3Mtpa (Stage 1)_expanding to 6Mtpa(Stage 2)_after 4 years
Pre-production capital estimate_(including all infrastructure)_ A$970 million_(Stage 2 expected to be covered from revenue)_
Total operating costs_(including mining, processing, transport & royalties)_ A$167 per tonne
Total revenue (life-of-mine) A$27.3 billion
Operating cash flow (life-of-mine) A$13.6 billion
Net cash flow (life-of-mine) A$11.6 billion
Payback period 4 years
Net annual operating cash flow A$780M
IRR pre-tax 41%
NPV (at 8% discounted) A$4.9 billion

Refer ASX announcement 31 July 2015.

6

Mount Peake: Concept Mine Layout Plan

==> picture [960 x 396] intentionally omitted <==

7

TNG: A Global Network for Funding, Development and Off-take

8

Mount Peake: Binding Off-take Agreements

Binding LOM Off-take

Agreements

  • Vanadium Products:

  • Binding Life-of-Mine (LOM) Off-take Agreement and Technology Transfer Agreement with WOOJIN Metals

  • WOOJIN’s proprietary technology currently has the world’s highest vanadium recovery rate and is expected to significantly enhance the Project’s profitability

  • Iron Products:

  • Binding Term Sheet for LOM Off-take Agreement with major global commodity trader Gunvor (Singapore)

  • Titanium Products:

==> picture [163 x 80] intentionally omitted <==

==> picture [118 x 122] intentionally omitted <==

  • Off-take to be agreed

9

Mount Peake: Project Development Agreements

  • European-based global engineering giant

  • Binding agreement for engineering, design and construction of the TIVAN™ refinery in Darwin

Project Development Agreements

  • MOU for joint commercial exploitation of TIVAN™ technology

  • Assisting TNG to obtain funding for refinery construction through Export Credit Agencies or other structured finance

  • SMS is one of the most significant writers of new business for Germany’s Export Credit Agencies, which provide finance on competitive terms to new projects or industries which could benefit German industry

  • Global engineering and services provider

  • Pre-Mine development, operations and investment agreement for total project delivery

==> picture [210 x 30] intentionally omitted <==

==> picture [201 x 76] intentionally omitted <==

  • Downer is a leading service provider in markets including mining, minerals and metals processing, transport services, technology and communication services, utilities services, engineering, construction and maintenance (EC&M) and rail, employing around 20,000 people worldwide

10

TIVAN™ Process: The Key Ingredients

Processing polymetallic ores

  • Use of abundant and low-cost raw material : titanomagnetite

  • Extraction of three target metals : Fe, V and Ti

Uses well-proven technology

  • Based on an innovative reconfiguration of proven components

  • Individual process steps successfully demonstrated at industrial scale

Small environmental footprint

  • Hydrometallurgical process

  • No smelters involved

Highly economic process

  • Multiple revenue streams from products with one common processing train

  • Low operating cost

11

Titano-magnetite Ores: Key Strategic Advantages

  • ABUNDANT: many known, accessible and easy-to-mine deposits

  • ILMENITE SHORTAGE: high-grade ilmenites, suitable for synthetic rutile production are becoming scarce

  • GROWING VANADIUM DEMAND: urbanization in fast-growing emerging markets calls for the construction of high rises, requiring large quantities of vanadium-reinforced rebar

  • POTENTIAL FOR ADDITIONAL PRODUCTS: the hydrometallurgical processing of titano-magnetite also allows the extraction of other valuable fractions, such as scandium, high-purity silicon and MgO

==> picture [325 x 178] intentionally omitted <==

==> picture [325 x 179] intentionally omitted <==

12

TIVAN™: Beneficiation Efficiency Flowsheet

==> picture [143 x 20] intentionally omitted <==

13

TIVAN’S Products: Titanium Dioxide

Titanium dioxide pigment (TiO2)

► World demand: 6,600,000tpa

  • TNG’s Phase 1 production: 236,000tpa (3.5% of world demand)

  • ► Main usage: Paint, plastics, paper and inks

  • ► TNG’s cost of production: Approx US$1,380/tonne (dotted line below)

==> picture [699 x 231] intentionally omitted <==

----- Start of picture text -----

5,000
US$1,380/t TiO2 $US/t Real 2016 Values
4,500
4,000
3,500
3,000
2,500
2,000
1,500
1,000
500
0
1970 1971 1972 1973 1974 1975 1976 1977 1978 1979 1980 1981 1982 1983 1984 1985 1986 1987 1988 1989 1990 1991 1992 1993 1994 1995 1996 1997 1998 1999 2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017
----- End of picture text -----

==> picture [172 x 178] intentionally omitted <==

==> picture [172 x 133] intentionally omitted <==

==> picture [172 x 114] intentionally omitted <==

Source: Artikol

14

TIVAN’S Products: Vanadium Pentoxide

Vanadium Pentoxide (V2O5)

World demand: 140,000tpa TNG’s Phase 1 production: 17,560tpa (12.5% of world demand) Main usage: Steel, non-ferrous alloys, chemicals, catalysts and energy storage (VRB) TNG’s cost of production: Approx US$2.50/lb (shaded line below)

==> picture [645 x 234] intentionally omitted <==

----- Start of picture text -----

20
18 US$2.50/lb V2O5 US$/lb
16
14
12
10
8
6
4
2
0
Jul-06 Oct-06 Jan-07 Apr-07 Jul-07 Oct-07 Jan-08 Apr-08 Jul-08 Oct-08 Jan-09 Apr-09 Jul-09 Oct-09 Jan-10 Apr-10 Jul-10 Oct-10 Jan-11 Apr-11 Jul-11 Oct-11 Jan-12 Apr-12 Jul-12 Oct-12 Jan-13 Apr-13 Jul-13 Oct-13 Jan-14 Apr-14 Jul-14 Oct-14 Jan-15 Apr-15 Jul-15 Oct-15 Jan-16 Apr-16 Jul-16
----- End of picture text -----

Source: Metal Bulletin

==> picture [272 x 436] intentionally omitted <==

15

Vanadium Redox Flow Batteries : The future concept for energy storage

Market Forecast – Development of Power on the Energy Storage Market

  • Industry CAGR 2015-2020: 30.8%

  • Stronger growth in utility scale from 2018 onwards

  • US$6 billion market opportunity in 2020

==> picture [268 x 229] intentionally omitted <==

==> picture [330 x 224] intentionally omitted <==

Sources: Gildemeister, Pike Research, Navigant Research, Lux Research, Roland Berger, IHS, SNL Power

==> picture [207 x 400] intentionally omitted <==

16

TIVAN’S Products: Vanadium Electrolyte – a new technology

  • A potential new vanadium application that can be mined and produced by TNG

  • Vanadium flow batteries store energy in the electrolyte fluid

  • Currently this electrolyte fluid has to be imported from overseas

  • Life of a commercial lithium-ion battery = 5 to 8yrs

  • Life of a vanadium flow battery is up to 20yrs

  • At the end of that life the contents of the vanadium battery

  • can be re-used

==> picture [271 x 367] intentionally omitted <==

17

TIVAN’S Products: Pig Iron

Pig Iron

World demand: 1.2 billion tpa TNG’s Phase 1 production: 637,000tpa (0.05% of world demand) Main usage: Steel making TNG’s cost of production: Approx US$137/t (shaded line below)

==> picture [678 x 260] intentionally omitted <==

----- Start of picture text -----

1,200
1,000
US$137/t Pig Iron US$/t
800
600
400
200
0
Source: Metal Bulletin
Jul-06 Oct-06 Jan-07 Apr-07 Jul-07 Oct-07 Jan-08 Apr-08 Jul-08 Oct-08 Jan-09 Apr-09 Jul-09 Oct-09 Jan-10 Apr-10 Jul-10 Oct-10 Jan-11 Apr-11 Jul-11 Oct-11 Jan-12 Apr-12 Jul-12 Oct-12 Jan-13 Apr-13 Jul-13 Oct-13 Jan-14 Apr-14 Jul-14 Oct-14 Jan-15 Apr-15 Jul-15 Oct-15 Jan-16 Apr-16 Jul-16
----- End of picture text -----

==> picture [213 x 410] intentionally omitted <==

18

TNG a key player in the development of the Northern Territory

A pro-resource development government

  • Darwin – Australia’s northern development hub

  • PFA signed in 2017 for TIVAN Metals Refinery

  • ‘Whole of Government’ development approach

  • Established Project Control Group led by government and TNG

  • Excellent geological and infrastructure support

  • Mount Peake Project adding positive economic and social contribution

Working together to create opportunities for Aboriginal people

  • A proactive consultative approach with Traditional Owners

  • Creating pathways for training, employment and business opportunities

  • Positive support for Mount Peake project development

  • Clearance obtained for mine and infrastructure

==> picture [272 x 179] intentionally omitted <==

==> picture [272 x 197] intentionally omitted <==

19

TIVAN™: Northern Territory Government Land Allocation

==> picture [633 x 438] intentionally omitted <==

20

Darwin Processing Plant

==> picture [134 x 19] intentionally omitted <==

==> picture [852 x 433] intentionally omitted <==

21

TNG: Mount Peake Highlights

► A Vanadium-Iron-Titanium Project, located in northern Australia’s development hub ► World-scale project with 17 year mine life: circa A$27.3b

► Project Facilitation Agreement (PFA) signed with Northern Territory Government ► TIVAN™metals refinery to produce high-purity products for export including:

► 17,560t V2O5,

► 236,000t TiO2 pigment

► 637,000t pig iron

► Binding Heads of Agreement with SMS Group for design of TIVAN™refinery

► MOU for mine/refinery construction and operation

► Development ready: feasibility study completed in 2015, final approvals due this quarter

► Robust economics: A$4.9b NPV, 41% IRR

► Advanced financing discussions and binding offtake agreements in place

22