Tata Power Co. Ltd Capital/Financing Update 2023

Dec 1, 2023

60774_rns_2023-12-01_a681be0c-2987-43c7-b0ae-fd69bee7f387.pdf

Capital/Financing Update

Open in viewer

Opens in your device viewer

==> picture [92 x 73] intentionally omitted <==

December 1, 2023

BSE Limited Corporate Relationship Department 1[st] Floor, New Trading Ring Rotunda Bldg., P. J. Towers Dalal Street, Fort Mumbai – 400 001. Scrip Code: 500400

National Stock Exchange of India Limited Exchange Plaza, 5[th] Floor Plot No. C/1, G Block Bandra-Kurla Complex Bandra (East) Mumbai – 400 051. Symbol: TATAPOWER EQ

Dear Sirs,

Disclosure under Regulation 30 of the SEBI (Listing Obligations and Disclosure Requirements) Regulations, 2015

Pursuant to Regulation 30 of the Securities and Exchange Board of India (Listing Obligations and Disclosure Requirements) Regulations, 2015 ("Listing Regulations"), we would like to inform that the Company has received Letter of Intent (LOI) from PFC Consulting Limited (a subsidiary of Power Finance Corporation) to acquire Bikaner-III Neemrana-II Transmission Limited, a project special purpose vehicle (SPV).

Kindly find below details pursuant to SEBI Circular No. SEBI/HO/CFD/CFD-PoD-1/P/CIR/2023/123 dated July 13, 2023 (‘SEBI Circular’) -

S. No. Particulars Response
a) Name of the entity to which order(s)/contract(s)
is awarded;
The Tata Power Company Limited
b) Whether order(s) / contract(s) is awarded to
domestic/ international entity
Domestic Entity
c) Significant terms and conditions of
order(s)/contract(s) awarded, in brief;
The Project SPV (Bikaner III Neemrana
II Transmission Limited) would be
developed
on
Build-Own-Operate-
Transfer basis, to provide transmission
service for 35 years from the schedule
date of commercial operation (SCOD)
which is 24 months from the date of SPV
acquisition.
Major terms and conditions:
SCOD– 24 months from Effective date
(SPV transfer)
Transmission
Service
Agreement
period– 35 years
Annual
Transmission
charges
-
₹ 162.659 crore
Payment Security– As per CERC
Sharing Regulations
Contract Performance Guarantee
₹ 42 crore
d) Time period, if any, associated with the
order(s)/contract(s)
The award is placed on the Company
for a period of 35 years.
e) Broad commercial consideration or size of the
order(s)/contract(s);
Estimated Project Cost
~₹1,544 crore

==> picture [467 x 108] intentionally omitted <==

==> picture [92 x 73] intentionally omitted <==

Annual Transmission charges –
₹ 162.659 crore payable for 35 years.
f) Whether the promoter/ promoter group/group
companies have any interest in that entity to
whom the order(s)/contract(s) is awarded? If
Yes, nature of interest and details thereof;
Not applicable
g) Whether the same would fall within related
party transactions? If yes, whether the same is
done at“arm’s length”.
Not applicable

The above information is being made available on the website of the Company: www.tatapower.com.

This is for your information and records.

Yours faithfully, For The Tata Power Company Limited HANOZ Digitally signed by HANOZ MINOO MINOO MISTRY Date: 2023.12.01 MISTRY 21:46:27 +05'30'

(H. M. Mistry) Company Secretary FCS 3606