AI assistant
SUNSTONE METALS LTD — Capital/Financing Update 2013
Apr 10, 2013
65870_rns_2013-04-10_15ddd72a-c769-4819-83d0-30b605e5ab4a.pdf
Capital/Financing Update
Open in viewerOpens in your device viewer
11 APRIL 2013

Viscaria Base Case NPV Increases to US$97M
HIGHLIGHTS
- Updated Scoping Study results indicate that the potential NPV of the Base Case open pit mining scenario is now US$97 million dollars (using US$3.25/lb copper price, US$150/t magnetite concentrate price and 60° pit slope), increased by US$46M from prior to current drill program;
- Increase in Base Case NPV relates to revised open pit analysis of the upgraded D Zone Mineral Resource released on 4 April 2013;
- Result shows that converting part of the Development Case A exploration target into Mineral Resources has been achieved and is still ongoing with further drilling at D Zone;
- Updated Scoping Study results indicate that the Base Case open pit mining scenario produces 10,000t of Cu and 343,000t of Fe per annum at a C1 cash cost (net of Fe credits) of US$0.65/lb, over a 7 year mine life;
- At US$3.50/lb copper price the Base Case open pit mining scenario has a NPV of US$119M;
- The upgraded D Zone Mineral Resource is currently being subjected to further economic analysis to estimate the value of any potentially underground mineable tonnes (Development Case C).
Australian resources company Avalon Minerals Limited ('Avalon' or 'Company') (ASX: AVI) is pleased to announce the results of a revision of the Base Case open pit mining scenario Net Present Value ('NPV') from the Scoping Study completed on the Viscaria Project by Xstract Mining Consultants (announced 11 October 2012).
The updated Scoping Study revised the Base Case open pit mining scenario using the interim updated Mineral Resources currently defined on the Viscaria Project, which were announced to the ASX on 4 April 2013. The economic assessments used price assumptions of US$3.25/lb copper and US$150/t magnetite concentrate as well as a 60° pit slope.

The Company's Managing Director, Mr Jeremy Read, said "By recalculating the Base Case open pit mining scenario using the upgraded interim D Zone Mineral Resource announced last week and revised pit slopes, the NPV has increased by US$46 million dollars to US$97 million dollars, which is an excellent achievement. This shows that we are well on the way to delivering on Development Case A from the October 2012 Scoping Study."
"As the D Zone resource extension drill program still has approximately 30% to go to complete the planned program, there is still potential to continue to grow the D Zone Mineral Resource and deliver further value creation through conversion of exploration targets to Mineral Resources, which should further increase the NPV of D Zone" he said.
"Currently, we are assessing various options for underground mining the plunging shoots of +2% CuEq mineralisation at D Zone and we believe there is further value to be created through understanding the full underground mining potential of D Zone" Mr Read said.
Revised Base Case open pit mining scenario
The revised Base Case open pit mining scenario assessed the viability and potential value of the currently defined Mineral Resources on the Viscaria Copper Project, which are based upon the interim Mineral Resources announced to the ASX on 4 April 2013 (see Table 1). These interim Mineral Resources were subjected to open pit optimisations using the parameters and revenue assumptions outlined in Table 2. Using these parameters several open pit shells were generated along the near-surface trends of the A Zone, B Zone and D Zone Mineral Resources (Figure 1). During this exercise it was established that only the D Zone Pit and the A Zone Pit-A significantly contributed to the project NPV and therefore, only these prospects were included in the Base Case open pit mining scenario. Figure 2 and Table 3 show the production profile developed for the Base Case scenario.
| Resource Name | Classification | Tonnes (t) | Cu Grade(%) | Cu Metal (t) |
|---|---|---|---|---|
| Measured | 14,439,000 | 1.7 | 240,000 | |
| Indicated | 4,690,000 | 1.2 | 57,000 | |
| A Zone* | Inferred | 2,480,000 | 1.0 | 26,000 |
| Subtotal | 21,609,000 | 1.5 | 323,000 | |
| Measured | 123,000 | 1.3 | 2,000 | |
| Indicated | 4,118,000 | 0.7 | 30,000 | |
| B Zone* | Inferred | 15,410,000 | 0.8 | 118,000 |
| Subtotal | 19,651,000 | 0.8 | 150,000 | |
| Indicated** | 5,200,000 | 0.9 | 48,000 | |
| D ZoneCu Resource | Inferred** | 2,700,000 | 0.8 | 23,000 |
| Subtotal | 7,900,000 | 0.9 | 71,000 | |
| Overall Cu | Total | 49,160,000 | 1.1 | 544,000 |
| Table 1: Currently Defined Mineral Resources on the Viscaria Project. |
|---|

| Resource Name | Classification | Tonnes (t) | Fe Grade (%) | Fe MassRecovery(%) | Fe Metal (t) |
|---|---|---|---|---|---|
| D Zone | Indicated*** | 12,100,000 | 27.3 | 31.3 | 4,000,000 |
| Fe Resource | Inferred*** | 6,800,000 | 25.6 | 31.6 | 2,200,000 |
| Overall Fe | Total | 18,900,000 | 26.9 | 32.6 | 6,200,000 |
* 2011 Mineral Resources for A Zone and B Zone are reported above a cut‐off grade of 0.4% Cu.
** 2013 Copper Mineral Resource for D Zone above a cut‐off grade of 0.4% Cu.
*** 2013 Iron Mineral Resource for D Zone above a cut‐off grade of 15% Fe Mass Recovery.
Note that the total Indicated and Inferred Mineral Resource reported for Copper (Table 1) and for above 15% Fe Mass Recovery are not mutually exclusive; the Mineral Resource for above 15% Fe Mass Recovery excludes 1.8 million tonnes at 0.8% Cu above a cut-off grade of 0.4% Cu.
| Table 2: Pit optimisation parameters and revenue assumptions | ||||||
|---|---|---|---|---|---|---|
| -- | -- | -- | -- | -- | -- | -------------------------------------------------------------- |
| Parameter | Unit | Value | Comments |
|---|---|---|---|
| Overall pit slope angle | Degrees | 55 | |
| Copper Price | US$/t | US$7,165 | US$3.25/lb Cu |
| Magnetite Price | US$/t | US$150 | Magnetite Concentrate price |
| Mining Cost (ore) | US$/t | US$4.55 | |
| Mining Cost (waste) | US$/t | US$4.55 | |
| Mining Recovery | % | 95% | |
| Mining Dilution | % | 5% | |
| % Cu | 90% | ||
| Metallurgical Recovery | % Fe | 76% | |
| % Cu | 25% | ||
| Concentrate Grade | % Fe | 69% | |
| Processing Costs | US$/t ore | US$12.04 | |
| Admin Costs | US$/t ore | US$3.08 | |
| Payable Copper | % Cu contained | 98% | |
| Payable Magnetite | % Fe contained | 98% | |
| Copper Conc. Treatmentcharge | c/lb Cu | 45 | |
| Copper Conc.Refining charge | c/lb Cu | 4.5 | |
| MagnetiteConc.Treatment charge | US$/dmt | 28 |




Figure 2: Base Case production profile

| Table 3: Base Case production summary | |||||||
|---|---|---|---|---|---|---|---|
| Year | TonnesMined(kt) | % Cu | % Fe | CopperConcProduced(kDMT) | ContainedCopper(kt) | MagnetiteConcProduced(kDMT) | ContainedIron(kt) |
| 2014 | |||||||
| 2015 | 2,100 | 0.53 | 20.4 | 40 | 10 | 494 | 343 |
| 2016 | 2,100 | 0.53 | 20.4 | 40 | 10 | 494 | 343 |
| 2017 | 2,100 | 0.53 | 20.4 | 40 | 10 | 494 | 343 |
| 2018 | 2,100 | 0.53 | 20.4 | 40 | 10 | 494 | 343 |
| 2019 | 2,100 | 0.53 | 20.4 | 40 | 10 | 494 | 343 |
| 2020 | 1,600 | 0.53 | 20.4 | 30 | 17 | 369 | 256 |
| 2021 | |||||||
| Total | 12,100 | 0.53 | 20.4 | 230 | 57 | 2,865 | 1,971 |
The economic Base Case open pit mining scenario was assessed using pit slope angles of 55° and 60°. The 55° pit slope angle option is given in Table 4 and the 60° pit slope angle option is given in Table 5.
Table 4: Summary of the economic assessment of the Base Case open pit mining scenario at 55° overall pit wall slope
| Base Case | Revised D Zone Open Pit and A Zone Open Pit-A at 55° Overall Pit Slope | |||
|---|---|---|---|---|
| Resource Base | 11.5 Mt @ 0.55% Cu 21.4% Fe | Undiluted by mining factors | ||
| Optimum Mining Rate | 2.1 Mtpa | |||
| Mine Life | 6 years | |||
| Pre-Production Capex | US$138 M | Includes US$17.2M pre-strip | ||
| Life-of-Mine Capex | US$150 M | Excludes closure costs | ||
| NPV10% REAL | US$76 M | US$3.25/lbCuUS$150/tMagnetite concentrate | ||
| NPV + | US$96 M | US$3.50/lb Cu | ||
| NPV - | US$55 M | US$3.00/lb Cu |

Table 5: Summary of the economic assessment of the Base Case open pit mining scenario at 60° overall pit wall slope
| Base Case | Slope | Revised D Zone Open Pit and A Zone Open Pit-A at 60° Overall Pit |
|---|---|---|
| Resource Base | 13.3 Mt @ 0.54% Cu 22.2% Fe | Undiluted by mining factors |
| Optimum Mining Rate | 2.1 Mtpa | |
| Mine Life | 7 years | |
| Pre-Production Capex | US$138.7 M | Includes US$17.9M pre-strip |
| Life-of-Mine Capex | US$152.2 M | Excludes closure costs |
| NPV10% REAL | US$97 M | US$3.25/lbCuUS$150/tMagnetiteconcentrate |
| NPV + | US$119 M | US$3.50/lbCuUS$150/tMagnetiteconcentrate |
| NPV - | US$75 M | US$3.00/lbCuUS$150/tMagnetiteconcentrate |
Cost and Revenue Assumptions
The capital costs used in the Base Case open pit mining scenario have been summarised in Table 6, with the operating costs assumptions in Table 7. The C1 copper cash operating costs, net of iron credits, for the Base Case open pit mining scenario are predicted to be $0.65/lb Cu, which is in the lower quartile of copper producers.
| Item | Base Case US$M | Comments |
|---|---|---|
| Process Plant | 111.7 | Scalable on production capacity |
| Pit D site establishment | 2.5 | Includes provision of site services andaccess roads |
| Pit A site establishment | 1.7 | |
| Pre-Strip | 17.2 | |
| Tailings Storage Facility | 5.0 | |
| Replacement Capital | 11.7 | |
| Closure Costs | - | Not Included |
| Total | 150 |
| Table 6: Capital Cost assumptions | ||||
|---|---|---|---|---|
| -- | -- | -- | -- | ----------------------------------- |

| Parameter | Unit | Value | Comments |
|---|---|---|---|
| Mining Cost (ore) | US$/t | $4.55 | |
| Mining Cost (waste) | US$/t | $4.55 | |
| Processing Costs | US$/t ore | $12.04 | Variable – assumes 40% fixedcosts and 12.04/t @ 1.5Mtpa |
| Admin Costs | US$/t ore | $3.08 | |
| Copper Conc. Transport | US$/DMT conc | 15.75 | Assumes local smelter |
| Magnetite Conc. Transport | US$/DMT conc | 1.50 | Assumes slurry pipe to LKAB |
Table 7: Operating Cost assumptions
Comparison with previous Base Case results
The economic summary of the previous Base Case open pit mining scenario as announced in October 2012 is displayed in Table 8. The current Base Case open pit mining scenario economic summary has an increased resource base of 0.5Mt but more importantly, a higher copper grade of 0.55% Cu, compared to 0.50% Cu previously. The increased grade and size of the potential open pittable portion of the D Zone Mineral Resource, as well as a reduction to the pre-production capital costs has increased the Base Case open pit mining scenario NPV from US$61 million dollars to US$76 million for the 55° pit slope angle option and the NPV to US$97M for the 60° pit slope angle option.
| Table 8: Summary of the economic assessment of the previous Base Case mining scenario | ||
|---|---|---|
| --------------------------------------------------------------------------------------- | -- | -- |
| Base Case | D Zone Open Pit and A Zone Open Pit-A | |
|---|---|---|
| Resource Base | 11.0 Mt @ 0.50% Cu 22.2% Fe | Undiluted by mining factors |
| Optimum Mining Rate | 2.1 Mtpa | |
| Mine Life | 5.5 years | |
| Pre-Production Capex | US$144 M | Includes $18.3M pre-strip |
| Life-of-Mine Capex | US$155 M | Excludes closure costs |
| NPV10% REAL | US$61 M | US$3.25/lb Cu US$150/t Magnetiteconcentrate |
Further Resource Definition Drill Program
The current resource extension drill program at the D Zone Prospect is only 70% complete. Therefore, there is potential to continue to grow the D Zone Mineral Resource and deliver further value creation through conversion of exploration targets to Mineral Resources.

Economic Analysis of Underground Mining Potential
Currently, the upgraded D Zone Mineral Resource is being subjected to further economic analysis to estimate the value of any potentially underground mineable tonnes (Development Case C from the October 2012 Scoping Study). This estimate is expected to be announced within the next few weeks.
For further information please visit www.avalonminerals.com.au or contact:
Mr Jeremy Read - Managing Director Avalon Minerals Limited Tel: 07 3368 9888 Em: [email protected] Web: www.twitter.com/avalonminerals
Mr James Harris Professional Public Relations Tel: 08 9388 0944 Em: [email protected]
Competent Persons Statement
The information in this report that relates to Mineral Resources and exploration targets is based upon information reviewed by Mr Jeremy Read BSc (Hons) who is a Member of the Australasian Institute of Mining and Metallurgy. Mr Read is a full time employee of Avalon Minerals Ltd and has sufficient experience which is relevant to the style of mineralisation and type of deposit under consideration and to the activity which he is undertaking to qualify as a Competent Person as defined in the 2004 Edition of the "Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves". Mr Read consents to the inclusion in the report of the matters based on his information in the form and context in which it appears.
The Mineral Resource estimate for the D Zone Prospect was compiled and prepared by Matthew Readford (MAusIMM) of Xstract Mining Consultants who is a Competent Person as defined by the Australasian Code for the reporting of Exploration Results, Mineral Resources and Ore Reserves (JORC Code) 2004 Edition and who consents to the inclusion in this report of the matters based on the information in the form and context in which it appears.
The Scoping Study results were compiled and prepared by Tim Horsley (MAusIMM) of Xstract Mining Consultants who is a Competent Person as defined by the Australasian Code for the reporting of Exploration Results, Mineral Resources and Ore Reserves (JORC Code) 2004 Edition and who consents to the inclusion in this report of the matters based on the information in the form and context in which it appears.
The Scoping Study referred to in this announcement is based on low level technical and economic assessments and is insufficient to support Ore Reserves or to provide assurance of an economic development case at this stage or to provide certainty that the conclusions of the Scoping Study will be realised.
The Base Case includes material that from Inferred Mineral Resources and therefore, exploration drilling and reestimation may result in changes to the economically minable portion of the resources.
Development Case A, B and C includes material that has not yet been discovered or defined and is considered an exploration target.
JORC – Exploration Targets
It is common practice for a company to comment on and discuss its exploration in terms of target size and type. The information relating to exploration targets should not be misunderstood or misconstrued as an estimate of Mineral Resources or Ore Reserves. Hence the terms Resource(s) or Reserve(s) have not been used in this context. The potential quantity and grade is conceptual in nature, since there has been insufficient work completed to define them beyond exploration targets and that it is uncertain if further exploration will result in the determination of a Mineral Resource.