Skip to main content

AI assistant

Sign in to chat with this filing

The assistant answers questions, extracts KPIs, and summarises risk factors directly from the filing text.

SUNSTONE METALS LTD Capital/Financing Update 2013

Apr 10, 2013

65870_rns_2013-04-10_15ddd72a-c769-4819-83d0-30b605e5ab4a.pdf

Capital/Financing Update

Open in viewer

Opens in your device viewer

11 APRIL 2013

Viscaria Base Case NPV Increases to US$97M

HIGHLIGHTS

  • Updated Scoping Study results indicate that the potential NPV of the Base Case open pit mining scenario is now US$97 million dollars (using US$3.25/lb copper price, US$150/t magnetite concentrate price and 60° pit slope), increased by US$46M from prior to current drill program;
  • Increase in Base Case NPV relates to revised open pit analysis of the upgraded D Zone Mineral Resource released on 4 April 2013;
  • Result shows that converting part of the Development Case A exploration target into Mineral Resources has been achieved and is still ongoing with further drilling at D Zone;
  • Updated Scoping Study results indicate that the Base Case open pit mining scenario produces 10,000t of Cu and 343,000t of Fe per annum at a C1 cash cost (net of Fe credits) of US$0.65/lb, over a 7 year mine life;
  • At US$3.50/lb copper price the Base Case open pit mining scenario has a NPV of US$119M;
  • The upgraded D Zone Mineral Resource is currently being subjected to further economic analysis to estimate the value of any potentially underground mineable tonnes (Development Case C).

Australian resources company Avalon Minerals Limited ('Avalon' or 'Company') (ASX: AVI) is pleased to announce the results of a revision of the Base Case open pit mining scenario Net Present Value ('NPV') from the Scoping Study completed on the Viscaria Project by Xstract Mining Consultants (announced 11 October 2012).

The updated Scoping Study revised the Base Case open pit mining scenario using the interim updated Mineral Resources currently defined on the Viscaria Project, which were announced to the ASX on 4 April 2013. The economic assessments used price assumptions of US$3.25/lb copper and US$150/t magnetite concentrate as well as a 60° pit slope.

The Company's Managing Director, Mr Jeremy Read, said "By recalculating the Base Case open pit mining scenario using the upgraded interim D Zone Mineral Resource announced last week and revised pit slopes, the NPV has increased by US$46 million dollars to US$97 million dollars, which is an excellent achievement. This shows that we are well on the way to delivering on Development Case A from the October 2012 Scoping Study."

"As the D Zone resource extension drill program still has approximately 30% to go to complete the planned program, there is still potential to continue to grow the D Zone Mineral Resource and deliver further value creation through conversion of exploration targets to Mineral Resources, which should further increase the NPV of D Zone" he said.

"Currently, we are assessing various options for underground mining the plunging shoots of +2% CuEq mineralisation at D Zone and we believe there is further value to be created through understanding the full underground mining potential of D Zone" Mr Read said.

Revised Base Case open pit mining scenario

The revised Base Case open pit mining scenario assessed the viability and potential value of the currently defined Mineral Resources on the Viscaria Copper Project, which are based upon the interim Mineral Resources announced to the ASX on 4 April 2013 (see Table 1). These interim Mineral Resources were subjected to open pit optimisations using the parameters and revenue assumptions outlined in Table 2. Using these parameters several open pit shells were generated along the near-surface trends of the A Zone, B Zone and D Zone Mineral Resources (Figure 1). During this exercise it was established that only the D Zone Pit and the A Zone Pit-A significantly contributed to the project NPV and therefore, only these prospects were included in the Base Case open pit mining scenario. Figure 2 and Table 3 show the production profile developed for the Base Case scenario.

Resource Name Classification Tonnes (t) Cu Grade(%) Cu Metal (t)
Measured 14,439,000 1.7 240,000
Indicated 4,690,000 1.2 57,000
A Zone* Inferred 2,480,000 1.0 26,000
Subtotal 21,609,000 1.5 323,000
Measured 123,000 1.3 2,000
Indicated 4,118,000 0.7 30,000
B Zone* Inferred 15,410,000 0.8 118,000
Subtotal 19,651,000 0.8 150,000
Indicated** 5,200,000 0.9 48,000
D ZoneCu Resource Inferred** 2,700,000 0.8 23,000
Subtotal 7,900,000 0.9 71,000
Overall Cu Total 49,160,000 1.1 544,000
Table 1: Currently Defined Mineral Resources on the Viscaria Project.

Resource Name Classification Tonnes (t) Fe Grade (%) Fe MassRecovery(%) Fe Metal (t)
D Zone Indicated*** 12,100,000 27.3 31.3 4,000,000
Fe Resource Inferred*** 6,800,000 25.6 31.6 2,200,000
Overall Fe Total 18,900,000 26.9 32.6 6,200,000

* 2011 Mineral Resources for A Zone and B Zone are reported above a cut‐off grade of 0.4% Cu.

** 2013 Copper Mineral Resource for D Zone above a cut‐off grade of 0.4% Cu.

*** 2013 Iron Mineral Resource for D Zone above a cut‐off grade of 15% Fe Mass Recovery.

Note that the total Indicated and Inferred Mineral Resource reported for Copper (Table 1) and for above 15% Fe Mass Recovery are not mutually exclusive; the Mineral Resource for above 15% Fe Mass Recovery excludes 1.8 million tonnes at 0.8% Cu above a cut-off grade of 0.4% Cu.

Table 2: Pit optimisation parameters and revenue assumptions
-- -- -- -- -- -- --------------------------------------------------------------
Parameter Unit Value Comments
Overall pit slope angle Degrees 55
Copper Price US$/t US$7,165 US$3.25/lb Cu
Magnetite Price US$/t US$150 Magnetite Concentrate price
Mining Cost (ore) US$/t US$4.55
Mining Cost (waste) US$/t US$4.55
Mining Recovery % 95%
Mining Dilution % 5%
% Cu 90%
Metallurgical Recovery % Fe 76%
% Cu 25%
Concentrate Grade % Fe 69%
Processing Costs US$/t ore US$12.04
Admin Costs US$/t ore US$3.08
Payable Copper % Cu contained 98%
Payable Magnetite % Fe contained 98%
Copper Conc. Treatmentcharge c/lb Cu 45
Copper Conc.Refining charge c/lb Cu 4.5
MagnetiteConc.Treatment charge US$/dmt 28

Figure 2: Base Case production profile

Table 3: Base Case production summary
Year TonnesMined(kt) % Cu % Fe CopperConcProduced(kDMT) ContainedCopper(kt) MagnetiteConcProduced(kDMT) ContainedIron(kt)
2014
2015 2,100 0.53 20.4 40 10 494 343
2016 2,100 0.53 20.4 40 10 494 343
2017 2,100 0.53 20.4 40 10 494 343
2018 2,100 0.53 20.4 40 10 494 343
2019 2,100 0.53 20.4 40 10 494 343
2020 1,600 0.53 20.4 30 17 369 256
2021
Total 12,100 0.53 20.4 230 57 2,865 1,971

The economic Base Case open pit mining scenario was assessed using pit slope angles of 55° and 60°. The 55° pit slope angle option is given in Table 4 and the 60° pit slope angle option is given in Table 5.

Table 4: Summary of the economic assessment of the Base Case open pit mining scenario at 55° overall pit wall slope

Base Case Revised D Zone Open Pit and A Zone Open Pit-A at 55° Overall Pit Slope
Resource Base 11.5 Mt @ 0.55% Cu 21.4% Fe Undiluted by mining factors
Optimum Mining Rate 2.1 Mtpa
Mine Life 6 years
Pre-Production Capex US$138 M Includes US$17.2M pre-strip
Life-of-Mine Capex US$150 M Excludes closure costs
NPV10% REAL US$76 M US$3.25/lbCuUS$150/tMagnetite concentrate
NPV + US$96 M US$3.50/lb Cu
NPV - US$55 M US$3.00/lb Cu

Table 5: Summary of the economic assessment of the Base Case open pit mining scenario at 60° overall pit wall slope

Base Case Slope Revised D Zone Open Pit and A Zone Open Pit-A at 60° Overall Pit
Resource Base 13.3 Mt @ 0.54% Cu 22.2% Fe Undiluted by mining factors
Optimum Mining Rate 2.1 Mtpa
Mine Life 7 years
Pre-Production Capex US$138.7 M Includes US$17.9M pre-strip
Life-of-Mine Capex US$152.2 M Excludes closure costs
NPV10% REAL US$97 M US$3.25/lbCuUS$150/tMagnetiteconcentrate
NPV + US$119 M US$3.50/lbCuUS$150/tMagnetiteconcentrate
NPV - US$75 M US$3.00/lbCuUS$150/tMagnetiteconcentrate

Cost and Revenue Assumptions

The capital costs used in the Base Case open pit mining scenario have been summarised in Table 6, with the operating costs assumptions in Table 7. The C1 copper cash operating costs, net of iron credits, for the Base Case open pit mining scenario are predicted to be $0.65/lb Cu, which is in the lower quartile of copper producers.

Item Base Case US$M Comments
Process Plant 111.7 Scalable on production capacity
Pit D site establishment 2.5 Includes provision of site services andaccess roads
Pit A site establishment 1.7
Pre-Strip 17.2
Tailings Storage Facility 5.0
Replacement Capital 11.7
Closure Costs - Not Included
Total 150
Table 6: Capital Cost assumptions
-- -- -- -- -----------------------------------

Parameter Unit Value Comments
Mining Cost (ore) US$/t $4.55
Mining Cost (waste) US$/t $4.55
Processing Costs US$/t ore $12.04 Variable – assumes 40% fixedcosts and 12.04/t @ 1.5Mtpa
Admin Costs US$/t ore $3.08
Copper Conc. Transport US$/DMT conc 15.75 Assumes local smelter
Magnetite Conc. Transport US$/DMT conc 1.50 Assumes slurry pipe to LKAB

Table 7: Operating Cost assumptions

Comparison with previous Base Case results

The economic summary of the previous Base Case open pit mining scenario as announced in October 2012 is displayed in Table 8. The current Base Case open pit mining scenario economic summary has an increased resource base of 0.5Mt but more importantly, a higher copper grade of 0.55% Cu, compared to 0.50% Cu previously. The increased grade and size of the potential open pittable portion of the D Zone Mineral Resource, as well as a reduction to the pre-production capital costs has increased the Base Case open pit mining scenario NPV from US$61 million dollars to US$76 million for the 55° pit slope angle option and the NPV to US$97M for the 60° pit slope angle option.

Table 8: Summary of the economic assessment of the previous Base Case mining scenario
--------------------------------------------------------------------------------------- -- --
Base Case D Zone Open Pit and A Zone Open Pit-A
Resource Base 11.0 Mt @ 0.50% Cu 22.2% Fe Undiluted by mining factors
Optimum Mining Rate 2.1 Mtpa
Mine Life 5.5 years
Pre-Production Capex US$144 M Includes $18.3M pre-strip
Life-of-Mine Capex US$155 M Excludes closure costs
NPV10% REAL US$61 M US$3.25/lb Cu US$150/t Magnetiteconcentrate

Further Resource Definition Drill Program

The current resource extension drill program at the D Zone Prospect is only 70% complete. Therefore, there is potential to continue to grow the D Zone Mineral Resource and deliver further value creation through conversion of exploration targets to Mineral Resources.

Economic Analysis of Underground Mining Potential

Currently, the upgraded D Zone Mineral Resource is being subjected to further economic analysis to estimate the value of any potentially underground mineable tonnes (Development Case C from the October 2012 Scoping Study). This estimate is expected to be announced within the next few weeks.

For further information please visit www.avalonminerals.com.au or contact:

Mr Jeremy Read - Managing Director Avalon Minerals Limited Tel: 07 3368 9888 Em: [email protected] Web: www.twitter.com/avalonminerals

Mr James Harris Professional Public Relations Tel: 08 9388 0944 Em: [email protected]

Competent Persons Statement

The information in this report that relates to Mineral Resources and exploration targets is based upon information reviewed by Mr Jeremy Read BSc (Hons) who is a Member of the Australasian Institute of Mining and Metallurgy. Mr Read is a full time employee of Avalon Minerals Ltd and has sufficient experience which is relevant to the style of mineralisation and type of deposit under consideration and to the activity which he is undertaking to qualify as a Competent Person as defined in the 2004 Edition of the "Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves". Mr Read consents to the inclusion in the report of the matters based on his information in the form and context in which it appears.

The Mineral Resource estimate for the D Zone Prospect was compiled and prepared by Matthew Readford (MAusIMM) of Xstract Mining Consultants who is a Competent Person as defined by the Australasian Code for the reporting of Exploration Results, Mineral Resources and Ore Reserves (JORC Code) 2004 Edition and who consents to the inclusion in this report of the matters based on the information in the form and context in which it appears.

The Scoping Study results were compiled and prepared by Tim Horsley (MAusIMM) of Xstract Mining Consultants who is a Competent Person as defined by the Australasian Code for the reporting of Exploration Results, Mineral Resources and Ore Reserves (JORC Code) 2004 Edition and who consents to the inclusion in this report of the matters based on the information in the form and context in which it appears.

The Scoping Study referred to in this announcement is based on low level technical and economic assessments and is insufficient to support Ore Reserves or to provide assurance of an economic development case at this stage or to provide certainty that the conclusions of the Scoping Study will be realised.

The Base Case includes material that from Inferred Mineral Resources and therefore, exploration drilling and reestimation may result in changes to the economically minable portion of the resources.

Development Case A, B and C includes material that has not yet been discovered or defined and is considered an exploration target.

JORC – Exploration Targets

It is common practice for a company to comment on and discuss its exploration in terms of target size and type. The information relating to exploration targets should not be misunderstood or misconstrued as an estimate of Mineral Resources or Ore Reserves. Hence the terms Resource(s) or Reserve(s) have not been used in this context. The potential quantity and grade is conceptual in nature, since there has been insufficient work completed to define them beyond exploration targets and that it is uncertain if further exploration will result in the determination of a Mineral Resource.