TANTALUM PROJECT CONFERENCE LEAFLET

The Directors of Gippsland Limited [ASX: GIP, DB: GIX] advise that the following leaflet relating to the Company's Abu Dabbab - Nuweibi Tantalum Project will be distributed at upcoming national and international resource industry conferences.

RJ (Jack) Telford Director, Chief Executive Officer

For further information, please contact:

Jack Telford Gippsland Limited Tel: +61 8 9340 6000 Email: [email protected] Web: www.gippslandltd.com

Abu Dabbab – Nuweibi Tantalum Project Non-conflict tantalum for several decades

Location: Red Sea Coast –Egypt
Resources: Abu Dabbab*44.5 million tonnes -Nuweibi*98 million tonnes -
TotalResource: 142.5 million tonnes*
Ore Reserves: million tonnes*30.24
Production: Based upon an initial mill feed of 2 million tonnes per year
Tantalum (Ta2O5) 650,000 pounds per year World's largest tantalum miner
Tinmetal 1,530 tonnesper year Significant additional revenue
Feldspar 1.5 million tonnes per year Significant additional revenue
Process waste 0.5 million tonnesper year 80% of all ore mined to be sold

Gippsland Limited is an Australian based company listed on the Australian Stock Exchange (ASX: GIP), and also trades of the Frankfurt Deutsche Börse (DB: GIX). Through its subsidiary Tantalum Egypt JSC, it holds a controlling interest in the Abu Dabbab and Nuweibi tantalum-tin-feldspar projects via 30 year Mining Licences which can be extended for a further 30 years.

The 44.5 million tonne Abu Dabbab project is forecast to become the world's largest tantalum mine with an expected mine life in excess of 20 years. The nearby 98 million tonne Nuweibi deposit will extend this project life significantly.

The Abu Dabbab project is exceptional in that approximately 80% of all ore mined is expected to be sold, either in the form of tantalum, tin metal or feldspar. The contribution of by-products to revenue is expected to ensure the project sets a new global standard for low net cash cost of production for its tantalum products. Shipment of the Abu Dabbab tantalum product will not be constrained by IMO Class 7 (Radioactivity) regulations.

Gippsland Directors consider the Abu Dabbab project to be the world's most advanced new tantalum project, which is unique as it has the JORC Code compliant Resource base to sustain long-term, low-cost, non-conflict tantalum production for several decades.

Table 1:Abu Dabbab Mineral Resources (100g/t Ta2O5cut-off)
Category Million Tonnes Ta2O5(g/t) Sn (%)
Measured Resource 15.2 290 0.143%
Indicated Resource 17.3 250 0.078%
Inferred Resource 12 200 0.03%
Total Resource 44.5 250 0.09%
Table 2:Abu Dabbab Ore Reserves(100g/t Ta2O5cut-off)
Category Million tonnes Ta2O5(g/t) Sn (%)
Proved Ore Reserve 15.20 260 0.133
Probable Ore Reserve 15.04 250 0.084
Total Proved & Probable Ore Reserve 30.24 255 0.109
Table 3:Nuweibi Mineral Resources (100g/t Ta2O5cut-off)
Category Million Tonnes Ta2O5(g/t) Nb2O5(g/t)
Indicated Resource 48 147 90
Inferred Resource 50 138 95
Total Resource 98 143 93

* Abu Dabbab & Nuweibi JORC Compliant Mineral Resources and Ore Reserves as at 01-09-2008

NB: Numbers in Tables 1, 2 & 3 may not correlate exactly due to rounding. In accordance with Listing Rule 5.6 of the Australian Stock Exchange Limited, the geological information in this report that relates to Exploration Results, Mineral Resources and Ore Reserves is based on data compiled by Dr John Chisholm, a Fellow of The Australasian Institute of Mining and Metallurgy. Dr Chisholm has sufficient experience which is relevant to the style of mineralisation and type of deposit under consideration and to the activity which he is undertaking to qualify as a Competent Person as defined in the 2004 Edition of the "Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves". Dr Chisholm consents to the inclusion in the report of the matters based on his information in the form and contest in which it appears.

Typical Mineral Resources Project Development Timetable

Year Milestone Abu Dabbab Status Make your own tantalum projectdevelopment timetable comparison
1 Project acquisition, tenement approvals Completed
1 Geological studies, mapping Completed
2 Initial geological exploration Completed
3 Drilling programme Completed
3 Inferred Mineral Resources Completed62.0 Mt
4 Scoping Study Completed
4 Drilling Programme Completed
4 Indicated Mineral Resources Completed65.3 Mt
5 Drilling Programme Completed
5 Measured Mineral Resources Completed15.2 Mt
5 Pre-Feasibility Study Completed
7 Detailed Metallurgical Studies Completed
8 Definitive Feasibility Study Completed
8 Proven & Probable Ore Reserves Completed30.24 Mt
8 Environmental Impact Assessment (EIA) Completed
9 Project Finance In progress
9 Detailed engineering design Scheduled 2010
10 Construction Scheduled 2010
11 CommissioningScheduled 2012

For further information, please refer to: