STREAMPLAY STUDIO LIMITED — Capital/Financing Update 2012
Jul 2, 2012
65841_rns_2012-07-02_6454e806-9e4a-4cfa-89aa-058712882af7.pdf
Capital/Financing Update
Open in viewerOpens in your device viewer

3 July 2012
ABU DABBAB – ALLUVIAL TIN PROJECT UPDATE FIRST SHIPMENT COMPLETED
Highlights
• First cassiterite shipment despatched to Malaysia Smelting Corporation Bhd ('MSC')
Gippsland Limited ('Gippsland' or the 'Company') [ASX: GIP, FRA: GIX] provides the following update for the alluvial tin project (the "Abu Dabbab Alluvial Tin Project") in Egypt, previously referred to in ASX announcements dated 25 April, 3 August, 7 October 2011, 23 January, 27 February and 12 June 2012.
Mining of the Wadi Quaria placer tin deposit has continued and whilst the ramp up to full production has been slower than expected, the Company is pleased to announce that its first product despatch from the mine site was completed on Thursday 28th June.
Project Status Summarized
The latest milestones achieved are set out below:
Mining Contract
Table 1 summarises the mining contractor's output to the end of May. Ongoing performance has been satisfactory.
| Table 1. Mining Contract Output | ||
|---|---|---|
| Material Movement | Project to date | |
| Ore Mined, BCM | 47,381 | |
| Waste removed, BCM | 3,805 | |
| Ore screened, BCM | 47,381 | |
| -6mm screened, LCM | 10,599 |
* LCM = Loose Cubic Metres, BCM = Bank Cubic Metres
Project Schedule and Costs
Project to date capital costs at the end of the period were $688,507 (budget US$815,797 including contingency of $135,000); project to date direct operating costs were $460,758 (budget $639,154), indirect operating costs $209,861 (budget $139,712). Overall, capital and operating costs have therefore remained within budget.
Ore Processing
Screening of run of mine ore has continued and re-screening of the -6 mm screened ore fraction was completed towards the end of June. Ore processing was switched over to treatment of -2mm feed from the start of June. Ore processing to the end of May is summarised in Table 2.

| Table 2. Ore Processed | |
|---|---|
| Material Handled | Project to date |
| Plant feed, LCM * | 2,478 |
| Rougher concentrate, LCM * | 74.4 |
| Table concentrate, t | 2.7 |
* Estimates based on survey and/or truck count
Product Despatch and Sales
The product finishing, bagging and despatch facilities were completed early in the month so as to enable the first product despatch to be prepared and completed. Details of the first shipment are presented in Table 3.
| Table 3. Shipping Details | ||
|---|---|---|
| Details | Amount | |
| Shipment number | 1 | |
| Jumbo bags | 12 | |
| Despatch date from site | 28 June 2012 | |
| Total wet mass, t | 9.0 | |
| Provisional grade, %Sn | 46.0 |
* Grade determined by averaging 9 Niton hand-held XRF readings for each of 12 bags containing 750kg concentrate/bag, and rounded down to zero decimal points. The final grade is to be determined by independent laboratory assay.
A further shipment is planned for late July 2012.

Figure 1: Product finishing area at project Free Zone


Figure 2: Bag loading in progress

Figure 3: Independent superintendence of grade and tonnage


Figure 4: Completed shipment prior to despatch
For further detail, contact [email protected]
Suite 4, 207 Stirling Highway Claremont WA 6010 Australia
Phone +61 8 9340 6000
Signed
J Dunlop
Executive Director