SSH Mining Commences Site Works at Mt Fisher Gold Project 9/09/2025

==> picture [89 x 30] intentionally omitted <==

SSH Group Ltd ACN 140 110 130

SSH Mining Commences Site Works at Mt Fisher Gold Project

HIGHLIGHTS

  • Site works commenced on historic stockpiles and tailings at Mt Fisher.

  • RC/AC drilling program and metallurgical test work scheduled to begin within coming weeks.

  • Fast-tracking updated Wagtail Mineral Resource Estimate (“MRE”) to support Ore Reserve studies.

  • SSH will be the mining contractor and also receive a 15% profit share from net proceeds.

  • SSH Mining is also tendering on multiple surface and underground mining projects.

  • Additional Joint Venture opportunity under review.

  • Rapidly building operational and technical capability with a focus on acquiring mineral assets.

==> picture [497 x 219] intentionally omitted <==

Page 1 of 5

www.sshgroup.com.au

ASX: SSH

SSH Mining Commences Site Works at Mt Fisher Gold Project 9/09/2025

==> picture [89 x 30] intentionally omitted <==

ASX ANNOUNCEMENT

SSH Group Ltd (ASX: SSH) (“SSH” or “the Company”) is pleased to advise that its mining services vertical, SSH Mining, has commenced site preparation works at the historic Stockpile and Tailings at the Mt Fisher Gold Project in Western Australia for High-Tech Metals Limited (ASX: HTM) (“HTM”).

MT FISHER GOLD PROJECT UPDATE.

SSH Mining has mobilised its operations team to commence dozer works across historic stockpiles and the tailings dam at Mt Fisher. These activities pave the way for a bulk sampling program and reverse circulation (“RC”) and aircore (“AC”) drilling, scheduled to begin within the fortnight. Additional locations across the lease have also been identified for rehandle material sampling.

Metallurgical test work will immediately follow drilling, aimed at validating historic recovery results and confirming processing

==> picture [196 x 115] intentionally omitted <==

pathways. The program is designed to support the planned transport of rehandle material to nearby processing facilities.

In parallel, SSH Mining is advancing a shallow drilling program targeting the Wagtail deposit, designed to upgrade ounces from Inferred into Indicated and Measured categories. This work underpins an updated Mineral Resource Estimate (“MRE”) and will support future Ore Reserve studies.

Mr Sam Baker, Chief Operating Officer of SSH Mining commented:

“We’re excited by the rapid progress at Mt Fisher and the quality of work underway. This program is designed to unlock the value of historic stockpiles and tailings while advancing the Wagtail resource workstreams. In a strong gold market, we believe this project has the potential to deliver meaningful outcomes for our client and create attractive optionality for SSH Mining as we execute our ‘Hire, Mine, Own’ strategy.”

==> picture [496 x 165] intentionally omitted <==

Page 2 of 5

www.sshgroup.com.au

ASX: SSH

SSH Mining Commences Site Works at Mt Fisher Gold Project 9/09/2025

==> picture [89 x 30] intentionally omitted <==

SSH MINING GROWTH PIPELINE

SSH Mining is actively broadening its project pipeline and capabilities, with tenders currently underway for surface mining projects and underground mining projects. The Company is also evaluating additional joint venture opportunities to secure near-term exposure, while strengthening its operational and technical teams to enhance delivery and execution capability.

These initiatives represent an important milestone in developing SSH Mining as an established mining services provider, while also securing exposure to mineral assets. In line with SSH Group’s “Hire, Mine, Own” strategy, the Company remains focused on progressing opportunities that create long-term value for both shareholders and clients.

Table 1 - Mt Fisher and Mt Eureka Mineral Resource Estimate. Table 1 - Mt Fisher and Mt Eureka Mineral Resource Estimate. Table 1 - Mt Fisher and Mt Eureka Mineral Resource Estimate. Table 1 - Mt Fisher and Mt Eureka Mineral Resource Estimate. Table 1 - Mt Fisher and Mt Eureka Mineral Resource Estimate.
Au Cutoff
Volume
Tonnes Density Au Au
Classification
**g/t **
m3 (t) (t/m3) (g/t) koz
Mt Fisher
Measured 0.5 15,900 41,300 2.60 1.94 26
Mt Fisher Indicated
Inferred
0.5
0.5
50,600
108,900
129,100
294,100
2.55
2.70
1.97
2.53
8
24
Total 0.5 175,400 464,400 2.65 2.32 35
Indicated 0.5 354,300 726,200 2.05 1.87 44
Damsel Inferred 0.5 284,500 678,000 2.38 1.43 31
Total 0.5 638,900 1,404,200 2.20 1.66 75
Measured 0.5 5,000 11,300 2.28 10.53 4
Wagtail Indicated
Inferred
0.5
0.5
14,200
6,200
36,200
16,200
2.54
2.62
7.75
3.31
9
2
Total 0.5 25,400 63,700 2.51 7.11 15
Total 0.5 839,700 1,932,300 2.30 2.00 124
Mt Eureka
Taipan Inferred
Total
0.5
0.5
324,800
324,800
640,800
640,800
1.97
1.97
1.21
1.21
25
25
Indicated 0.5 211,200 488,400 2.31 1.32 21
Southern Inferred 0.5 172,400 457,600 2.66 1.18 17
Total 0.5 383,500 946,100 2.47 1.25 38
Total 0.5 708,300 1,586,900 2.30 1.23 63
Total
Resource 0.5 1,548,000 3,519,200 2.27 1.65 187

*Refer HTM ASX Announcement – 26 February 2025 titled Transformational Gold Resources Acquisition – Presentation. HTM confirms to SSH that it is not aware of any new information or data that materially affects the information included in this announcement and all material assumptions and technical parameters underpinning the Mineral Resource Estimate included in this announcement continue to apply and have not materially changed.

Page 3 of 5

www.sshgroup.com.au

ASX: SSH

SSH Mining Commences Site Works at Mt Fisher Gold Project 9/09/2025

==> picture [89 x 30] intentionally omitted <==

==> picture [499 x 593] intentionally omitted <==

Figure 1 - Mt Fisher and Mt Eureka Gold Project tenements, resources and exploration targets on 1:250,000k solid geology interpretation.

* Refer HTM ASX Announcement – 26 February 2025 titled Transformational Gold Resources Acquisition – Presentation.

Page 4 of 5

www.sshgroup.com.au

ASX: SSH

SSH Mining Commences Site Works at Mt Fisher Gold Project 9/09/2025

==> picture [89 x 30] intentionally omitted <==

AUTHORISATION

This release has been authorised in accordance with the Company’s published continuous disclosure policy and approved for release by the Board of SSH Group Ltd.

ABOUT SSH GROUP

SSH Group Ltd operates across the Mining, Civil and Construction sectors. Its model, Hire, Mine and Own, underpins its strategy to become a vertically integrated, diversified metals and mining company.

FURTHER DETAILS

Investor Enquiries

Company Secretary

[email protected] [email protected] +61 428 893 215 PO Box 189 WELSHPOOL DC 6986

Page 5 of 5

www.sshgroup.com.au

ASX: SSH