AI assistant
SSH GROUP LTD — Regulatory Filings 2025
Sep 8, 2025
65863_rns_2025-09-08_7bbccd68-e3b4-4447-95ca-1827f481d651.pdf
Regulatory Filings
Open in viewerOpens in your device viewer
SSH Mining Commences Site Works at Mt Fisher Gold Project 9/09/2025
==> picture [89 x 30] intentionally omitted <==
SSH Group Ltd ACN 140 110 130
SSH Mining Commences Site Works at Mt Fisher Gold Project
HIGHLIGHTS
-
Site works commenced on historic stockpiles and tailings at Mt Fisher.
-
RC/AC drilling program and metallurgical test work scheduled to begin within coming weeks.
-
Fast-tracking updated Wagtail Mineral Resource Estimate (“MRE”) to support Ore Reserve studies.
-
SSH will be the mining contractor and also receive a 15% profit share from net proceeds.
-
SSH Mining is also tendering on multiple surface and underground mining projects.
-
Additional Joint Venture opportunity under review.
-
Rapidly building operational and technical capability with a focus on acquiring mineral assets.
==> picture [497 x 219] intentionally omitted <==
Page 1 of 5
www.sshgroup.com.au
ASX: SSH
SSH Mining Commences Site Works at Mt Fisher Gold Project 9/09/2025
==> picture [89 x 30] intentionally omitted <==
ASX ANNOUNCEMENT
SSH Group Ltd (ASX: SSH) (“SSH” or “the Company”) is pleased to advise that its mining services vertical, SSH Mining, has commenced site preparation works at the historic Stockpile and Tailings at the Mt Fisher Gold Project in Western Australia for High-Tech Metals Limited (ASX: HTM) (“HTM”).
MT FISHER GOLD PROJECT UPDATE.
SSH Mining has mobilised its operations team to commence dozer works across historic stockpiles and the tailings dam at Mt Fisher. These activities pave the way for a bulk sampling program and reverse circulation (“RC”) and aircore (“AC”) drilling, scheduled to begin within the fortnight. Additional locations across the lease have also been identified for rehandle material sampling.
Metallurgical test work will immediately follow drilling, aimed at validating historic recovery results and confirming processing
==> picture [196 x 115] intentionally omitted <==
pathways. The program is designed to support the planned transport of rehandle material to nearby processing facilities.
In parallel, SSH Mining is advancing a shallow drilling program targeting the Wagtail deposit, designed to upgrade ounces from Inferred into Indicated and Measured categories. This work underpins an updated Mineral Resource Estimate (“MRE”) and will support future Ore Reserve studies.
Mr Sam Baker, Chief Operating Officer of SSH Mining commented:
“We’re excited by the rapid progress at Mt Fisher and the quality of work underway. This program is designed to unlock the value of historic stockpiles and tailings while advancing the Wagtail resource workstreams. In a strong gold market, we believe this project has the potential to deliver meaningful outcomes for our client and create attractive optionality for SSH Mining as we execute our ‘Hire, Mine, Own’ strategy.”
==> picture [496 x 165] intentionally omitted <==
Page 2 of 5
www.sshgroup.com.au
ASX: SSH
SSH Mining Commences Site Works at Mt Fisher Gold Project 9/09/2025
==> picture [89 x 30] intentionally omitted <==
SSH MINING GROWTH PIPELINE
SSH Mining is actively broadening its project pipeline and capabilities, with tenders currently underway for surface mining projects and underground mining projects. The Company is also evaluating additional joint venture opportunities to secure near-term exposure, while strengthening its operational and technical teams to enhance delivery and execution capability.
These initiatives represent an important milestone in developing SSH Mining as an established mining services provider, while also securing exposure to mineral assets. In line with SSH Group’s “Hire, Mine, Own” strategy, the Company remains focused on progressing opportunities that create long-term value for both shareholders and clients.
| Table 1 - Mt Fisher and Mt Eureka Mineral Resource Estimate. | Table 1 - Mt Fisher and Mt Eureka Mineral Resource Estimate. | Table 1 - Mt Fisher and Mt Eureka Mineral Resource Estimate. | Table 1 - Mt Fisher and Mt Eureka Mineral Resource Estimate. | Table 1 - Mt Fisher and Mt Eureka Mineral Resource Estimate. | |||
|---|---|---|---|---|---|---|---|
| Au Cutoff | Volume |
Tonnes | Density | Au | Au | ||
| Classification | **g/t ** |
m3 | (t) | (t/m3) | (g/t) | koz | |
| Mt Fisher | |||||||
| Measured | 0.5 | 15,900 | 41,300 | 2.60 | 1.94 | 26 | |
| Mt Fisher | Indicated Inferred |
0.5 0.5 |
50,600 108,900 |
129,100 294,100 |
2.55 2.70 |
1.97 2.53 |
8 24 |
| Total | 0.5 | 175,400 | 464,400 | 2.65 | 2.32 | 35 | |
| Indicated | 0.5 | 354,300 | 726,200 | 2.05 | 1.87 | 44 | |
| Damsel | Inferred | 0.5 | 284,500 | 678,000 | 2.38 | 1.43 | 31 |
| Total | 0.5 | 638,900 | 1,404,200 | 2.20 | 1.66 | 75 | |
| Measured | 0.5 | 5,000 | 11,300 | 2.28 | 10.53 | 4 | |
| Wagtail | Indicated Inferred |
0.5 0.5 |
14,200 6,200 |
36,200 16,200 |
2.54 2.62 |
7.75 3.31 |
9 2 |
| Total | 0.5 | 25,400 | 63,700 | 2.51 | 7.11 | 15 | |
| Total | 0.5 | 839,700 | 1,932,300 | 2.30 | 2.00 | 124 | |
| Mt Eureka | |||||||
| Taipan | Inferred Total |
0.5 0.5 |
324,800 324,800 |
640,800 640,800 |
1.97 1.97 |
1.21 1.21 |
25 25 |
| Indicated | 0.5 | 211,200 | 488,400 | 2.31 | 1.32 | 21 | |
| Southern | Inferred | 0.5 | 172,400 | 457,600 | 2.66 | 1.18 | 17 |
| Total | 0.5 | 383,500 | 946,100 | 2.47 | 1.25 | 38 | |
| Total | 0.5 | 708,300 | 1,586,900 | 2.30 | 1.23 | 63 | |
| Total | |||||||
| Resource | 0.5 | 1,548,000 | 3,519,200 | 2.27 | 1.65 | 187 |
*Refer HTM ASX Announcement – 26 February 2025 titled Transformational Gold Resources Acquisition – Presentation. HTM confirms to SSH that it is not aware of any new information or data that materially affects the information included in this announcement and all material assumptions and technical parameters underpinning the Mineral Resource Estimate included in this announcement continue to apply and have not materially changed.
Page 3 of 5
www.sshgroup.com.au
ASX: SSH
SSH Mining Commences Site Works at Mt Fisher Gold Project 9/09/2025
==> picture [89 x 30] intentionally omitted <==
==> picture [499 x 593] intentionally omitted <==
Figure 1 - Mt Fisher and Mt Eureka Gold Project tenements, resources and exploration targets on 1:250,000k solid geology interpretation.
* Refer HTM ASX Announcement – 26 February 2025 titled Transformational Gold Resources Acquisition – Presentation.
Page 4 of 5
www.sshgroup.com.au
ASX: SSH
SSH Mining Commences Site Works at Mt Fisher Gold Project 9/09/2025
==> picture [89 x 30] intentionally omitted <==
AUTHORISATION
This release has been authorised in accordance with the Company’s published continuous disclosure policy and approved for release by the Board of SSH Group Ltd.
ABOUT SSH GROUP
SSH Group Ltd operates across the Mining, Civil and Construction sectors. Its model, Hire, Mine and Own, underpins its strategy to become a vertically integrated, diversified metals and mining company.
FURTHER DETAILS
Investor Enquiries
Company Secretary
[email protected] [email protected] +61 428 893 215 PO Box 189 WELSHPOOL DC 6986
Page 5 of 5
www.sshgroup.com.au
ASX: SSH