Earnings Release • Aug 29, 2025
Earnings Release
Open in ViewerOpens in native device viewer

Sif will host a webcast analyst meeting on 29 August 2025 at 10.00 hrs AM CET. A link to the webcast can be found webcast analyst presentation or on the homepage of the Sif website www.sif-group.com

Fred van Beers, CEO of Sif: "After the successful completion of the construction and infrastructure works related to the expansion of our manufacturing facilities at Maasvlakte 2 Rotterdam in 2024, despite being behind our initial ramp-up planning, foundations for the launching project were delivered within the specifications to Empire Offshore Wind to meet the installation window of their project in the United States. The factory in Roermond showed steady efficiency in producing transition pieces and top sections for Empire Wind 1, Ecowende and Baltyk.
The original business plan factored in that there would be a steep ramp-up in the new Maasvlakte 2 facility during the first half year of 2025 to reach the anticipated production levels from the third quarter onwards. However, during this period we have learnt that the training of our new workforce, as well as the further stabilisation of equipment and implementing improved working procedures for the new manufacturing facilities require significantly more time than initially anticipated. Following a thorough review of our production and equipment challenges, and in line with our committed focus to safety, quality and then output, we have concluded that the time required to ramp up production will continue into the first half year of 2026. This results in lower output in 2025 than originally anticipated, and a delay of 6 - 9 months compared to the original business case.
This delay in reaching the anticipated production levels is a clear set back but given the proof of realised deliveries and initiated actions, we remain confident that the new manufacturing facilities will have the capability to produce the number of monopiles that we originally envisaged. Production has commenced on HKW VI for Ecowende, and in parallel we are running a significant equipment and process modification and stabilisation program with external support from specialists and our key equipment suppliers. This will ensure a more stable ramp-up of production into the first half of 2026. We are strengthening the operations organisation with a new COO, with the present COO focusing on the technical completion of the ramp up plan, and new dedicated roles to support the stabilisation and further ramp-up of the Maasvlakte 2 facilities.
We remain confident in the medium to long term outlook for the offshore wind market but expect a further offshore wind project development slowdown short term mainly due to non-market conform tender criteria, grid congestion and prices for electricity. Various governments have altered their ambitions for offshore wind to a more realistic level, and, although late, realise that they must adjust tender procedures and qualifications to match market conditions and preferences. The industry has strongly advised governmental bodies multiple times in the past to match tender criteria with today's economic reality as part of a total energy system approach (windfarms, strengthen the grid and market conform electricity prices). We are pleased by the

changed attitude and sense of reality since the need for energy transition and energy independence in the EU remains unchanged. We see this new reality reflected in tender activity for projects from mid-2028 onwards. Our confidence in the medium to long term outlook for the offshore wind market is further underpinned by a 200 Kton addition to our orderbook for 2027 and part of 2028. This project, that had a preferred status, has now reached the phase of exclusive negotiations.
Rather than focusing on the alternative of short-term EBITDA maximisation, our focus now is achieving robust and stable operations, and taking the time needed to implement the right industrialisation measures. As a result, we are adjusting our 2025 adjusted EBITDA guidance to EUR 45m. Based on the progress made, the stabilization plan and modifications ongoing in our Maasvlakte 2 facilities, we reiterate the mid-term annualized adjusted EBITDA run rate target of at least EUR 160m. This remains the goal for 2026. Achieving the required output to underpin the adjusted EBITDA run rate is expected to shift into the first half of 2026. Therefore, the provisional minimum adjusted EBITDA guidance for 2026 is set at EUR 135m. Based on the actual progress of the actions being undertaken and the output during the second half of 2025, we will provide further guidance towards the end of the year."
For the interim report see link to 2025 Interim report or the attachment to this message.
| Sif Holding N.V. | |
|---|---|
| Fons van Lith | |
| +31 (0)475 385 777 | |
| +31 (0)6 513 14952 | |
| [email protected] |
Sif offers total solutions for the design and production of foundations for offshore wind farms, including logistics services and marshalling. Sif traditionally serves the markets of Northwestern Europe and is working on a global presence. Sif combines two highly automated and flexible production facilities in Roermond and Rotterdam (Second Maasvlakte) with technological leadership in the field of rolling and welding of heavy steel plates, based on 75 years of experience and innovative self-developed techniques and processes. Sif mainly produces monopiles, transition parts and piles with which jacket foundations for wind turbines can be anchored in the seabed.