SANTOS LIMITED Interim / Quarterly Report 2021

Jul 21, 2021

65872_rns_2021-07-21_634689dd-baf3-4c74-9afb-10c9f6dc07e7.pdf

Interim / Quarterly Report

Open in viewer

Opens in your device viewer

For period ending 30 June 2021

ASX: STO | ADR: SSLZY

22 July 2021

Record sales revenue and strong free cash flow

  • Strong base business performance and improved commodity prices delivered record quarterly sales revenue of US$1.1 billion and record first half sales revenue of over US$2 billion
  • Second quarter production of 22.5 mmboe was nine per cent lower than the first quarter, primarily due to completion of the 25 per cent sell down in Bayu-Undan and Darwin LNG to SK E&S on 30 April 2021, partially offset by stronger gas production in Western Australia and Queensland
  • First half production of 47.3 mmboe was 23 per cent above the corresponding period and sees 2021 guidance narrowed to the upper part of the range
  • Continued growth in GLNG equity gas production from the Roma and Arcadia fields supports annualised LNG production above 6.2 mtpa for 2021

• US$270 million in free cash flow in the second quarter, bringing first half free cash flow to US$572 million

Key growth milestones achieved and balance sheet strengthened

  • Initiated major workstreams for the Barossa gas and condensate project, including cutting first steel for the FPSO turret, commencing manufacturing of subsea and export flowlines, and assembly of subsea trees
  • Entered FEED phase for the Dorado integrated oil and gas project
  • Issued US$1 billion 10-year senior unsecured fixed rate bond in the US 144A/Reg S market
  • Strong free cash flows reduced net debt (including leases) to US$3.4 billion and gearing to 32 per cent at the end of the quarter

Energy transition to cleaner fuels

  • Signed MOU with Eni to cooperate on opportunities in northern Australia and Timor-Leste, including repurposing Bayu-Undan into a carbon capture and storage (CCS) hub for projects in the region with a potential capacity of ~10 mtpa of CO2
  • Awarded A$15 million in funding for the Moomba CCS project from the Australian Government's Carbon Capture Use and Storage Development Fund. The 1.7 mtpa Moomba CCS project is FID-ready, subject to confirmation of eligibility for Australian Carbon Credit Units

Santos Managing Director and Chief Executive Officer Kevin Gallagher said Santos had delivered another strong quarter of production, sales volumes and revenues, as the business benefited from stronger demand and higher prices. Domestic gas sales volumes were up 7% as we responded to higher customer demand.

"Our disciplined, low-cost operating model continues to drive strong performance with US$572 million of free cash flow generated in the first half, and the business remains on track to deliver a free cash flow breakeven oil price of US$25 per barrel this year. At current oil prices, Santos should generate over US$1.1 billion in free cash flow in 2021.

"Consistent with our 2021 strategic priorities, after taking the FID on Barossa in March, we completed the sell-downs in Bayu-Undan and Darwin LNG, and have now commenced all key workstreams on Barossa as well as entering FEED for the Dorado project. As I have always said, we will remain disciplined and cost-focused during this next phase of growth. Despite cost challenges across the industry, I am pleased that our continued focus on costs sees a lowering of our upstream production cost guidance.

"The Moomba CCS project is FID-ready, and we are actively exploring CCS opportunities at Bayu-Undan and the production of zero-emissions hydrogen at Moomba. These projects provide a competitive advantage as we seek to decarbonise our oil and gas assets on the path to net-zero emissions by 2040," Mr Gallagher said.

Comparative performance

Santos share Unit Q2 2021 Q1 2021 Change 2021 YTD 2020 YTD Change
Production mmboe 22.5 24.8 -9% 47.3 38.5 23%
Sales volume mmboe 26.4 27.4 -4% 53.8 46.9 15%
Sales revenue $million 1,076 964 12% 2,040 1,668 22%
Capital expenditure1 $million 334 201 66% 535 372 44%

Investor enquiries 1 Capital expenditure including restoration expenditure but excluding capitalised interest.

Media enquiries James Murphy

+61 (0) 478 333 974 [email protected] Andrew Nairn +61 8 8116 5314 / +61 (0) 437 166 497 [email protected]

Santos Limited ABN 80 007 550 923 GPO Box 2455, Adelaide SA 5001 T +61 8 8116 5000 F +61 8 8116 5131 www.santos.com

Product Unit Q2 2021 Q1 2021 Q2 2020 2021 YTD 2020 YTD
LNG 000 t 1,064.9 1,327.6 920.5 2,392.5 1,772.1
Domestic sales gas & ethane PJ 67.2 62.9 64.8 130.1 120.3
Crude oil 000 bbls 2,770.9 1,713.5 2,769.8 4,484.4 5,728.3
Condensate 000 bbls 1,413.8 1,781.3 1,539.4 3,195.1 2,953.5
LPG 000 t 67.8 64.3 50.4 132.1 94.9
Sales
Own product mmboe 20.5 22.8 20.1 43.2 37.3
Third-party mmboe 5.9 4.6 4.5 10.5 9.6
Total sales volume mmboe 26.4 27.4 24.6 53.8 46.9

Sales volumes (Santos share)

Second quarter sales volumes were lower than the prior quarter primarily due to completion of the 25 per cent sell down in Bayu-Undan and Darwin LNG to SK E&S at the end of April, partially offset by an increased number of liquids liftings in Western Australia, higher third-party crude volumes and higher domestic gas sales. Sales volumes in the second half are expected to be lower than the first half due to the Bayu-Undan sell-down, with guidance narrowed to 100-105 mmboe for the full year.

Sales revenues (Santos share)

Product Unit Q2 2021 Q1 2021 Q2 2020 2021 YTD 2020 YTD
LNG $million 421 427 400 848 797
Domestic sales gas & ethane $million 319 285 247 604 456
Crude oil $million 205 107 85 312 274
Condensate $million 95 108 35 203 102
LPG $million 36 37 18 73 39
Sales
Own product $million 832 779 628 1,611 1,260
Third-party $million 244 185 157 429 408
Total sales revenue $million 1,076 964 785 2,040 1,668
Third-party purchase costs $million 167 157 119 324 309

Second quarter sales revenues were a record and higher than the prior quarter, reflecting improved commodity prices partially offset by lower overall sales volumes due to the Bayu-Undan sell-down.

Average realised prices

Product Unit Q2 2021 Q1 2021 Q2 2020 2021 YTD 2020 YTD
LNG price US$/mmBtu 7.52 6.12 8.27 6.74 8.57
Domestic gas price US$/GJ 4.74 4.54 3.82 4.65 3.79
East coast domestic US$/GJ 5.35 5.32 4.58 5.33 4.60
West coast domestic US$/GJ 4.43 4.18 3.21 4.31 3.08
Crude oil price US$/bbl 74.06 62.29 30.78 69.57 47.83
Condensate price US$/bbl 67.65 60.41 22.72 63.61 34.37
LPG price US$/t 517.02 581.26 358.31 548.28 408.74

The average realised LNG price was higher than the prior quarter reflecting the linkage of sales contracts to an improving lagged Japan Customs-cleared Crude (JCC) price, but offset by lower JKM spot prices. Three-month lagged JCC averaged US$56/bbl in the second quarter compared to US$44/bbl in the first quarter. Santos' LNG projects shipped 63 cargoes in the second quarter, of which ten were spot cargoes from Darwin LNG (9) and PNG LNG (1).

Production by asset (Santos share)

Product Unit Q2 2021 Q1 2021 Q2 2020 2021 YTD 2020 YTD
Western Australia mmboe 8.5 8.1 7.2 16.6 13.4
Cooper Basin mmboe 3.9 4.0 4.1 7.9 8.5
Queensland & NSW mmboe 3.4 3.3 3.3 6.7 6.6
PNG mmboe 3.0 3.1 3.2 6.1 6.5
Northern Australia & Timor-Leste mmboe 3.7 6.3 2.6 10.0 3.5
Total production mmboe 22.5 24.8 20.6 47.3 38.5

Production by product (Santos share)

Product Unit Q2 2021 Q1 2021 Q2 2020 2021 YTD 2020 YTD
Sales gas to LNG plant PJ 54.7 68.8 43.9 123.5 78.7
Domestic sales gas & ethane PJ 59.0 58.4 59.5 117.4 112.0
Crude oil 000 bbls 1,343.4 1,063.8 1,189.6 2,407.2 2,750.7
Condensate 000 bbls 1,249.4 1,494.6 1,275.5 2,744.0 2,349.2
LPG 000 t 48.6 60.7 51.4 109.3 92.8
Total production mmboe 22.5 24.8 20.6 47.3 38.5

Second quarter production was lower than the prior quarter primarily due to the 25 percent sell-down in Bayu-Undan and Darwin LNG to SK E&S completing on 30 April 2021. This was partially offset by stronger oil and gas production in Western Australia and higher gas production in Queensland. Although production volumes in the second half are expected to be lower than the first half due to the Bayu-Undan sell-down, strong production performance across the portfolio sees the production guidance range narrowed upwards to 87-91 mmboe for the full year.

A data worksheet containing unaudited quarterly sales, revenue, production and capital expenditure tables in Excel format is available on Santos' website.

2021 Guidance

Production and sales volume guidance are narrowed to 87-91 mmboe and 100-105 mmboe, respectively. Capital expenditure guidance is unchanged with spend expected to be weighted to the second half. Production cost guidance is revised down to $7.90-8.30/boe. Depreciation, depletion and amortisation (DD&A) is expected to be in the range of $1.15-1.25 billion in 2021, higher than the prior year primarily due to higher DD&A in Western Australia due to the writedown of Reindeer gas reserves in 2020.

2021 guidance item Previous guidance Updated guidance
Production 84-91 mmboe 87-91 mmboe
Sales volumes 98-105 mmboe 100-105 mmboe
Capital expenditure – base ~$900 million No change
Capital expenditure – major growth ~$700 million No change
Upstream production costs $8.00-8.50/boe $7.90-8.30/boe
Depreciation, depletion and amortisation na $1.15-1.25 billion

2021 Half-year results

Santos will release its results for the half-year ended 30 June 2021 on Tuesday 17 August 2021. The first-half report (incorporating Appendix 4D) and associated investor presentation will be available on Santos' website at www.santos.com. A webcast briefing including investor/analyst questions will also be available on Santos' website from 12:30pm AEST on 17 August 2021. Financial information included in this report is unaudited and subject to finalisation of the company's accounting and audit processes, and Board review. As such, actual results for the half-year ended 30 June 2021 may differ from the information given in this report.

Western Australia

Santos share Unit Q2 2021 Q1 2021 Q2 2020 2021 YTD 2020 YTD
Sales volume
Sales gas PJ 43.4 42.4 36.1 85.8 63.8
Condensate 000 bbls 310.0 319.6 295.1 629.6 619.4
Crude oil 000 bbls 1,165.0 - 311.6 1,165.0 1,142.4
Total sales volume mmboe 8.9 7.6 6.8 16.5 12.7
Total sales revenue $million 304 196 125 500 274
Production
Sales gas PJ 43.4 42.3 37.1 85.7 65.8
Condensate 000 bbls 374.6 346.7 373.5 721.3 694.5
Crude oil 000 bbls 766.3 473.4 543.2 1,239.7 1,456.8
Total production mmboe 8.5 8.1 7.2 16.6 13.4
Capital expenditure $million 90 44 23 134 52

Domestic gas production and sales increased in the second quarter reflecting increased contract and spot market demand.

Oil production was higher in the second quarter due to start-up of the Ningaloo Vision FPSO in late March. Cyclone avoidance activity in early April required shutdowns of both the Ningaloo Vision and Pyrenees Venture FPSOs. Ningaloo Vision then commenced a planned maintenance shutdown in late June. Sales volumes and revenues are higher than the previous quarter reflecting increased liquids liftings.

The three-well Van Gogh infill drilling campaign commenced in the second quarter and is on track for completion in the fourth quarter. Drilling and completion and tie-in activities have been completed for the first well, with start-up expected in the third quarter of 2021. A better than expected reservoir outcome was realised in the well, with a total horizontal section of 5,430 metres across the two laterals, almost 500 metres of additional reservoir section than originally planned. The Valaris MS-1 rig has commenced drilling activity on the second well in the program.

As previously announced, the Dorado development moved into FEED in June with a number of key detailed design, procurement and regulatory approval work fronts being advanced. Major FEED contracts for the FPSO and the Wellhead Platform are expected to be awarded in the third quarter. The project is targeting a final investment decision around mid-2022. The initial phase of development will involve gas reinjection to maximise liquids recovery ahead of a second phase of gas export from the field. This future phase of gas export offers backfill supply to Santos' existing domestic gas infrastructure in Western Australia.

The Noble Tom Prosser rig is scheduled to mobilise to the Carnarvon Basin late in the fourth quarter to drill the Dancer prospect, located seven kilometres from the Reindeer field. This will then be followed by drilling the Pavo and Apus prospects in the Bedout Basin, located 35 to 40 kilometres from the Dorado field, and would be developed as subsea tiebacks to the Dorado development in a success case.

Consistent with Santos' strategy to phase growth projects and review equity levels in-line with disciplined capital management, Santos is undertaking a process to explore interest from the market in non-operated equity in Dorado and potentially other WA oil assets.

Cooper Basin

Santos share Unit Q2 2021 Q1 2021 Q2 2020 2021 YTD 2020 YTD
Sales volume
Sales gas and ethane1 PJ 16.4 18.6 17.9 35.0 36.4
Condensate1 000 bbls 603.1 388.5 395.1 991.6 1,002.8
LPG1 000 t 44.2 38.0 41.7 82.2 81.6
Crude oil
Own product 000 bbls 488.5 632.7 1,123.1 1,121.2 1,837.5
Third-party 000 bbls 1,116.4 1,079.7 1,332.2 2,196.1 2,742.7
Total 000 bbls 1,604.9 1,712.4 2,455.3 3,317.3 4,580.2
Total sales volume mmboe 5.4 5.6 6.3 11.0 12.5
Total sales revenue $million 244 222 185 466 440
Production
Sales gas and ethane PJ 16.0 16.6 16.9 32.6 34.8
Condensate 000 bbls 270.2 270.1 252.3 540.3 599.5
LPG 000 t 35.1 35.6 37.3 70.7 74.5
Crude oil 000 bbls 576.1 589.3 644.0 1,165.4 1,288.7
Total production mmboe 3.9 4.0 4.1 7.9 8.5

1 Sales volumes include own product and third-party volumes.

Cooper Basin total production in the second quarter was 3.9 mmboe, lower than the previous quarter primarily due to higher unplanned surface downtime and lower drilling activity due to impact of COVID on joint venture budgets. Oil production reflects natural field decline with no new oil wells drilled in the first half consistent with the joint venture budgets.

Thirteen wells were drilled with three rigs in the second quarter, including six development wells, five appraisal wells and two exploration wells. A fourth rig was added to the program at the end of the quarter and will see a higher number of wells drilled in the second half compared to the first as the drilling program recovers from budget phasing caused by COVID during the first half.

The horizontal well programme continued in the second quarter with a positive result at Tarwonga 7 and preparation is well progressed for increased activity in the second half of the year with four horizontal gas wells and seven horizontal oil wells planned to be drilled.

Santos was awarded A$15 million in funding for the Moomba CCS project through the Australian Government's CCUS Development Fund. Engagement with the Clean Energy Regulator and industry on the CCS methodology continued and the methodology has been released for public consultation. Eligibility for Australia Carbon Credit Units (ACCUs) for CCS is the key remaining milestone that would enable an FID decision on the project.

Work continued on the Moomba Zero Emissions Hydrogen project. Market development opportunities continue to be explored with domestic and international players to secure off-take arrangements.

Queensland & NSW

Santos share Unit Q2 2021 Q1 2021 Q2 2020 2021 YTD 2020 YTD
Sales volume
GLNG Joint Venture
LNG 000 t 449.6 471.2 425.5 920.8 906.5
Domestic contracts PJ 1.3 0.2 2.7 1.5 5.1
Eastern Qld (non-GLNG)1 PJ 4.9 4.3 5.0 9.2 10.4
Total sales volume2 mmboe 5.3 5.2 5.3 10.5 11.2
Total sales revenue2 $million 209 167 236 376 502
Production
GLNG Joint Venture PJ 15.4 15.1 14.3 30.5 28.1
Eastern Qld (non-GLNG)1 PJ 4.1 4.0 4.8 8.1 9.8
NSW PJ 0.3 0.2 0.2 0.5 0.4
Total production2 mmboe 3.4 3.3 3.3 6.7 6.6
Capital expenditure $million 41 38 51 79 93

1 Combabula, Scotia (Santos legacy domestic volumes), Spring Gully and Denison.

2 Total sales volume, sales revenue and production include sales gas from NSW assets.

GLNG operational data (gross) Unit Q2 2021 Q1 2021 Q2 2020 2021 YTD 2020 YTD
Sales gas to domestic market1 PJ 17 11 17 28 31
LNG produced2 000 t 1,468 1,569 1,368 3,037 2,944
Sales gas to LNG plant
GLNG equity gas PJ 49 51 48 100 92
Santos portfolio gas PJ 14 13 9 27 24
Third-party PJ 25 31 25 56 60
Total sales gas to LNG plant PJ 89 95 82 183 177
LNG cargoes shipped 25 26 24 51 51

1Includes APLNG equity share of Fairview, Arcadia and Roma East.

2Includes LNG produced from GLNG equity gas, Santos portfolio gas and third-party quantities.

Gross GLNG-operated upstream sales gas production reached a record 700 TJ/day at the end of the second quarter. Upstream production continues to build and perform well. In the Arcadia field, production continues to ramp more quickly than anticipated, reaching 87 TJ/day with surface debottlenecking completed in both the field and plant. We continue to see safe and reliable production from the Scotia field producing 72 TJ/day, Roma field producing 195 TJ/day and Fairview field producing 345 TJ/day at the end of the quarter, in line with expectations.

LNG production was lower than the previous quarter due to a planned one-month statutory LNG train shut down in May. Based on current shipping plans, LNG production is expected to be above 6.2 mtpa for the full-year.

Fifty-two wells were drilled and sixty connected across the GLNG acreage in the second quarter.

Santos' share of non-operated Eastern Queensland production was lower than the prior quarter due to planned facilities maintenance.

Following the Narrabri Gas Project EIS approval by the NSW Independent Planning Commission (IPC) and Federal approval under the EPBC Act, Santos has been progressing activities to address EIS and EPBC consent conditions to allow the commencement of the appraisal drilling program, which is required to inform the phased development at Narrabri. An appeal against the NSW IPC approval has been lodged with a hearing scheduled in August.

PNG

Santos share Unit Q2 2021 Q1 2021 Q2 2020 2021 YTD 2020 YTD
Sales volume
PNG LNG
LNG1 000 t 265.2 270.8 265.2 536.0 553.0
Condensate 000 bbls 341.2 341.3 364.0 682.5 724.9
Crude oil 000 bbls 0.9 1.2 2.9 2.1 5.7
Total sales volume mmboe 2.9 2.9 2.9 5.8 6.0
Total sales revenue $million 142 119 118 261 267
Production
PNG LNG
Sales gas to LNG1 PJ 15.8 16.6 17.3 32.4 34.4
Condensate 000 bbls 272.0 290.8 319.9 562.8 643.7
Crude oil 000 bbls 1.0 1.1 2.5 2.1 5.2
Total production mmboe 3.0 3.1 3.2 6.1 6.5
Capital expenditure $million 1 3 12 4 26

1Includes SE Gobe

PNG LNG operational data (gross) Unit Q2 2021 Q1 2021 Q2 2020 2021 YTD 2020 YTD
Production
LNG 000 t 1,988 2,090 2,181 4,078 4,344
Sales gas to LNG plant PJ 118 124 129 242 257
Condensate1 000 bbls 2,011 2,149 2,361 4,160 4,755
Sales gas (SE Gobe)2 PJ 2 2 2 4 4
LNG cargoes shipped 27 26 29 53 57

1Measured at the Kutubu entry point.

2 Purchased by PNG LNG.

During the quarter, PNG LNG operated at an annualised rate of approximately 8.0 mtpa. Sales gas, condensate and LNG production were lower than the first quarter due to planned maintenance activities at Hides Gas Conditioning Plant and the LNG plant, which lasted for approximately five weeks.

Despite COVID-19 constraints, the maintenance activities were completed approximately one week ahead of schedule. COVID-19 management plans continue to be implemented to support stable production and shipping.

Northern Australia & Timor-Leste

Santos share Unit Q2 2021 Q1 2021 Q2 2020 2021 YTD 2020 YTD
Sales volume
Darwin LNG
LNG 000 t 350.1 585.6 229.7 935.7 312.6
Bayu-Undan
Condensate 000 bbls 159.8 732.2 485.7 892.0 607.5
LPG 000 t 23.7 26.4 8.7 50.1 13.4
Total sales volume mmboe 3.7 6.5 2.8 10.2 3.7
Total sales revenue $million 146 237 103 383 146
Production
Darwin LNG
Sales gas to LNG PJ 18.6 32.5 12.9 51.1 17.5
Bayu-Undan
Condensate 000 bbls 332.6 587.0 329.7 919.6 411.4
LPG 000 t 13.6 25.0 14.2 38.6 18.4
Total production mmboe 3.7 6.3 2.6 10.0 3.5
Capital expenditure $million 109 39 15 148 37
DLNG operational data (gross) Unit Q2 2021 Q1 2021 Q2 2020 2021 YTD 2020 YTD
Production
LNG 000 t 742 902 536 1,644 1,392
Sales gas to LNG plant PJ 45 52 33 98 85
Condensate 000 bbls 846 1,019 838 1,865 1,818
LPG 000 t 33 42 38 75 85
LNG cargoes shipped 11 12 8 23 22

Santos' interest in Bayu-Undan and Darwin LNG reduced from 68.4 per cent to 43.4 per cent at the end of April following completion of the 25 per cent sell-down in both assets to Barossa partner SK E&S. As a result, production and sales volumes in the second half will be lower than the first half.

LNG production at Darwin LNG was lower than the prior quarter primarily due to a planned shutdown at Bayu-Undan and unplanned maintenance at Darwin LNG. Reservoir deliverability at Bayu-Undan continues in-line with expectations.

The Phase 3C infill drilling program at the Bayu-Undan field commenced in May with the first of three planned wells drilled to a total depth of 3,410 metres. The well encountered unswept reservoir section as per prognosis and was being completed at the end of the quarter in preparation for testing and tie-in to the production facility. Two further infill wells will be drilled in the coming months.

Following FID at the end of the first quarter, work on the US$3.6 billion Barossa gas and condensate project ramped-up across all workscopes. BW Offshore, the project's FPSO contractor, let major contracts for the hull engineering and fabrication, for the topsides engineering and fabrication and for the turret mooring EPC. First steel for the FPSO turret was cut on 13 July. Plate manufacturing for the gas export pipeline has commenced and fabrication of subsea hardware and in-field flowlines is progressing. The project remains on track for first gas production in the first half of 2025.

Planning continues for the Darwin LNG life extension project and the tie-in of Barossa into Darwin. Santos and JERA continue to progress the sale and purchase agreement for JERA to acquire a 12.5 per cent interest in Barossa. Santos and Eni have signed an MOU to cooperate on opportunities in Northern Australia and Timor-Leste, including opportunities to re-purpose Bayu-Undan into a CCS hub for the region once existing production ceases.

In the onshore McArthur Basin (Beetaloo Sub-basin) in the Northern Territory, the Tanumbirini 2H horizontal well was spudded on 11 May targeting the B Shale interval of the Velkerri gas play. At the end of the quarter, the well was drilling ahead 8 ½" directional hole in Velkerri target formation. Following Tanumbirini 2H, Santos is planning to drill a second horizontal well, Tanumbirini 3H, targeting the Lower B Shale interval. Upon completion of drilling operations, multi-stage stimulation and flow testing of both wells is planned.

Corporate, exploration and eliminations

Santos share Unit Q2 2021 Q1 2021 Q2 2020 2021 YTD 2020 YTD
Total sales volume mmboe 0.2 (0.4) 0.5 (0.2) 0.8
Total sales revenue $million 31 23 17 54 39

Sales volumes and revenues in the corporate segment primarily represent gas trading activities.

Capital expenditure

Total exploration, evaluation and development expenditure is summarised in the table below.

$million Q2 2021 Q1 2021 Q2 2020 2021 YTD 2020 YTD
Capital expenditure
Exploration 29 13 21 42 31
Evaluation 26 57 18 83 43
Development and other capex (inc restoration) 279 131 147 410 298
Capital expenditure excl capitalised interest 334 201 186 535 372
Capitalised interest 12 9 7 21 10
Total capital expenditure 346 210 193 556 382
Exploration and evaluation expensed
Exploration 20 8 13 28 20
Evaluation 12 1 2 13 5
Total current year expenditure 32 9 15 41 25
Write-off of amounts capitalised in prior years - - - - -
Total expensed 32 9 15 41 25

Capital expenditure in the second quarter comprised US$190 million in the base business (including $7 million for restoration costs) and US$144 million for major growth projects.

Oil price hedging

7.3 million barrels of oil hedging matured in the first half resulting in a net outflow before tax of US$66 million.

7.7 million barrels of oil equivalent are currently hedged for the remainder of 2021 using zero cost collars, with an average floor price of US$42 per barrel and an average ceiling price of US$55 per barrel.

For 2022, 6 million barrels of oil equivalent are currently hedged at an average floor price of US$50 per barrel and an average ceiling price of US$64 per barrel using a combination of zero cost collars and three-way option structures. For 2.0 million barrels, there is also the ability to re-participate at an oil price greater than US$65 per barrel due to their three-way option structure.

Seismic activity

In the Bedout Sub-basin, acquisition of the Archer 3D was completed at the end of May with high quality data acquired. The Keraudren Extension 3D, which followed directly after Archer, was 50 per cent complete at the end of the quarter.

Drilling summary

Near-field exploration (NFE) / Appraisal wells

Cooper Basin gas
Well name Area Santos Well status
Anna North 3* QLD 60.06% C&S, successful
Anna North 4 QLD 60.06% C&S, successful
Houby 1 QLD 60.06% C&S, successful
Viper 1 QLD 60.06% P&A
Moonanga 2 SA 60.0% P&A
Raven 5 SA 66.6% P&A
Raven 6 SA 66.6% P&A

*Spud in Q1, completed in Q2

McArthur Basin gas
Well name Area Santos Well status
Tanumbirini 2H NT 75% Drilling
Queensland GLNG gas
Well name Area Santos Well status
Sunshine Ranch 2 Scotia 30.0% C&S, successful
Sunshine Ranch 3 Scotia 30.0% C&C, successful
Vincent Downs 1 Scotia 30.0% C&C, successful

Development wells

Carnarvon Basin oil (Van Gogh)
Well name Area Santos Well status
VGA 18H WA 52.5% C&C, successful
Bayu-Undan gas and condensate
Well name Area Santos Well status
BU W13ST2 TL 43.4% C&C, successful
Cooper Basin gas
Well name Area Santos Well status
Durham DownsNorth 9 QLD 60.06% Drilling
Beckler 7 SA 66.6% C&C, successful
Big Lake 153 SA 66.6% P&A
Big Lake 154 SA 66.6% Drilling
Big Lake 155 SA 66.6% P&A
Big Lake 157 SA 66.6% C&S, successful
Boongala 3 SA 66.6% Drilling
Dilchee 5 SA 66.6% C&S, successful
Tarwonga 7 SA 66.6% C&S, successful
Queensland - GLNG gas
Well name Area Santos Well status
FV07-37-1 Fairview 22.82% C&S, successful
FV11-107-1 Fairview 22.82% C&C, successful
FV12-100-1 Fairview 22.82% C&C, successful
FV12-105-1 Fairview 22.82% C&C, successful
FV12-107-1 Fairview 22.82% C&C, successful
FV12-90-2 Fairview 22.82% C&S, successful
FV12-94-1 Fairview 22.82% C&C, successful
FV17-16-2 Fairview 22.82% C&C, successful
Mount Kingsley 39 Arcadia 22.85% C&S, successful
RM01-05-5 Roma 30.0% C&S, successful
RM09-30-2 Roma 30.0% C&S, successful
RM12-78-1 Roma 30.0% C&S, successful
RM13-13-1 Roma 30.0% C&C, successful
RM13-51-1 Roma 30.0% C&C, successful
RM13-52-1 Roma 30.0% C&C, successful
RM13-54-1 Roma 30.0% C&C, successful
RM13-68-2 Roma 30.0% C&C, successful
RM14-27-2 Roma 30.0% C&C, successful
RM14-27-3 Roma 30.0% C&C, successful
RM15-100-1 Roma 30.0% C&S, successful
RM15-101-1 Roma 30.0% C&S, successful
RM15-108-1 Roma 30.0% C&S, successful
RM15-108-2 Roma 30.0% C&S, successful
RM15-109-1 Roma 30.0% C&S, successful
RM15-110-1 Roma 30.0% C&S, successful
Queensland - GLNG gas
Well name Area Santos Well status
RM15-111-1 Roma 30.0% C&S, successful
RM15-21-1 Roma 30.0% C&C, successful
RM15-23-1 Roma 30.0% C&C, successful
RM15-50-1 Roma 30.0% C&C, successful
RM15-57-1 Roma 30.0% C&C, successful
RM15-58-1 Roma 30.0% C&C, successful
RM15-59-1 Roma 30.0% C&C, successful
RM15-61-1 Roma 30.0% C&S, successful
RM15-62-1 Roma 30.0% C&S, successful
RM15-71-1 Roma 30.0% C&C, successful
RM15-72-1 Roma 30.0% C&S, successful
RM15-80-1 Roma 30.0% C&S, successful
RM15-81-2 Roma 30.0% C&S, successful
RM15-89-1 Roma 30.0% C&S, successful
RM15-89-2 Roma 30.0% C&S, successful
RM15-90-1 Roma 30.0% C&S, successful
RM15-91-1 Roma 30.0% C&S, successful
RM15-92-1 Roma 30.0% C&S, successful
RM15-98-1 Roma 30.0% C&C, successful
RM15-99-2 Roma 30.0% C&C, successful
RM49-167-1 Roma 24.57% C&C, successful
RM49-168-1 Roma 24.57% C&C, successful
RM49-170-1 Roma 24.57% C&C, successful
RM49-171-1 Roma 24.57% C&C, successful

Abbreviations and conversion factors

Abbreviations Conversion factors
C&C cased and completed Sales gas and ethane, 1 PJ 171.937 boe x 10³
C&S cased and suspended Crude oil, 1 barrel 1 boe
gas natural gas Condensate, 1 barrel 0.935 boe
DES delivered ex-ship LPG, 1 tonne 8.458 boe
FEED front-end engineering and design LNG, 1 PJ 18,040 tonnes
FID final investment decision LNG, 1 tonne 52.54 mmBtu
FPSO floating production, storage and offloading
GJ gigajoules
JCC Japan Customs-cleared Crude
kbbls thousand barrels
kt thousand tonnes
LNG liquefied natural gas
LPG liquefied petroleum gas
m million
mmbbl million barrels
mmboe million barrels of oil equivalent
mmBtu million British thermal units
mmscf million standard cubic feet
mt million tonnes
mtpa million tonnes per annum
NFE near-field exploration
mBRT metres below rotary table
P&A plugged and abandoned
pa per annum
PJ petajoules
PSC production sharing contract
t tonnes
TJ terajoules

Disclaimer

This report contains forward looking statements that are subject to risk factors associated with the oil and gas industry. It is believed that the expectations reflected in these statements are reasonable, but they may be affected by a range of variables which could cause actual results or trends to differ materially, including but not limited to: price fluctuations, actual demand, currency fluctuations, geotechnical factors, drilling and production results, gas commercialisation, development progress, operating results, engineering estimates, reserve estimates, loss of market, industry competition, environmental risks, physical risks, legislative, fiscal and regulatory developments, economic and financial markets conditions in various countries, approvals and cost estimates.

All references to dollars, cents or $ in this document are to United States currency, unless otherwise stated. Totals in the tables may not add due to rounding. The symbol "~" means approximately.

Free cash flow (operating cash flows less investing cash flows net of acquisitions and disposals and major growth capital expenditure, less lease liability payments) is a non-IFRS measure that is presented to provide an understanding of the performance of Santos' operations.

This ASX announcement was approved and authorised for release by Kevin Gallagher, Managing Director and Chief Executive Officer.