ROX RESOURCES LIMITED Interim / Quarterly Report 2013

Apr 29, 2013

65741_rns_2013-04-29_f87b84a2-a65f-4700-9c07-bfa838965228.pdf

Interim / Quarterly Report

Open in viewer

Opens in your device viewer

==> picture [103 x 51] intentionally omitted <==

HIGHLIGHTS

Mt Fisher Gold-Nickel

  • Exploration of Rox’s Camelwood nickel sulphide discovery at Fisher East continued during the quarter, with 4,522m of diamond drilling and 3,916m of RC drilling completed

  • Drilling drilling extended the deposit dimensions to over 800m in strike length and down to 400m depth

  • Mineralisation still open along strike and at depth

  • Selected drill intercepts include:

  • 11.4 metres grading 2.9% Ni in hole MFED001, including 6.4 metres grading 3.8% Ni, including 2.9 metres grading 4.7% Ni

  • 16.3 metres grading 1.8% Ni in hole MFED002, including 6.3 metres grading 2.5% Ni, including 0.47 metres grading 5.4% Ni

  • 5.7 metres grading 2.25% Ni in hole MFED005, including 3.1 metres grading 3.4% Ni, including 1.7 metres grading 4.6% Ni

  • 6.15 metres grading 3.3% Ni in hole MFED010, including 1.6 metres grading 5.8% Ni and 0.2 metres grading 11.0% Ni

  • Thicker, higher grade sections of the deposit defined into a Main Zone and a Northern Zone

  • Ground EM surveys that covered 8km strike of prospective stratigraphy defined a number of conductors for drill testing

  • Grant of adjacent exploration licence, completion of heritage survey and approval of PoW

  • Definition of a geological model for the deposit as a typical Kambalda style komatiite-hosted nickel sulphide deposit with zones of massive , semi-massive (matrix) , and disseminated sulphide

Myrtle-Reward Zinc

  • Significant diamond drilling (4,500m) planned to commence at the Teena prospect in the next quarter

Bonya Copper

  • Exploration planned to commence in the next quarter

Corporate

  • $4.6 million raised in a Share Placement

Rox Resources Limited Level 1

30 Richardson Street WEST PERTH WA 6005 Telephone: (61 8) 9226 0044 Facsimile: (61 8) 9325 6254

ROX RESOURCES LIMITED QUARTERLY REPORT For Quarter Ended 31 March 2013

==> picture [103 x 51] intentionally omitted <==

==> picture [310 x 265] intentionally omitted <==

Figure 1: Rox Project Location Map

MT FISHER GOLD-NICKEL PROJECT, WA (Rox 100% & option to purchase 100%)

Rox continues to explore the Mt Fisher project area 450km north of Kalgoorlie in Western Australia, (Figure 1) which hosts the Camelwood nickel sulphide discovery and also has the potential to host a multi-million ounce gold inventory.

Camelwood Nickel Sulphide Deposit

An intense drilling campaign commenced at Camelwood in mid-February 2013 and continued throughout the quarter. One diamond core rig and one reverse circulation (RC) rig were operating. This resulted in 4,522 metres of diamond core drilling in 14 holes and 3,916 metres of RC drilling in 24 holes being completed during the quarter.

Selected highlights from the diamond core drilling are listed below, with complete results listed in Table 1.

MFED001: 11.4m @ 2.9% Ni , including 6.4m @ 3.8% Ni , including 2.9m @ 4.7% Ni from 282.6m

MFED002: 16.3m @ 1.8% Ni , including 6.3m @ 2.5% Ni from 211.7m, and including 0.47m @ 5.4% Ni from 212.0m

MFED005: 5.7m @ 2.3% Ni , including 0.4m @ 5.4% Ni from 382.0m, and including 3.1m @ 3.4% Ni , including 1.7m @ 4.6% Ni from 384.6m

MFED007: 1.2m @ 5.2% Ni , including 0.7m @ 7.8% Ni from 388.7m

  • 2 -

ROX RESOURCES LIMITED QUARTERLY REPORT For Quarter Ended 31 March 2013

==> picture [103 x 51] intentionally omitted <==

MFED008: 1.8m @ 2.8% Ni , including 0.3m @ 4.0% Ni from 350.5m

MFED010: 6.15m @ 3.3% Ni from 341.11m, including 1.6m @ 5.8% Ni from 342.25m

MFED014: 7.4m @ 1.9% Ni , including 1.45m @ 3.6% Ni from 130.6m

Selected highlights from the RC drilling are listed below.

MFEC010: 18m @ 1.5% Ni , including 9m @ 2.0% Ni from 118m

MFEC021: 19m @ 1.3% Ni from 105m

Geological Model

Continued drilling has allowed interpretation of the geological setting as that of a typical komatiite-hosted (Kambalda type) nickel sulphide deposit.

All of the nickel sulphide mineralisation occurs at or near to the “basal contact” of an intensely talc-carbonate altered, high-magnesium ultramafic rock (komatiite lava flow) with the stratigraphic footwall felsic sediment. Stratigraphically above the high-magnesium komatiite flow is a sequence of lower magnesium komatiite flows overlain by a sequence of mafic rocks (lavas and possible intrusive sills).

The mineralised zone itself is zoned, with a stratigraphically lowermost massive sulphide zone (e.g. Figure 5) overlain by a semi-massive (matrix) sulphide zone and then an uppermost disseminated sulphide zone, hosted within the intensely talc-carbonate altered high-magnesium ultramafic rocks. Due to faulting and other structural complications not all of these mineralised zones are present in all holes.

The evolving understanding of the geological setting of the deposit will greatly assist in planning and optimising ongoing drill programs.

Drilling to date at Camelwood has been undertaken with two main aims:

  1. To define the lateral extent of mineralisation (along strike) and to characterise the mineralisation at depth.

  2. To define lenses/pods of thicker, higher grade mineralisation.

That approach has been highly successful with an 800m strike length defined and mineralisation drilled down to approximately 400m below surface on selected sections. Of the 44 holes drilled to date (20 diamond core and 24 RC, including 6 diamond holes drilled in April) only 4 have not intersected significant nickel mineralisation. The limits of the mineralised system have yet to be defined both along strike and at depth. This is clearly an extensive and continuous mineralised system.

The drilling to define thicker higher grade mineralisation has also been successful where two broad areas of mineralisation have now become apparent at Camelwood, termed the Main Zone and the Northern Zone (Figures 2 & 3).

  • 3 -

ROX RESOURCES LIMITED QUARTERLY REPORT For Quarter Ended 31 March 2013

==> picture [103 x 51] intentionally omitted <==

Recent drilling has concentrated on the Northern Zone where a potentially thicker, higher grade zone of mineralisation is present. It is defined by such holes as MFEC010 (18m @ 1.53% Ni), MFEC021 (19m @ 1.3% Ni) and new hole MFED014: 7.4m @ 1.9% Ni, including 1.45m @ 3.6% Ni from 130.6m (see Figures 2 & 3 and Table 1).

The Main Zone is defined by holes such as MFED001 (11.4m @ 2.9% Ni), MFED002 (16.3m @ 1.8% Ni), MFED005 (5.7m @ 2.25% Ni), MFED008 (1.8m @ 2.8% Ni) and MFED010 (6.15m @ 3.3% Ni). This mineralisation forms a zone that is interpreted to plunge north (Figures 3 & 4) and is still open at depth. Already it has the dimensions to be a potentially economic zone of mineralisation.

Ground EM Survey

A ground EM survey using a fixed loop configuration was undertaken to map out the prospective nickel-sulphide bearing horizon along 8km of strike, including the Corktree and Silverbark VTEM anomalies, which lie along strike from Camelwood (Figure 6).

The results confirmed the strong VTEM conductive zones at Corktree, Camelwood and Silverbark, and also highlighted the area between Camelwood and Silverbark as a conductive zone at depth.

Looking Ahead

Diamond and RC drilling is continuing at Camelwood. New holes recently drilled are shown on Figures 2 & 3.

Ongoing diamond drilling is focussing on extending and defining the thicker and higher grade zone in the Main Zone that is interpreted to be plunging north from holes MFED002 through MFED001 and MFED010 (Figures 3 & 4).

In addition, step back drilling on the newly granted Exploration Licence E53/1716 (Figure 7) to test the southern and deeper portions of the Main Camelwood EM conductor is now able to commence as the heritage survey has been completed and the Program of Works (PoW) has been approved by the WA Department of Mines and Petroleum.

The nickel sulphide discovery is located on tenements that Rox has under an Option to Purchase. The exercise price is $3.5 million, with approximately 15 months of the Option still to run.

  • 4 -

ROX RESOURCES LIMITED QUARTERLY REPORT For Quarter Ended 31 March 2013

==> picture [103 x 51] intentionally omitted <==

==> picture [441 x 522] intentionally omitted <==

Figure 2: Camelwood Prospect Drill Hole Plan

  • 5 -

ROX RESOURCES LIMITED QUARTERLY REPORT For Quarter Ended 31 March 2013

==> picture [103 x 51] intentionally omitted <==

==> picture [632 x 413] intentionally omitted <==

Figure 3: Camelwood Drill Long Section

  • 6 -

ROX RESOURCES LIMITED QUARTERLY REPORT For Quarter Ended 31 March 2013

==> picture [103 x 51] intentionally omitted <==

==> picture [443 x 609] intentionally omitted <==

Figure 4: Camelwood Main Zone Long Section

  • 7 -

ROX RESOURCES LIMITED QUARTERLY REPORT For Quarter Ended 31 March 2013

==> picture [103 x 51] intentionally omitted <==

==> picture [180 x 239] intentionally omitted <==

Figure 5: Massive Sulphide core from hole MFED001

==> picture [250 x 354] intentionally omitted <==

Figure 6: Ground EM Channel 25, Z component, Camelwood to Silverbark, showing possible fault offset (dashed black line) north of Camelwood. Strong EM responses are white/red, while weaker responses are blue/green

  • 8 -

ROX RESOURCES LIMITED QUARTERLY REPORT For Quarter Ended 31 March 2013

==> picture [103 x 51] intentionally omitted <==

==> picture [428 x 557] intentionally omitted <==

Figure 7: Tenement Plan Mt Fisher Project. Black and red shaded tenements are 100% owned by Rox, while blue shaded tenements are subject to an Option to Purchase Agreement

  • 9 -

ROX RESOURCES LIMITED QUARTERLY REPORT For Quarter Ended 31 March 2013

==> picture [103 x 51] intentionally omitted <==

Table 1: Camelwood RC Drilling Results

Hole East North Depth
(m)
Dip Azimuth From
(m)
To
(m)
Interval Ni%
MFEC001 355899 7035798 162 -70 270 130 133 3 1.27
Including 130 132 2 1.58
MFEC002 355956 7035802 242 -75 270 212 216 4 1.99
MFEC003 355986 7035594 172 -65 270 141 146 5 1.45
And 152 155 3 1.72
Including 152 154 2 2.22
MFEC004 355974 7035692 182 -60 270 159 179 20 1.06
Including 159 165 6 1.36
Including 169 174 5 1.49
MFEC005 355903 7035893 187 -60 270 147 148 1 2.99
MFEC006 355994 7035506 150 -65 270 126 126 1 2.48
MFEC007 355854 7035998 150 -60 268 118 121 3 1.82
MFEC010 355829 7036103 150 -60 270 118 136 18 1.53
Including 119 128 9 2.04
MFEC012 355832 7036200 168 -70 270 153 154 1 1.10
MFEC013 355818 7036247 162 -60 270 Terminated short of target
MFEC015 355845 7036059 162 -60 270 125 130 5 1.33
MFEC016 355881 7035958 156 -60 270 129 133 4 1.11
MFEC017 355720 7036259 86 -60 270 NSR (gossanous 56-65m)
MFEC020 355928 7035750 174 -60 270 141 146 5 1.80
Including 141 143 2 2.49
And 157 159 2 1.49
MFEC021 355769 7036249 150 -60 270 105 124 19 1.32
MFEC022 355933 7035854 216 -60 270 186 187 1 2.55
MFEC023 355750 7036300 141 -60 270 101 120 19 0.44
MFEC024 355970 7035650 186 -60 270 144 148 4 1.27
And 155 159 4 1.04
MFED001 355997 7035799 397.3 -75 270 282.6 294.0 11.4 2.93
Including 282.6 289.0 6.4 3.80
Including 282.6 285.5 2.9 4.66
MFEC002 355996 7035702 261.5 -75 270 211.7 228 16.3 1.79
Including 211.7 218 6.3 2.53
Including 212.0 212.47 0.47 5.42
MFED003 355991 7035593 210.9 -80 270 178.3 185.8 7.5 1.22
Including 178.3 178.7 0.4 3.76
MFED004 355900 7036097 216.1 -60 270 197.3 214.4 17.1 0.47
MFED005 355995 7035900 421.3 -78 270 382.0 387.7 5.7 2.25
Including 382.0 382.4 0.4 5.38
And 384.6 387.7 3.1 3.37
Including 384.6 386.3 1.7 4.64
MFED006 355995 7035900 346.2 -70 270 317.7 319.0 1.3 2.55
Including 317.7 318.3 0.6 3.76
MFED007 356000 7035795 421.1 -85 270 388.7 389.9 1.2 5.20
Including 388.7 389.4 0.7 7.79
MFED008 355999 7035850 376.3 -80 275 350.5 352.3 1.8 2.81
  • 10 -

ROX RESOURCES LIMITED QUARTERLY REPORT For Quarter Ended 31 March 2013

==> picture [103 x 51] intentionally omitted <==

Including Including Including Including Including Including 350.5 350.8 0.30 4.03
MFED009 355999 7035850 426.9 -85 270 401.66 403.70 2.04 1.61
Including 401.66 401.88 0.22 3.49
And 402.75 403.70 0.95 2.60
MFED010 355999 7035850 367.2 -72 270 341.11 347.26 6.15 3.30
Including 341.11 341.38 0.27 3.43
And 341.66 341.85 0.19 10.97
And 342.25 347.26 5.01 3.43
Including 342.25 343.89 1.64 5.81
MFED011 355999 7035850 316 -62 274 293.71 293.98 0.27 1.88
MFED012 355996 7035702 427.1 -90 270 375.68 376.42 0.74 3.84
MFED013 355823 7036149 171.45 -65 268 140.87 141.55 0.68 5.88
MFED014 355823 7036149 162.3 -55 268 130.60 138.00 7.40 1.89
Including 130.60 132.05 1.45 3.60

Notes:

  • Grid coordinates GDA94: Zone 51, Collar positions determined by hand held GPS.

  • All holes nominal RL 530 AHD.

  • RC drilling (hole prefix MFEC) by reverse circulation face sampling hammer, then 1 metre samples split and bagged.

  • Diamond drilling (hole prefix MFED) by HQ/NQ diamond core, with core cut in half and sampled to either significant geological boundaries or even metre intervals.

  • Diamond drill samples weighed in water and air to determine bulk density, and then crushed to 6.5mm

  • 3-5kg sample preparation by pulp mill to nominal P80/75um.

  • Ni assays by ICP-OES following a 4 acid digest (Intertek analysis code 4A/OE).

  • Certified Reference Standards and field duplicate samples were inserted at regular intervals to provide assay quality checks. Review of the standards and duplicates are within acceptable limits.

  • Cut-off grade 1% Ni with up to 2m of internal dilution allowed (with the exception of holes MFED004 & MFEC023).

  • Given the angle of the drill holes and the interpreted dip of the host rocks, reported intercepts will be more than true width.

  • 11 -

ROX RESOURCES LIMITED QUARTERLY REPORT For Quarter Ended 31 March 2013

==> picture [103 x 51] intentionally omitted <==

MYRTLE-REWARD ZINC-LEAD PROJECT, NT (Rox 100%, Teck earning up to 70%)

Teck Australia Pty Ltd. (“Teck”) may earn an initial 51% interest in the Myrtle-Reward project located adjacent to the McArthur River zinc-lead mine in the Northern Territory by expenditure of $5 million by August 2014, and can earn up to a 70% interest through the expenditure of $15 million by August 2018. Teck is operator of the project while it is sole contributing to expenditure, or is the majority owner, and to date has expended approximately $2.8 million.

Drilling to confirm the impressive grades and thicknesses from historic drilling previously reported from the Teena prospect (Figure 11) is expected to occur early in the 2013 field season.

BONYA COPPER PROJECT, NT (Rox earning up to 70%)

Under the terms of a farm-in and joint venture agreement with Arafura Resources, Rox can earn an initial 51% interest in the copper, lead, zinc, silver, gold, bismuth and PGE mineral rights (Cu-Pb-Zn-Ag-Au-Bi-PGE) in the project by expenditure of $500,000 in the first 2 years, with a minimum expenditure of $150,000 in the first year. Rox can elect to earn a further 19%, and increase its interest to a total of 70%, by spending a further $1 million over an additional 2 years.

Located adjacent to the Jervois copper deposit (JORC Mineral Resource of 11.9 Mt @ 1.3% Cu, 25 g/tAg), 350km east of Alice Springs, Northern Territory (Figure 1), visible outcropping copper mineralisation has returned rock chip assays up to 33% copper, 55 g/t silver and 0.6 g/t gold, including significant levels of lead (Pb).

Rox plans to commence exploration at Bonya in the next quarter with some airborne geophysics and surface mapping, prior to drilling.

MARQUA PHOSPHATE PROJECT, NT (Rox 100%)

Rox is seeking a strategic partnership to take the Marqua phosphate project forward.

CORPORATE

Following a capital raising (share placement) of $4.6 million during the quarter, cash on hand at the end of the quarter was $5.32 million.

Dated this 30th day of April 2013.

Signed on behalf of the Board of Rox Resources Limited.

==> picture [140 x 60] intentionally omitted <==

IAN MULHOLLAND Managing Director

  • 12 -

ROX RESOURCES LIMITED QUARTERLY REPORT For Quarter Ended 31 March 2013

==> picture [103 x 51] intentionally omitted <==

About Rox Resources

Rox Resources Limited is an emerging Australian minerals exploration company. The company has four key assets at various levels of development with exposure to gold, nickel, zinc, lead, copper and phosphate, including the Mt Fisher Gold Project (WA), Myrtle/Reward Zinc-Lead Project (NT), the Bonya Copper Project (NT) and the Marqua Phosphate Project (NT).

Mt Fisher Gold-Nickel Project (100% + Option to Purchase)

The Mt Fisher gold project is located in the highly prospective North Eastern Goldfields region of Western Australia and in addition to being well endowed with gold the project hosts a strong potential for nickel. The total project area is 655km[2] , consisting of a 485km[2] area 100% owned by Rox and an Option to purchase 100% of a further 170km[2] .

Initial drilling by Rox has defined numerous high-grade targets and defined a Measured, Indicated and Inferred Mineral Resource of 973,000 tonnes grading 2.75 g/t gold to be defined for 86,000 ounces of gold (Measured: 171,900 tonnes grading 4.11 g/t Au, Indicated: 204,900 tonnes grading 2.82 g/t Au, Inferred: 596,200 tonnes grading 2.34 g/t Au).

Drilling at the Camelwood nickel prospect has intersected semi-massive to massive and disseminated nickel sulphide mineralisation in a number of holes along an 800m strike length and up to 350m depth, including 11.4m @ 2.9% Ni and 6.15m @ 3.3% Ni , with the mineralisation open in all directions.

Reward Zinc-Lead Project (Farm-out Agreement)

Rox has signed an Earn-In and Joint Venture Agreement with Teck Australia Pty Ltd. (“Teck”) to explore its 670km[2] Myrtle/Reward zinc-lead tenements, located 700km south-east of Darwin, Northern Territory. The Myrtle deposit has a current Inferred Mineral Resource of 43.6 Mt @ 5.04% Zn+Pb (Indicated: 5.8 Mt @ 3.56% Zn, 0.90% Pb; Inferred: 37.8 Mt @ 4.17% Zn, 0.95% Pb). Historic drill intercepts of sediment-hosted mineralisation exist at the Teena prospect, including 11.3m @ 10.9% Zn+Pb and 8.6m @ 9.84% Zn+Pb . Under the terms of the agreement, Teck are required to spend A$5m by 31 August 2014 to earn an initial 51% interest. Teck can increase its interest in the project to 70% by spending an additional A$10m (A$15m in total) over an additional 4 years.

Bonya Copper Project (Farm-in Agreement to earn up to 70%)

In October 2012 Rox signed a Farm-in Agreement with Arafura Resources Limited to explore the Bonya Copper Project located 350km east of Alice Springs, Northern Territory. Outcrops of visible copper grading up to 33% Cu and 55 g/t Ag are present. Under the agreement, Rox can earn a 51% interest in the copper, lead, zinc, silver, gold, bismuth and PGE mineral rights by spending $500,000 within the first two years. Rox can elect to earn a further 19% (for 70% in total) by spending a further $1 million over a further two years. Once Rox has earned either a 51% or 70% interest it can form a joint venture with Arafura to further explore and develop the area.

Marqua Phosphate Project (100%)

Rox owns four tenements covering approximately 1,900 km[2] in the Northern Territory which comprise the Marqua Phosphate project. The project has the potential for a sizeable phosphate resource to be present, with surface sampling returning values up to 39.4% P2O5 and drilling (including 6m @ 19.9% P2O5 and 5m @ 23.7% P2O5) confirming a 30km strike length of phosphate bearing rocks. In addition to phosphate, there is also potential for lead-zinc mineralisation. The project is located 300km south-west of Mt Isa, and is situated 250km from the nearest railhead and gas pipeline at Phosphate Hill.

Competent Person Statement:

The information in this report that relates to Exploration Results and Mineral Resources is based on information compiled by Mr Ian Mulholland BSc (Hons), MSc, FAusIMM, FAIG, FSEG, MAICD, who is a Fellow of The Australasian Institute of Mining and Metallurgy and a Fellow of the Australian Institute of Geoscientists. Mr Mulholland has sufficient experience which is relevant to the style of mineralisation and type of deposit under consideration, and to the activity which he is undertaking to qualify as a Competent Person as defined in the 2004 Edition of the “Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves”. Mr Mulholland is a full time employee of the Company and consents to the inclusion in the report of the matters based on his information in the form and context in which it appears.

  • 13 -

ROX RESOURCES LIMITED QUARTERLY REPORT For Quarter Ended 31 March 2013

==> picture [115 x 58] intentionally omitted <==

APPENDIX 5B

Mining Exploration Entity Quarterly Report

Name of entity

Name ofentity
ROX RESOURCES LIMITED Quarterended (“current quarter”)
ACNor ARBN
107 202 602
Consolidated statement of cash flows
31 March 2013
Cash flows related to operating activities
1.1
Receipts from product sales and related debtors
1.2
Payments for: (a) exploration and evaluation
(b) development
(c) production
(d) administration
1.3
Dividends received
1.4
Interest and other items of a similar nature received
1.5
Interest and other costs of finance paid
1.6
Income taxes paid
1.7
Other – Security bonds repayments
Net Operating Cash Flows
Current Quarter
A$’000
Year to Date
(9 months)
$A’000
-
(876)
-
-
(296)
-
23
-
-
-
-
(1,443)
-
-
(721)
-
40
-
-
-
(1,149) (2,124)
Cash flows related to investing activities
1.8
Payment for purchases of:
(a) prospects
(b) equity investments
(c) other fixed assets
1.9
Proceeds from sale of:
(a) prospects
(b) equity investments
(c) other fixed assets
1.10 Loans to other entities
1.11 Loans repaid by other entities
1.12 Other -
Net investing cash flows
1.13 Total operating and investing cash flows (carried
forward)
-
-
(22)
-
-
-
-
-
-
-
-
(23)
-
54
-
-
-
-
(22) 31
(1,171)) (2,093)
  • 14 -

ROX RESOURCES LIMITED QUARTERLY REPORT For Quarter Ended 31 March 2013

==> picture [115 x 58] intentionally omitted <==

1.13 Total operating and investing cash flows (brought
forward)
(1,171) (2,093)
Cash flows related to financing activities
1.14 Proceeds from issues of shares (net of costs)
1.15 Proceeds from sale of forfeited shares
1.16 Proceeds from borrowings
1.17 Repayment of borrowings
1.18 Dividends paid
1.19 Other
Net financing cash flows
4,607
-
-
-
-
-
6,102
-
-
-
-
-
4,607 6,102
Net increase (decrease) in cash held
1.20 Cash at beginning of quarter/year to date
1.21 Exchange rate adjustments to 1.20
1.22Cash at end of quarter
3,436
1,883
-
4,009
1,310
-
5,319 5,319

Payments to directors of the entity and associates of the directors Payments to related entities of the entity and associates of the related entities

1.23 Aggregate amount of payments to the parties included in item 1.2
1.24 Aggregate amount of loans to the parties included in item 1.10
Current quarter
$A’000
130
-
  • 1.25 Explanation necessary for an understanding of the transactions

N/A

Non-cash financing and investing activities

  • 2.1 Details of financing and investing transactions which have had a material effect on consolidated assets and liabilities but did not involve cash flows

Nil

  • 2.2 Details of outlays made by other entities to establish or increase their share in projects in which the reporting entity has an interest

  • 15 -

ROX RESOURCES LIMITED QUARTERLY REPORT For Quarter Ended 31 March 2013

==> picture [115 x 58] intentionally omitted <==

Financing facilities available

Add notes as necessary for an understanding of the position.

3.1 Loan facilities
3.2 Credit standby arrangements
Amount available
$A’000
Amount used
$A’000
- -
- -

Estimated cash outflows for next quarter

4.1
Exploration and evaluation
4.2
Development
4.3
Production
4.4
Administration
$A’000
2,400
-
-
300
Total 2,700

Reconciliation Of Cash

Reconciliation Of Cash
Reconciliation of cash at the end of the quarter (as shown in
the consolidated statement of cash flows) to the related items
inthe accountsis asfollows.
Current quarter
$A’000
Previous quarter
$A’000
5.1
Cash on hand and at bank
5.2
Deposits at call
5.3
Bank overdraft
5.4
Other (provide details)
4,559 1,078
760 755
- -
- -
Total: cash at end of quarter(item 1.22) 5,319 1,833

Changes in interests in mining tenements

Tenement
reference
Nature of
Interest
Interest at
beginning of
quarter
Interest at
end of
quarter
6.1
Interest in mining tenements
relinquished, reduced or lapsed
6.2
Interest in mining tenements acquired or
increased
- - - -
- - - -
  • 16 -

ROX RESOURCES LIMITED QUARTERLY REPORT For Quarter Ended 31 March 2013

==> picture [115 x 58] intentionally omitted <==

Issued and quoted securities at end of current quarter

Total number Number
quoted
Issue price per
security (cents)
Amount paid up per
security (cents)
7.1Preference
securities
(description)
7.2 Changes during
quarter
-
-
7.3Ordinary
securities
7.4 Changes during
quarter
- Issued
- Options exercised
590,809,744 590,809,744
90,000,000
-
90,000,000
-
$0.055
-
$0.055
-
7.5Convertible debt
securities
(description and
conversion factor)
7.6 Changes during
quarter
-
-
7.7Options
(description and
conversion factor)
550,000
8,500,000
Nil
Nil
Exercise Price
$0.047
$0.025
Expires
30 Nov 2014
30 Nov 2015
7.8 Issued during
quarter
- - - -
7.9 Exercised during
quarter
- - - -
7.10 Expired during
quarter
- - - -
7.11Debentures
(totals only)
- - - -
7.12Unsecured notes
(totals only)
- - - -
  • 17 -

ROX RESOURCES LIMITED QUARTERLY REPORT For Quarter Ended 31 March 2013

==> picture [115 x 58] intentionally omitted <==

Compliance statement

  1. This statement has been prepared under accounting policies which comply with accounting standards as defined in the Corporations Law or other standards acceptable to ASX.

  2. This statement does give a true and fair view of the matters disclosed.

Sign here:

Date: 30 April 2013

==> picture [109 x 44] intentionally omitted <==

Company Secretary

Print Name: Brett Dickson

  • 18 -