AI assistant
Resolute Mining Limited — Investor Presentation 2018
Aug 23, 2018
10548_rns_2018-08-23_48818790-ae64-497f-9788-2d22df7a2c3e.pdf
Investor Presentation
Open in viewerOpens in your device viewer
==> picture [235 x 224] intentionally omitted <==
Mine Gold. Create Value.
Maintaining Profitability During Development
2018 Full Year Results Presentation | August 2018
==> picture [960 x 19] intentionally omitted <==
==> picture [960 x 22] intentionally omitted <==
Important Notices and Disclaimers
This presentation contains information about Resolute Mining Limited (Resolute or the Company) and its activities that is current as at the date of this presentation unless otherwise stated. The information in this presentation remains subject to change without notice. This presentation has been prepared by Resolute and no party other than Resolute has authorised or caused the issue, lodgement, submission, despatch or provision of this presentation. The information in this presentation is general in nature and does not purport to be complete. This presentation is not a prospectus, disclosure document or other offering document under Australian law or under the laws of any other jurisdiction. This presentation is provided for information purposes and does not constitute an offer, invitation or recommendation to subscribe for or purchase securities in Resolute in any jurisdiction.
The information contained in this presentation has been prepared in good faith by Resolute, however no guarantee, representation or warranty expressed or implied is or will be made by any person (including Resolute and its affiliates and their directors, officers, employees, associates, advisers and agents) as to the accuracy, reliability, correctness, completeness or adequacy of any statements, estimates, options, conclusions or other information contained in this presentation.
To the maximum extent permitted by law, Resolute and its affiliates and their directors, officers, employees, associates, advisers and agents each expressly disclaims any and all liability, including, without limitation, any liability arising out of fault or negligence, for any loss or damage suffered by any person relating in any way to the use of or reliance on information contained in this presentation including, without limitation:
-
from representations or warranties or in relation to the accuracy or completeness of the information contained within this presentation;
-
from statements, opinions, forecasts, reports or other matters, express or implied, contained in, arising out of or derived from this presentation; or
-
for omissions from this presentation including, without limitation, any financial information, any estimates, forecasts, or projections and any other financial information derived therefrom.
This presentation does not constitute financial product advice, investment, legal, taxation or other advice and is not intended to be used or relied upon as the basis for making an investment decision. This presentation is not a recommendation to acquire Resolute securities and has been prepared without taking into account the investment objectives, taxation situation, financial situation or needs of individuals. Before making any investment decision in connection with any acquisition of Resolute securities, prospective investors should consider the appropriateness of the information having regard to their own objectives, tax situation, financial situation and needs and seek financial, legal and taxation advice appropriate to their jurisdiction.
Past performance information given in this presentation is for illustrative purposes only and should not be relied upon as an indication of future performance. This presentation includes certain forward-looking statements, including statements regarding our intent, belief or current expectations with respect to Resolute’s business and operations, market conditions, results of operations and financial condition, and risk-management practices. Words such as ‘project’, ‘foresee’, ‘plan’, ‘expect’, ‘aim’, ‘intend’, ‘anticipate’, ‘believe’, ‘estimate’, ‘may’, ‘should’, ‘will’ and similar expressions are intended to identify forward-looking statements. Indications of, and guidance on, future earnings and financial position and performance are also forward-looking statements. Forward-looking statements are provided as a general guide only and should not be relied upon as an indication or guarantee of future performance. These statements are based upon a number of estimates and assumptions that, while considered reasonable by Resolute, are inherently subject to significant uncertainties and contingencies, many of which are outside the control of Resolute, involve known and unknown risks and uncertainties that could cause actual events or results to differ materially from estimated or anticipated events or results reflected in such forward looking statements on certain assumptions, which may prove to be incorrect. Actual results, performance, actions and developments of Resolute may differ materially from those expressed or implied by the forward-looking statements in this presentation.
As an Australian company listed on the Australian Securities Exchange (ASX), Resolute is required to report ore reserves and mineral resources in Australia in accordance with the Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves (JORC Code). Recipients should note that while Resolute’s mineral resource and ore reserve estimates comply with the JORC Code, they may not comply with relevant guidelines in other countries.
For details of the Mineral Resources and Ore Reserves used in this presentation, please refer to ASX Announcement dated 16 August 2018 titled “Annual Ore Reserve and Mineral Resource Statement as at 30 June 2018”. The Company is not aware of any new information or data that materially affects the Mineral Resources and Ore Reserves as reported in that ASX Announcement and confirms that all material assumptions and technical parameters underpinning this plan continue to apply and have not materially changed. The form and context in which the Competent Persons’ findings are presented have not been materially modified.
Notes
-
US$ numbers quoted are weighted average in US$, at prevailing exchange rates
-
All in Sustaining Costs (AISC) per ounce of gold produced are calculated in accordance with World Gold Council guidelines. These measures are included to assist investors to better understand the performance of the ‐
-
business. Cash cost per ounce of gold produced and AISC are non International Financial Reporting Standards financial information
==> picture [960 x 10] intentionally omitted <==
1
==> picture [109 x 103] intentionally omitted <==
Mine Gold. Create Value.
FY19 Guidance Market 300koz at Capitalisation US$960/oz A$1bn (A$1,280/oz)
Portfolio 3 Mines Multiple Strategic Investments
Global Mineral Resources Landholding 16.5Moz 5,300 Global Ore Reserves km[2] 5.9Moz
Note: Global Ore Reserves and Global Mineral Resources are as at 30 June 2018 and based on Resolute’s managed inventory plus Resolute’s attributable share of Resources associated with its strategic equity investments in various listed explorers.
2
==> picture [960 x 19] intentionally omitted <==
==> picture [960 x 22] intentionally omitted <==
(ASX:RSG) Corporate Summary
~~Ca italisation p~~
| Corporate Su |
mmary | (ASX:RSG) |
|---|---|---|
| ~~Capitalisation~~ | A$ | US$ |
| Share Price | $1.34 | $0.99 |
| Shares Outstanding | 752.8m | |
| Market Capitalisation | $1,009m | $746m |
| Cash, Bullion, Investments | $112m | $83m |
| Borrowings | $33m | $24m |
| Enterprise Value | $930m | $687m |
Price Performance and Trading
YTD Daily Trading Averages : Volume: 6.4m / Value: A$7.8m
Availability Liquidity of ~A$250m
Cash Bullion Invmts Undrawn Facility 17% 15% 13% 55% A$42m A$37m A$33m A$135m
Dividend Policy
FY18 Dividend
==> picture [64 x 43] intentionally omitted <==
2% of annual sales revenue offered in gold or cash
2.0 cents per share 3.3% of sales revenue
Note: market data as at 23 August 2018. Cash, bullion, investments, borrowings and undrawn facility as at 30 June 2018.
==> picture [960 x 10] intentionally omitted <==
3
==> picture [960 x 20] intentionally omitted <==
FY18: Maintaining Profitability During Development
Syama DFS Update delivers >300kozpa at US$746/oz LOM AISC (14 year life) Development progressing well at Syama Underground; on track for sub-level caving by December 2018 Ravenswood Expansion Project delivers 115kozpa at US$823/oz LOM AISC (14 year life) Bibiani Update demonstrates ~100kozpa at ~US$750/oz LOM AISC (10 year life) Nafolo and Tabakoroni: stunning exploration results Major gold inventory upgrade; 16.5Moz Global Resources / 5.9Moz Global Reserves Development project optionality enhanced through multiple strategic investments US$100m revolver secured to maximise financial flexibility Profitability maintained during development phase; Net Profit After Tax of A$78m Strong shareholder returns; Dividend of 2.0 cents per share (dividend payout of 3.3% of FY18 revenue)
4
==> picture [960 x 20] intentionally omitted <==
Mine Gold. FY18 284,185oz US$1,052/oz Total Gold Production All-In Sustaining Cost (A$1,355/oz) 262,381oz US$1,318/oz Total Gold Sold Ave Price Received (A$1,703/oz)
5
==> picture [960 x 20] intentionally omitted <==
Create Value. FY18 A$446m A$112m Revenue from Gold and Silver Sales Cash, Bullion and Listed Investments A$78m 35% Net Profit After Tax Increase in Global Mineral Resources A$0.09 A$0.02 Diluted Earnings Per Share Dividend Per Share
6
==> picture [960 x 19] intentionally omitted <==
==> picture [960 x 22] intentionally omitted <==
Dividend Declared of 2.0c per share
Resolute’s Commitment to Shareholder Returns
Dividend Summary
- The 2.0c per share cash or gold dividend payment will total A$14.8m which equates to 3.3% of FY18 revenue
GOLD your today
- Shareholders with 5,000 shares or more at Record Date can elect to receive their dividend in as part of GOLD Resolute’s innovative collaboration with the governmentguaranteed, Perth Mint
Key Dates
Ex-Dividend Date
31 August 2018
Record Date
3 September 2018
Election Date
1 October 2018
Payment Date
12 October 2018
==> picture [960 x 10] intentionally omitted <==
7
==> picture [960 x 19] intentionally omitted <==
==> picture [960 x 22] intentionally omitted <==
Financial Performance During Development
Revenue (A$m)
==> picture [303 x 171] intentionally omitted <==
----- Start of picture text -----
555
541
459
446
FY15 FY16 FY17 FY18
----- End of picture text -----
EBITDA (A$m)(A$m)
==> picture [616 x 194] intentionally omitted <==
----- Start of picture text -----
EBITDA (A$m)(A$m) Net Profit After Tax (A$m)
35% 32% 33% 12% 71 155 177 69
180 176 201
158 166
78
FY15 FY16 FY17 FY18
52
FY15 FY16 FY17 FY18 (569)
Margin Gross Profit
----- End of picture text -----
Return On Equity (%)
==> picture [303 x 171] intentionally omitted <==
----- Start of picture text -----
122
49
12
FY15 FY16 FY17 FY18
(81)
----- End of picture text -----
Earnings Per Share (Ac/share)
Dividend Per Share (Ac/share)
==> picture [606 x 171] intentionally omitted <==
----- Start of picture text -----
26.1
18.6 2.0 2.0
8.7 1.7
FY15 FY16 FY17 FY18
Nil
(78.4) )
FY15 FY16 FY17 FY18
----- End of picture text -----
==> picture [960 x 10] intentionally omitted <==
8
==> picture [960 x 19] intentionally omitted <==
==> picture [960 x 22] intentionally omitted <==
Operating Performance During Development
Production (koz) FY19: 300koz
==> picture [451 x 171] intentionally omitted <==
----- Start of picture text -----
329 330
315
284
FY15 FY16 FY17 FY18
----- End of picture text -----
Gold Sales (koz)
==> picture [452 x 171] intentionally omitted <==
----- Start of picture text -----
341
313 317
262
FY15 FY16 FY17 FY18
----- End of picture text -----
All-In Sustaining Cost (US$/oz) FY19: US$960/oz
==> picture [451 x 171] intentionally omitted <==
----- Start of picture text -----
1,094 1,200 1,132 1,355
1,052
916
874 853
FY15 FY16 FY17 FY18
A$/oz
----- End of picture text -----
Realised Price (US$/oz)
==> picture [452 x 171] intentionally omitted <==
----- Start of picture text -----
1,468 1,624 1,717 1,703
1,274 1,295 1,318
1,223
FY15 FY16 FY17 FY18
A$/oz
----- End of picture text -----
==> picture [960 x 10] intentionally omitted <==
9
==> picture [960 x 19] intentionally omitted <==
==> picture [960 x 22] intentionally omitted <==
Extensive Reserve and Resource Growth Resolute has added ~8Moz to its Global Resource since 2010
Global Mineral Resources
2010 2018 8.1 Moz 16.5 Moz Global Ore Reserves
==> picture [59 x 97] intentionally omitted <==
2010 2.9 Moz
2018 5.9 Moz
FY18 Reserves Contribution (Moz)
5.9 5.3
Discovery Cost of A$36.5 per Reserve Ounce
10
Note: FY10 and FY18 Reserves and Resources are as at 30 June 2018 and reported on a 100% basis. Investments (Attributable) is Resolute’s share of Resources associated with its investments in listed exploration companies.
==> picture [960 x 19] intentionally omitted <==
==> picture [960 x 22] intentionally omitted <==
Significant Investment Enables Transformation
Expenditure (A$m)
==> picture [446 x 167] intentionally omitted <==
----- Start of picture text -----
275
Capital Exploration Strategic Investment
140
93
55
FY15 FY16 FY17 FY18
----- End of picture text -----
Resources (Moz)
==> picture [446 x 167] intentionally omitted <==
----- Start of picture text -----
Resolute Managed Resources Strategic Investments - Attributable Resources
16.5
14.0
12.1 12.1
FY15 FY16 FY17 FY18
----- End of picture text -----
==> picture [156 x 72] intentionally omitted <==
----- Start of picture text -----
Syama
----- End of picture text -----
==> picture [156 x 73] intentionally omitted <==
----- Start of picture text -----
Ravenswood
----- End of picture text -----
==> picture [156 x 73] intentionally omitted <==
----- Start of picture text -----
Bibiani
----- End of picture text -----
==> picture [156 x 73] intentionally omitted <==
----- Start of picture text -----
Strategic
Investments
----- End of picture text -----
Mine Life (Years) Operating Statistics 2012 2018 • +300kozpa • 6 14 • US$746/oz AISC Fully automated sublevel caving • ~115kozpa • US$823/oz AISC 4 14 • Bulk open pit mining • ~100kozpa • ~US$750/oz AISC NA 10 • FID post Syama UG ramp-up
==> picture [306 x 73] intentionally omitted <==
==> picture [960 x 10] intentionally omitted <==
11
==> picture [960 x 19] intentionally omitted <==
==> picture [960 x 22] intentionally omitted <==
Clear Pathway to 500kozpa
==> picture [930 x 384] intentionally omitted <==
----- Start of picture text -----
Production Outlook (koz)
500
400
300
200
100
FY18 FY19 FY20 FY21 FY22
Annual Gold Production (koz)
----- End of picture text -----
Note: The target ounces are entirely based on current Ore Reserves. All Ore Reserves which underpin the plan have been prepared by a Competent Person or Persons in accordance with the JORC Code. For details of Ore Reserves used for the plan, please refer to the ASX Announcement dated 16 August 2018 titled Annual Ore Reserve and Mineral Resource Statement as at 30 June 2018
==> picture [960 x 10] intentionally omitted <==
12
==> picture [960 x 19] intentionally omitted <==
==> picture [960 x 22] intentionally omitted <==
2019 Priorities
Assets
-
Completion of Syama underground development
-
Commencement of open pit mining at Tabakoroni
-
Progress Ravenswood Expansion Project
-
Commence operational readiness at Bibiani
Financial
-
Reduce AISC to drive improved margins
-
Disciplined capital prioritisation and management
-
Generation of strong operating cash flows
-
Maintain balance sheet strength
Exploration
-
Accelerate Tabakoroni sulphide resource drilling
-
Upgrade Nafolo resource to indicated status
-
Seek small high grade deposits at Ravenswood
-
Commence exploration in Egypt and Sudan
Enhancement
-
Syama Underground expansion studies
-
Tabakoroni Underground Mine studies
-
Portfolio optimisation through M&A
-
Maintain and expand junior equity investments
==> picture [960 x 10] intentionally omitted <==
13
Invest in Resolute Transformation enables bold ambition
==> picture [109 x 104] intentionally omitted <==
Proven operator: Resolute has mined more than 8Moz from 9 gold mines in Australia and Africa
Long life, low cost, large scale assets: 14 year life at operating assets; clear pathway to 500kozpa; AISC of US$746/oz at Syama Large and growing resource base: 16.5Moz of Global Resources and 5.9Moz of Reserves Strong commitment to exploration: 8.4Moz Resources and 3.0Moz Reserves added since 2010 Focus on technology and innovation: Resolute is developing the world’s first custom built, fully automated sub-level cave Unique skill set and reputation in Africa: long term track record of successfully operating in the region Compelling valuation proposition: valuation upside from delivery of Syama development and ramp-up Building a portfolio of Resolute gold mines: strategic investments in 6 African-focused explorers
14
Portfolio Summary
Syama Gold Mine
Ravenswood Gold Mine
A world class, fully automated sub-level cave gold mine on track to be delivered by December 2018
Proven producing asset with multiple open pits which underpin long-term production
14 ear mine-life y
14 ear mine-life y
==> picture [196 x 104] intentionally omitted <==
----- Start of picture text -----
Global Total
7.9 Moz Resource 3.5 Moz Reserve
Life of Mine All-In Sustaining Cost Expected Site Production
US$746 /oz +300 kozpa
Site Processing Capacity
~4.0 Mtpa
----- End of picture text -----
==> picture [199 x 104] intentionally omitted <==
----- Start of picture text -----
4.7 Moz Total Resource 1.7 Moz Total Reserve
Life of Mine All-In Sustaining Cost Life of Mine Average Production
US$823 /oz ~115 kozpa
Process Capacity -Current Nameplate Capacity
2.8 Mtpa 5.0 Mtpa
----- End of picture text -----
==> picture [211 x 103] intentionally omitted <==
==> picture [215 x 103] intentionally omitted <==
==> picture [109 x 103] intentionally omitted <==
Strategic Investments
Bibiani Gold Mine
Recent feasibility study update completed which demonstrates potential for a long life, high margin project
Multiple strategic positions in highly prospective African explorers with significant land positions
==> picture [444 x 250] intentionally omitted <==
----- Start of picture text -----
~10 year target mine-life 17%
Total
2.5 Moz Resource 27%
Life of Mine All-In Sustaining Cost Proposed Annual Production
US$764 /oz ~100 kozpa
27%
Available Process Capacity Start-Up Capital
3 Mtpa US$75 Mtpa
23%
19%
10%
----- End of picture text -----
15
Note: Global Reserve and Resource estimates for Syama are inclusive of Tabakoroni and Northern Pits.
==> picture [960 x 19] intentionally omitted <==
==> picture [960 x 22] intentionally omitted <==
Syama Gold Mine
==> picture [960 x 10] intentionally omitted <==
16
Syama Gold Mine Sub-level caving from December 2018
==> picture [109 x 104] intentionally omitted <==
FY18 Summary Statistics
- Production : 194koz
DFS Update
LOM AISC reduced to US$746/oz (from US$881/oz)
-
Cash Cost: A$1,196/oz (US$928/oz)
-
AISC: A$1,286/oz (US$998/oz)
-
Average Price Achieved: A$1,699/oz (US$1,317/oz)
-
Underground Development: 8,257m
Reserves 3.5 Moz
Resources 7.9 Moz
UG Probable Reserve increased by 38% to 3.0Moz Mine life extended by 4 years from 2028 to 2032 Cost savings through automation, power upgrade Resource and reserve expansion expected Increased throughput may be achievable
17
Note: Reserves and Resources estimates for Syama are inclusive of Tabakoroni and Northern Pits.
==> picture [960 x 19] intentionally omitted <==
==> picture [960 x 22] intentionally omitted <==
Syama Underground
==> picture [960 x 10] intentionally omitted <==
18
Sub Level Cave Mining at Syama A world class sub-level cave gold mine in the making
==> picture [109 x 103] intentionally omitted <==
-
Controlled, high-productivity ore delivery
-
Full automation maximises operating efficiencies
-
Early access to ore without leaving a crown pillar below the open pit
-
A flexible method with ability to adapt cut-off grades depending on economic inputs
-
Low upfront capex
-
Strong partnership with Sandvik
19
==> picture [960 x 19] intentionally omitted <==
==> picture [960 x 22] intentionally omitted <==
Syama Underground DFS Update Overview
Improvements made to all aspects of Syama Redesign and rescheduling of mine plan 38% increase in UG Ore Reserves to 3.0Moz Mine life extended by 3 years to 2032 Introduction of autonomous mining Site power generation facilities improved Lower mining and processing costs LOM AISC reduced to US$746/oz Capital intensity reduced to US$177/oz (from US$186/oz)
==> picture [502 x 359] intentionally omitted <==
==> picture [960 x 10] intentionally omitted <==
20
==> picture [960 x 19] intentionally omitted <==
==> picture [960 x 22] intentionally omitted <==
Underground DFS Update (cont’d) Long Section: Current Plan relative to Original DFS
==> picture [508 x 363] intentionally omitted <==
A key element of the enlarged Reserve is the increased mining footprint
DFS Update provides for expanded production of ore from sub-level open stope mining of zones outside the sub-level cave limits
The revised design is substantially larger than its predecessor. In addition, draw point orientation and ore pass locations have been changed to reflect geotechnical advice
==> picture [960 x 10] intentionally omitted <==
Expanded Mining Envelope
21
==> picture [960 x 19] intentionally omitted <==
==> picture [960 x 22] intentionally omitted <==
Underground DFS Update (cont’d) Production Schedule: DFS Update v Original DFS
==> picture [925 x 167] intentionally omitted <==
----- Start of picture text -----
3
DFS Actual/DFS Update
3
2
2
1
1
FY19 FY20 FY21 FY22 FY23 FY24 FY25 FY26 FY27 FY28 FY29 FY30 FY31 FY32
Ore Tonnage (Mt)
----- End of picture text -----
Development and Stoping Tonnages
==> picture [927 x 156] intentionally omitted <==
----- Start of picture text -----
3
Development Stoping
3
2
2
1
1
FY19 FY20 FY21 FY22 FY23 FY24 FY25 FY26 FY27 FY28 FY29 FY30 FY31 FY32
Ore Tonnage (Mt)
----- End of picture text -----
==> picture [960 x 10] intentionally omitted <==
22
==> picture [960 x 19] intentionally omitted <==
==> picture [960 x 22] intentionally omitted <==
Automation in Mining and Resolute’s Partnership with Sandvik
==> picture [144 x 93] intentionally omitted <==
==> picture [144 x 96] intentionally omitted <==
==> picture [144 x 97] intentionally omitted <==
==> picture [960 x 10] intentionally omitted <==
23
==> picture [960 x 19] intentionally omitted <==
==> picture [960 x 22] intentionally omitted <==
Partnership with Sandvik
A formalised commerical relationship exists between Resolute and Sandvik for the full automation of the Syama Underground including the delivery of mobile and fixed equipment and delivery of training to maintenance and operational personnel
==> picture [381 x 113] intentionally omitted <==
==> picture [505 x 292] intentionally omitted <==
Sandvik is a leading global engineering group with headquarters in Sweden specialising in mining and rock excavation, metal-cutting and materials technology
==> picture [960 x 10] intentionally omitted <==
24
==> picture [960 x 19] intentionally omitted <==
==> picture [960 x 22] intentionally omitted <==
Automation at Syama
Increased machine productivity and performance
Reduction in number of machines required leading to capital and maintenance savings
Reduced risk and better safety outcomes including reduced emissions, noise, and vibration Reduction in required personnel underground
Lower production costs per tonne
Greater control of mining with less variation which results in less dilution Increased productivity and efficiency and optimised scheduling Greater machine life
Opportunity for mining rate increases without requirement for additional infrastructure
Ability to train the Syama workforce using new intuitive technologies
==> picture [960 x 10] intentionally omitted <==
25
==> picture [960 x 19] intentionally omitted <==
==> picture [960 x 22] intentionally omitted <==
Syama and AutoMine[®] Increased productivity and lower operating costs
==> picture [56 x 53] intentionally omitted <==
==> picture [56 x 52] intentionally omitted <==
==> picture [56 x 52] intentionally omitted <==
==> picture [56 x 52] intentionally omitted <==
Greater utilisation of equipment with 24/7 continuous production Longer operating hours = more tonnes = lower unit costs Production execution from remote locations = lower unit costs Less damage to equipment = less maintenance = increased utilisation of equipment
==> picture [564 x 346] intentionally omitted <==
==> picture [960 x 10] intentionally omitted <==
26
Note: illustrations for Automine Productivity Improvements sourced from Sandvik.
==> picture [960 x 19] intentionally omitted <==
==> picture [960 x 22] intentionally omitted <==
Processing
==> picture [960 x 10] intentionally omitted <==
27
==> picture [960 x 19] intentionally omitted <==
==> picture [960 x 22] intentionally omitted <==
Processing Overview
-
Series of processing upgrades with the objective of increasing the total sulphide gold recovery to a minimum of 85% completed
-
The process upgrades included:
-
Flotation Tails CIL: calcine CIL circuit has been repurposed to treat the flotation tails
-
New Calcine CIL: a new dedicated calcine CIL circuit has been installed and commissioned
-
Regrind: the coarse calcine product will now be reground prior to CIL
-
Upgrade of current flotation circuit: a series of minor upgrades are being completed to the current flotation circuit to improve the operational performance
==> picture [669 x 380] intentionally omitted <==
==> picture [960 x 10] intentionally omitted <==
28
==> picture [960 x 19] intentionally omitted <==
==> picture [960 x 22] intentionally omitted <==
Exploration
==> picture [960 x 10] intentionally omitted <==
29
==> picture [960 x 19] intentionally omitted <==
==> picture [960 x 22] intentionally omitted <==
Active, Multi-Rig Exploration Program Resolute controls 80km strike length of Syama greenstone belt
==> picture [960 x 10] intentionally omitted <==
30
==> picture [960 x 19] intentionally omitted <==
==> picture [960 x 22] intentionally omitted <==
Nafolo: A Major Gold Discovery at Syama
Extension potential for existing Syama underground
==> picture [641 x 366] intentionally omitted <==
-
Remains open in all directions
-
Untested to the south and at depth
-
All drillholes to date have intersected gold mineralisation
• Nafolo mineralisation can potentially be accessed from existing Syama Underground infrastructure and may form part of a future expanded mining operation
-
Updated inferred Nafolo Mineral Resource Estimate in Q1 FY19
-
Infill resource drilling to upgrade to indicated status Q4 FY19
==> picture [960 x 10] intentionally omitted <==
Syama and Nafolo resource model and drillhole locations
31
==> picture [960 x 19] intentionally omitted <==
==> picture [960 x 22] intentionally omitted <==
Tabakoroni: High Grade UG Mine Potential
Numerous wide high grade gold intersections
==> picture [668 x 363] intentionally omitted <==
-
Located 35km south of Syama
-
TARD621 returned 41m at 12.15g/t Au: displays the significant grades and widths seen in the main zone mineralisation
-
The current drilling program is ongoing with two diamond drill rigs in operation at Tabakoroni to fully define the new zones
-
An updated and expanded Mineral Resource Estimate for Tabakoroni, including a maiden underground mineral resource, will be available later in 2018
==> picture [960 x 10] intentionally omitted <==
32
==> picture [960 x 19] intentionally omitted <==
==> picture [960 x 22] intentionally omitted <==
Tabakoroni: Standalone UG Mine Potential
==> picture [669 x 376] intentionally omitted <==
----- Start of picture text -----
Coherent High Grade Zones
>50 gram metres
----- End of picture text -----
==> picture [245 x 329] intentionally omitted <==
==> picture [960 x 10] intentionally omitted <==
Visible gold in new Tabakoroni core samples
33
Syama Gold Mine A world class fully automated underground gold mine in the making
Mine Life Production AISC 14 Years +300kozpa US$746/oz
34
==> picture [960 x 19] intentionally omitted <==
==> picture [960 x 22] intentionally omitted <==
Ravenswood Gold Mine
==> picture [960 x 10] intentionally omitted <==
35
Ravenswood Gold Mine
==> picture [109 x 104] intentionally omitted <==
Multiple open pits underpin long-term production FY18 Summary Statistics
Project Study Update
- Production : 90koz
Significant enhancements to Ravenswood Expansion Project All required approvals received; Buck Reef West prioritised LOM AISC reduced to A$1,097/oz (US$823/oz) LOM average production of ~115kozpa of gold Mine life extended by three years to 2032
-
Cash Cost: A$1,330/oz (US$1,019/oz)
-
AISC: A$1,394/oz (US$1,071/oz)
-
Average Price Achieved: A$1,710/oz (US$1,321/oz)
Reserves Resources 1.7 Moz 4.7 Moz
Staged development plan; FY19 capex of only A$33 million Major expansion capital deferred through sequencing changes
Ravenswood confirmed as a long life, low risk, low cost project
36
==> picture [960 x 19] intentionally omitted <==
==> picture [960 x 22] intentionally omitted <==
Ravenswood Expansion Project: Study Update Overview
Summary Statistics
Physicals
Received all required government approvals
Optimised mining and processing schedule
Revised processing and tailings management strategy
New technologies incorporated to improve efficiency
1.5Moz of gold over 13 years; production of 115kozpa Mine life has been extended by three years to 2031
LOM AISC has reduced from A$1,097/oz (US$823/oz) LOM project capital of A$327 million
~A$100 million of major project capital deferred
Buck Reef West open pit accelerated
| Underground Mining | ||
|---|---|---|
| Ore Mined | kt | 540 |
| Ore Mined Gold Grade | g/t | 2.33 |
| Gold Contained (ROM) | koz | 40 |
Open Pit Mining |
||
| Ore Mined | kt | 65,637 |
| Waste Mined | kt | 100,783 |
| Total Movement | kt | 166,420 |
| Life of Mine Strip Ratio | Waste:Ore | 1.5 |
| Ore Mined Gold Grade | g/t | 0.78 |
| Gold Contained (ROM) | koz | 1,639 |
Processing |
||
| Ore Crushed | kt | 65,637 |
| Ore Milled | kt | 47,015 |
| Ore Milled Gold Grade | g/t | 1.12 |
| Gold Contained (ROM) | koz | 1,687 |
Processing Recovery |
% | 91% |
| Gold Recovered | koz | 1,529 |
| Mine Life (incl. pre-production) | years | 13 |
| Cost Analysis | ||
Costs |
A$m | A$/t milled |
| Mining (incl. underground) | 598 | 12.7 |
| Processing | 768 | 16.3 |
| G&A | 173 | 3.7 |
| Royalty | 124 | 2.6 |
| Sustaining capital | 30 | 0.6 |
Unit Costs |
A$m | A$/oz |
| All-In Sustaining Cost | 1,740 | 1,097 |
==> picture [960 x 10] intentionally omitted <==
37
==> picture [960 x 19] intentionally omitted <==
==> picture [960 x 22] intentionally omitted <==
Ravenswood Expansion Project: Study Update Proposed Sequencing Life of Mine Gold Production
Life of Mine Gold Production
==> picture [442 x 156] intentionally omitted <==
----- Start of picture text -----
160,000 2.00
Gold Produced Milled Grade
140,000
120,000 1.50
100,000
80,000 1.00
60,000
40,000 0.50
20,000
- -
2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032
Gold Produced (oz) Milled Grade (g/t Au)
----- End of picture text -----
Mining at Mt Wright to be extended to the end of FY19, with mining and processing of a further of 540kt of ore
Mining of Nolans East to be completed in September 2018, with processing of stockpiled ore supplemented by existing low-grade stocks to the end of 2019
Mining and processing of the Buck Reef West open pit from July 2019
Processing plant to be upgraded to 3.2Mtpa (currently 2.8Mtpa) by the start of 2020
Expansion of the Nolans processing plant to 5.0Mtpa in FY24
Mining and processing of ore from the Sarsfield open pit from FY25
Life of Mine Processed Tonnes
==> picture [442 x 156] intentionally omitted <==
----- Start of picture text -----
6,000
Mt Wright Nolans East/Low Grade Stocks Buck Reef West Sarsfield
5,000
4,000
3,000
2,000
1,000
-
2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032
Processing (ktpa)
----- End of picture text -----
==> picture [960 x 10] intentionally omitted <==
38
==> picture [960 x 19] intentionally omitted <==
==> picture [960 x 22] intentionally omitted <==
Sarsfield and Buck Reef West
Two large scale, bulk tonnage open pits
==> picture [409 x 350] intentionally omitted <==
----- Start of picture text -----
Buck Reef West
----- End of picture text -----
==> picture [430 x 350] intentionally omitted <==
----- Start of picture text -----
Sarsfield
----- End of picture text -----
==> picture [960 x 10] intentionally omitted <==
39
==> picture [960 x 19] intentionally omitted <==
==> picture [960 x 22] intentionally omitted <==
Bibiani Gold Mine
==> picture [960 x 10] intentionally omitted <==
40
==> picture [109 x 103] intentionally omitted <==
Bibiani Gold Mine Potential for a long life, high margin project with robust economics
Study Update
Environmental Permit Authorisation received Mineral Resource of 2.5Moz of gold (3.6 g/t Au) Potential for over a ~100kozpa 10 year mine life LOM AISC reduced to US$764/oz Start-up capital requirement of ~US$75m Operational readiness planning to commence during FY19 Final Investment Decision expected post Syama UG ramp-up Reserves Resources 0.6 Moz 2.5 Moz
| Summary Statistics | Summary Statistics | ||||
|---|---|---|---|---|---|
| Units | 2018 Study | 2016 Study | |||
| Underground development Ore development |
m | 23,883 | 9,841 | ||
| Waste development Vertical development |
m m |
10,234 1,548 |
16,389 1280 |
||
| Total development Ore production Development ore |
m kt |
34,117 878 |
27,510 609 |
||
| Stoping ore Total ore |
kt kt |
9,182 10,060 |
4,748 5,357 |
||
| Metal grade (ROM) Metal contained (ROM) |
g/t koz |
3.4 1,084 |
3.7 645 |
||
| Metal recovery Processing recovery |
% | 89.9 | 87 | ||
| Metal (recovered) Operating unit costs |
koz | 974 | 561 | ||
| Underground Mining (excl. pre-production) | US$/t | 31.3 | 34.6 | ||
| Processing | US$/t | 21.6 | 22.5 | ||
| General and Admin Royalty and refining costs |
US$/t US$/t |
9.0 6.8 |
11.2 7.2 |
||
| Costs Sustaining capital Operating cost AISC |
US$m US$/m US$/oz |
63 624 764 |
89.6 391.7 858 |
||
| Mine life (incl. pre-production) | years | 11.0 | 6.1 | ||
| 41 |
==> picture [960 x 19] intentionally omitted <==
==> picture [960 x 22] intentionally omitted <==
Bibiani Study Update Development Schedule
Recovery Schedule
==> picture [437 x 343] intentionally omitted <==
----- Start of picture text -----
1,200 4.5
1,000 3.75
800 3
600 2.25
400 1.5
200 0.75
0 0
1 2 3 4 5 6 7 8 9 10 11 12
Ore - development Ore - Stoping LHS Grade
Ore tonnes (kt) Grade (g/t)
----- End of picture text -----
==> picture [472 x 343] intentionally omitted <==
----- Start of picture text -----
160
140
120
100
80
60
40
20
0
1 2 3 4 5 6 7 8 9 10 11 12
Mined ounces Recovered ounces (Effective)
Ounces (koz)
----- End of picture text -----
==> picture [960 x 10] intentionally omitted <==
42
==> picture [960 x 19] intentionally omitted <==
==> picture [960 x 22] intentionally omitted <==
Strategic Investments
==> picture [141 x 134] intentionally omitted <==
==> picture [960 x 10] intentionally omitted <==
43
Strategic Investments Overview
Objective
Establish a portfolio of investments in emerging 27% stake 19% stake gold explorers to expand our project pipeline and provide a source of medium term potential growth opportunities 27% stake 17% stake Focus Equity investments in well managed African focused exploration teams holding promising tenure in highly prospective gold regions 23% stake 10% stake
Multiple potential opportunities for the development of future Resolute gold mines
44
==> picture [960 x 19] intentionally omitted <==
==> picture [960 x 22] intentionally omitted <==
Community, Safety and Environment
==> picture [141 x 134] intentionally omitted <==
==> picture [960 x 10] intentionally omitted <==
45
==> picture [960 x 19] intentionally omitted <==
==> picture [960 x 22] intentionally omitted <==
Community Highlights
Syama Workforce Stability Agreement signed with Syama Workers Union in Mali to secure industrial relations environment
Malian Talent Development Program enters second year at Syama to advance the skills, capabilities and careers of Malian employees
Tabakoroni Community Relations Management plan has been implemented ahead of proposed mine development
Partnership with University of Queensland for the development of conservation management plans for heritage sites in Ravenswood
Native Title Agreement with Birriah Aboriginal Corporation for the REP leases / tenements finalised
Resolute Foundation Advisory Panel at Bibiani implemented a number of community-driven education, health and income-generating initiatives
==> picture [397 x 390] intentionally omitted <==
==> picture [960 x 10] intentionally omitted <==
46
==> picture [960 x 19] intentionally omitted <==
==> picture [960 x 22] intentionally omitted <==
The Resolute Foundation
Mine Gold Create[(More) ] Value
-
The Resolute Foundation is the vehicle through which Resolute will deliver future community development initiatives
-
The Resolute Foundation will drive fiscal discipline, enable Resolute to leverage expertise and funding from partners and provide opportunities to increase the scale and reach of our programs and initiatives, delivering greater benefits and increasing value for the business, our local communities and host countries
-
We will take a considered and methodical approach as we grow the Resolute Foundation , focusing our effort where we believe we are most likely to make a difference and using the inherent strengths, skills and capacities of the company, our partners, our host governments and local people
==> picture [571 x 309] intentionally omitted <==
----- Start of picture text -----
TARGET THE MANAGE THE LEVERAGE
EFFORT SPEND CONTRIBUTIONS
SUPPORTS THE RESOLUTE
Resolute STRATEGY
Business CONTRACTORS
Drivers
SAFE & ETHICAL
PARTNERS
Community Global INFORMED &
Needs and Imperatives UNDERSTOOD DONATIONS
Aspirations (SDGs)
FULL COST
Host CAPTURE
THE
Government
Priorities BUILDS ON
STRENGTHS FOUNDATION
----- End of picture text -----
==> picture [960 x 10] intentionally omitted <==
47
==> picture [960 x 19] intentionally omitted <==
==> picture [960 x 22] intentionally omitted <==
R-CARE at Resolute Resolute’s approach to Safety
Committed:
-
to working safely, all of the time
-
to taking pride, in everything we do
-
to improving the way we work
Responsible:
-
to our families
-
to the way we treat others
-
for learning from our mistakes
==> picture [265 x 220] intentionally omitted <==
Accountable:
-
to the people we work with
-
for the quality of our work
-
to the expectation of our business
-
Empowered:
-
to speak up and share our ideas
-
to stop anything we believe is unsafe
-
to challenge the things we could do better
==> picture [960 x 10] intentionally omitted <==
48
==> picture [960 x 19] intentionally omitted <==
==> picture [960 x 22] intentionally omitted <==
Environment Update
Heritage Agreements signed for Ravenswood Expansion Project
Environmental Approval received the Buck Reef West
Graduate Environment Officer Program at Ravenswood
Environmental Permit Authorisation received to recommission Bibiani
New Syama power concept to utilise advanced technologies to deliver a more efficient, cost effective and environmentally friendly power solution
==> picture [321 x 350] intentionally omitted <==
==> picture [960 x 10] intentionally omitted <==
49
==> picture [960 x 356] intentionally omitted <==
Mine Gold. Create Value.
John Welborn Level 2, Australia Place 15-17 William St Managing Director & CEO Perth, Western Australia 6000 Jeremy Meynert General Manager – T: +61 8 9261 6100 Business Development & F: +61 8 9322 7597 Investor Relations E: [email protected]