Siviour Graphite Scoping Study Demonstrates Robust Economics

ASX RELEASE May 22, 2017

ASX: RNU

Renascor Resources Ltd ABN 90 135 531 341

HEAD OFFICE

36 North Terrace Kent Town, SA 5067 Australia

CONTACT

T: +61 8 8363 6989 F: +61 8 8363 4989 [email protected] www.renascor.com.au

ASX CODE RNU

Renascor Resources (ASX: RNU) is pleased to announce the results of a Scoping Study for a proposed open pit mine and graphite production plant at the Siviour Graphite Deposit in South Australia's Eyre Peninsula. The Scoping Study was prepared by independent mining consulting group BatteryLimits.

The project economics are encouraging and highlight Renascor's potential to become a long-term graphite producer in Australia.

Scoping Study Parameters – Cautionary Statements

The Scoping Study referred to in this announcement has been undertaken to determine the potential viability of an open pit mine and graphite production plant constructed adjacent to the Siviour Graphite Deposit and to reach a decision to proceed with more definitive feasibility studies.

This Scoping Study is a preliminary technical and economic study of the potential viability of the Siviour Graphite Deposit. It is based on low level technical and economic assessments that are not sufficient to support the estimation of ore reserves. Further evaluation work and appropriate studies are required before Renascor will be in a position to estimate any ore reserves or to provide any assurance of an economic development.

Renascor has chosen to base 100% of the total Life of Mine (LOM) production target on resources identified within the Indicated Resource category. The Scoping Study has not included any Inferred Resources in the LOM production target because there is a lower level of geological certainty associated with Inferred Resources.

This Scoping Study is based on the material assumptions outlined elsewhere in this announcement. These include assumptions about the availability of funding. While Renascor considers all of the material assumptions to be based on reasonable grounds, there is no certainty that they will prove to be correct or that the range of outcomes indicated by the Scoping Study will be achieved.

To achieve the range of outcomes indicated in the Scoping Study, additional funding will likely be required. Investors should note that there is no certainty that Renascor will be able to raise that amount of funding when needed. It is also possible that such funding may only be available on terms that may be dilutive to or otherwise affect the value of Renascor's existing shares. It is also possible that Renascor could pursue other 'value realisation' strategies such as a sale, partial sale or joint venture of the project. If it does, this could materially reduce Renascor's proportionate ownership of the project.

This announcement contains forward-looking statements. The Company has concluded it has a reasonable basis for providing the forward looking statements included in this announcement and believes it has reasonable basis to expect it will be able to fund development of the project. However, a number of factors could cause actual results, or expectations to differ materially from the results expressed or implied in the forward-looking statements.

Given the uncertainties involved, investors should not make any investment decisions based solely on the results of the Scoping Study.

Key Outcomes of Scoping Study

The Scoping Study considered multiple mine options based on a 20-year mine life in which the entire Life of Mine (LOM) graphite production target would be entirely included within the existing Indicated Resource of Siviour. Based on market requirements and potential capital raising capacity, an annual production rate of 123,000 tonnes per annum was selected as the most viable scenario.

The Scoping Study is based on producing flake graphite concentrates from a proposed open pit mine and graphite production plant to be located on the project site in South Australia. The potential to produce spherical graphite or other advanced materials through downstream processing is to be considered in further studies.

A summary of the key results of the Scoping Study is described below in Table 1. Additional information, including the material assumptions used in the study, are included elsewhere in this announcement.

Annual graphite concentrate production(tonnes per annum) 123,000
Plant throughput (tonnes per annum) 1,650,000
LOM average feed grade (TGC) 8.1%
NPV10 (after tax) AU$551m US$408m
IRR (after tax) 59%
Cash cost of production (per tonne ofconcentrate) AU$450 US$333
Capital cost (pre-production) AU$144m US$107m
Sustaining capital AU$28m US$21m
Basket sales price AU$1,420 US$1,051
Payback (after-tax) from first production 1.7 years

Table 1. Summary of key results from Scoping Study

Next Steps

Renascor considers the project economics of the Scoping Study to be highly encouraging and to support additional developmental programs and a more advanced feasibility study. Upcoming work programs are expected to include:

  • Further metallurgical tests designed to optimise the existing flow sheet parameters
  • Advanced materials tests to assess the potential to produce premium-priced products
  • The collection of a bulk sample and pilot plant preparation of concentrates
  • Offtake discussions with potential end-users
  • An advanced mining study to consider further efficiencies in mine scheduling
  • Hydrogeological testing
  • Continued compliance permitting and community engagement
  • Preparation of an advanced feasibility study

Overview of Scoping Study

BatteryLimits, an independent mining consulting group, acted as the Scoping Study manager and supervising engineer. In its capacity as study manager, BatteryLimits compiled the preliminary assumptions and conceptual financial models for the Scoping Study using information and assumptions provided by Renascor and a range of specialist consultants who have consented to the information used in the context in which it appears in this announcement.

Details of the consultants who contributed to key components of this Scoping Study are provided below in Table 2.

Consultant Scope of Work
(MAusIMM), Optiro Pty LtdChristine Standing Resource estimate
Simon Hall (MAusIMM) Metallurgical testwork
Ben Brown (MAusIMM), Optima Consulting andContracting Pty Ltd Mining study
Dave Pass (MAusIMM), BatteryLimits Pty Ltd Process plant and infrastructure
Ben Jeuken (MAusIMM), Ground WaterScience Pty Ltd Hydrogeology
Evelyn G Poole (AAusIMM), Evelyn G Poole &Associates Environmental and social permitting
Andrew Reeves and George Wilby Logistics

Table 2. Consultants contributing to Scoping Study

Key Components of Scoping Study

1. Location and ownership

The Siviour Graphite Deposit is part of Renascor's Arno Graphite Project. The project is located in South Australia's Eyre Peninsula, approximately 15km west of the coastal township Arno Bay, 120km northeast of Port Lincoln and 150km southwest of Whyalla. See Figure 1.

Figure 1. Project location

The project area consists of four granted exploration licences, covering an area of approximately 1,370 km2 .

Renascor has the right to acquire the project through an option agreement between Renascor's wholly-owned subsidiary Eyre Peninsula Minerals Pty Ltd (EPM) and Ausmin Development Pty Ltd (Ausmin). EPM's option to acquire the project entitles EPM to 100% of Ausmin in exchange for a 22% equity interest in a listed vehicle holding the project and a 1% gross royalty. The option is exercisable upon completing a feasibility study in relation to the commercial development of graphite within the project area.

2. Mineral Resources

The Scoping Study utilises Renascor's JORC Mineral Resource Estimate for Siviour as announced on 17 March 2017. See Table 3.

Category Tonnes ofmineralisation (millions) TGC Tonnes of containedgraphite (millions)
Indicated 51.8 8.1% 4.2
Inferred 28.8 7.6% 2.2
Total 80.6 7.9% 6.4

Note: Cut-off grade of 3% total graphitic carbon

Table 3. Siviour Mineral Resource estimate as of 15 March 2017

For the purpose of the Scoping Study, one hundred percent (100%) of the total life of mine (LOM) production target is included within the Indicated Resources of Siviour.

3. Mining and Mine Design

The mining schedule and physicals were developed based on an approximately twenty-year mine life. Mining is based on Indicated Resources only.

The Scoping Study considered multiple mining methods, including conventional open pit mining, mobile in-put crush and convey (IPCC), continuous surface-mining with in-pit loading and conveying and highwall mining after conventional open pit mining. Waste rock disposal systems considered included conventional waste rock storage on waste rock dumps outside the pit area, inpit (e.g., strip mining or cell mining where overburden is placed back in the previous mining zone), dry-stack tailings with waste rock dumps and dry-stack tailings with in-pit disposal.

For the purpose of the Scoping Study, conventional mining, using drill and blast, load and haul and crusher feed and in-pit wet disposal were adopted. Further studies into alternative mining and disposal methods will be considered in future studies.

4. Metallurgical Testwork

Metallurgical testwork has been undertaken at ALS Metallurgy (Adelaide) and Bureau Veritas Minerals (Adelaide) on three composite samples obtained from core samples from 16 diamond holes drilled within areas of the Siviour mineralised body. Core samples were selected on the basis of being representative of the typical mineralised zone within each core hole. Examination of these samples has demonstrated continuity of the quality of the graphite.

The flake size distribution from the test work to date is summarised in Table 4. These results were achieved at a weighted average graphite concentrate grade of 94% TCG and a recovery rate of 85%.

Particle size
Flake category Microns (μm) Mesh (#) Distribution
Jumbo >300 +48 8%
Large 180 to 300 -48 to +80 25%
Medium 150 to 180 -80 to +100 15%
Small 75 to 150 -100 to +200 39%
Fine <75 -200 13%

Table 4. Summary of Siviour concentrate size distribution

Additional test work has demonstrated the ability to achieve higher purity levels, including grades of over 99% TCG with an additional regrind and flotation circuit.

5. Process Plant Design

The process plant is designed to recover graphite concentrate by froth flotation. Ore from the mine will be primary, secondary and tertiary stage-crushed, followed by grinding, flotation, filtering, sizing and drying, before being bagged and containerised for shipment

The results presented are based on an annual process plant treatment of 1.65mtpa. The proposed processing plant incorporates the following unit process operations:

  • Run of mine (ROM) ore will be stage crushed in primary, secondary and tertiary crushers
  • Ore will be wet ground by primary rod mill for concentration by flotation
  • Graphite concentrate will be recovered by desliming followed by flotation roughing and cleaning stages with re-grind targeting coarse graphite recovery
  • Graphite concentrate will be dried, sized and bagged
  • Flotation tailings will be thickened to enhance water recovery and discharged in-pit.

A simplified flow sheet is shown in Figure 2.

Figure 2. Process flow sheet

6. Infrastructure and Logistics

Process plant and infrastructure

The process plant and infrastructure will include:

  • Raw water and process water dams
  • Water supply bores and desalination facility
  • Access roads within the plant and the project site
  • Process plant, including complementary equipment and office facilities.

Electricity

Electricity is expected to be supplied from an existing 11-33kV transmission line that supplies power to customers between Cleve and Arno Bay. The transmission line, which is owned and operated by SA Power Networks (SAPN), is approximately 14km to the north of Siviour.

Water supply and management

The Scoping Study is based on supplying the plant with ground water from local bore holes. It is expected that water will be desalinated on site by reverse osmosis and blended for plant treatment purposes, with waste brine re-injected to an aquifer and tails returned to the pit. Upcoming work programs are expected to include hydrogeological testing and will include comprehensive studies into optimal brine and tailings disposal.

Transport

Concentrates will be bagged and containerised for road from the project site to Port Adelaide. It is proposed that concentrates will be packed, bagged and loaded at the plant. The transport route from the project site to Port Adelaide is generally approved for use by restricted access vehicles, such as road trains, with the exception of approximately 5km of road covering the distance from the project site and an arterial road that connects to the Port Lincoln Highway.

Workforce

It is expected that Renasor will employ the majority of personnel from local communities within the vicinity of the project site, with personnel not based in the district having access to air service from Adelaide to either Port Lincoln or Whyalla. Housing will not be provided on site, with personnel needing accommodation having access to rental units in Arno Bay and other nearby townships. Significant medical requirements are expected to be sourced from Cleve, Tumby Bay, Port Lincoln or Whyalla hospitals, with first aid services to be maintained on site.

6. Environmental and Social Permitting Requirements

Renascor has initiated studies as part of the compliance and permitting process to establish baseline characteristics, including studies relating to climate, hyrdogeology, pedology, ecology, relief and drainage, air, water and noise quality and social conditions, including economic activities, infrastructure and services. Preliminary studies have not indicated material impediments to the proposed development of Siviour.

As part of the subsequent permitting process, Renascor will need to undertake a comprehensive environmental and social impact assessment. It is anticipated that these assessments will support an application for a Mining Lease (ML) under Section 35 of South Australia's Mining Act 197. Approval of a Program of Environmental Protection and Rehabilitation (PEPR) will be needed to enable operations to commence.

7. Product Pricing

A basket price of $1,051/t has been calculated based on discussions with potential end-users and market professionals, as well as investigations into prices adopted by peer companies. See Table 5.

Particle size Pricing – FOB
Flake category Microns (μm) Mesh (#) Distribution (US$)
Jumbo >300 +48 8% 2,100/t
Large 180 to 300 -48 to +80 25% 1,450/t
Medium 150 to 180 -80 to +100 15% 1,150/t
Small 75 to 150 -100 to +200 39% 750/t
Fine <75 -200 13% 425/t
Basket price US$1,051/t
Table 5. Graphite pricing assumptions for basket price
-- -- -- -------------------------------------------------------- -- -- --

8. Capital Costs

Estimated pre-production capital costs are provided below in Table 6.

Process Plant AU$87.9m US$65.0m
Site Infrastructure AU$16.7m US$12.4m
EPCM AU$15.3m US$11.3m
Contingency AU$5.1m US$3.8m
Owners' costs AU$15.7m US$11.6m
Other AU$3.1m US$2.3m
Total AU$143.9m US$106.5m

Table 6. Pre-production capital cost estimate summary

9. Operating Costs

Estimated annual cash operating costs are provided below in Table 7.

Area AU$/year AU$/ tonne ofconcentrate US$/year US$/ tonne ofconcentrate
Mining and technicalservices 14.4m 117 10.7m 87
Processing and power 27.9 m 224 20.6m 166
General andadministration 2.4m 19 1.8m 14
Product logistics FOB 11.1m 90 8.2m 67
Total AU$55.8 AU$450 US$41.3m US$333

Table 7. Operating cost estimate summary

10. Financial Evaluation

Key financial results

A summary of the key results of the Scoping Study is described below in Table 8.

Annual graphite concentrate production(tonnes per annum) 123,000
Process plant throughput (tonnes perannum) 1,650,000
LOM average feed grade (TGC) 8.1%
Strip ratio 1.5
NPV10 (after tax) AU$551m US$408m
IRR (after tax) 59%
Cash cost of production (per tonne ofconcentrate) AU$450 US$333
Capital cost (pre-production) AU$144m US$107
Sustaining capital AU$28m US$21
Basket sales price AU$1,420 US$1,051
Payback (after-tax) from first production 1.7 years

Table 8. Summary of key results from Scoping Study

Financial sensitivities

The sensitivity of the net present value (10% discount rate, after-tax) as expressed in Australian Dollars to changes in product price, the Australian-US exchange rate, grade, operating expenditure and capital expenditure is set out below is Table 9.

-10% unfavourable +10% favourable
Variable AU$m US$m AU$m US$m
Capital Expenditure 537 397 564 417
Operating Expenditure 514 380 587 434
Grade 459 340 642 475
Exchange Rate 458 339 663 491
Price 449 332 652 482

Table 9. NPV sensitivity

11. Preliminary Schedule

The project development schedule is based on completing feasibility studies in the second half of 2018 and completing construction in the first half of 2020. Subject to obtaining funding and relevant project approvals, the Scoping Study contemplates the commencement of production in 2020. See Table 10.

Table 10. Project implementation schedule

Bibliography

    1. Renascor ASX announcement dated 17 March 2017, "Siviour Now Among Ten Largest Graphite Deposits in the World"
    1. Renascor ASX announcement dated 31 March 2017, "High Purity Coarse Flake Graphite from Metallurgical Tests"
    1. Renascor ASX announcement dated 10 November 2016, "99% TGC Product from Simple Flotation at Siviour"
    1. Renascor ASX announcement dated 1 September 2016, "Acquisition of 100% of Eyre Peninsula Minerals"

Renascor confirms that it is not aware of any new information or data that materially affects the information included in the original market announcements and that all material assumptions and technical parameters underpinning the estimates in the relevant market announcement continue to apply and have not materially changed. Renascor confirms that the form and context in which the Competent Person's findings are presented have not been materially modified from the original market announcement.

Competent Person Statements

Mineral Resource

The information in this document that relates to Mineral Resources is based upon information compiled by Mrs Christine Standing who is a Member of the Australasian Institute of Mining and a Member of the Australian Institute of Geoscientists. Mrs Standing is an employee of Optiro Pty Ltd and has sufficient experience relevant to the style of mineralisation, the type of deposit under consideration and to the activity undertaken to qualify as a Competent Person as defined in the 2012 edition of the Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves. Mrs Standing consents to the inclusion in the report of a summary based upon her information in the form and context in which it appears.

Exploration Results

The information in this document that relates to exploration activities and exploration results is based on information compiled and reviewed by Mr G.W. McConachy who is a Fellow of the Australasian Institute of Mining and Metallurgy. Mr McConachy is a director of the Company. Mr McConachy has sufficient experience relevant to the style of mineralisation and type of deposits being considered to qualify as a Competent Person as defined by the 2012 Edition of the Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves (the JORC Code, 2012 Edition). Mr McConachy consents to the inclusion in the report of the matters based on the reviewed information in the form and context in which it appears.

Mining Study

The information in this document that relates to mine design and mine plan scheduling is based on information complied and reviewed by Mr Ben Brown, who is a Member of the Australasian Institute of Mining and Metallurgy. Mr Brown is an employee of Optima Consulting and Contracting Pty Ltd and a consultant to the Company. Mr Brown has sufficient experience relevant to the type of deposit under consideration to qualify as a Competent Person as defined by the 2012 Edition of the Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves (the JORC Code, 2012 Edition). Mr Brown consents to the inclusion in the report of the matters based on the reviewed information in the form and context in which it appears.

Metallurgical Results

The information in this document that relates to metallurgical test work results is based on information compiled and reviewed by Mr Simon Hall, who is a Member of the Australasian Institute of Mining and Metallurgy. Mr Hall is a consultant to the Company. Mr Hall has sufficient experience relevant to the mineralogy and type of deposit under consideration and the typical beneficiation thereof to qualify as a Competent Person as defined by the 2012 Edition of the Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves (the JORC Code, 2012 Edition). Mr Hall consents to the inclusion in the report of the matters based on the reviewed information in the form and context in which it appears.

Scoping Study

The information in this document that relates to the process plant and infrastructure design for a Scoping Study level assessment is based on information compiled and reviewed by Mr David Pass, who is a Member of the Australasian Institute of Mining and Metallurgy. Mr Pass is an employee of BatteryLimits. Mr Pass has sufficient experience relevant to process plant and infrastructure design thereof to qualify as a Competent Person as defined by the 2012 Edition of the Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves (the JORC Code, 2012 Edition). Mr Pass consents to the inclusion in the report of the matters based on the reviewed information in the form and context in which it appears.

This report may contain forward-looking statements. Any forward-looking statements reflect management's current beliefs based on information currently available to management and are based on what management believes to be reasonable assumptions. It should be noted that a number of factors could cause actual results, or expectations to differ materially from the results expressed or implied in the forward-looking statements.

FOR FURTHER INFORMATION, PLEASE CONTACT:

David Christensen Managing Director +61 8 8363 6989 [email protected] Angelo Gaudio Company Secretary

Material Assumptions

Material assumptions used in the estimation of the production targets and associated financial information are set out in the following table.

Criteria Commentary
Study Status The production target and financial information in thisrelease are based on a Scoping Study. The ScopingStudy referred to in this announcement is based on lowleveltechnicalandeconomicassessmentsandisinsufficient to support the estimation of Ore Reserves orto provide assurance of an economic development caseat this stage or to provide certainty that the conclusions ofthe Scoping Study will be realised.
Mineral resource estimateunderpinning the productiontarget The Mineral Resource estimate declared in March 2017(see Renascor ASX release dated 17 March 2017)underpins the production target.This estimate wasprepared by a Competent Person in accordance withJORC Code 2012 (the JORC Code).The JORC Code(Clause 49) requires that industrial minerals must bereported "in terms of the mineral or minerals on which theproject is to be based and must include the specificationof those minerals" and that "it may be necessary, prior tothe reporting of a Mineral Resource or Ore Reserve, totake particular account of certain key characteristics orqualities such as likely product specifications, proximity tomarketsandgeneralproductmarketability."Thelikelihoodofeventualeconomicextractionwasconsidered in terms of possible open pit mining, likelyproduct specifications, possible product marketability andpotentially favourable logistics to port.
Mining factors or assumptions Mining is based on an open cut operation utilisingconventional drill and blast, load and haul and crusherfeed, with mining to be undertaken by experienced miningcontractors. It is expected that wet or paste tailing wouldbe disposed in-pit.
Metallurgical factors orassumptions Metallurgical parameters are based on test work on threecomposite samples which achieved average purity of94% TGC and recovery of 87% TGC.For purposes ofthe Scoping Study, a process flowsheet has beenadopted which is similar to flowsheets that have beenadopted by similar flake graphite operations.Furthertestwork is currently underway and will include furtheroptimisation work, variability testing, salinity testing andthe generation of a bulk sample.
Infrastructureand logistics The infrastructure required to support the plant and mineis based on raw water and process dams, water supplybores and a reverse osmosis facility, access roads within

ASX: RNU

the plant and project site and the process plant, togetherwith complementary equipment and facilities.Power isbased on accessing on-grid power from South AustraliaPower Network (SAPN) and subsequently negotiating acontract tariff with electricity providers.Renascor hascommenced discussions with SAPN to access its existingline located approximately 14km north of the project area.Water is expected to be supplied from local boreholesand provision is made for desalination on site by reverseosmosis. Waste brine would be re-injected to an aquiferand tails returned to the pit. Transport is based on roadhaulage from the project site to Port Adelaide.
Capital costs Thecapitalcostestimatehasbeencompiledby
BatteryLimits based on a high level preliminary processdesign, for the design, supply, fabrication, constructionand commissioning of the process plant facility. Theprocess design criteria and high-level process flowsheetunderliethebasisofthisestimate.Theestimateincorporates direct costs and indirect costs and containsestimates for project infrastructure. The estimate hasbeen prepared as a factored estimate based uponsupplied cost of equipment from current in-house datafrom recent projects and industry standard estimatingfactors, and excludes working capital, financing costs,relocationandresettlementcosts,rehabilitationandclosure costs.A project contingency allowance of 15%has been applied to the estimate.EPCM refers toengineering, procurement and construction managementcosts and is applied at a rate of 12.5% - 15% of directcosts.Owners Costs is estimated on comparableprojects and includes allocations forpre-production labourand G&A, commissioning, first fills and opening stocks,landacquisitioncostestimateandmiscellaneoussoftware and equipment. The capital cost estimates werecompiled in AU$ with a base date of Q4 2016 with noallowance for escalation to an accuracy of +/-35%.
Operating costs The operating cost estimate for the project includes all
costs associated with mining, processing, infrastructure,and site-based general and administration costs.Theoperating cost estimate is presented on an annualisedbasis and there has been no allowance for initial ramp-upperiods or contingencies applied. The operating costshave been developed in AU$ by BatteryLimits based oncost database, industry standards from similar operations,first principle estimates based on typical operating dataand information by Optima Consulting (mining costs) andRenasor (labour force estimates and logistics).Theoperatingcostestimatesexcludeexchangeratevariations, price escalation and interest charges.
Revenue factors Revenue from the project is derived from the sale of
graphite concentrates.Renascor has established the

characteristics of expected final products through testprograms undertaken on composite samples from Siviourcore.Renascorhasreceivedmarketfeedbackthatgraphite concentrates produced to a minimum purity ofapproximately 94% TGC will be attractive to potentialcustomers at premium or near premium pricing levels(provided the concentrates do not otherwise contain anypotentiallydisqualifyingcontaminants).Accordingly,Renascor designed its metallurgical test work to meet thisminimumpuritythreshold.Renascorhasreceivedadditionalmarketfeedbackregardingthepotentialbenefits of increasing purity levels to make its graphiteconcentrates more attractive to potential customers.Renascor's continuing metallurgical work will includeinvestigations designed to further increase the purity ofRenascor'sconcentrates,whilemaintainingothervariables (e.g. flake size, recoveries and capital andoperating costs) at optimal levels.Product prices are based on discussions with end-usersand market professionals and examination of otherstudies.Risks associated these assumptions used in productpricing include that the product split is notachieved andthat the price assumptions are not met by the prevailinggraphite market.
Schedule and timeframe Theprojectdevelopmentscheduleisbasedoncompletingapre-feasibilitystudy,transitioningto adefinitive feasibility study without material modificationandhavingfundingreadilyinplacetocommenceconstruction in Q4 2018. The schedule assumes a likelyEPC implementation strategy. This results in a timeline of20 months from funding approval to operation.Thescheduleassumesthatpermittingprogressesconcurrently with the schedule.
Market assessment The majority of current world demand for graphite (>80%)isdrivenbyindustrialapplications(steelmaking,refractories and lubricants) that are growing at around 3%per annum.Within the industrial sector, lithium ionbatteries represent a potential high growth area due tothe impact of electric vehicles and grid power storage.Other new applications comprising expandable graphite(flame retardant materials, graphite foil, graphite paper,knitted tape), and specialist applications (micronisedgraphite, and graphene) are leading to an increase indemand.
Funding To achieve the range of outcomes indicated in theScoping Study, funding of up to AU$167 or US$125m willlikelyberequiredforcapitalworks,pre-productionoperating costs and contingency. It is anticipated that thefinance will be sourced through a combination of equityand debt instruments from existing shareholders, new

ASX: RNU

equity investment and debt providers from Australia and
overseas.
The Company has sufficient cash on hand at the date of
this announcement to undertake the next stage of
planned work programs, including continued metallurgical
testing,thecollectionofabulksample,andthecommencementofadvancedmining,geotechnical,
hyrdro-geological and other technical studies.
Renascor's Board believes that there is a reasonable
basis to assume that funding will be available to complete
all feasibility studies and finance the pre-production
activities necessary to commence production on thefollowing basis:
•Renascor's Board and executive team have a
strongfinancingtrackrecordindeveloping
resources projects;
•The Company has a proven ability to attract new
capital;
•Renascor's Board believes this Scoping Study
demonstrates the project's strong potential to
deliver favourable economic return; and•
Othercompaniesatasimilarstageindevelopment have been able to raise similar
amounts of capital in recent capital raisings.
Economic A discount rate of 10% has been used for financial
modeling. This number was selected as a generic cost of
capital and considered a prudent and suitable discount
rate for project funding and economic forecasts. The
model has been run as a life of mine model and includessustaining capital and closure costs. The Study outcome
was tested for key financial inputs including: basket price,
capital and operating costs and US/AU exchange rate.
All of these inputs were tested for variations of+/- 10%.
Exchange rate The exchange rate used is of AU$1.00 = US$0.74.
Social The local community includes the townships of Arno Bay,
Cleve, Port Neill and Cowell.Renasor has commencedmeetings with stakeholders within these communities,
and the general acceptance of the project has been
favourable. There are no known community issues that
Renascorhasidentifiedasbeingalikelymaterial
impediment to developing the project.
Other There are several other material risks to this project
including product price, competition, regulatory approval,social licence, scheduling and other risks typical of
projects of similar scale.
Audits or reviews The Scoping Study was internally reviewed by Renascor
andthefollowingconsultants:BenBrown(Optima
Consulting), in relation to the mining component, Simon
Hall, in relation to the metallurgical component, Ben
Jeuken,(GroundwaterScience)inrelationtothe

hydrogeological component, Evelyn Poole, in relation to
the environmental component, and Andrew Reeves and
George Wilby, in relation to logistics. No material issues
were identified by the reviewers. All study inputs were
preparedbyCompetentPersonsidentifiedinthis
announcement.