REGIS RESOURCES LIMITED — Interim / Quarterly Report 2016
Jan 13, 2016
65733_rns_2016-01-13_918cab46-9bbc-4f2f-b97f-bd86dc1b2f00.pdf
Interim / Quarterly Report
Open in viewerOpens in your device viewer
==> picture [17 x 22] intentionally omitted <==
----- Start of picture text -----
11
----- End of picture text -----
REGIS RESOURCES LTD
==> picture [128 x 108] intentionally omitted <==
DECEMBER 2015 QUARTERLY REPORT & EXPLORATION UPDATE
22
DISCLAIMER & COMPETENT PERSONS STATEMENT
This presentation contains only a brief overview of Regis Resources Limited and its associated entities (“Regis or RRL") and their respective activities and operations. The contents of this presentation, including matters relating to the geology of Regis’ projects, may rely on various assumptions and subjective interpretations which it is not possible to detail in this presentation and which have not been subject to any independent verification.
This presentation contains a number of forward-looking statements. Known and unknown risks and uncertainties, and factors outside of Regis’ control, may cause the actual results, performance and achievements of Regis to differ materially from those expressed or implied in this presentation. To the maximum extent permitted by law, Regis does not warrant the accuracy, currency or completeness of the information in this presentation, nor the future performance of Regis, and will not be responsible for any loss or damage arising from the use of the information. The information contained in this presentation is not a substitute for detailed investigation or analysis of any particular issue. Current and potential investors and shareholders should seek independent advice before making any investment decision in regard to Regis or its activities.
The information in this presentation that relates to Exploration Results and the updated Baneygo Resource is extracted from the ASX announcement released 14 January 2016 entitled “Exploration Update & Baneygo Resource ” and for which Competent Person’s consents were obtained. The Competent Person’s consents remain in place for subsequent releases by the Company of the same information in the same form and context, until the consent is withdrawn or replaced by a subsequent report and accompanying consent.
The information in this presentation that relates to Mineral Resources or Ore Reserves is extracted from the Mineral Resource and Ore Reserve Statement released to the Australian Securities Exchange (ASX) on 16 July 2015 and for which Competent Person’s consents were obtained. The Competent Person’s consents remain in place for subsequent releases by the Company of the same information in the same form and context, until the consent is withdrawn or replaced by a subsequent report and accompanying consent.
The Company confirms that it is not aware of any new information or data that materially affects the information included in the original ASX announcements released on 16 July 2015 and 14 January 2016 and, in the case of estimates or Mineral Resources or Ore Reserves, that all material assumptions and technical parameters underpinning the estimates in the original ASX announcements continue to apply and have not materially changed. The Company confirms that the form and context in which the Competent Person’s findings are presented have not been materially modified from the original ASX announcement.
ASX announcements are available on the Company’s website at www.regisresources.com.au
==> picture [720 x 48] intentionally omitted <==
33
REVIEW OF FY2016 Q2 OPERATIONS
PRODUCTION AT UPPER END OF GUIDANCE & DELIVERING STRONG CASHFLOW
| Q2 | Q1 | OPERATIONS | |
|---|---|---|---|
| Ore mined (Mbcm) | 1.13 | 1.27 | Q2 production 75,544 ounces |
| Run rate at upper end of FY2016 guidance of 275-305koz | |||
| Waste mined (Mbcm) | 5.21 | 5.85 | Q2 throughput consistent with Q1 & ≈ 10.3mtpa |
| Stripping ratio (w:o) | 4.61 | 4.62 | Q2 recovery 91%,↑3% - GW optimizing & more oxide Q2 grade 1.00g/t - in line with Q1 |
| Ore mined (Mtonnes) | 2.62 | 3.00 | Q2 Duketon strip ratio in line with Q1 |
| Ore milled (Mtonnes) | 2.58 | 2.56 | GW continues to decrease to LOM average Q2 reconciliation to reserve positive for Duketon |
| Head grade (g/t) | 1.00 | 1.04 | GW continuing to improve and Dec15 in line COSTS |
| Recovery (%) | 91 | 88 | Q2 cash costs $789/oz –↓4% (Q1: $821/oz) |
| Gold production (ounces ‘000) |
76 | 75 | Unit costs consistent RMT cutback excluded |
| Cash cost (A$/oz) | 789 | 821 | Q2 AISC $918/oz -↓6% (Q1: $973/oz) Below lower end of FY2016 guidance of $970 - |
| Cash cost inc royalty (A$/oz) All in Sustaining Cost (A$/oz)1 |
861 918 |
888 973 |
$1,070/oz Q2 operating cashflow $49.8m (Q1: $50.8m) OPERATING CASH-FLOW |
1 AISC calculated on a per ounce of production basis
==> picture [57 x 48] intentionally omitted <==
44 FY2016 Q2 OPERATING RESULTS
| Moolart Well Rosemont Garden Well Total Ore mined (bcm ) 336,847 298,844 496,224 1,131,915 Waste mined (bcm) 1,273,692 2,403,341 1,536,669 5,213,702 Stripping ratio (w:o) 3.8 8.0 3.1 4.6 Ore mined (tonnes) 691,834 694,357 1,236,819 2,623,011 Ore milled (tonnes) 726,088 608,178 1,248,141 2,582,406 Head grade (g/t) 0.90 1.36 0.89 1.00 Recovery (%) 91.5 92.9 89.0 90.9 Gold production (ounces) 19,208 24,622 31,714 75,544 Cash cost (A$/oz) 805 629 903 789 Cash cost inc royalty (A$/oz) 878 705 971 861 All in Sustaining Cost (A$/oz) 991 778 983 918 |
||
==> picture [720 x 48] intentionally omitted <==
55
FY2016 Q2 OPERATING RESULTS
| Moolart Well |
Rosemont Garden Well Total |
|
|---|---|---|
| Ore mined (bcm ) | 336,847 | 298,844 496,224 1,131,915 |
| Waste mined (bcm) | 1,273,692 | 2,403,341 1,536,669 5,213,702 |
| Stripping ratio (w:o) | 3.8 | 8.0 3.1 4.6 |
| Ore mined (tonnes) | 691,834 | 694,357 1,236,819 2,623,011 |
| Ore milled (tonnes) | 726,088 | 608,178 1,248,141 2,582,406 |
| Head grade (g/t) | 0.90 | 1.36 0.89 1.00 |
| Recovery (%) | 91.5 | 92.9 89.0 90.9 |
| Gold production (ounces) | 19,208 | 24,622 31,714 75,544 |
| Cash cost (A$/oz) | 805 | 629 903 789 |
| Cash cost inc royalty (A$/oz) | 878 | 705 971 861 |
| All in Sustaining Cost (A$/oz) |
991 | 778 983 918 |
MOOLART WELL
Production run rate in line with mid point of FY2016 guidance range
Strip ratio slightly higher than guidance due to commencement of prestrip at Wellington pit
All in sustaining cost $991/oz in line with guidance.
==> picture [720 x 48] intentionally omitted <==
66
MOOLART WELL
==> picture [720 x 455] intentionally omitted <==
77
FY2016 Q2 OPERATING RESULTS
| Moolart Well |
Rosemont | Garden Well Total |
|---|---|---|
| Ore mined (bcm ) 336,847 |
298,844 | 496,224 1,131,915 |
| Waste mined (bcm) 1,273,692 |
2,403,341 | 1,536,669 5,213,702 |
| Stripping ratio (w:o) 3.8 |
8.0 | 3.1 4.6 |
| Ore mined (tonnes) 691,834 |
694,357 | 1,236,819 2,623,011 |
| Ore milled (tonnes) 726,088 |
608,178 | 1,248,141 2,582,406 |
| Head grade (g/t) 0.90 |
1.36 | 0.89 1.00 |
| Recovery (%) 91.5 |
92.9 | 89.0 90.9 |
| Gold production (ounces) 19,208 |
24,622 | 31,714 75,544 |
| Cash cost (A$/oz) 805 |
629 | 903 789 |
| Cash cost inc royalty (A$/oz) 878 |
705 | 971 861 |
| All in Sustaining Cost (A$/oz) 991 |
778 | 983 918 |
ROSEMONT
-
Strip ratio lower than forecast – will commence catch up in Q3
-
Higher grade reflects positive reconciliation to reserve grade
-
Recovery in line with guidance
-
Throughput for quarter equates to annualised rate of 2.43Mtpa – top end of FY2016 guidance range
-
Production run rate above top of guidance range and AISC below bottom of guidance range
-
Cutback cost of $4.9m treated as expansionary capex (non AISC) as per FY2016 guidance
==> picture [720 x 48] intentionally omitted <==
88
ROSEMONT
==> picture [720 x 459] intentionally omitted <==
99
FY2016 Q2 OPERATING RESULTS
| Moolart Well Rosemont |
Garden Well |
Total | |
| Ore mined (bcm ) 336,847 298,844 |
496,224 | 1,131,915 | |
| Waste mined (bcm) 1,273,692 2,403,341 |
1,536,669 | 5,213,702 | |
| Stripping ratio (w:o) 3.8 8.0 |
3.1 | 4.6 | |
| Ore mined (tonnes) 691,834 694,357 |
1,236,819 | 2,623,011 | |
| Ore milled (tonnes) 726,088 608,178 |
1,248,141 | 2,582,406 | |
| Head grade (g/t) 0.90 1.36 |
0.89 | 1.00 | |
| Recovery (%) 91.5 92.9 |
89.0 | 90.9 | |
| Gold production (ounces) 19,208 24,622 |
31,714 | 75,544 | |
| Cash cost (A$/oz) 805 629 |
903 | 789 | |
| Cash cost inc royalty (A$/oz) 878 705 |
971 | 861 | |
| All in Sustaining Cost (A$/oz) 991 778 |
983 | 918 | |
| Strip ratio reduced from 3.2 (Q1) to 3.1 and down sharply from 5.85 (Q4 2015) Grade at 0.89g/t in line with reserve for areas mined in the quarter Mining reconciliation continues improving and in line with reserve for Dec15 Incremental improvements in throughput and recovery as plant optimisation continues Production 31,714oz at a run rate of 127kozpa in line with guidance mid-point Cash cost $903/oz and AISC $983/oz consistent with Q1 and in line with guidance GARDEN WELL |
GARDEN WELL
-
Strip ratio reduced from 3.2 (Q1) to 3.1 and down sharply from 5.85 (Q4 2015)
-
Grade at 0.89g/t in line with reserve for areas mined in the quarter
-
Mining reconciliation continues improving and in line with reserve for Dec15
-
Incremental improvements in throughput and recovery as plant optimisation continues
-
Production 31,714oz at a run rate of 127kozpa in line with guidance mid-point
-
Cash cost $903/oz and AISC $983/oz consistent with Q1 and in line with guidance
==> picture [720 x 48] intentionally omitted <==
1010
GARDEN WELL
==> picture [720 x 455] intentionally omitted <==
1111
CORPORATE
DECEMBER 2015 QUARTER
-
Paid 6cps fully franked dividend $30m cash payment October 2015
-
$4.6m of income tax paid
-
Operating cashflow $49.8 million (Q1: $50.8m)
-
Cash and bullion holdings increased from $98.1m to $98.5m $35m cash build allowing for dividend and tax
-
Debt unchanged at $20m
-
Gold sold 75,237oz at $1,567/oz (Q1: 74,799 @ $1,545)
-
Work progressing on securing infrastructure requirements for McPhillamys Gold Project in NSW
-
Continuing to review bolt on acquisition opportunities around Duketon
-
Board restructure
-
Paul Thomas COO joins board, Frank Fergusson retires
-
Nick Giorgetta retires as Chairman but remains non-exec director
-
Mark Clark becomes Exec Chairman, Mark Okeby Lead Independent Director
==> picture [720 x 48] intentionally omitted <==
1212
CASHFLOW WATERFALL
==> picture [613 x 332] intentionally omitted <==
Strong cash-flow from operations of $49.8m for Q2 and cash build after allowing for $30m dividend and $4.6m income tax paid in the quarter
==> picture [720 x 48] intentionally omitted <==
1313
CASHFLOW WATERFALL
==> picture [550 x 338] intentionally omitted <==
Business optimisations leading to trend of strong operating cash-flow and conversion to cash build
==> picture [720 x 48] intentionally omitted <==
1414
EXPLORATION UPDATE
SIGNIFICANT RESULTS AT DUKETON IN DEC15Q
-
Completed 41,582m of exploration drilling on 7 gold projects and prospects
-
Further significant gold results at a number of projects:
-
Baneygo – 12km south of Rosemont mill
- Final RC drilling programme returned high grade results
-
Updated Indicated & Inferred Resource quoted 7.1MT @ 1.03g/t for 237,000 oz
-
Gloster – 26km west of Moolart Well
- High grade results from 177 RC holes for 21,287m,
-
Resource estimation Jan 2016, Ore Reserve estimation later Mar 16Q
-
Idaho – 2.2km north of Baneygo
-
Infill 40m x 20m RC drilling – significant results
-
Early indications of potential for 10km shear north of Idaho to Rosemont
-
-
Tooheys Well – 2.5km south of Garden Well mill
-
RC drilling continued returning early very high grade results
-
Drilling to continue in Mar 16Q
-
-
Coopers – 11km south of Moolart Well mill
- Significant results continue, resource estimation Mar 16Q
==> picture [720 x 48] intentionally omitted <==
15 15 GLOSTER GOLD DEPOSIT FAMOUS BLUE GEOLOGY
==> picture [332 x 130] intentionally omitted <==
----- Start of picture text -----
Felsic Volcanics
M38/1268
1km
----- End of picture text -----
INFILL & EXTENSIONAL DRILLING COMPLETE – RESOURCE UPDATE PENDING
-
Located 26km west of Moolart Well
-
Historic resource* at 0.5g/t lower cut:
==> picture [278 x 89] intentionally omitted <==
-
December 2015 RC drilling programme on 25m x 25m grid shown in Red
-
New Mining Licence M38/1268 granted in December 2015
-
177 RC holes drilled in the Dec15Q for 21,287m
-
New Resource and maiden Ore Reserve estimations in March 2016Q
Basalt
Historical drilling grey. Regis drilling Dec 15Q in red
- Compliant with 1996 JORC Code and Guidelines (refer ASX announcement 16 July 2015)
==> picture [57 x 48] intentionally omitted <==
16 16
GLOSTER DRILL RESULTS December 2015 Quarter
| Hole No Northing (mN) Easting (mE) Hole Depth (m) From (m) To (m) Interval (m) Gold (g/t) |
Hole No Northing (mN) Easting (mE) Hole Depth (m) From (m) To (m) Interval (m) Gold (g/t) |
|---|---|
| RRLGLRC012 | 6950658 408353 69 16 35 19 3.48 |
| RRLGLRC028 | 6950772 408424 143 122 130 8 10.01 |
| RRLGLRC031 | 6950463 408465 43 8 22 14 5.03 |
| RRLGLRC056 | 6950749 408491 150 29 46 17 3.49 |
| RRLGLRC064 | 6950693 408495 114 93 108 15 7.4 |
| RRLGLRC067 | 6950724 408632 174 85 102 17 1.88 |
| RRLGLRC069 | 6950693 408610 162 77 93 16 2.2 |
| RRLGLRC077 | 6950755 408456 150 25 47 22 2.14 |
| RRLGLRC078 | 6950766 408478 160 29 44 15 3.21 |
| RRLGLRC082 | 6950647 408563 130 19 34 15 2.53 |
| RRLGLRC088 | 6950636 408566 115 96 99 3 10.4 |
| RRLGLRC091 | 6950482 408566 90 8 36 28 3.01 |
| RRLGLRC091 | 6950482 408566 90 46 72 26 2.06 |
| RRLGLRC092 | 6950492 408588 138 71 76 5 9.27 |
| RRLGLRC093 | 6950503 408612 138 78 87 9 4.04 |
| RRLGLRC096 | 6950534 408681 184 57 63 6 5.61 |
| RRLGLRC097 | 6950542 408702 192 119 126 7 4.37 |
| RRLGLRC104 | 6950409 408864 174 113 117 4 13.26 |
| RRLGLRC113 | 6950395 408876 160 132 138 6 7.06 |
| RRLGLRC144 | 6950437 408847 180 133 137 4 12.83 |
| RRLGLRC148 | 6950497 408545 120 27 38 11 2.74 |
| RRLGLRC149 | 6950507 408570 110 38 53 15 3.02 |
| RRLGLRC150 | 6950551 408546 135 31 40 9 4.44 |
| RRLGLRC154 | 6950565 408633 145 79 91 12 3.5 |
| RRLGLRC155 | 6950575 408657 223 92 94 2 38.25 |
| RRLGLRC158 | 6950517 408591 100 50 59 9 3.5 |
| RRLGLRC160 | 6950522 408726 174 135 145 10 3.07 |
| RRLGLRC163 | 6950453 408629 140 28 42 14 2.3 |
| RRLGLRC166 | 6950489 408713 175 107 127 20 3.94 |
20gm intersections are highlighted
All coordinates are AGD 84. All holes were drilled at -60° to 244°
All Intercepts calculated using a 0.5g/t lower cut, no upper cut, maximum 2m internal dilution. All assays determined on 1m split samples by fire assay
==> picture [55 x 47] intentionally omitted <==
16
17 17
GLOSTER SECTION 6950495mN
==> picture [708 x 398] intentionally omitted <==
----- Start of picture text -----
Base of Alluvium
500mRL
Top of Saprock
Diorite
450mRL
Top of Fresh Rock
Gloster Gold Project
Cross Section 6950495mN
Diorite Gold Mineralised Envelope
Au InterceGoldpt 18m @ 1.1g/t
400mRL
Clay oxidised Volcanics
Regis Drill Holes: GLRC091 Diorite
Intermediate Volcaniclastics
408500mE 408600mE 6950500mN 408700mE
----- End of picture text -----
==> picture [720 x 48] intentionally omitted <==
18 18 BANEYGO GOLD PROJECT
==> picture [101 x 21] intentionally omitted <==
----- Start of picture text -----
Section 6907677mN
Section 6907638mN
----- End of picture text -----
FIRST RESOURCE UPGRADE FROM THE 20KM ROSEMONT-BANEYGO SHEAR
- Baneygo 12km south of Rosemont mine
==> picture [26 x 10] intentionally omitted <==
----- Start of picture text -----
1km
----- End of picture text -----
-
Gold hosted in Quartz Dolerite similar to Rosemont
-
Baneygo previous 2004 Resource 43koz Au in 4 small deposits
-
Regis drilled on 20m traverses 49 RC holes for 4,618m in Dec 15Q
-
Highly significant new gold mineralisation defined over 3km strike outside 2004 Resource
-
Diamond drilling completed for geotechnical and metallurgical purposes
Historical drilling grey. Regis drilling blue and Dec 15Q in red
- Updated Resource estimation completed
==> picture [389 x 48] intentionally omitted <==
19 19
BANEYGO SECTIONS September 2015Q drilling
TOFR TOFR
==> picture [720 x 48] intentionally omitted <==
20
BANEYGO DRILL RESULTS December 2015 Quarter
| Hole No | Northing (mN) Easting (mE) Hole Depth (m) From (m) To (m) Interval (m) Gold g/t |
|---|---|
| RRLBYRC332 | 6907484 431906 72 17 24 7 1.28 |
| RRLBYRC332 | 6907484 431906 72 55 59 4 7.71 |
| RRLBYRC333 | 6907485 431930 102 39 56 17 1.48 |
| RRLBYRC333 | 6907485 431930 102 67 75 8 1.44 |
| RRLBYRC335 | 6907755 431845 72 46 58 12 2.05 |
| RRLBYRC336 | 6907645 431905 118 93 108 15 2.24 |
| RRLBYRC338 | 6907634 431868 54 21 31 10 0.86 |
| RRLBYRC341 | 6907771 431902 147 118 128 10 0.97 |
| RRLBYRC342 | 6907766 431883 120 95 100 5 2.01 |
| RRLBYRC344 | 6907728 431910 141 111 127 16 1.35 |
| RRLBYRC345 | 6907723 431891 120 84 87 3 4.90 |
| RRLBYRC347 | 6907713 431853 69 36 45 9 3.86 |
| RRLBYRC350 | 6907690 431917 153 135 147 12 6.16 |
| RRLBYRC352 | 6907650 431924 156 108 130 22 1.71 |
| RRLBYRC352 | 6907650 431924 156 147 150 3 2.72 |
| RRLBYRC355 | 6905841 432445 108 40 49 9 1.88 |
| RRLBYRC356 | 6905801 432451 81 28 31 3 6.24 |
| RRLBYRC357 | 6905807 432471 117 51 63 12 1.24 |
| RRLBYRC359 | 6905847 432465 135 58 59 1 13.30 |
| RRLBYRC359 | 6905847 432465 135 111 113 2 6.64 |
| RRLBYRC362 | 6905926 432442 99 72 79 7 3.47 |
| RRLBYRC364 | 6906147 432331 51 35 39 4 2.15 |
| RRLBYRC365 | 6906152 432350 78 37 47 10 0.95 |
| RRLBYRC368 | 6906477 432320 129 74 82 8 1.71 |
| RRLBYRC368 | 6906477 432320 129 108 116 8 1.50 |
| RRLBYRC370 | 6906511 432314 153 81 83 2 12.70 |
| RRLBYRC370 | 6906511 432314 153 105 107 2 4.53 |
| RRLBYRC370 | 6906511 432314 153 110 118 8 6.36 |
| RRLBYRC372 | 6907681 431898 117 79 110 31 3.04 |
| RRLBYRC376 | 6908251 431641 57 48 52 4 6.59 |
8gm intersections are tabled
All coordinates are AGD 84. All holes were drilled at -60 ° to 254 °
All Intercepts calculated using a 0.5g/t lower cut, no upper cut, maximum 2m internal dilution. All assays determined on 1m split samples by fire assay
==> picture [55 x 47] intentionally omitted <==
21 21
BANEYGO GOLD PROJECT
DECEMBER 2015 RESOURCE UPDATE
- Updated Resource estimated at a 0.4g/t gold lower cut:
| Indicated | Indicated | Indicated | Inferred | Inferred | Inferred | Total | Total | Total |
|---|---|---|---|---|---|---|---|---|
| Tonnes (MT) |
Grade (g/t) |
Ounces (‘000) |
Tonnes (MT) |
Grade (g/t) |
Ounces (‘000) |
Tonnes (MT) |
Grade (g/t) |
Ounces (‘000) |
| 6.2 | 1.03 | 204 | 1.0 | 1.06 | 32 | 7.1 | 1.03 | 237 |
Errors of summation may occur due to rounding.
-
Fivefold increase in quoted Resource at Baneygo
-
Does not yet include Idaho or the sparsely drilled but mineralised 4km along strike to the south of Baneygo.
-
This resource will be used as the basis for an Ore Reserve estimate later in the March 2016 quarter.
-
Highlights the potential to add significant resource ounces along the highly prospective 20km Rosemont-Baneygo shear where previous drilling is sparse and largely ineffective (mostly less than 50m deep holes).
==> picture [720 x 48] intentionally omitted <==
22 22
ROSEMONT TO BANEYGO
REGIONAL SCALE OPPORTUNITY
==> picture [713 x 433] intentionally omitted <==
----- Start of picture text -----
REGIONAL SCALE OPPORTUNITY
Rosemont
Rosemont to Baneygo trend 20km
poorly tested.
Quartz dolerite host rock at
Rosemont continues to Baneygo and
22m @ 2.6g/t, f 22m
10km
beyond to the south
Garden
King John
Well Recent RC drilling around historic
3m @ 7.7g/t, f 41m
4m @ 8.5g/t, f 28m Baneygo resource.
Significant gold intercepts from
Rosemont to Baneygo
10m @ 1.8g/t, f 22m
8m @ 1.9g/t, f 14m New discovery Idaho
13m @ 4.9g/t, f 17m Idaho
20km corridor requires further drilling
•
33m @ 8.4g/t, f 50m Previous drilling max 100m deep with
11m @ 7.3g/t, f 21m
most only 50m deep
21m @ 9.3g/t, f 16m Erlistoun
•
Up to 800m gaps between drill lines
Baneygo
Continue to test strike continuation north
22m @ 2.5g/t, f 26m to Rosemont on 400m traverses
5m @ 4.6g/t, f 7m
2m @ 12.6g/t, f 13m
----- End of picture text -----
23 23
IDAHO GOLD PROSPECT
IDAHO DISCOVERY FURTHER CONFIRMS PROSPECTIVITY OF ROSEMONT-BANEYGO TREND
500m
Section 6909156mN Section 6908944mN
-
10km south of Rosemont and 2.2km north of Baneygo
-
Gold hosted in Quartz Dolerite similar to Rosemont and Baneygo
-
No historical resource - new discovery
-
Regis drilled on 40m traverses 36 RC holes for 2,993m in Dec 15Q
-
Highly significant new gold mineralisation defined over 650m strike
Historical drilling grey. Regis drilling blue and Dec 15Q in red
==> picture [720 x 48] intentionally omitted <==
24
IDAHO DRILL RESULTS
December 2015 Quarter
| Hole No Northing (mN) Easting (mE) Hole Depth (m) From (m) To (m) Interval (m) Gold (g/t) |
Hole No Northing (mN) Easting (mE) Hole Depth (m) From (m) To (m) Interval (m) Gold (g/t) |
|---|---|
| RRLIHRC018 | 6908707 431463 60 28 42 14 0.94 |
| RRLIHRC021 | 6908778 431421 24 15 18 3 8.73 |
| RRLIHRC023 | 6908819 431420 48 40 46 6 4.27 |
| RRLIHRC024 | 6908825 431440 78 30 52 22 1.39 |
| RRLIHRC025 | 6908852 431435 78 29 65 36 1.35 |
| RRLIHRC025 | 6908852 431435 78 75 78 3 16.04 |
| RRLIHRC026 | 6908901 431413 66 36 62 26 1.43 |
| RRLIHRC027 | 6908906 431433 102 53 77 24 1.25 |
| RRLIHRC027 | 6908906 431433 102 97 99 2 8.15 |
| RRLIHRC028 | 6909009 431389 90 49 65 16 0.73 |
| RRLIHRC030 | 6909161 431336 108 62 71 9 3.00 |
| RRLIHRC030 | 6909161 431336 108 81 83 2 4.24 |
| RRLIHRC034 | 6909391 431270 78 50 56 6 3.02 |
| RRLIHRC038 | 6909468 431248 66 45 56 11 1.11 |
| RRLIHRC043 | 6908843 431414 54 32 34 2 13.80 |
| RRLIHRC043 | 6908843 431414 54 42 49 7 4.55 |
| RRLIHRC044 | 6908667 431461 33 9 16 7 2.22 |
| RRLIHRC051 | 6908942 431408 81 46 64 18 1.13 |
| RRLIHRC051 | 6908942 431408 81 70 75 5 11.79 |
| RRLIHRC052 | 6908948 431428 135 63 93 30 4.34 |
| RRLIHRC058 | 6909042 431363 81 22 26 4 2.16 |
| RRLIHRC058 | 6909042 431363 81 42 56 14 0.60 |
| RRLIHRC059 | 6909048 431383 111 61 83 22 1.63 |
| RRLIHRC062 | 6909085 431366 120 51 58 7 1.52 |
| RRLIHRC062 | 6909085 431366 120 61 69 8 2.45 |
| RRLIHRC064 | 6909119 431342 99 45 58 13 1.21 |
| RRLIHRC064 | 6909119 431342 99 73 75 2 5.22 |
| RRLIHRC065 | 6909124 431362 140 72 91 19 2.03 |
| RRLIHRC066 | 6909165 431359 159 73 96 23 2.21 |
| RRLIHRC068 | 6909195 431318 75 5 7 2 5.19 |
| RRLIHRC068 | 6909195 431318 75 47 50 3 3.37 |
| RRLIHRC069 | 6909230 431292 63 30 44 14 0.75 |
| RRLIHRC070 | 6909235 431312 88 41 55 14 1.81 |
| RRLIHRC072 | 6909544 431225 75 48 68 20 1.92 |
| RRLIHRC074 | 6909107 431304 45 29 34 5 2.19 |
8gm intersections are tabled
All coordinates are AGD 84. All holes were drilled at -60 ° to 254 °
All Intercepts calculated using a 0.5g/t lower cut, no upper cut, maximum 2m internal dilution. All assays determined on 1m split samples by fire assay
==> picture [55 x 47] intentionally omitted <==
25 25
IDAHO SECTIONS December 2015 Results
| 450mRL 431350mE |
431400mE | 6908950mN | 6908950mN | k NEW GOLD DISCOVERY AT IDAHO Significant new gold mineralisation defined Dec 15Q holes RRIHRC051 18m @ 1.13g/t from 46m RRIHRC051 5m @ 11.79g/t from 70m RRIHRC052 30m @ 4.34g/t from 63m Highly significant new gold mineralisation defined over 650m strike Further drilling planned in March 2016Q and maiden Resource to follow |
||
|---|---|---|---|---|---|---|
| 400mRL | To Top of |
p of Fre |
Saproc sh Rock |
|||
| 350mRL | 431450mE | |||||
Idaho Gold Pr Gold Mineralise Cross Section 6908 |
oje |
ct velope 4mN |
||||
| d En 94 |
||||||
| ~~Gold~~ Au Intercept 5m |
@ | 1.08g/t | ||||
26
IDAHO GOLD PROSPECT
Idaho Gold Prospect
New Gold Discovery Idaho 2.2km North of Baneygo
Baneygo Gold Deposit
North
Block Model g/t Au
==> picture [87 x 97] intentionally omitted <==
==> picture [98 x 45] intentionally omitted <==
==> picture [720 x 48] intentionally omitted <==
2727
TOOHEYS WELL DRILL RESULTS
| 17m @ 1.54g/t 12m @ 3.34g/t 7m @ 5.03g/t 200m 8m @ 5.47g/t 16m @ 3.23g/t 22m @ 3.15g/t |
~~S~~ection 6909340mN 35m @ 1.1g/t 44m @ 1.18g/t 19m @ 1.34g/t 24m @ 1.78g/t 54m @ 3.6g/t 50m @ 2.76g/t 48m @ 2.38g/t 23M @ 2.26G/T |
A BOLT ON FOR GARDEN WELL Gold shear zones hosted by chert and shale 2013 RC drilling returned significant go intercepts on the Western shear Regis drilled on 40m traverses, 30 RC for 3,908m in Dec 15Q Recent 2015 drilling has defined a parallel Eastern shear: • Eastern Shear high grade and ope south for 600m • December 15Q gold results in red Eastern Shear open to the north and s Western Shear open to the south Further drill testing planned in Mar 16Q Resource estimation to follow |
|---|---|---|
-
2013 RC drilling returned significant gold intercepts on the Western shear
-
Regis drilled on 40m traverses, 30 RC holes for 3,908m in Dec 15Q
-
Eastern Shear high grade and open to south for 600m
-
Eastern Shear open to the north and south
-
Western Shear open to the south
-
Further drill testing planned in Mar 16Q
2828
TOOHEYS WELL DRILL RESULTS December 2015 Quarter
| Hole No | Northing (mN) Easting (mE) Hole Depth (m) From (m) To (m) Interval (m) Gold (g/t) |
|---|---|
| RRLTWRC046 | 6909340 437840 148 55 82 27 2.48 |
| RRLTWRC046 | 6909340 437840 148 85 135 50 2.75 |
| RRLTWRC047 | 6909340 437860 178 46 57 11 1.60 |
| RRLTWRC047 | 6909340 437860 178 72 88 16 1.42 |
| RRLTWRC047 | 6909340 437860 178 95 122 27 1.38 |
| RRLTWRC047 | 6909340 437860 178 134 147 13 3.03 |
| RRLTWRC048 | 6909300 437860 145 70 118 48 2.38 |
| RRLTWRC048 | 6909300 437860 145 122 145 23 2.26 |
| RRLTWRC050 | 6909140 437860 98 60 78 18 0.89 |
| RRLTWRC051 | 6909140 437900 148 92 99 7 1.83 |
| RRLTWRC054 | 6909060 437900 138 82 94 12 1.13 |
| RRLTWRC054 | 6909060 437900 138 97 103 6 1.74 |
| RRLTWRC057 | 6909380 437780 93 59 63 4 5.15 |
| RRLTWRC058 | 6909380 437800 68 55 68 13 2.50 |
| RRLTWRC059 | 6909060 437940 168 81 90 9 2.04 |
| RRLTWRC059 | 6909060 437940 168 125 135 10 0.88 |
==> picture [55 x 47] intentionally omitted <==
8gm intersections are tabled. ° ° All coordinates are AGD 84. All holes were drilled at -60 to 270 . All Intercepts calculated using a 0.5g/t lower cut, no upper cut, maximum 2m internal dilution. All assays determined on 1m split samples by fire assay.
29 29
==> picture [720 x 516] intentionally omitted <==
----- Start of picture text -----
29
TOOHEYS WELL GOLD PROSPECT
December 2015 Results
500mRL
450mRL
Top of Saprock
Top of Fresh Rock
400mRL
Tooheys Well Gold Project
Cross Section 6909340mN
Gold Mineralised Envelope
Gold Intercept 11m @ 1.59g/tGold
350mRL
Chert
Black Sulphidic Shale
Banded Iron Formation
Shear Zone
43770mE 43780mE 43790mE
----- End of picture text -----
30
COOPERS GOLD PROSPECT
| 2 9m @ 3. 5m @ 5.4 5m @ 1 11m @ |
2 9m @ 3. 5m @ 5.4 5m @ 1 11m @ |
2 9m @ 3. 5m @ 5.4 5m @ 1 11m @ |
00m | 00m | 00m | 00m | .28g/t @ 49.3g/t 6934420mN @ 2.78g/t n t .68g/t 5.73/t 9.0g/t |
Gold mineralisation over 500m strike • N-S trending moderately W dipping gold mineralised shear zone • Discovered under a thin palaeochannel • Defined to 100m depth in oxidised dolerite and diorite • Defined in Aircore and RC drilling on 40m and 80m spaced E-W sections Regis drilled on 40m traverses 50 RC holes for 4,4628m in Dec 15Q Gold results for most holes expected in Mar 16Q December 15Q gold results in red Resource estimation in March 16Q ANOTHER BOLT ON FOR MOOLART WELL |
|
|---|---|---|---|---|---|---|---|---|---|
| 11m @ | 2.05/t | ||||||||
| 9m @ 3. | 46g/t | ||||||||
| 5m @ 1 | 4.1g/t | ||||||||
| 5m @ 5.4 | 9g/t | ||||||||
| Coopers Proje Coopers Gold |
Gold ct Project |
||||||||
| 8m @ 2 | .28g/t | ||||||||
31 31
COOPERS GOLD PROSPECT
==> picture [492 x 402] intentionally omitted <==
----- Start of picture text -----
50m
BOCO
TOFR
----- End of picture text -----
==> picture [720 x 48] intentionally omitted <==
3232
RECAP OF PRESENTATION
-
FY2016 Q2 gold production 75,544 ounces at AISC of A$918/oz
-
Production run rate at upper end of FY16 guidance 275-305koz
-
AISC below lower end of FY16 guidance of $970-1,070/oz
-
Consistent production and cost performance at all operations
-
Rosemont operations continue to outperform
-
Reconciliation to reserve positive for Duketon and in line for GW by Dec15
-
Cash-flow from operations $49.8m for Q2 (Q1: $50.8m)
-
6cps fully franked dividend paid Oct15
-
Cash and bullion increased to $98.5m (net cash position $78.5m)
- $35m cash build allowing for dividend and income tax paid
-
Work continuing to secure infrastructure required for McPhillamys project
-
Continued exciting exploration results at Duketon
-
Including Baneygo, Idaho, Tooheys Well & Coopers
-
Pointing to extensions of mine life at all three operations
==> picture [720 x 48] intentionally omitted <==
3333
JORC COMPLIANT MINERAL RESOURCES 31 MARCH 2015
Group Mineral Resources
| Group Mineral Resources | Group Mineral Resources | Group Mineral Resources | Group Mineral Resources | Group Mineral Resources | Group Mineral Resources | Group Mineral Resources | Group Mineral Resources | Group Mineral Resources | Group Mineral Resources | Group Mineral Resources | Group Mineral Resources | ||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| as at 31 March 2015 | |||||||||||||||
| Gold | Measured | Indicated | Inferred | Total Resource | Competent Person4 |
||||||||||
| Project | Type | Cut-Off (g/t) |
Tonnes (Mt) |
Gold Grade (g/t) |
Gold Metal (koz) |
Tonnes (Mt) |
Gold Grade (g/t) |
Gold Metal (koz) |
Tonnes (Mt) |
Gold Grade (g/t) |
Gold Metal (koz) |
Tonnes (Mt) |
Gold Grade (g/t) |
Gold Metal (koz) |
|
| Moolart Well1 | Open-Pit | 0.4 | 3.0 | 0.89 | 87 | 29.2 | 0.75 | 706 | 15.0 | 0.62 | 300 | 47.3 | 0.72 | 1,093 | A |
| Garden Well1 | Open-Pit | 0.4 | 2.7 | 0.63 | 54 | 73.8 | 0.90 | 2,131 | 10.2 | 0.88 | 288 | 86.7 | 0.89 | 2,473 | B |
| Rosemont1 | Open-Pit | 0.4 | 5.4 | 1.31 | 228 | 20.1 | 1.27 | 824 | 2.8 | 1.78 | 160 | 28.3 | 1.33 | 1,212 | B |
| Duketon Main Deposits | Sub Total | 11.1 | 1.03 | 369 | 123.2 | 0.92 | 3,661 | 28.0 | 0.83 | 748 | 162.3 | 0.92 | 4,777 | ||
| Erlistoun | Open-Pit | 0.4 | - | - | - | 5.7 | 1.34 | 247 | 1.1 | 1.00 | 37 | 6.9 | 1.28 | 284 | A |
| Dogbolter | Open-Pit | 0.4 | - | - | - | 2.8 | 1.11 | 102 | 0.4 | 1.02 | 13 | 3.2 | 1.10 | 115 | A |
| Petra | Open-Pit | 0.4 | - | - | - | 1.2 | 1.08 | 42 | 0.1 | 1.09 | 2 | 1.3 | 1.08 | 44 | A |
| Anchor | Open-Pit | 0.4 | - | - | - | 0.2 | 1.75 | 9 | 0.1 | 0.95 | 2 | 0.2 | 1.53 | 11 | A |
| King John3 | Open-Pit | 1.0 | - | - | - | - | - | - | 0.7 | 3.19 | 72 | 0.7 | 3.20 | 72 | C |
| Russells Find3 | Open-Pit | 1.0 | - | - | - | - | - | - | 0.4 | 3.86 | 55 | 0.4 | 4.28 | 55 | C |
| Baneygo3 | Open-Pit | 0.5 | - | - | - | - | - | - | 0.8 | 1.67 | 43 | 0.8 | 1.67 | 43 | C |
| Reichelts Find3 | Open-Pit | 1.0 | - | - | - | 0.1 | 3.69 | 17 | - | - | - | 0.1 | 3.69 | 17 | C |
| Duketon Satellite Deposits | Sub Total | - | - | - | 10.1 | 1.28 | 416 | 3.6 | 1.96 | 223 | 13.6 | 1.46 | 640 | ||
| Duketon | Total | 11.1 | 1.03 | 369 | 133.2 | 0.95 | 4,077 | 31.5 | 0.96 | 971 | 175.9 | 0.96 | 5,417 | ||
| McPhillamys | Total | 0.4 | - | - | - | 69.2 | 0.94 | 2,087 | 3.9 | 0.98 | 123 | 73.2 | 0.94 | 2,210 | B |
| Regis | Grand Total | 11.1 | 1.03 | 369 | 202.5 | 0.95 | 6,164 | 35.5 | 0.96 | 1,094 | 249.1 | 0.95 | 7,627 |
Notes
The above data has been rounded to the nearest 100,000 tonnes, 0.01 g/t gold grade and 1,000 ounces. Errors of summation may occur due to rounding.
All Mineral Resources are reported inclusive of Ore Reserves to JORC Code 2012 unless otherwise noted
-
Mineral Resources and Ore Reserves are reported inclusive of ROM Stockpiles at cut-off grade of 0.4 g/t
-
Reported under JORC Code 2004
-
Refer to Group Competent Person Notes
-
5 As this table is quoted at 31 March 2015 the updated Baneygo resource referred to in the body of this presentation has not been updated. It will be updated as part of the next full annual update
==> picture [720 x 48] intentionally omitted <==
3434
JORC COMPLIANT ORE RESERVES 31 MARCH 2015
Group Ore Reserves
| Group Ore Reserves | Group Ore Reserves | Group Ore Reserves | Group Ore Reserves | Group Ore Reserves | Group Ore Reserves | Group Ore Reserves | Group Ore Reserves | Group Ore Reserves | ||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| as at 31 March 2015 | ||||||||||||
| Gold | Proved | Probable | Total Ore Reserve | Competent Person3 |
||||||||
| Project | Type | Cut-Off (g/t)2 |
Tonnes (Mt) |
Gold Grade (g/t) |
Gold Metal (koz) |
Tonnes (Mt) |
Gold Grade (g/t) |
Gold Metal (koz) |
Tonnes (Mt) |
Gold Grade (g/t) |
Gold Metal (koz) |
|
| Moolart Well1 | Open-Pit | > 0.4 | 2.7 | 0.93 | 79 | 3.9 | 0.92 | 115 | 6.5 | 0.92 | 194 | D |
| Garden Well1 | Open-Pit | > 0.4 | 2.7 | 0.63 | 54 | 31.9 | 0.93 | 955 | 34.5 | 0.91 | 1,009 | D |
| Rosemont1 | Open-Pit | > 0.4 | 4.4 | 1.34 | 188 | 8.9 | 1.36 | 387 | 13.2 | 1.35 | 574 | D |
| Duketon Main Deposits | Sub Total | 9.7 | 1.03 | 321 | 44.6 | 1.02 | 1,456 | 54.3 | 1.02 | 1,777 | ||
| Erlistoun | Open-Pit | > 0.5 | - | - | - | 3.8 | 1.48 | 181 | 3.8 | 1.48 | 181 | D |
| Dogbolter | Open-Pit | > 0.5 | - | - | - | 0.3 | 1.57 | 16 | 0.3 | 1.57 | 16 | D |
| Petra | Open-Pit | > 0.5 | - | - | - | 0.6 | 1.26 | 25 | 0.6 | 1.26 | 25 | D |
| Anchor | Open-Pit | > 0.5 | - | - | - | 0.1 | 2.07 | 6 | 0.1 | 2.07 | 6 | D |
| Duketon Satellite Deposits | Sub Total | - | - | - | 4.8 | 1.47 | 229 | 4.8 | 1.47 | 229 | ||
| Regis | Grand Total | 9.7 | 1.03 | 321 | 49.4 | 1.06 | 1,685 | 59.1 | 1.06 | 2,006 |
Notes
The above data has been rounded to the nearest 100,000 tonnes, 0.01 g/t gold grade and 1,000 ounces. Errors of summation may occur due to rounding.
-
Mineral Resources and Ore Reserves are reported inclusive of ROM Stockpiles at cut-off grade of 0.4 g/t
-
Cutoff grades vary according to oxidation and lithology domains. Refer to Group Ore Reserves Lower Cut Notes
-
Refer to Group Competent Person Notes
==> picture [720 x 48] intentionally omitted <==