AI assistant
REGIS RESOURCES LIMITED — Interim / Quarterly Report 2015
Jul 15, 2015
65733_rns_2015-07-15_cb114edd-529f-4643-bd13-b0bab0188c6f.pdf
Interim / Quarterly Report
Open in viewerOpens in your device viewer
16 July 2015
==> picture [128 x 40] intentionally omitted <==
ABN 28 009 174 761
Manager Announcements Company Announcements Office Australian Securities Exchange Limited Level 4, 20 Bridge Street Sydney NSW 2000
www.regisresources.com Level 1 1 Alvan Street Subiaco WA 6008 Australia P 08 9442 2200 F 08 9442 2290
Gold Production, Outlook & Corporate Update
The board of Regis Resources Ltd provides the following gold production summary and corporate update in advance of the release of the full June 2015 quarterly report.
June 2015 Quarter Gold Production
Regis produced 75,372 ounces of gold in the June 2015 quarter (March 15: 65,949 oz) which was in line with revised guidance for the June 15 quarter given in early March 2015. Gold production for the full 2015 financial year was 310,204 ounces (within original guidance).
Operating results for the Regis group for the June 2015 quarter were as follows:
| Moolart Well |
Rosemont | Garden Well |
Total | |
|---|---|---|---|---|
| Ore mined (bcm ) | 339,493 | 270,215 | 438,565 | 1,048,273 |
| Wastemined (bcm) | 1,122,832 | 2,795,517 | 2,565,988 | 6,484,337 |
| Strippingratio (w:o) | 3.31 | 10.34 | 5.85 | 6.19 |
| Oremined (tonnes) | 711,967 | 603,281 | 1,174,324 | 2,489,572 |
| Ore milled (tonnes) | 743,599 | 638,280 | 1,162,159 | 2,544,038 |
| Head grade (g/t) | 0.95 | 1.45 | 0.85 | 1.03 |
| Recovery (%) | 90.4% | 94.1% | 83.9% | 89.5% |
| Gold production(ounces) | 20,655 | 27,951 | 26,766 | 75,372 |
| Cashcost (A$/oz) | 753 | 727 | 1,112 | 871 |
| Cashcostincroyalty (A$/oz) | 823 | 796 | 1,184 | 941 |
| All inSustaining Cost (A$/oz)1 | 899 | 1,066 | 1,426 | 1,148 |
1 AISC calculated on a per ounce of production basis
The June 2015 quarter saw a number of improvements in operations from the March 2015 quarter including:
-
Total Duketon throughput at 2.54MT was up 6% and recoveries were up 2% as a result of ongoing improvements at Rosemont and Garden Well as those milling operations continue to be fine tuned; and
-
Overall grade was up 6% as higher grade zones available at Rosemont were mined and milled.
Cash costs of operation for the quarter at $871 per ounce were 7% better than the March 2015 quarter ($936/oz) due to the above improvements. As a result of these operational improvements, all in sustaining costs (AISC) at $1,148 per ounce for the quarter were in line with the March 2015 quarter of $1,159/oz despite large cutbacks in both Garden Well and Rosemont pits significantly increasing mining stripping costs included in AISC. In particular Q4 stripping ratio (w:o) of 5.85 for Garden Well compared to Q3 of 4.43 and 3.82 for the first three quarters of FY2015. This is expected to reduce to 2.5 in FY2016 and 1.91 for remaining life of mine.
AISC for FY2015 for the Duketon operation was $994 per ounce.
Cash and Bullion Position
The board of Regis is pleased to advise that the Duketon project generated strong operating* cashflow of $47.6 million in the June 2015 quarter. This saw Regis’ cash and gold bullion holdings at 30 June 2015 increase to $73.1 million (March 15: $45.8 million).
The operating* cash flow for FY2015 was $150.9 million which has led, as shown below, to Regis’ net cash position increasing by $100 million in the twelve months to June 2015.
==> picture [338 x 224] intentionally omitted <==
----- Start of picture text -----
80
60
40
20
-
Dec-13 Mar-14 Jun-14 Sep-14 Dec-14 Mar-15 Jun-15
-20
-40
-60
Cash & gold bullion
Debt (debt includes the deferred contractor payment amounts negotiated for flood affected period
of operations)
Net cash/(debt)
$ Millions
----- End of picture text -----
Production Guidance for 2016
Regis expects gold production for the 2016 financial year to be within the range of 275,000 – 305,000 ounces at an AISC (all in sustaining cost) of $950 - $1,050 per ounce. The mid-point of this (+/- 5%) guidance range is summarised as follows:
| Moolart Well |
Rosemont | Garden Well |
Total | |
|---|---|---|---|---|
| Oremined (Mbcm) | 1.5 | 1.0 | 2.2 | 4.7 |
| Wastemined (Mbcm) | 4.4 | 9.3 | 5.9 | 19.6 |
| Stripping ratio (w:o) | 3.1 | 9.7 | 2.5 | 4.2 |
| Ore mined (Mtonnes) | 2.8 | 2.2 | 5.6 | 10.6 |
| Oremilled (Mtonnes) | 2.9 | 2.3 | 5.0 | 10.1 |
| Head grade (g/t) | 0.89 | 1.23 | 0.91 | 0.98 |
| Recovery (%) | 91 | 93 | 88 | 91 |
| Gold production (ounces‘000) | 75 | 85 | 130 | 290 |
| Cashcost (A$/oz) | 820 | 840 | 900 | 860 |
| Cashcostincroyalty (A$/oz) | 880 | 910 | 970 | 930 |
| All inSustaining Cost (A$/oz) | 950 | 1,070 | 1,040 | 1,020 |
Note: errors in summation may occur in this table due to rounding
At the mid-point of guidance and the current gold price (≈A$1,550/oz) the Duketon operations are expected to generate an operating cashflow (derived using AISC as operating cost) of around A$150 million in FY2016. Additional expansion capital expenditures are expected to be in the order of A$15-20 million.
2
- operating cash flow in relation to Q4 2015 and FY2015 is quoted under the Appendix 5B classification protocol and as such does not include payments for pre-strip and deferred mining costs as these are classified as investing activities.
Capital Management
The Company’s cash position and the strong outlook for the 2016 financial year have underpinned the board’s decision to implement the following capital management strategies:
Dividend
It is the board’s intention to recommence the payment of dividends in relation to the 2015 financial year (30 June 2015) with a target of 5-7 cents per share payment in the December 2015 quarter. Further details on the quantum of dividend will be provided at the time of the release of financial results in September 2015. Long term intentions are to establish and maintain a dividend payout ratio in the order of 60% of net profit after tax.
The target 2015 dividend payment and the long term payout ratio are subject to numerous factors including but not limited to gold price and exchange rates, gold production and operational performance, profitability, cash flow, working capital requirements, other expenditure requirements (including capital expenditures, acquisitions, developments and exploration) and the availability of sufficient franking credits.
Share Buyback
The board has also decided to implement an on-market share buy-back programme for up to 5% of the Company’s issued capital or approximately 25 million shares over the next twelve months. This follows the continued improvement in the Company’s financial and cash position since overcoming the flooding disruptions of the second half of FY2014 and the board’s view of the outlook for the Company’s operations.
An Appendix 3C in relation to the on-market buyback will be released shortly.
Yours sincerely Regis Resources Limited
==> picture [91 x 54] intentionally omitted <==
Mark Clark Managing Director