16 June 2011

Manager Announcements Company Announcements Office Australian Securities Exchange Limited Level 4, 20 Bridge Street Sydney NSW 2000

ABN 28 009 174 761 www.regisresources.com

Level 1 1 Alvan Street Subiaco WA 6008 Australia PO Box 862 Subiaco WA 6904 Australia P 08 9442 2200 F 08 9442 2290

Garden Well Gold Project

DFS and Board Approval for Development

Highlights

  • Completion of a Definitive Feasibility Study (DFS) in to the development of the Garden Well Gold Project shows a very robust and highly profitable project.

  • Board approval granted for development.

  • The plant design is based on a nominal 4.0mtpa throughput utilising a three stage crushing circuit, a scrubber and a single ball mill followed by gravity and carbon in leach circuits.

  • Key operating results of the DFS include:

Total gold production 1.57 million ounces
Average annual gold production 180,000 ounces
Year 1 gold production 247,000 ounces
(cash cost less than A$400/oz)
Capital cost A$109 million
Cashoperating cost (life of mine, preroyalties) A$555 perounce
  • Key financial results (at A$1,400/oz gold price) of the DFS include:
Revenue A$2.2 billion
Net cash flow (after capex, before tax) A$1.1 billion
NPV @ 6% (after capex, before tax) A$750 million
IRR 143%
Paybackperiod 7 months
  • Funding of development to be sourced from internal cash-flow and extension of corporate debt facility. No issue of equity is contemplated.

  • Project development to commence on site in July 2011 and commercial production forecast to commence early in the September 2012 quarter.

  • Achievement of this timetable will be a remarkable achievement for Regis given that it will mean that the deposit will have transitioned from discovery drill hole to first gold production in only two and a half years.

  • Development of the Garden Well Gold Project will take Regis total gold production to around 350,000 ounces for fiscal year 2012/13. This will elevate Regis in to the mid tier of world gold producers.

1

==> picture [65 x 20] intentionally omitted <==

Garden Well - Definitive Feasibility Study

The board of directors of Regis Resources Ltd is pleased to announce the completion of the definitive feasibility study (DFS) into the development of the Company’s 100% owned Garden Well Gold Project in Western Australia. On the basis of the DFS results the board has approved development of the project, located approximately 30 kilometres south of Regis’ operating Moolart Well Gold Mine.

Operating Parameters

The results of the DFS show a robust project with the following parameters:

Mining
Ore mined bcm 13,074,000
Waste mined bcm 45,690,000
Stripping ratio w/o 3.49
Milling
Tonnes milled Tonnes 35,061,000
Grade g/t 1.46
Recovery % 95
Recovered gold Ounces 1,568,046
Annual throughput Tonnes 4,000,000
Project life
Mine life years 9
Maxannualproduction ounces (yr 1)247,000
Average annual production ounces 180,000

Mining will be conducted using truck and shovel excavation methods. Regis conducted a competitive pricing process for contract earthmoving and drill & blast services, which in April 2011 culminated in the issue of a letter of intent to award a contract to Mining and Civil Australia Limited (MACA). MACA is already supplying the same services at Moolart Well and has the machinery available to commence preproduction mining at Garden Well in September 2011 as required by the development schedule.

The plant design is based on a nominal 4.0mtpa throughput utilising a three stage crushing circuit, a scrubber and a single ball mill followed by gravity and carbon in leach circuits. The process flow sheet is attached at Appendix 1 to this announcement. This is a robust and well proven configuration, which in management’s prior operating experience, has the capacity to exceed the nominal throughput rating. The recently built Moolart Well processing plant is currently operating at in excess of 2.5mtpa compared to its nameplate throughput rating of 2.0mtpa.

The forecast gold production of 247,000 ounces at a cash cost of less than A$400/oz in the first year of operation is a reflection of the higher grade nature of the oxide zone of the deposit (down to 80 metres below surface) which will be mined early in the project mine life. This high early production enhances the NPV and payback of the project.

Operating Costs

The DFS reported the following forecast operating costs for the Garden Well Gold Project:

Operating costs
Cash Costs **A$/oz **
Mining 328
Milling 195
Laboratory 2
Administration 30
Total Cash Costs 555

2

==> picture [65 x 20] intentionally omitted <==

A$/oz
Other Operating Costs
Rehabilitation 4
Royalties 72
Total other operating costs 76
Total Operating Costs 631

The cash cost of operation, at A$555 per ounce, is $17 per ounce (approx $27 million gross cost) lower than the cash cost of A$572 per ounce reported in the Company’s ASX announcement of the most recent mining reserve on 31 March 2011. This is due to the necessity to spend approximately $27 million of the operating mining costs prior to commencement of gold production in mid 2012. This early stage mining will facilitate the removal of overburden waste material in the open pit, building of an ore stockpile for start up operations and provision of suitable material for TSF construction.

Capital Costs

The DFS forecast the following capital costs for the development of the Garden Well Gold Project:

Capital Costs
A$’000
Construction Overheads 12,722
Primary & Secondary Crushing 16,284
Grinding, Scrubbing & Tertiary Crushing 23,069
Leaching, Adsorption & Desorption 12,977
Reagents 1,446
Services (Power & Water) 4,910
Tailings Storage 2,242
Infrastructure 21,772
Capital Spares 1,421
FirstFills 942
EPCM 9,735
Owners Costs 300
Pre-Production-Mine and Plant 1,640
Total Capital Cost **109,461 **

Operating and capital costs have been forecast using current third party pricing, the significant operating experience of management, current operating costs at Regis’ Moolart Well Gold Mine and input from external engineering consultants Mintrex.

Construction and other development activities will be managed in house by Regis. This is the same approach as was used very successfully in the development of the Moolart Well Gold Mine in 2009/10. This approach contributed to the timely and highly cost effective delivery of that project and is expected to achieve a similar result at Garden Well.

Purchase of Long Lead Capital Items

The capital cost estimate includes the purchase of new equipment and other capital items for which orders have already been placed. These items include the following:

  • Ball mill (new) - Outotec 6.0MW, 5.8m x 9.2m

  • Primary crusher (new) – Metso s50-65 gyratory

  • Drum scrubber and trommel (new) - Outotec 315kW, 3.8m x 5.73m (scrubber)

  • Accommodation camp (new) - units, associated buildings and infrastructure for 250 man camp

  • Various mobile equipment

3

==> picture [65 x 20] intentionally omitted <==

These items were ordered in advance of the completion of the DFS in order to keep the development of the project on the fast track timetable targeted by Regis. The total commitment made to date on the purchase of long lead capital items is approximately $22.9 million of which $5.7 million had been spent by 31[st] May 2011.

Financial Analysis

A summary of the financial results of the Garden Well Gold Project DFS is shown below:

**Financial Analysis (gold price US$1,250, ** aud:usd 0.90)
Revenue $’000 2,195,000
Net cash flow (after capex, before tax) $’000 1,051,000
NPV @ 6% (after capex, before tax) $’000 750,000
IRR % 143
Paybackperiod Months 7

The financial analysis shows that the project is expected to be very robust and highly profitable. The internal rate of return of 143% and capital payback of 7 months are testament to the high quality of the project.

Funding

The development of the project will be funded through a combination of internal cash-flow from Regis’ Moolart Well operations and an extension of the existing corporate debt facility. The board does not envisage any requirement for the Company to issue any further equity to fund the development.

Development Timetable

The timetable under which the development of the project is scheduled to proceed is as follows:

Commence construction September 2011 quarter
Mill delivery and commencement of installation March 2012 quarter
Commissioning and first gold production September 2012 quarter

The development schedule forecasts an eleven month construction period. This should see commercial gold production commencing early in the September 2012 quarter. Completion of the project development on this timetable will be a remarkable achievement for Regis given that it will mean that the deposit will have transitioned from discovery drill hole to first gold production in only two and a half years. This will be a feat rarely, if ever, matched in the Australian gold industry for a project of the size and scope of Garden Well.

Licensing & Permitting

The Garden Well project is located on granted mining leases. Various licences are required to develop and operate the project. Applications for all required licenses and consents have been made in the timeframes, allowing for statutory processing periods, required to meet the development schedule. Two clearing permits are required for the project. The first was granted in April 2011, whilst the second has been approved by the Department of Mines and Petroleum (DMP) and is currently in the final stage of the grant process with grant expected in June 2011. A mining proposal application for approval to mine the project was submitted to the DMP in May 2011 with grant anticipated within accepted statutory timeframes. A works approval application was submitted to the Department of Environment and Conservation in March 2011 and the works approval instrument is now in the final stages of the grant process.

4

==> picture [65 x 20] intentionally omitted <==

Resource & Reserve Update

The DFS was based on the JORC compliant reserve announced to ASX on 31 March 2011. Regis expects to update both the resource and reserve at Garden Well in the near future to include further drill results (announced to ASX 12 April 2011) at depth since the last resource estimation.

Regis Managing Director Mark Clark commented:

“The completion of the DFS for the Garden Well Gold Project confirms that the project is very robust and highly profitable. The internal rate of return of 143% and a capital payback of 7 months are quite remarkable. Construction will commence in earnest in the next month and the development schedule should see commencement of gold production in mid 2012. The first year of gold production of 247,000 ounces, at a cash cost of less than A$400 per ounce, from Garden Well will take Regis total gold production to around 350,000 ounces for fiscal year 2012/13. This will elevate Regis in to the mid tier of world gold producers”

Further enquiries should be directed to Mr Mark Clark, Managing Director.

Yours sincerely Regis Resources Limited

==> picture [90 x 53] intentionally omitted <==

Mark Clark Managing Director

Background

Reserve

Garden Well was discovered in November 2009 and since that time Regis has drilled in excess of 90,000 metres of drilling at the project. The JORC compliant reserve at Garden Well is as follows:

Category Tonnes (Millions) Gold Grade (g/t) Contained Gold (Ounces)
Proven 0 0 0
Probable 35.3 1.46 1,660,000
35.3 1.46 1,660,000

Notes: 0.6 g/t Au lower SMU block cut off grade. Rounded to two significant figures.

Regis’ total JORC compliant gold reserves stand at 2.5 million ounces, as detailed in Appendix 2 to this announcement.

Resource

The JORC compliant resource (inclusive of reserves) for the Garden Well Gold Deposit is 2.14 million ounces of contained gold. The resource was estimated by independent geological consultants SRK Consulting using the Ordinary Kriging estimation technique on a block size of 20 m x 20 m x 5 m. Uniform conditioning was used to estimate the proportion of the kriged panel estimate above the 0.5 g/t Au cut-off using a selective mining unit (SMU) size of 5 m x 5 m x 2.5 m. The breakdown of the resource is as follows:

Category Tonnes (Millions) Gold Grade (g/t) Contained Gold (Ounces)
Indicated 39.5 1.39 1,760,100
Inferred 9.5 1.23 375,800
49.0 1.36 2,135,900

Notes: Rounded to two significant figures. Rounding errors may occur.

Regis’ total JORC compliant gold resources stand at 5.8 million ounces, as detailed in Appendix 3 to this announcement.

5

==> picture [65 x 20] intentionally omitted <==

- Appendix 1 Garden Well Process Plant Flow Sheet

==> picture [757 x 394] intentionally omitted <==

6

==> picture [65 x 20] intentionally omitted <==

Qualification Statement

The technical information in this report has been reviewed and approved by Mr Morgan Hart who is a member of the Australasian Institute of Mining and Metallurgy. Mr Hart has sufficient experience which is relevant to the style of mineralisation and type of deposit under consideration and to the activity which he is undertaking to qualify as a Competent Person as defined in the 2004 edition of the ‘Australasian Code for the Reporting of Exploration Results, Mineral Resources and Ore Reserves’. Morgan Hart is a director and full time employee of Regis Resources Ltd and consents to the inclusion in the report of the matters based on his information in the form and context in which it appears.

APPENDIX 2 JORC COMPLIANT GOLD RESERVES

Proven Proven Probable Total Cut-
off
Grade
g/t
Project million
tonnes
grade
g/t

gold
koz

million
tonnes
grade
g/t
gold
koz

million
tonnes
grade
g/t

gold
koz
Garden Well 35.3 1.46 1,660 35.3 1.46 1,660 0.60
Moolart
Well
Laterite 9.5 1.44 437 0.6 0.98 19 10.1 1.41 455 0.50
Oxide 1.2 1.85 71 1.2 2.02 77 2.4 1.94 148 0.50
Total
Moolart
Well
10.7 1.48 508 1.8 1.66 96 12.5 1.51 603
Erlistoun 1.3 2.34 95 1.4 2.37 108 2.7 2.36 203 0.70
Total
Reserves
12.0 1.56 603 38.5 1.51 1,864 50.5 1.52 2,466

Notes – all reserves other than Garden Well and Erlistoun quoted at 30/6/10. Tonnes and Ounces are rounded, rounding errors may occur. MT = million tonnes, g/t = gold grade in grams per tonne, koz = thousands of ounces.

7

==> picture [65 x 21] intentionally omitted <==

APPENDIX 3 JORC COMPLIANT GOLD RESOURCES (INCLUSIVE OF RESERVES)

Measured Measured Indicated Indicated Inferred Total Resources Total Resources Total Resources
Cut-off
Grade
g/t
Project million
tonnes
grade
gold

million
grade
gold

million
grade
gold

million
grade
gold
g/t koz tonnes g/t koz tonnes g/t koz tonnes g/t koz
Garden Well 39.5 1.39 1,760 9.5 1.23 376 49.0 1.36 2,136 0.50
Moolart Well
Laterite 9.8 1.45 459 1.0 0.90 29 0.3 0.88 8 11.1 1.39 496 0.50
Oxide 1.2 1.85 71 3.9 1.52 192 6.7 1.45 314 11.9 1.51 577 0.80
Sulphide 2.4 1.37 108 2.4 1.37 108 1.00
Low Grade 4.0 0.42 54 13.9 0.47 212 48.5 0.50 774 66.4 0.49 1,040 0.30
Total Moolart Well 15.0 1.21 584 18.8 0.72 433 58.0 0.65 1,204 91.8 0.75 2,220
Erlistoun 2.3 1.92 143 3.0 1.88 179 5.3 1.90 321 0.50
Satellite Deposits
Dogbolter 0.9 2.91 87 0.9 2.91 87 1.00
Rosemont 14.7 1.72 815 14.7 1.72 815 1.00
KingJohn 0.7 3.18 72 0.7 3.18 72 1.00
Russells Find 0.4 3.84 55 0.4 3.84 55 1.00
Baneygo 0.8 1.70 43 0.8 1.70 43 0.50
Reichelts Find 0.1 3.69 17 0.1 3.69 17 1.00
Petra 0.4 3.12 42 0.4 3.12 42 2.00
Total Satellite
Deposits
0.1 3.69 17 17.9 1.94 1,114 18.0 1.95 1,131
Total 17.3 1.31 727 61.4 1.21 2,389 85.4 0.98 2,694 164.1 1.10 5,810
Regis share 5,788

Notes – all resources other than Garden Well and Erlistoun quoted at 30/6/10. Tonnes and Ounces are rounded, rounding errors may occur. MT = million tonnes, g/t = gold grade in grams per tonne, koz = thousands of ounces

8