A future with growth

2023 Annual General Meeting Jim Beyer – Managing Director and CEO 23 November 2023

==> picture [676 x 768] intentionally omitted <==

==> picture [36 x 30] intentionally omitted <==

Acknowledgment of country

The Board, Executive and Team at Regis Resources acknowledges the First Nations peoples - the Mantjintjarra Ngalia, Noongar, Spinifex and Wongatha peoples in Western Australia, and the Wiradjuri people in New South Wales - as the original inhabitants of the lands on which our Company currently operates and plans to develop new operations. We recognise their ongoing connections with land, waters, and community, and pay our . respects to elders past and present

==> picture [671 x 448] intentionally omitted <==

a future with growth

2

==> picture [36 x 30] intentionally omitted <==

Cautionary statement

This presentation contains only a brief overview of Regis Resources Limited and its associated entities (“Regis or RRL”) and their respective activities and operations. The contents of this presentation, including matters relating to the geology of Regis’ projects, may rely on various assumptions and subjective interpretations which it is not possible to detail in this presentation and which have not been subject to any independent verification.

This presentation contains a number of forward-looking statements that are subject to risk factors associated with gold exploration, mining and production businesses. It is believed that the forward looking statements in this presentation are reasonable based on information available as at the date of this presentation but known and unknown risks and uncertainties, and factors outside of Regis’ control, may cause the actual results, performance and achievements of Regis to differ materially from those expressed or implied in this presentation. These risk factors include, but are not limited to, changes in commodity prices, foreign exchange fluctuations and general economic conditions, increased costs and demand for production inputs, the speculative nature of exploration and project development, including the risks of obtaining necessary licenses and permits and diminishing quantities or grades of reserves, political and social risks, changes to the regulatory framework within which the Company operates or may in the future operate, environmental conditions including extreme weather conditions, recruitment and retention of personnel, industrial relations issues and litigation. Readers are cautioned not to place undue reliance on forward looking statements. No representation or warranty, express or implied is made as to the accuracy, currency or completeness of the information in this presentation, nor the future performance of Regis. Except as required by applicable law or regulations, Regis does not undertake to publicly update or review any forward-looking statements, whether as a result of new information or future events. Current and potential investors and shareholders should seek independent advice before making any investment decision in regard to Regis or its activities.

Mineral Resources, Ore Reserves and Exploration Results are extracted from the Mineral Resource and Ore Reserve Statement released to the ASX on 20 June 2023 and the Quarterly Activities Report released on 28 July 2023 (the Relevant ASX Announcements).

In each case, appropriate Competent Person’s consents were obtained for the release of that information in the Relevant ASX Announcements and those consents remain in place for subsequent releases by the Company of the same information in the same form and context, until the consent is withdrawn or replaced by a subsequent report and accompanying consent.

The Company confirms that it is not aware of any new information or data that materially affects the information included in the Relevant ASX Announcements and in each case the Production Targets, forecast financial information and estimates of Mineral Resources or Ore Reserves, that all material assumptions and technical parameters underpinning that information in the Relevant ASX Announcements, continue to apply and have not materially changed. The Company confirms that the form and context in which the Competent Person’s findings are presented have not been materially modified from the original ASX announcement.

This presentation uses mineral reserves and mineral resources classification terms that comply with reporting standards in Australia. These standards differ significantly from the requirements of the United States Securities and Exchange Commission that are applicable to domestic United States reporting companies and, therefore, are not comparable.

Past performance and pro-forma financial information given in this document, including in relation to upgrades to resources and reserves, is given for illustrative purposes only and should not be relied upon as (and is not) an indication of future performance, nor of Regis’ views on the Company’s future financial performance or condition. Investors should note that past performance of Regis, including the historical trading prices of its shares, cannot be relied upon as an indicator of and provides no guidance as to) Regis’ future performance, including the future trading price of its shares. The historical information included in this presentation is, or is based on, information that has previously been released to the market.

As noted above, an investment in Regis shares is subject to known and unknown risks, some of which are beyond the control of Regis. Regis does not guarantee any particular rate of return or the performance of the Company, nor does it guarantee the repayment of capital from Regis or any particular tax treatment.

The distribution of this presentation (including an electronic copy) outside of Australia (including the United States) may be restricted by law and any such restrictions should be observed. Any non-compliance with these restrictions may contravene applicable securities laws.

References to Tropicana are at 30% ownership unless otherwise noted.

ASX announcements are available on the Company’s website at www.regisresources.com.au

3

a future with growth

==> picture [36 x 30] intentionally omitted <==

Exploration Target

Exploration Target at Garden Well (noted on Slide 11) is extracted from ASX release “Mineral Resource and Ore Reserve Statement” dated 20 June 2023. The Exploration Target on the Garden Well underground deposit is based on drilling data up to 30 March 2023.

The Exploration Target is estimated to contain between 9Mt and 18Mt at a grade ranging between 2.3 g/t Au and 2.9 g/t Au across the deposit. The Exploration Target area includes the known Garden Well underground mineral system as well as potential down plunge depth extensions and open areas along strike, both North and South, with a 1,000m vertical extent from +350m RL to -650m RL.

Study work has identified that Garden Well underground is a potentially large mineralised system, with significant untested resource potential in the south direction and at depth. Known mineralisation patterns suggest continuity at depth, but significant resource risk and uncertainty remains. The potential quantity and grade of the Exploration Target is conceptual in nature and therefore is an approximation. There has been insufficient exploration to estimate a Mineral Resource and it is uncertain if further exploration will result in the estimation of a Mineral Resource. The Exploration Target has been prepared and reported in accordance with JORC Code 2012.

The Exploration Target has been reasonably defined based on a review of the Garden Well deposit using existing data, including drill hole databases, geophysical data sets and the 2022 Mineral Resource Estimate (MRE) data. The MRE included block models for the Garden Well open pit, Garden Well South underground and Garden Well Main underground resources. The drill data shown as gram-metre intervals was used to assist in defining the volumes used to quantify the Exploration Target. The number of drill holes and assays used to support the definition of Exploration Target comprises 672 drill holes and 96,750 assays.

The Exploration Target mineralised zones are constructed to form a volume for block model estimation with the same parameters as the Garden Well underground resources. Tonnage estimates are generated by applying bulk densities from the Garden Well deposit and underground mining shapes assume the same mining methods and cost structure as for the Garden Well South underground operation.

To mitigate the risk and further evaluate the Exploration Target, a high-level drill program has been proposed. The proposed drilling schedule has been designed with Stage 1 testing of the initial target area expected to be completed by December 2023. Further stages of drill testing will be planned based on the results of Stage 1.

ASX announcements are available on the Company’s website at www.regisresources.com.au

a future with growth

4

==> picture [36 x 30] intentionally omitted <==

Long life assets in tier 1 locations

Strong platform to launch disciplined growth

Darwin

10+ years McPhillamys

Duketon 6+ years

  • Stabilised operational performance

  • Substantial growth potential from underground mines

==> picture [19 x 12] intentionally omitted <==

----- Start of picture text -----

NT
----- End of picture text -----

QLD

  • One of Australia’s largest

  • undeveloped open-pittable gold deposits

  • Final key NSW approval received in March 2023

==> picture [429 x 258] intentionally omitted <==

----- Start of picture text -----

SA Brisbane
MCPHILLAMYS
NSW
Sydney
Adelaide
Canberra
VIC
Melbourne
TAS
Hobart
----- End of picture text -----

==> picture [250 x 80] intentionally omitted <==

----- Start of picture text -----

DUKETON
TROPICANA
Perth
----- End of picture text -----

==> picture [11 x 10] intentionally omitted <==

Tropicana 10+ years

  • 30% stake in a Tier-1 asset that consistently generates exceptional returns

Total Resources 7Moz Total Reserves 4Moz

  • Delivered ~$200M operating cash flow in FY23

  • Commercial production declared at Havana open pit

a future with growth

5

==> picture [36 x 30] intentionally omitted <==

FY23 highlights

A platform for improving cash flows and scale

==> picture [83 x 70] intentionally omitted <==

Record gold production of 458 koz

==> picture [127 x 149] intentionally omitted <==

Cash flow from operations of $455M

==> picture [65 x 65] intentionally omitted <==

Group LTIFR reduced to 0.9

==> picture [65 x 62] intentionally omitted <==

Cash and bullion of $243M*

==> picture [64 x 64] intentionally omitted <==

==> picture [23 x 32] intentionally omitted <==

AISC cost margin of $666/oz

==> picture [88 x 51] intentionally omitted <==

3[rd] biggest Australian gold miner on the ASX

a future with growth

6

  • Based on cash and bullion on hand of 13,371oz at $2,884/oz

==> picture [36 x 30] intentionally omitted <==

FY23 highlights

Continuing year on year progress

==> picture [29 x 30] intentionally omitted <==

==> picture [44 x 34] intentionally omitted <==

Commercial production at new mines

Carbon and diesel reduction

  • Commenced* commissioning of 9MW solar at Duketon

  • Garden Well South underground (Duketon)

  • Havana open pit (Tropicana)

  • Committed to 62MW renewable energy facility at Tropicana

==> picture [80 x 55] intentionally omitted <==

270% increase in rehabilitated land

Exploration Target established at Garden Well Main

  • Total gold at 0.8Moz to 1.3Moz • Total rehabilitated to date land increased to 12%

  • • Grade at 2.3g/t to 2.9g/t

21% female employees

  • 33% female Board members

  • Above industry average

==> picture [80 x 61] intentionally omitted <==

39% reduction in abstracted groundwater

  • Total abstracted groundwater of 1.65GL

a future with growth

7

*completed in August 2023

==> picture [36 x 30] intentionally omitted <==

Investment phase of producing assets is over…

…transitioning to the cash build phase with accompanying increase in return on investment (ROI)

Cash build phase will accelerate in FY25

Completed Jun Q FY23

==> picture [14 x 12] intentionally omitted <==

==> picture [14 x 11] intentionally omitted <==

Commercial production at Garden Well underground (Duketon) Commercial production at Havana open pit (Tropicana)

==> picture [36 x 88] intentionally omitted <==

At the end of FY24

==> picture [14 x 12] intentionally omitted <==

==> picture [14 x 11] intentionally omitted <==

FY25 will see the initiation of planned ramp down in waste movement (Tropicana) Release ~$170M/yr* of additional pre-tax cash flow through completion of the existing hedge book (Corporate)

==> picture [36 x 90] intentionally omitted <==

==> picture [19 x 16] intentionally omitted <==

8

a future with growth

  • at gold price of A$3,100/oz

==> picture [36 x 30] intentionally omitted <==

The pathway to 500koz per year with margin

A business with scale and multiple organic growth options

FY24 to FY26

==> picture [175 x 37] intentionally omitted <==

Target 500koz in FY27

==> picture [987 x 161] intentionally omitted <==

----- Start of picture text -----


Ramp up and optimise undergrounds

Duketon Grow Garden Well Reserve and expand production 200-250 [#] koz

Rolling Reserve replacement
----- End of picture text -----

==> picture [987 x 237] intentionally omitted <==

----- Start of picture text -----


Ramp up Havana open pit and reduce waste movement from FY25
Tropicana 135-150^koz

Commence access decline and deliver Feasibility Study

Final investment decision in FY24
McPhillamys 165-180koz

Construct and commission ready for first gold pour in FY27
----- End of picture text -----

==> picture [220 x 392] intentionally omitted <==

----- Start of picture text -----

Ongoing
delivery
required to
maintain rates
beyond FY27
----- End of picture text -----

500koz pa – a key target behind our objectives

9

a future with growth

Assumes no new open pit discovery

^ During open pit and underground phase

==> picture [36 x 30] intentionally omitted <==

Duketon has bright future underground

300koz+ producer where the transition underground is showing its potential

Garden Well in August 2021 - Then

==> picture [914 x 417] intentionally omitted <==

Garden Well underground mine commenced with portal and start of development

Surface drill holes indicated continuity of mineralisation in the north

a future with growth

10

==> picture [36 x 30] intentionally omitted <==

Duketon has bright future underground

300koz+ producer where the transition underground is showing its potential

Garden Well in August 2023 - Now

==> picture [930 x 420] intentionally omitted <==

Exploration decline into Garden Well Main complete

Exploration Target of 0.8 to 1.3Moz

established along with first Resource at the northern end

a future with growth

11

==> picture [36 x 30] intentionally omitted <==

Tropicana – a genuine tier 1 asset

Long term mine life with no end in sight

==> picture [923 x 361] intentionally omitted <==

----- Start of picture text -----

Tropicana
Havana
Boston Shaker
Havana South
Tropicana
Underground
Havana South Boston Shaker
22m @ 3.0
Underground Underground
Havana
(Conceptual) 3m @ 8.3
Underground
3m @ 4.4
(PFS)
25m @ 4.0 22m @ 4.0
----- End of picture text -----

==> picture [15 x 12] intentionally omitted <==

==> picture [15 x 12] intentionally omitted <==

==> picture [15 x 12] intentionally omitted <==

==> picture [15 x 12] intentionally omitted <==

==> picture [15 x 12] intentionally omitted <==

Strong cash generation over the life of the mine

Mine life targeted to 10+ years

Underground Reserves outpacing depletion

Decrease in material movement from FY25

Installing 62MW of clean energy (solar/wind/battery)

Development/Stopes by year

already mined 2023 Au (g/t) 2024 >10.0 2025 onwards 1.6 to 10.0

a future with growth

12

==> picture [36 x 30] intentionally omitted <==

McPhillamys – long life mine

Top tier project producing up to 200koz per year over 10+years in Australia

NSW state IPC determination received in March 2023

==> picture [15 x 12] intentionally omitted <==

Expecting response on Federal Section 10 shortly

==> picture [15 x 12] intentionally omitted <==

Final investment decision expected June quarter FY24

==> picture [15 x 11] intentionally omitted <==

==> picture [15 x 11] intentionally omitted <==

Design is a 7Mtpa throughput with a conventional Carbon-In-Leach flowsheet Located on the highly endowed Lachlan Fold belt which hosts over 150Moz of gold Grade gets better at depth Exploration to accelerate in FY24

==> picture [15 x 11] intentionally omitted <==

==> picture [481 x 574] intentionally omitted <==

13

a future with growth

==> picture [36 x 30] intentionally omitted <==

McPhillamys – just the start of the province

Further drilling could see more ounces added to the future mine plan

==> picture [433 x 433] intentionally omitted <==

Discovery Ridge has 390koz in Resource and with further drilling has the potential for Reserve additions

==> picture [364 x 433] intentionally omitted <==

Encouraging drill intercepts across the road at Kings Plains 85m @ 1g/t

a future with growth

14

==> picture [36 x 30] intentionally omitted <==

The investment case

==> picture [14 x 12] intentionally omitted <==

==> picture [15 x 12] intentionally omitted <==

==> picture [15 x 12] intentionally omitted <==

==> picture [15 x 12] intentionally omitted <==

==> picture [15 x 12] intentionally omitted <==

==> picture [15 x 12] intentionally omitted <==

==> picture [15 x 12] intentionally omitted <==

Strong financial platform with robust operating cash flows Scale and leverage to gold price Upcoming cash flow inflection point Hedge book removal by June 2024 Growth project with scale approaching delivery of feasibility study Exclusively in tier 1 locations

Trading discount will erode as cash builds and McPhillamys feasibility study is delivered

==> picture [36 x 36] intentionally omitted <==

==> picture [36 x 35] intentionally omitted <==

==> picture [36 x 36] intentionally omitted <==

==> picture [36 x 36] intentionally omitted <==

==> picture [36 x 36] intentionally omitted <==

==> picture [36 x 36] intentionally omitted <==

==> picture [36 x 36] intentionally omitted <==

==> picture [209 x 301] intentionally omitted <==

a future with growth

15

==> picture [56 x 44] intentionally omitted <==

==> picture [126 x 11] intentionally omitted <==

Further information Ben Goldbloom Head of Investor Relations + 61 8 9442 2200

==> picture [36 x 30] intentionally omitted <==

FY24 guidance

A disciplined production plan

==> picture [19 x 16] intentionally omitted <==

Operation Duketon Tropicana (30%) Group
Production (koz) 280 – 305 135 – 150 415 – 455
AISC ($/oz) 2,050 - 2,360 1,800 - 2,120 1,995 - 2,315
Growth Capital ($M) 85 - 95 <5 85 – 95
Exploration ($M) 48 – 55
McPhillamys ($M) 22 - 25

==> picture [15 x 12] intentionally omitted <==

==> picture [15 x 12] intentionally omitted <==

==> picture [15 x 12] intentionally omitted <==

==> picture [15 x 12] intentionally omitted <==

==> picture [15 x 12] intentionally omitted <==

Focus for profitable ounces AISC includes $200/oz of non-cash stockpile draw Material reduction in growth capital in FY24 Duketon undergrounds to accelerate as open pits deplete

Tropicana open pit to accelerate ore production

a future with growth

17

==> picture [36 x 30] intentionally omitted <==

Reserve Table

ORE RESERVES as at 31 December 2022(Regis Attributable) ORE RESERVES as at 31 December 2022(Regis Attributable) ORE RESERVES as at 31 December 2022(Regis Attributable) ORE RESERVES as at 31 December 2022(Regis Attributable) ORE RESERVES as at 31 December 2022(Regis Attributable) ORE RESERVES as at 31 December 2022(Regis Attributable)
Gold Proved Probable Total Ore Reserve Competent Person3
Project1 Equity Type Cut-Off
(g/t)2
Tonnes
(Mt)
Gold
Grade
(g/t)
Gold Metal
(koz)
Tonnes
(Mt)
Gold
Grade
(g/t)
Gold Metal
(koz)
Tonnes
(Mt)
Gold
Grade
(g/t)
Gold Metal
(koz)
DNO ROM Ore Reserves Open-Pit ROM 0.6 0.1 1.0 <10 2 1.1 80 2 1.1 80 B
DNO LG Ore Reserves Open-Pit LG 0.3 2 0.3 20 0.3 0.5 <10 2 0.4 30 B
Duketon North Deposits
Sub Total
2
0.4
30
3
1.1
90
5
0.7
110
DSO ROM Ore Reserves4 Open-Pit ROM 0.5 9 1 200 7 1.3 290 16 0.9 490 B
DSO ROM Ore Reserves Underground ROM 1.9 - - - 4 2.5 330 4 2.5 330 C
DSO LG Ore Reserves Open-Pit LG 0.3 1 0.4 10 0.2 0.4 <10 1 0.4 20 B
Duketon South Deposits
Sub Total
10
1
210
11
1.7
620
21
1.2
840
Duketon Total 100% Sub Total 12 0.6 230 14 1.6 710 26 1.1 950
Tropicana ROM Ore Reserves5 Open-Pit ROM 0.7 1 1.8 50 7 1.9 410 7 1.9 460 F
Tropicana ROM Ore Reserves5
Tropicana ROM Ore Reserves5
Underground
Stockpiles
ROM
ROM
2.5
0.6
1
2
2.9 110
60
-
-
- 0
0
1
2
3.0 110
60
G
F
0.8 - 0.8
Tropicana Total 30% Sub Total 4 1.6 220 7 1.9 410 11 1.8 630
McPhillamys 100% Open-Pit ROM 0.4 - - - 61 1.0 2,020 61 1.0 2,020 B
REGIS TOTAL GRAND TOTAL 16 0.9 450 81 1.2 3,150 98 1.1 3,600

Notes

The above data has been rounded to the nearest 1,000,000 tonnes, 0.1 g/t gold grade and 10,000 ounces. Errors of summation may occur due to rounding.

  1. Ore Reserves are reported inclusive of associated Stockpiles except for Tropicana.

  2. Cutoff grades vary according to oxidation and lithology domains. Listed cut-offs are the weighted average of these various cut-offs grades for that project classification. 3. Refer to Group Competent Person Notes.

  3. Regis owns 70% of the King John project - part of the DSO operations. This project has a total Ore Reserve of 20 koz at 100%. Only the 70% Regis share has been included in the above table. 5. Regis 30% holding in Tropicana. Tropicana previously reported in ASX release "Mineral Resource and Ore Reserve Update at Tropicana" dated 23 February 2023.

a future with growth

18

==> picture [36 x 30] intentionally omitted <==

Resource Table

MINERAL RESOURCES as at 31 December 2022(Regis Attributable) MINERAL RESOURCES as at 31 December 2022(Regis Attributable) MINERAL RESOURCES as at 31 December 2022(Regis Attributable) MINERAL RESOURCES as at 31 December 2022(Regis Attributable) MINERAL RESOURCES as at 31 December 2022(Regis Attributable) MINERAL RESOURCES as at 31 December 2022(Regis Attributable) MINERAL RESOURCES as at 31 December 2022(Regis Attributable) MINERAL RESOURCES as at 31 December 2022(Regis Attributable) MINERAL RESOURCES as at 31 December 2022(Regis Attributable) MINERAL RESOURCES as at 31 December 2022(Regis Attributable) MINERAL RESOURCES as at 31 December 2022(Regis Attributable) MINERAL RESOURCES as at 31 December 2022(Regis Attributable) MINERAL RESOURCES as at 31 December 2022(Regis Attributable) MINERAL RESOURCES as at 31 December 2022(Regis Attributable) MINERAL RESOURCES as at 31 December 2022(Regis Attributable) MINERAL RESOURCES as at 31 December 2022(Regis Attributable) MINERAL RESOURCES as at 31 December 2022(Regis Attributable)
Gold Measured Indicated Inferred Total Resource Competent Person2
Project1 Equity Type Cut-Off
(g/t)
Tonnes
(Mt)
Gold
Grade
(g/t)
Gold
Metal
(koz)
Tonnes
(Mt)
Gold
Grade
(g/t)
Gold
Metal
(koz)
Tonnes
(Mt)
Gold
Grade
(g/t)
Gold
Metal
(koz)
Tonnes
(Mt)
Gold
Grade
(g/t)
Gold
Metal
(koz)
Duketon North Open Pit3 Open-Pit 0.4 4 0.5 60 15 1.0 480 4 0.9 120 23 0.9 660 A/B
Duketon North Underground4 Underground 1.5 - - - - - - 1 2.0 60 1 2.0 60 A
Duketon North Deposits Sub Total 4 0.5 60 15 1.0 480 5 1.1 180 24 0.9 720
Duketon South Open Pit5,6 Open-Pit 0.4 15 0.6 280 15 1.2 580 3 1.3 120 33 0.9 970 A
Duketon South Underground7 Underground 1.5/1.7/1.8 2 3.4 240 2 2.6 210 4 2.4 320 9 2.7 770 A
Duketon South Deposits Sub Total 17 0.9 520 17 1.4 790 7 1.9 440 41 1.3 1,740
Duketon Total 100% Total 21 0.8 580 32 1.2 1,260 12 1.6 610 65 1.2 2,460
Tropicana Open Pit8 Open-Pit 0.3/0.4 1 1.5 50 9 1.7 460 0.0 0.7 0 10 1.6 510 E
Tropicana Underground8 Underground 1.6 4 2.7 340 2 2.8 130 10 2.4 760 15 2.5 1,230 E
Tropicana Stockpiles8 Stockpiles 7 0.6 140 - - - - - - 7 0.6 140 E
Tropicana 30% Sub Total 12 1.3 530 10 1.8 590 10 2.4 760 32 1.8 1,880
McPhillamys Open-Pit 0.4 - - - 69 1.0 2280 1 0.6 10 70 1.0 2290 A
DiscoveryRidge Open-Pit 0.4 - - - 8 1.3 330 2 0.8 60 10 1.2 390 A
NSW Deposits 100% Sub Total - - - 77 1.1 2,610 3 0.8 70 80 1.0 2,680
REGIS TOTAL GRAND TOTAL 34 1.0 1,110 119 1.2 4,470 25 1.8 1,440 178 1.2 7,020

Notes

The above data has been rounded to the nearest 1,000,000 tonnes, 0.1 g/t gold grade and 10,000 ounces. Errors of summation may occur due to rounding. All Mineral Resources are reported inclusive of Ore Reserves to JORC Code 2012 unless otherwise noted.

  1. Mineral Resources and Ore Reserves are reported inclusive of Ore Stockpiles.

  2. Refer to Group Competent Person Notes.

  3. Open Pit Mineral Resources for Duketon North are Moolart Well, Gloster, Dogbolter-Coopers, Petra, Commonwealth, Ventnor and Terminator.

  4. Underground Duketon North Mineral Resource is at Gloster. Resource reported within MSO shells at an economic cutoff of 1.5g/t.

  5. Open Pit Mineral Resources for Duketon South are Garden Well, Rosmont Open Pit, Toohey's Well, Baneygo, Erlistoun, Beamish, Reichelt's Find, Russell's Find, King John, King of Creation and Lancefield North.

  6. King John reported at 70% ownership.

  7. Underground Duketon South Mineral Resources are Rosemont Underground, Garden Well Underground, Toohey's Well, and Ben Hur. All resources reported within MSO shells. Garden Well Underground reported at an Economic cutoff of 1.8g/t, Rosemont Underground reported at an economic cutoff of 1.7g/t, Ben Hur, and Toohey's Well reported at an economic cutoff of 1.5g/t.

  8. Regis 30% holding in Tropicana. Tropicana previously reported in ASX release "Mineral Resource and Ore Reserve Update at Tropicana" dated 23 February 2023.

a future with growth