The Listing Manager Australian Securities Exchange Level 4 20 Bridge Street SYDNEY NSW 2000
June 10, 2014
Monthly Production Report for May 2014
The production schedule at Rubicon and Hornet was re‐optimized, using some of the resources from Raleigh, to minimize the production shortfall at Raleigh due to the February earthquake. Rehabilitation at Raleigh is proceeding and production is now expected to recommence before the end of June.
End of Month Status Raleigh – Rehabilitation
==> picture [451 x 193] intentionally omitted <==
Rubicon – Development and Production
==> picture [451 x 139] intentionally omitted <==
(green indicates new developments)
| MINE PRODUCTION | |||
| **Raleigh U/G ** | **Rubicon U/G ** | ||
| Ore | t | 139 | 40,315 |
| Grade | g/t Au | 8.73 | 11.57 |
| Gold | oz | 39 | 14,990 |
| Rand’s Entitlement | % | 12.50 | 12.25 |
| MINE OPERATING COSTS | |||||||||
| Unit Cost | Raleigh | Rubicon | |||||||
| $/t ore | 0 | 88 | |||||||
| $/ozgold | 0 | 236 | |||||||
| MINE DEVELOPMENT | |||||||||
| **Raleigh ** | Rubicon | ||||||||
| Capital | Decline | m | 0.0 | 226.8 | |||||
| Secondary | m | 0.0 | 145.7 | ||||||
| Operating | Waste | m | 0.0 | 0.0 | |||||
| Ore | m | 0.0 | 118.9 | ||||||
| Past Fill | m | 0.0 | 75.0 | ||||||
| End of monthposition | RL(m) | below surface(m) | |||||||
| Raleigh Decline | bottom | 5618 | 727 | ||||||
| Rubicon Decline | bottom | 6032 | 311 | ||||||
| Hornet Incline | top | 6244 | 99 | ||||||
| Hornet Decline | bottom | 5926 | 417 | ||||||
| Pegasus Access | bottom | 6166 | 177 |
| End of month EKJV STOCKPILES | End of month EKJV STOCKPILES | ||
|---|---|---|---|
| ROMpad | Ore Source | Ore | Grade |
| t | g/t Au | ||
| **Raleigh ** | Raleigh | 140 | 8.7 |
| Rubicon | Rubicon | 19,600 | 14.1 |
| Kanowna Belle | Rubicon | 22,200 | 13.6 |
Toll Processing
During the month 45,442 tonnes (wet) of Rubicon ore were hauled to the Kanowna Belle Plant and 38,380 tonnes of EKJV ore were processed.
| Bullion accredited to RAND and TRIBUNE Accounts from Kanowna Belle | |||
| Month | Gold(oz) | Silver(oz) | Rand’s sharegold |
| May 14 | 8,338.166 | 1,993.796 | 2,084.541 |
| April 14 | 6,699.230 | 1,499.492 | 1,674.807 |