RAND MINING LIMITED — Interim / Quarterly Report 2011
Jul 27, 2011
65721_rns_2011-07-27_812fd7de-9593-4c9a-9e83-76576b78cdc8.pdf
Interim / Quarterly Report
Open in viewerOpens in your device viewer
==> picture [595 x 94] intentionally omitted <==
July 28, 2011
The Listing Manager Australian Securities Exchange Level 4 20 Bridge Street SYDNEY NSW 2000
Quarterly Report for June 2011
Highlights
-
During the quarter, 10,774 tonnes of Raleigh ore were processed and 8,391 oz of gold and 1,326 oz of silver were credited to Rand and Tribune Bullion Accounts. (Rand’s share is 25%)
-
At the end of the quarter
approximately 11,300 tonnes of Raleigh ore at an estimated grade of 14.6 g/t remain as a Bed Blend Stockpile on the ROM pad at the Raleigh Mine (Rand’s entitlement is 12.5%)
no Raleigh ore remains on the ROM pad at the Moonbeam Mine (Rand’s share is 25%)
approximately 29,900 tonnes of Raleigh ore at an estimated grade of 14.2 g/t remains on the ROM pad at the Greenfields Plant (Rand’s share is 25%)
no gold was in transit between the Greenfields Plant and the Perth Mint (Rand’s share is 25%)
==> picture [595 x 94] intentionally omitted <==
GEOLOGY AND MINING
EAST KUNDANA JOINT VENTURE
Raleigh Underground Mine Production
Stope production from the 6202, 6034, 6017, 6000, 5983, 5966, 5949, 5932, 5915, 5898, 5881, 5864, 5847, 5830, 5812, 5795, 5778, 5761, 5744, 5722 and 5705 levels continued during the quarter.
Contained gold in stope development and stope ore mined during the quarter, estimated by grade control face chip sampling, is tabulated below:
| quarter. Contained gold in stope development and stope ore mined during the quarter, estimated grade control face chip sampling, is tabulated below: |
quarter. Contained gold in stope development and stope ore mined during the quarter, estimated grade control face chip sampling, is tabulated below: |
quarter. Contained gold in stope development and stope ore mined during the quarter, estimated grade control face chip sampling, is tabulated below: |
quarter. Contained gold in stope development and stope ore mined during the quarter, estimated grade control face chip sampling, is tabulated below: |
|---|---|---|---|
| RALEIGH UNDERGROUND GRADE CONTROL ESTIMATES | |||
| Month | Tonnes | Grade | Ounces |
| t | g/t | troy oz | |
| April | 19,068 | 14.82 | 9,087 |
| May | 24,727 | 14.56 | 11,575 |
| June | 22,163 | 14.57 | 10,385 |
| June 11Q | 65,958 | 14.6 | 31,047 |
| March 11Q | 74,661 | 13.7 | 33,075 |
Rand’s Entitlements (12.5%)
| June 11Q | 8,245 | 14.6 | 3,881 |
|---|---|---|---|
| March 11Q | 27,998 | 13.7 | 12,403 |
Approximately half of the ore mined in June was hauled in June. 11,300 tonnes remains as a Bed Blend Stockpile on the ROM pad at the Raleigh Mine and will be hauled in early July.
Raleigh Underground Mine Development
At the end of the quarter, the bottom of the Raleigh Decline is at 5619 m RL, 726 m from the surface.
Development progressed on the 5671, 5654, 5631 and 5614 levels.
| RALEIGH UNDERGROUND DEVELOPMENT | |||||
| Month | Capital | Operating | |||
| Decline (m) |
Secondary (m) |
Waste (m) |
Ore (m) |
Paste Fill (m) |
|
| April | 9.3 | 75.9 | 74.0 | 19.4 | 55.0 |
| May | 0.0 | 44.0 | 66.6 | 109.3 | 51.5 |
| June | 0.0 | 0.0 | 51.6 | 54.3 | 60.0 |
| June 11Q | 9.3 | 119.9 | 192.2 | 183.0 | 166.5 |
| March 11Q | 198.3 | 9.7 | 68.5 | 302.1 | 140.0 |
The diagrams below show the status of the mine at the end of each month of the quarter.
==> picture [266 x 11] intentionally omitted <==
----- Start of picture text -----
April 11 Red indicates new development at Raleigh
----- End of picture text -----
==> picture [451 x 206] intentionally omitted <==
May 11 Green indicates new development at Raleigh
==> picture [451 x 202] intentionally omitted <==
June 11 Pink indicates new development at Raleigh
==> picture [451 x 219] intentionally omitted <==
Mine operating costs incurred during the June 2011 Quarter were $204 per tonne mined or $434 per ounce mined compared with the March 2011 Quarter costs of $177 and $400 respectively.
Rubicon Underground Mine Development
The first portal cut of the Decline for the Rubicon Underground Mine was completed on February 27, 2011. The in‐pit portal access is at 6245 m RL, 100 m below the top of the pit.
At the end of the quarter, the bottom of the Rubicon Decline is at 6190 m RL, 155 m from the surface and the bottom of the crosscut to Hornet is at 6189 m RL, 156 m from the surface.
| RUBICON UNDERGROUND DEVELOPMENT | |||||
| Month | Capital | Operating | |||
| Decline (m) |
Secondary (m) |
Waste (m) |
Ore (m) |
Paste Fill (m) |
|
| April | 135.1 | 90.9 | 0.0 | 0.0 | 0.0 |
| May | 171.3 | 102.7 | 0.0 | 0.0 | 0.0 |
| June | 183.7 | 83.5 | 0.0 | 0.0 | 0.0 |
| June 11Q | 490.1 | 277.1 | 0.0 | 0.0 | 0.0 |
| March 11Q | 142.8 | 63.5 | 0.0 | 0.0 | 0.0 |
The diagram below shows the status of the mine at the end of the quarter.
June 11 Green indicates new development at Rubicon
==> picture [431 x 216] intentionally omitted <==
Toll Processing
During the quarter, 32,100 tonnes (wet) of Raleigh ore were hauled to the Greenfields Plant. The eighteenth toll treatment campaign at the Greenfields Plant, which started on March 23, 2011, finished on April 6, 2011. During the quarter, 10,774 tonnes of Raleigh ore were processed. At the end of the quarter, approximately 29,900 tonnes of Raleigh ore remains on the ROM pad at the Greenfields Plant.
| Bullion accredited to RAND and | Bullion accredited to RAND and | Bullion accredited to RAND and | TRIBUNE |
|---|---|---|---|
| Quarter | Gold(oz) | Silver(oz) | Rand’s sharegold |
| June 11 | 8,391.965 | 1,316.760 | 2,097.989 |
| March 11 | 25,283.925 | 3,349.075 | 6,320.979 |
EKJV Exploration
Three drilling programmes have been recently approved:
Raleigh – extensional drilling at the south end of the ore‐body and final ultra‐deep holes to test down dip extension of the main ore‐body,
Rubicon – drilling designed to progress material below the Rubicon pit from inferred to indicated category,
Hornet – drilling to test for mineralisation along the Mary Fault.
OTHER EXPLORATION
Wongan Hills (Rand’s Interest 100%)
A drilling programme to test previously reported anomalies has been planned and will start when a drill rig is available.
Seven Mile Hill Joint Venture (Rand’s Interest 50%)
Discussions to farm out the Seven Mile Hill tenements are continuing.
CORPORATE
On 23 Dec 2010, Rand announce that it had entered into a conditional option agreement with Resource Capital Limited ( RCL ) (a company incorporated in the Republic of the Seychelles) and Iron Resources Limited ( IRL ) (a company incorporated in the Republic of Ghana) ( Option Agreement ).
Under the terms and conditions of the original Option Agreement, Rand had acquired a six month option ( Option ) to acquire all of the issued share capital in IRL from RCL. IRL is the registered holder of an iron ore mineral exploration license over a 600km² area which encompasses the Gbi Range located in Northern‐Central Liberia, West Africa ( Project Area ).
The Project Area contains an extensive sequence of iron formations located within the emerging Liberian‐Guinean iron ore province, host to several of West Africa’s most important iron ore deposits, including the world class Simandou deposit.
Rand’s due diligence with regard to the Transaction is continuing and the Company has been granted a 3 month extension of term to complete this exercise.