AI assistant
RAND MINING LIMITED — Interim / Quarterly Report 2004
Apr 28, 2004
65721_rns_2004-04-28_cd292f64-a568-43e7-962d-1de3ca2c1f47.pdf
Interim / Quarterly Report
Open in viewerOpens in your device viewer

29 April 2004
The Listing Manager Australian Stock Exchange Level $10$ 20 Bond Street SYDNEY
Quarterly Report for Period ending 31 March 2004 Geology and mining
Highlights
- $\bullet$ EKJV recovered 24,974 ounces of gold during the Quarter.
- EKJV recovered a total of 247,653 ounces of gold.
- Production from the Raleigh pit was completed in January 2004.
- Processing EKJV ore at Kundana ceased in February 2004.
- Negotiations to develop the Raleigh underground mine continue.
- Oretek embarks on identifying projects to demonstrate commercial viability of its technology.
REVIEW OF OPERATIONS
The East Kundana Joint Venture in which your company has a 12.25% interest ceased processing at the Kundana plant ore sourced from the Raleigh and Rubicon open cut pits on 12 February 2004.
During the March 2004 Quarter the EKJV recovered 24,974 ounces of gold. A total of 32,594 ounces of gold and 4,624 ounces of silver bullion were delivered to the EKJV.
Negotiations to finance the development of the Raleigh underground operation are reaching a final stage. Processing the Raleigh ore at another facility now that the Kundana plant has been decommissioned by Placer Dome Asia Pacific have been agreed subject to final negotiation of joint venture and financing matters.
The development of the EKJV resources continues to be the main focus of the company.
EAST KUNDANA JOINT VENTURE
Mining operations were completed to design at the Raleigh open cut pit.
Dewatering of the Raleigh and Rubicon pits is being maintained in preparation for commencement of the underground operations.
| Month | Tonnes | Estimated Ounces | Grade $(g/t)$ | |
|---|---|---|---|---|
| January 04 | Raleigh | 18,869 | 17,362 | 28.6 |
| Rubicon | U | U | ||
| February 04 | Raleigh | 0 | ${}$ | |
| Rubicon | 0 | € | ||
| March 04 | Raleigh | 0 | ||
| Rubicon | 0 | |||
| Total for March 04 Quarter | Combined | 18,869 | 17,362 | 28.6 |
| Total for December 03 Quarter | Combined | 83,451 | 30,030 | 11.2 |
| Total project to date | Combined | 748,705 | 237,192 | 9.8 |
EKJV mine production for March 04 Ouarter
Raleigh
- Raleigh stage 3 pit mining was completed in January to its designed depth of 118 metres below surface.
- Production for the quarter totalled 18,869 dry tonnes at 29 $g/t$ containing 17,362 ounces compared to 28,300 dry tonnes at 29g/t Au containing 26,723 ounces for the previous quarter.
The performance of mining production estimates compared to reserves is:
| Raleigh Pit 100% EKJV | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|
| Production | Reserve | % Variation | ||||||||
| Fonnes | Grade | Gold | Tonnes | Grade | Gold | tonnes | g/t | ounces | ||
| tonnes | g/t | ounces | tonnes | g/t | ounces | $\%$ | % | $\%$ | ||
| March 04 Ouarter | 18,869. | 28.6 | 17,362 | 10,412 | 49.7 | 16,649 | $+81$ | $-42$ | $+4$ | |
| December 03 Quarter | 28,300 | 29.4 | 26,723 | 19.306 | 47.5 | 29,503 | $+46$ | $-38$ | -9 | |
| July 03 to March 04 | 67,732 | 22.6 | 49.183 | 44,079 | 36.5 | 51,788 | $+54$ | $-38$ | $-5$ | |
| Project To 31 March 04 | 368,775 | 11.6 | 137.341 | 171.395 | 18.1 | 110,486 | $+115$ | $-36$ | $+24$ |
Rubicon
Mining was completed in the December 2003 Quarter to its designed depth of 132 $\bullet$ metres below surface.
The performance of mining production estimates compared to reserves is:
| Rubicon Pit 100% EKJV | |||||||||
|---|---|---|---|---|---|---|---|---|---|
| Production | Reserve | Variation | |||||||
| Tonnes | Grade | Gold oz | Tonnes | Grade | Gold oz | tonnes | g/t | ounces | |
| tonnes | g/t | Ounces | tonnes | g/t | ounces | $\frac{0}{0}$ | $\%$ | $\%$ | |
| March 04 Ouarter | |||||||||
| December 03 Ouarter | 43.239 | 10.3 | 14.318 | 26.343 | 14.9 | 12.587 | $+64$ | $-31$ | $+14$ |
| July 03 to 30 Dec $03$ | 106.128 | l 1.5 | 39,250 | 61.142 | 14.0 | 27.474 | $+74$ | $-18$ | $+43$ |
| Project To 31 Dec 03 | 379.930 | 8.2 | 99.851 | 231,685 | 9.1 | 67.380 | $+64$ | $-10$ | $+48$ |
MINERAL PROCESSING
- The EKJV project has recovered 247,653 ounces of gold since commencement of $\bullet$ processing on $15^{th}$ May 2002.
- 45,937 dry tonnes of ore at 17.5g/t was processed for the EKJV at the Kundana Mill during the quarter compared to $108,330$ dry tonnes at $16.9g/t$ the previous quarter. A total of 886,344 dry tonnes at 9.0g/t has been processed project to date at an overall 96.7% recovery and 98.6% mill availability.
- Gold recovered for the quarter was 45,937 ounces at a 96.5% recovery compared to 57,537 ounces at a 97.5% recovery for the previous quarter.
- The processing campaign ceased on 12 February 2004.
- Gravity recoverable gold from fresh ore has decreased to 51% down from 57% in the March Quarter 2004. Gravity gold recovered for the project averaged 52%.
| ERJ V goru bumon produced | ||||||||
|---|---|---|---|---|---|---|---|---|
| Period | Ore | Gold | Bullion | Calc Head | Total | |||
| processed | Recovered | outturn | grade (g/t) | recovery | ||||
| (dry tonnes) | (oz) | (oz) | (%) | |||||
| Jan 04 | 35,384 | 19,650 | 24,412 | 17.92 | 96.4 | |||
| Feb 04 | 10,553 | 5,3424 | 8,174 | 16.19 | 96.9 | |||
| Mar 04 | 0 | NA | NA | |||||
| Quarter | 45,937 | 24,974 | 32,594 | 17.52 | 96.5 | |||
| Fiscal YTD | 298,939 | 112,588 | 118,073 | 12.05 | 97.2 | |||
| PTD | 886,344 | 247,653 | 246,734 | 8.99 | 96.7 |
EK IV gold bullion produced
NA not applicable.
A total of 5,708 tonnes at 5 $g/t$ of mill scats containing 919 ounces of gold remain to be sold.
Project Development
The Raleigh underground and Hornet open cut stage 1 developments are waiting for the conclusion to the joint venture matters between the parties to be finalised.
The status of projects under study for development is:
| Project | Status |
|---|---|
| Raleigh Open Cut Pit | Mining and Processing completed |
| Rubicon Open Cut Pit | Mining and Processing completed |
| Raleigh Underground | Feasibility Study |
| Hornet Stage 1 Open Cut Pit | Feasibility Study |
| Hornet Stage 2 Open Cut Pit | Scoping Study |
| Hornet Underground | Pre-feasibility Study |
| Rubicon Underground Stage 1 | Pre-feasibility Study |
| Pegasus Open Cut Pit | Scoping Study |
| Pegasus Underground | Pre-feasibility Study |
EXPLORATION
Resource infill drilling was performed in the Hornet open cut stage 2 development to delineate mineralisation in depleted zones within the transitional zone.
The significant intersections within the depleted zone are:
| Hole | Hole Depth | Downhole Interval |
Grade | Target | |||
|---|---|---|---|---|---|---|---|
| From | To | ||||||
| (m) | (m) | (m) | g/t | ||||
| HOP150 | 48 | 62 | 14 | 1.24 | K 2 | ||
| HOP150 | 69 | 71 | $\overline{2}$ | 2.54 | K 2 | ||
| HOP151 | 68 | 75 | 7 | 12.02 | K2 | ||
| HOP152 | 59 | 64 | 5 | 5.62 | K2 | ||
| HOP153 | 68 | 73 | 5 | 9.18 | K 2 | ||
| HOP154 | 70 | 72 | $\overline{2}$ | 1.6 | K 2 | ||
| HOP154 | 75 | 77 | 2 | 31.32 | K 2 | ||
| HOP155 | 59 | 62 | 3 | 7.36 | K 2 | ||
| HOP156 | 60 | 66 | 6 | 6.86 | K 2 | ||
| HOP157 | 57 | 61 | 4 | 9.3 | K 2 | ||
| HOP158 | 64 | 70 | 6 | 7.09 | K 2 |
Drilling statistics
| Period | Aircore | Reverse circulation | Diamond | |||
|---|---|---|---|---|---|---|
| No. holes | Metres | No. Holes | Metres | No. Holes | Metres | |
| Jan 04 | 782 | |||||
| Feb 04 | ||||||
| Mar 04 | ||||||
| Mar Qtr | ||||||
| Yr to date | 20 | 926 | 99 | 9,257 | 40 | 7,422 |
Seven Mile Hill Joint Venture (50%)
A total of 42 holes drilled to blade refusal for 1,954m of drilling. A total of 506 four metre composites were submitted for gold determination by aqua regia/ASS. Composite samples returning values greater than 0.1g/t Au considered anomalous were re-sampled in 1m intervals and submitted for gold assay by fire assay/ASS.
All results have now been received from this drilling programme. The following table lists the significant ( $>1g/t$ Au) results.
| Hole | Northing | Easting | From | To | М | $g/t$ Au |
|---|---|---|---|---|---|---|
| BAC106 | 6582200 | 349350 | 37 | 38 | 1 | 5.23 |
| 44 | 46 EOH | $\overline{2}$ | 1.28 | |||
| BAC107 | 6582200 | 349300 | 47 | 48 | 1 | 1.17 |
| 51 | 52 | $\mathbf{1}$ | 1.48 | |||
| BAC115 | 6582400 | 349400 | 32 | 33 | 1 | 1.36 |
| BAC116 | 6582400 | 349350 | 28 | 35 | 7 | 1.22 |
| BAC119 | 6582600 | 349350 | 35 | 36 | 1 | 2.63 |
| 47 | 48 | 1 | 2.22 | |||
| BAC122 | 6582600 | 349200 | 37 | 38 | 1 | 1.19 |
| BAC123 | 6582600 | 349150 | 52 | 53 | 1 | 2.11 |
| BAC126 | 6582600 | 348900 | 44 | 45 | 1 | 1.70 |
| BAC132 | 6582800 | 348700 | 49 | 50 | 1 | 1.04 |
| BAC133 | 6583000 | 348725 | 32 | 35 | 3 | 1.84 |
| 51 | 52 | 1 | 2.21 | |||
| 56 | 57 | 1 | 1.10 | |||
| BAC134 | 6583000 | 348625 | 36 | 39 | 3 | 1.01 |
| 52 | 53 | 1 | 1.60 | |||
| BAC135 | 6582200 | 349343 | 50 | 51 EOH | 1 | 1.05 |
| BAC142 | 6582800 | 349050 | 17 | 21 | $\overline{4}$ | 1.06 |
| 25 | 26 | 1 | 1.81 | |||
| 32 | 33 EOH | 1 | 1.66 |
Note EOH means the hole ended in mineralisation.
Numerous other holes intersected values ranging between 0.5-0.99g/t Au, particularly near the ends of the holes.
Two zones of mineralisation at or near to the saprolite/bedrock interface, approximately 500m apart have been defined on either side of a felsic porphyry intrusive, similar to mineralisation immediately to the north at Binduli. The known mineralisation is associated with gently west dipping zones of quartz stockwork, within sheared and sericite altered felsic volcaniclastics.
Larkinville
Field work was performed in preparation of an exploration drilling programme.
Oretek Joint Venture (20% Interest in patents)
In order to more rapidly advance the Oretek technologies the Company has embarked upon a program of project identification, to enable the technologies to be demonstrated on a commercial scale. Confidential negotiations are being conducted with various parties to locate a suitable orebody. Joint Venture discussions will then commence.
With this in mind, the research work being conducted as part of the ARC Linkage copper cyanide project is being expanded to enable its findings to be incorporated into a commercial copper or copper/gold treatment project. The work is being conducted under the direction of Drs. Breuer and Jeffrey, Department of Chemical Engineering, Monash University.
Yours faithfully
Dr W Jay Director
Appendix 5B
Mining exploration entity quarterly report
| Name of entity | |
|---|---|
RAND MINING NL
ACN or ARBN
004 669 658
Quarter ended (current quarter)
31 March 2004
Consolidated statement of cash flows
| Cash flows related to operating activities | Current quarter $$A=000$ |
Year to date (9 months) $$A=000$ |
|
|---|---|---|---|
| 1.1 | Receipts from product sales and related debtors | 2,329 | 8,207 |
| 1.2 | Payments for exploration and evaluation (a) (b) development (c) production administration (note 2) (d) |
(219) (4) (999) (187) |
(764) (57) (2,493) (707) |
| 1.3 | Dividends received | ||
| 1.4 | Interest and other items of a similar nature received | 4 | 16 |
| 1.5 | Interest and other costs of finance paid | ||
| 1,6 | Taxes paid | ||
| 1,7 | Re-imbursement of Exploration Costs | ||
| Net operating cash flows | 924 | 4,202 | |
| Cash flows related to investing activities | |||
| 1.8 1.9 |
Payment for purchase of: prospects (a) equity investments (b) - other fixed assets (c) Proceeds from sale of: (a) prospects |
(579) (10) |
(828) (12) |
| (b) equity investments other fixed assets (c) |
|||
| 1.10 | Loans to other entities (note 3) | (21) | (187) |
| 1.11 | Loans repaid by other entities | ||
| 1.12 | Other (provide details if material) | ||
| Net investing cash flows | (610) | (1,027) | |
| 1,13 | Total operating and investing cash flows (carried forward) | 314 | 3,175 |
| 1.13 | Total operating and investing cash flows (brought forward) | 314 | 3,175 |
|---|---|---|---|
| Cash flows related to financing activities | |||
| 1.14 | Proceeds from issues of shares, options, etc. | ||
| 1.15 | Proceeds from sale of forfeited shares | ||
| 1.16 | Proceeds from borrowings | 413 | 826 |
| 1.17 | Repayment of borrowings | ||
| 1.18 | Dividends paid | ||
| 1.19 | Commissions on capital raising | ||
| Net financing cash flows | 413 | 826 | |
| Net increase (decrease) in cash held | 727 | 4,001 | |
| 1.20 | Cash at beginning of quarter/year to date | 5,856 | 2,582 |
| 1.21 | Exchange rate adjustment to 19 | ||
| 1.22 | Cash at end of quarter | 6,583 | 6,583 |
Non-cash financing and investing activities
- $2.1$ Details of financing and investing transactions which have had a material effect on consolidated assets and liabilities but did not involve cash flows $N/A$
- $2.2$ Details of outlays made by other entities to establish or increase their share in projects in which the reporting entity has an interest $N/A$
Financing facilities available
Add notes as necessary for an understanding of the position.
| Amount available \$A=000 |
Amount used $$A=000$ |
||
|---|---|---|---|
| , 3.1 | Loan facilities | $\overline{\phantom{0}}$ | |
| 3.2 | Credit standby arrangements | $\sim$ |
Estimated cash outflows for next quarter
| \$A=000 | ||
|---|---|---|
| 4.1 | Exploration and evaluation | 120 |
| 4.2 | Development | 15 |
| Total | 135 |
Reconciliation of cash
| Reconciliation of cash at the end of the quarter (as shown in the consolidated statement of cash flows) to the related items in the accounts is as follows. |
Current quarter $A = 000$ |
Previous quarter $A = 000$ |
|
|---|---|---|---|
| 5.1 | Cash on hand at bank | 125 | 925 |
| 5.2 | Deposits at call | 97 | 97 |
| 5.3 | Bank overdraft | ||
| 5.4 | Other – gold bullion on hand | 6,361 | 4,834 |
| Total: cash at end of quarter (item 1.22) | 6,583 | 5,856 |
Changes in interest in mining tenements
| Tenement reference |
Nature of interest (note(4)) |
Interest at beginning of quarter |
Interest at end of quarter |
||
|---|---|---|---|---|---|
| 6.1 | Interests in mining tenements relinquished, reduced or lapsed |
||||
| 6.2 | Interest in mining tenements acquired or increased |
Issued and quoted securities at end of current quarter
Description includes rate of interest and any redemption or conversion rights together with process and dates
| Number issued | Number quoted | Par value (cents) | paid-up value (cents) | ||
|---|---|---|---|---|---|
| 7.1 | Preference securities (description) |
||||
| 7.2 | Issued during quarter | ||||
| 7.3 | Ordinary Securities | 38,260,813 | 38,260,813 | 20 cents | 20 cents |
| 7.4 | Issued during quarter | ||||
| 7.5 | Convertible debt securities (description) |
||||
| 7.6 | Issued during quarter | ||||
| 7.7 | Options (description) |
2,300,000 | Exercise Price 20 cents |
Expiry Date 30 April 2005 |
|
| 7.8 | Issued during quarter | ||||
| 7.9 | Exercised during quarter |
||||
| 7.10 | Expired during quarter | $\overline{\phantom{a}}$ | |||
| 7.11 | Debentures (totals only) |
||||
| 7.12 | Unsecured notes (Totals only) |
Compliance statement
- This statement has been prepared under accounting policies which comply with accounting 1 standards as defined in the Corporations Law or other standards acceptable to ASX (see $note 6).$
- $\overline{2}$ This statement does give a true and fair view of the matters disclosed.
Sign here: ...................................
Print name: ....................................
Notes
- 1 The quarterly report provides a basis for informing the market how the entity's activities have been financed for the past quarter and the effect on its cash position. An entity wanting to disclose additional information is encouraged to do so, in a note or notes attached to this report.
- $\overline{2}$ The aggregate amount of payments to suppliers and employees (item 1.2) made to directors of the entity and its related entities, associates of directors and associates of the entities (specified parties) must be disclosed by way of note with additional explanations necessary for an understanding of the transactions.
\$46,000.00 was paid to STT Pty Ltd for salaries and management fees for the March quarter.
œ
3 The aggregate amount of loans (item 1.10) made to specified parties must be disclosed by way of note.
The aggregate amount of loans made to specified parties are as follows:
| Oretek Limited | J. 20,898 |
|---|---|
| 20,898 |
- 4 The Nature of interest (items 6.1 and 6.2) includes options in respect of interests in mining tenements acquired, exercised or lapsed during the reporting period. If the entity is involved in a joint venture agreement and there are conditions precedent which will change its percentage interest in a mining tenement, it should disclose the change of percentage interest and conditions precedent in the list required for items 6.1 and 6.2.
- 5 The definitions in, and provisions of, AASB 1022: Accounting for Extractive Industries and AASB 1026: Statement of Cash Flows apply to this report.
- 6 Accounting Standards ASX will accept, for example, the use of International Accounting Standards for foreign entities. If the standards used do not address a topic, the Australian standard on that topic (if any) must be complied with.