QUANTUM GRAPHITE LIMITED — Investor Presentation 2015
Jan 26, 2015
65646_rns_2015-01-26_f3439689-70e9-4775-917d-0b01a59c9b1e.pdf
Investor Presentation
Open in viewerOpens in your device viewer
==> picture [142 x 162] intentionally omitted <==
Valence Industries Australia’s Only Graphite Producer Asia Pacific I Europe I North America
ASX : VXL & VXLO
January-February 2015
Manufacturing Our Carbon Future[TM]
Valence (noun). the combining power of an element, especially as measured by the number of hydrogen atoms it can displace or combine with: carbon always has a valence of 4.
© Valence Industries Limited
www.valenceindustries.co m
1
==> picture [57 x 67] intentionally omitted <==
Corporate Overview
| Capital & Shares Ordinary Shares 186.7m Options 68.4m Market cap (@45 cents) $84m Cash (End Q3 2014) ~$14.5m Debt Nil |
Major Shareholders Strategic Energy Resources Ltd (Restricted) 11.67% HSBC Custody Nominees (Australia) Ltd 5.08% Avatar Energy P/L 4.11% EERC Australasia P/L (restricted) 3.55% BNP Paribas Nominees P/L 2.15% Top 20 shareholders hold 43.90% |
|
|---|---|---|
==> picture [57 x 58] intentionally omitted <==
www.valenceindustries.co m
2
==> picture [57 x 67] intentionally omitted <==
Corporate Overview
==> picture [714 x 392] intentionally omitted <==
----- Start of picture text -----
Valence Industries
Directors & Officers
Graham Spurling AM
Chairman
Christopher Darby
MD & CEO
Glenister Lamont
Non-Exec. Director
Ian Schache
Non-Exec. Director
Ian Pattison
Non-Exec. Director
ASX chart of daily prices over 1 year for VXL compared to Mining & Metals Index
----- End of picture text -----
==> picture [57 x 58] intentionally omitted <==
www.valenceindustries.co m
3
==> picture [57 x 67] intentionally omitted <==
Operating Graphite Manufacturer
==> picture [321 x 287] intentionally omitted <==
----- Start of picture text -----
25000tpa
REFINING &
ORE RESERVE &
MICRONISING
MINE
Completed
Uley Pit 2 = 2Mt @
11.7%gC
High Purity &
LOM 5+ Years
TENEMENTS &
ENVIRONMENTAL
APPROVALS
Holds Mining,
Retention &
Exploration Licences
& Environmental
GRAPHITE PLANT Approvals
Commissioning
----- End of picture text -----
==> picture [57 x 58] intentionally omitted <==
www.valenceindustries.co m
4
==> picture [57 x 67] intentionally omitted <==
Exceptional Location
23km from Major Regional Centre Road, Rail, Port, Electricity, Water & Light Industrial Infrastructure
==> picture [371 x 235] intentionally omitted <==
Freehold Land for Phase I & Phase II Operations & All Mining Rights 100% Owned by Valence Industries
==> picture [319 x 343] intentionally omitted <==
==> picture [57 x 58] intentionally omitted <==
www.valenceindustries.co m
Data sourced from Feasibility Study, 31 December 2014 5**
==> picture [57 x 67] intentionally omitted <==
Valence Industries Now
==> picture [57 x 455] intentionally omitted <==
Established Current Sales Facilities & Contracts & Production Programs
Existing Traditional Graphite Plant Existing Plant capacity of 14000tpa
Sales Commenced in Mid-2014 & Further Sales & Exports on Track Long Term Commitments with 80000 of MoUs 2015 to 2019
Pre-processed fines stockpile processing on-track & started December 2014
Multiple sales contracts signed or in final negotiation for full plant capacity
ROM Stockpile pre-processing on-track & commenced December 2014 Full ROM Stockpile production on track & set to commence early 2015
Exports to Established Customers Commence in Early 2015 As Scheduled
Average Prices Per Tonne: Traditional A$1669t & Consistent with Forecast
Ore Reserves & Extensive Tenements
Only Operating Australian Graphite Mine
Largest Australian Graphite Ore Reserve 5+ Years LOM
Significant Resource Growth Potential
High Grade Material with Unique Flake Quality
Additional Mineral Resource & Ore Reserve Targeted for Q2 2015
www.valenceindustries.co m
6
==> picture [57 x 67] intentionally omitted <==
Current Production
Screen & Resize Existing Stockpiles
New ROM Stockpiles for Grading
Primary Grinding & Slurry Circuit
Secondary Process Building & Workshops
==> picture [57 x 58] intentionally omitted <==
www.valenceindustries.co m
7
==> picture [57 x 67] intentionally omitted <==
Current Production
Flotation Cells Producing Graphite
Bagging of Production in Phase I Plant
Filled Processed Graphite Tank
Bagging of Production in Phase I Plant
==> picture [57 x 58] intentionally omitted <==
www.valenceindustries.co m
8
==> picture [57 x 67] intentionally omitted <==
Transformation & Growth
Original Growth Plan Traditional Graphite Production
Feasibility Study Growth Plan Traditional & Advanced Graphite Production
==> picture [290 x 327] intentionally omitted <==
----- Start of picture text -----
Phase I
Existing Plant Refurbished
2014
& Recommissioned
Phase II
Expanded Traditional
2015-2016
Production Capacity
Phase III
Future Program 2019-2020
----- End of picture text -----
==> picture [367 x 327] intentionally omitted <==
----- Start of picture text -----
Phase II (Stage 1)
Operate Existing Plant & Mine Expand Existing Plant x25000tpa
2014 - Ongoing 2015-2016
Phase III (Stage 1)
Advanced Product Handling High Purity & Micronised
2015-2016 2015-2016
Phase II (Stage 2) & Phase III (Stage 2)
Expand Existing Plant x25000tpa Expand High Purity & Micronised
2017-2018 2017-2018
----- End of picture text -----
==> picture [57 x 58] intentionally omitted <==
www.valenceindustries.co m
9
==> picture [57 x 67] intentionally omitted <==
Expansion: Operational Strategy
==> picture [727 x 409] intentionally omitted <==
www.valenceindustries.co m
10
**Data sourced from Feasibility Study, 31 December 2014
==> picture [57 x 67] intentionally omitted <==
Foundations for Advanced Manufacturing
The first western company to manufacture high quality Traditional Flake Graphite & Advanced Specialist Graphite products
High Grades & Arterial Flake[TM] = High Quality Flake Graphite Unique & globally significant area of graphite mineralisation
Combination of
high grades (11.7%gC) & easy liberation & absence of natural contaminants delivers large % of Jumbo Flake and Super-Jumbo Flake (4mm+ Flake Sizes)
Advanced Product Handling = Value Added Opportunity High Quality Traditional flake graphite concentrate from Uley Graphite[TM] deliver unique precursor material for value-added processing
Advanced Manufacturing principles allow Manufacture of specialist high-value product lines for Traditional Markets
Unique Arterial Flake[TM] (up to 60%gC) processing opportunities that decrease physical intervention & increase flake size retention
PHASE I & PHASE II AS PLANNED
==> picture [57 x 58] intentionally omitted <==
==> picture [62 x 61] intentionally omitted <==
Further refining & reprocessing produce high-purity & micronised for High-Margin Production
NEW PHASE III FAST TRACKED
Data sourced from Feasibility Study, 31 December 2014 11**
www.valenceindustries.co m
==> picture [57 x 67] intentionally omitted <==
Expansion Program (2015-2016)
==> picture [132 x 73] intentionally omitted <==
----- Start of picture text -----
Existing
Traditional
Graphite Plant
----- End of picture text -----
==> picture [146 x 73] intentionally omitted <==
----- Start of picture text -----
Expand Traditional
Graphite Plant &
New Uley Pit 2
----- End of picture text -----
==> picture [132 x 73] intentionally omitted <==
----- Start of picture text -----
Advanced
Product
Handling
----- End of picture text -----
==> picture [15 x 281] intentionally omitted <==
2014 2015-2016 2015-2016 2015-2016 In Production Feasibility Feasibility Feasibility Commissionin Study Study Study g Completed Completed Completed Existing Add Specialist Purify & 14000tpa 25000tpa Blending & Micronise Capacity Capacity Refining Uley Graphite Uley Graphite Port Adelaide Port Adelaide Site Site Site Site
==> picture [57 x 58] intentionally omitted <==
www.valenceindustries.co m
12
==> picture [57 x 67] intentionally omitted <==
| Expansion Program | Expansion Program | (2016-2017) |
|---|---|---|
| Expanded Traditional Graphite Plant |
Expanded Advanced Manufacturing Plant |
|
| Pit & Process | ||
| Optimisation & | ||
| 2016-2017 | 2016-2017 | QA QC Systems |
| Feasibility Study |
Verification Study to be |
Value Added Automated |
| Completed | Conducted | Manufacturing |
| Add 25000tpa Capacity |
Increase Capacity to Purify & Micronise |
Multiple Specialist Graphite Products Packaged & Delivered to Global Customers |
| Uley Graphite | Port Adelaide | |
| Site | Site |
==> picture [57 x 58] intentionally omitted <==
www.valenceindustries.co m
13
==> picture [57 x 67] intentionally omitted <==
Focus on Margin
| As Modelled in Feasibility Study |
Avg COP (per tonne) |
Avg Sales Price (per tonne)*** |
Avg Margin (per tonne)*** |
|
| Traditional Base Flake Graphite Production |
$750-$950 (FOB Adelaide)* |
$1670 | $720-$920 | |
| Advanced Flake Graphite Production |
$4770 | $3820-$4020 | ||
| Strategy: A Strong Value-Added Manufacturing Blend to Deliver Increased & Sustained Margins |
- Ex Works Globally Competitive @ A$400-A$500 per tonne Data sourced from Feasibility Study, 31 December 2014 14 *rounded numbers
www.valenceindustries.co m
==> picture [57 x 67] intentionally omitted <==
Capital Allocation & Funding
| Capital spread across 4 years & applied to match corresponding sales plan Modest capital draw in context of revenue & EBIT target over period Phased capital allocation gives flexibility as capacity increases Term sheets & negotiations with range of funders established Assessment of Risk & Cost of Capital Sources Underway Funding sources: capital reserves, revenue, debt & equity all available Plant Capital Expanded Traditional Plant & New Uley Pit 2 2015-2016 $36.7M Expanded Traditional Plant 2017-2018 Advanced Product Handling 2015-2016 $13.2M Advanced Manufacturing Plant 2015-2016 Data sourced from Feasibility Study, 31 December 2014 & Working Capital Not Included |
|
|---|---|
==> picture [57 x 58] intentionally omitted <==
www.valenceindustries.co m
15
==> picture [57 x 67] intentionally omitted <==
Revenue & Dividend Forecast
==> picture [607 x 409] intentionally omitted <==
Year 4 Revenue ~$97M Year 4 EBIT ~$53M Year 4 Dividend 25% of EBIT distribution
==> picture [57 x 58] intentionally omitted <==
Note: Conservative estimate at <5% of volume contributed by advanced processing. Margin & revenue increases for each tonne of advanced processing. www.valenceindustries.co m
16
**Data sourced from Feasibility Study, 31 December 2014
==> picture [57 x 67] intentionally omitted <==
Mining Tenements & Regulatory Approvals
| VALENCE INDUSTRIES MINING TENEMENTS | VALENCE INDUSTRIES MINING TENEMENTS | VALENCE INDUSTRIES MINING TENEMENTS |
|---|---|---|
| Number | Status | Area |
| ML5561 | Current | 44 ha |
| ML5562 | Current | 22 ha |
| RL 66 | Current | 225 ha |
| RL 67 | Current | 187.5 ha |
| EL 4778 | Current | 75km2 |
| (**Renewal and extension of tenements is anticipated to be granted in the normal course) |
PROGRAM FOR ENVIRONMENTAL PROTECTION & REHABILITATION (PEPR) 23 December 2014 Environmental Approval Granted Authorises Phase I Operations & Phase II Expansion Program at Uley Graphite[TM] facilities Authorises Uley Pit 2 Mining Program From Surface to 16m & Then Simple Process to go below 16m
==> picture [329 x 173] intentionally omitted <==
----- Start of picture text -----
Arterial Flake [TM]
Core sample from new
pegmatite zone
----- End of picture text -----
==> picture [57 x 58] intentionally omitted <==
www.valenceindustries.co m
17
**Data sourced from Feasibility Study, 31 December 2014
==> picture [57 x 67] intentionally omitted <==
No Shortage of High Quality Raw Material
| ORE RESERVE – ULEY PIT 2 (JORC 2012) Classification Tonnage Average Grade %C Proved 319,000 17.9 Probable 1,716,000 11.9 Total 2,035,000 12.9 Uley Pit 2 – Fresh Graphitic Drill Core |
MINERAL RESOURCE & EXPLORATION TARGETS (JORC 2012) Classification Tonnage Average Grade %C Measured 340,000 17.92 Indicated 1,850,000 11.84 Indicated (Stockpiles) 174,000 6.23 Inferred (Uley Pit 2) 850,000 8.89 Total 3,214,000 11.54 Exploration Target 9,000,000 to 12,000,000 9 to 12 |
|
|---|---|---|
==> picture [57 x 58] intentionally omitted <==
www.valenceindustries.co m
18
==> picture [57 x 67] intentionally omitted <==
Ore Reserve Growth Potential
==> picture [339 x 369] intentionally omitted <==
Exploration Targets (JORC 2012)
All Located ML5561 & ML 5562 & RL66 & RL 67 Immediate Vicinity of Uley Pit 2
Current Drilling Program On Track on Uley Pit 2 Extension with Strong Visual Intersections & Results Due from Late March 2015 Onwards
Exploration Licence
Location 75km[2]
South and West of Uley Pit 2 Significant Potential with Historical Prospect Areas
**AREAS IN PINK = JORC 2012 EXPLORATION TARGET AREAS
==> picture [57 x 58] intentionally omitted <==
www.valenceindustries.co m
19
**Data sourced from Feasibility Study, 31 December 2014
==> picture [57 x 67] intentionally omitted <==
Ore Reserve Growth Potential
==> picture [57 x 455] intentionally omitted <==
==> picture [655 x 403] intentionally omitted <==
www.valenceindustries.co m
20
**Data sourced from Feasibility Study, 31 December 2014
==> picture [57 x 67] intentionally omitted <==
Expansion Economics
| Description | Outcome | Element | Assumption / Input | |
|---|---|---|---|---|
| Model Start Date | Dec 2014 | |||
| NPV 10 (after tax) | $65m | |||
| Modelling period | Monthly | |||
| IRR | 46% | |||
| Key Financial Output | Free Cash Flow to Equity |
|||
| Total Ore Mined | 2,035 kt | Real/Nominal Basis | Real | |
| Exchange Rate USD/AUD |
0.80 | |||
| Average Head Grade | 12.9% | |||
| Discount rate | 10% (after tax) | |||
| Life of Mine | 5 Years | |||
| Tax Modelling | After tax | |||
| Total Graphite Concentrate Sold |
235kt | |||
| Graphite Resource Mined |
2,035kt (Uley pit 2) | |||
| NOTE: This analysis is based on current formal Ore Reserve only as the key determinant of NPV. Every 1Mt of Ore Reserve adds A$32M to NPV. |
Note: After Tax Free Cash to Equity representative of cash flows likely to be received over CURRENT life of the expanded operations as determined by current formal Ore Reserve only |
==> picture [57 x 58] intentionally omitted <==
21
www.valenceindustries.co m
**Data sourced from Feasibility Study, 31 December 2014
==> picture [57 x 67] intentionally omitted <==
VXL Graphite Products
==> picture [57 x 58] intentionally omitted <==
www.valenceindustries.co m w w w . v a l e n c e i n d u s t r i e s . c o m
22
**Data sourced from Feasibility Study, 31 December 2014
==> picture [57 x 67] intentionally omitted <==
Market Engagement & Sales Strategy
MOU’s signed with multiple customers & agents representing 80,000+ tonnes of annual graphite production over 2-3 years As Production Qualifications from Operating Plant are Completed Convert to Sales Agreements
==> picture [57 x 58] intentionally omitted <==
==> picture [573 x 355] intentionally omitted <==
www.valenceindustries.co m
23
**Data sourced from Feasibility Study, 31 December 2014
==> picture [57 x 67] intentionally omitted <==
Global Graphite Leader
==> picture [674 x 322] intentionally omitted <==
==> picture [57 x 58] intentionally omitted <==
www.valenceindustries.co m
24
==> picture [57 x 67] intentionally omitted <==
Contact
Christopher S. Darby CEO & Managing Director Valence Industries Limited i n f o @ v a l e n c e i n d u s t r i e s . c o m I + 6 1 8 8 4 1 8 8 5 6 4
==> picture [285 x 251] intentionally omitted <==
==> picture [239 x 129] intentionally omitted <==
==> picture [173 x 130] intentionally omitted <==
==> picture [239 x 131] intentionally omitted <==
==> picture [173 x 124] intentionally omitted <==
==> picture [148 x 122] intentionally omitted <==
www.valenceindustries.co m
25
==> picture [57 x 67] intentionally omitted <==
Disclaimer
This presentation includes certain statements that may be deemed forward-looking statements. All statements in these presentation materials (other than statements of historical facts) which address future production, reserve potential, exploration activities & events or developments that the Company expects, are forward-looking statements. Such forward-looking statements include, without limitation: (i) estimates of future graphite prices, supply, demand &/or production; (ii) estimates of future cash costs; (iii) estimates of future capital expenditures; (iv) estimates regarding timing of future development, construction, production or closure activities; (v) statements regarding future exploration results; (vi) statements regarding cost structure, project economics, or competitive position, &; (vii) statements comparing the Company’s properties to other mines, projects or metals. Although the Company believes that such forward-looking statements are based on reasonable assumptions, such statements are not guarantees of future performance & actual results or developments may differ materially from those in the forward-looking statements. Factors that could cause actual results to differ materially from those in forward-looking statements include market prices, exploitation & exploration successes, continued availability of capital & financing, & general economic, market or business conditions. Investors are cautioned that any such statements are not guarantees of future performance, that the Company expressly disclaims any responsibility for revising or expanding the forward-looking statements to reflect actual results or developments, & that actual results or developments may differ materially from those projected, in the forward- looking statements. No representation or warranty is given by the Company as to the accuracy or completeness of the information contained in this presentation. Neither the Company nor its officers or employees accept responsibility or liability (to the maximum extent permitted by law) for any loss of damage suffered or incurred by any other person or entity however caused & relating in any way to these presentation materials including, without limitation, the information contained in the presentation material & its accuracy, completeness, currency or reliability. This presentation does not constitute a recommendation regarding the securities of the Company, & should not be construed as legal or financial advice. It has been prepared for information purposes only & contains general summary information & does not take into account the circumstances of any individual investor. Prospective investors in the Company are encouraged to obtain separate & independent advice with regard to any investment in the Company. By accepting the presentation materials, the recipient agrees to keep permanently confidential the information contained herein. Valence Industries confirms that it is not aware of any new information or data that materially affects the information included in this announcement and that all material assumptions and technical parameters underpinning the estimates in this announcement continue to apply and have not materially changed. The announcements previously released and referenced in the announcement are: “Valence Doubles Existing ROM Stockpiles” (6/8/14), “Discovery of High Grade Arterial Flake Graphite” (9/10/14), “Uley Graphite Grade Increases to 11.7%” (17/11/2014), “Maiden High Grade Graphite Ore Reserve” (17/12/14) and “VXL Feasibility Study Expansion and Adv Manufacturing” (2/1/2015).
Photographs, maps, charts, diagrams & schematic drawings appearing in this presentation are owned by & have been prepared by or commissioned by the Company, unless otherwise stated. Maps & diagrams used in the presentation are illustrative only & may not be drawn to scale. Unless otherwise stated, all data contained in charts, graphs & tables is based on information available at the date of this presentation. By accepting this presentation the Recipient agrees to be bound by the foregoing statements.
© Valence Industries Limited