AI Terminal

MODULE: AI_ANALYST
Interactive Q&A, Risk Assessment, Summarization
MODULE: DATA_EXTRACT
Excel Export, XBRL Parsing, Table Digitization
MODULE: PEER_COMP
Sector Benchmarking, Sentiment Analysis
SYSTEM ACCESS LOCKED
Authenticate / Register Log In

Prosafe SE

Investor Presentation Feb 1, 2024

3718_rns_2024-02-01_7abafaf3-ab5e-430e-8064-16f273aab46a.pdf

Investor Presentation

Open in Viewer

Opens in native device viewer

Q4 2023 Results

01 February 2024

Disclaimer

All statements in this presentation other than statements of historical fact are forward-looking statements, which are subject to a number of risks, uncertainties, and assumptions that are difficult to predict and are based upon assumptions as to future events that may not prove accurate. Certain such forward-looking statements can be identified by the use of forward-looking terminology such as "believe", "may", "will", "should", "would be", "expect" or "anticipate" or similar expressions, or the negative thereof, or other variations thereof, or comparable terminology, or by discussions of strategy, plans or intentions. Although we believe that the expectations reflected in such forward -looking statements are reasonable, these forward-looking statements are based on a number of assumptions and forecasts that, by their nature, involve risk and uncertainty. Various factors could cause our actual results to differ materially from those projected in a forward-looking statement or affect the extent to which a particular projection is realized. Should one or more of these risks or uncertainties materialise, or should underlying assumptions prove incorrect, actual results may vary materially from those described in this presentation as anticipated, believed or expected. To the extent this information includes information sourced from third parties, such as concerning the industry in which Prosafe operates, has not prepared such information and assumes no responsibility for it. Prosafe does not intend and does not assume any obligation to update any industry information or forward-looking statements set forth in this presentation to reflect subsequent events or circumstances.

Key events Q4 2023

Outlook

  • Four out of six options declared for Safe Concordia, increasing firm backlog with USD 12.7 million and extending the fixed term to November 2024
  • Controlling significant share of high-end available accommodation capacity in 2024-2026
  • North Sea operators planning future campaigns with ongoing bidding for 2025. No longer in dialogue regarding the announced NCS contract for 2025
  • Strong demand in Brazil with further long and short-term contracts expected

Operations and HSSE

  • Good operating and safety performance on all vessels
  • Utilisation of 50%, four out of seven vessels operating during the quarter
  • Safe Concordia, Safe Notos and Safe Zephyrus with 100% uptime. Safe Eurus 50% on-hire due to SPS in quarter

Financials

  • Q4 revenue of USD 29.6 million and EBITDA of USD (2.7) million
  • FY 2023 revenue of USD 97.7 million and EBITDA of USD (10.5) million
  • Liquidity of USD 74.6 million at year end
  • Strong investor support, USD 34.7 million in proceeds from private placement and subsequent offering

Market

Late-cyclical market trailing E&P spending and drilling rates

Growth in E&P Capex vs. fleet utilisation

Trailing 12-month average fixture rates Jack-up vs. accommodation

Rates in Brazil and the North Sea reaching 2015 levels

Brazil day rate development (USD/d) North Sea day rate development (USD/d)

2 Assuming only summer work in the North Sea

6

Durations, backlog and contract horizon confirm tight market1

1) Includes high end (tier-1) units in North Sea, Brazil, GoM, Canada and Australia (13 units), including options 2) Time to the end of latest firm fixture (including gaps between contracts)

Brazil FPSO growth driving increased demand

Brazil market (units)1 Floating production units in Brazil2

1) Source: Prosafe, company and market reports 2) Source: Petrobras Strategic Plan 2024-28, market reports

8

Tight North Sea market with Prosafe holding capacity

North Sea capable accommodation rigs (UK+NCS) Comment

2023 2024 2025 2026 2027
Vessel Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
Safe Boreas DP3 vessel in Region (UK and NCS capable)
Safe Caledonia Available for work in UK
Safe Zephyrus Brazil Available for work in Brazil/North Sea (UK and NCS)
Floatel Endurance Norway Norway Canada Norway
Floatel Superior Nor. Norway Norway Norway Norway
Floatel Triumph Australia UK Australia Australia (LOI)
Floatel Victory Brazil US Brazil
Haven (jack-up) Denmark Norway Norway
- Firm/option - Actual or potential mob - Expected awards
  • North Sea operators planning future campaigns
  • Ongoing bidding for 2025 and awards expected in H1 2024
  • Safe Boreas only DP3 semi in North Sea region available for 2024 and 2025 summer work
  • Safe Caledonia available for UK work with limited competition in coming years
  • Currently, limited prospects for 2024
  • Controlling the open capacity in 2026 when adjusted for vessel location / mobilisation
  • Upside potential in rates from last high fixture of USD 200-210k per day

Past EBITDA per vessel of USD 29 million from current fleet1

1) Based on historical current fleet of Safe Concordia, Safe Caledonia, Safe Eurus, Safe Notos, Safe Zephyrus, Safe Boreas and Safe Scandinavia (excluding TSV contract). Excluding SG&A

2) Assumes Brazil capable vessel at a total cost of USD 350m, discounted at 12.5% WACC, rig life of 30 years, USD 56k/d opex, 3% topline tax, USD 4m in capex per year (incl. SPS)

Indicative earnings potential in an improving market

Current fleet EBITDA potential

Current NIBD of USD 345m5 vs EBITDA potential
USD million Current
market1
Peak2
2014-15
Growth
Case3
EBITDA/vessel North Sea 22 50 40
EBITDA/vessel Brazil/RoW 25 30 30
# vessels in North Sea
# vessels in Brazil/RoW
2
4
2
4
3
6
EBITDA 144 220 300
Selling, General & Administrative (SG&A)4 (19) (20) (25)
Illustrative EBITDA 125 200 275

1) Based on latest observable and relevant fixtures of USD 200k/day in North Sea and USD 120k/day in Brazil, excluding Safe Scandinavia

2) Excluding Mexico and Safe Scandinavia during TSV operation. Excludes Safe Scandinavia

3) Includes newbuilds Nova and Vega plus Safe Scandinavia, calculations exclude required delivery payments, mobilisation and reactivation costs

4) Expected underlying SG&A run rate

11

5) NIBD per Q4'23, NIBD is reduced by a USD 9.5 million fair value adjustment of which USD 2.9 million is short-term

Enterprise value to replacement cost among the lowest

Accommodation vessels attractively priced compared to other assets1

▪ Lower Average EV / replacement than other assets ▪ Accommodation vessels trading at 30% to 45% of

12

Low Prosafe asset valuation relative to replacement cost2

  • historical newbuild cost
  • Broker valuations confirm robust asset backing to EV

Operations

Good operations

  • Safe Notos and Safe Zephyrus on contract with Petrobras in Brazil with 100% utilisation
  • Safe Concordia on-hire in US Gulf of Mexico and extended to 09 November 2024 with additional options outstanding
  • Safe Eurus was off-hire for SPS during Q4
  • TSV Safe Scandinavia laid up in Norway and marketed for both tender support and accommodation work
  • Safe Boreas and Safe Caledonia laid up in Norway and UK respectively and being actively tendered for 2025 work

1) Expected utilisation rate based on firm contracts

Backlog into 2027

  • Year-end backlog of USD 238 million
  • Safe Eurus, Safe Notos, Safe Zephyrus and Safe Concordia contracts
  • Safe Concordia firm contract extended to 9 November 2024 with 2x30-day options to January 2025 thereafter

Order backlog (USD million)

Expected phasing of order backlog (USD million)

Improved utilisation in 2024 with 4 of 7 rigs operating

Vessel 2023 2024 2025 2026 2027
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
Safe Zephyrus Petrobras (Brazil) North Sea
Safe Eurus Petrobras (Brazil) Petrobras (Brazil)
Safe Notos Petrobras (Brazil)
Petrobras (Brazil)
Safe Concordia US Gulf of Mexico
Safe Boreas North Sea
Safe Caledonia UK
Safe Scandinavia Cold-stacked (reactivation time of 6 to 9 months)
Safe Nova Newbuild at yard (delivery timeline of approximately 12 months)
Newbuild at yard
Safe Vega Newbuild at yard (delivery timeline of approximately 12 months)

Financials

17

Operating revenues

  • Charter income of USD 29 million in Q4, with lower utilisation due to Safe Eurus SPS
  • ‒ USD 1 million other income in Q4
  • EBITDA negatively impacted by off hire of Safe Eurus for SPS during the quarter

Operating revenues and EBITDA (USD million)

Income statement

  • Operating result before depreciation (EBITDA) of USD (2.7) million in Q4 and USD (10.5) million for 2023
  • Interest expense was USD 8.0 million in Q4 (USD 6.3 million), with interest rate of 7.6% in Q4 (5.9%). For the year, interest expense was USD 30.9 million (18.7 million), with an interest rate of 7.3% (4.4%)
  • Tax income of USD 6.5 million in Q4 (USD (1.2) million) mainly due to reversal of UK tax accrual. For the year, tax income was USD 5.4 million (USD (8.3) million) mainly due to UK tax reversal and no contract in Trinidad & Tobago in 2023
  • Remaining net mobilisation1) costs to be amortised are USD 3.1 million for Concordia and USD 3.0 million for Zephyrus through respective firm contract periods
(Unaudited figures in USD million) Q4 2023 Q4 2022 12M 2023 12M2022
Operating revenues 29.6 38.9 97.7 198.9
Operating expenses (32.3) (29.3) (108.2) (137.5)
Operating results before
depreciation
(2.7) 9.6 (10.5) 61.4
Depreciation (9.9) (7.7) (31.1) (29.5)
Operating profit/(loss) (12.6) 1.9 (41.6) 31.9
Interest income 0.5 0.3 2.1 0.7
Interest expenses (8.0) (6.3) (30.9) (18.7)
Other financial items (1.1) (1.8) (2.8) (4.1)
Net financial items (8.6) (7.8) (31.6) (22.1)
(Loss)/Profit before taxes (21.2) (5.9) (73.2) 9.8
Taxes 6.5 (1.2) 5.4 (8.3)
Net (loss)/profit (14.7) (7.1) (67.8) 1.5
0.1
EPS (1.01) (0.81) (6.00) 7
0.1
Diluted EPS (1.01) (0.81) (6.00) 7

Balance sheet

  • Total assets of USD 492.7 million, reduction from last year mainly related to the reduction in cash balance
  • Cash position of USD 74.6 million
  • Net working capital1 USD 5.1 million (USD 9.8 million), reduction driven by increase in accounts payable
  • Equity ratio of 6.9%
  • Q4 NIBD2of USD 344.9 million whereof USD 4.0 million is short-term debt
(Unaudited figures in USD million) 31.12.23 31.12.22
Vessels 383.7 376.8
New builds 0.0 0.0
Other non-current
assets 1.8 1.2
Total non-current assets 385.5 378.0
Accounts and other receivables 24.9 24.1
Other current assets 7.7 6.3
Cash and deposits 74.6 91.6
Total current
assets 107.2 122.0
Total assets 492.7 500.0
Share capital 24.8 12.4
Other equity 9.0 24.9
Total equity 33.8 37.3
Interest-free long-term liabilities 1.8 1.9
Interest-bearing long-term debt 415.5 418.5
Total long-term liabilities 417.3 420.4
Accounts and other payables 27.4 20.6
Tax payable 10.1 18.0
Current portion of long-term debt 4.0 3.7
Total current
liabilities 41.6 42.3
Total equity and liabilities 492.7 500.0

20

Operating cash flow

  • Operating cash flow of USD 3.8 million in Q4 and USD (11.5) million for full year
  • Capex spend of USD 4.8 million in Q4 driven by Safe Eurus SPS and USD 37.7 million for full year
  • Positive working capital impact due to increase in accounts payable, relating mainly to SPS of Safe Eurus
  • Net proceeds from private placement and secondary offering of USD 34.7 million in Q4
  • Cash position of USD 74.6 million at 31 December 20231

Cash flow in the quarter (USD million)

Summary and outlook

Summary

  • Good operating and safety performance on all vessels
  • 2023 has been a challenging year with lower utilisation than expected and increased costs related to mobilisation, hull cleaning and SPS
  • Strong investor support during the year with two private placements
  • Four out of six option periods secured for Safe Concordia
  • Controlling a significant share of open high-end accommodation capacity in 2024 to 2026
  • Strong and improving Brazil market with further long and shortterm contracts expected
  • North Sea operators planning future campaigns with ongoing bidding for 2025
  • Trend of increasing day rates and utilisation expected

Appendix

Vessel update - Brazil

Safe Eurus DP3 – Worldwide1

  • Contracted to Petrobras until February 2027
  • 100% utilisation in 2023 excluding SPS

Safe Notos DP3 – Worldwide1

  • Contracted to Petrobras until July 2026
  • 100% utilisation in 2023 excluding hull cleaning

Safe Zephyrus DP3 - Worldwide operations

  • Contracted to Petrobras until February 2025
  • 100% utilisation since contract start May 2023
  • Marketed for Brazil and North Sea contracts

Vessel update – North Sea and Gulf of Mexico

Safe Concordia DP2 – Worldwide2

  • Firm contract extended to 10 November 2024 with 2x30-day options to January 2025 in US Gulf of Mexico
  • 100% utilisation since contract start August 2023
  • SPS due March 2025

26

Safe Boreas DP3 - Worldwide

  • Actively marketed, currently in Norway
  • Potentially only NCS DP3-vessel available in 2025 and 2026 for work in North Sea

Safe Caledonia TAMS - UK North Sea

▪ Actively marketed, currently in the UK

Safe Scandinavia TSV/accommodation - UK / NCS

  • Tender assist ("TSV") or accommodation support
  • Accommodation capacity
  • ‒ 155 beds NCS
  • ‒ ~300 beds UK / Rest of world

Two newbuilds available at yard

  • Only two DP3 newbuild semis available at yard
  • ‒ 500 POB and suited for Petrobras requirements
  • ‒ Ongoing dialogue with the yard on how to facilitate delivery in expected future Petrobras tenders
  • ‒ Long-term contracts required to justify delivery
  • ‒ Typhoon in late September 2022 caused material damage that must be repaired prior to delivery
  • ‒ The yard is in the process of undertaking repairs

Fixed interest rate mechanism

Average day rate Year 1-2 Year 3-5 Year 6 to maturity
< USD
99k
- - 2 %
USD 100k -
124k
- 2 %-3% 3 %-5%
USD 125k -
149k
- 3 %-4% 5 %-8%
> USD150k - 4 % 8 %

Agreed delivery terms with COSCO (under discussion):

  • Remaining purchase price for vessels:
  • ‒ \$210m (Nova), \$212m (Vega), total \$422m, includes mobilisation costs of ~\$20m each
  • Funding at favorable credit terms:
  • ‒ Sellers Credit: \$165m (Nova), \$167m (Vega), 10 year term from August 2018
  • ‒ Estimated cash/equity requirement1 : \$45m (Nova), \$45m (Vega), total for both vessels of \$90m

27

SPS/maintenance capex

  • Maintenance capex of ~USD 1-2 million per vessel per year. Higher in Brazil than North Sea and increasing over time
  • 5-year SPS cost of USD 5 to 7 million per vessel, excluding life extension works
  • 10-year thruster overhaul cost of USD 6 to 7 million per vessel may be required in coming 12 to 24 months for Boreas and Zephyrus
  • SPS usually takes 1-2 months to complete and is targeted to be completed in off hire season in North Sea or between contracts in Brazil
  • Safe Concordia SPS due in March 2025, which is estimated at USD 15 to 20 million. Life extension will require additional capex
  • Reactivation of Safe Scandinavia is estimated to require USD ~20 million. Cost is highly dependent on whether vessel used for accommodation, TSV and contract location

SPS Schedule

2024 2025 2026 2027
Boreas Jan 2025
Zephyrus Nov 2025
Concordia March 2025
Notos Feb 2026
Eurus
Caledonia Before contract
Scandinavia Before contract

Analytical information

Item 2024
Estimated
(USDm)
Comment
SG&A ~18-201 SG&A may increase depending on activity
Depreciation ~32-33 Straight line depreciation
Interest expense
payable
~29-31 Exposed to interest rate changes
Tax payable ~2-3 Norwegian deferred tax asset base of USD 1.7bn per year
end 2022, local and contract specific taxes
Maintenance / contract
specific capex
~14-15 2024 capex mainly for Safe Eurus, Safe Notos, Safe
Concordia and new ERP system. Excludes potential re
activation capex / cost for 2025

P&L information Indicative opex/day by region

Region 2024 Opex
Estimated
(USDk/day)
UK (DP-Boreas/Zephyrus) 35-45k
UK (Moored –
Caledonia)
25-30k
Brazil3 50-54k
Norway (DP –
Boreas/Zephyrus)
2
60-65k
RoW (Concordia) 35-45k
US GoM (Concordia)2 45-50k
Scandinavia (cold) 2.5-3k
Stacking (warm)4 10-20k

2) Excluding amortisation of mobilisation cost.

3) Including approximately USD 5 -10/day in fuel cost

4) Ramp-up and ramp-down before and after contract at full operational cost. Stacking cost and re-activation highly dependent on time in lay-up and region

Outstanding debt

Two tranches
Main tranche COSCO Sellers Credit Debt maturity profile
Outstanding debt \$343m (250m + 93m Notos) \$93m
Pledged vessels Boreas, Zephyrus, Caledonia, Concordia,
Scandinavia, Notos
Eurus
Interest rate SOFR + Credit Adjustment Spread* +
2.5%. Unhedged
0% (increase to 2% from 2026) COSCO
Amortizations Cash sweep above \$67m forecasted
liquidity on 12-month forward basis
50-50 EBITDA split. Minimum \$6m/year,
\$7m/year from Q3 2026
343 Main Tranche
Maturity 2025 ~Q3 2028 or when debt reaches ~\$50m 6 6 6 7 7 56
PCG PSE fully liable \$60m 2023 2024 2025 2026 2027 2028
Financial Covenant 2022 cash > \$18 million
2023 cash > \$23 million
2024 cash > \$28 million
Cash held in the COSCO tranche shall be
deducted when calculating compliance with
the cash covenant. On 31 December, USD
4.3m was held in the COSCO tranche
Major corporate actions including M&A,
new indebtedness and delivery of new
vessels require 2/3 approval by the lenders
Newbuilds (Nova and Vega) could be
added to the COSCO silo
Delivery of newbuilds requires 2/3 approval
of lenders in main tranche
Ringfenced
Cash
flow
is
contracted
structure
on
COSCO
with
with
annual
tranche
Petrobras
to
upstreaming
coming
2027
to
from
Safe
main
tranche.
Eurus
which
  • Prosafe SE is a permanent tax resident in Norway and its Norwegian tax resident subsidiaries have a base for deferred tax assets of approximately USD 1.7 billion as at end 2022. The deferred tax assets are currently not recognized in the financial statements. In Q4 2023, the Norwegian tax authorities initiated a review of the basis for a portion of the deferred tax losses. This review may lead to a reduction in the unrecognized deferred tax asset base. At this time, Prosafe does not believe that this will have a material impact on Prosafe's financial position irrespective of the outcome of this review
  • The company will from time to time operate in countries where local taxes will apply. These taxes are included in the opex assumptions in this presentation where applicable. In relation to the historical Concordia contract in Trinidad and Tobago, a tax provision of USD 6 million is provided for in the 2022 accounts
  • At year end 2023, Prosafe released non-cash tax provisions of USD 8 million related to historical UK tax enquiries which were favorably resolved in late 2023
  • Prosafe and OSM Thome have jointly received a Tax Assessment from the Brazilian Tax Authorities imposing import taxes and customs penalties related to the challenging of the special customs regimes used to import the Safe Concordia for the Modec contract in the period from October 2018 to July 2019. Both Prosafe and OSM Thome have presented an administrative defence, challenging the view of the Brazilian Tax Authorities. Based on external advice, Prosafe is of the view that the enquiry has no merit, hence it has not made any provisions in the financial statements

We are headquartered in Norway and have offices in the UK, Brazil and Singapore

Head office:

Forusparken 2 N-4031 Stavanger Norway

prosafe.com

Talk to a Data Expert

Have a question? We'll get back to you promptly.