ASX RELEASE 2 March 2012
Q1 2012 DRILLING PROGRAMMES: KANGWANE CENTRAL, MBILA
-
Kangwane Central: Phase 3 drilling starts to upgrade measured resource; results expected Q3 2012
-
Mbila: 10 borehole infill drilling totalling 2 000m, to identify additional resources; results expected during April 2012
ZYL Limited (“ ZYL ” or the “ Company ”) ( ASX: ZYL ), the Perth-based emerging anthracite producer, is pleased to announce Q1 2012 drilling schedules for its key South African projects, Kangwane and Mbila.
Kangwane Central
Phase 3 drilling at Kangwane Central has begun to upgrade the first five years of mineable resources to the measured category. The 25-borehole programme totalling 5 000 metres, to be undertaken by GeoPractica, will comprise exploration, verification and geotechnical drilling. Core samples will be prepared and sent for analysis at an accredited laboratory. The full drilling programme, analysis and subsequent geological modelling will be completed in Q3 and the results will be announced shortly afterwards.
Mbila
Phase 1 of an infill drilling programme, to identify additional resources lying between Mbila S Block and the adjacent Msebe exploration permit area (see map on following page), is scheduled to begin during the first week of March. Phase 1, consisting of 10 diamond drill holes totalling 2 000 metres, is expected to be completed by the end of March, with analysis results available in the first half of April. Phase 2 will start in the last week of March, with results expected mid-April. The results from both drilling phases will be integrated into the existing geological model and any additional resources identified will be incorporated into Mbila’s resource base and mine planning. ZYL expects to be in a position to update shareholders on Mbila’s resource position during May.
==> picture [40 x 41] intentionally omitted <==
Corporate Office:
Level 8, 225 St Georges Terrace, Perth 6000,Western Australia Tel: +61 8 9486 4036 Email: [email protected] PO Box 7653, Cloisters Square, Perth 6850, Western Australia Fax: +61 8 9486 4799 Web: www.zyllimited.com.au
==> picture [344 x 249] intentionally omitted <==
Two structural definition drilling programmes will begin on the GA and AD Block at Mbila in the first week of March 2012. The programmes, consisting of 43 percussion drill holes totalling 2 580 metres, are to clarify structural definition in order for ZYL to complete the mine design for these two resource blocks. A further geotechnical drilling programme at S Block will start in the coming weeks, as technical information is required to complete the final mine design and scheduling for the Beaufort multi-seam underground mining configuration.
Commenting on the drilling programmes, Executive Chairman Bevan Tarratt said: “The new drilling programmes provide ZYL with the opportunity to expand and increase the resource at both the Kangwane and Mbila projects. The structural and geotechnical programmes to be completed at Mbila allow us to progress with completing the mine design as soon as possible.”
Contact:
Ian Benning, CEO, ZYL LIMITED T: +27 (0) 87 350 2751 M: +27 (0) 83 702 8221 E: [email protected]
Media - South Africa James Duncan, Russell and Associates T: +27 (0) 11 880 3924 M: +28 (0) 82 892 8052 E: [email protected]
Media - Australia Annette Ellis, Purple Communications T: +61 (0) 8 6314 6300 M: +61 (0) 45 820 039 E: [email protected]
Page | 2
About ZYL Limited
ZYL Limited is listed on the Australian Securities Exchange (ASX) and aims to become one of the world’s leading anthracite coal producers. The mission of ZYL is to develop high-margin metallurgical coal deposits for domestic and export markets. Flagship projects are the Mbila and Kangwane projects in South Africa, located close to rail, port, power and water infrastructure.
Important information
The information in this announcement is an overview and does not contain all information necessary to make an investment decision. To the extent permitted by law, no representation or warranty, express or implied, is made as to the accuracy, adequacy or reliability of any statements, estimates or opinions or other information contained in this announcement, any of which may change without notice. This document is not a prospectus, disclosure document or offering document under Australian law or under any other law. It does not constitute an offer or invitation to apply for securities. It is for information purposes only. This announcement is not an offer of securities for subscription or sale in the United States or any other jurisdiction in which such an offer or solicitation is not authorised or to any other person to whom it is unlawful to make such an offer or solicitation. Some of the information contained in this announcement constitutes forward-looking statements that are subject to various risks and uncertainties, not all of which may be disclosed. These statements discuss future objectives or expectations concerning results of operations or financial condition or provide other forward-looking information.
Prospective investors should make their own independent evaluation of an investment in the securities. The material contained in this document does not take into account the investment objectives, financial situation or particular needs of any particular investor. No recommendation to investors regarding the suitability of the securities has been made and the recipient must make its own assessment and/or seek independent advice on financial, legal, tax and other matters, including the merits and risk involved. This announcement and its contents have been distributed to you, in confidence, solely for your information and may not be retransmitted or otherwise reproduced or disclosed to third parties or made public in any way, in whole or in part, for any purpose without written permission.
Page | 3