Skip to main content

AI assistant

Sign in to chat with this filing

The assistant answers questions, extracts KPIs, and summarises risk factors directly from the filing text.

PERPETUAL RESOURCES LIMITED Capital/Financing Update 2021

Mar 16, 2021

65540_rns_2021-03-16_87a78adf-5ccd-43d4-9a9b-4c192eac090a.pdf

Capital/Financing Update

Open in viewer

Opens in your device viewer

==> picture [138 x 50] intentionally omitted <==

Maiden Ore Reserve at Beharra Underpins Outstanding PreFeasibility Study Result, Confirming a Compelling Low Capex & Strong Free Cashflow Project

ASX RELEASE

PFS Highlights

17[th] March 2021 ASX: PEC

  • Highly successful Pre-Feasibility Study (PFS) confirms Beharra as a compelling long life silica sand project set to become an essential low impurity supplier of high-quality silica sand products to the rapidly growing APAC glass and foundry sand markets.

CORPORATE DIRECTORY

Executive Chairman Julian Babarczy

Managing Director Robert Benussi

  • Compelling financial metrics demonstrate the robustness of the project which also affords expansion potential and the potential ability to respond to increases in market demand.

Non-Executive Director Brett Grosvenor

Non-Executive Director & Company Secretary George Karafotias

ct Beharra Project Economics Unit Base Case

Total Silica Sand Produced
Mt
Annual Production
Mt
In-situ Probable Ore Reserve (@ 98.6% SiO2)
Mt
Ore Reserve Life
Years
JORC Mineral Resource Estimate (@ 98.6% SiO2)
Mt
Total Life of Mine Revenue
A$M
Start-up Capital
A$M
Total Life of Mine Capital Expenditure
A$M
Total Life of Mine EBITDA
A$M
Total Life of Mine Free Cashflow
A$M
48
1.5
64
32
139
3,176
39
77
1,714
1,131
Post-tax Discounted Cashflow (NPV10) - ungeared
A$M
Post-tax Internal Rate of Return (IRR) - ungeared
%
Post-tax Discounted Cashflow (NPV10) - 40% geared
A$M
Post-tax Internal Rate of Return (IRR)-40% geared
%
231
55%
236
77%

Payback Period
Years
FOB Costs
A$/t
2
43.07

Projects

Beharra Silica Sands Project Sargon Hub Eneabba Hub

CONTACT DETAILS:

Suite 801 Level 8 84 Pitt Street Sydney NSW 2000

George Karafotias

Phone | +61 042 086 550

Robert Benussi

Phone | +61 410 415 335

  • Nameplate production capacity of 1.5 mtpa, produced from a Run of Mine (ROM) production of 2 Mtpa.

  • Simple mining and processing confirmed, with off-the-shelf processing technologies applied and optimal plant configuration sized to allow maximum flexibility and optimal capital cost.

  • Lowest known impurity profile of end product streams in the MidWest region, ideal for the burgeoning APAC markets.

Summary of Final Products SiO
~~2~~
Fe
~~2~~
O
~~3~~
Al
~~2~~
O
~~3~~
TiO
~~2~~
LOI Mass Yield
Beharra Special AFS #46
99.6%
280 ppm
1825 ppm
375 ppm
0.14%
68%
Beharra Premium AFS #44
99.6%
276 ppm
1789 ppm
369 ppm
0.14%
#46 & #27 combined
Beharra Special AFS #27
99.7%
235 ppm
1405 ppm
300 ppm
0.13%
6%
  • Considerable project upside potential through further optimisation of metallurgical circuit.

  • Scope to reduce operating and capital costs at Feasibility Study (or other subsequent) stage which would materially improve financial and return metrics for Beharra.

  • The Board of Perpetual consider the rigour and detail undertaken in this Beharra PFS to be considerable and the Company is currently reviewing potential for an accelerated development path (subject to regulatory and approval processes).

  • Base case planning assumes a subsequent project study and/or a decision to fund in 2021 with first production in late 2022.

Perpetual Resources Limited ( ASX: PEC , “PEC” or “the Company”) is pleased to announce the release of its Beharra PFS on its 100% owned Beharra Project located south east of Geraldton, Western Australia.

Perpetual’s Executive Chairman, Mr Julian Babarczy , provided the following commentary, “ The finalisation and announcement of the PFS results demonstrate that the Beharra silica sand project can produce the highest known quality silica sand product in the Mid-West Region of Western Australia. After the conclusion of extensive studies across all areas of project focus, the announced outcomes of the Beharra PFS are simply outstanding, and suggest a compelling project, across both financial and operating metrics. In our view, Beharra represents the stand-out project in the Mid-West region of Western Australia, which looks set to become a dominant supply source for high quality silica sand to the APAC region. In the Perpetual Board’s view, Beharra now sits atop all other projects in the region and we are excited to continue our rapid development as we move towards a subsequent project study and/or a decision to fund later in calendar year 2021”.

The PFS results, which are the culmination of over seven months of extensive independent study, confirm that the Beharra Project will deliver exceptionally strong margins over the initial 32-year mine life. Potential also exists to expand production in future years, with Beharra set to become an essential supplier to regional APAC silica sand markets.

==> picture [133 x 48] intentionally omitted <==

Level 8, 84 Pitt Street, Sydney, NSW, 2000 www.perpetualresourceslimited.com.au

A list of the standout features of the Beharra project are summarised below;

  • Exceptionally strong return metrics, with low capital requirements, strong margins and high resultant free cash flows, which offer a compelling financial case.

  • Investment returns anticipated to be of significant interest to both debt and equity investors in the region, once a decision to fund is reached in late 2021.

  • Standout metallurgical testing results confirms Beharra as the pre-eminent Mid-West silica sand project (based on publicly available data on known projects), with attainment of the lowest impurity profile of any known project in the region.

  • No fatal flaws identified throughout any of the studies undertaken, with significant scope for operational and financial optimisation once Feasibility or other studies are commenced.

  • Strong initial engagement with local and regional stakeholders suggests good community interest in development of the Beharra project.

  • Initial inbound and outbound enquiries from potential off takers and silica sand trading groups, as well as data compiled from independent price forecasters and other industry contacts, demonstrates strong support of Beharra’s ability to achieve robust sales prices in the growing APAC silica sand markets.

  • Simple, low cost flow sheet confirmed, with no requirement for the use of harmful chemicals and a very low subsequent environmental impact.

  • Beharra Project can be readily up-scaled based on a modular plant configuration, that will assist in achieving the lowest possible capital intensity and substantial project flexibility.

  • Overall, the key objectives of confirming a flexible and low capital project that also delivers compelling financial return metrics and delivers a highly attractive end product to the fast-growing APAC markets, has been achieved.

  • Significant scope for optimisation at Feasibility Study (or subsequent development path) level exists, with potential for metallurgical improvements, capital and operating cost reductions, as well as operational simplification programs which will further enhance the already compelling metrics of the Beharra project.

==> picture [133 x 48] intentionally omitted <==

Level 8, 84 Pitt Street, Sydney, NSW, 2000 www.perpetualresourceslimited.com.au

Ore Reserve Highlights

  • Total Probable Ore Reserves of 64.1 Mt @ 98.6% SiO2

  • Probable Ore Reserve underpins an initial 32-year mine life at Beharra.

  • Probable Ore Reserve estimated to produce a Saleable Product of 47.6 Mt @ 99.6% SiO2

  • Probable Ore Reserve positions Beharra as the pre-eminent silica sand project in the Mid West region of Western Australia (based on known projects).

  • Concurrent delivery of an outstanding Pre-Feasibility (PFS) demonstrates Beharra as a high quality, long life, low capital and high margin mining project.

Perpetual is also pleased to announce the details of its maiden Probable Ore Reserve at its Beharra Silica Sand Project (Beharra), located approximately 300 km north of Perth and 96km south of Geraldton.

Perpetual recently released an updated Mineral Resource Estimate (MRE) for Beharra, reporting Indicated Mineral Resources of 139 Mt @ 98.6% SiO2 (see ASX Announcement dated 9th March 2021, titled “Upgraded Mineral Resource Estimate - Beharra”). The MRE was prepared by Snowden Mining Consultants (Snowden), who has also prepared this Probable Ore Reserve estimate. The Ore Reserve is reported in accordance with Clause 49 of the JORC Code (2012), for the reporting of Industrial Minerals and Ore Reserves. The Ore Reserve estimate is provided in Table 1.

Table 1. Beharra Probable Ore Reserve March 2021

Sand Tonnes (Mt) SiO2 (%) Al2O3 (ppm) TiO2 (ppm) Fe2O3 (ppm) LOI (%)
In-situ 64.1 98.6 4,240 3,460 1,950 0.235
Saleable Product 47.6 99.6 1,789 369 276 0.100

Note 1 : Million tonnes are rounded to one decimal place. Grades are rounded to 3 significant figures.

Note 2: No cut off is applied to the silica sand product.

Note 3: The In-situ and Saleable Product are not additive, and the Saleable Product is a portion of the In-situ sand tonnage.

==> picture [133 x 48] intentionally omitted <==

Level 8, 84 Pitt Street, Sydney, NSW, 2000 www.perpetualresourceslimited.com.au

PEC’s Managing Director, Mr Robert Benussi provided the following commentary “the Ore Reserve estimate is based on saleable products that have been produced as part of the very successful and comprehensive metallurgical test work program, which was announced on 29[th] January 2021. This test work and the resultant Ore Reserve estimate clearly demonstrates that the Beharra end product is suitable for sale into the Asia Pacific glass and foundry sand industries, with the product readily positioned in a higher end segment of the market. The test work and Ore Reserve estimate show Beharra can comfortably service the 200 to 300ppm range of the APAC market (in relation to iron oxide, or Fe2O3), which is the key impurity of focus of end users. Further, the Ore Reserve estimate underpins a very long life mine plan of 32 years and enabled the release today of a compelling PFS study on Beharra which shows a low capital, high margin mining project that is, in our view, the pre-eminent silica sand project in the Mid-West region of Western Australia”.

There was no silica sand cut-off grade applied to the previously announced Indicated Mineral Resources for Beharra and the MRE is reported inclusive of the Ore Reserves. However, the Ore Reserve inventory includes only material with an Fe2O3 content averaging 2,000 ppm, which is considered optimal for plant feed considerations. The conversion from Mineral Resources to Ore Reserves was 46%, although, in addition to the Saleable Product Ore Reserve, an additional portion of the Indicated Mineral Resources was also identified (shown in Table 2 below). The additional portion of potentially economic material was identified using the same Modifying Factors as the Beharra insitu Ore Reserve and is reported as Indicated Mineral Resources. This is not a salable product and is higher in iron oxide (Fe2O3).

Table 2. Beharra additional portion of Indicated Mineral Resources March 2021

==> picture [419 x 60] intentionally omitted <==

Note 1: All of the additional portion tonnes are Indicated Mineral Resources (insitu) and reported exclusive of the Indicated Mineral Resources used to identify insitu Ore Reserves and inclusive of existing Indicated Mineral Resources.

Note 2: Cautionary Statement - For the additional portion tonnes, there is no certainty that the Indicated Mineral Resources will result in Ore Reserves.

The additional portion tonnes will be reassessed with a view to classifying the insitu tonnage as an Ore Reserve pending further metallurgical evaluation, however this is subject to future test work performance.

==> picture [133 x 48] intentionally omitted <==

Level 8, 84 Pitt Street, Sydney, NSW, 2000 www.perpetualresourceslimited.com.au

Mining Modifying Factors applied to the Ore Reserve estimate included pit optimisation to produce an economic mining shell followed by detailed pit design which was used to convert the Mineral Resources to an Ore Reserve. Mine equipment requirements and pricing were determined by contractors utilising load and haul mining and a mine production schedule that was developed by Snowden. Minor dilution was included due to boundary losses and offset corridors. Geotechnical analysis recommended pit slope design angles of 30[o] .

Calculation and determination of the Ore Reserves were based on producing Beharra Premium silica sand product #44, which has a SiO2 grade of >99.5% and Fe2O3 content of <280ppm. Mass yield into this product as per the test work was calculated at 74.4%. Refer to Table 3 below.

Table 3. Beharra Silica Sand Products

Testwork
Classification
Product
Classification
Mass by
ROM
Assays
% ppm ppm ppm %
SiO2 Al2O3 Fe2O3 TiO2 LOI
% 97.9 9,900 680 910 0.26
UCC
Underflow
(calc.)
Beharra
Premium #44
74.4 99.6 1,789 276 369 0.14
Screen O/S Beharra
Premium #27
6.3 99.7 1,405 235 300 0.13
Screen U/S Beharra
Premium #46
68.0 99.6 1,825 280 375 0.14

The mineral processing flowsheet and plant design incorporated industry standard activities, including industry standard processes of screening and desliming, gravity, magnetic and physical separation, and commonly seen equipment used in the mineral sands industry. Supply of a packaged plant and turnkey solutions were sought for the processing facility including capital cost estimates. Summary capital costs is presented in Table 4. Accuracy of capital costs is +/-25%.

==> picture [133 x 48] intentionally omitted <==

Level 8, 84 Pitt Street, Sydney, NSW, 2000 www.perpetualresourceslimited.com.au

Table 4. Capital Cost Estimate

Table 4. Capital Cost Estimate
Capex A$ Cost
($‘000)
Process Plant incl water distribution
Services & Onsite Infrastructure
Offsite Infrastructure
Indirects, PCM and site office costs
Total development capital
Owners’ costs
Owner’s contingency (10%)
19,287
3,537
9,272
2,338
34,434
1,343
3,443
Total pre-production capital 39,220

Operating costs were derived from contractor budget pricing, market quotations, and bottom-up estimates based on a 32-year LOM. Refer to Table 5 below.

Table 5. Operating Cost Estimate

Opex A$ Cost p.a.
($‘000.)
A$/t
Ore

A$/t
Product Con.
Mining (ROM+OB)
Processing
Reject Haulage
Admin
Transport + Port/ Ship loading
Rehab
Contingency
Royalty
10.6
5.0
0.6
2.4
39.4
1.8
2.8
3.5
5.18
2.46
0.29
1.18
19.40
0.43
1.40
1.71
6.97
3.31
0.36
1.58
26.09
0.58
1.88
2.30
Total Opex 66.1 32.05 43.07

Market assessment was provided by IMARC to provide an independent market review of Asia Pacific (APAC) region (in addition to discussions with sales and marketing consultants and industry contacts), specifically targeting selected countries and specific product grades. Consumption in the APAC region in 2020 amounted to a value of US$5,133.7 million and is forecast to grow by 7.1% per annum by 2026 to reach a value of US$7,638.1 million, equivalent to a demand of 174.3 million tons of silica sand.

==> picture [133 x 48] intentionally omitted <==

Level 8, 84 Pitt Street, Sydney, NSW, 2000 www.perpetualresourceslimited.com.au

Pricing ranges from country to country and is determined mostly by impurity levels (with a focus on Fe2O3), once a base level of SiO2 has been achieved (typically >99.5% SiO2). Please refer to Figure 1 below.

Figure 1. Regional APAC silica sand pricing for 200-300ppm Fe2O3

==> picture [436 x 259] intentionally omitted <==

source: IMARC Group (Asia Pacific Silica Sand Market)

Adopted pricing by Perpetual for the Ore Reserve estimate was set at US$50/mt FOB at a constant exchange rate of 0.75A$:1.00US$, resulting in an A$ sales price of $67/dry tonne.

This announcement has been approved for release by the Board of Perpetual.

-ENDS-

For enquiries regarding this release please contact:

Mr George Karafotias Company Secretary Ph +61 421 086 550

==> picture [133 x 48] intentionally omitted <==

Level 8, 84 Pitt Street, Sydney, NSW, 2000 www.perpetualresourceslimited.com.au

Cautionary Statement

The Pre-Feasibility Study (PFS) discussed herein has been undertaken to study a range of options to further develop the technical and economic feasibility of the Beharra Silica Sands Project (the Project). The production target incorporates the Probable Ore that sits within the proposed mining area. The is also an additional portion of the Indicated Mineral Resource within the area that is identified for further metallurgical test work.

There is a moderate level of geological confidence associated with Indicated Mineral Resources however there is no certainty that further exploration work will result in the determination of a Measured Mineral Resource or that the production target itself will be realised. For the additional portion of the Indicated Mineral Resource, there is no certainty that the Indicated Mineral Resources will result in Ore Reserves.

The Ore Reserve and Mineral Resource Estimate underpinning the PFS have been prepared by Competent Persons in accordance with the requirements of the JORC Code. Competent Persons’ Statements are included in this document.

Investors should note that there is no certainty that Perpetual Resources Limited (Perpetual) will be able to raise funding required to commercialise the project when needed. It is also possible that such funding may only be available on terms that may be dilutive to or otherwise affect the value of Perpetuals’ existing shares. It is also possible that Perpetual could pursue other ‘value realisation’ strategies to provide alternative funding options.

Given the uncertainties involved, investors should not make any investment decisions based solely on the results of the Project PFS.

Forward-looking statements

Certain statements contained in this document may be ‘forward-looking’ and may include, amongst other things, statements regarding production targets, economic analysis, resource trends, pricing, recovery costs, and capital expenditure. These ‘forward–looking’ statements are necessarily based upon a number of estimates and assumptions that, while considered reasonable by Perpetual, are inherently subject to significant technical, business, economic, competitive, political and social uncertainties and contingencies and involve known and unknown risks and uncertainties that could cause actual events or results to differ materially from estimated or anticipated events or results reflected in such forward-looking statements.

Forward-looking statements are often, but not always, identified by the use of words such as ‘believe’, ‘expect’, ‘anticipate’, ‘indicate’, ‘target’, ‘plan’, ‘intends’, ‘budget’, ‘estimate’, ‘may’, ‘will’, ‘schedule’ and others of similar nature.

Perpetual does not undertake any obligation to update forward-looking statements even if circumstances or management’s estimates or opinions should change. Investors should not place undue reliance on forward-looking statements as they are not a guarantee of future performance.

Disclaimer

No representation or warranty, express or implied, is made by Perpetual that the material contained in this document will be achieved or proved correct. Except for statutory liability and the ASX Listing Rules which cannot be excluded, Perpetual and each of its directors, officers, employees, advisors and agents expressly disclaims any responsibility for the accuracy, correctness, reliability or completeness of the material contained in this document and excludes all liability whatsoever (including in negligence) for any loss or damage which may be suffered by any person through use or reliance on any information contained in or omitted from this document.

==> picture [133 x 48] intentionally omitted <==

Level 8, 84 Pitt Street, Sydney, NSW, 2000 www.perpetualresourceslimited.com.au

COMPETENT PERSONS STATEMENTS

The information in this report that relates to the March 2020 Exploration information for the Beharra Project is based on information compiled and fairly represented by Mr Colin Ross Hastings, who is a Member of the Australasian Institute of Mining and Metallurgy and consultant to Perpetual Resources Limited. Mr Hastings is also a shareholder of Perpetual Resources Limited. Mr Hastings has sufficient experience relevant to the style of mineralisation and type of deposit under consideration, and to the activity which he has undertaken, to qualify as a Competent Person as defined in the 2012 Edition of the Joint Ore Reserves Committee (JORC) “Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves”. Mr Hastings consents to the inclusion in this report of the matters based on this information in the form and context in which it appears.

The information in this report that relates to the Exploration information for the Beharra Project from September 2020 onwards is based on information compiled and fairly represented by Mr John Doepel, who is a Member of the Australasian Institute of Mining and Metallurgy and consultant to Perpetual Resources Limited. Mr Doepel has sufficient experience relevant to the style of mineralisation and type of deposit under consideration, and to the activity which he has undertaken, to qualify as a Competent Person as defined in the 2012 Edition of the Joint Ore Reserves Committee (JORC) “Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves”. Mr Doepel consents to the inclusion in this report of the matters based on this information in the form and context in which it appears.

The information in this report that relates to Mineral Resources is based on information compiled by Elizabeth Haren, a Competent Person who is a Member and Chartered Professional of the Australasian Institute of Mining and Metallurgy and a Member of the Australian Institute of Geoscientists. Elizabeth Haren is employed as an associate Principal Geologist by Snowden Mining Consultants Pty Ltd, who was engaged by Perpetual Resources Limited. Elizabeth Haren has sufficient experience that is relevant to the style of mineralisation and type of deposit under consideration and to the activity being undertaken to qualify as a Competent Person as defined in the 2012 Edition of the “Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves”. Elizabeth Haren consents to the inclusion in the report of the matters based on her information in the form and context in which it appears.

The information in this report that relates to Mineral Resources is based on information compiled by Dr Andrew Scogings, a Competent Person who is a Member of the Australasian Institute of Mining and Metallurgy, a Member of the Australian Institute of Geoscientists and is a Registered Professional Geologist in Industrial Minerals. Andrew Scogings is employed as an associate Executive Consultant Geologist by Snowden Mining Consultants Pty Ltd. Dr Scogings has sufficient experience that is relevant to the style of mineralisation and type of deposit under consideration and to the activity being undertaken to qualify as a Competent Person as defined in the 2012 Edition of the “Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves”. Dr Scogings consents to the inclusion in the report of the matters based on his information in the form and context in which it appears.

The information in this report that relates to the Beharra Ore Reserve is based on information reviewed or work undertaken by Mr Frank Blanchfield (FAusIMM). Mr Blanchfield is an employee of Snowden and has relied on Perpetual for marketing, environmental, permitting, and financial modelling and any costs not relating to mining and metallurgy. The mine design and mining costs and economic viability of the project were assessed and completed by Snowden under his direction. Mr Blanchfield has sufficient experience relevant to the style of mineralisation and type of deposit under consideration and to the preparation of mining studies to qualify as a Competent Person as defined by the JORC Code 2012. Mr Blanchfield consents to the inclusion in the report of the matters based on his information in the form and context in which it appears.

The scientific and technical information in this report that relates to process metallurgy is based on information reviewed and work completed by Arno Kruger (MAusIMM), who is a metallurgical consultant and employee of IHC Robbins. The metallurgical factors including process flowsheet design and costs and assumptions for the bulk aircore sample that relate to Mineral Resources have been reviewed and accepted by Mr Kruger. Mr Kruger has sufficient experience that is relevant to the type of processing under consideration and to the activity being undertaken to qualify as a Competent Person as defined by the JORC Code 2012. Mr Kruger consents to the inclusion in the report of the matters based on his information in the form and context in which it appears.

==> picture [133 x 48] intentionally omitted <==

Level 8, 84 Pitt Street, Sydney, NSW, 2000 www.perpetualresourceslimited.com.au

JORC CODE (2012) TABLE 1 REPORTING (SECTIONS 1, 2, 3, and 4)

Section 1: Sampling Techniques and data

Criteria JORC Code explanation Commentary
Sampling
techniques
Nature and quality of sampling (e.g. cut
channels, random chips, or specific
specialised industry standard
measurement tools appropriate to the
minerals under investigation, such as
downhole gamma sondes, or handheld
XRF instruments, etc). These examples
should not be taken as limiting the broad
meaning of sampling.
Include reference to measures taken to
ensure sample representivity and the
appropriate calibration of any
measurement tools or systems used.
Aspects of the determination of
mineralisation that are Material to the
Public Report.
In cases where ‘industry standard’ work
has been done this would be relatively
simple (e.g. ‘reverse circulation drilling
was used to obtain 1 m samples from
which 3 kg was pulverised to produce a
30 g charge for fire assay’). In other
cases, more explanation may be required,
such as where there is coarse gold that
has inherent sampling problems. Unusual
commodities or mineralisation types (e.g.
submarine nodules) may warrant
disclosure of detailed information.
Aircore drilling and sampling referred to in this report
occurred in two separate programs: March 2020 and
September 2020.
March 2020: Aircore samples were collected via a
cyclone, the entire sample for each 1 m drill interval was
collected and placed in a calico sample bag. No
splitting on the rig was undertaken. The sample was
labelled with the drillhole number and sample interval,
and a waterproof tag nominating a sample number was
placed in the bag and then sealed with a tie.
September 2020: Aircore samples were collected via a
cyclone, the entire sample for each 1 m drill interval was
collected and placed in a calico sample bag, labelled
with the drillhole number and sample interval, and
weighed by a spring balance. A 1 kg split was taken by
spear and placed in a smaller calico bag, labelled with
a sample number.
Aircore samples were collected from each metre drilled
or part metre if the hole was not ended on a full metre.
For the September program, separate samples were
taken for 0–0.5 m and for 0.5–1 m. Only the latter had
a 1 kg split taken from it.
Representative samples of each interval drilled were
placed in a chip tray for reference.
Auger drilling and sampling referred to in this report
and reported previously were obtained from hand
auguring to a maximum depth of 2 m.
Three auger samples were collected from each hole
being surface to 0.5 m, 0.5–1.0 m, and 1.0–2.0 m. The
top metre of the hole was split into two samples to allow
a separate sample of the top 0.5 m that contains
organic matter associated with native ground cover. If
sand mining operations were to be carried out, this top
0.5 m would be stockpiled for future rehabilitation, so at
this time treating it separately is appropriate.
The shallow auger program was carried out to obtain
representative sand samples to a maximum depth of 2
m for the reasons as described in the Company release
of 12 February2019.

==> picture [133 x 48] intentionally omitted <==

Level 8, 84 Pitt Street, Sydney, NSW, 2000 www.perpetualresourceslimited.com.au

Criteria JORC Code explanation Commentary
Drilling
techniques
Drill type (e.g. core, reverse circulation,
open-hole hammer, rotary air blast,
auger, Bangka, sonic, etc) and details
(e.g. core diameter, triple or standard
tube, depth of diamond tails, face-
sampling bit or other type, whether core is
oriented and if so, by what method, etc).
March 2020: A total of 32 aircore drillholes were
completed to an average depth of 12.3 m, with the
deepest hole ending at 17 m.
September 2020 aircore drilling was undertaken using
a track mounted KL170 hydraulic top drive rig coupled
to a 250 psi compressor. An 84 mm vacuum bit was
fitted to a 76 mm outside diameter twin tube rod string.
The internal diameter was 51 mm. All holes were drilled
vertically.
March 2020: A total of 40 aircore drillholes were
completed for an average depth of 12.7 m, with the
deepest hole ending at 20 m.
March 2020 aircore drilling was undertaken using a
track mounted Hitachi hydraulic top drive rig coupled to
a 130 cfm/100 psi compressor. A 76 mm aircore bit
was fitted to 70 mm twin tube rod string. All holes were
drilled vertically.
Auger drilling consisted of a manually hand operated
75 mm diameter sand auger (Dormer Sand Auger) with
PVC casing utilised to reduce contamination potential as
the auger is withdrawn from the hole. The auger was
driven about 300 mm then retracted and the sample
was placed in a UV resistant plastic bag and this
continued until the sample interval was completed. The
sample was labelled with the drillhole number and
sample interval, then placed in a second plastic bag
and sealed and removed from site for logging and
samplepreparation.
Drill sample
recovery
Method of recording and assessing core
and chip sample recoveries and results
assessed.
Measures taken to maximise sample
recovery and ensure representative
nature of the samples.
Whether a relationship exists between
sample recovery and grade and whether
sample bias may have occurred due to
preferential loss/gain of fine/coarse
material.
March 2020: Aircore – each sample bag was weighed
to determine the actual sample recovery, which resulted
in an average sample weight of approximately
7.5 kg/m of sample.
September 2020: Aircore – each sample bag was
weighed to determine the actual sample recovery, which
resulted in an average sample weight of approximately
4 kg/m of sample.
March 2020: Aircore sampling was typically terminated
on reaching the water table, which occurred around 10–
12 m below surface level.
September 2020: Aircore sampling was typically
terminated 2 m below the water table. Hole depths
ranged from 9 m to 17 m.
The cyclones were cleaned regularly to ensure maximum
and representative recovery.
For auger sampling, each sample bag was weighed to
determine the actual sample recovery, which resulted in
an average sample weight of 7.5 kg/m of sample.
The type of sand auger used provided a clean sample
with less possibility of contamination compared to a
flight auger.

==> picture [133 x 48] intentionally omitted <==

Level 8, 84 Pitt Street, Sydney, NSW, 2000 www.perpetualresourceslimited.com.au

Criteria JORC Code explanation Commentary
Logging Whether core and chip samples have
been geologically and geotechnically
logged to a level of detail to support
appropriate Mineral Resource estimation,
mining studies and metallurgical studies.
Whether logging is qualitative or
quantitative in nature. Core (or costean,
channel, etc) photography.
The total length and percentage of the
relevant intersections logged.
The samples have been sufficiently logged including
estimates of grain size, sorting and texture, and colour.
Particular attention has been taken to ensure a more
scientific and less subjective approach to colour has
been adopted because colour (white to grey shades,
and pale yellow shades) is one of the targeting
features.
Chip tray samples for each hole were photographed.
Subsampling
techniques
and sample
preparation
If core, whether cut or sawn and whether
quarter, half or all core taken.
If non-core, whether riffled, tube sampled,
rotary split, etc and whether sampled wet
or dry.
For all sample types, the nature, quality
and appropriateness of the sample
preparation technique.
Quality control procedures adopted for
all subsampling stages to maximise
representivity of samples.
Measures taken to ensure that the
sampling is representative of the in-situ
material collected, including for instance
results for field duplicate/second-half
sampling.
Whether sample sizes are appropriate to
the grain size of the material being
sampled.
Aircore samples were transported to Welshpool in Perth
and locked in a secure storage shed.
March 2020: Further check logging was undertaken, and
representative subsamples were taken for duplicate
analysis. Subsampling was carried out by spearing the
samples selected and collecting approximately 400 g of
sample. The duplicates have been utilised at the rate of
1:20.
September 2020: Duplicate 1 kg subsamples were
taken in a ratio of 1:18 at site.
Blanks were generated from a publicly available
washed sand product and taken by spearing a 20-bulk
sample: March 2020 approx.400 g samples;
September 2020 approx. 1 kg samples. The blanks
have been utilised at the rate of 1:20 in March and
1:18 in September.
March 2020: The prepared subsamples (duplicates and
blanks) plus all the bulk drill samples were submitted to
Nagrom Metallurgical Analytical Laboratories located in
Kelmscott in Western Perth for drying, further splitting,
and pulverisation in a zircon bowl. A subsample of
100 g with a P90 -75 µm particle size was utilised for
analysis.
September 2020: The 1 kg subsamples, including
duplicates and blanks, were submitted to Intertek
Genalysis analytical laboratory located in Maddington
in Western Perth for drying, splitting to 100 g for
pulverisation to a P90 -75 µm particle size in a zircon
bowl.
Auger samples were submitted to Intertek Laboratory in
Maddington for drying, splitting, pulverisation in a
zircon bowl. A subsample of 200 g with a 75μm
particle size is utilised for analysis.
Allowance was made for duplication by drilling a twin
auger hole located within 1 m of each other. Three twin
holes were drilled representing 8% duplicate sample.
The sample preparation methods are considered
industry standard for silica sands. Records were kept
describing whether the samples were submitted wet or
dry.

==> picture [133 x 48] intentionally omitted <==

Level 8, 84 Pitt Street, Sydney, NSW, 2000 www.perpetualresourceslimited.com.au

Criteria JORC Code explanation Commentary
The laboratory sample size taken is appropriate for the
sand beingtargeted.
Quality of
assay data
and
laboratory
tests
The nature, quality and appropriateness
of the assaying and laboratory
procedures used and whether the
technique is considered partial or total.
For geophysical tools, spectrometers,
handheld XRF instruments, etc, the
parameters used in determining the
analysis including instrument make and
model, reading times, calibrations factors
applied and their derivation, etc.
Nature of quality control procedures
adopted (e.g. standards, blanks,
duplicates, external laboratory checks)
and whether acceptable levels of
accuracy (i.e. lack of bias) and precision
have been established.
March 2020: All the aircore samples prepared by
Nagrom were analysed at the same facility. The assay
method for multi-element analysis consisted of prepared
samples fused in a lithium borate flux with lithium nitrate
additive then analysed by XRF (test method XRF001).
LOI was also carried out on each sample out at 1,000°C
(test method TGA002).
Auger samples were submitted to the Intertek
Laboratory in Maddington, Perth, Western Australia.
The assay method for multi-element analysis consisted of
four-acid digest including hydrofluoric, nitric, perchloric
and hydrochloric acids in Teflon beakers with inductively
coupled plasma (ICP)-optical (atomic) emission
spectrometry finish. Silica is reported by difference.
March 2020: Inter-laboratory checking was carried out
by submitting 28 prepared representative pulps (umpire
samples) to the Intertek Laboratory located in
Maddington. The samples were analysed by two
methods, XRF (test method FB1/XRF20) and ICP-optical
(atomic) emission spectrometry (test method
4ABSi/OE901). Samples for ICP analysis consisted of a
four-acid digest including hydrofluoric, nitric, perchloric
and hydrochloric acids in Teflon beakers. Silica is
reported by difference.
March 2020: The same 28 samples analysed by Intertek
were also analysed by ICP at Nagrom’ s laboratory.
For analysis of Al2O3and SiO2the samples were fused
with sodium peroxide and digested in dilute
hydrochloric acid and then analysed by ICP (test method
ICP005). All other elements were determined by ICP
after dissolution in an acid mixture (test method ICP003).
March 2020: Final analyses of the aircore samples were
carried out at Intertek’s laboratory using four-acid
digest followed by ICP determination. The samples used
consisted of pulps that were prepared by Nagrom.
September 2020: Intertek’s analysis method for silica
sands analysis consisted of four-acid digestion followed
by silica sands 17-element ICP/OE analysis plus LOI at
1,000°C with SiO2reported by difference.
September 2020: Inter-laboratory umpire analysis was
carried out by submitting 20 pulps, and 20 non-
pulverised portions of the same samples, from Intertek
Genalysis to the Bureau Veritas laboratory located in
Canning Vale, Perth. The samples were analysed by
mixed acid digest (MA100) followed by 17 elements by
ICP-OES (MA101) and LOI (TG001). Silica was
reported bydifference.

==> picture [133 x 48] intentionally omitted <==

Level 8, 84 Pitt Street, Sydney, NSW, 2000 www.perpetualresourceslimited.com.au

Criteria JORC Code explanation Commentary
The extensive analysis by different laboratories and
different methods are industry standard procedures and
methods producing high level of confidence on the
results produced. The ICP method is considered industry
standard for reporting sand grades.
Nogeophysical tools were utilised for theprocess.
Verification of
sampling and
assaying
The verification of significant intersections
by either independent or alternative
company personnel.
The use of twinned holes.
Documentation of primary data, data
entry procedures, data verification, data
storage (physical and electronic)
protocols.
Discuss any adjustment to assay data.
March 2020: There were no twin aircore holes.
Twin holes were completed for three out of the 38
auger holes.
September 2020: One of the September aircore holes
was twinned; two of the March 2020 aircore holes were
twinned.
All drilling and sampling procedures were monitored on
site by an independent geologist on a hole-by-hole
basis.
All primary information was initially captured in a
written log on site by a geologist, data entered,
imported then validated and stored in a geological
database.
March 2020: Additional check logging was carried by
an independent geologist in Perth prior to samples
being submitted to Nagrom for analysis.
No adjustments to assay data have been performed.
External review of umpire samples reported by Intertek
and Bureau Veritas was carried out.
Location of
data points
Accuracy and quality of surveys used to
locate drillholes (collar and downhole
surveys), trenches, mine workings and
other locations used in Mineral Resource
estimation.
Specification of the grid system used.
Quality and adequacy of topographic
control.
The position of the aircore hole locations was
determined by a Trimble R6 RTK global positioning
system (GPS) in RTK mode. The survey was carried out
by Heyhoe Surveys from Geraldton. Accuracy of 0.05 m
relative to SSM Dongara 49.
The position of the auger hole locations was determined
by a GPS model Garmin GPS Map 64s with an
accuracy of 5 m.
The CRS used was GDA94/MGA Zone 50 (ex SSM
DON49).
The topography at the project site currently under
exploration is flat to gentle undulating terrain. Site
survey (Heyhoe Surveys) have produced a ± 50 cm
DTM across the entireproject area.
Data spacing
and
distribution
Data spacing for reporting of Exploration
Results.
Whether the data spacing and
distribution is sufficient to establish the
degree of geological and grade
continuity appropriate for the Mineral
Resource and Ore Reserve estimation
procedure(s) and classifications applied.
Whether sample compositing has been
applied.
The aircore drillholes were spaced on an approx. 350–
600 m (east west) x 480 m along strike (north-south)
grid.
The auger drillholes were spaced on an approx. 400 m
(east-west) x 800 m (north-south) grid.
The adopted spacing at this time is sufficient based on
the geological continuity of the sand formation being
tested, and sufficient to be applied in Mineral Resource
estimation.
No sample compositingof holes has been applied.

==> picture [133 x 48] intentionally omitted <==

Level 8, 84 Pitt Street, Sydney, NSW, 2000 www.perpetualresourceslimited.com.au

Criteria JORC Code explanation Commentary
Orientation of
data in
relation to
geological
structure
Whether the orientation of sampling
achieves unbiased sampling of possible
structures and the extent to which this is
known, considering the deposit type.
If the relationship between the drilling
orientation and the orientation of key
mineralised structures is considered to
have introduced a sampling bias, this
should be assessed and reported if
material.
The orientation utilised for the aircore drilling campaign
represents the entire strike length of the aeolian dune
within the initial prospective target area and as such is
not expected to introduce any particular bias.
Sample
security
The measures taken to ensure sample
security.
All samples have been bagged and removed from site
and are under the care of the contract senior geologist
and field sampling supervisor.
March 2020: Aircore samples initially stored a secure
facility in Welshpool where sample reconciliation was
undertaken before delivery to Nagrom Laboratory.
March 2020: Aircore samples were delivered to
Nagrom in Kelmscott. The laboratory carried out a
sample reconciliation which was audited against the
sample submission sheet.
September 2020: Aircore samples and returned
samples and pulps from Intertek Genalysis are in the
Welshpool facility along with chip trays from both the
March and September drill programs.
Auger samples were delivered to Intertek Maddington.
The laboratory provided a sample reconciliation report
which was audited against the sample submission sheet.
Audits or
reviews
The results of any audits or reviews of
sampling techniques and data.
Guidance was provided by an independent consultant,
Andrew Scogings, on sampling lengths and hole spacings
who carried out a site visit to inspect the drilling and
samplingoperations.

Section 2: Reporting of Exploration Results

Criteria JORC Code explanation Commentary
Mineral
tenement and
land tenure
status
Type, reference name/number, location and
ownership including agreements or material
issues with third parties such as joint ventures,
partnerships, overriding royalties, native title
interests, historical sites, wilderness or national
park and environmental settings.
The security of the tenure held at the time of
reporting along with any known impediments
to obtaining a licence to operate in the area.
Miscellaneous licence L70/219 comprises an
effective land area of 10.36 km2and was granted
on 18 November 2020 for a period of 21 years.
The holder is Perpetual Resources Limited. A 1%
vendor royalty applies minerals sold from the
Licence.
The licence area exploration is covered by Crown
Land.
No impediments on a licence to operate at time of
reporting.
Exploration
done by other
parties
Acknowledgment and appraisal of exploration
by other parties.
Past exploration by others targeting heavy mineral
sands. Refer to ASX release dated 6 February
2019, historical exploration.

==> picture [133 x 48] intentionally omitted <==

Level 8, 84 Pitt Street, Sydney, NSW, 2000 www.perpetualresourceslimited.com.au

Criteria JORC Code explanation Commentary
Geology Deposit type, geological setting and style of
mineralisation.
Unconsolidated Quaternary coastal sediments, part
of the Perth Basin. Aeolian quartz sand dunes
overlying Pleistocene limestones and paleo-
coastline.
Drill hole
information
A summary of all information material to the
understanding of the exploration results
including a tabulation of the following
information for all Material drillholes:

easting and northing of the drillhole collar

elevation or RL (Reduced Level –
elevation above sea level in metres) of
the drillhole collar

dip and azimuth of the hole

downhole length and interception depth

hole length.
If the exclusion of this information is justified on
the basis that the information is not Material
and this exclusion does not detract from the
understanding of the report, the Competent
Person should clearly explain why this is the
case.
Exploration Results are not being reported here;
however, drillhole information can be found in ASX
release dated 1 April 2020 and 7 December
2020.
Data
aggregation
methods
In reporting Exploration Results, weighting
averaging techniques, maximum and/or
minimum grade truncations (e.g. cutting of high
grades) and cut-off grades are usually
Material and should be stated.
Where aggregate intercepts incorporate short
lengths of high-grade results and longer
lengths of low-grade results, the procedure
used for such aggregation should be stated
and some typical examples of such
aggregations should be shown in detail.
The assumptions used for any reporting of
metal equivalent values should be clearly
stated.
Exploration Results are not being reported.
Relationship
between
mineralisation
widths and
intercept
lengths
These relationships are particularly important
in the reporting of Exploration Results.
If the geometry of the mineralisation with
respect to the drillhole angle is known, its
nature should be reported.
If it is not known and only the downhole
lengths are reported, there should be a clear
statement to this effect (e.g. ‘downhole length,
true width not known’).
Exploration Results are not being reported.
Diagrams Appropriate maps and sections (with scales)
and tabulations of intercepts should be
included for any significant discovery being
reported These should include, but not be
limited to a plan view of drillhole collar
locations and appropriate sectional views.
Refer to figures incorporated in the body of the
report.

==> picture [133 x 48] intentionally omitted <==

Level 8, 84 Pitt Street, Sydney, NSW, 2000 www.perpetualresourceslimited.com.au

Criteria JORC Code explanation Commentary
Balanced
reporting
Where comprehensive reporting of all
Exploration Results is not practicable,
representative reporting of both low and high
grades and/or widths should be practiced to
avoid misleading reporting of Exploration
Results.
Exploration Results are not being reported.
Other
substantive
exploration
data
Other exploration data, if meaningful and
material, should be reported including (but not
limited to): geological observations;
geophysical survey results; geochemical survey
results; bulk samples – size and method of
treatment; metallurgical test results; bulk
density, groundwater, geotechnical and rock
characteristics; potential deleterious or
contaminating substances.
Groundwater was intersected in all holes that
exceeded 10 m depth. Water table generally
occurred between 10 m and 12 m.
Average in situ density (dry) determined to be
1.64 t/m3from six sites. Density locations were
hand excavated to 0.4 m deep. The Instrument
used was an Instrotek model Explorer. Tests were
performed by Western Geotechnical & Laboratory
Services.
For the March 2020 program particle size
distribution analysis was carried out on eight
representative samples. Tests were undertaken by
Western Geotechnical & Laboratory Services.
Previous metallurgical testwork was undertaken by
Nagrom to establish possible process methods to
provide a beneficiated product. Refer to ASX
releases of 30 January 2020 and 24 February
2020.
Petrological examination by Paul Ashley
undertaken and reported on 18 February 2020.
An approximate two tonnes bulk sample from the
March aircore drilling was process tested by IHCR
with results received in December 2020.
In-situ PSD was determined for 12 aircore holes
from the March 2020 program south of the Mount
Adams Road and for six holes from the September
2020 program to the north. The March 2020
samples were tested using a dry sieving method by
Diamantina Laboratories, Malaga and the
September 2020 samples were tested by Nagrom,
Kelmscott using a wet screening method.
In-situ particle size is predominantly within the
range of 0.15 mm to 0.6 mm.
About 70% of the sand grains are between 0.125
mm and 0.6 mm.
Calculated AFS numbers for the March 2020
samples are predominantly in the range 40–50.
The sands appear to become finer grained with
depth. This is illustrated by P50 which decreases
from about 400 µm to 300 µm for the March
2020 samples.
The September 2020 aircore results are generally
finer than the March 2020 aircore samples. It

==> picture [133 x 48] intentionally omitted <==

Level 8, 84 Pitt Street, Sydney, NSW, 2000 www.perpetualresourceslimited.com.au

Criteria JORC Code explanation Commentary
appears that there is a general trend of
decreasing grain size going north.
The apparently finer size of the September 2020
samples may be due to the wet screening method
used, compared with dry screening for the March
2020 samples. Wet screening is likely to be more
efficient than dry screening.
Snowden is of the opinion that the PSD results from
both programs need verification, by umpire testing
of September 2020 Nagrom samples at
Diamantina. Twins 20B019 and 20B032 should be
included for testing at both Robbins and Nagrom.
Infill holes should also be tested for PSD.
Further work The nature and scale of planned further work
(e.g. tests for lateral extensions or depth
extensions or large-scale step-out drilling).
Diagrams clearly highlighting the areas of
possible extensions, including the main
geological interpretations and future drilling
areas, provided this information is not
commerciallysensitive.
The Company will carry out further metallurgical
testwork.

Section 3: Estimation and Reporting of Mineral Resources

Criteria JORC Code explanation Commentary
Database
integrity
Measures taken to ensure that data has not
been corrupted by, for example, transcription
or keying errors, between its initial collection
and its use for Mineral Resource estimation
purposes.
Data validation procedures used.
Selected checks by Snowden of drillhole data
against original assay certificates were completed
with no errors identified.
Statistical checks completed to ensure all assays
fall within acceptable limits.
Checks on overlapping or duplicate intervals
completed.
Checks were completed on all samples which fell
below analytical detection limits to ensure samples
were assigned half detection limit grades in
estimation.
Site visits Comment on any site visits undertaken by the
Competent Person and the outcome of those
visits.
If no site visits have been undertaken indicate
whythis is the case.
The Competent Person, Andrew Scogings, visited
the site during the aircore drilling program in
March 2020.
Geological
interpretation
Confidence in (or conversely, the uncertainty
of) the geological interpretation of the mineral
deposit.
Nature of the data used and of any
assumptions made.
The effect, if any, of alternative
interpretations on Mineral Resource estimation.
The use of geology in guiding and controlling
Mineral Resource estimation.
Snowden believes the local geology is well
understood as a result of work undertaken by
Perpetual and other companies working in the
region.
Surfaces of the sand layers were interpreted
based on a combination of geochemistry and the
geological logging. Each layer was treated as a
hard boundary for resource modelling.

==> picture [133 x 48] intentionally omitted <==

Level 8, 84 Pitt Street, Sydney, NSW, 2000 www.perpetualresourceslimited.com.au

Criteria JORC Code explanation Commentary
The factors affecting continuity both of grade
and geology.
Alternative interpretations of the mineralisation
are unlikely to significantly change the overall
volume of the layers in terms of the reported
classified material.
Dimensions The extent and variability of the Mineral
Resource expressed as length (along strike or
otherwise), plan width, and depth below
surface to the upper and lower limits of the
Mineral Resource.
The deposit has an extent of approx. 7.1 km
north-south x 1.9 km east-west in the south and
1.2 km east-west in the north.
The deposit is restricted by tenement boundaries
and the Yardanogo Nature Reserve in the west.
The deposit is open outside of these limits.
Estimation and
modelling
techniques
The nature and appropriateness of the
estimation technique(s) applied and key
assumptions, including treatment of extreme
grade values, domaining, interpolation
parameters and maximum distance of
extrapolation from data points. If a computer
assisted estimation method was chosen include
a description of computer software and
parameters used.
The availability of check estimates, previous
estimates and/or mine production records and
whether the MRE takes appropriate account of
such data.
The assumptions made regarding recovery of
by-products.
Estimation of deleterious elements or other
non-grade variables of economic significance
(e.g. sulphur for acid mine drainage
characterisation).
In the case of block model interpolation, the
block size in relation to the average sample
spacing and the search employed.
Any assumptions behind modelling of selective
mining units.
Any assumptions about correlation between
variables.
Description of how the geological
interpretation was used to control the resource
estimates.
Discussion of basis for using or not using grade
cutting or capping.
The process of validation, the checking process
used, the comparison of model data to
drillhole data, and use of reconciliation data if
available.
Ordinary kriging estimation using a parent cell
size of 200 mE x 240 mN x 2 mRL to estimate for
SiO2, Al2O3, TiO2, Fe2O3and LOI.
Sample selection honoured geological domains
which were developed considering the vertical
chemical and geological trends of the profile. Five
layers were modelled: Yellow, White Upper,
White Lower, Light Grey Pod, Grey Pod and
Grey.
Statistical analysis by domain was completed. Top
cuts were applied to some elements in some layers
where appropriate to control sporadic extreme
values during estimation; however, no top cut was
applied for SiO2.
Variography was completed for all elements. Due
to the low number of samples for individual layers,
data was combined for variogram modelling.
Correlations were largely maintained by using
similar estimation parameters. Validation of block
estimates included visual and statistical checks,
both global and local. Checks were completed
against original and de-clustered drillhole
samples. The validations show that while smoothed,
the block estimates reproduce the trends observed
in the drillhole data.
Moisture Whether the tonnages are estimated on a dry
basis or with natural moisture, and the method
of determination of the moisture content.
All tonnages have been estimated as dry
tonnages.

==> picture [133 x 48] intentionally omitted <==

Level 8, 84 Pitt Street, Sydney, NSW, 2000 www.perpetualresourceslimited.com.au

Criteria JORC Code explanation Commentary
Cut-off
parameters
The basis of the adopted cut-off grade(s) or
quality parameters applied.
No cut-off parameters have been applied as the
yellow and white sand being reported appears to
be readily amenable to beneficiation to a suitable
product specification through relatively simple
metallurgical processes as demonstrated by initial
reported metallurgical testingresults.
Mining factors
or assumptions
Assumptions made regarding possible mining
methods, minimum mining dimensions and
internal (or, if applicable, external) mining
dilution. It is always necessary as part of the
process of determining reasonable prospects
for eventual economic extraction to consider
potential mining methods, but the assumptions
made regarding mining methods and
parameters when estimating Mineral Resources
may not always be rigorous. Where this is the
case, this should be reported with an
explanation of the basis of the mining
assumptions made.
It is assumed that the deposit will be mined using
conventional open cut mining methods.
No assumptions regarding minimum mining widths
and dilution have been made.
No mining has occurred.
Metallurgical
factors or
assumptions
The basis for assumptions or predictions
regarding metallurgical amenability. It is
always necessary as part of the process of
determining reasonable prospects for eventual
economic extraction to consider potential
metallurgical methods, but the assumptions
regarding metallurgical treatment processes
and parameters made when reporting Mineral
Resources may not always be rigorous. Where
this is the case, this should be reported with an
explanation of the basis of the metallurgical
assumptions made.
Eight composites were made of three sand types
from the 2020 aircore drill program and tested
for particle size distribution at Western
Geotechnical in Welshpool during April 2020. The
samples were described as light grey-white sand,
grey clayey sand and yellow sand. The in-situ PSD
is fairly consistent irrespective of the type of sand,
with approximately 85% of the sand between
0.15 mm and 0.6 mm.
A composite sample weighing 178.6 kg from nine
shallow auger holes drilled in 2019 was submitted
to Nagrom of Kelmscott, WA for process test work
which was reported in February 2020. The
process flowsheet included screening at 1 mm,
washing, attritioning, spiral separation, medium
intensity magnetic separation, acid leaching and
calcination. Gravcon Consultancy PL was
commissioned by Perpetual in June 2020 to
review the Nagrom results and the following notes
are derived from the Gravcon report.
The percentage of SiO2in the samples increased
during the test process while Fe2O3, TiO2, Al2O3
and LOI decreased relative to the head grade.
Attritioning and washing the material removed
fines and silt, which increased the SiO2content.
The spirals test produced samples where the
largest fraction of SiO2was in the light and
middlings fractions.

==> picture [133 x 48] intentionally omitted <==

Level 8, 84 Pitt Street, Sydney, NSW, 2000 www.perpetualresourceslimited.com.au

Criteria JORC Code explanation Commentary Commentary Commentary
Magnetic separation indicated that the largest
fraction of SiO2was in the middlings and non-
magnetic fractions. Acid leach tests showed that
hydrochloric acid reduced Al2O3and Fe2O3.
Repeat leaching had minimal impact and the use
of sulphuric acid alone or combined with
hydrochloric acid had minimal impact. Calcination
tests indicated limited improvement to product
quality.
Examples of SiO2and Fe2O3results for each
process stage are summarised as:
Process stage SiO2%
(XRF)
Fe2O3%
(XRF)
Feed -1 mm 99.037 0.127
Deslimed +75 micron 99.297 0.111
Spiral lights + middlings 99.594 0.045
MIMS non-magnetics 99.647 0.030
HCl leach 99.746 0.009
The particle size distribution (aircore samples) and
process testwork (auger composite sample)
indicate that the Beharra deposit may be suitable
for the production of silica sand for markets such
as glass, ceramics and foundry. However, it is
noted that the composite auger sample was from
shallow holes less than 2 m depth, that the
composite may not be truly representative of the
Beharra deposit and that further metallurgical
testwork on, for example, aircore drill samples is
recommended to verify the auger sample results
and to provide samples for potential customers in
the target markets.
Environmental
factors or
assumptions
Assumptions made regarding possible waste
and process residue disposal options. It is
always necessary as part of the process of
determining reasonable prospects for eventual
economic extraction to consider the potential
environmental impacts of the mining and
processing operation. While at this stage the
determination of potential environmental
impacts, particularly for a greenfields project,
may not always be well advanced, the status
of early consideration of these potential
environmental impacts should be reported.
Where these aspects have not been
considered this should be reported with an
explanation of the environmental assumptions
made.
It is assumed that no environmental factors exist
that could prohibit any potential mining
development at the deposit.

==> picture [133 x 48] intentionally omitted <==

Level 8, 84 Pitt Street, Sydney, NSW, 2000 www.perpetualresourceslimited.com.au

Criteria JORC Code explanation Commentary
Bulk density Whether assumed or determined. If assumed,
the basis for the assumptions. If determined,
the method used, whether wet or dry, the
frequency of the measurements, the nature,
size and representativeness of the samples.
The bulk density for bulk material must have
been measured by methods that adequately
account for void spaces (vughs, porosity, etc),
moisture and differences between rock and
alteration zones within the deposit.
Discuss assumptions for bulk density estimates
used in the evaluation process of the different
materials.
Six in-situ bulk density measurements were
completed by Western Geotechnical &
Laboratory Services using a nuclear densometer
and reported on 16 April 2020. The sites were
sampled in accordance with AS 1289.1.2.1-6.5.1
and tested in accordance with AS 1289.2.1.1. and
AS 1289.5.8.1. The results from the seven
measurements are corrected based on the
measured moisture factor. The dry density ranged
from 1.57 t/m3to 1.68 t/m3with an average dry
in situ density result of 1.64 t/m3which was
applied to the estimate.
The Competent Person is of the opinion that the
bulk density determined using recovered sample
weight, and nominal aircore or vacuum hole
diameter, supported the results from the nuclear
densometer method (1.64 t/m3) and the loose and
tapped methods (1.66 t/m3). Based on all data,
an average density of 1.64 t/m3as determined
by the nuclear densometer has been assumed for
the Project.
Classification The basis for the classification of the Mineral
Resources into varying confidence categories.
Whether appropriate account has been taken
of all relevant factors (i.e. relative confidence
in tonnage/grade estimations, reliability of
input data, confidence in continuity of geology
and metal values, quality, quantity and
distribution of the data).
Whether the result appropriately reflects the
Competent Person’s view of the deposit.
The Mineral Resource was classified based on
data quality, sample spacing, grade continuity,
geological continuity of the domains and
metallurgical/process test results into Inferred
material. The grey sands are considered
uneconomic at this stage and have been excluded.
The reported Mineral Resource does not include
any material within the Yardanogo Nature
Reserve which occupies a strip approximately
300 m wide on the western side of the tenement
and excludes a buffer of 50 m south and north of
Mount Adams Road.
The Mineral Resource classification appropriately
reflects the view of the Competent Person.
Audits or
reviews
The results of any audits or reviews of MREs. Snowden is not aware of any independent reviews
of the MRE.
Snowden’s internal review process ensures all work
meetsqualitystandards.
Discussion of
relative
accuracy/
confidence
Where appropriate a statement of the
relative accuracy and confidence level in the
MRE using an approach or procedure deemed
appropriate by the Competent Person. For
example, the application of statistical or
geostatistical procedures to quantify the
relative accuracy of the resource within stated
confidence limits, or, if such an approach is not
deemed appropriate, a qualitative discussion
of the factors that could affect the relative
accuracyand confidence of the estimate.
The Mineral Resource has been validated both
globally and locally against the input sample
data.
Estimates are considered to be accurate to a level
which supports mine planning – Indicated.
There is no operating mine at the Project, and as
such, no production data is available.

==> picture [133 x 48] intentionally omitted <==

Level 8, 84 Pitt Street, Sydney, NSW, 2000 www.perpetualresourceslimited.com.au

Criteria JORC Code explanation Commentary
The statement should specify whether it relates
to global or local estimates, and, if local, state
the relevant tonnages, which should be
relevant to technical and economic evaluation.
Documentation should include assumptions
made and the procedures used.
These statements of relative accuracy and
confidence of the estimate should be
compared with production data, where
available.

Section 4: Estimation and Reporting of Ore Reserves

Item JORC Code explanation Comments Comments Comments
Mineral
Resource for
conversion to
Mineral
Reserves
Description of the MRE used as a
basis for the conversion to an Ore
Reserve.
Clear statement as to whether the
Mineral Resources are reported
additional to, or inclusive of, the Ore
Reserves.
Mineral Resources for the Beharra deposit were reported in
February 2021 from a Datamine model
“beharra_20210210.dm”. No cut-off grade is applied for
the silica sand Mineral Resources and is commensurate with
other deposits.
Mineral Resources are reported inclusive of the Ore
Reserves.
Site visits Comment on any site visits
undertaken by the Competent Person
and the outcome of those visits.
If no site visits have been undertaken
indicate why this is the case.
Site visits were completed
Persons:
by the following Competent
Competent Persons Items Date of site visit
Frank Blanchfield Mining Dec 2020
Arno Kruger Metallurgy Feb 2021
Study status The type and level of study
undertaken to enable Mineral
Resources to be converted to Ore
Reserves.
The Code requires that a study to at
least PFS level has been undertaken
to convert Mineral Resources to Ore
Reserves. Such studies will have been
carried out and will have determined
a mine plan that is technically
achievable and economically viable,
and that material Modifying Factors
have been considered.
The Beharra Silica Project has been under technical
investigation as a PFS completed in March 2021.
Cut-off
parameters
The basis of the cut-off grade(s) or
quality parameters applied.
The ore inventory was required to have a Fe2O3average
below 2000ppm forplant feed consideration.
Mining factors
and
assumptions
The method and assumptions used as
reported in the PFS or Feasibility
Study to convert the Mineral
Resource to an Ore Reserve (i.e.
either by application of appropriate
factors by optimisation or by
preliminary or detailed design).
The choice, nature and
appropriateness of the selected
Snowden completed a mining prefeasibility study for the
Beharra Project in 2021. The study reflects the latest
understanding of the Project.
An evaluation using pit optimisation to produce an economic
mining shell followed by detailed pit design was used to
convert the Mineral Resource to an Ore Reserve. A mine
layout was developed for mining of staged designs mine
layout development. Mine equipment requirements were
determined bycontractors,whoprovidedpricingusingthe

==> picture [133 x 48] intentionally omitted <==

Level 8, 84 Pitt Street, Sydney, NSW, 2000 www.perpetualresourceslimited.com.au

Item JORC Code explanation Comments
mining method(s) and other mining
parameters including associated
design issues such as pre-strip,
access, etc.
The assumptions made regarding
geotechnical parameters (e.g. pit
slopes, stope sizes, etc), grade
control and pre-production drilling.
The major assumptions made and
Mineral Resource model used for pit
and stope optimisation (if
appropriate).
The mining dilution factors used.
The mining recovery factors used.
Any minimum mining widths used.
The manner in which Inferred Mineral
Resources are utilised in mining
studies and the sensitivity of the
outcome to their inclusion.
The infrastructure requirements of the
selected mining methods
Snowden mine production schedule as a basis. Selective
mining using an open pit load and haul mining cycle is used
for mining activities.
Geotechnical
Snowden completed a geotechnical analysis to
recommended pit slope design parameters for Beharra for
80 m deep pit as summarised as:
Batter
angle
(º)
Berm
width at
base of
batter
(m)
Batter
height
(m)
Inter-ramp
slope angle
(crest to
crest, °)
Overall
slope
angle
(crest to
toe, °)
30
NA
10
NA
30
Grade control
The drill density for Indicated Resources is sufficient to
define the flat ore basement. As the mining floor limit is
elevated by 0.5 m and the grade control in the basement
will be visual. There is a 0.5 m roof ore loss and this will be
sufficient to maximise or guarantee the quality of the ore.
Dilution
Dilution was essentially zero, however there were ore losses
from boundary losses (neighbouring nature reserve, Mount
Adams Road and 10 m lease offset corridor that were
about 5% of the available resources and floor and roof
loses and internal waste that was about 8% of the
available resources.
Schedule
Snowden identified a LOM schedule of 33 years suitable
for Ore Reserve assessment.
No in-pit Inferred Resources were used to quantify Ore
Reserves.
Metallurgical
factors and
assumptions
The metallurgical process proposed
and the appropriateness of that
process to the style of factors or
mineralisation.
Whether the metallurgical process is
well-tested technology or novel in
nature.
The nature, amount and
representativeness of metallurgical
test work undertaken, the nature of
the metallurgical domaining applied
and the corresponding metallurgical
recovery factors applied.
Any assumptions or allowances made
for deleterious elements.
The existence of any bulk sample or
pilot scale test work and the degree
to which such samples are considered
Metallurgical testwork
To date, metallurgical testing has been carried out in two
phases. The first phase of mineralogical examination, PSD
of aircore samples and process testing of hand auger
samples was reported on previously by Haren and Scogings
(2020).
The initial Phase 1 process testwork program was conducted
on the composite auger drill samples and indicated that the
Beharra deposit was suitable for producing silica sand for
markets such as glass, ceramics and foundry.
The second phase of metallurgical test work commenced in
Q3 2020 with Perpetual supplying approximately two
tonnes of sand samples from the March 2020 aircore drill
program to IHCR of Brisbane, a specialist mineral sands
laboratory, for bulk process testwork. This programme was
conducted using full size or genuinely scalable equipment
and the results are demonstrated in IHCR report 1959-PM-
REP-0000-8002.

==> picture [133 x 48] intentionally omitted <==

Level 8, 84 Pitt Street, Sydney, NSW, 2000 www.perpetualresourceslimited.com.au

Item JORC Code explanation Comments Comments Comments Comments Comments Comments Comments Comments
representative of the orebody as a
whole.
For minerals that are defined by a
specification, has the ore reserve
estimation been based on the
appropriate mineralogy to meet the
specifications
The resultant products derived from the IHCR 2.0T bulk
metallurgical test program were of high quality as
demonstrated in the table below.
Testwork Classification Product Classification Mass by
ROM
Assay
% ppm ppm ppm %
SiO2 Al2O3 Fe2O3 TiO2 LOI
% 97.9 9990 680 910 0.26
UCC Underflow(calc) Beharra Premium #44 74.4 99.6 1789 276 369 0.14
Screen O/S Beharra Premium #27 6.3 99.7 1405 235 300 0.13
Screen U/S Beharra Premium #46 68 99.6 1825 280 375 0.14
Calculation and determination of Ore Reserves is based on
producing Beharra Premium silica sand product #44, which
will have a SiO2of >99.5% and a Fe2O3of <280 ppm.
Mass yield into this product as per test work is calculated at
74.4%. (Ref: 1959-PM-REP-0000-8001 Rev 2).
Mineral Processing
The mineral processing flowsheet and plant required for the
upgrading of the mined material at Beharra is commonly
seen and used both in the quarrying and aggregates and
mineral sands industry. The separation techniques employed
are commonplace and include screening and desliming,
gravity, magnetic and physical separation.
Given the relatively small throughput requirement and
simplicity, traditional package plant suppliers were
approached for an all-inclusive turnkey solution, based on
the provided sound engineering documentation and the
proposed flowsheetprovided byPerpetual.
Environmental The status of studies of potential
environmental impacts of the mining
and processing operation. Details of
waste rock characterisation and the
consideration of potential sites, status
of design options considered and,
where applicable, the status of
approvals for process residue
storage and waste drum s should be
reported.
Environment
Considerable baseline environmental studies, commissioned
by Tiwest (now Tronox) for its Dongara titanium minerals
project, immediately adjacent to the Beharra Project have
been procured from Tronox via a data share arrangement.
This data significantly contributes to the environmental
impact assessment process to support approvals for Beharra
and covers factors including groundwater and groundwater-
dependent ecosystems, surface water, flora, vegetation,
weeds and dieback, terrestrial and subterranean fauna, soil
profiles and acid sulphate soils and indigenous heritage.
In addition, studies conducted to date by Perpetual to
complement the extensive Tronox dataset and cover the
following areas: flora and vegetation, terrestrial fauna,
groundwater and groundwater-dependent ecosystems and
heritage.
Mine rehabilitation
A comprehensive study was undertaken to determine the
most suitable progressive rehabilitation method for the
Beharra Project based on the existing environment.
Consultation and benchmarking with other extractive sand
miners in the local area as well as expert rehabilitation
practitioners was undertaken to assist in developing the
method.

==> picture [133 x 48] intentionally omitted <==

Level 8, 84 Pitt Street, Sydney, NSW, 2000 www.perpetualresourceslimited.com.au

Item JORC Code explanation Comments
Infrastructure The existence of appropriate
infrastructure: availability of land for
plant development, power, water,
transportation (particularly for bulk
commodities), labour,
accommodation; or the ease with
which the infrastructure can be
provided or accessed.
The Project site is easily accessed via the sealed Brand
Highway and unsealed Adams Road. There will be a
requirement for some road and intersection upgrade works
to support the volume of haul trucks required to transport
the final product to Geraldton.
An on-site power station and water supply infrastructure will
need to be constructed.
Labour will be sourced from the nearby towns of Dongara
and Geraldton, removing the requirement for onsite
accommodation.
Costs The derivation of, or assumptions
made, regarding projected capital
costs in the study.
The methodology used to estimate
operating costs.
Allowances made for the content of
deleterious elements.
The derivation of assumptions made
of metal or commodity price(s), for
the principal minerals and co-
products.
The source of exchange rates used in
the study.
Derivation of transportation charges.
The basis for forecasting or source of
treatment and refining charges,
penalties for failure to meet
specification, etc.
The allowances made or royalties
payable, both government and
private.
The capital cost estimate prepared by Perpetual includes
direct plant and supporting infrastructure, indirect costs and
is to an accuracy level of ±25% with a contingency of 10%
included.
Budget pricing was received from a process plant supply
and install contractor (inclusive of engineering, process and
materials handling equipment, E, I & C, process water circuit,
and associated structure and piping).
Budget pricing was also received for civil works, concrete,
fuel storage, power station, administration, amenities and
workshop infrastructure.
The operating cost estimate was developed as a bottom-up
estimate over the 32-year LOM to obtain average
operating costs. All significant and measurable items are
itemised, with smaller items estimated based on other silica
sand operations and the experience/expertise of project
consultants.
Mining costs were derived from tenders fielded to
appropriately qualified contract mining companies using pit
models provided by Snowden. A contract mining model has
been adopted and the raw mining cost provided by the
selected tenderer, has been included in the operating cost
estimate. This rate has then been brought forward into the
mining model.
Rehabilitation costs have been provided by Tetris
(Trajectory) based on a $/ha breakdown.
Specific consumption rates for reagents and consumables
were estimated through a combination of equipment
operating data, bench-scale testwork and modelling
software.
Current market pricing was obtained for all major
consumables and reagents based on supplier budget
pricing as of December 2020. A small general allowance
was made for minor miscellaneous consumables based on
historical data from similar operations.
Power station supply and install is included as a $kw/hr,
BOOM operational cost – supplying power and sized
accordingto the drawn loads on the equipment list.

==> picture [133 x 48] intentionally omitted <==

Level 8, 84 Pitt Street, Sydney, NSW, 2000 www.perpetualresourceslimited.com.au

Item JORC Code explanation Comments Comments Comments Comments
Maintenance costs were estimated based on projected
capital estimates for the plant using industry benchmarked
factors.
Remuneration rates typically expected in this area for
discipline personnel were used to establish operating costs,
with labour rates being sourced from three contributors:
AMMA, Gravcon, and Allied PD.
Perpetual has elected to use a flat A$:US$ exchange rate
of 75c across the forecast period, which is considered a
reasonable estimation of a likely long run average level.
Perpetual acknowledges that wide exchange rate
fluctuations are possible and could positively or negatively
affect the profitability and economic viability of the
Beharra Project at any single point in time. This risk will be
managed by the management team and Board of Directors
who may utilise an exchange rate hedging strategy should
it be considered appropriate at the time.
Annual operating costs – average years 1-5 at full
production
An average summary of annual operating costs forecast for
the first fiveyears of fullproduction are set out below:
OPEX (A$) Cost per
annum
($‘000)
A$/t
ore
A$/t
product
concentrate
Mining (ROM+OB) 10.6 5.18 6.97
Processing 5.0 2.46 3.31
Reject haulage 0.6 0.29 0.36
Administration 2.4 1.18 1.58
Transport + Port/
shiploading
39.4 19.40 26.09
Rehabilitation 1.8 0.43 0.58
Contingency 2.8 1.40 1.88
Royalty 3.5 1.71 2.30
Total OPEX 66.1 32.05 43.07
Pre-production capital costs
A summary of the pre-production capital estimate is set out
below:
CAPEX A$ Cost
($‘000)
()
Processplant(incl. water distribution) 19,287
Services and onsite infrastructure 3,537
Offsite infrastructure 9,272
Indirect, PCM and site office costs 2,338
Total development capital 34,434
Owners’ costs 1,343

==> picture [133 x 48] intentionally omitted <==

Level 8, 84 Pitt Street, Sydney, NSW, 2000 www.perpetualresourceslimited.com.au

Item JORC Code explanation Comments
Owner’s contingency (10%) 3,443
Totalpre-production capital 39,220
Revenue
factors
The derivation of, or assumptions
made regarding revenue factors
including head grade, metal or
commodity price(s) exchange rates,
transportation and treatment
charges, penalties, net smelter
returns, etc.
The derivation of assumptions made
of metal or commodity price(s), for
the principal metals, minerals and co-
products.
The grade of the process feed and iron content is supported
by the information in the MRE and driven by the mining and
production schedule. Processing recoveries were estimated
based on a metallurgical test program completed during
the PFS, using scalable processing equipment.
Perpetual engaged IMARC, to prepare an independent
market assessment of the APAC region, specifically
targeting selected countries and product grades.
Beharra metallurgical testwork to date has confirmed that
Beharra end-product to be suitable for sale into the 200–
300 ppm Fe2O3markets in the APAC region. In 2019, silica
sand with 200–300 ppm Fe2O3recorded a price of
between US$41.10 in China and US$71.60 per metric ton
in Japan.
Sell prices, in US$, have been forecast out to 2026 by
IMARC.
Based on the above and advice provided by industry
experts, Perpetual is confident that a sell price of US$50
per metric ton and above is achievable.
Market
assessment
The demand, supply and stock
situation for the particular
commodity, consumption trends
assessment and factors likely to
affect supply and demand into the
future.
A customer and competitor analysis
along with the identification of likely
market windows for the product.
Price and volume forecasts and the
basis for these forecasts.
For industrial minerals the customer
specification, testing and acceptance
requirements prior to a supply
contract.
The APAC market assessment revealed the APAC region to
be amongst the largest consumers of silica sand in the world
based on increasing utilisation in the glass and foundry
industries, reaching a value of US$5,133.7 million in 2020.
The forecast market value is expected to reach US$7,638.1
million by 2026, exhibiting a CAGR of 7.1% during this
period.
The forecast market consumption volume is expected to
reach 174.25 million metric tons by 2026, exhibiting a
CAGR of 4.8% during the 2021–2026 period.
In 2020, the glass industry represented the largest end use
sector for silica sand accounting for 37.6% of the total
APAC market volume, with foundry sand accounting for
27.1%.
Perpetual’s marketing strategy therefore is focussed on
targeting the APAC glass sand industry in the higher end
market based on products, initially in the 200–300 ppm
range in relation to iron, where prices range from
US$41.10/t in China to US$71.60/t in Japan.
Pricing for silica sand products in the APAC region vary by
a number of factors, mostly dictated by country of purchase
and impurity levels. In China, silica sand prices for higher
purity grades sell for between US$45/t and US$115/t, in
Korea this price range is US$55/t to US$130/t, and in
Japan the range is US75/t to US$190/t. Perpetual has
conservatively chosen a price of US$50/t FOB Geraldton
which provides significant scope for pricing upside as
marketingchannels are developed.

==> picture [133 x 48] intentionally omitted <==

Level 8, 84 Pitt Street, Sydney, NSW, 2000 www.perpetualresourceslimited.com.au

Item JORC Code explanation Comments
Perpetual has sent a number of samples to potential
customers in the APAC region, and has signed one
Memorandum of Understanding for offtake for up to
250,000 tons per annum with a Chinese end user called
Yaoguo Solar Science & Technology Co. Ltd (Yaoguo).
Yaoguo has already tested samples of Beharra silica sand
and have provided a positive response, with further
samples being sent to develop deeper discussions. Strong
indications have been provided by Yaoguo that Beharra
silica sand is suitable for the Asian market.
Economic The inputs to the economic analysis to
produce the NPV in the study, the
source and confidence of these
economic inputs including estimated
inflation, discount rate, etc.
NPV ranges and sensitivity to
variations in the significant
assumptions and inputs.
Financial modelling was completed by Perpetual, Snowden
is reliant on the commodity price projections advised by
Perpetual. Snowden is not an expert in the forecasting of
commodity prices, and other than to draw attention to the
sensitivity of the project to these projections, is not able to
comment on the risk that these projections will change over
time. However the commodity price estimate is based on the
2019 price outlook provided by IMARC and also the
professional opinion of Stratum Resources, which is a
specialist industrial mineral consultancy that provides advice
and trading in the silica sand markets regionally.
The key financial metrics for just the reserve portion of the
project are the IRR 54.6% and NPV 230.9 million @ %10
discount rate.
A real, pre-tax discount rate of 10.0% was applied based
on Perpetual’s calculated weighted average cost of capital
and also a comparison to other similar projects.
A long-term AUD: USD FX rate averaging 0.75:1 over the
LOM was applied, reflecting an approximation of the
average exchange rate over the last 40 years.
A sensitivity analysis on the NPV is provided below, which
looks to analyse the economic impact of key variables for
the Beharra Pproject, including:

Revenue per tonne

Changes in operating costs

Changes in capital costs

Exchange rate fluctuations

Changes in levels of project gearing.

==> picture [133 x 48] intentionally omitted <==

Level 8, 84 Pitt Street, Sydney, NSW, 2000 www.perpetualresourceslimited.com.au

Item JORC Code explanation Comments
Social The status of agreements with key
stakeholders and matters leading to
social licence to operate.
Perpetual has undertaken an assessment of its key
stakeholders that have a (statutory) interest in the Project,
including local government authorities, government agencies,
and other interested parties, i.e. Shires, traditional owners
etc). Perpetual will maintain a program of engagement
throughout the life of the project. Consultation will be aimed
at developing relationships that are mutually beneficial to
both parties. Stakeholders will be engaged early in the
planning process, primarily in the interests of achieving a
collaborative approach to raise any concerns and provide
Perpetual with the means to respond to feedback and to
ensure that local knowledge is considered in the design and
management of the project. A stakeholder register and
records of engagement are maintained.
Classification The basis for the classification of the
Ore Reserves into varying confidence
categories.
Whether the result appropriately
reflects the Competent Person’s view
of the deposit.
The proportion of Probable Ore
Reserves that have been derived
from Measured Mineral Resources (if
any).
The Beharra Ore Reserves are classified using the
guidelines of the JORC Code (2012).
In-pit Indicated Mineral Resources were used as the basis
for Probable Ore Reserve.
Other The status of agreements with key
stakeholders and matters leading to
social licence to operate.
To the extent relevant, the impact of
the following on the project and/or
on the estimation and classification of
the Ore Reserves:

Any identified material naturally
occurring risks.

The status of material legal
agreements and marketing
arrangements.

The status of governmental
agreements and approvals
critical to the viability of the
project, such as mineral
tenement status, and
government and statutory
approvals. There must be
reasonable grounds to expect
that all necessary government
approvals will be received within
the timeframes anticipated in
the PFS or feasibility study.
Highlight and discuss the
materiality of any unresolved
matter that is dependent on a
Perpetual recognises there is a potential human health
exposure risk to RCS at Beharra. RCS could be produced as
an airborne dust when silica sand is disturbed through
mineral extraction, stockpiling, transportation and handling
and is dry enough to generate dust particles. These particles
can be small enough to lodge deep in the lungs and cause
illness or disease such as bronchitis, silicosis and lung cancer.
A WES exists for crystalline silica and represents the
concentration of an airborne hazardous chemical within a
worker’s breathing zone that should not cause adverse
health effects or undue harm. The current WES for RCS is
0.1 mg/m3over an eight-hour working day in Western
Australia, with the WES likely to be lowered to 0.05 mg/m3
by the end of 2020 to meet national standards.
RCS exposure and safety requirements are governed by
the following Western Australian Legislation:

Occupational Safety and Health Act 1984

Occupational Safety and Health Regulations 1995

Mines Safety and Inspection Act 1994

Mines Safety and Inspection Regulations 1995.
Prior to the commencement of any extraction activities at the
Project, a HRA will be undertaken to define key sources and
the pathways of RCS. With this information, defined dust
management procedures to reduce the risk of exposure to
personnel above the WES will be developed using the
hierarchy of controls – substitution, isolation, engineering,
administrative,PPE.

==> picture [133 x 48] intentionally omitted <==

Level 8, 84 Pitt Street, Sydney, NSW, 2000 www.perpetualresourceslimited.com.au

Item JORC Code explanation Comments
third party on which extraction
of the reserve is contingent.
Additionally, the HRA will be a key input to the preparation
of a HHMP in accordance with the DMIRS Guideline
‘Preparation of health and hygiene management plan –
guide’ (2018) and approved by DMIRS prior to operations
commencing at the Project. The HHMP will define as a
minimum the sources, pathways management and monitoring
of RCS. The HHMP will be reviewed annually to ensure it
meets current standards and capture any changes to
operational circumstances or procedural controls. This will
enable Perpetual to maintain continual compliance with its
legislative health and safety obligations.
Currently, final product samples of Beharra Premium have
been provided from the resultant bulk metallurgical test
program to a variety of potential off takers.
Perpetual has not entered into any binding agreements or
arrangements with marketing agencies or consultants at this
time.
Audits or
reviews
The results of any audits or reviews
of Ore Reserve estimates.
There have not been no external audits ore reviews of the
2021 PFS.
The MRE, pit optimisation, design and schedule as
developed for the Beharra PFS were reviewed internally by
Snowden.
Relative
accuracy/
confidence
Where appropriate a statement of
the relative accuracy and confidence
level in the Ore Reserve estimate
using an approach or procedure
deemed appropriate by the
Competent Person. For example, the
application of statistical or
geostatistical procedures to quantify
the relative accuracy of the reserve
within stated confidence limits, or, if
such an approach is not deemed
appropriate, a qualitative discussion
of the factors which could affect the
relative accuracy and confidence of
the estimate.
The statement should specify whether
it relates to global or local estimates,
and, if local, state the relevant
tonnages, which should be relevant to
technical and economic evaluation.
Documentation should include
assumptions made and the
procedures used.
Accuracy and confidence discussions
should extend to specific discussions
of any applied Modifying Factors
that may have a material impact on
Ore Reserve viability, or for which
there are remainingareas of
The capital cost estimates in this study relating to mining,
processing and cost performance are underpinned by a
pre-feasibility level study. The capital cost estimate has an
assessed accuracy of ±25% and complies with the AusIMM
Class 4 PFS criteria.

==> picture [133 x 48] intentionally omitted <==

Level 8, 84 Pitt Street, Sydney, NSW, 2000 www.perpetualresourceslimited.com.au

Item JORC Code explanation Comments
uncertainty at the current study
stage.
It is recognised that this may not be
possible or appropriate in all
circumstances. These statements of
relative accuracy and confidence of
the estimate should be compared
with production data, where
available.

==> picture [133 x 48] intentionally omitted <==

Level 8, 84 Pitt Street, Sydney, NSW, 2000 www.perpetualresourceslimited.com.au

==> picture [195 x 60] intentionally omitted <==

BEHARRA SILICA PROJECT PRE-FEASIBILITY STUDY

MARCH 2021

==> picture [85 x 27] intentionally omitted <==

Document No. Rev Reason for Issue Date Author Review Approved
5221-PM-REP-0000-8010 A Draft for CP review 03/03/21 MRO Squad RBE
5221-PM-REP-0000-8010 B Final Issue 14/03/21 MRO JBA RBE

BEHARRA SILICA PROJECT PRE-FEASIBILITY STUDY

==> picture [85 x 27] intentionally omitted <==

CAUTIONARY STATEMENT

The Pre-Feasibility Study (PFS) discussed herein has been undertaken to study a range of options to further develop the technical and economic feasibility of the Beharra Silica Sands Project (the Project). The production target incorporates the Probable Ore Reserve that sits within the proposed mining area. There is also an additional portion of the Indicated Mineral Resource within the area that is identified for further metallurgical test work.

There is a moderate level of geological confidence associated with Indicated Mineral Resources however there is no certainty that further exploration work will result in the determination of a Measured Mineral Resource or that the production target itself will be realised. For the additional portion of the Indicated Mineral Resource, there is no certainty that the Indicated Mineral Resources will result in Ore Reserves.

The Ore Reserve and Mineral Resource Estimate underpinning the PFS have been prepared by Competent Persons in accordance with the requirements of the JORC Code. Competent Persons’ Statements are included in this document.

Investors should note that there is no certainty that Perpetual Resources Limited (Perpetual) will be able to raise funding required to commercialise the project when needed. It is also possible that such funding may only be available on terms that may be dilutive to or otherwise affect the value of Perpetuals’ existing shares. It is also possible that Perpetual could pursue other ‘value realisation’ strategies to provide alternative funding options.

Given the uncertainties involved, investors should not make any investment decisions based solely on the results of the Project PFS.

FORWARD-LOOKING STATEMENTS

Certain statements contained in this document may be ‘forward-looking’ and may include, amongst other things, statements regarding production targets, economic analysis, resource trends, pricing, recovery costs, and capital expenditure. These ‘forward–looking’ statements are necessarily based upon a number of estimates and assumptions that, while considered reasonable by Perpetual, are inherently subject to significant technical, business, economic, competitive, political and social uncertainties and contingencies and involve known and unknown risks and uncertainties that could cause actual events or results to differ materially from estimated or anticipated events or results reflected in such forward-looking statements.

Forward-looking statements are often, but not always, identified by the use of words such as ‘believe’, ‘expect’, ‘anticipate’, ‘indicate’, ‘target’, ‘plan’, ‘intends’, ‘budget’, ‘estimate’, ‘may’, ‘will’, ‘schedule’ and others of similar nature.

Perpetual does not undertake any obligation to update forward-looking statements even if circumstances or management’s estimates or opinions should change. Investors should not place undue reliance on forward-looking statements as they are not a guarantee of future performance.

DISCLAIMER

No representation or warranty, express or implied, is made by Perpetual that the material contained in this document will be achieved or proved correct. Except for statutory liability and the ASX Listing Rules which cannot be excluded, Perpetual and each of its directors, officers, employees, advisors and agents expressly disclaims any responsibility for the accuracy, correctness, reliability or completeness of the material contained in this document and excludes all liability whatsoever (including in negligence) for any loss or damage which may be suffered by any person through use or reliance on any information contained in or omitted from this document.

BEHARRA SILICA PROJECT PRE-FEASIBILITY STUDY

==> picture [85 x 27] intentionally omitted <==

TABLE OF CONTENTS

EXECUTIVE SUMMARY ..................................................................................................................................... 1

1. INTRODUCTION INTRODUCTION ................................................................................................................................ 8
1.1 SCOPE OFSTUDY ........................................................................................................................... 8
1.1.1 Report objectives and scope ................................................................................................................... 8
1.1.2 Methodology ............................................................................................................................................... 8
1.1.3 Conventions.................................................................................................................................................. 9
1.2 SITECONDITIONS ........................................................................................................................ 13
1.2.1 Location and site description ................................................................................................................ 13
1.2.2 Access and transport .............................................................................................................................. 14
1.2.3 Climatic conditions................................................................................................................................... 14
1.2.4 Local infrastructure.................................................................................................................................. 15
1.2.5 Population and socioeconomics ............................................................................................................ 15
1.2.6 Geraldton ................................................................................................................................................. 16
1.2.7 Dongara – Port Denison ........................................................................................................................ 16
1.2.8 Land use, flora and fauna .................................................................................................................... 17
1.3 PERMITS ANDAUTHORISATIONS .................................................................................................... 17
1.3.1 Government policy and regulations .................................................................................................... 17
2. MARKET ANALYSIS ......................................................................................................................... 19
2.1 SILICASANDS ............................................................................................................................. 19
2.1.1 Product specifications ............................................................................................................................. 19
2.1.2 Demand forecasts ................................................................................................................................... 22
2.1.3 Supply forecasts ...................................................................................................................................... 25
2.1.4 Marketing strategy ................................................................................................................................. 26
2.1.5 Target customers ..................................................................................................................................... 26
2.1.6 Pricing assumptions ................................................................................................................................. 26
3. MINERAL SPECIFICS ........................................................................................................................ 29
3.1 GEOLOGY ANDMINERALRESOURCE............................................................................................... 29
3.1.1 Geology and geological interpretation ............................................................................................ 29
3.1.2 Drilling, sampling and assaying ........................................................................................................... 29
3.1.3 Mineral Resource estimation ................................................................................................................. 29
3.1.4 Recommendations .................................................................................................................................... 30
3.2 MINING ..................................................................................................................................... 30
3.2.1 Introduction ............................................................................................................................................... 30
3.2.2 Conventions............................................................................................................................................... 30
3.2.3 Tenure description ................................................................................................................................... 31
3.2.4 Historical production ............................................................................................................................... 32
3.2.5 Mining method development ................................................................................................................ 32
3.2.6 Clearing and stripping ........................................................................................................................... 34
3.2.7 Drilling ....................................................................................................................................................... 34
3.2.8 Excavation guidance .............................................................................................................................. 34
3.2.9 Loading ..................................................................................................................................................... 35
3.2.10 Hauling ...................................................................................................................................................... 35
3.2.11 Tipping ...................................................................................................................................................... 36
3.2.12 Rehabilitation ........................................................................................................................................... 36
3.2.13 Ancillary .................................................................................................................................................... 36
3.2.14 Pit optimisation ........................................................................................................................................ 36
3.2.15 Mine design .............................................................................................................................................. 43
3.2.16 Mine schedule .......................................................................................................................................... 49
3.2.17 Life of mine schedule .............................................................................................................................. 51

BEHARRA SILICA PROJECT PRE-FEASIBILITY STUDY

==> picture [85 x 27] intentionally omitted <==

3.2.18 Reserve schedule ..................................................................................................................................... 55
3.2.19 Mine requirements .................................................................................................................................. 59
3.3 METALLURGY .............................................................................................................................. 60
3.3.1 Testwork regimes and programs ......................................................................................................... 60
3.3.2 Ore characteristics .................................................................................................................................. 61
3.3.3 Process selection and basis ................................................................................................................... 63
3.3.4 Feed preparation ................................................................................................................................... 63
3.3.5 Wet gravity circuit .................................................................................................................................. 64
3.3.6 Magnetic separation circuit .................................................................................................................. 65
3.3.7 Attritioning circuit .................................................................................................................................... 65
3.3.8 Classification circuit................................................................................................................................. 66
3.3.9 Product quality and recoveries ............................................................................................................ 67
3.3.10 Process flow overview ............................................................................................................................ 68
3.3.11 Process options......................................................................................................................................... 68
3.4 MINERALTREATMENT ANDHANDLING ............................................................................................ 69
3.4.1 Process facility description .................................................................................................................... 69
3.4.2 Process water supply.............................................................................................................................. 71
3.4.3 Rejects and water disposal ................................................................................................................... 71
3.4.4 Final product handling ........................................................................................................................... 72
4. INFRASTRUCTURE AND SERVICES .................................................................................................. 73
4.1 INFRASTRUCTUREREQUIREMENTS ................................................................................................... 73
4.2 **UTILITIES ** .................................................................................................................................... 73
4.2.1 Power supply ........................................................................................................................................... 73
4.2.2 Water supply ........................................................................................................................................... 74
4.2.3 Fuel supply................................................................................................................................................ 79
4.3 BUILDINGS ANDFACILITIES ............................................................................................................ 79
4.3.1 Offices ....................................................................................................................................................... 79
4.3.2 Workshops ................................................................................................................................................ 79
4.3.3 Mineral laboratory ................................................................................................................................. 79
4.4 TRANSPORTINFRASTRUCTURE ....................................................................................................... 79
4.4.1 Road .......................................................................................................................................................... 79
4.4.2 Rail ............................................................................................................................................................. 83
4.4.3 Port of Geraldton ................................................................................................................................... 85
4.5 COMMUNICATIONS ANDINFORMATIONSYSTEMS ............................................................................. 86
4.6 WASTEDISPOSAL ........................................................................................................................ 87
4.6.1 Surface water management ................................................................................................................. 87
4.6.2 Wastewater ............................................................................................................................................. 87
4.6.3 Solid waste ............................................................................................................................................... 87
4.7 TEMPORARYFACILITIES ................................................................................................................ 87
4.8 OTHER ....................................................................................................................................... 88
4.8.1 Security ...................................................................................................................................................... 88
4.8.2 Fire control ................................................................................................................................................ 88
4.8.3 Emergency services ................................................................................................................................. 88
5. OPERATIONS MANAGEMENT ......................................................................................................... 89
5.1 OPERATIONSSTRUCTURE .............................................................................................................. 89
5.1.1 Operating philosophy ............................................................................................................................ 89
5.1.2 Management structure and organisation ........................................................................................... 89
5.1.3 Contract strategy and management ................................................................................................... 89
5.2 OPERATIONALASPECTS ............................................................................................................... 89
5.2.1 Management and administration ........................................................................................................ 89

BEHARRA SILICA PROJECT PRE-FEASIBILITY STUDY

==> picture [85 x 27] intentionally omitted <==

5.2.2 Mining ........................................................................................................................................................ 89
5.2.3 Processing ................................................................................................................................................. 90
5.2.4 Technical services .................................................................................................................................... 90
5.2.5 Maintenance ............................................................................................................................................. 90
5.2.6 Procurement and supply ........................................................................................................................ 91
5.2.7 Transport and logistics ........................................................................................................................... 91
6. HEALTH, SAFETY, ENVIRONMENT, AND COMMUNITY .................................................................. 95
6.1 POLICY ANDPLANNING ................................................................................................................ 95
6.1.1 Company policy and objectives .......................................................................................................... 95
6.1.2 Statutory obligations and other commitments ................................................................................... 95
6.1.3 HSEC management systems .................................................................................................................. 95
6.1.4 Key performance indicators ................................................................................................................. 95
6.2 HEALTH ANDSAFETY ................................................................................................................... 95
6.2.1 Risk assessment summary ....................................................................................................................... 95
6.2.2 Silica-specific considerations ................................................................................................................ 95
6.2.3 Management and monitoring plan ...................................................................................................... 96
6.3 ENVIRONMENT ............................................................................................................................ 97
6.3.1 Environmental baseline studies ............................................................................................................. 97
6.3.2 Aspects and impacts assessment summary ........................................................................................ 97
6.3.3 Environmental management plan ........................................................................................................ 97
6.4 MINEREHABILITATION ANDCLOSURE ............................................................................................. 98
6.4.1 Mine rehabilitation.................................................................................................................................. 98
6.5 CULTURALHERITAGE ................................................................................................................. 100
6.5.1 Traditional owners ................................................................................................................................ 100
6.5.2 Native Title ............................................................................................................................................. 100
6.6 COMMUNITY ............................................................................................................................. 100
6.6.1 Community management and development .................................................................................... 100
6.6.2 External relations and stakeholder management .......................................................................... 101
6.6.3 Mine closure ........................................................................................................................................... 101
7. INDUSTRIAL RELATIONSHIP AND HUMAN RESOURCES .............................................................. 102
7.1 INDUSTRIALRELATIONSHIP .......................................................................................................... 102
7.1.1 Statutory obligations and other commitments ................................................................................. 102
7.1.2 Employee relations strategy ............................................................................................................... 102
7.2 HUMAN RESOURCES .................................................................................................................. 102
7.2.1 Organisational model and requirements ......................................................................................... 102
8. RISK MANAGEMENT ..................................................................................................................... 103
8.1 OBJECTIVES .............................................................................................................................. 103
8.2 SCOPE ..................................................................................................................................... 103
8.3 METHODOLOGY ........................................................................................................................ 103
8.4 PERMITTING ANDAPPROVALS ..................................................................................................... 104
8.4.1 Land use planning ................................................................................................................................. 104
8.4.2 Identified key risks ................................................................................................................................ 104
8.4.3 Scope of further investigations........................................................................................................... 104
8.4.4 Environmental conditions ...................................................................................................................... 105
8.4.5 Scope of further investigations........................................................................................................... 105
8.5 SURFACEGROUNDWATER ANDHYDROGEOLOGY ........................................................................... 105
8.5.1 Identified key risks ................................................................................................................................ 105
8.5.2 Discussion of key risks ........................................................................................................................... 106

BEHARRA SILICA PROJECT PRE-FEASIBILITY STUDY

==> picture [85 x 27] intentionally omitted <==

8.5.3 Scope of further investigation ............................................................................................................ 106
8.6 NATIVETITLE ANDHERITAGE ...................................................................................................... 106
8.6.1 Identified key risks ................................................................................................................................ 106
8.6.2 Discussion of key risks ........................................................................................................................... 106
8.6.3 Scope of further investigation ............................................................................................................ 106
8.7 TERRESTRIALECOLOGY ............................................................................................................... 106
8.7.1 Identified key risks ................................................................................................................................ 106
8.7.2 Discussion of key risks ........................................................................................................................... 107
8.7.3 Scope of further investigation ............................................................................................................ 107
8.8 COMMUNITY-BASEDRISKS .......................................................................................................... 107
8.8.1 Identified key risks ................................................................................................................................ 107
8.8.2 Scope of further investigation ............................................................................................................ 107
8.9 NON-ENVIRONMENTAL .............................................................................................................. 108
8.9.1 Identified key risks ................................................................................................................................ 108
8.9.2 Discussion of key risks ........................................................................................................................... 108
8.9.3 Scope of further investigation ............................................................................................................ 108
8.10 SUMMARY OFOUTCOMES ........................................................................................................... 108
8.11 RECOMMENDEDACTIONS ........................................................................................................... 109
8.12 RISKMANAGEMENTPLAN .......................................................................................................... 109
9. PROJECT MANAGEMENT ASPECTS ............................................................................................... 110
9.1 PROJECT MANAGEMENT ............................................................................................................. 110
9.1.1 Objectives ............................................................................................................................................... 110
9.1.2 Execution methodology ........................................................................................................................ 110
9.1.3 Cost management ................................................................................................................................. 110
9.1.4 Quality assurance ................................................................................................................................. 110
9.1.5 Risk management .................................................................................................................................. 111
9.1.6 Change management ........................................................................................................................... 111
9.1.7 Reporting and coordination ................................................................................................................ 111
9.2 PROJECT EXECUTION ................................................................................................................. 111
9.2.1 Work breakdown structure ................................................................................................................. 111
9.2.2 Project organisation .............................................................................................................................. 111
9.2.3 Contracting strategies .......................................................................................................................... 112
9.2.4 Engineering ............................................................................................................................................. 112
9.2.5 Construction ............................................................................................................................................ 112
9.2.6 Commissioning ........................................................................................................................................ 112
9.2.7 Commissioning handover ..................................................................................................................... 112
10. FINANCIAL ANALYSIS .................................................................................................................. 113
10.1 CONTEXT ................................................................................................................................. 113
10.1.1 Assumptions ............................................................................................................................................ 113
10.1.2 Taxation profile..................................................................................................................................... 115
10.2 CAPITALEXPENDITUREESTIMATE ................................................................................................. 115
10.2.1 Accuracy and scope of estimate ........................................................................................................ 115
10.2.2 Basis of estimate ................................................................................................................................... 117
10.2.3 Foreign exchange ................................................................................................................................. 117
10.3 OPERATINGCOSTESTIMATE ........................................................................................................ 117
10.3.1 Accuracy and scope of estimate ........................................................................................................ 117
10.3.2 Basis of estimate ................................................................................................................................... 117
10.3.3 Summary of estimate............................................................................................................................ 117
10.3.4 Cash flow model ................................................................................................................................... 117

BEHARRA SILICA PROJECT PRE-FEASIBILITY STUDY

==> picture [85 x 27] intentionally omitted <==

10.4 INVESTMENTEVALUATION .......................................................................................................... 118
10.4.1
Valuation methodology ....................................................................................................................... 118
10.4.2
Key project variables ........................................................................................................................... 119
10.4.3
Sensitivity analysis ................................................................................................................................ 119
10.4.4
Valuation results and key metrics ...................................................................................................... 120
11. JORC CODE (2012) TABLE 1 REPORTING (SECTIONS 1, 2, 3, AND 4) .......................................... 121
11.1 SECTION1: SAMPLINGTECHNIQUES AND DATA .............................................................................. 121
11.2 SECTION2: REPORTING OFEXPLORATIONRESULTS ......................................................................... 126
11.3 SECTION3: ESTIMATION ANDREPORTING OFMINERALRESOURCES .................................................. 128
11.4 SECTION4: ESTIMATION ANDREPORTING OFORERESERVES............................................................ 132
12. COMPETENT PERSONS STATEMENTS ............................................................................................ 141
13. EMBEDDED OPPORTUNITIES AND OPTIONS ................................................................................ 142
13.1 DRYMINING ANDSLURRIFICATIONUNIT(DMSU) .......................................................................... 142
13.2 CAMPAIGNMINING ................................................................................................................... 143
13.3 OTHER ..................................................................................................................................... 143
14. FURTHER WORKS .......................................................................................................................... 144
14.1 GEOLOGY ................................................................................................................................ 144
14.2 METALLURGY ............................................................................................................................ 144
14.3 LOGISTICS ................................................................................................................................ 144

BEHARRA SILICA PROJECT PRE-FEASIBILITY STUDY

==> picture [85 x 27] intentionally omitted <==

Index of Tables

Table 1.1: Beharra Indicated Mineral Resource (February 2021) ............................................................................................................... 1
Table 1.2: Beharra Probable Ore Reserve (March 2021) ............................................................................................................................. 2
Table 1.3: Beharra additional portion of Indicated Mineral Resources (March 2021) ........................................................................... 2
Table 1.4: Resultant products derived from the IHCR 2.0 tonne bulk metallurgical test program........................................................ 2
Table 1.5: Capital cost estimate ............................................................................................................................................................................ 5
Table 1.6: Operating cost estimate ...................................................................................................................................................................... 5
Table 1.1 Study conventions .................................................................................................................................................................................. 9
Table 1.2 Approvals and permitting ................................................................................................................................................................ 17
Table 3.1 Beharra Indicated Mineral Resource (February 2021) ............................................................................................................ 30
Table 3.2 Beharra tenement............................................................................................................................................................................... 31
Table 3.3 Ancillary equipment ........................................................................................................................................................................... 36
Table 3.4 Resource and mining model comparison ....................................................................................................................................... 39
Table 3.5 Pit optimisation result summary ....................................................................................................................................................... 42
Table 3.6 Pit inventory by profile ..................................................................................................................................................................... 46
Table 3.7 Pit inventory by panel....................................................................................................................................................................... 46
Table 3.8 Plant pad volumes.............................................................................................................................................................................. 47
Table 3.9 Wall backfill volumes........................................................................................................................................................................ 49
Table 3.10 Processing rate ................................................................................................................................................................................... 50
Table 3.11 Equipment............................................................................................................................................................................................. 60
Table 3.12 Consumables ........................................................................................................................................................................................ 60
Table 3.13 Personnel .............................................................................................................................................................................................. 60
Table 3.14 Homogenous sample makeup ......................................................................................................................................................... 61
Table 3.15 Head assay (as ROM)....................................................................................................................................................................... 62
Table 3.16 Head sample sizing ........................................................................................................................................................................... 62
Table 3.17 Head feed characterisation ............................................................................................................................................................ 63
Table 3.18 Feed preparation process (FPP) assay and distribution summary ......................................................................................... 63
Table 3.19 Gravity concentration process (GCP) assay and distribution summary ................................................................................ 65
Table 3.20 Magnetic upgrade process (MUP) assay and distribution summary ..................................................................................... 65
Table 3.21 Classification assay and distribution summary ............................................................................................................................ 66
Table 3.22 Product classification data ............................................................................................................................................................... 67
Table 3.23 Intermediate product assays ........................................................................................................................................................... 68
Table 4.1 Bulk commodities – Geraldton Port ............................................................................................................................................... 85
Table 5.1 Summary of costs ............................................................................................................................................................................... 92
Table 6.1 Beharra rehabilitation method........................................................................................................................................................ 98
Table 6.2 External stakeholders ...................................................................................................................................................................... 101
Table 8.1 Preliminary risk assessment categories ....................................................................................................................................... 104
Table 8.2 Land use planning ............................................................................................................................................................................ 104
Table 8.3 Environmental conditions – construction phase risks ................................................................................................................. 105
Table 8.4 Environmental conditions – operational phase risks ................................................................................................................. 105
Table 8.5 Surface water, groundwater, and hydrogeology – construction phase risks .................................................................... 105
Table 8.6 Surface water, groundwater, and hydrogeology – operational phase risks ................................................................... 105
Table 8.7 Native Title and heritage – project risks .................................................................................................................................... 106
Table 8.8 Terrestrial ecology – construction risks........................................................................................................................................ 106
Table 8.9 Terrestrial ecology – operational risks ....................................................................................................................................... 107
Table 8.10 Community-based risks ................................................................................................................................................................... 107
Table 8.11 Identified risks – non-environmental ............................................................................................................................................ 108
Table 8.12 Summary – key project risks.......................................................................................................................................................... 108
Table 10.1 Key financial model inputs ............................................................................................................................................................. 113
Table 10.2 Key financial model outputs .......................................................................................................................................................... 113
Table 10.3 Summary of cash costs .................................................................................................................................................................... 117
Table 10.4 NPV and IRR assessments under various assumptions .............................................................................................................. 118
Table 10.5 NPV and IRR assessed values........................................................................................................................................................ 118
Table 10.6 NPV sensitivity analysis given a change in one discrete variable of the financial model ............................................. 119
Table 10.7 NPV sensitivity analysis given a change in both price and operating cost in the financial model .............................. 119
Table 10.8 Key financial model outputs .......................................................................................................................................................... 120
Table 11.1 Beharra Probable Ore Reserve, March 2021 .......................................................................................................................... 132

Index of Figures

Figure 1 Price per tonne for 200–300 ppm Fe2O3silica sand (2017 to 2026) ................................................................................... 4
Figure 2 Key assessment criterion ...................................................................................................................................................................... 6
Figure 3 Beharra Project timeline and permitting and approvals ............................................................................................................. 6
Figure 1.1 Project location ................................................................................................................................................................................... 13
Figure 1.2 Representative site conditions and heath woodland ................................................................................................................. 14
Figure 1.3 Average maximum and minimum temperatures ......................................................................................................................... 14
Figure 1.4 Average monthly precipitation ....................................................................................................................................................... 15

BEHARRA SILICA PROJECT PRE-FEASIBILITY STUDY

==> picture [85 x 27] intentionally omitted <==

Figure 1.5 Mid-West region, WA ...................................................................................................................................................................... 15
Figure 1.6 Geraldton to site ................................................................................................................................................................................ 16
Figure 1.7 Dongara to site ................................................................................................................................................................................... 17
Figure 2.1 Silica sand microscopy– Beharra Project ..................................................................................................................................... 19
Figure 2.2 Beharra Premium technical data .................................................................................................................................................... 20
Figure 2.3 Beharra Special # 27 technical data ........................................................................................................................................... 21
Figure 2.4 Beharra Special #46 technical data ............................................................................................................................................ 22
Figure 2.5 APAC silica sand market forecast consumption value (2021–2026) .................................................................................... 23
Figure 2.6 APAC silica sand market forecast consumption volume (2021–2026) ................................................................................. 24
Figure 2.7 APAC silica sand market: breakup by end use .......................................................................................................................... 24
Figure 2.8 APAC silica sand market forecast consumption value (2021–2026) .................................................................................... 25
Figure 2.9 APAC silica sand market – supply market concentration ratio (2019) ................................................................................. 25
Figure 2.10 Market share analysis ....................................................................................................................................................................... 26
Figure 2.11 Silica sand pricing in APAC region ................................................................................................................................................ 27
Figure 2.12 Silica sand pricing in APAC region ................................................................................................................................................ 28
Figure 3.1 Beharra tenement............................................................................................................................................................................... 32
Figure 3.2 Beharra Resource profile ................................................................................................................................................................. 33
Figure 3.3 Mining cycle ......................................................................................................................................................................................... 34
Figure 3.4 50-tonne operating weight FEL ...................................................................................................................................................... 35
Figure 3.5 ADT ........................................................................................................................................................................................................ 35
Figure 3.6 Mineable area .................................................................................................................................................................................... 37
Figure 3.7 Pit optimisation results – physical ................................................................................................................................................... 40
Figure 3.8 Pit optimisation results – financial .................................................................................................................................................. 41
Figure 3.9 Pit optimisation pit shells .................................................................................................................................................................. 43
Figure 3.10 Pit design.............................................................................................................................................................................................. 44
Figure 3.11 Pit depth (m) ........................................................................................................................................................................................ 45
Figure 3.12 Plant pads ............................................................................................................................................................................................ 47
Figure 3.13 Pit wall backfill ................................................................................................................................................................................... 48
Figure 3.14 Pit wall backfill example section .................................................................................................................................................... 48
Figure 3.15 Cell sequence ...................................................................................................................................................................................... 50
Figure 3.16 Total movement by panel ................................................................................................................................................................ 51
Figure 3.17 Ex-pit movement by profile group ................................................................................................................................................ 51
Figure 3.18 Ex-pit movement and haul distance ............................................................................................................................................... 52
Figure 3.19 Ore feed by profile group .............................................................................................................................................................. 52
Figure 3.20 Ore feed grades ............................................................................................................................................................................... 53
Figure 3.21 Ore feed grades ............................................................................................................................................................................... 53
Figure 3.22 Plant product and rejects ................................................................................................................................................................. 54
Figure 3.23 Disturbance .......................................................................................................................................................................................... 54
Figure 3.24 Rehabilitation ...................................................................................................................................................................................... 55
Figure 3.25 Total movement by panel ................................................................................................................................................................ 55
Figure 3.26 Ex-pit movement by profile group ................................................................................................................................................ 56
Figure 3.27 Ex-pit movement and haul distance ............................................................................................................................................... 56
Figure 3.28 Ore feed by profile group .............................................................................................................................................................. 57
Figure 3.29 Ore feed grades ............................................................................................................................................................................... 57
Figure 3.30 Ore feed grades ............................................................................................................................................................................... 58
Figure 3.31 Plant product and rejects ................................................................................................................................................................. 58
Figure 3.32 Disturbance .......................................................................................................................................................................................... 59
Figure 3.33 Rehabilitation ...................................................................................................................................................................................... 59
Figure 3.34 Drilling samples identified for bulk sample composite ............................................................................................................. 61
Figure 3.35 Representative head sample makeup........................................................................................................................................... 62
Figure 3.36 Feed preparation – process flowsheet and mass flow ............................................................................................................. 63
Figure 3.37 Wet gravity circuit – process flowsheet and mass flow ........................................................................................................... 64
Figure 3.38 Magnetic separation circuit – process flowsheet and mass flow ............................................................................................ 65
Figure 3.39 Classification circuit – process flowsheet and mass flow .......................................................................................................... 66
Figure 3.40 Product size distribution .................................................................................................................................................................... 67
Figure 3.41 Process flowsheet ............................................................................................................................................................................... 68
Figure 3.42 Silica sand plant ................................................................................................................................................................................. 70
Figure 4.1 Typical thermal power station ........................................................................................................................................................ 73
Figure 4.2 Thermal power station – internal layout ...................................................................................................................................... 74
Figure 4.3 Yarragadee aquifer – saturated aquifer thickness................................................................................................................... 75
Figure 4.4 Yarragadee aquifer – groundwater salinity .............................................................................................................................. 76
Figure 4.5 Groundwater sub-areas (namely, Dongara, Eneabba Plains and Twin Hills) ..................................................................... 77
Figure 4.6 Typical pit section showing yellow, white, grey sands and water table .............................................................................. 78
Figure 4.7 Mount Adams Road – typical view east ....................................................................................................................................... 80
Figure 4.8 Mount Adams Road upgrade – route and elevation ................................................................................................................ 80
Figure 4.9 Brand Highway–Mount Adams Road intersection ...................................................................................................................... 81

BEHARRA SILICA PROJECT PRE-FEASIBILITY STUDY

==> picture [85 x 27] intentionally omitted <==

Figure 4.10 Proposed Dongara to Geraldton inland corridor ...................................................................................................................... 82
Figure 4.11 Dongara to Geraldton consultation timeline ............................................................................................................................... 83
Figure 4.12 Site to rail head ................................................................................................................................................................................. 83
Figure 4.13 Road and rail alignment .................................................................................................................................................................. 84
Figure 4.14 Geraldton Port ................................................................................................................................................................................... 85
Figure 4.15 Geraldton Port Master Plan ............................................................................................................................................................ 86
Figure 4.16 Telstra 4G coverage – Beharra project site ............................................................................................................................... 87
Figure 5.1 Road transport route – site to Narngulu ...................................................................................................................................... 92
Figure 5.2 Double configuration ......................................................................................................................................................................... 93
Figure 5.3 Pocket Road Train configuration .................................................................................................................................................... 93
Figure 5.4 PBS Super Triple configuration ....................................................................................................................................................... 93
Figure 5.5 Combination End Tipper ................................................................................................................................................................... 93
Figure 5.6 Combination Belly Dump .................................................................................................................................................................. 94
Figure 5.7 Narngulu to Geraldton Port locality ............................................................................................................................................. 94
Figure 7.1 Organisational model ..................................................................................................................................................................... 102
Figure 10.1 Beharra cumulative undiscounted and ungeared after-tax cash flow chart ..................................................................... 114
Figure 10.2 Discounted after-tax ungeared cash flow and NPV ............................................................................................................... 115
Figure 10.3 Summary of capital estimate ........................................................................................................................................................ 116
Figure 10.4 Beharra net undiscounted cash flow chart ................................................................................................................................. 118
Figure 10.5 After-tax NPV sensitivity to key variables ................................................................................................................................ 119
Figure 13.1 DMSU as quoted by IHCR .............................................................................................................................................................. 142
Figure 13.2 Alternative tracked containerised unit ........................................................................................................................................ 143
Figure 13.3 Alternative skid containerised unit ............................................................................................................................................... 143

Appendices Appendix 1 Scope of Works Packaged Plant and Equipment - prs2002-swr-gnr000-003 Rev 0 Appendix 2 Process Design Data - prs2002-spc-mch000-001 Rev 0 Appendix 3 Engineering Design Criteria - prs2002-dcr-gnr000-001 Rev 0 Appendix 4 IMARC Report Appendix 5 2021 01 AU10330 Perpetual Beharra Mineral Resource Estimate Report- March 2021 Appendix 6 Ore Reserve Statement Appendix 7 Drill Samples included in Bulk Sample Appendix 8 PFS Metallurgy Testwork Appendix 9 Site Layout 5221-M-GA-0000-8098 Rev A Appendix 10 Work Breakdown Structure Appendix 11 Estimate Basis Memorandum Appendix 12 Power Supply Report Appendix 13 Process Plant GA

BEHARRA SILICA PROJECT PRE-FEASIBILITY STUDY

==> picture [85 x 27] intentionally omitted <==

EXECUTIVE SUMMARY

INTRODUCTION

Perpetual Resources (“Perpetual” or “the Company”) is a progressive resource company actively pursuing opportunities in the silica sand market. The Company’s flagship asset, the Beharra Silica Project (“the Project”) is located 300 km north of Perth and is 96 km south of the port town of Geraldton in Western Australia.

Access to the Project from Geraldton and Perth is via the sealed Brand Highway, then via Mount Adams Road providing access to the centre of the Beharra project site. The seamless alignment of this infrastructure solution is considered a key sustainable advantage of the Beharra Project, which will utilise sealed roads the entire way from site through to an open-access deep water bulk commodities port.

Early positive results at Beharra have recently accelerated the Company’s efforts to develop the potential Project with a view to first production in Q4 2022.

This Pre-Feasibility Study (PFS) examines the requirement for the Project to generate a >99.5%+ SiO2 purity silica sand product at a production rate of nominally 1.51 Mtpa.

Some key features of the Beharra Project are:

  • A high quality SiO2, low Fe2O3 silica product

  • Readily extracted, uncomplicated free-flowing material

  • Simple metallurgical process flowsheet

  • Proximal to high quality road and port infrastructure

  • Environmental issues are well understood, data is shared by peer projects and manageable

  • Use of proven mine rehabilitation methods leads to a lower risk profile

  • Mineral sands history in the area equals skilled labour market available from Dongara, Geraldton areas

  • Located in a geopolitically stable jurisdiction

  • Demand for silica sand in the Asia Pacific (APAC) region continues to grow with strong buy price pressures.

The Company has been pragmatic and conservative in the project development process which has resulted in a largely de-risked project profile. Perpetual is pleased to present the PFS to investors and stakeholders alike, with positive financial results apparent and significant upside to be realised.

Further, the Company also considers that the level of detail and analysis in this PFS positions Perpetual well to consider a more rapid start-up or project advancement scenario.

GEOLOGY AND RESOURCE

Silica sand mineralisation at Beharra occurs within the coastal regions of the Perth Basin, and the targeted silica sand deposits are the aeolian quartz sand dunes that overlie the Pleistocene limestones and paleo-coastline.

The Mineral Resource was classified as Indicated based on data quality, sample spacing, grade continuity, geological continuity of the domains and metallurgical/process test results.

No cut-off grade has been used for the reported Mineral Resource as the layers considered potentially economic are amenable to beneficiation to a suitable product specification through relatively simple processes.

The Beharra Indicated Mineral Resource as of February 2021, with potential recovery fraction is reported below.

Table 1.1: Beharra Indicated Mineral Resource (February 2021) Beharra Indicated Mineral Resource (February 2021) Beharra Indicated Mineral Resource (February 2021) Beharra Indicated Mineral Resource (February 2021)
Sand Tonnes (Mt) SiO2 (%) Al2O3 (%) TiO2 (%) Fe2O3 (%) LOI % >75 **µm **
Tonnes (Mt) % Tonnes
Yellow
White
13.2
125.8
98.2
98.6
0.50
0.41
0.23
0.36
0.23
0.23
0.51
0.21
11.7
115.9
88.8
92.1
Total 139.0 98.6 0.42 0.35 0.23 0.24 127.6 91.8

BEHARRA SILICA PROJECT PRE-FEASIBILITY STUDY

1

==> picture [85 x 27] intentionally omitted <==

RESERVE AND MINING

Snowden Mining Industry Consultants Pty Ltd (Snowden) was engaged by Perpetual to undertake a PFS on the Beharra Silica Project. The objective of this study was to develop an Ore Reserve, and the works were conducted in two phases.

During the first phase of work, Snowden used the Beharra Inferred Mineral Resources to identify a mineral inventory, thus enabling planning for other study disciplines and to support mining operations budget quotations from mining contractors. Given the free-digging nature of the orebody, conventional truck and shovel methodologies were selected as the base case for mining operations.

During the second phase of works, mining costs derived from the quotations were used to support Ore Reserves using the updated Indicated Mineral Resources. All other aspects of the PFS, including the development of non-mining related operating costs and capital costs, were provided by Perpetual and its consultants for use as Modifying Factors in the estimation of Ore Reserves.

The Mineral Resource within the mining area has been classified as Indicated and the Ore Reserve classified as Probable.

The Ore Reserve estimate is provided as tabled below. The Ore Reserve is reported in accordance with Clause 49 of the JORC Code (2012) for the reporting of industrial minerals and Ore Reserves. The saleable silica product is reported rather than the “as-mined” product. Details of the completed mine planning process are available in the PFS document titled “Beharra Silica Project Pre-Feasibility Study”.

Table 1.2: Beharra Probable Ore Reserve (March 2021)

Sand Tonnes (Mt) SiO2 (%) Al2O3 (ppm) TiO2 (ppm) Fe2O3 (ppm) LOI (%)
In situ
Saleableproduct
64.1
47.6
98.6
99.6
4240
1789
3460
369
1950
276
0.235
0.100

An additional portion tonnage is also identified as provided in the table below. The portion is higher in iron and is reported without a saleable product.

Table 1.3: Beharra additional portion of Indicated Mineral Resources (March 2021)

Sand Tonnes (Mt) SiO2 (%) Al2O3 (ppm) TiO2 (ppm) Fe2O3 (ppm) LOI (%)
In situ 59.9 98.6 3900 3500 2640 0.270

Further details are provided in the Beharra Competent Persons Assessment JORC Code (2012), Table 1, Section 4.

METALLURGY

To date, metallurgical testing has been carried out in two phases. The first phase of mineralogical examination, particle size distribution (PSD) of aircore samples and process testing of hand auger samples was reported on previously by Haren and Scogings (2020).

The initial Phase 1 process testwork program was conducted on the composite auger drill samples and indicated that the Beharra deposit was suitable for producing silica sand for markets such as glass, ceramics and foundry.

The second phase of metallurgical testwork commenced in Q3 2020 with Perpetual supplying approximately 2 tonnes of sand samples from the March 2020 aircore drill program to IHC Robbins (IHCR) of Brisbane, a specialist mineral sands laboratory, for bulk process testwork. This program was conducted using full size or genuinely scalable equipment and the results are demonstrated in IHCR report 1959-PM-REP-0000-8002.

The resultant products derived from the IHCR 2.0 tonne bulk metallurgical test program were of high quality, as demonstrated in the table below.

Table 1.4: Resultant products derived from the IHCR 2.0 tonne bulk metallurgical test program

Testwork
classification
Product
classification
Mass by
ROM
Assay
SiO2 (%) Al2O3 (ppm) Fe2O3 (ppm) TiO2 (ppm) LOI (%)
% 97.9 9990 680 910 0.26
UCC Underflow
(calc.)
Beharra
Premium #44
74.4 99.6 1789 276 369 0.14
Screen O/S Beharra
Premium #27
6.3 99.7 1405 235 300 0.13
Screen U/S Beharra
Premium #46
68 99.6 1825 280 375 0.14

Source: Extract IHC Robbins report 1959-PM-REP-0000-8002.

2

BEHARRA SILICA PROJECT PRE-FEASIBILITY STUDY

==> picture [85 x 27] intentionally omitted <==

MINERAL PROCESSING

The mineral processing flowsheet and plant required for the upgrading of the mined material at Beharra is commonly seen and used both in the quarrying and aggregates and mineral sands industry. The separation techniques employed are commonplace and include screening and desliming, gravity, magnetic and physical separation. The process flowsheet chosen as the basis for the study is the result of extensive testwork, with the initial focus on achieving a lowest impurity prolife, particularly Fe2O3. The process flowsheet is therefore based on freely available equipment, readily customised to suite the Beharra orebody.

Given the relatively small throughput requirement and simplicity, traditional package plant suppliers were approached for an all-inclusive turnkey solution, based on sound engineering documentation and the proposed flowsheet provided by Perpetual.

MARKET ANALYSIS

The primary end use market suitable for Beharra product is the APAC glass industry, with a secondary focus on the APAC foundry industry. The glass goods industry is growing in APAC, especially in countries such as China, Japan, South Korea, India, and many other South-East Asian countries such as Vietnam, Thailand, Indonesia, etc. (as cited in IMARC Report SR090221K2).

DEMAND

APAC is amongst the largest consumers of silica sand based on its increasing utilisation in the glass and foundry industries as well as many other high growth applications. The current and forecast rising demand (Source: IMARC Report SR090221K2 – 6.1.2 and 6.2.2) for silica sand in the APAC region is being driven by many factors, including the following:

  • The rapid development of solar infrastructures is catalysing the installation of glass-based photovoltaic (PV) modules

  • • Increase in specialty glass demand due to the growing consumer electronics sector in the region

  • Increasing demand for foundry sand in the automobile industry

  • Manufacturing of PV panels and silicon-metal composite materials

  • The expanding construction industry

  • Rapid urbanisation propelling the demand for high-grade construction materials in both residential and commercial sectors

  • The growing infrastructural investments in various countries, such as China, India, Japan, South Korea, Vietnam, etc.

The APAC silica sand market reached a value of US$5,133.7 million in 2020 and looking forward is expected to reach a value of US$7,638.1 million by 2026 (Source: IMARC Report SR090221K2 – 5.7.2).

MARKET

The Beharra products fall in the 200–300 ppm range in relation to Fe2O3 (which is considered the key impurity of focus for buyers and end users). Based on the below and advice provided by industry experts, Perpetual is confident that a sell price of US$50/metric tonne FOB (free on board) Geraldton and above is achievable (Source: IMARC Report SR090221K2 – Price Trends figures 24, 37, 42, Industry Contacts, Perpetual Sales & Marketing Consultants).

3

BEHARRA SILICA PROJECT PRE-FEASIBILITY STUDY

==> picture [85 x 27] intentionally omitted <==

==> picture [428 x 247] intentionally omitted <==

Figure 1 Price per tonne for 200–300 ppm Fe2O3 silica sand (2017 to 2026) Source: IMARC Report SR090221K2

Based on ongoing testwork, potential exists for Perpetual to achieve a Beharra product that is <200 ppm Fe2O3, which, if achieved, may lead to a material increase in the revenue per tonne from the Project (Source: IMARC Report SR090221K2 – Price Trends figures 24, 37, 42, Industry Contacts, Perpetual Sales & Marketing Consultants). None of this potential revenue per ton upside has been modelled in this PFS but will be actively analysed and pursued in subsequent efforts.

HEALTH AND SAFETY

The Project will be delivered in accordance with highest health and safety standards and the Project execution is seen as low risk due to simple mining and operational requirements.

ENVIRONMENT

Considerable baseline environmental studies, commissioned by Tiwest (now Tronox) for its Dongara titanium minerals project, immediately adjacent to the Beharra Project, have been procured from Tronox via a data share arrangement.

This data significantly contributes to the Environmental Impact Assessment (EIA) process to support approvals for Beharra.

In addition, studies conducted to date by Perpetual to complement the extensive Tronox dataset and cover the following areas: flora and vegetation; terrestrial fauna; groundwater and groundwater dependent ecosystems; and heritage.

These past and ongoing efforts are considerable and are anticipated to enable Perpetual to achieve successful environmental approval in time. Perpetual will always adhere to a collaborative engagement process with the required state and federal departments as managing the environmental impact is acknowledged as a key element of a successful project.

MINE REHABILITATION

A comprehensive study was undertaken to determine the most suitable progressive rehabilitation method for the Beharra Project based on the existing environment. Consultation and benchmarking with other extractive sand miners in the local area as well as expert rehabilitation practitioners was undertaken to assist in developing the method. The chosen method of rehabilitation is seen as practical and effective while remaining economically viable.

RISK ASSESSMENT

The preliminary risk assessment was performed, and the Project was benchmarked against existing operations and detailed investigation of all aspects was undertaken. No fatal flaws have been highlighted and initial government and community engagement has been positive.

BEHARRA SILICA PROJECT PRE-FEASIBILITY STUDY

4

==> picture [85 x 27] intentionally omitted <==

There were no risks categorised as fatal flaws and a risk management plan and risk register will be developed and maintained as part of the Definitive Feasibility Study (DFS) and further works. Project risks can be found in Section 8.

CAPITAL AND OPERATING ESTIMATES

The capital estimate was compiled by Perpetual using pricing sought from suitably qualified vendors. Requests for quotation were circulated to the market via a competitive bid process for major items and recent historical pricing included where appropriate for minor plant and equipment. Perpetual considers that an exhaustive list of the capital items has been included in the capital estimates for the Beharra Project, as detailed in the table below.

The estimated capital requirement for the Project, inclusive of all direct, indirect, on-site and off-site infrastructure costs, is A$39.22 million. In addition, sustaining capital covering both operational and plant moves has been allowed for at A$1.2 million per annum.

Table 1.5: Capital cost estimate

Capital Cost (A$’000)
Process plant (including water distribution
Services and on-site infrastructure
Off-site infrastructure
Indirects,procurement construction management, and site office costs
19,287
3,537
9,272
2,338
Total development capital 34,434
Owner’s costs
Owner’s contingency (10%)
1,343
3,443
TOTAL PRE-PRODUCTION CAPITAL 39,220

The operating cost estimate includes all site-related operating costs associated with mining and processing ore to produce a >99.5% + silica sand product including transport on an FOB ship basis. A base estimate mining rate of nominally 2.0 Mtpa was established and on this basis the nett cost per tonne of product on an FOB basis is calculated to be A$43.07/t and A$66.1 million for the first five years at full production.

Table 1.6: Operating cost estimate

Capital Cost per annum
(A$’000)
$A/t ore A$/t production
Mining ROM + OB
Processing
Reject haulage
Administration
Transport + Port
Rehabilitation
Contingency
Royalty
10.6
5
0.6
2.4
39.4
1.8
2.8
3.5
5.18
2.46
0.29
1.18
19.4
0.43
1.4
1.71
6.97
3.31
0.36
1.58
26.09
0.58
1.88
2.3
TOTAL OPEX 66.1 32.05 43.07

The capital and operating costs are in line with similar types of industrial minerals projects.

FINANCIAL ANALYSIS

The financial analysis completed by Perpetual has been performed using discounted cash flow (DCF) analysis. All amounts are in Australian dollars (A$) and are nominal. Variability of input assumptions for capital, operating and sales price has been assessed using sensitivity analysis.

The key assessment criterion is the internal rate of return (IRR) on a nominal, after tax basis. Net present value (NPV) (@ 10%, nominal after tax), payback periods and capital funding requirements have also been assessed.

BEHARRA SILICA PROJECT PRE-FEASIBILITY STUDY

5

==> picture [85 x 27] intentionally omitted <==

==> picture [464 x 225] intentionally omitted <==

Figure 2 Key assessment criterion

SUMMARY

The Beharra PFS results confirm a highly cash positive mineral resource project. This outcome has been realised even when applying a conservative approach to all aspects of the study scope and costings.

Moving forward, reduction of capital and operating costs will be a key focus of future study efforts with potential for revenue increase by way of achieving higher final product yield, sourcing of additional higher priced markets, improvements in the impurity profile of Beharra end-product which may lead to increased revenue per tonne of product sold, and investigations of expansion cases will be thoroughly explored.

Perpetual is engaged in a variety of regulatory and development works for the Beharra Project. The overall timeline for development, permitting and approval activities is targeting commencement of construction in Q2 2022 with commencement of mining and processing operations in Q4 2022. The schedule is contingent upon regulatory and funding approvals as demonstrated in the schedule below.

==> picture [497 x 114] intentionally omitted <==

Figure 3 Beharra Project timeline and permitting and approvals

Opportunities and further works that have presented themselves during the study process are inclusive of but not limited to the following:

  • Selective processing of the white sand horizons which have potential to produce a lower impurity end-product which has potential to achieve a higher revenue per ton of product sales price

  • Campaign mining and processing scenarios that may have the potential to reduce operating costs

  • Dry mining and slurrification option (hydro-transport of run of mine (ROM)) which will potentially reduce operating cost

  • Potential truncation and simplifying of the metallurgical flowsheet to lower capital and operating costs whilst achieving a 200–300 ppm Fe2O3 product

  • Freight alternatives such as road + rail or rail which have potential to reduce operating costs

  • Direct port access as part of Mid-West Ports expansion project which could lead to increased sales tonnage and a reduction in unit costs

6

BEHARRA SILICA PROJECT PRE-FEASIBILITY STUDY

==> picture [85 x 27] intentionally omitted <==

  • Reduction of initial capital such as off-site infrastructure costs – for example, road intersection and upgrades (conversion to opex or shared costs with other operators)

  • Investigations of expansion cases in terms of increased plant throughput.

BEHARRA SILICA PROJECT PRE-FEASIBILITY STUDY

7

==> picture [85 x 27] intentionally omitted <==

1. INTRODUCTION

1.1 SCOPE OF STUDY

1.1.1

Report objectives and scope

This PFS addresses the greenfield development potential of Perpetual’s Beharra Silica Project. The Beharra Project is fully owned by Perpetual.

The PFS examines the requirement for the project to generate a >99.5%+ SiO2 purity silica sand product at a production rate of nominally 1.51 Mtpa. The purpose of the study is to develop capital costs and operating costs to a level of ±25% accuracy, based on JORC 2012 compliant Mineral Resource and Ore Reserve estimates.

Scope of study includes:

  • Geology and Resources

  • Mining, material handling and Reserves

  • Metallurgy and process plant

  • Infrastructure

  • Product handling and ship loading

  • Permitting, community and environment

  • Industrial relations

  • Capital and operating costs

  • Financial assessment

  • Risk management

  • Implementation schedule and plan.

The study includes recommendations and proposals for works going forward to further define operating parameters, capital estimation and resultant financial performance. These opportunities provide an avenue to add value to the Project by lowering operating costs and reducing operating complexity.

1.1.2

Methodology

In considering the requirements for the proposed Beharra Project, selected industry consultants and companies were engaged, including key professionals with significant experience in silica and mineral sands operations.

The core objectives adopted during the PFS are listed below:

  • Act in a responsible and respectful manner when engaging with all stakeholders

  • Maintain and comply with the JORC 2012 guidelines for project development

  • Further develop and quantify the mineral resource and upgrade the Mineral Resource estimate (MRE)

  • Carry out a representative bulk metallurgical program using composite samples derived from previous drill programs

  • Ensure the metallurgical program employed full size or genuinely scalable separation equipment in order to ensure real world results and identify the most amenable and cost-effective processing path (i.e. a physical separation lab)

  • Identify achievable silica product(s) specifications

  • Expend sufficient engineering effort to meet the ±25% confidence factor for the capital expenditure (CAPEX) estimate

  • Provide the Board of Perpetual with a comprehensive PFS document.

During this phase of study, much energy was directed towards further defining the mineral resource and conducting a representative bulk metallurgical test program to identify a sustainable final silica product quality.

8

BEHARRA SILICA PROJECT PRE-FEASIBILITY STUDY

==> picture [85 x 27] intentionally omitted <==

In parallel, further drilling was carried out under the direction of Competent Persons for exploration and resource estimation with the view to upgrade the MRE and further confirm the consistency of the orebody.

In relation to the development of the process and conceptual plant design, traditionally in the mineral sands industry, plant designs are bespoke by nature and require a significant engineering effort to be expended during study phases to quantify the plant and equipment. This is required due to the often highly variable mineral assemblages and convoluted retreat processes to arrive at either concentrate or final products.

By contrast, silica beneficiation plants are diametrically opposed in many ways to the heavy mineral sands industry in so much that rather than processing large throughputs in order to extract a relatively low grade of heavy mineral concentrate, silica operations generally provide high product yields returning relatively low ratio of rejects to the mine pit.

Given these much lower processing rates, they are more closely related to the quarrying and aggregates industry; this creates additional opportunities to access an array of package plants routinely operating in this sector.

With this in mind, the adopted strategy in relation to this processing plant involved the development of solid base engineering documentation and then the production of a very prescriptive Scope of Work (SoW) – attached at Appendix 1 – that was fielded to appropriately qualified package plant providers.

This SoW included metallurgical data, process flow diagrams and basis of design documents including firm battery limits in relation to the scope of supply. The process design and engineering design documents are attached at Appendix 2 and Appendix 3, respectively.

In relation to mine infrastructure, generally a minimalistic approach was applied to the operation, and enquiries were fielded to a variety of vendors for pricing in relation to site amenities, roadways, power supply etc.

Fortuitously, there is a wealth of information available in many aspects relating to the Mid-West coast of Western Australia (WA) that has been investigated by either active or prospective major mineral sands operators. This provided a good platform for additional investigations by Perpetual’s nominated consultants.

The study is to a PFS level for the capital and operating costs, based on a JORC 2012 compliant Ore Reserve.

The format of this report is:

  • Executive Summary

  • Introduction (Project overview) – Chapter 1

  • Individual sections of the report – Chapters 2 to 14

  • Supporting appendices.

1.1.3 Conventions

Table 1.1 Study conventions

Acronym Description of convention
$/t Australian dollars per tonne of product
$/ha Australian dollars per hectare
$c/kwhr Australian dollars and cents per kilowatt hour
$/litre Australian dollars per litre
ADT Articulated dump truck
AFS No. American Foundry Society Number
aka Also known as
APAC Asia Pacific
ASX Australian Stock Exchange
Al2O3 Aluminium oxide
Allied PD Allied Project Developments
ARC ARC Infrastructure
AUD Australian dollar

9

BEHARRA SILICA PROJECT PRE-FEASIBILITY STUDY

==> picture [85 x 27] intentionally omitted <==

Acronym Description of convention
BCM Bank cubic metre
BOOM Build-own-operate-maintain
CAGR Compound annual growth rate
CAPEX Capital expenditure
CCIWA Chamber of Commerce and Industry Western Australia
CCTV Closed circuit television
CMS Contractor Management System
Company Perpetual Resources Limited
CP Competent Person (as outlined under the JORC 2012 guidelines for project development)
DCF Discounted cash flow
dt Dry tonnes
DFS Definitive Feasibility Study
DMIRS Department of Mines, Industry Regulation and Safety
DMSU Dry mining slurrification unit
DPLH Department of Planning, Lands and Heritage
DSO Direct shipped ore
DWER Department of Water and Environmental Regulation
EBITDA Earnings before interest, taxes, depreciation and amortisation
EIA Environmental Impact Assessment
EMP Environmental Management Plan
PCM Procurement construction management
Fe Iron
Fe2O3 Iron oxide
FEL Front-end loader
FPP Feed preparation process
FOB Free on board
FTE Full-time employee
GCP Gravity concentration process
g/t Grams per tonne
GL Gigalitre
GPS Global positioning system
Gravcon Gravcon Consultants
GW Giga watts
GWhpa Giga watt hours per annum
ha Hectares
HCl Hydrogen chloride
HHMP Health and Hygiene Management Plan
HRA Health Risk Assessment
HR/IR Human Resources/Industrial Relations
HSEC Health, Safety, Environment and Community
ICP Inductively coupled plasma
IHCR IHC Robbins
ILUA Indigenous Land Use Agreement
IRR Internal rate of return
IPP Independent power provider

10

BEHARRA SILICA PROJECT PRE-FEASIBILITY STUDY

==> picture [85 x 27] intentionally omitted <==

Acronym Description of convention
JORC (Australian) Joint Ore Reserves Committee (Guidelines 2012)
kdt Thousands of dry tonnes
kg/t Kilograms per tonne
kl Kilolitre(s)
km Kilometre(s)
km2 Square kilometres
LOD Level of detection
LOI Loss on ignition
LOM Life of mine
LTI Lost-time injury
M Million(s)
Cubic metres
m³/hr Cubic metres an hour
Mdt Million dry tonnes
MI Mining Insights Pty Ltd
MG12 Spiral Separator
ML Mining Lease
mm Millimetres
Mm3 Million cubic metres
MRE Mineral Resource estimate
MRWA Main Roads Western Australia
Mt Million tonnes
Mtpa Million tonnes per annum
MUP Magnetic Upgrade Process
MWPA Mid-West Ports Authority
NPV Net present value
OEM Original equipment manufacturer
OPEX Operational expenditure
O/S Oversize
PEP Project Execution Plan
Perpetual Perpetual Resources Limited
PCS Project Consultancy Services Pty Ltd
PFS Prefeasibility study
PSD Particle size distribution
PPE Personal protective equipment
ppm Parts per million
P50 50% product passing size
P80 80% product passing size
PV Photovoltaic
QAQC Quality assurance/quality control
RCS Respirable crystalline silica
ROM Run of mine
RSO Radiation Safety Officer
SiO2 Silicon dioxide
SG Specific gravity

BEHARRA SILICA PROJECT PRE-FEASIBILITY STUDY

11

==> picture [85 x 27] intentionally omitted <==

Acronym Description of convention
SMP Safety management plan
SoW Scope of Work
t Tonnes
t/m3 Tonnes per cubic metre
tph Tonnes per hour
TDS Total dissolved solids
TiO2 Titanium dioxide
UCC Up-current classifier
µm Micrometre (also called micron)
US$ United States dollar(s)
UTM Universal Transverse Mercator
WA Western Australia
WBS Work breakdown structure
WHS Workplace Health and Safety
WES Workplace Exposure Standard
WHIMS Wet high-intensity magnetic separation
XRF X-ray fluorescence

12

BEHARRA SILICA PROJECT PRE-FEASIBILITY STUDY

==> picture [85 x 27] intentionally omitted <==

1.2 SITE CONDITIONS

1.2.1 Location and site description

The Beharra Project is located in WA, approximately 100 km south of the port town of Geraldton. The Project location is shown in Figure 1.1.

==> picture [298 x 432] intentionally omitted <==

Figure 1.1 Project location

The project area lies north and south of Mount Adams Road, is relatively flat to mildly undulating, and covered with low heath woodland. The total profile is sand and there are no seasonal watercourses. An example of the heath woodland is shown in Figure 1.2.

13

BEHARRA SILICA PROJECT PRE-FEASIBILITY STUDY

==> picture [85 x 27] intentionally omitted <==

==> picture [455 x 227] intentionally omitted <==

Figure 1.2 Representative site conditions and heath woodland

1.2.2 Access and transport

Access to the Project site from Geraldton (to the north) and Perth (to the south) is via the sealed Brand Highway, then the unsealed Mount Adams Road providing access to the centre of the tenure. The western end of Mount Adams Road links to the Perth-Geraldton railway via Carsons Road.

Separate studies have been conducted into road and rail transportation with transportation of final product by road being selected at this stage of the Project. Rail has not been discounted and is being considered as a future opportunity requiring further investigation as project development progresses. Pursuing a road transport scenario in early years affords Perpetual maximum operating and production flexibility.

1.2.3 Climatic conditions

The average monthly temperature recorded at Carnamah and the average monthly precipitation recorded at Green Grove are provided in Figure 1.3 and Figure 1.4, respectively. These provide an indication of the expected temperature and rainfall on the Beharra project site.

==> picture [455 x 106] intentionally omitted <==

Figure 1.3 Average maximum and minimum temperatures

Source: http://www.bom.gov.au

BEHARRA SILICA PROJECT PRE-FEASIBILITY STUDY

14

==> picture [85 x 27] intentionally omitted <==

==> picture [459 x 222] intentionally omitted <==

Figure 1.4 Average monthly precipitation Source: http://www.bom.gov.au

1.2.4

Local infrastructure

The Project is located south of Geraldton, which hosts a regional airport, accommodation, and health care facilities. Given the size of the commercial and industrial centre, the city is well placed to support the operation, inclusive of goods, services, and labour supply.

The Port of Geraldton is fully established and operational. The port is multimodal and will provide a location from which final product can be barged.

1.2.5

Population and socioeconomics

The Mid-West region shown in Figure 1.5 covers nearly one-fifth of WA’s land area, spanning around 478,000 km[2] from Green Head to Kalbarri and more than 800 km inland to Wiluna in the Gibson Desert. The region is divided into three subregions that demonstrate similarities in environment, land use, demography, and industry. These are the Batavia Coast, Murchison, and North Midlands sub-regions.

==> picture [455 x 263] intentionally omitted <==

Figure 1.5 Mid-West region, WA Source: DPIRD – WA – Mid West

BEHARRA SILICA PROJECT PRE-FEASIBILITY STUDY

15

==> picture [85 x 27] intentionally omitted <==

The Mid West has a diverse economy built around mining, agriculture, tourism, and fishing. Mining is its most valuable sector, with a range of minerals and energy deposits available including gold, iron ore, copper, nickel, silver, mineral sands, natural gas, and silica sand. Demand for the region’s resources has driven a rise in employment, triggering a number of new mining and construction projects and job growth in associated service sectors.

1.2.6 Geraldton

Geraldton, the region’s capital, is currently in the midst of an economic expansion and has significant capacity for further growth. Land availability is good, housing prices are affordable and existing infrastructure is wellestablished.

Strong business and economic connections exist between Geraldton and the Pilbara. Cutting edge science and technology will complement mining activity in the region and bring a variety of economic, training and education opportunities for its residents.

Geraldton is located 418 km (4.5 hours) by road northwest of Perth and 64 km (45 minutes) north of Dongara. Geraldton’s relationship to the Beharra project site by road is nominally 100 km (1 hour and 6 minutes). Figure 1.6 refers.

==> picture [455 x 269] intentionally omitted <==

Figure 1.6 Geraldton to site Source: Google Maps

1.2.7

Dongara – Port Denison

Dongara is located at the mouth of the Irwin River, nominally 350 km north-northwest of Perth accessed via the Brand Highway. Dongara is the seat of the Shire of Irwin which has a population of approximately 3,569, with 2,782 residing in the towns of Dongara and Port Denison. Dongara’s relationship to the Beharra project site by road is nominally 33 km (23 minutes). Figure 1.7 refers.

16

BEHARRA SILICA PROJECT PRE-FEASIBILITY STUDY

==> picture [85 x 27] intentionally omitted <==

==> picture [454 x 121] intentionally omitted <==

==> picture [454 x 121] intentionally omitted <==

Figure 1.7 Dongara to site

Source: Google Maps

1.2.8

Land use, flora and fauna

The project area lies to the north and south of Mount Adams Road. Apart from this road, some minor tracks and small areas of disturbance from previous exploration activities, the vegetation and soils are undisturbed. The area is part of a much larger expanse of native vegetation that is connected to Yardanogo Nature Reserve in the west and forms a broad corridor of native vegetation between cleared agricultural land. Clearing to the east is particularly extensive, but there are large reserves to the west and southwest.

1.3 PERMITS AND AUTHORISATIONS

1.3.1 Government policy and regulations

Key legislation and associated permits relevant to the Beharra Project are defined in Table 1.2. Perpetual has commenced the preparation of State and Federal statutory permits to enable the continued development of the Beharra Project.

Table 1.2 Approvals and permitting

Primary health, safety and Primary health, safety and environmental approvals and permitting – Project-specific environmental approvals and permitting – Project-specific
Legislation Permit Department Description Estimated
submission
Environmental Protection
and Biodiversity
Conservation Act 1999
Part 7 Referral
and EIA
Department of Agriculture,
Water and the Environment
Assessment and approval
of impacts to the Carnaby’s
Cockatoo
Q2 2021
Environmental Protection
Act 1986
Part IV
Referral and
EIA
Environmental Protection
Authority
Department of Water and
Environmental Regulation
Assessment and approval
of impacts to terrestrial
fauna, flora and
vegetation factors
Q2 2021
Part V Works
Approval and
Licence
Department of Water and
Environmental Regulation
Prescribed activities licence
to enable on site processing
of ore
Q4 2021
Mining Act 1978 Mining
Proposal
Department of Mines, Industry
Regulation and Safety
Approval for the
construction of mine
infrastructure and
undertaking mining
activities
Q4 2021

BEHARRA SILICA PROJECT PRE-FEASIBILITY STUDY

17

==> picture [85 x 27] intentionally omitted <==

Primary health, safety and Primary health, safety and environmental approvals and permitting – Project-specific environmental approvals and permitting – Project-specific
Legislation Permit Department Description Estimated
submission
Mine Closure
Plan
Department of Mines, Industry
Regulation and Safety
Defines rehabilitation and
closure prescriptions and
accompanies the Mining
Proposal
Q4 2021
Mines Safety and
Inspection Act 1994
Project
Management
Plan
Department of Mines, Industry
Regulation and Safety
Project safety plan
approval
Q4 2021
Rights in Water and
Irrigation Act 1914
26D Licence to
Construct a
Well
Department of Water and
Environmental Regulation
Enables the construction of
a water supply bore/s
Q4 2021
5C Licence to
Abstract
Water
Department of Water and
Environmental Regulation
Enables the abstraction and
use of water from supply
bore/s
Q4 2021

18

BEHARRA SILICA PROJECT PRE-FEASIBILITY STUDY

==> picture [85 x 27] intentionally omitted <==

2. MARKET ANALYSIS

2.1 SILICA SANDS

Silica sand, also called industrial sand, is primarily composed of quartz and other materials, such as feldspars, carbonates, clay mineral, iron oxides, etc. Silica sand finds diverse applications in glassmaking, hydraulic fracturing, water filtration, industrial casting, sandblasting, etc. This can be accredited to its several benefits, such as high granularity, strength, durability, better resistance against heat and chemical reactions, etc.

Silica sand forms the major ingredient among natural raw materials required for glass making, and it is also used in foundry, ferro-silica alloy and cement industries besides being used in many other industries like ceramic, fertiliser, abrasives, chemical, coal washery, electrode, paint, rubber, textile, water filtration, construction, etc.

The primary end use market suitable to Beharra product is the glass industry, with a secondary focus on the foundry industry. The glass goods industry is growing in APAC (IMARC Report SR090221K2), especially in countries such as China, Japan, South Korea, India, and many other South-East Asian countries such as Vietnam, Thailand, Indonesia, etc. Major global players in the glass industry are shifting their production base to APAC countries. Rapid industrialisation, urbanisation and increasing adoption of smart and energy-efficient methods are driving glass production rates throughout the region. Furthermore, the use of specialty glass in electronic materials in developed countries, such as Japan, is projected to drive the market in the future.

A sample of silica sand from the Beharra project site is shown in Figure 2.1.

==> picture [389 x 292] intentionally omitted <==

Figure 2.1 Silica sand microscopy– Beharra Project

2.1.1 Product specifications

Three products have been produced as a result of the metallurgical test program conducted during the PFS: Beharra Premium#44, Beharra Special #27, and Beharra Special #46.

The yield to Beharra Premium #44 represents 74.4% of the bulk ROM feed sample, derived from Beharra Special #27 and Beharra Special #46 combined to form the single saleable glass sand product being used as the basis for the PFS.

Product specifications are provided in the technical data sheets located in Figure 2.2, Figure 2.3 and Figure 2.4, respectively.

19

BEHARRA SILICA PROJECT PRE-FEASIBILITY STUDY

==> picture [85 x 27] intentionally omitted <==

==> picture [395 x 525] intentionally omitted <==

Figure 2.2 Beharra Premium technical data

20

BEHARRA SILICA PROJECT PRE-FEASIBILITY STUDY

==> picture [85 x 27] intentionally omitted <==

==> picture [455 x 604] intentionally omitted <==

Figure 2.3 Beharra Special # 27 technical data

21

BEHARRA SILICA PROJECT PRE-FEASIBILITY STUDY

==> picture [85 x 27] intentionally omitted <==

==> picture [455 x 598] intentionally omitted <==

Figure 2.4 Beharra Special #46 technical data

It should be noted that Perpetual continues to analyse and test the Beharra orebody and anticipates additional potential product streams will be identified. Perpetual aims to maximise the potential revenue per tonne from Beharra through optimisation of product specifications produced.

2.1.2 Demand forecasts

Perpetual engaged IMARC to provide a report, attached at Appendix 4, on the APAC silica sand market, incorporating industry trends, share, size, growth, opportunities and forecasts out to 2026.

22

BEHARRA SILICA PROJECT PRE-FEASIBILITY STUDY

==> picture [85 x 27] intentionally omitted <==

APAC is amongst the largest consumers of silica sand based on its increasing utilisation in the glass and foundry industries as well as many other high growth applications. The current and forecast rising demand for silica sand in the APAC region is being driven by many factors, including the following:

  • The rapid development of solar infrastructures is catalysing the installation of glass-based PV modules

  • Increase in specialty glass demand due to the growing consumer electronics sector in the region

  • Increasing demand for foundry sand in the automobile industry

  • Manufacturing of PV panels and silicon-metal composite materials

  • The expanding construction industry

  • Rapid urbanisation propelling the demand for high-grade construction materials in both residential and commercial sectors

  • The growing infrastructural investments in various countries, such as China, India, Japan, South Korea, Vietnam, etc.

The APAC silica sand market reached a value of US$5,133.7 million in 2020.

Looking forward, the APAC silica sand market is expected to reach a value of US$7,638.1 million by 2026, exhibiting a compound annual growth rate (CAGR) of 7.1% during 2021–2026. Figure 2.5 refers.

==> picture [347 x 199] intentionally omitted <==

Figure 2.5 APAC silica sand market forecast consumption value (2021–2026) Source: IMARC Group

Market growth is expected to reach a consumption volume 174.25 million metric tons by 2026, growing at a CAGR of 4.8% during 2021–2026. Figure 2.6 refers.

23

BEHARRA SILICA PROJECT PRE-FEASIBILITY STUDY

==> picture [85 x 27] intentionally omitted <==

==> picture [369 x 239] intentionally omitted <==

Figure 2.6 APAC silica sand market forecast consumption volume (2021–2026) Source: IMARC Group

In 2020, the glass industry represented the largest end use sector for silica sand accounting for 37.6% of the total volume of the APAC silica sand market. See Figure 2.7 for end-use market breakup.

==> picture [264 x 266] intentionally omitted <==

Figure 2.7 APAC silica sand market: breakup by end use Source: IMARC Group

By 2026, the glass industry is expected to dominate the APAC silica sand market, accounting for 38.9% of the total market, with foundry sand applications the next largest, comprising 25.6% of the total market. Figure 2.8 refers.

24

BEHARRA SILICA PROJECT PRE-FEASIBILITY STUDY

==> picture [85 x 27] intentionally omitted <==

==> picture [455 x 88] intentionally omitted <==

Figure 2.8 APAC silica sand market forecast consumption value (2021–2026) Source: IMARC Group

The growth for silica sand in glass making is attributed to increasing demand from the food and beverage sector, owing to rise in demand for transparency and hygienic packaging of products, as well as the rapid increase in architectural glass used in construction.

Emerging trends such as increasing usage of hybrid guide plate, solar control glazing for automotive and building glasses, lightweight glazing glass, and advanced nanotechnology in flat glass are also contributing towards the growth of the glass industry, consequently, boosting the demand for silica sand.

The forecast market in this segment is expected to reach a consumption volume of 67.84 million metric tons by 2026, exhibiting a CAGR of 5.4% during 2021–2026.

2.1.3

Supply forecasts

The supply market concentration ratio in 2019 for the APAC silica sand market is shown in Figure 2.9 and market share analysis in Figure 2.10.

==> picture [455 x 222] intentionally omitted <==

Figure 2.9 APAC silica sand market – supply market concentration ratio (2019) Source: UMR Analysis

25

BEHARRA SILICA PROJECT PRE-FEASIBILITY STUDY

==> picture [85 x 27] intentionally omitted <==

==> picture [455 x 261] intentionally omitted <==

Figure 2.10 Market share analysis Source: UMR Analysis

The Beharra Project will be competing within the larger Tier 3 supply market which consists of a multitude of companies, each having held a market share less than 0.5% on average.

2.1.4

Marketing strategy

Companies in the APAC silica sand market are expected to adopt the following strategies to compete in the market:

  • New applications: The use of this sand in specialty glass used in the production of electronic components is projected to create opportunities for market players in the near future.

  • Local suppliers: Sourcing local suppliers can reduce transportation costs and time taken for transportation. Choosing local supplier is projected to create opportunities for small local businesses to enter the market.

  • Competitive prices: Currently, the APAC silica sand market is fragmented with many suppliers trying to sell their products. Selling the silica sand at competitive prices in the market can help suppliers to gain presence in the market, although this strategy is hampered by logistics costs and also the prevalence of suitable geological characteristics.

  • Adoption of omni-channel concept: The adoption of online sales channels by companies is important, as many retailers are engaged in ordering products in bulk through online stores. Moreover, this strategy helps companies to withstand the uncertain crisis in the market such as COVID-19.

2.1.5

Target customers

The Beharra product can be supplied into the glass sand and foundry end use markets. Perpetual will be targeting potential customers in the APAC region within both these market areas.

2.1.6

Pricing assumptions

The price of silica sand varies according to the product grade and geographic region of end use. The main (but not only) determinant of silica sand product grade is the concentration of Fe2O3 in the final end-product, measured in parts per million (ppm).

The lower the ppm grade level, the higher the purity level of the silica sand.

In 2019, silica sand with 150–200 ppm recorded a price of between US$102.30 in China and US$184.50 per metric ton in Japan (refer Figure 2.11).

26

BEHARRA SILICA PROJECT PRE-FEASIBILITY STUDY

==> picture [85 x 27] intentionally omitted <==

==> picture [459 x 269] intentionally omitted <==

Figure 2.11 Silica sand pricing in APAC region Source: IMARC

A very high purity silica sand of lowest ppm grade has become one of today’s key strategic minerals with applications in high-tech industries including semiconductors, high temperature lamp tubing, telecommunications and optics, microelectronics and solar silicon applications. Due to its varied applicability, the demand for respective grade level has been increasing over the years, resulting in a consistent increase in its prices since 2017. Perpetual’s metallurgical testing has not demonstrated an ability to service this market, although additional testing is underway to test Beharra silica sand for its suitability for this higher priced market.

Beharra metallurgical testwork to date has confirmed the Beharra end-product to be suitable for sale into the 200–300 ppm Fe2O3 markets in the APAC region. This market is a higher volume market which attracts lower pricing than the 150–200 ppm Fe2O3 markets, although still represents a compelling sales price and generates strong margins for the Beharra Project.

In 2019, silica sand with 200–300 ppm Fe2O3 recorded a price of between US$41.10 in China and US$71.60 per metric ton in Japan (refer Figure 2.12).

27

BEHARRA SILICA PROJECT PRE-FEASIBILITY STUDY

==> picture [85 x 27] intentionally omitted <==

==> picture [459 x 265] intentionally omitted <==

Figure 2.12 Silica sand pricing in APAC region Source: IMARC

Perpetual has a strategy to optimise the potential revenue per ton from the Beharra Project and will continue to explore options for upgrading of product to achieve the premium prices enjoyed in the 150–200 ppm Fe2O3 silica sand markets.

As the Beharra products fall in the 200–300 ppm range in relation to Fe2O3, based on the above and advice provided by industry experts, Perpetual is confident that a sell price of US$50 per metric ton FOB Geraldton and above is achievable (Source: IMARC Report SR090221K2).

28

BEHARRA SILICA PROJECT PRE-FEASIBILITY STUDY

==> picture [85 x 27] intentionally omitted <==

3. MINERAL SPECIFICS

3.1 GEOLOGY AND MINERAL RESOURCE

The MRE report (attached at Appendix 5) describes the Mineral Resource estimation completed by Snowden for Perpetual for the extent of the Beharra Project.

3.1.1

Geology and geological interpretation

Silica sand mineralisation at Beharra occurs within the coastal regions of the Perth Basin, and the targeted silica sand deposits are the aeolian quartz sand dunes that overlie the Pleistocene limestones and paleocoastline.

3.1.2

Drilling, sampling and assaying

The Beharra deposit was initially explored in February 2019 using auger drilling across the southern extent of tenement E70/5221. A total of 38 holes to a maximum depth of 2 m were completed on a ~800 mE x ~400 mN grid, covering 7,215 m of strike and an average width of 1,700 m.

Following positive analytical results from the auger holes, 40 aircore drillholes for a total depth of 506.7 m were drilled between 18 and 23 March 2020. A sum of 509 samples were obtained, with one interval missing from the bottom of hole AC_20 below the water table; 502 of the assayed samples were 1 m in length, one was 1.5 m, five were 0.5 m, and one was 0.2 m in length. X-ray fluorescence (XRF) assays were obtained for 509 samples analysed by Nagrom and 485 assay results were obtained by inductively coupled plasma (ICP) techniques from Intertek Genalysis.

Following the maiden MRE in July 2020, a further 32 holes for a total depth of 394 m were drilled in September 2020. A sum of 394 samples were obtained, 362 of the assayed samples were 1 m in length with the remainder 0.5 m which represented the interval from 0.5 m to 1.0 m downhole. The first 0.5 m was not sampled to remove any effects of surface vegetation contamination. All assay results were obtained by ICP techniques from Intertek Genalysis.

The estimate described in this report only uses ICP assay results.

Samples were submitted to the Intertek Laboratory in Maddington, Perth, WA. The assay method for multielement analysis consisted of four-acid digest including perchloric and hydrochloric acids in Teflon beakers with ICP-optical (atomic) emission spectrometry finish. Silica is reported by difference.

Internal laboratory quality assurance/quality control (QAQC), which includes duplicates, standards and blanks, was utilised. In addition, a high-purity silica standard has been utilised at the rate of 1:20.

No geophysical tools were utilised during drilling.

The Mineral Resources were estimated within horizons defining the white and yellow sands above the logged water table surface. Surfaces were based on the geological boundaries of logged sand types and chemical analysis results from the drill data.

3.1.3

Mineral Resource estimation

Grade estimation was completed using ordinary kriging with hard boundaries applied between identified layers. Top cuts were applied to the data where required.

Six in-situ bulk density measurements were completed by Western Geotechnical and Laboratory Services using a nuclear densometer and reported on 16 April 2020. The sites were sampled in accordance with AS 1289.1.2.1-6.5.1 and tested in accordance with AS 1289.2.1.1. and AS 1289.5.8.1. The results from the seven measurements are corrected based on the measured moisture factor. The dry density ranged from 1.57 t/m[3] to 1.68 t/m[3] with an average dry in-situ density result of 1.64 t/m[3] which was applied to the estimate.

The Mineral Resource was classified as Indicated based on data quality, sample spacing, grade continuity, geological continuity of the domains, and metallurgical/process test results. The grey sands are considered low grade at this stage, and as there is no metallurgical testwork, have therefore been excluded. The reported Mineral Resource does not include any material within the Yardanogo Nature Reserve which occupies a strip approximately 300 m wide on the western side of the tenement plus a 50 m buffer to the boundary and is limited to a buffer of 50 m north and south of Mount Adams Road. The surface humus layer is typically about

29

BEHARRA SILICA PROJECT PRE-FEASIBILITY STUDY

==> picture [85 x 27] intentionally omitted <==

300 mm thick. The upper 500 mm (overburden) is likely to be reserved for rehabilitation purposes and was therefore excluded from the Mineral Resource.

No cut-off grade has been used for the reported Mineral Resource as the layers considered potentially economic are amenable to beneficiation to a suitable product specification through relatively simple processes, as demonstrated by initial metallurgical testing results of shallow auger samples.

The Beharra Indicated Mineral Resource is reported in Table 3.1.

Table 3.1 Beharra Indicated Mineral Resource (February 2021)

Sand Volume
**(Mm3) **
Density Tonnes
(Mt)
SiO2 Al2O3 TiO2 Fe2O3 LOI
Yellow
White
8.1
76.7
1.64
1.64
13.2
125.8
98.2
98.6
0.50
0.41
0.23
0.36
0.23
0.23
0.51
0.21
Total 84.8 1.64 139.0 98.6 0.42 0.35 0.23 0.24

3.1.4 Recommendations

Snowden makes the following recommendations to improve confidence in the geology model (geology, grade, and quality continuity), and verify product quality (metallurgy):

  • The PSD results from both drilling programs should be verified by umpire testing of some of the September 2020 Nagrom samples at the laboratory used by Robbins (Diamantina Laboratories, Malaga)

  • Twins 20B019 and 20B032 should be included for PSD testing at Nagrom and Diamantina, to compare with AC_16 and AC_38, respectively

  • Additional (infill) samples from the March 2020 (if available) and September 2020 drilling programs should be tested for PSD to improve confidence in trends with depth and laterally across the deposit

  • The Mineral Resource block model should be used, in conjunction with individual borehole data to identify domains for further metallurgical testwork

  • Metallurgical variability tests should be carried out per geological domain to assess the effect (if any) of subtle geochemical and PSD changes across and vertically through the deposit on processing and product characteristics

  • Petrographic and/or microprobe analyses to be completed to determine deportment of Fe2O3 and Al2O3 contaminants.

3.2 MINING

3.2.1 Introduction

Snowden was engaged by Perpetual to develop an Ore Reserve on the Beharra Silica Project. The complete Ore Reserve Statement is attached at Appendix 6.

The Snowden work was divided into two phases. The first phase used the Beharra Inferred Mineral Resources to identify a mineral inventory, thus enabling planning for other study disciplines and to support mining operations budget quotations from mining contractors. The second phase of the study saw the mining costs from the quotations used to support Ore Reserves using the updated Indicated Mineral Resources. All other aspects of the PFS, including the development of non-mining related operating costs and capital costs, were provided by Perpetual and relevant consultants, for use as Modifying Factors in the estimation of Ore Reserves.

3.2.2

Conventions

Unless otherwise specified, all costs and prices are in Australian dollars (A$).

The units of measure (volume, distance, etc) used in this report are metric.

Spatial data measurements are formatted as XYZ. Where X refers to the easting, Y to the northing and Z to the vertical distance above mean sea level.

The coordinate system used is based on the Universal Transverse Mercator (UTM) datum using Zone 50.

30

BEHARRA SILICA PROJECT PRE-FEASIBILITY STUDY

==> picture [85 x 27] intentionally omitted <==

3.2.3 Tenure description

The Beharra tenement covers a total area of approximately 48.48 km[2] . Details of the tenement are provided in Table 3.2 and shown in Figure 3.1 (with block model location outlined in the southern end) and apply to a depth of 30 m.

Table 3.2 Beharra tenement

Table 3.2
Beharra tenement
Tenement E70/5221
Status Live
Application date 11/10/2018
Grant date 13/06/2019
Expiration date 12/06/2024
Term (years) 5
Area (ha) – ()BL) 4,848.69 ha – 19 BL
Expenditure commitments ($) $20,000
Holder Perpetual Resource Limited
Coordinates Latitude 29.43603 S, longitude 115.11151E

31

BEHARRA SILICA PROJECT PRE-FEASIBILITY STUDY

==> picture [85 x 27] intentionally omitted <==

==> picture [190 x 505] intentionally omitted <==

Figure 3.1 Beharra tenement

3.2.4 Historical production

Beharra is an undeveloped project and consequently has no historical production.

3.2.5 Mining method development

Resource description

For Mineral Resource estimation, five layers were modelled: Yellow, White Upper, White Lower, Light Grey Pod, Grey Pod, and Grey.

The resources were only developed to the water table and the model is unsaturated. The water table will be in the sand below and is typically 10–12 m below the surface. The top 500 mm were excluded from Mineral Resource, being yellow sand with the upper 300 mm containing humus. Yellow sand below 500 mm deep was eligible for processing. The resource profile is in Figure 3.2.

32

BEHARRA SILICA PROJECT PRE-FEASIBILITY STUDY

==> picture [85 x 27] intentionally omitted <==

==> picture [459 x 237] intentionally omitted <==

==> picture [156 x 19] intentionally omitted <==

----- Start of picture text -----

Figure 3.2 Beharra Resource profile
Source: Snowden, 2021
----- End of picture text -----

Grey Pod A was present in seven drillholes, average depth of 2.1 m, higher Al2O3, Fe2O3, LOI, K2O, than Upper White. Grey Pod B pods were small within White layers, present in two drillholes, average depth of 5.0 m, lower SiO2, high Al2O3, high LOI. The pod material was mined as waste and not processed. The pods are internal waste.

Geotechnical parameters

The resource report has defined aeolian quartz sands largely of medium grain size with an average fines content (-0.075 mm) of ~3.5% (~8% in “grey” sand). Even the “grey” sand is 93.5% quartz with negligible clay minerals and this material is not eligible for processing because the deleterious minerals. The deposit overlies limestones and paleo-coastline, so may locally be underlain by “clayey/peaty” lacustrine/swamp deposits.

Trafficability on the sand unlikely to be an issue, but roads would be needed over any lacustrine/swamp deposits that are affected by winter rainfall.

The diggability assessment is that aeolian sands are all free dig.

Snowden recommends that 30° walls will be sufficient for developing the pit limits during mining. If a seasonal water table variation is experienced the pit wall angle may need to be flattened or the mining scheduled to a time when the water drains during the dry season, however this is unlikely due to the water table being two metres below the resource.

Mining method

The proposed mining cycle is summarised in Figure 3.3.

33

BEHARRA SILICA PROJECT PRE-FEASIBILITY STUDY

==> picture [85 x 27] intentionally omitted <==

==> picture [457 x 334] intentionally omitted <==

----- Start of picture text -----

START
FINISH
Clearing and soil
Rehabilitation
stripping
Excavation
Rehandle: guidance
Rejects (grade
control)
Tipping:
Backfill and Loading
stockpiles
Hauling
----- End of picture text -----

==> picture [112 x 9] intentionally omitted <==

----- Start of picture text -----

Figure 3.3 Mining cycle
----- End of picture text -----

3.2.6 Clearing and stripping

Mining areas will be cleared of vegetation using track dozers. Vegetation will be stockpiled for spreading on rehabilitated slopes.

Soil will be stripped from cleared areas (with exception of soil stockpile areas), to a nominal depth of 500 mm (potentially in two passes with the actual depth depending on location, soil characteristics and prevalence of tree roots and rootlets), using graders and track dozers forming windrows which will be reclaimed using frontend loaders (FELs) and hauled in rigid rear dump trucks.

3.2.7

Drilling

Production drilling will not be required for blasting due to the loose nature of the material.

Grade control drilling will not be required. The Indicated Resource drill density is sufficient to define the ore basement. As there will be an ore loss envelope around the grey sand, any grade control in the basement will be visual only.

3.2.8

Excavation guidance

In general, excavation guidance will involve the following steps:

  • Ore/Waste elevation determination:

  • Dig plan creation.

  • Ore control:

  • Mark out by surveyors

  • Ore spotting, if required.

  • Reconciliation:

  • Comparison of mined and processed with resource block model.

34

BEHARRA SILICA PROJECT PRE-FEASIBILITY STUDY

==> picture [85 x 27] intentionally omitted <==

3.2.9 Loading

All material will be mined, as far as practicable, to the profile (e.g. upper white) up to a maximum height of 6 m. Above this height, the profile would be split into benches. Material will be loaded using 50-tonne FELs. An example of this size and type of equipment is shown in Figure 3.4.

==> picture [455 x 244] intentionally omitted <==

Figure 3.4 50-tonne operating weight FEL Source: Caterpillar (AEHQ5618-01 (3-06))

There may be an opportunity to reduce mining costs by utilising an excavator instead of FELs although this would be at the expense of operational flexibility.

3.2.10 Hauling

Trafficability will be below average based on the material type. Given the low volume, articulated dump trucks (ADTs) will be used as they are generally able to handle soft and uneven ground conditions better than rigid body haul trucks. All material will be hauled using 55-tonne capacity ADTs. Figure 3.5 shows an example of this size and type of equipment. Occasionally, roads will be sheeted if they are semi-permanent, or if any clay areas are encountered.

==> picture [455 x 207] intentionally omitted <==

Figure 3.5 ADT Source: Volvo (20050609_A)

35

BEHARRA SILICA PROJECT PRE-FEASIBILITY STUDY

==> picture [85 x 27] intentionally omitted <==

3.2.11 Tipping

Ore will be direct tipped into the feed hopper.

Any waste material will be backfilled into the pit.

Material rejected from the processing plant will be deposited into a hopper that is configured for direct loading of empty ore trucks on their return cycle from the crusher.

Waste and rejects from starting cells (i.e. initial pit area) will need to be stockpiled until pit floor space is available for backfilling.

There is an opportunity to slurry the rejects back into the pit; however, this would need to be evaluated as it may require the wall angles to be reduced because of potential erosion.

3.2.12 Rehabilitation

Pits will be backfilled with waste and rejects and progressively rehabilitated over the project life. Pit wall angles will be reduced to 8° using waste and rejects against the dug pit walls. Track dozers will be used to reprofile the paddock tips.

Growth media collected during mining operations will then be rehandled from stockpile to the rehabilitation face and spread to a depth of between 200 mm and 300 mm. Finally, timber mulch is evenly spread as soon as practicable to protect the soil surface from wind erosion. Based on the low batter angles on the outer pit walls, sandy soil profile and lack of local surface water drainage features that may contribute to water erosion, it is not expected that significant repair or maintenance earthworks will be required after rehabilitation of each cell.

3.2.13 Ancillary

All parts of the mining cycle will be supported with the use of ancillary equipment. They will be required to complete the following tasks:

  • Clearing and stripping of topsoil

  • Construction of haul roads and ramps (temporary and long term)

  • Pit and stockpile floor maintenance

  • Clean-up of spillage around pit and stockpile working areas and haul roads and ramp

  • Paddock tip and pit wall reprofiling for rehabilitation

  • Topsoil spreading, ripping, and seeding.

Table 3.3 lists the ancillary equipment that was selected to match the proposed load and haul units.

Table 3.3 Ancillary equipment

**Type ** Class
Track dozer 70 t operatingweight
Grader 14 foot blade
Water truck 30 kL capacity
Service truck 50 kL capacity
Vibratingroller 16 t

3.2.14 Pit optimisation

Mining model

The Resource model was modified into a mining model suitable for mine planning purposes. The following steps were undertaken on the resource model to derive the mining model:

  • Grey Pod B reassigned from “White” to “Grey” profile

  • Model parent cell size reduced to allow better estimation of wall angles

  • Identification of surface blocks and coding of the 0.5 m thick surface material as waste.

Identification of blocks available for mining using 30° walls (Figure 3.6) 30 m offset from lease (20 m plus 10 m for crest access):

36

BEHARRA SILICA PROJECT PRE-FEASIBILITY STUDY

==> picture [85 x 27] intentionally omitted <==

  • 60 m offset from Yardanogo Nature Reserve (50 m plus 10 m for crest access)

  • 160 m wide corridor for Mount Adams Road

  • Application of ore loss envelope around Grey floor and Grey Pod A

  • 0.5 m above Grey floor

  • 0.5 m below and 1 m above the Grey Pod in case of voids.

==> picture [301 x 558] intentionally omitted <==

Figure 3.6 Mineable area

Table 3.4 shows a comparison between the resource and mining models. A total of 13,886 kdt is removed from the resource in converting it to the mining model:

  • 5,685 kdt is due to the Grey envelope (floor and Pod B)

37

BEHARRA SILICA PROJECT PRE-FEASIBILITY STUDY

==> picture [85 x 27] intentionally omitted <==

  • 7,667 kdt is due to the offsets

  • 534 kdt is due to both the offsets and Grey envelope.

38

BEHARRA SILICA PROJECT PRE-FEASIBILITY STUDY

==> picture [85 x 27] intentionally omitted <==

Table 3.4 Resource and mining model comparison

Resource model Resource model Resource model Mining model Mining model Mining model
X Y Z X Y Z
Origin 315,100 6,740,315 0 315,100 6,740,315 0
Extent 318,500 6,748,475 36 318,500 6,748,475 36
Parent cell size(m) 200 240 2 10 10 1
Minimum sub-cell size(m) 10 10 0.25 10 10 0.25
Volume(kbcm) 419,637 419,637
Mass(kdt) 688,204 688,204
Resource(kdt) 138,991 125,105
Al2O3 (%) 0.419 0.409
CaO(%) 0.0068 0.0069
Cr2O3 (%) 0.00078 0.00077
Fe2O3 (%) 0.228 0.228
K2O(%) 0.106 0.101
MgO(%) 0.0134 0.0138
MnO(%) 0.0053 0.0053
Na2O(%) 0.0109 0.0105
SiO2 (%) 98.58 98.60
TiO2 (%) 0.349 0.348
V2O5 (%) 0.0011 0.0011
LOI(%) 0.241 0.241
Total assay (%) 99.97 99.97

Parameters and Modifying Factors

Resource classification

Only Indicated Mineral Resources (no Measured or Inferred) are available in the Resource model for pit optimisation.

Starting surface

The initial surface for the optimisation was the original topography which was coded into the Resource model.

Boundaries

Exclusion areas were coded into the mining model.

Geotechnical constraints

A 30° overall wall angle was applied for the pit optimisation.

Dilution and mining recovery

Ore loss was favoured over dilution resulting in a mining recovery of 95.5%.

Process rate

A constant processing rate of 2,031 kdt/a was used in the optimisation.

Process recovery

A constant mass yield of 74.37% was used. This comprised 6.35% to product #27 and 68.02% to product #46 based on the metallurgical testwork.

Results

Figure 3.7 shows a summary of the physicals resulting from the pit optimisation. There are two significant mass increases:

  • 0.75 to 0.8 revenue factor which indicates that a decrease in price (or mass yield) of more than 20% will render the Project uneconomic

39

BEHARRA SILICA PROJECT PRE-FEASIBILITY STUDY

==> picture [85 x 27] intentionally omitted <==

  • 1.2 to 1.3 which coincides with majority of the partial ore loss blocks around the grey profiles becoming economic.

==> picture [360 x 367] intentionally omitted <==

Figure 3.7 Pit optimisation results – physical

Figure 3.8 shows a summary of the financials resulting from the pit optimisation. Like the physicals, there are two corresponding decreases in unit cash flow at the same revenue factors.

40

BEHARRA SILICA PROJECT PRE-FEASIBILITY STUDY

==> picture [85 x 27] intentionally omitted <==

==> picture [402 x 411] intentionally omitted <==

==> picture [194 x 8] intentionally omitted <==

----- Start of picture text -----

Figure 3.8 Pit optimisation results – financial
----- End of picture text -----

Table 3.5 summarises values of select pit shells from the pit optimisation.

BEHARRA SILICA PROJECT PRE-FEASIBILITY STUDY

41

==> picture [85 x 27] intentionally omitted <==

Table 3.5 Pit optimisation result summary

General
Pit shell 1 2 4 6 9 15
Revenue factor 0.75 0.80 0.90 1.00 1.30 2.00
Apparentprice(US$/dtproduct) 33.75 36.00 40.50 45.00 58.50 90.00
Physicals
Ore (Mdmt)
Waste(Mdmt)
9.1
0.5
120.8
8.3
122.5
9.4
123.9
10.8
125.0
14.0
125.1
14.4
Total (Mdmt) 9.6 129.1 131.8 134.8 139.1 139.5
Stripratio(waste:ore) 0.05 0.07 0.08 0.09 0.11 0.11
Resource conversion(%) 6.6 86.9 88.1 89.2 90.0 90.0
White ore (Mdt)
White SiO2 (%)
8.0
98.65
108.2
98.65
109.9
98.65
111.3
98.64
112.4
98.64
112.5
98.64
Yellow ore (Mdt)
Yellow SiO2 (%)
1.1
98.26
12.5
98.23
12.6
98.23
12.6
98.23
12.6
98.23
12.6
98.23
Totalproduct (Mdt) 6.7 88.6 89.8 90.9 91.7 91.7
Massyield(%) 74.4 74.4 74.4 74.4 74.4 74.4
Economics
Mining cost ($ M)
Miningcost($/dmt)
68.5
7.12
926.3
7.17
945.4
7.17
965.4
7.16
994.9
7.15
997.6
7.15
Ore cost ($ M)
Ore cost($/dt ore)
39.0
4.26
554.1
4.59
562.1
4.59
568.8
4.59
573.9
4.59
574.2
4.59
Selling cost ($ M)
Sellingcost($/dtproduct)
197.1
29.39
2,602.9
29.39
2,639.7
29.39
2,670.6
29.39
2,694.4
29.39
2,695.9
29.39
Total cost ($ M)
Total cost($/dtproduct)
304.5
45.41
4,083.3
46.11
4,147.2
46.17
4,204.8
46.27
4,263.2
46.50
4,267.6
46.52
Revenue ($ M)
Revenue($/dtproduct)
402.4
60
5,313.9
60
5,389.1
60
5,452.2
60
5,500.8
60
5,503.7
60
Undiscounted cash flow ($ M)
Undiscounted cash flow ($/dt
product)
97.8
14.59
1,230.5
13.89
1,241.9
13.83
1,247.3
13.73
1,237.5
13.50
1,236.1
13.48

Figure 3.9 show the pit shells generated in the pit optimisation. After the rapid size increase from pit shell 1 to 2, the remaining pit shells are predominately adding incremental tonnes along the pit floor and around “Grey Pod B” (due to the block height these blocks typically contain both ore and waste).

42

BEHARRA SILICA PROJECT PRE-FEASIBILITY STUDY

==> picture [85 x 27] intentionally omitted <==

==> picture [459 x 458] intentionally omitted <==

Figure 3.9 Pit optimisation pit shells

At the completion of the scheduling, another pit optimisation was run to check the impact of the cost and price changes. Despite a decrease in costs of about 7% and increase in price of about 11%, there was little physical change pit shell with marginally more ore and waste included around the grey profiles (floor and pod B). The revised revenue factor 1 pit shell was equivalent to the original revenue factor 1.3 pit shell (Table 3.5) containing 125 Mdt of ore (<1% change).

3.2.15 Mine design

Pit

The following parameters were used in the pit designs:

  • 30° wall angle

  • 1 m high bench flitches

  • 20 m wide ramps at 1:10 gradient.

The ultimate pit design was split into panels aimed at balancing the number of plant movements and minimising haul distances. The panels were sequenced to access the marginally better grades first whilst minimising road development and maintaining a logical grouping sequence. Figure 3.10 shows the ultimate and panel pit designs. These panels will be further subdivided into cells for scheduling.

43

BEHARRA SILICA PROJECT PRE-FEASIBILITY STUDY

==> picture [85 x 27] intentionally omitted <==

==> picture [459 x 435] intentionally omitted <==

Figure 3.10 Pit design

Figure 3.11 shows the pit depths. The deepest sections, at around 15 m, are in the northwest corner of panels 5 and 6 whilst the shallowest sections, at around 3 m, are in the east of panels 8 and 9. Due to the 1 m minimum height used in the design it clips the water table, in practice mining would stop above the water table.

BEHARRA SILICA PROJECT PRE-FEASIBILITY STUDY

44

==> picture [85 x 27] intentionally omitted <==

==> picture [232 x 657] intentionally omitted <==

==> picture [30 x 287] intentionally omitted <==

Figure 3.11 Pit depth (m)

Table 3.6 summarises the ultimate pit design by profile.

BEHARRA SILICA PROJECT PRE-FEASIBILITY STUDY

45

==> picture [85 x 27] intentionally omitted <==

Table 3.6 Pit inventory by profile

DOMNAME Overburden
(topsoil)
Grey Pod A Yellow White
Upper
White
Lower
Grey Pod
B
Grey
Floor
Total
REPMINE Overburden White Yellow White White Grey Grey -
Total(Mdmt) 7.7 1.8 12.6 73.3 39.4 0.1 0.0 134.8
Waste(Mdmt) 7.7 - - 0.7 2.4 0.1 0.0 10.9
Ore(Mdmt) - 1.8 12.6 72.6 37.0 - - 123.9
Al2O3 (%) - 0.50 0.50 0.30 0.59 - - 0.41
CaO(%) - 0.005 0.013 0.006 0.007 - - 0.007
Cr2O3 (%) - 0.001 0.001 0.001 0.001 - - 0.001
Fe2O3 (%) - 0.26 0.23 0.22 0.25 - - 0.23
K2O(%) - 0.09 0.08 0.06 0.18 - - 0.10
MgO(%) - 0.01 0.05 0.01 0.01 - - 0.01
MnO(%) - 0.005 0.003 0.005 0.006 - - 0.005
Na2O(%) - 0.01 0.01 0.01 0.02 - - 0.01
SiO2 (%) - 98.54 98.23 98.84 98.28 - - 98.60
TiO2 (%) - 0.34 0.23 0.35 0.38 - - 0.35
V2O5 (%) - 0.001 0.001 0.001 0.001 - - 0.001
LOI(%) - 0.21 0.51 0.19 0.25 - - 0.24
Total assay (%) - 100.0 99.9 100.0 100.0 - - 100.0
Massyield(%) - 74.37 74.37 74.37 74.37 - - 74.37
Product(Mdt) - 1.3 9.4 54.0 27.5 - - 92.2

Table 3.7 summarises the ultimate pit design by panel. There are only minor grade differences between the panels; however, in general, the lower numbered panels have slightly higher alumina and slightly lower Fe2O3 grades.

Table 3.7 Pit inventory by panel

Panel 1 2 3 4 5 6 7 8 9 10 Total
Total volume(Mbcm) 10.3 12.8 11.1 8.4 8.3 8.7 7.0 6.3 5.2 4.3 82.2
Waste volume(Mbcm) 0.8 0.9 0.9 0.7 0.5 0.5 0.6 0.6 0.6 0.4 6.7
Ore volume(Mbcm) 9.5 11.9 10.1 7.6 7.8 8.1 6.4 5.6 4.6 3.9 75.6
Total mass(Mdmt) 16.9 20.9 18.2 13.7 13.6 14.2 11.4 10.3 8.5 7.1 134.8
Waste mass(Mdmt) 1.4 1.5 1.6 1.2 0.8 0.9 0.9 1.0 0.9 0.7 10.9
Stripratio(wst:ore) 0.09 0.08 0.09 0.10 0.07 0.07 0.09 0.11 0.12 0.11 0.09
Ore mass(Mdmt) 15.5 19.4 16.6 12.5 12.8 13.3 10.5 9.2 7.6 6.4 123.9
Al2O3 (%) 0.41 0.44 0.44 0.41 0.50 0.40 0.36 0.34 0.32 0.36 0.41
CaO(%) 0.007 0.007 0.006 0.006 0.010 0.006 0.006 0.009 0.009 0.005 0.007
Cr2O3 (%) 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001
Fe2O3 (%) 0.22 0.22 0.17 0.15 0.33 0.27 0.26 0.20 0.25 0.24 0.23
K2O(%) 0.13 0.13 0.09 0.07 0.15 0.09 0.06 0.07 0.08 0.07 0.10
MgO(%) 0.01 0.01 0.01 0.00 0.03 0.02 0.01 0.01 0.06 0.01 0.01
MnO(%) 0.005 0.005 0.005 0.004 0.006 0.005 0.006 0.005 0.006 0.006 0.005
Na2O(%) 0.01 0.01 0.01 0.01 0.02 0.01 0.00 0.01 0.01 0.01 0.01
SiO2 (%) 98.61 98.59 98.64 98.68 98.31 98.61 98.69 98.77 98.53 98.62 98.60
TiO2 (%) 0.35 0.36 0.35 0.32 0.32 0.31 0.37 0.33 0.41 0.42 0.35
V2O5 (%) 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001
LOI(%) 0.23 0.21 0.25 0.26 0.30 0.26 0.22 0.23 0.24 0.22 0.24
Total assay (%) 100.0 100.0 100.0 99.9 100.0 100.0 100.0 100.0 99.9 100.0 100.0
Massyield(%) 74.37 74.37 74.37 74.37 74.37 74.37 74.37 74.37 74.37 74.37 74.37
Product(Mdt) 11.5 14.5 12.3 9.3 9.5 9.9 7.8 6.9 5.7 4.8 92.2
Rejects(Mdt) 4.0 5.0 4.3 3.2 3.3 3.4 2.7 2.4 2.0 1.6 31.8

46

BEHARRA SILICA PROJECT PRE-FEASIBILITY STUDY

==> picture [85 x 27] intentionally omitted <==

Plant pads

To maximise the resource and accommodate panel sequences that advance away from the road corridor it will be necessary to construct plant and stockpile pads plus access road for some panels out of waste and rejects. The remaining panels will locate the plant and stockpile on unmined panels. Figure 3.12 shows these locations and backfilled pads.

==> picture [218 x 406] intentionally omitted <==

Figure 3.12 Plant pads

Table 3.8 summarises the backfill volumes required for constructing the plant pads.

Table 3.8 Plant pad volumes

Pad forpanel Volume (Mlcm)
2
3
4
7
10
1.0
1.0
0.6
1.7
1.6
Total 5.9

If insufficiently dry rejects are available, it will be necessary to modify the panel sequence such that they a ll retreat towards the road corridor and/or sterilise some of the inventory to allow the plant to sit on unmined areas.

Backfill

To ensure long term stability of the pit walls, it will be necessary to reduce the angle of the pit walls to 8°. To maximise the resource, the walls are mined to 30° so to reduce the slope angle it is necessary to backfill waste

BEHARRA SILICA PROJECT PRE-FEASIBILITY STUDY

47

==> picture [85 x 27] intentionally omitted <==

and rejects against the pit walls. Figure 3.13 shows the backfilled material around the pit edge with an example cross section in

==> picture [455 x 111] intentionally omitted <==

Figure 3.14.

==> picture [303 x 370] intentionally omitted <==

Figure 3.13 Pit wall backfill

==> picture [455 x 110] intentionally omitted <==

==> picture [188 x 8] intentionally omitted <==

----- Start of picture text -----

Figure 3.14 Pit wall backfill example section
----- End of picture text -----

Table 3.9 summarises the backfill volumes required to stabilise the pit walls.

48

BEHARRA SILICA PROJECT PRE-FEASIBILITY STUDY

==> picture [85 x 27] intentionally omitted <==

Table 3.9 Wall backfill volumes

Panel Volume (Mlcm)
1
2
3
4
5
6
7
8
9
10
0.5
0.4
0.4
0.6
0.9
0.5
0.5
0.3
0.2
0.3
Total 4.6

About half the waste and reject volume is required between the plant pads and pit wall backfill, the remainder will be rehandled to the pit floor prior to rehabilitation.

The waste and rejects from the first cell in each mining area (north and south of the road) will need to be stockpiled on the surface until sufficient pit floor is open.

3.2.16 Mine schedule

A mine schedule was completed for the first four panels and limited the Fe2O3 to an average of 2000 ppm life of mine (LOM). This was used for the Ore Reserve estimate. A second schedule was also provided that added additional tonnes with higher iron at 2640 ppm (panels 6 to 10). The additional portion of Indicated Mineral Resources will be re-assessed with a view to classifying the in-situ tonnage as an Ore Reserve pending further feasibility study metallurgical evaluation.

Material groups

Material was grouped by the following fields:

  • Water table (above or below)

  • DOMNAME (Overburden, Yellow, Upper White, Lower White, Grey Pod A, Grey Pod B, Grey Floor)

  • REPNAME and REPMINE (Overburden, Yellow, White, Grey) with a change from yellow or white to grey indicating ore loss

  • RESCAT (Indicated or Unclassified).

Time scale

The schedule was completed in quarterly increments over the life of the Project. All quarters were considered the same (i.e. all 91.25 days long).

Resolution

Based on the selected time scale, quantities were aggregated to a 4 m bench level by panel, cell, and material group.

Precedencies

All benches within a cell were dependent on the bench above being mined out. To ensure that panels were opened to allow sufficient time to build the plant pads, the fixed sequence in Figure 3.15 was followed.

49

BEHARRA SILICA PROJECT PRE-FEASIBILITY STUDY

==> picture [85 x 27] intentionally omitted <==

==> picture [171 x 198] intentionally omitted <==

==> picture [171 x 198] intentionally omitted <==

Figure 3.15 Cell sequence

Active mining areas

The number of active cells that can be mined in any period is one.

Bench turnover

Bench turnover was not restricted due to the shallow depths and relatively fixed mining rate.

Mining

The mining rate was not restricted.

Processing

Table 3.10 summarises the processing rate constraint.

Table 3.10 Processing rate
Quarter Mass (Mdt/qtr)
1 -
2 140,680
3 140,680
4 348,075
5 487,305
6 onwards 507,750

Constraints were not applied to any grades.

50

BEHARRA SILICA PROJECT PRE-FEASIBILITY STUDY

==> picture [85 x 27] intentionally omitted <==

Product

No constraint was applied to the product although by virtue of the fixed mass yield it was controlled by the processing rate.

3.2.17 Life of mine schedule

The LOM schedule includes the entire pit design inventory and is summarised annually.

Mining

Figure 3.16 summarises the total movement by panel. Apart from year 3 and 4 when there is rehandle of the previous year’s rejects, there are slight movement variations caused by the waste mining.

==> picture [459 x 240] intentionally omitted <==

Figure 3.16 Total movement by panel

Figure 3.17 shows the ex-pit movement (i.e. no rehandle) by profile group.

==> picture [459 x 241] intentionally omitted <==

Figure 3.17 Ex-pit movement by profile group

Figure 3.18 shows the ex-pit ore and waste movement together with the haul distance estimate. The ore hauls are more variable in the first four panels due to their extra width. This variation could be reduced by mining from two or more cells at a time (i.e. one close to the plant and one far).

BEHARRA SILICA PROJECT PRE-FEASIBILITY STUDY

51

==> picture [85 x 27] intentionally omitted <==

==> picture [459 x 237] intentionally omitted <==

Figure 3.18 Ex-pit movement and haul distance

Processing

Figure 3.19 shows the ore feed by profile group. The plant is fully utilised until the final year of the schedule.

==> picture [459 x 242] intentionally omitted <==

Figure 3.19 Ore feed by profile group

Figure 3.20 and Figure 3.21 show the ore feed grades. In general, the second half of the schedule is more variable than the first.

52

BEHARRA SILICA PROJECT PRE-FEASIBILITY STUDY

==> picture [85 x 27] intentionally omitted <==

Figure 3.20 Ore feed grades

Figure 3.21 Ore feed grades

Figure 3.22 shows the plant product and rejects. Due to the constant mass yield, these are constant except for the first and final years of production.

53

BEHARRA SILICA PROJECT PRE-FEASIBILITY STUDY

==> picture [85 x 27] intentionally omitted <==

==> picture [459 x 243] intentionally omitted <==

Figure 3.22 Plant product and rejects

Environmental

Figure 3.23 shows the estimated annual area cleared for topsoil stripping. Road construction distances are for access to the plant locations by road trains transporting the product.

==> picture [459 x 242] intentionally omitted <==

Figure 3.23 Disturbance

Figure 3.24 shows the estimated annual area rehabilitated and the topsoil spread over the rehabilitated area.

BEHARRA SILICA PROJECT PRE-FEASIBILITY STUDY

54

==> picture [85 x 27] intentionally omitted <==

==> picture [459 x 260] intentionally omitted <==

Figure 3.24 Rehabilitation

3.2.18 Reserve schedule

The Reserve schedule includes the pit design inventory for panels 1 to 4 and is shown quarterly.

Mining

Figure 3.25 summarises the total movement by panel. The mining ramp-up mirrors the processing plant rampup due to the very low strip ratio. Mining peaks in years 3 and 4 when there is rehandle of rejects and waste from the first cell. Movement varies due to the presence of small amounts of waste.

==> picture [459 x 246] intentionally omitted <==

==> picture [163 x 8] intentionally omitted <==

----- Start of picture text -----

Figure 3.25 Total movement by panel
----- End of picture text -----

Figure 3.26 shows the ex-pit movement (i.e. no rehandle) by profile group. The movement of the yellow plus white profiles are consistent, with slight variations due to ore loss.

BEHARRA SILICA PROJECT PRE-FEASIBILITY STUDY

55

==> picture [85 x 27] intentionally omitted <==

==> picture [459 x 243] intentionally omitted <==

Figure 3.26 Ex-pit movement by profile group

Figure 3.27 shows the ex-pit ore and waste movement together with the haul distance estimate. The ore hauls trend from short to long as mining progresses through the panel. This variation could be reduced by mining from two or more cells at a time (i.e. one close to the plant and one far).

==> picture [459 x 240] intentionally omitted <==

Figure 3.27 Ex-pit movement and haul distance

Processing

Figure 3.28 shows the ore feed by profile group. The plant ramp-up over four quarters is visible and is fully utilised until the last processing quarter.

56

BEHARRA SILICA PROJECT PRE-FEASIBILITY STUDY

==> picture [85 x 27] intentionally omitted <==

==> picture [459 x 240] intentionally omitted <==

Figure 3.28 Ore feed by profile group

Figure 3.29 and Figure 3.30 show the ore feed grades. These vary between quarters with no clear trends.

==> picture [459 x 255] intentionally omitted <==

Figure 3.29 Ore feed grades

BEHARRA SILICA PROJECT PRE-FEASIBILITY STUDY

57

==> picture [85 x 27] intentionally omitted <==

==> picture [459 x 238] intentionally omitted <==

Figure 3.30 Ore feed grades

Figure 3.31 shows the plant product and rejects. Due to the constant mass yield these are constant except for the first and final years of production.

==> picture [459 x 247] intentionally omitted <==

Figure 3.31 Plant product and rejects

Environmental

Figure 3.32 shows the estimated area cleared for topsoil stripping by quarters. Road construction distances are for access to the plant locations by road trains transporting the product.

58

BEHARRA SILICA PROJECT PRE-FEASIBILITY STUDY

==> picture [85 x 27] intentionally omitted <==

==> picture [459 x 246] intentionally omitted <==

==> picture [111 x 9] intentionally omitted <==

----- Start of picture text -----

Figure 3.32 Disturbance
----- End of picture text -----

Figure 3.33 shows the estimated area rehabilitated and the topsoil spread over the rehabilitated area by quarters.

==> picture [459 x 255] intentionally omitted <==

==> picture [119 x 9] intentionally omitted <==

----- Start of picture text -----

Figure 3.33 Rehabilitation
----- End of picture text -----

3.2.19 Mine requirements

Mining equipment and support

Table 3.11 summarises the average primary and ancillary equipment numbers required to mine the schedules.

59

BEHARRA SILICA PROJECT PRE-FEASIBILITY STUDY

==> picture [85 x 27] intentionally omitted <==

Table 3.11 Equipment

**Type ** Units
FEL 2
ADT 3
Track dozer 1
Grader 1
Water truck 1
Service truck 1
Vibratingroller 1

Table 3.12 summarises the energy consumables required by the mining operation.

Table 3.12 Consumables

**Type ** Units
Fuel(ML/a) 1.2
Electricity (MW/a) 1.314

Table 3.13 summarises the mining full-time employees (FTEs) required.

Table 3.13 Personnel

**Type ** FTEs
Managers
Administration
Supervisors
Operators
Maintainers
Technical
1
2
6
31
21
4
Total 65

3.3 METALLURGY

3.3.1 Testwork regimes and programs

As part of the PFS, a bulk sample (+2 tonne) was generated from exploration drilling samples that conformed to the resource definition criteria being:

  • White or yellow sand horizons only

  • Above the water table

  • Maximum depth 10 m

  • 98% SiO2.

A full list of the drill samples included in the bulk sample is provided in Appendix 7.

The drilling samples, see Figure 3.34, were composited and used to complete the PFS testwork, including:

  • Ore characterisation

  • Flowsheet development

  • Preparation of marketing samples

  • Slime settling characteristics

  • Definition of the mass balance.

The testwork was completed at IHCR, a recognised mineral sand testing specialist, from October to December 2020 and reported in report 1959-PM-REP-0000-8001 Rev 2 “Pre-Feasibility Metallurgy Testwork” provided in Appendix 8.

60

BEHARRA SILICA PROJECT PRE-FEASIBILITY STUDY

==> picture [85 x 27] intentionally omitted <==

==> picture [459 x 214] intentionally omitted <==

Figure 3.34 Drilling samples identified for bulk sample composite

3.3.2 Ore characteristics

The resource definition compliant samples, such as:

  • Intervals within the yellow and white definition only

  • Intervals to a maximum of either the water table or 10 m below surface

  • Greater than 98.2% SiO2

  • Representing four complete traverse drill lines of the deposit.

were recovered and blended to provide a homogeneous sample (see Table 3.14).

Table 3.14 Homogenous sample makeup

BHID SAMPNUM FROM TO BHID SAMPNUM FROM TO BHID SAMPNUM FROM TO BHID SAMPNUM FROM TO
AC_16 B03601 0 1 AC_26 B01049 2 3 AC_38 B01209 3 4 AC_51 B01405 3 4
AC_16 B03602 1 2 AC_26 B01050 3 4 AC_38 B01210 4 5 AC_51 B01407 5 6
AC_16 B03603 2 3 AC_26 B01051 4 5 AC_38 B01211 5 6 AC_51 B01408 6 7
AC_16 B03604 3 4 AC_26 B01052 5 6 AC_38 B01212 6 7 AC_51 B01409 7 8
AC_16 B03605 4 5 AC_26 B01053 6 7 AC_38 B01213 7 8 AC_52 B01390 0 1
AC_16 B03606 5 6 AC_26 B01054 7 8 AC_38 B01214 8 9 AC_52 B01391 1 2
AC_16 B03607 6 7 AC_26 B01055 8 9 AC_39 B01218 0 1 AC_52 B01392 2 3
AC_16 B03608 7 8 AC_26 B01056 9 10 AC_39 B01219 1 2 AC_52 B01393 3 4
AC_16 B03609 8 9 AC_27 B01030 0 1 AC_39 B01220 2 3 AC_52 B01394 4 5
AC_17 B03621 0 1 AC_27 B01031 1 2 AC_39 B01221 3 4 AC_52 B01395 5 6
AC_17 B03622 1 2 AC_27 B01032 2 3 AC_39 B01222 4 5 AC_52 B01396 6 7
AC_17 B03623 2 3 AC_27 B01033 3 4 AC_39 B01223 5 6 AC_52 B01397 7 8
AC_17 B03624 3 4 AC_36 B01179 1 2 AC_39 B01224 6 7 AC_52 B01398 8 9
AC_17 B03625 4 5 AC_36 B01180 2 3 AC_39 B01226 8 9 AC_53 B01378 0 1
AC_17 B03626 5 6 AC_36 B01181 3 4 AC_39 B01227 9 10 AC_53 B01379 1 2
AC_18 B03641 0 1 AC_36 B01182 4 5 AC_40 B01231 0 1 AC_53 B01380 2 3
AC_18 B03642 1 2 AC_36 B01183 5 6 AC_40 B01232 1 2 AC_53 B01381 3 4
AC_18 B03643 2 3 AC_36 B01184 6 7 AC_40 B01233 2 3 AC_53 B01382 4 5
AC_18 B03644 3 4 AC_36 B01185 7 8 AC_40 B01234 3 4 AC_53 B01383 5 6
AC_18 B03645 4 5 AC_36 B01186 8 9 AC_40 B01235 4 5 AC_53 B01384 6 7
AC_25 B01059 0 1 AC_37 B01192 0 1 AC_40 B01236 5 6 AC_53 B01385 7 8
AC_25 B01060 1 2 AC_37 B01193 1 2 AC_50 B01414 0 1 AC_54 B01366 0 1
AC_25 B01061 2 3 AC_37 B01194 2 3 AC_50 B01415 1 2 AC_54 B01367 1 2
AC_25 B01062 3 4 AC_37 B01195 3 4 AC_50 B01416 2 3 AC_54 B01368 2 3
AC_25 B01063 4 5 AC_37 B01196 4 5 AC_50 B01417 3 4 AC_54 B01369 3 4
AC_25 B01064 5 6 AC_37 B01197 5 6 AC_50 B01418 4 5 AC_54 B01371 5 6
AC_25 B01065 6 7 AC_37 B01198 6 7 AC_50 B01419 5 6 AC_54 B01372 6 7
AC_25 B01066 7 8 AC_37 B01199 7 8 AC_50 B01420 6 7 AC_54 B01373 7 8
AC_25 B01067 8 9 AC_37 B01200 8 9 AC_50 B01421 7 8 AC_54 B01374 8 9
AC_25 B01068 9 10 AC_37 B01201 9 10 AC_51 B01402 0 1 AC_54 B01375 9 10
AC_26 B01047 0 1 AC_38 B01207 1 2 AC_51 B01403 1 2
AC_26 B01048 1 2 AC_38 B01208 2 3 AC_51 B01404 2 3

61

BEHARRA SILICA PROJECT PRE-FEASIBILITY STUDY

==> picture [85 x 27] intentionally omitted <==

==> picture [459 x 285] intentionally omitted <==

Figure 3.35 Representative head sample makeup

A representative 100 kg head sample was split to provide material for analysis and any requests for ROM/DSO material for marketing purposes. Refer Figure 3.35.

The head sample presented the ore characteristics as shown in Table 3.15 and Table 3.16.

Table 3.15 Head assay (as ROM)

SiO2
(%)
Ag2O
(ppm)
Al2O3
(ppm)
As2O3
(ppm)
BaO
(ppm)
CaO
(ppm)
CdO
(ppm)
CoO
(ppm)
Cr2O3
(ppm)
CuO
(ppm)
Fe2O3
(ppm)
K2O
(ppm)
Li2O
(ppm)
MgO
(ppm)
99.1 BDL 2780 BDL BDL 10 BDL BDL 1 BDL 2053 511 BDL 6
MnO
(ppm)
MoO3
(ppm)
Na2O
(ppm)
NiO
(ppm)
P2O5
(ppm)
PbO
(ppm)
SO3
(ppm)
Sc2O3
(ppm)
SrO
(ppm)
TiO2
(ppm)
V2O5
(ppm)
Y2O3
(ppm)
ZnO
(ppm)
ZrO2
(ppm)
59 BDL 10 BDL 3 BDL 33 BDL BDL 3440 2 BDL BDL 51

Table 3.16 Head sample sizing

Particle size distribution Particle size distribution Particle size distribution
Size (µm) Retained (%) Cumulative retained (%) Passing (%)
1000
850
710
600
425
300
250
180
125
75
0
0.7
0.9
2.1
4.5
16.9
26.9
15.8
17.4
9.1
3.1
2.5
0.7
1.6
3.8
8.2
25.1
52.0
67.8
85.2
94.3
97.5
100.0
99.3
98.4
96.2
91.8
74.9
48.0
32.2
14.8
5.7
2.5
0.0
Total 100.0 - -
P50 (µm)
P80(µm)
308
472

A split of the head sample was characterised by screening at 1 mm, 75 µm and the -1 mm +75 µm fraction being separated using heavy liquid at 2.65sg giving the results shown in Table 3.17.

62

BEHARRA SILICA PROJECT PRE-FEASIBILITY STUDY

==> picture [85 x 27] intentionally omitted <==

Table 3.17 Head feed characterisation

1959 head feed characterisation Mass (%) Assay Assay
Fraction SiO2 (%) Al2O3 (ppm) Fe2O3 (ppm) TiO2 (ppm)
O/S(+1.0 mm) 0.7 98.7 8500 1600 1350
Fines(-75µm) 2.5 94.0 9300 17000 26700
Sand(-1.0 mm,+75µm) 96.8 99.2 2567 1667 2850
HM(+2.85sg) 0.6 13.4 100300 183000 427600
Floats(-2.85sg) 96.1 99.7 1900 300 350
Total feed 100.0 99.1 2780 2053 3440

3.3.3 Process selection and basis

The process flowsheet followed a route derived from earlier testwork completed on a smaller and nonrepresentative sample completed by Nagrom.

3.3.4 Feed preparation

Phase 1 was a preliminary feed classification, including:

  • Removal of +1 mm trash

  • Desliming by cyclone.

The process flowsheet and mass flows are presented in Figure 3.36 below.

==> picture [390 x 334] intentionally omitted <==

----- Start of picture text -----

Head Feed
100.0 wt%
T01
Unit: 1.0mm Vibrating Screen
O/S
1.1
U/S
98.9 O/F
1.4
T01
Unit: 75mm Hydrocyclone
U/F
97.5
Sand Slimes O/S
97.5 1.4 1.1
Figure 3.36 Feed preparation – process flowsheet and mass flow
----- End of picture text -----

The oversize contained the bulk of the organic matter and the very coarse silica sand. Subject to available marketing opportunities scope exists to separate the silica sand and organics by various processes to generate a potential filter sand product.

Table 3.18 below shows the assays and relevant recoveries of SiO2 and contaminants. The data indicates the elevated rejection of contaminants in the cyclone overflow.

Table 3.18 Feed preparation process (FPP) assay and distribution summary

Assay Distribution

63

BEHARRA SILICA PROJECT PRE-FEASIBILITY STUDY

==> picture [85 x 27] intentionally omitted <==

FPP summary
(BVM ICP)
Dry
mass
(%)
SiO2
(%)
Al2O3
(ppm)
Fe2O3
(ppm)
TiO2
(ppm)
SiO2
(%)
Al2O3
(%)
Fe2O3
(%)
TiO2
(%)
Screen O/S 1.1 98.7 8500 1600 1350 1.1 2.9 0.9 0.5
Cyclone O/F 1.4 94.0 9300 17000 26700 1.4 4.3 13.5 13.0
Cyclone U/F
(Sand)
97.5 99.2 3000 1600 2650 97.6 92.9 85.6 86.6
Head feed 100.0 99.1 3150 1823 2985 100.0 100.0 100.0 100.0

The cyclone overflow was a mixture of silt +10 µm and clays -10 µm. This material was collected, and a flocculant supplier (BASF) was commissioned to conduct some preliminary flocculant selections and provided indicative consumption rates for use in the financial model. The results of this testwork are presented in BASF Report RM-006, which has been included with Appendix 8 metallurgical report and associated documents.

3.3.5 Wet gravity circuit

Phase 2 included a two-stage wet gravity circuit aiming to reject the heavy minerals which carry the bulk of the contaminant minerals (i.e. Fe2O3, TiO2, Al2O3 et al.). The second stage of the spirals received the primary middling.

A series of sighter tests were conducted on the primary spiral feed material to assess two alternative spiral types with the better performing spiral MT MG 12 being selected. For expediency, the data was based on heavy mineral results. The process flowsheet, mass flows, and metallurgical results are presented in the Figure 3.37 and Table 3.19 below.

==> picture [459 x 360] intentionally omitted <==

----- Start of picture text -----

FPP U/F
100.0 wt%
T02
Unit: MG12
Solids Feed Rate: 2.2tph
Feed Solids: 35% solids
S/Conc + Conc Tails
12.4 54.6
Mids
32.9
T03
Unit: MG12
Solids Feed Rate: 2.2tph
20% mids recirculation
(1.8tph fresh feed)
Feed Solids: 35% solids
S/Conc + Conc Tails
5.4 27.5
Mids
HMC Silica Tailings Product
17.9 82.1
----- End of picture text -----

Figure 3.37 Wet gravity circuit – process flowsheet and mass flow

64

BEHARRA SILICA PROJECT PRE-FEASIBILITY STUDY

==> picture [85 x 27] intentionally omitted <==

Table 3.19 Gravity concentration process (GCP) assay and distribution summary

GCP
summary
Mass
yield
(%)
Assay (BVM Assay (BVM ICP) Distribution Distribution
HM
(%)
Floats
(%)
SiO2
(%)
Al2O3
(ppm)
Fe2O3
(ppm)
TiO2
(ppm)
LOI
(%)
HM
(%)
Floats
(%)
SiO2
(%)
Al2O3
(%)
Fe2O3
(%)
TiO2
(%)
HMC 17.9 3.9 96.1 97.3 3818 7382 13640 - 100.0 17.3 17.5 27.7 81.4 86.4
Tails
product
82.1 0.0 100.0 99.6 2166 367 467 - 0.0 82.7 82.5 72.3 18.6 13.6
Feed 100.0 0.7 99.3 99.2 2461 1620 2819 - 100.0 100.0 100.0 100.0 100.0 100.0

3.3.6 Magnetic separation circuit

Phase 3 incorporated a magnetic separation stage to reject residual contaminant magnetic minerals carrying Fe2O3 and TiO2.

A set of sighter tests were conducted to define the preferred operating parameters with regards to wash water addition. The two conditions assessed were the standard parameters used in mineral sands and an alternative using no non-magnetics wash water to minimise the risk of washing off magnetic minerals into the non-magnetics product. The results supported the nil non-magnetics wash water with a lower non-magnetics product grades for Fe2O3 and TiO2 for negligible additional loss of mass into the magnetics product. This would also prove advantageous to operating costs.

The process flowsheet and mass flows are presented in Figure 3.38 and Table 3.20 below.

==> picture [459 x 229] intentionally omitted <==

----- Start of picture text -----

Spiral Tailings Product
T04 100.0 wt%
Unit: HMD WHIMS (16 pole, 8 feed port)
Solids Feed Rate: 32 tph equivalent
Feed Solids: 35%
Magnetic Intensity: 100%
Magnetic Flux Density: 12,500 Gauss Mag
N/M Flush Water: 0 L/min per feed port 2.4
Mag Flush Water: 60 L/min per feed port
N/M
97.6
----- End of picture text -----

Figure 3.38 Magnetic separation circuit – process flowsheet and mass flow

Table 3.20 Magnetic upgrade process (MUP) assay and distribution summary

MUP
summary
Mass yield
(%)
Assay (BVM ICP) Assay (BVM ICP) Distribution Distribution
SiO2
(%)
Al2O3
(ppm)
Fe2O3
(ppm)
TiO2
(ppm)
SiO2
(%)
Al2O3
(%)
Fe2O3 (%) TiO2
(%)
Mag 2.4 99.2 3200 1700 2400 2.4 3.6 9.6 14.6
N/M 97.6 99.7 2167 400 350 97.6 96.4 90.4 85.4
Feed 100.0 99.7 2192 432 400 100.0 100.0 100.0 100.0

3.3.7 Attritioning circuit

Phase 4 investigated the potential for the improvement of the product quality due to surface staining. Eight splits of the wet high-intensity magnetic separation (WHIMS) non-magnetics were used to test the impacts of high density attritioning. The series of tests covered options re: residence times (i.e. three, six, and nine minutes), reagents (HCl) and Freevis9934 (a viscosity modifier) and reagent dosages (i.e. 15 kg/t and 32 kg/t of HCl

65

BEHARRA SILICA PROJECT PRE-FEASIBILITY STUDY

==> picture [85 x 27] intentionally omitted <==

or 15 kg/t and 32 kg/t of Freevis). Post attritioning each sample was screened at 75 µm to effect removal of slimes. A sample was screened only to provide a baseline.

All tested conditions provided negligible changes in contaminant levels and with consideration of capital and operating costs, this option was not followed.

3.3.8 Classification circuit

Phase 5 applied further classification steps to align the final product to industry standard parameters. The bulk non-magnetics product was subjected to a stage of up-current classification to affect a removal of fines with a target cut point of 150 µm. The underflow (aka coarse fraction) was then wet screened at 600 µm.

The process flowsheet, mass flows and metallurgical results are presented in Figure 3.39 and Table 3.21 below.

==> picture [303 x 344] intentionally omitted <==

----- Start of picture text -----

WHIMS N/M
100.0 wt%
O/F
4.8
U/F
95.2
O/S
U/S (Final Product) 8.1
87.1
----- End of picture text -----

Figure 3.39 Classification circuit – process flowsheet and mass flow

Table 3.21 Classification assay and distribution summary

Classification
summary
Mass by
stage (%)
Assay Distribution Distribution
SiO2
(%)
Al2O3
(ppm)
Fe2O3
(ppm)
TiO2
(ppm)
LOI
(%)
SiO2
(%)
Al2O3
(%)
Fe2O3
(%)
TiO2
(%)
UCC O/F 4.8 97.9 9990 680 910 0.26 4.7 22.0 11.1 11.1
UCC U/F (Calc.) 95.2 99.6 1789 276 369 0.14 95.3 78.0 88.9 88.9
Screen O/S 8.1 99.7 1405 235 300 0.13 8.1 5.2 6.4 6.2
Screen U/S 87.1 99.6 1825 280 375 0.14 87.2 72.8 82.5 82.8
Feed (Calc.) 100.0 99.5 2184 296 395 0.14 100.0 100.0 100.0 100.0
Feed (Assay) - 99.5 2100 310 390 0.18 - - - -

66

BEHARRA SILICA PROJECT PRE-FEASIBILITY STUDY

==> picture [85 x 27] intentionally omitted <==

3.3.9 Product quality and recoveries

Following completion of the testwork, Perpetual prepared three preliminary products (see Table 3.22 below) with product data sheets, being:

  • The up-current classifier (UCC) underflow fraction, which fraction which the assigned product name of Beharra Premium #44 which has a nominal AFS No. of 44

  • The screen oversize fraction which the assigned product name of Beharra Special #27 which has a nominal AFS No. of 27

  • The screen undersize fraction which the assigned product name of Beharra Special #46 which has a nominal AFS No. of 46

Table 3.22 Product classification data

Testwork
classification
Product
classification
Mass by
ROM
Assay
SiO2
(%)
Al2O3
(ppm)
Fe2O3
(ppm)
TiO2
(ppm)
LOI
(%)
% 97.9 9990 680 910 0.26
UCC Underflow
(calc.)
Beharra
Premium #44
74.4 99.6 1789 276 369 0.14
Screen O/S Beharra
Premium #27
6.3 99.7 1405 235 300 0.13
Screen U/S Beharra
Premium #46
68 99.6 1825 280 375 0.14

Product size distributions for each of the above products are presented in Figure 3.40 below.

==> picture [416 x 290] intentionally omitted <==

Figure 3.40 Product size distribution

The yield to Beharra Premium #44 represents 74.4% of the bulk ROM feed sample and for the PFS, only one product yield is sufficient for the Ore Reserves estimates, and only one suite of product grades (yielded chemistry grades) is used for estimation of Ore Reserves.

Assays of intermediate products that may also be of a marketable quality are presented in Table 3.23.

67

BEHARRA SILICA PROJECT PRE-FEASIBILITY STUDY

==> picture [85 x 27] intentionally omitted <==

Table 3.23 Intermediate product assays

Process stream Mass %
vs ROM
SiO2 (%) Al2O3 (%) Fe2O3 (%) TiO2 (%) LOI (%)
Primaryspiral tails 53.8 99.5 2240 340 460 0.11
Mid retreat tails 26.8 99.6 1860 280 370 0.08
Combined spiral tails 80.6 99.5 2114 320 430 0.10
WHIMS non-magnetics 78.1 99.5 2100 310 390 0.18

3.3.10 Process flow overview

The process flowsheet for the bulk sample and the relevant intermediate potential product qualities is detailed in Figure 3.41 below.

==> picture [459 x 449] intentionally omitted <==

Figure 3.41 Process flowsheet

3.3.11 Process options

During the process of the flowsheet development, an abbreviated assay technique was used. This involved the assays being completed using an ICP analysis with a constrained level of precision and accuracy, i.e. a minimum level of detection (LOD) of 100 ppm and accuracy of ±50 ppm.

On completion of the test program, a more definitive ICP procedure was used with a minimum LOD of 10 ppm and accuracy of ±5 ppm. This procedure is used for certification of bulk shipping samples and are certified results.

68

BEHARRA SILICA PROJECT PRE-FEASIBILITY STUDY

==> picture [85 x 27] intentionally omitted <==

The results derived from the definitive assay procedure for the preliminary products indicated considerable improvement in the combined spiral products Fe2O3 results (i.e. from 370 ppm to 320 ppm) but comparable results for the SiO2, Al2O3 and TiO2.

As a function of the initial results, a large mass rejection (i.e. 17.4% of the ROM) resulted from the wet gravity processing phase.

With the revised assays, future testwork will focus on the reduction in this mass rejection at this stage and would be expected to generate a higher mass yield to the final products with minimal, if any loss in product quality.

Further work is also planned to assess any potential product quality impacts from the processing of the yellow and white horizon sands separately.

3.4 MINERAL TREATMENT AND HANDLING

3.4.1 Process facility description

The preliminary planning for operations is for the transport of ore by truck to the fixed process facility.

ROM material will be stockpiled near the feed module for loading into the feed bin by FEL at a nominal rate of 250 tph.

The feed module consists of feed bin (30 m[3] ) sized to provide sufficient surge capacity (approximately five minutes) to allow continuous feed delivery during refuelling of the loader, operator shift change and any ancillary stockpiling activities required.

Feed is drawn from the bin by a feed belt onto a transfer conveyor fitted with a belt weigher. The belt weigher provides feed back to the belt feeder drive to maintain the required feed rate.

The feed discharges the belt and is slurried with water for presentation to a 1 mm screen for rejection of coarse material being both mineral and organics.

The oversize is conveyed to a separate stockpile for either return to the mine void or potential site use.

The slurried undersize is pumped via a hydro-cyclone to effect desliming and fines rejection with a cut point of approximately 75 µm.

69

BEHARRA SILICA PROJECT PRE-FEASIBILITY STUDY

==> picture [85 x 27] intentionally omitted <==

==> picture [455 x 343] intentionally omitted <==

Figure 3.42 Silica sand plant Source: CDE

The cyclone overflow reports with other cyclone stage overflows to the thickener.

The cyclone underflow is collected in a sump and pumped to two stages of wet gravity spiral separators in a Primary (108 starts) and Mid Retreat (36 starts) configuration and associated pumping stages to reject elevated sg minerals from the free silica sands.

The spiral tails are combined with other sand reject streams and pumped to the rejects dewatering screens.

The spiral product streams are pumped to a distributor feeding four WHIMS units to reject magnetic contaminants from the non-magnetics free silica sands. The magnetic rejects are added to the spiral rejects.

The non-magnetic fraction is pumped via a distributor to two clusters of dewatering cyclones each mounted above two crossflow UCCs. The overflows report to the thickener and the underflows feed to the classifiers.

The classifiers are operated to reject fine minerals to effect both contaminant mineral rejection which predominate the fine fraction and to reject fine silica, which is typically a negative characteristic to silica sand marketing.

The classifier overflow reports to the thickener. Subject to marketing requirements the underflow is either pumped to the final product dewatering screens as the Beharra Premium #44 product and the dewatered product is conveyed to the nominated product stockpile.

Alternatively, the underflow is pumped to a classification screen to prepare a coarse and fine product. The screen aperture will be selected to meet defined marketing requirements. In the testwork, the screens used a 600 µm aperture and produced the Beharra Special #27 (coarse) and Beharra Special #46 (fine) products.

The screen oversize already being dewatered is conveyed to the nominated stockpile area. The screen undersize is pumped to the final product dewatering screens and conveyed to the relevant stockpile.

Dewatering screen supernatant reports to the thickener

Reject streams from the spirals and WHIMS mags are pumped to a cyclone cluster mounted above the rejects dewatering screen. The dewatered sand fraction is conveyed to the rejects bin mounted for direct dumping

70

BEHARRA SILICA PROJECT PRE-FEASIBILITY STUDY

==> picture [85 x 27] intentionally omitted <==

into the ore trucks for return to the mined-out void. Nominally, one or two trucks per hour will backload these rejects.

The various fines/slimes-bearing flows will report to the thickener with a suitable flocculant added to generate a clear overflow for reuse within the process water circuit.

The thickener underflow will be pumped to a plate press to further densify the fines/slimes. The solids discharge will be combined with the sand rejects into the rejects bin for return to the mine void. The supernatant will be recycled to the thickener feed.

Automatic samplers will be fitted to allow all potential product streams to be sampled, located as follows:

  • Slurry samplers

  • WHIMS feed

  • UCC feed

  • Screen feed

  • Screen undersize

  • Conveyor crosscut samplers

  • Screen oversize.

For plant mass balancing, each of the following slurry streams will be fitted with mass low/density instrumentation:

  • Spiral feed

  • WHIMS feed

  • UCC feed

  • Screen feed

  • Screen undersize.

A preliminary GA can be found at Appendix 13.

3.4.2

Process water supply

Operation of the plant will see a high level of reuse of the process water to minimise both the demand for additional make-up water and minimise the impact on the water table.

It is proposed to utilise a large process water storage tank to which the thickener overflow reports.

Water to make up for losses into both the final product and rejects will be sourced from a deep aquifer bore fitted with a suitable pump to bring to the surface and a booster pump to deliver the water to the process water tank to meet demand.

The process water will be reticulated to the plant in two services with one being a low-pressure supply for sump make up and high-volume dilution requirements and a second lower volume, high-pressure supply to meet demand for high and or constant pressure demands (i.e. WHIMS wash water, screen sprays etc.).

The makeup water requirement for the plant is nominally 29.5 m³/hr.

3.4.3

Rejects and water disposal

The reject rate is relatively low (<60 tph) and rejects other than the primary screen oversize will be collected in the elevated rejects bin. The bin will be fitted with a dump valve that can be operated from the truck by the operator to effect the load out of rejects for return to the mine void. This equates to three trucks being assigned a back haul duty in every two-hour period.

The primary screen oversize will be stockpiled for possible use for the rehabilitation to utilise the elevated level of organics likely to be present and the coarseness of the sand to minimise windage of the surface during rehabilitation.

This solution ensures that rejects are dewatered directly by the dewatering screen at nominally 10% moisture, thus minimising water loss, and can be placed back on to the pit floor to meet the soil profile and the rehabilitation recommendations.

BEHARRA SILICA PROJECT PRE-FEASIBILITY STUDY

71

==> picture [85 x 27] intentionally omitted <==

Water disposal will not be required as the site will be a nett user of water due to:

  • Evaporation of retained water in the product stockpiles and replaced rejects

  • Seepage of retained water in the product stockpiles and replaced rejects and from plant spillages/overflows following operational disturbances

  • Water retained in product being transported off site.

Due to the substrate surrounding the plant site, there will be negligible stormwater occurrences. The minimal roofing of plant and equipment will have any flows directed via the thickener for supplementation of bore water demands.

3.4.4 Final product handling

Subject to the market requirement, multiple defined product stockpiles will be delineated using concrete bollards. The final product is dewatered using dewatering screens giving a moisture content of nominally 10%. The final product is then stacked using a radial stacker conveyor. This provides a stockpile pre transport of nominally 15,000 tonnes.

As the stacker conveyor travels radially the final product is further dewatered using an under-stockpile dewatering system. This system uses drain coil type pipework connected to a vacuum pump. The reclaimed water is then pumped back to the process water bin for reuse in the process.

This provides a final moisture content of around 5% remaining in the transported product.

Product loading will be by FEL into the truck. To prevent access to incorrect stockpiles for load out, suitable barriers will be put in place.

72

BEHARRA SILICA PROJECT PRE-FEASIBILITY STUDY

==> picture [85 x 27] intentionally omitted <==

4. INFRASTRUCTURE AND SERVICES

4.1 INFRASTRUCTURE REQUIREMENTS

Due to the close proximity of the Beharra project site to Dongara and Geraldton, on-site infrastructure requirements during the construction phase will be minimal and supply services during mine and process plant operations readily available.

4.2 UTILITIES

4.2.1

Power supply

Process plant energy consumption will be nominally 12 GWhpa at peak production, achieved within the first three years of operation.

Perpetual engaged PCS to provide an evaluation of energy supply options for the Beharra Project. The PCSissued Beharra Silica Project energy supply strategy report is attached at Appendix 12.

A range of power station configurations were evaluated and found that the thermal (diesel fuelled) power station design was optimal with the potential introduction of solar at a later date. This allows the Project to commence with a reliable thermal power solution and potentially augment the power station with solar PV should demand increase. Figure 4.1 shows a typical thermal power station located on site.

==> picture [455 x 188] intentionally omitted <==

Figure 4.1 Typical thermal power station

Proposed power stations consist of multiple generators providing redundancy and maintenance opportunities minimising operational impact. The power station will be located within close proximity to the process plant, and be diesel fuelled via a self-bunded fuel storage tank. Taking into consideration a mine life in excess of 15 years, the power station will also be relocatable. Figure 4.2 depicts the internal layout of a thermal power station.

73

BEHARRA SILICA PROJECT PRE-FEASIBILITY STUDY

==> picture [85 x 27] intentionally omitted <==

==> picture [455 x 215] intentionally omitted <==

Figure 4.2 Thermal power station – internal layout

An opportunity remains to connect to the South West Interconnected System, but based on initial inquiries with Western Power, the cost to connect to and upgrade the existing distribution power lines to the Beharra project site are unlikely to be economic compared to the standalone option.

4.2.2 Water supply

Groundwater overview

Perpetual is currently investigating various options for the securing of a groundwater licence for the proposed Beharra operation. The Beharra deposit sits over the northern extents of the deep confined Yaragadee aquifer.

*The Yarragadee north aquifer is the largest regional aquifer in the northern Perth Basin, containing a great thickness of low-salinity groundwater (Figure 4.3). The Yarragadee aquifer extends south from the Greenough River to the Perth region, covering a total area about 17,600 km[2] .

The Yarragadee aquifer consists of a multi-layered sequence of sandstone beds with very fine to very coarse grained and granule-sized quartz sand that are often feldspathic with variable amounts of matrix clay, and interbedded siltstone, shale and claystone.

There are four sub-units within the Yarragadee Formation that have distinctive lithologies: units A and C are predominantly unconsolidated sandstone, while units B and D are predominantly siltstone, shale and claystone.

Groundwater recharge into the Yarragadee aquifer is mostly by direct rainfall infiltration over outcrop areas as well as downward leakage from overlying aquifers. Concentrated recharge from rivers and streams is also important in some areas.

Groundwater within the Yarragadee aquifer is generally fresh to marginally brackish (Figure 4.4) but varies considerably both laterally and with depth. This variability is due to salt input from recharge, depth of groundwater flow and residence time.

*Source: Department of Water – North Perth Basin, Geology, hydrogeology and groundwater resources

BEHARRA SILICA PROJECT PRE-FEASIBILITY STUDY

74

==> picture [85 x 27] intentionally omitted <==

==> picture [455 x 650] intentionally omitted <==

==> picture [249 x 19] intentionally omitted <==

----- Start of picture text -----

Figure 4.3 Yarragadee aquifer – saturated aquifer thickness
Source: Department of Water
----- End of picture text -----

BEHARRA SILICA PROJECT PRE-FEASIBILITY STUDY

75

==> picture [85 x 27] intentionally omitted <==

==> picture [460 x 683] intentionally omitted <==

----- Start of picture text -----

Figure 4.4 Yarragadee aquifer – groundwater salinity
Source: Department of Water
----- End of picture text -----

76

BEHARRA SILICA PROJECT PRE-FEASIBILITY STUDY

==> picture [85 x 27] intentionally omitted <==

Perpetual is currently investigating the practicalities of securing a groundwater licence from the Yarragadee aquifer within the Dongara and Twin Hills sub-areas, both of which are accessible to the Beharra Project (refer Figure 4.5).

==> picture [447 x 655] intentionally omitted <==

----- Start of picture text -----

Figure 4.5 Groundwater sub-areas (namely, Dongara, Eneabba Plains and Twin Hills)
Source: Pennington Scott
----- End of picture text -----

BEHARRA SILICA PROJECT PRE-FEASIBILITY STUDY

77

==> picture [85 x 27] intentionally omitted <==

Perpetual, together with our groundwater consultants, are in liaison with the Department of Water and Environmental Regulation (DWER) and will continue to work towards optimising the water supply during the DFS.

Water table – interface

Generally, the water table in the proposed mining pit is nominally +10 m below natural ground level. The water table is associated with grey sands which are not of significant commercial value due to the higher levels of contaminants they contain.

As part of the early mine pit optimisation study, the pit floor was raised by 0.5 m in the pit shell model to ensure a cleaner interface between the white and grey sands and to ensure the operation was operating above the water table at all times (refer Figure 4.6).

==> picture [455 x 314] intentionally omitted <==

==> picture [330 x 19] intentionally omitted <==

----- Start of picture text -----

Figure 4.6 Typical pit section showing yellow, white, grey sands and water table
Source: Snowden (2021)
----- End of picture text -----

Process water requirement

As part of the process plant circuit development, the mass balance identified the make-up water requirement for the process plant and various other minor consumers of water for the operation. The make-up water requirement to satisfy the operation is between 0.5 GL and 0.7 GL.

As noted during the metallurgical bulk test program, the Beharra feedstock contains very low slimes (-75 um material) by mass at around 1.4% of the dry feed. One of the added advantages of this relatively clean material is the ability to recycle the plant process water with a high efficiency and minimal losses.

The abovementioned material profile, in conjunction with excellent settling rates achieved during the floc tests conducted by BASF further minimised the makeup water requirement. This is achieved by eliminating large settling and process water ponds which are prone to high levels of evaporative loss.

The ground water resources in the area are suitable for the process water application as the salinity and Total Dissolved Solids (TDS) is generally <1000 ppm.

Perpetual will further work to optimise the process water consumption during the next phase of project development.

78

BEHARRA SILICA PROJECT PRE-FEASIBILITY STUDY

==> picture [85 x 27] intentionally omitted <==

4.2.3 Fuel supply

Fuel is available on a contract delivery basis from well-established distributors based out of Geraldton and tanker deliveries will be maintained to support process plant operations utilising on site storage. A self-bunded fuel tank located at the process plant area will provide a total storage capacity of 69 kL and is designed to accommodate a 10-day fuel supply, with 25% buffer, for the power station and light vehicle usage.

Fuel supply and storage for mining operations will be provided by the mining contractor.

4.3 BUILDINGS AND FACILITIES

4.3.1 Offices

Site administration offices are of containerised relocatable design. Offices and amenities also included in this group are first aid, ablutions, crib room and laboratory. Allowances for basic fit out have been made.

4.3.2 Workshops

Workshop and store facilities consist of a typical covered containerised dome shelter construction utilising 2 x 12 m shipping containers adjoined using a dome shelter and concrete slab. A double stacked site store and additional office facility is also included.

4.3.3 Mineral laboratory

The site mineral laboratory will consist of a 6 m relocatable containerised unit housing basic site quality assurance production monitoring equipment, such as vibratory sieve shaker, PSD screens, and sampling equipment. Production assays will be sent offsite for analysis and final product assays conducted at the wharf prior to shipment.

4.4 TRANSPORT INFRASTRUCTURE

4.4.1 Road

The investigations into the transport of the Beharra Project final product by road required an appraisal of the existing offsite infrastructure, existing road conditions and likely upgrades required for the hauling of final product.

Given that the most cost-effective and practical solution is utilising PBS approved 100T Super Triples as the road transport vehicle, these loads and transport frequencies were then applied to the road network and the following upgrades and options were identified.

Mount Adams Road

Currently, Mount Adams Road is rated at RAV 3.1 standard and can accommodate 55T doubles only. Hauling this size payload is undesirable from both cost and frequency perspectives.

Mount Adams Road will require upgrading to the RAV 7.3 standard in order to accommodate 100T Super Triple Road trains. The distance from the turnoff from the Brand Highway to site is nominally 9.0 km (refer Figure 4.7 and Figure 4.8).

79

BEHARRA SILICA PROJECT PRE-FEASIBILITY STUDY

==> picture [85 x 27] intentionally omitted <==

==> picture [455 x 215] intentionally omitted <==

Figure 4.7 Mount Adams Road – typical view east

While a full seal of this road has been allowed for in terms of capital, further engineering investigations will be required to determine whether a full seal of the road surface will be required, or whether sealing of the approach to the rise of the various elevations will be sufficient. This work is to be carried out during the DFS.

==> picture [455 x 281] intentionally omitted <==

Figure 4.8 Mount Adams Road upgrade – route and elevation Source: Google Earth Pro

The upgrade costs associated with these types of road upgrades are reasonably well understood and indicative costs are between A$0.6 million/km and A$0.8 million/km.

Given the size and frequency of the vehicle movements, consultation with a variety of existing stakeholders using Mount Adams Road currently and discussions with other project developers will be undertaken during the DFS.

Final apportioned costs will be determined once the various stakeholders have been further consulted and in principle agreements are in place.

80

BEHARRA SILICA PROJECT PRE-FEASIBILITY STUDY

==> picture [85 x 27] intentionally omitted <==

Brand Highway–Mount Adams Road intersection

As part of the road upgrades required, the Brand Highway-Mount Adams Road intersection will need to be upgraded. This is based upon the selected transport configuration, in this case the Super Triple 100T units.

As trucks exit Mount Adams Road on to the Brand Highway and turn north to Geraldton, an acceleration lane will be needed to enable safe merging with other northbound road users. In addition, a turnoff lane will be required to enable safe exit from the traffic flow running south. Refer Figure 4.9.

==> picture [455 x 296] intentionally omitted <==

Figure 4.9 Brand Highway–Mount Adams Road intersection Source: Google Earth Pro

As a recent example, Image Resources are using the same 100T Triples for its Boonanarring mineral sands operation and was required to upgrade the intersection of Wannamal Road West and the Brand Highway running south to Bunbury. This upgrade was approximately a A$2.5 million exercise and it is likely that similar costs will be incurred for the Mount Adams Road upgrade.

Main Roads Western Australia (MRWA) is currently investigating an inland corridor that will bypass Dongara on the way to Geraldton (refer Figure 4.10 and Figure 4.11). The road will take a more direct route to Geraldton and could potentially eliminate about 20 km of road haul length from the freight route depicted in Section 5.2.7, thereby reducing freight costs in the future.

81

BEHARRA SILICA PROJECT PRE-FEASIBILITY STUDY

==> picture [85 x 27] intentionally omitted <==

==> picture [461 x 631] intentionally omitted <==

Figure 4.10 Proposed Dongara to Geraldton inland corridor Source: MRWA

82

BEHARRA SILICA PROJECT PRE-FEASIBILITY STUDY

==> picture [85 x 27] intentionally omitted <==

==> picture [455 x 228] intentionally omitted <==

Figure 4.11 Dongara to Geraldton consultation timeline Source: MRWA

4.4.2 Rail

As part of the freight and logistics study exercise, a road + rail solution was also investigated to ascertain whether any opportunities were available to rail the final product to Geraldton.

There is an existing rail line some 13.0 km to the west of the Beharra site. If a combined road and rail operation is adopted, the methodology would be generally as follows. The product would be loaded onto road units at the mine site, then transported some 13 km, via Mount Adams Road, crossing the Brand Highway, to the end of Carson Road where a new rail loading loop would be built (as shown in Figure 4.12).

==> picture [455 x 316] intentionally omitted <==

Figure 4.12 Site to rail head Source: Google Earth Pro

83

BEHARRA SILICA PROJECT PRE-FEASIBILITY STUDY

==> picture [85 x 27] intentionally omitted <==

At the proposed rail loop location, a hardstand, open-air storage and wagon loading facility would be set up. The product would be loaded onto wagons using a FEL and transported by rail to Geraldton Port where they will be unloaded using the rail bottom dump facility.

The product would then be stored in an undercover storage structure and when ready for despatch, loaded onto ships using the existing ship-loading system. A conveyor system may need to be set up to link the storage facility to the ship-loading system. The rail infrastructure is owned by ARC Infrastructure (ARC), a subsidiary of Brookfield Infrastructure Partners LP.

The rail segment between the proposed rail load loop and Dongara (some 24 km) is a piece of rail infrastructure which has not seen any commercial activity in the last 15 years or so; however, ARC mentioned the rail corridor has been regularly checked and maintained appropriately.

Prior to any reactivation of the line, a review and maintenance of the line would be undertaken, this is a relatively simple activity and routinely performed, as advised by ARC.

In terms of infrastructure, Carsons Road would require significant upgrade as it appears to be little more than basic hardstand in nature. To run the short haul truck operation, this would have to be upgraded to the correct standard dependant on the selection of transport vehicles.

Also of note, there is a slight misalignment at the Carsons–Brand–Mount Adams intersection in an east-west direction that may need to be rectified should the rail option be considered (refer Figure 4.13).

==> picture [455 x 331] intentionally omitted <==

----- Start of picture text -----

Carsons–Mount Adams Road intersection on Brand Highway Rail looking north
Carsons Road end – adjacent to rail line Carsons Road end – view east to rail line
Figure 4.13 Road and rail alignment
----- End of picture text -----

While a direct spur line from the Beharra site to the existing rail line has also been considered, this solution may prove difficult and costly due to the crossing of the Brand Highway.

Road and rail options will be further considered during the DFS.

84

BEHARRA SILICA PROJECT PRE-FEASIBILITY STUDY

==> picture [85 x 27] intentionally omitted <==

4.4.3 Port of Geraldton

Overview

Given the Beharra site location, the Port of Geraldton (see Figure 4.14) is the only real option where bulk product can be exported. The Port is keen to facilitate trade, extremely active and is currently in discussions with a variety of proponents who are either expanding existing operations or seeking opportunities such as Perpetual for its developing projects.

==> picture [455 x 143] intentionally omitted <==

Figure 4.14 Geraldton Port Source: MWPA

The Port trade volume for 2019/20 was 14.95 Mt, slightly down on the previous year by 6% (0.96 Mt), primarily attributable to the reduced grain season and some impacts of COVID-19.

The Port handles a variety of bulk commodities as listed in Table 4.1 below.

Table 4.1 Bulk commodities – Geraldton Port

Product Product detail Loading berth/method
Ores Iron ore Bulk via Berth 7 and 5
Manganese Bulk via Berth 5
Heavy metals and
concentrates
Lead sulphide concentrate (HMC) Bulk via Berth 4
Containers via Berth 6
Copper concentrate Bulk via Berth 4 Containers via Berth 6
Zinc concentrate Bulk via Berth 4
Containers via Berth 6
Nickel concentrate Containers via Berth 6
Mineral sands concentrate Containers via Berth 6
Sands Clean fill and construction sands Bulk via Berth 5 and 4
Mineral sands Bulk via Berth 4
Other Fertilisers Discharge via Berth 6/Berth 2

Source: MWPA

Other opportunities – Port Master Plan

Mid-West Ports Authority (MWPA) has undertaken the development of a Port Master Plan for the Port of Geraldton. The plan (shown at Figure 4.15) provides a high-level analysis of potential trade growth and required infrastructure to accommodate this growth over a 30-year planning timeframe.

85

BEHARRA SILICA PROJECT PRE-FEASIBILITY STUDY

==> picture [85 x 27] intentionally omitted <==

==> picture [455 x 321] intentionally omitted <==

Figure 4.15 Geraldton Port Master Plan Source: MWPA

It further considers the development required in the short to medium term (i.e. over the next 15 years) to maximise the throughput and efficiency of the existing Port, prior to considering longer term expansion options, at either Geraldton or the Oakajee Port. While the long-term expansion options are considered, additional investigations, consultation and design work would be required to enable a preferred option to be recommended.

Ultimately the best solution for Beharra operations would be to have a custom-built storage facility as part of the new port development project. This would deliver a high degree of independence, eliminate the need for offsite storage and reduce operating cost. This option is dependent upon the Port acting and executing the proposed plan.

Perpetual will remain engaged with MWPA and pursue this going forward.

4.5 COMMUNICATIONS AND INFORMATION SYSTEMS

There is currently no 4G or 5G signal coverage on the Beharra project site, with no planned expansion of existing networks in the near future, as depicted in Figure 4.16.

On-site communications will be conducted through use of satellite phones and two-way radios in lieu.

86

BEHARRA SILICA PROJECT PRE-FEASIBILITY STUDY

==> picture [85 x 27] intentionally omitted <==

==> picture [459 x 222] intentionally omitted <==

Figure 4.16 Telstra 4G coverage – Beharra project site

Source: Telstra

4.6 WASTE DISPOSAL

4.6.1

Surface water management

Product stockpile dewatering systems are incorporated into the process plant design to recover and pump reclaimed surface water back to primary process water tank.

Any surface water resulting from rain events will be dispersed through infiltration into the sands around the site.

4.6.2

Wastewater

Wastewater comprises water within the operational area, including process water, pit water, tailings water and hardstand runoff, that is not recoverable back into the process water circuit or is in excess of the capacity of the process water system.

Process plant design incorporated equipment that recirculates water back to the main process water tank thereby minimising wastewater. Accordingly, the volume of wastewater is considered to be negligible during mine operations.

Any wastewater water will be released principally through infiltration into the sands around the site.

4.6.3

Solid waste

A waste management plan will be developed describing the necessary procedures and infrastructure for solid waste management.

Disposal of solid waste on site will be restricted to that of inert material that will not impact groundwater quality. All other solid wastes will be stored in appropriately constructed facilities prior to offsite disposal in accordance with relevant legislation.

4.7 TEMPORARY FACILITIES

Due to the proximity of the townships of Dongara and Geraldton to the Beharra project site, there is no requirement for a camp or mess facilities during construction or operations.

A 20 kVA genset with portable fuel day tank will provide power during the construction phase and be retained as an emergency power back up post construction.

The 25 kl fire services tank will be installed early during construction to provide the water required for concrete works and onsite/access road dust suppression.

87

BEHARRA SILICA PROJECT PRE-FEASIBILITY STUDY

==> picture [85 x 27] intentionally omitted <==

Site offices will be provided by the process plant installation contractor and mining contractor, with temporary fencing and ablutions provided by Perpetual.

4.8 OTHER

4.8.1 Security

A chain wire perimeter security fence will be installed around the administration and amenities area only. Sensor activated floodlights and localised closed circuit television (CCTV) will be installed around the administration, amenities and process plant areas.

4.8.2 Fire control

The site will be supplied with a fire water system incorporating a dedicated 25 kl water tank and associated electric primary supply pump and jacking pump and in the event of a power loss a diesel back-up pump.

Fire extinguishers will also be located within the administration, amenities and process plant areas for fire suppression, if required.

4.8.3 Emergency services

The nearest emergency services to the Beharra project site are at Dongara, which is a 23-minute drive. Facilities and services available are a medical centre, hospital, St Johns Ambulance and Fire and Rescue. Geraldton (a 1 hour and 6 minute drive from site) has additional emergency services capability.

88

BEHARRA SILICA PROJECT PRE-FEASIBILITY STUDY

==> picture [85 x 27] intentionally omitted <==

5. OPERATIONS MANAGEMENT

5.1 OPERATIONS STRUCTURE

5.1.1 Operating philosophy

The Beharra Project will be operated from the commissioning phase into sustained operations under a formal Operations Plan and Health, Safety, Environment and Community (HSEC) management systems.

5.1.2 Management structure and organisation

The Operations management structure for the Beharra site will be similar to many of the smaller quarrying and aggregates businesses with overall responsibilities in an operational sense falling under the remit of the site senior executive and a small team covering the key roles such as Safety, Health, Environment, Quality, Production Management, and Maintenance. This structure will be further developed during the DFS.

5.1.3

Contract strategy and management

A variety of key contracts will be required for the operation. There has been some early identification of the range of contracts likely to be required for the Beharra operation and some of the major operational contracts are outlined below:

  • Mining – Mining contract scope including grubbing and stripping, overburden removal, ore excavation, delivery to process plant feed hopper, product loadout and rejects return basis $/t delivered.

  • Rehabilitation – Contract to include acquisition and storage of seed, place and stockpile mulched vegetation, topsoil stockpile and management, dump and spread surfaces in preparation for soil growth media placement, load, haul, dump and spread stockpile topsoil to rehabilitation face and spread of native seed. Basis $/ha.

  • Freight and logistics – Haulage inclusive of transport of final product from the Beharra site to offsite storage facility, then short haul from storage facility to Port of Geraldton on a $/t basis.

  • Power supply – Supply of power by Independent Power provider (IPP). IPP to supply power station and all fuelling maintenance etc., build-own-operate-maintain (BOOM) contract power supplied on a $c/kwhr basis.

  • Fuel supply – Diesel fuel delivery and decanting service – basis $/litre delivered.

A formal Contractor Management System (CMS) will be developed and implemented that will ensure contractor capability and suitability prior to engagement, and ongoing monitoring during the period of engagement.

Further development of contract scopes and management systems will be identified in the Project Execution Plan (PEP) at DFS stage.

5.2 OPERATIONAL ASPECTS

5.2.1 Management and administration

PEC will utilise a small corporate management team with site focus to minimise overhead and operational costs. Corporate/marketing and major contract management activities will be based offsite with only operations staffing located at the Beharra site.

5.2.2

Mining

Currently, the mining activities will be performed under a contract mining scenario and invoiced on a $/BCM basis. Quantities will be assessed using conventional bulk site survey techniques and back checked using a weight-o-meter fitted to the processing plant feed hopper reading tonnes of material.

The mining contractor shall provide all plant equipment and labour necessary to ensure the continuous, safe, and reliable delivery of ore and return of waste to the mining pit. The contractor will operate under the site regulations and relevant legislative requirements.

The contractor shall operate autonomously in relation to all on and offsite costs included and attributed to the single $/BCM fee.

89

BEHARRA SILICA PROJECT PRE-FEASIBILITY STUDY

==> picture [85 x 27] intentionally omitted <==

5.2.3 Processing

The process plant will be operated on a 24 hour/7 days per week basis.

The plant feed is loaded under the terms of the mining contractor at the nominal rate of 250 tph.

The plant is operated from a centrally located control room with a high level of automation/instrumentation, allowing operation by two operators per shift working three roster rotations. The operators are supported by a shift coordinator and two day-crew to provide cover for planned and unplanned crew absences during dayshift, five days per week.

Operational maintenance will be supported by five maintenance personnel working dayshift only, on a 4-on 3-off/3-on 4-off roster with a provisional eight-hour planned maintenance shutdown per month.

Technical support will be provided by a plant metallurgist on a five-day per week roster.

The plant will provide a high degree in flexibility to meet multiple product requirements and will allow sections of the plant to be bypassed directly to the final product classification screen or dewatering screens.

Final products will be loaded onto the road trains by the mining contractor.

Product stockpile management will be a one of the primary roles of the plant metallurgist and shift coordinator.

Preliminary site layout 5221-M-GA-0000-8098 Rev A, inclusive of process plant and major infrastructure, is

included at Appendix 9.

5.2.4

Technical services

The final product samples will be automatically sampled and collected on a shift basis. These shift samples will be dried, and sub sampled for transport to an offsite laboratory for product quality assays.

Splits of these samples will also be routinely subjected to site screening tests to confirm settings on the upstream

classifier and for blinding or holes on the final classification screen.

The Metallurgist will also be responsible for routine calibration of mass flow density gauges (including being the Radiation Safety Officer), belt weigher, and adjustment of metallurgical settings.

Technical services will also provide all other non-operational functions in support of operations and include the

following key processes:

  • Mine surveying for mining control, tailings survey, land acquisition, infill drilling and exploration

  • Exploration and geological support

  • Mine planning, long and short term

  • Metallurgical control

  • Mineral sampling, handling, and analysis

  • Environmental management, inclusive of rehabilitation, topsoil replacement, product superintending for shipment of product.

5.2.5

Maintenance

Maintenance will provide all support for both operations and general project infrastructure, which will include the following:

  • Fixed plant

  • Light vehicles

  • Buildings, power supply, diesel generators and general infrastructure.

Day-to-day operational maintenance on the fixed plant shall be addressed by the owner’s maintenance team with use of external contractors to support major shutdowns.

Typically for this type of wet process plant, maintenance is largely preventative consisting of the replacement of pump liner wear parts and screening assemblies which can be readily planned to fall under a scheduled maintenance shutdown routine.

Allowance of an eight-hour planned maintenance shutdown per month has been included.

90

BEHARRA SILICA PROJECT PRE-FEASIBILITY STUDY

==> picture [85 x 27] intentionally omitted <==

The diesel power station will be maintained under a BOOM contract and the maintenance built into the power price. Light vehicles will be serviced by a local dealership.

5.2.6

Procurement and supply

A Procurement Plan will be developed during the Beharra Project DFS, detailing the processes and procedures to be adopted during procurement activities.

Perpetual will attempt to procure off the shelf items locally or within Australia. In the case of an original equipment manufacturer (OEM) being an international company, the local agent for the OEM will be approached.

Where possible, similar types of equipment will be procured from the same vendor (i.e. pumps) in order to standardise the equipment and minimise spares holdings.

5.2.7

Transport and logistics

Overview

Qube provided a complete transport solution which was used as the basis for the Beharra Project.

With an output of 1.51 Mtpa considered, the final product transport component of the Project contributes significantly to the operating cost as expected. This will continue to be optimised going forward during the DFS.

In addition to the means of transport, port options and facilities have also been investigated. Perpetual has met with MWPA representatives and discussed possible export quantities, storage options, and berth availability at the Port of Geraldton.

Various road freight options have been put forward and considered from both a practicality and cost perspective. While rail is to be considered, initially the road solution is preferred as it provides flexibility during the initial stages of operations, the approvals and issues are well understood, and there are some unknowns regarding timing and rail access to be discussed later in this document.

A commentary on the base case that has been adopted in relation to the transport and logistics methodology

at this juncture are outlined below.

Methodology

Operational breakdown:

  • Loading final product at site

  • Long haulage site to Narngulu offsite storage facility

  • Offsite storage offload and reload activities at Narngulu

  • Short haulage from Narngulu to Port/Berth

  • Ship loading activities.

Final product will be loaded from the final product stockpile using a FEL and loaded into trucks bound for the Port of Geraldton.

Site loading in the current operational model is the responsibility of the mining contractor.

From the loading point the trucks will travel approximately 2.8 km on the internal haul road from which point they will turn left onto Mount Adams Road.

The trucks then travel nominally 9 km until they reach the Brand Highway intersection.

This intersection will need upgrading (discussed in infrastructure) to include both an acceleration lane and turning lane for the return trip. Turning right onto the Brand Highway, the trucks travel some 86 km to Narngulu to a 60,000-tonne capacity stockpiling shed of which various options are to be considered.

Once dumped, the trucks return back to the Beharra site to be reloaded (see Figure 5.1).

91

BEHARRA SILICA PROJECT PRE-FEASIBILITY STUDY

==> picture [85 x 27] intentionally omitted <==

==> picture [455 x 245] intentionally omitted <==

Figure 5.1 Road transport route – site to Narngulu Source: Google Earth Pro

The transport configuration for the short-haul assignment from Narngulu to the port is different from the longhaul exercise as the dump point is either hopper (end tip) or drive over (belly dump) infrastructure.

The Narngulu shed is filled and when a vessel is ready to be loaded at the port, the short haul cycles begin to transport the product to the ship loading shed where either drive over or end tip options are available into the hopper, likely to be Berth 4.

Some overflow storage is available on the port site, but limited to around 12,000 tonnes, and with competing users on a lease arrangement.

Summary of costs

Costs at the wharf in relation to ship loading and wharfage have been captured and are identified in the summary of costs at Table 5.1.

Table 5.1 Summary of costs

Freight and logistics –preliminary cost schedule – Beharra (RAV 7.3) Freight and logistics –preliminary cost schedule – Beharra (RAV 7.3)
Item Road charges Unit ($/t)
1 Loading product at site Incl.
2 Haulproduct – Beharra to Narngulu Incl.
3 Stockpile management – Narngulu Inc.
4 Haulage – Narngulu to Port of Geraldton(Berth 4) Inc.
Port charges
5 Wharfage – MWP Incl.
6 Shiploading– Berth 4 Incl.
Subtotal $24.85
- *Moisture modifyingfactor 5% added
TOTAL $26.09

*Moisture content added to dry tonnes.

Site to Narngulu – truck body configurations considered

There are three mainstream truck body options that are considered for use in meeting the required duty to transport the final product to the Narngulu offsite storage facility. These are demonstrated below.

92

BEHARRA SILICA PROJECT PRE-FEASIBILITY STUDY

==> picture [85 x 27] intentionally omitted <==

RAV3.1 – Double configuration

Currently, access to site via Mount Adams Road is limited to a RAV3.1 network which allows the Double configuration (shown at Figure 5.2) to operate, achieving an estimated payload of 55 tonnes.

==> picture [341 x 52] intentionally omitted <==

==> picture [148 x 9] intentionally omitted <==

----- Start of picture text -----

Figure 5.2 Double configuration
----- End of picture text -----

RAV4.3 – Pocket Road Train

If access roads and intersections were to be upgraded to a RAV4.3 network, it would allow a Pocket Roan Train configuration (shown at Figure 5.3) to operate, achieving an estimated payload of 65 tonnes.

==> picture [336 x 56] intentionally omitted <==

==> picture [186 x 8] intentionally omitted <==

----- Start of picture text -----

Figure 5.3 Pocket Road Train configuration
----- End of picture text -----

RAV7.3 – PBS Super Triple

If access roads and intersections were to upgraded to a RAV7.3 network, it would allow PBS Super Triples configuration (shown at Figure 5.4) to operate, achieving an estimated payload of 100 tonnes.

==> picture [430 x 53] intentionally omitted <==

Figure 5.4 PBS Super Triple configuration

After considering the options available, the PBS Super Triple was selected for the duty in order to minimise truck movements and operating costs. Based upon transporting 1.517 Mtpa of product to Port, truck movements per day adopting this solution are reduced to nominally 42 per day as opposed to 64 per day with the Pocket Road Train and 76 using the Base Double 55t configuration.

Further works in relation to the permitting of this vehicle and engagement with various stakeholders such as Irwin Shire Council, City of Geraldton, and MRWA is underway and will be progressed further during the DFS.

Narngulu to Port – truck body configurations considered

The infrastructure at Berth 4 drives the selection of the vehicle configurations as only hopper (end tip) or drive over (belly dump), infrastructure is available as a direct input.

However, if on-port storage is available, then side tip bodies may be considered.

The Combination End Tipper and Combination Belly Dump are shown at Figure 5.5 and Figure 5.6, respectively.

==> picture [423 x 56] intentionally omitted <==

Figure 5.5 Combination End Tipper

93

BEHARRA SILICA PROJECT PRE-FEASIBILITY STUDY

==> picture [85 x 27] intentionally omitted <==

==> picture [416 x 67] intentionally omitted <==

Figure 5.6 Combination Belly Dump

Narngulu – offsite storage

After investigating the possibilities of a direct road to on-port storage solution for the Beharra product, it became clear that given the variety of commodities vying for storage and berth access at the Port, offsite storage is the more practical option with the current MWPA infrastructure in place.

The locality of Narngulu to Geraldton Port is demonstrated in Figure 5.7 below.

==> picture [455 x 263] intentionally omitted <==

Figure 5.7 Narngulu to Geraldton Port locality Source: Google Earth

Offsite bulk storage is currently being utilised at Narngulu from the port by a number of exporters, including Iluka Resources and GMA Garnet for bulk offsite sand storage.

Ship loading

The options in terms of berths available and suitable for the Beharra product are No’s 4 and 5.

The Berth 5 ship-loader has a theoretical maximum speed of 5,000 tph; however, in reality, this is constrained by the load out rate from the storage sheds and time lost due to vessel de-ballasting, hatch changes, etc. With iron ore typically they see load rates of 3–3,500 tph, but silica sand is more typically 2,000 tph given its lower bulk density.

As an important consideration, the sharing of Berth 5 running iron ore, irrespective of thorough decontamination procedures, is undesirable given the Beharra low iron product specifications.

The Berth 4 ship-loader has a theoretical maximum speed of 1,800 tph; however, this is also constrained by the rate of delivery to bulk handling system and by time lost due to vessel de-ballasting, hatch changes, etc. With the Berth 4 mineral sands products, typically loading rates of 900–1,200 tph are achieved. Rates on silica would be lower again at around 740 tph.

From investigations and discussions thus far, both with Perpetual’s consultants and MWPA, Berth 4 would be the most appropriate for the loading of the Beharra product. While Berth 4 tends to be used for smaller “parcel” shipments of 10–20,000 tonnes, this may well suit the initial shipment sizes.

94

BEHARRA SILICA PROJECT PRE-FEASIBILITY STUDY

==> picture [85 x 27] intentionally omitted <==

6. HEALTH, SAFETY, ENVIRONMENT, AND COMMUNITY

6.1 POLICY AND PLANNING

6.1.1 Company policy and objectives

Perpetual will develop a HSEC policy designed to provide a controlled work environment that protects the health, safety and welfare of all employees and other persons at its work sites.

6.1.2

Statutory obligations and other commitments

Perpetual will meet its obligations to the current Australian and WA Workplace Health and Safety (WHS) Act, Regulations, Standards and Codes of Practice by developing and maintaining a HSEC Management System appropriate to the management of health, safety, and environment at all work sites.

6.1.3

HSEC management systems

The HSEC Management System will form the basis for management and control and development will be undertaken with consideration to:

  • ISO 45001:2018 – Occupational health and safety management systems

  • ISO 14001:2016 – Environmental management systems

  • ISO 31000:2018 – Risk management

  • Corporate Social Responsibility obligations.

6.1.4

Key performance indicators

HSEC key performance indicators will be developed post-DFS to ensure a quantifiable measure is used to evaluate how effectively Perpetual is achieving set business objectives.

6.2 HEALTH AND SAFETY

6.2.1 Risk assessment summary

The key health and safety risk identified for the Project is exposure to and working around silica. Considerations with respect to this risk are discussed below.

6.2.2

Silica-specific considerations

Perpetual recognises there is a potential human health exposure risk to respirable crystalline silica (RCS) at the Beharra Project. RCS could be produced as an airborne dust when silica sand is disturbed through mineral extraction, stockpiling, transportation, and handling and is dry enough to generate dust particles. These particles can be small enough to lodge deep in the lungs and cause illness or disease such as bronchitis, silicosis, and lung cancer.

A Workplace Exposure Standard (WES) exists for crystalline silica and represents the concentration of an airborne hazardous chemical within a worker’s breathing zone that should not cause adverse health effects or undue harm. The current WES for RCS is 0.1 mg/m[3] over an eight-hour working day in WA, with the WES likely to be lowered to 0.05 mg/m[3] by the end of 2020 to meet national standards.

RCS exposure and safety requirements are governed by the following Western Australian Legislation:

  • Occupational Safety and Health Act 1984

  • Occupational Safety and Health Regulations 1996

  • Mines Safety and Inspection Act 1994

  • Mines Safety and Inspection Regulations 1995.

Prior to the commencement of any extraction activities at the Beharra site, a Health Risk Assessment (HRA) will be undertaken to define key sources and the pathways of RCS. With this information, defined dust management procedures to reduce the risk of exposure to personnel above the WES will be developed using

95

BEHARRA SILICA PROJECT PRE-FEASIBILITY STUDY

==> picture [85 x 27] intentionally omitted <==

the hierarchy of controls – substitution, isolation, engineering, administrative, personal protective equipment (PPE).

Additionally, the HRA will be a key input to the preparation of a Health and Hygiene Management Plan (HHMP) in accordance with the Department of Mines Industry Regulation and Safety (DMIRS) Guideline “Preparation of health and hygiene management plan – guide” (2018) and approved by DMIRS prior to operations commencing. The HHMP will define as a minimum the sources, pathways management and monitoring of RCS. The HHMP will be reviewed annually to ensure it meets current standards and capture any changes to operational circumstances or procedural controls. This will enable Perpetual to maintain continual compliance with its legislative health and safety obligations.

6.2.3 Management and monitoring plan

Perpetual is responsible and accountable for providing quality processes, practices, structures, equipment and verification of personnel competency and training, to ensure that Perpetual employees, employees of its subcontractors and all other personnel sharing the work areas with Perpetual are free from the risk of workplace injury or illness.

A Perpetual Safety Management Plan (SMP) will be developed as part of the HSEC management system to enable a uniform and effective standard of health and safety management to be applied to all Beharra Project activities. The SMP will been designed to comply with Australian Regulations, Codes of Practice, Perpetual Policies and Procedures and to ensure that all subcontractor systems are in alignment.

96

BEHARRA SILICA PROJECT PRE-FEASIBILITY STUDY

==> picture [85 x 27] intentionally omitted <==

6.3 ENVIRONMENT

6.3.1 Environmental baseline studies

Considerable baseline environmental studies were commissioned by Tiwest (now Tronox) for its Dongara titanium minerals project, immediately adjacent to the east of the Beharra Project. Many of the baseline studies covered the Beharra project area and have been procured from Tronox via a data share arrangement. This data will significantly contribute to the environmental impact assessment process to support approvals for Beharra and covers factors such as:

  • Groundwater and groundwater-dependent ecosystems

  • Surface water

  • Flora, vegetation, weeds, and dieback

  • Terrestrial and subterranean fauna

  • Soil profiles and acid sulphate soils

  • Indigenous heritage.

Additional studies conducted to date by Perpetual to complement the extensive Tronox dataset cover the following factors:

  • Flora and vegetation

  • Terrestrial fauna

  • Groundwater and groundwater-dependent ecosystems

  • Heritage.

Further baseline studies will be conducted during the ongoing project development.

6.3.2

Aspects and impacts assessment summary

The key potential impacts associated with the Beharra Project are believed to be:

  • Medium term direct impact to vegetation and groundwater dependent ecosystems (vegetation) from clearing nominally 550 ha. Duration assumes successful rehabilitation.

  • Short term indirect impact to groundwater dependent ecosystems (vegetation) through groundwater drawdown during operations.

  • Medium term direct loss of Carnaby Cockatoo foraging habitat. Duration assumes successful rehabilitation.

  • Direct loss of Carnaby Cockatoo birds through vehicle strike.

Other potential impacts could include:

  • Hydrocarbon and chemical contamination of soils and groundwater

  • Dust emissions and impacts to surrounding vegetation

  • Indirect impact to the Yardanogo Nature Reserve

  • Introduction of weeds, dieback, and feral animals

  • Altered fire regimes.

A comprehensive aspect and impacts assessment will be conducted at a later stage as the Project development plan becomes more refined.

6.3.3 Environmental management plan

An Environmental Management Plan (EMP) and associated procedures will be developed as part of the HSEC Management System. The following aspects will be included within the plan:

  • Air quality

  • Hydrocarbon management

  • Groundwater management

  • Waste control

97

BEHARRA SILICA PROJECT PRE-FEASIBILITY STUDY

==> picture [85 x 27] intentionally omitted <==

  • Flora and vegetation

  • Fauna

  • Dieback.

6.4 MINE REHABILITATION AND CLOSURE

6.4.1 Mine rehabilitation

A comprehensive study was undertaken to determine the most suitable progressive rehabilitation method for the Beharra Project based on the existing environment. Consultation and benchmarking with other extractive sand miners in the local area as well as expert rehabilitation practitioners was undertaken to assist in developing the method defined in Table 6-1.

Table 6.1 Beharra rehabilitation method

Activity Method
Acquire and store seed A seed mix will be defined based on veg units with a focus on Carnaby Cockatoo foraging
species and collected on an annual basis up to 250 kg per annum (benchmarked on Iluka
Eneabba program), dependent on reproductive success and climatic conditions. The first
location for seed acquisition will be that which can be acquired prior to clearing. This may
involve picking seed over the entire LOM project and in adjacent local areas outside of the
disturbance footprint within a provenance zone where species relevant to the project
vegetation types can be harvested. It will be important not to have the provenance zone too
constrained as this can sometimes be the case without practical knowledge from seed pickers
and benchmarks from other sites. Seed would be stored at a controlled temperature, in an
approved supplier’s facility. Different seed types would be treated with various dormancy
breaking treatments (scarification/smoky water etc.); however, a percentage of seeds would
go untreated. Further work is required on defining recalcitrant flora species (typically
Restionaceae,Cyperaceae,Dilleniaceae) and methods for enhancing germination success. Some
species mayrequire supplyfrom nurserytube stock and directplanted.
Clear and grub area,
mulch vegetation place in
separate stockpile
Vegetation will be cut from the surface, usually with a light dozer, and windrowed. If the
vegetation has root balls below the surface, ideally these will be removed during clearing and
grubbing as they will interfere with the spread of topsoil. The windrowed material will be fed
into a tub grinder/mulcher to generate a wood mulch with pieces generally no larger than 50
cm long x 10 cm in diameter, with the majority much smaller. This will be stockpiled separately
as with the soil. However, direct placement after soil placement will occur where it is feasible
to do so.
Load, haul and dump top
500 mm to soil to stockpile
Load, haul and dump of growth media will occur from areas which has been cleared of
vegetation. Although the nominal depth for soil harvest/excavation is 500 mm of soil and
subsoil, pit testing demonstrates a very large variety of both soil type near the surface and
subsoils at depth. In many cases there will be little value in harvesting the barren sands below
the top 100–300 mm of soil. The Project will be best served to manage depth of harvest very
carefully and not mix good quality growth media with the underlying barren material which
has little if any growth media properties. As such, a smaller volume may be harvested to
achieve the best results when re spread. However, this needs to occur based on educating the
supervising and operators with to respond to the inherent variability of depth and soil type.
Single recovery depth of topsoil only will be the most appropriate approach as there is too
little depth and too little distinction between soil types to harvest two soil types. The material
will be stored in paddock dumped piles no greater than 2 m high. This soil material is highly
susceptible to mechanical degradation. Hence, the material should be placed in dumped piles
at the correct density to spread the material to up to 500 mm depth with minimal pushing
distance. The material will be rotated onto the next available rehabilitation surface. Where
direct transfer is feasible,this should occur.

98

BEHARRA SILICA PROJECT PRE-FEASIBILITY STUDY

==> picture [85 x 27] intentionally omitted <==

Activity Method
Load, haul, dump and
spread rejects on floor
area
During production activities trucks will return dewatered tails/rejects back to the mined pit
floor to increase the distance to the water table and limit seasonal inundation of the root zone
and act as growth media. It is important rejects clay content is maintained from 4% to 12% to
enable suitable moisture retention within the soil profile for plant availability. This material
should be spread evenly on the pit floor (and not dumped on the pit batters) and well mixed
so as to not form clay layers that will limit water and plant root penetration. Dumped material
will be pushed flat so another layer can be placed. If the material moisture content is too high
(rejects anticipated to be around 5% moisture content) it may need to lie fallow for some time
before rehabilitation commences to avoid issues associated with compaction. Monitoring of
claycontent will occurprogressivelyat this time.
Dozer trim all
dumped/spread surfaces
in preparation for soil
growth media placement
Prior to the placement of soil on rehabilitation surfaces, including side batters and pit floor, all
rehabilitation will be cut to a very high quality of trim. This is generally completed with a
dozer and the objective is to achieve very even compaction and no significant windrows or
gaps. Such features will increase the susceptibility of soil erosion post closure. Ideally, after
trimming the only thing visible on a surface is track shoe marks. Given the low grades of
batters, it may be worth experimenting with a grader. Generally, a light dozer is used
otherwise. See below.
Load, haul, dump and
spread stockpile topsoil to
rehabilitation face
Growth media is rehandled from stockpile to the rehabilitation face. This soil material is highly
susceptible to mechanical degradation. Hence, the material should be placed in dumped piles
at the correct density to spread between 200 mm and 300 mm depth with minimal pushing
distance. A light dozer (Komatsu 155 or Cat D7) would be much more suited to this task to
minimise track degradation due to machine weight. Given the low hectares for rehabilitation
each year, the surface trimming and topsoil spreading may be best carried out by a
contractor with rehabilitation experience and fit forpurpose machinery.
Load, haul, dump and
spread stockpiled timber
mulch to rehabilitation face
As is the case, timber mulch piles placed at the ideal density for spreading evenly, with fit for
purpose machinery and an experienced operator. Note the timber mulch should be spread as
soon as practicable to protect the soil surface from wind erosion. It will also be a very
valuable source of seeds.
Spread native seed Some sites, where there is a dense placement of timber mulch, choose not to cross rip. Cross
ripping is generally undertaken to enhance infiltration and minimise erosion. In this instance the
materials into which the seed is sown is high infiltration with adequate clay content and
dispersal through the growth media. The timber mulch is similar to a rock mulch or other erosion
resistant covers. From a seed broadcast perspective, further to benchmarking and trials, it may
be that the seed is hand broadcast at the optimal time of year after the timber mulch is
placed at a rate similar to nearby peers. Alternatively, because of the differences in the
mining processes at Beharra, if the soils and timber mulch are direct placed which is likely to
have suitable seed retention, it may be the case that the rehab success is assessed at least 24
months after final timber spreading in each cell, and if adequate species diversity and density
is not achieved per defined completion criteria (pending rehabilitation/closure plan),
seed/tube stock can be dispersed. Seed to be dispersed at 5 kg per hectare.
Monitoring/reporting and
maintenance
Subject to the development of detailed Rehabilitation Plan, a formal rehabilitation monitoring
will commence within 24 months after final rehabilitation activities within the first 15 ha cell
and once per annum after that (note this frequency can be adjusted based on findings).
Having a regular monitoring regime in the early years will assist identifying opportunities for
improvement in the rehabilitation process and adjusting/trialling different operational and
rehabilitation methods to improve future revegetation outcomes. It’s not uncommon that the first
few years of revegetation, consistent with ecosystem regeneration (such as after fire) will
feature short lived early colonisers and monitoring results will report this accordingly.
Monitoring results will be analysed with previous data and outcomes reported internally to
PEC and externally via the regulatory annual reporting processes. The strategies of selecting
the highest quality soils, converting tree trash into a mulch product, developing gentle slope
angle and the favourable clay contents in the substrate, the project will develop very
favourable conditions to re-establish an ecosystem generally similar to that which occurs as the
baseline.

99

BEHARRA SILICA PROJECT PRE-FEASIBILITY STUDY

==> picture [85 x 27] intentionally omitted <==

Activity Method
Based on the low batter angles on the outer pit walls, sandy soil profile and lack of local
surface water drainage features that may contribute to water erosion, it is not expected that
significant repair or maintenance earthworks will be required after rehabilitation of each cell.
Typical maintenance that could be expected would include:

Repair of minor erosion gullies

Respond to unplanned ponding of water locally

Re-seeding where revegetation performance is not aligned with broader performance

Weed surveillance and treatment where required

Reinstatement of drainage control drains and bunds (drains to remove water from topsoil
stockpile storage areas,for instance.

6.5 CULTURAL HERITAGE

6.5.1 Traditional owners

The recognised traditional owners for the Project are the Southern Yamatji.

6.5.2

Native Title

The Southern Yamatji Native Title claim was concluded in October 2020. An Indigenous Land Use Agreement (ILUA) now exists between the Southern Yamatji and the WA Government. Therefore, Native Title has been extinguished over the project area.

6.6

COMMUNITY

6.6.1 Community management and development

Long-term relationships with local communities are essential to business success and Perpetual recognises the importance of these strong relationships within the community. Through development of a community engagement plan providing a forum to communicate company activities and receive feedback, Perpetual will achieve active community participation providing tangible benefits and positive outcomes to the local communities.

Local service industry

Majority of services and supplies required during construction and operations are available within the Dongara, Geraldton area and Perpetual shall prioritise utilising these local suppliers where possible.

Employment and recruitment

Perpetual will recruit and employ personnel during the construction and operational phases of the Beharra Project from a range of sources, including:

  • Locally, in close proximity to the Project

  • Within the WA labour market

  • Within the Australian labour market

  • Through subcontractor arrangements.

Accommodation and housing

Accommodation will not be required on site due to the proximity of local townships. Dongara has temporary accommodation capacity and availability to meet requirements during the construction phase. During operations, personnel employed at the mine site will be required to provide their own housing within the nearby towns, supporting the local community.

Other risk items

Identified risks related to the community have been detailed in Sections 8.8 and 8.9 of this report, titled Community Based Risks and Non-Environmental Risks, respectively.

100

BEHARRA SILICA PROJECT PRE-FEASIBILITY STUDY

==> picture [85 x 27] intentionally omitted <==

6.6.2 External relations and stakeholder management

Perpetual has undertaken an assessment of its key stakeholders that have an interest in the Beharra Project. These are defined in Table 6.2.

Table 6.2 External stakeholders

Group Stakeholder
Local Government Authorities Shire of Irwin
Government Agencies Department of Agriculture, Water and the Environment (Federal)
Environmental Protection Authority
Department of Mines, Industry Regulation and Safety
Department of Water and Environmental Regulation
Main Roads WA
Other Interested Parties Yamatji Southern Regional Council
Shire of Irwin Community
Beach Energy

Perpetual will maintain a program of engagement throughout the construction, operation and decommissioning phases of the Project. Consultation will be aimed at developing relationships that are mutually beneficial to both parties.

Stakeholders will be engaged early in the planning process, primarily in the interests of achieving a collaborative approach to raise any concerns and provide Perpetual with the means to respond to feedback and to ensure that local knowledge is considered in the design and management of the Project.

A stakeholder register and records of engagement are maintained.

6.6.3

Mine closure

The closure of the site has two components; that of progressive rehabilitation of the land disturbed directly through the mining process and the removal of fixed infrastructure and utilities followed by remediation of the land it occupied.

The ongoing rehabilitation process is described in Section 6.4.1 and involves the progressive backfilling of the mined area, contouring of the material and replacement of topsoil. Vegetation will then be established to stabilise the area. Costs associated with this activity are included in the annual operating costs.

Following completion of mining and processing activity site clearance will be undertaken. The silica sands abstraction process results in no major tailings facility or waste dumps; this along with limited reagent use makes site clearance straightforward.

It is planned that much of the equipment will be retained for other operations or sold. The nature of the plant with portable conveyors, plant design being conducive to relocation within the site and the use of mobile equipment for mining purposes being a substantial component makes this realistic.

Following removal of infrastructure, the land will be contoured, and vegetation established. On this basis, no specific costs have been allocated to site closure following removal of infrastructure and remediation of the land it occupied.

Costs associated with progressive rehabilitation are in the annual operating costs.

101

BEHARRA SILICA PROJECT PRE-FEASIBILITY STUDY

==> picture [85 x 27] intentionally omitted <==

7. INDUSTRIAL RELATIONSHIP AND HUMAN RESOURCES

7.1 INDUSTRIAL RELATIONSHIP

7.1.1 Statutory obligations and other commitments

Perpetual will remain compliant with any applicable industrial relations laws and regulations.

Perpetual will utilise the services of employer associations including Chamber of Commerce and Industry WA (CCIWA), the Australian Industry Group, also the Australian Mines and Metals Association to assist in meeting statutory obligations.

7.1.2 Employee relations strategy

A Human Resources/Industrial Relations Management Plan (HR/IR Plan) will be developed during the DFS to enable Perpetual to define the HR/IR Strategy for work on the Beharra Pproject.

7.2 HUMAN RESOURCES

7.2.1 Organisational model and requirements

During the development and construction phases of the Beharra Project, the Perpetual owner’s team will be responsible for overall project management, administration/contract management, and site safety. The construction workforce will primarily consist of subcontractors for civil, concrete, and electrical distribution from the power supply to process plant works. The process plant and power station packaged plants will be supplied and constructed by OEM-provided workforces.

The proposed operational workforce will consist of subcontractors for mining and product loadout, with Perpetual employees operating and maintaining the process plant and supporting infrastructure. Figure 7.1 (organisational model) is indicative of the staffing arrangement on which the PFS costs are based and will be optimised further during DFS.

==> picture [454 x 129] intentionally omitted <==

Figure 7.1

Organisational model

102

BEHARRA SILICA PROJECT PRE-FEASIBILITY STUDY

==> picture [85 x 27] intentionally omitted <==

8. RISK MANAGEMENT

An internal preliminary risk assessment was carried out to identify and categorise key planning and operational risks to the Beharra Project.

8.1

OBJECTIVES

The objectives of the preliminary risk assessment were to:

  • Identify and document the key planning and operational risks associated with the current project concept

  • Assign a broad risk category to the risks, thereby identifying any potential fatal flaws and to assist in the scoping and focus of technical investigations.

8.2

SCOPE

The preliminary risk assessment was carried out by Perpetual and key discipline consultants. The assessment was held to identify key planning and operational risks related to the Project, with additional focus on any that may impact on the feasibility of the Project. The exercise covered risks associated with both the construction and operational phases of the Project.

8.3

METHODOLOGY

Risks were considered for technical areas that are likely to require investigation during the Project approvals process, including:

  • Land use planning

  • Surface water and groundwater

  • Terrestrial ecology

  • Landscape and visual amenity

  • Indigenous community

  • Social and community impact

  • Air quality, noise, and vibration

  • Site contamination

  • Rehabilitation

  • Other.

It was considered that key risks to the Project could exist in these technical areas which could be further investigated at the pre-feasibility level using the existing project description and publicly available information (and with minimal stakeholder consultation).

As risks in each technical area were identified, they were categorised into one of the following four categories:

  • Category F : Risk areas that may have no viable solution, considered to represent a potential fatal flaw in the Project as described.

  • Category A : Risk areas requiring detailed investigation and assessment, and complex or detailed management as part of the approvals process.

  • Category B : Risk areas requiring moderate levels of investigation, targeted assessment, and standard management measures as part of the approvals process.

  • Category C : Risk areas requiring minimal attention as part of the approvals process and subject to standard management measures.

The matters considered in determining the category for a particular risk were:

  • Level of sensitivity

  • Potential scale and severity of impacts

  • Capacity for management of potential impacts.

103

BEHARRA SILICA PROJECT PRE-FEASIBILITY STUDY

==> picture [85 x 27] intentionally omitted <==

Considerations associated with these matters are detailed in Table 8.1.

Table 8.1 Preliminary risk assessment categories

Category Level of sensitivity Potential scale and
severity of impacts
Capacity for management of potential impacts
F High sensitivity, significant
assets or values lost
Severe impact Viable measures not expected to be available to
manage risk; proposed action or impact unacceptable
to regulators
A High sensitivity, significant
assets or values under
threat
Medium to high impact Complex and detailed management measures are
available that can be adopted with some tailoring
B Moderate sensitivity, some
significant assets or values
may be affected
Medium to low impact Standard management measures are available that
can be adopted with some tailoring
C Significant assets or values
absent or probably
avoidable
Low impact Standard management measures are available

It is recognised that these preliminary assessments were made using information available at the time of study. A conservative approach was therefore adopted whereby reasonable worst cases were assumed when the risk could not be ruled out on the basis of available information.

The method outlined above for the preliminary risk assessment was considered appropriate at this early stage of the Project, given the limited amount of Project-specific information available. It is expected that a later detailed risk assessment would be run using a risk assessment methodology based upon the Australian/New Zealand Standard, AS/NZS ISO 31000:2018 Risk Management – Principles and Guidelines as part of the project impact assessment and approvals process.

8.4

8.4.1

PERMITTING AND APPROVALS

Land use planning

Land use planning is the process of regulating the use of land in an effort to promote more desirable social and environmental outcomes as well as a more efficient use of resources. Land use planning is important to ensure sustainability and minimal impact on future generations.

8.4.2

Identified key risks

The key land use planning related risks identified, rated, and discussed during the assessment are presented below in Table 8.2.

Table 8.2 Land use planning

Risk Category/risk level
Land useplanning
Mining Act tenement application approval process for mining lease may result in:

Significant delay in project schedule

Cost impacts

Atworst,Project notapproved.
B
Mining impact to the Yardanogo Nature Reserve which is located on the western boundary of the
tenement.
B
Mine site access using existing roads through the Yardanogo Nature Reserve may not be
approved.
C

8.4.3

Scope of further investigations

The next steps in this technical area would be:

  • Additional review of existing and future land uses of the subject site and adjacent land and their impacts, and determine whether there are any sensitive uses in proximity to these areas

  • Consultation with WA Government and local indigenous groups.

104

BEHARRA SILICA PROJECT PRE-FEASIBILITY STUDY

==> picture [85 x 27] intentionally omitted <==

8.4.4 Environmental conditions

Identified key risks

The key environmental conditions related risks identified, rated, and discussed during the assessment are presented below. Construction phase risks are presented in Table 8.3 and operational phase risks are presented in Table 8.4.

Table 8.3
Environmental conditions – construction phase risks
Category risk level
B
Risk Category risk level
Environmental conditions
Approval conditions potentially unreasonable and cause significant limitations on mine footprint,
operations or staging which adversely impacts the project schedule, design, budget. and economic
viability.
B
Table 8.4
Environmental conditions – operational phase risks
Risk Category/risk level
Environmental conditions
Approval conditions may be unreasonably onerous and apply significant limitations which
adversely impacts schedules, mine operation output/logistics, efficiency, and economic viability.
B
Mine operation may give rise to significant complaints in reference to working with Silica and
potential impact of silica dust.
B
Mine operation may give rise to significant complaints(e.g. noise, air, water, and waste). C

8.4.5

Scope of further investigations

The next steps in this technical area would be:

  • Review of WA and local policies

  • Implementation of a silica hygiene management policy

  • Consultation with WA Government and local indigenous groups.

These actions would provide local area context, help to determine the level of government and community support for the Project and assist in identifying the range of permitting and approval issues associated with the Project.

8.5 SURFACE GROUNDWATER AND HYDROGEOLOGY

8.5.1 Identified key risks

The surface water, groundwater and hydrogeological risks identified, rated, and discussed during the assessment are presented below. Construction phase risks are shown in Table 8.5 and operational risks are shown in Table 8.6.

Table 8.5
Surface water, groundwater, and hydrogeology – construction phase risks
Risk Category/risk level
Surface water, groundwater,and hydrogeology.
Uncontrolled spill, discharge from site(s), or erosion may result in significant impact on beneficial
uses of surface waters(waterqualityand hydrogeology)– e.g. stormwater and drainage.
C
Interaction with local groundwater may result in (real or perceived) significant impacts on water
level in aquifer, including economic and operational beneficial uses.
C
Table 8.6
Surface water, groundwater, and hydrogeology – operational phase risks
Risk Category/risk level
Surface water, groundwater, and hydrogeology
Water allocation from remote aquifer results in additional capital and operatingcost increases. B
Remote water source(s) pumpstation or supplyline is interrupted/damaged. C
Drawdown of the local aquifer results in impact to groundwater dependent ecosystems
(vegetation). Cumulative impact with Tronox Dongara project exacerbates impacts resulting in
challenging environmental approvals.
A

105

BEHARRA SILICA PROJECT PRE-FEASIBILITY STUDY

==> picture [85 x 27] intentionally omitted <==

8.5.2 Discussion of key risks

Securing a water supply allocation from a nearby source is required to keep both the capital and operating costs to a minimum.

Perceived impacts on the water level, GDE and quality of local aquifers from mining activity needs to be managed through plant design and operation practices.

It is anticipated that potential risks to surface water associated with discharges (during both construction and operation) will be able to be mitigated using standard measures and management strategies.

8.5.3

Scope of further investigation

As the Project matures to a definitive level, further detailed investigation relating to water supply will be required.

8.6 NATIVE TITLE AND HERITAGE

8.6.1

Identified key risks

Risks associated with Native Title and heritage identified, rated and, discussed during the assessment are shown in Table 8.7.

Table 8.7 Native Title and heritage – project risks

Risk Category/risk level
**Heritage **
High level of investigation (field survey work) in relation to development on or near the Southern
Yamatji native title land. Recommendation by Southern Yamatji representatives to use previously
established historic tracks mayalter mine location(to avoid impacts).
C
If human remains, skeletal materials that may be human, or materials that may belong to a human
grave are discovered during exploration or resource evaluation within the cleared survey areas,
Perpetual must follow the DPLH procedures and stop work immediately.
B
Relationshipwith indigenous communitybreaks down, causingdelays and increased costs. C

8.6.2 Discussion of key risks

Disharmony amongst locals relating to land owning rights, employment privileges.

Mining operation reveals human remains, artefacts or materials that may belong to a human grave delaying approvals and Project construction/operations.

Perpetual employees and contractors executing the proposed works must be informed of their obligations under the Aboriginal Heritage Act 1972 .

8.6.3

Scope of further investigation

Continued consultation and maintaining discussions with the Southern Yamatji people, regarding any future matters that may arise in relation to the areas surveyed, including any further proposed excavation or ground disturbance activities or access to uncleared proximate areas. A Standard Heritage Agreement between Perpetual Resources and Southern Yamatji will be required as a condition of mining tenure.

8.7

TERRESTRIAL ECOLOGY

8.7.1

Identified key risks

The risks to terrestrial ecology identified, rated, and discussed during the assessment are presented below. Construction risks are shown in Table 8.8 and operational risks are shown in Table 8.9.

Table 8.8 Terrestrial ecology – construction risks

Risk Category/risk level
Terrestrial ecology
Direct loss of the foraging habitat for Carnaby’s Black-Cockatoo a Federally listed threatened
(Endangered)bird species.
A

106

BEHARRA SILICA PROJECT PRE-FEASIBILITY STUDY

==> picture [85 x 27] intentionally omitted <==

Direct impact to Carnaby’s Black Cockatoo as a result of vehicle/machinerystrike. C
Lack of available suitable Carnaby Black-Cockatoo foraging habitat in the local region to offset
direct impact from vegetation clearing at a 3:1 ratio. Restricts area of mine disturbance and
therefore mine life.
A
Direct loss of restricted wetland vegetation communities and Kwongan sandplains flora species
diversity.
A
Table 8.9
Terrestrial ecology – operational risks
Risk Category/risk level
Terrestrial ecology
Poor standard of rehabilitation resulting in low recruitment and return of Carnaby Cockatoo
foraginghabitat in the local area.
A
Direct impact to Carnaby’s Black Cockatoo as a result of vehicle/machinerystrike. C
Poor standard of rehabilitation resulting in low recruitment and return of flora species diversity
similar to those found in restricted wetland vegetation communities and Kwongan sandplains.
A

8.7.2

Discussion of key risks

Impacts to terrestrial flora and fauna environment need to be avoided/mitigated.

8.7.3 Scope of further investigation

A comprehensive impact assessment needs to be carried out after the development plan becomes more refined.

8.8 COMMUNITY-BASED RISKS

8.8.1

Identified key risks

These generally relate to issues which are routinely managed and investigated during the approvals process and, with the exception of those relating to community opposition, are not expected to represent significant risks to the Project.

Opposition to mining projects from at least some sections of the local communities is a possibility. While such opposition does not often prevent a project from proceeding, it can potentially result in significant delays, increased costs and pose a reputational threat to the proponent. Community-based risks are shown in Table 8.10.

Table 8.10 Community-based risks

Risk Category/risk level
Additional
Community may raise concerns that information and communication regarding the approvals
process, nature of the Project, management measures and impacts/benefits is inadequate.
Community may feel they have not been able to have a say and/or see how their say has been
addressed.
C
Community may raise concerns that impact to landscape character, landforms and visual amenity
of the countryside is significant.
C
Community/Community Groups may raise concerns that impact to Carnaby Black-Cockatoo
foraging habitat is excessive and provide considerable input to environmental approvals process
resultingin significant delays.
B
Community and authorities raise concerns that project may have a negative social and economic
impact(rather than benefit).
C
Community/landowners may not be satisfied that final landform and rehabilitation will be able to
be achieved or could have long-term legacy/risks.
C
Potential community (real or perceived) concern and impacts from hazardous substances and
dangerousgoods.
C
Potential complaints and non-compliance with health and safety policies during construction and
operations regardingair emissions(e.g. silica dust).
C

8.8.2

Scope of further investigation

Continued consultation and maintaining discussions with the local community and local authorities, during the continued development of the Project.

107

BEHARRA SILICA PROJECT PRE-FEASIBILITY STUDY

==> picture [85 x 27] intentionally omitted <==

8.9 NON-ENVIRONMENTAL

8.9.1 Identified key risks

Risks identified in Table 8.11 relate to issues within the process plants and mining and marketing.

Table 8.11 Identified risks – non-environmental

Risk Category/risk level
Resource
Expected SiO2 grades are not realised C
Mining
Poor mineplanningresultingin increased operational costs B
Processplant
Slime’s removal – handlingand disposal C
Spiralperformance/recoveries C
Equipment configuration C
Overallplantperformance/recoveries C
Water management C
Industrial Relations
Union industrial action at theport delays equipment imports duringthe constructionphases B
Union industrial action at theport restrictsproduct deliverytoport and/or export B
Marketing
Product market and offtake availability B
Force Majeure
Pandemic (COVID 19) continued outbreaks – preventing receipt of interstate or international
based equipment and commissioningcrews
A

8.9.2 Discussion of key risks

Project development is following JORC (2012) guidelines ensuring in-situ resource is well understood.

Multiple levels of metallurgical testing and hence confidence supports spiral performance/ recoveries.

Well understood process from multiple phases of testwork with considerable flexibility in equipment configuration. Equipment selection in relation to product stacking and rejects disposal is being incorporated into the design thereby minimising water consumption and make-up water volume requirements.

Material is less than 2% silt/slimes with excellent settling rates demonstrated during testwork.

Suitably qualified mine planner or contract miner to be engaged during operations to ensure compliance and efficiency of mining.

8.9.3 Scope of further investigation

Further optimise circuit flowsheet during further DFS testwork.

Identify, develop and sign-up long term reputable offtake customers during DFS.

Optimise selected mine methodology during DFS.

8.10

SUMMARY OF OUTCOMES

The assessment uncovered a number of issues that require further investigation in the shorter term. There were no Category F risks identified, and Category A risks are shown Table 8.12.

Table 8.12 Summary – key project risks

Risk Category/risk level
Surface groundwater and hydrogeology
Drawdown of the local aquifer results in impact to groundwater-dependent ecosystems
(vegetation). Cumulative impact with Tronox Dongara project exacerbates impacts resulting in
challengingenvironmental approvals.
A
Terrestrial ecology

108

BEHARRA SILICA PROJECT PRE-FEASIBILITY STUDY

==> picture [85 x 27] intentionally omitted <==

Direct loss of the foraging habitat for Carnaby’s Black-Cockatoo a Federally listed threatened
(Endangered)bird species.
A
Lack of available suitable Carnaby Black-Cockatoo foraging habitat in the local region to
offset direct impact from vegetation clearing at a 3:1 ratio. Restricts area of mine disturbance
and therefore mine life.
A
Direct loss of restricted wetland vegetation communities and Kwongan sandplains flora species
diversity
A
Poor standard of rehabilitation resulting in low recruitment and return of Carnaby’s Cockatoo
foraginghabitat in the local area.
A
Poor standard of rehabilitation resulting in low recruitment and return of flora species diversity
similar to those found in restricted wetland vegetation communities and Kwongan sandplains.
A
Force Majeure
Pandemic (COVID-19) continued outbreaks – preventing receipt of interstate or international
based equipment and commissioningcrews.
A

As a further note, the risks identified and rated during this assessment were addressed in isolation only. Snowden has also included Force Majeure as a potential risk which is difficult to quantify, but for the purposes of this study rated as a Category A.

8.11

RECOMMENDED ACTIONS

Additional activities during the definitive study phase of the Project which would result in a higher level of risk definition and the capacity/cost to address these include:

  • Further stakeholder engagement with government departments, community and Southern Yamatji representatives

  • Further process definition to confirm flowsheet and water balance

  • Determine availability of suitable Carnaby’s Black Cockatoo habitat in the region for environmental offset opportunities

  • Desktop flora and vegetation review of Tronox survey data to update classifications and ensure consistent with current survey guidance requirements

  • Confirm water bore extraction location for construction/operational purposes, model drawdown and undertake cumulative impact assessment with Tronox data on potential impacts to groundwaterdependant ecosystems.

8.12 RISK MANAGEMENT PLAN

A risk management plan and risk register will be developed and maintained as part of the DFS works.

109

BEHARRA SILICA PROJECT PRE-FEASIBILITY STUDY

==> picture [85 x 27] intentionally omitted <==

9. PROJECT MANAGEMENT ASPECTS

9.1 PROJECT MANAGEMENT

9.1.1 Objectives

The Project objective is to provide the most cost effective and timely establishment of operations and to ensure the ramp-up to full production is achieved with no lost-time injuries (LTIs) and in an efficient and productive timeframe.

9.1.2

Execution methodology

Upon completion of this PFS, and audit of results, the Project may enter a DFS for further project review and optimisation. The aim of this phase is to address all items raised during the PFS as requiring further works or investigation.

Upon completion of a DFS, a final investment decision will be made and if successful, the Project will be in a position to move into the execution phase, subject to statutory mining and funding approvals.

To expedite the project, prior to receiving Mining Approval, Perpetual may enter into Early Contractor Involvement for the design of a packaged Process Plant and site power supply options.

Once mining and funding approvals have been received, the Project will then progress through the following stages:

  • Award of packaged plant supply and power supply contract(s)

  • Tender and award of offsite infrastructure supply and installation contract(s) (roads)

  • Tender and award of on-site civil, concrete, mechanical and electrical construction and installation contract(s)

  • Tender and award on-site service contracts (e.g. fuel, waste management)

  • Construction

  • Commissioning and handover.

The general execution methodology for the Project will be presented in a series of execution plans outlined below:

  • Project Execution Plan

  • Project Management Plan

  • Health and Safety Plan (including Health and Hygiene Management Plan)

  • Environmental Management Plan

  • Quality Management Plan

  • Risk Management Plan

  • HR/IR Plan

  • Contract Management and Procurement Plan

  • Construction Management Plan

  • Operations Management Plan.

These plans will be developed to varying levels of completion during the DFS.

9.1.3

Cost management

The Project estimate produced in the DFS will be used to develop a project budget based against the work breakdown structure which will then be adopted for project cost control purposes.

9.1.4 Quality assurance

A project Quality Management Plan will be developed prior to project execution to ensure best practice during project implementation.

110

BEHARRA SILICA PROJECT PRE-FEASIBILITY STUDY

==> picture [85 x 27] intentionally omitted <==

9.1.5 Risk management

A preliminary risk assessment was carried out to identify and categorise key planning and operational risks to the Beharra Project. Refer to Section 8 for further detail. The preliminary risk assessment will form the basis of a project risk register, which will be further developed during the DFS.

9.1.6 Change management

A change management system will be developed and implemented prior to the execution phase of the Project. The change management process will apply to all variations, including project scope, budget, and schedule.

9.1.7 Reporting and coordination

Prior to, and during project execution, formal communication, and reporting requirements with respect to cost, time, regulatory compliance, safety performance and any other issues will be established for all stakeholders.

9.2 PROJECT EXECUTION

9.2.1 Work breakdown structure

A high-level Work Breakdown Structure (WBS) has been developed based on the PFS project scope. The WBS is attached at Appendix 10.

Primary areas are as follows:

  • Mining

  • Wet processing plant

  • Onsite infrastructure

  • Offsite infrastructure

  • Commissioning

  • PCM

  • Indirects and owner’s costs.

9.2.2

Project organisation

The Project will be developed using an Owner’s Team execution model, which is considered appropriate given the size of the Project.

An Owners Team–PCM execution model will be adopted for the Beharra Project through to commissioning. This model is clarified below.

The owner’s team will consist of a Project Manager, Procurement/Contracts management/administration team, Construction Manager and HSE Officer.

A variety of packages of work will be awarded to suppliers, such as the process plant, power supply, earthworks with contracts managed directly by the owner’s team “ P ”.

The owners team Construction Manager will manage, supervise and coordinate all suppliers and contractors on site during the construction phase “ CM ”.

The CAPEX has been generated using this model.

BEHARRA SILICA PROJECT PRE-FEASIBILITY STUDY

111

==> picture [85 x 27] intentionally omitted <==

==> picture [375 x 120] intentionally omitted <==

9.2.3 Contracting strategies

The project execution and operational models will require a variety of major and minor contracts to be awarded to suppliers. A Contractor Management Plan will be developed during the DFS to define the policies, procedures, and management systems to be used in administration of supply, construction, and service contracts during the execution and operational phases of the Project.

9.2.4 Engineering

Process flow, process plant scope of works and technical specifications, site layout and infrastructure requirements will be developed to near completion, during the DFS.

On completion of the DFS, majority of the engineering works for the Beharra Project will be carried out by the successful process plant supply and install contractor.

Internal Perpetual engineering requirements, will be minimal and consist of finalising process plant scope of works documents, then updating site layouts, infrastructure scope of work documents post process plant signoff. These works will be subcontracted to an engineering house.

9.2.5 Construction

Perpetual’s construction manager will superintend all facets of the site works and road upgrade programs. Prior to commencement of site works, a Project Management Plan, including safety management must be developed and approved by DMIRS.

In addition to the above, a construction management plan will be developed during the DFS detailing methodology and providing a timeline for all phases of the proposed site works.

9.2.6

Commissioning

Key infrastructure, which includes power supply, water supply, diesel storage will be commissioned by the respective vendors prior to process plant commissioning.

Process plant commissioning on water will be conducted by the supply and install contractor, with Perpetual operations staff on site to commence training.

9.2.7

Commissioning handover

When commissioning on water activities is successfully complete and operators are trained to operate the systems and equipment, performance acceptance testing will be conducted.

Performance testing of the plant will be carried out on ore over a period of two to four weeks. In addition to the contractor, Perpetual’s project manager, qualified consulting metallurgist and engineer will be overseeing the performance testing. As part of the handover, the contractor shall provide operating and maintenance manuals, and all other project related documentation to Perpetual.

When performance testing and document delivery is successfully completed, Perpetual will accept handover of the process plant from contractor.

112

BEHARRA SILICA PROJECT PRE-FEASIBILITY STUDY

==> picture [85 x 27] intentionally omitted <==

10. FINANCIAL ANALYSIS

10.1 CONTEXT

10.1.1 Assumptions

The base Beharra financial model has been prepared by Perpetual with input from Mining Insights Pty Ltd (MI), who has extensive experience in the analysis and evaluation of potential mining projects across multiple commodity sectors. Perpetual and MI have applied the LOM plan and associated physical schedule against appropriate and verified cost inputs. Perpetual has then used this model as a basis to apply a range of assumptions and variables, such as exchange rate, commodity price, equity discount rate, gearing proportion, gearing costs and other financial metrics, to derive outputs such as EBITDA (earnings before interest, taxes, depreciation, and amortisation), operating costs and other important financial outcomes, with the end result being an assessment of project value using NPV and IRR calculations.

Where possible, the Beharra financial model has relied on a first principles assessment of the various inputs into the financial model, with key workstreams tendered to professionals in their respective fields, with the resulting inputs used as the basis for many of the inputs in the financial model.

While primary proposals from potential service providers have been relied upon for many of the key financial model inputs, there remains several key assumptions that Perpetual has made in the financial model, which will be further interrogated and explored as the project progresses through to DFS.

These key assumptions in the financial model are supplied in Table 10.1 below, along with the resultant key financial model outputs shown later in Table 10.2.

Table 10.1 Key financial model inputs

Key financial model input Units Assumed value Notes
Silica Sand Sales Price US$/t $50/t A nominal sales price of US$50/t FOB has been used
throughout the forecast period. Perpetual considers this a
conservative estimate of the likely sales price and is based
on feedback from a range of specialised silica sand market
intermediaries, industry forecasters, as well as direct
discussions with end users.
Exchange rate US$ 0.75 See Section 10.2.3 below.
Equity discount rate % 10% An equity discount rate of 10% has been used, which is
consistent with the discount rate used by mining
development project peers with projects at a similar stage
of evaluation and development.
Debt borrowing rate % 7.5% Where a gearing assumption has been made, a debt
borrowing rate of 7.5% has been used, which is consistent
with the debt borrowing rate achieved by mining
development project peers with projects at a similar stage
of evaluation and development
Debt payback period years 10 Where a gearing assumption has been made, a debt
payback period of 10 years has been used, which is
consistent with typical debt payback periods achieved by
mining development project peers with projects at a similar
stage of evaluation and development.
Gearing ratio % 40% Where a gearing assumption has been made, a gearing
ratio of 40% has been used, which is considered an
acceptable gearing ratio for a project that exhibits
relatively low capital costs, high margins, and quick debt
payback, which are all attributes exhibited by the Beharra
Project.
Inflation rate % 2.5% An inflation rate of 2.5% has been applied to both revenue
and costs, throughout the forecast period, which is
considered a reasonable longterm inflation rate.
Mine life years 32 The financial model assumes a 32-year mine life, which is
considered a reasonable assumption as it represents a
subset of the reserve calculation that was prepared by
industry specialists, Snowden.
Table 10.2
Key financial model outputs
Project economics at assumedproduction scenario Unit Base case

113

BEHARRA SILICA PROJECT PRE-FEASIBILITY STUDY

==> picture [85 x 27] intentionally omitted <==

Total silica sandproduced Mt 47.6
Annualproduction target Mt 1.51
Probable Ore [email protected]% SiO2 Mt 64.1
Ore Reserve life years 32
JORC Mineral Resources Mt 139
Total LOM revenue A$ M 3,176
Total LOM capital expenditure A$ M 76.9
Total LOM EBITDA A$ M 1,714
Total LOM mine free cash flow A$ M 1,131
Post-tax DCF(NPV10)– ungeared A$ M 231
Post-tax IRR – ungeared % 55
Post-tax DCF(NPV10)–geared A$ M 236
Post-tax IRR –geared % 77
Paybackperiod years 2
FOB costs A$/t 43.07

Perpetual completed the PFS under a base scenario where production is assumed to be from a single plant that is funded and constructed in year 1 of operations and then fully ramped up during that same year and then operated for a 32-year mine life.

The Beharra Project is forecasted to be strongly cash flow positive, with post-tax capital payback estimated to be achieved in around two years from first production. The strong cash flow profile of the Beharra Project can be seen in Figure 10.1. The cash flow profile shown in Figure 10.1 delivers a predicted post-tax ungeared IRR of 54.6%.

The return profiles are considered highly attractive and are expected to be of interest to a range of debt and equity investors when potential funding is sought.

==> picture [459 x 177] intentionally omitted <==

Figure 10.1 Beharra cumulative undiscounted and ungeared after-tax cash flow chart

As shown in the preceding charts, the Beharra Project is forecast to generate very strong annual free cash flow, which position the Project to deliver rapid payback on capital investment (around two years) and very strong post-tax ungeared IRRs. Figure 10.2 below is a graphical representation of the discounted cash flow profile of the Beharra Project.

BEHARRA SILICA PROJECT PRE-FEASIBILITY STUDY

114

==> picture [85 x 27] intentionally omitted <==

==> picture [459 x 162] intentionally omitted <==

Figure 10.2 Discounted after-tax ungeared cash flow and NPV

10.1.2 Taxation profile

As Perpetual is an Australian public company, with all operations in Australia, it has been assumed that corporate tax applies to all relevant project profits, at the rate of 30%, which is the statutory company tax rate in Australia. Where available, typical tax deductions (such as depreciation and financing costs, among others) have been modelled, in line with relevant tax laws in Australia.

The Beharra financial model does not take into account any accumulated tax losses held by the parent entity, Perpetual Resources Limited, as the applicability of these to the project have not yet been determined. As a result, the Beharra Project is assumed to be tax paying from year 2 of operations.

10.2 CAPITAL EXPENDITURE ESTIMATE

10.2.1 Accuracy and scope of estimate

The CAPEX was produced by Perpetual with input from major equipment, infrastructure and service suppliers. The estimate includes all process plant, onsite/offsite infrastructure and indirect costs associated with installation of a 250 tph processing plant on the Beharra project site.

Enough process information, engineering design and supplier pricing is available to support an estimate at ±25% accuracy, suitable for PFS level.

A summary of the estimate is shown at Figure 10.3.

BEHARRA SILICA PROJECT PRE-FEASIBILITY STUDY

115

==> picture [26 x 84] intentionally omitted <==

Figure 10.3
Summary of capital estimate
Area
Area Description
Sub Areas
Details
Unit
Cost $
Extended Cost $
Unit
Cost
Factor
Extended Cost $
Fabrication
Detailing
Freight
LINE TOTAL $
1.0
Mining
11,575
2.0
Wet Processing Plant
19,086,457
85,999
11,728
3.0
On-Site Infrastructure
3,291,780
177,069
67,879
4.0
Off-Site Infrastructure
9,242,550
24,431
5,553
5.0
Commissioning
91,050
T1
Total Direct Material and Labour
T1 (M)
31,723,412
T1 (L)
287,498
32,010,910
T2
Total Freight
85,159
85,159
T3
Total Fabrication Detailing
All fabrication detailing included in Package Plant
T4
SUB-TOTAL DIRECT FIELD COSTS ( = T1 (M&L)
32,096,069
T5
Labour indirects (% OF T1 (J))
15.0%
43,125
T6
PCM Fees (% of (T4+T5))
7.0%
2,249,744
T7
PCM Home and Site Office Expenses (% of T6)
2.0%
44,995
T8
SUB-TOTAL INDIRECT COSTS (= T5 + T6 +T7)
2,337,863
T9
PROJECT SUB TOTAL (DIRECT+INDIRECT COSTS = T4 + T8)
34,433,932
T10 Project Insurances (% of T9)
0.4%
Indicative only
137,736
T11 Commissioning Spares (% of T9)
Included in Area 2.0
T12 Year 1 Operational Spares (% of T9)
1.5%
Indicative only
516,509
T13 Owners costs (% of T9)
2.0%
(Staff, travel, accomm, Shire and Development fees
etc.)
688,679
T14 Project Contingency (% of T9)
10.0%
Covers unforeseen items; bad weather, bad soil
conditions, labour disputes, minor oversights etc.
3,443,393
T15 TOTAL = SUM T9-T14 (Excluding Escalation)
T15 is accurate to PFS level (+/- 25%%)
$39,220,249
This Estimate is exclusive of GST, Taxes, Duties and Interest during construction.

This area left blank.
Figure 10.3
Summary of capital estimate
Area
Area Description
Sub Areas
Details
Unit
Cost $
Extended Cost $
Unit
Cost
Factor
Extended Cost $
Fabrication
Detailing
Freight
LINE TOTAL $
1.0
Mining
11,575
2.0
Wet Processing Plant
19,086,457
85,999
11,728
3.0
On-Site Infrastructure
3,291,780
177,069
67,879
4.0
Off-Site Infrastructure
9,242,550
24,431
5,553
5.0
Commissioning
91,050
T1
Total Direct Material and Labour
T1 (M)
31,723,412
T1 (L)
287,498
32,010,910
T2
Total Freight
85,159
85,159
T3
Total Fabrication Detailing
All fabrication detailing included in Package Plant
T4
SUB-TOTAL DIRECT FIELD COSTS ( = T1 (M&L)
32,096,069
T5
Labour indirects (% OF T1 (J))
15.0%
43,125
T6
PCM Fees (% of (T4+T5))
7.0%
2,249,744
T7
PCM Home and Site Office Expenses (% of T6)
2.0%
44,995
T8
SUB-TOTAL INDIRECT COSTS (= T5 + T6 +T7)
2,337,863
T9
PROJECT SUB TOTAL (DIRECT+INDIRECT COSTS = T4 + T8)
34,433,932
T10 Project Insurances (% of T9)
0.4%
Indicative only
137,736
T11 Commissioning Spares (% of T9)
Included in Area 2.0
T12 Year 1 Operational Spares (% of T9)
1.5%
Indicative only
516,509
T13 Owners costs (% of T9)
2.0%
(Staff, travel, accomm, Shire and Development fees
etc.)
688,679
T14 Project Contingency (% of T9)
10.0%
Covers unforeseen items; bad weather, bad soil
conditions, labour disputes, minor oversights etc.
3,443,393
T15 TOTAL = SUM T9-T14 (Excluding Escalation)
T15 is accurate to PFS level (+/- 25%%)
$39,220,249
This Estimate is exclusive of GST, Taxes, Duties and Interest during construction.

This area left blank.
Figure 10.3
Summary of capital estimate
Area
Area Description
Sub Areas
Details
Unit
Cost $
Extended Cost $
Unit
Cost
Factor
Extended Cost $
Fabrication
Detailing
Freight
LINE TOTAL $
1.0
Mining
11,575
2.0
Wet Processing Plant
19,086,457
85,999
11,728
3.0
On-Site Infrastructure
3,291,780
177,069
67,879
4.0
Off-Site Infrastructure
9,242,550
24,431
5,553
5.0
Commissioning
91,050
T1
Total Direct Material and Labour
T1 (M)
31,723,412
T1 (L)
287,498
32,010,910
T2
Total Freight
85,159
85,159
T3
Total Fabrication Detailing
All fabrication detailing included in Package Plant
T4
SUB-TOTAL DIRECT FIELD COSTS ( = T1 (M&L)
32,096,069
T5
Labour indirects (% OF T1 (J))
15.0%
43,125
T6
PCM Fees (% of (T4+T5))
7.0%
2,249,744
T7
PCM Home and Site Office Expenses (% of T6)
2.0%
44,995
T8
SUB-TOTAL INDIRECT COSTS (= T5 + T6 +T7)
2,337,863
T9
PROJECT SUB TOTAL (DIRECT+INDIRECT COSTS = T4 + T8)
34,433,932
T10 Project Insurances (% of T9)
0.4%
Indicative only
137,736
T11 Commissioning Spares (% of T9)
Included in Area 2.0
T12 Year 1 Operational Spares (% of T9)
1.5%
Indicative only
516,509
T13 Owners costs (% of T9)
2.0%
(Staff, travel, accomm, Shire and Development fees
etc.)
688,679
T14 Project Contingency (% of T9)
10.0%
Covers unforeseen items; bad weather, bad soil
conditions, labour disputes, minor oversights etc.
3,443,393
T15 TOTAL = SUM T9-T14 (Excluding Escalation)
T15 is accurate to PFS level (+/- 25%%)
$39,220,249
This Estimate is exclusive of GST, Taxes, Duties and Interest during construction.

This area left blank.
Figure 10.3
Summary of capital estimate
Area
Area Description
Sub Areas
Details
Unit
Cost $
Extended Cost $
Unit
Cost
Factor
Extended Cost $
Fabrication
Detailing
Freight
LINE TOTAL $
1.0
Mining
11,575
2.0
Wet Processing Plant
19,086,457
85,999
11,728
3.0
On-Site Infrastructure
3,291,780
177,069
67,879
4.0
Off-Site Infrastructure
9,242,550
24,431
5,553
5.0
Commissioning
91,050
T1
Total Direct Material and Labour
T1 (M)
31,723,412
T1 (L)
287,498
32,010,910
T2
Total Freight
85,159
85,159
T3
Total Fabrication Detailing
All fabrication detailing included in Package Plant
T4
SUB-TOTAL DIRECT FIELD COSTS ( = T1 (M&L)
32,096,069
T5
Labour indirects (% OF T1 (J))
15.0%
43,125
T6
PCM Fees (% of (T4+T5))
7.0%
2,249,744
T7
PCM Home and Site Office Expenses (% of T6)
2.0%
44,995
T8
SUB-TOTAL INDIRECT COSTS (= T5 + T6 +T7)
2,337,863
T9
PROJECT SUB TOTAL (DIRECT+INDIRECT COSTS = T4 + T8)
34,433,932
T10 Project Insurances (% of T9)
0.4%
Indicative only
137,736
T11 Commissioning Spares (% of T9)
Included in Area 2.0
T12 Year 1 Operational Spares (% of T9)
1.5%
Indicative only
516,509
T13 Owners costs (% of T9)
2.0%
(Staff, travel, accomm, Shire and Development fees
etc.)
688,679
T14 Project Contingency (% of T9)
10.0%
Covers unforeseen items; bad weather, bad soil
conditions, labour disputes, minor oversights etc.
3,443,393
T15 TOTAL = SUM T9-T14 (Excluding Escalation)
T15 is accurate to PFS level (+/- 25%%)
$39,220,249
This Estimate is exclusive of GST, Taxes, Duties and Interest during construction.

This area left blank.
Figure 10.3
Summary of capital estimate
Area
Area Description
Sub Areas
Details
Unit
Cost $
Extended Cost $
Unit
Cost
Factor
Extended Cost $
Fabrication
Detailing
Freight
LINE TOTAL $
1.0
Mining
11,575
2.0
Wet Processing Plant
19,086,457
85,999
11,728
3.0
On-Site Infrastructure
3,291,780
177,069
67,879
4.0
Off-Site Infrastructure
9,242,550
24,431
5,553
5.0
Commissioning
91,050
T1
Total Direct Material and Labour
T1 (M)
31,723,412
T1 (L)
287,498
32,010,910
T2
Total Freight
85,159
85,159
T3
Total Fabrication Detailing
All fabrication detailing included in Package Plant
T4
SUB-TOTAL DIRECT FIELD COSTS ( = T1 (M&L)
32,096,069
T5
Labour indirects (% OF T1 (J))
15.0%
43,125
T6
PCM Fees (% of (T4+T5))
7.0%
2,249,744
T7
PCM Home and Site Office Expenses (% of T6)
2.0%
44,995
T8
SUB-TOTAL INDIRECT COSTS (= T5 + T6 +T7)
2,337,863
T9
PROJECT SUB TOTAL (DIRECT+INDIRECT COSTS = T4 + T8)
34,433,932
T10 Project Insurances (% of T9)
0.4%
Indicative only
137,736
T11 Commissioning Spares (% of T9)
Included in Area 2.0
T12 Year 1 Operational Spares (% of T9)
1.5%
Indicative only
516,509
T13 Owners costs (% of T9)
2.0%
(Staff, travel, accomm, Shire and Development fees
etc.)
688,679
T14 Project Contingency (% of T9)
10.0%
Covers unforeseen items; bad weather, bad soil
conditions, labour disputes, minor oversights etc.
3,443,393
T15 TOTAL = SUM T9-T14 (Excluding Escalation)
T15 is accurate to PFS level (+/- 25%%)
$39,220,249
This Estimate is exclusive of GST, Taxes, Duties and Interest during construction.

This area left blank.
Figure 10.3
Summary of capital estimate
Area
Area Description
Sub Areas
Details
Unit
Cost $
Extended Cost $
Unit
Cost
Factor
Extended Cost $
Fabrication
Detailing
Freight
LINE TOTAL $
1.0
Mining
11,575
2.0
Wet Processing Plant
19,086,457
85,999
11,728
3.0
On-Site Infrastructure
3,291,780
177,069
67,879
4.0
Off-Site Infrastructure
9,242,550
24,431
5,553
5.0
Commissioning
91,050
T1
Total Direct Material and Labour
T1 (M)
31,723,412
T1 (L)
287,498
32,010,910
T2
Total Freight
85,159
85,159
T3
Total Fabrication Detailing
All fabrication detailing included in Package Plant
T4
SUB-TOTAL DIRECT FIELD COSTS ( = T1 (M&L)
32,096,069
T5
Labour indirects (% OF T1 (J))
15.0%
43,125
T6
PCM Fees (% of (T4+T5))
7.0%
2,249,744
T7
PCM Home and Site Office Expenses (% of T6)
2.0%
44,995
T8
SUB-TOTAL INDIRECT COSTS (= T5 + T6 +T7)
2,337,863
T9
PROJECT SUB TOTAL (DIRECT+INDIRECT COSTS = T4 + T8)
34,433,932
T10 Project Insurances (% of T9)
0.4%
Indicative only
137,736
T11 Commissioning Spares (% of T9)
Included in Area 2.0
T12 Year 1 Operational Spares (% of T9)
1.5%
Indicative only
516,509
T13 Owners costs (% of T9)
2.0%
(Staff, travel, accomm, Shire and Development fees
etc.)
688,679
T14 Project Contingency (% of T9)
10.0%
Covers unforeseen items; bad weather, bad soil
conditions, labour disputes, minor oversights etc.
3,443,393
T15 TOTAL = SUM T9-T14 (Excluding Escalation)
T15 is accurate to PFS level (+/- 25%%)
$39,220,249
This Estimate is exclusive of GST, Taxes, Duties and Interest during construction.

This area left blank.
Figure 10.3
Summary of capital estimate
Area
Area Description
Sub Areas
Details
Unit
Cost $
Extended Cost $
Unit
Cost
Factor
Extended Cost $
Fabrication
Detailing
Freight
LINE TOTAL $
1.0
Mining
11,575
2.0
Wet Processing Plant
19,086,457
85,999
11,728
3.0
On-Site Infrastructure
3,291,780
177,069
67,879
4.0
Off-Site Infrastructure
9,242,550
24,431
5,553
5.0
Commissioning
91,050
T1
Total Direct Material and Labour
T1 (M)
31,723,412
T1 (L)
287,498
32,010,910
T2
Total Freight
85,159
85,159
T3
Total Fabrication Detailing
All fabrication detailing included in Package Plant
T4
SUB-TOTAL DIRECT FIELD COSTS ( = T1 (M&L)
32,096,069
T5
Labour indirects (% OF T1 (J))
15.0%
43,125
T6
PCM Fees (% of (T4+T5))
7.0%
2,249,744
T7
PCM Home and Site Office Expenses (% of T6)
2.0%
44,995
T8
SUB-TOTAL INDIRECT COSTS (= T5 + T6 +T7)
2,337,863
T9
PROJECT SUB TOTAL (DIRECT+INDIRECT COSTS = T4 + T8)
34,433,932
T10 Project Insurances (% of T9)
0.4%
Indicative only
137,736
T11 Commissioning Spares (% of T9)
Included in Area 2.0
T12 Year 1 Operational Spares (% of T9)
1.5%
Indicative only
516,509
T13 Owners costs (% of T9)
2.0%
(Staff, travel, accomm, Shire and Development fees
etc.)
688,679
T14 Project Contingency (% of T9)
10.0%
Covers unforeseen items; bad weather, bad soil
conditions, labour disputes, minor oversights etc.
3,443,393
T15 TOTAL = SUM T9-T14 (Excluding Escalation)
T15 is accurate to PFS level (+/- 25%%)
$39,220,249
This Estimate is exclusive of GST, Taxes, Duties and Interest during construction.

This area left blank.
Figure 10.3
Summary of capital estimate
Area
Area Description
Sub Areas
Details
Unit
Cost $
Extended Cost $
Unit
Cost
Factor
Extended Cost $
Fabrication
Detailing
Freight
LINE TOTAL $
1.0
Mining
11,575
2.0
Wet Processing Plant
19,086,457
85,999
11,728
3.0
On-Site Infrastructure
3,291,780
177,069
67,879
4.0
Off-Site Infrastructure
9,242,550
24,431
5,553
5.0
Commissioning
91,050
T1
Total Direct Material and Labour
T1 (M)
31,723,412
T1 (L)
287,498
32,010,910
T2
Total Freight
85,159
85,159
T3
Total Fabrication Detailing
All fabrication detailing included in Package Plant
T4
SUB-TOTAL DIRECT FIELD COSTS ( = T1 (M&L)
32,096,069
T5
Labour indirects (% OF T1 (J))
15.0%
43,125
T6
PCM Fees (% of (T4+T5))
7.0%
2,249,744
T7
PCM Home and Site Office Expenses (% of T6)
2.0%
44,995
T8
SUB-TOTAL INDIRECT COSTS (= T5 + T6 +T7)
2,337,863
T9
PROJECT SUB TOTAL (DIRECT+INDIRECT COSTS = T4 + T8)
34,433,932
T10 Project Insurances (% of T9)
0.4%
Indicative only
137,736
T11 Commissioning Spares (% of T9)
Included in Area 2.0
T12 Year 1 Operational Spares (% of T9)
1.5%
Indicative only
516,509
T13 Owners costs (% of T9)
2.0%
(Staff, travel, accomm, Shire and Development fees
etc.)
688,679
T14 Project Contingency (% of T9)
10.0%
Covers unforeseen items; bad weather, bad soil
conditions, labour disputes, minor oversights etc.
3,443,393
T15 TOTAL = SUM T9-T14 (Excluding Escalation)
T15 is accurate to PFS level (+/- 25%%)
$39,220,249
This Estimate is exclusive of GST, Taxes, Duties and Interest during construction.

This area left blank.
Figure 10.3
Summary of capital estimate
Area
Area Description
Sub Areas
Details
Unit
Cost $
Extended Cost $
Unit
Cost
Factor
Extended Cost $
Fabrication
Detailing
Freight
LINE TOTAL $
1.0
Mining
11,575
2.0
Wet Processing Plant
19,086,457
85,999
11,728
3.0
On-Site Infrastructure
3,291,780
177,069
67,879
4.0
Off-Site Infrastructure
9,242,550
24,431
5,553
5.0
Commissioning
91,050
T1
Total Direct Material and Labour
T1 (M)
31,723,412
T1 (L)
287,498
32,010,910
T2
Total Freight
85,159
85,159
T3
Total Fabrication Detailing
All fabrication detailing included in Package Plant
T4
SUB-TOTAL DIRECT FIELD COSTS ( = T1 (M&L)
32,096,069
T5
Labour indirects (% OF T1 (J))
15.0%
43,125
T6
PCM Fees (% of (T4+T5))
7.0%
2,249,744
T7
PCM Home and Site Office Expenses (% of T6)
2.0%
44,995
T8
SUB-TOTAL INDIRECT COSTS (= T5 + T6 +T7)
2,337,863
T9
PROJECT SUB TOTAL (DIRECT+INDIRECT COSTS = T4 + T8)
34,433,932
T10 Project Insurances (% of T9)
0.4%
Indicative only
137,736
T11 Commissioning Spares (% of T9)
Included in Area 2.0
T12 Year 1 Operational Spares (% of T9)
1.5%
Indicative only
516,509
T13 Owners costs (% of T9)
2.0%
(Staff, travel, accomm, Shire and Development fees
etc.)
688,679
T14 Project Contingency (% of T9)
10.0%
Covers unforeseen items; bad weather, bad soil
conditions, labour disputes, minor oversights etc.
3,443,393
T15 TOTAL = SUM T9-T14 (Excluding Escalation)
T15 is accurate to PFS level (+/- 25%%)
$39,220,249
This Estimate is exclusive of GST, Taxes, Duties and Interest during construction.

This area left blank.
Figure 10.3
Summary of capital estimate
Area
Area Description
Sub Areas
Details
Unit
Cost $
Extended Cost $
Unit
Cost
Factor
Extended Cost $
Fabrication
Detailing
Freight
LINE TOTAL $
1.0
Mining
11,575
2.0
Wet Processing Plant
19,086,457
85,999
11,728
3.0
On-Site Infrastructure
3,291,780
177,069
67,879
4.0
Off-Site Infrastructure
9,242,550
24,431
5,553
5.0
Commissioning
91,050
T1
Total Direct Material and Labour
T1 (M)
31,723,412
T1 (L)
287,498
32,010,910
T2
Total Freight
85,159
85,159
T3
Total Fabrication Detailing
All fabrication detailing included in Package Plant
T4
SUB-TOTAL DIRECT FIELD COSTS ( = T1 (M&L)
32,096,069
T5
Labour indirects (% OF T1 (J))
15.0%
43,125
T6
PCM Fees (% of (T4+T5))
7.0%
2,249,744
T7
PCM Home and Site Office Expenses (% of T6)
2.0%
44,995
T8
SUB-TOTAL INDIRECT COSTS (= T5 + T6 +T7)
2,337,863
T9
PROJECT SUB TOTAL (DIRECT+INDIRECT COSTS = T4 + T8)
34,433,932
T10 Project Insurances (% of T9)
0.4%
Indicative only
137,736
T11 Commissioning Spares (% of T9)
Included in Area 2.0
T12 Year 1 Operational Spares (% of T9)
1.5%
Indicative only
516,509
T13 Owners costs (% of T9)
2.0%
(Staff, travel, accomm, Shire and Development fees
etc.)
688,679
T14 Project Contingency (% of T9)
10.0%
Covers unforeseen items; bad weather, bad soil
conditions, labour disputes, minor oversights etc.
3,443,393
T15 TOTAL = SUM T9-T14 (Excluding Escalation)
T15 is accurate to PFS level (+/- 25%%)
$39,220,249
This Estimate is exclusive of GST, Taxes, Duties and Interest during construction.

This area left blank.
Figure 10.3
Summary of capital estimate
Area
Area Description
Sub Areas
Details
Unit
Cost $
Extended Cost $
Unit
Cost
Factor
Extended Cost $
Fabrication
Detailing
Freight
LINE TOTAL $
1.0
Mining
11,575
2.0
Wet Processing Plant
19,086,457
85,999
11,728
3.0
On-Site Infrastructure
3,291,780
177,069
67,879
4.0
Off-Site Infrastructure
9,242,550
24,431
5,553
5.0
Commissioning
91,050
T1
Total Direct Material and Labour
T1 (M)
31,723,412
T1 (L)
287,498
32,010,910
T2
Total Freight
85,159
85,159
T3
Total Fabrication Detailing
All fabrication detailing included in Package Plant
T4
SUB-TOTAL DIRECT FIELD COSTS ( = T1 (M&L)
32,096,069
T5
Labour indirects (% OF T1 (J))
15.0%
43,125
T6
PCM Fees (% of (T4+T5))
7.0%
2,249,744
T7
PCM Home and Site Office Expenses (% of T6)
2.0%
44,995
T8
SUB-TOTAL INDIRECT COSTS (= T5 + T6 +T7)
2,337,863
T9
PROJECT SUB TOTAL (DIRECT+INDIRECT COSTS = T4 + T8)
34,433,932
T10 Project Insurances (% of T9)
0.4%
Indicative only
137,736
T11 Commissioning Spares (% of T9)
Included in Area 2.0
T12 Year 1 Operational Spares (% of T9)
1.5%
Indicative only
516,509
T13 Owners costs (% of T9)
2.0%
(Staff, travel, accomm, Shire and Development fees
etc.)
688,679
T14 Project Contingency (% of T9)
10.0%
Covers unforeseen items; bad weather, bad soil
conditions, labour disputes, minor oversights etc.
3,443,393
T15 TOTAL = SUM T9-T14 (Excluding Escalation)
T15 is accurate to PFS level (+/- 25%%)
$39,220,249
This Estimate is exclusive of GST, Taxes, Duties and Interest during construction.

This area left blank.
Figure 10.3
Summary of capital estimate
Area
Area Description
Sub Areas
Details
Unit
Cost $
Extended Cost $
Unit
Cost
Factor
Extended Cost $
Fabrication
Detailing
Freight
LINE TOTAL $
1.0
Mining
11,575
2.0
Wet Processing Plant
19,086,457
85,999
11,728
3.0
On-Site Infrastructure
3,291,780
177,069
67,879
4.0
Off-Site Infrastructure
9,242,550
24,431
5,553
5.0
Commissioning
91,050
T1
Total Direct Material and Labour
T1 (M)
31,723,412
T1 (L)
287,498
32,010,910
T2
Total Freight
85,159
85,159
T3
Total Fabrication Detailing
All fabrication detailing included in Package Plant
T4
SUB-TOTAL DIRECT FIELD COSTS ( = T1 (M&L)
32,096,069
T5
Labour indirects (% OF T1 (J))
15.0%
43,125
T6
PCM Fees (% of (T4+T5))
7.0%
2,249,744
T7
PCM Home and Site Office Expenses (% of T6)
2.0%
44,995
T8
SUB-TOTAL INDIRECT COSTS (= T5 + T6 +T7)
2,337,863
T9
PROJECT SUB TOTAL (DIRECT+INDIRECT COSTS = T4 + T8)
34,433,932
T10 Project Insurances (% of T9)
0.4%
Indicative only
137,736
T11 Commissioning Spares (% of T9)
Included in Area 2.0
T12 Year 1 Operational Spares (% of T9)
1.5%
Indicative only
516,509
T13 Owners costs (% of T9)
2.0%
(Staff, travel, accomm, Shire and Development fees
etc.)
688,679
T14 Project Contingency (% of T9)
10.0%
Covers unforeseen items; bad weather, bad soil
conditions, labour disputes, minor oversights etc.
3,443,393
T15 TOTAL = SUM T9-T14 (Excluding Escalation)
T15 is accurate to PFS level (+/- 25%%)
$39,220,249
This Estimate is exclusive of GST, Taxes, Duties and Interest during construction.

This area left blank.
Figure 10.3
Summary of capital estimate
Area
Area Description
Sub Areas
Details
Unit
Cost $
Extended Cost $
Unit
Cost
Factor
Extended Cost $
Fabrication
Detailing
Freight
LINE TOTAL $
1.0
Mining
11,575
2.0
Wet Processing Plant
19,086,457
85,999
11,728
3.0
On-Site Infrastructure
3,291,780
177,069
67,879
4.0
Off-Site Infrastructure
9,242,550
24,431
5,553
5.0
Commissioning
91,050
T1
Total Direct Material and Labour
T1 (M)
31,723,412
T1 (L)
287,498
32,010,910
T2
Total Freight
85,159
85,159
T3
Total Fabrication Detailing
All fabrication detailing included in Package Plant
T4
SUB-TOTAL DIRECT FIELD COSTS ( = T1 (M&L)
32,096,069
T5
Labour indirects (% OF T1 (J))
15.0%
43,125
T6
PCM Fees (% of (T4+T5))
7.0%
2,249,744
T7
PCM Home and Site Office Expenses (% of T6)
2.0%
44,995
T8
SUB-TOTAL INDIRECT COSTS (= T5 + T6 +T7)
2,337,863
T9
PROJECT SUB TOTAL (DIRECT+INDIRECT COSTS = T4 + T8)
34,433,932
T10 Project Insurances (% of T9)
0.4%
Indicative only
137,736
T11 Commissioning Spares (% of T9)
Included in Area 2.0
T12 Year 1 Operational Spares (% of T9)
1.5%
Indicative only
516,509
T13 Owners costs (% of T9)
2.0%
(Staff, travel, accomm, Shire and Development fees
etc.)
688,679
T14 Project Contingency (% of T9)
10.0%
Covers unforeseen items; bad weather, bad soil
conditions, labour disputes, minor oversights etc.
3,443,393
T15 TOTAL = SUM T9-T14 (Excluding Escalation)
T15 is accurate to PFS level (+/- 25%%)
$39,220,249
This Estimate is exclusive of GST, Taxes, Duties and Interest during construction.

This area left blank.
Figure 10.3
Summary of capital estimate
Area
Area Description
Sub Areas
Details
Unit
Cost $
Extended Cost $
Unit
Cost
Factor
Extended Cost $
Fabrication
Detailing
Freight
LINE TOTAL $
1.0
Mining
11,575
2.0
Wet Processing Plant
19,086,457
85,999
11,728
3.0
On-Site Infrastructure
3,291,780
177,069
67,879
4.0
Off-Site Infrastructure
9,242,550
24,431
5,553
5.0
Commissioning
91,050
T1
Total Direct Material and Labour
T1 (M)
31,723,412
T1 (L)
287,498
32,010,910
T2
Total Freight
85,159
85,159
T3
Total Fabrication Detailing
All fabrication detailing included in Package Plant
T4
SUB-TOTAL DIRECT FIELD COSTS ( = T1 (M&L)
32,096,069
T5
Labour indirects (% OF T1 (J))
15.0%
43,125
T6
PCM Fees (% of (T4+T5))
7.0%
2,249,744
T7
PCM Home and Site Office Expenses (% of T6)
2.0%
44,995
T8
SUB-TOTAL INDIRECT COSTS (= T5 + T6 +T7)
2,337,863
T9
PROJECT SUB TOTAL (DIRECT+INDIRECT COSTS = T4 + T8)
34,433,932
T10 Project Insurances (% of T9)
0.4%
Indicative only
137,736
T11 Commissioning Spares (% of T9)
Included in Area 2.0
T12 Year 1 Operational Spares (% of T9)
1.5%
Indicative only
516,509
T13 Owners costs (% of T9)
2.0%
(Staff, travel, accomm, Shire and Development fees
etc.)
688,679
T14 Project Contingency (% of T9)
10.0%
Covers unforeseen items; bad weather, bad soil
conditions, labour disputes, minor oversights etc.
3,443,393
T15 TOTAL = SUM T9-T14 (Excluding Escalation)
T15 is accurate to PFS level (+/- 25%%)
$39,220,249
This Estimate is exclusive of GST, Taxes, Duties and Interest during construction.

This area left blank.
Figure 10.3
Summary of capital estimate
Area
Area Description
Sub Areas
Details
Unit
Cost $
Extended Cost $
Unit
Cost
Factor
Extended Cost $
Fabrication
Detailing
Freight
LINE TOTAL $
1.0
Mining
11,575
2.0
Wet Processing Plant
19,086,457
85,999
11,728
3.0
On-Site Infrastructure
3,291,780
177,069
67,879
4.0
Off-Site Infrastructure
9,242,550
24,431
5,553
5.0
Commissioning
91,050
T1
Total Direct Material and Labour
T1 (M)
31,723,412
T1 (L)
287,498
32,010,910
T2
Total Freight
85,159
85,159
T3
Total Fabrication Detailing
All fabrication detailing included in Package Plant
T4
SUB-TOTAL DIRECT FIELD COSTS ( = T1 (M&L)
32,096,069
T5
Labour indirects (% OF T1 (J))
15.0%
43,125
T6
PCM Fees (% of (T4+T5))
7.0%
2,249,744
T7
PCM Home and Site Office Expenses (% of T6)
2.0%
44,995
T8
SUB-TOTAL INDIRECT COSTS (= T5 + T6 +T7)
2,337,863
T9
PROJECT SUB TOTAL (DIRECT+INDIRECT COSTS = T4 + T8)
34,433,932
T10 Project Insurances (% of T9)
0.4%
Indicative only
137,736
T11 Commissioning Spares (% of T9)
Included in Area 2.0
T12 Year 1 Operational Spares (% of T9)
1.5%
Indicative only
516,509
T13 Owners costs (% of T9)
2.0%
(Staff, travel, accomm, Shire and Development fees
etc.)
688,679
T14 Project Contingency (% of T9)
10.0%
Covers unforeseen items; bad weather, bad soil
conditions, labour disputes, minor oversights etc.
3,443,393
T15 TOTAL = SUM T9-T14 (Excluding Escalation)
T15 is accurate to PFS level (+/- 25%%)
$39,220,249
This Estimate is exclusive of GST, Taxes, Duties and Interest during construction.

This area left blank.
Figure 10.3
Summary of capital estimate
Area
Area Description
Sub Areas
Details
Unit
Cost $
Extended Cost $
Unit
Cost
Factor
Extended Cost $
Fabrication
Detailing
Freight
LINE TOTAL $
1.0
Mining
11,575
2.0
Wet Processing Plant
19,086,457
85,999
11,728
3.0
On-Site Infrastructure
3,291,780
177,069
67,879
4.0
Off-Site Infrastructure
9,242,550
24,431
5,553
5.0
Commissioning
91,050
T1
Total Direct Material and Labour
T1 (M)
31,723,412
T1 (L)
287,498
32,010,910
T2
Total Freight
85,159
85,159
T3
Total Fabrication Detailing
All fabrication detailing included in Package Plant
T4
SUB-TOTAL DIRECT FIELD COSTS ( = T1 (M&L)
32,096,069
T5
Labour indirects (% OF T1 (J))
15.0%
43,125
T6
PCM Fees (% of (T4+T5))
7.0%
2,249,744
T7
PCM Home and Site Office Expenses (% of T6)
2.0%
44,995
T8
SUB-TOTAL INDIRECT COSTS (= T5 + T6 +T7)
2,337,863
T9
PROJECT SUB TOTAL (DIRECT+INDIRECT COSTS = T4 + T8)
34,433,932
T10 Project Insurances (% of T9)
0.4%
Indicative only
137,736
T11 Commissioning Spares (% of T9)
Included in Area 2.0
T12 Year 1 Operational Spares (% of T9)
1.5%
Indicative only
516,509
T13 Owners costs (% of T9)
2.0%
(Staff, travel, accomm, Shire and Development fees
etc.)
688,679
T14 Project Contingency (% of T9)
10.0%
Covers unforeseen items; bad weather, bad soil
conditions, labour disputes, minor oversights etc.
3,443,393
T15 TOTAL = SUM T9-T14 (Excluding Escalation)
T15 is accurate to PFS level (+/- 25%%)
$39,220,249
This Estimate is exclusive of GST, Taxes, Duties and Interest during construction.

This area left blank.
Figure 10.3
Summary of capital estimate
Area
Area Description
Sub Areas
Details
Unit
Cost $
Extended Cost $
Unit
Cost
Factor
Extended Cost $
Fabrication
Detailing
Freight
LINE TOTAL $
1.0
Mining
11,575
2.0
Wet Processing Plant
19,086,457
85,999
11,728
3.0
On-Site Infrastructure
3,291,780
177,069
67,879
4.0
Off-Site Infrastructure
9,242,550
24,431
5,553
5.0
Commissioning
91,050
T1
Total Direct Material and Labour
T1 (M)
31,723,412
T1 (L)
287,498
32,010,910
T2
Total Freight
85,159
85,159
T3
Total Fabrication Detailing
All fabrication detailing included in Package Plant
T4
SUB-TOTAL DIRECT FIELD COSTS ( = T1 (M&L)
32,096,069
T5
Labour indirects (% OF T1 (J))
15.0%
43,125
T6
PCM Fees (% of (T4+T5))
7.0%
2,249,744
T7
PCM Home and Site Office Expenses (% of T6)
2.0%
44,995
T8
SUB-TOTAL INDIRECT COSTS (= T5 + T6 +T7)
2,337,863
T9
PROJECT SUB TOTAL (DIRECT+INDIRECT COSTS = T4 + T8)
34,433,932
T10 Project Insurances (% of T9)
0.4%
Indicative only
137,736
T11 Commissioning Spares (% of T9)
Included in Area 2.0
T12 Year 1 Operational Spares (% of T9)
1.5%
Indicative only
516,509
T13 Owners costs (% of T9)
2.0%
(Staff, travel, accomm, Shire and Development fees
etc.)
688,679
T14 Project Contingency (% of T9)
10.0%
Covers unforeseen items; bad weather, bad soil
conditions, labour disputes, minor oversights etc.
3,443,393
T15 TOTAL = SUM T9-T14 (Excluding Escalation)
T15 is accurate to PFS level (+/- 25%%)
$39,220,249
This Estimate is exclusive of GST, Taxes, Duties and Interest during construction.

This area left blank.
Figure 10.3
Summary of capital estimate
Area
Area Description
Sub Areas
Details
Unit
Cost $
Extended Cost $
Unit
Cost
Factor
Extended Cost $
Fabrication
Detailing
Freight
LINE TOTAL $
1.0
Mining
11,575
2.0
Wet Processing Plant
19,086,457
85,999
11,728
3.0
On-Site Infrastructure
3,291,780
177,069
67,879
4.0
Off-Site Infrastructure
9,242,550
24,431
5,553
5.0
Commissioning
91,050
T1
Total Direct Material and Labour
T1 (M)
31,723,412
T1 (L)
287,498
32,010,910
T2
Total Freight
85,159
85,159
T3
Total Fabrication Detailing
All fabrication detailing included in Package Plant
T4
SUB-TOTAL DIRECT FIELD COSTS ( = T1 (M&L)
32,096,069
T5
Labour indirects (% OF T1 (J))
15.0%
43,125
T6
PCM Fees (% of (T4+T5))
7.0%
2,249,744
T7
PCM Home and Site Office Expenses (% of T6)
2.0%
44,995
T8
SUB-TOTAL INDIRECT COSTS (= T5 + T6 +T7)
2,337,863
T9
PROJECT SUB TOTAL (DIRECT+INDIRECT COSTS = T4 + T8)
34,433,932
T10 Project Insurances (% of T9)
0.4%
Indicative only
137,736
T11 Commissioning Spares (% of T9)
Included in Area 2.0
T12 Year 1 Operational Spares (% of T9)
1.5%
Indicative only
516,509
T13 Owners costs (% of T9)
2.0%
(Staff, travel, accomm, Shire and Development fees
etc.)
688,679
T14 Project Contingency (% of T9)
10.0%
Covers unforeseen items; bad weather, bad soil
conditions, labour disputes, minor oversights etc.
3,443,393
T15 TOTAL = SUM T9-T14 (Excluding Escalation)
T15 is accurate to PFS level (+/- 25%%)
$39,220,249
This Estimate is exclusive of GST, Taxes, Duties and Interest during construction.

This area left blank.
Figure 10.3
Summary of capital estimate
Area
Area Description
Sub Areas
Details
Unit
Cost $
Extended Cost $
Unit
Cost
Factor
Extended Cost $
Fabrication
Detailing
Freight
LINE TOTAL $
1.0
Mining
11,575
2.0
Wet Processing Plant
19,086,457
85,999
11,728
3.0
On-Site Infrastructure
3,291,780
177,069
67,879
4.0
Off-Site Infrastructure
9,242,550
24,431
5,553
5.0
Commissioning
91,050
T1
Total Direct Material and Labour
T1 (M)
31,723,412
T1 (L)
287,498
32,010,910
T2
Total Freight
85,159
85,159
T3
Total Fabrication Detailing
All fabrication detailing included in Package Plant
T4
SUB-TOTAL DIRECT FIELD COSTS ( = T1 (M&L)
32,096,069
T5
Labour indirects (% OF T1 (J))
15.0%
43,125
T6
PCM Fees (% of (T4+T5))
7.0%
2,249,744
T7
PCM Home and Site Office Expenses (% of T6)
2.0%
44,995
T8
SUB-TOTAL INDIRECT COSTS (= T5 + T6 +T7)
2,337,863
T9
PROJECT SUB TOTAL (DIRECT+INDIRECT COSTS = T4 + T8)
34,433,932
T10 Project Insurances (% of T9)
0.4%
Indicative only
137,736
T11 Commissioning Spares (% of T9)
Included in Area 2.0
T12 Year 1 Operational Spares (% of T9)
1.5%
Indicative only
516,509
T13 Owners costs (% of T9)
2.0%
(Staff, travel, accomm, Shire and Development fees
etc.)
688,679
T14 Project Contingency (% of T9)
10.0%
Covers unforeseen items; bad weather, bad soil
conditions, labour disputes, minor oversights etc.
3,443,393
T15 TOTAL = SUM T9-T14 (Excluding Escalation)
T15 is accurate to PFS level (+/- 25%%)
$39,220,249
This Estimate is exclusive of GST, Taxes, Duties and Interest during construction.

This area left blank.
Figure 10.3
Summary of capital estimate
Area
Area Description
Sub Areas
Details
Unit
Cost $
Extended Cost $
Unit
Cost
Factor
Extended Cost $
Fabrication
Detailing
Freight
LINE TOTAL $
1.0
Mining
11,575
2.0
Wet Processing Plant
19,086,457
85,999
11,728
3.0
On-Site Infrastructure
3,291,780
177,069
67,879
4.0
Off-Site Infrastructure
9,242,550
24,431
5,553
5.0
Commissioning
91,050
T1
Total Direct Material and Labour
T1 (M)
31,723,412
T1 (L)
287,498
32,010,910
T2
Total Freight
85,159
85,159
T3
Total Fabrication Detailing
All fabrication detailing included in Package Plant
T4
SUB-TOTAL DIRECT FIELD COSTS ( = T1 (M&L)
32,096,069
T5
Labour indirects (% OF T1 (J))
15.0%
43,125
T6
PCM Fees (% of (T4+T5))
7.0%
2,249,744
T7
PCM Home and Site Office Expenses (% of T6)
2.0%
44,995
T8
SUB-TOTAL INDIRECT COSTS (= T5 + T6 +T7)
2,337,863
T9
PROJECT SUB TOTAL (DIRECT+INDIRECT COSTS = T4 + T8)
34,433,932
T10 Project Insurances (% of T9)
0.4%
Indicative only
137,736
T11 Commissioning Spares (% of T9)
Included in Area 2.0
T12 Year 1 Operational Spares (% of T9)
1.5%
Indicative only
516,509
T13 Owners costs (% of T9)
2.0%
(Staff, travel, accomm, Shire and Development fees
etc.)
688,679
T14 Project Contingency (% of T9)
10.0%
Covers unforeseen items; bad weather, bad soil
conditions, labour disputes, minor oversights etc.
3,443,393
T15 TOTAL = SUM T9-T14 (Excluding Escalation)
T15 is accurate to PFS level (+/- 25%%)
$39,220,249
This Estimate is exclusive of GST, Taxes, Duties and Interest during construction.

This area left blank.
Figure 10.3
Summary of capital estimate
Area
Area Description
Sub Areas
Details
Unit
Cost $
Extended Cost $
Unit
Cost
Factor
Extended Cost $
Fabrication
Detailing
Freight
LINE TOTAL $
1.0
Mining
11,575
2.0
Wet Processing Plant
19,086,457
85,999
11,728
3.0
On-Site Infrastructure
3,291,780
177,069
67,879
4.0
Off-Site Infrastructure
9,242,550
24,431
5,553
5.0
Commissioning
91,050
T1
Total Direct Material and Labour
T1 (M)
31,723,412
T1 (L)
287,498
32,010,910
T2
Total Freight
85,159
85,159
T3
Total Fabrication Detailing
All fabrication detailing included in Package Plant
T4
SUB-TOTAL DIRECT FIELD COSTS ( = T1 (M&L)
32,096,069
T5
Labour indirects (% OF T1 (J))
15.0%
43,125
T6
PCM Fees (% of (T4+T5))
7.0%
2,249,744
T7
PCM Home and Site Office Expenses (% of T6)
2.0%
44,995
T8
SUB-TOTAL INDIRECT COSTS (= T5 + T6 +T7)
2,337,863
T9
PROJECT SUB TOTAL (DIRECT+INDIRECT COSTS = T4 + T8)
34,433,932
T10 Project Insurances (% of T9)
0.4%
Indicative only
137,736
T11 Commissioning Spares (% of T9)
Included in Area 2.0
T12 Year 1 Operational Spares (% of T9)
1.5%
Indicative only
516,509
T13 Owners costs (% of T9)
2.0%
(Staff, travel, accomm, Shire and Development fees
etc.)
688,679
T14 Project Contingency (% of T9)
10.0%
Covers unforeseen items; bad weather, bad soil
conditions, labour disputes, minor oversights etc.
3,443,393
T15 TOTAL = SUM T9-T14 (Excluding Escalation)
T15 is accurate to PFS level (+/- 25%%)
$39,220,249
This Estimate is exclusive of GST, Taxes, Duties and Interest during construction.

This area left blank.
Figure 10.3
Summary of capital estimate
Area
Area Description
Sub Areas
Details
Unit
Cost $
Extended Cost $
Unit
Cost
Factor
Extended Cost $
Fabrication
Detailing
Freight
LINE TOTAL $
1.0
Mining
11,575
2.0
Wet Processing Plant
19,086,457
85,999
11,728
3.0
On-Site Infrastructure
3,291,780
177,069
67,879
4.0
Off-Site Infrastructure
9,242,550
24,431
5,553
5.0
Commissioning
91,050
T1
Total Direct Material and Labour
T1 (M)
31,723,412
T1 (L)
287,498
32,010,910
T2
Total Freight
85,159
85,159
T3
Total Fabrication Detailing
All fabrication detailing included in Package Plant
T4
SUB-TOTAL DIRECT FIELD COSTS ( = T1 (M&L)
32,096,069
T5
Labour indirects (% OF T1 (J))
15.0%
43,125
T6
PCM Fees (% of (T4+T5))
7.0%
2,249,744
T7
PCM Home and Site Office Expenses (% of T6)
2.0%
44,995
T8
SUB-TOTAL INDIRECT COSTS (= T5 + T6 +T7)
2,337,863
T9
PROJECT SUB TOTAL (DIRECT+INDIRECT COSTS = T4 + T8)
34,433,932
T10 Project Insurances (% of T9)
0.4%
Indicative only
137,736
T11 Commissioning Spares (% of T9)
Included in Area 2.0
T12 Year 1 Operational Spares (% of T9)
1.5%
Indicative only
516,509
T13 Owners costs (% of T9)
2.0%
(Staff, travel, accomm, Shire and Development fees
etc.)
688,679
T14 Project Contingency (% of T9)
10.0%
Covers unforeseen items; bad weather, bad soil
conditions, labour disputes, minor oversights etc.
3,443,393
T15 TOTAL = SUM T9-T14 (Excluding Escalation)
T15 is accurate to PFS level (+/- 25%%)
$39,220,249
This Estimate is exclusive of GST, Taxes, Duties and Interest during construction.

This area left blank.
Figure 10.3
Summary of capital estimate
Area
Area Description
Sub Areas
Details
Unit
Cost $
Extended Cost $
Unit
Cost
Factor
Extended Cost $
Fabrication
Detailing
Freight
LINE TOTAL $
1.0
Mining
11,575
2.0
Wet Processing Plant
19,086,457
85,999
11,728
3.0
On-Site Infrastructure
3,291,780
177,069
67,879
4.0
Off-Site Infrastructure
9,242,550
24,431
5,553
5.0
Commissioning
91,050
T1
Total Direct Material and Labour
T1 (M)
31,723,412
T1 (L)
287,498
32,010,910
T2
Total Freight
85,159
85,159
T3
Total Fabrication Detailing
All fabrication detailing included in Package Plant
T4
SUB-TOTAL DIRECT FIELD COSTS ( = T1 (M&L)
32,096,069
T5
Labour indirects (% OF T1 (J))
15.0%
43,125
T6
PCM Fees (% of (T4+T5))
7.0%
2,249,744
T7
PCM Home and Site Office Expenses (% of T6)
2.0%
44,995
T8
SUB-TOTAL INDIRECT COSTS (= T5 + T6 +T7)
2,337,863
T9
PROJECT SUB TOTAL (DIRECT+INDIRECT COSTS = T4 + T8)
34,433,932
T10 Project Insurances (% of T9)
0.4%
Indicative only
137,736
T11 Commissioning Spares (% of T9)
Included in Area 2.0
T12 Year 1 Operational Spares (% of T9)
1.5%
Indicative only
516,509
T13 Owners costs (% of T9)
2.0%
(Staff, travel, accomm, Shire and Development fees
etc.)
688,679
T14 Project Contingency (% of T9)
10.0%
Covers unforeseen items; bad weather, bad soil
conditions, labour disputes, minor oversights etc.
3,443,393
T15 TOTAL = SUM T9-T14 (Excluding Escalation)
T15 is accurate to PFS level (+/- 25%%)
$39,220,249
This Estimate is exclusive of GST, Taxes, Duties and Interest during construction.

This area left blank.
Figure 10.3
Summary of capital estimate
Area
Area Description
Sub Areas
Details
Unit
Cost $
Extended Cost $
Unit
Cost
Factor
Extended Cost $
Fabrication
Detailing
Freight
LINE TOTAL $
1.0
Mining
11,575
2.0
Wet Processing Plant
19,086,457
85,999
11,728
3.0
On-Site Infrastructure
3,291,780
177,069
67,879
4.0
Off-Site Infrastructure
9,242,550
24,431
5,553
5.0
Commissioning
91,050
T1
Total Direct Material and Labour
T1 (M)
31,723,412
T1 (L)
287,498
32,010,910
T2
Total Freight
85,159
85,159
T3
Total Fabrication Detailing
All fabrication detailing included in Package Plant
T4
SUB-TOTAL DIRECT FIELD COSTS ( = T1 (M&L)
32,096,069
T5
Labour indirects (% OF T1 (J))
15.0%
43,125
T6
PCM Fees (% of (T4+T5))
7.0%
2,249,744
T7
PCM Home and Site Office Expenses (% of T6)
2.0%
44,995
T8
SUB-TOTAL INDIRECT COSTS (= T5 + T6 +T7)
2,337,863
T9
PROJECT SUB TOTAL (DIRECT+INDIRECT COSTS = T4 + T8)
34,433,932
T10 Project Insurances (% of T9)
0.4%
Indicative only
137,736
T11 Commissioning Spares (% of T9)
Included in Area 2.0
T12 Year 1 Operational Spares (% of T9)
1.5%
Indicative only
516,509
T13 Owners costs (% of T9)
2.0%
(Staff, travel, accomm, Shire and Development fees
etc.)
688,679
T14 Project Contingency (% of T9)
10.0%
Covers unforeseen items; bad weather, bad soil
conditions, labour disputes, minor oversights etc.
3,443,393
T15 TOTAL = SUM T9-T14 (Excluding Escalation)
T15 is accurate to PFS level (+/- 25%%)
$39,220,249
This Estimate is exclusive of GST, Taxes, Duties and Interest during construction.

This area left blank.
Figure 10.3
Summary of capital estimate
Area
Area Description
Sub Areas
Details
Unit
Cost $
Extended Cost $
Unit
Cost
Factor
Extended Cost $
Fabrication
Detailing
Freight
LINE TOTAL $
1.0
Mining
11,575
2.0
Wet Processing Plant
19,086,457
85,999
11,728
3.0
On-Site Infrastructure
3,291,780
177,069
67,879
4.0
Off-Site Infrastructure
9,242,550
24,431
5,553
5.0
Commissioning
91,050
T1
Total Direct Material and Labour
T1 (M)
31,723,412
T1 (L)
287,498
32,010,910
T2
Total Freight
85,159
85,159
T3
Total Fabrication Detailing
All fabrication detailing included in Package Plant
T4
SUB-TOTAL DIRECT FIELD COSTS ( = T1 (M&L)
32,096,069
T5
Labour indirects (% OF T1 (J))
15.0%
43,125
T6
PCM Fees (% of (T4+T5))
7.0%
2,249,744
T7
PCM Home and Site Office Expenses (% of T6)
2.0%
44,995
T8
SUB-TOTAL INDIRECT COSTS (= T5 + T6 +T7)
2,337,863
T9
PROJECT SUB TOTAL (DIRECT+INDIRECT COSTS = T4 + T8)
34,433,932
T10 Project Insurances (% of T9)
0.4%
Indicative only
137,736
T11 Commissioning Spares (% of T9)
Included in Area 2.0
T12 Year 1 Operational Spares (% of T9)
1.5%
Indicative only
516,509
T13 Owners costs (% of T9)
2.0%
(Staff, travel, accomm, Shire and Development fees
etc.)
688,679
T14 Project Contingency (% of T9)
10.0%
Covers unforeseen items; bad weather, bad soil
conditions, labour disputes, minor oversights etc.
3,443,393
T15 TOTAL = SUM T9-T14 (Excluding Escalation)
T15 is accurate to PFS level (+/- 25%%)
$39,220,249
This Estimate is exclusive of GST, Taxes, Duties and Interest during construction.

This area left blank.
Figure 10.3
Summary of capital estimate
Area
Area Description
Sub Areas
Details
Unit
Cost $
Extended Cost $
Unit
Cost
Factor
Extended Cost $
Fabrication
Detailing
Freight
LINE TOTAL $
1.0
Mining
11,575
2.0
Wet Processing Plant
19,086,457
85,999
11,728
3.0
On-Site Infrastructure
3,291,780
177,069
67,879
4.0
Off-Site Infrastructure
9,242,550
24,431
5,553
5.0
Commissioning
91,050
T1
Total Direct Material and Labour
T1 (M)
31,723,412
T1 (L)
287,498
32,010,910
T2
Total Freight
85,159
85,159
T3
Total Fabrication Detailing
All fabrication detailing included in Package Plant
T4
SUB-TOTAL DIRECT FIELD COSTS ( = T1 (M&L)
32,096,069
T5
Labour indirects (% OF T1 (J))
15.0%
43,125
T6
PCM Fees (% of (T4+T5))
7.0%
2,249,744
T7
PCM Home and Site Office Expenses (% of T6)
2.0%
44,995
T8
SUB-TOTAL INDIRECT COSTS (= T5 + T6 +T7)
2,337,863
T9
PROJECT SUB TOTAL (DIRECT+INDIRECT COSTS = T4 + T8)
34,433,932
T10 Project Insurances (% of T9)
0.4%
Indicative only
137,736
T11 Commissioning Spares (% of T9)
Included in Area 2.0
T12 Year 1 Operational Spares (% of T9)
1.5%
Indicative only
516,509
T13 Owners costs (% of T9)
2.0%
(Staff, travel, accomm, Shire and Development fees
etc.)
688,679
T14 Project Contingency (% of T9)
10.0%
Covers unforeseen items; bad weather, bad soil
conditions, labour disputes, minor oversights etc.
3,443,393
T15 TOTAL = SUM T9-T14 (Excluding Escalation)
T15 is accurate to PFS level (+/- 25%%)
$39,220,249
This Estimate is exclusive of GST, Taxes, Duties and Interest during construction.

This area left blank.
Figure 10.3
Summary of capital estimate
Area
Area Description
Sub Areas
Details
Unit
Cost $
Extended Cost $
Unit
Cost
Factor
Extended Cost $
Fabrication
Detailing
Freight
LINE TOTAL $
1.0
Mining
11,575
2.0
Wet Processing Plant
19,086,457
85,999
11,728
3.0
On-Site Infrastructure
3,291,780
177,069
67,879
4.0
Off-Site Infrastructure
9,242,550
24,431
5,553
5.0
Commissioning
91,050
T1
Total Direct Material and Labour
T1 (M)
31,723,412
T1 (L)
287,498
32,010,910
T2
Total Freight
85,159
85,159
T3
Total Fabrication Detailing
All fabrication detailing included in Package Plant
T4
SUB-TOTAL DIRECT FIELD COSTS ( = T1 (M&L)
32,096,069
T5
Labour indirects (% OF T1 (J))
15.0%
43,125
T6
PCM Fees (% of (T4+T5))
7.0%
2,249,744
T7
PCM Home and Site Office Expenses (% of T6)
2.0%
44,995
T8
SUB-TOTAL INDIRECT COSTS (= T5 + T6 +T7)
2,337,863
T9
PROJECT SUB TOTAL (DIRECT+INDIRECT COSTS = T4 + T8)
34,433,932
T10 Project Insurances (% of T9)
0.4%
Indicative only
137,736
T11 Commissioning Spares (% of T9)
Included in Area 2.0
T12 Year 1 Operational Spares (% of T9)
1.5%
Indicative only
516,509
T13 Owners costs (% of T9)
2.0%
(Staff, travel, accomm, Shire and Development fees
etc.)
688,679
T14 Project Contingency (% of T9)
10.0%
Covers unforeseen items; bad weather, bad soil
conditions, labour disputes, minor oversights etc.
3,443,393
T15 TOTAL = SUM T9-T14 (Excluding Escalation)
T15 is accurate to PFS level (+/- 25%%)
$39,220,249
This Estimate is exclusive of GST, Taxes, Duties and Interest during construction.

This area left blank.
Figure 10.3
Summary of capital estimate
Area
Area Description
Sub Areas
Details
Unit
Cost $
Extended Cost $
Unit
Cost
Factor
Extended Cost $
Fabrication
Detailing
Freight
LINE TOTAL $
1.0
Mining
11,575
2.0
Wet Processing Plant
19,086,457
85,999
11,728
3.0
On-Site Infrastructure
3,291,780
177,069
67,879
4.0
Off-Site Infrastructure
9,242,550
24,431
5,553
5.0
Commissioning
91,050
T1
Total Direct Material and Labour
T1 (M)
31,723,412
T1 (L)
287,498
32,010,910
T2
Total Freight
85,159
85,159
T3
Total Fabrication Detailing
All fabrication detailing included in Package Plant
T4
SUB-TOTAL DIRECT FIELD COSTS ( = T1 (M&L)
32,096,069
T5
Labour indirects (% OF T1 (J))
15.0%
43,125
T6
PCM Fees (% of (T4+T5))
7.0%
2,249,744
T7
PCM Home and Site Office Expenses (% of T6)
2.0%
44,995
T8
SUB-TOTAL INDIRECT COSTS (= T5 + T6 +T7)
2,337,863
T9
PROJECT SUB TOTAL (DIRECT+INDIRECT COSTS = T4 + T8)
34,433,932
T10 Project Insurances (% of T9)
0.4%
Indicative only
137,736
T11 Commissioning Spares (% of T9)
Included in Area 2.0
T12 Year 1 Operational Spares (% of T9)
1.5%
Indicative only
516,509
T13 Owners costs (% of T9)
2.0%
(Staff, travel, accomm, Shire and Development fees
etc.)
688,679
T14 Project Contingency (% of T9)
10.0%
Covers unforeseen items; bad weather, bad soil
conditions, labour disputes, minor oversights etc.
3,443,393
T15 TOTAL = SUM T9-T14 (Excluding Escalation)
T15 is accurate to PFS level (+/- 25%%)
$39,220,249
This Estimate is exclusive of GST, Taxes, Duties and Interest during construction.

This area left blank.
Figure 10.3
Summary of capital estimate
Area
Area Description
Sub Areas
Details
Unit
Cost $
Extended Cost $
Unit
Cost
Factor
Extended Cost $
Fabrication
Detailing
Freight
LINE TOTAL $
1.0
Mining
11,575
2.0
Wet Processing Plant
19,086,457
85,999
11,728
3.0
On-Site Infrastructure
3,291,780
177,069
67,879
4.0
Off-Site Infrastructure
9,242,550
24,431
5,553
5.0
Commissioning
91,050
T1
Total Direct Material and Labour
T1 (M)
31,723,412
T1 (L)
287,498
32,010,910
T2
Total Freight
85,159
85,159
T3
Total Fabrication Detailing
All fabrication detailing included in Package Plant
T4
SUB-TOTAL DIRECT FIELD COSTS ( = T1 (M&L)
32,096,069
T5
Labour indirects (% OF T1 (J))
15.0%
43,125
T6
PCM Fees (% of (T4+T5))
7.0%
2,249,744
T7
PCM Home and Site Office Expenses (% of T6)
2.0%
44,995
T8
SUB-TOTAL INDIRECT COSTS (= T5 + T6 +T7)
2,337,863
T9
PROJECT SUB TOTAL (DIRECT+INDIRECT COSTS = T4 + T8)
34,433,932
T10 Project Insurances (% of T9)
0.4%
Indicative only
137,736
T11 Commissioning Spares (% of T9)
Included in Area 2.0
T12 Year 1 Operational Spares (% of T9)
1.5%
Indicative only
516,509
T13 Owners costs (% of T9)
2.0%
(Staff, travel, accomm, Shire and Development fees
etc.)
688,679
T14 Project Contingency (% of T9)
10.0%
Covers unforeseen items; bad weather, bad soil
conditions, labour disputes, minor oversights etc.
3,443,393
T15 TOTAL = SUM T9-T14 (Excluding Escalation)
T15 is accurate to PFS level (+/- 25%%)
$39,220,249
This Estimate is exclusive of GST, Taxes, Duties and Interest during construction.

This area left blank.
Figure 10.3
Summary of capital estimate
Area
Area Description
Sub Areas
Details
Unit
Cost $
Extended Cost $
Unit
Cost
Factor
Extended Cost $
Fabrication
Detailing
Freight
LINE TOTAL $
1.0
Mining
11,575
2.0
Wet Processing Plant
19,086,457
85,999
11,728
3.0
On-Site Infrastructure
3,291,780
177,069
67,879
4.0
Off-Site Infrastructure
9,242,550
24,431
5,553
5.0
Commissioning
91,050
T1
Total Direct Material and Labour
T1 (M)
31,723,412
T1 (L)
287,498
32,010,910
T2
Total Freight
85,159
85,159
T3
Total Fabrication Detailing
All fabrication detailing included in Package Plant
T4
SUB-TOTAL DIRECT FIELD COSTS ( = T1 (M&L)
32,096,069
T5
Labour indirects (% OF T1 (J))
15.0%
43,125
T6
PCM Fees (% of (T4+T5))
7.0%
2,249,744
T7
PCM Home and Site Office Expenses (% of T6)
2.0%
44,995
T8
SUB-TOTAL INDIRECT COSTS (= T5 + T6 +T7)
2,337,863
T9
PROJECT SUB TOTAL (DIRECT+INDIRECT COSTS = T4 + T8)
34,433,932
T10 Project Insurances (% of T9)
0.4%
Indicative only
137,736
T11 Commissioning Spares (% of T9)
Included in Area 2.0
T12 Year 1 Operational Spares (% of T9)
1.5%
Indicative only
516,509
T13 Owners costs (% of T9)
2.0%
(Staff, travel, accomm, Shire and Development fees
etc.)
688,679
T14 Project Contingency (% of T9)
10.0%
Covers unforeseen items; bad weather, bad soil
conditions, labour disputes, minor oversights etc.
3,443,393
T15 TOTAL = SUM T9-T14 (Excluding Escalation)
T15 is accurate to PFS level (+/- 25%%)
$39,220,249
This Estimate is exclusive of GST, Taxes, Duties and Interest during construction.

This area left blank.
Figure 10.3
Summary of capital estimate
Area
Area Description
Sub Areas
Details
Unit
Cost $
Extended Cost $
Unit
Cost
Factor
Extended Cost $
Fabrication
Detailing
Freight
LINE TOTAL $
1.0
Mining
11,575
2.0
Wet Processing Plant
19,086,457
85,999
11,728
3.0
On-Site Infrastructure
3,291,780
177,069
67,879
4.0
Off-Site Infrastructure
9,242,550
24,431
5,553
5.0
Commissioning
91,050
T1
Total Direct Material and Labour
T1 (M)
31,723,412
T1 (L)
287,498
32,010,910
T2
Total Freight
85,159
85,159
T3
Total Fabrication Detailing
All fabrication detailing included in Package Plant
T4
SUB-TOTAL DIRECT FIELD COSTS ( = T1 (M&L)
32,096,069
T5
Labour indirects (% OF T1 (J))
15.0%
43,125
T6
PCM Fees (% of (T4+T5))
7.0%
2,249,744
T7
PCM Home and Site Office Expenses (% of T6)
2.0%
44,995
T8
SUB-TOTAL INDIRECT COSTS (= T5 + T6 +T7)
2,337,863
T9
PROJECT SUB TOTAL (DIRECT+INDIRECT COSTS = T4 + T8)
34,433,932
T10 Project Insurances (% of T9)
0.4%
Indicative only
137,736
T11 Commissioning Spares (% of T9)
Included in Area 2.0
T12 Year 1 Operational Spares (% of T9)
1.5%
Indicative only
516,509
T13 Owners costs (% of T9)
2.0%
(Staff, travel, accomm, Shire and Development fees
etc.)
688,679
T14 Project Contingency (% of T9)
10.0%
Covers unforeseen items; bad weather, bad soil
conditions, labour disputes, minor oversights etc.
3,443,393
T15 TOTAL = SUM T9-T14 (Excluding Escalation)
T15 is accurate to PFS level (+/- 25%%)
$39,220,249
This Estimate is exclusive of GST, Taxes, Duties and Interest during construction.

This area left blank.
Figure 10.3
Summary of capital estimate
Area
Area Description
Sub Areas
Details
Unit
Cost $
Extended Cost $
Unit
Cost
Factor
Extended Cost $
Fabrication
Detailing
Freight
LINE TOTAL $
1.0
Mining
11,575
2.0
Wet Processing Plant
19,086,457
85,999
11,728
3.0
On-Site Infrastructure
3,291,780
177,069
67,879
4.0
Off-Site Infrastructure
9,242,550
24,431
5,553
5.0
Commissioning
91,050
T1
Total Direct Material and Labour
T1 (M)
31,723,412
T1 (L)
287,498
32,010,910
T2
Total Freight
85,159
85,159
T3
Total Fabrication Detailing
All fabrication detailing included in Package Plant
T4
SUB-TOTAL DIRECT FIELD COSTS ( = T1 (M&L)
32,096,069
T5
Labour indirects (% OF T1 (J))
15.0%
43,125
T6
PCM Fees (% of (T4+T5))
7.0%
2,249,744
T7
PCM Home and Site Office Expenses (% of T6)
2.0%
44,995
T8
SUB-TOTAL INDIRECT COSTS (= T5 + T6 +T7)
2,337,863
T9
PROJECT SUB TOTAL (DIRECT+INDIRECT COSTS = T4 + T8)
34,433,932
T10 Project Insurances (% of T9)
0.4%
Indicative only
137,736
T11 Commissioning Spares (% of T9)
Included in Area 2.0
T12 Year 1 Operational Spares (% of T9)
1.5%
Indicative only
516,509
T13 Owners costs (% of T9)
2.0%
(Staff, travel, accomm, Shire and Development fees
etc.)
688,679
T14 Project Contingency (% of T9)
10.0%
Covers unforeseen items; bad weather, bad soil
conditions, labour disputes, minor oversights etc.
3,443,393
T15 TOTAL = SUM T9-T14 (Excluding Escalation)
T15 is accurate to PFS level (+/- 25%%)
$39,220,249
This Estimate is exclusive of GST, Taxes, Duties and Interest during construction.

This area left blank.
Figure 10.3
Summary of capital estimate
Area
Area Description
Sub Areas
Details
Unit
Cost $
Extended Cost $
Unit
Cost
Factor
Extended Cost $
Fabrication
Detailing
Freight
LINE TOTAL $
1.0
Mining
11,575
2.0
Wet Processing Plant
19,086,457
85,999
11,728
3.0
On-Site Infrastructure
3,291,780
177,069
67,879
4.0
Off-Site Infrastructure
9,242,550
24,431
5,553
5.0
Commissioning
91,050
T1
Total Direct Material and Labour
T1 (M)
31,723,412
T1 (L)
287,498
32,010,910
T2
Total Freight
85,159
85,159
T3
Total Fabrication Detailing
All fabrication detailing included in Package Plant
T4
SUB-TOTAL DIRECT FIELD COSTS ( = T1 (M&L)
32,096,069
T5
Labour indirects (% OF T1 (J))
15.0%
43,125
T6
PCM Fees (% of (T4+T5))
7.0%
2,249,744
T7
PCM Home and Site Office Expenses (% of T6)
2.0%
44,995
T8
SUB-TOTAL INDIRECT COSTS (= T5 + T6 +T7)
2,337,863
T9
PROJECT SUB TOTAL (DIRECT+INDIRECT COSTS = T4 + T8)
34,433,932
T10 Project Insurances (% of T9)
0.4%
Indicative only
137,736
T11 Commissioning Spares (% of T9)
Included in Area 2.0
T12 Year 1 Operational Spares (% of T9)
1.5%
Indicative only
516,509
T13 Owners costs (% of T9)
2.0%
(Staff, travel, accomm, Shire and Development fees
etc.)
688,679
T14 Project Contingency (% of T9)
10.0%
Covers unforeseen items; bad weather, bad soil
conditions, labour disputes, minor oversights etc.
3,443,393
T15 TOTAL = SUM T9-T14 (Excluding Escalation)
T15 is accurate to PFS level (+/- 25%%)
$39,220,249
This Estimate is exclusive of GST, Taxes, Duties and Interest during construction.

This area left blank.
- LINE TOTAL $ This area left blank. 32,010,910 85,159 32,096,069 43,125 2,249,744 44,995 2,337,863 34,433,932 137,736 516,509 688,679 3,443,393 $39,220,249
Freight 11,728 67,879 5,553 85,159
Fabrication
Detailing
Installation Extended Cost $ 85,999 177,069 24,431 287,498
Unit
Cost
Ft
acor T1 (L)
Equip/ Material Extended Cost $
11,575 19,086,457 3,291,780 9,242,550 91,050 31,723,412
Unit
Cost $
T1 (M)
BEHARRA - CAPITAL EXPENDITURE ESTIMATE - SUMMARY SHEET Details All fabrication detailing included in Package Plant Indicative only Included in Area 2.0 Indicative only (Staff, travel, accomm, Shire and Development fees
etc.)
Covers unforeseen items; bad weather, bad soil
conditions, labour disputes, minor oversights etc.
T15 is accurate to PFS level (+/- 25%%)
Sub Areas 15.0% 7.0% 2.0% PROJECT SUB TOTAL (DIRECT+INDIRECT COSTS = T4 + T8) 0.4% 1.5% 2.0% 10.0%
Area Description Mining Wet Processing Plant On-Site Infrastructure Off-Site Infrastructure Commissioning Total Direct Material and Labour Total Freight Total Fabrication Detailing SUB-TOTAL DIRECT FIELD COSTS ( = T1 (M&L) Labour indirects (% OF T1 (J)) PCM Fees (% of (T4+T5)) PCM Home and Site Office Expenses (% of T6) SUB-TOTAL INDIRECT COSTS (= T5 + T6 +T7) Project Insurances (% of T9)
Commissioning Spares (% of T9)

Year 1 Operational Spares (% of T9)

Owners costs (% of T9)
Project Contingency (% of T9) TOTAL = SUM T9-T14 (Excluding Escalation) This Estimate is exclusive of GST, Taxes, Duties and Interest during construction.
Area 1.0 2.0 3.0 4.0 5.0 T1 T2 T3 T4 T5 T6 T7 T8 T9 **T10 ** **T11 ** **T12 ** **T13 ** **T14 ** **T15 **

==> picture [85 x 27] intentionally omitted <==

10.2.2 Basis of estimate

A breakdown of the Base Case CAPEX basis of estimate can be found in Appendix 11 (Estimate Basis Memorandum).

10.2.3 Foreign exchange

Perpetual has elected to use a flat A$:US$ exchange rate of 0.75c across the forecast period, which is considered a reasonable estimation of a likely long run average level. As Beharra is a long-life project, wide exchange rate fluctuations are possible, with this risk to be managed by the management team and Board of Directors who may utilise an appropriate exchange rate hedging strategy at the relevant time.

10.3 OPERATING COST ESTIMATE

10.3.1 Accuracy and scope of estimate

The operating cost estimate includes all site-related operating costs associated with mining and processing ore to produce a >99.5% + silica sand product and product transport on an FOB ship basis.

The operating cost estimate was developed based on an annual production of nominally 1.51 Mtpa of >99.5% SiO2 product (the Base Case scenario); the base mining rate required to achieve this is nominally 2.0 Mtpa which are reflected in the Base Case project financial model. A base estimate mining rate of nominally 2.0 Mtpa was established and on this basis the nett cost per tonne of product on an FOB basis is calculated to be A$43.07/t.

Escalation/inflation have not been addressed within the operating cost estimate but have been separately modelled in the financial model at a rate of 2.5% per annum.

10.3.2 Basis of estimate

A breakdown of the basis of estimate can be found in Appendix 11 (Estimate Basis Memorandum).

10.3.3 Summary of estimate

A summarised table of operating cash cost categories are outlined in Table 10.3 below.

Table 10.3 Summary of cash costs

Capital $A/t ore
Mining ROM + OB
Processing
Reject haulage
Administration
Transport + Port
Rehabilitation
Contingency
Royalty
5.18
2.46
0.29
1.18
19.40
0.43
1.40
1.71
TOTAL OPEX 32.05

10.3.4 Cash flow model

MI, in conjunction with Perpetual, undertook the financial analysis of the Project with all price assumptions and operational and capital expenditure estimates provided to MI through Perpetual. These assumptions and estimates were in A$.

The financial analysis has been performed using DCF analysis. All amounts are in A$ and are nominal. Variability of input assumptions for capital, operating and sales price has been assessed using sensitivity analysis.

The key assessment criterion is the IRR on a nominal, after tax basis. NPV (@10%, nominal after tax), payback periods and capital funding requirements have also been assessed.

BEHARRA SILICA PROJECT PRE-FEASIBILITY STUDY

117

==> picture [85 x 27] intentionally omitted <==

The financial analysis indicates the following post-tax NPV and post-tax IRR calculations. Scenarios have also been run, assuming the Project is geared to 40% (debt to equity), with a debt payback period of 10 years and a cost of debt of 7.5% per annum. The outcomes of this analysis are shown in Table 10.4 below.

Table 10.4 NPV and IRR assessments under various assumptions

Condition Base Case
NPV(post-tax)– ungeared $231 million
IRR(post-tax)– ungeared 54.6%
NPV(post-tax)–geared $236 million
IRR(post-tax)–geared 77.4%

A maximum cash draw before tax of A$40 million is calculated in year 1 in the financial model, when the Project is assumed to be constructed and commissioned. Payback of the original capital is achieved early in year 2 of operations. Figure 10.4 demonstrates the net undiscounted cash flow profile.

==> picture [459 x 177] intentionally omitted <==

Figure 10.4 Beharra net undiscounted cash flow chart

10.4 INVESTMENT EVALUATION

10.4.1 Valuation methodology

It is considered that the most relevant valuation methodology for the Beharra Project is a DCF methodology.

DCF is a valuation method used to estimate the value of an investment based on its expected future cash flows. DCF analysis attempts to determine the value of an investment today, based on projections of how much free cash it will generate in the future.

The DCF for Beharra has therefore been constructed by estimating the annual revenue that the Beharra Project could generate and subtracting the various operating, capital, tax and financing expenses (if applicable) in any given year, which generates an annual free cash flow amount for the entire life of the Project, modelled as 32 years.

These annual cash flows are then discounted back to today’s dollars using a discount rate of 10%. When project gearing is assumed, a debt-to-equity ratio of 40% is applied.

The summation of the 32 years of after-tax discounted cashflows is then presented as a NPV of the Project, which is used as the base valuation of the Project, and which equals the assessed values shown in Table 10.5 below under gearing assumptions.

Table 10.5 NPV and IRR assessed values

Condition Base Case
NPV (post-tax) – ungeared $231 million
IRR (post-tax) – ungeared 54.6%
NPV (post-tax) – geared $236 million
IRR (post-tax) – geared 77.4%

118

BEHARRA SILICA PROJECT PRE-FEASIBILITY STUDY

==> picture [85 x 27] intentionally omitted <==

10.4.2 Key project variables

The results of the PFS demonstrate a robust economic case, with a number of key financial sensitivities that could affect the ultimate financial outcome.

10.4.3 Sensitivity analysis

The key financial sensitivities for the project, and their impact on valuation and return metrics, is summarised in Table 10.6 and *Sensitivity variations are zero due to base case gearing of 0%

Table 10.7 below. Sensitivities have been detailed in this section, as the Base Case sensitivities provide sufficient indicative variability of the key metrics, with the percentage impact on valuation broadly the same irrespective of annual production level.

Table 10.6 NPV sensitivity analysis given a change in one discrete variable of the financial model

Sensitivity 80% 90% 100% 110% 120%
Price $75.6 $153.3 $230.9 $308.6 $386.2
Exchange rate $425.1 $317.2 $230.9 $160.3 $101.5
Operating cost $330.9 $280.9 $230.9 $180.9 $131.0
Project capital $240.1 $235.5 $230.9 $226.3 $221.8
Gearing ratio* $230.9 $230.9 $230.9 $230.9 $230.9

*Sensitivity variations are zero due to base case gearing of 0%

Table 10.7 NPV sensitivity analysis given a change in both price and operating cost in the financial model

Price
$230.9 80% 90% 100% 110% 120%
Operating
cost
80% 170.0 250.5 330.9 411.3 491.7
90% 120.0 200.5 280.9 361.3 441.8
100% 70.1 150.5 230.9 311.3 391.8
110% 20.1 100.5 180.9 261.4 341.8
120% -30.2 50.5 131.0 211.4 291.8

The sensitivity of the post-tax project cashflows and the DCF to changes of ±0 to 20% is shown in Figure 10.5 below.

==> picture [460 x 226] intentionally omitted <==

----- Start of picture text -----

After Tax NPV Sensitivity to Key Variables - Base Case
Gearing Ratio
Project Capital
Oper. Cost
Exchange Rate
Price
(200.00) (150.00) (100.00) (50.00) - 50.00 100.00 150.00 200.00
NPV Impact
80% 120%
----- End of picture text -----

Figure 10.5 After-tax NPV sensitivity to key variables

119

BEHARRA SILICA PROJECT PRE-FEASIBILITY STUDY

==> picture [85 x 27] intentionally omitted <==

As is typical with many resource related projects, the key financial metrics are most sensitive to changes in revenue and operating cost assumptions, with exchange rate sensitivity also seen as a major influence on the ultimate financial outcomes of the Beharra Project.

10.4.4 Valuation results and key metrics

Table 10.8 Key financial model outputs

Project economics at assumedproduction scenario Unit Base Case
Total silica sandproduced Mt 47.6
Annualproduction target Mt 1.51
Probable Ore [email protected]% SiO2 Mt 64.1
Ore Reserve Life years 32
JORC Resources Mt 139
Total LOM revenue A$ M 3,176
Total LOM capital expenditure A$ M 76.9
Total LOM EBITDA A$ M 1,714
Total LOM free cash flow A$ M 1,131
Post-tax DCF(NPV10)– ungeared A$ M 231
Post-tax IRR – ungeared % 55
Post-tax DCF(NPV10)–geared A$ M 236
Post-tax IRR –geared % 77
Paybackperiod years 2
FOB costs A$/t 43.07

The key financial metrics shown in Table 10.8 above demonstrate that the Beharra Project is considered robust on key financial measures, exhibiting rapid payback, high IRRs and high resulting NPVs, and has potential to become a significant export project in the Mid-West region of WA.

120

BEHARRA SILICA PROJECT PRE-FEASIBILITY STUDY

==> picture [85 x 27] intentionally omitted <==

11. JORC CODE (2012) TABLE 1 REPORTING (SECTIONS 1, 2, 3, AND 4)

11.1 SECTION 1: SAMPLING TECHNIQUES AND DATA

Criteria JORC Code explanation Commentary
Sampling
techniques
Nature and quality of sampling (e.g. cut
channels, random chips, or specific
specialised industry standard measurement
tools appropriate to the minerals under
investigation, such as downhole gamma
sondes, or handheld XRF instruments, etc).
These examples should not be taken as
limiting the broad meaning of sampling.
Include reference to measures taken to
ensure sample representivity and the
appropriate calibration of any
measurement tools or systems used.
Aspects of the determination of
mineralisation that are Material to the
Public Report.
In cases where ‘industry standard’ work has
been done this would be relatively simple
(e.g. ‘reverse circulation drilling was used to
obtain 1 m samples from which 3 kg was
pulverised to produce a 30 g charge for
fire assay’). In other cases, more
explanation may be required, such as
where there is coarse gold that has inherent
sampling problems. Unusual commodities or
mineralisation types (e.g. submarine
nodules) may warrant disclosure of detailed
information.
Aircore drilling and sampling referred to in this report
occurred in two separate programs: March 2020 and
September 2020.
March 2020: Aircore samples were collected via a
cyclone, the entire sample for each 1 m drill interval was
collected and placed in a calico sample bag. No splitting
on the rig was undertaken. The sample was labelled with
the drillhole number and sample interval, and a
waterproof tag nominating a sample number was placed
in the bag and then sealed with a tie.
September 2020: Aircore samples were collected via a
cyclone, the entire sample for each 1 m drill interval was
collected and placed in a calico sample bag, labelled with
the drillhole number and sample interval, and weighed by
a spring balance. A 1 kg split was taken by spear and
placed in a smaller calico bag, labelled with a sample
number.
Aircore samples were collected from each metre drilled or
part metre if the hole was not ended on a full metre. For
the September program, separate samples were taken for
0–0.5 m and for 0.5–1 m. Only the latter had a 1 kg split
taken from it.
Representative samples of each interval drilled were
placed in a chip tray for reference.
Auger drilling and sampling referred to in this report and
reported previously were obtained from hand auguring to
a maximum depth of 2 m.
Three auger samples were collected from each hole being
surface to 0.5 m, 0.5–1.0 m, and 1.0–2.0 m. The top metre
of the hole was split into two samples to allow a separate
sample of the top 0.5 m that contains organic matter
associated with native ground cover. If sand mining
operations were to be carried out, this top 0.5 m would be
stockpiled for future rehabilitation, so at this time treating
it separately is appropriate.
The shallow auger program was carried out to obtain
representative sand samples to a maximum depth of 2 m
for the reasons as described in the Company release of 12
February2019.

121

BEHARRA SILICA PROJECT PRE-FEASIBILITY STUDY

==> picture [85 x 27] intentionally omitted <==

Criteria JORC Code explanation Commentary
Drilling
techniques
Drill type (e.g. core, reverse circulation,
open-hole hammer, rotary air blast, auger,
Bangka, sonic, etc) and details (e.g. core
diameter, triple or standard tube, depth of
diamond tails, face-sampling bit or other
type, whether core is oriented and if so, by
what method, etc).
March 2020: A total of 32 aircore drillholes were
completed to an average depth of 12.3 m, with the
deepest hole ending at 17 m.
September 2020 aircore drilling was undertaken using a
track mounted KL170 hydraulic top drive rig coupled to a
250 psi compressor. An 84 mm vacuum bit was fitted to a
76 mm outside diameter twin tube rod string. The internal
diameter was 51 mm. All holes were drilled vertically.
March 2020: A total of 40 aircore drillholes were
completed for an average depth of 12.7 m, with the
deepest hole ending at 20 m.
March 2020 aircore drilling was undertaken using a track
mounted Hitachi hydraulic top drive rig coupled to a
130 cfm/100 psi compressor. A 76 mm aircore bit was
fitted to 70 mm twin tube rod string. All holes were drilled
vertically.
Auger drilling consisted of a manually hand operated
75 mm diameter sand auger (Dormer Sand Auger) with
PVC casing utilised to reduce contamination potential as
the auger is withdrawn from the hole. The auger was
driven about 300 mm then retracted and the sample was
placed in a UV resistant plastic bag and this continued until
the sample interval was completed. The sample was
labelled with the drillhole number and sample interval,
then placed in a second plastic bag and sealed and
removed from site for loggingand samplepreparation.
Drill sample
recovery
Method of recording and assessing core
and chip sample recoveries and results
assessed.
Measures taken to maximise sample
recovery and ensure representative nature
of the samples.
Whether a relationship exists between
sample recovery and grade and whether
sample bias may have occurred due to
preferential loss/gain of fine/coarse
material.
March 2020: Aircore – each sample bag was weighed to
determine the actual sample recovery, which resulted in an
average sample weight of approximately 7.5 kg/m of
sample.
September 2020: Aircore – each sample bag was
weighed to determine the actual sample recovery, which
resulted in an average sample weight of approximately
4 kg/m of sample.
March 2020: Aircore sampling was typically terminated on
reaching the water table, which occurred around 10–12 m
below surface level.
September 2020: Aircore sampling was typically
terminated 2 m below the water table. Hole depths
ranged from 9 m to 17 m.
The cyclones were cleaned regularly to ensure maximum
and representative recovery.
For auger sampling, each sample bag was weighed to
determine the actual sample recovery, which resulted in an
average sample weight of 7.5 kg/m of sample.
The type of sand auger used provided a clean sample
with less possibility of contamination compared to a flight
auger.

122

BEHARRA SILICA PROJECT PRE-FEASIBILITY STUDY

==> picture [85 x 27] intentionally omitted <==

Criteria JORC Code explanation Commentary
Logging Whether core and chip samples have been
geologically and geotechnically logged to
a level of detail to support appropriate
Mineral Resource estimation, mining studies
and metallurgical studies.
Whether logging is qualitative or
quantitative in nature. Core (or costean,
channel, etc) photography.
The total length and percentage of the
relevant intersections logged.
The samples have been sufficiently logged including
estimates of grain size, sorting and texture, and colour.
Particular attention has been taken to ensure a more
scientific and less subjective approach to colour has been
adopted because colour (white to grey shades, and pale
yellow shades) is one of the targeting features.
Chip tray samples for each hole were photographed.
Subsampling
techniques and
sample
preparation
If core, whether cut or sawn and whether
quarter, half or all core taken.
If non-core, whether riffled, tube sampled,
rotary split, etc and whether sampled wet
or dry.
For all sample types, the nature, quality and
appropriateness of the sample preparation
technique.
Quality control procedures adopted for all
subsampling stages to maximise
representivity of samples.
Measures taken to ensure that the sampling
is representative of the in-situ material
collected, including for instance results for
field duplicate/second-half sampling.
Whether sample sizes are appropriate to
the grain size of the material being
sampled.
Aircore samples were transported to Welshpool in Perth
and locked in a secure storage shed.
March 2020: Further check logging was undertaken, and
representative subsamples were taken for duplicate
analysis. Subsampling was carried out by spearing the
samples selected and collecting approximately 400 g of
sample. The duplicates have been utilised at the rate of
1:20.
September 2020: Duplicate 1 kg subsamples were taken
in a ratio of 1:18 at site.
Blanks were generated from a publicly available washed
sand product and taken by spearing a 20-bulk sample:
March 2020 approx.400 g samples; September 2020
approx. 1 kg samples. The blanks have been utilised at the
rate of 1:20 in March and 1:18 in September.
March 2020: The prepared subsamples (duplicates and
blanks) plus all the bulk drill samples were submitted to
Nagrom Metallurgical Analytical Laboratories located in
Kelmscott in Western Perth for drying, further splitting, and
pulverisation in a zircon bowl. A subsample of 100 g with
a P90 -75 µm particle size was utilised for analysis.
September 2020: The 1 kg subsamples, including
duplicates and blanks, were submitted to Intertek
Genalysis analytical laboratory located in Maddington in
Western Perth for drying, splitting to 100 g for
pulverisation to a P90 -75 µm particle size in a zircon
bowl.
Auger samples were submitted to Intertek Laboratory in
Maddington for drying, splitting, pulverisation in a zircon
bowl. A subsample of 200 g with a 75μm particle size is
utilised for analysis.
Allowance was made for duplication by drilling a twin
auger hole located within 1 m of each other. Three twin
holes were drilled representing 8% duplicate sample.
The sample preparation methods are considered industry
standard for silica sands. Records were kept describing
whether the samples were submitted wet or dry.
The laboratory sample size taken is appropriate for the
sand beingtargeted.
Quality of
assay data
and laboratory
tests
The nature, quality and appropriateness of
the assaying and laboratory procedures
used and whether the technique is
considered partial or total.
March 2020: All the aircore samples prepared by
Nagrom were analysed at the same facility. The assay
method for multi-element analysis consisted of prepared
samples fused in a lithium borate flux with lithium nitrate
additive then analysed byXRF(test method XRF001). LOI

123

BEHARRA SILICA PROJECT PRE-FEASIBILITY STUDY

==> picture [85 x 27] intentionally omitted <==

Criteria JORC Code explanation Commentary
For geophysical tools, spectrometers,
handheld XRF instruments, etc, the
parameters used in determining the analysis
including instrument make and model,
reading times, calibrations factors applied
and their derivation, etc.
Nature of quality control procedures
adopted (e.g. standards, blanks, duplicates,
external laboratory checks) and whether
acceptable levels of accuracy (i.e. lack of
bias) and precision have been established.
was also carried out on each sample out at 1,000°C (test
method TGA002).
Auger samples were submitted to the Intertek Laboratory
in Maddington, Perth, Western Australia. The assay
method for multi-element analysis consisted of four-acid
digest including hydrofluoric, nitric, perchloric and
hydrochloric acids in Teflon beakers with inductively
coupled plasma (ICP)-optical (atomic) emission
spectrometry finish. Silica is reported by difference.
March 2020: Inter-laboratory checking was carried out by
submitting 28 prepared representative pulps (umpire
samples) to the Intertek Laboratory located in Maddington.
The samples were analysed by two methods, XRF (test
method FB1/XRF20) and ICP-optical (atomic) emission
spectrometry (test method 4ABSi/OE901). Samples for ICP
analysis consisted of a four-acid digest including
hydrofluoric, nitric, perchloric and hydrochloric acids in
Teflon beakers. Silica is reported by difference.
March 2020: The same 28 samples analysed by Intertek
were also analysed by ICP at Nagrom’ s laboratory. For
analysis of Al2O3and SiO2the samples were fused with
sodium peroxide and digested in dilute hydrochloric acid
and then analysed by ICP (test method ICP005). All other
elements were determined by ICP after dissolution in an
acid mixture (test method ICP003).
March 2020: Final analyses of the aircore samples were
carried out at Intertek’s laboratory using four-acid digest
followed by ICP determination. The samples used consisted
of pulps that were prepared by Nagrom.
September 2020: Intertek’s analysis method for silica
sands analysis consisted of four-acid digestion followed by
silica sands 17-element ICP/OE analysis plus LOI at
1,000°C with SiO2reported by difference.
September 2020: Inter-laboratory umpire analysis was
carried out by submitting 20 pulps, and 20 non-pulverised
portions of the same samples, from Intertek Genalysis to
the Bureau Veritas laboratory located in Canning Vale,
Perth. The samples were analysed by mixed acid digest
(MA100) followed by 17 elements by ICP-OES (MA101)
and LOI (TG001). Silica was reported by difference.
The extensive analysis by different laboratories and
different methods are industry standard procedures and
methods producing high level of confidence on the results
produced. The ICP method is considered industry standard
for reporting sand grades.
Nogeophysical tools were utilised for theprocess.
Verification of
sampling and
assaying
The verification of significant intersections
by either independent or alternative
company personnel.
The use of twinned holes.
Documentation of primary data, data entry
procedures, data verification, data storage
(physical and electronic) protocols.
Discuss anyadjustment to assaydata.
March 2020: There were no twin aircore holes.
Twin holes were completed for three out of the 38 auger
holes.
September 2020: One of the September aircore holes was
twinned; two of the March 2020 aircore holes were
twinned.
All drilling and sampling procedures were monitored on
site byan independentgeologist on a hole-by-hole basis.

124

BEHARRA SILICA PROJECT PRE-FEASIBILITY STUDY

==> picture [85 x 27] intentionally omitted <==

Criteria JORC Code explanation Commentary
All primary information was initially captured in a written
log on site by a geologist, data entered, imported then
validated and stored in a geological database.
March 2020: Additional check logging was carried by an
independent geologist in Perth prior to samples being
submitted to Nagrom for analysis.
No adjustments to assay data have been performed.
External review of umpire samples reported by Intertek
and Bureau Veritas was carried out.
Location of
data points
Accuracy and quality of surveys used to
locate drillholes (collar and downhole
surveys), trenches, mine workings and other
locations used in Mineral Resource
estimation.
Specification of the grid system used.
Quality and adequacy of topographic
control.
The position of the aircore hole locations was determined
by a Trimble R6 RTK global positioning system (GPS) in
RTK mode. The survey was carried out by Heyhoe Surveys
from Geraldton. Accuracy of 0.05 m relative to SSM
Dongara 49.
The position of the auger hole locations was determined
by a GPS model Garmin GPS Map 64s with an accuracy
of 5 m.
The CRS used was GDA94/MGA Zone 50 (ex SSM
DON49).
The topography at the project site currently under
exploration is flat to gentle undulating terrain. Site survey
(Heyhoe Surveys) have produced a ± 50 cm DTM across
the entireproject area.
Data spacing
and
distribution
Data spacing for reporting of Exploration
Results.
Whether the data spacing and distribution
is sufficient to establish the degree of
geological and grade continuity
appropriate for the Mineral Resource and
Ore Reserve estimation procedure(s) and
classifications applied.
Whether sample compositing has been
applied.
The aircore drillholes were spaced on an approx. 350–
600 m (east west) x 480 m along strike (north-south) grid.
The auger drillholes were spaced on an approx. 400 m
(east-west) x 800 m (north-south) grid.
The adopted spacing at this time is sufficient based on the
geological continuity of the sand formation being tested,
and sufficient to be applied in Mineral Resource
estimation.
No sample compositing of holes has been applied.
Orientation of
data in relation
to geological
structure
Whether the orientation of sampling
achieves unbiased sampling of possible
structures and the extent to which this is
known, considering the deposit type.
If the relationship between the drilling
orientation and the orientation of key
mineralised structures is considered to have
introduced a sampling bias, this should be
assessed and reported if material.
The orientation utilised for the aircore drilling campaign
represents the entire strike length of the aeolian dune
within the initial prospective target area and as such is not
expected to introduce any particular bias.
Sample
security
The measures taken to ensure sample
security.
All samples have been bagged and removed from site
and are under the care of the contract senior geologist
and field sampling supervisor.
March 2020: Aircore samples initially stored a secure
facility in Welshpool where sample reconciliation was
undertaken before delivery to Nagrom Laboratory.
March 2020: Aircore samples were delivered to Nagrom
in Kelmscott. The laboratory carried out a sample
reconciliation which was audited against the sample
submission sheet.
September 2020: Aircore samples and returned samples
andpulps from Intertek Genalysis are in the Welshpool

125

BEHARRA SILICA PROJECT PRE-FEASIBILITY STUDY

==> picture [85 x 27] intentionally omitted <==

Criteria JORC Code explanation Commentary
facility along with chip trays from both the March and
September drill programs.
Auger samples were delivered to Intertek Maddington. The
laboratory provided a sample reconciliation report which
was audited against the sample submission sheet.
Audits or
reviews
The results of any audits or reviews of
sampling techniques and data.
Guidance was provided by an independent consultant,
Andrew Scogings, on sampling lengths and hole spacings
who carried out a site visit to inspect the drilling and
samplingoperations.

11.2 SECTION 2: REPORTING OF EXPLORATION RESULTS

Criteria JORC Code explanation Commentary
Mineral
tenement and
land tenure
status
Type, reference name/number, location and
ownership including agreements or material
issues with third parties such as joint ventures,
partnerships, overriding royalties, native title
interests, historical sites, wilderness or national
park and environmental settings.
The security of the tenure held at the time of
reporting along with any known impediments to
obtaining a licence to operate in the area.
Miscellaneous licence L70/219 comprises an effective
land area of 10.36 km2and was granted on 18
November 2020 for a period of 21 years. The
holder is Perpetual Resources Limited. A 1% vendor
royalty applies minerals sold from the Licence.
The licence area exploration is covered by Crown
Land.
No impediments on a licence to operate at time of
reporting.
Exploration
done by other
parties
Acknowledgment and appraisal of exploration
by other parties.
Past exploration by others targeting heavy mineral
sands. Refer to ASX release dated 6 February 2019,
historical exploration.
Geology Deposit type, geological setting and style of
mineralisation.
Unconsolidated Quaternary coastal sediments, part
of the Perth Basin. Aeolian quartz sand dunes
overlyingPleistocene limestones andpaleo-coastline.
Drill =ole
information
A summary of all information material to the
understanding of the exploration results including
a tabulation of the following information for all
Material drillholes:

easting and northing of the drillhole collar

elevation or RL (Reduced Level – elevation
above sea level in metres) of the drillhole
collar

dip and azimuth of the hole

downhole length and interception depth

hole length.
If the exclusion of this information is justified on
the basis that the information is not Material and
this exclusion does not detract from the
understanding of the report, the Competent
Person should clearly explain why this is the
case.
Exploration Results are not being reported here;
however, drillhole information can be found in ASX
release dated 1 April 2020 and 7 December 2020.
Data
aggregation
methods
In reporting Exploration Results, weighting
averaging techniques, maximum and/or minimum
grade truncations (e.g. cutting of high grades)
and cut-off grades are usually Material and
should be stated.
Where aggregate intercepts incorporate short
lengths of high-grade results and longer lengths
of low-grade results, the procedure used for such
aggregation should be stated and some typical
Exploration Results are not being reported.

126

BEHARRA SILICA PROJECT PRE-FEASIBILITY STUDY

==> picture [85 x 27] intentionally omitted <==

Criteria JORC Code explanation Commentary
examples of such aggregations should be shown
in detail.
The assumptions used for any reporting of metal
equivalent values should be clearlystated.
Relationship
between
mineralisation
widths and
intercept lengths
These relationships are particularly important in
the reporting of Exploration Results.
If the geometry of the mineralisation with respect
to the drillhole angle is known, its nature should
be reported.
If it is not known and only the downhole lengths
are reported, there should be a clear statement
to this effect (e.g. ‘downhole length, true width
not known’).
Exploration Results are not being reported.
Diagrams Appropriate maps and sections (with scales) and
tabulations of intercepts should be included for
any significant discovery being reported These
should include, but not be limited to a plan view
of drillhole collar locations and appropriate
sectional views.
Refer to figures incorporated in the body of the
report.
Balanced
reporting
Where comprehensive reporting of all
Exploration Results is not practicable,
representative reporting of both low and high
grades and/or widths should be practiced to
avoid misleading reporting of Exploration
Results.
Exploration Results are not being reported.
Other
substantive
exploration data
Other exploration data, if meaningful and
material, should be reported including (but not
limited to): geological observations; geophysical
survey results; geochemical survey results; bulk
samples – size and method of treatment;
metallurgical test results; bulk density,
groundwater, geotechnical and rock
characteristics; potential deleterious or
contaminating substances.
Groundwater was intersected in all holes that
exceeded 10 m depth. Water table generally
occurred between 10 m and 12 m.
Average in situ density (dry) determined to be 1.64
t/m3from six sites. Density locations were hand
excavated to 0.4 m deep. The Instrument used was
an Instrotek model Explorer. Tests were performed
by Western Geotechnical & Laboratory Services.
For the March 2020 program particle size
distribution analysis was carried out on eight
representative samples. Tests were undertaken by
Western Geotechnical & Laboratory Services.
Previous metallurgical testwork was undertaken by
Nagrom to establish possible process methods to
provide a beneficiated product. Refer to ASX
releases of 30 January 2020 and 24 February
2020.
Petrological examination by Paul Ashley undertaken
and reported on 18 February 2020.
An approximate two tonnes bulk sample from the
March aircore drilling was process tested by IHCR
with results received in December 2020.
In-situ PSD was determined for 12 aircore holes from
the March 2020 program south of the Mount Adams
Road and for six holes from the September 2020
program to the north. The March 2020 samples were
tested using a dry sieving method by Diamantina
Laboratories,Malaga and the September 2020

127

BEHARRA SILICA PROJECT PRE-FEASIBILITY STUDY

==> picture [85 x 27] intentionally omitted <==

Criteria JORC Code explanation Commentary
samples were tested by Nagrom, Kelmscott using a
wet screening method.
In-situ particle size is predominantly within the range
of 0.15 mm to 0.6 mm.
About 70% of the sand grains are between 0.125
mm and 0.6 mm.
Calculated AFS numbers for the March 2020 samples
are predominantly in the range 40–50.
The sands appear to become finer grained with
depth. This is illustrated by P50 which decreases from
about 400 µm to 300 µm for the March 2020
samples.
The September 2020 aircore results are generally
finer than the March 2020 aircore samples. It
appears that there is a general trend of decreasing
grain size going north.
The apparently finer size of the September 2020
samples may be due to the wet screening method
used, compared with dry screening for the March
2020 samples. Wet screening is likely to be more
efficient than dry screening.
Snowden is of the opinion that the PSD results from
both programs need verification, by umpire testing of
September 2020 Nagrom samples at Diamantina.
Twins 20B019 and 20B032 should be included for
testing at both Robbins and Nagrom. Infill holes
should also be tested for PSD.
Further work The nature and scale of planned further work
(e.g. tests for lateral extensions or depth
extensions or large-scale step-out drilling).
Diagrams clearly highlighting the areas of
possible extensions, including the main
geological interpretations and future drilling
areas, provided this information is not
commerciallysensitive.
The Company will carry out further metallurgical
testwork.

11.3 SECTION 3: ESTIMATION AND REPORTING OF MINERAL RESOURCES

Criteria JORC Code explanation Commentary
Database
integrity
Measures taken to ensure that data has not been
corrupted by, for example, transcription or
keying errors, between its initial collection and its
use for Mineral Resource estimation purposes.
Data validation procedures used.
Selected checks by Snowden of drillhole data
against original assay certificates were completed
with no errors identified.
Statistical checks completed to ensure all assays fall
within acceptable limits.
Checks on overlapping or duplicate intervals
completed.
Checks were completed on all samples which fell
below analytical detection limits to ensure samples
were assigned half detection limit grades in
estimation.
Site visits Comment on any site visits undertaken by the
Competent Person and the outcome of those
visits.
The Competent Person, Andrew Scogings, visited the
site during the aircore drilling program in March
2020.

128

BEHARRA SILICA PROJECT PRE-FEASIBILITY STUDY

==> picture [85 x 27] intentionally omitted <==

Criteria JORC Code explanation Commentary
If no site visits have been undertaken indicate
whythis is the case.
Geological
interpretation
Confidence in (or conversely, the uncertainty of)
the geological interpretation of the mineral
deposit.
Nature of the data used and of any assumptions
made.
The effect, if any, of alternative interpretations
on Mineral Resource estimation.
The use of geology in guiding and controlling
Mineral Resource estimation.
The factors affecting continuity both of grade
and geology.
Snowden believes the local geology is well
understood as a result of work undertaken by
Perpetual and other companies working in the
region.
Surfaces of the sand layers were interpreted based
on a combination of geochemistry and the
geological logging. Each layer was treated as a
hard boundary for resource modelling.
Alternative interpretations of the mineralisation are
unlikely to significantly change the overall volume of
the layers in terms of the reported classified
material.
Dimensions The extent and variability of the Mineral
Resource expressed as length (along strike or
otherwise), plan width, and depth below surface
to the upper and lower limits of the Mineral
Resource.
The deposit has an extent of approx. 7.1 km north-
south x 1.9 km east-west in the south and 1.2 km
east-west in the north.
The deposit is restricted by tenement boundaries and
the Yardanogo Nature Reserve in the west.
The deposit is open outside of these limits.
Estimation and
modelling
techniques
The nature and appropriateness of the
estimation technique(s) applied and key
assumptions, including treatment of extreme
grade values, domaining, interpolation
parameters and maximum distance of
extrapolation from data points. If a computer
assisted estimation method was chosen include a
description of computer software and
parameters used.
The availability of check estimates, previous
estimates and/or mine production records and
whether the MRE takes appropriate account of
such data.
The assumptions made regarding recovery of
by-products.
Estimation of deleterious elements or other non-
grade variables of economic significance (e.g.
sulphur for acid mine drainage characterisation).
In the case of block model interpolation, the
block size in relation to the average sample
spacing and the search employed.
Any assumptions behind modelling of selective
mining units.
Any assumptions about correlation between
variables.
Description of how the geological interpretation
was used to control the resource estimates.
Discussion of basis for using or not using grade
cutting or capping.
The process of validation, the checking process
used, the comparison of model data to drillhole
data,and use of reconciliation data if available.
Ordinary kriging estimation using a parent cell size
of 200 mE x 240 mN x 2 mRL to estimate for SiO2,
Al2O3, TiO2, Fe2O3and LOI.
Sample selection honoured geological domains which
were developed considering the vertical chemical
and geological trends of the profile. Five layers
were modelled: Yellow, White Upper, White Lower,
Light Grey Pod, Grey Pod and Grey.
Statistical analysis by domain was completed. Top
cuts were applied to some elements in some layers
where appropriate to control sporadic extreme
values during estimation; however, no top cut was
applied for SiO2.
Variography was completed for all elements. Due to
the low number of samples for individual layers,
data was combined for variogram modelling.
Correlations were largely maintained by using
similar estimation parameters. Validation of block
estimates included visual and statistical checks, both
global and local. Checks were completed against
original and de-clustered drillhole samples. The
validations show that while smoothed, the block
estimates reproduce the trends observed in the
drillhole data.

129

BEHARRA SILICA PROJECT PRE-FEASIBILITY STUDY

==> picture [85 x 27] intentionally omitted <==

Criteria JORC Code explanation Commentary
Moisture Whether the tonnages are estimated on a dry
basis or with natural moisture, and the method of
determination of the moisture content.
All tonnages have been estimated as dry tonnages.
Cut-off
parameters
The basis of the adopted cut-off grade(s) or
quality parameters applied.
No cut-off parameters have been applied as the
yellow and white sand being reported appears to
be readily amenable to beneficiation to a suitable
product specification through relatively simple
metallurgical processes as demonstrated by initial
reported metallurgical testingresults.
Mining factors
or assumptions
Assumptions made regarding possible mining
methods, minimum mining dimensions and internal
(or, if applicable, external) mining dilution. It is
always necessary as part of the process of
determining reasonable prospects for eventual
economic extraction to consider potential mining
methods, but the assumptions made regarding
mining methods and parameters when estimating
Mineral Resources may not always be rigorous.
Where this is the case, this should be reported
with an explanation of the basis of the mining
assumptions made.
It is assumed that the deposit will be mined using
conventional open cut mining methods.
No assumptions regarding minimum mining widths
and dilution have been made.
No mining has occurred.
Metallurgical
factors or
assumptions
The basis for assumptions or predictions
regarding metallurgical amenability. It is always
necessary as part of the process of determining
reasonable prospects for eventual economic
extraction to consider potential metallurgical
methods, but the assumptions regarding
metallurgical treatment processes and
parameters made when reporting Mineral
Resources may not always be rigorous. Where
this is the case, this should be reported with an
explanation of the basis of the metallurgical
assumptions made.
Eight composites were made of three sand types
from the 2020 aircore drill program and tested for
particle size distribution at Western Geotechnical in
Welshpool during April 2020. The samples were
described as light grey-white sand, grey clayey
sand and yellow sand. The in-situ PSD is fairly
consistent irrespective of the type of sand, with
approximately 85% of the sand between 0.15 mm
and 0.6 mm.
A composite sample weighing 178.6 kg from nine
shallow auger holes drilled in 2019 was submitted to
Nagrom of Kelmscott, WA for process test work
which was reported in February 2020. The process
flowsheet included screening at 1 mm, washing,
attritioning, spiral separation, medium intensity
magnetic separation, acid leaching and calcination.
Gravcon Consultancy PL was commissioned by
Perpetual in June 2020 to review the Nagrom results
and the following notes are derived from the
Gravcon report.
The percentage of SiO2in the samples increased
during the test process while Fe2O3, TiO2, Al2O3and
LOI decreased relative to the head grade.
Attritioning and washing the material removed fines
and silt, which increased the SiO2content. The spirals
test produced samples where the largest fraction of
SiO2was in the light and middlings fractions.
Magnetic separation indicated that the largest
fraction of SiO2was in the middlings and non-
magnetic fractions. Acid leach tests showed that
hydrochloric acid reduced Al2O3and Fe2O3. Repeat
leaching had minimal impact and the use of sulphuric
acid alone or combined with hydrochloric acid had
minimal impact. Calcination tests indicated limited
improvement toproductquality.

130

BEHARRA SILICA PROJECT PRE-FEASIBILITY STUDY

==> picture [85 x 27] intentionally omitted <==

Criteria JORC Code explanation Commentary Commentary
Examples of SiO2and Fe2O3results for
stage are summarised as:
Process stage SiO2%
(XRF)
Fe2O3%
(XRF)
Feed -1 mm 99.037 0.127
Deslimed +75 micron 99.297 0.111
Spiral lights + middlings 99.594 0.045
MIMS non-magnetics 99.647 0.030
HCl leach 99.746 0.009
Environmental
factors or
assumptions
Assumptions made regarding possible waste and
process residue disposal options. It is always
necessary as part of the process of determining
reasonable prospects for eventual economic
extraction to consider the potential
environmental impacts of the mining and
processing operation. While at this stage the
determination of potential environmental
impacts, particularly for a greenfields project,
may not always be well advanced, the status of
early consideration of these potential
environmental impacts should be reported.
Where these aspects have not been considered
this should be reported with an explanation of
the environmental assumptions made.
It is assumed that no environmental factors exist that
could prohibit any potential mining development at
the deposit.
Bulk density Whether assumed or determined. If assumed, the
basis for the assumptions. If determined, the
method used, whether wet or dry, the frequency
of the measurements, the nature, size and
representativeness of the samples.
The bulk density for bulk material must have
been measured by methods that adequately
account for void spaces (vughs, porosity, etc),
moisture and differences between rock and
alteration zones within the deposit.
Discuss assumptions for bulk density estimates
used in the evaluation process of the different
materials.
Six in-situ bulk density measurements were
completed by Western Geotechnical & Laboratory
Services using a nuclear densometer and reported
on 16 April 2020. The sites were sampled in
accordance with AS 1289.1.2.1-6.5.1 and tested in
accordance with AS 1289.2.1.1. and AS 1289.5.8.1.
The results from the seven measurements are
corrected based on the measured moisture factor.
The dry density ranged from 1.57 t/m3to 1.68 t/m3
with an average dry in situ density result of
1.64 t/m3which was applied to the estimate.
The Competent Person is of the opinion that the bulk
density determined using recovered sample weight,
and nominal aircore or vacuum hole diameter,
supported the results from the nuclear densometer
method (1.64 t/m3) and the loose and tapped
methods (1.66 t/m3). Based on all data, an average
density of 1.64 t/m3as determined by the nuclear
densometer has been assumed for the Project.

131

BEHARRA SILICA PROJECT PRE-FEASIBILITY STUDY

==> picture [85 x 27] intentionally omitted <==

Criteria JORC Code explanation Commentary
Classification The basis for the classification of the Mineral
Resources into varying confidence categories.
Whether appropriate account has been taken of
all relevant factors (i.e. relative confidence in
tonnage/grade estimations, reliability of input
data, confidence in continuity of geology and
metal values, quality, quantity and distribution of
the data).
Whether the result appropriately reflects the
Competent Person’s view of the deposit.
The Mineral Resource was classified based on data
quality, sample spacing, grade continuity, geological
continuity of the domains and metallurgical/process
test results into Inferred material. The grey sands are
considered uneconomic at this stage and have been
excluded. The reported Mineral Resource does not
include any material within the Yardanogo Nature
Reserve which occupies a strip approximately 300 m
wide on the western side of the tenement and
excludes a buffer of 50 m south and north of Mount
Adams Road.
The Mineral Resource classification appropriately
reflects the view of the Competent Person.
Audits or
reviews
The results of any audits or reviews of MREs. Snowden is not aware of any independent reviews
of the MRE.
Snowden’s internal review process ensures all work
meetsqualitystandards.
Discussion of
relative
accuracy/
confidence
Where appropriate a statement of the relative
accuracy and confidence level in the MRE using
an approach or procedure deemed appropriate
by the Competent Person. For example, the
application of statistical or geostatistical
procedures to quantify the relative accuracy of
the resource within stated confidence limits, or, if
such an approach is not deemed appropriate, a
qualitative discussion of the factors that could
affect the relative accuracy and confidence of
the estimate.
The statement should specify whether it relates to
global or local estimates, and, if local, state the
relevant tonnages, which should be relevant to
technical and economic evaluation.
Documentation should include assumptions made
and the procedures used.
These statements of relative accuracy and
confidence of the estimate should be compared
withproduction data,where available.
The Mineral Resource has been validated both
globally and locally against the input sample data.
Estimates are considered to be accurate to a level
which supports mine planning – Indicated.
There is no operating mine at the Project, and as
such, no production data is available.

11.4 SECTION 4: ESTIMATION AND REPORTING OF ORE RESERVES

Table 11.1 Beharra Probable Ore Reserve, March 2021

Sand Tonnes (Mt) SiO2 (%) Al2O3 (ppm) TiO2 (ppm) Fe2O3 (ppm) LOI (%)
In situ 64.1 98.6 4240 3460 1950 0.235
Saleable product 47.6 99.6 1,789 369 276 0.100

Notes:

  • Million tonnes are rounded to one decimal place. Grades are rounded to three significant figures.

  • No cut-off is applied to the silica sand product.

  • The in-situ and saleable product are not additive, and the saleable product is a portion of the in-situ sand tonnage.

A checklist of assessment and reporting criteria according to JORC guidelines and including Competent Person’s assessment and comment on the Ore Reserve estimates, is shown in Table 1, Section 4.

Item JORC Code explanation Comments
Mineral
Resource for
Description of the MRE used as a basis
for the conversion to an Ore Reserve.
Mineral Resources for the Beharra deposit were reported in
February2021 from a Datamine model

132

BEHARRA SILICA PROJECT PRE-FEASIBILITY STUDY

==> picture [85 x 27] intentionally omitted <==

Item JORC Code explanation Comments Comments Comments
conversion to
Mineral
Reserves
Clear statement as to whether the
Mineral Resources are reported
additional to, or inclusive of, the Ore
Reserves.
“beharra_20210210.dm”. No cut-off grade is applied for the
silica sand Mineral Resources and is commensurate with other
deposits.
Mineral Resources are reported inclusive of the Ore Reserves.
Site visits Comment on any site visits undertaken
by the Competent Person and the
outcome of those visits.
If no site visits have been undertaken
indicate why this is the case.
Site visits were completed
Persons:
by the following Competent
Items
Date of site visit
Mining
Dec 2020
Metallurgy
Feb 2021
Competent Persons Items Date of site visit
Frank Blanchfield Mining Dec 2020
Arno Kruger Metallurgy Feb 2021
Study status The type and level of study
undertaken to enable Mineral
Resources to be converted to Ore
Reserves.
The Code requires that a study to at
least PFS level has been undertaken to
convert Mineral Resources to Ore
Reserves. Such studies will have been
carried out and will have determined a
mine plan that is technically achievable
and economically viable, and that
material Modifying Factors have been
considered.
The Beharra Silica Project has been under technical
investigation as a PFS completed in March 2021.
Cut-off
parameters
The basis of the cut-off grade(s) or
quality parameters applied.
The ore inventory was required to have a Fe2O3average
below 2000ppm forplant feed consideration.
Mining factors
and
assumptions
The method and assumptions used as
reported in the PFS or Feasibility Study
to convert the Mineral Resource to an
Ore Reserve (i.e. either by application
of appropriate factors by optimisation
or by preliminary or detailed design).
The choice, nature and
appropriateness of the selected mining
method(s) and other mining parameters
including associated design issues such
as pre-strip, access, etc.
The assumptions made regarding
geotechnical parameters (e.g. pit
slopes, stope sizes, etc), grade control
and pre-production drilling.
The major assumptions made and
Mineral Resource model used for pit
and stope optimisation (if
appropriate).
The mining dilution factors used.
The mining recovery factors used.
Any minimum mining widths used.
The manner in which Inferred Mineral
Resources are utilised in mining studies
and the sensitivity of the outcome to
their inclusion.
The infrastructure requirements of the
selected mining methods
Snowden completed a mining prefeasibility study for the
Beharra Project in 2021. The study reflects the latest
understanding of the Project.
An evaluation using pit optimisation to produce an economic
mining shell followed by detailed pit design was used to
convert the Mineral Resource to an Ore Reserve. A mine layout
was developed for mining of staged designs mine layout
development. Mine equipment requirements were determined
by contractors, who provided pricing using the Snowden mine
production schedule as a basis. Selective mining using an open
pit load and haul mining cycle is used for mining activities.
Geotechnical
Snowden completed a geotechnical analysis to recommended
pit slope design parameters for Beharra for 80 m deep pit as
summarised as:
Batter
angle
(º)
Berm
width at
base of
batter (m)
Batter
height
(m)
Inter-ramp
slope angle
(crest to crest,
°)
Overall
slope
angle
(crest to
toe, °)
30
NA
10
NA
30
Grade control
The drill density for Indicated Resources is sufficient to define
the flat ore basement. As the mining floor limit is elevated by
0.5 m and the grade control in the basement will be visual.
There is a 0.5 m roof ore loss and this will be sufficient to
maximise or guarantee the quality of the ore.
Dilution

133

BEHARRA SILICA PROJECT PRE-FEASIBILITY STUDY

==> picture [85 x 27] intentionally omitted <==

Item JORC Code explanation Comments
Dilution was essentially zero, however there were ore losses
from boundary losses (neighbouring nature reserve, Mount
Adams Road and 10 m lease offset corridor that were about
5% of the available resources and floor and roof loses and
internal waste that was about 8% of the available resources.
Schedule
Snowden identified a LOM schedule of 33 years suitable for
Ore Reserve assessment.
No in-pit Inferred Resources were used to quantify Ore
Reserves.
Metallurgical
factors and
assumptions
The metallurgical process proposed
and the appropriateness of that
process to the style of factors or
mineralisation.
Whether the metallurgical process is
well-tested technology or novel in
nature.
The nature, amount and
representativeness of metallurgical test
work undertaken, the nature of the
metallurgical domaining applied and
the corresponding metallurgical
recovery factors applied.
Any assumptions or allowances made
for deleterious elements.
The existence of any bulk sample or
pilot scale test work and the degree to
which such samples are considered
representative of the orebody as a
whole.
For minerals that are defined by a
specification, has the ore reserve
estimation been based on the
appropriate mineralogy to meet the
specifications
Metallurgical testwork
To date, metallurgical testing has been carried out in two
phases. The first phase of mineralogical examination, PSD of
aircore samples and process testing of hand auger samples
was reported on previously by Haren and Scogings (2020).
The initial Phase 1 process testwork program was conducted
on the composite auger drill samples and indicated that the
Beharra deposit was suitable for producing silica sand for
markets such as glass, ceramics and foundry.
The second phase of metallurgical test work commenced in Q3
2020 with Perpetual supplying approximately two tonnes of
sand samples from the March 2020 aircore drill program to
IHCR of Brisbane, a specialist mineral sands laboratory, for
bulk process testwork. This programme was conducted using
full size or genuinely scalable equipment and the results are
demonstrated in IHCR report 1959-PM-REP-0000-8002.
The resultant products derived from the IHCR 2.0T bulk
metallurgical test program were of high quality as
demonstrated in the table below.
Calculation and determination of Ore Reserves is based on
producing Beharra Premium silica sand product #44, which
will have a SiO2of >99.5% and a Fe2O3of <280 ppm. Mass
yield into this product as per test work is calculated at 74.4%.
(Ref: 1959-PM-REP-0000-8001 Rev 2).
Mineral Processing
The mineral processing flowsheet and plant required for the
upgrading of the mined material at Beharra is commonly seen
and used both in the quarrying and aggregates and mineral
sands industry. The separation techniques employed are
commonplace and include screening and desliming, gravity,
magnetic and physical separation.
Given the relatively small throughput requirement and
simplicity, traditional package plant suppliers were
approached for an all-inclusive turnkey solution, based on the
provided sound engineering documentation and the proposed
flowsheetprovided byPerpetual.
%
ppm
ppm
ppm
%
SiO2
Al2O3
Fe2O3
TiO2
LOI
%
97.9
9990
680
910
0.26
Beharra Premium #44
74.4
99.6
1789
276
369
0.14
Beharra Premium #27
6.3
99.7
1405
235
300
0.13
Beharra Premium #46
68
99.6
1825
280
375
0.14
Assay
Mass by
ROM
Testwork Classification
Product Classification
UCC Underflow(calc)
Screen O/S
Screen U/S
Environmental The status of studies of potential
environmental impacts of the mining
and processing operation. Details of
waste rock characterisation and the
consideration ofpotential sites,status
Environment
Considerable baseline environmental studies, commissioned by
Tiwest (now Tronox) for its Dongara titanium minerals project,

134

BEHARRA SILICA PROJECT PRE-FEASIBILITY STUDY

==> picture [85 x 27] intentionally omitted <==

Item JORC Code explanation Comments
of design options considered and,
where applicable, the status of
approvals for process residue storage
and waste drum s should be reported.
immediately adjacent to the Beharra Project have been
procured from Tronox via a data share arrangement.
This data significantly contributes to the environmental impact
assessment process to support approvals for Beharra and
covers factors including groundwater and groundwater-
dependent ecosystems, surface water, flora, vegetation,
weeds and dieback, terrestrial and subterranean fauna, soil
profiles and acid sulphate soils and indigenous heritage.
In addition, studies conducted to date by Perpetual to
complement the extensive Tronox dataset and cover the
following areas: flora and vegetation, terrestrial fauna,
groundwater and groundwater-dependent ecosystems and
heritage.
Mine rehabilitation
A comprehensive study was undertaken to determine the most
suitable progressive rehabilitation method for the Beharra
Project based on the existing environment. Consultation and
benchmarking with other extractive sand miners in the local
area as well as expert rehabilitation practitioners was
undertaken to assist in developingthe method.
Infrastructure The existence of appropriate
infrastructure: availability of land for
plant development, power, water,
transportation (particularly for bulk
commodities), labour, accommodation;
or the ease with which the
infrastructure can be provided or
accessed.
The Project site is easily accessed via the sealed Brand
Highway and unsealed Adams Road. There will be a
requirement for some road and intersection upgrade works to
support the volume of haul trucks required to transport the
final product to Geraldton.
An on-site power station and water supply infrastructure will
need to be constructed.
Labour will be sourced from the nearby towns of Dongara and
Geraldton, removing the requirement for onsite
accommodation.
Costs The derivation of, or assumptions
made, regarding projected capital
costs in the study.
The methodology used to estimate
operating costs.
Allowances made for the content of
deleterious elements.
The derivation of assumptions made of
metal or commodity price(s), for the
principal minerals and co- products.
The source of exchange rates used in
the study.
Derivation of transportation charges.
The basis for forecasting or source of
treatment and refining charges,
penalties for failure to meet
specification, etc.
The allowances made or royalties
payable, both government and
private.
The capital cost estimate prepared by Perpetual includes
direct plant and supporting infrastructure, indirect costs and is
to an accuracy level of ±25% with a contingency of 10%
included.
Budget pricing was received from a process plant supply and
install contractor (inclusive of engineering, process and
materials handling equipment, E, I & C, process water circuit,
and associated structure and piping).
Budget pricing was also received for civil works, concrete, fuel
storage, power station, administration, amenities and
workshop infrastructure.
The operating cost estimate was developed as a bottom-up
estimate over the 32-year LOM to obtain average operating
costs. All significant and measurable items are itemised, with
smaller items estimated based on other silica sand operations
and the experience/expertise of project consultants.
Mining costs were derived from tenders fielded to
appropriately qualified contract mining companies using pit
models provided by Snowden. A contract mining model has
been adopted and the raw mining cost provided by the
selected tenderer, has been included in the operating cost
estimate. This rate has then been brought forward into the
mining model.
Rehabilitation costs have been provided by Tetris (Trajectory)
based on a $/ha breakdown.

135

BEHARRA SILICA PROJECT PRE-FEASIBILITY STUDY

==> picture [85 x 27] intentionally omitted <==

Item JORC Code explanation Comments Comments
Specific consumption rates for reagents and consumables were
estimated through a combination of equipment operating
data, bench-scale testwork and modelling software.
Current market pricing was obtained for all major
consumables and reagents based on supplier budget pricing
as of December 2020. A small general allowance was made
for minor miscellaneous consumables based on historical data
from similar operations.
Power station supply and install is included as a $kw/hr,
BOOM operational cost – supplying power and sized
according to the drawn loads on the equipment list.
Maintenance costs were estimated based on projected capital
estimates for the plant using industry benchmarked factors.
Remuneration rates typically expected in this area for
discipline personnel were used to establish operating costs,
with labour rates being sourced from three contributors:
AMMA, Gravcon, and Allied PD.
Perpetual has elected to use a flat A$:US$ exchange rate of
75c across the forecast period, which is considered a
reasonable estimation of a likely long run average level.
Perpetual acknowledges that wide exchange rate fluctuations
are possible and could positively or negatively affect the
profitability and economic viability of the Beharra Project at
any single point in time. This risk will be managed by the
management team and Board of Directors who may utilise an
exchange rate hedging strategy should it be considered
appropriate at the time.
Annual operating costs – average years 1-5 at full
production
An average summary of annual operating costs forecast for
the first fiveyears of fullproduction are set out below:
OPEX (A$)
Cost per
annum
($‘000)
A$/t
ore
A$/t
product
concentrate
Mining (ROM+OB)
10.6
5.18
6.97
Processing
5.0
2.46
3.31
Reject haulage
0.6
0.29
0.36
Administration
2.4
1.18
1.58
Transport + Port/ ship
loading
39.4
19.40
26.09
Rehabilitation
1.8
0.43
0.58
Contingency
2.8
1.40
1.88
Royalty
3.5
1.71
2.30
Total OPEX
66.1
32.05
43.07
Pre-production capital costs
A summary of the pre-production capital estimate is set out
below:
CAPEX (A$)
Cost
($‘000)
Processplant(incl. water distribution)
19,287
Services and onsite infrastructure
3,537
Offsite infrastructure
9,272
Cost
CAPEX (A$) ($‘000)
Processplant(incl. water distribution) 19,287
Services and onsite infrastructure 3,537
Offsite infrastructure 9,272

136

BEHARRA SILICA PROJECT PRE-FEASIBILITY STUDY

==> picture [85 x 27] intentionally omitted <==

Item JORC Code explanation Comments
Indirect,PCM and site office costs 2,338
Total development capital 34,434
Owners’ costs 1,343
Owner’s contingency (10%) 3,443
Totalpre-production capital 39,220
Revenue factors The derivation of, or assumptions made
regarding revenue factors including
head grade, metal or commodity
price(s) exchange rates, transportation
and treatment charges, penalties, net
smelter returns, etc.
The derivation of assumptions made of
metal or commodity price(s), for the
principal metals, minerals and co-
products.
The grade of the process feed and iron content is supported
by the information in the MRE and driven by the mining and
production schedule. Processing recoveries were estimated
based on a metallurgical test program completed during the
PFS, using scalable processing equipment.
Perpetual engaged IMARC, to prepare an independent
market assessment of the APAC region, specifically targeting
selected countries and product grades.
Beharra metallurgical testwork to date has confirmed that
Beharra end-product to be suitable for sale into the 200–
300 ppm Fe2O3markets in the APAC region. In 2019, silica
sand with 200–300 ppm Fe2O3recorded a price of between
US$41.10 in China and US$71.60 per metric ton in Japan.
Sell prices, in US$, have been forecast out to 2026 by IMARC.
Based on the above and advice provided by industry experts,
Perpetual is confident that a sell price of US$50 per metric ton
and above is achievable.
Market
assessment
The demand, supply and stock situation
for the particular commodity,
consumption trends assessment and
factors likely to affect supply and
demand into the future.
A customer and competitor analysis
along with the identification of likely
market windows for the product.
Price and volume forecasts and the
basis for these forecasts.
For industrial minerals the customer
specification, testing and acceptance
requirements prior to a supply
contract.
The APAC market assessment revealed the APAC region to be
amongst the largest consumers of silica sand in the world
based on increasing utilisation in the glass and foundry
industries, reaching a value of US$5,133.7 million in 2020.
The forecast market value is expected to reach US$7,638.1
million by 2026, exhibiting a CAGR of 7.1% during this
period.
The forecast market consumption volume is expected to reach
174.25 million metric tons by 2026, exhibiting a CAGR of
4.8% during the 2021–2026 period.
In 2020, the glass industry represented the largest end use
sector for silica sand accounting for 37.6% of the total APAC
market volume, with foundry sand accounting for 27.1%.
Perpetual’s marketing strategy therefore is focussed on
targeting the APAC glass sand industry in the higher end
market based on products, initially in the 200–300 ppm range
in relation to iron, where prices range from US$41.10/t in
China to US$71.60/t in Japan.
Pricing for silica sand products in the APAC region vary by a
number of factors, mostly dictated by country of purchase and
impurity levels. In China, silica sand prices for higher purity
grades sell for between US$45/t and US$115/t, in Korea this
price range is US$55/t to US$130/t, and in Japan the range
is US75/t to US$190/t. Perpetual has conservatively chosen a
price of US$50/t FOB Geraldton which provides significant
scope for pricing upside as marketing channels are
developed.
Perpetual has sent a number of samples to potential customers
in the APAC region, and has signed one Memorandum of
Understanding for offtake for up to 250,000 tons per annum
with a Chinese end user called Yaoguo Solar Science &
TechnologyCo. Ltd(Yaoguo). Yaoguo has alreadytested

137

BEHARRA SILICA PROJECT PRE-FEASIBILITY STUDY

==> picture [85 x 27] intentionally omitted <==

Item JORC Code explanation Comments
samples of Beharra silica sand and have provided a positive
response, with further samples being sent to develop deeper
discussions. Strong indications have been provided by Yaoguo
that Beharra silica sand is suitable for the Asian market.
Economic The inputs to the economic analysis to
produce the NPV in the study, the
source and confidence of these
economic inputs including estimated
inflation, discount rate, etc.
NPV ranges and sensitivity to
variations in the significant assumptions
and inputs.
Financial modelling was completed by Perpetual, Snowden is
reliant on the commodity price projections advised by
Perpetual. Snowden is not an expert in the forecasting of
commodity prices, and other than to draw attention to the
sensitivity of the project to these projections, is not able to
comment on the risk that these projections will change over
time. However the commodity price estimate is based on the
2019 price outlook provided by IMARC and also the
professional opinion of Stratum Resources, which is a specialist
industrial mineral consultancy that provides advice and trading
in the silica sand markets regionally.
The key financial metrics for just the reserve portion of the
project are the IRR 54.6% and NPV 230.9 million @ %10
discount rate.
A real, pre-tax discount rate of 10.0% was applied based on
Perpetual’s calculated weighted average cost of capital and
also a comparison to other similar projects.
A long-term AUD: USD FX rate averaging 0.75:1 over the
LOM was applied, reflecting an approximation of the
average exchange rate over the last 40 years.
A sensitivity analysis on the NPV is provided below, which
looks to analyse the economic impact of key variables for the
Beharra project, including:

Revenue per tonne

Changes in operating costs

Changes in capital costs

Exchange rate fluctuations

Changes in levels of project gearing.
Social The status of agreements with key
stakeholders and matters leading to
social licence to operate.
Perpetual has undertaken an assessment of its key
stakeholders that have a (statutory) interest in the Project,
including local government authorities, government agencies,
and other interested parties, i.e. Shires, traditional owners etc).
Perpetual will maintain a program of engagement throughout
the life of the project. Consultation will be aimed at
developing relationships that are mutually beneficial to both
parties. Stakeholders will be engaged early in the planning
process, primarily in the interests of achieving a collaborative
approach to raise any concerns and provide Perpetual with
the means to respond to feedback and to ensure that local

138

BEHARRA SILICA PROJECT PRE-FEASIBILITY STUDY

==> picture [85 x 27] intentionally omitted <==

Item JORC Code explanation Comments
knowledge is considered in the design and management of the
project. A stakeholder register and records of engagement
are maintained.
Classification The basis for the classification of the
Ore Reserves into varying confidence
categories.
Whether the result appropriately
reflects the Competent Person’s view of
the deposit.
The proportion of Probable Ore
Reserves that have been derived from
Measured Mineral Resources(if any).
The Beharra Ore Reserves are classified using the guidelines
of the JORC Code (2012).
In-pit Indicated Mineral Resources were used as the basis for
Probable Ore Reserve.
Other The status of agreements with key
stakeholders and matters leading to
social licence to operate.
To the extent relevant, the impact of
the following on the project and/or on
the estimation and classification of the
Ore Reserves:

Any identified material naturally
occurring risks.

The status of material legal
agreements and marketing
arrangements.

The status of governmental
agreements and approvals critical
to the viability of the project, such
as mineral tenement status, and
government and statutory
approvals. There must be
reasonable grounds to expect that
all necessary government
approvals will be received within
the timeframes anticipated in the
PFS or feasibility study. Highlight
and discuss the materiality of any
unresolved matter that is
dependent on a third party on
which extraction of the reserve is
contingent.
Perpetual recognises there is a potential human health
exposure risk to RCS at Beharra. RCS could be produced as
an airborne dust when silica sand is disturbed through mineral
extraction, stockpiling, transportation and handling and is dry
enough to generate dust particles. These particles can be small
enough to lodge deep in the lungs and cause illness or disease
such as bronchitis, silicosis and lung cancer.
A WES exists for crystalline silica and represents the
concentration of an airborne hazardous chemical within a
worker’s breathing zone that should not cause adverse health
effects or undue harm. The current WES for RCS is 0.1 mg/m3
over an eight-hour working day in Western Australia, with the
WES likely to be lowered to 0.05 mg/m3by the end of 2020
to meet national standards.
RCS exposure and safety requirements are governed by the
following Western Australian Legislation:

Occupational Safety and Health Act 1984

Occupational Safety and Health Regulations 1995

Mines Safety and Inspection Act 1994

Mines Safety and Inspection Regulations 1995.
Prior to the commencement of any extraction activities at the
Project, a HRA will be undertaken to define key sources and
the pathways of RCS. With this information, defined dust
management procedures to reduce the risk of exposure to
personnel above the WES will be developed using the
hierarchy of controls – substitution, isolation, engineering,
administrative, PPE.
Additionally, the HRA will be a key input to the preparation of
a HHMP in accordance with the DMIRS Guideline ‘Preparation
of health and hygiene management plan – guide’ (2018) and
approved by DMIRS prior to operations commencing at the
Project. The HHMP will define as a minimum the sources,
pathways management and monitoring of RCS. The HHMP will
be reviewed annually to ensure it meets current standards and
capture any changes to operational circumstances or
procedural controls. This will enable Perpetual to maintain
continual compliance with its legislative health and safety
obligations.
Currently, final product samples of Beharra Premium have
been provided from the resultant bulk metallurgical test
program to a varietyofpotential off takers.

139

BEHARRA SILICA PROJECT PRE-FEASIBILITY STUDY

==> picture [85 x 27] intentionally omitted <==

Item JORC Code explanation Comments
Perpetual has not entered into any binding agreements or
arrangements with marketing agencies or consultants at this
time.
Audits or
reviews
The results of any audits or reviews of
Ore Reserve estimates.
There have not been no external audits ore reviews of the
2021 PFS.
The MRE, pit optimisation, design and schedule as developed
for the Beharra PFS were reviewed internallybySnowden.
Relative
accuracy/
confidence
Where appropriate a statement of the
relative accuracy and confidence level
in the Ore Reserve estimate using an
approach or procedure deemed
appropriate by the Competent Person.
For example, the application of
statistical or geostatistical procedures
to quantify the relative accuracy of the
reserve within stated confidence limits,
or, if such an approach is not deemed
appropriate, a qualitative discussion of
the factors which could affect the
relative accuracy and confidence of
the estimate.
The statement should specify whether it
relates to global or local estimates,
and, if local, state the relevant
tonnages, which should be relevant to
technical and economic evaluation.
Documentation should include
assumptions made and the procedures
used.
Accuracy and confidence discussions
should extend to specific discussions of
any applied Modifying Factors that
may have a material impact on Ore
Reserve viability, or for which there
are remaining areas of uncertainty at
the current study stage.
It is recognised that this may not be
possible or appropriate in all
circumstances. These statements of
relative accuracy and confidence of
the estimate should be compared with
production data,where available.
The capital cost estimates in this study relating to mining,
processing and cost performance are underpinned by a pre-
feasibility level study. The capital cost estimate has an
assessed accuracy of ±25% and complies with the AusIMM
Class 4 PFS criteria.

140

BEHARRA SILICA PROJECT PRE-FEASIBILITY STUDY

==> picture [85 x 27] intentionally omitted <==

12. COMPETENT PERSONS STATEMENTS

The information in this report that relates to the March 2020 exploration information for the Beharra Project is based on information compiled and fairly represented by Mr Colin Ross Hastings, who is a Member of the Australasian Institute of Mining and Metallurgy and a consultant to Perpetual. Mr Hastings is also a shareholder of Perpetual. Mr Hastings has sufficient experience relevant to the style of mineralisation and type of deposit under consideration, and to the activity which he has undertaken, to qualify as a Competent Person as defined in the 2012 Edition of the Joint Ore Reserves Committee (JORC) “Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves”. Mr Hastings consents to the inclusion in this report of the matters based on this information in the form and context in which it appears.

The information in this report that relates to the exploration information for the Beharra Project from September 2020 onwards is based on information compiled and fairly represented by Mr John Doepel, who is a Member of the Australasian Institute of Mining and Metallurgy and a consultant to Perpetual. Mr Doepel has sufficient experience relevant to the style of mineralisation and type of deposit under consideration, and to the activity which he has undertaken, to qualify as a Competent Person as defined in the 2012 Edition of the Joint Ore Reserves Committee (JORC) “Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves”. Mr Doepel consents to the inclusion in this report of the matters based on this information in the form and context in which it appears.

The information in this report that relates to Mineral Resources is based on information compiled by Ms Elizabeth Haren, a Competent Person who is a Member and Chartered Professional of the Australasian Institute of Mining and Metallurgy and a Member of the Australasian Institute of Geoscientists. Ms Haren is employed as an associate Principal Geologist by Snowden, who was engaged by Perpetual. Ms Haren has sufficient experience that is relevant to the style of mineralisation and type of deposit under consideration and to the activity being undertaken to qualify as a Competent Person as defined in the 2012 Edition of the “Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves”. Ms Haren consents to the inclusion in the report of the matters based on her information in the form and context in which it appears.

The information in this report that relates to Mineral Resources is based on information compiled by Dr Andrew Scogings, a Competent Person who is a Member of the Australasian Institute of Mining and Metallurgy, a Member of the Australian Institute of Geoscientists, and is a Registered Professional Geologist in Industrial Minerals. Dr Scogings is employed as an Associate Executive Consultant Geologist by Snowden. Dr Scogings has sufficient experience that is relevant to the style of mineralisation and type of deposit under consideration and to the activity being undertaken to qualify as a Competent Person as defined in the 2012 Edition of the “Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves”. Dr Scogings consents to the inclusion in the report of the matters based on his information in the form and context in which it appears.

The information in this report that relates to the Beharra Ore Reserve is based on information reviewed or work undertaken by Mr Frank Blanchfield, who is a Fellow of the Australasian Institute of Mining and Metallurgy. Mr Blanchfield is an employee of Snowden and has relied on Perpetual for marketing, environmental, permitting, and financial modelling and any costs not relating to mining and metallurgy. The mine design and mining costs and economic viability of the Project were assessed and completed by Snowden under his direction. Mr Blanchfield has sufficient experience relevant to the style of mineralisation and type of deposit under consideration and to the preparation of mining studies to qualify as a Competent Person as defined by the JORC Code (2012).

The information in this report that relates to process metallurgy is based on information reviewed and work completed by Mr Arno Kruger, who is a Member of the Australasian Institute of Mining and Metallurgy, a metallurgical consultant, and an employee of IHC Robbins. The metallurgical factors including process flowsheet design and costs and assumptions for the bulk aircore sample that relate to Mineral Resources have been reviewed and accepted by Mr Kruger. Mr Kruger has sufficient experience that is relevant to the type of processing under consideration and to the activity being undertaken to qualify as a Competent Person as defined by the JORC Code (2012).

BEHARRA SILICA PROJECT PRE-FEASIBILITY STUDY

141

==> picture [85 x 27] intentionally omitted <==

13. EMBEDDED OPPORTUNITIES AND OPTIONS

13.1 DRY MINING AND SLURRIFICATION UNIT (DMSU)

As part of the study investigation into various mining options the DMSU was compared to conventional truck and shovel. The DMSU enables the pulping of slurry in the mine pit where the slurried material is then pumped via pipeline back to the processing plant.

The cost savings are considerable as the pumping aspect largely removes the truck haulage component of the operation.

The unit proposed would be of skid design enabling it to be periodically moved around the pit floor. The ROM would be fed to the unit via FEL, and process water would be piped to the unit. The oversize (O/S) +1.0 mm material would be screened in pit and the remaining screen underflow is mixed in the transfer slurry bin and then pumped to the process plant.

With the very low O/S component between 2 tph and 3 tph, the +1.0 mm in-pit O/S could be either direct trammed or loaded into the reject haul truck using the FEL. Alternatively, the aperture size can be increased to further eliminate the quantity of O/S reporting to screen oversize.

Given the relatively low reject rate, a truck component was retained for the purposes of returning reject to the pit. This provides the added advantages of minimising water loss by returning a largely dewatered reject in lieu of the conventional field cyclone stacking option.

Truck reject deposition also minimises the work required to create the rehabilitation soil profile. At this point, truck and shovel costs have been incorporated in the operating cost estimate given its flexibility irrespective of higher operating cost. Investigation into the DMSU option will be taken early in the DFS works.

A cost comparison was conducted against truck and shovel on an optimum 800 m haul distance which demonstrated the delivery of ore via truck and shovel being $0.99c per tonne of ore vs the DMSU at $0.34c per tonne of ore.

Budget pricing received from IHCR for the DMSU as below, including an additional stage slurry pump unit, was circa A$1.5 million.

==> picture [426 x 166] intentionally omitted <==

Figure 13.1 DMSU as quoted by IHCR

A variety of design options are available as demonstrated in Figure 13.2 and Figure 13.3.

142

BEHARRA SILICA PROJECT PRE-FEASIBILITY STUDY

==> picture [85 x 27] intentionally omitted <==

==> picture [370 x 162] intentionally omitted <==

==> picture [206 x 8] intentionally omitted <==

----- Start of picture text -----

Figure 13.2 Alternative tracked containerised unit
----- End of picture text -----

==> picture [370 x 152] intentionally omitted <==

Figure 13.3 Alternative skid containerised unit

13.2 CAMPAIGN MINING

Pros: Potential reduction in cost due to economies of scale and potential to blend ore, if required.

Cons: Additional space required to stockpile ore and rejects and Increased mobilisation and demobilisation costs.

13.3 OTHER

If specific grade ranges are required mining will be required in multiple cells. This will increase the scheduling complexity and require stockpiling of additional waste and rejects as pit floors will not always be available (i.e. longer to expose floors).

There may be an opportunity to reduce mining costs by utilising an excavator instead of FELs although this would be at the expense of operational flexibility.

There is an opportunity to slurry the rejects back into the pit; however, this would need to be evaluated as it may require the wall angles to be reduced.

143

BEHARRA SILICA PROJECT PRE-FEASIBILITY STUDY

==> picture [85 x 27] intentionally omitted <==

14. FURTHER WORKS

14.1 GEOLOGY

Snowden makes the following recommendations to improve confidence in the geology model and product quality.

The in-situ PSD results from both drilling programs should be verified by umpire testing to assess any material

difference between wet and dry screening methods.

Twins 20B019 and 20B032 should be included for PSD testing at Nagrom and Diamantina, to compare with AC_16 and AC_38, respectively.

Additional (infill) samples from the March 2020 (if available) and September 2020 drilling programs should be tested for PSD to improve the understanding of trends through the deposit.

The Mineral Resource block model should be used, in conjunction with individual borehole data, to identify domains for further metallurgical testwork.

Metallurgical variability tests should be carried out per geological domain to assess the effect (if any) of subtle geochemical and PSD changes across and vertically through the deposit on processing and product characteristics.

Petrographic and/or microprobe analyses to be completed to determine deportment of Fe2O3 and Al2O3 contaminants.

14.2 METALLURGY

From the processing of the PFS bulk sample, two metallurgical programs will be progressed to assess possible enhanced projects outcomes.

The resource consists of two different lithologies being “yellow” and “white” sands with the yellow sand predominantly sighted in the top 1–4 m of the orebody and the white sand running from surface or below the yellow sand to the basement of the resource.

The test program will investigate the potential for a higher quality product from a white only lithology.

In the processing of the PFS bulk sample a large mass split was rejected at the wet gravity/spiral stage (i.e. 17.4%). In the knowledge gained in the downstream processing, it is believed that there is significant potential to reduce this loss and hence increase the yield to the final product with little or no deterioration to the product quality.

Variability testing to establish the link between the feed grades that vary from 97.0% to 99.0% SiO2 with yield and corresponding chemistry upgrades.

Assessments on PSDs for their effects on yield and chemistry upgrades/(downgrades)

14.3 LOGISTICS

Following on from the broad investigations carried out during the PFS, and given the significant apportioned operating cost that the final product transport component contributes, Perpetual intend to further pursue the following opportunities going forward to DFS:

  • Perpetual will develop more detailed road option scopes for the progression of civil/road engineering works to further define requirements and firm up costs associated with the Mount Adams Road–Brand Highway intersection and Mount Adams Road upgrade to RAV 7.3 Network standard

  • Investigate off site port storage alternatives and short haul solution by road

  • Investigate further the road and rail option including upgrade to Carson’s Road and development of road rail siding options

  • Progress discussion with both above and below rail providers in relation to rail transport, off port warehousing and rail to port solution

  • Continue interaction and progress various agreements with relevant stakeholders.

BEHARRA SILICA PROJECT PRE-FEASIBILITY STUDY

144

==> picture [85 x 27] intentionally omitted <==

- REPORT END -

BEHARRA SILICA PROJECT PRE-FEASIBILITY STUDY

145