ASX Announcement (ASX: OBM)

30 June 2020

Ora Banda Completes Davyhurst DFS and Outlines Regional Growth Strategy

DFS confirms strong returns for technically robust Davyhurst re-start

HIGHLIGHTS:

  • Ø DFS focussed on recommencement of operations at Ora Banda’s 100% owned Davyhurst Gold Project

  • Ø Significant existing infrastructure enables rapid and low-capex path to production

  • Ø 460,000-ounce Au Ore Reserve (6.1 Mt @ 2.4g/t Au), six deposits within 50 km of plant

  • Ø Production target of 418koz over initial 5-year mine life based on Probable Reserve

  • average of 81 koz / year with peak of 95 koz / year

  • Ø Life of mine C1 costs of A$1,427/oz

  • Ø Life of mine AISC of A$1,566/oz

  • Ø Average annual free cash flow of A$33.6M (pre-tax, at A$2,100/oz gold price)

  • Increases to A$68.8M (pre-tax, at A$2,550/oz gold price)

  • Ø Pre-tax undiscounted free cash flow of A$175M, pre-tax NPV6 of A$137M, and IRR of 109% (at A$2,100/oz gold price)

  • Pre-tax NPV6 increases to A$290M, with 237% IRR at A$2,550/oz gold price

  • Ø Carried forward tax losses of A$258M – increases free cash flow in the early years

  • Ø Pre-production capex of $45M, with short 14-month payback period

  • Payback period reduces to 7-months at A$2,550/oz gold price

  • Ø Mining scheduled to commence in Q4, CY2020, with first gold pour in Q1, CY2021, subject to completion of suitable financing arrangements during Q3, CY2020

  • Ø All major approvals and permits obtained or reasonably expected to be obtained

  • Ø Final phase development activities to commence immediately

  • Ø Strong underground Mineral Resources of 0.5 Moz Au (3.7 Mt @ 4.4 g/t Au) provides opportunity for mine-life extensions below open pit mine designs

  • Ø Exploration programs across the Company’s 1,350km[2] prospective landholding ongoing:

  • further resource definition drilling programs

  • follow-up drilling programs for near-mine prospects, including Riverina South

  • significant regional exploration program along 200km of prospective strike

Ora Banda Mining Limited (ASX: OBM) (“ Ora Banda ”, “ Company ”) is pleased to announce the results of the Definitive Feasibility Study (“ DFS ”) to re-start production at its Davyhurst Gold Project, located 120km north-west of Kalgoorlie within the Eastern Goldfields of Western Australia (“ Davyhurst ” or “ Project ”).

Page 1 of 65

ADDRESS Level 1, 2 Kings Park Rd, Perth WA 6005 POST PO Box 464, West Perth WA 6872 ABN 69 100 038 266 PHONE +61 8 6365 4548 PHONE (TOLL FREE) 1300 035 592 WEBSITE www.orabandamining.com.au ENQUIRES [email protected]

Underpinned by pre-existing infrastructure, including a conventional CIP process plant, the DFS confirms that Ora Banda can undertake a rapid and low-capital path to achieving sustainable gold production at Davyhurst.

Ore will be delivered to the process plant from a combination of open pit and underground mines all located within a 50km radius. The study demonstrates that the Project is expected to generate strong cash flows and financial returns over a 5.2-year mine life, with average estimated pre-tax annual free cash flows of A$33.6M (A$68.8M at A$2,550/oz), following a 7 to 14 month payback period, further leveraged by carried forward tax-losses of A$258M (as at 30 June 2019).

Development activities will start immediately and will focus on the final piece of refurbishment of the Davyhurst plant together with early works for mine development at both Riverina open pit and Golden Eagle underground mines. Plant commissioning is expected to commence in Q4, CY20 with first gold pour targeted for Q1, CY21.

In parallel, the Company will continue to undertake drilling programs across its highly prospective 1,350km[2] landholding, covering 200km of strike, focussing on:

  • regional targets, for which Ora Banda has already identified a number of high priority prospects;

  • follow up drilling programs on near-mine prospects, including Riverina South; and

  • • resource infill.

Managing Director Comment

Ora Banda Managing Director, David Quinlivan, said : “The completion of the DFS represents the culmination of an extensive 12-month work program focussed on a measured and value driven production restart at Davyhurst. The DFS confirms that the significant existing infrastructure will enable Ora Banda to pursue a rapid and low-capex path to production, with the first gold pour targeted for January 2021. The DFS also marks an important step in the Company’s evolution towards its ultimate objective of unlocking the significant value we believe is held in Ora Banda’s strategic and prospective landholding.”

Page 2 of 65

ADDRESS Level 1, 2 Kings Park Rd, Perth WA 6005 POST PO Box 464, West Perth WA 6872 ABN 69 100 038 266 PHONE +61 8 6365 4548 PHONE (TOLL FREE) 1300 035 592 WEBSITE www.orabandamining.com.au ENQUIRES [email protected]

Key DFS Outcomes

Reserves reported for Waihi and Callion

Ora Banda is pleased to declare a maiden JORC (2012) Probable Ore Reserve for Waihi open pit of:

Ø 1.5 Mt @ 2.3 g/t Au for 108Koz

Ora Banda is also pleased to declare a maiden JORC (2012) Probable Ore Reserve for Callion open pit of:

Ø 0.24 Mt @ 2.6 g/t Au for 21Koz

This brings the total JORC (2012) Probable Ore Reserves for the Davyhurst Project to:

Ø 6.1 Mt @ 2.4 g/t Au for 460Koz

A Riverina underground ore reserve is not included in this DFS as it requires more time to be finalised.

Strong Economic Returns

DFS estimates for the Project show a pre-tax, free cashflow of A$175M over a 5.2-year mine life using a A$2,100/oz gold price. Life of mine (LOM) average annual gold production is 81koz with low C1 cost of A$1,427/oz and all-in sustaining costs (“ AISC ”) of A$1,566/oz.

Metric
Unit Base Case Spot Case
Goldprice A$/oz 2,100 2,550
Goldproduced(LOM) Koz 418 418
Goldproduced(annual average – LOM) Koz/yr 81 81
Gold headgrade(LOM,Ore Reserve) g/t Au 2.4 2.4
Gold recovery (LOM) % 90.3 90.3
Pre-production capital cost(includingcontingencies) A$M 45.1 45.1
Projectpayback Months 14 7
All-in sustainingcosts(AISC) (LOM) A$/oz 1,566 1,578
Cash costs(C1) (LOM) A$/oz 1,427 1,427
Project free cashflow(pre-tax) A$M 174.6 357.8
Pre-tax NPV(6% discount rate) A$M 137.4 290.7
Post-tax NPV(6% discount rate) A$M 137.4 290.7
Pre-tax IRR % 109.3 237.8
Post-tax IRR % 109.3 237.8

Pre-production Capital Costs

Davyhurst benefits from substantial pre-existing infrastructure, including a 1.2 Mt/a processing plant, 172-person accommodation camp, extensive haul road network, mains power and licensed working process-water borefields, all of which are under a full care and maintenance program.

This infrastructure significantly reduces the capital required to re-commence production at Davyhurst which is set out below.

Page 3 of 65

ADDRESS Level 1, 2 Kings Park Rd, Perth WA 6005 POST PO Box 464, West Perth WA 6872 ABN 69 100 038 266 PHONE +61 8 6365 4548 PHONE (TOLL FREE) 1300 035 592 WEBSITE www.orabandamining.com.au ENQUIRES [email protected]

**A$M **
Processing plant – direct costs 8.7
Processing plant – indirect costs 2.6
Infrastructure (includes Tailings Storage Facility and road maintenance, site
accommodation)

10.4
First fills,spareparts 2.1
Development capital expenditure 23.8
Pre-production miningcosts 19.3
Pre-production capital costs 43.1
Contingency (processing plant & infrastructure) 2.0
Totalpre-production capital costs 45.1

LOM Operating Costs

Total (A$M) LOM LOM
(A$/t) (A$/oz)
Mining (includingroad haulage & ROM loading) 452 74.0 1,082
Processing 123 20.1 293
Site General & Administration 21 3.5 51
**Cash costs(C1) ** 596 97.6 1,427
Royalties(at A$2,100/oz) 22 3.6 53
Sustainingcapital 1 0.2 3
Corporate & exploration (including tenement rents, rates &
MiningRehabilitation Fund)

35
5.8 84
AISC 654 107.2 1,566

A centrally located 1.2mtpa process plant will be supplied by a combination of open pit and underground mines. The study assumes power will be supplied to site via an LNG fired power station built and operated under a BOO contract. Gas fired power costs are estimated at 0.197 c/kWh, whilst diesel cost prior to rebate and GST amounts to A$0.92/litre. All gold production from the Davyhurst Gold Project is subject to a State royalty and there are several minor third-party royalties applicable to some of the Project tenements. Royalty costs have been included where applicable.

Production Profile

Multiple production sources are expected to underpin a potential long-life mining operation at the Project, with six deposits contributing to the initial five-year mine plan, and which will be mined by a combination of conventional open pit and underground mining techniques.

The mine plan is based solely on Probable Ore Reserve contained within the six deposits as set out below.

Page 4 of 65

ADDRESS Level 1, 2 Kings Park Rd, Perth WA 6005 POST PO Box 464, West Perth WA 6872 ABN 69 100 038 266 PHONE +61 8 6365 4548 PHONE (TOLL FREE) 1300 035 592 WEBSITE www.orabandamining.com.au ENQUIRES [email protected]

Ore Grade Au
(kt) (Aug/t) (koz)
Riverina 1,400 1.8 81
Sand King 1,300 2.6 110
Missouri 1,500 2.6 130
Waihi 1,500 2.3 110
Callion 240 2.6 21
Total Open Pit 5,900 2.3 440
Golden Eagle 130 3.7 16
Total Underground 130 3.7 16
Total 6,100 2.4 460

Note: Refer to notes on Ore Reserve in Section 4.4 and Appendix 2 Section 4 of this announcement.

The ore production forecast is summarised below.

Mined
Ore(kt)
Mined
Ore(kt)
Processed Grade Gold Produced
AISC
Ore(kt) (Aug/t) (koz) (A$/oz)
Firstproduction to 30 June 2021 530 500 2.2 35 1,615
FY22 1,200 1,200 2.3 89 1,579
FY23 1,300 1,200 2.7 106 1,609
FY24 1,200 1,200 2.3 89 1,738
FY25 1,600 1,200 2.2 86 1,719
FY26(to end ofproject life) 35 810 2.2 56 860
Life of Mine 6,100 6,100 2.4 460 1,566

The values in the above table have been rounded.

The first phase of mining will involve the Riverina open pit and Golden Eagle underground. Mining of the five open pits and one underground area will be carried out in phases to optimise cash flow over the life of the project. The first phase of mining will involve the Riverina open pit and Golden Eagle underground.

Riverina open pit design showing mineralised lodes (looking north-east)

==> picture [346 x 198] intentionally omitted <==

Page 5 of 65

ADDRESS Level 1, 2 Kings Park Rd, Perth WA 6005 POST PO Box 464, West Perth WA 6872 ABN 69 100 038 266 PHONE +61 8 6365 4548 PHONE (TOLL FREE) 1300 035 592 WEBSITE www.orabandamining.com.au ENQUIRES [email protected]

Golden Eagle long section (looking east)

==> picture [483 x 232] intentionally omitted <==

Once the process plant is recommissioned and ramped up to full capacity, the second phase will involve mining of the Missouri and Sand King deposits.

Missouri open pit design showing mineralised lodes Looking north)

==> picture [425 x 290] intentionally omitted <==

Page 6 of 65

ADDRESS Level 1, 2 Kings Park Rd, Perth WA 6005 POST PO Box 464, West Perth WA 6872 ABN 69 100 038 266 PHONE +61 8 6365 4548 PHONE (TOLL FREE) 1300 035 592 WEBSITE www.orabandamining.com.au ENQUIRES [email protected]

Sand King open pit design showing mineralised lodes (looking north)

==> picture [487 x 315] intentionally omitted <==

Subsequent mining will then involve successive cutbacks at Riverina Stage 2, Waihi and Callion.

Waihi open pit design showing mineralised lodes (looking south)

==> picture [228 x 237] intentionally omitted <==

Callion open pit design showing mineralised lodes (looking north-east)

==> picture [252 x 234] intentionally omitted <==

Page 7 of 65

ADDRESS Level 1, 2 Kings Park Rd, Perth WA 6005 POST PO Box 464, West Perth WA 6872 ABN 69 100 038 266 PHONE +61 8 6365 4548 PHONE (TOLL FREE) 1300 035 592 WEBSITE www.orabandamining.com.au ENQUIRES [email protected]

Ore Production & Processing Schedules

==> picture [460 x 336] intentionally omitted <==

==> picture [462 x 299] intentionally omitted <==

Page 8 of 65

ADDRESS Level 1, 2 Kings Park Rd, Perth WA 6005 POST PO Box 464, West Perth WA 6872 ABN 69 100 038 266 PHONE +61 8 6365 4548 PHONE (TOLL FREE) 1300 035 592 WEBSITE www.orabandamining.com.au ENQUIRES [email protected]

Ore Production & Processing Schedules (Continued)

==> picture [487 x 309] intentionally omitted <==

==> picture [487 x 311] intentionally omitted <==

Page 9 of 65

ADDRESS Level 1, 2 Kings Park Rd, Perth WA 6005 POST PO Box 464, West Perth WA 6872 ABN 69 100 038 266 PHONE +61 8 6365 4548 PHONE (TOLL FREE) 1300 035 592 WEBSITE www.orabandamining.com.au ENQUIRES [email protected]

Permitting

All major approvals and permits have been obtained or are reasonably expected to be obtained in the next 2 months. Refer to Section 10 – Approvals on page 32 for further details.

Funding

Ora Banda’s Board has approved the immediate commencement of the first phase of development activities, which will be funded by the Company’s current cash reserves.

Ora Banda will consider financing the remaining pre-production capital and ongoing exploration costs via an equity capital raising of up to A$55 million, with the option of a stand-by debt facility. The Company is confident that the Project will be able to be financed on attractive terms given the relatively low capital requirement and expected short time frame to first production. Ora Banda has continued to advance discussions with interested financiers and has made good progress with significant preparation already underway for the formal financing process that is expected to be completed in Q3, CY20.

Next steps: Optimisation and contract negotiations

The company plans to continue optimising the DFS over the next several months with a view of refining its plans, including trade off studies and inclusion of the latest technical information. Preparations for a competitive tender process for contract mining is underway and is expected to be finalised by Q1 FY 2021. Discussions with GR Engineering in relation to the plant refurbishment are in final stages and expected to be concluded Q1 FY 2021.

Ongoing Exploration Programs

In parallel with the final phase of project development activities, Ora Banda will continue to undertake drilling programs across its highly strategic and prospective 1,350km[2] landholding covering 200km of strike.

Exploration activities will be undertaken in parallel across three key areas. The Davyhurst Gold Project (inclusive of Mt Ida) has a total mineral resource of 23.7 Mt @ 2.8 g/t Au for 2.1 Moz of contained gold. This includes underground mineral resources defined beneath existing open pits and these areas remain infill drilling targets. The Company intends to increase its regional exploration program, testing a number of prospective targets within its 1,350km[2] landholding.

Resource Definition and Upgrade

Ora Banda will continue to focus on infill drilling that seeks to upgrade existing resources.

Near Mine Prospects – Riverina South

Follow-up drilling is ongoing and will continue at near-mine prospects, including Riverina South that adjoins the southern end of the Riverina open pit.

Regional Exploration

Regional exploration programs are being planned for which Ora Banda already has identified several high priority targets, including well-defined but poorly tested prospect-scale gold occurrences. Whilst consolidation of the tenements comprising Ora Banda’s landholding occurred in 2007, no coherent

Page 10 of 65

ADDRESS Level 1, 2 Kings Park Rd, Perth WA 6005 POST PO Box 464, West Perth WA 6872 ABN 69 100 038 266 PHONE +61 8 6365 4548 PHONE (TOLL FREE) 1300 035 592 WEBSITE www.orabandamining.com.au ENQUIRES [email protected]

exploration effort has yet been undertaken across the area. Priority targets include Flame, Young Australian/Peach Tree, Missouri and Golden Eagle.

Additional Information

A summary of the key information material to the reported Ore Reserve and DFS production metrics is provided below and is followed by Appendix 2 (JORC Code 2012 Table 1 – Sections 1 to 4).

Page 11 of 65

ADDRESS Level 1, 2 Kings Park Rd, Perth WA 6005 POST PO Box 464, West Perth WA 6872 ABN 69 100 038 266 PHONE +61 8 6365 4548 PHONE (TOLL FREE) 1300 035 592 WEBSITE www.orabandamining.com.au ENQUIRES [email protected]

DEFINITIVE FEASIBILITY STUDY DETAILS

1 PROJECT DESCRIPTION

The Company is the owner of the Davyhurst Gold Project (“ Davyhurst Project ”) in the highly prospective, Tier 1 gold mining province of Eastern Goldfields in Western Australia. The Davyhurst Project (inclusive of Mt Ida) has a total Mineral Resource of 23.7 Mt at a grade of 2.8 grams per tonne gold for 2.1 million ounces of contained gold and hosts many other highly prospective exploration and gold development targets.

The Davyhurst Project is located 120 km northwest of the major gold mining hub of Kalgoorlie in Western Australia and comprises 111 granted individual mining tenements covering a combined area of 1,350 km[2] . These tenements extend for more than 200 strike kilometres from north to south along the highly prospective Mt Ida Fault and Zuleika Shear system. Substantial infrastructure including a 1.2 Mt/a processing plant, 172 person camp, extensive road network, mains power and licensed working borefields exist at Davyhurst and these facilities are currently being preserved on a full care and maintenance program.

The various ore deposits that will feed the Davyhurst Processing Plant have estimated Ore Reserves of 6.1 million tonnes of ore grading 2.4 grams per tonne for 460,000 ounces of contained gold providing over five years of mine life. Mining will be undertaken by both conventional open cut and underground methods. The primary underground mining method will be sub-level open stoping using up-hole benching.

Figure 1 - Davyhurst Project Location Map Highlighting Key Development Projects

==> picture [488 x 298] intentionally omitted <==

Page 12 of 65

ADDRESS Level 1, 2 Kings Park Rd, Perth WA 6005 POST PO Box 464, West Perth WA 6872 ABN 69 100 038 266 PHONE +61 8 6365 4548 PHONE (TOLL FREE) 1300 035 592 WEBSITE www.orabandamining.com.au ENQUIRES [email protected]

Average annual mine production of 1.2 Mt/a is expected to be achieved in April 2021 following a three month ramp up period. Ore will be trucked via a combination of private and public Level 4 – RAV’s (Categories 9-10) rated haul roads from the five mine sites to a central 1.2 Mt/a processing facility located at Davyhurst. A conventional gold three stage crushing circuit followed by a Carbon in Pulp (“CIP”) processing plant will produce gold doré bars. Metallurgical testwork has shown that overall gold recovery will be 90.3%. Gold doré bars will be transported to the Perth Mint for refining and sale.

The operation will run 24 hours a day and be manned by a workforce that will work 12 hours per day on a range of roster schedules. Accommodation will be provided on site in the accommodation village.

This DFS demonstrates optimised cash flows by scheduling production from six distinct mining operations, namely, Riverina, Missouri, Sand King, Waihi and Callion open pits and the Golden Eagle underground. The location of these operations is shown in Figure 1 above.

The mine design physicals and associated costs for these mines feed into individual mine models. The outputs from each mining model then form part of an integrated mining and processing plan to optimise mining and processing schedules to deliver annual average throughput of 1.2 Mt/a.

The DFS has adopted a contractor model for mining costs. The contractor model has lower capital intensity for a 5-year operation than an owner-mining model and was selected as the most efficient and lowest risk operational approach.

2 PROJECT TEAM

This DFS has been prepared jointly by OBM and GR Engineering Services Ltd ( GRES ) with other parties undertaking respective workstreams.

3 GEOLOGY AND MINERAL RESOURCES

3.1 Geology

Ora Banda has undertaken extensive resource development activities over the last 12 months on five advanced projects, namely Riverina, Waihi, Siberia (includes Sand King & Missouri deposits), Callion and Golden Eagle. This includes over 37,000 metres of resource definition drilling and other associated technical (metallurgical & geotechnical) drilling.

The Davyhurst-Mt Ida project area is located on the western branch of the Norseman-Wiluna Belt. The project straddles the boundary between the Kalgoorlie Terrane (~2.7Ga) of the Eastern Goldfields Province and the Barlee Domain (~3.0Ga) of the Southern Cross Province. The boundary between the provinces is defined by the crustal-scale Ida Lineament, a deep, mantle tapping crustal structure that trends north to NNW and dips steeply to the east. The project also includes portions of the Zuleika Shear which separates the Coolgardie and Ora Banda Domains within the Kalgoorlie Terrane.

The Barlee Domain, to the west of the Ida Lineament, comprises a sequence of banded iron formation (“BIF”), shale, chert, and basalt, all poorly outcropping against basement granites. These lower units are overlain by a thick monotonous sequence of tholeiitic basalt to the east to the Ida Lineament.

Page 13 of 65

ADDRESS Level 1, 2 Kings Park Rd, Perth WA 6005 POST PO Box 464, West Perth WA 6872 ABN 69 100 038 266 PHONE +61 8 6365 4548 PHONE (TOLL FREE) 1300 035 592 WEBSITE www.orabandamining.com.au ENQUIRES [email protected]

The Ida Lineament is a poorly defined structure but is commonly interpreted to be along the western contact of the western most ultramafic unit as defined by aeromagnetics. East of the Ida Lineament, greenstones of the Coolgardie and Ora Banda Domains consist of sedimentary and felsic volcanoclastic rocks to the west, and mafic to ultramafic volcanic and felsic rocks to the east. The project is generally bounded by basement granite and gneiss terrane. Internal to the greenstone belt, there are several granite intrusions of various ages. The most prominent of these granites is the Ularring Granite, located midway between the Davyhurst and Riverina area.

There are two alteration events observed, an initial pervasive greenschist to lower amphibolite alteration event related to metamorphism, and a later hydrothermal alteration event related to shearing. The shears have acted as conduits to hydrothermal fluids causing localised alteration and gold mineralisation. Host lithologies include extrusive and intrusive mafic to ultramafic rocks, finegrained sedimentary rocks and felsic volcanic and volcaniclastic rocks. Alteration associated with gold mineralisation is commonly an assemblage of minerals namely biotite-carbonate-feldsparpyrrhotite-pyrite. The mineralisation is within distinctive alteration haloes, generally around quartz vein arrays. Thickness of the alteration zones varies from centimetres to several metres. A sharp transition is evident between altered, mineralised basalt and unaltered, unmineralised basalt (Missouri and Sand King). A more gradational contact between mineralisation and barren host rocks is evident at the other deposits (Riverina, Waihi, Callion and Golden Eagle).

Weathering effects are highly variable, extending to shallow depths at Waihi (<5 m) to average depths of 40 m to 50 m at Riverina. Generally, the Davyhurst weathering profile can be considered shallow. Weathering effects have resulted in apparent re-mobilisation of gold in some deposits. At times gold depletion in highly oxidised areas can be observed along with zones of potential supergene gold enrichment, generally toward the base of oxidation.

3.2 Mineral Resources

All Mineral Resource Estimates undertaken by OBM have been classified and reported in accordance with the 2012 Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves (2012 JORC Code) and is summarised in Table 3.1 with further details provided in Appendix 1.

The open pit in situ Mineral Resources for each deposit, except Callion, are reported from the Localised Uniform Conditioning ( LUC ) models at a 0.5 g/t cut-off and above an optimised shell based on assumed recoveries, costs and a gold price of A$2,400 per ounce. The Callion deposit is reported from the OK model at a 0.5 g/t cut-off and above an optimised shell based on assumed recoveries, costs and a gold price of A$2,400 per ounce. Pit shells have been used as the limiting basis for reasonable expectations of the estimated blocks being a viable open pit option at some time in the future. The 0.5 g/t cut-off grade is considered a realistic figure based on generalised current open pit mining and processing costs. All blocks outside the pit shell are reported from the kriged block models at a 2 g/t cut-off to represent potential extraction by underground mining methods. The underground portion of the resources is not reported from the LUC models as the SMU block size implies a mining selectivity that could not be achieved by underground mining methods. The reported blocks in each Mineral Resource Estimate ( MRE ) have been limited to those within the optimised shell, above 0.5 g/t and below the optimised shell, above 2 g/t. Mineral Resources included in the DFS are reported in Table 3.1.

Page 14 of 65

ADDRESS Level 1, 2 Kings Park Rd, Perth WA 6005 POST PO Box 464, West Perth WA 6872 ABN 69 100 038 266 PHONE +61 8 6365 4548 PHONE (TOLL FREE) 1300 035 592 WEBSITE www.orabandamining.com.au ENQUIRES [email protected]

LUC resource estimates were completed by OBM with specialised geostatistical guidance and support from mining industry consultants, CSA Global Pty Ltd ( CSA ). OBM defined the parameters required for Ordinary Kriged ( OK ) estimates, including domain selection, gold assay composites and estimation parameters. OBM provided CSA with the input composites, OK block models for both the panel/parent and SMU scale estimates, and all adopted estimation parameters and domaining selections. This ensured that the same parameters could be carried through to generate valid LUC estimates for each of the deposits. LUC estimates are conditioned to the OK panel estimates, preserving the metal content.

Golden Eagle was estimated using Ordinary Kriging, with parameters suited to underground mining.

Table 3.1: Mineral Resources Included in the DFS

DEPOSIT RESOURCE
MODEL
CUT-OFF
GRADE
('000t)
(g/t Au)

MEASURED
('000t)
(g/t Au)

MEASURED
INDICATED INDICATED INFERRED INFERRED ('000t)
(g/t Au)
('000oz.)
TOTAL MATERIAL
('000t)
(g/t Au)
('000oz.)
TOTAL MATERIAL
('000t)
(g/t Au)
('000oz.)
TOTAL MATERIAL
(g/t Au) ('000t) (g/t Au) ('000t) (g/t Au) ('000t) (g/t Au)
RIVERINA
Open Pit
LUC 0.5 116 1.8 2,694 1.8 183 3.0 2,993 1.9 183
Underground OK 2.0 226 5.7 502 6.1 728 5.9 139
TOTAL 116 1.8 2,920 2.1 685 5.3 3,721 2.7
322
WAIHI
Open Pit
LUC 0.5 1,948 2.4 131 2.9 2,079 2.4 159
Underground OK 2.0 188 3.7 195 4.0 383 3.8 47
TOTAL 2,136 2.5 326 3.5 2,462 2.6 206
SAND KING
Open Pit
LUC 0.5 1,252 3.4 128 3.3 1,380 3.4 150
Underground OK 2.0 438 3.7 698 3.8 1,136 3.7 136
TOTAL 1,690 3.5 826 3.7 2,516 3.5 286
MISSOURI
Open Pit
LUC 0.5 1,460 3.4 17 3.5 1,477 3.4 160
Underground OK 2.0 364 3.4 258 3.4 622 3.4 68
TOTAL 1,824 3.4 275 3.4 2,099 3.4 227
GOLDEN EAGLE
Underground
OK 2.0 247 4.1 146 3.4 393 3.9 49
CALLION
Open Pit
OK 0.5 241 3.7 28 1.6 269 3.5 30
Underground OK 2.0 255 6.0 156 5.5 411 5.8 77
TOTAL 496
4.9
184
4.9
680
4.9
107
RESOURCE TOTALS 116 1.8 9,313 2.9 2,442 4.1 11,871 3.1 1,198

Notes

  1. Missouri, Sand King, Riverina, Waihi, Callion & Golden Eagle Mineral Resources have been updated in accordance with all relevant aspects of the JORC code 2012, and initially released to the market on 15 December 2016 & 26 May 2020 (Missouri), 3 January 2017 & 26 May 2020 (Sand King), 2 December 2019, 26 May 2020 & 4 June 2020 (Riverina), 4 February 2020 (Waihi), 15 May 2020 & 29 June 2020 (Callion) & 8 April 2020 (Golden Eagle).

  2. The Riverina, Waihi, Sand King, Missouri and Callion Open Pit Mineral Resource Estimates are reported within a A$2,400/oz pit shell above 0.5g/t. The Riverina, Waihi, Sand King, Missouri, Callion and Golden Eagle Underground Mineral Resource Estimates are reported from material outside a A$2,400 pit shell and above 2.0 g/t.

  3. Mineral Resources quoted are inclusive of Ore Reserves

  4. The values in the above table have been rounded.

4 MINING AND ORE RESERVES

The feasibility study evaluated six individual mining locations: five open pits and one underground. The evaluation was based on the convertible Mineral Resources described in Section 3. The study considered technical and operational aspects of each as well as project specific costing sourced from the industry within the last six months. A mine plan was developed considering operational readiness of the various sites and the ability to deliver a strong cash flow.

Page 15 of 65

ADDRESS Level 1, 2 Kings Park Rd, Perth WA 6005 POST PO Box 464, West Perth WA 6872 ABN 69 100 038 266 PHONE +61 8 6365 4548 PHONE (TOLL FREE) 1300 035 592 WEBSITE www.orabandamining.com.au ENQUIRES [email protected]

4.1 Open Pit

4.1.1 Mining Method

All open pits within the Davyhurst Gold Project will be mined using selective mining techniques. The alteration associated with the gold mineralisation is visually identifiable, facilitating the enabling the proposed method to be adopted.

The mining fleet will comprise, top-hammer blast hole drills, 120 t or 200 t class excavators and 90 to 100 t class rigid body dump trucks, as well as supporting ancillary fleet. This size and type of equipment is commonly used by owners and contractors alike throughout the Western Australian goldfields. All pits will be drilled and blasted on 5 m benches, with the excavators operating on the full bench height of 5 m in waste and nominal flitch heights of 2.5 m in ore. Ore will be hauled from the pit to a designated Mine-Ore-Pad (“MOP”) stockpile adjacent to each pit. From here, road trains will transport the ore to the Run-of-Mine (“ROM”) pad adjacent to the Davyhurst processing plant.

Underground voids exist within the proximity of the Riverina and Callion open pits. An effective voids management plan will be developed to safely manage mining through these areas. Surveying and probe drilling will be used to properly locate the voids and they will be backfilled from a safe location prior to mining.

Waihi requires tailings to be re-mined. It is proposed that this material will be mined conventionally with consideration given to the trafficability of tails. The excavated material will be co-disposed on surface with waste rock mined concurrently from the pit. The tailings management plan is still under development and is still to be approved by government regulators.

Mining Department personnel will consist of management, technical staff and operations with a mix of both local and FIFO personnel. Within the first 12 months the total mining workforce will ramp up to around 130 persons onsite at any time including contractors, increasing to a peak of around 140 later in the project. The number of personnel will vary depending on the mining phase.

Mine office and workshop facilities will be provided by the contractor for the mining operation at each location together with fuel storage and wash down facilities.

4.1.2 Dilution Modelling

For Riverina, Missouri, Sand King and Waihi, modifying factors for the open pits were determined using the LUC Mineral Resource models described in Section 3. The SMU blocks within the models have a width of 2.0 m, strike length of 5.0 m and vertical extent of 2.5 m. The visual nature of the mineralisation lends itself to selective mining thereby allowing separation of waste from ore at the contact, resulting in lower dilution and loss factors when estimating the Ore Reserve. This selectivity is not reflected in the diluted LUC grade of the resource model’s SMU; hence, mining dilution was modelled by factoring the grade for a dilution skin reflective of the proposed mining method. Based on lode boundary analysis conducted during preparation of the MRE, SMU block grades were factored down to allow for dilution thickness based on the “hardness” of their boundaries. Dilution skins of approximately 0.5 m were applied at Missouri and Sand King and 0.25 m at Riverina, Waihi and Callion, owing to their softer boundary condition and the dilution inherent in the lode wireframe. Dilution factors were determined using the unconstrained global resource to approximate the effective required dilution skin. This approach accounts for the greater selectivity that can be achieved by optimising the digging orientation to the ore blocks. The technique accounts for dilution

Page 16 of 65

ADDRESS Level 1, 2 Kings Park Rd, Perth WA 6005 POST PO Box 464, West Perth WA 6872 ABN 69 100 038 266 PHONE +61 8 6365 4548 PHONE (TOLL FREE) 1300 035 592 WEBSITE www.orabandamining.com.au ENQUIRES [email protected]

at a localised scale and the resultant model was used as a diluted model in the pit optimisation analysis.

For Callion, the modifying factors were estimated using an Ordinary Kriged Mineral Resource model. The model was sub-celled to conform to the mineralisation wireframe. Dilution for the Callion pit optimisation was modelled using the expanded wireframe technique. The wireframes were expanded by 0.3 m in all directions. Each block in the model was coded with a proportion inside the expanded wireframes. The diluted grade was determined by reporting the average grade of each lode in increments of 2.5 mN by 2.5 mRL for the full width of the lode. These diluted grades were then written into the model for use in the pit optimisation.

The equivalent global dilution within each of the pits is given in Table 4.1.

Table 4.1: Global Dilution

Deposit Global Dilution
Riverina 25%
Sand King 34%
Missouri 50%
Waihi 14%
Callion 27%

4.1.3 Cut-off Grade

The open pit Ore Reserve was estimated within the mining envelope using incremental cut-off grades determined for each weathering domain for each deposit. The cut-off grades ranged from 0.54 to 0.69 g/t Au depending on location and domain. These cut-offs were applied to diluted grades within the pit design envelope. A summary of the cut-off grade and inputs are given in Table 4.2.

Table 4.2: Parameters used to derive cut-off grades for the open pit mines

Deposit
Domain
Gold Price Royalties & Smelter
Charges
Process Recovery Grade control Ore haulage Crusher loading Processing cost Site G&A and Third
Party Royalty
Total Incremental
Cost
Cut-off grade
A$/oz A$/oz % **A$/t ** **A$/t ** **A$/t ** **A$/t ** **A$/t ** **A$/t ** **g/t **
Riverina
Oxide
Trans
Fresh
2100 $44.55 95% $0.93 $9.27 $1.17 $24.92 $5.17 $41.46 0.66
2100 $44.55 95% $0.98 $8.98 $1.14 $24.92 $5.17 $41.19 0.66
2100 $44.55 95% $1.66 $8.80 $1.11 $24.92 $5.17 $41.65 0.66
Sand King
Oxide
Trans
Fresh
2100 $44.55 94% $0.93 $7.55 $1.17 $23.80 $5.37 $38.82 0.62
2100 $44.55 92% $1.12 $7.31 $1.14 $23.80 $5.37 $38.74 0.64
2100 $44.55 85% $1.18 $7.16 $1.11 $23.80 $5.37 $38.62 0.69
Missouri
Oxide
Trans
Fresh
2100 $44.55 94% $0.63 $7.55 $1.17 $23.80 $5.37 $38.52 0.62
2100 $44.55 92% $0.76 $7.31 $1.14 $23.80 $5.37 $38.38 0.63
2100 $44.55 92% $1.27 $7.16 $1.11 $23.80 $5.37 $38.71 0.63
Waihi
Oxide
Trans
Fresh
2100 $44.55 94% $0.93 $2.28 $1.17 $23.80 $5.37 $33.55 0.54
2100 $44.55 92% $0.98 $2.21 $1.14 $23.80 $5.37 $33.50 0.55
2100 $44.55 90% $1.66 $2.16 $1.11 $23.80 $5.37 $34.10 0.57
Callion
Oxide
Trans
Fresh
2100 $44.55 91% $0.93 $3.95 $1.17 $23.39 $5.57 $35.01 0.58
2100 $44.55 91% $0.98 $3.83 $1.14 $23.39 $5.57 $34.91 0.58
2100 $44.55 90% $1.66 $3.75 $1.11 $23.39 $5.57 $35.48 0.60

Page 17 of 65

ADDRESS Level 1, 2 Kings Park Rd, Perth WA 6005 POST PO Box 464, West Perth WA 6872 ABN 69 100 038 266 PHONE +61 8 6365 4548 PHONE (TOLL FREE) 1300 035 592 WEBSITE www.orabandamining.com.au ENQUIRES [email protected]

4.1.4 Pit Optimisation

Pit optimisations were performed on each of the deposits to determine approximate economic mining envelopes. Geovia Whittle software was used to determine pit limits by applying economic and operational modifying factors to the diluted Mineral Resource models and standard LerchsGrossman techniques.

Pit slope parameters were derived from geotechnical analysis following site investigation, review, and logging of core. Parameters were provided for each of the weathering domains at each of the deposits (i.e. oxide, transition and fresh). Sand King slope parameters also included provision for the ultramafic domain located in the northeast region of the pit. Where the excavation encroached on waste landforms stable slope parameters were used as a maximum. Adjustments were made to the pit slope angles to allow for in-pit ramps based on the fleet described in Section 4.1.1. Double lane ramp widths of 25 m and single lane ramp widths of 15 m were allowed for in the base of the pit. The pit slope parameters applied in the optimisation are given in Table 4.3.

Table 4.3: Pit Slope Parameters

Deposit N E S W
Riverina Oxide
Trans
Fresh
37.8 37.8 37.8 34.8
43.7 35 43.7 43.7
52.5 52.5 52.5 40.6
Sand King Oxide
Trans
Fresh
37.8 37.8 20.2 37.8
45.2 45.2 30.8 36.9
56.3 54.3 47 41.8
Sand King - Ultramafic Oxide
Trans
Fresh
WLF
37.8 37.8 37.8 37.8
40.9 40.9 40.9 40.9
48.8 48.8 48.8 48.8
26.6 26.6 26.6 26.6
Missouri Oxide
Trans
Fresh
WLF
18.3 42.1 42.1 42.1
30.8 45.2 45.2 35.5
51.4 48.4 44.4 44.4
14.9 14.9 14.9 14.9
Waihi Oxide
Trans
Fresh
WLF
32.6 32.6 32.6 32.6
35.3 35.3 35.3 35.3
46.0 46.0 46.0 46.0
14.9 14.9 14.9 14.9
Callion Oxide
Trans
Fresh
WLF
29.7 37.8 34.8 37.8
33.7 43.7 40.3 43.7
40.6 52.5 45.2 52.5
21.9 21.9 21.9 21.9

A nominal mining recovery of 95% was applied (5% ore loss) in the optimisation. Mining dilution was inherent in the model, using the skin dilution methods described above

Mining costs were derived from contractor-supplied pricing for a scope specific to the project. The scope included drill, blast, load and haul as well as provision for waste landform rehabilitation. Cost regressions were derived from the cost profiles provided by the contractors and applied in the model on and incremental cost by depth basis. The costs also included provision for the OBM mining team overheads.

The average mining costs for the selected pit shells, including rehabilitation, are given in Table 4.4.

Page 18 of 65

ADDRESS Level 1, 2 Kings Park Rd, Perth WA 6005 POST PO Box 464, West Perth WA 6872 ABN 69 100 038 266 PHONE +61 8 6365 4548 PHONE (TOLL FREE) 1300 035 592 WEBSITE www.orabandamining.com.au ENQUIRES [email protected]

Table 4.4: Average mining cost

Deposit Ave Mining Cost($/t)
Riverina $4.37
Sand King $4.56
Missouri $5.06
Waihi $4.44
Callion $3.86

Ore haulage costs were derived from contractor budget pricing received in 2020 for a scope of work specific to the project. These costs are stated in Table 4.2.

Processing costs were based on preliminary estimates by GR Engineering Pty Ltd. These costs are stated in Table 4.2.

General and Administration costs were based on a preliminary estimate approved by OBM senior management. These costs are stated in Table 4.2.

State Royalties and smelter charges were allowed for as selling costs. These costs are stated in Table 4.2.

Processing recoveries were based on available test work or assumptions provided by OBM’s metallurgical consultant, based on values consistent with typical industry values. These recoveries are stated in Table 4.2.

Pit shells were adjusted for a minimum mining width of 20 m to allow safe working room around the existing pit excavations and pit floors. Pit shells were selected based on maximum NPV following consideration of all the above factors and contemplated mining on a single stage basis. Where pit staging was proposed the pit shell selection considered maximum cash flow.

4.1.5 Pit Design

From the pit shells, practical mining shapes were developed and formed the basis of the Ore Reserve estimate. The pit designs observed the preliminary slope parameters used in the pit optimisation. Double and single lane ramps were located to provide practical access to the lower levels of the pit by the contractor’s fleet.

Minimum mining bench widths of 20 m were allowed for on all walls mined adjacent to existing excavations. Final drop cuts were designed at 15 m minimum mining width and “good-bye” cuts allowed for at the base of each pit to a depth of 5 m. The pit inventories reconciled to within 12% or less of the pit shells.

The designs developed for the feasibility study are shown in Figure 4.1.

Page 19 of 65

ADDRESS Level 1, 2 Kings Park Rd, Perth WA 6005 POST PO Box 464, West Perth WA 6872 ABN 69 100 038 266 PHONE +61 8 6365 4548 PHONE (TOLL FREE) 1300 035 592 WEBSITE www.orabandamining.com.au ENQUIRES [email protected]

Figure 4.1: Feasibility Ultimate Pit Designs

==> picture [488 x 496] intentionally omitted <==

----- Start of picture text -----

Riverina Missouri
Sand King Waihi
Callion
----- End of picture text -----

4.1.6 Waste Landforms

Approximately 79 Mt of the waste material will be generated during open pit and underground mining operations. Whilst some of this material will be used in general construction of facilities such as MOP pads, haul roads and abandonment bunding, the remaining waste will be placed in surface waste landforms. These will be constructed progressively as the project develops. Prior to their construction, the footprint of the landforms will be cleared and topsoil removed. The topsoil will be either placed directly onto available waste landforms that have reached their final design formation or stockpiled for use in later rehabilitation.

Page 20 of 65

ADDRESS Level 1, 2 Kings Park Rd, Perth WA 6005 POST PO Box 464, West Perth WA 6872 ABN 69 100 038 266 PHONE +61 8 6365 4548 PHONE (TOLL FREE) 1300 035 592 WEBSITE www.orabandamining.com.au ENQUIRES [email protected]

4.2 Underground

4.2.1 Mining Method

Golden Eagle is a brownfields project. The mining method proposed for Golden Eagle is narrow-vein long hole open stoping using up-hole-benching techniques. This method has been successfully used at Golden Eagle in the past.

Capital and ore drive development will be mined using a conventional mining fleet and ore mining will be directly supervised by OBM personnel. An underground contractor will provide the mining fleet that includes a twin boom jumbo, 50 t dump truck(s) and an appropriately sized underground loader. Stope production will use 64 mm diameter blast holes and conventional explosives and blasting techniques.

4.2.2 Dilution Modelling

Modifying factors were applied to the underground Mineral Resource to estimate the Ore Reserve for Golden Eagle. Stope optimisation techniques were performed on the resource model using a minimum practical stope width of 0.7 m and a 0.3 m unplanned dilution skin applied to both the hanging wall and footwall. Only indicated Mineral Resources were contemplated. A nominal provision for unplanned dilution of 5% was also included as a contingency. The global dilution was estimated to be 34%. A nominal ore loss factor of 5% was also applied.

4.2.3 Cut-off Grade

The cut-off grade was estimated using contractor pricing provided in April 2020, based on a preliminary scope of work.

The Ore Reserve was estimated using a stope cut-off grade of 2.7 g/t Au. The cut-off grade allows for all stope activities including drill, blast, load and haul, as well as the downstream costs such as ore haulage, processing, selling costs and smelter charges.

It also includes provision for ore drive development and slotting for stope establishment. In addition, an incremental cut-off grade of 0.7 g/t Au was applied to ore drive development on a cut by cut basis. Parameters for the cut-off grade estimate are given in Table 4.5.

Table 4.5: Golden Eagle cut-off grade parameters

Parameter Units Cut-off Value
Development and stoping A$/t 118.22
Mine overheads A$/t 13.33
Haulage,processingand site G&A A$/t 34.55
Total unit costs A$/t 166.1
Gold Price A$/oz 2,100
Process Recovery % 92
Smelter Charge A$/t 0.48
Transport and security A$/t 2.09
Royalties % 2.5
Cut-off Grade g/t 2.7

Stope optimisation of the Indicated Mineral Resource was used to determine practical mining shapes. These shapes were used to develop a mine layout. After completing the design, each level was

Page 21 of 65

ADDRESS Level 1, 2 Kings Park Rd, Perth WA 6005 POST PO Box 464, West Perth WA 6872 ABN 69 100 038 266 PHONE +61 8 6365 4548 PHONE (TOLL FREE) 1300 035 592 WEBSITE www.orabandamining.com.au ENQUIRES [email protected]

evaluated to ensure it was above the breakeven cost including all capital development and associated infrastructure.

4.2.4 Underground Design

The Golden Eagle underground will extend the existing workings to undeveloped stoping areas. In addition to ore drives and stopes, provision was made for declines, ventilation drives, stockpiles, return airways and escapeways.

Given the ground conditions at Golden Eagle, all existing excavations are expected to be reused following a programme of re-support where required. The orebody was previously accessed at 20 m level intervals, resulting in 15 m pillars between sub-levels. Future planned stopes will be mined using the same underhand sub-level open stoping method employed previously. Pillars will be left at designated intervals to maintain void stability.

A Ground Control Management Plan (GCMP) was developed, during previous mining activities, by an independent geotechnical consultant. Recommendations from the GCMP were adopted in the mine design.

The design extends the existing workings to as yet undeveloped stoping areas. In addition to ore drives and stopes, provision was made for declines, ventilation drives, stockpiles, return airways and escapeways. The proposed Golden Eagle underground layout is shown in Figure 4.2.

Figure 4.2: Golden Eagle underground layout

==> picture [483 x 232] intentionally omitted <==

Page 22 of 65

ADDRESS Level 1, 2 Kings Park Rd, Perth WA 6005 POST PO Box 464, West Perth WA 6872 ABN 69 100 038 266 PHONE +61 8 6365 4548 PHONE (TOLL FREE) 1300 035 592 WEBSITE www.orabandamining.com.au ENQUIRES [email protected]

4.3 Mining Schedule

A summary of key physical metrics for the Davyhurst Project, by mining location, is set out in Table 4.6.

Table 4.6: Key Physical Metrics by Location[1 ]

Key Physical Metrics by Location1
Location Waste Strip Ratio Ore Grade (Au) Gold
(Mt) (w:o) (kt) (g/t) (koz)
Open Pit
Riverina 13.3 9:1 1,400 1.8 81
Sand King 19.9 16:1 1,300 2.6 110
Missouri 16.7 11:1 1,500 2.6 130
Waihi 24.1 16:1 1,500 2.3 110
Callion 5.1 21:1 240 2.6 21
Total – Open Pit 79.0 13:1 5,940 2.3 445
Underground
Golden Eagle - 130 3.8 16
Total – Underground 0 130 3.8 16
Total 79.0 6,100 2.4 460
  1. The table contains rounding adjustments to two significant figures and does not total exactly.

Based on the values in Table 4.6, an integrated mine schedule was developed to demonstrate the required production rate can be achieved to maintain feed to the process plant. Stockpiling low grade and high-grade ore was also modelled to optimise the grade processed to improve early cash flow.

The open pits were notionally scheduled using typical mining productivities consistent with the West Australian mining industry. Consideration was also given to operational constraints such as vertical advance of the pit floor and operating area. The schedule was then resource levelled based on expected excavator fleet capacity.

The underground schedule considered development and stoping activities using interlinked logic constraints and typical mining productivities consistent with the West Australian mining industry. The schedule was resource levelled for underground fleet capacities.

The scheduled developed contemplates mining of the five main open pits and one underground area being carried out in phases to optimise cash flow over the life of the project. The first phase will involve mining the Riverina open pit and Golden Eagle underground. Once the process plant is recommissioned and has ramped up to full capacity, the next phase will be implemented which involves mining of Missouri and Sand King. This will be followed in turn by successive cutbacks in the Riverina Stage 2, Waihi and Callion open pits.

Ore will be mined at a sufficient rate to supply ore to the 1.2 Mt/a plant over a 5.2-year project life. Lower grade material will be stockpiled initially to enable high grade ore to be processed as soon as possible. This will facilitate higher cash flows in the early phases of the project.

The total material movement, processing and stockpiling schedules for the project is given in Figure 4.3, Figure 4.4 and Figure 4.5 respectively.

Page 23 of 65

ADDRESS Level 1, 2 Kings Park Rd, Perth WA 6005 POST PO Box 464, West Perth WA 6872 ABN 69 100 038 266 PHONE +61 8 6365 4548 PHONE (TOLL FREE) 1300 035 592 WEBSITE www.orabandamining.com.au ENQUIRES [email protected]

Figure 4.3: Total Material Movement Schedule

==> picture [426 x 310] intentionally omitted <==

Figure 4.4: Ore Processing Schedule

==> picture [426 x 310] intentionally omitted <==

Page 24 of 65

ADDRESS Level 1, 2 Kings Park Rd, Perth WA 6005 POST PO Box 464, West Perth WA 6872 ABN 69 100 038 266 PHONE +61 8 6365 4548 PHONE (TOLL FREE) 1300 035 592 WEBSITE www.orabandamining.com.au ENQUIRES [email protected]

Figure 4.5: Stockpiling Schedule

==> picture [426 x 310] intentionally omitted <==

Page 25 of 65

ADDRESS Level 1, 2 Kings Park Rd, Perth WA 6005 POST PO Box 464, West Perth WA 6872 ABN 69 100 038 266 PHONE +61 8 6365 4548 PHONE (TOLL FREE) 1300 035 592 WEBSITE www.orabandamining.com.au ENQUIRES [email protected]

4.4 Ore Reserve

All Measured and Indicated Mineral Resources within the pit envelopes were included in the Probable Ore Reserve.

The Ore Reserve estimate underpinning the DFS was based on the MRE’s shown in Table 3.1. The Ore Reserves were estimated from practical mining envelopes developed from conventional optimisation methods, following the application of modifying factors for mining dilution and ore loss. The designs consider the geotechnical constraints specific to each mining location.

The Combined Ore Reserves for the DFS are summarised in Table 4.7

Table 4.7: DFS Ore Reserves

PROJECT PROVED PROVED PROBABLE PROBABLE TOTAL MATERIAL TOTAL MATERIAL TOTAL MATERIAL
('000t) (g/t Au) ('000t) (g/t Au) ('000t) (g/t Au) ('000oz.)
Sand King - - 1,300 2.6 1,300 2.6 110
Missouri - - 1,500 2.6 1,500 2.6 130
Riverina Open Pit - - 1,400 1.8 1,400 1.8 81
Golden Eagle - - 130 3.8 130 3.8 16
Waihi - - 1,500 2.3 1,500 2.3 110
Callion - - 240 2.6 240 2.6 21
TOTAL - - 6,100 2.4 6,100 2.4 460

Notes:

  1. The table contains rounding adjustments to two significant figures and does not total exactly.

  2. This Ore Reserve was estimated from practical mining envelopes and the application of modifying factors for mining dilution and ore loss. 3. For the open pit Ore Reserve dilution skins were applied to the undiluted LUC Mineral Resource estimate at zero grade. The in-pit global dilution is estimated to be 29% at Sand King, 43% at Missouri, 22% at Riverina, 13% at Waihi and 23% at Callion all of which were applied at zero grade. The lower dilution at Riverina, Waihi and Callion reflecting the softer lode boundary and allows for inherent dilution within the lode wireframe. All Inferred Mineral Resources were considered as waste at zero grade.

  3. The Open Pit Ore Reserve was estimated using incremental cut-off grades specific to location and weathering classification. They range from 0.54 g/t to 0.69 g/t Au and are based on a price of A$2100 per ounce and include ore transport, processing, site overheads and selling costs and allow for process recovery specific to the location and domain and which range from 85% (Sand King fresh ore) to 95%.

  4. Approximately 100,000 t at 1.8 g/t at Riverina was downgraded from Proved to Probable due to uncertainty at the time surrounding metallurgical recovery. Subsequent test work estimated the Riverina recoveries to be 90.1%, 97.6% and 94.3% for oxide, transition and fresh, respectively.

  5. The underground Ore Reserve was estimated from practical mining envelopes derived from expanded wireframes to allow for unplanned dilution. A miscellaneous unplanned dilution factor of 5% at zero grade was also included. The global dilution factor was estimated to be 32% with an average grade of 0.77 g/t Au.

  6. The underground Ore Reserve was estimated using stoping cut-off of 2.7 g/t Au which allows for ore drive development, stoping and downstream costs such as ore haulage, processing, site overheads and selling costs. An incremental cut-off grade of 0.7 g/t Au was applied to ore drive development and considers downstream costs only. Cut-off grades were derived from a base price of A$2100 per ounce and allow for an assumed process recovery of 92%. Subsequent test work estimated the Golden Eagle fresh recovery to be 90.6%

Probable Reserves for Sand King, Missouri and Riverina Open Pits as well as the Golden Eagle underground were published on the 26 May 2020 and have not materially changed from that date.

Waihi and Callion Open Pit Reserves are maiden Ore Reserves.

All material was subjected to an economic evaluation following detailed cost modelling using project specific costs sourced from contractors, vendors or external consultants. The mine plan has shown

Page 26 of 65

ADDRESS Level 1, 2 Kings Park Rd, Perth WA 6005 POST PO Box 464, West Perth WA 6872 ABN 69 100 038 266 PHONE +61 8 6365 4548 PHONE (TOLL FREE) 1300 035 592 WEBSITE www.orabandamining.com.au ENQUIRES [email protected]

to be technically and financially feasible with a positive net present value at a discount rate of 6%. A flat gold price assumption of A$2,100 / ounce was used for the Ore Reserve financial evaluation.

All economic Mineral Resources evaluated have been converted to Probable Ore Reserves.

Open pit dilution was estimated by applying dilution skins at varying rates, based on the nature of the mineralisation and the proposed mining method. The dilution was applied at zero grade and all Inferred Mineral Resource was considered waste at zero grade. The underground dilution at Golden Eagle was applied using expanded wireframe techniques through the application of mineable stope shape optimisation.

5 PROCESSING

5.1 Process description

The existing Davyhurst plant will use conventional Carbon-in-Pulp (CIP) and gravity concentration methods to recover gold from the ore. The existing processing facility contains the following unit operations:

  • Three stage crushing;

  • Ore storage and reclaim;

  • Two stage grinding and classification;

  • Gravity separation and concentrate processing;

  • Leach and adsorption;

  • Carbon elution and gold recovery;

  • Tailings thickening and disposal;

  • Reagent storage, mixing and distribution; and

  • Water and air services.

5.2 Crushing and Screening

The crushing circuit consists of a three stage crushing configuration with a new double deck inclined vibrating screen producing three product streams:

  • (i) oversize which is directed back to the secondary crusher (ii) mid-stream back to tertiary crusher

  • (iii) undersize to the fine ore bin (FOB).

It is designed to operate 18 hours per day at 180 tph.

5.3 Grinding, Concentration and Classification

The grinding, concentration and classification circuit operates 24 hours per day, 7 days per week. The circuit consists of two stages of ball milling, with two Knelson concentrators and a classifying hydrocyclone cluster.

The primary mill is equipped with a 1,300-kW fixed speed motor processing a nominal 150 tph. Cyclone underflow is split between the gravity screen or to either the primary or secondary mill via a

Page 27 of 65

ADDRESS Level 1, 2 Kings Park Rd, Perth WA 6005 POST PO Box 464, West Perth WA 6872 ABN 69 100 038 266 PHONE +61 8 6365 4548 PHONE (TOLL FREE) 1300 035 592 WEBSITE www.orabandamining.com.au ENQUIRES [email protected]

splitter box. When following the usual path to the secondary mill, it is combined with process water and passes through the 1,120 kW secondary ball mill. The nominal grind targets P80 at 106 µm.

Secondary cyclone underflow is split, with most of the product reporting back to the secondary mill and the remainder reporting to the gravity circuit.

5.4 Leach & Adsorption

The leaching and adsorption circuit treats the material from the cyclone overflow which feeds a trash screen to remove any waste material, with the trash screen underflow reporting to the first of three leach tanks.

Gold is leached into solution via the cyanidation process and adsorbed onto the activated carbon which is pumped counter current to the slurry through six adsorption. Loaded carbon is recovered from adsorption tank 1, where the gold is stripped from the carbon in the elution circuit and the barren carbon is returned to the adsorption tank 6.

5.5 Tailings Disposal

Slurry exiting the final adsorption tank passes over a carbon safety screen. Carbon recovered from the screen is placed in a bunded area for reuse.

Screen undersize reports to the tailings thickener feed hopper where one of two (duty/standby) variable speed centrifugal pumps transfers the slurry into the tailings thickener. Slurry entering the high-rate thickener is combined with diluted flocculant and thickened to approximately 50% solids w/w and pumped to the tailings storage facility (TSF) via one of two (duty/standby) variable speed underflow pumps. The TSF was designed and constructed to the standards set by the Department of Mining, Industry and Resources Safety. A Tailing Management Plan is in place.

The flowsheet also details other features of the circuit including:

  • Elution and gold recovery

  • Carbon regeneration

  • Reagent storage, mixing, distribution and usage

  • Radiation hazards and management

5.6 Metallurgical Test Work

Metallurgical evaluation was undertaken to validate the metallurgical inputs for the DFS. The purpose of the test work was to identify the metallurgical and physical properties of the ore when being processed through the existing Davyhurst processing plant. Drill samples were collected from the six mining locations on a metallurgical domain basis.

The samples were tested over several programmes by ore type using single hole half and quarter core composites (where available). The following testing was undertaken:

  • Bond abrasion index;

  • Bond Ball mill work index;

  • Bond Rod mill work index;

  • SMC testing on fresh ore;

  • Head assays (ICP): Au, Ag, Al, As, Ba, Be, Bi, C-total, C-organic, Ca, Cd, Co, Cr, Cu, Fe, Hg, K, Li, Mg, Mn, Mo, Na, Ni, P, Pb, S-total, S-sulphide, Sb, SiO2, Sr, Te, Ti, V, Y and Zn;

Page 28 of 65

ADDRESS Level 1, 2 Kings Park Rd, Perth WA 6005 POST PO Box 464, West Perth WA 6872 ABN 69 100 038 266 PHONE +61 8 6365 4548 PHONE (TOLL FREE) 1300 035 592 WEBSITE www.orabandamining.com.au ENQUIRES [email protected]

  • Gravity recovery via a lab scale Knelson concentrator, gravity tails returned to leach feed;

  • Cyanide leach tests at grind sizes: P80 75 µm, 106 µm, 125 µm;

  • 48 hours leach;

  • Cyanide initial concentration of 0.05%, maintained at 0.02%;

  • Oxygen sparged;

  • Tests performed in site water, from the Battery borefields;

  • pH target 9.0-9.5;

  • Full ICP assay on feed sample.

  • All testing was conducted using Battery borefield water from OBM to best represent the full scale production.

Metallurgical test work has shown that overall life of mine gold recovery will be 90.3% at a grind size of P80 106 µm. The individual metallurgical domains are tabled 5.1.

Table 5.1: Metallurgical recoveries used to estimate the Ore Reserves at Davyhurst

Average Gold Extraction by Ore Source Average Gold Extraction by Ore Source Average Gold Extraction by Ore Source
Deposit Domain Au Extraction(%)
Riverina Oxide 90.1%
Transitional 97.6%
Fresh 94.3%
Missouri Oxide* 94.0%
Transition* 92.0%
Fresh 92.2%
Sand King Oxide* 95.7%
Transitional 95.7%
Fresh 85.0%
Waihi Oxide* 94.0%
Transition* 92.0%
Fresh 89.8%
Callion Oxide* 91.3%
Transitional 91.3%
Fresh 92.5%
Golden Eagle Fresh 90.6%

The DFS mine plan includes the processing of some minor metallurgical domains that were not specifically tested and have assumed recovery values based on historical plant performance. The domains are minor in their overall contribution to the total milling schedule, being 2.3% of the total tonnes and 1.8% of total ounces. More specifically:

  • Sand King Oxide - 3.3% of deposit tonnes, 2.5% of deposit ounces

  • Missouri Oxide – 1.1% of deposit tonnes, 1.0% of deposit ounces

  • Missouri Transitional - 4.9% of deposit tonnes, 4.0% of deposit ounces

  • Waihi Oxide – 0.9% of deposit tonnes, 0.6% of deposit ounces

  • Waihi Transitional - 3.3% of deposit tonnes, 2.3% of deposit ounces

  • Callion Oxide – 9.0% of deposit tonnes, 6.4% of deposit ounces

Page 29 of 65

ADDRESS Level 1, 2 Kings Park Rd, Perth WA 6005 POST PO Box 464, West Perth WA 6872 ABN 69 100 038 266 PHONE +61 8 6365 4548 PHONE (TOLL FREE) 1300 035 592 WEBSITE www.orabandamining.com.au ENQUIRES [email protected]

6 INFRASTRUCTURE

The main items of infrastructure for the project is shown in Table 6.1.

Table 6.1: Main infrastructure items at the Davyhurst Gold Project

Infrastructure Capacity/Size
Crusher Plant 180 tonnesper hour
Processing plant 1,200,000 T/a
Process water supply & storage 8 bores & two storage dams approximately 30 m x 30 m with over 12,000 cubic
metres of combinedprocessplant storage
Potable water & storage 2 bores with potable water generated via a 200 m3/day Reverse Osmosis (RO)
Plant
Workshops & Warehouse 1x Electrical, 1 x Mechanical, 1 x Warehouse
Laydown and office areas Fully equipped and functioning office facility for administration and technical staff
Power Nominal 6 MW power station with auxiliary mains power supply via Western
Power’s South West Interconnected System(SWIS)
Fuel farm 500,000 litres – administration & power station
300,000 litres – Riverina area
300,000 litres – Siberia area
368,000 litre LNG storage tank
Vehicle Wash Down Pad Heavy vehicle + light vehicle
ROMpad 5 ha
Tailings storage facility Paddock style TSF
Office infrastructure Administration & technical services buildings, communications, ablution, first aid,
warehouse,laboratoryand central workshopbuildings
Road network Extensive major surface haul roads for access from the all deposits to the process
plant ROMpad
Single persons accommodation 172 room camp
Core Shed Extensive drill core processing facility
Callion Airstrip 1,200 m long

7 REVENUE ASSUMPTIONS

Revenue was based on a gold price assumption of A$2,100/oz before selling costs and is below the current spot price of around A$2,550 as of the date of this announcement. The price used is considered by Ora Banda Mining to be a conservative estimate of the medium-term gold price.

The standard Western Australian government royalty of 2.5% was applied in the financial model. Where applicable OBM has also made provision for minor third-party royalties.

8 CAPITAL AND OPERATING COSTS

A detailed financial model to a Definitive Feasibility Study level of accuracy was generated to assess the economic viability of the Riverina, Missouri, Sand King, Waihi, Callion and Golden Eagle deposits.

Plant refurbishment cost were estimated following a detailed review of the Davyhurst process plant and associated infrastructure by GR Engineering Services Ltd ( GRES ) (refer ASX announcement, 2 August 2019).

Page 30 of 65

ADDRESS Level 1, 2 Kings Park Rd, Perth WA 6005 POST PO Box 464, West Perth WA 6872 ABN 69 100 038 266 PHONE +61 8 6365 4548 PHONE (TOLL FREE) 1300 035 592 WEBSITE www.orabandamining.com.au ENQUIRES [email protected]

The remaining costs were generated from first principals cost modelling and supported by external contractor pricing where applicable.

9 FINANCIAL AND SENSITIVITY ANALYSIS

The Ore Reserve estimate is supported by a financial model that has been prepared to a Definitive Feasibility Study level of accuracy. All inputs from open pit and underground operations, processing, transportation and sustaining capital as well as contingencies have been scheduled and evaluated to generate a life of mine financial model. Economic inputs have been sourced from suppliers, contractors or independent consultant databases. A discount rate of 6% pa was applied. The Net Present Value (NPV) of the project was demonstrated to be positive at the assumed commodity price. The project economics based on mining the Ore Reserve retains a reasonable margin of profitability at the assumed gold price.

==> picture [596 x 258] intentionally omitted <==

Sensitivities were conducted on key project parameters such as gold price, process recovery, grade, mining costs and processing costs. The NPV sensitivity of the Project was tested at various input parameters over a nominal +/-10% range. In all cases, the NPV remained positive. The project was shown to be most sensitive to the usual parameters that are direct revenue drivers, being gold price, grade and recovery. Mining costs were shown to be less sensitive whereas processing costs variances were shown to be the least sensitive.

Page 31 of 65

ADDRESS Level 1, 2 Kings Park Rd, Perth WA 6005 POST PO Box 464, West Perth WA 6872 ABN 69 100 038 266 PHONE +61 8 6365 4548 PHONE (TOLL FREE) 1300 035 592 WEBSITE www.orabandamining.com.au ENQUIRES [email protected]

==> picture [596 x 322] intentionally omitted <==

Mining costs for the Project total A$451 million and comprise 76% of the total operating costs. Sensitivity analysis of the costs indicated a 10% variation in the mining costs will vary net cash flow by A$45 million.

Processing costs of the Project total A$123 million comprising 21% of the total operating costs. Sensitivity analysis of the costs indicated a 10% variation in the processing costs will vary net cash flow by A$12 million.

Ancillary facility costs for the Project total A$21 million comprising 4% of the total operating costs. Sensitivity analysis of the costs indicated a 10% variation in the processing costs will vary net cash flow by A$2 million.

10 APPROVALS

Prior to being placed on care and maintenance in 2018, the Davyhurst Gold Project was fully operational with all relevant permits and approvals in place at the time. Permitting studies for the recommencement of mining at the four Davyhurst brownfield mine sites commenced in 2019, following environmental risk assessments and consultation with key stakeholders.

Secondary approvals required under subordinate legislation include Native Vegetation Clearing Permits (Environmental Protection Act 1986), Groundwater Licence applications and amendments (Rights in Water and Irrigation Act 1914). Save for Callion (NVCP approved pending grant of tenure) these permits and licenses are in force.

Mining Proposal Amendments and Mine Closure Plan Amendments covering planned development changes for each site have been prepared and will be lodged with the Department of Mines, Industry Regulation and Safety (DMIRS) in July 2020.

Page 32 of 65

ADDRESS Level 1, 2 Kings Park Rd, Perth WA 6005 POST PO Box 464, West Perth WA 6872 ABN 69 100 038 266 PHONE +61 8 6365 4548 PHONE (TOLL FREE) 1300 035 592 WEBSITE www.orabandamining.com.au ENQUIRES [email protected]

Risk based Environmental Management Plans are in preparation, based on site audits, legal compliance requirements and the findings of environmental studies. Project implementation will be achieved using proven mining and processing technologies suited to local climatic conditions and tested in the Eastern Goldfields of Western Australia.

Project Management Plan (PM-727-392535) governing process plant remedial works has been assessed by DMIRS and approved by the State Mining Engineer.

OBM is not aware of any reason why the suite of previously issued permits and approvals would not be endorsed, or new permits and / or approvals granted within a reasonable time frame.

10.1 Company Standards

Ora Banda is committed to the recommencement of mining operations at Davyhurst in a manner that benefits its shareholders, employees, contractors, suppliers, partners and the community.

Ora Banda aims to achieve best practice standards of environmental care in carrying out its exploration and mining activities. To do this the Company will:

  • Comply with all laws, statutory regulations and standards with respect to the environment;

  • Minimise the effect that the Company’s activities have on the environment and the communities in which it operates through proper planning, operating procedures and rehabilitation protocols;

  • Ensure that employees and contractors are informed about and comply with Ora Banda’s standards and expectations;

  • Periodically review and audit the Company’s standards and requirements with regard to environmental issues and continuously strive to achieve the highest standard of environmental care;

Ora Banda also:

  • Supports standard industry practice throughout the Project development and operational phases;

  • Seeks to optimise social impacts in areas relating to the Project and to avoid negative impacts resulting from its activities; and

  • Will work to ensure that operations contribute to the implementation of relevant local and regional development plans.

11 KEY RISKS

The proposed future activities of the Company are subject to several risks and other factors which may impact its future performance. Some of these risks can be managed and mitigated by planning and the use of safeguards and appropriate controls. However, many of the risks are outside the control of the Company and cannot be mitigated.

OBM has identified several key risks to the Project. These include, but are not limited to:

  • Confidence in the resource model – the Company has undertaken resource drilling to upgrade the majority of the resource to the Indicated Mineral Resource category. This has formed the basis for the Ore Reserve used in the DFS. The resource estimates, by their very nature, are necessarily imprecise and depend to some extent on interpretations, which may prove to be

Page 33 of 65

ADDRESS Level 1, 2 Kings Park Rd, Perth WA 6005 POST PO Box 464, West Perth WA 6872 ABN 69 100 038 266 PHONE +61 8 6365 4548 PHONE (TOLL FREE) 1300 035 592 WEBSITE www.orabandamining.com.au ENQUIRES [email protected]

inaccurate and require adjustment. Adjustments to resource estimates could affect the Company's future plans and ultimately its financial performance and value.

  • Geotechnical Risks – will be managed using industry standard design criteria and ground control methods tailored to the specific requirements of the DGP in line with the recommendations from geotechnical modelling and analysis. Geotechnical work completed is at DFS level and has been completed by an external consultant that has conducted geotechnical evaluations at each of the mining areas.

  • Mining Risks – the proposed mine schedule and mining method is considered conventional in approach and is expected to provide the run-of-mine ore tonnage and quality. The operational aspects of development and production are generally considered relatively low risk. Most of the operational workforce will be supplied by the selected mining contractor. The mining contractor costs included in the DFS are material in value and are based on a response to a budget level “Request For Quotation” (RFQ) specific to the proposed work. Tendered rates and are subject to final contract negotiations with the selected preferred contractor. Mining around historical underground voids will be managed through conventional void management plans and procedures commonly implemented throughout the goldfields.

  • Hydrogeology Risks – dewatering requirements are based on modelling of inflow volumes, both in-pit and underground, across the Project. The Company believes the estimates of inflows are conservative, however variations can occur.

  • Processing Risks – the Company proposed to treat all ores through the Davyhurst Process Plant, which has been on care and maintenance since September 2018. OBM has processes in place to manage the transition from care and maintenance to operations.

  • Accuracy of production and development rates and associated costs – production scenarios are modelled using benchmarked production rates. Costs have been based on a response to a budget level “Request For Quotation” (“RFQ”) specific to the proposed work.

  • COVID-19 – the likelihood and severity of impacts from the COVID-19 pandemic are difficult to predict. Should issues surrounding the spread and longevity of COVID-19 persist for an extended period, sourcing the required workforce along with supply chain issues could become problematic and result in Project start-up delays and/or changes in costs.

  • Pre-production and plant capital – the capital costs required to restart the Company's existing processing plant and mining operations at Davyhurst have been scoped and estimated to cost approximately $45.1 million (+/- 10% level of confidence). This capital cost to restart the project is an estimate only and such capital costs may vary.

  • Funding Risks – OBM is reliant on additional funding to secure pre-production CAPEX and complete full mine commissioning. While the process to secure financing has commenced, there is no guarantee that funding will be achieved. There are other risks, in addition to those identified here, which may impact a financiers funding appetite, and these mainly include geopolitical and international risks, commodity pricing views and foreign exchange forecasts.

  • Amount and timing of pre-production capital – current capital expenditure estimates are at DFS level and are subject to change. The processing plant refurbishment capital estimate included a A$2 million contingency provision. The remaining DFS capital estimates do not include a contingency provision as majority of the capital costs are mine development costs which are subject to contractor rates.

Page 34 of 65

ADDRESS Level 1, 2 Kings Park Rd, Perth WA 6005 POST PO Box 464, West Perth WA 6872 ABN 69 100 038 266 PHONE +61 8 6365 4548 PHONE (TOLL FREE) 1300 035 592 WEBSITE www.orabandamining.com.au ENQUIRES [email protected]

  • Project delays and cost overruns – the Company's ability to develop and potentially commercialise the Davyhurst Project on schedule may be affected by factors including project delays and cost overruns. If the Company experiences project delays or cost overruns, this could result in the Company not realising its operational or development plans or result in such plans costing more than expected or taking longer to realise than expected.

  • Lower than forecast commodity price (A$) – A prolonged suppression of the gold price or a substantial strengthening of the Australian dollar has the potential to reduce the Project NPV. The financial model supporting the Project is based on a flat gold price derived from medium to long term consensus pricing. A hedging strategy can be enacted to protect from any downside movements in commodity pricing.

This announcement was authorised for release to the ASX by David Quinlivan, Managing Director. For more information about Ora Banda Mining and its projects please visit our website at www.orabandamining.com.au

Investor & Media Queries: David Quinlivan Managing Director +61 8 6365 4548 [email protected]

Page 35 of 65

ADDRESS Level 1, 2 Kings Park Rd, Perth WA 6005 POST PO Box 464, West Perth WA 6872 ABN 69 100 038 266 PHONE +61 8 6365 4548 PHONE (TOLL FREE) 1300 035 592 WEBSITE www.orabandamining.com.au ENQUIRES [email protected]

Competent Persons Statement

The information in this announcement that relates to exploration results, and the Riverina, Waihi, Golden Eagle, Sand King, Missouri and Callion Mineral Resources is based on information compiled under the supervision of Mr Andrew Czerw, an employee of Ora Banda Mining Limited, who is a Member of the Australian Institute of Mining and Metallurgy. Mr Czerw has sufficient experience which is relevant to the style of mineralisation and type of deposit under consideration and to the activity which he is undertaking to qualify as a Competent Person as defined in the 2012 Edition of the ‘Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves’. Mr Czerw consents to the inclusion in the report of the matters based on his information in the form and context in which it appears.

Sand King, Missouri, Riverina, Waihi, Golden Eagle, and Callion Mineral Resources are reported in accordance with the JORC Code (2012). The Company confirms that it is not aware of any new information or data that materially affects the information included in the original market announcements dated 15 December 2016 (Missouri) and 3 January 2017 (Sand King), 2 December 2019 (Riverina), 4 February 2020 (Waihi), 8 April 2020 (Golden Eagle), 15 May 2020 (Callion) and restated in market announcement ‘Davyhurst Gold Project - Ore Reserve Update’ dated 26 May 2020. The Company further confirms that all material assumptions and technical parameters underpinning the Mineral Resource estimates in the relevant market announcements continue to apply and have not materially changed.

Mineral Resources other than Sand King, Missouri, Riverina, Waihi, Golden Eagle and Callion, were first reported in accordance with the JORC 2004 code in Swan Gold Mining Limited Prospectus released to the market on 13 February 2013. Mineral Resources other than Sand King, Missouri Riverina, Waihi, Golden Eagle and Callion have not been updated to comply with JORC Code (2012) on the basis that the information has not materially changed since it was first reported.

The information in this report that relates to Ore Reserves is based on information compiled by Mr Geoff Davidson, who is an independent mining engineering consultant, and has sufficient relevant experience to advise Ora Banda Mining Limited on matters relating to mine design, mine scheduling, mining methodology and mining costs. Mr Davidson has sufficient experience which is relevant to the style of mineralisation and type of deposit under consideration and to the activity which he is undertaking to qualify as a Competent Person as defined in the 2012 Edition of the ‘Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves’. Mr Davidson is a Fellow member of the Australasian Institute of Mining and Metallurgy. Mr Davidson is satisfied that the information provided in this statement has been determined to a feasibility level of accuracy, based on the data provided by Ora Banda Mining Limited. Mr Davidson consents to the inclusion in the report of the matters based on his information in the form and context in which it appears.

Forward-looking Statements

This announcement contains forward-looking statements which may be identified by words such as "believes", "estimates", "expects', "intends", "may", "will", "would", "could", or "should" and other similar words that involve risks and uncertainties. These statements are based on an assessment of present economic and operating conditions, and on a number of assumptions regarding future events and actions that, as at the date of this announcement, are expected to take place.

Such forward-looking statements are not guarantees of future performance and involve known and unknown risks, uncertainties, assumptions and other important factors, many of which are beyond the control of the Company, the Directors and management of the Company. These and other factors could cause actual results to differ materially from those expressed in any forward-looking statements.

The Company has no intention to update or revise forward-looking statements, or to publish prospective financial information in the future, regardless of whether new information, future events or any other factors affect the information contained in this announcement, except where required by law.

The Company cannot and does not give assurances that the results, performance or achievements expressed or implied in the forward-looking statements contained in this announcement will actually occur and investors are cautioned not to place undue reliance on these forward-looking statements.

Page 36 of 65

ADDRESS Level 1, 2 Kings Park Rd, Perth WA 6005 POST PO Box 464, West Perth WA 6872 ABN 69 100 038 266 PHONE +61 8 6365 4548 PHONE (TOLL FREE) 1300 035 592 WEBSITE www.orabandamining.com.au ENQUIRES [email protected]

APPENDIX 1 – MINERAL RESOURCE TABLE

PROJECT Cut-Off ('000t)
(g/t Au)
MEASURED
('000t)
(g/t Au)
MEASURED
INDICATED INDICATED INFERRED INFERRED ('000t)
(g/t Au)
('000oz.)
TOTAL MATERIAL
('000t)
(g/t Au)
('000oz.)
TOTAL MATERIAL
('000t)
(g/t Au)
('000oz.)
TOTAL MATERIAL
(g/t Au) ('000t) (g/t Au) ('000t) (g/t Au) ('000t) (g/t Au)
GOLDEN EAGLE 2.0 - - 247 4.1 146 3.4 393 3.9 49
LIGHTS OF ISRAEL 3.0 - - 74 4.3 180 4.2 254 4.2 34
MAKAI SHOOT 1.0 - - 1,985 2.0 153 1.7 2,138 2.0 137
Open Pit 0.5 - - 1,948 2.4 131 2.9 2,079 2.4 159
WAIHI Underground
2.0
- - 188 3.7 195 4.0 383 3.8 47
TOTAL - - 2,136 2.5 326 3.5 2,462 2.6 206
Central Davyhurst Subtotal - - 4,442 2.4 805 3.3 5,247 2.5
427
LADY GLADYS 1.0 - - 1,858 1.9 190 2.4 2,048 1.9 125
Open Pit 0.5 116 1.8 2,694 1.8 183 3.0 2,993 1.9 183
RIVERINA AREA Underground 2.0 - - 226 5.7 502 6.1 728 5.9 139
TOTAL 116 1.8 2,843 1.8 763 3.8 3,721 2.7 322
FOREHAND 1.0 - - 386 1.7 436 1.9 822 1.8 48
SILVER TONGUE 1.0 - - 155 2.7 19 1.3 174 2.5 14
SUNRAYSIA 1.0 - - 175 2.1 318 2.0 493 2.0 32
Riverina-Mulline Subtotal 116 1.8 5,494 1.9 1,648 2.9 7,258 2.3
540
Open Pit - - 1,252 3.4 128 3.3 1,380 3.4 150
SAND KING Underground 0.5 - - 438 3.7 698 3.8 1,136 3.7 136
TOTAL 2.0 - - 1,690 3.5 826 3.7 2,516 3.5 286
Open Pit - - 1,460 3.4 17 3.5 1,477 3.4 160
MISSOURI Underground 0.5 - - 364 3.4 258 3.4 622 3.4 68
TOTAL 2.0 - - 1,824 3.4 275 3.4 2,099 3.4 227
PALMERSTON / CAMPERDOWN 1.0 - - 118 2.3 174 2.4 292 2.4 23
BEWICK MOREING 1.0 - - - - 50 2.3 50 2.3 4
BLACK RABBIT 1.0 - - - - 434 3.5 434 3.5 49
THIEL WELL - - - - 18 6.0 18 6.0 3
Siberia Subtotal - - 3,632 3.4 1,777 3.5 5,409 3.4
592
Open Pit 0.5 - - 241 3.7 28 1.6 269 3.5 30
Callion Underground 2.0 - - 255 6.0 156 5.5 411 5.8 77
TOTAL -
-
496
4.9
184
4.9
680
4.9
107
Callion Subtotal - - 496 4.9 184 4.9 680 4.9 107
FEDERAL FLAG 1.0 32 2 112 1.8 238 2.5 382 2.3 28
SALMON GUMS 1.0 - - 199 2.8 108 2.9 307 2.8 28
WALHALLA 1.0 - - 448 1.8 216 1.4 664 1.7 36
WALHALLA NORTH 1.0 - - 94 2.4 13 3.0 107 2.5 9
MT BANJO 1.0 - - 109 2.3 126 1.4 235 1.8 14
MACEDON 1.0 - - - - 186 1.8 186 1.8 11
Walhalla Subtotal 32 2.0 962 2.1 887 2.0 1,881 2.1
125
IGUANA 1.0 - - 690 2.1 2,032 2.0 2,722 2.0 175
LIZARD 1.0 106 4 75 3.7 13 2.8 194 3.8 24
Lady Ida Subtotal 106
~~254~~
4.0 765
~~15,791~~
2.3 2,045
~~7,346~~
2.0 2,916
~~23,391~~
2.1
199
Davyhurst Total 300 2.7 15,800 2.5 7,300 2.8 23,400 2.6 1,990
BALDOCK - - - 136 18.6 0 0.0 136 18.6 81
METEOR - - - - - 143 9.3 143 9.3 43
WHINNEN - - - - - 39 13.3 39 13.3 17
Mount Ida Total - - 140 18.6 180 10.2 320 13.8 140
Combined Total 300 2.7 15,900 2.6 7,500 2.9 23,700 2.8 2,130

Notes

  1. The Missouri, Sand King, Riverina, Waihi, Callion & Golden Eagle Mineral Resources have been updated in accordance with all relevant aspects of the JORC code 2012, and initially released to the market on 15 December 2016 & 26 May 2020 (Missouri), 3 January 2017 & 26 May 2020 (Sand King), 2 December 2019 & 26 May 2020 (Riverina), 4 February 2020 (Waihi), 15 May 2020 & 29 June 2020 (Callion) & 8 April 2020 (Golden Eagle).

  2. All Mineral Resources listed above, with the exception of the Missouri, Sand King, Riverina, Waihi, Callion & Golden Eagle Mineral Resources, were prepared previously and first disclosed under the JORC Code 2004 (refer Swan Gold Mining Limited Prospectus released to the market on 13 February 2013). These Mineral Resources have not been

Page 37 of 65

ADDRESS Level 1, 2 Kings Park Rd, Perth WA 6005 POST PO Box 464, West Perth WA 6872 ABN 69 100 038 266 PHONE +61 8 6365 4548 PHONE (TOLL FREE) 1300 035 592 WEBSITE www.orabandamining.com.au ENQUIRES [email protected]

updated in accordance with JORC Code 2012 on the basis that the information has not materially changed since it was first reported.

  1. The Riverina, Waihi, Sand King, Missouri and Callion Open Pit Mineral Resource Estimates are reported within a A$2,400/oz pit shell above 0.5g/t. The Riverina, Waihi, Sand King, Missouri, Callion and Golden Eagle Underground Mineral Resource Estimates are reported from material outside a A$2,400 pit shell and above 2.0 g/t.

  2. The values in the above table have been rounded.

Page 38 of 65

ADDRESS Level 1, 2 Kings Park Rd, Perth WA 6005 POST PO Box 464, West Perth WA 6872 ABN 69 100 038 266 PHONE +61 8 6365 4548 PHONE (TOLL FREE) 1300 035 592 WEBSITE www.orabandamining.com.au ENQUIRES [email protected]

APPENDIX 2 – JORC CODE 2012 – TABLE 1

Table 1, Sections 1, 2 and 3 information for Riverina, Sand King, Missouri and Golden Eagle were reported on 26 May 2020 “Davyhurst Gold Project – Ore Reserve Update”. Sections 1, 2 and 3 for Callion and Waihi are reported below. Section 4 for all deposits is reported below.

11.1 Section 1 Sampling Techniques and Data – Waihi

Criteria JORC Code explanation Commentary
Sampling
techniques

Nature and quality of sampling (e.g. cut channels,
random chips, or specific specialised industry
standard measurement tools appropriate to the
minerals under investigation, such as down hole
gamma sondes, or handheld XRF instruments, etc).
These examples should not be taken as limiting the
broad meaning of sampling.

Include reference to measures taken to ensure
sample representivity and the appropriate calibration
of any measurement tools or systems used.

Aspects of the determination of mineralisation that
are Material to the Public Report.

In cases where ‘industry standard’ work has been
done this would be relatively simple (e.g. ‘reverse
circulation drilling was used to obtain 1 m samples
from which 3 kg was pulverised to produce a 30 g
charge for fire assay’). In other cases more
explanation may be required, such as where there is
coarse gold that has inherent sampling problems.
Unusual commodities or mineralisation types (e.g.
submarine nodules) may warrant disclosure of
detailed information.

Billiton - RAB and RC 1m samples with RAB being composited to 2m. Diamond core of NQ size. Assay sample techniques
undocumented

Consolidated Exploration (Consex) – RAB 1m samples usually dispatched as 3m composites but occasional 1m. RC a mix of
1m sampling or 2m composites. Lady Eileen programs RC drilling made use of roller, Blade or hammer with crossover sub all
nominally 5.5-inch diameter to obtain 2-3kg sample. Composite 2m samples were hammer milled, mixed and split to 200g
then pulverised. 1m samples single stage mix and ground. Subsamples taken for aqua regia and fire assay.

Cons Gold (Consolidated Gold) – RC 1m samples where alteration is visible. Remainder of hole composited to 4m. 2 to 3 kg
samples, including core, sent to laboratory for crushing, pulverising and 50g Fire Assay.

Croesus – RC 1m samples collected under cyclone. 5m comps assayed for gold by 50g Fire assay. NQ diamond except for
geotechnical purposes (HQ triple).

DPPL (Davyhurst Project Pty. Ltd.)- 4.25 to 5.5-inch RC drilling with face hammer. Potential mineralisation sampled and
assayed on a metre basis otherwise 4m composites. Samples jaw crushed and pulverised before taking a 50gm charge for
fire assay.

Ora Banda Mining Limited (OBM) - RC samples collected from the levelled cone splitter directly off rig into calico bags. Splitter
maintained on level site to ensure sample representivity. 1m samples are dried, crushed, pulverised and a 50g charge is
analysed by Fire Assay. Half core samples cut by saw. Core sample intervals selected by geologist and defined by geological
and/or mineralisation boundaries, or sampled to 1m. Samples are crushed, pulverized and a 40g or 50g charge is analysed by
Fire Assay.

WMC - RC Sampling on 1m basis, assayed by aqua regia method, unknown laboratory.
Drilling techniques
Drill type (e.g. core, reverse circulation, open-hole
hammer, rotary air blast, auger, Bangka, sonic, etc)
and details (e.g. core diameter, triple or standard
tube, depth of diamond tails, face-sampling bit or
other type, whether core is oriented and if so, by
what method, etc).

Billiton RAB and RC (Conventional hammer) diameter undocumented with use of roller/blade and hammer. NQ Diamond core

Consex - RC drilling with roller, blade or hammer with crossover sub.

Cons Gold – NQ diamond and HQ (triple) for geotechnical holes. RAB and RC. 4.25 to 5.5-inch RC drilling with stabilisers and
face sampling hammers.

Croesus – Diamond holes NQ2 diameter. RC and RAB details undocumented but assumed to be industry standard at the time
being 5.5-inch face sampling hammers and 4-inch diameter respectively.

Delta – RAB - details undocumented

DPPL - NQ core and HQ for geotechnical holes. RC drilling with stabilisers and face sampling hammers.

OBM - HQ3 coring to approx. 40m, then NQ2 to BOH. All core oriented by reflex instrument. RC drilled with face sampling
hammer, 5.5” – 5.625" diameter

WMC – Conventional RC hammer, diameter unknown and RAB drilling details undocumented.

Page 39 of 65

Criteria JORC Code explanation Commentary
Drill
sample
recovery

Method of recording and assessing core and chip
sample recoveries and results assessed.

Measures taken to maximise sample recovery and
ensure representative nature of the samples.

Whether a relationship exists between sample
recovery and grade and whether sample bias may
have occurred due to preferential loss/gain of
fine/coarse material.

RC drill recoveries were not recorded by Aberfoyle/Bardoc, Anaconda, Ashton, Consolidated Gold, Croesus, Delta, DPPL, Hill
Minerals, Intrepid, Monarch, Mt Kersey, Normandy, Pancontinental, Texas Gulf, West coast holdings or WMC

Billiton – Recoveries for some RC drilling programs were examined in 1986 but raw data not available.

Consex – 2 metre plastic pipe inserted into cyclone vent. Cyclone washed at the end of each hole or if water injected. Sample
weights measured for Homeward bound (no bias observed) and Lady Eileen prospects (generally no bias observed aside
from two high grade samples perceived to be due to coarse grained gold)

OBM - Diamond drill recoveries are recorded as a percentage calculated from measured core against downhole drilled
intervals (core blocks). RC sample recoveries are approximated based on the size of the bulk sample and recorded in drill log
tables.

It is unknown whether a relationship exists between sample recovery and grade or whether sample bias may have occurred.
Logging
Whether core and chip samples have been
geologically and geotechnically logged to a level of
detail to support appropriate Mineral Resource
estimation, mining studies and metallurgical
studies.

Whether logging is qualitative or quantitative in
nature. Core (or costean, channel, etc)
photography.

The total length and percentage of the relevant
intersections logged.

Billiton - Qualitative: lithology, alteration for Diamond and RAB. RC logging details unavailable

Consolidated Exploration- Qualitative: lithology, colour, alteration, grainsize (at times). Quantitative: Quartz mineralisation at
times

Consolidated Gold/ DPPL - Qualitative: lithology, colour, oxidation, alteration, with grainsize, texture and structure often
recorded in diamond drilling. Quantitative: Quartz veining. Core photographed. Logging entered directly into HPLX200 data
loggers.

Croesus - Most holes photographed, geologically logged and geotechnical and magnetic susceptibility measurements were
taken. Qualitative: Lithology, colour, grainsize, alteration, oxidation, texture, structures, regolith. Quantitative: Quartz veining

OBM - Qualitative: Lithology, colour, oxidation, grainsize, texture, structure, hardness, regolith. Quantitative: estimates are
made of quartz veining, sulphide and alteration percentages. Core photographed wet and dry. Magnetic susceptibility
recorded for core holes. Bulk density measurements taken at regular intervals for core holes (determined by Archimedes
Principle).

WMC RC: Qualitative: Lithology, Colour, Grainsize, Alteration and oxidation

Some logging detail was lost during translation from one logging system to another. This has been rectified by referring back
to original logs.

Entire holes were logged byall operators
Sub-sampling
techniques
and
sample preparation

If core, whether cut or sawn and whether quarter,
half or all core taken.

If non-core, whether riffled, tube sampled, rotary
split, etc and whether sampled wet or dry.

For all sample types, the nature, quality and
appropriateness of the sample preparation
technique.

Quality control procedures adopted for all sub-
sampling stages to maximise representivity of
samples.

Measures taken to ensure that the sampling is
representative of the in-situ material collected,
including for instance results for field
duplicate/second-half sampling.

Whether sample sizes are appropriate to the grain
size of the material being sampled.

Billiton – Sub-sampling methods undocumented. 1m repeat fire assays of 2m RAB comps at Lady Eileen were done.
Duplicates for RAB and RC inserted however frequency unknown.

Consex – RC holes sampled on 1m basis and riffle split to 1-2kg samples for 3m composites or 2-3kg samples for 2m
composites. Composite 2m samples were hammer milled, mixed and split to 200g then pulverised to 200#. 1m samples single
stage mix and ground to 200#.

Consgold - RC Samples collected via cyclone at 1m intervals and passed through 3 stage riffle splitter. A 2-3kg fraction was
calico bagged for analysis, the residue collected in plastic bags and stored on site. Potentially mineralised zones were sampled
at 1m intervals, the remainder composited to 4m by unknown method. Composite samples returning >0.19g/t were re submitted
at 1m intervals. Samples underwent mixer mill preparation (2-3kg) by Amdel Laboratories. RAB 4m composite samples using
PVC spear. Samples returning >0.19g/t were re submitted at 1m intervals. Diamond drill samples were sawn into half core. One
half was jaw crushed, then pulverised using a labtechnics mill. A quartz blank was pulverised between each sample to avoid
contamination. Field duplicates from residues at 1 in 20 frequency submitted.

Croesus RC/RAB - 1m samples collected under cyclone. 5m comps, spear sampled with 50mm PVC pipe. Wet RC drill
samples were thoroughly mixed in the sample retention bag and scoop sampled to form a composite sample. 3-5kg five metre
composite analytical samples, returning values greater than 0.1g/t gold, were riffle split at 1m intervals, were samples where
dry, and grab sampled where wet. RAB 1m resampling method undocumented.
Samples were dried, crushed and split to obtain a sample less than 3.5kg, and then fine pulverised prior to a 50gm charge being
collected and analysed. Every 20thsample was duplicated in the field and submitted for analysis. Diamond tails were cut to half
core and sampled based on geological boundaries and identified prospective zones. Samples size varied from 0.2m to1m. Core
samples were sent to Ultratrace Laboratories of Perth

Page 40 of 65

ADDRESS Level 1, 2 Kings Park Rd, Perth WA 6005 POST PO Box 464, West Perth WA 6872 ABN 69 100 038 266 PHONE +61 8 6365 4548 PHONE (TOLL FREE) 1300 035 592 WEBSITE www.orabandamining.com.au ENQUIRES [email protected]

Criteria JORC Code explanation Commentary

DPPL – RC 3 stage riffle split then 4m compositing. RAB 4m composites sampled using PVC spear. Both RC and RAB
composites returning >0.19ppm Au re-submitted as 1m samples. Field duplicates from residues at 1 in 20 frequency
submitted.

OBM – RC samples split into 2 x calico bags each metre using a cone splitter. Wet or moist samples are noted during
sampling. Core was cut with diamond saw and half core sampled. All mineralized zones are sampled, including portions of
visibly un-mineralised hanging wall and footwall zones. Sample weights range from >1kg to 3.5kg. Samples weighed by
laboratory, dried and split to <3kg if necessary and pulverized by LM-5

WMC - RC Samplingon 1m basis,methods undocumented. Assaybyaqua regia method,unknown laboratory.
Quality of assay
data and laboratory
tests

The nature, quality and appropriateness of the
assaying and laboratory procedures used and
whether the technique is considered partial or total.

For geophysical tools, spectrometers, handheld
XRF instruments, etc, the parameters used in
determining the analysis including instrument make
and model, reading times, calibrations factors
applied and their derivation, etc.

Nature of quality control procedures adopted (e.g.
standards, blanks, duplicates, external laboratory
checks) and whether acceptable levels of accuracy
(i.e. lack of bias) and precision have been
established.

Billiton - Laboratory and methods undocumented. Standards for RAB and RC inserted however frequency unknown

Consex – Genalysis composite 2m samples were hammer milled, mixed and split to 200g then pulverised to 200#. 1m
samples single stage mix and ground to 200#. Phase 1 standard wet chemical multi acid digestion and AAS. Second phase
were also pre-roasted. Results of >1g/t re-assayed by fire assay. Check assays at umpire lab (Classic labs) for Lady Eileen
drilling - significant differences in high grade samples, otherwise considered good.

Consolidated Gold/ DPPL – RC and RAB - Mixer mill prep with fire assay 50g charge at AMDEL, Minilab or Analabs
Laboratories in Kalgoorlie. Half core was diamond sawn, jaw crushed, milled using LABTECHNICS mill at AMDEL for 50g
charge by fire assay. Gannet standards submitted to monitor lab accuracy for infill resource drilling. Pulp umpire analysis was
done but frequency unknown (1995). Screen fire assays of selected high grade samples. Quartz blanks submitted between
each diamond core sample.

Croesus samples analysed for Au by Fire Assay/ICPOES by Ultratrace in Perth. Gannet standards and blank samples made
by Croesus were submitted with split sample submissions. QAQC analysis of repeats was analysed by Croesus Mining NL.
for their drilling completed during 2000.

OBM - Samples sent to Nagrom in Perth. The samples have been analysed by Firing a 50gm portion of the sample. Lower
sample weights may be employed for samples with very high sulphide and metal contents. This is the classical fire assay
process and will give total separation of gold. An ICPOES finish is used. Commercially prepared standard samples and blanks
are inserted in the sample stream at a rate of 1:25 for standards and 1:25 for blanks. Sizing results (percentage of pulverised
sample passing a 75μm mesh) are undertaken on approximately 1 in 40 samples. Duplicate samples are submitted for RC
holes only at a rate of approximately 1:30. The accuracy (standards) and precision (repeats) of assaying are deemed
acceptable.

WMC drill samples were assayed by aqua regia method, unknown laboratory.

Fire assay is considered a total technique and aqua regia is considered a partial technique.

Historic operators assayed by“AAS”. This is assumed to be aqua regia.
Verification
of
sampling
and
assaying

The verification of significant intersections by either
independent or alternative company personnel.

The use of twinned holes.

Documentation of primary data, data entry
procedures, data verification, data storage (physical
and electronic) protocols.

Discuss any adjustment to assay data.

OBM geologists have viewed selected diamond holes from certain deposits, including Waihi and verified the location of
mineralised intervals.

Cons Gold – Each metre interval geologically logged directly into HPLX2000 with standardised logging codes.

Twinned holes were occasionally used by previous operators, but this practice was not common.

OBM - Geological and sample data logged directly into field computer (Panasonic Toughbook CF-31) using Geobank Mobile.
Data is exported onto company servers and imported into Geobank SQL database by the database administrator (DBA).
Assay files are received in .csv format and loaded directly into the database by the DBA. Hardcopy and/or digital copies of
data are kept for reference if necessary.

Data entry, verification and storage protocols for remaining operators is unknown.

No adjustments have been made to assaydata
Location of data
points

Accuracy and quality of surveys used to locate drill
holes (collar and down-hole surveys), trenches,
mine workings and other locations used in Mineral
Resource estimation.

Specification of the grid system used.

Quality and adequacy of topographic control.

RAB and AC holes are/were not routinely collar surveyed or downhole surveyed due to their limited use in resource
estimation. To this end, discussion of RAB and AC drilling is omitted from this section. RC/GC (grade control) and shallow RC
holes are/were not routinely downhole surveyed due to their shallow nature reducing the chance of significant deviation.
Barren exploration RC holes were not routinely downhole surveyed, or collar surveyed. DD holes were routinely collar and
downhole surveyed by most operators or have been re-surveyed by subsequent operators.

The influence of magnetic rocks on the azimuths of magnetic down hole surveys is minor. Early holes surveyed in AMG zone
51 and converted to MGA usingGeobank and or Datashed data management software.

Page 41 of 65

ADDRESS Level 1, 2 Kings Park Rd, Perth WA 6005 POST PO Box 464, West Perth WA 6872 ABN 69 100 038 266 PHONE +61 8 6365 4548 PHONE (TOLL FREE) 1300 035 592 WEBSITE www.orabandamining.com.au ENQUIRES [email protected]

Criteria JORC Code explanation Commentary

Billiton (RC, DD) Local Lights of Israel grid undergone 2-point transformation. Downhole surveys when performed were by
undocumented method with a 25m interval average

Consex (RC). Drilled on local grids (possibly truncated AMG84, zone 51). Holes appear to have been surveyed using AMG,
zone 51 grid at a later stage. Numerous vertical holes not down-hole surveyed. Downhole surveys when performed were by
undocumented method with a 9m interval average

Cons Gold/DPPL (RC, DD) Local grids and AMG84 zone 51 used. RC and DD Collars surveyed by licensed surveyors to
respective grids. Holes of all types routinely collar surveyed whist RC resource holes routinely downhole surveyed by various
methods including gyro and EMS with average intervals ranging between 10-25m.

Croesus (RC, DD) Various local grids and AMG zone 51. RC, DD holes routinely collar surveyed and downhole surveyed
using Electronic Multishot (EMS), GRYO, Eastman single shot or combination thereof at 10-15m average interval.

Hills (RC) Local grid used.

OBM (RC, DD) MGA94 Zone 51. Drill hole collars are marked out and collar positions (post-drilling) picked up by a registered
surveyor using RTK-GPS. Drill-hole, downhole surveys are recorded every 18-30m using a reflex digital downhole camera
(RC) or Gyro tool (DD). Some RC holes were not surveyed if holes short and/or drilling an early stage exploration project.

WMC (RC, DD) - Digital data provided by Cons Gold. (Wamex report a50226). Downhole surveys when performed were by
undocumented method with a 16m interval average
Data spacing and
distribution

Data spacing for reporting of Exploration Results.

Whether the data spacing and distribution is
sufficient to establish the degree of geological and
grade continuity appropriate for the Mineral
Resource and Ore Reserve estimation procedure(s)
and classifications applied.

Whether sample compositing has been applied.

Data spacing nominally 20m x 20m but down to circa 10m x 10m and grade control drilling at circa 5m x 5m.

Drill hole spacing is adequate to establish geological and grade continuity for the Waihi deposit for the purpose of Mineral
Resource and Ore Reserve estimation.

Composites of drill intercepts are length weighted, 1g/t lower cut-off, not top-cut, maximum 2m internal dilution
Orientation of data
in
relation
to
geological
structure

Whether the orientation of sampling achieves
unbiased sampling of possible structures and the
extent to which this is known, considering the
deposit type.

If the relationship between the drilling orientation
and the orientation of key mineralised structures is
considered to have introduced a sampling bias, this
should be assessed and reported if material.

Mineralised structures at Waihi are steep dipping and strike circa 320oto 345oDrilling is dominantly oriented to the east on a
Waihi local grid which is rotated -14 degrees from the MGA north. Drilling is therefore oriented towards 76oon the MGA grid
and to a lesser extent 256o, orthogonal to the mineralisation strike. Drill hole inclinations range from -50 to -90o. At Homeward
bound some drill holes were drilled down the structure in an attempt to better define the folding present.

It is unknown whether the orientation of sampling achieves unbiased sampling, though it is considered unlikely as it the
majority of holes have optimally intersected the mineralised lodes.
Sample security
The measures taken to ensure sample security.

Undocumented for most early operators.

Cons Gold – RC residues stored onsite

OBM – Samples are bagged into cable-tied polyweave bags and stored in bulka bags in a secure yard. Once submitted to the
laboratories they are stored in cages within a secure fenced compound. Samples are tracked through the laboratory via their
LIMS.
Audits or reviews
The results of any audits or reviews of sampling
techniques and data.

OBM has reviewed historic digital data and compared it to hardcopy and digital (Wamex) records. Changes were made to the
SQL database where necessary.

No audits of samplingtechniques have been done.

Page 42 of 65

ADDRESS Level 1, 2 Kings Park Rd, Perth WA 6005 POST PO Box 464, West Perth WA 6872 ABN 69 100 038 266 PHONE +61 8 6365 4548 PHONE (TOLL FREE) 1300 035 592 WEBSITE www.orabandamining.com.au ENQUIRES [email protected]

11.2 Section 1 Sampling Techniques and Data – Callion

Criteria JORC Code explanation Commentary
Sampling
techniques

Nature and quality of sampling (e.g. cut channels,
random chips, or specific specialised industry
standard measurement tools appropriate to the
minerals under investigation, such as down hole
gamma sondes, or handheld XRF instruments, etc).
These examples should not be taken as limiting the
broad meaning of sampling.

Include reference to measures taken to ensure
sample representivity and the appropriate calibration
of any measurement tools or systems used.

Aspects of the determination of mineralisation that
are Material to the Public Report.

In cases where ‘industry standard’ work has been
done this would be relatively simple (e.g. ‘reverse
circulation drilling was used to obtain 1 m samples
from which 3 kg was pulverised to produce a 30 g
charge for fire assay’). In other cases more
explanation may be required, such as where there is
coarse gold that has inherent sampling problems.
Unusual commodities or mineralisation types (e.g.
submarine nodules) may warrant disclosure of
detailed information.

Centamin - 90 and 130mm AC, RC drilling with 1m sampling using ECM350 Crawlair and Schramm T64
drill rigs respectively. Individual or 2m composite samples were analysed by both aqua regia and fire assay
of undocumented charge and laboratory.

Consolidated Gold - 1m sampling from RC rig. Potential mineralisation assayed on a metre basis at 2-3kg
target weight - otherwise as 4m composites. Composites returning significant results were re-submitted as
individual metres. Samples were pulverised and a 50g charge for Fire Assay performed.

Crest - 1 m sampling of RAB holes from which 4m composite samples were submitted from which a 50g
charge was used for fire assay (NRAB holes) or aqua regia (CLN holes).

Croesus - RC, RAB and AC 1m samples collected under cyclone. 5m composite samples were crushed,
pulverised and assayed for gold by 50g Fire assay. HQ Diamond core was halved and sampled over the
entire hole at 1m and 0.5m intervals. Core samples were sent to Ultratrace Laboratories of Perth and
analysed for Au, Pt and Pd by fire assay (50gm charge).

Delta - RC and RAB 5 metre composites for a 50g charge by aqua-regia analysis. 1m re-samples and NQ2
diamond tail core were milled and assayed by 50g charge fire assay.

Eastern Goldfields Limited (EGS) - 1m RC samples using face sampling hammer with samples collected
under cone splitter. 1m and 4m composite samples were dispatched for pulverising and 50g charge Fire
Assay. Half core samples cut by saw. Core sample intervals selected by geologist and defined by
geological boundaries. Samples are crushed, pulverized and a 40g charge is analysed by Fire Assay.

Lonestar – RC drilling. 1m sampling and logging. 3m composites or 1m samples were crushed, pulverised
and analysed by Fire assay.

Lubbock - 1m RC drilling with composite samples of 2m in length and 1m in areas of quartz veining or
areas of interest. Analysis by aqua regia with re-assays by fire assay at SGS Kalgoorlie or Comlabs. RC
Laterite assaying by aqua regia only. RAB assay methods undocumented. Not all Diamond drilling details
known but some were NQ and were cut and assayed by Fire Assay

Monarch - RAB 2m-4m scoop composites and 1m intervals were despatched for analysis by aqua regia.
Not all intervals were sampled.

Ora Banda Mining Limited (OBM) - 1m RC samples using face sampling hammer with samples collected
under a level cyclone / cone splitter configuration. Two split samples collected every metre. 1m and 4m
composite samples were dispatched for pulverising and 50g charge Fire Assay. Half-core samples cut by
core saw. Core sample intervals selected by geologist and defined by geological and mineralisation
boundaries. Samples are crushed, pulverized and a 50g charge is analysed by Fire Assay.

WMC - RAB drilling. 1m sampling, details undocumented
Drilling techniques
Drill type (e.g. core, reverse circulation, open-hole
hammer, rotary air blast, auger, Bangka, sonic, etc)
and details (e.g. core diameter, triple or standard
tube, depth of diamond tails, face-sampling bit or
other type, whether core is oriented and if so, by what
method, etc).

Centamin - Aircore 90mm and RC 130mm diameter holes (Conventional hammer)

Consolidated Gold - RC Face sampling hammers. Undocumented diameter and bit size.

Crest - RAB - details undocumented

Croesus - Diamond holes HQ diameter. RC with 5.5-inch face sampling hammer and 4-inch RAB holes

Delta - RAB and RC - details undocumented. NQ2 diamond tails

Lonestar – RC drilling details undocumented. Presumably industry standard of 5.5-inch face sampling hammer.

Lubbock - RAB, RC and Diamond details of which are undocumented for all types. Diamond drilling was of NQ diameter
and included pre-collars and tails and wedges. Core was not oriented.

Monarch - RAB samples were collected by Kennedy Drilling using a 4-inch blade.

Ora Banda Mining Limited (OBM) – 5.5 – 5.625-inch diameter RC holes using face sampling hammer with samples
collected under cone splitter. Core holes have RC pre-collars up to 150m depth, then NQ2 coring to BOH. All core
oriented byreflex instrument.

Page 43 of 65

ADDRESS Level 1, 2 Kings Park Rd, Perth WA 6005 POST PO Box 464, West Perth WA 6872 ABN 69 100 038 266 PHONE +61 8 6365 4548 PHONE (TOLL FREE) 1300 035 592 WEBSITE www.orabandamining.com.au ENQUIRES [email protected]

Criteria JORC Code explanation Commentary

Eastern Goldfields Limited (EGS) - 5-inch diameter RC holes using face sampling hammer with samples collected under
cone splitter. HQ3 coring to approx. 40m, then NQ2 to BOH. All core oriented by spear and/or reflex instrument
WMC - RAB details undocumented
Drill
sample
recovery

Method of recording and assessing core and chip
sample recoveries and results assessed.

Measures taken to maximise sample recovery and
ensure representative nature of the samples.

Whether a relationship exists between sample
recovery and grade and whether sample bias may
have occurred due to preferential loss/gain of
fine/coarse material.

Historic operators have not captured recovery data from RAB or RC drilling.

Eastern Goldfields Limited (EGS) - Diamond drill recoveries are recorded as a percentage calculated from measured
core against downhole drilled intervals (core blocks).

Ora Banda Mining Limited (OBM) – RC drilling recoveries recorded on a pre metre basis based on sample size.
Diamond drill recoveries are recorded as a percentage calculated from measured core against downhole drilled
intervals (core blocks).

There is no known relationship between sample recovery and grade.
Logging
Whether core and chip samples have been
geologically and geotechnically logged to a level of
detail to support appropriate Mineral Resource
estimation, mining studies and metallurgical studies.

Whether logging is qualitative or quantitative in
nature. Core (or costean, channel, etc) photography.

The total length and percentage of the relevant
intersections logged.

In all cases, entire holes were geologically logged

Centamin - Basic descriptive logging with quartz and weathering notations

Consolidated Gold - Qualitative: Lithology, colour, Oxidation, alteration, sulphides, structure, moisture. Quantitative:
logging applied to veining percentage

Crest - Qualitative: Lithology, Colour, Oxidation, alteration, grainsize. Quantitative: logging applied to veining percentage

Croesus - All DD holes photographed, geologically logged and geotechnical and magnetic susceptibility measurements
were taken. Qualitative: Lithology, colour, grainsize, alteration, oxidation, texture, structures, regolith. Quantitative:
Quartz veining

Delta - Colour, oxidation, structural, lithology, alteration, veining, mineralogy

Lonestar - Colour, oxidation, lithology, alteration, veining, minerals

Lubbock - Logging of diamond holes was descriptive. Qualitative: Lithology, alteration, texture, structure, minerals,
grainsize. RC/RAB logging believed to have been done however documentation unavailable.

Monarch - Qualitative: Regolith, Grain Size, Lithology, Colour, Texture, Structure, Oxidation, Alteration. Quantitative:
Sulphide, Mineral, Veining

Ora Banda Mining Limited (OBM)- Qualitative: Lithology, colour, oxidation, grainsize, texture, structure, hardness,
regolith. Quantitative: estimates are made of quartz veining, sulphide and alteration percentages. Magnetic susceptibility
recorded on a per metre basis in core holes. Core hole RQD logged. Core photographed wet and dry. Bulk density
determination using Archimedes Principle is routinely undertaken using whole core segments.

Eastern Goldfields Limited (EGS) - Qualitative: Lithology, colour, oxidation, grainsize, texture, structure, hardness,
regolith. Quantitative: estimates are made of quartz veining, sulphide and alteration percentages. Core photographed.
WMC - No details available
Sub-sampling
techniques
and
sample preparation

If core, whether cut or sawn and whether quarter, half
or all core taken.

If non-core, whether riffled, tube sampled, rotary split,
etc and whether sampled wet or dry.

For all sample types, the nature, quality and
appropriateness of the sample preparation technique.

Quality control procedures adopted for all sub-
sampling stages to maximise representivity of
samples.

Measures taken to ensure that the sampling is
representative of the in-situ material collected,
including for instance results for field
duplicate/second-half sampling.

All laboratories performed repeats conducted at the discretion of the laboratory

Centamin - Methods undocumented. Samples mostly submitted on 1m basis with limited 2m composites

Consolidated Gold - RC: Riffle split to 2-3kg; residue placed in plastic bags. Intervals of prospective mineralisation or of
geological interest were dispatched as individual metres with the remainder of the hole composited to 4m by
undocumented method. RAB 4m composite samples using PVC spear. Both RC and RAB composites returning
>0.19ppm or .24ppm for Callion holes re-submitted as 1m samples. Samples were dried the pulverised in Mixer mill until
90% of sample is 106 microns or less. Duplicates at 1 in 20 frequency from residues submitted. Field duplicates
submitted every 20th sample for RC, AC, and RAB

Crest - All sub sampling techniques undocumented

Croesus - 1m samples collected under cyclone. 5m comps, spear sampled with 50mm PVC pipe. Wet RC drill samples
were thoroughly mixed in the sample retention bag and scoop sampled to form a composite sample. RAB and AC scoop
samples taken from piles laid on ground. Five metre composite analytical samples, returning values greater than 0.1g/t
gold, were riffle split (RC) or scoop (RAB, AC) at 1m intervals, where samples were dry, and grab sampled where wet.

Page 44 of 65

ADDRESS Level 1, 2 Kings Park Rd, Perth WA 6005 POST PO Box 464, West Perth WA 6872 ABN 69 100 038 266 PHONE +61 8 6365 4548 PHONE (TOLL FREE) 1300 035 592 WEBSITE www.orabandamining.com.au ENQUIRES [email protected]

Criteria JORC Code explanation Commentary

Whether sample sizes are appropriate to the grain
size of the material being sampled.
Diamond tails were cut to half core and sampled based on geological boundaries and identified prospective zones.
Sample size varied from 0.5m to1m. Core samples were sent to Ultratrace Laboratories of Perth The analytical samples
were dried, crushed and split to obtain a sample less than 3.5kg, and then fine pulverised prior to a 50gm charge being
collected and analysed.

Delta - 5m composites by scoop re-submitted as 1m scoop samples if composite result >0.1ppm Au. Core was cut in
half. Mixer mill lab preparation. Duplicates submitted although frequency unknown

Lonestar - 1m samples and 3m composites by undocumented methods

Lubbock- RC drilling with samples of 2m in length and 1m in areas of quartz veining. Splitting and compositing methods
undocumented. RC laterite sampling/assaying on individual metre basis. RAB sampling methods undocumented. Core
was cut by diamond saw but proportion undocumented. Average sample length of approximately 1m.

Monarch - Samples were composited to 2-4m by scoop. Duplicates are taken 1 in 25 when taking 1m splits straight from
the rig. When doing re-splits on composite results 1 in 20 duplicates with occasional triplicates (about 1 every 50 re-
splits).

Ora Banda Mining Limited (OBM) – RC samples were submitted as individual 1m split samples (cone splitter) or
composited to 4m by PVC spear. Half-core samples cut by automated core saw. Core sample intervals selected by
geologist and defined by geological and/or mineralisation boundaries. RC samples were dried, crushed, split, pulverised
and a 50gm charge taken. Field duplicates, blanks and standards were submitted for QAQC analysis.

Eastern Goldfields Limited (EGS) - Samples were composited to 4m by scoop or submitted as individual samples. Half
core samples cut by saw. Core sample intervals selected by geologist and defined by geological boundaries. RC
samples were dried, crushed, split, pulverised and a 50gm charge taken. Field duplicates, blanks and standards were
submitted for QAQC analysis.

WMC-1m sampling of chips by undocumented method
Quality
of
assay
data and laboratory
tests

The nature, quality and appropriateness of the
assaying and laboratory procedures used and
whether the technique is considered partial or total.

For geophysical tools, spectrometers, handheld XRF
instruments, etc, the parameters used in determining
the analysis including instrument make and model,
reading times, calibrations factors applied and their
derivation, etc.

Nature of quality control procedures adopted (e.g.
standards, blanks, duplicates, external laboratory
checks) and whether acceptable levels of accuracy
(i.e. lack of bias) and precision have been
established.

Aqua regia is considered a partial technique whilst Fire Assay is considered total.

Centamin - Both aqua regia and fire assay of unknown charge size and laboratory.

Consolidated Gold - Mixer mill prep with fire assay 50g charge at AMDEL or Analabs Laboratories in
Kalgoorlie. Standards supplied by Gannet Labs. Standard results falling outside 2 standard deviations
queried and checked. MWRC holes showed variance with grade indicating possible coarse gold.

Crest - NRAB holes 50g fire assay/AAS to 0.01ppm. CLN holes analysed by ALS for Gold by method PM
205 (50 gm aqua regia digest / solvent extraction / graphite furnace AAS)

Croesus - Analysis for gold (Fire assay/ICP Optical Spectrometry) by Ultratrace Laboratory in Perth.
Diamond core analysed for Au, Pt and Pd by fire assay at Ultratrace Perth. Every 20th sample was
duplicated in the field and submitted for analysis. Gannet standards and blank samples made by Croesus
were submitted with split sample submissions. RC drilling included a standard followed by a blank sample
submitted every 50th and 51st sample respectively.

Delta - 5m comps: Total mixer mill prep, Aqua-regia with 50g charge, 0.01ppm detection limit. 1m samples
and core: as above but with fire assay. Genalysis Kalgoorlie or ALS Kalgoorlie. Core at ALS Kalgoorlie.
Standards submitted although frequency and certification unknown

Lonestar - Fire assay of unknown charge and AAS at Amdel laboratories Kalgoorlie. Umpire pulp analysis
by ALS laboratories using original pulp residues

Lubbock - Core was fire assayed, detail undocumented. RC (non-laterite) samples by aqua regia and
results returning 1.0g/t were re-assayed by fire assay at Comlabs Kalgoorlie or SGS. RAB by fire assay,
details undocumented. Laterite RC drilling by aqua regia at Comlabs Kalgoorlie. 23 pulps from laterite drill
program were split and sent to 3 other labs. Screen fire assays performed on 1984 Glasson drilling
(Wamex report A16848).

Monarch – RAB samples analysed at SGS by 50g aqua regia/AAS. Standards: 1 in every 20 samples for
RC drillingand 1 in 25 for RAB drilling (comps).

Page 45 of 65

ADDRESS Level 1, 2 Kings Park Rd, Perth WA 6005 POST PO Box 464, West Perth WA 6872 ABN 69 100 038 266 PHONE +61 8 6365 4548 PHONE (TOLL FREE) 1300 035 592 WEBSITE www.orabandamining.com.au ENQUIRES [email protected]

Criteria JORC Code explanation Commentary

Ora Banda Mining Limited (OBM) - Samples sent to Intertek, SGS and Nagrom laboratories. The samples
have been analysed by firing a 50gm portion of the sample. This is the classical fire assay process and will
give total separation of gold. An ICPOES finish is used. Commercially prepared standard samples and
blanks are inserted in the sample stream at a rate of 1:20 for standards and 1:20 for blanks. Sizing results
(percentage of pulverised sample passing a 75μm mesh) are undertaken on approximately 1 in 40
samples. Duplicate samples are taken in RC drill holes at a rate of approximately 1:30. The accuracy
(standards) and precision (repeats) of assaying are acceptable.

Eastern Goldfields Limited (EGS) – as per OBM

WMC - No details found - DB states FA-AAS
Verification
of
sampling
and
assaying

The verification of significant intersections by either
independent or alternative company personnel.

The use of twinned holes.

Documentation of primary data, data entry
procedures, data verification, data storage (physical
and electronic) protocols.

Discuss any adjustment to assay data.

Twinned holes were not routinely used by previous operators.

Monarch Gold Mining Company Ltd; Geological and sample data was logged digitally and .csv or .xls files imported into
Datashed SQL database with in-built validation. Samples bags were put into numbered plastic bags and then cable tied.
Samples collected daily from site by laboratory

Eastern Goldfields Limited (EGS) - Geological and sample data logged directly into field computer at the core yard using
Field Marshall. Data is transferred to Perth via email and imported into Geobank SQL database by the database
administrator (DBA). Assay files are received in .csv format and loaded directly into the database by the DBA. Hardcopy
and/or digital copies of data are kept for ref

Ora Banda Mining Limited (OBM) - Geological and sample data logged directly into field computer (Panasonic
Toughbook CF-31) at the core yard or at the drill rig using Geobank Mobile. Data is exported from the logging computer,
copied onto the company servers and imported into Geobank SQL database by the database administrator (DBA).
Assay files are received in .csv format and loaded directly into the database by the DBA. Hardcopy and/or digital copies
of data are kept for reference if necessary.

Data entry, verification and storage protocols for remaining operators is unknown.
Location of data
points

Accuracy and quality of surveys used to locate drill
holes (collar and down-hole surveys), trenches, mine
workings and other locations used in Mineral
Resource estimation.

Specification of the grid system used.

Quality and adequacy of topographic control.

Centamin – Accuracy of collars and downhole survey unknown. Collars located on Centamin local grid using theodolite
and chain.

Consolidated Gold - All collars surveyed by licensed surveyors to respective grids. CNRC holes used in Callion deposit
resource were downhole surveyed with Eastman single shot using aluminium collar above hammer. Local grids with 2
point transformation to AMG84 zone 51 grid

Crest - Collars were un-surveyed post drilling, located on AMG84 zone 51 grid

Croesus - Majority of Croesus RC and DD holes were collar surveyed. An exception appears to be the TTRC holes.
Local grid was used. Diamond and CNRC prefixed holes were downhole surveyed by EMS with readings every 5 to 10
metres.

Delta - No holes appear to have been surveyed by collar or downhole. AMG84 zone 51 grid

Lonestar - Collars were surveyed upon completion by an undocumented method. Glasson Local grid.

Lubbock- Diamond holes down-hole surveyed every 24m by Eastman camera. Local grids originally utilised. Selected
diamond holes were surveyed by EGL staff in MGA94 zone 51 grid using Trimble DGPS.

Monarch - No RAB holes were surveyed post drilling MGA94 zone 51 grid used. No down hole surveys.

Ora Banda Mining Limited (OBM) - MGA94, zone 51. Drill hole collar mark outs are conducted by surveying contractors
using RTK GPS (sub-cm accuracy). Subsequent to drilling, holes are picked up using RTK GPS. Drill-hole downhole
surveys are recorded every 18-30m using a reflex digital downhole camera (RC) or Gyro tool (DD).

Eastern Goldfields Limited (EGS) - MGA94, zone 51. Drill hole collar positions are picked up using a Trimble DGPS
subsequent to drilling. Drill-hole, downhole surveys are recorded every 30m using a reflex digital downhole camera.
Some RC holes not surveyed if holes short and/or drilling an early stage exploration project.

WMC - No holes appear to have been surveyed

Page 46 of 65

ADDRESS Level 1, 2 Kings Park Rd, Perth WA 6005 POST PO Box 464, West Perth WA 6872 ABN 69 100 038 266 PHONE +61 8 6365 4548 PHONE (TOLL FREE) 1300 035 592 WEBSITE www.orabandamining.com.au ENQUIRES [email protected]

Criteria JORC Code explanation Commentary
Data spacing and
distribution

Data spacing for reporting of Exploration Results.

Whether the data spacing and distribution is sufficient
to establish the degree of geological and grade
continuity appropriate for the Mineral Resource and
Ore Reserve estimation procedure(s) and
classifications applied.

Whether sample compositing has been applied.

Historic data spacing highly variable from wide spaced ~800m x ~80m regional RAB to close spaced resource drilling
~20m x ~20m and grade control drilling at ~5m x ~5m.

Drill hole spacing is adequate to establish geological and grade continuity for the Callion deposit.

Drill intercepts are length weighted, 1g/t lower cut-off, no top-cut, maximum 2m internal dilution.
Orientation of data
in
relation
to
geological
structure

Whether the orientation of sampling achieves
unbiased sampling of possible structures and the
extent to which this is known, considering the deposit
type.

If the relationship between the drilling orientation and
the orientation of key mineralised structures is
considered to have introduced a sampling bias, this
should be assessed and reported if material.

For most of the deposits in and around Callion the prevailing geological and structural trend is approx. North-South.
Once the orientation of mineralisation was established drilling was mostly oriented between 255oand 270oor 75oand
80o. Holes were generally inclined between 50oand 65ofor RC and DD.

It is unknown whether the orientation of sampling achieves unbiased sampling, though it is considered unlikely.
Sample security
The measures taken to ensure sample security.

Eastern Goldfields Limited (EGS) - Samples were bagged, tied and in a secure yard. Once submitted to the laboratories
they are stored in cages within a secure fenced compound. Samples are tracked through the laboratory via their LIMS.

Monarch - Pre-numbered sample bags were put into numbered plastic bags. These numbers were written on the
submission forms which were checked by the geologist. Plastic bags were then securely cable tied and placed in a
secure location. Samples were then picked up by the Lab in Kalgoorlie or deliver to Perth via courier. A work order
conformation was emailed to Monarch personnel for each sample submission once samples were received by the
Laboratory.

Ora Banda Mining Limited (OBM) - Samples were collected on the day of drilling and bagged into cable tied polyweave
bags. Polyweave bags are stored into bulka bags on pallets in a secure yard on-site. Once submitted to the laboratories
they are stored in cages within a secure fenced compound. Samples are tracked through the laboratory via their LIMS.

No documentation for other operators
Audits or reviews
The results of any audits or reviews of sampling
techniques and data.

OBM has reviewed historic digital data and compared it to hardcopy and digital (Wamex) records.

No audits of sampling techniques have been done.

11.3 Section 2 Reporting of Exploration Results - Waihi

Criteria JORC Code explanation Commentary Commentary
Mineral
tenement
and
land
tenure
status

Type, reference name/number, location and
ownership including agreements or material issues
with third parties such as joint ventures,
partnerships, overriding royalties, native title
interests, historical sites, wilderness or national
park and environmental settings.

The security of the tenure held at the time of
reporting along with any known impediments to
obtaining a licence to operate in the area.



All tenure pertaining to this report is listed below
TENEMENT
HOLDER
Expiry Date AGREEMENTS
M30/255
CARNEGIE GOLD PTY
LTD.
10/01/2038 Nil
Carnegie Gold PTY LTD is a wholly owned subsidiary of OBM.
There are no known heritage or native title issues.
There are no known impediments to obtaining a licence to operate in the area.

Page 47 of 65

ADDRESS Level 1, 2 Kings Park Rd, Perth WA 6005 POST PO Box 464, West Perth WA 6872 ABN 69 100 038 266 PHONE +61 8 6365 4548 PHONE (TOLL FREE) 1300 035 592 WEBSITE www.orabandamining.com.au ENQUIRES [email protected]

Criteria JORC Code explanation Commentary
Exploration
done
by other parties

Acknowledgment and appraisal of exploration by
other parties.

Modern exploration commenced at the Davyhurst sites in the 1980s. Three companies, Jones Mining, Western Mining
Corporation (WMC) and Hill Minerals pegged claims surrounding the historic Davyhurst sites. In 1986, WMC established a
300,000 tonne per annum carbon-in-pulp (CIP) treatment plant at Davyhurst and commenced open pit mining at Golden Eagle
and Waihi. In 1988 WMC’s and Jones Mining’s assets were acquired by Consolidated Exploration Ltd. Consolidated
Exploration then developed open cut mines at Great Ophir, Lady Eileen, Lady Eileen South and Homeward Bound. At about
the same time Aberfoyle Resources / Hill Minerals commenced open-pit mining at the Lights of Israel Deposit and trucked the
ore 80 km to the Bardoc processing plant. During 1995/96 Consolidated Exploration Ltd. restructured as Consolidated Gold
NL (CGNL) and commenced tenement acquisition and exploration activities in the area. This resulted in the consolidation of
holdings in the district. In December 1996 CGNL acquired the assets of Aberfoyle Resources in the area, including the
Bardoc Processing plant, in an equity transaction. The Bardoc plant was relocated to the Davyhurst site and upgraded to 1.2
Mt/y. In October 1998 Davyhurst Project Pty Ltd (DPPL), a subsidiary of NM Rothschild and Sons (Australia), acquired the
project. In 2000, Croesus Mining NL (“Croesus”) acquired the Davyhurst Project and continued operations until 2005. In
January 2006, Monarch Gold Mining Company Limited (Monarch) acquired Davyhurst and operated the project until 2008.

Drilling, sampling and assay procedures and methods as stated in the database and confirmed from Wamex reports and hard
copy records are considered acceptable and to industry standards of the time. There is sufficient understanding of drilling,
sampling and assay methodologies for the majority of drilling in the Waihi area. The company is confident that previous
operators completed work to standards considered acceptable for the time. As part of each resource upgrade, OBM is
committed to additional drillingto confirm the style,widths and tenor of mineralisation at each deposit.
Geology
Deposit type, geological setting and style of
mineralisation.

Regional Geology- Rocks of the Coolgardie domain (Kalgoorlie Terrane) are prevalent in the Davyhurst area. Rocks of the
Coolgardie Domain are not well exposed at Davyhurst and the distribution of rock types suggests that it is mainly represented
by the upper part of the stratigraphic sequence, namely basalts, felsic volcanics and sedimentary rocks. The abundant
ultramafic-mafic sills of the Ora Banda Domain do not occur in the Coolgardie Domain. Granitoids in the Davyhurst Project area
can be classified by magnetic signature into three types: low, medium and high magnetic response. Binns et al. (1976)
distinguished ‘static style’ and ‘dynamic style’ regional metamorphism. Static style areas generally occupy the central, low-strain
part of the greenstone regions away from the granitoids and typically have lower metamorphic grades (prehnite–pumpellyite to
upper greenschist facies). Strain is concentrated in narrow zones so that textures are well preserved in more massive and
competent rocks. Dynamic-style areas of greenstone have higher metamorphic grades (upper greenschist to upper amphibolite
facies) and are characterized by more pervasive foliation, particularly along the contacts with large granitoid terrains. There
appears to be two major controls on mineralisation in the Davyhurst area. Both mineralisation styles rely on mineralisation taking
place during reactivation of earlier ductile shear zones. In the case of the Lights of Israel group of deposits, the early shears are
moderately to gently west dipping, whereas in the Federal Flag – Lady Eileen group of deposits, the early shear is steeply west
dipping. In the northern portion of the Davyhurst tenements most gold mineralisation is aligned in planar corridors that have N-
to NW-trends. The overall dip of the mineralised corridors is mostly steep (>75º) E- or W-dipping with moderate to steep (~60º)
and shallow-dipping (~15º) ore zones at the Federal Flag and Lady Gladys deposits, respectively. Within these planar corridors
of mineralisation linear trends to gold distribution are mostly shallowly plunging. Internal variations within the corridors at
individual deposits are common and discussed later. Mineralisation at the Lights of Israel and Makai deposits differs from the
other examined deposits in that mineralisation has a linear form that plunges moderately (~20º) to the NNW.

Local Geology- The two major rock types within the Waihi deposit are:
o
Tremolite/Actinolite/Chlorite Amphibolite._Weakly to strongly foliated, fine to medium grained rocks
composed of tremolite/actinolite within a fibrous Mg chlorite matrix. High Mg Basalt
o
Fine Grained Basalt
._ Massive to weakly foliated, very fine grained rock composed of actinolite and
plagioclase (albite) with trace magnetite. Tholeiitic basalt
Late stage lepidolite bearing pegmatite dykes striking 060° and dipping steeply 75° north cut across the stratigraphy at several
places. A quartz felspar porphyry sub parallel to regional foliation has been mapped in the old Homeward Bound pit. Detailed
mapping by Cons Gold of the Waihi and Homeward Bound pits shows the area is dominated by a strong penetrative foliation
striking 347° and dipping 75° to 80° west. A second weaker foliation striking 040° and dipping 75° north was also recognised in
both pits. Several post mineralisation faults striking approximately 070° and dipping north have been mapped or inferred from
the drilling. The faults have only minor lateral displacement. Several of the faults are infilled by lepidolite pegmatite.

Gold mineralisation at Waihi occurs within both the tholeiitic and high Mgbasalts. Mineralisation is characterised bymultiple

Page 48 of 65

ADDRESS Level 1, 2 Kings Park Rd, Perth WA 6005 POST PO Box 464, West Perth WA 6872 ABN 69 100 038 266 PHONE +61 8 6365 4548 PHONE (TOLL FREE) 1300 035 592 WEBSITE www.orabandamining.com.au ENQUIRES [email protected]

Criteria JORC Code explanation Commentary
loads and broad alteration haloes. Mineralisation also appears to have a moderate northerly plunge of approximately 40°
towards 340°. Folding is common at Waihi and numerous folds and re-folded folds are noted in pit and in in drill core. Fold
hinges have a consistent ~40oplunge to the north. Within the deposit there is a pervasive biotite alteration halo. Associated
with gold mineralisation, biotite plus silica and quartz veining occur. Higher grade gold mineralisation is generally associated
with extreme silica flooding and quartz veining which has destroyed the majority of the rock fabric. Diopside as an alteration
mineral also occurs throughout the resource. Quartz veining sub parallel to, or cross cutting the regional fabric also occurs
within the deposit. These veins are discontinuous and can form boudins with the ore zone. Grade distribution within these
blobs is erratic (Lennartz, 1988). Controls on ore shoots within the resource are not well understood at this stage. From the
data available there appears to be a major zone of mineralisation plunging north from the south end of the Waihi pit. From the
old stope plans of the Waihi Shaft, it would appear that the higher grade mineralisation has a steeply dipping lensoidal shape,
with occasional glory holes, which WMC inferred were fold hinges. Around the Homeward Bound and east lode areas the higher
grade mineralisation appears to have a 40° plunge to the north. Pyrrhotite, pyrite and arsenopyrite are the dominant sulphides
within the resource. Trace to accessory concentrations of chalcopyrite, pentlandite, gesdorfite, and bismuth have been
recognised
Drill
hole
Information

A summary of all information material to the
understanding of the exploration results including a
tabulation of the following information for all
Material drill holes:
o
easting and northing of the drill hole
collar
o
elevation or RL (Reduced Level –
elevation above sea level in metres)
of the drill hole collar
o
dip and azimuth of the hole
o
down hole length and interception
depth
o
hole length.

If the exclusion of this information is justified on the
basis that the information is not Material and this
exclusion does not detract from the understanding
of the report, the Competent Person should clearly
explain why this is the case.

Individual drill intercepts are previously reported.For previous announcements relating to Waihi please refer to ASX
announcement dated 22 February 2017, 29 July 2019, 14 October 2019, 6 November 2019, 22 November 2019, 24
December 2019, 21 January 2020

Any widths reported in a Significant Intercepts table are all down hole lengths.
Data
aggregation
methods

In reporting Exploration Results, weighting
averaging techniques, maximum and/or minimum
grade truncations (e.g. cutting of high grades) and
cut-off grades are usually Material and should be
stated.

Where aggregate intercepts incorporate short
lengths of high grade results and longer lengths of
low grade results, the procedure used for such
aggregation should be stated and some typical
examples of such aggregations should be shown in
detail.

The assumptions used for any reporting of metal
equivalent values should be clearly stated.

Original assays are length weighted. For reporting exploration results grades are not top cut. Lower cut off is nominally 0.5g/t.
Maximum 2m internal dilution.

No metal equivalents reported
Relationship
between
mineralisation

These relationships are particularly important in the
reporting of Exploration Results.

If thegeometry of the mineralisation with respect to

Intercept widths are down hole lengths. True widths are not reported given the varying orientation of drilling and mineralisation
at each deposit/prospect mentioned in the report.

Page 49 of 65

ADDRESS Level 1, 2 Kings Park Rd, Perth WA 6005 POST PO Box 464, West Perth WA 6872 ABN 69 100 038 266 PHONE +61 8 6365 4548 PHONE (TOLL FREE) 1300 035 592 WEBSITE www.orabandamining.com.au ENQUIRES [email protected]

Criteria JORC Code explanation Commentary
widths
and
intercept lengths
the drill hole angle is known, its nature should be
reported.

If it is not known and only the down hole lengths are
reported, there should be a clear statement to this
effect (e.g. ‘down hole length, true width not
_known’). _
Diagrams
Appropriate maps and sections (with scales) and
tabulations of intercepts should be included for any
significant discovery being reported These should
include, but not be limited to a plan view of drill hole
collar locations and appropriate sectional views.

See plans and sections provided within this announcement.
Balanced reporting
Where comprehensive reporting of all Exploration
Results is not practicable, representative reporting
of both low and high grades and/or widths should
be practiced to avoid misleading reporting of
Exploration Results.

Results reported include both low and high gram metre (g/t x down hole length) values.

The significant intercept table (previously reported – see references in Section on Drill hole Information) provides details of
drill hole intercepts shown on diagrams. There is no lower cut-off grade, the holes listed include those with NSI (no significant
intercept). Holes in the significant intercept table are shown on diagrams coloured according to gram metre grade bins. This
provides spatial context to the number of holes in the project area with significant gold intercepts versus the number of holes
with lesser or no significant intercepts
Other substantive
exploration data

Other exploration data, if meaningful and material,
should be reported including (but not limited to):
geological observations; geophysical survey
results; geochemical survey results; bulk samples –
size and method of treatment; metallurgical test
results; bulk density, groundwater, geotechnical
and rock characteristics; potential deleterious or
contaminating substances.

Metallurgical and geotechnical work has been completed for numerous previously mined deposits, including Waihi.

Waihi deposit was previously mined and processed at Davyhurst plant with no known metallurgical issues.

Ongoing geological/ structural evaluation to determine the controls on mineralisation

New metallurgical holes from Waihi have been drilled and are being tested. Results are pending.

Geotechnical holes have been planned, drilling to commence soon.
Further work
The nature and scale of planned further work (e.g.
tests for lateral extensions or depth extensions or
large-scale step-out drilling).

Diagrams clearly highlighting the areas of possible
extensions, including the main geological
interpretations and future drilling areas, provided
this information is not commercially sensitive.

Data evaluation and geological assessment of all deposits, including Waihi, will be followed by additional resource drilling and
updated JORC 2012 compliant Mineral Resources.

Local exploration targeting extensions to the south and east of Waihi are proposed.

11.4 Section 2 Reporting of Exploration Results - Callion

Criteria JORC Code explanation Commentary
Mineral
tenement
and
land
tenure
status

Type, reference name/number, location and
ownership including agreements or material issues
with third parties such as joint ventures,
partnerships, overriding royalties, native title
interests, historical sites, wilderness or national park
and environmental settings.

The security of the tenure held at the time of
reporting along with any known impediments to

The Callion deposit is located on M30/103

M30/103 is held by Carnegie Gold Pty ltd, a wholly owned subsidiary of Ora Banda Mining Limited

Pursuant to the Crown Diamonds Royalty Agreement, a royalty is payable on all material mined and processed from
M30/103 of:
o
$1.00 per tonne if the grade is equal to or less than 3.0 grams per tonne.
o
$2.50 per tonne if the grade is greater than 3.0 grams per tonne but equal to or less than 4 grams per tonne.
o
$4.00 per tonne if the grade is greater than 4.0 grams per tonne; and

Page 50 of 65

ADDRESS Level 1, 2 Kings Park Rd, Perth WA 6005 POST PO Box 464, West Perth WA 6872 ABN 69 100 038 266 PHONE +61 8 6365 4548 PHONE (TOLL FREE) 1300 035 592 WEBSITE www.orabandamining.com.au ENQUIRES [email protected]

Criteria JORC Code explanation Commentary
obtaining a licence to operate in the area. o
$5.50 per tonne if the grade is greater than 7.0 grams per tonne and the ore is extracted by underground
operations.

The royalty was payable severally 60/40 to two parties but the Company’s predecessor in title acquired the 60% royalty
entitlement under a buy-back arrangement. The Company remains liable to pay 40% of the royalty to Crown Diamonds
Pty Ltd.

There are no known heritage or native title issues.
Exploration
done
by other parties

Acknowledgment and appraisal of exploration by
other parties.

Drilling, sampling and assay procedures and methods as stated in the database and confirmed from Wamex reports and hard
copy records are considered acceptable and to industry standards of the time. There is sufficient understanding of drilling,
sampling and assay methodologies for the majority of drilling in the Callion area. The company is confident that previous
operators completed work to standards considered acceptable for the time. As part of each resource upgrade, Ora Banda Mining
Ltd will commit to additional drilling to confirm the style, widths and tenor of mineralisation at each deposit.
Geology
Deposit type, geological setting and style of
mineralisation.

Callion lies in the Barlee Terrain, West of the Ida Fault. The Mount Ida Greenstone Belt of the Barlee Terrane in the Callion area
is described by Wyche & Witt (1994), as an east-dipping sequence of tholeiitic basalt and dolerite intercalated with several BIF
and shale units in the east. The westernmost, and presumably the lowermost (as facing is indeterminate), rock type mapped in
the area is a +700m thick sequence of sandstone, wacke, shale, chert and banded iron formation (herein termed BIF), interleaved
with several sills of dolerite and gabbro. The chert and BIF units define a prominent range of hills, whereas the sandstone and
shale units, together with the mafic sills are recessive features. The BIF units become chertier and less magnetic towards the
east. These rocks are overlain by a ~100m thick sequence of thinly bedded shale, siltstone and fine grained sandstone with thin
interbeds of chert. Bedding in the BIF’s generally dips at 45º to the east, although it can range between 25º and 75º. The BIF’s
and cherts become progressively higher metamorphic grade in a northward direction (i.e. along strike). Overlying the fine grained
sediments is a 250-600m thick composite dolerite and gabbro sill that is thickest in the centre of the area and thinnest at the
southern limit of the mapping. To aid description this sill is herein termed the Lady Mary Sill. East of the Lady Mary Sill is a
~1500m thick sequence of basalt that displays pillow structures, amygdales, and rare variolitic flows. Interflow sediments are
absent from this thick pile of basalt. Intruded into the basalt is ~1000m of dolerite spread over two dozen discrete sills ranging
from 20m to 200m thick. The intrusions are generally conformable with the Lady Mary Sill to the west, although the dolerite
intrusions do strike N-S along the eastern side of the mapped area. The eastern boundary of the mapped area was arbitrary;
however, a strong shear zone is present on the eastern flank of the easternmost outcrop mapped and coincides with a distinctive
linear high in magnetic data. Intruding the basalt and dolerite rocks east of the Lady Mary Sill in the northern half of the mapping
is a +4km2 area of massive granitoid, described as a monzonite by Arnold (2001).

The metamorphic grade of the Davyhurst area is described by Wyche & Witt (1994) as being low pressure and moderate to
high temperature middle to upper amphibolite facies.

The structural setting of the Glasson-Callion area is relatively simple. Strain is strongly heterogenous, being partitioned into very
narrow shear zones, leaving the neighbouring country rock largely undeformed. The BIF/chert sequence dips on average 45º
to the east, although some variation in dip and strike is noted, and bedding is folded about mesoscopic, asymmetric, parasitic
drag folds with consistent S-vergence. The drag folds are reclined, having fold axes plunging at a similar orientation to the dip
of the long limbs.

The mineralisation at Callion is associated with massive quartz veining or quartz vein stockworks. Mineralised quartz veins are
situated both within narrow shear zones within mafic rocks, or at the contact between basalts and interflow felsic rocks.
Drill
hole
Information

A summary of all information material to the
understanding of the exploration results including a
tabulation of the following information for all Material
drill holes:
o
easting and northing of the drill hole collar

Individual drill intercepts previously reported. For previous announcements relating to Callion please refer to ASX announcement
dated 24 November 2016, 10 January 2017, 20 February 2017, 31 August 2017, 28 January 2020, 3 March 2020, 30 April 2020.

Any widths reported in a Significant Intercepts table are all down hole lengths.

Page 51 of 65

ADDRESS Level 1, 2 Kings Park Rd, Perth WA 6005 POST PO Box 464, West Perth WA 6872 ABN 69 100 038 266 PHONE +61 8 6365 4548 PHONE (TOLL FREE) 1300 035 592 WEBSITE www.orabandamining.com.au ENQUIRES [email protected]

Criteria JORC Code explanation Commentary
o
elevation or RL (Reduced Level – elevation
above sea level in metres) of the drill hole collar
o
dip and azimuth of the hole
o
down hole length and interception depth
o
hole length.

If the exclusion of this information is justified on the
basis that the information is not Material and this
exclusion does not detract from the understanding of
the report, the Competent Person should clearly
explain why this is the case.
Data
aggregation
methods

In reporting Exploration Results, weighting averaging
techniques, maximum and/or minimum grade
truncations (e.g. cutting of high grades) and cut-off
grades are usually Material and should be stated.

Where aggregate intercepts incorporate short
lengths of high grade results and longer lengths of
low grade results, the procedure used for such
aggregation should be stated and some typical
examples of such aggregations should be shown in
detail.

The assumptions used for any reporting of metal
equivalent values should be clearly stated.

Original assays are length weighted. For reporting exploration results grades are not top cut. Lower cut off is nominally 0.5g/t.
Maximum 2m internal dilution.

No metal equivalents reported.
Relationship
between
mineralisation
widths
and
intercept lengths

These relationships are particularly important in the
reporting of Exploration Results.

If the geometry of the mineralisation with respect to
the drill hole angle is known, its nature should be
reported.

If it is not known and only the down hole lengths are
reported, there should be a clear statement to this
effect (e.g.‘down hole length, true width not known’).

All intercept widths reported are down hole lengths. No attempt has been made here to report true widths.

Generally, resource drilling was drilled at orientations perpendicular to the established trend of mineralisation.
Diagrams
Appropriate maps and sections (with scales) and
tabulations of intercepts should be included for any
significant discovery being reported These should
include, but not be limited to a plan view of drill hole
collar locations and appropriate sectional views.

Refer to diagrams in release.
Balanced reporting
Where comprehensive reporting of all Exploration
Results is not practicable, representative reporting of
both low and high grades and/or widths should be
practiced to avoid misleading reporting of
Exploration Results.

Results reported include both low and high gram metre (g/t x down hole length) values.

The significant intercept table (previously reported – see references in Section on Drill Hole Information) provides details of drill
hole intercepts shown on diagrams. There is no lower cut-off grade, the holes listed include those with NSI (no significant
intercept). Holes in the significant intercept table are shown on diagrams coloured according to gram metre grade bins. This
provides spatial context to the number of holes in the project area with significant gold intercepts versus the number of holes
with lesser or no significant intercepts.
Other substantive
exploration data

Other exploration data, if meaningful and material,
should be reported including (but not limited to):
geological observations; geophysical survey results;
geochemical survey results; bulk samples – size and
method of treatment; metallurgical test results; bulk
density, groundwater, geotechnical and rock
characteristics; potential deleterious or

Callion deposit was previously mined and processed at Davyhurst plant with no known metallurgical issues.

New metallurgical holes from Callion have been drilled and are currently being tested. Results are pending.

New geotechnical holes at Callion have been drilled with results currently being reviewed by external geotechnical consultants.

All exploration data believed to be meaningful and material to this release has been included.

Page 52 of 65

ADDRESS Level 1, 2 Kings Park Rd, Perth WA 6005 POST PO Box 464, West Perth WA 6872 ABN 69 100 038 266 PHONE +61 8 6365 4548 PHONE (TOLL FREE) 1300 035 592 WEBSITE www.orabandamining.com.au ENQUIRES [email protected]

Criteria JORC Code explanation Commentary
contaminating substances.
Further work
The nature and scale of planned further work (e.g.
tests for lateral extensions or depth extensions or
large-scale step-out drilling).

Diagrams clearly highlighting the areas of possible
extensions, including the main geological
interpretations and future drilling areas, provided this
information is not commercially sensitive.

Further data evaluation and geological assessment of drilling conducted at the Callion deposit.

Metallurgical and geotechnical studies are ongoing.

Geological and resource modelling targeting underground potential at Callion.

11.5 Section 3 Estimation and Reporting of Mineral Resources - Waihi

Criteria JORC Code explanation Commentary
Database integrity
Measures taken to ensure that data has not been
corrupted by, for example, transcription or keying
errors, between its initial collection and its use for
Mineral Resource estimation purposes.

Data validation procedures used.

Data from EGL/OBM drilling captured into Field Marshall logging software. Data sent from site and imported into SQL database
via DBMS. Validation checks in SQL database are carried out to ensure data integrity is not compromised.

The data is verified by company geologists before being sent to the DBA for validation or passing Geobank Software validation
protocols

Historic data has been verified by checking historical reports on the project.

The Competent Person has undertaken a number of validation checks on the database, using Micromine software which
include, but are not limited to, checks for overlapping intervals, checks for missing data/records, visual checks on drill hole
locations and traces to identify any possible survey issues. No major issues were detected.
Site visits
Comment on any site visits undertaken by the
Competent Person and the outcome of those visits.

If no site visits have been undertaken indicate why
this is the case.

Numerous site visits have been completed by the Competent Person with the following objectives:
o
View geology in existing open pit
o
View drilling operations
o
View and log drill core
Geological
interpretation

Confidence in (or conversely, the uncertainty of) the
geological interpretation of the mineral deposit.

Nature of the data used and of any assumptions
made.

The effect, if any, of alternative interpretations on
Mineral Resource estimation.

The use of geology in guiding and controlling Mineral
Resource estimation.

The factors affecting continuity both of grade and
geology.

Mineralised structures at Waihi strike from 320oto 345oand are steeply west dipping. Mineralised lodes at Homeward Bound
strike 325oand are steep east dipping. The main Waihi lodes are interpreted to be the west limbs of a tightly folded antiform.
Homeward Bound lodes are the east limbs of the same antiform. Late stage E-W structures have been mapped and may offset
the mineralised lodes slightly. These structures have also been exploited by thin pegmatite dykes.

Geology model proposed by Model Earth PTY. LTD following a site visit to map pit exposures and selected core

Structural data from OBM drilling was used to guide the orientation of mineralised lodes where possible.

Inspection of core, RC chips and pit exposures shows the mineralisation to be associated with biotite and silica alteration and
quartz-carbonate veining.

Geological continuity of mineralised strictures is well defined, although sometimes terminate abruptly, possibly due to the minor
offsets caused by the E-W structures. The main lodes at Waihi are geologically continuous over 0.9 km and are known to
extend a further 400m south to the Dexy prospect. Grade continuity is less extensive but well defined at a low cut-off grade
(0.4g/t)
Dimensions
The extent and variability of the Mineral Resource
expressed as length (along strike or otherwise), plan
width, and depth below surface to the upper and
lower limits of the Mineral Resource.

The main lodes at Waihi are geologically continuous over 0.9 km in a N-S direction and defined to a depth of 200m below
surface.

The Homeward Bound Lodes are continuous over 0.3 km in a NW-SE direction and defined from surface to a depth of 230 m
below surface.

Page 53 of 65

ADDRESS Level 1, 2 Kings Park Rd, Perth WA 6005 POST PO Box 464, West Perth WA 6872 ABN 69 100 038 266 PHONE +61 8 6365 4548 PHONE (TOLL FREE) 1300 035 592 WEBSITE www.orabandamining.com.au ENQUIRES [email protected]

Criteria JORC Code explanation Commentary
Estimation
and
modelling
techniques

The nature and appropriateness of the estimation
technique(s) applied and key assumptions, including
treatment of extreme grade values, domaining,
interpolation parameters and maximum distance of
extrapolation from data points. If a computer
assisted estimation method was chosen include a
description of computer software and parameters
used.

The availability of check estimates, previous
estimates and/or mine production records and
whether the Mineral Resource estimate takes
appropriate account of such data.

The assumptions made regarding recovery of by-
products.

Estimation of deleterious elements or other non-
grade variables of economic significance (e.g.
sulphur for acid mine drainage characterisation).

In the case of block model interpolation, the block
size in relation to the average sample spacing and
the search employed.

Any assumptions behind modelling of selective
mining units.

Any assumptions about correlation between
variables.

Description of how the geological interpretation was
used to control the resource estimates.

Discussion of basis for using or not using grade
cutting or capping.

The process of validation, the checking process
used, the comparison of model data to drill hole
data, and use of reconciliation data if available.

Ordinary Kriging (OK) and Localised Uniform Conditioning (LUC) was used to estimate gold grades into 3-dimensional block
models. The same mineralisation wireframes were used for the OK and LUC estimations. LUC is a non-linear method able to
estimate the grade distribution of small blocks relative to the available data spacing (i.e. Selective Mining Unit [SMU] sized blocks)
without over-smoothing. Over-smoothing is common when using a linear method such as Ordinary Kriging (OK) on positively
skewed and highly variable gold grade distributions, where the data spacing is relatively wide.

1m composite samples coded to the mineralised domains used as inputs to estimation. Only RC and diamond drilling samples
used for estimation.

Estimation parameters derived from modelled semi-variograms. MicromineTMsoftware was used for the OK estimation. IsatisTM
software was used for the LUC estimation. LUC estimates were exported from Isatis was imported into MicromineTMfor further
processing.

High grade cuts up to 45 g/t were applied to 1m composite data based on analysis of individual domains.

The parent block dimensions used were 10mN by 2mE by 10mRL with sub-cells of 1m by 0.5m by 1.0m. Drill hole spacing is
approximately 20m between section and 20m along section. The parent block size was selected (approx. 50% of data spacing)
using QKNA. The LUC selective mining unit (SMU) was 2m NS by 2.5m EW by 2.5m vertical.

An orientated ellipsoid search was used to select data and was based on Kriging Neighbourhood parameters derived from the
variography.

Estimation completed in 3 runs each with less restrictive search, and minimum sample parameters. The initial interpolation
pass was used with a maximum range less than the range of the principal direction of the modelled variograms. Maximum
number of samples was 16, minimum was 4. A four-sector search was applied to maximise sample representivity in all
directions. Range increased progressively and number of samples required reduced for the third run only.

No estimation of deleterious elements was carried out. Deleterious elements have not been recorded during mining by
previous operators Only Au was interpolated into the block model.

Previous resource estimates have been completed in 2001

The MRE makes use of RC grade control drilling from the previous mining episode in 2003. Production records are not
available to make comparisons.

No assumptions have been made regarding recovery of by-products. Silver has not been routinely assayed.

The relatively narrow (across strike) selective mining unit (SMU) was defined based on a selective mining method (rather than
bulk mining) and reflects a minimum size that could be defined by grade control drilling.

Only Au was estimated so correlation analysis was not possible

The deposit mineralisation was constrained by wireframes constructed using a 0.4 g/t Au cut-off grade in association with
logged geology, particularly the presence of quartz veining and biotite-sulphide alteration. The wireframes were applied as hard
boundaries in the estimate.

The validation was carried out by three methods:
o
Visual comparison of block grades with nearby drill assay results on a section by section basis.
o
Statistical comparison of estimated grades and composite grades on a domain by domain basis.
o
Trend analysis of estimated block model grades versus composite grades on 10m northing and 5m vertical
intervals.
Moisture
Whether the tonnages are estimated on a dry basis
or with natural moisture, and the method of
determination of the moisture content.

Tonnages and grades were estimated on a dry in situ basis. No moisture values were reviewed.
Cut-off parameters
The basis of the adopted cut-off grade(s) or quality
parameters applied.

The open pit Mineral Resource has been reported at a 0.5 g/t Au cut-off from the LUC model based on assumptions about
economic cut-off grades for open pit mining.

The portions of the Mineral Resource that exists below the pit shell was reported from the OK model using a 2 g/t cut-off grade,
being an approximate estimate of the incremental cut-off for narrow vein underground open stoping.
Mining factors or
assumptions

Assumptions made regarding possible mining
methods, minimum mining dimensions and internal
(or, if applicable, external) mining dilution. It is

It is intended to adopt a selective open cut mining practise at the deposit.

Reasonable prospects for eventual economic extraction for the Waihi Mineral Resource update was confirmed by applying the
conceptual AU$2,400per ouncepit shell which wasgenerated usingthe Mineral Resource block model described above. A

Page 54 of 65

ADDRESS Level 1, 2 Kings Park Rd, Perth WA 6005 POST PO Box 464, West Perth WA 6872 ABN 69 100 038 266 PHONE +61 8 6365 4548 PHONE (TOLL FREE) 1300 035 592 WEBSITE www.orabandamining.com.au ENQUIRES [email protected]

Criteria JORC Code explanation Commentary
always necessary as part of the process of
determining reasonable prospects for eventual
economic extraction to consider potential mining
methods, but the assumptions made regarding
mining methods and parameters when estimating
Mineral Resources may not always be rigorous.
Where this is the case, this should be reported with
an explanation of the basis of the mining
assumptions made.
theoretical economic mining volumes was determined from the Indicated and Inferred material within the unconstrained Mineral
Resource. Pit slopes used in the conceptual optimisation were based on preliminary geotechnical assessment of Waihi deposit.
Allowance was made in the pit slopes for in-pit ramps. Assumed mining costs were applied on a progressive bench by bench
basis using contractor supplied budget quotations for the Davyhurst project received in October 2018 for the Davyhurst project
area. The average mining costs for the pit shell was estimated to be $4.21 per tonne of material mined which included the cost
to remove the existing tailings. A dilution factor of 15% and mining recovery of 95% was applied to define the theoretical
economic mining volumes within the pit shell. The conceptual combined haulage, processing and administration cost applied
was $39.33 per tonne processed and process recoveries of between 92% and 93% were applied based on weathering domains.

The underground cut-off was based on a mining cost of $140 per tonne of ore, a dilution of 15% and mining recovery of 95%.
With the exception of the underground cut-off, no other modifying factors were applied to the underground portion of the
Mineral Resource.
Metallurgical
factors
or
assumptions

The basis for assumptions or predictions regarding
metallurgical amenability. It is always necessary as
part of the process of determining reasonable
prospects for eventual economic extraction to
consider potential metallurgical methods, but the
assumptions regarding metallurgical treatment
processes and parameters made when reporting
Mineral Resources may not always be rigorous.
Where this is the case, this should be reported with
an explanation of the basis of the metallurgical
assumptions made.

Waihi has no known reported metallurgical issues and has been previously mined.

Results from previous processing (using CIP) have demonstrated that good gold recovery can be expected from modern
conventional CIP processing methods.

Recent test work from Waihi ores give the following recoveries:
o
Oxide – 94%
o
Transitional – 92%
o
Fresh – 90%
Environmental
factors
or
assumptions

Assumptions made regarding possible waste and
process residue disposal options. It is always
necessary as part of the process of determining
reasonable prospects for eventual economic
extraction to consider the potential environmental
impacts of the mining and processing operation.
While at this stage the determination of potential
environmental impacts, particularly for a greenfields
project, may not always be well advanced, the status
of early consideration of these potential
environmental impacts should be reported. Where
these aspects have not been considered this should
be reported with an explanation of the environmental
assumptions made.

The area is not located in an environmentally sensitive area so there is no reason to believe that environmental approvals
would materially restrict development of the project and surface waste rock landforms for Waihi.
Bulk density
Whether assumed or determined. If assumed, the
basis for the assumptions. If determined, the method
used, whether wet or dry, the frequency of the
measurements, the nature, size and
representativeness of the samples.

The bulk density for bulk material must have been
measured by methods that adequately account for
void spaces (vugs, porosity, etc), moisture and
differences between rock and alteration zones within
the deposit.

Discuss assumptions for bulk density estimates used

Bulk density determinations were derived from measurements (immersion method) made on recent core samples drilled by
OBM. Results compared favourably with limited measurements taken by previous operators using the calliper method.

Bulk density values used in the resource were 1.9 t/m3, 2.5 t/m3 and 2.94 t/m3 for oxide, transitional and fresh material, both
ore and waste.

It is assumed there are minimal void spaces in the rocks within the Waihi deposit. Values applied in the Waihi block model are
similar to other known bulk densities from similar geological terrains.

Page 55 of 65

ADDRESS Level 1, 2 Kings Park Rd, Perth WA 6005 POST PO Box 464, West Perth WA 6872 ABN 69 100 038 266 PHONE +61 8 6365 4548 PHONE (TOLL FREE) 1300 035 592 WEBSITE www.orabandamining.com.au ENQUIRES [email protected]

Criteria JORC Code explanation Commentary
in the evaluationprocess of the different materials.
Classification
The basis for the classification of the Mineral
Resources into varying confidence categories.

Whether appropriate account has been taken of all
relevant factors (i.e. relative confidence in
tonnage/grade estimations, reliability of input data,
confidence in continuity of geology and metal values,
quality, quantity and distribution of the data).

Whether the result appropriately reflects the
Competent Person’s view of the deposit.
Mineral Resources were classified in accordance with the Australasian Code for the Reporting of Exploration Results, Mineral
Resources and Ore Reserves (JORC, 2012). The classification takes account of confidence in the geological interpretation, sample
density and assay QAQC. In order to avoid a mosaic style of classification, solid wireframes were constructed to encompass areas
considered to adequately fulfil the requirement to be classified as either, measured, indicated or inferred:

Measured – No areas of the current resource attained Measured status

Indicated – Areas with drill spacing up to approximately 30 mE x 30 mN and with reasonable confidence in the geological
interpretation and grade continuity

Inferred – Areas with drill spacing in excess of 30 mE x 30 mN and where grade continuity is poorer as defined by a
lower sample density, even though geological continuity may be apparent.

The input data is comprehensive and of sufficient quality for use in the MRE. Significant recent drilling, covering the entire
deposit, has confirmed the location and tenor of many historic drill-holes. Assay QAQC is of sufficient quality for the assays to
be used in the MRE. There is sufficient understanding of the geology to support the current interpretation in terms of continuity.

The Mineral Resource estimate appropriately reflects the view of the Competent Person.
Audits or reviews
The results of any audits or reviews of Mineral
Resource estimates.

The Waihi MRE has been reviewed by CSA Global.
Discussion
of
relative
accuracy/
confidence

Where appropriate a statement of the relative
accuracy and confidence level in the Mineral
Resource estimate using an approach or procedure
deemed appropriate by the Competent Person. For
example, the application of statistical or
geostatistical procedures to quantify the relative
accuracy of the resource within stated confidence
limits, or, if such an approach is not deemed
appropriate, a qualitative discussion of the factors
that could affect the relative accuracy and
confidence of the estimate.

The statement should specify whether it relates to
global or local estimates, and, if local, state the
relevant tonnages, which should be relevant to
technical and economic evaluation. Documentation
should include assumptions made and the
procedures used.

These statements of relative accuracy and
confidence of the estimate should be compared with
production data, where available.

The Waihi Mineral Resource estimate is considered to be reported with a reasonable degree of confidence. The data quality is
good and the drill holes from recent drilling have detailed logs produced by qualified geologists. Historic logging has been
reviewed.

The Mineral Resource statement relates to global estimates of tonnes and grade. Confidence in the estimate allows
reasonable quantification of global metal content. However, at a local scale there are risks associated with the estimation. The
interpretation is considered globally robust but at a local scale, variations to ore geometry can be expected.

The deposit is not currently being mined.

Waihi Production records up to December 1996 are available. Total ore reserves were 761Kt @ 2.41 g/t for 59,000 ounces. Mill
production was 704Kt @ 2.39 g/t for 54,000 ounces.

11.6 Section 3 Estimation and Reporting of Mineral Resources - Callion

Criteria JORC Code explanation Commentary
Database integrity
Measures taken to ensure that data has not been
corrupted by, for example, transcription or keying
errors, between its initial collection and its use for
Mineral Resource estimation purposes.

Data validationprocedures used.

Data from EGS/OBM drilling captured into Field Marshall logging software. Data sent from site and imported into SQL database
via DBMS. Validation checks in SQL database are carried out to ensure data integrity is not compromised.

The data is verified by company geologists before being sent to the DBA for validation or passing Geobank Software validation
protocols.

Historic data has been verified bycheckinghistorical reports on theproject.

Page 56 of 65

ADDRESS Level 1, 2 Kings Park Rd, Perth WA 6005 POST PO Box 464, West Perth WA 6872 ABN 69 100 038 266 PHONE +61 8 6365 4548 PHONE (TOLL FREE) 1300 035 592 WEBSITE www.orabandamining.com.au ENQUIRES [email protected]

Criteria JORC Code explanation Commentary

The Competent Person has undertaken a number of validation checks on the database, using Micromine software which include,
but are not limited to, checks for overlapping intervals, checks for missing data/records, visual checks on drill hole locations and
traces to identify any possible survey issues. No major issues were detected.
Site visits
Comment on any site visits undertaken by the
Competent Person and the outcome of those visits.

If no site visits have been undertaken indicate why
this is the case.

Site visits have been completed by the Competent Person with the following objectives:
o
View geology in existing open pit
o
View drilling operations
o
View drill core
Geological
interpretation

Confidence in (or conversely, the uncertainty of) the
geological interpretation of the mineral deposit.

Nature of the data used and of any assumptions
made.

The effect, if any, of alternative interpretations on
Mineral Resource estimation.

The use of geology in guiding and controlling Mineral
Resource estimation.

The factors affecting continuity both of grade and
_geology. _

The geology of the system and the gold distribution is modelled as a set of sub-parallel, NNW-SSE striking, steeply dipping
narrow lodes.

The continuity of mineralisation and volume controls are reasonably well established where drilling is at a nominal 10m (X) by
10m (Y) hole spacing.

The use of historical drilling provides a level of uncertainty as the company cannot validate all the QAQC data and downhole
survey data.

The selection of mineralised domains has used geological factors such as geological contacts, logged quartz and sulphides in
conjunction with a 0.5g/t cut-off. Gold values transition from background to ore grades over a very short distance.
Dimensions
The extent and variability of the Mineral Resource
expressed as length (along strike or otherwise), plan
width, and depth below surface to the upper and
lower limits of the Mineral Resource.

The reported mineralised corridor extends 900m NNW-SSE, up to 40m east/west (in multiple narrow lodes) and up to 150m
vertically.

Mineralised structures are present at surface for some lodes and have been mined by both open pit and underground methods.
Estimation
and
modelling
techniques

The nature and appropriateness of the estimation
technique(s) applied and key assumptions, including
treatment of extreme grade values, domaining,
interpolation parameters and maximum distance of
extrapolation from data points. If a computer
assisted estimation method was chosen include a
description of computer software and parameters
used.

The availability of check estimates, previous
estimates and/or mine production records and
whether the Mineral Resource estimate takes
appropriate account of such data.

The assumptions made regarding recovery of by-
products.

Estimation of deleterious elements or other non-
grade variables of economic significance (e.g.
sulphur for acid mine drainage characterisation).

In the case of block model interpolation, the block
size in relation to the average sample spacing and
the search employed.

Any assumptions behind modelling of selective
mining units.

Any assumptions about correlation between
variables.

Description of how thegeological interpretation was

1m composite samples coded to the mineralised domains used as inputs to estimation. Only RC & diamond drilling samples
used for estimation.

Ordinary Kriging (OK) was used to estimate gold grades into a 3-dimensional block model. Estimation parameters were derived
from modelled semi-variograms using SupervisorTMsoftware. SurpacTMsoftware was used for the estimation.

High grade cuts up to 60 g/t were applied to 1m composite data based on analysis of individual domains.

The parent block dimensions used were 5mE by 4mN by 5mRL with sub-cells of 0.25m by 0.5m by 1.25m. Drill hole spacing is
down to approximately 10m between sections and 10m along section. The parent block size selected is approx. 50% of data
spacing

An orientated ellipsoid search was used to select data and was based on parameters derived from the variography.

Estimation completed in 3 runs each with less restrictive search, and minimum sample parameters. The initial interpolation pass
used a search range of 30m, the second pass 60m. The third pass search expanded to fill blocks. Maximum number of samples
was 12, minimum was 6 and the maximum samples per hole was 4.

No estimation of deleterious elements was carried out. Deleterious elements have not been recorded during mining of Callion.
Copper is known to be present at Callion. Only Au was interpolated into the block model.

Previous resource estimates have been completed in 2008

Open pit production records are available for Callion from mining in 2005. The mined tonnes were 37% higher than the reserve
tonnes and the mined grade was 2.82g/t versus 2.29g/t for the reserve grade. 70% more ounces were mined. A comparison to
the grade control model has not been done as yet.

No assumptions have been made regarding recovery of by-products. Copper is present but has not been routinely assayed and
is not modelled.

Selective mining units were not modelled in the Mineral Resource.

Only Au was estimated so correlation analysis was not possible

The deposit mineralisation was constrained by wireframes constructed using a 0.5 g/t Au cut-off grade in association with logged
geology. The wireframes were applied as hard boundaries.

Page 57 of 65

ADDRESS Level 1, 2 Kings Park Rd, Perth WA 6005 POST PO Box 464, West Perth WA 6872 ABN 69 100 038 266 PHONE +61 8 6365 4548 PHONE (TOLL FREE) 1300 035 592 WEBSITE www.orabandamining.com.au ENQUIRES [email protected]

Criteria JORC Code explanation Commentary
used to control the resource estimates.

Discussion of basis for using or not using grade
cutting or capping.

The process of validation, the checking process
used, the comparison of model data to drill hole
data, and use of reconciliation data if available.

Grade Top cuts were selected to minimise the effect of isolated high-grade outliers, without severely reducing metal or cutting a
large proportion of data. Top cuts were decided by using a combination of methods including grade histograms, log probability
plots and statistical tools.

The block model validation was carried out by three methods:
o
Visual comparison of block grades with nearby drill assay results on a section by section basis.
o
Statistical comparison of estimated grades and composite grades on a domain by domain basis.
o
Trend analysis of estimated block model grades versus composite grades on 10m northing and 5m vertical intervals.
Moisture
Whether the tonnages are estimated on a dry basis
or with natural moisture, and the method of
determination of the moisture content.

Tonnages and grades were estimated on a dry in situ basis. No moisture values were reviewed.
Cut-off parameters
The basis of the adopted cut-off grade(s) or quality
parameters applied.

The Mineral Resource has been reported at a 0.5 g/t Au cut-off based on assumptions about economic cut-off grades for
selective open pit mining.
Mining factors or
assumptions

Assumptions made regarding possible mining
methods, minimum mining dimensions and internal
(or, if applicable, external) mining dilution. It is
always necessary as part of the process of
determining reasonable prospects for eventual
economic extraction to consider potential mining
methods, but the assumptions made regarding
mining methods and parameters when estimating
Mineral Resources may not always be rigorous.
Where this is the case, this should be reported with
an explanation of the basis of the mining
assumptions made.

It is initially intended to continue open pit mining at Callion using a selective mining method.

Reasonable prospects for eventual economic extraction for the Callion Mineral Resource update was confirmed by applying the
conceptual AU$2,400 per ounce pit shell which was generated using the Mineral Resource block model described above. A
theoretical economic mining volumes was determined from the Indicated and Inferred material within the unconstrained Mineral
Resource. Pit slopes used in the conceptual optimisation applied slope parameters typical of the region, with geotechnical
assessments for the DFS in progress. Allowance was made in the pit slopes for in-pit ramps. Assumed mining costs were
applied on a progressive bench by bench basis using contractor supplied budget quotations for the Davyhurst project received
in March 2020 for the Davyhurst project area. The average mining costs for the pit shell was estimated to be $3.93 per tonne
of material mined which included the cost to remove a portion of the adjacent waste landform and rehabilitate the site. A dilution
factor of 30% and mining recovery of 95% was applied to define the theoretical economic mining volumes within the pit
shell. The conceptual combined haulage, processing and administration cost applied was $34.66 per tonne processed.
Metallurgical
factors
or
assumptions

The basis for assumptions or predictions regarding
metallurgical amenability. It is always necessary as
part of the process of determining reasonable
prospects for eventual economic extraction to
consider potential metallurgical methods, but the
assumptions regarding metallurgical treatment
processes and parameters made when reporting
Mineral Resources may not always be rigorous.
Where this is the case, this should be reported with
an explanation of the basis of the metallurgical
assumptions made.

Callion has no known reported metallurgical issues and has been previously mined.

Results from previous processing (using CIP) have demonstrated that good gold recovery can be expected from modern
conventional CIP processing methods.

Recent test work from Callion ores give the following recoveries:
o
Oxide – 91%
o
Transitional – 91%
o
Fresh – 90%
Environmental
factors
or
assumptions

Assumptions made regarding possible waste and
process residue disposal options. It is always
necessary as part of the process of determining
reasonable prospects for eventual economic
extraction to consider the potential environmental
impacts of the mining and processing operation.
While at this stage the determination of potential
environmental impacts, particularly for a greenfields
project, may not always be well advanced, the status
of early consideration of these potential
environmental impacts should be reported. Where
these aspects have not been considered this should
be reported with an explanation of the environmental

The area is not located in an environmentally sensitive area so there is no reason to believe that environmental approvals
would materially restrict development of the project.

Page 58 of 65

ADDRESS Level 1, 2 Kings Park Rd, Perth WA 6005 POST PO Box 464, West Perth WA 6872 ABN 69 100 038 266 PHONE +61 8 6365 4548 PHONE (TOLL FREE) 1300 035 592 WEBSITE www.orabandamining.com.au ENQUIRES [email protected]

Criteria JORC Code explanation Commentary
assumptions made.
Bulk density
Whether assumed or determined. If assumed, the
basis for the assumptions. If determined, the method
used, whether wet or dry, the frequency of the
measurements, the nature, size and
representativeness of the samples.

The bulk density for bulk material must have been
measured by methods that adequately account for
void spaces (vugs, porosity, etc), moisture and
differences between rock and alteration zones within
the deposit.

Discuss assumptions for bulk density estimates used
in the evaluationprocess of the different materials.

Bulk density determinations were derived from measurements (immersion method) on core samples

Densities were applied based on weathering profile and whether in ore/waste.

Bulk density values used in the resource for ore were oxide = 1.74 t/m3, transitional=2.5 t/m3and fresh 2.78 t/m3. Waste
densities were 1.74 t/m3(oxide), 2.50 t/m3(trans), 3.0 t/m3(fresh Basalt) and 2.7 t/m3(fresh Felsite).

It is assumed there are minimal void spaces in the rocks within the Callion deposit. Values in the Callion block model are
similar to other known bulk densities from similar geological terrains.
Classification
The basis for the classification of the Mineral
Resources into varying confidence categories.

Whether appropriate account has been taken of all
relevant factors (i.e. relative confidence in
tonnage/grade estimations, reliability of input data,
confidence in continuity of geology and metal values,
quality, quantity and distribution of the data).

Whether the result appropriately reflects the
Competent Person’s view of the deposit.

Mineral Resources were classified in accordance with the Australasian Code for the Reporting of Exploration Results, Mineral
Resources and Ore Reserves (JORC, 2012). In order to avoid a mosaic style of classification, solid wireframes were constructed
to encompass areas considered to adequately fulfil the requirement to be classified as either indicated or inferred. Determining
classification involved consideration of multiple factors including confidence in the geological model, continuity of mineralized
zones, drill hole spacing, confidence in the underlying drill hole database, availability of bulk density information plus information
and knowledge from previous mining. In part, the lodes have been drilled down to 10m x 10m spacing, and even areas of 5m
by 5m grade control, on northing and easting, with drill lines running approximately ENE-WSW. Previous open pit and
underground mining knowledge adds significantly to the confidence of the classification, albeit minor uncertainty on known
underground voids. With all these factors considered, the resource estimate has in part been assigned to Indicated resources
with the remainder to the Inferred category. No Measured resources have been assigned.

The input data is comprehensive and of sufficient quality for use in the MRE. Significant recent drilling, covering the entire deposit,
has confirmed the location and tenor of many historic drill-holes. Assay QAQC is of sufficient quality for the assays to be used in
the MRE. There is sufficient understanding of the geology to support the current interpretation in terms of continuity.

The Mineral Resource estimate appropriately reflects the view of the Competent Person.
Audits or reviews
The results of any audits or reviews of Mineral
Resource estimates.

The reported Mineral Resource Estimate has been reviewed by CSA Global.
Discussion
of
relative
accuracy/
confidence

Where appropriate a statement of the relative
accuracy and confidence level in the Mineral
Resource estimate using an approach or procedure
deemed appropriate by the Competent Person. For
example, the application of statistical or
geostatistical procedures to quantify the relative
accuracy of the resource within stated confidence
limits, or, if such an approach is not deemed
appropriate, a qualitative discussion of the factors
that could affect the relative accuracy and
confidence of the estimate.

The statement should specify whether it relates to
global or local estimates, and, if local, state the
relevant tonnages, which should be relevant to
technical and economic evaluation. Documentation
should include assumptions made and the
procedures used.

These statements of relative accuracy and
confidence of the estimate should be compared with

The Callion Mineral Resource estimate reported with a reasonable degree of confidence. The data quality is good and the drill
holes from recent drilling have detailed logs produced by qualified geologists.

The Mineral Resource statement relates to global estimates of tonnes and grade. Confidence in the estimate allows reasonable
quantification of global metal content. However, at a local scale there are risks associated with the estimation. The interpretation
is considered globally robust but at a local scale variation to ore geometry can be expected.

Page 59 of 65

ADDRESS Level 1, 2 Kings Park Rd, Perth WA 6005 POST PO Box 464, West Perth WA 6872 ABN 69 100 038 266 PHONE +61 8 6365 4548 PHONE (TOLL FREE) 1300 035 592 WEBSITE www.orabandamining.com.au ENQUIRES [email protected]

Criteria JORC Code explanation Commentary
production data, where available.

11.7 Section 4 Estimation and Reporting of Ore Reserves

Criteria JORC Code explanation Commentary
Mineral Resource
estimate for
conversion to Ore
Reserves

Description of the Mineral Resource estimate used
as a basis for the conversion to an Ore Reserve.

Clear statement as to whether the Mineral
Resources are reported additional to, or inclusive
of, the Ore Reserves.

The Ordinary Kriged (OK) open pit Mineral Resources were completed by Ora Band Mining (OBM) and formed the basis for
re-estimation of the resources by Localised Uniform Conditioning (LUC) method. CSA Global were engaged to produce LUC
estimates at the SMU scale for Riverina, Waihi, Missouri and Sand King deposits, based on inputs provided by OBM.

Golden Eagle underground resource estimate and the Callion open pit resource estimate and were completed using the OK
method and details are available in the ASX announcements dated 8 April 2020 and 15 May 2020 respectively.

The LUC estimates were used as the basis of the open pit Ore Reserve for Riverina, Missouri, Sand King and Waihi deposits.

The OK estimates were used as the basis for the open pit Ore Reserve for Callion and the underground Ore Reserve for
Golden Eagle.

Mineral Resources are reported inclusive of the Ore Reserves.
Site visits
Comment on any site visits undertaken by the
Competent Person and the outcome of those visits.

If no site visits have been undertaken indicate why
this is the case.

The site was visited by Mr Geoff Davidson in DD May 20th, 2020 who is the Competent Person for this Ore Reserve estimate.
During the site visit, representative diamond drill core for each of the deposits was inspected for areas within the proposed
mining envelopes. In addition, visits were made to each of the proposed mining locations and inspections were made of the
existing plant site and associated infrastructure at Davyhurst. Mr Davidson is satisfied the conditions allowed for in this Ore
Reserve estimate is consistent with the observations made duringthe site visit.
Study status
The type and level of study undertaken to enable
Mineral Resources to be converted to Ore
Reserves.

The Code requires that a study to at least Pre-
Feasibility Study level has been undertaken to
convert Mineral Resources to Ore Reserves. Such
studies will have been carried out and will have
determined a mine plan that is technically
achievable and economically viable, and that
material Modifying Factors have been considered.

This Ore Reserve estimate forms the basis for Definitive Feasibility study for the Davyhurst operation. The mining costs for
Riverina, Sand King and Missouri open pits as well as Golden Eagle underground that were used to determine the economic
mining envelopes and convert Mineral Resources into Ore Reserves are based on budget level mining costs specific to the
locations considered for a similar scope of work. The mining costs for Waihi and Callion open pit were based on factored
estimates using composited costs from other mining areas within the study. Further investigative and analytical work is
required on rehandling and disposal of the tailings at Waihi. Both Waihi and Callion are considered to be at a pre-feasibility
level of study. Waihi and Callion are schedule to be mined after the estimated project payback period. The mining study is
considered to be at a feasibility level of confidence.

The Ore Reserve was developed using an indicative mine plan which is considered to be technically feasible and
economicallyviable. Modifyingfactors were applied when estimatingthe Ore Reserve from the Mineral Resource.
Cut-off parameters
The basis of the cut-off grade(s) or quality
parameters applied.

Cut-off grade parameters were determined using 2020 mining cost received from contractors in response to a preliminary
request for quotation for the Sand King, Missouri and Riverina open pits as well as Golden Eagle underground. The requested
used preliminary designs and schedules from earlier work carried out in 2019 and 2020. The mining costs include provision for
rehabilitation of waste rock landforms. Ore haulage costs were provided by haulage contractors in response to a preliminary
RFQ issued in 2020. Processing costs were compiled by GR Engineering Pty Ltd for the upgraded Davyhurst plant. Site
general costs and administration overheads (G&A) were based on a preliminary estimate. Selling costs were based on
quotation from the Perth Mint and Standard State Royalties were applied. Metallurgical process recoveries were based on
metallurgical test work conducted in 2019 and 2020 and supervised by OBM’s metallurgical consultant.

A base price of A$ 2100 per ounce was used to determine the economic mining envelope.

Ore treatment cost include grade control, ore haulage, crusher loading, processing and site G&A. The costs vary
between $34 and $42 per tonne depending on location and weathering classification (i.e. oxide, transition and fresh)

Processing recoveries vary between 85% and 95% depending on location and weathering classification.

Selling costs inclusive of smelter charges and state royalties were estimated to be $45 per ounce of recovered gold. No
provision was made for third party royalties.

The incremental cut-off grades for the open pits vary between 0.54 g/t and 0.77 g/t for the open pit, depending on
location and weatheringclassification.

Page 60 of 65

ADDRESS Level 1, 2 Kings Park Rd, Perth WA 6005 POST PO Box 464, West Perth WA 6872 ABN 69 100 038 266 PHONE +61 8 6365 4548 PHONE (TOLL FREE) 1300 035 592 WEBSITE www.orabandamining.com.au ENQUIRES [email protected]


The underground cut-off grade applied to Golden Eagle was estimated to be 2.7 g/t. This estimate includes provision for
stope development and drill, blast, load and haul as well as mining overheads specific to underground. These mining
costs were estimated to be $130 per tonne. The ore treatment costs were estimated to be $35 per tonne and includes
ore haulage and RoM operations. The process recovery was estimated to be 92% for both operations. An incremental
cut-off of 0.7 g/t was applied to development, based on the ore treatment costs.

For both open pit and underground operations the cut-off grades were applied to the diluted Mineral Resource, In the
case of the underground operations this was done followingstope optimisation and design
Mining factors or
assumptions

The method and assumptions used as reported in
the Pre-Feasibility or Feasibility Study to convert
the Mineral Resource to an Ore Reserve (i.e. either
by application of appropriate factors by optimisation
or by preliminary or detailed design).

The choice, nature and appropriateness of the
selected mining method(s) and other mining
parameters including associated design issues
such as pre-strip, access, etc.

The assumptions made regarding geotechnical
parameters (eg pit slopes, stope sizes, etc), grade
control and pre-production drilling.

The major assumptions made and Mineral
Resource model used for pit and stope optimisation
(if appropriate).

The mining dilution factors used.

The mining recovery factors used.

Any minimum mining widths used.

The manner in which Inferred Mineral Resources
are utilised in mining studies and the sensitivity of
the outcome to their inclusion.

The infrastructure requirements of the selected
mining methods.














Open Pit Mining Factors and Assumptions
Detailed mine designs were used as the basis for the Ore Reserve estimate. These designs were derived from economic
envelopes determined from Whittle pit optimisation using the parameters described above. Average mining costs allowed for
varied between $3.90 and $5.10 per tonne of material, depending on location, and include provisions for drill, blast, load, haul,
rehab and OBM mine management and technical support. Pit designs generally reconciled within 12% or better of the
generated pit shell.
The open pit costs are based on conventional selective mining methods. Open cut operations are planned around using a
combination of 120 t and 200 t class excavators, in combination with 90-100 t class dump trucks. All material, excluding
existing in-pit backfill or historical waste dumps, was assumed to require drilling and blasting using ANFO or emulsion for
costing and scheduling purposes. The mining method is conventional and deemed appropriate.
Minimum mining widths of 20 m were allowed on all open pit cutbacks required adjacent to existing pit excavations.
Waihi will require in-pit tailings to be rehandled and co-disposed with waste rock in a surface waste landform. This will require
specific mining techniques given their unconsolidated nature.
The mining methods proposed are well-known and widely used in the local mining industry, and productivity rates and costing
can be predicted with an appropriate degree of accuracy.
Suitable access exists to each of the mining operations.
The mining method contemplates selective separation waste from the ore to minimise dilution and ore loss. Ore faces will be
exposed by removing waste to the identified contact prior to removing the ore. For the underground operations blast holes for
stoping will be drilled close to or inside the ore-waste contact.
Independent consultants prepared a geotechnical analysis to a suitable level of detail. This forms the basis of pit wall design
criteria and underground pillar spacing, as well as ground support requirements.
Cost allowances were made for grade control activities, including in-pit reverse circulation drilling and face sampling.
Only the Indicated and Measured portion of the Mineral Resource were used to determine the Ore Reserve. All Inferred
material was treated as waste with a grade of zero. The Ore Reserve was determined to be technically and economically
viable at the base price, without the inclusion of Inferred Mineral Resource material.
Open pit mining blocks were diluted by applying a dilution skin of waste at zero grade. The dilution skin thickness varied
between 0.25 m and 0.5 m depending on the grade distribution at the wireframe boundary and the lode geometry. The thinner
dilution skins were used where low grade samples were included within the wireframe and used in the estimation. The thicker
dilution skins were used where grade boundaries were sharper and/or ore geometries were flatter. The global dilution factors
reconcile to 22% for Riverina, 43% for Missouri, 29% for Sand King, 13% for Waihi and 23% for Callion.
Open pit mining recovery was based on a nominal 5% ore loss applied to blocks above the economic cut off within the pit
design.
Underground Mining Factors and Assumptions
Golden Eagle is a ‘brownfields’ project. The mining method proposed for Golden Eagle is narrow-vein long hole open stoping
using up-hole-benching techniques. This method has been successfully and comprehensively used at Golden Eagle in the
past.
Stopes were defined by applying a 2.7 g/t to the diluted Mineral Resource. The cut-off allows for cost of ore drive development
and stoping, as well as load and haul downstream processing and sales.
The diluted Mineral Resource was defined using a stope shape optimiser. A minimum mining width of 0.7 m was used be
application of the dilution skin.

Page 61 of 65

ADDRESS Level 1, 2 Kings Park Rd, Perth WA 6005 POST PO Box 464, West Perth WA 6872 ABN 69 100 038 266 PHONE +61 8 6365 4548 PHONE (TOLL FREE) 1300 035 592 WEBSITE www.orabandamining.com.au ENQUIRES [email protected]


The dilution allows for a skin of 0.3 m on both hanging wall and footwall. In addition, a nominal allowance of 5% dilution was
included to account for unidentified dilution sources. The global dilution reconciled to 32% for Golden Eagle. The Golden
Eagle Ore Reserves includes dilution of 34,000 t at 0.77 g/t.

An incremental cut-off of 0.7 g/t was applied to ore drive development. This cut-off was applied on a cut by cut basis and
allows for ore haulage, processing and sales.

Each stoping level was evaluated for waste development costs to ensure the combined production from the level was above
breakeven.

Grade control will be by face sampling.
Infrastructure

Most of the infrastructure required for the operations is already in place at the Davyhurst Project, including a process plant and
associated infrastructure, camp, airstrip, offices, power reticulation, borefields and coreyards. A remote fly-camps will be
constructed near the Missouri and Sand King operations.

The Golden Eagle underground is readily accessible, and provisions are included to rehabilitate the relevant workings and re-
establish mine services.
Metallurgical factors
or assumptions

The metallurgical process proposed and the
appropriateness of that process to the style of
mineralisation.

Whether the metallurgical process is well-tested
technology or novel in nature.

The nature, amount and representativeness of
metallurgical test work undertaken, the nature of
the metallurgical domaining applied and the
corresponding metallurgical recovery factors
applied.

Any assumptions or allowances made for
deleterious elements.

The existence of any bulk sample or pilot scale test
work and the degree to which such samples are
considered representative of the orebody as a
whole.

For minerals that are defined by a specification,
has the ore reserve estimation been based on the
appropriate mineralogy to meet the specifications?

The proposed process for treating ore is conventional CIP with some gold recovered via gravity circuit. This is a standard gold
processing flowsheet used throughout the industry for this style of mineralisation.

Metallurgical test work was carried out on the fresh mineralisation domains for all deposits in this Ore Reserve estimate. Test
work has also been completed for oxide and transitional domains at Riverina. Metallurgical recoveries for Sand King and
Missouri oxide and transitional domains were assumed based on the metallurgical consultants past experience with similar
deposits. Metallurgical recoveries aregiven in the followingtable.
Oxide
Transition

Fresh
Oxide

Transition
Fresh

Location
Process Recovery
Proportion of Ore Reserve
Sand King
94%#
92%#,1
85%
3%
16%
81%
Missouri
94%#
92%#
92%
1%
5%
94%
Riverina
95%#,2
95%#,2
95%#,2
32%
41%
26%
Waihi
94%#
92%#
89.8%
1%
3%
96%
Callion
91%#
91%#,3
90%#,3
9%
66%
25%
Golden Eagle UG
N/A
N/A
92%#,4
0%
0%
100%
# Assumed value
* All values are rounded to two significant figures
1. Subsequent test work estimated the Sand King transitional recovery to be 95.7%
2. Subsequent test work estimated the Riverina recoveries to be 90.1%, 97.6% and 94.3% for oxide, transition and fresh, respectively.
3. Subsequent test work estimated the Callion transitional recovery to be 91.3% and fresh to be 92.5%
4. Subsequent test work estimated the Golden Eagle fresh recovery to be 90.6%

Metallurgical samples tested were taken from locations within their respective mining envelopes. Several samples were tested
from domains defined by weathering state and geology. Results are considered to be a reasonable indication of expected
metallurgical performance.

The process plant will have a nominal throughput rate of 1.2 Mtpa based on a grind size of 106 µm. The process plant was
operated successfully in the past and is currently on care and maintenance.

Metallurgical testing was performed on diamond drill holes in well-known and recognised laboratories to standard test
practices on enough samples to be representative of their respective different domains.

Riverina test work has indicated and increased lime consumption compared other locations. Adjustment to the processing cost
were included to allow for this. No other deleterious elements material to metallurgical performance were identified in the

Page 62 of 65

ADDRESS Level 1, 2 Kings Park Rd, Perth WA 6005 POST PO Box 464, West Perth WA 6872 ABN 69 100 038 266 PHONE +61 8 6365 4548 PHONE (TOLL FREE) 1300 035 592 WEBSITE www.orabandamining.com.au ENQUIRES [email protected]

material considered in this Ore Reserve.
Environmental
The status of studies of potential environmental
impacts of the mining and processing operation.
Details of waste rock characterisation and the
consideration of potential sites, status of design
options considered and, where applicable, the
status of approvals for process residue storage and
waste dumps should be reported.

All flora and fauna baseline studies have been completed for areas that may potentially be influenced by mining operations
contemplated in this Ore Reserve estimate. No conservation significant taxa were identified as being at risk.

Searches of Indigenous and European State Heritage Registers have not identified any sites that require active management.

Potential environmental impacts will be risk managed as part of the DMIRS Mining

Both historical and recent geochemical data indicate waste rock mass is non-acid forming.

Tailings from ore processing will be stored within the existing Tailings Storage Facility (TSF). Allowance has been made for
expansions to this facility as required by the mine plan.

Tailings from the Waihi pit will be co-disposed with waste rock. Test work and design for this facility are ongoing

The Competent Person is not aware of anyreason why permittingwill not begranted within a reasonable time frame.
Infrastructure
The existence of appropriate infrastructure:
availability of land for plant development, power,
water, transportation (particularly for bulk
commodities), labour, accommodation; or the ease
with which the infrastructure can be provided, or
accessed.

Substantial infrastructure exists on-site from previous operations which ceased in 2018 and has been under care and
maintenance since. Costs for refurbishment of this infrastructure was allowed for.

Road train haul routes will be upgraded or modified for the proposed operations where required.

Capacity of the existing tailings storage facility will be increased.

A fly-camps will be constructed at the Siberia (Sand King / Missouri) mine site and communication to these facilities will be
upgraded.
Costs
The derivation of, or assumptions made, regarding
projected capital costs in the study.

The methodology used to estimate operating costs.

Allowances made for the content of deleterious
elements.

The source of exchange rates used in the study.

Derivation of transportation charges.

The basis for forecasting or source of treatment
and refining charges, penalties for failure to meet
specification, etc.

The allowances made for royalties payable, both
Government and private.

The capital estimate for the process plant and infrastructure was compiled as a first principles estimated by GR Engineering
Pty Ltd using vendor quotes where applicable. The accuracy of the estimate is considered to be consistent with that required
for feasibility study level.

Mining and ore haulage costs were estimated from budget quotations provided by recognised contractors for a similar scope
of work, using conventional detailed pricing schedule format.

Power, diesel and accommodation costs were based on current vendor pricing. Staff costs were based on current market
salary levels.

Processing operating costs were estimated by GR Engineering Pty Ltd and consider the latest metallurgical test work.

Overhead costs were estimated by OBM from first principles.

No deleterious elements were identified or expected.

All costs were quoted and compiled in Australian dollars.

Nominal transport and security provisions were allowed for to deliver the dore to the Perth mint.

Smelter charges were based on budget quotations from the Perth Mint

The standard WA state government royalty was allowed for.

No allowance was made for third party royalties; however, third party royalties are applicable to a portion of Sand King but
have not been considered in this Ore Reserve estimate. They are applicable to approximately 50% of the Sand King reserve
and account for 2% of the included revenue for that deposit.
Revenue factors
The derivation of, or assumptions made regarding
revenue factors including head grade, metal or
commodity price(s) exchange rates, transportation
and treatment charges, penalties, net smelter
returns, etc.

The derivation of assumptions made of metal or
commodity price(s), for the principal metals,
minerals and co-products.

Revenue calculations were based on detailed mine plans and mining factors including provision for dilution and ore loss.

The metal price used for revenue calculation was A$2,100/oz before selling costs and is below the current spot price as of the
date of this announcement. The price used is considered by Ora Banda Mining to be a conservative estimate of the medium-
term gold price.

Nominal transport and security provisions were allowed for to deliver the dore to the Perth mint.

Smelter charges were based on budget quotations from the Perth Mint
Market assessment
The demand, supply and stock situation for the

There are no known major gold producers expecting to influence the global supply of gold over the period of the project.

Page 63 of 65

ADDRESS Level 1, 2 Kings Park Rd, Perth WA 6005 POST PO Box 464, West Perth WA 6872 ABN 69 100 038 266 PHONE +61 8 6365 4548 PHONE (TOLL FREE) 1300 035 592 WEBSITE www.orabandamining.com.au ENQUIRES [email protected]

particular commodity, consumption trends and
factors likely to affect supply and demand into the
future.

A customer and competitor analysis along with the
identification of likely market windows for the
product.

Price and volume forecasts and the basis for these
forecasts.

For industrial minerals the customer specification,
testing and acceptance requirements prior to a
supply contract.

Demand for gold is expected to be subject to usual global factors and global recovery from the Covid-19 pandemic.
Economic
The inputs to the economic analysis to produce the
net present value (NPV) in the study, the source
and confidence of these economic inputs including
estimated inflation, discount rate, etc.

NPV ranges and sensitivity to variations in the
significant assumptions and inputs.

The Ore Reserve estimate is based on a financial model prepared to a Feasibility Study level of accuracy. All inputs from
open pit and underground operations, processing, transportation and sustaining capital as well as contingencies have been
scheduled and evaluated to generate a full life of financial model.

Economic inputs were sourced from suppliers, contractors or independent consultant databases.

A discount rate of 6%pa was applied.

The NPV of the project is positive at the assumed commodity price. The Competent Person is satisfied that the project
economics based on mining the Ore Reserve retains a suitable margin of profitability.

Sensitivities testingof the keyoperatingand commercialparameters were conducted.
Social
The status of agreements with key stakeholders
and matters leading to social licence to operate.

To the best of the Competent Persons knowledge all agreements are in place and current with all key stakeholders including
traditional owner claimants.
Other
To the extent relevant, the impact of the following
on the project and/or on the estimation and
classification of the Ore Reserves:

Any identified material naturally occurring risks.

The status of material legal agreements and
marketing arrangements.

The status of governmental agreements and
approvals critical to the viability of the project, such
as mineral tenement status, and government and
statutory approvals. There must be reasonable
grounds to expect that all necessary Government
approvals will be received within the timeframes
anticipated in the Pre-Feasibility or Feasibility
study. Highlight and discuss the materiality of any
unresolved matter that is dependent on a third
party on which extraction of the reserve is
contingent.

No material risks specific to the project have been identified.

All proposed mining operations are contained within granted mining leases 100% owned by Ora Banda Mining.

The approvals process for commencement of mining operations is underway. Based on the information provided, the
Competent Person is unaware of any reason approvals will not be successfully granted within the anticipated timeframe.
Classification
The basis for the classification of the Ore Reserves
into varying confidence categories.

Whether the result appropriately reflects the
Competent Person’s view of the deposit.

The proportion of Probable Ore Reserves that have
been derived from Measured Mineral Resources (if
_any). _

The Probable Ore Reserves are based on that portion of the Measured and Indicated Mineral Resource within the mine
design that may be economically extracted and includes an allowance for dilution and ore loss.

.The result appropriately reflects the Competent Person’s view of the deposit.

Approximately 100,000 t at 1.8 g/t at Riverina was downgraded from Proved to Probable due to current uncertainty
surrounding metallurgical recovery. Test work results are pending and this material is expected to be upgraded for the DFS
Audits or reviews
The results of any audits or reviews of Ore Reserve
estimates.

The Ore Reserve estimate, along with the mine design and life of mine plan, has been peer-reviewed internally by Ora Banda
MiningPtyLtd.

Page 64 of 65

ADDRESS Level 1, 2 Kings Park Rd, Perth WA 6005 POST PO Box 464, West Perth WA 6872 ABN 69 100 038 266 PHONE +61 8 6365 4548 PHONE (TOLL FREE) 1300 035 592 WEBSITE www.orabandamining.com.au ENQUIRES [email protected]

Discussion of
relative accuracy/
confidence

Where appropriate a statement of the relative
accuracy and confidence level in the Ore Reserve
estimate using an approach or procedure deemed
appropriate by the Competent Person. For
example, the application of statistical or
geostatistical procedures to quantify the relative
accuracy of the reserve within stated confidence
limits, or, if such an approach is not deemed
appropriate, a qualitative discussion of the factors
which could affect the relative accuracy and
confidence of the estimate.

The statement should specify whether it relates to
global or local estimates, and, if local, state the
relevant tonnages, which should be relevant to
technical and economic evaluation. Documentation
should include assumptions made and the
procedures used.

Accuracy and confidence discussions should
extend to specific discussions of any applied
Modifying Factors that may have a material impact
on Ore Reserve viability, or for which there are
remaining areas of uncertainty at the current study
stage.

It is recognised that this may not be possible or
appropriate in all circumstances. These statements
of relative accuracy and confidence of the estimate
should be compared with production data, where
available.

The design, schedule and financial model on which the Ore Reserve is based was completed to a Feasibility level of
accuracy, and a corresponding level of confidence. The mining costs for Waihi and Callion open pit were based on factored
estimates using composited costs from other mining areas within the study. Further investigative and analytical work is
required on rehandling and disposal of the tailings at Waihi. Both Waihi and Callion are considered to be at a pre-feasibility
level of study. Waihi and Callion are schedule to be mined after the estimated project payback period.

The Ore Reserve is based on a global estimate.

There is a degree of uncertainty associated with geological estimates. The Reserve classifications reflect the levels of
geological confidence in the estimates.

There is a degree of uncertainty regarding estimates of impacts of natural phenomena including geotechnical assumptions,
hydrological assumptions and the modifying mining factors, commensurate with the level of study. The Competent Person is
satisfied that the analysis used to generate the modifying factors is appropriate, and that a suitable margin exists under
current market conditions to allow for the Reserve estimate to remain economically viable despite reasonably foreseeable
negative modifying factor results.

There is a degree of uncertainty regarding estimates of commodity prices and exchange rates, however the Competent
Person is satisfied that the assumptions used to determine the economic viability of the Ore Reserves are reasonable based
on current and historical data.

Page 65 of 65