ORA BANDA MINING LTD — Capital/Financing Update 2017
Jun 14, 2017
65475_rns_2017-06-14_2866bd26-702e-48cf-9437-9bb7fb9afa2d.pdf
Capital/Financing Update
Open in viewerOpens in your device viewer
ASX ANNOUNCEMENT 15 JUNE 2017
==> picture [148 x 422] intentionally omitted <==
DAVYHURST MILL REFURBISHMENT AND COMMISIONING UPDATE
HIGHLIGHTS
-
Mill refurbishment completed
-
Final installation of oxygen and cyanide reagent tanks
-
Crushing circuit feed to commence within two days
-
Mining contractor and haulage contractor commenced
-
Approximately 20Kt of low grade commissioning feed on crusher ROM
Eastern Goldfields Limited (ASX:EGS) is pleased to provide an update on refurbishment and commissioning progress at the Davyhurst mill located approximately 120 kilometres north west of Kalgoorlie, within the Davyhurst Mining Hub.
Refurbishment of the 1.2Mtpa mill is now complete with all circuits having been electrically commissioned or completed. The programme commenced in September 2016 and has focused on:
-
Refurbishment of all concrete and steel structures including feed bin upgrade;
-
Installation of two new cone crushers (secondary and tertiary) and a new triple deck screen in the three stage crushing circuit;
ISSUED CAPITAL
Shares: 546.9m Options: 60.1m Current Share Price: $0.33.2 Market Capitalisation: $181.6m Cash as at 31/03/2017: $551,000*
*Excluding total debt facilities of $35.0m, see ASX announcement 31 Jan 2017. Drawn to date $15.0m
-
Overhaul of all conveyors including new belts, guards, motors/gearboxes and, where required, rollers;
-
Installation of a new gravity circuit including two Nelson Concentrators and an Acacia reactor;
-
Installation of a new control room including new control systems and data fibre throughout the circuit;
-
Refurbishment of the preleach and CIP absorption circuits;
-
Refurbishment of the elution circuit and gold room;
-
Installation of a new tailings thickener; and
-
Installation of new liquid cyanide and oxygen tank facilities.
In addition, a new raw water dam has been constructed with storage capacity equivalent to seven days of raw water supply along with an upstream tailings lift of the existing Tailings Storage Facility (TSF) to provide 12 to 18 months capacity. A 5.5MW containerised diesel power station and 550,000 litre fuel storage facility is currently being installed and commissioned to supplement the existing 1.5MW grid based power supply currently available from the 17MW capacity power line linking the site to the Goldfields Power grid.
Eastern Goldfields Chairman, Michael Fotios, commented:
“With the major overhaul of the Davyhurst mill now complete, moving to the commissioning of the plant represents a significant milestone for Eastern Goldfields in its evolution to an Australian gold production company. We now have a very high quality and modernised plant that will serve the Company well into the future, as we build on the already pleasing exploration results seen on the surrounding tenure.”
REFURBISHMENT STATUS
Crushing Circuit
-
All pumps, gearboxes and motors have been repaired or replaced
-
Installation of new triple deck screen completed
-
Installation of new Secondary and Tertiary Terex cone crushers completed
-
Crushing circuit has been overhauled and, ready for feed
-
Tertiary and secondary crushers repaired or replaced
-
All belts, drives and rollers, repaired or replaced
Grinding Circuit and Classification Circuit
-
New control room has been installed
-
All pumps, gearboxes and motors have been repaired or replaced
-
New cyclone cluster has been installed
-
Installation of two new Nelson Concentrators completed
-
Installation of Acacia reactor completed
-
Ball mills refurbishment is complete both mechanically and electrically, ready for wet commissioning
-
All drives, motors and gearboxes have been repaired or replaced
-
Oil cooling and lubricating systems has been repaired or replaced
-
Classification and gravity circuit are mechanically and electrically complete
Leach and Adsorption
-
Leach tanks ready for water testing
-
All pumps, gearboxes and motors have been repaired or replaced
-
Gold room is completed, all equipment is installed, wiring and piping complete
-
New Outotec thickener, associated pumps and floc system have been installed
Other
-
Power station nearing completion and commissioning
-
Fuel farm in final construction, awaiting commissioning
Mining and Haulage
-
Site establishment works commenced at Siberia on 4 May 2017
-
Low grade ore at Siberia currently being stockpiled
-
Haulage of ore commenced 30 May 2017
-
Approximately 20Kt of ore hauled to Davyhurst ROM pad
-
Construction of Siberia bypass haul road nearing completion
-
Civil works relating to mining operations at Siberia continuing
-
Siberia grade control drilling expected to commence end of June 2017
==> picture [494 x 299] intentionally omitted <==
Refurbished Crushing Circuit with new triple deck screen (foreground) and upgraded feed bin (background).
==> picture [504 x 172] intentionally omitted <==
==> picture [504 x 172] intentionally omitted <==
New 5.5MW containerised diesel power station and 550,000 litre fuel storage facility
==> picture [504 x 245] intentionally omitted <==
Refurbished mill feed conveyor, grinding circuit, new cyclone cluster, new gravity circuit (Nelson Concentrators coloured green) and preleach tanks.
==> picture [500 x 146] intentionally omitted <==
==> picture [500 x 145] intentionally omitted <==
New mill control room, Nelson Concentrator and Acacia reactor installations.
Investor Enquiries
Michael Fotios Executive Chairman T: +61 8 6241 1888 E : [email protected]
Jon Snowball FTI Consulting T: +61 477 946 068 E: [email protected]
Forward Looking Statements
Eastern Goldfields Limited has prepared this announcement based on information available to it. No representation or warranty, express or implied, is made as to the fairness, accuracy, completeness or correctness of the information, opinions and conclusions contained in this announcement. To the maximum extent permitted by law, none of Eastern Goldfields Limited, its directors, employees or agents, advisers, nor any other person accepts any liability, including, without limitation, any liability arising from fault or negligence on the part of any of them or any other person, for any loss arising from the use of this announcement or its contents or otherwise arising in connection with it. This announcement is not an offer, invitation, solicitation or other recommendation with respect to the subscription for, purchase or sale of any security, and neither this announcement nor anything in it shall form the basis of any contract or commitment whatsoever. This announcement may contain forward looking statements that are subject to risk factors associated with gold exploration, mining and production businesses. It is believed that the expectations reflected in these statements are reasonable but they may be affected by a variety of variables and changes in underlying assumptions which could cause actual results or trends to differ materially, including but not limited to price fluctuations, actual demand, currency fluctuations, drilling and production results, reserve estimations, loss of market, industry competition, environmental risks, physical risks, legislative, fiscal and regulatory changes, economic and financial market conditions in various countries and regions, political risks, project delay or advancement, approvals and cost estimates.