Nirlon Limited Management Reports 2019

May 13, 2019

62538_rns_2019-05-13_2e42950d-0de2-437b-962d-95155f0bc55a.pdf

Management Reports

Open in viewer

Opens in your device viewer

NIRLON LIMITED

Western Express Highway, Goregaon (E), Mumbai - 400 063. T +91-22-4028 1919 / 2685 2256 - 59. F +91-22-4028 1940. www.nirlonltd.com, Email:[email protected] CIN:L17120 MH1958PLC 011045

May 13, 2019

The Secretary, BSE Limited, P.J. Towers, Dalal Street, Mumbai- 400 001.

Security Code: 500307

Dear Sir,

Sub: Outcome of the Board meeting held on May 13, 2019

Ref: Pursuant to the provisions of Regulation 30 of the Securities and Exchange Board of India (Listing Obligations and Disclosure Requirements) Regulations, 20 15

We hereby inform you that interalia; the Board of Directors of the Company, at their meeting held on May 13,2019, has taken on record update summary on the Phase 5 of Nirlon Knowledge Park (NKP) - March 2019.

The said information with details will also be made available on the website of the Company i.e. "www.nirlonltd.com".

We request you to take the same on record.

Thanking you, Yours faithfully, For Nirlon Limited

cq\ , >' €'"""---""°'"

Company Secretary, Vice President (Legal) & Compliance Officer FCS 4178 Encl: a/a.

Item 19

Nirlon Knowledge Park (NKP} - Phase 5 Update Summary - March

  1. The area of Phase 5 is approx. 11. 59 lakh sq. feet of Chargeable Area and approx. l 7 .83 lakh sq. feet of Constructed Area. The Budget for Phase 5 is Rs.1198.30 Crore - including Rs.30 Crore for the Marketing Cost - and is for the original area of 10.90 lakh sq. feet of Chargeable Area and 16.74 lakh sq. feet of Constructed Area. The actual area being developed is approx 6.6% higher, i.e. 11.59 lakh sq. feet of Chargeable area and 17 .83 lakh sq. feet of Constructed area. Details are shown in the Budget Variation Sheet attached as Annexure 1 A, 1 B & 1 C.

As on 31st March 2019, for Phase 5, the Company has incurred/ certified a cost of approximately Rs. 553.00 crore and the committed cost is approximately Rs.876.00 crore, out of the total budget of Rs.1198.30 crore. The Phase 5 Financial Summary is shown in Annexure 2.

Any cost reductions Nirlon Ltd. is targeting in the hard cost of Phase 5, will not be due to lesser /lower specs, material, brands etc. Licensees must rate the Phase 5 Buildings the same or better than the earlier Phases, from a technical and user experience point of view too.

A summary of the Company's debt including the debt for Phase 5 is shown in the attached Annexure 3.

  1. The Company has received regulatory approval to construct the entire area of 17.83 Lakh Sq. Feet. The IOD, which effectively constitutes the building approval, has been received in June 2018. Plans for this entire area have been approved simultaneously with a payment of approximately Rs.176 Crore to MCGM and UD (Town Planning & Urban Development). This payment constitutes the premium payable @ 30% of R.R Rates to be paid to GOM for the additional FSI from 2 to 3. Nirlon Ltd. will have utilized FSI of approximately 2.63 after the completion of Phase 5. As on date, Nirlon Ltd. has received all the relevant approvals to complete execution of the Phase 5 Project in

NKP. The C.C's for all the Blocks, 1.e. 89, B10 & Bl 1 have been received as of October 30, 2018.

    1. NKP is eligible for 3: 1 FSI and plans to develop 10.56 lakh sq. feet against a total potential area of 16.51 lakh sq. feet. The balance potential available (on payment of the applicable premium) including fungible FSI if desired, is therefore 5.95 lakh sq. Feet. However, as per the latest DP 2034 and revised latest DCR (Development Control Regulations for Mumbai), NKP could be eligible for 5: 1 FSI. This is contingent on the access road width. NKP has an access road width of greater than 27 meters, which potentially makes it eligible for 5 FSI.
    1. There are two primary objectives for Phase 5 at the present time. First, to continue to execute in as safe a manner as possible, and to try and complete the project within the revised target date due to higher productivity and technical innovations. Second, to try and execute 17.83 lakh sq.feet at the original Budget for 16.74 lakh sq. feet.
    1. The following factors have played a major role in the cost and time frame of Phase 5 :
  • Regulatory uncertainty has been a very serious issue. Premiums and regulations were fluctuating prior to the new DP 2034 and the latest revised DCR being released by the State Government of Maharashtra.
  • Steel Prices were at near record highs in India, and had increased up to 45% from the contract prices. Cement prices had increased up to 25% from Contract prices.
  • The Rupee has depreciated approximately 10% against the US Dollar from Phase 4.
  • GST has been introduced m April 2017 after the Budget for Phase 5 was finalized. This has resulted in a direct cost increase in some areas/cases.

However, despite these issues the Company will target completion of Phase 5 within the original Budget (excluding Marketing Cost), notwithstanding the increased volume and the negative factors mentioned above. Also, the Company will try and complete the Project by April 2020 and October 2020, in a phased wise manner which were the original targets, notwithstanding the loss of approx. 180 days at the start of the Project due to non formation of MOEF Committees.

    1. In Principle Marketing interest for Phase 5 remains strong. The Company would try and ensure that the profile of the Licensees in Phase 5 is similar to the existing phases 1-4 in NKP. Currently, there is a healthy interest from existing licensees in NKP, as well as potentially new licensees.
    1. As on date, the Company has completed approximately 70% of the Civil work, and is currently casting slabs for the 15th floor (out of a total of 23 floors), 9th floor (out of a total of 9 floors) and 3rd floor (out of a total of 7 floors) for the buildings B9, BIO and Bl 1 respectively.

NIRLON KNOWLEDGE PARK - PHASE S Annexure lA BUDGET VARIATION SHEET SUMMARY - HARD COST AND SOFT COST

SI.No. Budget Head Original Budget Anticipated / Targeted
. · Cost Variation
Projected I Targeted
!
Cost
Remark
'.
;
' "
In INR Crores
'
in INR Crores '
In INR Crores
Original Constructed
Area - 1674000 Sq.Ft.
Revised Constructed
Area - 1783000 Sq.Ft.
Original Chargeable
Area - 1090000 Sq.Ft.
Revised Chargeable
Area - 1159000 Sq. Ft.
1 Hard Cost 672.96 Less by 4.67 668.29 Hard Cost in Phase V will continue to
be carefully monitored. Further
increases in the price of Steel are
anticipated. There could also be
increases in the projected volume of
Steel for various reasons.
2 Soft Cost 495.35 Less by 25.00 470.35 Soft Cost should be approximately
5% lower than the original Budget
TOTAL COST 1,168.32
•,
Less by 29.67 1,138.65 Approximate Cost reduction of 2.5%
from the original Budgf>t, after
increased area

Marketing Cost has been excluded in this projection.

NIRLON KNOWLEDGE PARK - PHASES Annexure 18 BUDGET VARIATION SHEET SUMMARY - HARD COST

SI.No. Budget Head
Original Budget
Anticipated I Targeted
Cost Variation
Projected / Targeted
Cost
Remark
-
k •
In INR Crores in INR Crores in INR Crores
Original Constructed
Area - 1674000 Sq.Ft.
Revised Constructed
Area - 1783000 Sq.Ft.
Original Chargeable
Area - 1090000 Sq.Ft.
Revised Chargeable
Area - 1159000 Sq.Ft.
1 Preliminaries 5.74 2.00 7.74 Shore piling for the entire area was not
considered in budget. This was required from a
schedule and safety point of view. Approx Rs. 4.3
crore increases for shore piling and other misc.
work, however Rs. 2.30 crore received from the
demolition \YOO(, i.e. the net increase of Rs. 2.00
Cr.
2 Main Building- Core & Shell 302.47 40.00 342.47
Excavation and Site preparation
works
9.41 4.00 13.41 Increase includes Royalty charges. Budget was
for 2 basements. However work executed for
3 basements.
Main Building- Concrete Shell and
Civil Works
282.98
•,
36.00 318.98 This increase is inclusive of anticipated price
escalation of Rs. 30 crore (approx.) (as on date
Rs 20.07 crore), RS. 6 crore for Peri Skydeck
system, other GST variations after setoff, extra
items, etc However the overall BOO qty.
variation will be assessed on receipt of all
drawings (GFC's) from Consultant.
Post Tensioning work 9.48 - 9.48 The overall BOQ qty. variation if any will be
assessed on receipt of all drawings from
Consultant.
MS and GI Fabrication 0.60 - 0.60
-
3 Facade and Terrace Structures 100.13 Less by 6.00 94.13 As anticipated and projected, Facade Tender has
been fnalised for approximately Rs. 72 Crore.
With additional extra items, the toal facade
package should be approimately Rs. 94 Crores.
Structural Glazing and Fa,ade
Work
95.42
Special Fa,ade Fabrication works 4.70 -
-
4 Common Area Interiors 41.89 Less by 4.00 37.88 The overall variation if any will be assessed on
receipt of all drawings, BOO and tender
finalization.
Interior Fitout for common area -
Lobby, Staircase, Passages, toilet,
etc.
36.40 Less by 4.00 32.40 Rs. 4 crores will be the overall targeted saving
by value additional and negotiation
Signage 0.26 - 0.26
Fire and General MS Doors 4.83 - 4.83
Fire Sealing 0.39 - 0.39
-
5 External Development 20.86 - 20.86 The overall variation if any will be assessed on
receipt of all drawings, BOO and tender
finalization.
Hardscape - Road zone, Park
zone and Pathwav
8.91 - 8.91
Gratings and Covers 0.94 - 0.94
External Civil Works 7.38 7.38
Irrigation, rain water harvesting,
etc.
0.74
•,
- 0.74 •.
Softscape 2.30 - 2.30
Artifacts and Accessories 0.05 - 0.05
Water features 0.54 - 0.54
-

NIRLON KNOWLEDGE PARK - PHASE 5 Annexure lC BUDGET VARIATION SHEET SUMMARY - SOFT COST

51. No. Budget Head Original Budget Anticipated / Targeted
Cost Variation
Projected / Targeted Cost
Remark
in INR Crores In INR Crores In INR Crores $\frac{1}{2}$
Original Constructed
Area - 1674000 Sq.Ft.
Revised Constructed
Area - 1783000 Sq.Ft.
Original Chargeable
Area - 1090000 Sq.Ft.
Revised Chargeable
Area - 1159000 Sq.Ft.
$\mathbf{1}$ Soft Cost (Consultants) + MSC
Charges
109.62 Less by 5.00 104.62 The projected reduction is despite the fact that
approximately Rs. 3 Crores is lost due to change
in tax structure from Service Tax to GST. This is
a dead loss.
$\overline{2}$ Authorities (Fees, Connections,
etc.) and Land Cost/ FSI
Purchase Cost
235.55 Less by 10.00 225.55 Currently projected to be lesser by
approximately 10 Crores despite increased
volume. However, Statutory Costs remain very
unpredictable.
3 Finance Cost 110.18 Less by 10.00 100.18 Finance cost could have been lower. However,
Due to unpredictable nature of Statutory Costs
and fluctuating interest rates the finance costs
will vary.
Đ. ă,
4 Other (Non - Direct
Construction related eg Taxes,
Insurance, etc)
40.00 40.00
TOTAL SOFT COST 495.35 Less by 25.00 470.35
6 Utilities 190.18 Less by 26.00 164.18 Approximately Rs. 152 Crores of orders have
been placed. Balance packages of Access
Contr� and Luminaries will be finalised shortly.
Final Utilities Number will be approximately Rs.
164 Crores.
HVAC System 28.16 -
Electrical 36.50 -
Luminaries 5.21 -
DG Sets (8) with HSD Yard 46.93 -
PHE & Fire Fighting System 26.07 -
Sanitary ware. CP fittings 0.88 -
Elevators (29 ) 27.12 -
IBMS 13.56 -
STP 5.74 - -
7 Site Overheads 1.04 - 1.04
-
8 Contingency for Hard
cosUdirect construction\
10.67 10.67 (will be utilized) - This contingency will be utilized to offset the
increased in hard cost.
TOTAL HARD COST 672.96 Less bv 4.67 668.29

The overall cost will be subject to the final quantities and prices of Steel

Steel Prices were at a near record highs and are assumed to be at this price till the end of the Project.

Financial Summary- Phase 5

Annexure 2

Rs. Cr.
1,198.3
578.3
585.0
35.0
PHASE V -
COST SUMMARY
(Rs. Cr.)
Budgeted Committed Incurred/
Certified
Civil 302 300 203
MEP 190 142 25
Common Area Interiors 42 5 -
Landscape 21 1 1
Fac;:ade 100 72 4
FSI Premiums 186 128 128
Finance Cost/ Interest 110 22 22
Soft services and Others 247 206 171
TOTAL 1,198 876 553

Annexure 3

Debt Summary (as on 31 Ma 5 rch 19)

Particulars Debt o/s
(Rs.' Cr.}
Operational Areas
Phase V
581
274
TOTAL OUTSTANDING 855
Balance undrawn limit for Phase V 355
  • };-, The entire debt is borrowed from HDFC Ltd. and is secured by a mortgage on NKP.
  • }i;-- Interest is being serviced for the entire loan on a monthly basis.
  • };-, At present, the Company enjoys a principal repayment moratorium on the entire debt till F.Y. 2022 - 23 or till Phase 5 completion, post which the entire debt is proposed to be converted into an EMI repayment. Historically, HDFC loans to the Company have had a repayment tenure of 108 to 120 months.
  • }i;-- The weighted average gross cost of debt is 10.15% p.a. (floating rate).