==> picture [592 x 97] intentionally omitted <==

----- Start of picture text -----

7 July 2021
----- End of picture text -----

REVIEW OF NICKEL MINERAL RESOURCES AT MT EDWARDS COMPLETE

HIGHLIGHTS

  • Neometals completes review of 11 Nickel Mineral Resources across the Mt Edwards Project at Widgiemooltha;

  • Nine Mineral Resources have been re-estimated between November 2019 and June 2021 using new and existing data;

  • Assessment of Cooke and Widgie 3 Mineral Resources deemed that no re-estimation is required; and

  • Global contained nickel tonnes at the Mt Edwards Project now 162,560 tonnes, from 10.220 million tonnes at 1.6% Ni.

Neometals Ltd ( ASX: NMT ) ( “Neometals” or “the Company” ) is pleased to announce completion of a review of all eleven nickel Mineral Resource estimates at its Mt Edwards Nickel Project (“ Mt Edwards ”). The review commenced mid-2019 with the first estimate completed on the Munda deposit in November 2019. Since this time Neometals has been progressively reviewing all available data, including government and third party sourced, to increase its understanding of Mt Edwards.

The increase for the Mt Edwards 26N Mineral Resource announced 30 June 2021 is the last re-estimation considered necessary with the current information ( for further details see Neometals ASX announcement titled “Updated 26 North Resource at Mt Edwards Increases by 51% dated 30 June 2021) . An assessment of the Cooke[1] and Widgie 3[2] Mineral Resources was completed by Richard Maddocks from Auralia Mining Consultants. In Mr Maddock’s assessment, the current estimates do not warrant reinterpretation given the available data.

Table 1 – The reviewed Mt Edwards Project with 11 Nickel Mineral Resource estimates for 162,560 contained nickel tonnes.

Indicated Indicated Inferred Inferred TOTAL Mineral Resources TOTAL Mineral Resources TOTAL Mineral Resources
Deposit Tonne (kt) Nickel (%) Tonne (kt) Nickel (%) Tonne (kt) Nickel (%) Nickel Tonnes
Widgie 32 626 1.5 626 1.5 9,160
Gillett5 1,306 1.7 1,306 1.7 22,500
Widgie Townsite9 1,183 1.7 1,293 1.5 2,476 1.6 39,300
Munda3 320 2.2 320 2.2 7,140
Mt Edwards 26N 871 1.4 871 1.4 12,400
132N6 34 2.9 426 1.9 460 2 9,050
Cooke1 154 1.3 154 1.3 2,000
Armstrong4 526 2.1 107 2 633 2.1 13,200
McEwen8 1,133 1.4 1,133 1.4 15,340
McEwen Hangingwall8 1,916 1.4 1,916 1.4 26,110
Zabel7&8 272 1.9 53 2 325 2 6,360
TOTAL 2,015 1.9 8,205 1.5 10,220 1.6 162,560

Mineral Resources quoted using a 1% Ni block cut-off grade, except Munda at 1.5% Ni. Small discrepancies may occur due to rounding

Note 1. refer announcement on the ASX: NMT 19 April 2018 titled - Mt Edwards JORC Code (2012 Edition) Mineral Resource 48,200 Nickel Tonnes Note 2. refer announcement on the ASX: NMT 25 June 2018 titled - Mt Edwards Project Mineral Resource Over 120,000 Nickel Tonnes Note 3. refer announcement on the ASX: NMT 13 November 2019 titled - Additional Nickel Mineral Resource at Mt Edwards Note 4. refer announcement on the ASX: NMT 16 April 2020 titled – 60% Increase in Armstrong Mineral Resource Note 5. refer announcement on the ASX: NMT 26 May 2020 titled – Increase in Mt Edwards Nickel Mineral Resource Note 6. refer announcement on the ASX: NMT 6 October 2020 titled – 132 Nickel Mineral Resource and Exploration Update at Mt Edwards Note 7. refer announcement on the ASX: NMT 23 December 2020 - Zabel Nickel Mineral Resource Update at Mt Edwards Note 8. refer announcement on the ASX: NMT 29 June 2021– McEwen Resources at Mt Edwards Increase 45% to 41.5kt Contained Nickel Note 9. refer announcement on the ASX: NMT 29 June 2021 – Updated Widgie Townsite Nickel Mineral Resources at Mt Edwards Note 10. refer announcement on the ASX: NMT 30 June 2021– Updated 26 North Resources at Mt Edwards Increase by 51%

[email protected] neometals.com.au

Locked Bag 8 West Perth WA 6872

ACN 099 116 361 Level 1, 1292 Hay Street West Perth WA 6005

T: +61 8 9322 1182 F: +61 8 9321 0556

==> picture [596 x 64] intentionally omitted <==

----- Start of picture text -----

7 July 2021 – REVIEW OF NICKEL MINERAL RESOURCES AT MT EDWARDS COMPLETE
----- End of picture text -----

Background

Neometals acquired Mt Edwards in the first half of 2018 and immediately began exploring for nickel and lithium. The Company is targeting new nickel discoveries at Mt Edwards while reviewing and enhancing existing nickel Mineral Resources. The Company owns, or holds nickel rights to, 36 mining tenements with a large land holding of more than 300km[2] across the Widgiemooltha Dome, a well-recognised nickel sulphide mining province.

Summary and Mineral Resource Estimation

Mr Richard Maddocks from Auralia Mining Consultants has reviewed both the Widgie 3 and Cooke Mineral Resource block models and reports and has not identified any fatal flaws in the geological interpretation nor in the grade estimation. Mr Maddocks asserts that the reporting of the Mineral Resource for each deposit has been underreported since 2018 due to rounding errors, with Widgie 3 having 626,000 tonnes (up from 625,000 tonnes) of mineralisation at 1.5% nickel, and Cooke 154,000 tonnes (up from 150,000 tonnes) at 1.3% nickel for 2,003 contained nickel tonnes (up from 1,950 nickel tonnes). The Widgie 3 and Cooke Mineral Resource estimate are summarised in Table 2.

Table 2 - Widgie 3 & Cooke Mineral Resource Estimate

Deposit Mineral Resource Category Cut-off Grade Ni % Tonnes Ni % Nickel Tonnes
Widgie 3 Inferred 1.0 626,000 1.5 9,160
Cooke Inferred 1.0 154,000 1.3 2,003

The Mineral Resource estimates are reported in accordance with the 2012 Edition of the ‘Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves’ prepared by the Joint Ore Reserves Committee of The Australasian Institute of Mining and Metallurgy, Australian Institute of Geoscientists and Minerals Council of Australia (JORC Code) and follows a detailed interrogation and review of the available data, including the earlier reported Mineral Resource estimates by the previous holders of the tenement.

The Widgie 3 and Cooke Mineral Resources were previously estimated by Titan Resources in 2005 and Apollo Phoenix in 2016. The 2005 estimates were completed by consultants Hellman and Schofield using ordinary kriging to estimate nickel and arsenic grades. The 2016 estimates were essentially an update using the same parameters as the 2005 estimate. These estimates were accompanied by the required JORC tables and tabulated drilling information to enable it to be quoted as compliant with the 2012 JORC Code, and they were reported on the ASX shortly after Neometals acquired the deposits in April 2018 (refer Note 1 to Table 1 above) and June 2018 (refer Note 2 to Table 1 above).

A summary of information relevant to the Widgie 3 and Cooke Mineral Resource estimate at the Mt Edwards Project is provided in these appendices attached to this announcement:

Appendix 1. Table 1 as per the JORC Code Guidelines (2012)

  • Appendix 2. Drill holes used in the Mt Edwards Widgie 3 and Cooke block model estimates

Appendix 3. Significant and Mineralised Drill Intersections at Widgie 3 and Cooke

Requirements applicable to reports of Mineral Resources for material mining projects

This announcement clarifies the Cooke and Widgie 3 Mineral Resources are in accordance with requirements applicable to reports of Mineral Resources for material mining projects, including location, geology and interpretation, sampling and drilling techniques, sample and assay analysis, classification, estimation methodology, cut-off grades, mining and metallurgical parameters and recommendations.

Location

The Widgie 3 Deposit is located about 75 kilometres south-south-easterly of Coolgardie in the Goldfields region of Western Australia and about 2.6km south-east from the townsite of Widgiemooltha. Access to the Widgie 3 Deposit (“ Widgie 3 ”) from the Coolgardie to Esperance Highway is via the Caves Hill Road and then well-established roads used for previous mining and exploration in the area. The Cooke Deposit (“ Cooke ”) is located about 64 kilometres south-south-easterly of Coolgardie in the Goldfields region of Western Australia and about 7km north-west from the townsite of Widgiemooltha. Access to Cooke from the Coolgardie to Esperance Highway is via well-established roads used for previous mining and exploration in the area.

2

neometals.com.au

==> picture [596 x 64] intentionally omitted <==

----- Start of picture text -----

7 July 2021 – REVIEW OF NICKEL MINERAL RESOURCES AT MT EDWARDS COMPLETE
----- End of picture text -----

==> picture [476 x 654] intentionally omitted <==

Figure 1 - Mt Edwards Project tenure over geology, showing the locations of the Widgie 3 Mineral Resource on M15/94 and the Cooke Mineral Resource on M15/101.

3

neometals.com.au

==> picture [596 x 64] intentionally omitted <==

----- Start of picture text -----

7 July 2021 – REVIEW OF NICKEL MINERAL RESOURCES AT MT EDWARDS COMPLETE
----- End of picture text -----

Geology and Geological Interpretation

The Widgiemooltha area lies within the southern part of the Norseman-Wiluna greenstone belt. The area is dominated by the Widgiemooltha Dome which is interpreted to be a syn-kinematic granitoid diapir. The granitoid core is flanked by ultramafics and mafic metavolcanics comprising tholeiitic and komatiitic extrusives, interflow sediments and minor high MgO mafic flows. Three phases of ductile deformation have been defined and are characterised by open to tight folding and cleavage development. Late-stage brittle deformation is characterised by north northwest and east west faults.

==> picture [279 x 299] intentionally omitted <==

Figure 2 – Plan of geology, drill traces and open pit workings at the Widgie 3 deposit.

==> picture [281 x 188] intentionally omitted <==

Figure 3 – Cross section of Widgie 3 and the adjacent Gillett Mineral Resource showing drill traces , geology, DHEM targets and significant intercepts.

Widgie 3 deposit geology

Widgie 3 is located on the northeast flank of the Widgiemooltha Dome, within a sequence of intercalated mafic and ultramafic rocks.

At the deposit scale the main ultramafic formation (Widgiemooltha Komatiite) is a maximum of 600m thick, and consists of numerous flows of picritic to peridotitic composition with minor interflow cherty sediments. The sequence generally strikes north-south, faces east and dips to the east at around 70[o] , steepening to 90[o] at depth and to the north. Rhyolitic porphyry dykes with a general north-northwest strike intrudes the sequence and in places stopes out mineralisation. The footwall rocks, west of the ultramafic sequence consists of relatively undeformed amphibolite (Mt Edwards Basalt).

Mineralisation is located along the contact of the amphibolite and ultramafics. The more massive higher grade mineralisation is developed within a serpentinite lens at the base of the ultramafics, in an embayment on the contact (the Widgie 3 embayment). The lens is 110m long, 30m thick and extends to a depth of at least 140m below surface. Matrix and disseminated mineralisation is located immediately above the more massive mineralisation and extends beyond the serpentinite lens at depth. The depth of oxidation ranges from 15 metres at the south end of the deposit to 30 metres below surface at the north end.

Mineralisation consists of contact massive sulphides (pyrite, pyrrhotite, pentlandite, chalcopyrite, gersdorffite) typically <1m thick, overlain by matrix sulphides and disseminated sulphides. The mineralised envelope can be up to 19 metres thick (decreasing with depth) and 200 metres strike length and is located within or at the base of the serpentinite lens.

The more massive basal mineralised lens is typically less than 2.5m thick; while the more disseminated hanging wall mineralised zones are typically greater than 3m thick depending on the cut-off used to define the mineralised boundary.

4

neometals.com.au

==> picture [596 x 64] intentionally omitted <==

----- Start of picture text -----

7 July 2021 – REVIEW OF NICKEL MINERAL RESOURCES AT MT EDWARDS COMPLETE
----- End of picture text -----

Cooke Geology

Nickel sulphide mineralisation developed on and above the ultramafic-amphibolite contact at Cooke is associated with a steep northerly plunging synclinal structure. Both the east and west contact are mineralised and the entire structure dips steeply to the west. The syncline plunges at about 50 degrees to the north and dips steeply to the east. WMC geologists recognised three mineralised surfaces;

  1. Western inner synclinal contact, within which mineralisation is variable, from heavy matrix contact mineralisation in the synclinal keel, to lower tenor disseminated mineralisation in the north.

  2. Eastern inner contact, which consists of high-grade low tonnage mineralised zone that has limited strike and down dip potential.

  3. Southern outer contact, which is typically heavy matrix in character, with minor massive mineralisation.

==> picture [238 x 361] intentionally omitted <==

Figure 5 – Cross section of the Cooke Mineral Resource showing drill traces, geology and significant intercepts.

==> picture [278 x 407] intentionally omitted <==

Figure 4 – Plan of geology, drill traces, and EM plates at Cooke.

Sampling

Sampling and sub-sampling techniques and procedures for Anaconda, Metals Exploration and WMC at Widgie 3 are not known. Sampling procedures for INCO and WMC drilling at Cooke are not known .

Titan Resources samples from RC drilling at both Cooke and Widgie 3 were collected via a cyclone and riffle split 75:25. One metre samples were laid out on the ground in rows of 20. Four metre composites or 1 metre splits were submitted to the laboratory at the geologist’s discretion. Four metre composites were sampled using a spear by taking an equal portion from each one metre sample. Zones of interest were sampled at 1 metre intervals. Nickel mineralisation was sampled for 10 metres above and 5 metres below the contact. Samples, typically weighing between 3 and 5kg, were submitted to the laboratory. Four metre composite samples assaying greater than 0.3% nickel or 0.3g/t gold were re-sampled at one metre intervals.

5

neometals.com.au

==> picture [596 x 64] intentionally omitted <==

----- Start of picture text -----

7 July 2021 – REVIEW OF NICKEL MINERAL RESOURCES AT MT EDWARDS COMPLETE
----- End of picture text -----

At Widgie 3 diamond core drilled by Titan was sampled according to lithology at the geologist’s discretion. The core was oriented and geotechnical logging was carried out prior to the core being cut. Half core or quarter core samples were submitted for analysis.

For RC drilling at both Cooke and Widgie 3 one metre geological reference samples were collected and stored in chip tray boxes. The location of these chip trays is not known.

At the end of each RC hole at Cooke an Eastman single-shot camera was used to record the dip. This was taken in the drill rod so azimuths were not recorded due to magnetic interference. Selected holes were then surveyed at 10m intervals down hole, by Surtron Technologies, using either a gyro or electronic multi-shot.

Drilling techniques - Widgie 3

The Widgie 3 Mineral Resource has been estimated from 110 drill holes totalling 14,768m. Of these 21 holes for 4,456m were drilled by Anaconda between 1967 and 1974, 3 holes for 245m by Metals Exploration and 78 holes for 8,295m were drilled by Western Mining (WMC) between 1980 and 1999. Finally Titan Resources drilled 8 holes for 1,772m in 2004.

Anaconda drilled 19 Diamond Core holes and 2 percussion holes. Titan drilled 4 RC holes and 4 Diamond Core holes.

==> picture [377 x 265] intentionally omitted <==

Figure 6 – Long section of the Widgie 3 Mineral Resource showing drill traces and nickel grade, significant intercepts and EM Plates.

The Titan RC holes at Widgie 3 were drilled by McKay Drilling of Kalgoorlie using a 1996 Hydco 1350 with an 1150/350 onboard compressor, a 1999 Western Air 1150/350 silenced compressor and 1800/900 Hurricane booster. One RC pre-collar was drilled by McKays and the remainder were drilled by Redmond Drilling or Ausdrill using a T685W Schramm with 1000 CFM @ 500PSI on board air along with auxiliary and booster compressors. A single RC pre-collar was drilled by Drillcorp Western Deephole using a late model UDR 1000 heavy duty multi-purpose rig with on board Sullair 900cfm x 350psi compressor. Diamond drilling was carried out by Drillcorp Western Deephole used a late model UDR 1000 heavy duty multi-purpose rig.

The Widgiemooltha database suggests all the WMC holes at Widgie 3 are Diamond Core but the shallow nature of the holes indicates that some, at least, are more likely to be percussion holes.

Samples from all holes have been considered in the Mineral Resource estimation of Widgie 3.

Drilling techniques - Cooke

Three metallurgical test holes were drilled at Cooke for a total of 314.5 metres of HQ3 diamond core. All holes were cored from surface by Drillcorp Western Deephole utilising a UDR 1000 heavy duty multi-purpose rig with a 900cfm x 350psi onboard compressor. Sixty-seven samples (Sample numbers WD2810 to WD2876), obtained from the drilling, were forwarded to AMMTEC Ltd for metallurgical test work.

6

neometals.com.au

==> picture [596 x 64] intentionally omitted <==

----- Start of picture text -----

7 July 2021 – REVIEW OF NICKEL MINERAL RESOURCES AT MT EDWARDS COMPLETE
----- End of picture text -----

==> picture [349 x 277] intentionally omitted <==

Figure 7 – Long section of the Cooke Mineral Resource showing drill traces and nickel grade, significant intercepts and EM Plates.

Four geotechnical holes were drilled at Cooke (M15/101), WDGT01 to WDGT04, for a total of 305.4 metres of HQ3 diamond core.

The Cooke Mineral Resource has been estimated from 114 drill holes totalling 14,105m. Of these 37 holes for 3,193m were drilled by INCO in 1970, 63 holes for 9,729m were drilled by Western Mining (WMC) between 1980 and 1999. Finally, Titan Resources drilled 14 holes for 1,193m in 2004.

Titan drilled 7 RC holes, 4 Diamond Core Geotechnical holes and 3 Diamond Core metallurgical holes. The Widgiemooltha database suggests all the INCO and WMC holes at Cooke are Diamond Core but the shallow nature of the holes indicates that some, at least, are more likely to be percussion holes.

Samples from all holes have been considered in the Mineral Resource estimation of Cooke.

Classification Criteria

The Widgie 3 and Cooke Mineral Resource estimates have been classified as Inferred. The historical nature of most of the drilling and the lack of supporting data means that a higher classification cannot be considered.

At Cooke the oxide material has not been classified due to potential metallurgical issues with supergene nickel species. Additional test-work is required in order for nickel oxide material to be considered for Mineral Resource classification.

Sample Analysis

Analysis of INCO and WMC drilling samples at Cooke is not known. Sample analysis for Anaconda, Metals Exploration and WMC at Widgie 3 are not known.

Analysis of Titan Resources samples for Cooke and Widgie 3 was undertaken by ALS Chemex, Perth. The entire sample was prepared by crushing and pulverising to a nominal 90% passing 75 microns. Analytical schemes and detection limits are as follows:

  • ME-ICP61s (formerly IC587) four acid digestion, HF-HNO3-HCLO4 acid digestion, HCL leach and ICP-AES, detection limits in brackets. Cu (1ppm), Co (1ppm), Ni (1ppm), Cr (1ppm), As (5ppm), Mn (5ppm), Al (0.01%), S (100ppm), Mg (0.01%) and Fe (0.01%);

  • Copper and nickel values in excess of 1% (considered to be Ore grade) were re-assayed using ME-OG62 four acid digest as above, elements determined by ICP-AES with lower detection limits of 0.01%;

  • After preparation a split or check sample was taken by ALS from every 20th sample and sent to Ultratrace Analytical Laboratories in Perth. The analytical method and detection limits at Ultratrace are as follows:

  • Four acid digest, detection limits in brackets. Cu (1ppm), Co (1ppm), Ni (1ppm), Cr (5ppm), As (5ppm), Mn (1ppm), Al (0.01%), S (0.01%), Mg (0.01%) and Fe (0.01%); and

  • Select samples from Widgie 3 were submitted at ALS for 50g fire assay with ICP-MS for Au, Pt, Pd (PGM-MS24).

7

neometals.com.au

==> picture [596 x 64] intentionally omitted <==

----- Start of picture text -----

7 July 2021 – REVIEW OF NICKEL MINERAL RESOURCES AT MT EDWARDS COMPLETE
----- End of picture text -----

Estimation Methodology

Widgie 3 and Cooke have been estimated using Ordinary Kriging estimation techniques.

Widgie 3 – Estimation Details

For Widgie 3 data was composited to 1m lengths for grade estimation. Analysis of the composite data resulted in a top cut of 7% being applied to nickel grades. This resulted in 9 samples out of 469 being cut to a nickel grade of 7%.

The variogram model details that was applied to the estimate is shown in Table 3. Nickel and arsenic were modelled. Search parameters used for the Widgie 3 estimation are contained in Table 4. A three-pass estimation was used. Block sizes were 5m X, 10mY, 10mZ with sub-blocks of 0.3125mX, 2.5mY, 2.5mZ. The modelled mineralised domains were all hard boundaries for the purpose of estimation.

The Widgie 3 block model was validated using swath plots and visually by section.

Table 3 - Widgie 3 Variogram Model details

==> picture [528 x 79] intentionally omitted <==

Table 4 - Search Parameters used in the Widgie 3 estimation

==> picture [439 x 77] intentionally omitted <==

Cooke – Estimation Details

Drill data from Cooke was composited to 1.5m lengths as this corresponds to the majority sampling interval of 5 feet (1.52m) in the older INCO and WMC drilling.

The variogram model that was applied is shown in Table 5. Search parameters used for the Cooke estimation are contained in Table 6. A three pass estimation was used. Block sizes were 5m X, 10mY, 10mZ with sub-blocks of 0.3125mX, 2.5mY, 2.5mZ.

The modelled mineralised domains were all hard boundaries for the purpose of estimation.

Table 5 - Cooke Variogram Model details

==> picture [491 x 74] intentionally omitted <==

Table 6 - Search Parameters used in the Cooke estimation

==> picture [375 x 130] intentionally omitted <==

8

neometals.com.au

==> picture [596 x 64] intentionally omitted <==

----- Start of picture text -----

7 July 2021 – REVIEW OF NICKEL MINERAL RESOURCES AT MT EDWARDS COMPLETE
----- End of picture text -----

Cut-off grades

The Cooke and Widgie 3 Mineral Resource estimates have been reported at a 1% nickel cut-off grade. This cut-off grade is consistent with other nickel producing companies in the Widgiemooltha region. This cut-off grade is appropriate when considering potential open pit and/or underground mining scenarios however the inferred classification precludes such assessments.

Mining or Metallurgical Parameters

No mining or metallurgical parameters or modifying factors have been applied to the Widgie 3 Mineral Resource estimation.

At Cooke metallurgical test-work was conducted by Titan in 2004. The flotation tests were conducted using WMC Resources Ltd - Kambalda Nickel Operations (KNO) standard flotation conditions. KNO process water was used.

The flotation test results indicated that the expected recoveries from processing of the Cooke mineralised material would be of the order of 70 to 80%. Nickel recovery and grade was poor for all of the tests conducted, with Composite 3, at natural pH, giving the best result of 77.2% at 8.98% nickel.

As the metallurgical assessment is preliminary no mining or metallurgical parameters have been applied to the model for the Cooke estimation.

Summary – Widgie 3

Richard Maddocks from Auralia has reviewed the existing model for Widgie 3 and has determined there are no fatal flaws in the geological interpretation or the grade estimation. Drilling data and wireframe mineralised shapes were loaded into Vulcan software for review. The reported tonnes and grade from the 2016 Marshall report were replicated when the model was transferred for review in Vulcan v20.2.

The Inferred Mineral Resource classification is appropriate given the historical nature of the drilling and the lack of supporting data i.e., QAQC, downhole surveys, sampling and assaying methods.

The geological interpretation has accounted for the intrusion of barren post-mineralisation porphyry dykes. In addition, there has been allowance for previous mining activity in both the open pit and underground mines, however the underground survey is of low confidence.

The grade estimation techniques and parameters are appropriate for this style of mineralisation. Ordinary kriging has been used with the application of a 7% nickel top cut.

Summary – Cooke

Richard Maddocks from Auralia has reviewed the existing model for Cooke and has determined there are no fatal flaws in the geological interpretation or the grade estimation. Given the small size of the Mineral Resource, Cooke has been poorly documented.

There is little information on the deposit geology and there appear to be no geology sections or plans available. There is sufficient drilling data and wireframe modelling data to enable a review of the modelled geology. This data was loaded into Vulcan v20.2 for review.

The 2005 Hellman and Schofield Mineral Resource at a 1% Ni cut-off was 196,000t @ 1.28% nickel. In the 2016 update by Apollo Phoenix the competent person, Mr Luke Marshall, reported 154,000t @ 1.34% nickel. This difference is due to Marshall not including several small modelled mineralised shapes that contained less than three drill-holes (Figure 2). Auralia agrees that these shapes are not included in the Mineral Resource due to lack of supporting drilling.

In addition, the oxide portion of the Mineral Resource was not classified due to potential metallurgical issues. Auralia agrees with this approach, and this is consistent with Auralia’s classification of oxide mineralisation in other Widgiemooltha deposits.

The Inferred Mineral Resource classification is appropriate given the historical nature of the drilling and the lack of supporting data i.e., QAQC, downhole surveys, sampling and assaying methods.

The grade estimation techniques and parameters are appropriate for this style of mineralisation. Ordinary kriging has been used with no top cuts applied.

9

neometals.com.au

==> picture [596 x 64] intentionally omitted <==

----- Start of picture text -----

7 July 2021 – REVIEW OF NICKEL MINERAL RESOURCES AT MT EDWARDS COMPLETE
----- End of picture text -----

==> picture [471 x 355] intentionally omitted <==

Figure 8 - Oblique view of Cooke drilling and wireframes looking NE. The 3 wireframes identified have not been included in the Mineral Resource estimate.

Recommendations - Cooke and Widgie 3

Auralia recommends additional drilling to infill the current drill density at both Cooke and Widgie 3. This should be predominantly diamond core drilling so that a thorough structural interpretation of the deposit can be completed. Controls on high grade nickel mineralisation appear to be complex so closer spaced drilling, along with an increased understanding of the structural history of the deposit should result in increased confidence in the distribution of high-grade nickel mineralisation.

Arsenic is an important element due to its deleterious impact on processing. The drilling described above should also focus on increased understanding on the distribution of arsenic mineralisation.

The additional drill core will enable dry bulk density measurements to be taken throughout the deposits.

It is recommended that drilling in the oxide and transitional zones be carried out for the purpose of mineralogical and metallurgical test-work. Oxide and secondary nickel minerals can impact metallurgical response, so it is important to determine the presence of these minerals.

Competent Person Attribution

The information in this report that relates to the Cooke and Widgie3 Mineral Resources is based on, and fairly represents, information compiled by Richard Maddocks,; MSc in Mineral Economics, BAppSc in Applied Geology and Grad Dip in Applied Finance and Investment, who is a Competent Person. Mr. Maddocks is a consultant to Auralia Mining Consulting and is a Fellow of the Australasian Institute of Mining and Metallurgy (member no. 111714) with over 30 years of experience. Mr. Maddocks has sufficient experience which is relevant to the style of mineralisation and type of deposit under consideration and to the activity which he is undertaking to qualify as a Competent Person as defined in the JORC Code. Mr. Maddocks consents to the inclusion in this report of the matters based on his information in the form and content in which it appears.

10 neometals.com.au

==> picture [596 x 64] intentionally omitted <==

----- Start of picture text -----

7 July 2021 – REVIEW OF NICKEL MINERAL RESOURCES AT MT EDWARDS COMPLETE
----- End of picture text -----

Compliance Statement

The information in this report that relates to Exploration Results and Mineral Resources for Neometals other than those discussed in this report relevant to Cooke and Widgie 3 are extracted from the ASX Announcements listed in the table below, which are also available on the Company’s website at www.neometals.com.au

19/04/2018 Mt Edwards Nickel - Mineral Resource Estimate
25/06/2018 Mt Edwards - Mineral Resource Over 120,000 Nickel Tonnes
05/08/2019 Mt Edwards Nickel – Drill Results
13/11/2019 Additional Nickel Mineral Resource at Mt Edwards
11/12/2019 Mt Edwards Nickel - Drill Results from Widgie South Trend
31/01/2020 Further Massive Nickel Sulphide Results from Mt Edwards
16/04/2020 Mt Edwards Nickel - Armstrong Resource increases 60%
26/05/2020 Mt Edwards Nickel - Gillett Resource increases 30%
06/10/2020 Mt Edwards Nickel - Mineral Resource and Exploration Update
23/12/2020 Mt Edwards Nickel - Zabel Mineral Resource Update
29/06/2021 Mt Edwards – McEwen Mineral Resources increase 45%
29/06/2021 Mt Edwards – Widgie Townsite Mineral Resource Update
30/06/2021 Mt Edwards – 26 North Mineral Resources Increase 51%

The Company confirms that it is not aware of any new information or data that materially affects the information included in the original market announcements and that all material assumptions and technical parameters underpinning the estimates in the market announcements continue to apply and have not materially changed. The Company confirms that the form and context in which the Competent Persons’ findings are presented have not been materially modified from the original market announcements.

Authorised on behalf of Neometals by Christopher Reed, Managing Director.

ENDS

For further information, please contact:

Chris Reed

Managing Director Neometals Ltd T: +61 8 9322 1182 E: [email protected]

Jeremy Mcmanus

General Manager - Commercial and IR Neometals Ltd T: +61 8 9322 1182

E: [email protected]

==> picture [558 x 26] intentionally omitted <==

About Neometals Ltd

  • Neometals innovatively develops opportunities in minerals and advanced materials essential for a sustainable future. With a focus on the energy storage megatrend, the strategy focuses on de-risking and developing long life projects with strong partners and integrating down the value chain to increase margins and return value to shareholders.

Neometals has three core projects that support the global transition to clean energy and span the battery value chain:

Recycling and Resource Recovery:

  • Lithium-ion Battery Recycling – a proprietary process for recovering nickel, cobalt and other valuable materials from spent and scrap lithium batteries. Completing construction of demonstration scale plant with 50:50 JV partner SMS group. Targeting a development decision in Mar Q 2022; and

  • Vanadium Recovery – sole funding evaluation studies to form a 50:50 joint venture with Critical Metals Ltd to recover high-purity vanadium pentoxide from processing by-products (“Slag”) from leading Scandinavian steelmaker SSAB. Underpinned by a 10-year Slag supply agreement, Neometals is targeting an investment decision to develop a 200,000tpa processing plant in DecQ 2022.

Upstream Industrial Minerals:

  • Barrambie Titanium and Vanadium Project - one of the world's highest-grade hard-rock titanium-vanadium deposits, working towards a development decision in 2022 with potential operating JV partner IMUMR and potential cornerstone product off-taker, Jiuxing Titanium Materials Co.

11

neometals.com.au

==> picture [596 x 64] intentionally omitted <==

----- Start of picture text -----

7 July 2021 – REVIEW OF NICKEL MINERAL RESOURCES AT MT EDWARDS COMPLETE
----- End of picture text -----

APPENDIX 1: Table 1 as per the JORC Code Guidelines (2012) for Widgie 3 Section 1 Sampling Techniques and Data

(Criteria in this section apply to all succeeding sections.)

Criteria JORC Code explanation JORC Code explanation Commentary Commentary
Sampling Nature and quality of sampling (e.g. cut channels, The Widgie 3 Mineral Resource has been drilled by percussion, diamond drilling and RC
techniques random chips, or specific specialised industry standard drilling. Drilling data exists for 110 drill holes for 14,733.96 metres. A total of 33 holes had
measurement tools appropriate to the minerals under one or more intercepts over 1% Ni. The majority of these holes were drilled by Western
investigation, such as down hole gamma sondes, or Mining Corporation and date from the 1980s – 1990s period.
handheld XRF instruments, etc.). These examples
should not be taken as limiting the broad meaning of
sampling.
The Mineral Resource has been drilled on a spacing of about 50m by 25m in the
mineralisation.
Diamond holes were selectively sampled through the visible mineralised zone on a
nominal 1m sample length, adjusted to geological and domain boundaries. Sample
lengths vary from 0.30m to about 1.5m.
Diamond core sampling techniques are not known but assumed to be industry standard
at the time of collection.
RC drill holes sampling techniques are not known but assumed to be industry standard
at the time of collection.
Include reference to measures taken to ensure Sample representivity for diamond core and RC samples is unknown but assumed to be
sample representivity and the appropriate calibration industry standard at the time of collection.
of any measurement tools or systems used.
Aspects of the determination of mineralisation that Sample lengths for diamond drilling range from 0.3 to 1.5 m with the modal value
are material to the Public Report. approximately 1.0 m. RC samples ranged from 4 metres in waste material to 1 metre in
or near mineralisation.
In cases where ‘industry standard’ work has been Mineralisation consists of contact massive sulphides (pyrite, pyrrhotite, pentlandite,
done this would be relatively simple (eg ‘reverse chalcopyrite and gersdorffite) typically less than 1 metre thick overlain by matrix
circulation drilling was used to obtain 1 m samples sulphides and disseminated sulphides
from which 3 kg was pulverised to produce a 30 g
charge for fire assay’). In other cases more explanation
may be required, such as where there is coarse gold
that has inherent sampling problems. Unusual

The majority of the drilling, sampling and assaying was completed by Western Mining
Corporation during the late 1980’s through to the early 1990’s. How the samples were
collected and which laboratory completed the analysis is unknown.
commodities or mineralisation types (eg submarine
nodules) may warrant disclosure of detailed
Minor copper, cobalt and arsenic occur in the mineralisation.
information
Drilling techniques Drill type (eg core, reverse circulation, open-hole The database used in the area of the mineral resource is comprised of diamond drilling
hammer, rotary air blast, auger, Bangka, sonic, etc) samples (57), RC drilling samples (273), and unspecified (3746).
and details (eg core diameter, triple or standard tube,
depth of diamond tails, face-sampling bit or other
Diamond drilling diameter is unknown.
type, whether core is oriented and if so, by what
method, etc).
Drill sample
recovery
Method of recording and assessing core and chip
sample recoveries and results assessed.
It is unknown whether core recoveries were recorded by WMC
Measures taken to maximise sample recovery and RC samples recoveries or weights were not recorded.
ensure representative nature of the samples. No sample recovery data exits for the historical drilling.
Whether a relationship exists between sample
recovery and grade and whether sample bias may
have occurred due to preferential loss/gain of
fine/coarse material.
Logging Whether core and chip samples have been Detailed drill hole logs are available for the majority of the drilling.
geologically and geotechnically logged to a level of
detail to support appropriate Mineral Resource
estimation, mining studies and metallurgical studies.
The logging is of a detailed nature, and of sufficient detail to support the current Mineral
RTesource estimate categories.
Whether logging is qualitative or quantitative in
nature. Core (or costean, channel, etc) photography.
The total length of drill intersections within the modelled domains used in the Mineral
Resource estimate is 463.36 metres.
The total length and percentage of the relevant
intersections logged.
Sub-sampling If core, whether cut or sawn and whether quarter, half
Core sampling techniques are unknown but are assumed to have been industry
techniques and or all core taken. standard at the time of collection.
sample
preparation
If non-core, whether riffled, tube sampled, rotary split,
RC drilling sampling techniques are unknown but are assumed to be industry standard

12 neometals.com.au

==> picture [596 x 64] intentionally omitted <==

----- Start of picture text -----

7 July 2021 – REVIEW OF NICKEL MINERAL RESOURCES AT MT EDWARDS COMPLETE
----- End of picture text -----

etc and whether sampled wet or dry. at the time.
For all sample types, the nature, quality and Sample conditions are unknown
appropriateness of the sample preparation technique. Sample preparation is unknown but assumed to have been industry standard for the
Quality control procedures adopted for all sub- time.
sampling stages to maximise representivity of
samples.
Quality control procedures are unlikely to have been used. considering the time period
(the late 1980’s through to the early 1990’s) the majority of drilling and sampling
Measures taken to ensure that the sampling is occurred.
representative of the in situ material collected,
including for instance results for field
duplicate/second-half sampling.
The host rock is mainly a serpentinite lens at the base of an ultramafic sequence. It is
assumed that WMC’s sampling would have been appropriate for the style of
mineralisation.
Whether sample sizes are appropriate to the grain size
of the material being sampled.
Criteria JORC Code explanation Commentary
Quality of assay For geophysical tools, spectrometers, handheld XRF No Quality control procedures were used at the time
data and
laboratory tests
instruments, etc, the parameters used in determining
the analysis including instrument make and model,
reading times, calibrations factors applied and their
No geophysical methods or hand-held XRF units have been used for determination of
grades in the Mineral Resource estimate.
derivation, etc.
Nature of quality control procedures adopted (eg
standards, blanks, duplicates, external laboratory
checks) and whether acceptable levels of accuracy (ie
lack of bias) and precision have been established.
Verification of The verification of significant intersections by either Multiple intersections reported have been checked back to original logs and assay data.
sampling and independent or alternative company personnel.
assaying
The use of twinned holes. No twin holes have been drilled.
Documentation of primary data, data entry procedures,
Drill hole data were sourced from digital sources and original hard-copy sampling and
data verification, data storage (physical and electronic) assay records, and imported into a central electronic database. Datashed software was
protocols. used by Apollo Phoenix to validate and manage the data.
Discuss any adjustment to assay data. Assays were composited to 1m lengths and where necessary, top cuts applied for
Mineral Resource estimation. Nickel and Arsenic grades were cut to account for outliers
in the populations.
Location of data Accuracy and quality of surveys used to locate drill holes
Surface topography is derived from drill hole collars and the historical WMC pick-ups of
points (collar and down-hole surveys), trenches, mine the Widgie 3 open pit and underground workings.
workings and other locations used in Mineral Resource
estimation.
It is assumed that the majority of the drillholes were downhole surveyed by a single shot
tool and by collar measurement with a clinometer and compass. A minority of holes
were down hole surveyed by a gyro. Survey type is not recorded for most of the drilling.
Specification of the grid system used. Original surveying was undertaken in Kambalda Nickel Operations Grid and then later
in GDA94 grid
Quality and adequacy of topographic control. Topographic control is considered poor and should be re-done using modern methods.
Data spacing Data spacing for reporting of Exploration Results. The Mineral Resource area has been drilled on a regular pattern and spacing by WMC.
and distribution The average spacing is estimated to be approximately 50m by 25m within the Mineral
Resource
Whether the data spacing and distribution is sufficient The drill data spacing and sampling is adequate to establish the geological and grade
to establish the degree of geological and grade continuity required for the current Mineral Resource estimate.
continuity appropriate for the Mineral Resource and
Ore Reserve estimation procedure(s) and classifications
applied.
Whether sample compositing has been applied Diamond drill hole samples were composited to 1.0 m down-hole intervals for resource
modelling. RC Samples used in the estimate were composited to 1m intervals already.

13 neometals.com.au

==> picture [596 x 64] intentionally omitted <==

----- Start of picture text -----

7 July 2021 – REVIEW OF NICKEL MINERAL RESOURCES AT MT EDWARDS COMPLETE
----- End of picture text -----

Orientation of Whether the orientation of sampling achieves unbiased The drill line and drill hole orientation is oriented as close as practicable to perpendicular
data in relation sampling of possible structures and the extent to which to the orientation of the general mineralised orientation.
to geological
structure
this is known, considering the deposit type. A majority of the drilling intersects the mineralisation at close to 90 degrees ensuring
If the relationship between the drilling orientation and intersections are representative of true widths.
the orientation of key mineralised structures is
considered to have introduced a sampling bias, this
should be assessed and reported if material.
Sample security The measures taken to ensure sample security. Sample security measures are unknown for WMC drilling.
Industry standard sample security standards were followed for Titan Resources drilling.
Audits or reviews The results of any audits or reviews of sampling Sample data reviews are unknown
techniques and data. Visualisation of drilling data was completed in three dimensional software (Micromine
and Surpac). Although these reviews are not definitive, they provide confidence in the
general reliability of the data.
Auralia undertook a review of the Mineral Resource usng Vulcan software in June 2021

Section 2 Reporting of Exploration Results

(Criteria listed in thepreceding (Criteria listed in thepreceding section also applyto this section.)
Criteria JORC Code explanation Commentary
Mineral tenement Type, reference name/number, location and Widgie 3 is on Mining Lease M15/94, beneficially owned by Mincor Resources
and land tenure
status
ownership including agreements or material issues
with third parties such as joint ventures,
partnerships, overriding royalties, native title
Neometals has held an interest in M15/94 since June 2018, hence all prior work has
been conducted by other parties.
interests, historical sites, wilderness or national park
and environmental settings.

Neometals holds nickel mineral rights on Mining Lease M15/94.
The security of the tenure held at the time of
reporting along with any known impediments to
obtaining a licence to operate in the area.
Exploration done by Acknowledgment and appraisal of exploration by Anaconda discovered Widgie 3 in 1967 as a result of gossan sampling. Diamond drilling
other parties other parties. by Anaconda and CRA delineated the first Mineral Resource in the late 1970s.
Exploration has been undertaken by previous holders, but predominantly Western
Mining Corporation (WMC) during the 1980s and early 1990s
Programs of RC and diamond drilling were undertaken by WMC as well as Mineral
Resource estimates, metallurgical test work and economic evaluations. WMC mined
Widgie 3 between 1988 to 1992.
Geology Deposit type, geological setting and style of
mineralisation.
The Widgie 3 deposit is located on the northeast flank of the Widgiemooltha Dome
within a sequence of intercalated mafic and ultramafic rocks.
Nickel mineralisation is located along the contact of basalt and ultramafic rocks. The
more massive higher grade mineralisation is developed within a serpentinite lens at the
base of the ultramafic sequence within an embayment along the contact.
The stratigraphy at a deposit scale consists of the Archaean Mt Edwards basalt overlain
by the Widgiemooltha Komatiite. The ultramafic succession consists of a series of flows
with intercalated sediments. It is approximately 250m thick and displays carbonate
alteration and serpentinisation. The mineral assemblages are talc-antigorite-chlorite-
magnetite and talc-magnesite-amphibolite-magnetite.
Mineralisation at Widgie 3 consists of contact massive sulphides (pyrite, pyrrhotite,
pentlandite, chalcopyrite and gersdorffite) typically less than 1 metre thick overlain by
matrix sulphides and disseminated sulphides. The mineralised envelope can be up to 19
metres thick (decreasing with depth) and 200 metres strike.
Depth of complete oxidation ranges from 15 to 30 metres.
Drill hole Information A summary of all information material to the See Drilling Information
understanding of the exploration results including a
tabulation of the following information for all
No information is excluded
Material drill holes:
o
easting and northing of the drill
hole collar
o
elevation or RL (Reduced Level
– elevation above sea level in

14 neometals.com.au

==> picture [596 x 64] intentionally omitted <==

----- Start of picture text -----

7 July 2021 – REVIEW OF NICKEL MINERAL RESOURCES AT MT EDWARDS COMPLETE
----- End of picture text -----

metres) of the drill hole collar
o
dip and azimuth of the hole
o
down hole length and
interception depth
o
hole length.
If the exclusion of this information is justified on the
basis that the information is not Material and this
exclusion does not detract from the understanding
of the report, the Competent Person should clearly
explain why this is the case.
Data aggregation In reporting Exploration Results, weighting Drill hole summary results are included in appendices to this report. The results
methods averaging techniques, maximum and/or minimum reported include all intersections included in the estimation of the Mineral Resource.
grade truncations (eg cutting of high grades) and
cut-off grades are usually Material and should be
A nominal cut off of 1.0% Ni was used to define the drill intersections composites.
stated. The table in the report contains all weighted composites included in the Mineral
Where aggregate intercepts incorporate short
lengths of high grade results and longer lengths of
Resource estimate. Higher grade intersections within the composites are included in
the table.
low grade results, the procedure used for such
aggregation should be stated and some typical
examples of such aggregations should be shown in
detail.
The assumptions used for any reporting of metal No metal equivalents are used in this Mineral Resource estimate.
equivalent values should be clearly stated.
Relationship These relationships are particularly important in the The drill line and drill hole orientation is oriented as close to 90 degrees to the
between reporting of Exploration Results. orientation of the anticipated mineralised orientation as practicable.
mineralisation
widths and intercept If the geometry of the mineralisation with respect The majority of the drilling intersects the mineralisation between 30 to 70 degrees.
lengths to the drill hole angle is known, its nature should be
reported.
If it is not known and only the down hole lengths
are reported, there should be a clear statement to
this effect (eg ‘down hole length, true width not
known’).
Diagrams Appropriate maps and sections (with scales) and Appropriate maps and tables are included in the body of the Reports.
tabulations of intercepts should be included for any
significant discovery being reported. These should
include, but not be limited to a plan view of drill
hole collar locations and appropriate sectional
views.
Balanced reporting Where comprehensive reporting of all Exploration All drill intercepts used in the estimation of the resource envelope irrespective of grade
Results is not practicable, representative reporting are reported in Table 3. The resource envelope is constructed using a nominal 1.0% Ni
of both low and high grades and/or widths should cut-off.
be practiced to avoid misleading reporting of
Exploration Results.
All drill hole collars are reported in Appendix 2
Other substantive Other exploration data, if meaningful and material, Mineral Resources were estimated from drill hole assay data, with geological logging
exploration data should be reported including (but not limited to): used to aid interpretation of mineralised contact positions.
geological observations; geophysical survey results;
geochemical survey results; bulk samples – size and
Geological observations are included in the report.
method of treatment; metallurgical test results;
bulk density, groundwater, geotechnical and rock
characteristics; potential deleterious or
Multi-element assay suites have been analysed and arsenic has been identified as a
potentially deleterious element.
contaminating substances. Bulk density measurements have been taken by WMC. Bulk density were assigned to
the block model using the formula. Bulk Density (t/m3) = 167.0654/(57.6714-Ni%)
Waste bulk density was assigned as 2.897. it is unknown how this figure was derived.
Further work The nature and scale of planned further work (eg No further work is planned at this stage.
tests for lateral extensions or depth extensions or
large-scale step-out drilling).
There is potential for possible extensions in the down plunge position to the current
mineral resource, but the grades are considered far too low to be economic at those
Diagrams clearly highlighting the areas of possible depths.
extensions, including the main geological
interpretations and future drilling areas, provided
this information is not commercially sensitive.
Drill spacing is currently considered adequate to undertake limited high level economic
evaluations on the project.

15

neometals.com.au

==> picture [596 x 64] intentionally omitted <==

----- Start of picture text -----

7 July 2021 – REVIEW OF NICKEL MINERAL RESOURCES AT MT EDWARDS COMPLETE
----- End of picture text -----

Section 3 Estimation and Reporting of Mineral Resources

(Criteria listed in section 1, and where relevant in section 2, also apply to this section.)

Criteria JORC Code explanation JORC Code explanation Commentary Commentary
Database integrity Measures taken to ensure that data has not
The drill hole database was sourced from original hard-copy sampling
been corrupted by, for example, and assay records
transcription or keying errors, between its
initial collection and its use for Mineral
Validation measures included spot checking between database and hard
Resource estimation purposes. copy drill logs and sections and plans in historic reports.
Data validation procedures used. The database is an extract from an Industry Standard SQL Server
database using a normalised assay data model produced by Datashed
Software.
Site visits Comment on any site visits undertaken by The Competent Person visited the Widgie 3 pit in March 2020 and
the Competent Person and the outcome of inspected the mineralised exposures in the historic open pit.
those visits.
If no site visits have been undertaken
indicate why this is the case.
Geological interpretation Confidence in (or conversely, the The Widgie 3 deposit was discovered in the 1967 by Anaconda. WMC
uncertainty of) the geological interpretation acquired the deposit by 1984 and mined it by open pit and underground
of the mineral deposit. methods between 1988 - 1991. Titan Resources acquired the deposit in
2004.
Nature of the data used and of any
assumptions made. Historical assay and geological data was used in the interpretations.
The effect, if any, of alternative For this Mineral Resource estimate a 1% Ni cut-off was used, with the
interpretations on Mineral Resource interpretation based on structural and stratigraphic controls. The only
estimation. valid departure from this interpretation would be to apply a different
The use of geology in guiding and grade cut-off; the effect of which can be found in the Appendix 3
controlling Mineral Resource estimation. Wireframe boundaries were regularised on sections, with the use of
The factors affecting continuity both of
grade and geology.
geological logging being used as a guide when considering the
interpretation of the mineralised wireframe. Interpretations were
prepared on 20m section spacings cut at bearing 90 degrees on a rotated
MGA94 zone 51 grid.
Given the drill spacing, pinching, swelling and truncation of the
mineralisation is possible between the drillholes, as observed in many of
the other nickel mining operations in the area.
The boundaries of the broader mineralised zone are consistent, but
within these zones, higher/ lower grade and thicker/ thinner zones occur.
Dimensions The extent and variability of the Mineral The Mineral Resource extends over a strike length of approximately 360
Resource expressed as length (along strike m. The Mineral Resource models extend to about 350 m depth below
or otherwise), plan width, and depth below surface.
surface to the upper and lower limits of the
Mineral Resource.
The near surface Mineral Resource has been mined
Estimation and modelling techniques The nature and appropriateness of the Grades were estimated predominantly by ordinary kriging estimation of
estimation technique(s) applied and key 1.0m down-hole composited nickel assay grades from diamond and RC
assumptions, including treatment of holes within mineralised domain wireframes.
extreme grade values, domaining,
interpolation parameters and maximum
distance of extrapolation from data points.
If a computer assisted estimation method
Surpac software was used by Apollo Phoenix for data compilation,
domain wire-framing, and coding of composite values, statistics,
geostatistics and Mineral Resource estimation
was chosen include a description of
computer software and parameters used.
The availability of check estimates, previous
Previous Mineral Resource estimates have been made by several
estimates and/or mine production records companies from 1970s onwards.
and whether the Mineral Resource
estimate takes appropriate account of such
1080Kt @ 1.21% Ni late 1970s by Anaconda
data. 144Kt @ 1.80% Ni in 1991 (post mining) by WMC
Production data from WMC
1988-1989 61,906 tonnes @ 1.9% Ni (open pit)
1989-1990 6,597 tonnes 0.59% Ni (open pit)
An additional 40K tones @ 0.9% Ni was stockpiled as low grade
oxide

16

neometals.com.au

==> picture [596 x 64] intentionally omitted <==

----- Start of picture text -----

7 July 2021 – REVIEW OF NICKEL MINERAL RESOURCES AT MT EDWARDS COMPLETE
----- End of picture text -----

1990-1991 12,074 tonnes @ 4.18% Ni (underground)
1991-1992 2,084 tonnes @ 3.35% Ni (underground)
WMC exploited 3 surfaces at Widgie 3. The original interpretation had
all lenses continuous however with open pit mining it was found that
one of the surfaces was discontinuous resulting in about a 20% drop in
tonnes
1990-1991 12,074 tonnes @ 4.18% Ni (underground)
1991-1992 2,084 tonnes @ 3.35% Ni (underground)
WMC exploited 3 surfaces at Widgie 3. The original interpretation had
all lenses continuous however with open pit mining it was found that
one of the surfaces was discontinuous resulting in about a 20% drop in
tonnes
1990-1991 12,074 tonnes @ 4.18% Ni (underground)
1991-1992 2,084 tonnes @ 3.35% Ni (underground)
WMC exploited 3 surfaces at Widgie 3. The original interpretation had
all lenses continuous however with open pit mining it was found that
one of the surfaces was discontinuous resulting in about a 20% drop in
tonnes

The assumptions made regarding recovery
of by-products.

Estimation of deleterious elements or other
non-grade variables of economic
significance (eg sulphur for acid mine
drainage characterisation).

No consideration has been made for the recovery of by-products.

Arsenic is a significant deleterious element. It is quoted in drill results in
Appendix 3.

No consideration has been made with regard to sulphur levels in the
waste material but the assays are available. This is due to the preliminary
nature of economic evaluation to date.

In the case of block model interpolation,
the block size in relation to the average
sample spacing and the search employed.

Mineral Resources were estimated into the block model with 10m x 2.5m
x 5m parent blocks (strike, cross strike, vertical,) aligned N-S on a rotated
MGA94 zone 51 grid.

For precise volume representation, sub-blocking was allowed to 2.5m
x0.3125m x 2.5m

The modelling used an anisotropic search ellipsoid with minimum data
requirements of 8 data points and a maximum of 32 data points. The
estimation used a 3 pass expanding approach. The first pass was 30m x
30m x 10m

Any assumptions behind modelling of
selective mining units.

The estimates are not intended to reflect a fixed mining method but
could be amenable to several mining techniques.

Details of potential mining parameters have been considered but reflect
the early stage of the project evaluation.

Any assumptions about correlation
between variables.

Correlations between variable were not considered apart from bulk
density and nickel

Description of how the geological
interpretation was used to control the
resource estimates.

The geology and grade information was used in the creation of the
mineralised domain wireframes. A nominal 1.0% Ni cut-off was used to
define the mineralisation outline within geological units.

Discussion of basis for using or not using
grade cutting or capping.

Grade cutting of the input samples was used to down grade the effect of
outliers in the sample population on the estimation.
Nickel
Uncut
Cut
Min
0.024%
0.024%
Max
20.65%
7.00%
Mean
1.294%
1.194%
Median
0.740%
0.740%
Variance
3.719
1.646
Coef. of
Variation
1.491
1.074
Number
Samples
469
9 samples cut
Arsenic
Uncut
Cut
Min
1.0ppm
1.0ppm
Max
11000.00
ppm
7000.00 ppm
Mean
547.703ppm
501.533ppm
Median
45.00ppm
45.00ppm
Variance
2588413.127
1838803.376
Coef. of
Variation
2.937
2.704
Number
Samples
235
5 samples cut
Nickel
Uncut Cut
Min 0.024% 0.024%
Max 20.65% 7.00%
Mean 1.294% 1.194%
Median 0.740% 0.740%
Variance 3.719 1.646
Coef. of
Variation
1.491 1.074
Number
Samples
469 9 samples cut
Arsenic
Uncut Cut
Min 1.0ppm 1.0ppm
Max 11000.00
ppm
7000.00 ppm
Mean 547.703ppm 501.533ppm
Median 45.00ppm 45.00ppm
Variance 2588413.127 1838803.376
Coef. of
Variation
2.937 2.704
Number
Samples
235 5 samples cut

17

neometals.com.au

==> picture [596 x 64] intentionally omitted <==

----- Start of picture text -----

7 July 2021 – REVIEW OF NICKEL MINERAL RESOURCES AT MT EDWARDS COMPLETE
----- End of picture text -----

The process of validation, the checking Model validation included visual comparison of model estimates and
process used, the comparison of model composite grades using section analysis with the raw drilling data and the
data to drill hole data, and use of composite data. It is likely that the Ni grades are slightly overestimated
reconciliation data if available. due to more than one sample population in the data despite the high
grade cuts.
Moisture Whether the tonnages are estimated on a Tonnages are estimated on a dry tonnage basis
dry basis or with natural moisture, and the
method of determination of the moisture
content.
Cut-off parameters The basis of the adopted cut-off grade(s) or The cut off grades reflect Apollos perception of the potential range of
quality parameters applied. operating costs and prices of nickel.
The mineralised envelope is modelled using a nominal 1.0% Ni cut-off
grade
Mining factors Assumptions made regarding possible mining methods, Apollo Phoenix considered the possibility of both open cut and underground
or assumptions minimum mining dimensions and internal (or, if applicable, mining on the project.
external) mining dilution. It is always necessary as part of the
process of determining reasonable prospects for eventual
economic extraction to consider potential mining methods, but
Dependent on the cost parameters used and the nickel price, Mineral Resource,
or part thereof, is potentially amenable to open cut or underground mining.
the assumptions made regarding mining methods and
parameters when estimating Mineral Resources may not
always be rigorous. Where this is the case, this should be
reported with an explanation of the basis of the mining
assumptions made.
Metallurgical
factors or
assumptions
The basis for assumptions or predictions regarding metallurgical
amenability. It is always necessary as part of the process of
determining reasonable prospects for eventual economic
There were no metallurgical test work results available for Widgie 3 for this
report
extraction to consider potential metallurgical methods, but the The high arsenic levels need to be controlled with greater understanding on
assumptions regarding metallurgical treatment processes and the controls of its distribution.
parameters made when reporting Mineral Resources may not
always be rigorous. Where this is the case, this should be
reported with an explanation of the basis of the metallurgical
assumptions made.
Environmen-tal Assumptions made regarding possible waste and process Mine waste from previous mining is currently held in an above ground waste
factors or residue disposal options. It is always necessary as part of the dump. It would be expected that this practice was continued when mining
assumptions process of determining reasonable prospects for eventual recommences.
economic extraction to consider the potential environmental
impacts of the mining and processing operation. While at this
stage the determination of potential environmental impacts,
High talc and carbonate content and the low sulphide content in the waste rock
suggest that ARD should not be a problem.
particularly for a greenfields project, may not always be well
advanced, the status of early consideration of these potential
environmental impacts should be reported. Where these
aspects have not been considered this should be reported with
an explanation of the environmental assumptions made.
Bulk density Whether assumed or determined. If assumed, the basis for the Bulk density measurements have been taken by WMC. Bulk density were
assumptions. If determined, the method used, whether wet or assigned to the block model using the formula. Bulk Density (t/m3) =
dry, the frequency of the measurements, the nature, size and 167.0654/57.6714*Ni%
representativeness of the samples. Waste bulk density was assigned as 2.897. it is unknown how this figure was
The bulk density for bulk material must have been measured by derived but it seems reasonable for the rock type and sufficient for the
methods that adequately account for void spaces (vugs, classification of the Mineral Resource.
porosity, etc), moisture and differences between rock and
alteration zones within the deposit.
Discuss assumptions for bulk density estimates used in the
evaluation process of the different materials.
Classification The basis for the classification of the Mineral Resources into Mineral Resource classification was assigned on the basis of geological
varying confidence categories. continuity and confidence.
Whether appropriate account has been taken of all relevant The Mineral Resource classification accounts for all relevant factors in the
factors (ie relative confidence in tonnage/grade estimations, opinion of the Competent Person
reliability of input data, confidence in continuity of geology and
metal values, quality, quantity and distribution of the data).

18 neometals.com.au

==> picture [596 x 64] intentionally omitted <==

----- Start of picture text -----

7 July 2021 – REVIEW OF NICKEL MINERAL RESOURCES AT MT EDWARDS COMPLETE
----- End of picture text -----

Whether the result appropriately reflects the Competent Classification of the estimates reflects the Competent Person’s views of the
Person’s view of the deposit. deposit
Audits or The results of any audits or reviews of Mineral Resource A detailed audit was completed by Auralia Mining Consulting on the Mineral
reviews estimates. Resource estimate to prepare this JORC 2012 statement
Discussion of Where appropriate a statement of the relative accuracy and Confidence in the relative accuracy of the estimates is reflected by the
relative confidence level in the Mineral Resource estimate using an classifications of the Mineral Resource resource.
accuracy/
confidence
approach or procedure deemed appropriate by the Competent
Person. For example, the application of statistical or
geostatistical procedures to quantify the relative accuracy of the
resource within stated confidence limits, or, if such an approach
is not deemed appropriate, a qualitative discussion of the
factors that could affect the relative accuracy and confidence of
The geostatistical procedures used to estimate, quantify and qualify the block
model were completed to a reasonable standard however only nickel and
arsenic were estimated. Usually a nickel estimate will include other attributes
including non-sulphide nickel, copper, cobalt, MgO, iron and sulphur. Only
nickel has been reported.
the estimate. There is a low – moderate level of confidence in the spatial accuracy of the
The statement should specify whether it relates to global or
local estimates, and, if local, state the relevant tonnages, which
datasets used in the Mineral Resource estimate as the survey control is
unknown
should be relevant to technical and economic evaluation.
Documentation should include assumptions made and the
procedures used.
Significant production data is available for the Widgie 3 deposit that would feed
back in an economic evaluation of the deposit
These statements of relative accuracy and confidence of the
estimate should be compared with production data, where
available.

APPENDIX 2: Table 1 as per the JORC Code Guidelines (2012) for Cooke

Section 1 Sampling Techniques and Data

(Criteria in this section apply to all succeeding sections.)

Criteria JORC Code explanation JORC Code explanation Commentary Commentary
Sampling Nature and quality of sampling (e.g. cut channels, random chips, The Cooke are has been drilled by Aircore, percussion, diamond drilling and RC
techniques or specific specialised industry standard measurement tools drilling. Accurate drilling data exists for 147 drill holes for 18,888.48 metres. A
appropriate to the minerals under investigation, such as down total of 58 holes had one or more intercepts over 1% Ni.
hole gamma sondes, or handheld XRF instruments, etc.). These
examples should not be taken as limiting the broad meaning of
sampling.
The holes have been drilled on irregular spacing as tight as 30m by 15m in the
central high grade part of the mineralisation.
Diamond holes were selectively sampled through the visible mineralised zone on
a nominal 1.5m sample length for historic drilling, and 1m for Titan Resources
drilling, adjusted to geological and domain boundaries. Sample lengths vary from
0.2m to 5.3m.
Diamond core samples have been sampled by a combination of quarter core
and half core cut samples and a combination of BQ, NQ and HQ diameter.
For Titan Resources drilling RC drill holes were sampled by 1m riffle split
composites. RC drilling was 5 ¼ inch in diameter. Samples were composited over
4 metre intervals in waste and 1 metre in mineralisation. For historic drilling RC
sampling techniques were not confirmed.
Include reference to measures taken to ensure sample Sample representivity for diamond core was ensured by the sampling of an
representivity and the appropriate calibration of any average length of 1m or 1.5m of core, which was then cut to quarter or half,
measurement tools or systems used. depending on the company operating at the time, for laboratory analysis.
RC sampling was riffle split from 1m composite bulk samples, producing a
nominal 3kg – 5kg representative sample for Titan drilling.
Aspects of the determination of mineralisation that are material Sample lengths for diamond drilling range from 0.05 to 5.3 m and average
to the Public Report. approximately 1.5 m from historical drilling. Titan drilling was sampled on a
nominal 1m length, adjusted to geological domains.
Mineralised intervals were determined by visual inspection and logging prior to
any sampling. Laboratory assays are then compared to the visual estimates and
logging to determine if any adjustments were required.

19

neometals.com.au

==> picture [596 x 64] intentionally omitted <==

----- Start of picture text -----

7 July 2021 – REVIEW OF NICKEL MINERAL RESOURCES AT MT EDWARDS COMPLETE
----- End of picture text -----

In cases where ‘industry standard’ work has been done this Mineralisation is identified pyrrhotite, pentlandite, violarite and pyrite with
would be relatively simple (eg ‘reverse circulation drilling was minor chalcopyrite hosted in talc-carbonate ultramafics.
used to obtain 1 m samples from which 3 kg was pulverised to
produce a 30 g charge for fire assay’). In other cases more
explanation may be required, such as where there is coarse gold
that has inherent sampling problems. Unusual commodities or
mineralisation types (eg submarine nodules) may warrant
disclosure of detailed information
For Titan, representative samples from RC and diamond drilling were collected
and sent to accredited laboratories for analysis. Accredited laboratories in
Kalgoorlie and Perth crushed and pulverised the samples in entirety, and took a
50g pulp for analysis. This process cannot be established for drilling completed
before the acquisition by Titan in 2001.
For Titan samples, analysis was performed by 4 acid digest and a combination
of ICP-MS and ICP-OES multi element analysis techniques. Gold and PGEs were
determined by a fire assay fusion followed by aqua regia digest and atomic
absorption spectrometer (AAS) finish. Analysis techniques were not established
for samples taken before 2001, but the results generally correlate well with
newer data.
Minor copper, cobalt and arsenic occur in the mineralisation.
International Nickel Australia Limited (INAL) and WMC Resources sampling and
assay techniques are unknown. These companies completed the majority of
the exploration and drilling work in the 1960’s and 1990’s respectively
Drilling Drill type (eg core, reverse circulation, open-hole hammer, rotary The database used in the mineral resource is comprised of diamond drilling
techniques air blast, auger, Bangka, sonic, etc.) and details (eg core diameter, samples (11253), RC drilling samples (4768), Percussion (904), Auger (64). Most
triple or standard tube, depth of diamond tails, face-sampling bit of the unspecified samples are actually historic diamond drilling drilled
or other type, whether core is oriented and if so, by what predominantly by Western Mining during the early 1990s.
method, etc.). Diamond drilling included NQ, HQ and BQ diameter core.
Drill sample
recovery
Method of recording and assessing core and chip sample
recoveries and results assessed.
Core recoveries were recorded for all resource database diamond core
collected by Titan. Handwritten geotechnical logging sheets were kept of all
Measures taken to maximise sample recovery and ensure drilling activities. Core recoveries are recorded in the database, however no
representative nature of the samples. information on the Cooke deposit could be located
Whether a relationship exists between sample recovery and RC samples recoveries or weights were not recorded.
grade and whether sample bias may have occurred due to
preferential loss/gain of fine/coarse material.
No relationship could be established between sample recovery and reported
grade. RC samples report a lower average grade than core samples overall which
is related their being drilled as RC pre-collars intersecting lower grades portions
outside of main body of the mineralisation, and diamond drilling focusing on
higher grade portions of the mineralisation.
Logging Whether core and chip samples have been geologically and Detailed drill hole logs (all drilling), geotechnical and structural logs (core only)
geotechnically logged to a level of detail to support appropriate are available for the drilling completed by Titan Resources Limited.
Mineral Resource estimation, mining studies and metallurgical
studies.
Separate sample logging sheets were kept including samples numbers for
duplicates, standards and blanks taken for QA/QC purposes.
Whether logging is qualitative or quantitative in nature. Core (or
costean, channel, etc.) photography.
The logging is of a detailed nature, and of sufficient detail to support the current
mineral resource estimate categories.
The total length and percentage of the relevant intersections
logged.
The total length of drill intersections used in the Mineral Resource estimate is
14,104.50m and 100% of those intersections are logged.
Sub-sampling If core, whether cut or sawn and whether quarter, half or all core The core was halved or quartered, depending on which company and phase of
techniques and taken. work, by sawing before sampling
sample
preparation
If non-core, whether riffled, tube sampled, rotary split, etc. and For Titan Resources, RC drilling was riffle split directly from the sample collection
whether sampled wet or dry. cyclone on the drilling rig.
For all sample types, the nature, quality and appropriateness of For Titan Resources, Sample condition field to record moisture and sample
the sample preparation technique. recovery is included in the sampling log sheet and populates the assay table of
Quality control procedures adopted for all sub-sampling stages to
maximise representivity of samples.
the database. Unfortunately, only a very small percentage of the logs have
captured this information so no determination can be made about the quality
of the RC samples.
Measures taken to ensure that the sampling is representative of
the in situ material collected, including for instance results for
field duplicate/second-half sampling.
Sample preparation is considered to be appropriate for RC and diamond drilling
as per industry standard practices for managing RC samples and diamond core.
Whether sample sizes are appropriate to the grain size of the
material being sampled.
For Titan Resources, quality control procedures included the inclusion of field
duplicates, standard samples and blank samples into the sampling stream for
laboratory analysis. 32 QAQC samples are included in the dataset used for this

20

neometals.com.au

==> picture [596 x 64] intentionally omitted <==

----- Start of picture text -----

7 July 2021 – REVIEW OF NICKEL MINERAL RESOURCES AT MT EDWARDS COMPLETE
----- End of picture text -----

mineral resource estimate.

  • Host rock is mainly a talc-carbonate ultramafic with minor interflow sediments (black shales). Samples of diamond core and RC samples produce appropriate size samples to be representative for the style of mineralisation and rock type encountered.

  • • International Nickel Australia Limited (INAL) and WMC Resources sampling and assay techniques are unknown. These companies completed the majority of the exploration and drilling work in the 1960’s and 1990’s respectively

Quality of assay For geophysical tools, spectrometers, handheld XRF For Titan Resources, quality control procedures included the inclusion of field
data and instruments, etc., the parameters used in determining the duplicates, standard samples and blank samples into the sampling stream for
laboratory tests analysis including instrument make and model, reading times, laboratory analysis.
calibrations factors applied and their derivation, etc. For Titan Resources, one standard, blank and field duplicate were inserted into
Nature of quality control procedures adopted (eg standards, the sample stream every 20 samples. These were offset through the sampling
blanks, duplicates, external laboratory checks) and whether stream and placed in areas of interest i.e. high grade standards and blanks in the
acceptable levels of accuracy (ie lack of bias) and precision have ore zone where possible.
been established.
For Titan Resources, overall, standards used reported values within 2 standard
deviations of the expected values with a few exceptions. These were usually
found to be sample miss labelling in the field and were largely able to be rectified
in the database.
It is unknown whether INAL or WMC used QAQC procedures.
No geophysical methods or hand-held XRF units have been used for
determination of grades in the mineral resource estimate.
Verification of The verification of significant intersections by either Intersections reported have been checked back to original logs and assay data.
sampling and independent or alternative company personnel.
assaying
The use of twinned holes. No twin holes have been drilled.
Documentation of primary data, data entry procedures, data Drill hole data were sourced from digital sources and original hard-copy
verification, data storage (physical and electronic) protocols. sampling and assay records, and imported into a central electronic database.
Datashed software was used to validate and manage the data.
Discuss any adjustment to assay data. Assays were composited to 1.5m lengths for Mineral Resource estimation.
Location of data Accuracy and quality of surveys used to locate drill holes (collar Surface topography appears to be derived from the surface position of drill
points and down-hole surveys), trenches, mine workings and other holes.
locations used in Mineral Resource estimation.
Collar co-ordinates were picked up by Spectrum Surveys in 2006.
A majority of the drill holes were downhole surveyed with gyroscopic survey
tool. The remaining holes were surveyed by single shot tool and by collar
measurement with a clinometer and compass.
Specification of the grid system used. Original surveying was undertaken in MGA94
Quality and adequacy of topographic control. Topographic control is considered adequate for the current Mineral Resource
estimate as it was completed by a licenced surveyor using a RTKDGPS.
Data spacing Data spacing for reporting of Exploration Results. The Mineral Resource area has been drilled on a regular pattern and spacing by
and distribution different companies over an extended period. The average spacing is estimated
to be approximately 30m by 15m within the mineral resource
Whether the data spacing and distribution is sufficient to The drill data spacing and sampling is adequate to establish the geological and
establish the degree of geological and grade continuity grade continuity required for the current Mineral Resource estimate.
appropriate for the Mineral Resource and Ore Reserve
estimation procedure(s) and classifications applied.
Whether sample compositing has been applied Diamond drill hole samples were composited to 1.5 m down-hole intervals for
Mineral Resource modelling.

21 neometals.com.au

==> picture [596 x 64] intentionally omitted <==

----- Start of picture text -----

7 July 2021 – REVIEW OF NICKEL MINERAL RESOURCES AT MT EDWARDS COMPLETE
----- End of picture text -----

Orientation of Whether the orientation of sampling achieves unbiased The drill line and drill hole orientation is oriented as close as practicable to
data in relation sampling of possible structures and the extent to which this is perpendicular to the orientation of the general mineralised orientation.
to geological
structure
known, considering the deposit type. A majority of the drilling intersects the mineralisation at close to 60 to 90
If the relationship between the drilling orientation and the degrees ensuring intersections are representative of true widths.
orientation of key mineralised structures is considered to have
introduced a sampling bias, this should be assessed and
reported if material.
Sample security The measures taken to ensure sample security. For Titan Resources, sample security measures adopted include the daily
movement of core samples in trays to the Kalgoorlie Office, where core was
kept in a secure area before cutting and sampling.
For Titan Resources, RC split samples were transported from site daily and
delivered to the accredited laboratory depot in Kalgoorlie for preparation and
analysis.
For Titan Resources, Reports and original log files indicate at a thorough process
of logging, recording, sample storage and dispatch to labs was followed at the
time of drilling.
The measures taken by INAL and WMC are unknown
Audits or The results of any audits or reviews of sampling techniques and Sample data reviews have included an inspection and investigation of all
reviews data. available paper and digital geological logs to ensure correct entry into the drill
hole database.
Visualisation of drilling data in three dimensional software (Micromine) and
QA/QC sampling review using Maxwell Geoservices QAQCR Software was
undertaken by Apollo Phoenix. Although these reviews are not definitive, they
provide confidence in the general reliability of the data.
Auralia Mining Consulting reviewed the Mineral Resource Estimation and
determined there were no fatal flaws with the estimate and interpretation.

Section 2 Reporting of Exploration Results

(Criteria listed in the preceding section also apply to this section.)

Criteria JORC Code explanation JORC Code explanation Commentary Commentary
Mineral tenement and
Type, reference name/number, location and ownership Neometals, either it its own right or through its 100% owned subsidiary Mt
land tenure status including agreements or material issues with third parties Edwards Lithium Pty Ltd, holds all mineral rights other than gold on Mining
such as joint ventures, partnerships, overriding royalties, Lease M15/101.
native title interests, historical sites, wilderness or national
park and environmental settings.
There are no known impediments to operate in the area.
The security of the tenure held at the time of reporting
along with any known impediments to obtaining a licence
to operate in the area.
Exploration done by Acknowledgment and appraisal of exploration by other Neometals has held an interest in M15/101 since April 2018, hence all prior
other parties parties. work has been conducted by other parties. Exploration has been undertaken
by previous holders, but predominantly Western Mining Corporation (WMC)
during the 1980s and early 1990s.
Programs of diamond and RC drilling were undertaken by WMC as well as
Mineral Resource estimates, metallurgical test work and economic evaluations.
Geology Deposit type, geological setting and style of mineralisation. The Widgiemooltha area lies within the southern part of the Norseman-Wiluna
greenstone belt.
The stratigraphy at a deposit scale consists of the Archaean Mt Edwards basalt
overlain by the Widgiemooltha Komatiite. The ultramafic succession consists of
a series of flows with intercalated sediments. It is approximately 250m thick and
displays carbonate alteration and serpentinisation. The mineral assemblages
are
talc-antigorite-chlorite-magnetite
and
talc-magnesite-amphibolite-
magnetite. Stronger carbonate –chlorite alteration is noted around the
mineralised lenses.
The nickel mineralisation at Cooke occurs on or above the ultramafic/mafic
contact and is associated with a steep northerly plunging synclinal structure. The
syncline plunges at about 50 degrees to the north and dips steeply to the east.

22

neometals.com.au

==> picture [596 x 64] intentionally omitted <==

----- Start of picture text -----

7 July 2021 – REVIEW OF NICKEL MINERAL RESOURCES AT MT EDWARDS COMPLETE
----- End of picture text -----

  • WMC geologists recognised three mineralised surfaces; o Western inner synclinal contact, within which mineralisation is variable, from heavy matrix contact mineralisation in the synclinal keel, to lower tenor disseminated mineralisation in the north.

  • Eastern inner contact, which consists of high grade low tonnage mineralised zone that has limited strike and down dip potential.

  • Southern outer contact, which is typically heavy matrix in character, with minor massive mineralisation.

  • The nickel mineralisation has been defined over a strike of 180 metres and to a depth of 350 metres below the surface. True thickness of mineralisation varies from 2 metres to up to 10 metres.

Depth of oxidation is up to 40 metres.
Drill hole Information A summary of all information material to the See Appendix 2- Drilling Information
understanding of the exploration results including a
tabulation of the following information for all Material drill
No information is excluded
holes:
o
easting and northing of the drill hole
collar
o
elevation or RL (Reduced Level –
elevation above sea level in metres) of
the drill hole collar
o
dip and azimuth of the hole
o
down hole length and interception
depth
o
hole length.
If the exclusion of this information is justified on the basis
that the information is not Material and this exclusion does
not detract from the understanding of the report, the
Competent Person should clearly explain why this is the
case.
Data aggregation In reporting Exploration Results, weighting averaging Drill hole summary results are included in this report. The results reported
methods techniques, maximum and/or minimum grade truncations include all intersections included in the estimation of the resource.
(eg cutting of high grades) and cut-off grades are usually
Material and should be stated.
A nominal cut off of 1.0% Ni was used to define the drill intersections
composites. A 2m maximum internal dilution was used.
Where aggregate intercepts incorporate short lengths of
high grade results and longer lengths of low grade results,
the procedure used for such aggregation should be stated
and some typical examples of such aggregations should be
Appendix 3 in the report contains all composites included in the Mineral
Resource estimate. Higher grade intersections within the composites are
included in the table.
shown in detail.
The assumptions used for any reporting of metal No metal equivalents are used in this Mineral Resource estimate.
equivalent values should be clearly stated.
Relationship between These relationships are particularly important in the The drill line and drill hole orientation is oriented as close to 90 degrees to the
mineralisation widths reporting of Exploration Results. orientation of the anticipated mineralised orientation as practicable.
and intercept lengths If the geometry of the mineralisation with respect to the
drill hole angle is known, its nature should be reported.
If it is not known and only the down hole lengths are
reported, there should be a clear statement to this effect
(eg ‘down hole length, true width not known’).
Diagrams Appropriate maps and sections (with scales) and Appropriate maps and tables are included in the body of the Report.
tabulations of intercepts should be included for any
significant discovery being reported. These should include,
but not be limited to a plan view of drill hole collar locations
and appropriate sectional views.
Balanced reporting Where comprehensive reporting of all Exploration Results All drill intercepts used in the estimation of the mineralised resource envelope
is notpracticable,representative reportingof both low and irrespective ofgrade are reported in Appendix 3. The mineralised resource

23 neometals.com.au

==> picture [596 x 64] intentionally omitted <==

----- Start of picture text -----

7 July 2021 – REVIEW OF NICKEL MINERAL RESOURCES AT MT EDWARDS COMPLETE
----- End of picture text -----

high grades and/or widths should be practiced to avoid envelope is constructed using a nominal 1.0% Ni cut-off and a maximum drilled
misleading reporting of Exploration Results. internal dilution of 2m.
All drill hole collars are reported in Appendix 2
Other substantive Other exploration data, if meaningful and material, should Mineral Resources were estimated from drill hole assay data, with geological
exploration data be reported including (but not limited to): geological logging used to aid interpretation of mineralised contact positions.
observations; geophysical survey results; geochemical
survey results; bulk samples – size and method of
treatment; metallurgical test results; bulk density,
groundwater, geotechnical and rock characteristics;
Geological observations are included in the report. All core drilled at Cooke was
available for review by Apollo Phoenix and is stored at the Fisher mine offices in
Kambalda.
potential deleterious or contaminating substances. Multi-element assay suites have been analysed and arsenic has been identified
as a potentially deleterious element.
Bulk density measurements have been taken and analysed. SGs were assigned
to the block model using the formula Bulk density (t/m3) = 167.0654/ (57.6714
– Ni %).
Further work The nature and scale of planned further work (eg tests for No further work is planned at this stage.
lateral extensions or depth extensions or large-scale step-
out drilling).
There is potential for possible extensions in the down plunge position to the
current mineral resource, but the grades are considered far too low to be
Diagrams clearly highlighting the areas of possible economic at those depths.
extensions, including the main geological interpretations
and future drilling areas, provided this information is not
commercially sensitive.
Drill spacing is currently considered adequate to undertake limited high level
economic evaluations on the project. Infill drilling would be required if more
detailed feasibility studies were to be undertaken.

Section 3 Estimation and Reporting of Mineral Resources

(Criteria listed in section 1, and where relevant in section 2, also apply to this section.)

Criteria JORC Code explanation JORC Code explanation Commentary Commentary
Database Measures taken to ensure that data has not been The drill hole database was sourced from original hard-copy sampling and assay records
integrity corrupted by, for example, transcription or keying
errors, between its initial collection and its use for
Mineral Resource estimation purposes.
Validation measures included spot checking between database and hard copy drill logs
and sections and plans in historic reports.
Data validation procedures used. The database used by Apollo Phoenix in 2016 was an extract from an Industry Standard
SQL Server database using a normalised assay data model produced by Datashed
Software.
Site visits Comment on any site visits undertaken by the The Competent Person visited the Armstrong and 132N deposits in March 2020. These
Competent Person and the outcome of those visits. two open pit mines are located along strike to the north and south respectively of the
If no site visits have been undertaken indicate why this unmined Cooke deposit and display very similar geological characteristics.
is the case.
Geological Confidence in (or conversely, the uncertainty of) the The Cooke deposit was discovered in the 1960’s. The project was acquired by WMC in
interpretation geological interpretation of the mineral deposit. 1979 and actively explored until the 1990’s. The project was acquired by Titan
Nature of the data used and of any assumptions made. Resources Limited in 2001 as part of the acquisition of the Widgiemooltha North
tenement package. Titan Resources were subsequently taken over by Consolidated
The effect, if any, of alternative interpretations on
Mineral Resource estimation.
Minerals (Consmin) in 2006. Consmin do not appear to have completed any meaningful
work. An extensive body of knowledge exists for the project and therefore confidence
in interpretations is relatively high.
The use of geology in guiding and controlling Mineral
Resource estimation.
Historical data as well as recent data collected by Titan were used in the interpretations.
The data from different companies and time periods correlated very well.
The factors affecting continuity both of grade and
geology.
For this Mineral Resource estimate a 1% Ni cut-off was used, with the interpretation
based on structural and stratigraphic controls. The only valid departure from this
interpretation would be to apply a different grade cut-off.
Wireframe boundaries do not appear to be “snapped” to drilling intercepts using the
sample positions. Interpretations were prepared on 30m section spacing cut at bearing
90 degrees on the MGA94 grid zone 51 grid.
The drill spacing is relatively wide and introduces sufficient uncertainty for the short
range variability and continuity in the deposit. The mineralisation is hosted in a high
strain environment which can adversely affect the continuity of the mineralisation and
mine reconciliations back to the Mineral Resource model.
Given the current wide drill spacing, pinching, swelling and truncation of the
mineralisation is possible between the drill holes, as observed in many of the nickel
mining operations in the area.

24

neometals.com.au

==> picture [596 x 64] intentionally omitted <==

----- Start of picture text -----

7 July 2021 – REVIEW OF NICKEL MINERAL RESOURCES AT MT EDWARDS COMPLETE
----- End of picture text -----

The boundaries of the broader mineralised zone are consistent, but within these zones,
higher/ lower grade and thicker/ thinner zones occur. It is expected that additional
drilling will define the distribution and nature of this variability.
Dimensions The extent and variability of the Mineral Resource The Mineral Resource model extends over a strike length of approximately 180 m. The
expressed as length (along strike or otherwise), plan resource models extend to 350 m depth below surface.
width, and depth below surface to the upper and lower
limits of the Mineral Resource.
The Mineral Resource is unmined
Estimation and The nature and appropriateness of the estimation Grades were estimated by ordinary kriging estimation of 1.5m down-hole composited
modelling technique(s) applied and key assumptions, including nickel and inverse distance squared for arsenic assay grades from diamond and RC
techniques treatment of extreme grade values, domaining, holes within mineralised domain wireframes.
interpolation parameters and maximum distance of
extrapolation from data points. If a computer assisted
estimation method was chosen include a description of
Micromine software was used for data compilation, domain wire-framing, and coding
of composite values, statistics, geostatistics and Mineral Resource estimation
computer software and parameters used.
The availability of check estimates, previous estimates Previous Mineral Resource estimates have been made by several companies from
and/or mine production records and whether the 1990’s onwards. The more recent estimates compare well with the current one as
Mineral Resource estimate takes appropriate account follows;
of such data.
o
126,0000 tonnes @ 1.85% Ni (WMC circa 1990’s)
o
163,989 tonnes @ 1.62% Ni (Titan Resources 2004)
The assumptions made regarding recovery of by- No consideration has been made for the recovery of by-products.
products. Arsenic is a significant deleterious element.
Estimation of deleterious elements or other non-grade
variables of economic significance (eg sulphur for acid
mine drainage characterisation).
No consideration has been made with regard to sulphur levels in the waste material
but the assays are available. This is due to the preliminary nature of economic
evaluation to date.
In the case of block model interpolation, the block size Mineral Resources were estimated into 10m x 10m x 2.5m parent blocks (strike,
in relation to the average sample spacing and the search vertical, cross strike) aligned around N-S on MGA94.
employed. For precise volume representation, sub-blocking was allowed to 2.5m x2.5m x
0.3125m
The nickel modelling used an anisotropic search ellipsoid with minimum data
requirements of 8 data points and a maximum of 32 points for pass 1 & 2. On the third
pass the number of samples was reduced to a minimum of 4 samples and a maximum
of 24. The starting search ellipse was 30m (Y) by 30m (Z) by 10m (X). This was increased
to 60m (Y) by 60m (Z) by 20m (X) on the second pass and 90m (Y) by 90m (Z) by 30m
(X) on the third pass. See table below.
Any assumptions behind modelling of selective mining The estimates are not intended to reflect a fixed mining method but could be
units. amenable to several mining techniques.
Details of potential mining parameters have been considered but reflect the early stage
of the project evaluation.
Any assumptions about correlation between variables. There is a strong correlation between nickel and copper; nickel and cobalt; and nickel
and sulphur (fresh rock). Further there is strong evidence that there is a good
correlation between nickel mineralisation and bulk density.
Description of how the geological interpretation was The geology and grade information was used in the creation of the mineralised domain
used to control the resource estimates. wireframes. A nominal 1.0% Ni cut-off was used to define the outline within geological
units. The selection of this cut-off is natural and corresponds with relatively “hard”
mineralisation boundaries.
Discussion of basis for using or not using grade cutting No grade cutting or capping has been used. Grades are relatively uniform within a
or capping. defined range, with no order of magnitude outlying high grades that would materially
affect the resource.
The process of validation, the checking process used, The block model was validated by viewing in vertical section and plan and comparing
the comparison of model data to drill hole data,and use to the samples. Declustered samplegrades were compared to the resource model

25 neometals.com.au

==> picture [596 x 64] intentionally omitted <==

----- Start of picture text -----

7 July 2021 – REVIEW OF NICKEL MINERAL RESOURCES AT MT EDWARDS COMPLETE
----- End of picture text -----

of reconciliation data if available. block grades.
There is no production information to reconcile against the model
Moisture Whether the tonnages are estimated on a dry basis or Tonnages are estimated on a dry tonnage basis
with natural moisture, and the method of
determination of the moisture content.
Cut-off The basis of the adopted cut-off grade(s) or quality The cut off grades reflect Apollos perception of the potential range of operating costs
parameters parameters applied. and prices of nickel and Auralia agrees that this view is acceptable.
The mineralised envelope is modelled using a 1.0% Ni cut-off grade
Mining factors or Assumptions made regarding possible mining The Mineral Resource has considered the possibility of both open cut and
assumptions methods, minimum mining dimensions and internal underground mining on the project.
(or, if applicable, external) mining dilution. It is
always necessary as part of the process of
determining reasonable prospects for eventual
economic extraction to consider potential mining
High level scoping studies have been completed by Titan Resources in 2006. Cooke
was found to be sub economic at the time, however there is the view that economic
extraction could occur in the future.
methods, but the assumptions made regarding
mining methods and parameters when estimating
Mineral Resources may not always be rigorous.
Dependent on the cost parameters used and the nickel price, Mineral Resource, or
part thereof, is potentially amenable to open cut or underground mining.
Where this is the case, this should be reported with
an explanation of the basis of the mining
assumptions made.
Metallurgical factors
or assumptions
The basis for assumptions or predictions regarding
metallurgical amenability. It is always necessary as
part of the process of determining reasonable
prospects for eventual economic extraction to
consider potential metallurgical methods, but the
Metallurgical test work was conducted by Western Mining in 1998 from nearby
deposits such as Widgiemooltha Townsite. The study indicated a nickel recovery of
90% producing a concentrate grade of 8% Ni, 5% MgO and 5000ppm As from a
head grade of 2.5% to 2.6% Ni.
assumptions regarding metallurgical treatment Bond Work index was low at 7.8KWhr/t which would result in lower processing costs
processes and parameters made when reporting
Mineral Resources may not always be rigorous. Talc content is approximately 45% in the mineralisation so suppression of talc would
Where this is the case, this should be reported with be of utmost importance.
an explanation of the basis of the metallurgical
assumptions made.
The high arsenic levels could present a problem if the concentrate was to feed the
NickelWest Smelter
Environmen-tal Assumptions made regarding possible waste and Precise details of potential waste and process residue disposal options are unclear
factors or process residue disposal options. It is always reflecting the early stage of project evaluation.
assumptions necessary as part of the process of determining
reasonable prospects for eventual economic
extraction to consider the potential environmental
impacts of the mining and processing operation.
High talc and carbonate content and low sulphide content in the waste rock suggest
that ARD should not be a problem, but further evaluation would be required for
approvals.
While at this stage the determination of potential
environmental impacts, particularly for a greenfields
project, may not always be well advanced, the status
of early consideration of these potential
environmental impacts should be reported. Where
these aspects have not been considered this should
be reported with an explanation of the
environmental assumptions made.
Bulk density Whether assumed or determined. If assumed, the Bulk density was derived from WMC’s historical regression where;
basis for the assumptions. If determined, the
method used, whether wet or dry, the frequency of
o
Bulk density (t/m3) = 167.0654/ (57.6714 – Ni %)
the measurements, the nature, size and o
Bulk density is quoted on a dry basis
representativeness of the samples.
Waste bulk density was not estimated (reason not known)
The bulk density for bulk material must have been
measured by methods that adequately account for
void spaces (vugs, porosity, etc.), moisture and
differences between rock and alteration zones
within the deposit.
Discuss assumptions for bulk density estimates used
in the evaluation process of the different materials.
Classification The basis for the classification of the Mineral Mineral Resource classification was assigned on the basis of geological continuity and
Resources into varying confidence categories. confidence and the number of drill hole intersections.

26

neometals.com.au

==> picture [596 x 64] intentionally omitted <==

----- Start of picture text -----

7 July 2021 – REVIEW OF NICKEL MINERAL RESOURCES AT MT EDWARDS COMPLETE
----- End of picture text -----

Whether appropriate account has been taken of all The Mineral Resource classification accounts for all relevant factors in the opinion of
relevant
factors
(ie
relative
confidence
in
the Competent Person
tonnage/grade estimations, reliability of input data,
confidence in continuity of geology and metal values,
quality, quantity and distribution of the data).
Whether the result appropriately reflects the Classification of the estimates reflects the Competent Person’s views of the deposit
Competent Person’s view of the deposit.
Audits or reviews The results of any audits or reviews of Mineral A detailed audit was completed on the Mineral Resource estimate to prepare this
Resource estimates. JORC 2012 statement
Discussion of relative Where appropriate a statement of the relative Confidence in the relative accuracy of the estimates is reflected by the classifications
accuracy/ confidence accuracy and confidence level in the Mineral assigned in the block model
Resource estimate using an approach or procedure
deemed appropriate by the Competent Person. For
example, the application of statistical or geostatistical
procedures to quantify the relative accuracy of the
resource within stated confidence limits, or, if such an
The geostatistical procedures used to estimate, quantify and qualify the block model
were completed to a reasonable standard. Usually a nickel estimate will include other
attributes including non-sulphide nickel, copper, cobalt, MgO, iron and sulphur. These
elements can be estimated with additional drilling, sampling and assaying data..
approach is not deemed appropriate, a qualitative
discussion of the factors that could affect the relative
accuracy and confidence of the estimate.
No blocks have been assigned an indicated or measured category which reflects the
relative confidence, or lack thereof, in the accuracy of the interpretations
The statement should specify whether it relates to
global or local estimates, and, if local, state the
relevant tonnages, which should be relevant to
technical and economic evaluation. Documentation
Significant doubts about the validity of the wireframe interpretations exist as the
Mineral Resource is located in a structurally complex and highly strained environment.
This has been demonstrated by mining activity on other similar deposits in the
Widgiemooltha area
should include assumptions made and the There is a low - moderate level of confidence in the spatial accuracy of the datasets
procedures used. used in the mineral resource estimate as the survey control is unknown
These statements of relative accuracy and No production data are available for reconciliation as no mining has been undertaken
confidence of the estimate should be compared with on the project
production data, where available.

APPENDIX 3 : Drillholes used in the Widgie 3 Mineral Resource estimate

Hole ID MGA94_North MGA94_East RL Depth Azimuth Dip
DWT121 6512105.59 365813.5 331.157 222 258.535 -45
DWT124 6512129.84 365838.97 331 84 258.535 -45
DWT125 6512130.53 365840.35 331 113 258.535 -60
DWT132A 6512077.24 365854.15 335.323 80 258.535 -45
DWT133 6512099.58 365877.13 332.477 132 258.535 -57
DWT136 6512041.87 365888.85 338.578 121 258.535 -45
DWT138 6512103.91 365949.96 330.73 211 253.535 -45
DWT141 6511991.53 365914.78 345.163 110.5 258.535 -45
DWT142 6512011.85 365934.63 340.557 201 250.535 -57
DWT143 6512011.35 365934.18 340.651 153 253.535 -50
DWT145 6511950.72 365941 348.162 120.12 258.535 -52
DWT146 6511971.24 365962.16 344.329 177 258.535 -60
DWT149 6512011.59 365893.44 343.28 96.36 248.535 -45
DWT150 6512091.05 365853.4 333.961 100 258.535 -60
DWT151 6511904.64 365896.1 350.597 60.5 78.535 -60
DWT152 6511907.64 365897.7 351.062 32 73.535 -49
DWT152A 6511907.64 365897.7 351.062 32 73.535 -59
DWT152B 6511907.64 365897.7 351.062 32 73.535 -59
DWT153 6511928.98 365850.15 349.223 54 81.535 -55

27 neometals.com.au

==> picture [596 x 64] intentionally omitted <==

----- Start of picture text -----

7 July 2021 – REVIEW OF NICKEL MINERAL RESOURCES AT MT EDWARDS COMPLETE
----- End of picture text -----

Hole ID MGA94_North MGA94_East RL Depth Azimuth Dip
DWT153A 6511928.98 365850.15 349.223 53.5 81.535 -55
DWT153B 6511928.98 365850.15 349.223 53.5 81.535 -55
DWT154 6511933.51 365854.36 350.258 31.5 84.535 -55
DWT154A 6511933.51 365854.36 350.258 31.5 84.535 -55
DWT154B 6511933.51 365854.36 350.258 31.5 84.535 -55
DWT155 6511936.51 365857.6 350.935 30.5 87.535 -60
DWT155A 6511936.51 365857.6 350.935 30.5 87.535 -60
DWT155B 6511936.51 365857.6 350.935 30.5 87.535 -60
DWT156 6512000.87 365847.98 345.762 38 78.535 -60
DWT156A 6512000.87 365847.98 345.762 37.5 78.535 -60
DWT156B 6512000.87 365847.98 345.762 37.5 78.535 -60
DWT157 6512005.75 365852.92 345.676 34 83.535 -60
DWT157A 6512005.75 365852.92 345.676 34 83.535 -60
DWT157B 6512005.75 365852.92 345.676 34 83.535 -60
DWT158 6512054.18 365830.71 336.915 38 82.535 -66
DWT158A 6512054.18 365830.71 336.915 38 82.535 -66
DWT158B 6512054.18 365830.71 336.915 38 82.535 -66
DWT159 6512055.241 365831.75 336.812 31 83.535 -60
DWT159A 6512055.241 365831.75 336.812 30.5 83.535 -60
DWT159B 6512055.241 365831.75 336.812 30.5 83.535 -60
DWT320 6512129.84 365907.56 330 60 258.535 -60
DWT321 6512117.34 365894.31 330.563 60 258.535 -60
DWT322 6512098.95 365878.03 332.431 60 258.535 -60
DWT323 6512087.02 365866.559 334.247 60 258.535 -60
DWT324 6512040.59 365748.81 336.968 55 258.535 -60
DWT325 6512025.589 365735.34 338.622 50 258.535 -60
DWT326 6512011.8 365719.79 340.275 60 258.535 -60
DWT327 6511997.1 365704.18 342.044 60 258.535 -60
DWT328 6511987.42 365692.18 342.91 60 258.535 -60
DWT329 6511935.25 365970.05 345.303 60 258.535 -60
DWT330 6511921.14 365956.17 349.16 60 258.535 -60
DWT331 6511907.02 365942.29 352.668 60 258.535 -60
DWT355 6512049.39 365927.21 334.951 169 219.535 -61.5
DWT356 6512049.39 365927.21 334.951 201 258.535 -55
DWT357 6511924.47 365804.06 344.111 217 83.535 -54.4
DWT358 6511924.47 365804.06 344.111 17 78.535 -60
DWT668 6511746.73 365972 330.39 744 78.535 -60
DWT670 6512213.49 366143.79 328.67 279 253.535 -55
HH569 6511950.21 365845.94 347.791 57.3 260.535 -60
HH570 6511979.23 365848.7 346.592 36.58 260.535 -50
WDC236 6512095 365895 332.044 180 259.905 -57.55
WDC237 6512162 365892 330 192 260.545 -49.96
WDC257 6512067 365907 Missing 120 Missing Missing
WDC258 6512085 365896 Missing 130 Missing Missing

28 neometals.com.au

==> picture [596 x 64] intentionally omitted <==

----- Start of picture text -----

7 July 2021 – REVIEW OF NICKEL MINERAL RESOURCES AT MT EDWARDS COMPLETE
----- End of picture text -----

Hole ID MGA94_North MGA94_East RL Depth Azimuth Dip
WDD080 6512054 365994 332.101 339.4 256.615 -56.24
WDD081 6512090.001 365972 330.585 330.6 258.205 -58
WDD082 6512140 365910 330 345.6 259.87 -62.99
WDD090 6512077.5 365922.5 Missing 100 Missing Missing
WPH54 6511995.49 365882.47 350.725 0 258.535 -45
WPH55 6511995.49 365882.47 350.725 54.03 258.535 -45
WPH56 6511985.81 365883.75 352.889 58.22 258.535 -45
WPH57 6511978.34 365887.13 354 30.33 258.535 -45
WPH60 6511858.36 365983.67 356 46.79 258.535 -45
WPH61 6511654.42 366108.35 324.89 41.91 258.535 -60
WPH62 6511727.37 366103.751 331.103 48.16 258.535 -60
WPH63 6511641.55 366123.45 324.89 32 258.535 -60
WPH64 6511669.5 366239.21 324.89 36.58 258.535 -60
WPH65 6511847.05 365943.78 352.697 58.06 303.535 -60
WPH66 6511694.83 366038.03 344.89 64.92 258.535 -60
WPS1 6512108.64 365841.61 331.672 82.3 258.535 -60
WPS2 6512090.51 365851.34 334.105 92.96 258.535 -60
WPT1 6512013.18 366167.69 329.411 75 258.535 -60
WPT2 6511713.54 366365.82 322.007 75 258.535 -62
WPT3 6511788.86 366370.57 322.327 95 258.535 -60
WWD1 6511993.05 365911.8 345.303 96.01 258.535 -45
WWD10 6512061.18 365980.24 331.925 155.14 78.535 -45
WWD11 6511953.079 366004.57 339.241 203.61 258.535 -45
WWD12 6512165.72 365949.871 330 247.35 258.535 -45
WWD13 6512269.93 365897.35 330 250.09 253.535 -43
WWD14 6511727.29 366236.69 322.39 156.51 258.535 -45
WWD15 6512064.6 365910.89 334.546 160.03 258.535 -45
WWD16 6511964.42 365904.67 352.615 77.05 258.535 -45
WWD17 6512167.73 365951.75 330 366.98 258.535 -60
WWD18 6511777.94 366100.3 330.866 150.27 258.535 -60
WWD19 6512245.93 365910.96 330 424.89 258.535 -65
WWD2 6512061.18 365980.24 331.925 206.96 258.535 -50
WWD20 6512104.3 366022.48 330.177 500.12 258.535 -60
WWD21 6512391.98 365915.67 337.49 455.98 258.535 -65
WWD22 6512058.74 366107.67 331.976 489.2 258.535 -60
WWD23 6511875.25 366062.74 336.691 181.66 258.535 -45
WWD24 6512127.43 365971.52 330 265 258.535 -46
WWD25 6511971.97 365958.89 344.4 344.2 258.535 -48
WWD26 6511991.67 366009.57 334.949 284 258.535 -61
WWD27 6511935.36 365954.18 347.841 142 258.535 -40
WWD28 6511786.01 366362.65 322.351 485 258.535 -65
WWD3 6511976.91 366028.461 334.877 286.66 258.535 -60
WWD30 6511942.85 366090.57 335.82 362 263.535 -65
WWD4 6512100.84 365885.48 331.814 134.11 258.535 -45

29

neometals.com.au

==> picture [596 x 64] intentionally omitted <==

----- Start of picture text -----

7 July 2021 – REVIEW OF NICKEL MINERAL RESOURCES AT MT EDWARDS COMPLETE
----- End of picture text -----

Hole ID MGA94_North MGA94_East RL Depth Azimuth Dip
WWD5 6512183.03 365822.17 331.089 120.24 258.535 -45
WWD6 6512292.42 365799.73 329.96 168.1 258.535 -45
WWD7 6511760.36 366083.42 330 120.58 258.535 -45

All coordinates are in MGA94_51S

APPENDIX 4 : Drillholes used in the Cooke Mineral Resource estimate

Hole_ID North_GDA94 EAST_GDA94 RL Depth Azimuth Dip
WD3216 6519981.98 361260.36 349 18.29 359.53 -90
WD3217 6519984.48 361275.39 348.03 30.48 359.53 -90
WD5000 6519979.49 361245.32 349.58 15.24 359.53 -90
WD5326 6519817.53 361386.21 347.11 153.01 260.53 -44
WD5335 6519827.07 361443.64 343.34 238.66 260.53 -44.59
WD5336 6519877.16 361371.53 346.35 150.88 260.53 -40.73
WD5339 6519847.36 361193.17 354.14 333.45 80.53 -65
WD5340 6519909.38 361195.19 355.6 238.96 89.12 -40.8
WD5348 6519996.78 361348.62 343.57 183.79 257.26 -45.28
WD5350 6519944.08 361404.02 344 232.87 245.9 -46.74
WD5408 6519781.52 361355.43 350.06 45.72 359.53 -90
WD5409 6519784.02 361370.46 348.99 18.29 359.53 -90
WD5410 6519786.52 361385.5 347.92 25.91 359.53 -90
WD5419 6519839.15 361330.42 349.18 42.67 80.53 -80
WD5420 6519808.59 361332.4 350.41 51.82 80.53 -80
WD5421 6519810.34 361342.93 349.82 39.62 80.53 -80
WD5422 6519806.59 361320.38 351.18 19.81 80.53 -80
WD5423 6519865.69 361307.22 348.89 51.82 80.53 -85
WD5424 6519869.21 361325.42 347.87 47.24 359.53 -90
WD5425 6519872.21 361343.47 347.45 24.38 359.53 -90
WD5426 6519864.72 361298.36 349.37 41.15 359.53 -90
WD5427 6519779.03 361340.41 351.06 22.86 359.53 -90
WD5428 6519810.59 361344.42 349.73 18.29 260.53 -50
WD5429 6519812.08 361353.45 349.21 44.2 260.53 -50
WD5430 6519810.59 361344.42 349.73 45.72 260.53 -50
WD5431 6519976.98 361230.3 350.22 36.58 359.53 -90
WD5432 6519974.49 361215.27 351.16 27.43 359.53 -90
WD5433 6519972 361200.23 352.19 13.72 359.53 -90
WD5665 6519923.1 361277.87 349.7 51.82 260.53 -70
WD5666 6519926.85 361300.41 347.66 56.39 260.53 -70
WD5802 6520006.9 361410.38 342.04 349 260.53 -61
WD6059 6519897.37 361327.54 346.72 88.39 260.53 -60
WD6256 6519786.52 361385.5 347.92 64.01 260.53 -60
WD6257 6519870.21 361331.43 347.73 60.96 260.53 -60
WD6258 6519931.6 361328.97 345.89 109.73 260.53 -60
WD6543 6519775.24 361392 347.72 118.87 260.53 -60
WD6544 6519842.15 361348.45 348.47 80.77 260.53 -65

30 neometals.com.au

==> picture [596 x 64] intentionally omitted <==

----- Start of picture text -----

7 July 2021 – REVIEW OF NICKEL MINERAL RESOURCES AT MT EDWARDS COMPLETE
----- End of picture text -----

Hole_ID North_GDA94 EAST_GDA94 RL Depth Azimuth Dip
WDC145 6519869.964 361316.873 354.444 80 270 -60
WDC146 6519834.985 361323.817 355.444 100 360 -90
WDC147 6519813.336 361357.72 355.444 94 270 -60
WDC148 6519798.659 361360.101 355.644 100 270 -60
WDC149 6519765.248 361365.488 352.744 70 270 -60
WDC150 6519781.956 361360.212 347.244 70 270 -60
WDC159 6519786.556 361355.985 350.444 49 360 -90
WDGT01 6519816.08 361280.584 360.044 60.2 268.78 -60.55
WDGT02 6519849.389 361268.942 363.944 120.2 90.87 -60.26
WDGT03 6519802.772 361360.95 345.744 60 80.48 -59.49
WDGT04 6519879.883 361320.718 350.444 65 88.35 -60.47
WDMT01 6519821.092 361355.867 354 114.5 268.69 -59.5
WDMT02 6519785.963 361361.395 349.044 80 270 -55.46
WDMT03 6519805.75 361359.754 346.844 120 270 -60
WID1237 6519810.86 361271.15 359.25 200 83.4 -65
WID1238 6519810.6 361411.44 345.73 200 262.52 -60.79
WID1423 6519912.51 361389.66 344.77 240.5 273.53 -57
WID1425 6519810.17 361398.71 346.53 211 269.53 -62
WID1645 6519783.76 361363.12 349.49 30 269.53 -60
WID1646 6519784.02 361373.15 348.81 50 269.53 -60
WID1647 6519784.87 361381.82 348.2 70 269.53 -60
WID1648 6519807.89 361343.63 349.87 60 271.53 -60
WID1649 6519806.84 361353.09 349.43 80 269.53 -60
WID1650 6519806.77 361361.18 348.97 100 269.53 -60
WID1651 6519832.22 361333.8 349.38 30 269.53 -60
WID1652 6519833.61 361344.08 348.97 50 269.53 -60
WID1653 6519834.26 361352.95 348.52 70 269.53 -60
WID1654 6519857.38 361311.51 349.12 30 269.53 -60
WID1655 6519857.89 361322.28 348.45 58 269.53 -60
WID1656 6519858.21 361329.74 348.27 80 269.53 -60
WID1657 6519880.74 361290.7 348.57 30 269.53 -60
WID1658 6519881.96 361300.78 348.12 52 269.53 -60
WID1659 6519883.18 361311.73 347.72 70 269.53 -60
WID1675 6519806.98 361385.47 347.45 150 261.22 -44.06
WID1779 6519884.51 361341.71 347.02 157.3 269.8 -61
WID1781 6519784.19 361360.97 349.63 111 269.53 -59
WID1791 6519839.71 361363.52 347.8 100 269.53 -60
WID1792 6519840.95 361373.9 347.19 100 269.53 -60
WID1793 6519858.95 361336.5 348.08 118 269.53 -60
WID1794 6519883.89 361321.06 347.41 92 269.53 -60
WID1795 6519885.1 361329.59 347.14 120 269.53 -60
WID1796 6519858.87 361357.38 347.47 146 269.53 -60
WID1797 6519912.48 361287.21 348.59 40 269.53 -60
WID1798 6519911.23 361296.72 347.74 60 269.53 -60

31 neometals.com.au

==> picture [596 x 64] intentionally omitted <==

----- Start of picture text -----

7 July 2021 – REVIEW OF NICKEL MINERAL RESOURCES AT MT EDWARDS COMPLETE
----- End of picture text -----

Hole_ID North_GDA94 EAST_GDA94 RL Depth Azimuth Dip
WID1799 6519909.75 361308.72 347.05 80 269.53 -60
WID1799Z 6519909.75 361308.71 347.05 80 269.53 -60
WID1800 6519907.94 361319.75 346.54 100 269.53 -60
WID1801 6519901.88 361329.34 346.5 112 269.53 -60
WID1803 6519762.64 361372.23 349.11 42 269.53 -60
WID1804 6519761.47 361384.18 348.31 80 269.53 -60
WID1836 6519811.03 361274.23 359.05 184.9 88.53 -56.8
WID1837 6519829.58 361285.05 354.49 144.5 86.53 -67.3
WID1838 6519832.83 361334.78 349.33 88 269.53 -60
WID1839 6519834 361343.78 348.97 100 269.53 -60
WID1840 6519932.11 361278.21 349.95 50 269.53 -60
WID1841 6519932.52 361287.68 348.91 70 269.53 -60
WID1842 6519932.93 361297.74 347.88 90 269.53 -60
WID1843 6519933.51 361309.6 347.14 106 269.53 -60
WID1844 6519934.09 361320.1 346.47 116 269.53 -60
WID2209 6519833.27 361336.2 349.27 215 257.53 -74.5
WID2211 6519913.52 361389.53 344.75 248.8 263.16 -52.05
WID2213 6519913.52 361389.62 344.75 234.3 266.53 -47
WID2215 6519781.56 361282.93 358.58 150 89.53 -44.5
WID2217 6519781.55 361281.01 358.85 175 90.53 -53.6
WID2221 6519953.63 361365.97 344 209.5 267.27 -46.61
WID2223 6519953.63 361365.97 344 228 265.5 -52.29
WID2225 6519953.63 361365.97 344 244 268.88 -57.74
WID2227 6519953.63 361365.18 344 326 264.53 -64
WID2229 6519956.24 361444.31 343.86 462 264.53 -60
WID2231 6520001.02 361377.67 342.66 469 266.55 -61.19
WID2267 6519936.31 361444.69 344 531 269.53 -64
WID2269 6519905.22 361434.48 343.37 451 263.53 -60
WID2271 6519905.21 361433.82 343.4 505 273.53 -62.9
WID2273 6519909.39 361060.31 372 540 84.53 -55.9
WID2350 6519829.78 361283.01 354.72 125 86.53 -46.9
WID2351 6519829.78 361283.01 354.72 133 86.5 -54.12
WID2351A 6519829.78 361283.01 354.72 133 89.53 -56

All coordinates are in MGA94_51S

APPENDIX 5: Drill Intersections in Mineralised Domains at Widgie 3

Drill hole Intersection Information. All composited intersections used in the Mineral Resource estimation. Composites created using the mineralisation wireframe boundaries as the cut-off. Note that not all historic holes have As assays

Hole_ID GDA94_North GDA94_East RL Ni_pct **As_ppm ** From To Width(m)
DWT121 6512101.30 365809.25 325.17 0.26 8 9 1
DWT124 6512108.52 365817.53 301.13 0.49 42 43 1
DWT124 6512108.00 365817.03 300.44 0.42 43 44 1
DWT124 6512107.48 365816.52 299.75 0.66 44 45 1
DWT125 6512106.35 365814.06 271.39 0.42 69 70 1

32

neometals.com.au

==> picture [596 x 64] intentionally omitted <==

----- Start of picture text -----

7 July 2021 – REVIEW OF NICKEL MINERAL RESOURCES AT MT EDWARDS COMPLETE
----- End of picture text -----

Hole_ID GDA94_North GDA94_East RL Ni_pct **As_ppm ** From To Width(m)
DWT125 6512105.98 365813.66 270.55 0.97 70 71 1
DWT132A 6512064.94 365842.70 318.90 0.50 23 24 1
DWT132A 6512064.41 365842.21 318.20 1.28 24 25 1
DWT132A 6512063.87 365841.73 317.51 0.47 25 26 1
DWT132A 6512063.34 365841.25 316.82 0.47 26 27 1
DWT132A 6512062.80 365840.76 316.13 0.42 27 28 1
DWT132A 6512062.26 365840.27 315.44 0.37 28 29 1
DWT132A 6512061.73 365839.79 314.75 0.54 29 30 1
DWT132A 6512061.19 365839.30 314.06 0.69 30 31 1
DWT132A 6512060.66 365838.81 313.37 2.88 31 32 1
DWT132A 6512060.13 365838.32 312.68 2.27 32 33 1
DWT133 6512054.98 365836.74 239.80 0.68 110 111 1
DWT133 6512054.58 365836.37 238.96 0.97 111 112 1
DWT133 6512054.19 365836.00 238.12 1.28 112 113 1
DWT133 6512053.79 365835.62 237.28 1.15 113 114 1
DWT133 6512053.40 365835.25 236.44 0.76 114 115 1
DWT133 6512053.00 365834.88 235.60 0.37 115 116 1
DWT133 6512052.61 365834.51 234.76 0.33 116 117 1
DWT133 6512052.22 365834.13 233.92 2.70 117 118 1
DWT133 6512051.82 365833.76 233.08 1.30 118 119 1
DWT133 6512051.43 365833.39 232.24 1.63 119 120 1
DWT136 6512015.97 365864.10 302.98 0.75 50 51 1
DWT136 6512015.46 365863.60 302.29 0.53 51 52 1
DWT136 6512014.95 365863.09 301.59 0.37 52 53 1
DWT136 6512014.44 365862.59 300.89 1.61 53 54 1
DWT136 6512013.93 365862.08 300.20 1.67 54 55 1
DWT138 6512010.24 365869.63 214.58 0.75 169 170 1
DWT138 6512009.70 365869.13 213.92 1.16 170 171 1
DWT138 6512009.15 365868.63 213.25 1.04 171 172 1
DWT138 6512008.60 365868.13 212.58 1.05 172 173 1
DWT138 6512008.04 365867.63 211.91 1.33 173 174 1
DWT138 6512007.49 365867.13 211.24 2.19 174 175 1
DWT138 6512006.94 365866.63 210.57 5.27 175 176 1
DWT138 6512006.39 365866.14 209.90 0.86 176 177 1
DWT141 6511962.78 365888.07 305.92 0.82 55 56 1
DWT141 6511962.25 365887.59 305.21 0.62 56 57 1
DWT141 6511961.73 365887.11 304.50 0.69 57 58 1
DWT141 6511961.21 365886.64 303.80 0.48 58 59 1
DWT141 6511960.69 365886.16 303.09 0.45 59 60 1
DWT141 6511960.17 365885.68 302.38 0.46 60 61 1
DWT141 6511959.65 365885.20 301.68 0.76 61 62 1
DWT141 6511959.13 365884.72 300.97 0.79 11 62 63 1
DWT141 6511958.61 365884.24 300.26 1.50 27 63 64 1
DWT141 6511958.09 365883.76 299.55 1.72 34 64 65 1

33 neometals.com.au

==> picture [596 x 64] intentionally omitted <==

----- Start of picture text -----

7 July 2021 – REVIEW OF NICKEL MINERAL RESOURCES AT MT EDWARDS COMPLETE
----- End of picture text -----

Hole_ID GDA94_North GDA94_East RL Ni_pct **As_ppm ** From To Width(m)
DWT141 6511952.89 365878.97 292.48 0.75 377 74 75 1
DWT141 6511952.37 365878.49 291.78 0.38 65 75 76 1
DWT141 6511951.86 365878.00 291.07 0.90 22 76 77 1
DWT141 6511951.34 365877.52 290.36 0.73 77 78 1
DWT141 6511950.82 365877.04 289.65 0.63 25 78 79 1
DWT141 6511950.30 365876.56 288.95 0.50 20 79 80 1
DWT141 6511949.78 365876.08 288.24 0.39 11 80 81 1
DWT141 6511949.26 365875.60 287.53 9.20 227 81 82 1
DWT141 6511948.75 365875.12 286.83 3.23 101 82 83 1
DWT142 6511962.04 365893.48 249.75 0.52 111 112 1
DWT142 6511961.61 365893.07 248.95 0.36 112 113 0.82
DWT143 6511960.78 365892.59 273.98 0.59 93 94 1
DWT143 6511960.23 365892.12 273.28 0.20 94 95 1
DWT143 6511959.69 365891.65 272.59 0.50 95 96 1
DWT143 6511959.14 365891.18 271.90 0.76 96 97 1
DWT143 6511958.59 365890.71 271.20 0.76 97 98 1
DWT143 6511958.04 365890.24 270.51 0.64 98 99 1
DWT143 6511957.49 365889.77 269.82 0.96 99 100 1
DWT143 6511956.95 365889.31 269.13 0.35 100 101 1
DWT143 6511956.40 365888.84 268.44 1.03 101 102 1
DWT143 6511955.85 365888.37 267.74 0.53 102 103 1
DWT143 6511955.30 365887.90 267.05 0.55 103 104 1
DWT143 6511954.75 365887.44 266.36 0.57 104 105 1
DWT143 6511950.88 365884.18 261.51 0.47 111 112 1
DWT143 6511950.33 365883.72 260.81 1.26 112 113 1
DWT143 6511949.78 365883.26 260.12 0.47 113 114 1
DWT143 6511949.23 365882.80 259.43 4.11 114 115 1
DWT143 6511948.67 365882.34 258.74 5.68 115 116 1
DWT145 6511922.53 365914.33 296.64 0.63 64 65 1
DWT145 6511922.10 365913.91 295.84 0.50 65 66 1
DWT145 6511921.66 365913.50 295.04 0.43 66 67 1
DWT145 6511921.23 365913.08 294.25 0.39 67 68 1
DWT145 6511920.79 365912.67 293.45 1.12 68 69 1
DWT145 6511920.35 365912.25 292.65 0.68 69 70 1
DWT145 6511919.92 365911.84 291.85 0.90 70 71 1
DWT145 6511919.48 365911.42 291.05 0.73 71 72 1
DWT145 6511919.04 365911.01 290.25 1.63 72 73 1
DWT145 6511918.61 365910.59 289.46 2.50 73 74 1
DWT146 6511921.78 365912.90 229.26 0.40 134.14 135.14 1
DWT146 6511921.38 365912.50 228.44 0.68 135.14 136.14 1
DWT146 6511920.98 365912.11 227.61 0.61 136.14 137.14 1
DWT146 6511920.58 365911.71 226.79 0.43 137.14 138.14 1
DWT146 6511920.17 365911.31 225.97 0.45 138.14 139.14 1
DWT146 6511919.77 365910.91 225.14 0.55 139.14 140.14 1

34 neometals.com.au

==> picture [596 x 64] intentionally omitted <==

----- Start of picture text -----

7 July 2021 – REVIEW OF NICKEL MINERAL RESOURCES AT MT EDWARDS COMPLETE
----- End of picture text -----

Hole_ID GDA94_North GDA94_East RL Ni_pct **As_ppm ** From To Width(m)
DWT146 6511919.36 365910.51 224.32 0.79 140.14 141.14 1
DWT146 6511918.96 365910.12 223.50 0.83 141.14 142.14 1
DWT146 6511918.55 365909.72 222.67 0.83 142.14 143.14 0.86
DWT149 6511985.21 365874.08 311.67 0.74 45 46 1
DWT149 6511984.63 365873.64 310.98 0.72 46 47 1
DWT149 6511984.04 365873.20 310.30 0.63 47 48 1
DWT149 6511983.46 365872.76 309.62 0.50 48 49 1
DWT149 6511982.87 365872.32 308.94 0.75 49 50 1
DWT149 6511982.29 365871.88 308.26 1.10 50 51 1
DWT149 6511981.70 365871.43 307.58 0.63 51 52 1
DWT149 6511981.11 365870.99 306.90 0.33 52 53 0.86
DWT149 6511968.53 365861.65 292.68 14.06 73.16 74.16 1
DWT149 6511967.94 365861.21 292.01 12.27 74.16 75.16 1
DWT149 6511967.34 365860.77 291.34 3.44 75.16 76.16 1
DWT149 6511966.74 365860.32 290.67 0.26 76.16 77.16 0.84
DWT150 6512070.22 365834.98 288.26 0.22 53 54 1
DWT150 6512069.82 365834.61 287.42 0.58 54 55 1
DWT150 6512069.42 365834.25 286.58 0.52 55 56 1
DWT150 6512069.02 365833.89 285.74 0.33 56 57 1
DWT150 6512068.61 365833.52 284.90 0.57 57 58 1
DWT150 6512068.21 365833.15 284.06 0.54 58 59 1
DWT150 6512067.81 365832.79 283.22 0.89 59 60 1
DWT150 6512067.41 365832.42 282.39 0.92 60 61 1
DWT150 6512067.01 365832.05 281.55 1.06 61 62 1
DWT150 6512066.60 365831.68 280.71 1.48 62 63 1
DWT150 6512066.20 365831.30 279.88 0.54 63 64 1
DWT150 6512065.80 365830.93 279.04 1.72 64 65 1
DWT150 6512065.39 365830.56 278.20 1.39 65 66 1
DWT150 6512064.99 365830.18 277.37 1.59 66 67 1
DWT150 6512064.58 365829.81 276.54 1.79 67 68 1
DWT150 6512064.18 365829.43 275.70 0.70 68 69 1
DWT150 6512063.78 365829.06 274.87 1.03 69 70 1
DWT150 6512063.37 365828.68 274.03 1.81 70 71 1
DWT150 6512062.97 365828.30 273.20 1.28 71 72 1
DWT150 6512062.56 365827.92 272.37 3.49 72 73 1
DWT150 6512062.16 365827.54 271.54 0.62 73 74 1
DWT150 6512059.36 365824.89 265.81 0.71 79.9 80.9 1
DWT150 6512058.95 365824.50 264.99 0.71 80.9 81.9 1
DWT150 6512058.55 365824.11 264.16 5.95 81.9 82.9 1
DWT152 6511920.66 365908.85 330.85 1.03 116 26 27 1
DWT152 6511921.14 365909.27 330.08 1.09 121 27 28 1
DWT152 6511921.62 365909.70 329.31 1.14 126 28 29 1
DWT152 6511922.10 365910.12 328.55 0.96 185 29 30 1
DWT152 6511922.58 365910.54 327.78 0.97 162 30 31 1

35 neometals.com.au

==> picture [596 x 64] intentionally omitted <==

----- Start of picture text -----

7 July 2021 – REVIEW OF NICKEL MINERAL RESOURCES AT MT EDWARDS COMPLETE
----- End of picture text -----

Hole_ID GDA94_North GDA94_East RL Ni_pct **As_ppm ** From To Width(m)
DWT152 6511923.06 365910.97 327.01 0.97 139 31 32 1
DWT153 6511946.65 365869.82 310.36 20.65 186 46.5 47.5 1
DWT153 6511947.02 365870.23 309.53 19.15 164 47.5 48.5 1
DWT153 6511947.38 365870.63 308.69 10.90 90 48.5 49.5 1
DWT153 6511947.75 365871.04 307.86 4.49 35 49.5 50.5 1
DWT153 6511948.11 365871.45 307.02 1.13 12 50.5 51.5 1
DWT153 6511948.48 365871.86 306.18 1.13 12 51.5 52.5 1
DWT153 6511948.84 365872.27 305.35 1.13 12 52.5 53.5 1
DWT154 6511938.25 365860.12 339.61 0.47 2 12.5 13.5 1
DWT154 6511938.62 365860.56 338.79 0.47 2 13.5 14.5 0.5
DWT154 6511939.89 365862.11 335.92 0.46 34 17 18 1
DWT154 6511940.26 365862.55 335.10 0.46 34 18 19 0.5
DWT154 6511941.89 365864.56 331.42 0.83 4 22.5 23.5 1
DWT154 6511942.25 365865.02 330.61 3.99 32 23.5 24.5 1
DWT154 6511942.61 365865.48 329.80 7.25 65 24.5 25.5 1
DWT154 6511942.96 365865.95 328.99 5.67 61 25.5 26.5 1
DWT154 6511943.32 365866.41 328.18 3.38 46 26.5 27.5 1
DWT154 6511943.67 365866.89 327.37 3.23 38 27.5 28.5 1
DWT154 6511944.02 365867.36 326.56 2.39 33 28.5 29.5 1
DWT154 6511944.37 365867.84 325.76 1.44 30 29.5 30.5 1
DWT154 6511944.71 365868.33 324.95 1.44 30 30.5 31.5 1
DWT155 6511940.82 365863.43 338.38 1.71 49 14 15 1
DWT155 6511941.12 365863.83 337.51 3.76 75 15 16 1
DWT155 6511941.41 365864.24 336.65 5.80 101 16 17 1
DWT155 6511941.71 365864.64 335.78 3.73 99 17 18 1
DWT155 6511942.01 365865.04 334.91 2.82 114 18 19 1
DWT155 6511942.31 365865.44 334.05 1.90 129 19 20 1
DWT155 6511942.60 365865.84 333.18 1.27 57 20 21 1
DWT155 6511942.90 365866.25 332.32 1.44 45 21 22 1
DWT155 6511943.20 365866.65 331.45 1.61 32 22 23 1
DWT155 6511943.50 365867.05 330.58 2.00 29 23 24 1
DWT155 6511943.79 365867.45 329.72 1.87 27 24 25 1
DWT155 6511944.09 365867.85 328.85 1.74 24 25 26 1
DWT155 6511944.39 365868.26 327.99 1.52 28 26 27 1
DWT155 6511944.68 365868.66 327.12 1.41 25 27 28 1
DWT155 6511944.98 365869.06 326.25 1.29 21 28 29 1
DWT155 6511945.28 365869.46 325.39 0.87 19 29 30 1
DWT155 6511945.58 365869.87 324.52 0.87 19 30 31 0.5
DWT156 6512010.91 365858.51 321.84 2.00 386 27.5 28.5 1
DWT156 6512011.26 365858.90 320.99 3.02 107 28.5 29.5 1
DWT156 6512011.61 365859.30 320.14 2.86 160 29.5 30.5 1
DWT156 6512011.96 365859.69 319.30 1.00 128 30.5 31.5 1
DWT156 6512012.32 365860.09 318.45 0.52 285 31.5 32.5 1
DWT156 6512012.67 365860.49 317.60 0.58 239 32.5 33.5 1

36 neometals.com.au

==> picture [596 x 64] intentionally omitted <==

----- Start of picture text -----

7 July 2021 – REVIEW OF NICKEL MINERAL RESOURCES AT MT EDWARDS COMPLETE
----- End of picture text -----

Hole_ID GDA94_North GDA94_East RL Ni_pct **As_ppm ** From To Width(m)
DWT156 6512013.01 365860.89 316.75 0.63 192 33.5 34.5 1
DWT156 6512013.36 365861.29 315.90 0.55 190 34.5 35.5 1
DWT156 6512013.71 365861.69 315.06 0.59 178 35.5 36.5 1
DWT156 6512014.05 365862.09 314.21 0.63 166 36.5 37.5 1
DWT157 6512010.56 365858.55 332.63 3.21 68 14.5 15.5 1
DWT157 6512010.87 365858.92 331.76 3.12 56 15.5 16.5 1
DWT157 6512011.19 365859.29 330.88 3.02 43 16.5 17.5 1
DWT157 6512011.50 365859.66 330.01 2.12 80 17.5 18.5 1
DWT157 6512011.82 365860.03 329.13 1.74 63 18.5 19.5 1
DWT157 6512012.13 365860.40 328.26 1.35 46 19.5 20.5 1
DWT157 6512012.44 365860.77 327.38 0.84 49 20.5 21.5 1
DWT157 6512012.76 365861.13 326.51 0.75 45 21.5 22.5 1
DWT157 6512013.07 365861.50 325.63 0.65 41 22.5 23.5 1
DWT157 6512013.38 365861.86 324.75 0.43 19 23.5 24.5 1
DWT157 6512013.69 365862.23 323.87 0.43 19 24.5 25.5 0.5
DWT158 6512061.75 365839.49 310.33 0.39 126 28.5 29.5 1
DWT158 6512062.01 365839.80 309.42 2.44 2800 29.5 30.5 1
DWT158 6512062.27 365840.11 308.50 1.10 1400 30.5 31.5 1
DWT158 6512062.52 365840.42 307.59 0.71 268 31.5 32.5 1
DWT158 6512062.78 365840.73 306.67 0.63 145 32.5 33.5 1
DWT159 6512061.00 365838.34 321.66 0.95 280 17 18 1
DWT159 6512061.33 365838.72 320.79 1.29 1790 18 19 1
DWT159 6512061.66 365839.09 319.92 1.62 3300 19 20 1
DWT159 6512062.00 365839.46 319.06 1.93 11000 20 21 1
DWT159 6512062.33 365839.83 318.19 1.94 5700 21 22 1
DWT159 6512062.66 365840.21 317.33 1.86 3200 22 23 1
DWT159 6512062.99 365840.58 316.46 0.86 1300 23 24 1
DWT159 6512063.32 365840.96 315.59 0.75 1450 24 25 1
DWT159 6512063.65 365841.33 314.73 0.64 1600 25 26 1
DWT356 6512000.51 365877.96 242.66 0.51 115 116 1
DWT356 6512000.07 365877.51 241.88 0.66 116 117 1
DWT356 6511999.63 365877.05 241.11 0.98 117 118 1
DWT356 6511999.19 365876.60 240.33 1.01 118 119 1
DWT356 6511998.75 365876.15 239.56 3.16 119 120 0.8
HH570 6511973.68 365842.85 336.99 0.12 12.04 13.04 1
HH570 6511973.24 365842.38 336.22 0.06 13.04 14.04 1
HH570 6511972.80 365841.92 335.45 0.02 14.04 15.04 0.74
WDC236 6512049.38 365837.20 228.31 1.62 28 127 128 1
WDC236 6512049.06 365836.63 227.55 2.18 33 128 129 1
WDC236 6512048.75 365836.06 226.79 2.05 35 129 130 1
WDC236 6512048.43 365835.48 226.04 2.36 48 130 131 1
WDC236 6512048.11 365834.91 225.28 1.54 29 131 132 1
WDC236 6512047.80 365834.33 224.53 1.36 27 132 133 1
WDC236 6512047.49 365833.75 223.77 1.11 20 133 134 1

37 neometals.com.au

==> picture [596 x 64] intentionally omitted <==

----- Start of picture text -----

7 July 2021 – REVIEW OF NICKEL MINERAL RESOURCES AT MT EDWARDS COMPLETE
----- End of picture text -----

Hole_ID GDA94_North GDA94_East RL Ni_pct **As_ppm ** From To Width(m)
WDC236 6512047.17 365833.18 223.02 0.66 24 134 135 1
WDC236 6512046.86 365832.59 222.27 0.80 100 135 136 1
WDC236 6512046.55 365832.01 221.52 1.51 448 136 137 1
WDC237 6512107.22 365831.18 236.19 0.54 81 124 125 1
WDC237 6512106.77 365830.69 235.44 0.54 81 125 126 1
WDC237 6512106.33 365830.19 234.70 0.54 81 126 127 1
WDC237 6512105.88 365829.70 233.95 0.54 81 127 128 1
WDC237 6512105.43 365829.20 233.21 1.26 41 128 129 1
WDC237 6512104.98 365828.71 232.46 1.26 41 129 130 1
WDC237 6512104.53 365828.21 231.72 1.26 41 130 131 1
WDC237 6512104.08 365827.72 230.98 1.26 41 131 132 1
WDC237 6512091.74 365814.28 211.07 0.42 124 158 159 1
WDC237 6512091.28 365813.79 210.34 0.38 9 159 160 1
WDC237 6512090.81 365813.29 209.60 0.66 13 160 161 1
WDC237 6512090.34 365812.79 208.87 0.58 14 161 162 1
WDC237 6512089.88 365812.30 208.14 1.49 266 162 163 1
WDC237 6512089.41 365811.80 207.40 1.07 720 163 164 1
WDD080 6511944.81 365891.83 84.38 0.55 17 289 290 1
WDD080 6511944.44 365891.48 83.52 0.73 10 290 291 1
WDD080 6511944.06 365891.13 82.66 0.32 13 291 292 1
WDD080 6511943.69 365890.78 81.80 0.36 6 292 293 1
WDD080 6511943.31 365890.42 80.95 0.27 68 293 294 1
WDD080 6511942.94 365890.07 80.09 0.79 142 294 295 1
WDD080 6511942.56 365889.72 79.23 0.65 163 295 296 1
WDD080 6511942.18 365889.36 78.38 0.41 108 296 297 0.77
WDD081 6511983.16 365867.53 72.17 0.32 66 298.2 299.2 1
WDD081 6511982.79 365867.20 71.30 0.50 162 299.2 300.2 1
WDD081 6511982.42 365866.88 70.43 0.43 262 300.2 301.2 1
WDD081 6511982.05 365866.55 69.56 0.32 14 301.2 302.2 1
WDD081 6511981.22 365865.82 67.63 0.44 58 303.42 304.42 1
WDD081 6511980.85 365865.50 66.76 0.68 57 304.42 305.42 0.63
WDD082 6512056.00 365819.41 45.35 0.65 272 310 311 1
WDD082 6512055.74 365819.12 44.43 1.28 91 311 312 0.89
WPH55 6511982.18 365869.37 332.05 0.63 15 25.91 26.91 1
WPH55 6511981.67 365868.88 331.34 0.52 12 26.91 27.91 1
WPH55 6511981.17 365868.38 330.64 0.52 12 27.91 28.91 1
WPH55 6511980.66 365867.88 329.93 0.71 18 28.91 29.91 1
WPH55 6511980.16 365867.39 329.22 0.60 15 29.91 30.91 1
WPH55 6511979.65 365866.89 328.52 0.58 17 30.91 31.91 1
WPH55 6511979.15 365866.40 327.81 0.59 17 31.91 32.91 1
WPH55 6511978.65 365865.90 327.10 0.71 13 32.91 33.91 1
WPH55 6511978.14 365865.40 326.39 0.68 7 33.91 34.91 1
WPH55 6511977.64 365864.91 325.69 0.68 4 34.91 35.91 1
WPH55 6511977.13 365864.41 324.98 0.67 2 35.91 36.91 1

38 neometals.com.au

==> picture [596 x 64] intentionally omitted <==

----- Start of picture text -----

7 July 2021 – REVIEW OF NICKEL MINERAL RESOURCES AT MT EDWARDS COMPLETE
----- End of picture text -----

Hole_ID GDA94_North GDA94_East RL Ni_pct **As_ppm ** From To Width(m)
WPH55 6511976.63 365863.92 324.27 0.15 5 36.91 37.91 1
WPH56 6511972.80 365870.96 334.65 0.57 8 25.3 26.3 1
WPH56 6511972.30 365870.46 333.94 0.58 8 26.3 27.3 1
WPH56 6511971.79 365869.96 333.23 0.49 8 27.3 28.3 1
WPH56 6511971.29 365869.47 332.52 0.43 28.3 29.3 1
WPH56 6511970.79 365868.97 331.82 0.59 29.3 30.3 1
WPH56 6511970.28 365868.48 331.11 0.47 30.3 31.3 1
WPH56 6511969.78 365867.98 330.40 0.65 31.3 32.3 1
WPH56 6511969.27 365867.48 329.70 0.46 32.3 33.3 1
WPH56 6511968.77 365866.99 328.99 0.58 33.3 34.3 1
WPH56 6511968.27 365866.49 328.28 0.64 34.3 35.3 1
WPH56 6511967.76 365866.00 327.58 0.71 35.3 36.3 1
WPH56 6511967.26 365865.50 326.87 0.74 36.3 37.3 1
WPH56 6511966.75 365865.00 326.16 0.60 37.3 38.3 1
WPH56 6511966.25 365864.51 325.45 0.87 38.3 39.3 1
WPH56 6511965.75 365864.01 324.75 0.73 39.3 40.3 1
WPH56 6511965.24 365863.52 324.04 0.35 40.3 41.3 1
WPH57 6511965.56 365874.56 336.08 0.50 24.84 25.84 1
WPH57 6511965.06 365874.07 335.38 0.64 25.84 26.84 1
WPH57 6511964.56 365873.57 334.67 0.65 26.84 27.84 1
WPH57 6511964.05 365873.08 333.96 0.86 27.84 28.84 1
WPH57 6511963.55 365872.58 333.25 0.74 28.84 29.84 1
WPH60 6511840.74 365966.34 331.29 0.73 18 34.44 35.44 1
WPH60 6511840.24 365965.85 330.59 0.77 8 35.44 36.44 1
WPH60 6511839.74 365965.35 329.88 0.72 18 36.44 37.44 1
WPH60 6511839.23 365964.85 329.17 1.10 45 37.44 38.44 1
WPH65 6511846.89 365924.10 318.61 0.48 38.86 39.86 1
WPH65 6511846.88 365923.60 317.74 0.61 39.86 40.86 1
WPS1 6512089.99 365823.26 286.36 0.23 51.82 52.82 1
WPS1 6512089.63 365822.91 285.50 0.23 52.82 53.82 1
WPS1 6512089.28 365822.56 284.63 0.19 53.82 54.82 1
WPS2 6512071.32 365832.46 287.48 0.25 53.34 54.34 1
WPS2 6512070.96 365832.11 286.61 0.29 54.34 55.34 1
WPS2 6512070.60 365831.76 285.75 0.58 55.34 56.34 1
WPS2 6512070.25 365831.41 284.88 0.63 56.34 57.34 1
WPS2 6512069.89 365831.06 284.01 0.46 57.34 58.34 1
WPS2 6512069.53 365830.71 283.15 0.44 58.34 59.34 1
WPS2 6512069.18 365830.36 282.28 0.41 59.34 60.34 1
WPS2 6512068.82 365830.00 281.42 0.50 60.34 61.34 1
WPS2 6512068.47 365829.65 280.55 0.82 61.34 62.34 1
WPS2 6512068.11 365829.30 279.68 1.21 62.34 63.34 1
WPS2 6512067.75 365828.95 278.82 1.41 63.34 64.34 1
WPS2 6512067.40 365828.60 277.95 0.81 64.34 65.34 1
WPS2 6512067.04 365828.25 277.09 0.67 65.34 66.34 1

39 neometals.com.au

==> picture [596 x 64] intentionally omitted <==

----- Start of picture text -----

7 July 2021 – REVIEW OF NICKEL MINERAL RESOURCES AT MT EDWARDS COMPLETE
----- End of picture text -----

Hole_ID GDA94_North GDA94_East RL Ni_pct **As_ppm ** From To Width(m)
WPS2 6512066.68 365827.90 276.22 0.76 30 66.34 67.34 1
WPS2 6512066.33 365827.55 275.35 1.37 30 67.34 68.34 1
WPS2 6512065.97 365827.20 274.49 1.19 19 68.34 69.34 1
WPS2 6512065.61 365826.85 273.62 1.10 17 69.34 70.34 1
WPS2 6512065.26 365826.50 272.76 1.30 25 70.34 71.34 1
WPS2 6512064.90 365826.15 271.89 2.03 11 71.34 72.34 1
WPS2 6512064.54 365825.80 271.02 1.58 16 72.34 73.34 1
WPS2 6512064.19 365825.45 270.16 2.45 14 73.34 74.34 1
WPS2 6512063.83 365825.09 269.29 2.96 22 74.34 75.34 1
WPS2 6512063.47 365824.74 268.43 1.13 11 75.34 76.34 1
WPS2 6512063.12 365824.39 267.56 0.77 76.34 77.34 1
WPS2 6512060.45 365821.77 261.08 6.23 83.82 84.82 1
WPS2 6512060.09 365821.42 260.22 6.76 84.82 85.82 1
WPS2 6512059.74 365821.07 259.35 2.89 1200 85.82 86.82 1
WPS2 6512059.38 365820.72 258.48 0.61 86.82 87.82 0.81
WWD1 6511964.22 365883.44 304.86 0.50 56.69 57.69 1
WWD1 6511963.71 365882.94 304.16 0.49 57.69 58.69 1
WWD1 6511963.21 365882.45 303.45 0.04 58.69 59.69 1
WWD1 6511962.71 365881.95 302.74 0.21 59.69 60.69 1
WWD1 6511962.20 365881.45 302.04 0.25 60.69 61.69 1
WWD1 6511961.70 365880.96 301.33 0.13 61.69 62.69 1
WWD1 6511961.19 365880.46 300.62 0.65 62.69 63.69 1
WWD1 6511960.69 365879.97 299.91 0.69 63.69 64.69 1
WWD1 6511960.18 365879.47 299.21 0.31 64.69 65.69 0.99
WWD1 6511957.92 365877.24 296.03 0.56 69.19 70.19 1
WWD1 6511957.41 365876.74 295.32 0.63 70.19 71.19 1
WWD1 6511956.91 365876.25 294.61 0.66 71.19 72.19 1
WWD1 6511956.40 365875.75 293.90 0.52 72.19 73.19 1
WWD1 6511955.90 365875.25 293.20 0.37 73.19 74.19 1
WWD1 6511955.40 365874.76 292.49 0.64 74.19 75.19 1
WWD1 6511954.89 365874.26 291.78 0.79 75.19 76.19 1
WWD1 6511954.39 365873.77 291.08 0.95 76.19 77.19 1
WWD1 6511953.88 365873.27 290.37 0.41 77.19 78.19 1
WWD1 6511953.38 365872.77 289.66 0.56 78.19 79.19 1
WWD1 6511949.92 365869.38 284.82 0.47 85.04 86.04 1
WWD1 6511949.42 365868.88 284.11 8.98 86.04 87.04 1
WWD11 6511886.41 365944.82 255.74 0.14 121.92 122.92 1
WWD11 6511885.87 365944.33 255.06 0.16 122.92 123.92 1
WWD11 6511885.33 365943.84 254.38 0.17 123.92 124.92 1
WWD11 6511865.80 365926.07 229.33 0.05 160.32 161.32 1
WWD11 6511865.27 365925.56 228.64 0.05 161.32 162.32 1
WWD11 6511864.74 365925.06 227.95 0.05 162.32 163.32 1
WWD12 6512059.18 365847.89 192.07 0.85 201.5 202.5 1
WWD12 6512058.63 365847.34 191.44 0.64 202.5 203.5 1

40 neometals.com.au

==> picture [596 x 64] intentionally omitted <==

----- Start of picture text -----

7 July 2021 – REVIEW OF NICKEL MINERAL RESOURCES AT MT EDWARDS COMPLETE
----- End of picture text -----

Hole_ID GDA94_North GDA94_East RL Ni_pct **As_ppm ** From To Width(m)
WWD12 6512058.08 365846.80 190.81 0.86 203.5 204.5 1
WWD12 6512057.52 365846.26 190.18 1.09 600 204.5 205.5 1
WWD12 6512056.97 365845.71 189.55 1.15 600 205.5 206.5 1
WWD12 6512056.42 365845.17 188.92 1.33 206.5 207.5 1
WWD12 6512055.86 365844.62 188.29 1.34 207.5 208.5 1
WWD12 6512055.31 365844.08 187.66 1.35 208.5 209.5 1
WWD12 6512054.76 365843.54 187.03 1.35 209.5 210.5 1
WWD12 6512054.20 365842.99 186.40 1.24 210.5 211.5 1
WWD12 6512053.65 365842.45 185.77 0.96 211.5 212.5 1
WWD12 6512053.10 365841.90 185.14 1.37 212.5 213.5 1
WWD12 6512052.54 365841.36 184.51 1.05 213.5 214.5 1
WWD12 6512051.99 365840.81 183.88 0.67 214.5 215.5 1
WWD12 6512051.43 365840.27 183.25 0.72 215.5 216.5 1
WWD12 6512050.88 365839.72 182.62 1.18 80 216.5 217.5 1
WWD12 6512050.32 365839.17 181.99 4.34 65 217.5 218.5 1
WWD12 6512049.77 365838.63 181.36 0.61 218.5 219.5 0.56
WWD13 6512142.12 365798.41 199.50 0.13 207.57 208.57 1
WWD13 6512141.43 365797.94 198.96 0.12 208.57 209.57 1
WWD13 6512140.73 365797.47 198.41 0.11 209.57 210.57 1
WWD13 6512140.04 365797.00 197.87 0.17 210.57 211.57 1
WWD13 6512139.35 365796.53 197.32 0.17 211.57 212.57 0.81
WWD13 6512134.54 365793.24 193.54 0.07 218.51 219.51 1
WWD15 6512018.39 365869.04 273.78 0.84 19 86.56 87.56 1
WWD15 6512017.86 365868.56 273.08 0.88 21 87.56 88.56 1
WWD15 6512017.33 365868.09 272.38 0.93 25 88.56 89.56 1
WWD15 6512016.79 365867.62 271.67 0.80 187 89.56 90.56 1
WWD15 6512016.26 365867.15 270.97 0.69 483 90.56 91.56 1
WWD15 6512015.73 365866.68 270.27 3.80 257 91.56 92.56 1
WWD16 6511947.74 365888.26 328.11 0.78 15 33.38 34.38 1
WWD16 6511947.26 365887.79 327.38 1.40 15 34.38 35.38 1
WWD16 6511946.77 365887.31 326.65 0.59 15 35.38 36.38 1
WWD16 6511946.28 365886.83 325.92 0.61 15 36.38 37.38 1
WWD16 6511945.80 365886.35 325.18 0.65 15 37.38 38.38 1
WWD16 6511945.31 365885.87 324.45 0.51 2 38.38 39.38 1
WWD16 6511944.83 365885.40 323.72 0.61 5 39.38 40.38 1
WWD16 6511944.34 365884.92 322.99 0.67 20 40.38 41.38 1
WWD16 6511943.86 365884.44 322.26 0.66 20 41.38 42.38 1
WWD16 6511943.37 365883.96 321.52 1.07 20 42.38 43.38 1
WWD16 6511942.88 365883.48 320.79 1.25 20 43.38 44.38 1
WWD16 6511942.39 365883.00 320.07 0.58 10 44.38 45.38 1
WWD16 6511941.91 365882.52 319.34 0.49 20 45.38 46.38 1
WWD16 6511941.42 365882.04 318.61 0.50 18 46.38 47.38 1
WWD16 6511940.93 365881.56 317.88 0.57 15 47.38 48.38 1
WWD16 6511940.44 365881.08 317.15 0.90 15 48.38 49.38 1

41 neometals.com.au

==> picture [596 x 64] intentionally omitted <==

----- Start of picture text -----

7 July 2021 – REVIEW OF NICKEL MINERAL RESOURCES AT MT EDWARDS COMPLETE
----- End of picture text -----

Hole_ID GDA94_North GDA94_East RL Ni_pct **As_ppm ** From To Width(m)
WWD16 6511939.95 365880.60 316.43 0.82 19 49.38 50.38 1
WWD16 6511939.46 365880.11 315.70 0.69 21 50.38 51.38 1
WWD16 6511938.97 365879.63 314.98 0.62 25 51.38 52.38 1
WWD16 6511938.47 365879.15 314.25 0.77 31 52.38 53.38 1
WWD16 6511937.98 365878.66 313.53 0.88 35 53.38 54.38 1
WWD16 6511937.49 365878.18 312.81 0.72 20 54.38 55.38 1
WWD16 6511937.00 365877.69 312.08 1.05 5 55.38 56.38 1
WWD16 6511936.50 365877.21 311.36 2.09 14 56.38 57.38 1
WWD16 6511936.01 365876.72 310.64 7.16 27 57.38 58.38 1
WWD17 6512054.03 365824.11 51.18 0.26 50 326.65 327.65 1
WWD17 6512053.68 365823.69 50.34 3.99 2804 327.65 328.65 1
WWD17 6512053.32 365823.27 49.51 0.58 100 328.65 329.65 1
WWD17 6512052.96 365822.85 48.67 0.58 100 329.65 330.65 0.78
WWD19 6512128.31 365795.26 34.79 0.49 1 337.87 338.87 1
WWD19 6512127.91 365794.86 33.96 0.66 2341 338.87 339.87 1
WWD19 6512127.51 365794.47 33.14 1.15 9000 339.87 340.87 1
WWD19 6512127.11 365794.07 32.31 1.08 6240 340.87 341.87 1
WWD19 6512126.70 365793.67 31.49 1.52 3360 341.87 342.87 1
WWD19 6512126.30 365793.28 30.66 1.87 847 342.87 343.87 1
WWD19 6512125.90 365792.88 29.84 4.60 51 343.87 344.87 1
WWD2 6511971.63 365891.32 184.93 0.60 193.24 194.24 1
WWD2 6511971.16 365890.85 184.18 1.58 194.24 195.24 1
WWD2 6511970.68 365890.38 183.44 2.62 195.24 196.24 1
WWD2 6511970.21 365889.92 182.69 1.19 196.24 197.24 1
WWD2 6511969.73 365889.45 181.95 0.73 197.24 198.24 1
WWD2 6511969.25 365888.98 181.20 0.66 198.24 199.24 1
WWD2 6511968.78 365888.51 180.46 0.68 199.24 200.24 0.74
WWD24 6512035.63 365858.70 186.69 0.59 588 204 205 1
WWD24 6512035.10 365858.14 186.06 0.87 1680 205 206 1
WWD24 6512034.57 365857.57 185.43 1.57 1080 206 207 1
WWD24 6512034.05 365857.00 184.80 1.61 573 207 208 1
WWD24 6512033.52 365856.43 184.17 1.33 58 208 209 1
WWD24 6512032.98 365855.86 183.54 2.83 128 209 210 1
WWD24 6512032.45 365855.29 182.92 1.97 115 210 211 1
WWD24 6512031.92 365854.73 182.29 1.52 153 211 212 1
WWD24 6512031.38 365854.16 181.67 1.07 895 212 213 1
WWD24 6512030.84 365853.59 181.04 2.38 2696 213 214 1
WWD24 6512030.31 365853.02 180.42 1.12 2900 214 215 0.6
WWD25 6511923.79 365906.79 265.08 0.21 29 106 107 1
WWD25 6511923.37 365906.26 264.34 0.17 4 107 108 1
WWD26 6511902.99 365919.77 109.59 0.62 1755 258 259 1
WWD26 6511902.58 365919.37 108.76 0.34 370 259 260 1
WWD26 6511902.18 365918.98 107.93 0.47 210 260 261 1
WWD26 6511901.78 365918.59 107.11 1.94 6390 261 262 1

42 neometals.com.au

==> picture [596 x 64] intentionally omitted <==

----- Start of picture text -----

7 July 2021 – REVIEW OF NICKEL MINERAL RESOURCES AT MT EDWARDS COMPLETE
----- End of picture text -----

Hole_ID GDA94_North GDA94_East RL Ni_pct **As_ppm ** From To Width(m)
WWD26 6511901.38 365918.19 106.28 1.41 7900 262 263 1
WWD26 6511900.98 365917.79 105.46 4.05 10850 263 264 1
WWD26 6511900.58 365917.40 104.63 3.02 588 264 265 1
WWD26 6511900.17 365917.00 103.81 1.65 7100 265 266 1
WWD26 6511899.77 365916.60 102.98 1.42 815 266 267 1
WWD26 6511899.36 365916.21 102.16 1.94 375 267 268 1
WWD26 6511898.96 365915.81 101.34 0.71 6025 268 269 1
WWD27 6511886.10 365905.73 294.16 0.19 8 87 88 1
WWD27 6511885.54 365905.17 293.55 0.57 6 88 89 1
WWD3 6511859.40 365928.16 109.79 0.45 272.86 273.86 1
WWD3 6511858.90 365927.81 109.00 0.99 273.86 274.86 0.86
WWD4 6512057.49 365846.76 276.34 1.50 79.86 80.86 1
WWD4 6512056.95 365846.26 275.67 0.24 80.86 81.86 1
WWD4 6512056.40 365845.76 274.99 0.26 81.86 82.86 1
WWD4 6512055.86 365845.26 274.32 0.83 82.86 83.86 1
WWD4 6512055.31 365844.75 273.65 0.48 83.86 84.86 1
WWD4 6512054.77 365844.25 272.98 0.33 84.86 85.86 1
WWD4 6512054.22 365843.74 272.31 0.95 85.86 86.86 1
WWD4 6512048.86 365838.73 265.74 1.31 1000 95.71 96.71 1
WWD4 6512048.32 365838.22 265.08 0.90 30 96.71 97.71 1
WWD4 6512047.78 365837.70 264.41 1.15 30 97.71 98.71 1
WWD4 6512047.23 365837.19 263.75 2.72 619 98.71 99.71 1
WWD5 6512141.08 365786.44 277.05 0.27 76.69 77.69 1
WWD5 6512140.53 365785.98 276.35 0.23 77.69 78.69 1

Appendix 6: Drill Intersections in Mineralised Domains from Cooke

Drill hole Intersection Information. All composited intersections used in the Mineral Resource estimation. Composites created using the mineralisation wireframe boundaries as the cut-off. Note that not all historic holes have As, Co, Fe, MgO assays

Hole Id From To Length Ni% Asppm Cuppm Coppm Fe% MgO%
WD5336 55.78 57.3 1.52 0.50 380
WD5336 111.4 116.43 5.03 1.77 1690
WD5339 267.92 269.44 1.52 0.50 470
WD5340 139.9 148.93 9.03 1.01 994
WD5340 149.08 152.4 3.32 2.04 1015
WD5340 172.21 173.74 1.53 0.74 560
WD5348 131.98 133.5 1.52 0.57 250
WD5348 150.27 151.79 1.52 0.66 480
WD5350 192.94 197.51 4.57 0.60 514
WD5350 207.17 208.48 1.31 2.07 2660
WD5408 7.62 19.81 12.19 1.05 406
WD5408 21.34 22.86 1.52 0.61 290
WD5409 3.05 12.19 9.14 1.09 6265
WD5419 0 10.67 10.67 1.10 1213
WD5419 33.53 35.05 1.52 0.55 500
WD5420 10.67 18.29 7.62 1.68 1935
WD5420 41.15 51.82 10.67 1.50 1891

43 neometals.com.au

==> picture [596 x 64] intentionally omitted <==

----- Start of picture text -----

7 July 2021 – REVIEW OF NICKEL MINERAL RESOURCES AT MT EDWARDS COMPLETE
----- End of picture text -----

Hole Id From To Length Ni% Asppm Cuppm Coppm Fe% MgO%
WD5421 12.19 13.72 1.53 0.50 240
WD5421 19.81 28.96 9.15 1.00 1063
WD5423 7.62 21.34 13.72 1.15 2015
WD5423 27.43 30.48 3.05 0.73 1551
WD5423 35.05 50.29 15.24 0.99 1417
WD5424 0 1.52 1.52 0.54 540
WD5424 3.05 6.1 3.05 0.69 625
WD5428 10.67 18.29 7.62 1.43 1712
WD5429 13.72 15.24 1.52 0.86 990
WD5429 30.48 39.62 9.14 1.63 1694
WD5429 42.67 44.2 1.53 0.54 520
WD5430 4.57 7.62 3.05 1.16 1172
WD5802 266.09 268.83 2.74 0.57 275
WD5802 313.82 314.95 1.13 0.66 560
WD5802 329.18 330.71 1.53 0.52 240
WD5802 331.9 333.54 1.64 0.71 246
WD6059 77.72 82.3 4.58 0.62 517
WD6059 85.34 88.39 3.05 0.76 510
WD6257 30.48 41.15 10.67 0.98 1429
WD6257 53.34 56.39 3.05 0.95 795
WD6258 94.49 97.54 3.05 0.72 640
WD6544 74.68 79.25 4.57 1.12 1320
WDC145 13 14 1 0.53 51 372 142 5.31 30.35
WDC145 15 21 6 0.77 214 894 297 9.87 23.46
WDC145 22 24 2 0.71 454 1270 321 10.50 30.02
WDC146 13 14 1 0.56 1360 2040 417 17.40 14.05
WDC146 54 55 1 0.50 6 395 184 8.34 19.24
WDC146 77 79 2 0.59 11 1023 236 16.55 5.73
WDC147 36 54 18 1.71 37 1850 456 13.02 19.60
WDC147 64 78 14 1.60 83 2353 474 14.35 21.67
WDC147 79 80 1 0.55 21 876 198 8.64 22.22
WDC147 81 82 1 0.69 286 752 246 10.20 21.23
WDC148 5 6 1 0.58 100 1575 200 14.95 17.66
WDC148 19 38 19 2.49 70 4243 712 19.57 15.21
WDC148 43 44 1 0.59 13 768 225 8.00 23.71
WDC148 53 69 16 1.42 21 1871 419 13.79 23.92
WDC148 72 73 1 1.16 8 1455 338 12.55 21.89
WDC148 74 75 1 1.09 11 1165 315 12.40 22.39
WDC149 18 19 1 0.68 1300 3950 242 13.50 7.26
WDC149 22 24 2 1.05 212 1002 447 11.23 12.83
WDC150 1 15 14 1.40 92 2556 479 16.47 11.95
WDC150 16 28 12 1.09 179 1563 376 10.66 16.22
WDC150 51 53 2 0.61 7 932 214 9.95 23.46
WDC150 54 56 2 2.78 73 3875 857 17.70 11.85
WDC159 0 16 16 3.23 55 5304 835 16.54 12.84
WDGT02 78 83 5 2.13 38 3321 636 16.33 22.65
WDMT01 37.6 44 6.4 2.43 27 2753 707 15.62 21.34
WDMT01 47.7 53 5.3 2.01 156 3558 600 15.86 23.88
WDMT01 70 87 17 1.57 42 1888 506 13.20 25.35

44

neometals.com.au

==> picture [596 x 64] intentionally omitted <==

----- Start of picture text -----

7 July 2021 – REVIEW OF NICKEL MINERAL RESOURCES AT MT EDWARDS COMPLETE
----- End of picture text -----

Hole Id From To Length Ni% Asppm Cuppm Coppm Fe% MgO%
WDMT02 8 11 3 4.20 82 5180 824 22.03 6.68
WDMT02 12 22 10 1.54 79 4686 447 19.07 14.13
WDMT02 23 26 3 0.99 114 23 202 7.13 17.74
WDMT02 31 33 2 0.63 111 1458 170 13.90 10.27
WDMT02 39 46 7 1.29 10 1571 419 11.63 27.44
WDMT03 31 47 16 1.99 29 2606 568 14.18 21.11
WDMT03 70 77 7 1.94 13 1614 612 15.49 26.03
WID1237 104 114 10 1.19 1398 320
WID1237 118 120 2 0.64 770 220
WID1423 137 138 1 1.23 100 2031 368
WID1423 142.3 146.2 3.9 2.25 100 2090 451
WID1423 155.5 156.5 1 0.72 100 1675 295
WID1423 179.9 180.9 1 0.51 100 220 160
WID1423 199.5 204 4.5 1.80 100 2017 574
WID1645 8 30 22 1.58 100 3259 379
WID1648 27 40.5 13.5 1.53 43 1200 458
WID1648 42 43.5 1.5 0.50 0 380 170
WID1649 0 6 6 0.64 100 573 217
WID1649 8 28 20 0.65 100 802 220
WID1649 42 60 18 1.47 100 2470 423
WID1649 68 70 2 0.58 100 730 200
WID1650 32 52 20 2.08 190 2735 518
WID1650 66 86 20 1.21 100 1368 363
WID1651 24 28 4 1.18 100 1365 405
WID1652 42 50 8 2.36 125 2675 695
WID1653 16 18 2 0.74 100 1450 370
WID1653 22 24 2 0.55 100 760 240
WID1654 10 18 8 0.96 100 1408 328
WID1655 2 10 8 0.59 100 585 208
WID1655 22 32 10 1.51 100 1828 496
WID1655 34 36 2 0.97 100 1310 380
WID1656 10 16 6 0.57 100 620 227
WID1656 34 38 4 1.21 150 2135 430
WID1656 42 46 4 1.10 200 1120 210
WID1656 54 56 2 0.52 200 350 160
WID1657 2 6 4 0.75 100 1120 290
WID1658 14 18 4 0.84 250 1490 445
WID1658 26 28 2 0.53 100 580 230
WID1659 20 22 2 0.54 200 800 240
WID1659 26 46 20 0.87 490 1217 325
WID1659 56 62 6 0.71 133 953 243
WID1675 69.3 72.3 3 0.58 100 675 217
WID1675 86.8 97 10.2 1.17 3385 1282 297
WID1675 99.5 100.5 1 0.52 100 1160 190
WID1779 77.35 78.45 1.1 0.51 470 190
WID1779 84.7 85.8 1.1 0.54 650 210
WID1779 109.1 110.15 1.05 2.98 2870 860
WID1781 0 19 19 2.38 105 3781 696
WID1781 39 45 6 1.04 100 1278 328

45 neometals.com.au

==> picture [596 x 64] intentionally omitted <==

----- Start of picture text -----

7 July 2021 – REVIEW OF NICKEL MINERAL RESOURCES AT MT EDWARDS COMPLETE
----- End of picture text -----

Hole Id From To Length Ni% Asppm Cuppm Coppm Fe% MgO%
WID1781 46 47 1 0.84 100 730 230
WID1781 50 52 2 0.71 100 1150 230
WID1781 53 54 1 0.55 3700 520 180
WID1791 52 58 6 1.85 1430 553
WID1791 68 70 2 0.79 1110 260
WID1793 58 70 12 1.38 4350 1007 290
WID1793 74 78 4 0.98 1320 285
WID1794 20 22 2 0.57 610 200
WID1794 34 54 20 0.83 80 1084 267
WID1794 58 60 2 0.53 670 210
WID1794 62 64 2 0.51 390 170
WID1794 68 78 10 0.71 702 226
WID1795 22 34 12 0.95 5595 313
WID1795 64 70 6 0.54 660 203
WID1795 76 78 2 0.57 500 190
WID1795 82 92 10 1.99 2430 472
WID1795 104 106 2 0.56 720 190
WID1796 58 62 4 0.73 725 240
WID1796 92 96 4 0.68 1450 310
WID1796 134 144 10 1.16 60 1774 322
WID1797 18 22 4 0.72 1155 320
WID1798 30 32 2 0.53 710 210
WID1798 36 38 2 1.05 1340 400
WID1800 58 60 2 0.54 350 190
WID1800 62 64 2 1.18 790 420
WID1801 68 70 2 0.59 780 200
WID1801 74 84 10 0.86 1072 284
WID1801 94 96 2 0.66 740 220
WID1836 86.85 91 4.15 2.23
WID1837 71.35 87.55 16.2 2.07 121 3393 455
WID1838 28 34 6 1.14 42 2063 370
WID1839 48 70 22 2.17 252 2724 591
WID1842 50 52 2 0.60 710 240
WID1843 48 52 4 0.68 610 245
WID1843 68 70 2 0.53 440 190
WID1843 74 78 4 1.07 2340 370
WID1844 54 56 2 0.55 450 200
WID1844 94 102 8 0.60 653 258
WID2209 72.3 101.15 28.85 1.95 100 2356 484
WID2209 104.35 107.3 2.95 2.18 344 2532 483
WID2211 164.55 167.7 3.15 2.40 1711 243 661
WID2221 129 131.9 2.9 0.68 100 540 210
WID2221 149.5 151.2 1.7 0.58 100 762 245
WID2223 144.6 147.6 3 0.69 0 893 257
WID2223 169 170.5 1.5 0.57 233 447 203
WID2225 151 166.4 15.4 0.65 100 1355 226
WID2225 179.5 180.5 1 0.60 100 510 265
WID2225 181 183.5 2.5 0.61 100 574 242
WID2225 184.5 190.25 5.75 1.25 100 1955 443

46 neometals.com.au

==> picture [596 x 64] intentionally omitted <==

----- Start of picture text -----

7 July 2021 – REVIEW OF NICKEL MINERAL RESOURCES AT MT EDWARDS COMPLETE
----- End of picture text -----

Hole Id From To Length Ni% Asppm Cuppm Coppm Fe% MgO%
WID2227 206.6 207.6 1 3.13 74350 975 620
WID2227 209.4 215.2 5.8 1.40 10758 1108 384
WID2227 218.2 221.4 3.2 0.56 2288 235 161
WID2227 224.2 225.2 1 1.08 100 1084 310
WID2227 226.35 227.5 1.15 0.52 800 340 190
WID2227 240.65 241.65 1 0.62 200 510 190
WID2229 412.55 418.6 6.05 3.38 100 4027 610
WID2231 308.6 319.5 10.9 1.44 100 1734 433
WID2231 321.7 335.25 13.55 1.38 100 1890 419
WID2267 210.55 211.65 1.1 0.52 100 980 350
WID2269 302.7 303.75 1.05 0.63 300 700 250
WID2271 377 378 1 0.53 100 670 190
WID2350 48 55 7 1.10 100 1893 310
WID2351A 57 66 9 2.08 55 2368 551
WID2652 133 135 2 0.54 100 695 205
WID2652 136 147 11 0.88 100 1107 322
WID2652 148 164 16 0.73 100 898 268
WID2652 165 167 2 0.68 100 715 245
WID2652 185.3 189 3.7 1.25 1381 1175 372
WID2653 203.7 205 1.3 1.77 100 2465 580
WID2653 207.4 208.7 1.3 1.28 100 1370 358
WID2657 151 153 2 0.55 350 900 205
WID2657 157 159.8 2.8 1.03 764 891 273
WID2657 164 169 5 1.34 480 1456 402
WID2657 169.2 170.2 1 0.75 980 924 198
WID2658 244 245 1 0.53 35 490 36.15
WID2658 247.5 250.2 2.7 2.27 37 2261 21.77
WID2658 254 261 7 1.15 33 1899 27.15
WID2812 252 254 2 0.85 100 735 370
WID2814 232.9 235.8 2.9 1.78 46 2707 20.04
WID2814 236.6 241.2 4.6 1.22 31 1308 30.20
WID2815 254.8 256.2 1.4 0.56 314 391 191
WID2815 269 270 1 0.55 100 1570 170

47 neometals.com.au