MOUNT GIBSON IRON LIMITED (“MOUNT GIBSON”) QUARTERLY REPORT FOR THE PERIOD ENDED 31 DECEMBER 2011 ASX ANNOUNCEMENT 25 JANUARY 2012

HIGHLIGHTS

  • Extension Hill commenced commercial operation with its first shipment of hematite ore

  • Commissioning of Extension Hill crushing and screening plant

  • Koolan Island commenced mining of stage 1 Main Pit ore

  • Completion of sea wall at Koolan Island

  • Work at the Geraldton Port Infrastructure continues with good progress on upgraded rail unloader and the new Shed 5 facility

CORPORATE

  • Jim Beyer appointed as Chief Operating Officer and subsequently Acting Chief Executive Officer

  • Appointment of experienced mining and engineering professionals Russell Barwick and Paul Dougas as independent non-executive directors

  • Resignation of Craig Readhead as a director of the company

  • Luke Tonkin stepped down from his position as Managing Director

OPERATIONS

Koolan Island

The December quarter saw the Koolan Island operation continue to improve in performance. In addition two significant milestones were achieved; the completion of the sea wall adjacent to Main Pit and the first high grade ore mined in Main Pit.

Overall mining performance improved slightly with waste movement increasing by more than 6% compared with the previous quarter. Ore production was 6% higher and the crusher and screening throughput increased by 5% relative to the previous quarter. Ore mining occurred in Mullet, Barramundi West and Main Pits. Weather has been conducive to steady operations over this period.

==> picture [516 x 67] intentionally omitted <==

==> picture [542 x 151] intentionally omitted <==

Ore shipments were down from the previous quarter by 17% primarily due to late loading of the final December ship. Loading of this ship was completed on 3[rd] January.

Looking forward, Main Pit will increasingly become the main area of mining activity as Barramundi West and Mullet Pits are due for completion over the coming months. With the onset of the traditional wet season some delays due to inclement wet weather are anticipated, however these have been factored into production forecast.

Skilled labour availability continues to reflect the general shortage across the industry however the site has been able make good progress with the implementation of some targeted changes to recruitment, in particular greater emphasis on employing local trainees and increasing training resources.

Production statistics for the half year to December 2011 are shown in the table below.

Sept-11 Dec-11 Total 11-12
**Qtr ** **Qtr **
000’s 000’s 000’s
Mining
Waste Mined bcm 2,205 2,350 4,555
Ore Mined wmt 685 726 1,411
Crushing
Lump wmt 353 321 674
Fines wmt 382 448 830
**Total ** wmt 735 769 **1,504 **
Shipping
Lump wmt 365 285 650
Fines wmt 508 442 950
**Total ** wmt 873 727 1,600

==> picture [516 x 67] intentionally omitted <==

==> picture [542 x 151] intentionally omitted <==

==> picture [347 x 261] intentionally omitted <==

Figure 1- Showing pit development in Main Pit by end of December 2011 – Ore zone shown in red dashed area

==> picture [327 x 243] intentionally omitted <==

Figure 2 – Completed Sea Wall looking West

==> picture [516 x 67] intentionally omitted <==

==> picture [542 x 151] intentionally omitted <==

Extension Hill Hematite Mine

The December quarter saw Extension Hill make significant progress on its plans to become a key contributor to the company’s long term production profile. Two major milestones were achieved with the successful commissioning of the crushing and screening plant and the successful export of the first shipment at the Geraldton Port.

Mine ore production was 3% higher than the previous quarter. With the crushing and screening plant now in production, Run of Mine stockpile constraints previously experienced have started to reduce giving the mine greater material movement flexibility. Crushing operations continued to ramp up during the quarter.

Road haulage from Extension Hill to Perenjori began during the December quarter with 216,000 tonnes transported in the Perenjori siding railhead. Railing of lump product commenced with a total of 125,000 tonnes transported to the company’s existing shed, which is shared with Tallering Peak, at the Geraldton Port.

This quarter saw Extension Hill Hematite export the first 121,000 tonnes of lump ore to two customers during December on two ships.

==> picture [516 x 67] intentionally omitted <==

==> picture [542 x 151] intentionally omitted <==

Production for the December quarter is detailed in the following table.

: Sept
Dec
**Total **
Sept
Dec
**Total **
Sept
Dec
**Total **
2011-12Qtr
2011-12Qtr
11-12
000's
000's
000's
Mining
Waste Mined
Ore Mined (>55%Fe)
Crushing
Lump
Fines
Total
Transport to Perenjori Railhead
Lump
Fines
Total
Transport to Geraldton Port
Lump
Fines
Total
Shipping
Lump
Fines
bcm
wmt
wmt
wmt
wmt
wmt
wmt
wmt
wmt
wmt
wmt
wmt
wmt
226
444
0
0
265
459
260
133
491
903
260
133
0 393 393
0
0
154
62
154
62
0 216 216
0
0
125
0
125
0
0 125 125
0
0
121
0
121
0
Total wmt 0 121 121

==> picture [516 x 67] intentionally omitted <==

==> picture [542 x 151] intentionally omitted <==

Tallering Peak

Waste material movement was down 19% and ore mined was 21% down on the previous quarter. Overall performance was hampered by labour skills shortages in key production areas. This was further compounded by very tight working areas in advancing the cutback along with delays associated with pitwall areas requiring unplanned ground support. These near term operational issues impacted on achieving the planned mine extraction sequences and are being worked through with activities continuing to focus on minimizing the impacts as the site’s performance returns to expected levels.

Shipping was down 53% compared with the previous quarter driven by a delayed shipment that rolled into early January and by the near term ore availability constraints discussed above.

Production for the December 2011 quarter and comparison with the previous quarter is detailed in the following table:

Sept-11 Dec-11 Total 11-12
**Qtr ** **Qtr **
000’s 000’s 000’s
Mining
Waste Mined bcm 1,658 1,341 2,999
Ore Mined wmt 694 546 1,240
Crushing
Lump wmt 479 398 877
Fines wmt 329 266 595
Total wmt 808 664 1,472
Transport to Mullewa Railhead
Lump wmt 469 403 872
Fines wmt 327 230 557
Total 796 633 1,429
Transport to Geraldton Port
Lump wmt 305 241 546
Fines wmt 369 114 483
Total 674 355 1,029
Shipping
Lump wmt 351 240 591
Fines wmt 409 117 526
**Total ** wmt 760 357 1,117

==> picture [516 x 67] intentionally omitted <==

==> picture [542 x 151] intentionally omitted <==

==> picture [372 x 277] intentionally omitted <==

Figure 3 - Main Range pit looking west from the T2 backfill Waste dump at the end of December 2011

Outlook for Mid West Operations

During the 2012 March Quarter the company’s Mid West operations will be output constrained with batch transporting ore from Tallering Peak and Extension Hill to the Geraldton Port. This is due to a combination of considerable rail downtime associated with rail line infrastructure upgrade for the Karara Mining Limited operation and the rail out loading constraints that will be in place until the common user facilities upgrades at the port are completed.

Completion of the rail line upgrades, train unloader upgrades at the port and the commissioning of the company’s Shed 5 will significantly increase out loading capacity. These infrastructure works, along with the Tallering Peak operation returning to more consistent output, will allow the company to fully utilise its existing train paths and drive towards its planned six million tonne per annum haulage rates from the Tallering Peak and Extension Hill sites.

These construction activities have had an impact on the December quarter and until the work is completed the two Mid West operations will continue to experience limitations to total railing capacity. This work is now progressing at a satisfactory rate and these one off impacts will continue as construction tie-ins are completed at the port, rail upgrades are completed and the port facilities are commissioned. The internally managed activities are scheduled for late March/early April and the company is working closely with third parties to minimize the disruption to the business. In summary, the company expects these impacts to continue in the current March quarter with a guidance shipping range similar to the December quarter.

==> picture [516 x 67] intentionally omitted <==

==> picture [542 x 151] intentionally omitted <==

EXPLORATION AND RESOURCE DEFINITION ACTIVITY

Koolan Island

Exploration drilling for the quarter focused on an area west of the Mullet Acacia resource (10.5Mt @ 59.87% Fe - 30 June 2011). A total of 5,164 metres were drilled over 24 holes investigating a possible extension to the Mullet - Acacia mineralised horizon west of the current pit.

Results to date have been very positive with the discovery of continuation of the Acacia mineralisation, (the Acacia West area). Holes were drilled at a nominal 150m east-west spacing. Due to challenging topography some of the drill sites host two or three drill collars, with a variety of angled orientations between 60[o] and 90[o] (vertical).

Assay results have been received for all holes completed, with 21 holes of 24 drilled encountering significant mineralization (>55% Fe).

Some outstanding intersections have been drilled including :

PKRC1514: 52m @ 66.26% Fe from 120 metres downhole PKRC1507: 45m @ 67.08% Fe from 111 metres downhole PKRC1502; 26m @ 67.37% Fe from 117 metres downhole PKRC1491: 26m @ 64.59% Fe from 211 metres downhole

==> picture [516 x 67] intentionally omitted <==

==> picture [542 x 151] intentionally omitted <==

Significant Intercepts Fe>55%
HoleID from to Width (m) Fe % **SiO2 % ** **Al2O3 % ** P % LOI % EOH (m)
PKRC1491 190 202 12 62.83 8.99 0.55 0.011 0.14 240
211 237 26 64.59 7.06 0.42 0.008 0.15
PKRC1492 224 236 12 62.69 10.08 0.31 0.006 0.12 246
PKRC1493 198 203 5 63.72 8.99 0.16 0.003 0.02 216
PKRC1494 132 148 16 67.49 3.61 0.23 0.003 0.03 216
184 189 5 64.88 7.16 0.30 0.009 0.21
PKRC1495 No significant results 162
PKRC1496 91 109 18 61.96 10.48 0.51 0.007 0.16 150
PKRC1497 No significant results 138
PKRC1498 110 113 3 56.47 18.47 0.36 0.007 0.17 204
122 126 4 63.55 8.92 0.31 0.006 0.12
135 142 7 63.07 9.58 0.20 0.006 0.02
146 156 10 59.78 14.02 0.27 0.010 0.04
PKRC1499 No significant results 246
PKRC1500 133 142 9 60.76 11.72 0.82 0.011 0.23 204
PKRC1501 130 135 5 57.02 17.60 0.57 0.013 0.15 210
143 167 24 63.58 8.80 0.19 0.006 0.09
PKRC1502 117 143 26 67.37 3.84 0.19 0.002 0.05 180
152 167 15 63.11 9.50 0.28 0.005 0.03
PKRC1503 201 215 14 66.60 4.06 0.36 0.003 0.17 232
PKRC1504 198 218 20 64.44 7.48 0.31 0.004 0.11 264
230 233 3 66.37 4.99 0.78 0.004 0.17
236 246 10 60.03 13.34 0.174 0.014 0.08
PKRC1505 177 195 18 65.63 5.79 0.34 0.004 0.12 252
236 239 3 66.53 4.64 0.25 0.016 0.08
PKRC1506 176 198 22 68.89 1.38 0.18 0.003 0.07 234
228 232 4 63.78 7.63 0.87 0.020 0.28
PKRC1507 111 156 45 67.08 3.59 0.27 0.005 0.07 198
PKRC1508 212 223 11 65.57 6.04 0.21 0.004 0.07 276
252 262 10 62.14 10.93 0.19 0.007 0.05
PKRC1509 201 205 4 63.50 8.35 0.73 0.004 0.24 240
209 223 14 66.21 5.14 0.17 0.003 0.08
226 234 8 63.78 8.50 0.29 0.006 0.08
PKRC1510 No Significant Results 210
PKRC1511 113 126 13 60 12.84 0.2 0.006 0.14 216
130 150 20 65.38 4.98 0.32 0.005 0.13
PKRC1512 126 130 4 60.90 7.89 0.28 0.012 0.54 216
134 147 13 65.35 5.06 0.24 0.004 0.14
158 169 11 62.30 9.87 0.26 0.006 0.16
176 180 4 60.78 11.84 0.43 0.006 0.22
PKRC1513 No Significant Results 204
PKRC1514 120 172 52 66.26 3.96 0.30 0.005 0.14 180

==> picture [516 x 67] intentionally omitted <==

==> picture [542 x 151] intentionally omitted <==

Results confirm hematite mineralisation continues west of the Mullet Acacia resource. Significant intersections vary between 4 and 52 metres true width, with the mineralisation typically found along the contact of the Elgee Siltstone the Yampi Sandstone.

Several drill holes encountered two or more mineralised intersections which are thought to represent both southerly dipping limbs of a tight recumbent anticline. The wide intercepts of PKRC1514 (52m @ 66.26%) and PKRC1507 (45m @ 67.08%) are interpreted as having intersected the hinge of the fold.

The interpreted fold geometry is a tight recumbent fold with both limbs dipping to the south. The fold axis has a shallow westerly plunge. The High Grade Mineralisation is open to the west with further drilling planned in 2012.

The success of the Acacia West exploration during the 2011 December quarter is encouraging however additional drilling of similar intercepts is required before resource estimation can be considered.

==> picture [472 x 232] intentionally omitted <==

Figure 4 - Plan showing location of exploration RC holes drilled at Acacia West on Koolan Island during the quarter (blue circles). GDA 94 coordinates shown

==> picture [516 x 67] intentionally omitted <==

==> picture [542 x 151] intentionally omitted <==

==> picture [491 x 344] intentionally omitted <==

Figure 5 - Cross Section of Acacia West 9900mE looking west. Colours on drill trace represent Fe% assay results; (grey <10%, blue 10%–40%, green 40%–50%, yellow 50%–55%, orange 55%–60%, red 60%–65%, pink >65

==> picture [516 x 67] intentionally omitted <==

==> picture [542 x 151] intentionally omitted <==

Attribution

The information in this report that relates to Exploration Results is based on information compiled by Gregory Hudson, who is a member of the Australasian Institute of Mining and Metallurgy. Gregory Hudson is an employee of Mount Gibson Mining Limited, and has sufficient experience relevant to the styles of mineralisation and type of deposit under consideration and to the activity he is undertaking, to qualify as a Competent Person as defined in the December 2004 Edition of the “Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves”. Gregory Hudson has consented to the inclusion of the matters in this report based on his information in the form and context in which it appears.

The information in this report relating to Mineral Resources is based on information compiled by Rolf Forster, who is a member of the Australasian Institute of Mining and Metallurgy. Rolf Forster is a consultant to Mount Gibson Mining Limited, and has sufficient experience relevant to the styles of mineralisation and type of deposit under consideration and to the activity he is undertaking, to qualify as a Competent Person as defined in the December 2004 Edition of the “Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves”. Rolf Forster has consented to the inclusion of the matters in this report based on his information in the form and context in which it appears.

The information in this report relating to Mining Reserves is based on information compiled by Rolf Forster and Weifeng Li, who are both members of the Australasian Institute of Mining and Metallurgy. Rolf Forster and Weifeng Li are consultants to Mount Gibson Mining Limited, and have sufficient experience relevant to the styles of mineralisation and type of deposit under consideration and to the activity which they are undertaking, to each qualify as a Competent Person as defined in the December 2004 Edition of the “Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves”. Rolf Forster and Weifeng Li have consented to the inclusion of the matters in this report based on their information in the form and context in which it appears.

David Berg Company Secretary