16 May 2007

AUSTRALIAN STOCK EXCHANGE Via Electronic Lodgement

DRILLING REPORT

Metgasco (ASX:MEL) advises that the following drilling activity has taken place over the past week:

Corella-E8
Location
Spud Date:
Status:
Metgasco 85%, CS Energy earning 15%
PEL 16, Stratheden Joint Venture Area
15 May 2007
Current depth is 15m and drilling ahead prior to placing conductor
casing.
Corella-E7
Location:
Spud Date:
Status:
Metgasco 85%, CS Energy earning 15%
PEL 16, Stratheden Joint Venture Area
26 April 2007
Drilled to a depth of 312m. Casing has now been placed and cemented
prior to commencing coring operations.
Corella-E6
Location:
Spud Date:
Status:
Metgasco 85%, CS Energy earning 15%
PEL 16, Stratheden Joint Venture Area
2 April 2007
Coring operations have been completed with the well now drilled to a
total depth of 771 metres. A total of 42m of coal has been sampled for
testing.
In the last week drilling encountered a zone of interest comprising
fractured, gas charged sandstone which has exhibited characteristics of
a conventional gas reservoir. An 80m cement plug has now been placed
and a wellhead has been installed to allow further testing to occur. The
Company is currently mobilising equipment to conduct a DST.
Corella -E4 Metgasco 85%, CS Energy earning 15%
Location: PEL 16, Stratheden Joint Venture Area
Spud Date: 29 March 2007
Status: Suspended pending additional testing.
Corella-E5 Metgasco 85%, CS Energy earning 15%
Location: PEL 16, Stratheden Joint Venture Area
Spud Date: 19 February 2007
Status: Suspended pending additional testing.
Corella-E3 Metgasco 85%, CS Energy earning 15%
Location: PEL 16, Stratheden Joint Venture Area
Spud Date: 12 February 2007
Status: Suspended pending additional testing.
Metgasco 85%, CS Energy earning 15%
PEL 16, Stratheden Joint Venture Area
27 January 2007
Suspended pending additional testing.
Riflebird-E2 Metgasco 100%
Location: PEL 16
Spud Date: 22 January 2007
Status: Suspended pending additional testing.
Riflebird-E1 Metgasco 100%
Location: PEL 16
Spud Date: 15 January 2007
Status: Suspended pending additional testing.

For further information contact:

David Johnson Glenda McLoughlin

Managing Director Chief Financial Officer

Metgasco Limited
ACN 088 196 383
Level 3, 32 Walker St
North Sydney NSW 2060
Tel: (02) 9923 9100
Fax: (02) 9923 9199
Website: www.metgasco.com.au