METEORIC RESOURCES NL — Capital/Financing Update 2025
Jul 20, 2025
65311_rns_2025-07-20_40123a31-fa5e-47dc-843f-8c8bc99c6a12.pdf
Capital/Financing Update
Open in viewerOpens in your device viewer
==> picture [596 x 39] intentionally omitted <==
==> picture [596 x 39] intentionally omitted <==
----- Start of picture text -----
21 July 2025
----- End of picture text -----
Pre-Feasibility Study confirms Caldeira as a globally strategic, long-life rare earths project with significant growth potential
Backed by over $30M of investment in extensive resource drilling, metallurgical testwork and environmental programs, the PFS confirms strong operational and financial performance across market cycles
HIGHLIGHTS
Maiden Ore Reserve underpins confidence in recovering high value magnetic rare earth oxides
-
Probable Ore Reserve of 103Mt @ 4,091ppm TREO for 421kt of contained TREO based on extensive exploration programs delivering 71,000m of drilling and 45,000 samples
-
Measured Resources are defined by a maximum of 50m x 50m drill spacing
-
Indicated Resources are defined by a maximum of 100m x 100m drill spacing
Optimised plan delivers higher annual production at lower capital intensity compared to Scoping Study
-
Total Rare Earth Oxide ( TREO[1] ) of ~271kt, a 40% increase over the Life of Mine ( LOM )
-
Plant throughput increased by 20% to 6Mtpa (dry)
-
Pre-production capital cost of US$443M, a 10% increase, inclusive of US$86M in contingency
-
Higher average annual TREO production of 13,584t LOM
-
Average NdPr Oxide production of 4,228t per year (84,572t LOM)
-
Average DyTb Oxide production of 130t per year (2,600t LOM)
-
Operating costs of US$8.91/kg TREO for the first five years
-
NdPr Oxide operating cost of US$21.80/kg (with DyTb by-product credits at consensus pricing)
Essential testwork and piloting completed to support process design, flowsheet and PFS estimates
-
ANSTO continuous 15-day pilot program has de-risked the process flowsheet
-
ANSTO testing confirms world class LOM recoveries of 71% Magnetic Rare Earth Oxides ( Magnetic REO[2] ) and 55% TREO using an ammonium sulfate wash at pH 4.5 – 5.0
-
Less than 2% impurities in mixed rare earth carbonate ( MREC )
-
Successfully piloted de-watering technologies inclusive of reagents and clay management
-
Planned piloting testwork expected to identify significant opportunity for future cost improvements
-
Outstanding financial metrics based on broker consensus rare earth pricing
-
Undiscounted free cashflow of US$2.0 billion post-tax using consensus pricing
-
NPV8 pre-tax of US$821 million at consensus pricing and US$2.0 billion using forecast pricing
-
Internal rate of return (IRR) of 28% pre-tax
-
Payback of less than three years
-
Breakeven NdPr price of US$48/kg over life of Project
The PFS life of mine ore feed contains approximately 89% Measured & Indicated Resources and 11% Inferred Mineral Resources. An Inferred Mineral Resource has a lower level of geological confidence than an Ore Reserve or a Measured or Indicated Mineral Resource and there is no certainty that further exploration work will result in the conversion of the Inferred mineralisation into an Ore Reserve or that the production target itself will be realised.
2 Magnetic Rare Earth Oxides (Magnetic REO) = Pr6O11 + Nd2O3 +Tb4O7 + Dy2O3
==> picture [596 x 61] intentionally omitted <==
----- Start of picture text -----
1 [st] Floor PO Box 475 Meteoric.com.au
35 Ventnor Avenue Inglewood WA 6932 ABN: 64 107 985 651
West Perth WA 6005
----- End of picture text -----
1 All references to Oxides are based on the contained level of those Oxides within the MREC product, noting the TREO contains La2O3 + CeO2 +Pr6O11 + Nd2O3 + Sm2O3 + Eu2O3 + Gd2O3 + Tb4O7 + Dy2O3 + Ho2O3 + Er2O3 + Tm2O3 + Yb2O3 + Lu2O3 + Y2O3
==> picture [595 x 39] intentionally omitted <==
==> picture [595 x 39] intentionally omitted <==
Strong sustainability credentials and local government support
-
100% of Caldeira energy requirements to be sourced from renewable energy sources
-
MoU signed with the State of Minas Gerais designates Caldeira as a priority state project
-
Environmental studies are continuing to support permitting process
-
Permitting on track to allow construction to commence in 2026
-
Social programs implemented focussing on underprivileged youth, individual technical skills development, local business readiness, and indigenous communities
Project rapidly advancing and systematically de-risked
-
Establishment of a scalable 25kg/hour pilot plant at Poços de Caldas is underway:
-
Continuous production of an MREC product using preferred flowsheet
-
Opportunity to optimise flowsheet and test downstream rare earth separation at a pilot scale
-
Commence targeted cost reduction and optimisation initiatives including:
-
Geotechnical field work to support mine and plant design (commenced May 2025)
-
Additional piloting to optimise reagent consumption and moisture content of spent clays
-
Mine scheduling review targeting mining efficiencies
-
Inclusion of recent near mine discoveries
MP Materials and US Department of Defense ( DoD ) Public-Private Partnership to accelerate REE magnet independence highlights demand for alternative and additional REE supply
-
Setting of US$110/kg NdPr floor price commitment for 10 years as part of a magnet offtake agreement with MP Materials
-
Expansion of MP Materials magnet making capacity to 10kt per annum
-
DoD commit to purchase 100% of MP Materials’ magnet making for defence consumption
-
US Government financial support through convertible instruments and loans
Economic Outcomes at a US$110/kg price threshold
-
Undiscounted free cashflow of US$2.8 billion post tax
-
NPV8 pre-tax of US$1.3 billion
-
IRR of 36% pre-tax & 28% post-tax
-
Payback period of 2.5 years
Meteoric Managing Director and CEO, Stuart Gale, commented:
“The PFS completion represents a significant step forward for Meteoric and the Caldeira Project. With an investment of more than $30M over the past two-and-a-half years on resource development, process testwork and environmental programs, we have an excellent understanding of the Project and where we can further optimise the asset as we move into the final piloting and studies phase.
Our drilling programs have confirmed the world-class scale and high-grade ionic absorption rare earths mineralisation at the Project. The volume of close-spaced drilling supports the maiden Ore Reserve with significant scope for this to grow and support future mine life or production expansions.
Our confidence in the PFS and process more broadly is based on the enormous effort devoted to testing and refining the process and flowsheet. In particular, the work conducted at ANSTO to confirm recoveries, quality of the initial MREC product and materials handling have supported the engineering effort lead by Ausenco. We will continue to fine tune and further optimise our processes to lower our operational costs.
Optimisation of the processing plant design increased capacity by 20% to 6Mtpa. This delivers an improved return on capital investment, levering both the size of the Caldeira Project resource and economies of scale. The PFS metallurgical testwork program has validated our original process flowsheet and we will now use this flowsheet to construct a pilot plant at site to assist in fine tuning the process and provide MREC for qualification
Meteoric Resources July 2025 Preliminary Feasibility Study
Page 2 of 41
==> picture [595 x 39] intentionally omitted <==
==> picture [595 x 39] intentionally omitted <==
with our customers.
Detailed bottom-up operating and capital cost estimates provide a higher degree of confidence than earlier studies and confirm the Caldeira Project is firmly positioned as a low-cost producer of rare earths and competitive through any price cycle. The exceptional economics are achieved by simple free-dig mining, highgrade ionic clay ore, excellent Magnetic REO recoveries, a fast leach reaction time of 30 minutes with a simple ammonium sulfate flowsheet and low-cost renewable energy. These characteristics combine to make a compelling case for Caldeira Project to be a sustainable global supplier of rare earths products.
The Caldeira Project PFS arrives at an opportune time as the US and other western economies seek to establish responsible and reliable rare earths supply chains. It was very encouraging to see the MP Material and US DoD agreement which solidifies the US Government’s commitment to support the acceleration of magnet production capacity. The Calderia Project resource, scale and location make it an ideal asset to supply these developments.
Our priorities are clear – establishment of the on-site pilot plant; commence targeted improvement initiatives; progress permitting towards the issue of a Construction License in 2026; and concluding strategic discussions about project funding, offtake and potential downstream opportunities.”
Introduction
Meteoric Resources NL ( ASX: MEI: Meteoric or the Company ) is pleased to present the Pre-Feasibility Study ( PFS ) outcomes for its Caldeira Rare Earth Ionic Clay Project ( Caldeira Project or Project ), located in the state of Minas Gerais in Brazil.
The PFS builds on the outcomes previously outlined in the Scoping Study and the Updated Scoping Study completed in July 2024 and October 2024 respectively.
Meteoric engaged leading global engineering group Ausenco Pty Ltd ( Ausenco ) to support co-ordination of the PFS workstreams and assist with process flowsheet development. The Australian Nuclear Science and Technology Organisation ( ANSTO ) completed pilot scale metallurgical testwork as part of the PFS. Detailed bottom-up cost estimates performed by Ausenco based on the confirmed flowsheet have been completed in the PFS to an estimated accuracy of +/- 25%.
Key PFS Outcomes and Assumptions
The PFS confirms the robust technical and economic viability for development of a mining and processing operation to produce a MREC product at the Caldeira Project. Further, potential remains to expand the Project and move downstream into the production of separated rare earth element ( REE ) oxides at later dates.
Since the completion of the Caldeira Project Scoping Study in July 2024, a substantial 12-month work program has been completed to de-risk mining and processing elements and deliver more robust cost estimates built on vendor pricing. This has included:
-
Significant diamond ( DD ) and aircore ( AC ) drill programs which now total >57,000m, producing 31,000 samples for chemical assay in addition to 14,000m of historical auger drilling and sampling
-
Delivered an updated global Mineral Resource Estimate of 1.5Bt @ 2,359ppm TREO with:
-
Measured Resources defined by a maximum of 50m x 50m drill spacing
-
Indicated Resources defined by a maximum of 100m x 100m drill spacing
-
Inferred Resources defined by a maximum of 400m x 400m drill spacing
-
Substantial metallurgical testwork with ANSTO and other consultants, including a 15-day continuous piloting program
-
Detailed test work on settling the clays, dewatering technology and materials handling
-
Scrubbing solutions vendor testing
A summary of the physical and financial evaluation of the Project utilising a Processing Plant with a 6.0Mtpa throughput rate is shown in Table 1 and 2, respectively. Additional details are set out below in the PFS Executive Summary.
Meteoric Resources July 2025 Preliminary Feasibility Study
Page 3 of 41
==> picture [595 x 39] intentionally omitted <==
==> picture [595 x 39] intentionally omitted <==
Table 1: Production Outcomes and Assumptions
==> picture [483 x 202] intentionally omitted <==
----- Start of picture text -----
Updated Scoping Study Pre-Feasibility Study
Key Production Outcomes Unit
Years 1-5 LOM Years 1-5 LOM
Ore Mined kt 23,004 98,000 26,523 128,989
Strip Ratio waste:ore 0.08 0.21 0.52 0.38
Average TREO Feed Grade ppm 4,591 3,724 4,515 3,701
TREO Recovery % 53 53 54 55
Magnetic REO Recovery % 73 73 73 71
Average annual production [2] (REO) t 11,453 9,685 12,382 13,584
Production (REO) t 57,258 193,584 61,912 271,687
NdPr % (in TREO concentrate) % 32 33 31 31
----- End of picture text -----
The calculations in Table 2a are based on three sets of TREO pricing assumptions:
-
The spot price;
-
A broker consensus price[3] ; and
-
An average forecast price[4] by independent market analysts Adamus Intelligence and Project Blue.
The financial outcomes assessed in the PFS highlight the robust nature of the Caldeira Project, at current spot prices, and highlight significant upside in higher pricing environments. The key financial outcomes based on the three pricing assumptions are presented below.
Table 2a: Key Financial Outcomes and Assumptions
==> picture [504 x 303] intentionally omitted <==
----- Start of picture text -----
Years 1-5 LOM
Cashflow, Cost &
Unit
Earnings Metrics Spot Consensus Forecast Spot Consensus Forecast
Annual Average
Revenue US$M 210 284 330 245 315 485
EBITDA US$M 79 147 189 86 150 305
Operating Cashflow US$M 60 104 132 58 100 203
Total
Revenue US$M 1,050 1,422 1,650 4,927 6,330 9,756
EBITDA US$M 397 737 944 1,707 2,987 6,111
Net profit After Tax
US$M 186 410 546 710 1,561 3,625
(NPAT)
Cumulative post tax
cashflow excluding US$M 298 522 659 1,165 1,994 4,058
construction cost
Annual operating cost US$M 110 133
Annual operating cost US$/kg TREO 8.91 9.78
Annual AISC [5] US$/kg TREO 11.16 11.69 12.01 12.62 13.07 14.18
NdPr average pricing US$/kg NdPr 67 91 107 67 86 135
NdPr average operating
cost (net of DyTb US$/kg NdPr 20.58 21.80
-
by product credits)
----- End of picture text -----
2 Includes ramp up in Years 1 and 2.
3 Consensus reflecting the long term real available pricing expectations from multiple brokers as of May 2025, source Macquarie Bank.
4 Forecast is calculated as the average between Adamas Intelligence & Project Blue long term pricing reported at Q1, 2025.
5 ASIC will vary based on royalty costs changing under differing pricing scenarios.
Meteoric Resources July 2025 Preliminary Feasibility Study
Page 4 of 41
==> picture [595 x 39] intentionally omitted <==
==> picture [595 x 39] intentionally omitted <==
Table 2b: Key Financial Outcomes and Assumptions continued.
==> picture [438 x 385] intentionally omitted <==
----- Start of picture text -----
LOM
Financial Outputs Unit
Spot Consensus US$110/kg Forecast
NdPr
Annual Revenue US$M 245 315 385 485
Annual EBITDA US$M 86 150 213 305
Annual Operating Cashflow US$M 58 100 143 203
Annual operating costs (ex-royalties) US$M 133
Annual operating costs (ex-royalties) US$/kg TREO 9.78
Annual AISC (including royalties) US$/Kg TREO 12.62 13.07 13.53 14.18
Basket price [6] TREO US$/kg TREO 26 33 41 51
NdPr Average pricing US$/kg NdPr 67 86 110 135
Payability % 70
NdPr Gross operating cost US$/kg NdPr 31
NdPr Net Operating costs [7] US$/kg NdPr 22
Capex inclusive of 25% contingency US$M 443
Cumulative post tax cashflow
US$M 1,165 1,994 2,842 4,058
(excluding construction cost)
Pre-tax NPV8 US$M 251 821 1,347 1,985
Post-tax NPV8 US$M 109 488 835 1,256
Pre-tax IRR % 15 28 36 39
Post-tax IRR % 11 21 28 31
Payback period years 6.1 2.9 2.5 2.8
----- End of picture text -----
Table 2b. above, includes the financial outputs inclusive of a US$110/kg NdPr floor price reflected in the recent announcement by MP Materials and DOD. Meteoric has assumed consensus pricing for all other rare earth elements in it’s REE basket in this comparison.
Project Overview
The Project comprises 77 Mining and Exploration Licences (with total landholdings over 18,292 hectares) located between the cities of Caldas, Poços de Caldas, and Andrades in the southwest region of the state of Minas Gerais in Brazil (Figure 1). Caldeira is located 254km from the city of Sao Paulo and approximately 350km from the port of Santos.
The Alkaline Intrusive Complex of the Poços de Caldas area is one of the most important economic and geological terrains in Brazil. To date, only a small number of the 77 licences held by Meteoric have been explored, creating considerable geological upside.
Rare earths mineralisation at Caldeira is enriched in magnet rare earths of dysprosium and terbium (DyTb) and neodymium and praseodymium (NdPr). The mineralisation is hosted in weathered clays which have significant cost and operating advantages relative to hard rock rare earths deposits.
6 The basket price of TREO refers to the weighted average price of the individual REE contained in a specific mineral concentrate or product, based on their relative proportions and current market prices
7 Operating costs net of DyTb credits at consensus pricing per kilogram of NdPr produced
Meteoric Resources July 2025 Preliminary Feasibility Study
Page 5 of 41
==> picture [595 x 39] intentionally omitted <==
==> picture [595 x 39] intentionally omitted <==
Figure 1: Caldeira Project Licences (four southern licenses included in the PFS highlighted in red).
==> picture [475 x 475] intentionally omitted <==
Meteoric Resources July 2025 Preliminary Feasibility Study
Page 6 of 41
==> picture [595 x 39] intentionally omitted <==
==> picture [595 x 39] intentionally omitted <==
A Mineral Resource Estimate ( MRE ) for the Caldeira Project was first reported in May 2023. The MRE has grown significantly with subsequent drilling programs totalling ~57,000m completed by Meteoric and was last updated on 15 April 2025 (Table 3). At its current scale of 1.5 billion tonnes, the Project is one of the largest known ionic absorption clay rare earth deposits globally.
Table 3: Caldeira Global Mineral Resource
| Licence | JORC Material Tonnes TREO Pr6O11 Nd2O3 Tb4O7 Dy2O3 Magnetic REO Magnetic REO |
|---|---|
| Category Type Mt ppm ppm ppm ppm ppm ppm /TREO |
|
| Capão do Mel | Measured Clay 11 3,888 222 586 6 28 842 21.7% |
| Cupim Vermelho Norte |
Measured Clay 26 2,607 156 477 5 25 663 25.4% |
| Total | Measured 37 2,983 176 509 5 26 715 24.0% |
| Capão do Mel | Indicated Clay 74 2,908 163 449 5 23 640 22.0% |
| Barra do Pacu | Indicated Clay 77 2,917 143 376 4 21 545 18.7% |
| Soberbo | Indicated Clay 86 2,730 165 476 5 23 669 24.5% |
| Figueira | Indicated Clay 138 2,844 145 403 5 28 582 20.5% |
| Cupim Vermelho Norte |
Indicated Clay 90 2,658 163 489 5 26 683 25.7% |
| Dona Maria 1 | Indicated Clay 111 2,253 128 376 4 23 531 23.6% |
| Dona Maria 2 | Indicated Clay 53 2,303 132 390 4 22 548 23.8% |
| Total | Indicated 629 2,668 148 422 5 24 599 22.4% |
| Total | Measured + Indicated 666 2,685 150 427 5 25 605 22.5% |
| Capão do Mel | Inferred Clay 32 1,791 79 207 2 13 302 16.9% |
| Barra do Pacu | Inferred Clay 190 2,153 112 296 3 18 429 19.9% |
| Soberbo | Inferred Clay 89 2,713 167 478 5 24 675 24.9% |
| Figueira | Inferred Clay 9 3,105 139 379 5 28 551 17.7% |
| Cupim Vermelho Norte |
Inferred Clay 78 2,237 126 377 4 23 530 23,8% |
| Dona Maria 1 | Inferred Clay 49 2,225 121 383 5 25 534 24.0% |
| Dona Maria 2 | Inferred Clay 29 2,324 130 397 4 21 552 23.8% |
| Capão do Mel | Inferred Transition 25 1,752 86 239 3 14 341 19.5% |
| Barra do Pacu | Inferred Transition 122 1,837 95 253 3 15 355 19.9% |
| Soberbo | Inferred Transition 54 2,207 138 395 4 20 558 25.3% |
| Figueira | Inferred Transition 24 2,174 115 328 4 21 468 21.5% |
| Cupim Vermelho Norte |
Inferred Transition 67 1,665 92 281 3 17 393 23.6% |
| Dona Maria 1 | Inferred Transition 42 1,703 95 275 3 17 390 22.9% |
| Dona Maria 2 | Inferred Transition 21 1,615 86 251 3 15 355 22.0% |
| Total | Inferred 832 2,097 115 325 4 19 462 22.0% |
| Total | Measured + Indicated + Inferred 1,497 2,359 130 370 4 21 526 22.3% |
Approximately 40% of the MRE is in the higher confidence Measured and Indicated JORC categories, positioning the Caldeira Project as the largest inventory of REO of ionic absorption clay deposits in the world (Figure 2).
Meteoric Resources July 2025 Preliminary Feasibility Study
Page 7 of 41
==> picture [595 x 39] intentionally omitted <==
==> picture [595 x 39] intentionally omitted <==
Figure 2: Graph of tonnage v TREO grade for reported Measured and Indicated Resources of Ionic Adsorption Clay deposits. The size of the sphere is related to contained metal (Refer Appendix 2).
==> picture [484 x 234] intentionally omitted <==
----- Start of picture text -----
3,500
3,000
Colossus Caldeira
2,500 PCH
Penco Module
2,000
1,500 Pela Ema
1,000 Deep Leads - Rubble
Mound - Wind Break
Makuutu
500
-
- 100 200 300 400 500 600 700 800
Measured + Indicated Resource (Mt)
TREO Grade (ppm)
----- End of picture text -----
Infrastructure and Utilities
The Caldeira Project is favourably located close to existing infrastructure and utilities which supports cost outcomes and future operational logistics. A summary of key infrastructure and utilities aspects of the Project is included in Table 4.
A satellite plan view of the planned Southern Operation of the Caldeira Project area including the process plant site, the location of key infrastructure and four licence areas considered in the PFS is shown in Figure 3.
Table 4: Caldeira Project Infrastructure and Utilities
==> picture [483 x 316] intentionally omitted <==
----- Start of picture text -----
Item Summary
Various accommodation options available in the nearby towns of Caldas and Poços de
Accommodation Caldas.
No camp is required either for operations or the ~1,200 person construction workforce.
Water will be supplied to the facilities from an existing nearby dam, approximately 400m
Water
from the Caldeira Project plant site.
100% of Meteoric’s energy requirements will be sourced from renewable energy (hydro,
solar and wind), an option provided by the grid operator, CEMIG.
Power Power will be connected to the site via a ~2.5km overhead power line to a local 138kV
network connection at the nearby substation.
The connected load is estimated at 20MW, with Plant average demand at ~13MW.
The proposed main access road is shown in Figure 3. Approximately ~3km of new
unsealed road will need to be constructed to connect the plant site with the existing public
road network.
Road Access
By road the Project site is ~447km from the capital Belo Horizonte and 254km from the city
of São Paulo on good quality sealed roads.
The Project site is ~31km to the south of the city of Poços de Caldas.
All required facilities exist.
Port During construction and operations containerized cargo is expected to enter and leave
Brazil at Santos port near the city of Sao Paulo. Itaguaí (in Rio state) was identified as an
alternate port that may suit breakbulk cargo if required.
There is mobile phone and Starlink reception on site for communications prior to plant
Telecommunications []
commissioning.
----- End of picture text -----
Meteoric Resources July 2025 Preliminary Feasibility Study
Page 8 of 41
==> picture [595 x 39] intentionally omitted <==
==> picture [595 x 39] intentionally omitted <==
| Meteoric has a preference for fibre optic connection via the grid connected power supply OHL as the backbone for operations. |
|
|---|---|
| Fuel Storage | The fuel storage facility will be in the Mine Infrastructure Area with sufficient diesel storage to support mining operations for ~7 days. |
| Fleet & Vehicles | A list of plant vehicles and mobile equipment fleet necessary to support operations was developed during the PFS and will be leased initially to minimise capital expenditure. |
| Waste | Domestic and industrial waste will be processed at a WSF on site before disposal. Classification and segregation of materials will be performed at the Classification Shed at the WSF. |
Figure 3: Caldeira Project – Plan View of PFS Licences and Mine Infrastructure.
==> picture [484 x 229] intentionally omitted <==
==> picture [484 x 115] intentionally omitted <==
Meteoric Resources July 2025 Preliminary Feasibility Study
Page 9 of 41
==> picture [595 x 39] intentionally omitted <==
==> picture [595 x 39] intentionally omitted <==
Government Support
Meteoric has received strong support from the governments of Minas Gerais and Brazil for the Caldeira Project.
A Memorandum of Understanding was agreed with the state of Minas Gerais in August 2023 which designates the Caldeira Project as a priority state project. This status confers government assistance for the Project in terms of permitting and assistance during the implementation and operations phases.
The Project was one of six ventures named in the Brazil Climate and Ecological Transformation Investment Platform ( BIP ). Led by Brazil’s government and the Brazilian Development Bank ( BNDES ), BIP plans to help scale energy transition investment from both public and private sectors, mobilise capital at scale, and ensure effective resource deployment to further the Brazilian government’s climate transition plans across key sectors.
Mining Methods and Assumptions
Economics of the Caldeira Project benefit from exclusively mining soft clay material. This means there is no requirement for blasting, with ore to be extracted through conventional excavation and hauled to the processing plant on dedicated haul roads.
The Mine Plan has been designed to prioritise high-grade ore with excellent metallurgical recoveries. This approach will accelerate the payback period and deliver higher financial returns over the life of the Project. It will also allow expansion opportunities to be funded through operational cash flow.
Mining activities will initially commence at the Capão do Mel ( CDM ) deposit, which is located closest to the planned processing plant site, before expanding to the Figueira ( FIG ), Barra do Pacu ( BDP ) and Soberbo ( SOB ) licences.
Figure 4: Total Ore Mined by Deposit
==> picture [484 x 271] intentionally omitted <==
----- Start of picture text -----
8.0Mt
FIG CDM SOB BDP
7.0Mt
6.0Mt
5.0Mt
4.0Mt
3.0Mt
2.0Mt
1.0Mt
0.0Mt
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
----- End of picture text -----
The Project benefits from a low LOM strip ratio of 0.38 (waste:ore). Waste material will be used for construction purposes (roads, bunds, etc) and the remainder will be stored using ex-pit and predominantly in-pit dumps. The plan is to only use ex-pit dumps in the first two years of mining before backfilling can commence in completed sections of the open pits using waste and spent clay rejects from the plant. There is no requirement for the construction of a tailings dam.
Topsoil will be stockpiled in accessible areas near the mine to be used for rehabilitation once a section of the pit has been backfilled and contoured to final landform. The processing plant capacity will be 6.0Mtpa and the monthly requirement for material movement will on average 0.5M bank cubic metres ( BCM ) per month.
Meteoric Resources July 2025 Preliminary Feasibility Study
Page 10 of 41
==> picture [595 x 39] intentionally omitted <==
==> picture [595 x 39] intentionally omitted <==
Average mining costs of US$2.54/kg TREO recovered are based on the first five years of operations using an owner-mining fleet.
Table 5: Pit Design Inventory by Deposit and by Resource Classification
==> picture [483 x 134] intentionally omitted <==
----- Start of picture text -----
Caldeira Project
Measured Indicated Inferred Waste Total
TREO Cont. TREO Cont. TREO Cont.
Deposit Mt Mt Mt Mt Mt
(ppm) REO (kt) (ppm) REO (kt) (ppm) REO (kt)
CDM 7 4,682 32 30 3,756 114 - - - 23 60
FIG - - - 16 4,951 80 - - - 11 27
SOB - - - 24 3,735 91 - - - 11 36
BDP - - - 25 4,130 105 14 3,628 51 16 55
Total 7 4,682 32 96 4,050 390 14 3,628 51 61 178
----- End of picture text -----
Maiden Ore Reserve
Meteoric estimates a Maiden JORC Ore Reserve of 103Mt at 4,091ppm TREO from four licenses. These Ore Reserves represent 27% of the currently defined Measured and Indicated MRE for these four deposits. The Ore Reserves for the Project have been estimated as at 24 April 2025 in accordance with the JORC Code (2012) and summarised by Deposit in Table 6 below.
Table 6: Caldeira JORC Ore Reserves
==> picture [483 x 275] intentionally omitted <==
----- Start of picture text -----
Classification Tonnes (Mt) TREO ppm Prppm6O11 Ndppm2O3 Cont. REOkt
Capão do Mel (CDM)
Proved - - - - -
Probable 37.1 3,925 243 667 146
Total 37.1 3,925 243 667 146
Figueira (FIG)
Proved - - - - -
Probable 16.1 4,951 450 938 75
Total 16.1 4,951 450 938 75
Soberbo (SOB)
Proved - - - - -
Probable 24.3 3,735 256 736 91
Total 24.3 3,735 256 736 91
Barra do Pacu (BDP)
Proved - - - - -
Probable 25.5 4,130 234 621 105
Total 25.5 4,130 234 621 105
Total Caldeira Project
Proved - - - - -
Probable 103.0 4,091 276 714 416
Total 103.0 4,091 276 714 416
----- End of picture text -----
1. Ore Reserve estimates are not precise calculations, being dependent on the underlying Mineral Resource and based on limited information in respect to modifying factors. The totals contained in the above table have been rounded to reflect the relative uncertainty of the estimate.
2. Only material that is CLAY and has a resource classification of Measured or Indicated have been included.
3. Measured and Indicated have been converted to Probable only.
4. Ore Reserves are reported in accordance with the Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves (The Joint Ore Reserves Committee Code – JORC 2012 Edition).
Meteoric Resources July 2025 Preliminary Feasibility Study
Page 11 of 41
==> picture [595 x 39] intentionally omitted <==
==> picture [595 x 39] intentionally omitted <==
Processing
Meteoric has been conducting metallurgical testwork on the Project since 2023, building on work completed by SGS-Geosol for JOGMEC on a 200kg composite sample from CDM deposit in 2019.
In 2023, ANSTO was commissioned to execute the test work program for Meteoric. The objective of the testwork was to develop an optimal flowsheet for the extraction of REE through leaching, impurity removal, and the precipitation of rare earth minerals.
Testwork results confirmed that rare earth minerals at the Caldeira Project can be extracted using a low acidity ammonium sulfate solution within a 30 minute leach reaction time. This method will result in an average processing cost of US$6.37 per tonne during the first five years of operations.
A continuous pilot program was also conducted at ANSTO using a 2.5 tonne composite sample from CDM (representative of the CDM starter pit). The campaign successfully validated and de-risked the process flowsheet, achieving a comparable MREO recovery to the LOM average rate of 71% and producing a highquality MREC with less than 2% impurities. Further piloting is scheduled to take place in Brazil in the December quarter 2025.
The Caldeira Project processing plant is designed to process 6.0Mtpa dry feed to produce ~24,000 tonnes per annum of dry MREC product. The processing plant will operate 24 hours per day at 750tph (dry) for 8,000 hours per year (assumes 91% utilisation).
The feed grades and recoveries used in the PFS design are based on composites from the CDM, FIG and SOB deposits and Meteoric supplied data derived from an average of the batch tests completed by ANSTO. The impurities contained in the feed ore are based on the CDM master composite.
A combination of vendor and ANSTO batch and piloting test work data was used as the basis for the plant design development. Design factors have been applied to determine equipment sizing.
Table 7: Mining and Processing Summary
==> picture [480 x 137] intentionally omitted <==
----- Start of picture text -----
Unit LOM
Mining
Life of Mine Years 20
Total ROM Feed Tonnes (M) 128,989
Total Waste Tonnes (M) 48,581
Processing
TREO Tonnes 271,687
NdPr oxides Tonnes 84,572
Dy oxide Tonnes 2,143
Tb oxide Tonnes 457
----- End of picture text -----
The extraction of the rare earths from the REE-bearing ionic clays in the Caldeira Project deposits occurs through an ion exchange mechanism between ammonium sulfate (liquid phase) and the rare earths which are Ionically attached to the outside surface of the clay (solid phase) mineral. The desorption process uses ammonium sulfate ((NH4)2SO4) as the leaching agent under mildly acidic conditions (pH 4.5 -5.0).
Following leaching, the slurry is transferred to the residue dewatering circuit to further extract REE from residue. This is followed by separation and washing of REE sulfates contained in the pregnant leach solution ( PLS ) from the barren leach solids. The final residue with an appropriate sulfate level will be de-watered and sent for in-pit tailings disposal. The counter current decantation ( CCD ) thickener circuit will provide washing of the leached residue to maximise recovery of REE to PLS through counter current washing and additional extraction.
Meteoric Resources July 2025 Preliminary Feasibility Study
Page 12 of 41
==> picture [595 x 39] intentionally omitted <==
==> picture [595 x 39] intentionally omitted <==
Figure 5: Process Flowsheet
==> picture [478 x 316] intentionally omitted <==
Figure 6: Plant Layout
==> picture [480 x 232] intentionally omitted <==
Permitting
Brazil has a clearly defined three stage Environmental permitting process for Class 6 mineral projects. Meteoric is progressing through the permitting process which aligns with the current development timeline. The Project is currently in the Preliminary License ( LP ) phase in satisfying right to mine requirements in Brazil:
Meteoric Resources July 2025 Preliminary Feasibility Study
Page 13 of 41
==> picture [595 x 39] intentionally omitted <==
==> picture [595 x 39] intentionally omitted <==
1. Preliminary License (LP)
The LP is designed to evaluate project social and environmental feasibility and establish basic preliminary conditions. The principal document supporting the LP was the Environmental Impact Study ( EIS ) which was completed by ALGER and submitted to State Bureau of Environment and Sustainable Development ( SEMAD ) in May 2024.
EIS results evidence the strong Project socio-environmental feasibility and reaffirm Meteoric’s strong commitment to sustainable practices, supporting local communities and preserving the Project environment.
Apart from the procurement of third-party specialist environmental advice to complete the licencing process, no further costs are associated with the LP and Meteoric anticipates SEMAD will grant the LP in 2025.
There are two Environmental areas within the municipality of Caldas which encroach upon the current resources at Soberbo, Capão do Mel, and Barra do Pacu (Figure 1), being:
-
(i) Environmental Protection Area ( APA ) Ecological Sanctuary of Serra da Pedra Branca (established by Municipal Law of Caldas/MG nº 1.973/2006) and
-
(ii) a 3km strip surrounding the APA ( Buffer Zone ).
Part of the SOB deposit is within the APA whilst the majority of SOB, 80% of BDP and all of the CDM starter deposit are within the Buffer Zone.
Article 51 of Law of Caldas/MG nº 1.973/2006 stipulates that mining activity is currently not permitted within the APA (other than for existing activity with operating licenses). The current PFS development scenario and LP application do not propose any activity inside the APA area.
Mining activity within the Buffer Zone is permitted and may be undertaken upon completion of an Environmental Impact Assessment ( EIA ), a proposal of measures necessary to mitigate any possible impact on ecosystems, a Certificate of Regularity for Land Use and Occupation from the municipality of Caldas Municipal Environmental Council ( CODEMA ), and authorisation of the APA Management Council (outstanding).
Meteoric has conducted extensive research and consultation from mid-2023 with the objective of seeking and obtaining permission to conduct mining activities in the Buffer Zone and is confident of obtaining favourable consideration from the relevant authorities. That confidence is based upon: Environmental Impact Statement ( EIS ) and relevant flora and fauna and ethnographic studies completed over the area, ongoing dialogue and consultation with multiple stakeholders including favourable feedback from a Social Diagnosis and Stakeholder Survey of the Caldeira Project conducted by EcoDue Ambiental in December 2023, and specifically by reason of the terms of a written Protocol of Intent entered into between the Government of Minas Gerais and Meteoric Brazil.
As such Meteoric considers there are reasonable prospects for eventual economic extraction to justify the Mineral Classifications of Measured and Indicated Resources (within the Buffer Zone), and the subsequent Probable Reserves. A majority of the LP milestones have been achieved already, including:
-
Multiple environmental baseline surveys and social mapping surveys
-
Submission of the EIS
-
Mandatory public hearing in Caldas City chaired by SEMAD
-
Certificate of Regularity for Land Use and Occupation from CODEMA
-
Considerable landholder engagement to support required consents and royalty agreements for future mining areas
2. Installation License (LI)
In parallel with the LP process, Meteoric is already making advances towards satisfying future LI requirements including the completion of additional environmental studies (Environmental Control Plan – PCA), securing required landowner consents and having the ANM specify rare earths on tenement titles.
Upon issue of the LI, the Company is entitled to commence Project construction, installation of equipment, and start mining.
Meteoric anticipates the LI grant will occur in 2026.
Meteoric Resources July 2025 Preliminary Feasibility Study
Page 14 of 41
==> picture [595 x 39] intentionally omitted <==
==> picture [595 x 39] intentionally omitted <==
3. Operating License (LO)
Meteoric will require an LO to commence the Project operation. This is a short, audit style process during which SEMAD confirms Project compliance with LI obligations. Meteoric can continue with all Project testing and commissioning activities whilst this process is ongoing.
Pricing Assumptions and Forecast Methodology
The economic model has been developed using spot pricing, broker consensus pricing, and forecast data from two highly regarded independent market analysts, Project Blue and Adamas Intelligence. While their forecasts differ materially, both are considered credible and reflect the inherent uncertainty in today’s REO market environment. In light of this, Meteoric has chosen to present an average of both sets of projections as one set of the potential forward pricing scenarios. The Company believes this approach offers investors a more balanced and transparent view of potential market scenarios and provides a robust foundation for long-term financial modelling and strategic planning.
These forecasts are underpinned by comprehensive analysis of global supply and demand trends. On the demand side, projections reflect anticipated growth in key sectors such as electric vehicle drivetrains, wind turbines, energy transition technologies, robotics, and defence. Supply assumptions incorporate current global production levels and publicly announced future projects, offering a well-rounded view of the evolving market.
Meteoric’s financial modelling incorporates the current spot price carried forward and two sets of TREO forecast pricing scenarios to assess project resilience and value under varying market conditions.
Operating Costs
The robustness of PFS operating cost estimates relative to the Scoping Study have evolved significantly. Whereas parts of the Scoping Study relied on a certain assumptions and cost benchmarking, the PFS operating cost estimates are based on bottom-up, first principles methodology and vendor pricing based on a process flowsheet refined with extensive piloting.
The estimated costs were formulated by general area and are reflective of the effort required to process a nominal 6Mtpa (dry) of ore and nominal production of 13,500tpa of TREO.
Table 8: Operating Costs Breakdown
| Operating Costs (Real LOM) | Annual Cost (US$M) Year 1-5 |
Unit Cost (US$/kg TREO) Year 1-5 |
Annual Cost (US$M) LOM |
Unit Cost (US$/kg TREO) LOM |
|---|---|---|---|---|
| Mining | 31 | 2.54 | 39 | 2.89 |
| Processing | 79 | 6.37 | 94 | 6.89 |
| Total operating costs | 110 | 8.91 | 133 | 9.78 |
Total operating costs per kilogram of TREO varies, based on the grade of ore being mined and pit location. Over the first five years the cost of TREO is US$8.91/kg based on an average ore grade of 4,500ppm and US$9.78/kg LOM based on average ore grades of 3,700ppm.
Increases in operating cost estimates relative to the Scoping Study have arisen from increased waste ore due partially to the strip ratio rising from 0.21 to 0.38 in the PFS. Previous estimates excluded low recovery blocks and backfill costs which were underestimated in the Scoping Study. De-risking metallurgical testwork, together with an improved process flow, has reduced initial capital costs however additional flocculant requirements to settle and dewater spent clays have contributed to an increase in processing costs.
These revised estimates have arisen out of additional refinements to the mining and process flowsheet, significantly de-risking the project while continuing to outline a technically robust operating cost model.
The total operating cost for NdPr remains at a highly attractive level of US$21.80/kg net of DyTb by-product credits at consensus pricing. Total operating costs continue to confirm the Caldeira Project as a highly competitive project.
Meteoric Resources July 2025 Preliminary Feasibility Study
Page 15 of 41
==> picture [595 x 39] intentionally omitted <==
==> picture [595 x 39] intentionally omitted <==
Figure 7: Operating cost per kilogram of NdPr against Spot, Consensus & Forecast Pricing
==> picture [418 x 212] intentionally omitted <==
----- Start of picture text -----
$180
$160
$140
$120
$100
$80
$60
$40
$20
$-
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
Cash Costs $/ Kg NdPr (Net DyTb) $/Kg DyTb credits at Consensus
NdPr Spot Price NdPr Consensus
NdPr Forecast NdPr US$110
US$ / kg
----- End of picture text -----
Figure 8: Annual Operational Costs and Cash Surplus based on Consensus pricing
==> picture [422 x 267] intentionally omitted <==
----- Start of picture text -----
400
350
300
250
200
150
100
50
-
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
Operating Cost Fees & Royalties Sustaining Capital Taxes Paid Cash Surplus
Cost Breakdown in US$M
----- End of picture text -----
Mining costs include expenditure relating to the return of spent clay to pits or dump areas, while general and administrative ( G&A ) costs have been included within the overall processing costs. It is important to note that tax calculations involve complex variables that can only be accurately determined during actual operations. Consequently, the actual after-tax results may vary from these preliminary estimates.
Fees and royalties include contracted royalties paid for Mining Rights (4.75%), Federal Government Royalties (CFEM 2%), State Government minerals tax (US$0.39 per tonne) and fees payable to landholders (US$1 per tonne of ore extracted). Royalties are calculated based on the value of products extracted or sold and will vary depending on the market prices.
Meteoric Resources July 2025 Preliminary Feasibility Study
Page 16 of 41
==> picture [595 x 39] intentionally omitted <==
==> picture [595 x 39] intentionally omitted <==
Capital Costs
Capital costs reflect more detailed estimates based on the adoption of an agreed work breakdown structure that incorporates further detailed design and up-to-date budget quotes from reputable Brazilian contractors.
The estimated capital cost reflects the modifications to the processing plant to a 6Mtpa base case operation along with optimised process plant flowsheet mine schedule, for a total cost of US$443M inclusive of a ~25% contingency of US$86M. An addition to the cost estimates relative to the Scoping Study is the inclusion of a pre-operational mining fleet with an estimated cost of approximately US$12M. All additional capital requirements pertaining to this owner-operated mining fleet will be captured under sustaining capital.
The Caldeira Project retains a low capital intensity supportive of future project development and highly competitive against alternative global rare earth projects at this stage of development.
Table 9: Summary of Capital Expenditure
==> picture [367 x 95] intentionally omitted <==
----- Start of picture text -----
Cost Contingency Total
Description
(US$M) (US$M) (US$M)
Mining 24 3 28
Plant Direct 259 65 323
Plant Indirect 74 18 92
Total 357 86 443
----- End of picture text -----
Cashflows
Figure 8 below presents the Project's cumulative cash flow generation based on forecast, consensus, and spot pricing scenarios. The Project is projected to have a payback period of less than three years under both forecast and consensus pricing assumptions.
Figure 8: Cumulative Operational Cash Profile
==> picture [484 x 187] intentionally omitted <==
----- Start of picture text -----
4,000
3,500
3,000
2,500
2,000
1,500
1,000
500
-
-2 -1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
(500)
(1,000)
Spot Consensus Forecast
US$m
Net Operational cash position
----- End of picture text -----
Meteoric Resources July 2025 Preliminary Feasibility Study
Page 17 of 41
==> picture [595 x 39] intentionally omitted <==
==> picture [595 x 39] intentionally omitted <==
Sensitivity Analysis
A sensitivity analysis was performed for the Project, highlighting its resilience to variations in capital costs, operating costs, payability and rare earth pricing. The Project exhibits moderate sensitivity to fluctuations in operating costs and greater sensitivity to changes in the rare earth basket price.
Figure 9: Pre-Tax NPV Sensitivity Analysis at Consensus
==> picture [484 x 244] intentionally omitted <==
----- Start of picture text -----
$1,600
$1,200
$800
$400
–
-20% -10% 0% 10% 20%
Basket Price Opex Initial Capex Payability
NPV (USDM)
----- End of picture text -----
Funding
Meteoric is continuing to advance funding discussions with various groups to support the estimated US$443M (including US$86M contingency) pre-production capital requirements of the Project. The technical and economic fundamentals provide a strong platform for Meteoric to source traditional project financing. This view is supported by the fact that the United States Export-Import ( EXIM ) Bank which has already provided a US$250M letter of interest.
Typical project development financing would involve a combination of debt and equity. Meteoric has formed the view there is a reasonable basis to believe requisite future funding for Project development will be available when required. The grounds which support this reasonable basis include:
-
The Project is world-class by the nature of its simple mining and processing, high grades, low operating costs and capital intensity. The PFS release provides a strong platform for Meteoric to advance outcomes with potential financiers.
-
Global debt and equity finance availability for rare earths projects remains positive. Recent examples of significant funding being made available for rare earths exploration and development projects includes Arafura Rare Earths, Brazilian Rare Earths, Australian Strategic Materials and Iluka Resources.
-
Meteoric has also commenced early-stage discussions with a number of potential strategic partners which have interest in supporting the Project through off-take prepayments, equity investments or a combination thereof.
-
Meteoric has a current market capitalisation of approximately A$351M and no debt. The Company has a simple corporate and capital structure. Meteoric also owns 100% of the Project.
-
These are all factors expected to be highly attractive to potential financiers.
-
Collectively, the Meteoric Board and Management team hold extensive experience in financing resources industry projects and ASX-listed resources companies.
-
The publication of the PFS is expected to lead into more formal engagement with funding partners and downstream offtake partners together with the evaluation and appointment of our preferred debt
Meteoric Resources July 2025 Preliminary Feasibility Study
Page 18 of 41
==> picture [595 x 39] intentionally omitted <==
==> picture [595 x 39] intentionally omitted <==
and legal advisors.
- The Brazil federal government has strongly supported the Caldeira Project, making it one of six ventures under the BIP, and Meteoric was selected as a priority company to join the Brazilian government committee at the Futuro Minerals Forum in Saudi Arabia in January 2025.
Forward Work Program
The Meteoric Board has endorsed the PFS outcomes and approved the commencement of target workstreams to improve and optimise Project Development.
Activities to support the establishment of a 25kg/hour pilot plant in Poços de Caldas are underway. An operational readiness plan has been implemented, and long lead items have already ordered to ensure timely commissioning and execution.
The pilot plant aims to validate the technical, environmental, and commercial viability of the Caldeira Project by producing MREC for testwork and offtake agreements. It will also support stakeholder engagement, future ore testing, workforce training, and overall project de-risking ahead of full-scale development. The pilot plant also affords the opportunity to test downstream rare earth separation.
Work programs will further de-risk the Project’s cost estimates, metallurgical flowsheet and operating plan, while also providing a control budget for execution of the Project.
ASX Listing Rule 5.9 Disclosures – Caldeira Project
Material Assumptions and Outcomes
The PFS was completed with the following material assumptions:
-
Ore to be extracted through conventional excavation and trucked to the processing plant. No requirement for blasting.
-
Topsoil will be stockpiled in accessible piles near the mining area so it can be used for rehabilitation once a section of the pit has been backfilled and contoured to final landform.
-
The processing plant capacity will be 6.0Mtpa and the monthly requirement for material movement will on average 0.5M bank cubic metres (bcm) per month.
-
The Mine Plan has been designed to prioritise high-grade ore with excellent metallurgical recoveries. This approach will accelerate the payback period and deliver higher financial returns over the life of the Project. It will also allow expansion opportunities to be funded through operational cash flow.
-
Overall metallurgical recovery is ~55% TREO. Individual oxide elemental recoveries have been applied.
-
These recovery factors have been statistically validated against randomised diagnostic leach tests conducted on a wide range of ore samples, confirming their reliability across the mine plan.
-
Average mining costs of US$2.54/kg TREO are based on the first five years of operations using a fully owned mining fleet.
-
Mining economics are based on a cash flow model applied to individual mining blocks. Blocks are included in the ore reserve where Revenue minus cost >$0. Revenue is based on individual REO values published by the Shanghai Metal Market multiplied by individual oxide recoveries. These values reflect gross spot prices, inclusive of VAT. A payability factor of 70% is applied to the separated oxide prices to determine the final MREC pricing. Costs include mining and processing costs.
-
The economic model is denominated in US dollars ( USD ), with local cost estimates converted from Brazilian Reals ( BRL ) using an assumed exchange rate of 6.0 BRL/USD. The exchange rate assumption is based on December 2024 rates.
-
Transportation charges for MREC to Santos Port, Brazil (CIF) are estimated from budget pricing provided by logistics contractors. Transport charges ex-Brazil to the customer have been reflected within the estimated payability factor.
Meteoric Resources July 2025 Preliminary Feasibility Study
Page 19 of 41
==> picture [595 x 39] intentionally omitted <==
==> picture [595 x 39] intentionally omitted <==
-
Treatment and refining charges are not directly applicable, as the product is an intermediate feedstock for separation facilities rather than a fully refined REO product.
-
No smelter penalties are expected, as the MREC has been confirmed to meet industry purity requirements through ANSTO metallurgical test work.
-
Mining activities will initially commence at the Capão do Mel ( CDM ) deposit, which is located closest to the planned processing plant site, before expanding to the Figueira ( FIG ), Barra do Pacu ( BDP ) and Soberbo ( SOB ) licences.
-
Total ore mined by deposit is depicted in Figure 4 and key production outcomes and assumptions are set out in Table 2 above.
Criteria for Classification
The Mineral Reserve is classified as a Probable Ore Reserve only using the guidelines of the JORC Code (2012 Edition). Measured and Indicated have been converted to Probable only. The Ore Reserve consists of 100% Probable Ore Reserves.
The Competent Person is satisfied that the stated Ore Reserve classification reflects the outcome of technical and economic studies. The confidence in the Ore Reserves is reflected by the classifications shown above. In general, the project’s geology is well understood and confidence in the Mineral Resource interpretation is good.
Mining Method & Assumptions
The proposed mining method and assumptions are set out above on page 10.
Processing Method and Assumptions
The processing method and assumptions are set out above on page 12.
Basis for Cut-off Grades
The economic cut-off grades for the project were determined on a block by block value basis and are determined by calculating net revenue from recovered REO less processing and selling costs on a block-byblock (diluted) basis. Only clay material has been included. There will be variations in the equivalent TREO cut-off grade as the quantity of each oxide element varies between the resource blocks as follows:
==> picture [221 x 138] intentionally omitted <==
----- Start of picture text -----
Resource Cut-Off (TREO ppm)
Deposit Lowest Highest
CDM 1,895 4,310
FIG 2,130 3,872
SOB 2,047 2,860
BDP 2,000 4,500
----- End of picture text -----
Estimated operating costs for Mining are shown below.
| Operating Costs (Real LOM) | Annual Cost (US$M) Year 1-5 |
Unit Cost (US$/kg TREO) Year 1-5 |
Annual Cost (US$M) |
Unit Cost (US$/kg TREO) |
|---|---|---|---|---|
| Mining | 31 | 2.54 | 39 | 2.89 |
| Processing | 79 | 6.37 | 94 | 6.89 |
| Total operating costs | 110 | 8.91 | 133 | 9.78 |
Costs are inclusive of the processing of lower grade stockpiles from year 6.
Estimation Methodology
The study carried out as part of the Caldeira Project’s maiden Ore Reserve is to a Pre-Feasibility Study level. The relative accuracy of the estimate is reflected in the reporting of the Ore Reserve as per the guidelines regarding modifying factors, study levels and Competent Persons contained in the JORC Code (2012). These
Meteoric Resources July 2025 Preliminary Feasibility Study
Page 20 of 41
==> picture [595 x 39] intentionally omitted <==
==> picture [595 x 39] intentionally omitted <==
Ore Reserves represent 27% of the currently defined Measured and Indicated MRE for these four deposits. The Ore Reserves for the Project have been estimated as at 24 April 2025 in accordance with the JORC Code.
Material Modifying Factors
The following Modifying Factors were considered in relation to the development of the Caldeira Ore Reserve:
Existing Infrastructure and Site Accessibility
The Caldeira Project is strategically located in Caldas, Minas Gerais, a well-established mining and industrial region with significant infrastructure.
-
The PFS area which includes: Capao do Mel, Soberbo, Figueira, and Barra do Pacu licenses, spans 2,369 hectares (23.7km²), providing ample land for mine development, processing infrastructure, and future expansions. The regions of Caldas and Poços de Caldas are home to existing bauxite, alumina, clay, and chemical processing plants, ensuring access to an experienced mining and industrial workforce.
-
The proposed pits and processing facility are well-connected via a network of paved roads and private gravel roads, facilitating efficient ore transport.
Power Supply
-
The Caldeira Project will utilise 100% renewable energy from hydroelectric, solar, and wind power available through the existing grid infrastructure in Minas Gerais.
-
The project is located within 3km of high-capacity power transmission lines, ensuring a stable and reliable energy supply for mining and processing operations.
Water Supply and Management
The Caldeira Project will incorporate advanced water recycling technologies, including ultrafiltration and reverse osmosis (RO) systems, to minimise freshwater consumption and ensure minimal industrial effluent discharge.
-
The ore beneficiation process is designed for high water efficiency, with >75% of process water recirculated within the plant.
-
Additional hydrogeological studies are planned to optimise water sourcing and management strategies further.
Ore Transport and Logistics
-
Ore will be transported by trucks via internal haul roads (dominantly), existing gazetted roads, and private gravel roads to the central processing facility at Capao do Mel.
-
The Project benefits from proximity to major highways, facilitating the transport of MREC products to export hubs.
-
Brazil’s well-developed port infrastructure, including Santos (São Paulo), provides efficient access to global markets.
Labour and Accommodation
-
Caldas municipality (~14,000 people) and the neighbouring city of Poços de Caldas (~175,000 people) have a long history of mining and possess a large, skilled workforce which reduces the need to attract significant numbers from outside the region. Additionally, the Company has started supporting the development of relevant skills in the Caldas population.
-
No on-site accommodation is required, as the city of Caldas along with surrounding cities including Poços de Caldas and Andrades provides sufficient housing, amenities, and services for workers.
-
The project is expected to create significant employment opportunities, benefiting the local economy of Caldas (and Andrades and Pocos de Caldas) and strengthening community support.
Future Considerations
- The existing infrastructure significantly de-risks the Project, reducing capital expenditures for building new roads, power lines, or water supply networks.
Meteoric Resources July 2025 Preliminary Feasibility Study
Page 21 of 41
==> picture [595 x 39] intentionally omitted <==
==> picture [595 x 39] intentionally omitted <==
-
The processing facility location was carefully selected to ensure minimal environmental impact and logistical efficiency to the deposits.
-
Additional investment in site infrastructure will focus on enhancing water management, optimising ore transport logistics, and expanding processing capacity in future project phases.
Environmental
- Brazil has a clearly defined three stage Environmental permitting process for Class 6 mineral projects. Meteoric is progressing through the permitting process which aligns with the current development timeline. The Project is currently in the Preliminary License (LP) phase in satisfying right to mine requirements in Brazil. Further information in relation to the environmental permitting process is set out on page 14 above.
ASX Listing Rule 5.16 Requirements
The material assumptions that the production target for the Project is based on are detailed in the body of this announcement and the Executive Summary which is included in Appendix 1.
The production target is based on 89% Measured & Indicated Resources and 11% Inferred Mineral Resources that have been prepared by Competent Persons in accordance with the requirements of the JORC Code (2012). Refer also to the Cautionary Statement regarding Inferred Mineral Resources on page 1.
This release has been approved by the Board of Meteoric Resources NL.
For further information, please contact:
Stuart Gale
Michael Vaughan
Managing Director and CEO Investor and Media Relations
Meteoric Resources NL Fivemark E [email protected] E [email protected] T +61 08 6166 9112 T +61 422 602 720
Meteoric Resources July 2025 Preliminary Feasibility Study
Page 22 of 41
==> picture [596 x 102] intentionally omitted <==
APPENDIX 1 –
CALDEIRA RARE EARTHS PRE-FEASIBILITY STUDY
EXECUTIVE SUMMARY July 2025
Studies Manager:
==> picture [596 x 102] intentionally omitted <==
==> picture [596 x 102] intentionally omitted <==
==> picture [596 x 100] intentionally omitted <==
==> picture [76 x 57] intentionally omitted <==
Table of Contents
Introduction .......................................................................................................................................................4 Geology and Resource.....................................................................................................................................5 Exploration ........................................................................................................................................................6 Mining ................................................................................................................................................................8 Optimised Resources ......................................................................................................................................9 Geotechnical Parameters ................................................................................................................................9 Net Return .................................................................................................................................................... 10 Pit Designs ................................................................................................................................................... 10 Mining Method .............................................................................................................................................. 16 Mining and Processing Schedules ............................................................................................................... 16 Life of Mine (LOM) Schedule ....................................................................................................................... 17 Metallurgy ....................................................................................................................................................... 20 Testwork Background and Objectives ......................................................................................................... 20 Composite Overview .................................................................................................................................... 20 Mineralogy and Element Deportment .......................................................................................................... 20 Desorption Testing and Reagent Optimisation ............................................................................................ 21 Impurity Removal ......................................................................................................................................... 21 MREC Precipitation and Product Quality ..................................................................................................... 21 Processing ..................................................................................................................................................... 22 Process Overview ........................................................................................................................................ 22 Infrastructure and Site Access ..................................................................................................................... 25 Local Area .................................................................................................................................................... 25 Existing Infrastructure .................................................................................................................................. 26 Government Support .................................................................................................................................... 27 Environmental and Community ................................................................................................................... 28 Background .................................................................................................................................................. 28 Tenure – Mineral Rights ............................................................................................................................... 29 Brazil Legal Framework ............................................................................................................................... 30 Ownership of Mineral Resources ................................................................................................................. 30 Mineral rights & security of tenure ............................................................................................................... 30 Right to mine requirements .......................................................................................................................... 30 Current Status .............................................................................................................................................. 31
Page | 2 of 49
==> picture [76 x 57] intentionally omitted <==
Surface Land Access & Ownership ............................................................................................................. 31 Environmental Approvals ............................................................................................................................. 32 Stage 1 – Preliminary Licence (LP) .......................................................................................................... 32 Environmental Impact Statement .......................................................................................................... 33 Stage 2 – Installation Licence (LI) ............................................................................................................ 34 Stage 3 – Operating Licence (LO) ............................................................................................................ 34 Expansion Licence ....................................................................................................................................... 34 Environmental Compensation ...................................................................................................................... 34 Atlantic Forest Biome ............................................................................................................................... 35 Endangered Species ................................................................................................................................ 35 Environmental Preservation – APP .......................................................................................................... 35 Mineral Compensation ............................................................................................................................. 35 Legal Reserve .......................................................................................................................................... 35 Liability ......................................................................................................................................................... 36 Implementation Plan ...................................................................................................................................... 36 Project Development .................................................................................................................................... 36 Capital Cost Estimate .................................................................................................................................... 37 Basis of Estimate ......................................................................................................................................... 37 CAPEX Results ............................................................................................................................................ 37 Operating Cost Estimate ............................................................................................................................... 38 Reagents and Consumables Costs ............................................................................................................. 40 Operational Readiness .................................................................................................................................. 40 Financial and Commercial Analysis ............................................................................................................ 41 Pricing Assumptions and Forecast Methodology ...................................................................................... 41 Financial Summary ........................................................................................................................................ 43 Financial Model Metrics ............................................................................................................................ 43 Operating Costs, Royalties, Sustaining Capital and Taxes...................................................................... 46 Cashflows ................................................................................................................................................. 47 Capital Expenditure .................................................................................................................................. 48 Sensitivity Analysis ................................................................................................................................... 48
Page | 3 of 49
==> picture [76 x 57] intentionally omitted <==
Executive Summary
==> picture [489 x 237] intentionally omitted <==
Figure 1: Schematic drawing of Processing Plant Layout at Capao do Mel.
Introduction
Meteoric Resources NL ( Meteoric, or Company ) is an ASX-listed rare earth exploration and development company and the owner of the Caldeira Project ( Project or Caldeira Project ) in the Brazilian state of Minas Gerais. The Project is located between the cities of Caldas, Poços de Caldas and Andrades, in the southern region of Minas Gerais.
A Scoping Study completed in May 2024, then subsequently updated in October 2024, recommended the completion of a Pre-Feasibility Study ( PFS ) into the Project.
The Project is being developed to mine and process rare earth rich ionic clays at a rate of 6 million tonnes per annum ( Mtpa ) to produce a mixed rare earth carbonate ( MREC ). Since acquiring the Caldeira Project in March 2023, Meteoric has undertaken an extensive program of exploration, resource development drilling, resource estimation, metallurgical characterisation of ore, process design testwork, material handling study, mine scheduling and design, and other related technical studies. This work has significantly enhanced the Company’s understanding of the Project’s scale, quality and strategic potential. With its long mine life and cost advantages, the Caldeira Project has the potential to disrupt the global rare earth industry by emerging as a major low-cost supplier of rare earth element ( REE ) products.
While the Project is currently modelled with a 20-year mine life, the scale of the existing Mineral Resource base has the potential to support a significantly extended operational life, subject to the receipt of all necessary additional approvals.
Importantly, the Project’s Mineral Resource contains higher confidence classification of Measured and Indicated Resource of 666Mt at 2,685ppm TREO. This places the Caldeira Project as one of the highestgrade ionic absorption clay rare earths deposits in the world.
The ore body is shallow, commencing at surface in some areas, and consists of free dig clays with a low mining strip ratio. Combined with high grades, excellent REE recoveries, and a simple ammonium sulfate ( AMSUL ) wash flowsheet to treat the ionic clays, results in an inherently low operating cost compared to hard rock REE deposits. This flowsheet has been validated by extensive testwork carried out at the Australian Nuclear Science and Technology Organisation ( ANSTO ).
Page | 4 of 49
==> picture [76 x 57] intentionally omitted <==
==> picture [456 x 456] intentionally omitted <==
Figure 2: Caldeira Project Licences (four southern licenses included in the PFS highlighted in red).
Geology and Resource
The key geological feature of the Project area is the Mesozoic Poços de Caldas Alkaline Complex ( PCAC ) which was intruded into the metamorphosed Paleoproterozoic rocks of the Brazilian shield. The intrusion of the PCAC and the associated volcanic equivalents were emplaced approximately 80 million years ago. The event is related to the final stages of the breakup of the Gondwana Continent and the formation of the Atlantic Ocean during the late Cretaceous. Initial volcanism is followed by collapse, leading to the formation of a major geomorphologic feature, comprising a large circular volcanic/intrusive edifice of over 800km[2] that rises approximately 600-800m above the metamorphic basement.
The main rock types found are intrusive and volcanic alkaline rocks of the nepheline syenite system, comprising phonolites and foidolites (syenites). High rainfalls and the unique potassium enriched chemistry of the intrusives that lack any primary quartz has led to the formation of a deep regolith profile. Within the regolith profile, clays and partially weathered rock (transition) have been identified up to 200m below the current land surface.
Page | 5 of 49
==> picture [76 x 57] intentionally omitted <==
The geological interpretation of Meteoric’s exploration drilling subdivides the regolith into three main zones:
-
A soil layer 0 – 2m thick;
-
A clay zone 5 – 70m thick comprising illite, montmorillonite, halloysite and gibbsite as the main clay species; and
-
A transition zone defined by the appearance of visible weathered rock fragments which gradually increase with proximity to fresh rock in a zone that can vary between 5 – 120m thick.
Primary uranium and REE deposits have been known within the area since the 1950s and are characterised by late stage sulphidic breccias containing uranium oxides and bastnaesite with accessory monazite and xenotime as the major REE ore minerals. However, away from the higher-grade U-REE deposits, the dominant REE mineral in the source rock (syenite) beneath the clay zone is bastnaesite, a major source of REE worldwide. Bastnaesite is the primary REE mineral at well-known deposits such as Mountain Pass (USA) and Bayan Obo (Asia). Bastnaesite is a REE carbonate-fluoride mineral (REE)CO3F which has very low levels of uranium and thorium in its mineralogical structure. Concentration of REE within ion adsorption deposits has been proposed to be a dominantly supergene process, where easily degradable REE-minerals break down and release REE that are then adsorbed onto clay mineral surfaces.
The target REE mineralisation for Meteoric occurs below the soil layer within the clay zone (Table 1). This is where REE grades and leaching recoveries are highest due to the ionic adsorption nature of the bonds between the REE and the clay minerals. The target ionic clay REE mineralisation (defined by >40% recovery of REE using a standard AMSUL wash at pH 4) is confined to the soil, clay, and weakly weathered transition layers. A total of 65% to 90% of these highly weathered zones are composed of minerals in a clay fraction (granulometry <2µm). Mineralisation ranges from 2ppm to 56,000ppm REE. Mineralisation is present throughout the vertical profile, but it is not distributed homogenously.
Table 1: Depth of Mineralised Clays at key Caldeira Project deposits.
==> picture [423 x 115] intentionally omitted <==
----- Start of picture text -----
Tenement Mineralised Clay Depth – Variable (m) Average Depth (m)
Capão do Mel 4 - 50 23.4
Figueira 4 - 62.5 28.2
Soberbo 1.5 - 77.4 16.9
Barra do Pacu 8 - 50 29.2
----- End of picture text -----
Exploration
Since signing an agreement to acquire the Caldeira Project in December 2022, Meteoric has completed an extensive amount of work including:
-
Check assaying of historic samples;
-
Soil sampling;
-
Hyperspectral analysis of clays;
-
Geophysical surveys;
-
LIDAR topography surveys;
-
3D geologic modelling;
-
Aircore and diamond drilling; and
-
Resource estimation.
Page | 6 of 49
==> picture [76 x 57] intentionally omitted <==
In December 2022, a resampling program of auger drill holes from JOGMEC’s 2016-2019 drilling program was undertaken. A total of 398 samples were submitted to ALS laboratory in Belo Horizonte (MG), being a combination of 296 pulp samples plus 102 re-samples of coarse reject from the auger drilling. There was no statistically significant bias between the original results and check assays, with >95% of check assays within 10% of original result. This excellent correlation provides confidence in the previous work.
Meteoric completed 93 diamond drill holes between March 2023 and February 2024 for 4,186m. The objective of the program was to:
-
Test the tenor and depth of clay mineralisation below the highest-grade anomalies defined in regional soil sampling program of JOGMEC (described above),
-
In-fill drill and test the depth of clay mineralisation on six licenses where JOGMEC had defined nonJORC resources, to enable a maiden JORC Resource Estimate, and
-
Collect samples for metallurgical characterization testwork of the mineralisation.
Meteoric purchased its own multi-purpose drill rig in May 2023. The rig was configured to drill Aircore ( AC ) holes. Since commissioning in August 2023 the Company has drilled >57,000m of AC across eight licenses, producing ~31,000 samples for assay (Table 2).
Table 2: Drilling statistics for Resource areas.
==> picture [485 x 206] intentionally omitted <==
----- Start of picture text -----
Auger Aircore Diamond
Target Samples
Holes Metres Holes Metres Holes Metres
Capão do Mel 337 3,461 492 12,397 14 428 10,726
Soberbo 323 2,987 323 5,514 14 374 6,483
Figueira 92 950 292 8,587 9 582 6,755
Barra do Pacú - - 224 6,540 7 327 3,612
Cupim Vermelho Norte 185 1,849 430 12,077 5 148 7,176
Dona Maria 1 316 3,160 271 6,144 7 180 6,527
Dona Maria 2 143 1,303 170 3,687 4 86 3,254
----- End of picture text -----
After only two years of drilling the Company has defined a global Mineral Resource of 1.5Bt at 2,359ppm TREO at a 1,000ppm cut-off grade, including Magnetic Rare Earths Oxide ( MREO ) grades of 526ppm (22.3% of the TREO basket). Measured and Indicated Mineral Resources total 666Mt at 2,685ppm TREO and 605ppm MREO (22.3% of the TREO basket).
A subset of the global Mineral Resource from four southern licences – Capão do Mel ( CDM ), Barra do Pacu ( BDP ), Soberbo ( SOB ) and Figueira ( FIG ) – were included in the PFS and are shown in Table 3. This forms the basis of the maiden Ore Reserve for the Caldeira Project.
Page | 7 of 49
==> picture [76 x 57] intentionally omitted <==
Table 3: Mineral Resource Estimate for licences considered in PFS.
==> picture [507 x 452] intentionally omitted <==
----- Start of picture text -----
Licence JORC Material Tonnes TREO Pr6O11 Nd2O3 Tb4O7 Dy2O3 MREO MREO
Category Type Mt ppm ppm ppm ppm ppm ppm /TREO
Capão do Mel Measured Clay 11 3,888 222 586 6 28 842 21.7%
Total Measured 11 3,888 222 586 6 28 842 21.7%
Capão do Mel Indicated Clay 74 2,908 163 449 5 23 640 22.0%
Barra do Pacu Indicated Clay 77 2,917 143 376 4 21 545 18.7%
Soberbo Indicated Clay 86 2,730 165 476 5 23 669 24.5%
Figueira Indicated Clay 138 2,844 145 403 5 28 582 20.5%
Total Indicated 374 2,846 153 423 5 25 606 21.3%
Total Measured + Indicated 385 2,875 155 428 5 25 613 21.3%
Capão do Mel Inferred Clay 32 1,791 79 207 2 13 302 16.9%
Barra do Pacu Inferred Clay 190 2,153 112 296 3 18 429 19.9%
Soberbo Inferred Clay 89 2,713 167 478 5 24 675 24.9%
Figueira Inferred Clay 9 3,105 139 379 5 28 551 17.7%
Capão do Mel Inferred Transition 25 1,752 86 239 3 14 341 19.5%
Barra do Pacu Inferred Transition 122 1,837 95 253 3 15 355 19.9%
Soberbo Inferred Transition 54 2,207 138 395 4 20 558 25.3%
Figueira Inferred Transition 24 2,174 115 328 4 21 468 21.5%
Total Inferred 546 2,120 113 307 3 18 441 20.8%
Measured +
Total 931 2,432 130 357 4 21 512 21.0%
Indicated + Inferred
----- End of picture text -----
Mining
Project Ore Reserves of 103Mt at 4,091ppm TREO are estimated at 24 April 2025, in accordance with the JORC Code (2012). Meteoric determined suitable modifying factors to apply in the Ore Reserve estimation process following a review of site data including environmental and metallurgical characteristics, the available Resource estimate, and flow sheet and mine design studies completed as part of this PFS. The modifying factors have been applied exclusively to Measured and Indicated Resources at CDM, BDP, SOB, and FIG. Measured and Indicated Resource have been converted to Probable Reserves considering confidence levels in geotechnical, material handling and some metallurgical parameters.
Page | 8 of 49
==> picture [76 x 57] intentionally omitted <==
The Proved and Probable JORC Ore Reserves estimates for the Project are summarised in Table 4.
Table 4: Caldeira Ore Reserve.
==> picture [483 x 364] intentionally omitted <==
----- Start of picture text -----
Tonnes TREO Pr6O11 Nd2O3 Cont. REO
Classification
(Mt) ppm ppm ppm kt
Capão do Mel
Proved - - - - -
Probable 37.1 3,925 243 667 146
Total 37.1 3,925 243 667 146
Figueira
Proved - - - - -
Probable 16.1 4,951 450 938 75
Total 16.1 4,951 450 938 75
Soberbo
Proved - - - - -
Probable 24.3 3,735 256 736 91
Total 24.3 3,735 256 736 91
Barra do Pacu
Proved - - - - -
Probable 25.5 4,130 234 621 105
Total 25.5 4,130 234 621 105
Total Caldeira Project
Proved - - - - -
Probable 103.0 4,091 276 714 416
Total 103.0 4,091 276 714 416
----- End of picture text -----
Notes to the Ore Reserve:
1. Ore Reserve estimates are not precise calculations, being dependent on the underlying Mineral Resource and based on limited information in respect to modifying factors. The totals contained in the above table have been rounded to reflect the relative uncertainty of the estimate.
2. Only clay material with a resource classification of Measured or Indicated have been included.
3. Measured and Indicated have been converted to Probable only.
4. Ore Reserves are reported in accordance with the Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves (The Joint Ore Reserves Committee Code – JORC 2012 Edition).
Optimised Resources
Initially, only Measured and Indicated resource classifications were used for optimisation and final pit design of the four deposits. An additional optimisation was done on Inferred Resources at BDP to increase the Mine Life beyond 20 years.
Geotechnical Parameters
Geotechnical inputs for pit optimisation and design remain outstanding at the time of this report. The overall slope angle used in the optimisation was 30º based on observations of a nearby mine operation, and the value Brazilian Mining consultant BNA provided for the Scoping Study.
Page | 9 of 49
==> picture [76 x 57] intentionally omitted <==
Net Return
The optimisations were run using a cashflow methodology. A block will be selected to be processed when:
(Total REO x Recovery x Basket Price) – Ore costs > $0.
This means there will be variations in the TREO cut-off grade within the mining model as the grade of each oxide element varies in a block.
Table 5 shows the range of TREO grades that are close to Net Value = $0.
Table 5: TREO Cut-Off Grades by Deposit (variable).
| Cut-Off | (TREO ppm) | |
|---|---|---|
| Deposit | Lowest | Highest |
| CDM FIG SOB |
1,895 2,130 2,047 |
4,310 3,872 2,860 |
| BDP | 2,000 | 4,500 |
Pit Designs
From the selected shells of each stage of development and final optimisation shells, pit designs were completed for the four deposits using the parameters contained in Table 6.
Table 6: Pit Design Parameters.
==> picture [278 x 162] intentionally omitted <==
----- Start of picture text -----
Item Value
Inter-ramp Angle 35 degrees
Default Berm 3m width (every 5m vertical)
Default Batter Angle 50 degrees
Bench Height 5m
Ramp Width 10m
Ramp Gradient 1:10
----- End of picture text -----
Total pit inventory of Project resources by Resource Classification is shown in Table 7.
Page | 10 of 49
==> picture [76 x 57] intentionally omitted <==
Table 7: Resource Inventory within the final Pit Designs by Resource Classification.
==> picture [485 x 205] intentionally omitted <==
----- Start of picture text -----
Caldeira Project
Measured Indicated Inferred Waste Total
Cont.
TREO Cont. TREO Cont. TREO
Deposit Mt Mt Mt REO Mt Mt
(ppm) REO (kt) (ppm) REO (kt) (ppm)
(kt)
CDM 7 4,682 32 30 3,756 114 - - - 23 60
FIG - - - 16 4,951 80 - - - 11 27
SOB - - - 24 3,735 91 - - - 11 36
BDP - - - 25 4,130 105 14 3,628 51 16 55
TOTAL 7 4,682 32 96 4,050 390 14 3,628 51 61 178
----- End of picture text -----
Figures 3 - 6 show stages and final pit designs of the four deposits. For clarity, as ramp access to the larger pits will change over time the ramps are not shown.
Page | 11 of 49
==> picture [75 x 57] intentionally omitted <==
==> picture [730 x 157] intentionally omitted <==
==> picture [730 x 157] intentionally omitted <==
==> picture [730 x 79] intentionally omitted <==
Figure 3: CDM staged and final pit designs.
Page | 12 of 49
==> picture [75 x 57] intentionally omitted <==
==> picture [735 x 148] intentionally omitted <==
==> picture [735 x 223] intentionally omitted <==
----- Start of picture text -----
N
----- End of picture text -----
Figure 4: Figueira staged and final pit designs (image has been rotated from North/South to West/East).
Page | 13 of 49
==> picture [76 x 57] intentionally omitted <==
==> picture [483 x 219] intentionally omitted <==
==> picture [483 x 219] intentionally omitted <==
==> picture [483 x 110] intentionally omitted <==
Figure 5: Soberbo final pit designs.
Page | 14 of 49
==> picture [76 x 57] intentionally omitted <==
==> picture [480 x 239] intentionally omitted <==
==> picture [480 x 240] intentionally omitted <==
==> picture [480 x 120] intentionally omitted <==
Figure 6: BDP staged and final Pit Designs (designs based on inferred inventory are highlighted in yellow)
Page | 15 of 49
==> picture [76 x 57] intentionally omitted <==
Mining Method
Mining activities will commence in CDM, which is located closest to the process plant, and then expand to include FIG, SOB and BDP.
The proposed mining activities in all four areas will be conducted in the form of a conventional open pit load and haul operation. Drill and blast activities are not anticipated as the material to be mined is free-diggable soil and clays.
Ore will be hauled direct from the CDM and BDP pit to the process plant located on the western end of the CDM tenement. Once mining commences in FIG and SOB, ore will be hauled to the process plant using dedicated haul roads to be constructed by Meteoric.
Waste material will be used for construction purposes (roads, bunds, etc) with the remainder to be stored using ex-pit and predominantly in-pit dumps. The plan is to only use ex-pit dumps in the first two years of mining before backfilling can commence in mined out sections of the open pits, using waste and spent clay rejects from the plant. Topsoil will be stockpiled in accessible piles near the mining area for rehabilitation use once a section of the pit has been backfilled and contoured to final landform.
The process plant capacity will be 6.0Mtpa and the monthly requirement for material movement will be on average 0.5M BCM per month.
Spent clays from the process plant will initially be stored in ex-pit storage facilities until sufficient space is available in the open pits for the material to be returned and deposited in accordance with the Project’s final landform design.
Mining and Processing Schedules
With the completion of the staged and final pit designs a detailed life-of-mine ( LOM ) yearly production schedule was completed using MineSched software with the following assumptions:
-
Plant throughput of 6.0Mtpa with a ramp-up of 3.0Mt in Year 1 and 5.0Mt in Year 2.
-
Targeted recovered oxide output of 13,500tpa in the first 10 years.
-
Plant feed has been broken down into TREO grade bins (all >$0 net value) to enable priority on grade bins to enable blending and smooth plant feed:
-
Low grade: <2,500ppm
-
Medium grade: 2,500ppm to 3,500ppm
-
High grade: 3,500ppm to 4,500ppm
-
Very high grade: >4,500ppm
-
-
Transport of ore from FIG to the CDM plant site constrained to 1.0Mtpa due to local road access restrictions. Minimum mining block size (x, y, z) = 10m x 10m x 5m.
-
Bench height = 5m.
-
Terraced mining with vertical lag distances of up to 100m.
Page | 16 of 49
==> picture [76 x 57] intentionally omitted <==
Life of Mine (LOM) Schedule
LOM mining and production schedule features are documented in Table 8 below.
Table 8: LOM Mining and Production Statistics.
==> picture [483 x 432] intentionally omitted <==
----- Start of picture text -----
LOM Details
Mine Life 20 years
Total material mined 177MT
Total ore to be mined 117Mt @ 4,036ppm TREO (high grade)
12Mt @ 2,000ppm TREO (low grade)
Overall Strip Ratio 0.38:1
Contained REO mined 742kt (includes 51kt Inferred)
Total Plant Feed 129Mt at 3,701ppm TREO over 20 years
Recovered REO output 272kt
LOM: average TREO recovery 55%
Overall Nd-Pr to TREO in 0.31:1
Process Plant product
Mining Activities Year 1 – CDM
Year 3 – FIG
Year 4 – BDP
Year 12 – SOB
Mining total movement 9.0Mtpa (Average)
ROM stockpiles Will be used to manage grade blending as well as maintaining plant feed rates
during the wet season. A nominal 800,000t stockpile is located at CDM for this
purpose.
From Year 6 onwards an additional ~800ktpa of low grade material initially mined
as waste and stockpiled is processed by the plant. The above figures are inclusive
of the processing of stockpiled low grade material.
----- End of picture text -----
Page | 17 of 49
==> picture [76 x 57] intentionally omitted <==
==> picture [484 x 253] intentionally omitted <==
----- Start of picture text -----
Total Mined (ore + waste) (t)
12.0Mt
FIG CDM SOB BDP
10.0Mt
8.0Mt
6.0Mt
4.0Mt
2.0Mt
0.0Mt
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
----- End of picture text -----
Figure 7: Total material mined (ore + waste).
==> picture [484 x 268] intentionally omitted <==
----- Start of picture text -----
Total Ore Mined (t)
8.0Mt
FIG CDM SOB BDP
7.0Mt
6.0Mt
5.0Mt
4.0Mt
3.0Mt
2.0Mt
1.0Mt
0.0Mt
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
----- End of picture text -----
Figure 8: Total ore tonnes mined by deposit.
Page | 18 of 49
==> picture [76 x 57] intentionally omitted <==
==> picture [484 x 253] intentionally omitted <==
----- Start of picture text -----
Plant Feed (t)
7.0Mt
FIG CDM SOB BDP
6.0Mt
5.0Mt
4.0Mt
3.0Mt
2.0Mt
1.0Mt
0.0Mt
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
----- End of picture text -----
Figure 9: Processing plant - annual feed tonnes by deposit.
==> picture [484 x 271] intentionally omitted <==
----- Start of picture text -----
Recovered TREO (t) & Feed Grade (ppm)
16,000 7,000
15,000
14,000
6,000
13,000
12,000
5,000
11,000
10,000
9,000 4,000
8,000
7,000 3,000
6,000
5,000
2,000
4,000
3,000
1,000
2,000
1,000
- -
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
Metal RecoveredRecovered TREO(t) Feed Grade
Recovered TREO (t) Feed Grade (ppm)
----- End of picture text -----
Figure 10: Recovered REO tonnes by year.
Page | 19 of 49
==> picture [76 x 57] intentionally omitted <==
Metallurgy
Testwork Background and Objectives
The Project is characterised by shallow, weathered clay-hosted REE mineralisation amenable to simple surface mining and ambient temperature leaching. Given the nature of ionic clays, the REE are loosely adsorbed onto clay minerals and can be desorbed under weakly acidic (pH 4.5 - 5) conditions, ambient temperature and pressure with rapid desorption (<30 minutes) kinetics with an AMSUL lixiviant.
The primary objective of the ANSTO designed testwork program was to develop a processing route that maximises recovery of magnet REE while producing a marketable MREC product with acceptable impurity levels. Particular emphasis was placed on:
-
Desorption efficiency under varied reagent regimes
-
Impurity precipitation (especially Al, Fe, U, and Zn)
-
Pilot-scale validation and refining of operational parameters
-
Characterisation of metallurgical variability across prospects
A systematic program of mineralogical, chemical, and metallurgical testwork was undertaken to characterise mineralisation, focusing initially on the CDM prospect and subsequently expanding to other tenements including FIG, Dona Maria 1 and 2, Cupim Vermelho Norte ( CVN ), BDP and SOB.
Composite Overview
A total of four composites from diamond core were generated for the PFS, with the table below summarising recoveries:
Table 9: Summary of Composite Recoveries.
| Tenement | Result |
|---|---|
| CDM | Initial focus of development and pilot-scale tests 72% MREO recovery to MREC |
| FIG | High REE grades 71% Magnetic REO recovery to MREC |
| SOB | 67% Magnetic REO recovery to MREC |
| BDP | Contiguous to CDM southern boundary 72% MREO recovery to MREC |
A continuous pilot-scale program was conducted at ANSTO using a 2.5-tonne sample representative of the CDM starter pit. The campaign successfully validated and de-risked the process flowsheet, achieving MREO recovery of 69% and producing a high-quality MREC product with less than 2% impurities.
Additional pilot testing is scheduled to take place in Brazil during the December quarter of 2025.
Mineralogy and Element Deportment
Detailed QEMSCAN and XRD work revealed that clays constituted ~27% of CDM and 25–30% of SOB and FIG samples. Kaolinite is the major clay mineral in the samples, K-feldspar ~33% and muscovite ~28% are also major mineral phases. Minor concentrations of smectites, biotite/annite and Fe-oxide/hydroxide were also
Page | 20 of 49
==> picture [76 x 57] intentionally omitted <==
detected along with trace concentrations of Mn-oxide/hydroxide, organic material, rutile/anatase, albite, quartz, zircon, ilmenite, monazite, cerianite, cerite and crandallite group minerals. The degree of weathering and clay composition had a direct correlation with REE recoverability.
In addition, about 80% of La and Nd from CDM were inferred to be desorpable based on assay-to-QEMSCAN reconciliation.
Desorption Testing and Reagent Optimisation
Desorption testing was the cornerstone of the process development work, given the ionic clay nature of the Caldeira Project deposits. The objective was to determine the most effective reagent systems and operating conditions to liberate loosely bound REE from the clay surface, without requiring high-temperature, or highly acidic treatment. The testing program was designed to evaluate various reagent types, concentrations, pH targets, solid-liquid ratios, and desorption durations, primarily using the CDM composite.
Three reagent systems were trialled extensively:
-
Ammonium sulfate (AMSUL): A common ionic clay lixiviant with high selectivity for REE
-
Magnesium sulfate (MS): A potential alternative with similar ionic exchange potential
-
Sodium chloride (NaCl): Tested as a benchmark
Testing was carried out under fixed conditions of 40 wt% slurry density and pH 4.5, with reagent molarities ranging from 0.2M to 1.5M. Initial desorption tests established baseline recoveries:
-
AMSUL (0.22M) yielded 78% TREY-Ce recovery from CDM
-
MS (0.4M) achieved a slightly lower but consistent 75% TREY-Ce
-
NaCl (1.5M) was significantly less effective at just 54% recovery
In all cases, Ce recovery remained persistently low (3–7%), attributed to its stable +4 oxidation state and partial association with cerianite, which is not ion-exchangeable.
Kinetic testing confirmed that desorption reached 95% of its equilibrium extraction within the first 15 minutes of contact time. This rapid response indicates a favourable process dynamic for continuous operation. Nonetheless, a 30-minute contact time was adopted as standard to ensure robustness across ore types and potential scaling factors.
Based on the totality of results, AMSUL was selected as the preferred primary desorption reagent due to its superior selectivity, availability, and established use in ionic clay REE operations. MS remains a viable fallback or blending option, especially where sulfate build-up or magnesium precipitation is manageable. NaCl was ruled out due to poor efficiency and high sodium load implications.
Impurity Removal
Following desorption, the leach liquor contains dissolved impurities including Al, Fe, Zn which must be removed prior to MREC precipitation. Two impurity removal approaches were tested:
-
pH adjustment using MgO or ammonium bicarbonate
-
Direct addition to slurry vs. treatment of filtered liquor
The best performance was obtained by treating filtered liquor. This condition effectively precipitated Al and Fe whilst minimising REE losses <1-2% at the optimum pH target.
MREC Precipitation and Product Quality
The final step in the flowsheet involves precipitation of REE as an MREC product using ammonium bicarbonate
Page | 21 of 49
==> picture [76 x 57] intentionally omitted <==
at the target pH. Across all tests, >99.5% of REE were successfully precipitated from purified liquor. The quality of the resulting MREC was excellent with total impurities <2%.
==> picture [394 x 342] intentionally omitted <==
Figure 11: Overall Process Block Flow Diagram.
Processing
The Caldeira Project process plant is designed to process 6Mtpa dry feed to produce approximately 24,000tpa dry MREC product cake. It will operate 8,000 hours/year, 24 hours/day at 750tph (dry). The feed grades and recovery used in the PFS design are based on the CDM master composite and an average of the batch tests completed by ANSTO for SOB and FIG. The impurities contained in the feed ore are also based on the CDM master composite.
A combination of vendor and ANSTO batch and piloting test work data was used as the basis for the plant design development. Design factors have been applied to determine equipment sizing. In general, the Caldeira Project plant will be running with no standby equipment.
Process Overview
The feed preparation circuit rejects +10mm oversized low-grade material from the ROM before subsequent processing by washing in a drum scrubber. Scrubbed material will feed the leaching circuit. Two large CAT 922 loaders (or equivalent) will be required to reclaim ore from the ROM stockpile area and feed the plant.
The extraction of the rare earths from the REE-bearing ionic clays occurs through an ion exchange mechanism between ammonium sulfate (liquid phase) and the lanthanide (solid phase) present in the mineral. The desorption process uses ammonium sulfate ((NH4)2SO4) as the leaching agent under mildly acidic conditions.
Following leaching, slurry is transferred to the residue dewatering circuit to further extract REE from residue.
Page | 22 of 49
==> picture [76 x 57] intentionally omitted <==
This is followed by separation and washing of REE sulfates contained in the pregnant leach solution ( PLS ) from the barren leach solids. The final residue with an appropriate sulfate level will be de-watered and sent for in-pit tailings disposal. The counter current decantation ( CCD ) thickener circuit will provide washing of the leached residue to maximise recovery of REE to PLS through counter current washing and additional extraction.
The PLS (CCD1 overflow) will be cleaned in dynamic bed clarifiers ( DBC ) before being transferred to the MREC circuit to recover REE from the clean PLS solution and produce a MREC product cake for sale.
The REE deficient MREC barren solution will also be clarified in DBC before transfer to the water recovery system ( WRS ). The MREC produced in the DBC will be dewatered in two centrifuges in a series configuration. The MREC cake will require repulp washing to remove any impurities such as soluble sulfates in the liquid phase to meet product specifications. The repulped cake will be dewatered in the secondary centrifuge. The washed cake is then transferred by a belt feeder to the automated packaging system for bagging.
The WRS is used to process MREC barren solution to produce clean water for the upstream plant and to recover ammonium sulfate. Additionally, this circuit will remove manganese, silica and calcium before the reverse osmosis ( RO ) membrane circuits. The RO permeate will be the main source of clean water for the plant and will be used to wash the leached ore residue before discharging to final residue.
It was found that running a partial WRS circuit consisting of RO pretreatment and one stage of RO membranes, processing a minimum 2250m[3] /h of MREC barren solution, would meet the environmental discharge requirement, given the use of clay lining. Any run-off from the mined-out clay lined pit will be returned to the plant, or treated, prior to discharge to the environment. It was found the natural bleed from the residue moisture is insufficient to remove the buildup of impurities in the circuit.
Page | 23 of 49
==> picture [75 x 57] intentionally omitted <==
==> picture [628 x 405] intentionally omitted <==
Figure 12: Process Flowsheet.
Page | 24 of 49
==> picture [76 x 57] intentionally omitted <==
Infrastructure and Site Access
Local Area
The Caldeira Project is located between the cities of Caldas, Poços de Caldas, and Andrades, in the state of Minas Gerais, in the southeast region of Brazil. The PFS areas are located in the Municipality of Caldas, which has a population of approximately 14,000. The regional service hub is Poços de Caldas, a city located approximately 30km from the Caldeira Project site, with a population of around 175,000. The area benefits from high quality road and rail connections to major cities such as Belo Horizonte (464km), Brasília (910km), São Paulo (270km) and Santos Port (342km). Historically, the Caldas area has been a centre for clay mining for brick production and refractory clays. For more than 70 years, companies such as Alcoa, Mineracao Curimbaba, Togni Refractories Ltda, and Companhia Brasileira de Alumínio ( CBA ) have operated in the area, providing generational employment opportunities.
==> picture [443 x 457] intentionally omitted <==
Figure 13: Regional Map of Brazil
Page | 25 of 49
==> picture [76 x 57] intentionally omitted <==
Existing Infrastructure
The long history of established mining activities in and around the Caldeira Project support a broad and wellestablished network of service industries. This will greatly assist the Project’s construction and operations. The Project is located near significant existing infrastructure and is relatively well serviced. On-site infrastructure such as offices, warehouses and maintenance facilities have been designed to support both the process plant and mining operations.
Table 10: Summary of Utilities and Infrastructure.
==> picture [483 x 550] intentionally omitted <==
----- Start of picture text -----
Item Status
Accommodation Various accommodation options available in the nearby towns of Caldas and Poços de
Caldas.
No camp is required either for operations or the ~1,200 person construction workforce.
Water Water will be supplied to the facilities from an existing nearby dam, approximately 400
metres from the Caldeira plant site.
Power 100% of Meteoric’s energy requirements will be sourced from renewable energy (hydro,
solar and wind), an option provided by the grid operator Companhia Energética de Minas
Gerais (CEMIG), the largest energy company in Brazil.
Power will be connected to the site via a ~2.5km overhead power line to a local 138kV
network connection at the nearby substation.
The connected load is estimated at 20MW, with Plant average demand at ~13MW. The
general route for the overhead line is shown in Figure 14 (pink easement).
Road Access The proposed main access road is also shown in Figure 14. Approximately ~3km of new
unsealed road will need to be constructed to connect the plant site with the existing public
road network.
By road the Project site is ~447km from the capital Belo Horizonte and 254km from the city
of São Paulo on good quality sealed roads.
The Project site is ~31km to the south of the city of Poços de Caldas.
Port All required facilities exist.
During construction and operations containerized cargo is expected to enter and leave
Brazil at Santos port near the city of Sao Paulo. Itaguaí (in Rio state) was identified as an
alternate port that may suit breakbulk cargo if required.
Telecommunications There is mobile phone and Starlink reception on site for communications prior to plant
commissioning.
Meteoric has a preference for fibre optic connection via the grid connected power supply
OHL as the backbone for operations.
Fuel Storage The fuel storage facility will be in the Mine Infrastructure Area (MIA) with sufficient diesel
storage to support mining operations for ~7 days.
Fleet & Vehicles A list of plant vehicles and mobile equipment fleet necessary to support operations was
developed during the PFS and will be leased initially to minimise capital expenditure.
Waste Domestic and industrial waste will be processed at a Waste Sorting Facility (WSF) on site
before disposal.
Classification and segregation of materials will be performed at the Classification Shed at
the WSF.
----- End of picture text -----
Page | 26 of 49
==> picture [76 x 57] intentionally omitted <==
==> picture [483 x 307] intentionally omitted <==
----- Start of picture text -----
N
----- End of picture text -----
Figure 14: Grid power overhead line route (pink easement) and main access road
Government Support
The Brazil federal government has shown strong support for the Caldeira Project. Most recently:
-
The Caldeira Project was included in the Brazilian Platform for Investments in Climate and Ecological Transformation ( BIP ) which was recently announced at the fourth meeting of the G20. The BIP seeks to expand investments in ecological transformation towards the de-carbonisation of the economy, sustainable use of resources and quality of life improvement. The Caldeira Project was the only mining project of the six ventures listed.
-
In June 2025 Meteoric was included in Brazilian Financial Agency for Studies and Project ( Finep ) and the National Bank for Economic and Social Development ( BNDES ) Strategic Minerals funding program. The funding program totals BRL 5 billion and is a Brazilian State initiative designed to support Strategic Minerals Projects to expanding production capacity and encouraging research, development and innovation.
-
Meteoric was selected as a priority company (the only REE project) and invited to join the Brazilian government committee at the Futuro Minerals Forum held in Saudi Arabia, January 2025.
-
In August 2023, a Memorandum of Understanding was executed with the State of Minas Gerais, formally designating the Caldeira Project as a priority state initiative. This designation provides the Project with enhanced government support, particularly in relation to permitting processes and facilitation during both the implementation and operational phases.
Page | 27 of 49
==> picture [76 x 57] intentionally omitted <==
Environmental and Community
Background
On 17 March 2023 Meteoric entered into a Development and Implementation Agreement for the Caldeira Project ( Togni Agreement ) with the various parties ( Togni Parties ) which own the mining tenements required for the Caldeira Project. In summary, the Togni Agreement:
-
Granted Meteoric exclusive rights to REE on all mining tenements required for the Caldeira Project ( Mining Tenements );
-
Requires the Mining Tenements to be transferred, leased or assigned to Meteoric; and
-
Established royalties payable to the Togni Parties.
When combined, the Mining Tenements comprise an area of approximately 11,271 hectares. Meteoric has subsequently acquired the right to additional mining tenements making a total area of 18,292 hectares available to Meteoric for Caldeira Project mining activities.
==> picture [496 x 336] intentionally omitted <==
Figure 15: Map of Caldeira Tenements and Licenses
Page | 28 of 49
==> picture [76 x 57] intentionally omitted <==
Tenure – Mineral Rights
Under Brazilian law, a party may only engage in construction and mining activities upon a Mining Licence approved by, and registered with, the ANM. The Mining Tenements do not currently list REE on the title documents. To have REE specified on the register, the licence holder must communicate to the ANM:
-
Details of the new substance to be added to the register (i.e. REE);
-
A re-evaluation of the reserves and resource relating to the REE on each tenement ( RRR ); and
-
A Preliminary Economic Assessment ( PAE) .
Meteoric requires full surface rights to all impacted areas within the following four key Mining Tenements, as well as additional minor areas for infrastructure to comply with the PFS mine schedule:
Table 11: Mining Licences which comprise the PFS areas.
==> picture [483 x 115] intentionally omitted <==
----- Start of picture text -----
Tenement Status
Capão do Mel Mining Licence Application (Clay)
Soberbo Mining Licence (Clay)
Figueira Mining Licence (Clay)
Bara do Pacu Mining Licence (Clay)
----- End of picture text -----
The CDM, BDP and SOB tenements are contiguous, with FIG approximately 5km away.
==> picture [439 x 310] intentionally omitted <==
Figure 16: Caldeira Project (EIA) plan view – Layout of proposed pits, process plant, infrastructure and three licenses included in the Preliminary Licence (LP) application of May 2024.
Page | 29 of 49
==> picture [76 x 57] intentionally omitted <==
Brazil Legal Framework
Brazil is a democratic federation which operates under a civil law system and has the world’s eighth largest economy. Brazil is governed under a three-tiered administrative structure divided into federal, state and municipal bodies. The federal government has broad and exclusive powers over mining activities under the Federal Constitution ( Constitution ) .
Brazilian law permits foreign investment and ownership in mining projects. Meteoric operates the Caldeira Project via its Brazilian subsidiary Meteoric Caldeira Mineração Ltda (Meteoric Brazil ).
Ownership of Mineral Resources
Under Brazilian laws, mineral resources are owned by the federal government and separate from the land upon which they are located. As legal owner, the government is:
-
Empowered to grant mineral rights for exploration and mining of mineral deposits; and
-
Entitled to receive a share in the results of mining, in the form of royalties.
Mineral rights & security of tenure
Landowners hold surface rights and are entitled to be compensated for the impact of mining activities conducted upon their land. Miners, such as Meteoric, are:
-
Granted various rights to engage in mining activities; and
-
Entitled to ownership of all product from mining activities.
Granted mineral rights permit exploration and mining of specified resources but do not transfer land ownership. All transfers, assignments and other interests created in respect of mineral rights must be registered with the National Mining Agency (Agência Nacional de Mineração or ANM ). The ANM is the federal body responsible for the management of mining activity in Brazil including the grant of rights, title administration and collection of certain licence fees.
Right to mine requirements
To commence construction activities at the Caldeira Project, Meteoric must acquire the following two rights:
Installation Issued by the state of Minas Gerais Secretariat for the Environment and Sustainable Licence (LI) Development ( SEMAD ) Mining Licence Issued by the ANM which must have REE specified on the licence document together with an approved Mine Economic Plan ( PAE ).
To commence mining activities, Meteoric will also require an Operating Licence ( LO ) issued by SEMAD.
Meteoric is in the process of securing all required governmental, regulatory and landowner consents to obtain approvals to commence construction and mining activities at the Caldeira Project.
Page | 30 of 49
==> picture [76 x 57] intentionally omitted <==
Current Status
All documentation required for the ANM to specify REE on the SOB, FIG and CDM tenement registers has been submitted. Meteoric anticipates ANM approval will be granted for SOB and FIG in late 2025 and for CDM in the June quarter 2026.
Meteoric is finalising all documentation required by the ANM to add REE to the BDP licence document.
The remaining Mining Tenements are not currently required under the scope of the PFS mine schedule. Meteoric intends to submit the necessary documentation to the ANM to include REE as a specified commodity on the relevant licence titles. Following confirmation from the ANM that REE has been incorporated into the tenement titles, these tenements will be promptly transferred, leased, or assigned to Meteoric Brazil, with the corresponding interests duly registered with the ANM.
Surface Land Access & Ownership
Meteoric requires the consent in the form of right of way, or easement, agreements with all landowners affected by the Project. These agreements are needed to facilitate Project activities, including:
-
Mineral extraction areas (pit);
-
Industrial plant, piles and manoeuvring areas;
-
Ancillary needs such as office, accommodation and restaurant facilities; and
-
Ingress and egress to the Caldeira Project.
Meteoric must agree the following with each landowner affected by Caldeira Project activities:
Table 12: Land Access Requirements.
| Activities | Requirement |
|---|---|
| Non-Mining | Landowner Agreement - with each impacted landowner to provide adequate compensation for land use: e.g. Easement Agreement |
| Mining | Royalty Agreement – with each landowner upon whose land mining occurs. Under Brazil law, royalty rights are prescribed by statute. For Rare Earths, Meteoric must pay a minimum of 1% of gross revenue. Note: Meteoric may need to enter into separate Landowner and Royalty Agreements with certain landowners. |
Meteoric is in the process of securing all required agreements and has made considerable progress. Upon execution, each relevant document is submitted to the ANM for the Meteoric interest to be registered on the tenement title. Each Landowner Agreement is also submitted to the local Municipal Notary Public responsible for registering interests on land registers.
The Company is not obligated to make compensation payments to landowners until their land is directly impacted by Project activities. Such impacts will not occur until Meteoric has secured all necessary rights to mine REE and has commenced on-ground operations at the Project site.
In the event that access negotiations with a landowner are unsuccessful, Meteoric is entitled to initiate legal proceedings to obtain a court order permitting access to the relevant property. Should the matter proceed to trial, the legal process may extend over several years.
Page | 31 of 49
==> picture [76 x 57] intentionally omitted <==
Environmental Approvals
The Constitution mandates protection of the environment to:
-
Ensure and preserve people's quality of life for present and future generations; and
-
Facilitate sound management of natural resources.
All mining activities in Brazil are subject to mandatory licensing requirements within a framework of federal, state and municipal laws and regulations.
Responsibility for the grant of environmental approvals in Minas Gerais lies with SEMAD which must act in accordance with applicable laws and regulations. SEMAD has classified the Caldeira Project as a Class 6 Project given its size, location and potential for environmental impact. The process for obtaining required environmental approvals for Class 6 Projects occurs in three stages.
Table 13: Class 6 Projects – Required Environmental Licences,
| Stage | Licence | Purpose |
|---|---|---|
| Stage 1 | Preliminary Licence (LP) | Evaluate project social and environmental feasibility. Establish basic preliminary conditions to be met. |
| Stage 2 | Installation Licence (LI) | Authorise commencement of construction and installation of equipment. Review detailed project design and associated social and environmental control measures. |
| Stage 3 | Operating Licence (LO) | Authorise commencement of mining operations. Define control methods and operating conditions. |
Stage 1 – Preliminary Licence (LP)
Meteoric commenced the LP application process in respect of the SOB, FIG and CDM tenements in September 2023. The BDP tenement does not form part of the current LP application. Upon LP issue, Meteoric will apply for the BDP tenement to be incorporated into the Caldeira Project via an Expansion Licence (see below).
==> picture [478 x 172] intentionally omitted <==
Figure 17: Meteoric Licensing Process – Current Status
Page | 32 of 49
==> picture [76 x 57] intentionally omitted <==
Meteoric has already achieved several notable project milestones including:
-
Environmental Impact Statement ( EIS ) - Submitted
-
Public Hearing (Caldas City) – Conducted by SEMAD (November 2024)
-
Certificate of Regularity for Land Use and Occupation from Municipal Environmental Council ( CODEMA ) - Obtained (March 2025)
-
EPA Site Inspection – Technical visit complete (March 2025)
During this LP stage, Meteoric is also making advances towards satisfying LI requirements including completion of additional environmental studies and securing required landowner consents.
Environmental Impact Statement
The EIS is the principal document supporting the application for the LP. As required by Brazilian law, Meteoric engaged an independent consultant company, Alger Consultoria Socioambiental ( ALGER ) to complete the EIS. Additional studies were provided by CERN Consultoria, also from Belo Horizonte.
The environmental field studies within the areas affected by the Project (EIS area) were initiated in September 2023. The EIS addressed all required SEMAD terms of reference, including:
-
Air quality
-
Surface water quality
-
Groundwater quality
-
Noise and vibration
-
Natural springs mapping
-
Mapping of caves
-
Fauna survey
-
Flora survey
The baseline data was gathered from September 2023 to January 2024, with results used to:
-
Assess the potential socioenvironmental impacts generated by the Project.
-
Design programs to mitigate or compensate negative impacts, and to maximize positive impacts.
-
Design socioenvironmental controls and monitoring programs.
-
Provide a reference point during the construction, operation, and closure stages of the Project with the aim of assessing the efficacy of environmental controls/programs implemented during the mine life and establishing if additional corrective measures are necessary.
The EIS concluded the proposed mitigation of environmental impacts including:
-
management of water resources
-
preservation of biodiversity
-
control of air quality, and
-
rehabilitation of degraded areas (including the backfill of pits and the re-shaping of the land)
Based on technical and legal analyses, the EIS concluded the implementation and operation of the Project in the municipality of Caldas will bring many benefits to the local community including significant opportunities for socio-economic development including job creation, training programs, material growth in Municipal taxes and financial support and associated contributions to the social and economic well-being of the Caldas region.
Page | 33 of 49
==> picture [76 x 57] intentionally omitted <==
The EIS was finalised and submitted to the state EPA in May 2024. and includes an Environmental Impact Report ( EIR ). A copy of the full EIS submission and summary report ( RIMA ) can be found at: https://encr.pw/projetocaldeira.
Save for procuring certain specialist environmental advice to complete the licencing process, no further costs are associated with the LP. Meteoric anticipates SEMAD will grant the LP in late 2025.
Stage 2 – Installation Licence (LI)
Following LP grant, Meteoric will apply to SEMAD for an LI. This involves the preparation and submission of a detailed Environmental Control Plan ( PCA ). LI grant is scheduled to occur in 2026, at which time Meteoric will be entitled to commence construction activities and must assume various environmental obligations including:
-
Environmental Compensation obligations; and
-
Payment of the Environmental Compensation Fee to SEMAD. Under Brazilian law, each mining company must compensate the state government with a payment equivalent to 0.5% of Project capital cost. Payment obligations are generally negotiated to be paid in multiple tranches over a period.
Stage 3 – Operating Licence (LO)
Upon completion of construction, Meteoric will deliver a final construction report to SEMAD, confirming construction has been completed in accordance with LI requirements. Upon receipt of this report, SEMAD will inspect the Project to verify compliance with licence requirements. This is generally a short formulaic process, given:
-
Meteoric must deliver bi-annual progress reports to SEMAD during the LI term; and
-
SEMAD conducts regular inspections throughout the construction phase.
Meteoric is permitted to carry out equipment testing and commissioning of the process plant, pending LO grant. The LO will specify which Mining Tenements are available for immediate mining at the Project. The initial LO term is 10 years and can be renewed for multiple successive periods.
Expansion Licence
Meteoric may, at any time after receiving the LO, apply to SEMAD to issue Operating Licences for additional Mining Licences via an Expansion Licence. Given Meteoric will hold an existing LO this is a straightforward and expedited process which involves the preparation and submission of an EIS. The process can be completed within 1-2 years. The BDP licence will be incorporated into the Caldeira Project via an Expansion Licence. The grant of an Expansion Licence will require Meteoric to assume additional Environmental Compensation obligations in the manner prescribed for LI grant.
Meteoric’s entitlement to request, and be granted, multiple Expansion Licences will enable mining operations to continue with the initial facilities on an indefinite basis.
Environmental Compensation
There are five applicable categories of environmental obligations to be assumed by Meteoric to enable activities associated with the Caldeira Project:
-
Atlantic Forest Biome
-
Endangered Species
-
Environmental Preservation (APP)
-
Mineral Compensation
Page | 34 of 49
==> picture [76 x 57] intentionally omitted <==
- Legal Reserve
The nature of each form of compensation is defined by various Brazilian laws. The nature and scope of required compensation for each category will be approval by SEMAD. The assumption of the compensation occurs upon grant of the LI and any Expansion Licence.
Atlantic Forest Biome
The Caldeira Project is located within an area defined under Brazilian law as the Atlantic Forest Biome ( Atlantic Forest ). Any Meteoric activity which involves the clearance of Atlantic Forest vegetation will require the Company to compensate the state of Minas Gerais by replanting an area, equivalent to twice that cleared, within the same Biome. Meteoric is in the process of finalising the optimal way to comply with this obligation.
Endangered Species
Under Brazilian law, any activity involving the clearing of tree species classified as ‘endangered’ will require Meteoric to plant an identical amount of species cleared within the same biome. Meteoric has conducted extensive survey and mapping of Project areas and identified the quantum and location of tree species likely to be impacted. Meteoric is confident any obligations arising will not be significant.
Environmental Preservation – APP
Brazil law dictates any land designated as a permanent Environmental Preservation Area ( APP ) shall be protected. Certain areas within the Caldeira Project area fall within an APP. Mining activities are permitted within APP areas provided adequate compensation is made by replanting an equivalent area of that impacted by mining activities with similar vegetation within an APP zone.
Meteoric has conducted extensive survey and mapping of Project areas and identified the nature and scope of APP land likely to be impacted. Meteoric is confident any APP obligations arising will be minor in nature and its obligations will be easily satisfied.
Mineral Compensation
Meteoric must compensate the Minas Gerais state for any activities occurring within a forested area. This compensation involves Meteoric acquiring an equivalent area of land within an ‘Official Conservation Unit’ - an area of land subject to strict environmental protection. Upon acquisition, the area is donated to Minas Gerais state.
Meteoric has identified the areas likely to be affected by the Caldeira Project and identified a parcel of land inside an Official Conservation Unit which should satisfy all its mineral compensation obligations to be assumed.
Legal Reserve
Each rural property in Minas Gerais is legally required to retain a forested area, equivalent of 20% of the property area as a ‘legal reserve’. This area must be registered with the Municipal Notary Public. Where a mining project impacts a legal reserve, the landowner must relocate the legal reserve impacted within the same rural property or in another rural property located within the same biome and notify the Municipal Notary Public. As part of securing landowner consent, Meteoric will assume landowner legal reserve responsibilities for land affected by the Project’s activities.
Meteoric is in the process of identifying appropriate land to discharge legal reserve obligations. Given the high cost of acquiring land in the Caldeira Project region, Meteoric is seeking to acquire acceptable land elsewhere in the biome and intends to satisfy its legal reserve obligations in relation to the CDM, FIG and SOB tenements by September 2025.
Page | 35 of 49
==> picture [76 x 57] intentionally omitted <==
Liability
Environmental liability is strict under Brazilian law and Meteoric will be subject to strict liability for any environmental violations and any environmental damage created by Caldeira Project activities. Liability can be civil (damages, remedial acts and indemnification); administrative (fines, remedial acts and sanctions); and criminal (criminal penalties). Meteoric is implementing comprehensive environmental management measures to mitigate potential environmental risks associated with the Project.
Implementation Plan
==> picture [483 x 234] intentionally omitted <==
Figure 18 Drawing of Process Plant layout at CDM.
Project Development
A Definitive Feasibility Study ( DFS ) is now planned to be completed to support a potential Financial Investment Decision ( FID ). This will produce a AACE Class 3 estimate (+/-15% accuracy) to support FID and provide a control budget for Project execution. This is intended to be completed around three months prior to FID.
During the period of DFS preparation, Meteoric plans to commission and operate a pilot plant in Poços do Caldas to deliver significant Project benefits including to produce MREC in support of offtake agreements and providing a focal point for stakeholder engagement.
Following the DFS, it is proposed to undertake a Front End Engineering Design ( FEED ) phase – essentially a limited notice to proceed which will permit the selected engineering consultant to prepare and issue long lead tenders and early works contracts in the time prior to FID.
A Project schedule has been developed to achieve the Meteoric goal of first product to market in 2028. This includes the issue of a licence to construct (LI) in 2026. followed by ~24 months of construction prior to plant commissioning.
This Project Execution Plan is based on an Engineering Procurement Construction Management ( EPCM ) strategy where these services are contracted to experienced consultants operating under Meteoric’s direction. Procurement will target global tier 1 equipment suppliers with a strong preference for those operating in Brazil. Fabrication and Construction will be undertaken by experienced Brazilian contractors.
The proposed execution strategy is the dominant strategy for mid-tier mining projects in Brazil, with 92% of mining projects completed in Brazil in the last five years undertaken on this basis. Undertaking an EPC strategy is estimated to negatively impact project schedule by 6 – 8 months and no full EPC contractors have
Page | 36 of 49
==> picture [76 x 57] intentionally omitted <==
been identified who are prepared to provide a fixed lump sum price for work following DFS completion.
Capital Cost Estimate
Basis of Estimate
-
The Capital estimate is an Ausenco Class 4 Pre-Feasibility Study Capital Cost Estimate with a nominal accuracy of +/- 25%, as defined by Ausenco’s standard guidelines and in accordance with the American Association of Cost Engineering ( AACE ).
-
Ausenco developed the estimates adopting an agreed work breakdown structure ( WBS ).
-
Ausenco’s strategy was to source budget pricing for major mechanical equipment with costs from recent in-house pricing for minor mechanical equipment.
-
Pricing for earthworks, concrete, structural steel, platework, mechanical installation and off plot piping is based on budget enquiry submissions from reputable Brazilian fabricators and contractors.
-
High voltage electrical was also costed based on budget enquiry submissions from reputable Brazilian contractors.
-
Costs for process plant piping and process plant E&I were factored based on in-house data.
-
Architectural buildings costed based on similar type buildings from other recent projects or similar detailed budget quotes in the region.
-
Indirect costs include project implementation costs, field indirect, spares, first fills and contingency are factored based on in-house data.
CAPEX Results
The total cost of capital is summarised in the tables below. The total estimated cost for the Caldeira Project Process Plant CAPEX is US$415.5 million, including direct, indirect, and contingency costs.
The total estimated cost for Mine CAPEX is US$16.4M, including the mine contingency cost. This excludes Mining Fleet CAPEX which has been estimated at a capital cost of US$11.6M at the start of operations. Subsequent capital requirements have been captured under sustaining capital.
Total estimated initial CAPEX of US$443.4 million.
Table 14: Summary CAPEX (Process Plant).
==> picture [483 x 107] intentionally omitted <==
----- Start of picture text -----
Description CAPEX Total with Taxes (R$) CAPEX Total with Taxes (USD)
Process Plant Direct Cost 1,552,654,165 $258,775,694
Process Plant Indirect Cost 441,562,559 $73,593,760
Process Plant Contingency 498,554,181 $83,092,363
TOTAL WITH CONTINGENCY 2,492,770,905 $415,461,817
----- End of picture text -----
Page | 37 of 49
==> picture [76 x 57] intentionally omitted <==
Table 15: Summary – Mine Costs (Excluding Mining Fleet).
==> picture [483 x 143] intentionally omitted <==
----- Start of picture text -----
Description CAPEX Total with Taxes (R$) CAPEX Total with Taxes (USD)
Mining Cost 50,641,350 8,440,225
Mine Industrial Area 27,871,023 4,645,171
Mine Cost 78,512,373 13,085,396
Mine Contingency 19,628,093 3,271,349
TOTAL WITH CONTINGENCY 98,140,466 16,356,744
----- End of picture text -----
Operating Cost Estimate
Table 16 summarises the annual operating costs for the process plant based on design throughput and grade (and therefore differs slightly from the financial model which uses yearly production grades). Mining comprises 30.5% of operating costs. Labour, maintenance and general expense costs are considered a fixed cost and are not impacted by the variations in throughput. These amount to 15.5% of total costs. Process Plant variable costs make up for 54% of the total operating costs at the full nameplate capacity. Reagents and consumable costs are in turn the largest portion of this at 42% of total operating costs.
Table 16: Design Operating Cost Metrics.
==> picture [484 x 251] intentionally omitted <==
----- Start of picture text -----
Costs
Cost Centre
USD M/y USD/dry t USD/kg TREO
Standard Year ROM Product
Nominal Quantities per annum 6Mt 15,000t
Fixed Costs
Labour 5.42 0.90 0.36
Maintenance 7.97 1.33 0.53
General Expenses 6.26 1.04 0.42
Sub-total (Fixed Costs) 19.64 3.27 1.31
Variable Costs
Power 5.79 0.97 0.39
Reagents & Operating Consumables 53.59 8.93 3.57
Product Transportation (CIF Santos, Brazil) 9.01 1.50 0.60
Sub-total (Variable Costs) 68.38 11.40 4.56
Process Plant Sub-total 88.02 14.67 5.87
Mine Operating Expense 38.58 6.43 2.57
STANDARD YEARLY COSTS AND RATES 126.60 21.10 8.44
----- End of picture text -----
The above rates per dry tonne of ROM Ore and per kilogram of TREO are nominal annual rates from the cost modelling and scheduling performed by Ausenco. These rates have been utilised as inputs to the financial model to generate the annual costs and LOM costs summarised in the Financial Summary section. These annualised costs exclude the transportation and processing of low grade stockpiles.
Page | 38 of 49
==> picture [76 x 57] intentionally omitted <==
==> picture [371 x 265] intentionally omitted <==
Figure 19: Distribution of Processing Plant Operating Costs
Table 17: Total Mining Costs Per Annum
| Mining Cost | Cost per year (US$/y) |
|---|---|
| 6Mtpa | 38,580,000 |
This equates to US$6.43/dry tonne ROM feed or US$2.57/dry tonne moved. These costs assume:
-
An average of 15Mt (dry) moved per year (6Mt ore, 3Mt waste, 6Mt spent clay returned to the pits).
-
20% moisture for all movements.
-
US$1/L diesel.
-
No equipment fleet costs (included within capital and sustaining capital).
-
No contingency.
-
No re-handling of materials (i.e. wet season stockpiles or spent clay).
-
Use of 80 tonne (PC 800) excavator and Scania (10 x 4) tippers (40t capacity) as basis of main fleet. Support equipment allowed includes D8 dozers, G14 graders, Volvo35 water carts, Volvo EC480 scratch back excavators.
-
No drilling or blasting of hard ground.
-
Maximum annualised operating hours of 5,500 hours.(SMU 6,050 hours).
-
Dewatering and haul road maintenance included.
Grade control / sampling, survey, geology, mine planning and management costs are included in Process Plant labour.
Page | 39 of 49
==> picture [76 x 57] intentionally omitted <==
Reagents and Consumables Costs
The cost of reagents and consumables were derived from first principles using the consumption rates with prices quoted by suppliers for reagents delivered to site.
The ore specification was incorporated in the Metsim mass balance, based on the CDM tenement. The consumption of reagents varies as the ore feed grade varies. The consumption rate is based on the pilot campaign test work. Annual consumption of reagents used in the WRS circuit is calculated based on vendor proposal estimated dosage following vendor testwork.
The reagent and consumable rates were obtained from quotes received from alternative suppliers and benchmarking with rates from the Ausenco database.
The cost of power used is US$60.34/MW hr directed by Meteoric based on a CMU proposal for estimated power costs in the free energy market.
Operational Readiness
Operational Readiness is:
-
The practice of establishing the people, processes and systems necessary to operate and maintain a new asset;
-
The preparation work necessary for an organisation to assume full operational ownership and maintainability of the new asset, safely and sustainably; and
-
The positioning of people, processes and systems associated with the key functional areas to allow sustained operation of the new asset upon project completion.
During the PFS, Operational Readiness has been considered through the development of:
-
A high-level operational and maintenance philosophy;
-
A high-level Operational Readiness philosophy that supports this; and
-
Budget allowances in subsequent study phases and the capital estimate to allow further development.
==> picture [459 x 215] intentionally omitted <==
Figure 20: Operational Readiness (OR) Roadmap
Page | 40 of 49
==> picture [76 x 57] intentionally omitted <==
During the execution phase, the initial components of the Operational Readiness Plan will be led by the Meteoric team, supported by specialist consultants. Twelve months prior to ore commissioning, the formation of the Operations team will commence with the appointment of the Operations Director. This team will progressively expand in preparation for wet commissioning, assuming responsibility for the implementation of the Operational Readiness Plan.
By the time wet commissioning begins, the Operations team will be fully staffed, with a primary focus on training and supporting the Project commissioning team. Upon commencement of ore commissioning, the Operations team will take full operational control, with the Project commissioning team continuing to provide technical support as needed.
Financial and Commercial Analysis
The PFS economic evaluation presents the Net Present Value ( NPV ), applying an 8% discount rate over a 20year period, and using three different price books (as illustrated in Figure 21). This methodology evaluates the capital and operating strategy to confirm that the NPV remains positive, even at historically low spot prices.
Ausenco has compiled the operating costs used in the modeling of the LOM economic model. This model provides annual pre-tax and post-tax NPV calculations, based on an 8% discount rate, along with cash flow projections and payback period estimations. Additionally, the model includes sensitivity analyses for key project drivers such as operating costs, capital costs, and REE pricing.
It is important to note that tax calculations involve complex variables that can only be accurately determined during actual operations. Consequently, the actual after-tax results may vary from these preliminary estimates.
Pricing Assumptions and Forecast Methodology
The economic model has been developed using spot pricing, broker consensus pricing, and forecast data from two highly regarded independent market analysts, Project Blue and Adamas Intelligence. The use of three forward pricing scenarios has been done to assess project resilience and value under varying market conditions.
Consensus pricing reflects the long-term real available pricing expectations sourced from Macquarie Bank in May 2025 and compiled and summarised by them using data collected from multiple brokers.
Forecast pricing uses an average of Project Blue and Adamus Intelligence projections, as of the March quarter 2025. While their forecasts differ materially, both are considered credible and reflect the inherent uncertainty in today’s REO market environment. The Company believes this approach offers investors a more balanced and transparent view of potential market scenarios and provides a robust foundation for long-term financial modelling and strategic planning.
The market analysts’ forecasts are underpinned by comprehensive analysis of global supply and demand trends. On the demand side, projections reflect anticipated growth in key sectors such as electric vehicle drivetrains, wind turbines, energy transition technologies, robotics, and defence. Supply assumptions incorporate current global production levels and publicly announced future projects, offering a well-rounded view of the evolving market landscape.
Importantly, the 10-year forecast horizon is a deliberate and strategic choice, reflecting the timeframe over which market analysts have the highest confidence in data quality, project visibility, and policy direction. This period aligns with typical investment and development cycles, allowing for meaningful insights into mediumterm market dynamics while avoiding the speculative nature of longer-term projections. The methodology balances near-term certainty with long-term strategic relevance, providing a robust foundation for financial modelling and decision-making.
Page | 41 of 49
==> picture [76 x 57] intentionally omitted <==
==> picture [484 x 248] intentionally omitted <==
----- Start of picture text -----
$180
$160
$140
$120
$100
$80
$60
$40
$20
$-
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
NdPr Spot Price NdPr Consensus NdPr Forecast
US$ / kg
----- End of picture text -----
Figure 21: Pricing assumptions over the Project LOM
Page | 42 of 49
==> picture [76 x 57] intentionally omitted <==
Financial Summary
Financial Model Metrics
Table 18: Executive Summary
==> picture [412 x 378] intentionally omitted <==
----- Start of picture text -----
Executive Summary
Financial Unit Spot Consensus Forecast
Total Revenue US$M 4,927 6,330 9,756
EBITDA US$M 1,707 2,987 6,111
Cumulative post tax cashflow
US$M 1,165 1,994 4,058
excluding construction cost
Pre-tax NPV8 US$M 251 821 1,985
Post-Tax NPV8 US$M 109 488 1,256
Physicals
Life of Mine Years 20
Total ROM Feed Tonnes (M) 128,989
Total Waste Tonnes (M) 48,581
Production
TREO Tonnes 271,687
Neodymium Praseodymium (NdPr) Tonnes 84,572
Dysprosium (Dy) Tonnes 2,143
Terbium (Tb) Tonnes 457
----- End of picture text -----
Table 19: Key Production Outcomes
==> picture [352 x 177] intentionally omitted <==
----- Start of picture text -----
Pre-Feasibility Study
Key Production Outcomes Unit
Years 1-5 LOM
Ore Mined kt 26,523 128,989
Strip Ratio waste:ore 0.52 0.38
Average TREO Feed Grade ppm 4,515 3,701
TREO Recovery % 54 55
MREO Recovery % 73 71
Average annual production [1] (TREO) t 12,382 13,584
Production (TREO) t 61,912 271,687
NdPr % (in TREO concentrate) % 31 31
----- End of picture text -----
1 Includes ramp up in Years 1 and 2
Page | 43 of 49
==> picture [76 x 57] intentionally omitted <==
Table 20: Cashflow, Cost & Earnings Metrics
==> picture [502 x 333] intentionally omitted <==
----- Start of picture text -----
Years 1-5 LOM
Cashflow, Cost &
Unit
Earnings Metrics Spot Consensus [2] Forecast [3] Spot Consensus Forecast
Annual Average
Revenue US$M 210 284 330 245 315 485
EBITDA US$M 79 147 189 86 150 305
Operating Cashflow US$M 60 104 132 58 100 203
Total
Revenue US$M 1,050 1,422 1,650 4,927 6,330 9,756
EBITDA US$M 397 737 944 1,707 2,987 6,111
Net profit After Tax
US$M 186 410 546 710 1,561 3,625
(NPAT)
Cumulative post tax
cashflow excluding US$M 298 522 659 1,165 1,994 4,058
construction cost
Annual operating cost US$M 110 133
US$/kg
Annual operating cost 8.91 9.78
TREO
US$/kg
Annual AISC [44] 11,16 11.69 12.01 12.62 13.07 14.18
TREO
US$/kg
NdPr Average pricing 67 91 107 67 86 135
NdPr
NdPr average
operating cost (net of US$/kg
20.58 21.80
DyTb by-product NdPr
credits)
----- End of picture text -----
2 Consensus reflecting the long term real available pricing expectations from multiple brokers as of May 2025, source Macquarie Bank. 3 Forecast is calculated as the average between Adamas Intelligence & Project Blue long term pricing reported at Q1, 2025.
4 AISC vary, as royalty costs vary under differing pricing scenarios
Page | 44 of 49
==> picture [76 x 57] intentionally omitted <==
Table 21: Financial Outputs
==> picture [438 x 369] intentionally omitted <==
----- Start of picture text -----
LOM
Financial Outputs Unit US$110/Kg
Spot Consensus NdPr Forecast
Annual Revenue US$M 245 315 385 485
Annual EBITDA US$M 86 150 213 305
Annual Operating Cashflow US$M 58 100 143 203
Annual operating costs (ex-royalties) US$M 133
Annual operating costs (ex-royalties) US$/kg TREO 9.78
Annual AISC (including royalties) US$/Kg TREO 12.62 13.07 13.53 14.18
Basket price [5] TREO US$/kg TREO 26 33 41 51
NdPr Average pricing US$/kg NdPr 67 86 110 135
Payability 70
NdPr Gross operating cost 31
NdPr Net Operating costs [6] US$/kg NdPr 22
Capex inclusive of 25% contingency 443
Cumulative post tax cashflow
US$M 1,165 1,994 2,842 4,058
(excluding construction cost)
Pre-tax NPV8 US$M 251 821 1,347 1,985
Post-tax NPV8 US$M 109 488 835 1,256
Pre-tax IRR % 15 28 36 39
Post-tax IRR % 11 21 28 31
Payback period years 6.1 2.9 2.5 2.8
----- End of picture text -----
Table 21 above includes the financial outputs inclusive of a US$110/kg NdPr floor price reflected in the recent announcement by MP Materials and DOD. Meteoric has assumed consensus pricing for all other rare earth elements in it’s REE basket in this comparison.
5 The basket price of TREO refers to the weighted average price of the individual REE contained in a specific mineral concentrate or product, based on their relative proportions and current market prices
6 Operating costs net of DyTb credits at consensus pricing per kilogram of NdPr produced
Page | 45 of 49
==> picture [76 x 57] intentionally omitted <==
Operating Costs, Royalties, Sustaining Capital and Taxes
Figure 22 below provides a detailed breakdown of annual costs, including the surplus free cash annually for the Caldeira Project. Operating costs have been developed by general area using a bottom-up, first principles approach. The estimated costs reflect the effort required to process a nominal 6Mtpa of ore and produce a nominal 13,500tpa of TREO.
==> picture [430 x 267] intentionally omitted <==
Figure 22: Annual operational costs and cash surplus based on consensus pricing.
Mining costs for the project include expenditures associated with the responsible return of spent clay to either mined-out pits or designated waste dump areas, in line with environmental and operational best practices.
General and administrative ( G&A ) expenses have been incorporated within the broader processing cost framework to provide a more accurate reflection of total operating costs.
It is important to note that key financial metrics – specifically royalties, taxation, and surplus cash flow – are all sensitive to changes in the achieved sale price of MREC. As the MREC sale price fluctuates, it directly impacts revenue generation. This, in turn, affects the calculation of royalties (which are typically based on gross sales), the level of taxable income, and ultimately the amount of surplus cash available for reinvestment or distribution.
Taxation, in particular, involves a range of complex variables, including jurisdictional rules, allowable deductions, and timing of revenue recognition. These factors can only be accurately assessed once the project is in operation and actual financial performance data becomes available. As such, while preliminary financial models provide a useful guide, actual after-tax outcomes may vary depending on market conditions and final realised pricing.
This sensitivity to MREC pricing highlights the importance of ongoing market engagement and pricing strategy with significant potential upside in a strengthening rare earth market.
Page | 46 of 49
==> picture [76 x 57] intentionally omitted <==
Table 22: Operating Cost Breakdown
| Operating Costs (Real LOM) | Annual Cost (US$M) Year 1-5 |
Unit Cost (US$/kg TREO) Year 1-5 |
Annual Cost (US$M) LOM |
Unit Cost (US$/kg TREO) LOM |
|---|---|---|---|---|
| Mining | 31 | 2.54 | 39 | 2.89 |
| Processing | 79 | 6.37 | 94 | 6.89 |
| Total operating costs | 110 | 8.91 | 133 | 9.78 |
Total operating costs per kilogram of TREO varies, based on the grade of ore being mined. Over the first five years the cost per kg of TREO is US$8.91/kg based on an average ore grade of 4,500ppm and LOM is US$9.78/kg based on average ore grades of 3,700ppm.
Fees and royalties include contracted royalties paid for Mining Rights (4.75%), Federal Government Royalties (CFEM 2%), State Government minerals tax (US$0.39 per tonne) and fees payable to landholders (US$1 per tonne of ore extracted). Royalties are calculated based on the value of products extracted or sold and will vary depending on the market prices.
Mining operations will utilise an owner mining fleet, with sustaining capital allocated to increase equipment as the mine scheduling expands over time. Owner-mining fleet replacement is currently based on OEM recommendations, and during peak operational years, approximately US$6M per annum is planned for fleet replacement and upgrades.
The corporate tax rate in Brazil is 34%, not including any tax incentives or reduction initiatives for industrial development in specific regions. Meteoric will work with government and taxation authorities to explore potential incentives as it progresses with the Project's development.
Cashflows
The Caldeira Project cumulative cashflow utilising both consensus and forecast pricing scenarios result in a project pay-back of less than three years. Total after tax cash flows generated from the project (inclusive of construction costs) are US$1,551M at consensus pricing, US$3,615M at forecast pricing and US$722M using constant spot pricing.
==> picture [484 x 186] intentionally omitted <==
----- Start of picture text -----
4,000
3,500
3,000
2,500
2,000
1,500
1,000
500
-
-2 -1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
(500)
(1,000)
Spot Consensus Forecast
US$m
Net Operational cash position
----- End of picture text -----
Figure 23: Comparison of accumulated cashflows at varying price points.
Page | 47 of 49
==> picture [76 x 57] intentionally omitted <==
Capital Expenditure
The estimated capital cost was derived by factoring from a priced mechanical equipment list to generate a AACE Class 4 estimate (nominal accuracy +/- 25% before contingency).
The estimated capital cost for the 6Mtpa base case processing plant and mining operations is US$443M inclusive of a 24% contingency.
Table 23: Summary Breakdown of Capital Expenditures
==> picture [367 x 114] intentionally omitted <==
----- Start of picture text -----
Contingency
Description Cost (US$M) Total (US$M)
(US$M)
Mining 24 3 28
Plant Direct 259 65 323
Plant Indirect 74 18 92
Total 357 86 443
----- End of picture text -----
Sensitivity Analysis
==> picture [427 x 215] intentionally omitted <==
Figure 24: Pre-tax sensitivity analysis at consensus.
A comprehensive sensitivity analysis was conducted for the Project, demonstrating its strong resilience across a range of key variables, including capital expenditure, operating costs, and rare earth pricing. The results indicate that while the Project shows moderate sensitivity to changes in operating costs, it is significantly more responsive to movements in the rare earth basket price.
This heightened sensitivity to pricing presents a compelling upside opportunity for shareholders. As rare earth prices – particularly for magnet-critical elements such as Nd, Pr, Dy, and Tb – are forecast to strengthen in the near term due to accelerating demand from electric vehicles, wind energy, and advanced technologies, even modest price increases could have a material positive impact on project economics.
The analysis underscores the Project’s leverage to price growth, with higher realised prices translating directly into improved margins, stronger cash flows, and enhanced returns. This dynamic, positions the Project to benefit disproportionately from favourable market conditions, offering shareholders exposure to a sector with strong structural tailwinds and significant long-term value potential.
Page | 48 of 49
==> picture [75 x 57] intentionally omitted <==
==> picture [740 x 193] intentionally omitted <==
==> picture [740 x 192] intentionally omitted <==
Figure 25: Sensitivity tables
Page | 49 of 49
==> picture [595 x 39] intentionally omitted <==
==> picture [595 x 39] intentionally omitted <==
APPENDIX 2 – Peer Comparison Source Data Information
==> picture [483 x 229] intentionally omitted <==
----- Start of picture text -----
Cut- Magnetic
Resource Grade Bubble
Company Project Classification (Mt) (ppm) Off REO Size Reference
(ppm) (ppm)
Serra Verde Pela Ema Measured + 390 1,500 NSR 220 59 Minedocs August
Indicated 2016
Appia Rare Earths
Appia PCH Indicated 7 2,513 NSR 562 2 & Uranium Corp 1
March 2023
Measured + Viridis Mining &
Viridis Colossus 330 2,680 1,000 659 71 Minerals Ltd 22
Indicated
January 2025
Ionic Rare Earths
Ionic Rare
Earths Makuutu Indicated 518 640 200 152 33 Limited 15 May
2024
Aclara Resources
Measured +
Aclara Penco Module 28 2,292 NSR 523 6 Inc. 12 December
Indicated
2023
Deep Leads – Measured + ABx Group 2 May
Abx Group Rubble Mound 47 873 350 229 4
Indicated 2024
– Wind Break
Meteoric Caldeira Measured + This
666 2,685 1,000 605 179
Resources (Global) Indicated announcement
----- End of picture text -----
Dr. Beck Nader
The information in this report that relates to Mineral Resources is based on information compiled by Dr. Beck Nader, a Competent Person who is a Fellow of Australian Institute of Geoscientists #4472. Dr. Beck Nader is a consultant for BNA Mining Solutions. He has sufficient experience that is relevant to the style of mineralisation and type of deposit under consideration and to the activity being undertaken to qualify him as a Competent Person as defined in the 2012 Edition of the ‘Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves’. Dr. Beck Nader consents to the inclusion in the report of the matters based on his information in the form and context in which it appears.
Dr. Volodymyr Myadzel
The information in this report that relates to Mineral Resources is based on information compiled by Dr. Volodymyr Myadzel, a Competent Person who is a Member of Australian Institute of Geoscientists #3974. Dr. Volodymyr Myadzel is a consultant for BNA Mining Solutions. He has sufficient experience that is relevant to the style of mineralisation and type of deposit under consideration and to the activity being undertaken to qualify as a Competent Person as defined in the 2012 Edition of the ‘Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves’. Dr. Volodymyr Myadzel consents to the inclusion in the report of the matters based on his information in the form and context in which it appears.
The information in this announcement that relates to Mineral Resource Estimates at the Cupim Vermelho Norte and the Dona Maria 1 & 2 prospects was prepared by BNA Mining Solutions and released on the ASX platform on 12 March 2025. The information in this release that relates to Mineral Resource Estimates at the Soberbo and Capão del Mel deposits was prepared by BNA Mining Solutions and released on the ASX platform on 14 May and 13 June 2024 respectively. The information in this release that relates to Mineral Resource Estimates at the Figueira deposit was prepared by BNA Mining Solutions and released on the ASX platform on 5 August 2024. The information in this release that relates to Mineral Resource Estimates at the Bara do Pacu deposit was prepared by BNA Mining Solutions and released on the ASX platform on 15 April 2025.
The Company confirms that it is not aware of any new information or data that materially affects the Mineral Resources in this publication. The Company confirms that all material assumptions and technical parameters underpinning the estimates continue to apply and have not materially changed. The Company confirms that the form and context in which the BNA Mining Solutions findings are presented have not been materially modified.
Mr Steve O'Grady
The information in this report that relates to Ore Reserve is based on information compiled by Mr Steve O'Grady, a Competent Person who is a Member of Australasian Institute of Mining and Metallurgy. Mr Steve O'Grady is a consultant for Intermine Engineering Consultants. He has sufficient experience that is relevant to the style of mineralisation and type of deposit under consideration and to the activity being undertaken to qualify as a Competent Person as defined in the 2012 Edition of the ‘Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves’. Mr Steve O'Grady consents to the inclusion in the report of the matters based on his information in the form and context in which it appears.
Mr Tony Hadley
The information in this announcement that relates to the metallurgical results were compiled by Tony Hadley who is a permanent employee of Meteoric resources and is a Member of the Australasian Institute of Mining and Metallurgy (AusIMM). Mr. Hadley has sufficient experience that is relevant to the metallurgical testwork which was undertaken to qualify as a Competent Person as defined in the 2012 JORC Code. Mr. Hadley consents to the inclusion in this announcement of the matters based on the information in the form and context in which it appears.
Some statements in this document may be forward-looking statements. Such statements include, but are not limited to, statements with regard to capacity, future production and grades, projections for sales growth, estimated revenues and reserves, targets for cost savings, the construction cost of new projects, projected capital expenditures, the timing of new projects, future cash flow and debt levels, the outlook for minerals prices, the outlook for economic recovery and trends in the trading environment and may be (but are not necessarily)
Meteoric Resources July 2025 Preliminary Feasibility Study
Page 24 of 41
==> picture [595 x 39] intentionally omitted <==
==> picture [595 x 39] intentionally omitted <==
identified by the use of phrases such as “will”, “expect”, “anticipate”, “believe” and “envisage”.
By their nature, forward-looking statements involve risk and uncertainty because they relate to events and depend on circumstances that will occur in the future and may be outside Meteoric’s control. Actual results and developments may differ materially from those expressed or implied in such statements because of a number of factors, including levels of demand and market prices, the ability to produce and transport products profitably, the impact of foreign currency exchange rates on market prices and operating costs, operational problems, political uncertainty and economic conditions in relevant areas of the world, the actions of competitors, activities by governmental authorities such as changes in taxation or regulation.
Meteoric Resources July 2025 Preliminary Feasibility Study
Page 25 of 41
==> picture [595 x 39] intentionally omitted <==
==> picture [595 x 39] intentionally omitted <==
APPENDIX 3: JORC Table 1
Section 1 Sampling Techniques and Data (Criteria in this section apply to all succeeding sections.)
==> picture [499 x 691] intentionally omitted <==
----- Start of picture text -----
Criteria Commentary
Sampling The resources were sampled using: a powered auger drill machine (open hole), a diamond drill machine and an Aircore
techniques drill machine.
Auger (AUG) drill holes
o Each drill site was cleaned, removing leaves and roots from the surface. Tarps were placed on either side of the
hole and samples of soil and saprolite where collected every 1m of advance, logged, photographed with subsequent
bagging of the sample in plastic bags.
Diamond (DD) drill holes
o The intact drill cores are collected in plastic core trays with depth markers recording the depth at the end of each
drill run (blocks).
o Samples were collected at 1m intervals. In the saprolite zone the core is halved with a metal spatula and bagged
in plastic bags, the fresh rock was halved by a powered saw and bagged.
Aircore (AC) drill holes
o Two (2) metre composite samples are collected from the cyclone of the rig in plastic buckets. The material from
the plastic buckets is passed through a single tier, riffle splitter which generates a 50/50 split. One half is bagged
and numbered for submission to the laboratory, and the other half bagged and given the same number, then
stored as a duplicate at the core facility in Pocos de Caldas.
Drilling Powered Auger
techniques o Powered auger drilling employed a motorised post hole digger with a 4 inch diameter. All holes were drilled
vertical. The maximum depth achievable was 20m, providing the hole did not encounter fragments of
rocks/boulders within the weathered profile and/or excessive water. Final depths were recorded according to the
length of rods in the hole.
Diamond Core
o Diamond drilling employed a conventional wireline diamond drill rig (Mach 1200). All holes were drilled vertical
using PQ diameter core through soils and clays (85mm core diameter), reducing to HQ through transition material
and fresh rock (63.5mm core diameter). The maximum depth drilled was 48.1m. The final depth was recorded
using the length of the rods in the hole.
Aircore
o Drilling was completed using a HANJIN 8D Multipurpose Track Mounted Drill Rig, configured to drill 3-inch Aircore
holes. The rig is supported by an Atlas Copco XRHS800 compressor which supplies sufficient air to keep the
sample dry down to the current deepest depth of 73m. All holes are drilled vertical.
o Most drill sites require minimal to no site preparation. On particularly steep sites, the area is levelled with a
backhoe loader.
o Drilling is stopped at 'blade refusal' when the rotating bit is unable to cut the ground any further. This generally
occurs in the transition zones (below clay zone and above fresh rock). On occasions a face sampling hammer is
used once 'blade refusal' is reached to penetrate through the remaining transition zone and into the fresh rock.
Drill Auger sample recovery
sample o Estimated visually based on the amount of sample recovered per 1m interval drilled. Recoveries were generally
recovery in a range from 75% - 100%. If estimates dropped below 75% recovery in a 1m interval, the field crew aborted the
drill hole and redrilled the hole.
Diamond drill hole recovery
o Calculated after each run, comparing length of core recovery vs. drill depth. Overall core recoveries are 92.5%,
achieving 95% in the saprolite target horizon, 89% in the transition zone and 92.5% in fresh rock.
Aircore recovery
o Every 2m composite sample is collected in plastic buckets and weighed. Each sample averages approximately
12kg. This is considered acceptable given the hole diameter and specific density of the material.
Logging Auger drilling ,
o Material is described in a drilling bulletin every 1m and photographed. The description is made according to the
tactile-visual characteristics, such as material (soil, colluvium, saprolite, rock fragments); material color;
predominant particle size; presence of moisture; indicator minerals; extra observations.
Diamond drilling
o Geology description is made in a core facility, focused on the soil (humic) horizon, saprolite, transition zone and
fresh rock boundaries. The geology depth is honored and described with downhole depth (not metre by metre).
Parameters logged include: grainsize, texture and colour, which can help to identify the parent rock before
weathering.
o All drill holes are photographed and stored at Core facility in Pocos de Caldas.
Aircore drilling
o The material is logged at the drill rig by a geologist. Logging focused on soil (humic) horizon, saprolite/clay zones
and transition boundaries. Other parameters recorded includes: grainsize, texture and colour, which can help to
identify the parent rock before weathering.
o Logging is done on 2m intervals due to the nature of the drilling with 2m composite samples collected in a bucket
and presented for sampling and logging.
o The chip trays of all drilled holes have a digital photographic record and are retained at a Core facility in Pocos de
Caldas.
Sub- Auger material
sampling o Samples are weighed and if the samples are wet, they are dried for several days on rubber mats. After drying the
techniques samples are screened (5mm). Homogenization occurs by agitation in bags, followed by screening to <3mm.
and Fragments of rock or hardened clay that are retained in the sieves are fragmented with a 10kg manual
sample disintegrator and a 1kg hammer, until 100% of the sample passes through the screening. The sample is
preparation homogenized again by agitation in bags. Finally, the sample is Split in a Jones 12 channel splitter, where 500g is
----- End of picture text -----
Meteoric Resources July 2025 Preliminary Feasibility Study
Page 26 of 41
==> picture [595 x 39] intentionally omitted <==
==> picture [595 x 39] intentionally omitted <==
==> picture [499 x 721] intentionally omitted <==
----- Start of picture text -----
Criteria Commentary
sent to the lab (SGS_geosol laboratory in Vespasiano – Minas Gerais).
o Remaining samples are placed in 20-liter plastic buckets, clearly labelled by Hole ID and depth, and stored in
shed facility in Pocos de Caldas.
Diamond cores
o In the saprolite zone the core is halved with a metal spatula and bagged in plastic bags
o The fresh rock was halved by a powered saw and bagged into a plastic bag with a unique sequential number of
samples and sent to ALS laboratory in Vespasiano – Minas Gerais.
o Field duplicates consist of quarter core, with both quarters sent to the lab.
Aircore material
o Samples are weighed at the Rig. When the sample > 6kg it passes through a single tier Riffle splitter generating
a 50/50 split, one for ALS Laboratory and a duplicate which is retained in core facility. Samples are bagged in
plastic bags with unique tag for the interval.
o Given the grainsize if the mineralisation is extremely fine (clays) and shows little variability, the practice of
submitting 50% of original sample for analysis is deemed appropriate.
o Field Duplicates are routinely submitted and results analysed by examining the correlation between original and
duplicate samples. More than 90% of duplicates show <20% variance.
Quality of Auger samples were analysed at SGS Geosol laboratory in batches of 43 samples, 37 of which belong to exploration
assay data intervals and 6 are QA/QC samples (duplicate, blank and standards).
and o The sample preparation method employed was PRP102_E: the samples are dried at 100°C, crushed to 75% less
laboratory than 3 mm, homogenized and passed through a Jones riffle splitter (250g to 300g). This aliquot was then
tests pulverized in a steel mill to the point at which over 95% had a size of 150 microns.
o Analysis followed by IMS95A to determine the Rare Earth Elements. With this method, samples are melted with
lithium metaborate and read using the ICP-MS method, the limits or which are shown below.
Diamond and Aircore samples are analysed by ALS Laboratories (accredited) in Batches up to 72 samples. Upon
arriving at ALS Vespasiano samples receive additional preparation (drying, crushing, splitting, and pulverising):
o dried at 60°C
o the fresh rock is crushed to sub 2mm
o the saprolite is disaggregated with hammers
o Riffle split 800g sub-sample
o 800 g pulverized to 90% passing 75um, monitored by sieving.
o Aliquot selection from pulp packet
The aliquot obtained from the physical preparation process at Vespasiano is sent to ALS Lima or analysis by ME-MS81 –
which consists of analysis of Rare Earths and Trace Elements by ICP-MS for 32 elements by fusion with lithium borate as
seen below (with detection limits):
Code Analytes & Ranges (ppm)
Ba 0.5 - 10000 Gd 0.05 - 1000 Rb 0.2 - 10000 Ti 0.01 - 10%
Ce 0.1 - 10000 Hf 0.5 - 10000 Sc 0.5 - 500 Tm 0.01 - 1000
Cr 5 - 10000 Ho 0.01 - 10000 Sm 0.03 - 1000 U 0.05 - 1000
Cs 0.01 - 10000 La 0.1 - 10000 Sn 0.5 - 10000 V 5 - 10000
ME-MS81
Dy 0.05 - 1000 Lu 0.01 - 10000 Sr 0.1 - 10000 W 0.5 - 10000
Er 0.03 - 1000 Nb 0.05 - 2500 Ta 0.1 - 2500 Y 0.1 - 10000
Eu 0.02 - 1000 Nd 0.1 - 10000 Tb 0.01 - 1000 Yb 0.03 - 1000
Ga 0.1 - 10000 Pr 0.02 - 10000 Th 0.05 - 1000 Zr 1 - 10000
MEI QAQC protocols demand duplicate sample every 20 samples, and a blank and standard sample in each 30
samples. In addition, ALS inserted their own internal reference check samples as well as conducting repeat analysis.
Results show: 94.94% of Standards are within tolerance limits, 99.96% of Blanks are within tolerance limits, and only
4.92% of Duplicate samples showed >30% variation for the Original result.
Verification Given the nature of the ionic clay mineralisation visual checks are not appropriate for verification of mineralised intercepts.
of MEI completed several rounds of Twin Hole drilling:-
sampling o DD drill holes twinning historic Auger holes
and o A total of 32 DD holes were drilled to twin historic Auger holes and confirm the reported widths and grades
assaying across the 6 resource areas (February 2023 - January 2024). Results confirmed the width and general nature
of high-grade TREO mineralization, showing a slight (14%) Positive Bias in Auger results compared to DD
results. The apparent Bias is not considered significant.
o AC holes twinning existing DD holes
o A total of 17 AC holes were drilled at Soberbo, Capão do Mel and Figueira deposits to twin existing DD drill
holes and assess AC as a sampling method (March 2023 – March 2024). Results confirmed the width and
-
general nature of high grade TREO mineralization, showing a slight (20%) Negative Bias in AC results
----- End of picture text -----
Meteoric Resources July 2025 Preliminary Feasibility Study
Page 27 of 41
==> picture [595 x 39] intentionally omitted <==
==> picture [595 x 39] intentionally omitted <==
==> picture [499 x 729] intentionally omitted <==
----- Start of picture text -----
Criteria Commentary
compared to DD results. The apparent Bias is not considered significant.
For historic Auger holes, collar co-ordinates are recorded, and holes were logged and photographed at the drill site prior
to information being transferred into Excel Spreadsheets back at the office. Drilling data is kept in Excel Spreadsheets
in a well organised structure of file folders on a local network and in the ‘Cloud’. The original paper logging sheets were
not retained.
For all drilling conducted by MEI (DD and AC), data is recorded into MX Deposit tables (collar, survey, geology,
sample) using tablets/laptops at the Aircore Rig or in the Core Shed. Files are forwarded via email by Geologists to
Database manager for uploading into the Database. The data is stored in MX Deposit database (Sequent). Data
validation is turned ON during the import of data avoiding errors.
Raw assays are received as Elemental data (ppm) from ALS laboratories. The Elemental data is converted to
Element Oxide data using the following conversion factors:
Element Oxide Oxide Factor Element Oxide Oxide Factor
CeO2 1.2284 Pr6O11 1.2082
Dy2O3 1.1477 Sm2O3 1.1596
Er2O3 1.1435 Tb4O7 1.1762
Eu2O3 1.1579 ThO2 1.1379
Gd2O3 1.1526 Tm2O3 1.1421
Ho2O3 1.1455 U3O8 1.1793
La2O3 1.1728 Y2O3 1.2699
Lu2O3 1.1728 Yb2O3 1.1387
Nd2O3 1.1664
Location of Auger drill collars
data points o All holes were picked up by Nortear Topografia e Projectos Ltda., planialtimetric topographic surveyors. The GPS
South Galaxy G1 RTK GNSS was used, capable of carrying out data surveys and kinematic locations in real time
(RTK-Real Time Kinematic), consisting of two GNSS receivers, a BASE and a ROVER. The horizontal accuracy,
in RTK, is 8mm + 1ppm, and vertical 15mm + 1ppm.
o The coordinates were provided in the following formats: Sirgas 2000 datum, and UTM WGS 84 datum -
georeferenced to spindle 23S.
Diamond and Aircore collars
o The survey was made by MEI personal using a GPS CHCNAV i73 RTK GNSS capable of carrying out data surveys
and kinematic locations in real time (RTK-Real Time Kinematic), consisting of two GNSS receivers, a BASE and a
ROVER. The horizontal accuracy, in RTK, is 8mm +/- 1mm, and vertical 15mm +/- 1mm.
Topography imaging survey
Capao do Mel, Soberbo, Figueira
o A detailed imaging and topographic survey was done by GeoSense Engenharia e Geotecnologia Ltda. The survey
was done using a DJI Matrice 300 RTK drone with vertical accuracy with 0.1metre and horizontal accuracy of
0.3metre using visual system. Using the GPS system the vertical accuracy is 0.5metre and horizontal accuracy is
1.5metre. Using the RTK system the vertical accuracy is 0.1metre and horizontal accuracy is 0.1metre.
o A on board LiDAR Alpha Air 450 sensor was used which has a range of 450 metres, accuracy of 15mm, acquisition
tax of 240,000 points per second (first pass), 480,000 points per second (second pass) and 720,000 points per
second (third pass), equipped with a Sony A5100 camera with 26 Mega Pixels and an integrated GNSS receptor
(L1L2).
o For the base points it was used a GPS CHCNAV i73 RTK GNSS capable of carrying out data surveys and kinematic
locations in real time (RTK-Real Time Kinematic), consisting of two GNSS receivers, a BASE and a ROVER. The
horizontal accuracy, in RTK, is 8mm +/- 1mm, and vertical 15mm +/- 1mm.
Barra do Pacu
o A detailed imaging and topographic survey was done by Topografia Pedro Ernestto Ltda. The survey was done
using a DJI Matrice 350 RTK drone with vertical accuracy with 0.1meter and horizontal accuracy of 0.15meter using
visual system.
o An onboard Zenmuse L2 LiDAR sensor was used which has a range of 450 meters, accuracy of 15mm, acquisition
tax of 240,000 points per second and multiple return of1,200,000 points per second, equipped with a CMOS sensor
camera with 20 Mega Pixels and an integrated GNSS receptor (L1L2).
o For the base points it was used a GPS CHCNAV i73 RTK GNSS capable of carrying out data surveys and kinematic
locations in real time (RTK-Real Time Kinematic), consisting of two GNSS receivers, a BASE and a ROVER. The
horizontal accuracy, in RTK, is 8mm +/- 1mm, and vertical 15mm +/- 1mm.
Data Hole spacing for Auger holes varies across the prospect scale from a maximum of: 200m by 200m, infill drilled to 100m
spacing by 100m, with tighter spacing of 50m by 50m in the closest space areas. Aircore drilling was done at a nominal 100m x
and 100m, infill drilled to 50m x 50m in areas of high grade in the 2023 Inferred Resource. Diamond holes had no regular
distribution spacing but were designed to target specific geologic characteristics (i.e. grade, density).
Given the substantial geographic extent and generally shallow, flat lying geometry of the mineralisation, the spacing and
orientation are considered sufficient to establish geologic and grade continuity.
Sample compositing:
o Auger samples were collected at 1.0m composites.
o Diamond samples were collected at 1.00m composites, respecting the geological contacts.
o Aircore samples were collected at 2.00m composites.
Orientation The mineralisation is flat lying and occurs within the saprolite/clay zone of a deeply developed regolith (reflecting
of data in
----- End of picture text -----
Meteoric Resources July 2025 Preliminary Feasibility Study
Page 28 of 41
==> picture [595 x 39] intentionally omitted <==
==> picture [595 x 39] intentionally omitted <==
| Criteria | Commentary | |
|---|---|---|
| relation to geological structure |
topography and weathering). Vertical sampling from all sampling methods is considered most appropriate. | |
| Sample security |
|
Auger samples:oSamples were removed from the field by Company staff and transported back to a facility in Poços de Caldas. From here the samples are packed in plastic bags and transported to SGS-Geosol in Belo by a commercial Transport Company. oThe remaining sample is stored in 20 litre plastic buckets, labelled with the name of the target, hole name and sampled intervals. Samples are securely locked up in the storage shed. Diamond samples: oSamples are removed from the field by MEI staff and transported back to a Core shad to be logged and sampled. All samples for submission to the lab are packed in plastic bags (in batches) and sent to the lab where it is processed as reported above. The transport of samples from Poços de Caldas to ALS laboratory in Vespasiano was undertaken by a commercial Transport Company. Aircore samples: oSamples are split and bagged in the field and transported back to a Core shed. All samples for submission to the lab are packed in plastic bags (in batches) and despatched to ALS laboratory in Vespasiano using a commercial Transport Company. |
| Audits or | | MEI conducted a review of assay results as part of its Due Diligence prior to acquiring the project. Approximately 5% of |
| reviews | all stored coarse rejects from auger drilling were resampled and submitted to two (2) labs: SGS Geosol and ALS | |
| Laboratories. Results verified the existing assay results, returning values +/-10% of the original grades, well within | ||
| margins of error for the grade of mineralisation reported. (see ASX:MEI 13/03/23 for a more detailed discussion) | ||
| | A site visit was carried out by Volodymyr Myadzel from BNA Mining Solutions on 19-20 February 2024 to: inspect drilling | |
| and sampling procedures, verify survey methods, inspect the storage shed, verification of geological records, review of | ||
| QAQC procedures and review of geologic model. |
Section 2 Reporting of Exploration Results (Criteria in this section apply to all succeeding sections)
==> picture [483 x 424] intentionally omitted <==
----- Start of picture text -----
Criteria Commentary
Mineral tenement and Listed in Appendix 4.
land tenure status Given the rich history of mining and current mining activity in the Poços de Caldas there appears to be
no impediments to obtaining a License to operate in the area.
Exploration done by The Caldeira Project has had significant exploration in the form of surface geochem across 30 granted
other parties mining concessions, plus: geologic mapping, topographic surveys, and powered auger (1,396 holes for
12,963 samples).
MEI performed Due Diligence on historic exploration and are satisfied the data is accurate and correct
(refer ASX Release 13 March 2023 for a discussion).
Geology The Alkaline Complex of Poços de Caldas represents in Brazil one of the most important geological
terrains which hosts deposits of bauxite, clay, uranium, zirconium, rare earths and leucite. The different
types of mineralization are products of a history of post-magmatic alteration and weathering, in the last
stages of its evolution (Schorscher & Shea, 1992; Ulbrich et al., 2005).
The dominant REE mineral in the source rock (syenite) beneath the clay zone is Bastnaesite, a major
source of REE worldwide. Bastnaesite is a REE carbonate-fluoride mineral (REE)CO3F and has very
low levels of U and Th in its structure. Due to the chemistry of the underling intrusives and the intense
weathering of the region, a thick profile comprising soil, clay and saprolite (regolith) has formed (Figures
1, 6, and 7), and these are the hosts to the ionic clay REE mineralization.
The deposits are recognized as Ionic Adsorption Clays, where the Rare Earth Elements ions are trapped
by the surface or between the layers of the clays and these REE are easily leached with a moderate
acid substance.
Drill hole Information Information for all Auger holes was reported in a previous ASX Release on 01 May 2023 “Caldeira REE
Project Maiden Mineral Resource”.
Information for Soberbo drill holes was reported in a previous ASX Release on 13 May 2024, “150%
Increase in Soberbo Mining Licence Mineral Resource”.
Information for Capao do Mel drill holes was reported in a previous ASX Release on 12 June 2024,
“Capao do Mel Resource Update Doubles Caldeira M&I Resources”.
Information for Figueira drill holes was reported in a previous ASX Release on 04 August 2024, “Updated
Figueira Mineral Resources Estimate”.
Information for Barra do Pacu drill holes was reported in a previous ASX Release on 14 April 2025,
“Barra do Pacu Resource Adds Strategic High-Grade Rare Earths”.
Data aggregation Mineralised Intercepts are reported with a minimum of 4m width, lower cut-off 1,000ppm TREO, with a
methods maximum of 2m internal dilution.
High-Grade Intercepts reported as “including” are reported with a minimum of 2m width, lower cut-off
3,000 ppm TREO, with a maximum of 1m internal dilution.
Extreme High-Grade Intercepts reported as “with” are reported with a minimum of 2m width, lower cut-
off 10,000 ppm TREO, with a maximum of 1m internal dilution.
No Metal Equivalents are used.
Mineralisation widths All holes are vertical and mineralisation is developed in a flat lying clay and transition zone within the
and intercept lengths regolith. As such, reported widths are considered to equal true widths.
----- End of picture text -----
Meteoric Resources July 2025 Preliminary Feasibility Study
Page 29 of 41
==> picture [595 x 39] intentionally omitted <==
==> picture [595 x 39] intentionally omitted <==
==> picture [483 x 231] intentionally omitted <==
----- Start of picture text -----
Criteria Commentary
Diagrams Reported in the body of the text.
Balanced reporting Significant Intercepts for all Auger drill holes were reported in a previous ASX Release on 01 May 2023
“Caldeira REE Project Maiden Mineral Resource”.
Significant Intercepts for Soberbo drill holes was reported in a previous ASX Release on 13 May 2024,
“150% Increase in Soberbo Mining Licence Mineral Resource”.
Significant Intercepts for Capao do Mel drill holes was reported in a previous ASX Release on 12 June
2024, “Capao do Mel Resource Update Doubles Caldeira M&I Resources”.
Significant Intercepts for Figueira drill holes was reported in a previous ASX Release on 04 August 2024,
“Updated Figueira Mineral Resources Estimate”.
Significant Intercepts for Barra do Pacu drill holes was reported in a previous ASX Release on 14 April
2025, “Barra do Pacu Resource Adds Strategic High-Grade Rare Earths”.
Other substantive Preliminary metallurgical testwork was carried out on samples split from a 200kg composite sample,
exploration data which in turn was composed of a selection of 184 samples from 41 holes (100 x100m grid) across the
Capo do Mel Target. Head grade of the composite sample was 4,917ppm TREO. Results showed
excellent recoveries by desorption of Rare Earth Elements (REE) using ammonium sulfate solution
[(NH4)2SO4)] in weakly acidic conditions [pH 4]. Average recovery of the Pr + Nd was 58%.
Desorption was achieved using a standard ammonium sulfate solution at pH 4 and confirms the
Caldeira Project is an Ionic (Adsorption) Clay REE deposit (for further discussion refer ASX Release
20 December 2023).
Further work Proposed work is discussed in the body of the text.
----- End of picture text -----
Section 3 Estimation & Reporting of Mineral Resources (Criteria in this section apply to all succeeding sections.)
| Criteria | Commentary | |
|---|---|---|
| Database integrity | |
All data was imported into Micromine Software. The databases were validated using specific processes to verify the existence of the errors listed below: oThe drill hole’s name is present in the collar file but is missing from the analytical database; oThe drill hole’s name is present in the analytical database, but is absent in the collar file; oThe drill hole’s name appears repeated in the analytical database and in the collar file; oThe drill hole’s name does not appear in the collar file and in the analytical database; oOne or more coordinate notes are absent from the collar file; oFROM or TO are not present in the analytical database; oFROM > TO in the analytical database; oSampling intervals are not continuous in the analytical database (there are gaps between the logs); oSampling intervals overlap in the analytical database; oThe first sample does not correspond to 0 m in the analytical database; oThe hole total depth is shallower than the depth of the last sample. Random checks of the original data as received from SGS-Geosol and ALS laboratories was compared with the provided database and no errors were found. |
| Site visits | | A site visit was carried out by Volodymyr Myadzel from BNA Mining Solutions on 19-20 February 2024 to: inspect drilling and sampling procedures, verify survey methods, inspect the storage shed, verification of geological records, review of QAQC procedures and review of geologic model. |
| Geological interpretation |
Confidence in the geological interpretation of the rare earth mineralization in clay and saprolite is very high as drilling activities used a regular and relatively close-spaced drill spacing. Where there is no information from Diamond or Aircore drill holes (which drill to transition/fresh rock), and mineralisation was present at the end of Auger drill holes (in areas of known deep weathering), the mineralisation was assumed to extend 2m below the hole. Factors affecting rare earth mineralisation in saprolite rocks include the degree of weathering of primary rocks and variations in mineralization. These were detailed in Diamond, Aircore, and Auger drilling from surface and into the fresh rock. |
|
| Dimensions | |
The Mineral Resources have the following dimensions:oSoberbo - 2,600m x 3,800m in NE-SW direction oCapao do Mel - 2,600m x 3,800m in NE-SW direction oFigueira - 2,600m x 1,200m in N-S direction oBarra do Pacu - 1,900m x 4,000m in N-S direction. The top of the rare earth element mineralization is generally the topographic surface. |
| Estimation and | | The results are based on a block model interpolated by Ordinary Kriging (OK) method, using Micromine |
| modelling techniques | software. Ordinary Kriging was selected as the method for grade interpolation as the sample data has | |
| a log-normal distribution represented by a single generation. | ||
| | All analyzed elements were interpolated to the empty block model using Ordinary Kriging (OK) and | |
| IDW3 (Inverse Distance Weighting with inverse power 3) methods. The IDW3 method was used for | ||
| control and comparison. | ||
| | The grade estimation was performed in four consecutive passes (rounds) using different sizes of | |
| search radius, criteria of number of composite samples, and number of holes. |
Meteoric Resources July 2025 Preliminary Feasibility Study
Page 30 of 41
==> picture [595 x 39] intentionally omitted <==
==> picture [595 x 39] intentionally omitted <==
Criteria
==> picture [98 x 603] intentionally omitted <==
Commentary
| Search Ellipse parameters by Pass (all Deposits). | Search Ellipse parameters by Pass (all Deposits). | Search Ellipse parameters by Pass (all Deposits). | ||
|---|---|---|---|---|
| Pass | Search Ellipse (size factor) |
Min. No. Composites |
Max. No. Composites |
Min. No. Drill Holes |
| 01 | 0.667 | 4 | 3 | 2 |
| 02 | 1 | 2 | 3 | 2 |
| 03 | 2 | 2 | 3 | 1 |
| 04 | 100 | 1 | 3 | 1 |
-
Column ‘Min No. Composites’ is the minimum number of composites required for each of the estimation passes. Column ‘Max No. Composites’ is the maximum number of samples allowed for each of the four sectors of the ellipsoid used for the elements’ estimation process.
-
The Block Model created in the process of discretization of the wireframes using the sub-blocking process. Initially, the model was filled with blocks measuring 25 (X) by 25 (Y) by 5 (Z) meters, which were divided into subunits of smaller size, with a factor for size subdivision of 10 by 10 by 5 in contact with the surrounding three-dimensional wireframes.
-
The radii and the orientation of search ellipse were determined using standard variograms. The limitations presented by each sector of a search ellipse were: the maximum number of points in the sector and the minimum total number of points in the interpolation that varies depending on the size of the ellipse, from 3 to 1. Thus, the maximum total number of samples involved in the interpolation was 12 samples.
Radii of Search Ellipsoid by element.
==> picture [360 x 165] intentionally omitted <==
----- Start of picture text -----
Element SOB CDM FIG BDP
X Y Z X Y Z X Y Z X Y Z
La (ppm) 130 90 15 130 90 15 210 125 20 230 220 20
Ce (ppm) 130 90 15 130 90 15 150 110 20 230 230 20
Pr (ppm) 130 90 15 130 90 15 210 125 20 230 220 20
Nd (ppm) 130 90 15 130 90 15 210 125 20 230 220 20
Sm (ppm) 130 90 15 130 90 15 210 125 20 230 220 20
Eu (ppm) 130 90 15 130 90 15 210 125 20 230 220 20
Gd (ppm) 130 90 15 130 90 15 210 125 20 230 220 20
Tb (ppm) 130 90 15 130 90 15 210 125 20 230 220 20
Dy (ppm) 130 90 15 130 90 15 210 125 20 230 180 20
Ho (ppm) 130 90 15 130 90 15 210 125 20 230 180 20
Er (ppm) 130 90 15 130 90 15 210 125 20 230 220 20
Tm (ppm) 130 90 15 130 90 15 210 125 20 230 180 20
Yb (ppm) 130 90 15 130 90 15 210 125 20 230 220 20
Lu (ppm) 130 90 15 130 90 15 210 125 20 230 180 20
Y (ppm) 130 90 15 130 90 15 210 125 20 230 220 20
Th (ppm) 125 85 10 125 85 10 180 180 30 230 230 30
U (ppm) 125 85 10 125 85 10 180 140 20 240 240 20
----- End of picture text -----
Orientation of Azimuth of the search ellipsoid for every element (Dip = 0, Plunge = 0 for all
elements in all Deposits).
==> picture [322 x 157] intentionally omitted <==
----- Start of picture text -----
Element (ppm) SOB CDM FIG BDP
La 42 42 138 12
Ce 42 42 102 48
Pr 42 42 138 12
Nd 42 42 138 12
Sm 42 42 138 12
Eu 42 42 138 12
Gd 42 42 138 12
Tb 42 42 138 12
Dy 42 42 138 12
Ho 42 42 138 12
Er 42 42 138 12
Tm 42 42 138 0
Yb 42 42 138 0
Lu 42 42 138 12
Y 42 42 138 12
Th 144 144 108 108
U 144 144 132 144
----- End of picture text -----
-
The block model was validated in several ways: by running and Inverse Distance Weighted interpolation and comparing the results, and by comparing the means and standard deviations of the block grades to the composite data set.
-
Moisture All estimations are reported as a dry tonnage.
-
Cut-off parameters Cut-off grades for TREO were used to prepare the reported resource estimates. The selection of the cut-off was based on the experience of the Competent Person, plus a peer review of publicly available information from more advanced projects with comparable mineralisation styles (i.e clay and transition zone hosted rare earth mineralisation) and comparable conceptual processing methods.
-
The chosen cut-off grade of 1,000 ppm TREO is consistent with this.
-
Mining factors or The selected mining method will be open cut utilising truck and excavator in free digging the clay assumptions material. No drill and blast will be required.
Meteoric Resources July 2025 Preliminary Feasibility Study
Page 31 of 41
==> picture [595 x 39] intentionally omitted <==
==> picture [595 x 39] intentionally omitted <==
Commentary
-
Criteria
-
Metallurgical factors or The Caldeira Project is an ionic adsorption clay-hosted rare earth deposit, a mineralisation style that assumptions allows for low-cost, simple metallurgical processing. The proposed metallurgical process involves leaching with ammonium sulfate (AMSUL) at pH 5, followed by impurity removal using ammonium bicarbonate (BICARB) to produce a Mixed Rare Earth Carbonate (MREC). This process is highly appropriate for the mineralisation type, as ionic adsorption clay deposits allow for selective rare earth extraction at ambient temperature and pressure without complex beneficiation techniques such as flotation or roasting.
-
The metallurgical process incorporates a suite of well-established and mature unit operations, including scrubbing, desorption, counter-current decantation (CCD), pressure filtration, reverse osmosis, nanofiltration, and other dewatering technologies. These technologies are widely used across various mineral processing and chemical industries and are considered proven in terms of operational reliability and scalability. However, while these individual components are mature, their integration into a single flowsheet tailored specifically for rare earth ionic clay deposits is considered novel. To date, there are no known commercial operations outside of China that have successfully achieved design throughput and recovery targets for such deposits. The innovative sequencing and configuration of these unit operations in the proposed flowsheet represent a unique approach to processing ionic clays, designed to optimise recovery and manage the specific challenges associated with these ore types.
-
Extensive metallurgical test work has been conducted by the Australian Nuclear Science and Technology Organisation (ANSTO) to characterise the metallurgical response across all tenements included in the PFS. Representative bulk composite samples were prepared for each tenement ensuring coverage of orebody variability. To date, 320 diagnostic leach tests and 32 bulk slurry leach tests have been completed by ANSTO. Additionally, a 2.5-tonne composite sample, derived from 154 air core drill holes and representative of the first five years of production from the CDM starter pit, was used in a 15-day continuous pilot plant trial at ANSTO.
-
Testwork covers the full range of domains/lithologies—soil, clay, transition, and hard rock—both laterally and at depth.
-
Individual rare earth oxide recoveries were determined from the testwork (below). This equates to global average recoveries of 55% TREO and 71% Magnetic REO. These recovery factors have been statistically validated against a broad set of randomised diagnostic leach tests, confirming their robustness and applicability across the mine plan.
==> picture [364 x 76] intentionally omitted <==
----- Start of picture text -----
Deposit La Ce Pr Nd Sm Eu Gd Tb Dy Ho Er Tm Yb Lu Y
CDM 76 0.3 74 73 65 61 64 52 50 43 37 33 25 24 50
BDP 76 0.3 74 73 65 61 64 52 50 43 37 33 25 24 50
SOB 71 5 66 68 62 62 61 55 51 49 48 44 43 25 51
FIG 71 5 69 72 69 69 66 58 53 48 44 32 23 20 55
----- End of picture text -----
-
All drill samples are assayed for deleterious elements and the distribution analysed throughout the resource. Mixed Rare Earth Carbonate (MREC) product was also assayed for deleterious elements. Feedback from potential off-take partners and customers has not identified any concerns regarding deleterious elements in the MREC. A detailed composition of the final MREC product, including impurity levels (2% by weight), was publicly released on 29 February 2024. This composition meets market expectations and specifications. Furthermore, the recent pilot plant campaign conducted at ANSTO successfully validated the quality of the MREC product, confirming that deleterious elements are effectively managed within the proposed flowsheet and do not pose a risk to product acceptance or downstream processing.
-
A comprehensive bulk sampling and pilot-scale test program has been undertaken to validate the metallurgical performance and representativeness of the orebody. A 2.5-tonne bulk sample was compiled from 154 air core drill holes. This sample was selected to reflect the lithological and grade variability expected in the first five years of production. This sample was processed through a 15-day continuous pilot plant campaign at ANSTO and successfully demonstrated the operational viability of the proposed flowsheet and confirmed the consistency of metallurgical recovery and product quality.
-
This pilot-scale validation provides a high level of confidence in the scalability of the process and the reliability of recovery assumptions used in the PFS.
-
Detailed mineralogical and metallurgical studies of representative samples from the deposits confirm the presence of ion-adsorbed rare earth elements (REEs) within a clay matrix. Mineralogical characteristics include a dominance of kaolinite-hosted ion-adsorbed REEs and the absence of significant refractory REE minerals. The low acidity (pH 4.5 – 5) leach results and very low levels of deleterious elements such as Al, Fe, U in the leach liquor that need to be neutralised., support the ability to meet market specifications for MREC. Only those zones with demonstrated leachability and acceptable impurity profiles (appropriate mineralogy) have been included in the Ore Reserve estimate.
-
Environmental factors or There are two Environmental areas within the municipality of Caldas which encroach upon the current assumptions resources at Soberbo, Capão do Mel, and Barra do Pacu (Figure 1), being:
-
(i) Environmental Protection Area ( APA ) Ecological Sanctuary of Serra da Pedra Branca (established by Municipal Law of Caldas/MG nº 1.973/2006) and
-
(ii) a three (3) kilometre strip surrounding the APA ( Buffer Zone ).
-
Part of the Soberbo ( SB ) resource is within the APA whilst the remaining (larger) part of SB, the entire Capao do Mel ( CDM ) resource, and 80% of Barra do pacu ( BDP ) are within the Buffer Zone.
Meteoric Resources July 2025 Preliminary Feasibility Study
Page 32 of 41
==> picture [595 x 39] intentionally omitted <==
==> picture [595 x 39] intentionally omitted <==
==> picture [483 x 479] intentionally omitted <==
----- Start of picture text -----
Criteria Commentary
Article 51 of Law of Caldas/MG nº 1.973/2006 stipulates that mining activity is currently not permitted within
the APA (other than for existing activity with operating licenses). The current PFS development scenario
and Preliminary Environmental Permit (LP) application do not propose any activity inside the APA area.
Mining activity within the Buffer Zone is permitted and may be undertaken upon completion of an
Environmental Impact Assessment ( EIA ), a proposal of measures necessary to mitigate any possible
impact on ecosystems, a Certificate of Regularity for Land Use and Occupation from the municipality of
Caldas Municipal Environmental Council ( CODEMA ), and authorization of the APA Management Council
(outstanding).
Meteoric has conducted extensive research and consultation from mid-2023 with the object of seeking and
obtaining permission to conduct activities in the Buffer Zone and is confident of obtaining favourable
consideration from the relevant authorities. That confidence is based upon: Environmental Impact
Statement (EIS) and relevant flora and fauna and ethnographic studies completed over the area, ongoing
dialogue and consultation with multiple stakeholders including favourable feedback from a Social Diagnosis
and Stakeholder Survey of the Caldeira REE Project conducted by EcoDue Ambiental in December 2023,
and specifically by reason of the terms of a written Protocol of Intent entered into between the Government
of Minas Gerais and Meteoric Brazil [See ASX Announcement “Cooperation Agreement Signed with
Government of Minas Gerais and Invest Minas” - 11 August 2023].
As such we consider there are reasonable prospects for eventual economic extraction to justify the Mineral
Classifications of Measured and Indicated Resources (within the Buffer Zone), and the subsequent
Probable Reserves.
Bulk density Bulk Densities were calculated by ALS Laboratories analysing a bulk sample using method OA-
GRA09a. Diamond drill hole intervals representative of the entire profile (clay, transition, fresh) were
selected and the entire core was wrapped in plastic to maintain moisture and shipped to ALS.
Once received by ALS the core section is weighed (wet), unwrapped and dried at 105ºC for 12 hours,
then weighed again (dry), before being covered in a paraffin wax coat and weighed in the presence of
air. The sample is then weighed while it is suspended in water. The specific gravity is calculated using
the following equation:
S.G. = A .
B - C - [ ( B - A ) / D ]
where: A = weight of sample in air, B = weight of waxed sample in air, C = weight of waxed sample
suspended in water, and D = density of wax
Classification The Mineral Resources for the project have been classified as Measured, Indicated and Inferred.
The Competent Person is satisfied that the classification is appropriate based on: current drill hole
spacing, geological continuity, variography, and bulk density data available for the project.
Audits or reviews As yet there have been no third-party audits or reviews of the mineral resource estimates.
Discussion of relative The block model with interpolated grades was subject to visual and statistical verification. Histograms
accuracy/ confidence and probability graphs of the interpolated grades were built. Then, the interpolated grades of the block
model were compared with the same histograms and probability graphs of the composite samples. The
histograms and graphs of the interpolated grades and composite samples were similar, and the block
model histograms were smoother than the composite histograms. The comparisons confirmed the
validity and consistency of the built block model.
The mineral resource is a global resource estimate and locally resource estimates may vary in a
negative or positive manner.
----- End of picture text -----
Section 4 Estimation and Reporting of Ore Reserves.
==> picture [483 x 185] intentionally omitted <==
----- Start of picture text -----
Criteria Commentary
Mineral Resource The total Measured and Indicated Resources for Clay at the Capao do Mel, Soberbo, Figueira, and
estimate for conversion Barra do Pacu licences, used for the basis of conversion to the Reserve are 385 Mt at 2,875ppm TREO
to Ore Reserves using a cut-off grade of 1,000 ppm. Total Inferred Resources for Clay are 321 Mt at 2,299ppm TREO.
Only Measured and Indicated Resources were considered for inclusion in the Ore Reserve.
These Mineral Resources are reported inclusive of the Ore Reserves.
Site visits The Mining Competent Person (CP) did not visit the site but relied upon the reports of staff and
contractors who have visited the site.
Study status The current Pre-Feasibility Study has determined a mine plan that is technically achievable and
economically viable, considering assessment of preliminary material-modifying factors including
mining, processing, metallurgical recovery, infrastructure, environmental, legal, and financial
parameters. These will require further ongoing assessment in future study phases. This level of study
enables Mineral Resources to be converted to Ore Reserves.
Cut-off parameters The economic cut-off grade for the project was determined on a block value basis and is based on
calculating net revenue from recovered REO less processing and selling costs on a block-by-block
-
(diluted) basis. The cut off grade will vary depending on the make up of the basket (as seen below).
----- End of picture text -----
Meteoric Resources July 2025 Preliminary Feasibility Study
Page 33 of 41
==> picture [595 x 39] intentionally omitted <==
==> picture [595 x 39] intentionally omitted <==
Criteria
==> picture [98 x 117] intentionally omitted <==
Commentary
Variable TREO Cut-off Grades by Deposit
==> picture [221 x 76] intentionally omitted <==
----- Start of picture text -----
Deposit Lowest Highest
CDM 1,895 4,310
FG 2,130 3,872
SB 2,047 2,860
BDP 2,000 4,500
----- End of picture text -----
-
Mining factors or The following Modifying Factors were considered in relation to the development of the Caldeira Ore assumptions Reserve: - Selected mining method will be open cut utilising truck and excavator in free digging the clay material. No drill and blast will be required.
-
- Backfilling of mined pits using the spent clay rejects will aid in progressive rehabilitation and reduce external waste storage requirements.
-
- Pit design parameters are preliminary and based on existing slope configurations from nearby clay mining operations.
-
- Resource models were regularised to a 10 x 10 x 5 block size to account for dilution. Ore loss of 5% was then applied to pit design inventory.
-
- No additional dilution has been factored into the optimisation and reserve reporting.
-
Site specific field geotechnical studies and off site testwork on spent clay samples has commenced and the results once available will be used to validate the pit design, stability of temporary waste dumps and backfilling of the pits, and material handling properties of spent clays.
-
Metallurgical factors and The Caldeira Project is an ionic adsorption clay-hosted rare earth deposit, a mineralisation style that assumptions allows for low-cost, simple metallurgical processing. The proposed metallurgical process involves leaching with ammonium sulfate (AMSUL) at pH 5, followed by impurity removal using ammonium bicarbonate (BICARB) to produce a Mixed Rare Earth Carbonate (MREC). This process is highly appropriate for the mineralisation type, as ionic adsorption clay deposits allow for selective rare earth extraction at ambient temperature and pressure without complex beneficiation techniques such as flotation or roasting.
-
The metallurgical process incorporates a suite of well-established and mature unit operations, including scrubbing, desorption, counter-current decantation (CCD), pressure filtration, reverse osmosis, nanofiltration, and other dewatering technologies. These technologies are widely used across various mineral processing and chemical industries and are considered proven in terms of operational reliability and scalability. However, while these individual components are mature, their integration into a single flowsheet tailored specifically for rare earth ionic clay deposits is considered novel. To date, there are no known commercial operations outside of China that have successfully achieved design throughput and recovery targets for such deposits. The innovative sequencing and configuration of these unit operations in the proposed flowsheet represent a unique approach to processing ionic clays, designed to optimise recovery and manage the specific challenges associated with these ore types.
-
Extensive metallurgical test work has been conducted by the Australian Nuclear Science and Technology Organisation (ANSTO) to characterise the metallurgical response across all tenements included in the PFS. Representative bulk composite samples were prepared for each tenement ensuring coverage of orebody variability. To date, 320 diagnostic leach tests and 32 bulk slurry leach tests have been completed by ANSTO. Additionally, a 2.5-tonne composite sample, derived from 154 air core drill holes and representative of the first five years of production from the CDM starter pit, was used in a 15-day continuous pilot plant trial at ANSTO.
-
Testwork covers the full range of domains/lithologies—soil, clay, transition, and hard rock—both laterally and at depth.
-
Individual rare earth oxide recoveries were determined from the testwork (below). This equates to global average recoveries of 55% TREO and 71% Magnetic REO. These recovery factors have been statistically validated against a broad set of randomised diagnostic leach tests, confirming their robustness and applicability across the mine plan.
| Deposit | La | Ce | Pr | Nd | Sm | Eu | Gd | Tb | Dy | Ho | Er | Tm | Yb | Lu | Y |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| CDM | 76 | 0.3 | 74 | 73 | 65 | 61 | 64 | 52 | 50 | 43 | 37 | 33 | 25 | 24 | 50 |
| BDP | 76 | 0.3 | 74 | 73 | 65 | 61 | 64 | 52 | 50 | 43 | 37 | 33 | 25 | 24 | 50 |
| SOB | 71 | 5 | 66 | 68 | 62 | 62 | 61 | 55 | 51 | 49 | 48 | 44 | 43 | 25 | 51 |
| FIG | 71 | 5 | 69 | 72 | 69 | 69 | 66 | 58 | 53 | 48 | 44 | 32 | 23 | 20 | 55 |
All drill samples are assayed for deleterious elements and the distribution analysed throughout the resource. Mixed Rare Earth Carbonate (MREC) product was also assayed for deleterious elements. Feedback from potential off-take partners and customers has not identified any concerns regarding deleterious elements in the MREC. A detailed composition of the final MREC product, including impurity levels (2% by weight), was publicly released on 29 February 2024. This composition meets market expectations and specifications. Furthermore, the recent pilot plant campaign conducted at ANSTO successfully validated the quality of the MREC product, confirming that deleterious elements are
Meteoric Resources July 2025 Preliminary Feasibility Study
Page 34 of 41
==> picture [595 x 39] intentionally omitted <==
==> picture [595 x 39] intentionally omitted <==
==> picture [483 x 722] intentionally omitted <==
----- Start of picture text -----
effectively managed within the proposed flowsheet and do not pose a risk to product acceptance or
downstream processing
A comprehensive bulk sampling and pilot-scale test program has been undertaken to validate the
metallurgical performance and representativeness of the orebody. A 2.5-tonne bulk sample was
compiled from 154 air core drill holes. This sample was selected to reflect the lithological and grade
variability expected in the first five years of production. This sample was processed through a 15-day
continuous pilot plant campaign at ANSTO and successfully demonstrated the operational viability of
the proposed flowsheet and confirmed the consistency of metallurgical recovery and product quality.
This pilot-scale validation provides a high level of confidence in the scalability of the process and the
reliability of recovery assumptions used in the PFS.
Detailed mineralogical and metallurgical studies of representative samples from the deposits confirm
the presence of ion-adsorbed rare earth elements (REEs) within a clay matrix. Mineralogical
characteristics include a dominance of kaolinite-hosted ion-adsorbed REEs and the absence of
significant refractory REE minerals. The low acidity (pH 4.5 – 5) leach results and very low levels of
deleterious elements such as Al, Fe, U in the leach liquor that need to be neutralised., support the
ability to meet market specifications for MREC. Only those zones with demonstrated leachability and
acceptable impurity profiles (appropriate mineralogy) have been included in the Ore Reserve estimate.
Reagent consumption estimates in the PFS were revised based on pilot plant data, which more
accurately reflects full-scale operations due to its continuous processing nature and incorporation of
recycled process streams. This contrasts with the batch-style bench testwork used in the earlier
scoping study, which, while appropriate for early-stage evaluation, does not capture the dynamic
effects of recycling within a continuous circuit.
Environmental A comprehensive Environmental Impact Assessment (EIA) and Environmental Impact Report (RIMA)
have been submitted to the Environmental Agency of Minas Gerais (FEAM) as part of the application
for a Preliminary License (LP). The EIA/RIMA covers Capao do Mel, Soberbo, and Figueira licences
and assessed potential impacts on air quality, water resources, biodiversity, noise, and socio-economic
factors. The study includes 8 months of extensive environmental fieldwork, with surveys on flora,
fauna, hydrology, air quality, and community engagement. Studies have determined:
o The processing facility will recycle water via ultrafiltration and reverse osmosis (RO) systems.
o The project will operate with 100% renewable energy sourced from existing hydro, solar, and
wind power in Minas Gerais, significantly reducing its carbon footprint.
o Potential dust emissions from mining activities will be mitigated through water suppression
methods, including recycled process water.
Waste Rock Characterisation: The mining process involves extracting ionic adsorption clay-hosted rare
earths, which do not generate acid mine drainage or significant heavy metal contamination risks. Waste
rock is primarily low-grade clays (kaolinite, smectite, illite), which are chemically inert and pose minimal
environmental risk.
Residue Management: The spent residue is washed before backfilling, and the pit floor and walls
covered with a compacted clay liner of material sourced from within the pit, to ensure groundwater
contamination does not exceed environmentally acceptable levels. The progressive backfill approach
reduces the need for permanent waste dumps and facilitates rapid site rehabilitation.
No tailings dams will be built. All spent ore will be dry-stacked on temporary piles and progressively
backfilled and compacted into mined-out pits as voids become available (~24 months).
Infrastructure The Caldeira Project is strategically located in Caldas, Minas Gerais, a well-established mining and
industrial region with significant infrastructure. The existing infrastructure significantly de-risks the
project, reducing capital expenditures for building new roads, power lines, or water supply networks.
The PFS area spans 2,369 hectares (23.7 km²), providing ample land for mine development,
processing infrastructure, and future expansions. The proposed pits and processing facility are well-
connected via a network of paved roads and private gravel roads, facilitating efficient ore transport.
The regions of Caldas and Poços de Caldas are home to existing bauxite, alumina, clay, and chemical
processing plants, ensuring access to an experienced mining and industrial workforce. Additionally,
the Company has started supporting the development of relevant skills in the Caldas population.
The project is located within 3km of high-capacity power transmission lines, ensuring a stable and
reliable energy supply for mining and processing operations.
Access to water is via a 1 km long pipeline to a nearby dam. This will provide >80% of water needs
with supplementary water pumped from the operating pits.The ore beneficiation process is designed
for high water efficiency, with >75% of process water recirculated within the plant.
Ore will be transported by trucks via internal haul roads (dominantly), existing gazetted roads, and
private gravel roads to the central processing facility at Capao do Mel.
The project benefits from proximity to major highways, facilitating the transport of MREC products to
export hubs. Brazil’s well-developed port infrastructure, including Santos (São Paulo), provides
efficient access to global markets.
The city of Caldas along with surrounding cities including Pocos de Caldas and Andrades provides
sufficient housing, amenities, and services for workers.
Costs Mining costs have been built up from first principals and are based on an owner mining solution.
Conventional dig and haul equipment has been used (excavators with a fleet of rigid trucks) mining
clay ore and waste. Additional allowances were made for clearing, topsoil removal, spent clay return,
dewatering, fuel, hourly hire and haul road maintenance to determine the unit mining cost. The build-
up of costs uses data sourced from equipment Owner Equipment Manufacturer’s (OEM’s).
Processing of Ore costs – Inclusive of processing, concentrate transport, and mine and general
administration were determined based on PFS level buildup of OPEX for a 6.0 Mtpa plant by Ausenco.
Royalty charges are applied as follows:
o CFEM a federal royalty charge of 2.0% of Mineral Revenue
o TRFM a state royalty applied at an equivalent charge of US$0.39/tonne processed
o landowner royalty cost of US$1/tonne of ore .
----- End of picture text -----
Meteoric Resources July 2025 Preliminary Feasibility Study
Page 35 of 41
==> picture [595 x 39] intentionally omitted <==
==> picture [595 x 39] intentionally omitted <==
oroyalty of 4.75% to the Togni Group on recovered REO |
||
|---|---|---|
| Revenue factors | Sales revenue The project will produce an MREC product for sale, with pricing based on individual rare earth oxide values published by the Shanghai Metal Market. These values reflect gross spot prices, inclusive of VAT. A payability factor of 70% is applied to the separated oxide prices to determine the final MREC pricing. Exchange Rates and Economic Model Inputs The economic model is denominated in US dollars (USD), with local cost estimates converted from Brazilian Reais (BRL) using an assumed exchange rate of 6.0 BRL/USD. The exchange rate assumption is based on December 2024 rates. The project’s exposure to foreign exchange risks will be further assessed in future study phases, considering potential hedging strategies. Transportation and Treatment Charges Transportation charges for MREC exports (CIF Santos Port, Brazil) are estimated from budget pricing provided by logistics contractors. Treatment and refining charges are not directly applicable, as the product is an intermediate feedstock for separation facilities rather than a fully refined REO product. No smelter penalties are expected, as the MREC has been confirmed to meet industry purity requirements through ANSTO metallurgical test work. Future Considerations Future feasibility studies will refine the revenue model based on: Advanced marketing and offtake agreements, confirming final payability terms. Updated market forecasts, reflecting shifts in supply-demand dynamics for critical REOs. Potential government incentives, including tax exemptions and subsidies for critical mineral production. The project is well-positioned to capitalise on the growing demand for high-value magnet REOs, with potential pricing and revenue generation upside. |
|
| Market assessment | Market Demand and Supply Outlook | |
| | The Caldeira Project is set to produce Mixed Rare Earth Carbonate (MREC), a high-value product rich | |
| in Neodymium (Nd), Praseodymium (Pr), Dysprosium (Dy), and Terbium (Tb)—essential elements for | ||
| manufacturing permanent magnets used in electric vehicles (EVs), wind turbines, robotics, and | ||
| advanced technologies. | ||
| | With global demand for rare earth permanent magnets projected to grow at 8–10% annually over the | |
| next decade, the Caldeira Project is strategically positioned to meet the needs of rapidly expanding | ||
| sectors such as clean energy, electric mobility, and defense. | ||
| | Currently, global demand for rare earth oxides (REOs) exceeds 180,000 tonnes per year, and supply | |
| shortages—particularly for NdPr, Dy, and Tb—are expected by 2030, as industries seek to reduce | ||
| reliance on Chinese supply chains. Today, China controls over 90% of global REO separation capacity, | ||
| making supply diversification a top priority for governments and manufacturers worldwide. | ||
| Competitive Landscape and Market Positioning | ||
| | The Caldeira Project stands out as one of the few ionic clay-hosted rare earth projects outside China, | |
| offering a low-cost production model and a high-value Magnetic REO output. | ||
| | Key competitors include: | |
oSerra Verde (Brazil) – The only other ionic adsorption clay operation outside China producing |
||
| REE carbonate. | ||
oLynas Rare Earths (Australia/Malaysia) – A major REE producer from hard rock monazite |
||
| deposits, which require more complex processing. | ||
| Customer Landscape & Market Opportunity | ||
| | The Caldeira Project is targeting a well-defined and rapidly growing market for Mixed Rare Earth | |
| Carbonate (MREC), with key customers including rare earth separation facilities, magnet | ||
| manufacturers, and strategic industrial users across North America, Europe, Japan, and South Korea. | ||
| | Demand for non-Chinese sources of rare earths continues to accelerate, driven by: | |
oElectric vehicle manufacturers (e.g., Tesla, BYD, Volkswagen, Stellantis) |
||
oWind turbine producers (e.g., Vestas, Siemens Gamesa, GE Renewables) |
||
oDefense and aerospace sectors, which require secure supplies of Dysprosium (Dy) and Terbium |
||
| (Tb) for high-performance magnet applications | ||
| | Meteoric has already secured two non-binding Memoranda of Understanding (MOUs) with leading | |
| industry players: Ucore Rare Metals Inc. and Neo Performance Materials Inc. These MOUs reflect | ||
| strong early-stage interest in the Caldeira Project’s MREC product and support ongoing offtake | ||
| discussions with other Tier-1 partners. Formal agreements are anticipated during the Feasibility Study | ||
| phase. | ||
| | The current market environment is highly favorable, supported by strategic policy initiatives in Western | |
| economies aimed at building resilient, domestic rare earth supply chains. | ||
| Product Validation & Industry Alignment | ||
| | The Caldeira Project’s MREC product is undergoing rigorous testing to meet the commercial | |
| specifications required by leading separation facilities. Independent metallurgical analysis | ||
| by ANSTO has confirmed that the product meets industry standards for purity and impurity thresholds. | ||
| | Further customer qualification testing will be conducted during pilot plant operations, with early results | |
| indicating strong alignment with downstream processing requirements. The projected MREC | ||
| composition is well-suited for efficient separation and refining into high-purity rare earth oxides. | ||
| Strategic Outlook |
Meteoric Resources July 2025 Preliminary Feasibility Study
Page 36 of 41
==> picture [595 x 39] intentionally omitted <==
==> picture [595 x 39] intentionally omitted <==
-
Looking ahead, the project’s commercial strategy will focus on:
oSecuring binding offtake agreements with strategic partnersoRefining pricing and demand forecasts as part of the Feasibility StudyoLeveraging government-backed critical minerals policies to enhance project economics through funding, tax incentives, and trade facilitation -
With its unique position as a low-cost, high-value ionic clay-hosted REE project outside China, the Caldeira Project is poised to play a pivotal role in the global shift toward diversified, secure, and sustainable rare earth supply chains.
-
Economic Economic evaluation includes inputs and confidence levels which are supported by a technical prefeasibility study.
-
The Caldeira Project’s economic analysis incorporated in pre-feasibility study is based on a detailed financial model incorporating capital expenditures (CAPEX), operating costs (OPEX), revenue projections, and financial assumptions.
-
The Net Present Value (NPV) calculation uses a real, post-tax discount rate of 8% (NPV8), consistent with industry standards for mining projects in emerging markets.
-
Inflation assumptions are not explicitly factored into the financial model, as all cost and revenue estimates are presented in real (constant) 2025 US dollars. Corporate tax is assumed at 34%, in line with Brazilian mining sector regulations.
-
The economic study model analyses the outcome based at three different pricing scenarios. Spot price as at June 2025, broker consensus pricing and an average forecast price from two independent pricing agencies.
-
A summary of the key financial metrics is shown below:
==> picture [374 x 178] intentionally omitted <==
----- Start of picture text -----
LOM
Financial Outputs Unit
Spot Consensus Forecast
Pre-tax NPV8 US$M 251 821 1,985
Post-tax NPV8 US$M 109 488 1,256
Pre-tax IRR % 15 28 39
Post-tax IRR % 11 21 31
Payback period years 6.1 2.9 2.8
Basket price [8] TREO US$/kg TREO 26 33 51
NdPr Average pricing US$/kg NdPr 67 86 135
Payability % 70
NdPr Gross Operating cost US$/kg NdPr 31
NdPr Net Operating costs [9] US$/kg NdPr 22
Capex inclusive of 25% contingency US$M 443
----- End of picture text -----
Sensitivity Analysis A sensitivity analysis was conducted on key financial variables, including:
8 The basket price of TREO refers to the weighted average price of the individual REE contained in a specific mineral concentrate or product, based on their relative proportions and current market prices
9 Operating costs net of DyTb credits at consensus pricing per kilogram of NdPr produced
Meteoric Resources July 2025 Preliminary Feasibility Study
Page 37 of 41
==> picture [595 x 39] intentionally omitted <==
==> picture [595 x 39] intentionally omitted <==
==> picture [374 x 407] intentionally omitted <==
Future Considerations
-
The economic analysis will be further refined to incorporate, updated cost estimates from vendor quotes and detailed engineering, potential tax incentives or government subsidies.
-
Formalised offtake agreements improving payability terms.
Social Stakeholder Survey & Communication
-
Meteoric contracted a social diagnosis study following guidelines of the Social and Institutional Relationship Guide for the Mining Sector, from the Brazilian Mining Institute. From this the company developed an engagement strategy based on: specialized dialogue, active listening, transparency, and reporting regular information to the communities and institutions in the region where the Caldeira Project is being developed.
-
Meteoric has identified and looked to establish a dialogue with the major stakeholders from the Caldas Municipality, including: governmental organisations, educational organisations, sporting groups, traditional and indigenous groups, economic and industrial groups.
-
More than 50 meetings were conducted with local government leaders and registered municipal Organizations in 2024 to: introduce and explain the project, explain the proposed socio-economic benefits to Caldas and the surrounding region, clarify the licensing processes, and update stakeholders on the development status of the Caldeira Project. Additionally, Meteoric has developed a Caldeira Project Booklet (brochure) to communicate information contained in the Environmental Impact Study (EIS). Also, Meteoric have set up a WhatsApp channel named “Alô, Meteoric”, through which the community can reach out and contact the company to request information about its activities in any area.
Social Programs
-
In 2024, Meteoric established partnerships and provided financial investments in existing Social Programs in the Caldas Municipality in the areas of: Education, Sports and Culture. Meteoric also established a partnership with an elderly care facility in Caldas, arranging: working bee, social events, and gifts at Christmas.
-
In 2025 Meteoric will partner with up to 10 Municipal organisations to financially support selected social programs.
-
Engagement with Traditional Inhabitants and Indigenous Peoples
-
The Company has dialogue with the three indigenous groups, and Barreirinhos Quilombo communities who live in four (4) different rural villages in the Caldas Municipality. Meteoric carries out specific
Meteoric Resources July 2025 Preliminary Feasibility Study
Page 38 of 41
==> picture [595 x 39] intentionally omitted <==
==> picture [595 x 39] intentionally omitted <==
==> picture [483 x 342] intentionally omitted <==
----- Start of picture text -----
dialogue with the leadership of these indigenous and traditional groups’, respecting their
communication style and desire for specific information about the Caldeira Project e.g. presentation of
the ‘Caldeira Project Booklet’ (brochure) by the Company’s Community Development co-ordinator at
the villages. Meteoric has also implemented a Volunteer Program for employees, and its first
engagement was in the Barreirinhos Quilombo Community.
Other No significant geological, seismic, or environmental risks have been identified that could materially
impact project execution. The mineralisation does not contain uranium (U) or thorium (Th) at reportable
levels in Brazil, eliminating the need for radiological monitoring and complex environmental handling.
Meteoric holds the rights to mine REEs on the PFS licenses through a Royalty and Development
Agreement with Togni Refractories Ltda (the holder of the Mining Licences).
As part of the Installation Licence (LI) process Meteoric requires the consent of all Landowners who
are directly affected by the project. The Company already has agreements with seven (7) landowners
and continues to make progress on securing the remaining agreement.
Capao do Mel deposit is a Mining Licence application which needs to be granted prior to mining. The
application is pending an Installation Licence (LI) from the EPA, which is expected in 2026.
All four (4) licences require the addition of REEs onto the licence document prior to mining. This
requires: ANM to be notified of the new substance, a Resource Re-evaluation Report (RR) to be
submitted, and a Preliminary Economic Assessment (PAE) to be completed. The RRR and PAE for
CDM, SOB, and FG have been completed and are under examination by the ANM. The documents
are currently being drafted for BDP and will be lodged in Q3 2025.
As part of the Preliminary Licence (LP) process Meteoric require approval of the Management
Committee of the Pedra Branca APA (CONGEAPA) to mine inside the Buffer Zone of the APA. Meteoric
has conducted extensive research and consultation from mid-2023 with the object of seeking and
obtaining permission to conduct activities in the Buffer Zone and is confident of obtaining favourable
consideration from the CONGEAPA.
Classification The Mineral Reserve is classified as a Probable Ore Reserve only using the guidelines of the JORC
Code (2012 Edition). Measured and Indicated have been converted to Probable only.
Audits or reviews The MRE has undergone internal peer review and was prepared following the JORC Code (2012),
ensuring compliance with industry best practices.
The Ore Reserve has not been independently audited or externally reviewed as is considered industry
standard for the stage of development of the project.
Relative accuracy/ The estimates in this study relating to mining, processing and cost performance are underpinned by
confidence a PFS which has a confidence range of +25% to -25%.
----- End of picture text -----
Meteoric Resources July 2025 Preliminary Feasibility Study
Page 39 of 41
==> picture [595 x 39] intentionally omitted <==
==> picture [595 x 39] intentionally omitted <==
Appendix 4 - Caldeira REE Project - Licence details
==> picture [447 x 702] intentionally omitted <==
----- Start of picture text -----
License Status License Holder Area (Ha)
808027/1975 MINING CONCESSION COMPANHIA GERAL DE MINAS 600.76
809358/1975 MINING CONCESSION COMPANHIA GERAL DE MINAS 617.23
809359/1975 MINING CONCESSION COMPANHIA GERAL DE MINAS 317.36
815645/1971 MINING CONCESSION COMPANHIA GERAL DE MINAS 366.02
815682/1971 MINING CONCESSION COMPANHIA GERAL DE MINAS 575.26
817223/1971 MINING CONCESSION MINERAÇÃO DANIEL TOGNI LOUREIRO LTDA 772.72
803459/1975 MINING CONCESSION MINERAÇÃO PERDIZES LTDA 24.02
808556/1974 MINING CONCESSION MINERAÇÃO PERDIZES LTDA 204.09
811232/1974 MINING CONCESSION MINERAÇÃO PERDIZES LTDA 524.40
814251/1971 MINING CONCESSION MINERAÇÃO PERDIZES LTDA 124.35
815006/1971 MINING CONCESSION MINERAÇÃO PERDIZES LTDA 717.52
816211/1971 MINING CONCESSION MINERAÇÃO PERDIZES LTDA 796.55
835022/1993 MINING CONCESSION MINERAÇÃO PERDIZES LTDA 73.50
835025/1993 MINING CONCESSION MINERAÇÃO PERDIZES LTDA 100.47
814860/1971 MINING CONCESSION MINERAÇÃO ZELÂNDIA LTDA 341.73
815681/1971 MINING CONCESSION MINERAÇÃO ZELÂNDIA LTDA 766.54
820352/1972 MINING CONCESSION MINERAÇÃO ZELÂNDIA LTDA 26.40
820353/1972 MINING CONCESSION MINERAÇÃO ZELÂNDIA LTDA 529.70
820354/1972 MINING CONCESSION MINERAÇÃO ZELÂNDIA LTDA 216.49
2757/1967 MINING CONCESSION RAJ MINERIOS LTDA 20.10
5649/1963 MINING CONCESSION RAJ MINERIOS LTDA 12.41
803457/1975 MINING CONCESSION RAJ MINERIOS LTDA 60.64
825972/1972 MINING CONCESSION RAJ MINERIOS LTDA 377.42
833914/2007 MINING CONCESSION RAJ MINERIOS LTDA 6.99
002.349/1967 MINING CONCESSION VARGINHA MINERACAO E LOTEAMENTOS LTDA 74.01
830443/2018 EXPLORATION LICENSE FERTIMAX FERTILIZANTES ORGANICOS LTDA 79.24
830444/2018 EXPLORATION LICENSE FERTIMAX FERTILIZANTES ORGANICOS LTDA 248.34
830824/2006 EXPLORATION LICENSE RAJ MINERIOS LTDA 13.24
832350/2006 EXPLORATION LICENSE RAJ MINERIOS LTDA 27.14
832351/2006 EXPLORATION LICENSE RAJ MINERIOS LTDA 16.77
832671/2005 EXPLORATION LICENSE RAJ MINERIOS LTDA 16.91
832714/2016 EXPLORATION LICENSE RAJ MINERIOS LTDA 13.61
832800/2002 EXPLORATION LICENSE RAJ MINERIOS LTDA 6.94
831686/2012 EXPLORATION LICENSE VARGINHA MINERACAO E LOTEAMENTOS LTDA 6.50
832193/2012 EXPLORATION LICENSE VARGINHA MINERACAO E LOTEAMENTOS LTDA 12.46
807899/1975 MINING APPLICATION COMPANHIA GERAL DE MINAS 948.92
815274/1971 MINING APPLICATION COMPANHIA GERAL DE MINAS 739.73
833486/1996 MINING APPLICATION MINAS RIO MINERADORA LTDA 79.38
833655/1996 MINING APPLICATION MINAS RIO MINERADORA LTDA 249.11
833656/1996 MINING APPLICATION MINAS RIO MINERADORA LTDA 82.77
833657/1996 MINING APPLICATION MINAS RIO MINERADORA LTDA 68.25
834743/1995 MINING APPLICATION MINAS RIO MINERADORA LTDA 283.19
830513/1979 MINING APPLICATION MINERAÇÃO MONTE CARMELO LTDA 457.77
804222/1975 MINING APPLICATION MINERAÇÃO PERDIZES LTDA 403.65
813025/1973 MINING APPLICATION MINERAÇÃO PERDIZES LTDA 943.74
830000/1980 MINING APPLICATION MINERAÇÃO PERDIZES LTDA 203.85
831092/1983 MINING APPLICATION MINERAÇÃO PERDIZES LTDA 171.39
830391/1979 MINING APPLICATION MINERAÇÃO PERDIZES LTDA. 7.30
830633/1980 MINING APPLICATION MINERAÇÃO ZELÂNDIA LTDA 35.25
831880/1991 MINING APPLICATION MINERAÇÃO ZELÂNDIA LTDA 84.75
815237/1971 MINING APPLICATION RAJ MINERIOS LTDA 131.98
830722/2002 MINING APPLICATION RAJ MINERIOS LTDA 5.60
831250/2008 MINING APPLICATION RAJ MINERIOS LTDA 2.48
831598/1988 MINING APPLICATION RAJ MINERIOS LTDA 930.90
832889/2005 MINING APPLICATION RAJ MINERIOS LTDA 27.82
837368/1993 MINING APPLICATION RAJ MINERIOS LTDA 340.04
830551/1979 MINING APPLICATION TOGNI S/A MATERIAIS REFRATÃ RIOS 528.88
830416/2001 MINING APPLICATION VARGINHA MINERACAO E LOTEAMENTOS LTDA 166.22
831269/1992 MINING APPLICATION VARGINHA MINERACAO E LOTEAMENTOS LTDA 442.16
832146/2002 MINING APPLICATION VARGINHA MINERACAO E LOTEAMENTOS LTDA 18.95
832252/2001 MINING APPLICATION VARGINHA MINERACAO E LOTEAMENTOS LTDA 51.96
832572/2003 MINING APPLICATION VARGINHA MINERACAO E LOTEAMENTOS LTDA 204.49
833551/1993 MINING APPLICATION VARGINHA MINERACAO E LOTEAMENTOS LTDA 98.87
833553/1993 MINING APPLICATION VARGINHA MINERACAO E LOTEAMENTOS LTDA 98.13
830.697/2003 MINING APPLICATION VARGINHA MINERACAO E LOTEAMENTOS LTDA 5.38
830.461/2018 EXPLORATION APPLICATION FERTIMAX FERTILIZANTES ORGANICOS LTDA 50.88
832799/2002 EXPLORATION APPLICATION RAJ MINERIOS LTDA 38.35
----- End of picture text -----
Meteoric Resources July 2025 Preliminary Feasibility Study
Page 40 of 41
==> picture [595 x 39] intentionally omitted <==
==> picture [595 x 39] intentionally omitted <==
| License | Status | License Holder | Area(Ha) |
|---|---|---|---|
| 830955/2006 | EXPLORATION APPLICATION | VARGINHA MINERACAO E LOTEAMENTOS LTDA | 1993.50 |
| 833176/2008 | EXPLORATION APPLICATION | VARGINHA MINERACAO E LOTEAMENTOS LTDA | 634.00 |
Meteoric Resources July 2025 Preliminary Feasibility Study
Page 41 of 41