PRESS RELEASE - 15 JULY 2016
==> picture [121 x 45] intentionally omitted <==
INITIAL FORTNUM DEVELOPMENT PLAN
FORTNUM TO BECOME METALS X’S FOURTH GOLD OPERATION
The Board of Metals X Limited (“Metals X” or the “Company”) is pleased to provide its renovation plan for the Fortnum Gold Project (“FGP”) located 170km northwest of Meekatharra.
Fortnum was acquired and settled in late 2015 and Metals X has worked its way through engineering, permitting and approvals for the project to re-start. In addition Metals X has reworked the mineral resource and mining reserve estimates for the key initial feed sources for processing. This work is ongoing and the development plan is till yet to consider any of the main opportunities in the Peak Hill component of the project.
An initial 5 year development plan has been devised which presents a robust and low-capital risk start-up plan for the project. The key outputs of the initial 5 year plan are summarised:
-
Capital and infrastructure refurbishment cost
-
Refurbishment time-frame
-
A$15 million (incl. contingency)
-
16 weeks
-
-
Initial Ore Feeds:
-
Existing Low Grade Stocks 1.1 million tonnes @ 1.0 g/t
-
o Planned Open Pits 3.7 million tonnes @ 1.9 g/t o Planned Underground Mining 560,000 tonnes @ 4.1 g/t
Sub-total 5.4 million tonnes @ 2.0g/t (338,500ounces)
-
Gold Produced
-
Average Cash Operating Costs (inc. Royalties)
-
All in Cost
-
EBITDA
322,000 ounces A$ 64 per tonne or A$1,070 / ounce A$ 77 per tonne or A$ 1,290 / ounce A$218.2M
- Simple payback (including acquisition) 2 years
Significantly longer mine life exists beyond this initial 5 year plan from known resources which require more validation and drilling, especially the Peak Hill region which is yet to be considered in the development strategy.
In addition and in recognition of the excellent exploration and development upside in the project it would be the intent of Metals X to commit to an aggressive exploration effort over the first two years of the project. This is expected to significantly extend the project life and potential.
ENQUIRIES
Peter Cook Warren Hallam Rod Corps Executive Director & CEO Executive Director Manager – Investor Relations e: [email protected] e: [email protected] e: [email protected]
[email protected] www.metalsx.com.au
ASX Code: MLX
Level 3, 18–32 Parliament Place West Perth WA 6005
OTCQX Code: MLXEF
Australia
FORTNUM GOLD PROJECT (FGP) (Metals X 100%)
PREAMBLE
Metals X completed the acquisition of the Fortnum Gold Project, approximately 170km Northwest of Meekatharra in late 2015. The project was acquired by wholly owned subsidiary Aragon Resource Pty Ltd which in turn is wholly owned by the parent of Metals X’s gold division, the wholly owned Westgold Resources Pty Ltd.
The FGP is a development ready project and located within historic Horseshoe, Peak Hill and Labouchere gold mining centres that were in production until 2007. The FGP mining area has recent past production of 11.5 million tonnes at 2.8g/t producing just over 1 million ounces. In addition more than 900,000 ounces of gold was produced from the nearby Peak Hill Gold Project which closed in the late 1990’s.
The FGP encompasses the historic Horseshoe and Labouchere gold mining centres that were in production until 2007. and 11.5 million tonnes at 2.8g/t was mined producing just over 1 million ounces. In addition more than 900,000 ounces of gold was produced from the nearby Peak Hill Gold Project which closed in the late 1990’s.
The operation is leveraged to take advantages of this historical production base and synergies with Metals X’s nearby Central Murchison Gold Project.
The existing 1 Mtpa (nominal) process plant and infrastructure will be refurbished over a 14 week period with capital cost estimates of approximately A$15 million including contingency.
Permitting and licencing for the project re-start is essentially in place or will be in conjunction with the plant refurbishment.
INITIAL 5-YEAR DEVELOPMENT PLAN
The Fortnum Gold Mine has progressed to the point of a development decision and the outcomes of these works are a robust initial 5-year development plan designed to offer a low capital risk start-up with four key development phases:
-
Phase 1 – Refurbish the plant, re-align permits and approvals, commission and operate the plant on existing low-grade ore stocks.
-
In the past 6 months a majority of the existing low grade stockpiles have been identified and pattern drill tested. Whilst this work continues, the initial pool of low-grade stocks on surface totals 1.1 million tonnes at an average grade of 1.0 g/t gold, sufficient for a full year of milling without any mining additions.
-
Phase 2 – When the plant is operational, open pit mining is planned to commence from planned cutbacks and extensions to the existing open pits. This will progressively replace the lower grade stocks with these higher grade open pit ores increasing production output.
To this end, following some validation drilling and re-modelling Metals X has completely revised mineral resource and ore reserve estimates for the key pits in the initial 5 year plan. Revised open pit designs and mine scheduling will deliver 3.7 million tonnes of ore at 1.9 g/t over a four year period.
- Phase 3 – Dewater and recommission the Starlight Underground mine and replace/supplement the other ores with these higher grade ores increasing overall production.
The Starlight underground mine was operated by Perilya between 1999 and 2001, mining ores immediately below the Starlight open pit which had produced 4.65 million tonnes @ 2.8g/t for 425,000 ounces of production. The underground mine produced 612,000 tonnes @ 5.8 g/t for 113,000 ounces mined before being curtailed when Perilya shifted its focus to its newly acquired Broken Hill lead-zinc mines. Metals X has determined an initial ore reserve of 562,000 tonnes @ 4.1 g/t for 74,700 ounces in the area immediately beneath the Starlight pit to within 4 levels. Significant opportunity to expand this exists with the ore system remaining open and sparsely tested down-plunge and the parallel lodes of Twilight, Trev’s and Dougie’s remaining insitu and not developed.
- Phase 4 - Explore and develop the numerous targets and opportunities to create sustainable production from the existing 2 million ounce resource base and additions to it.
There remain many ore sources which are yet to undergo the rigorous re-evaluation of those in the initial 5-year development mine plan, many have significant potential for additional plant feed by both open pit and in the case of the Peak Hill Mine underground development. It is expected that these will be progressively evaluated as
FORTNUM DEVELOPMENT PLAN 2 PRESS RELEASE 15 JULY 2016
the project advances with some having the capability to become priority developments and move forward in the development plan.
The annualised schedule of production and costs of the initial 5-year development plan (refer to Appendix 1). Sees the mining and processing of 5.4 million tonnes of ore at an average grade of 2.0g/t and 322,000 ounces of gold produced and sold at an average cash cost of A$1,070 per ounce and an All-in cost of A$1,290 per ounce.
The initial 5 year development plan generates EBITDA of A$218.2 and has an NPV 8% of A$106.9 million.
The revised Mineral Resource and Ore Reserve estimates for the FGP as t 30 June 2016 are provided in Appendix 3 and 4 along with the Table 1 criteria (Appendix 6) for such process under JORC 2012.
FGP – FEASIBILITY ASSUMPTIONS/INPUT DATA
The following data summarises the key inputs and assumptions used in the initial 5 year development plan:
-
Financial
-
Australian Gold Price of A$1,750.
-
Diesel Fuel A$1.20 per litre (Net of Rebate Price of A$0.81/L).
-
No account for inflation, wage variance or revenue escalation.
-
No tax implications have been calculated within the analysis due to large group tax losses available for offset.
-
Cost Estimations
-
Open Pits cost estimates are based on current contractual rates at other Metals X operations.
-
Open Pit designs are based initially on A$1,450 Whittle Shells in order to identify the highest value blocks. Executable designs are based upon these shell contours.
-
Underground mining costs have been benchmarked against existing underground mines operated within the Metals X group for similar activity.
-
Ore processing and G&A costs are built from first principles and benchmarked against Metals X's other operations.
-
Physical Assumptions
-
Processing Plant rates for the various oxide states were applied as follows:
-
Oxide material 155 tph (equivalent to 1.17M tpa including downtime and availability),
-
Transitional material 130 tph (equivalent to 0.98M tpa including downtime and availability),
-
Fresh material 110 tph (equivalent to 0.83M tpa including downtime and availability).
-
-
Metallurgical recoveries varied over the Resources and between oxide states. The initial 5 year development plan utilised extensive historical Processing records as well as recent consultant reports to determine the metallurgical recoveries applied.
| OPEX Cost over the Development Plan term | OPEX Cost over the Development Plan term |
|---|---|
| Open Pits | $30 - $35 per ore tonne |
| Underground | $60.7 per ore tonne |
| G & A | $5.9 – $6.5 per ore tonne |
| Technical Services | $4.3 - $5.4 per ore tonne |
| Processing | $22.1 – $22.8 per ore tonne t |
| Royalties | $45-$47 per ounce produced |
INITIAL FORTNUM DEVELOPMENT PLAN 3 PRESS RELEASE 15 JULY 2016
FORTNUM PROCESSING PLANT
The Processing Plant at FGP consists of a single stage Primary Crusher, a SAG mill, Ball mill and Pebble Crusher followed by three leach and 5 adsorption tanks with a gold recovery / elusion circuit. The plant was placed under Care and Maintenance in May 2007, with some remedial maintenance and refurbishment works undertaken by the previous owners in 2012.
Due to the very high water quality (very low TDS) of the surrounding hydrological environment the plant has not suffered significant corrosion but shows signs of wear, tear and operating fatigue.
==> picture [518 x 265] intentionally omitted <==
Metallurgical profiling from testwork and past operating history reveals a generally fast leaching and free milling nature with a varying gravity recoverable component. Metallurgical recoveries are generally in the 93-96% range, depending upon the ore source and head grade.
Metals X has over the past 6 months liaised with various engineering and service providers to formulate a detailed cost estimate on refurbishing the historical plant and re-establishing the electrical system. The key components of the plant refurbishment are:
-
The re-skinning of the leach tanks,
-
Re-fitting of the Mill control room and control systems,
-
The re-establishment and refurbishment of the cyclone cluster,
-
The complete relining and some re-boring of the Ball and SAG Mills,
-
The refurbishment and re-commissioning the Pebble Crusher,
-
The refurbishment of the Elution Circuit,
-
The re-fitting of a contract power station and electrical circuits,
-
The re-establishment and expansion of the tailings storage facility,
-
The refurbishment and expansion of the mine village,
-
The re-fitting of the site warehouse, stores and first-fill inventory,
-
The re-fitting and establishment of telecoms and IT networks,
-
The re-establishment of light vehicle and maintenance equipment fleets, and
-
The re-establishment and re-fit of appropriate safety, first aid and OH&S service.
FORTNUM DEVELOPMENT PLAN 4 PRESS RELEASE 15 JULY 2016
Firm quotes from multiple tenderers have been received for all components and the complete capital re-start budget including contingency is A$15 million with the refurbishment timetable being 16-weeks from a formal decision to proceed.
The Process Plant operating cost profiles have been constructed from first principles using forecast manning levels, current quoted mill consumable rates, power generation and diesel price quotes specific to the operation, and site maintenance costs aligned to Metals X operating projects in Western Australia and historical reline frequencies. Consideration has been made for varying ore hardness and materials handling issues associated with varying ore blends.
EXISTING LOW-GRADE STOCKPILES
Historic data has indicated that low-grade stockpiles of nearly 2 million tonnes remain left-over from mining episodes at much lower gold prices. Metals X has been through a process of finding and re-evaluating these Resources and has so far confirmed 1.56 million tonnes at an estimated 0.86 g/t exist with a number of old rehabilitated area still be confirmed and tested. Of these Resources, 1.1 million tonnes have an estimated average grade of 1.02 g/t and contain 36,000 ounces and are converted to ore reserves. Ore cartage and operating cost parameters from the development plan should enable gold to be produced at an all-in cost of $1,010 per ounce. Metals X will continue to work through various regional piles at Nathans, Wilthorpe and Peak Hill in the ensuing periods in order to identify further opportunity as well as converting the remaining Resource statement into the Development Plan.
The table below shows the status of currently identified stockpiles in the region following drill testing and over 4,500 assays being collected:
==> picture [485 x 44] intentionally omitted <==
----- Start of picture text -----
Reserve
Prospect Further Resource Conversion
tonnes grade ounces
----- End of picture text -----
| Prospect | Reserve | Reserve | Reserve | Further Resource Conversion |
|---|---|---|---|---|
| tonnes | grade | ounces | ||
| Labouchere | 62,470 | 1.0 | 1,935 | |
| Harmony | 200,540 | 1.5 | 9,870 | |
| Peak Hill MW | 35,600 | 1.1 | 1,300 | Further drilling warranted in order to convert Resource. Planned drillingin late 2016. |
| Yarlarweelor | 161,600 | 0.6 | 3,350 | Convert remaining Resource (1,200 ounces). |
| Rom Skyway | 56,650 | 0.8 | 1,370 | Convert remaining Resource (700 ounces). |
| Eldorado | 106,600 | 0.7 | 2,445 | Convert remaining Resource (900 ounces). |
| Trev’s | 163,700 | 0.7 | 3,835 | Convert remaining Resource (1,000 ounces). |
| Starlight | 86,400 | 1.2 | 3,315 | |
| HCP | 177,600 | 1.2 | 6,635 | |
| Rom Fingers | 51,000 | 1.3 | 2,080 | |
| Peak Hill | Further drilling of the main LG stockpiles planned after more research. |
|||
| Jubilee | Further drilling warranted in order to confrm. | |||
| Wilthorpe | Further drilling warranted in order to identify and confrm. | |||
| Nathans | Further drilling warranted in order to identify and confrm. | |||
| TOTAL LG STOCK | 1,102,160 | 1.0 | 36,135 |
INITIAL FORTNUM DEVELOPMENT PLAN 5 PRESS RELEASE 15 JULY 2016
FGP – OPEN PIT MINES
More than 12 open pits of various scale have been mined in the project area over the past three decades with open pit production from within the Fortnum, Horseshoe, Peak Hill and Labouchere districts totalling 16.8Mt’s @ 3.1g/t for over 1.6 million ounces recovered.
Metals X has completed infill drilling, re-interpretation and re-modelling of the known resources for the more advanced of the open pit prospects and has completed mine optimisations at an A$1,450 per ounce gold price. The outcome shells of these optimisations were used as a reference for practical and workable open pit designs applying geotechnical recommendations from the numerous studies already completed.
The approach to open pit mining is considered in two phases. Firstly the bulk waste stripping utilising larger 100t trucks and then the deeper parts of the pits being mined with articulated 40t truck fleets.
Where possible, as is the case for the Yarlarweelor Resource, pit designs are staged in order to manage cash drawdowns. Each pit has associated dilution and ore loss modifying factors applied to resource blocks based upon oxidation state and blasting requirements.
Most open pit mines are in close proximity to the plant, but some will require ore cartage or rehandling. Ore cartage costs have been applied using tendered costs from various haulage service providers.
The schedule for executing each of these Open Pit Resources is provided in Appendix 2.
==> picture [519 x 150] intentionally omitted <==
Fortnum District - Yarlarweelor Pit (Looking East)
Mining begins initially within the localised region of the Fortnum Process Plant – excavating the Yarlarweelor Pit in stages. The more distant pits of Nathans and HCP are subsequently mined. With further optimisation of the resources and results from the planned August 2016 drill program, Metals X expects to be able to consider a re-shuffle or re-ordering of the pits to improve both fiscal outcome and mining flexibility.
FORTNUM DEVELOPMENT PLAN 6 PRESS RELEASE 15 JULY 2016
Details of the individual pits are summarised below:
==> picture [523 x 42] intentionally omitted <==
----- Start of picture text -----
Reserve
Prospect Further Resource Conversion
tonnes grade ounces
----- End of picture text -----
| Prospect | Reserve | Reserve | Reserve | Further Resource Conversion |
|---|---|---|---|---|
| tonnes | grade | ounces | ||
| Yarlarweelor (2,195kt’s @ 2.6g/t for 186.5k ounces)* |
2,239,950 | 1.9 | 134,730 | Further Resource growth on the southern plunge as well as opportunity to undertake Stage 2 North excavation. Updated LOM Plan in late 2016. |
| Callies (190kt’s @ 1.8g/t for 10.8k ounces)* |
Opportunity to convert the current Inferred Resource base into Mine Plan. Updated LOM Plan in late 2016 |
|||
| Toms (194kt’s @ 2.3g/t for 14.3k ounces)* |
198,600 | 1.7 | 10,600 | Potential for conversion of the Sam’s Resource (with infll drilling) which is parallel to Toms Resource. |
| Nathans (791kt’s @ 2.8g/t for 67.6k ounces)* |
563,200 | 1.8 | 32,160 | 1k ounces in Reserve Design envelope but not included due to Inferred categorisation. Further depth extension possible. Planned drilling in Aug2016. Updated LOM Plan in late 2016 |
| HCP (958kt’s @ 2.6g/t for 81.3k ounces)* |
415,000 | 2.3 | 30,410 | 2k ounces in Reserve Design envelope but not included due to Inferred categorisation. Further depth extension possible. Planned drilling in Aug2016. Updated LOM Plan in late 2016 |
| Harmony (2,090kt’s @ 3.2g/t for 221k ounces)* |
Metals X to work through this Resource with intent of updated LOM Plan in late 2016. Excellent potential for pit cutback and deepening. |
|||
| Jubilee | Metals X to work through this Resource with intent of updated LOM Plan in late 2016. Excellent potential for pit cutback and extensions along strike. |
|||
| Labouchere (1,270kt’s @ 2.6g/t for 80.2k ounces)* |
310,450 | 2.0 | 20,000 | Metals X to investigate for additional strike extension to the north. |
| Eldorado (136kt’s @ 1.4g/t for 5.7k ounces)* |
Metals X to work through this Resource with intent of updated LOM Plan in late 2016. A low priority but likely viable. |
|||
| Wilthorpe | Metals X to work through this Resource with intent of updated LOM Plan in late 2016. Goodpotential for modestpit. |
|||
| TOTAL OPEN PITS | 3,727,200 | 1.9 | 227,900 |
*Historical Production
INITIAL FORTNUM DEVELOPMENT PLAN 7 PRESS RELEASE 15 JULY 2016
FGP – Starlight Underground
Underground mines at Labouchere, Starlight and Peak Hill have been operational in various forms during the districts history. The Starlight Underground Mine was previous operated by Perilya Mines in 1999-2001 and produced 612k t’s @ 5.8g/t for 113k ounces mined. Metals X has reviewed and determined a re-start plan which refurbishes the existing development and continues its path into a well-defined +1,000 ounces per vertical metre resource horizon.
==> picture [515 x 362] intentionally omitted <==
Fortnum District - Starlight Underground Long Section (Looking West)
Capital cost estimates for the re-start are based on contractual rates at nearby Metals X operations and are inclusive of decline rehabilitation, pit dewatering, surface setup and crown pillar backfill.
The current mine plan and ore reserve estimate is contained within a finite mining envelope – constrained between 130 R.L to 250 R.L and within a 150m strike length. The plan at this stage extracts only this section of the Starlight lode with adjacent Twilight, Trev’s and Dougie’s lodes remaining in-situ. With further work and infill drilling these have significant potential to rapidly expand the mine footprint and size. As does the down-plunge and along strike extensions of the Starlight lodes which are sparsely tested.
FORTNUM DEVELOPMENT PLAN 8 PRESS RELEASE 15 JULY 2016
Details of the underground are summarised below:
| Prosect | Reserve | Reserve | Reserve | Further Resource Conversion |
|---|---|---|---|---|
| p | tonnes | grade | ounces | |
| Starlight Underground (612kt’s @ 5.8g/t for 113.2k ounces)* |
562,000 | 4.1 | 74,750 | Further Resource growth from strike and southern plunge exten- sions. Also the access of Twilight, Trev’s & Dougie’s parallel lodes in the hangingwall. Metals X to work through this Resource with intent of updated LOM Plan in late 2016 |
*Historical Production
ADDITIONAL PROJECT POTENTIAL
The significant omission from the development plan is the mines from the Peak Hill mining centre.
The available geological data-sets and state of historic records is such that it has not yet been possible to validate and complete mining studies to a level of integrity or standard that allows its inclusion. This however does not detract from the impressive historic production outcomes and obvious potential of the Peak Hill district to become a long-term significant contributor to the Fortnum Gold Project.
THE PEAK HILL MINE (MAIN PIT & 5-WAYS)
Gold was first discovered at Peak Hill in 1892 and during the following twenty years the area became a major gold mining centre with a gazetted township and becoming a regional centre for the Murchison district. Before 1913, the mine produced 264,000 ounce of gold from both near surface exploration as well as substantial underground workings reaching a depth of some 530 feet.
Modern mining operations in the area commenced at Mount Pleasant, with a total of 14,200 ounces of gold produced between 1974 and 1988. The Peak Hill Joint Venture partners (North Limited and Plutonic Resources Limited) re-opened Peak Hill mine in 1988, with gold production from open pits at Main, Fiveways, Harmony and Jubilee. The Five Ways Pit alone produced 3.2M tonnes at 3.8g/t for 406k ounces from 1982 to 1995. The western pit of Harmony produced 2.1M tonnes at 3.2g/t for 221k ounces over a similar period. By the end of September 1994 (closure of the plant) the joint venture had produced 627,000 ounces of gold, bringing the total modern era gold production from Peak Hill area to 641,000 ounces.
INITIAL FORTNUM DEVELOPMENT PLAN 9 PRESS RELEASE 15 JULY 2016
==> picture [473 x 281] intentionally omitted <==
Peak HIll District - Five Ways Open Pit (Looking East)
==> picture [281 x 380] intentionally omitted <==
Peak Hill District - Interpreted Geology at Five Ways Open Pit
FORTNUM DEVELOPMENT PLAN 10 PRESS RELEASE 15 JULY 2016
COMPETENT PERSONS STATEMENTS
The information in this report that relates to Mineral Resources compiled by Metals X technical employees under the supervision of Mr. Jake Russell B.Sc. (Hons), who is a member of the Australian Institute of Geoscientists. Mr Russell is a full-time employee of the company, and has sufficient experience which is relevant to the styles of mineralisation and types of deposit under consideration and to the activities which he is undertaking to qualify as a Competent Person as defined in the 2012 Edition of the Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves. Mr Russell consents to the inclusion in this report of the matters based on his information in the form and context in which it appears. Mr Russell is eligible to participate in short and long term incentive plans and holds performance rights in the Company as has been previously disclosed.
The information in this report that relates to Ore Reserve estimate is compiled by Metals X technical employees under the supervision of Mr. Anthony Buckingham B.Eng. (Mining Engineering) M.AusIMM (205126). Mr Buckingham is a full time employee of the company. Mr Buckingham has sufficient experience in relation to the styles of mineralisation and types of deposits under consideration and to the activities which he is undertaking to qualify as a Competent Person as defined in the 2012 Edition of the “Australian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves”. Mr Buckingham consents to the inclusion in this report of the matters based on his information in the form and context in which it appears. Mr Buckingham is eligible to participate in short and long term incentive plans and holds performance rights in the Company as has been previously disclosed.
The information in this report that relates to Exploration Targets, Exploration Results, Mineral Resources and Ore Reserves is based on information compiled by Mr Peter Cook BSc (App. Geol.), MSc (Min. Econ.) MAusIMM (11072) who has sufficient experience that is relevant to the styles of mineralisation, the types of deposits under consideration and the activity being undertaken to qualify as a Competent Person as defined in the 2012 Edition of the Australasian Code for the Reporting of Exploration Results, Mineral Resources and Ore Reserves. Mr Cook is the CEO and an Executive Director and a full time employee of Metals X Limited and consents to the inclusion in the reports of the matters based on his information in the form and context in which it appears. Mr Cook is a shareholder of Metals X and is entitled to participate in Metals X’s short term and long term incentive plans details of which are included in Metals X’s Remuneration Report in the Annual Report.
INITIAL FORTNUM DEVELOPMENT PLAN 11 PRESS RELEASE 15 JULY 2016
APPENDIX 1 – FGP – INITIAL 5 YEAR DEVELOPMENT PLAN - OUTCOME SUMMARY
==> picture [772 x 249] intentionally omitted <==
----- Start of picture text -----
Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 TOTAL
kounc- kounc- kounc- kounc- kounc- kounc- kounc-
kt g/t es kt g/t es kt g/t es kt g/t es kt g/t es kt g/t es kt g/t es
Low Grade Stock-
1,045 1.0 34.7 57 0.7 1.2 1,102 1.0 35.9
piles
Open Pit Mining 103 1.5 4.9 959 1.9 57.9 1,244 1.9 75.8 489 1.9 29.6 841 2.0 54.5 91 1.8 5.1 3,727 1.9 227.9
Underground
22 3.1 2.2 320 4.4 44.8 221 3.9 27.7 562 4.1 74.7
Mining
Total Mill
1,043 1.1 36.8 1,121 1.7 61.9 914 1.9 55.4 849 2.8 76.9 872 2.4 68.5 593 2.0 38.9 5,392 2.0 338.5
Production
Ounces Sold 34,868 ounces 58,582 ounces 52,735 ounces 73,343 ounces 65,303 ounces 36,949 ounces 321,781 ounces
EBITDA @ A$1750
A$ 20.5M A$ 37.6M A$ 23.4M A$ 52.9M A$ 39.9M A$ 43.9M A$ 218.2M
Cash Cost of A$ 1,160 / ounces A$ 1,110/ ounces A$ 1,305/ ounces A$ 1,030/ ounces A$ 1,140 / ounces A$ 560/ ounces A$ $1,070 / ounces
Sales / Rec
ounces
CAPEX A$ 19.4M A$ 17.1M A$ 15.3M A$ 12.1M A$ 4.5M A$ 1.1M A$ 69.5M
All-in Cost/ Rec A$ 1,720 / ounces A$ 1,400 / ounces A$ 1,595 / ounces A$ 1,195 / ounces A$ 1,210 / ounces A$ 590 / ounces A$ 1,290 / ounces
ounces
----- End of picture text -----
*Assumes no deferred waste stripping costs smoothing cash cost profile.
APPENDIX 1 – FGP – INITIAL 5 YEAR DEVELOPMENT PLAN - OUTCOME SUMMARY 12
==> picture [703 x 345] intentionally omitted <==
----- Start of picture text -----
O/P HCP Mining EBITDA A$ 218.2M
$200M O/P Yarlar Sth Stage 2 Mining
O/P Nathans Mining @ CCoS A$ 1,070/Oz
UG Starlight Mining
$150M O/P Yarlar Nth Mining
Net Cash A$146.6
O/P Yarlar Sth Mining O/P Toms Mining
@ All-in Cost A$ 1,290/Oz
$100M
LG S/P Milling
Startup CAPEX $50M
(A$15.0M)
8koz [8koz 8koz] 8koz
$M 7koz [7koz]
6koz 6koz [7koz] 6koz
5koz 6koz 6koz 5koz 5koz 5koz 5koz 5koz 5koz [5koz 6koz] 6koz 5koz 5koz [5koz ] 5koz [5koz 5koz] TOTAL
4koz 5koz 5koz 4koz 5koz 5koz [5koz 5koz] 5koz 5koz 5koz 5koz 4koz [5koz] 5koz 4koz 5koz PRODUCTION
-$50M 3koz [3koz 3koz] 4koz 3koz 3koz 4koz 4koz 3koz 4koz 4koz 4koz 4koz 4koz [4koz] 4koz 4koz 321.8k Oz Sold
2koz 3koz [3koz]
2koz
2koz
1koz
0koz
-$100M
Mth 1 Mth 2 Mth 3 Mth 4 Mth 5 Mth 6 Mth 7 Mth 8 Mth 9 Mth 10 Mth 11 Mth 12 Mth 13 Mth 14 Mth 15 Mth 16 Mth 17 Mth 18 Mth 19 Mth 20 Mth 21 Mth 22 Mth 23 Mth 24 Mth 25 Mth 26 Mth 27 Mth 28 Mth 29 Mth 30 Mth 31 Mth 32 Mth 33 Mth 34 Mth 35 Mth 36 Mth 37 Mth 38 Mth 39 Mth 40 Mth 41 Mth 42 Mth 43 Mth 44 Mth 45 Mth 46 Mth 47 Mth 48 Mth 49 Mth 50 Mth 51 Mth 52 Mth 53 Mth 54 Mth 55 Mth 56 Mth 57 Mth 58 Mth 59 Mth 60 Mth 61 Mth 62 Mth 63 Mth 64 Mth 65 Mth 66 Mth 67 Mth 68 Mth 69
----- End of picture text -----
APPENDIX 1 – FGP – INITIAL 5 YEAR DEVELOPMENT PLAN - OUTCOME SUMMARY 13
APPENDIX 2 – FGP – INITIAL 5 YEAR PLAN MINING PARAMETERS
| Yarlarweelor N Yarlarweelor S1 Yarlarweelor S2 Toms LG Stockpiles Nathans Horseshoe Cassidy Labouchere S/Light UG |
Yarlarweelor N Yarlarweelor S1 Yarlarweelor S2 Toms LG Stockpiles Nathans Horseshoe Cassidy Labouchere S/Light UG |
Yarlarweelor N Yarlarweelor S1 Yarlarweelor S2 Toms LG Stockpiles Nathans Horseshoe Cassidy Labouchere S/Light UG |
Yarlarweelor N Yarlarweelor S1 Yarlarweelor S2 Toms LG Stockpiles Nathans Horseshoe Cassidy Labouchere S/Light UG |
Yarlarweelor N Yarlarweelor S1 Yarlarweelor S2 Toms LG Stockpiles Nathans Horseshoe Cassidy Labouchere S/Light UG |
Yarlarweelor N Yarlarweelor S1 Yarlarweelor S2 Toms LG Stockpiles Nathans Horseshoe Cassidy Labouchere S/Light UG |
Yarlarweelor N Yarlarweelor S1 Yarlarweelor S2 Toms LG Stockpiles Nathans Horseshoe Cassidy Labouchere S/Light UG |
Yarlarweelor N Yarlarweelor S1 Yarlarweelor S2 Toms LG Stockpiles Nathans Horseshoe Cassidy Labouchere S/Light UG |
Yarlarweelor N Yarlarweelor S1 Yarlarweelor S2 Toms LG Stockpiles Nathans Horseshoe Cassidy Labouchere S/Light UG |
Yarlarweelor N Yarlarweelor S1 Yarlarweelor S2 Toms LG Stockpiles Nathans Horseshoe Cassidy Labouchere S/Light UG |
|
|---|---|---|---|---|---|---|---|---|---|---|
| Status | Reserve | Reserve | Reserve | Reserve | Reserve |
Reserve | Reserve | Reserve | Reserve | Reserve |
| Tonnes Grade Ounces Total Movement S/R |
562,628 |
331,802 | 1,345,507 | 198,583 | 1,102,142 | 563,200 | 328,914 | 86,043 | 310,454 | 562,315 |
1.9 |
2.0 | 1.8 | 1.7 | 1.0 | 1.8 | 2.3 | 2.3 | 2.0 | 4.1 | |
| 34,410 | 21,274 | 79,042 | 10,589 | 35,963 | 32,164 | 24,046 | 6,366 | 19,988 | 74,669 | |
| 1,763,154 BCM | 1,449,275 BCM | 6,938,117 BCM | 210,796 BCM | N/A | 2,129,659 BCM | 2,042,565 BCM | 355,814 BCM | 1,778,536 BCM | ||
6.3 |
9.7 |
12.5 |
1.5 |
N/A | 8.3 |
11.6 |
8.0 |
13.6 |
$13.02 M | |
| Dilution included in above Ore Loss included in above |
17%ox / 19%tr / 21%fr | 17%ox / 19%tr / 21%fr | 17%ox / 19%tr / 21%fr | 17%ox / 19%tr / 21%fr | N/A | 15%ox / 17%tr / 19%fr | 17%ox / 19%tr / 21%fr | 17%ox / 19%tr / 21%fr | 17%ox / 19%tr / 21%fr | 20% |
7% all oxide states |
7% all oxide states | 7% all oxide states | 7% all oxide states | N/A | 7% all oxide states | 7% all oxide states | 7% all oxide states | 7% all oxide states | 10% | |
| OPEX Costs | ||||||||||
| Contract Mining (w/ dewater) In Pit GC & Res Definition Ore Haulage Processing (w/ G&A) |
$15.0 / ORE t | $15.1 / ORE t | $23.1 / ORE t | $9.3 / ORE t | N/A | $21.3 / ORE t | $33.8 / ORE t | $24.2 / ORE t | $33.0 / ORE t | $69.0 / ORE t |
$5.4 / ORE t |
$5.6 / ORE t |
$5.5 / ORE t |
$4.3 / ORE t |
$.6 / ORE t | $4.1 / ORE t |
$5.5 / ORE t |
$6.0 / ORE t |
$4.2 / ORE t |
$5.8 / ORE t |
|
$.9 / ORE t |
$.9 / ORE t |
$.8 / ORE t |
$.3 / ORE t |
$3.6 / ORE t |
$1.5 / ORE t |
$6.2 / ORE t |
$6.1 / ORE t |
$3.2 / ORE t |
$.0 / ORE t |
|
$23.9 / ORE t |
$24.1 / ORE t |
$28.2 / ORE t |
$26.1 / ORE t |
$25.0 / ORE t |
$30.3 / ORE t |
$25.9 / ORE t |
$26.9 / ORE t |
$30.5 / ORE t |
$37.0 / ORE t |
|
| Cash Cost of Sales EBITDA *(@A$1,550) |
$886 / Rec Oz |
$941 / Rec Oz | $1,253 / Rec Oz | $866 / Rec Oz | $1,007 / Rec Oz | $1,229 / Rec Oz | $1,172 / Rec Oz | $1,162 / Rec Oz | $1,394 / Rec Oz | $976 / Rec Oz |
$21.37 M |
$10.12 M |
$21.73 M |
$6.81 M |
$18.25 M |
$9.29 M |
$7.95 M |
$1.74 M |
$2.48 M |
$40.62 M |
|
| Min Waste | 0.7 to 1 g/t | 0.7 to 1 g/t | 0.7 to 1 g/t | 0.7 to 0.9 g/t | 0.5 to 0.7 g/t | 0.7 to 0.9 g/t | 0.8 to 1.1 g/t | 0.8 to 1.1 g/t | 0.7 to 1 g/t | |
| Low Grade Ore | 1 to 1.1 g/t |
1 to 1.1 g/t |
1 to 1.1 g/t |
0.9 to 1.1 g/t |
0.7 to 0.8 g/t |
0.9 to 1.1 g/t |
1.1 to 1.3 g/t |
1.1 to 1.3 g/t |
1 to 1.2 g/t |
1.1 to 3.2 g/t |
| High Grade Ore | Above 1.1 g/t |
Above 1.1 g/t |
Above 1.1 g/t |
Above 1.1 g/t |
Above 0.8 g/t |
Above 1.1 g/t |
Above 1.3 g/t |
Above 1.3 g/t |
Above 1.2 g/t |
Above 3.2 g/t |
APPENDIX 2 – FGP – INITIAL 5 YEAR PLAN MINING PARAMETERS 14
APPENDIX 3 – FGP MINERAL RESOURCE ESTIMATE
==> picture [525 x 95] intentionally omitted <==
----- Start of picture text -----
METALS X LIMITED
FORTNUM GOLD PROJECT
Mineral Resource Statement
30/06/2016
Measured Indicated Inferred Total
Ore Body Cut- Gold Gold Gold Goled
Off Tonnes Grade Ounces Tonnes Grade Ounces Tonnes Grade Ounces Tonnes Grade Ounces
----- End of picture text -----
| APPENDIX 3 – FGP MINERAL RESOURCE ESTIMATE | APPENDIX 3 – FGP MINERAL RESOURCE ESTIMATE | APPENDIX 3 – FGP MINERAL RESOURCE ESTIMATE | APPENDIX 3 – FGP MINERAL RESOURCE ESTIMATE | APPENDIX 3 – FGP MINERAL RESOURCE ESTIMATE | APPENDIX 3 – FGP MINERAL RESOURCE ESTIMATE | APPENDIX 3 – FGP MINERAL RESOURCE ESTIMATE | APPENDIX 3 – FGP MINERAL RESOURCE ESTIMATE | APPENDIX 3 – FGP MINERAL RESOURCE ESTIMATE | APPENDIX 3 – FGP MINERAL RESOURCE ESTIMATE | APPENDIX 3 – FGP MINERAL RESOURCE ESTIMATE | APPENDIX 3 – FGP MINERAL RESOURCE ESTIMATE | APPENDIX 3 – FGP MINERAL RESOURCE ESTIMATE | APPENDIX 3 – FGP MINERAL RESOURCE ESTIMATE |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| METALS X LIMITED FORTNUM GOLD PROJECT Mineral Resource Statement 30/06/2016 |
|||||||||||||
| Ore Body | Measured | Indicated | Inferred | Total | |||||||||
| Cut- Of |
Gold | Gold | Gold | Goled | |||||||||
| Tonnes | Grade | Ounces | Tonnes | Grade | Ounces | Tonnes | Grade | Ounces | Tonnes | Grade | Ounces | ||
| Fortnum | |||||||||||||
| Callies | 0.50 | - | - | - | 2,326,456 | 1.43 | 106,960 | 1,527,233 | 1.10 | 54,012 | 3,853,689 | 1.30 | 160,972 |
| Eldorado | 0.70 | - | - | 53,575 | 1.65 | 2,834 | 32,600 | 1.65 | 1,733 | 86,175 | 1.65 | 4,567 | |
| Labouchere | 1.00 | - | - | - | 278,000 | 1.70 | 15,194 | 534,000 | 1.80 | 30,903 | 812,000 | 1.77 | 46,098 |
| Nathans | 1.00 | - | - | - | 823,642 | 1.94 | 51,373 | 240,368 | 1.91 | 14,760 | 1,064,010 | 1.93 | 66,133 |
| Regent | 0.60 | - | - | - | - | - | - | 328,290 | 1.35 | 14,299 | 328,290 | 1.35 | 14,299 |
| Starlight Group |
2.00 | - | - | - | 2,004,402 | 3.80 | 245,017 | 1,317,682 | 3.86 | 163,545 | 3,322,084 | 3.83 | 408,562 |
| Toms and Sams |
0.70 | 9,032 | 2.22 | 644 | 682,358 | 1.71 | 37,470 | 134,399 | 1.87 | 8,063 | 825,789 | 1.74 | 46,176 |
| Yarlarweelor | 0.70 | - | - | - | 3,261,917 | 1.85 | 193,805 | 761,838 | 1.82 | 44,505 | 4,023,755 | 1.84 | 238,310 |
| Horseshoe | |||||||||||||
| Horseshoe Group |
0.70 | - | - | - | 1,533,626 | 2.15 | 106,010 | 757,193 | 2.38 | 57,939 | 2,290,819 | 2.23 | 163,950 |
| Peak Hill* | |||||||||||||
| Enigma | 0.80 | - | - | - | 1,505,942 | 1.17 | 56,819 | 316,056 | 0.97 | 9,870 | 1,821,998 | 1.14 | 66,689 |
| Durack | 0.80 | - | - | - | 2,308,688 | 1.20 | 89,165 | 580,304 | 1.23 | 23,015 | 2,888,992 | 1.21 | 112,181 |
| Five Ways | 0.80 | - | - | - | 3,756,449 | 1.65 | 199,276 | 560,837 | 1.74 | 31,341 | 4,317,285 | 1.66 | 230,617 |
| Harmony | 0.80 | - | - | - | 1,594,021 | 1.65 | 84,632 | 296,629 | 2.12 | 20,251 | 1,890,650 | 1.73 | 104,883 |
| Jubilee | 1.00 | - | - | - | 99,995 | 1.94 | 6,238 | 505,616 | 2.49 | 40,500 | 605,610 | 2.40 | 46,739 |
| Stockpiles | |||||||||||||
| Eldorado | 0.00 | - | - | - | 154,080 | 0.67 | 3,301 | - | - | - | 154,080 | 0.67 | 3,301 |
| ROM Finger 1 | 0.00 | - | - | - | 1,915 | 0.78 | 48 | - | - | - | 1,915 | 0.78 | 48 |
| ROM Finger 2 | 0.00 | - | - | - | 5,112 | 1.78 | 293 | - | - | - | 5,112 | 1.78 | 293 |
| ROM Finger 3 | 0.00 | - | - | - | 18,693 | 0.95 | 571 | - | - | - | 18,693 | 0.95 | 571 |
| ROM Finger 4 | 0.00 | - | - | - | 3,059 | 1.71 | 168 | - | - | - | 3,059 | 1.71 | 168 |
| ROM Finger 5 | 0.00 | - | - | - | 5,989 | 0.87 | 168 | - | - | - | 5,989 | 0.87 | 168 |
| Scats | 0.00 | - | - | - | 16,240 | 1.60 | 835 | - | - | - | 16,240 | 1.60 | 835 |
| Skyway | 0.00 | - | - | - | 56,640 | 0.76 | 1,382 | - | - | - | 56,640 | 0.76 | 1,382 |
| Starlight | 0.00 | - | - | - | 86,400 | 1.19 | 3,314 | - | - | - | 86,400 | 1.19 | 3,314 |
| Trevs | 0.00 | - | - | - | 163,680 | 0.73 | 3,833 | - | - | - | 163,680 | 0.73 | 3,833 |
| Yarlarweelor | 0.00 | - | - | - | 283,872 | 0.50 | 4,595 | - | - | - | 283,872 | 0.50 | 4,595 |
| Horse- shoe-Cassidy |
0.00 | - | - | - | 177,600 | 1.16 | 6,636 | - | - | - | 177,600 | 1.16 | 6,636 |
| Harmony | 0.00 | - | - | - | 200,541 | 1.53 | 9,880 | - | - | - | 200,541 | 1.53 | 9,880 |
| Jubilee | 0.00 | - | - | - | 25,915 | 0.67 | 557 | - | - | - | 25,915 | 0.67 | 557 |
| Labouchere | 0.00 | - | - | - | 62,474 | 0.96 | 1,934 | - | - | - | 62,474 | 0.96 | 1,934 |
| Nathans / Wilthorpe |
0.00 | - | - | - | - | - | - | 16,208 | 0.54 | 282 | 16,208 | 0.54 | 282 |
| Peak Hill | 0.00 | - | - | - | 79,480 | 0.88 | 2,260 | - | - | - | 79,480 | 0.88 | 2,260 |
| Tom’s and Sam’s |
0.00 | - | - | - | 206,216 | 0.52 | 3,431 | - | - | - | 206,216 | 0.52 | 3,431 |
| Totals | 9,032 | 2.22 | 644 | 21,776,976 | 1.77 | 1,237,999 | 7,909,252 | 2.03 | 515,019 | 29,695,260 | 1.84 | 1,753,662 |
*This information was prepared and first disclosed under the JORC Code 2004. It has not been updated since to comply with the JOrD Code 2012 on the basis that the informaiton has not materially changed since it was last reported.
APPENDIX 3 – FGP MINERAL RESOURCE ESTIMATE 15
APPENDIX 4 – FGP ORE RESERVES STATEMENT
==> picture [492 x 100] intentionally omitted <==
----- Start of picture text -----
METALS X LIMITED
FORTNUM GOLD PROJECT
Ore Reserve Statement
30/06/2016
Proven Probable Total
Ore Body Gold Gold Gold
Tonnes Grade Ounces Tonnes rade Ounces Tonnes Grade Ounces
----- End of picture text -----
| METALS X LIMITED FORTNUM GOLD PROJECT Ore Reserve Statement 30/06/2016 |
METALS X LIMITED FORTNUM GOLD PROJECT Ore Reserve Statement 30/06/2016 |
METALS X LIMITED FORTNUM GOLD PROJECT Ore Reserve Statement 30/06/2016 |
METALS X LIMITED FORTNUM GOLD PROJECT Ore Reserve Statement 30/06/2016 |
METALS X LIMITED FORTNUM GOLD PROJECT Ore Reserve Statement 30/06/2016 |
METALS X LIMITED FORTNUM GOLD PROJECT Ore Reserve Statement 30/06/2016 |
METALS X LIMITED FORTNUM GOLD PROJECT Ore Reserve Statement 30/06/2016 |
METALS X LIMITED FORTNUM GOLD PROJECT Ore Reserve Statement 30/06/2016 |
METALS X LIMITED FORTNUM GOLD PROJECT Ore Reserve Statement 30/06/2016 |
METALS X LIMITED FORTNUM GOLD PROJECT Ore Reserve Statement 30/06/2016 |
|---|---|---|---|---|---|---|---|---|---|
| Ore Body | Proven | Probable | Total | ||||||
| Gold | Gold | Gold | |||||||
| Tonnes | Grade | Ounces | Tonnes | rade | Ounces | Tonnes | Grade | Ounces | |
| Fortnum | |||||||||
| Callies | - | - | - | - | - | - | - | - | - |
| Eldorado | - | - | - | - | - | - | - | - | - |
| Labouchere | - | - | - | 310,454 | 2.00 | 19,988 | 310,454 | 2.00 | 19,988 |
| Nathans | - | - | - | 563,200 | 1.78 | 32,160 | 563,200 | 1.78 | 32,160 |
| Regent | - | - | - | - | - | - | - | - | - |
| Starlight Group | - | - | - | 562,315 | 4.14 | 74,758 | 562,315 | 4.14 | 74,758 |
| Toms and Sams | - | - | - | 198,583 | 1.66 | 10,588 | 198,583 | 1.66 | 10,588 |
| Yarlarweelor | - | - | - | 2,239,938 | 1.87 | 134,726 | 2,239,938 | 1.87 | 134,726 |
| Horseshoe | |||||||||
| Horseshoe Group | - | - | - | 414,957 | 2.28 | 30,412 | 414,957 | 2.28 | 30,412 |
| Peak Hill | |||||||||
| Enigma | - | - | - | - | - | - | - | - | - |
| Durack | - | - | - | - | - | - | - | - | - |
| Five Ways | - | - | - | - | - | - | - | - | - |
| Harmony | - | - | - | - | - | - | - | - | - |
| Jubilee | - | - | - | - | - | - | - | - | - |
| Stockpiles | |||||||||
| Eldorado | - | - | - | 106,600 | 0.71 | 2,444 | 106,600 | 0.71 | 2,444 |
| ROM Finger 1 | - | - | - | 1,915 | 0.78 | 48 | 1,915 | 0.78 | 48 |
| ROM Finger 2 | - | - | - | 5,112 | 1.78 | 293 | 5,112 | 1.78 | 293 |
| ROM Finger 3 | - | - | - | 18,693 | 0.95 | 571 | 18,693 | 0.95 | 571 |
| ROM Finger 4 | - | - | - | 3,059 | 1.71 | 168 | 3,059 | 1.71 | 168 |
| ROM Finger 5 | - | - | - | 5,989 | 0.87 | 168 | 5,989 | 0.87 | 168 |
| Scats | - | - | - | 16,240 | 1.60 | 835 | 16,240 | 1.60 | 835 |
| Skyway | - | - | - | 56,640 | 0.76 | 1,382 | 56,640 | 0.76 | 1,382 |
| Starlight | - | - | - | 86,400 | 1.19 | 3,314 | 86,400 | 1.19 | 3,314 |
| Trevs | - | - | - | 163,680 | 0.73 | 3,833 | 163,680 | 0.73 | 3,833 |
| Yarlarweelor | - | - | - | 161,600 | 0.64 | 3,348 | 161,600 | 0.64 | 3,348 |
| Horseshoe-Cassidy | - | - | - | 177,600 | 1.16 | 6,636 | 177,600 | 1.16 | 6,636 |
| Harmony | - | - | - | 200,541 | 1.53 | 9,871 | 200,541 | 1.53 | 9,871 |
| Jubilee | - | - | - | - | - | - | - | - | - |
| Labouchere | - | - | - | 62,474 | 0.96 | 1,934 | 62,474 | 0.96 | 1,934 |
| Nathans / Wilthorpe | - | - | - | - | - | - | - | - | - |
| Peak Hill | - | - | - | 35,600 | 1.14 | 1,302 | 35,600 | 1.14 | 1,302 |
| Tom’s and Sam’s | - | - | - | - | - | - | - | - | - |
| Totals | - | - | - | 5,391,588 | 1.95 | 338,779 | 5,391,588 | 1.95 | 338,779 |
APPENDIX4 – FGP ORE RESERVES STATEMENT 16
APPENDIX 5 – SIGNIFICANT (>5gram metres) EXPLORATION RESULTS FOR THE QUARTER FORTNUM GOLD PROJECT
==> picture [506 x 28] intentionally omitted <==
----- Start of picture text -----
From
Lode Hole Collar N Collar E Collar RL Intercept (True Width) Dip Azi
(m)
----- End of picture text -----
| Lode | Hole | Collar N | Collar E | Collar RL | Intercept (True Width) | From (m) |
Dip | Azi |
|---|---|---|---|---|---|---|---|---|
| DEVELOPMENT PLAN RESOURCE DRILLING | ||||||||
| Yarlarweelor Re- source |
MXC0370 | 7196299.14 | 636915.256 | 429.325 | 20.2m at 1.44g/t Au | 20.0 | -67.0 | 150 |
| incl | 3.4m at 6.9g/t Au | 40.0 | ||||||
| MXC0371 | 7196329.12 | 636903.032 | 431.47 | 2m at 6.57g/t Au | 30.0 | -60.0 | 90 | |
| MXC0371 | 7196328.55 | 636912.769 | 414.101 | 9.2m at 3.96g/t Au | 46.0 | |||
| incl | 5.5m at 6.35g/t Au | 48.0 | ||||||
| MXC0373 | 7196347.8 | 636923.875 | 430.593 | 3m at 6.08g/t Au | 33.0 | |||
| MXC0374 | 7196368.78 | 636862.717 | 437.18 | 10.5m at 2.02g/t Au | 20.0 | -61.0 | 90 | |
| MXC0374 | 7196367.44 | 636887.006 | 389.496 | 10m at 0.65g/t Au | 72.0 | |||
| MXC0375 | 7196389.34 | 636901.665 | 420.32 | 14.6m at 2.62g/t Au | 37.0 | -73.0 | 90 | |
| incl | 7.3m at 4.73g/t Au | 37.0 | ||||||
| MXC0377 | 7196429.1 | 636883.292 | 402.491 | 13m at 0.93g/t Au | 59.0 | -63.0 | 90 | |
| incl | 2m at 3.54g/t Au | 70.0 | ||||||
| MXC0406 | 7195644.81 | 636713.445 | 383.187 | 29.3m at 0.78g/t Au | 113.8 | -63.0 | 90 | |
| incl | 4.5m at 2.59g/t Au | 142.0 | ||||||
| MXC0407 | 7195658.02 | 636766.574 | 427.481 | 5.4m at 2.14g/t Au | 83.0 | -59.0 | 74 | |
| MXC0409 | 7195681.92 | 636725.651 | 393.282 | 3.1m at 1.27g/t Au | 131.0 | -54.0 | 82 | |
| MXC0409 | 7195683.11 | 636741.745 | 368.96 | 11.2m at 0.84g/t Au | 155.0 | |||
| incl | 1.5m at 4.1g/t Au | 163.0 | ||||||
| MXC0412 | 7195744.9 | 636712.831 | 351.975 | 8.6m at 0.54g/t Au | 130.0 | -90.0 | 0 | |
| MXC0413 | 7195746 | 636736.701 | 397.368 | 5.4m at 0.75g/t Au | 90.0 | -78.0 | 90 | |
| MXC0414 | 7195762.59 | 636714.535 | 347.552 | 16m at 2.08g/t Au | 132.0 | -90.0 | 0 | |
| incl | 2.7m at 8.4g/t Au | 132 | ||||||
| incl | 1.3m at 4.55g/t Au | 154 | ||||||
| MXC0415 | 7195785.5 | 636727.979 | 374.288 | 11.4m at 1.03g/t Au | 109.0 | -83.0 | 90 | |
| incl | 3.6m at 1.84g/t Au | 19.0 | ||||||
| MXC0416 | 7195844.91 | 636739.26 | 389.737 | 9.1m at 1.26g/t Au | 99.0 | -69.0 | 90 | |
| incl | 6.3m at 1.68g/t Au | 103.0 | ||||||
| MXC0378 | 7196448.87 | 636879.232 | 402.429 | 9.3m at 0.89g/t Au | 62.0 | |||
| incl | 1.7m at 3.14g/t Au | 62.0 | ||||||
| MXC0379 | 7196449.56 | 636930.699 | 389.424 | 6.9m at 1.21g/t Au | 78.0 | |||
| incl | 4.3m at 1.7g/t Au | 80.0 | ||||||
| MXC0380 | 7196450.64 | 636937.976 | 408.542 | 1.8m at 21.06g/t Au | 61.0 | -60 | 90 | |
| MXC0380 | 7196450.95 | 636942.325 | 400.658 | 1.8m at 5.13g/t Au | 70.0 | |||
| MXC0381 | 7196478.63 | 636861.948 | 408.779 | 5.8m at 1.63g/t Au | 48.0 | |||
| MXC0382 | 7196468.51 | 636922.456 | 378.939 | 3.6m at 4.91g/t Au | 92.0 | |||
| MXC0383 | 7196475.64 | 636943.521 | 425.659 | 2.5m at 4.33g/t Au | 30.0 | |||
| MXC0383 | 7196473.21 | 636949.414 | 409.908 | 8.7m at 2.36g/t Au | 43.0 | -67 | 113 | |
| incl | 3.2m at 4.86g/t Au | 43.0 | ||||||
| MXC0384 | 7196485.81 | 636860.317 | 441.971 | 3.7m at 1.56g/t Au | 16.0 | |||
| MXC0384 | 7196486.93 | 636862.179 | 430.803 | 6.9m at 0.81g/t Au | 25.0 | |||
| MXC0385 | 7196493.31 | 636921.058 | 424.277 | 1.6m at 3.33g/t Au | 28.0 | -77 | 107 | |
| MXC0386 | 7196490.18 | 636933.42 | 431.706 | 2.6m at 2.05g/t Au | 21.0 | -62 | 90 |
APPENDIX 5 – SIGNIFICANT EXPLORATION RESULTS FOR THE QUARTER 17
==> picture [506 x 27] intentionally omitted <==
----- Start of picture text -----
From
Lode Hole Collar N Collar E Collar RL Intercept (True Width) Dip Azi
(m)
----- End of picture text -----
| Lode | Hole | Collar N | Collar E | Collar RL | Intercept (True Width) | From (m) |
Dip | Azi |
|---|---|---|---|---|---|---|---|---|
| MXC0386 | 7196490.3 | 636940.39 | 417.72 | 3.8m at 1.55g/t Au | 37.0 | |||
| MXC0389 | 7196510.58 | 636970.692 | 442.236 | 5.9m at 1.85g/t Au | 9.0 | -73 | 90 | |
| MXC0389 | 7196510.52 | 636973.306 | 433.647 | 3.6m at 3.38g/t Au | 20.0 | |||
| MXC0390 | 7196534.59 | 636939.189 | 430.759 | 6m at 1.26g/t Au | 21.0 | |||
| MXC0391 | 7196550.34 | 636919.499 | 423.018 | 6.1m at 2.18g/t Au | 36.0 | |||
| MXC0392 | 7196545.02 | 636938.13 | 441.576 | 1.8m at 12.38g/t Au | 15.0 | |||
| MXC0392 | 7196544.86 | 636944.696 | 430.125 | 11.8m at 3.75g/t Au | 23.0 | |||
| incl | 6.4m at 6.28g/t Au | 22.0 | ||||||
| MXC0392 | 7196544.42 | 636954.702 | 412.28 | 11.5m at 21.42g/t Au | 44.0 | |||
| incl | 3.8m at 6.91g/t Au | 44.0 | ||||||
| incl | 4.8m at 45.6g/t Au | 51.0 | ||||||
| MXC0393 | 7196545.75 | 636951.571 | 452.773 | 6m at 0.9g/t Au | 0.0 | -61 | 76 | |
| MXC0393 | 7196547 | 636956.954 | 442.752 | 10.5m at 2.39g/t Au | 9.0 | |||
| MXC0394 | 7196574.95 | 636922.83 | 429.874 | 3m at 4.52g/t Au | 27.0 | -62 | 90 | |
| MXC0405 | 7195626.24 | 636724.775 | 388.945 | 4.6m at 13.76g/t Au | 124.7 | |||
| incl | 0.5m at 120g/t Au | 124.7 | ||||||
| incl | 1.9m at 4.42g/t Au | 145.0 | ||||||
| MXC0409 | 7195683.11 | 636741.745 | 368.96 | 11.2m at 0.81g/t Au | 155.0 | |||
| incl | 1.4m at 4.1g/t Au | 163.0 | ||||||
| MXC0410 | 7195707.7 | 636717.922 | 371.301 | 4.5m at 5.09g/t Au | 120.1 | -73 | 176 | |
| incl | 2.1m at 9.24g/t Au | 125.8 | ||||||
| MXC0411 | 7195731.51 | 636712.635 | 343.385 | 1m at 7.55g/t Au | 147.5 | |||
| MXC0412 | 7195744.9 | 636712.831 | 351.975 | 4.8m at 1.1g/t Au | 130.0 | -90 | 270 | |
| MXC0414 | 7195763.7 | 636714.723 | 357.513 | 3.5m at 8.4g/t Au | 132.0 | -90 | 270 | |
| MXC0414 | 7195762.08 | 636714.48 | 343.223 | 10.9m at 1.07g/t Au | 141.0 | |||
| incl | 1.5m at 4.55g/t Au | 154.0 | ||||||
| MXC0415 | 7195785.5 | 636727.979 | 374.288 | 11.4m at 1.03g/t Au | 109.0 | -83 | 90 | |
| incl | 3.6m at 1.84g/t Au | 109.0 | ||||||
| MXC0416 | 7195844.91 | 636739.26 | 389.737 | 9.1m at 1.26g/t Au | 99.0 | -69 | 90 | |
| incl | 6.3m at 1.68g/t Au | 103.0 | ||||||
| MXC0417 | 7195933.3 | 636720.724 | 370.192 | 2.2m at 2.54g/t Au | 162.0 | -48 | 61 | |
| MXC0417 | 7195934.32 | 636722.94 | 366.005 | 4.3m at 11.62g/t Au | 166.0 | |||
| incl | 2.1m at 21.61g/t Au | 166.0 | ||||||
| Toms Resource | MXC0419 | 7198291.64 | 637267.648 | 456.219 | 11m at 0.63g/t Au | 60.0 | -48 | 62 |
| MXC0420 | 7198354.76 | 637250.781 | 483.475 | 4.8m at 2.94g/t Au | 4.0 | -90 | 0 | |
| MXC0422 | 7197143.06 | 636284.178 | 440.74 | 4.6m at 8.44g/t Au | 64.0 | |||
| incl | 2.3m at 15.19g/t Au | 65.0 | ||||||
| MXC0423 | 7197270.14 | 636257.518 | 439.312 | 11.6m at 1.42g/t Au | 60.0 | |||
| incl | 2.3m at 3.6g/t Au | 66.0 | ||||||
| DDH1-F4 | 7198000.37 | 637197.406 | 422.746 | 7.6m at 0.8g/t Au | 90.4 | -60 | 90 | |
| DDH1-F4 | 7198000.46 | 637204.334 | 410.742 | 15.3m at 1.55g/t Au | 101.0 | |||
| incl | 5m at 2.56g/t Au | 104.0 | ||||||
| incl | 3.8m at 2.22g/t Au | 112.0 | ||||||
| DDH1-F5 | 7198113.1 | 637071.832 | 470.602 | 2.5m at 3.46g/t Au | 38.0 | |||
| DDH1-F5 | 7198130.72 | 637088.956 | 428.048 | 5.1m at 1.02g/t Au | 85.0 | |||
| DDH1-F6 | 7198021.57 | 637067.151 | 460.934 | 2.5m at 2.86g/t Au | 49.2 | -60 | 135 |
APPENDIX 5 – SIGNIFICANT EXPLORATION RESULTS FOR THE QUARTER 18
| Lode | Hole | Collar N | Collar E | Collar RL | Intercept (True Width) | From (m) |
Dip | Azi |
|---|---|---|---|---|---|---|---|---|
| Composite | MXC0374 | 7196368.78 | 636862.717 | 437.18 | 9.5m at 1.68g/t Au | 20.0 | -61 | 90 |
| Resampling | incl | 5.7m at 2g/t Au | 24.0 | |||||
| MXC0381 | 7196479.04 | 636858.456 | 448.445 | 9.2m at 0.76g/t Au | 9.0 | -85 | 90 | |
| MXC0381 | 7196478.63 | 636861.948 | 408.779 | 5.8m at 1.04g/t Au | 49.0 | |||
| MXC0387 | 7196509.65 | 636904.283 | 421.807 | 22m at 2.97g/t Au | 26.0 | -56 | 90 | |
| incl | 12.4m at 4.65g/t Au | 31.0 | ||||||
| MXC0396 | 7196350.51 | 636979.442 | 450.919 | 4.6m at 1.83g/t Au | 4.0 | -46 | 90 | |
| incl | 1.8m at 3.96g/t Au | 4.0 | ||||||
| MXC0396 | 7196350.51 | 636979.442 | 450.919 | 5.4m at 1.18g/t Au | 17.0 | |||
| MXC0398 | 7196430.81 | 636987.144 | 452.547 | 4m at 1.37g/t Au | 6.0 | -55 | 90 | |
| MXC0415 | 7195785.5 | 636727.979 | 374.288 | 4.8m at 1.45g/t Au | 5.0 | -83 | 90 | |
| MXC0417 | 7195888.5 | 636635.283 | 502.5 | 3.8m at 4.36g/t Au | 30.0 | -48 | 61 | |
| incl | 1.9m at 8.22g/t Au | 32.0 | ||||||
| Lode | Hole | Collar N | Collar E | Collar RL | Intercept (True Width) | From (m) |
Dip | Azi |
| DEVELOPMENT PLAN LOW GRADE STOCKPILE DRILLING | ||||||||
| Yarlarweelor LGSP | MXC0013 | 7196665.87 | 637358.977 | 513.017 | 5m at 2.31g/t Au | 4.0 | -90.0 | 0.0 |
| MXC0015 | 7196665.4 | 637319.621 | 513.428 | 5m at 1.13g/t Au | 4.0 | |||
| MXC0029 | 7196645.49 | 637359.262 | 513.345 | 9m at 0.75g/t Au | 0.0 | -90.0 | 0.0 | |
| MXC0035 | 7196636.87 | 637390.25 | 513.971 | 10m at 0.55g/t Au | 0.0 | -90.0 | 0.0 | |
| MXC0036 | 7196635.66 | 637368.165 | 513.621 | 9m at 1.48g/t Au | 1.0 | -90.0 | 0.0 | |
| MXC0037 | 7196635.64 | 637349.36 | 513.474 | 10m at 0.77g/t Au | 0.0 | -90.0 | 0.0 | |
| MXC0047 | 7196615.74 | 637329.073 | 513.293 | 8m at 2g/t Au | 0.0 | -90.0 | 0.0 | |
| MXC0057 | 7196587.45 | 637361.743 | 515.5 | 13m at 0.57g/t Au | 0.0 | -90.0 | 0.0 | |
| MXC0058 | 7196579.65 | 637372.993 | 515.709 | 12m at 0.9g/t Au | 0.0 | -90.0 | 0.0 | |
| MXC0059 | 7196567.61 | 637386.279 | 516.74 | 6m at 2.31g/t Au | 1.0 | -90.0 | 0.0 | |
| MXC0060 | 7196601.82 | 637413.958 | 515.897 | 8m at 0.67g/t Au | 0.0 | -90.0 | 0.0 | |
| MXC0446 | 7196591.55 | 637405.692 | 516.064 | 10m at 4.66g/t Au | 0.0 | -90.0 | 0.0 | |
| MXC0448 | 7196550.43 | 637364.213 | 515.706 | 6m at 0.84g/t Au | 0.0 | -90.0 | 0.0 | |
| MXC0066 | 7196827.61 | 637525.258 | 504.829 | 3m at 3.18g/t Au | 0.0 | -90.0 | 0.0 | |
| MXC0085 | 7196798.29 | 637518.297 | 504.518 | 2m at 3.52g/t Au | 0.0 | -90.0 | 0.0 | |
| MXC0115 | 7196748.08 | 637528.1 | 505 | 2m at 6.39g/t Au | 0.0 | -90.0 | 0.0 | |
| ROM Skyway LGSP | MXC0135 | 7197761.3 | 636272.419 | 524.817 | 8m at 0.7g/t Au | 0.0 | -90.0 | 0.0 |
| MXC0138 | 7197751.41 | 636266.113 | 524.899 | 11m at 0.63g/t Au | 0.0 | -90.0 | 0.0 | |
| MXC0141 | 7197740.67 | 636293.608 | 524.791 | 8m at 0.65g/t Au | 0.0 | -90.0 | 0.0 | |
| MXC0142 | 7197740.53 | 636274.151 | 524.632 | 12m at 0.53g/t Au | 0.0 | -90.0 | 0.0 | |
| MXC0144 | 7197730.48 | 636303.219 | 524.77 | 7m at 0.76g/t Au | 0.0 | -90.0 | 0.0 | |
| MXC0145 | 7197730.66 | 636283.408 | 524.725 | 9m at 1.4g/t Au | 0.0 | -90.0 | 0.0 | |
| MXC0149 | 7197720.07 | 636293.442 | 524.935 | 11m at 0.96g/t Au | 0.0 | -90.0 | 0.0 | |
| MXC0152 | 7197710.35 | 636303.592 | 525.181 | 11m at 0.52g/t Au | 0.0 | -90.0 | 0.0 | |
| MXC0166 | 7197681.11 | 636333.783 | 515.502 | 6m at 0.89g/t Au | 0.0 | -90.0 | 0.0 | |
| MXC0178 | 7197662.47 | 636332.08 | 516.246 | 7m at 0.73g/t Au | 2.0 | -90.0 | 0.0 | |
| MXC0425 | 7197757.4 | 636310.552 | 522.661 | 10m at 1.55g/t Au | 0.0 | -90 | 0 | |
| MXC0426 | 7197767.88 | 636304.617 | 523.651 | 10m at 0.8g/t Au | 0.0 | -90 | 0 | |
| MXC0427 | 7197777.78 | 636299.884 | 525.973 | 10m at 0.92g/t Au | 0.0 | -90 | 0 |
APPENDIX 5 – SIGNIFICANT EXPLORATION RESULTS FOR THE QUARTER 19
==> picture [505 x 27] intentionally omitted <==
----- Start of picture text -----
From
Lode Hole Collar N Collar E Collar RL Intercept (True Width) Dip Azi
(m)
----- End of picture text -----
| Lode | Hole | Collar N | Collar E | Collar RL | Intercept (True Width) | From (m) |
Dip | Azi |
|---|---|---|---|---|---|---|---|---|
| MXC0428 | 7197789.28 | 636291.643 | 528.818 | 10m at 0.56g/t Au | 0.0 | -90 | 0 | |
| Eldorado LGSP | MXC0200 | 7197552.41 | 636386.916 | 514.26 | 5m at 1.71g/t Au | 0.0 | -90.0 | 0.0 |
| MXC0201 | 7197551.78 | 636367.001 | 514.133 | 5m at 27.21g/t Au | 0.0 | -90.0 | 0.0 | |
| incl | 1m at 132g/t Au | 4.0 | ||||||
| MXC0203 | 7197542.06 | 636396.93 | 514.222 | 6m at 0.86g/t Au | 0.0 | -90.0 | 0.0 | |
| MXC0204 | 7197542.6 | 636376.954 | 514.221 | 5m at 7.24g/t Au | 0.0 | -90.0 | 0.0 | |
| incl | 1m at 32.4g/t Au | 0.0 | ||||||
| MXC0222 | 7197473.19 | 636468.349 | 513.586 | 10m at 0.51g/t Au | 0.0 | -90.0 | 0.0 | |
| MXC0224 | 7197464.66 | 636496.684 | 512.117 | 10m at 0.56g/t Au | 0.0 | -90.0 | 0.0 | |
| MXC0225 | 7197463.34 | 636478.413 | 512.727 | 11m at 0.65g/t Au | 0.0 | -90.0 | 0.0 | |
| MXC0226 | 7197463.39 | 636458.545 | 513.165 | 9m at 0.77g/t Au | 0.0 | -90.0 | 0.0 | |
| MXC0227 | 7197453.35 | 636508.644 | 511.649 | 10m at 2.36g/t Au | 0.0 | -90.0 | 0.0 | |
| MXC0228 | 7197453.7 | 636488.031 | 511.858 | 10m at 1.28g/t Au | 0.0 | -90.0 | 0.0 | |
| MXC0230 | 7197444.57 | 636516.202 | 510.807 | 9m at 0.68g/t Au | 0.0 | -90.0 | 0.0 | |
| MXC0232 | 7197443.73 | 636479.265 | 511.923 | 9m at 1.05g/t Au | 0.0 | -90.0 | 0.0 | |
| MXC0234 | 7197433.85 | 636508.59 | 510.172 | 9m at 0.92g/t Au | 0.0 | -90.0 | 0.0 | |
| MXC0238 | 7197426.42 | 636498.87 | 509.244 | 8m at 0.71g/t Au | 0.0 | -90.0 | 0.0 | |
| MXC0240 | 7197416.38 | 636509.271 | 507.685 | 6m at 2.15g/t Au | 0.0 | -90.0 | 0.0 | |
| MXC0250 | 7197365.88 | 636558.292 | 506.678 | 5m at 1.1g/t Au | 0.0 | -90.0 | 0.0 | |
| Trev’s LGSP | MXC0251 | 7198459.06 | 636192.952 | 514.983 | 11m at 0.54g/t Au | 0.0 | -90.0 | 0.0 |
| MXC0252 | 7198459.47 | 636174.237 | 515.164 | 12m at 1.18g/t Au | 0.0 | -90.0 | 0.0 | |
| MXC0253 | 7198458.66 | 636153.921 | 515.839 | 13m at 0.74g/t Au | 0.0 | -90.0 | 0.0 | |
| MXC0254 | 7198458.04 | 636134.009 | 516.03 | 13m at 0.82g/t Au | 0.0 | -90.0 | 0.0 | |
| MXC0255 | 7198457.81 | 636113.641 | 515.591 | 10m at 1.07g/t Au | 3.0 | -90.0 | 0.0 | |
| MXC0256 | 7198450.07 | 636203.877 | 513.173 | 9m at 0.7g/t Au | 0.0 | -90.0 | 0.0 | |
| MXC0257 | 7198449.18 | 636184.099 | 515.128 | 11m at 0.66g/t Au | 0.0 | -90.0 | 0.0 | |
| MXC0258 | 7198449.95 | 636164.227 | 515.216 | 12m at 0.98g/t Au | 0.0 | -90.0 | 0.0 | |
| MXC0259 | 7198448.43 | 636144.975 | 515.829 | 12m at 0.65g/t Au | 0.0 | -90.0 | 0.0 | |
| MXC0260 | 7198448.22 | 636124.009 | 515.796 | 11m at 0.49g/t Au | 0.0 | -90.0 | 0.0 | |
| MXC0261 | 7198448.2 | 636104.585 | 515.945 | 9m at 1.76g/t Au | 0.0 | -90.0 | 0.0 | |
| MXC0264 | 7198440 | 636214.263 | 510.596 | 7m at 0.75g/t Au | 0.0 | -90.0 | 0.0 | |
| MXC0265 | 7198439.52 | 636193.006 | 514.332 | 11m at 0.9g/t Au | 0.0 | -90.0 | 0.0 | |
| MXC0266 | 7198438.75 | 636174.575 | 514.922 | 11m at 0.79g/t Au | 1.0 | -90.0 | 0.0 | |
| MXC0267 | 7198438.58 | 636154.604 | 515.516 | 12m at 0.64g/t Au | 0.0 | -90.0 | 0.0 | |
| MXC0268 | 7198438.69 | 636134.451 | 515.937 | 12m at 0.65g/t Au | 0.0 | -90.0 | 0.0 | |
| MXC0269 | 7198437.97 | 636114.43 | 515.636 | 11m at 0.85g/t Au | 0.0 | -90.0 | 0.0 | |
| MXC0273 | 7198429.68 | 636204.301 | 511.997 | 9m at 0.73g/t Au | 0.0 | -90.0 | 0.0 | |
| MXC0275 | 7198429.52 | 636163.834 | 515.422 | 12m at 0.55g/t Au | 0.0 | -90.0 | 0.0 | |
| MXC0276 | 7198428.99 | 636144.642 | 516.075 | 12m at 1.07g/t Au | 0.0 | -90.0 | 0.0 | |
| MXC0277 | 7198428.44 | 636124.578 | 515.786 | 12m at 0.86g/t Au | 0.0 | -90.0 | 0.0 | |
| MXC0278 | 7198428.27 | 636103.845 | 515.502 | 9m at 0.98g/t Au | 0.0 | -90.0 | 0.0 | |
| MXC0282 | 7198419.77 | 636214.408 | 510.642 | 7m at 0.79g/t Au | 0.0 | -90.0 | 0.0 | |
| MXC0284 | 7198410.17 | 636265.031 | 504.928 | 2m at 3.07g/t Au | 0.0 | -90.0 | 0.0 | |
| MXC0319 | 7198288.16 | 636166.511 | 510.144 | 1m at 7.4g/t Au | 6.0 | -90.0 | 0.0 | |
| MXC0332 | 7198248.75 | 636186.17 | 507.391 | 3m at 1.79g/t Au | 0.0 | -90.0 | 0.0 | |
| Toms LGSP | MXC0337 | 7198755.16 | 637328.988 | 523.859 | 10m at 1.34g/t Au | 0.0 | -90.0 | 0.0 |
| MXC0342 | 7198785.85 | 637358.714 | 522.619 | 2m at 8.31g/t Au | 1.0 | -90.0 | 0.0 |
APPENDIX 5 – SIGNIFICANT EXPLORATION RESULTS FOR THE QUARTER 20
==> picture [505 x 27] intentionally omitted <==
----- Start of picture text -----
From
Lode Hole Collar N Collar E Collar RL Intercept (True Width) Dip Azi
(m)
----- End of picture text -----
| Lode | Hole | Collar N | Collar E | Collar RL | Intercept (True Width) | From (m) |
Dip | Azi |
|---|---|---|---|---|---|---|---|---|
| MXC0345 | 7198775 | 637328.983 | 523.673 | 7m at 0.82g/t Au | 0.0 | -90.0 | 0.0 | |
| MXC0351 | 7198745.06 | 637319.177 | 524.12 | 9m at 2.62g/t Au | 0.0 | -90.0 | 0.0 | |
| MXC0356 | 7198725.27 | 637319.561 | 524.061 | 3m at 2.39g/t Au | 0.0 | -90.0 | 0.0 | |
| Starlight LGSP | MXC0358 | 7199237.11 | 637462.315 | 535.099 | 5m at 1.24g/t Au | 0.0 | -90.0 | 0.0 |
| MXC0359 | 7199226.82 | 637472.137 | 534.684 | 5m at 1.64g/t Au | 0.0 | -90.0 | 0.0 | |
| MXC0360 | 7199227.21 | 637452.676 | 534.953 | 5m at 4.81g/t Au | 0.0 | -90.0 | 0.0 | |
| MXC0361 | 7199217.23 | 637482.105 | 534.674 | 5m at 1.62g/t Au | 0.0 | -90.0 | 0.0 | |
| MXC0362 | 7199217.42 | 637462.863 | 534.785 | 5m at 1.33g/t Au | 0.0 | -90.0 | 0.0 | |
| MXC0363 | 7199217.29 | 637445.581 | 533.18 | 5m at 1.7g/t Au | 0.0 | -90.0 | 0.0 | |
| MXC0367 | 7199195.11 | 637463.103 | 532.838 | 4m at 1.89g/t Au | 0.0 | -90.0 | 0.0 | |
| Horseshoe LGSP | MXC0450 | 7182921.51 | 661291.913 | 539.228 | 6m at 1.62g/t Au | 0.0 | -90.0 | 0.0 |
| MXC0451 | 7182960.47 | 661269.726 | 539.111 | 6m at 1.55g/t Au | 0.0 | -90.0 | 0.0 | |
| MXC0453 | 7182939.98 | 661291.39 | 539.096 | 6m at 1.22g/t Au | 0.0 | -90.0 | 0.0 | |
| MXC0454 | 7182980.62 | 661289.185 | 538.87 | 6m at 1.67g/t Au | 0.0 | -90.0 | 0.0 | |
| MXC0457 | 7182709.79 | 661359.52 | 542.674 | 6m at 1.73g/t Au | 0.0 | -90.0 | 0.0 | |
| MXC0460 | 7182908.55 | 661399.937 | 538.902 | 6m at 1.13g/t Au | 0.0 | -90.0 | 0.0 | |
| MXC0461 | 7182766.86 | 661381.642 | 540.682 | 6m at 3.42g/t Au | 0.0 | -90.0 | 0.0 | |
| incl | 1m at 12.4g/t Au | 5.0 | ||||||
| MXC0462 | 7182770.85 | 661367.863 | 540.542 | 6m at 1.18g/t Au | 0.0 | -90.0 | 0.0 | |
| MXC0463 | 7182776.74 | 661342.582 | 540.437 | 6m at 1.11g/t Au | 0.0 | -90.0 | 0.0 | |
| MXC0465 | 7182828.98 | 661320.01 | 537.97 | 5m at 2.17g/t Au | 0.0 | -90.0 | 0.0 | |
| MXC0467 | 7182919.46 | 661266.293 | 539.439 | 6m at 3.07g/t Au | 0.0 | -90.0 | 0.0 | |
| incl | 1m at 10.9g/t Au | 4.0 | ||||||
| Peak Hill LGSP | MXC0469 | 7163140 | 671990 | 610.377 | 7m at 2.5g/t Au | 0 | -90 | 0 |
| MXC0470 | 7163120 | 671960 | 613.568 | 10m at 5.93g/t Au | 0 | -90 | 0 | |
| incl | 2m at 27.8g/t Au | 5 | -90 | 0 | ||||
| MXC0471 | 7163120 | 671980 | 613.544 | 10m at 0.72g/t Au | 0 | -90 | 0 | |
| MXC0473 | 7163100 | 671950 | 612.174 | 9m at 1.18g/t Au | 0 | -90 | 0 | |
| MXC0474 | 7163100 | 671970 | 612.656 | 9m at 0.61g/t Au | 0 | -90 | 0 | |
| MXC0477 | 7163080 | 671980 | 611.061 | 8m at 0.76g/t Au | 0 | -90 | 0 | |
| MXC0490 | 7162801.04 | 672418.69 | 609.857 | 5m at 1.48g/t Au | 0 | -90 | 0 | |
| MXC0491 | 7162787.61 | 672401.804 | 610.183 | 5m at 5.02g/t Au | 0 | -90 | 0 | |
| incl | 3m at 8.25g/t Au | 1 | -90 | 0 | ||||
| MXC0502 | 7164785.57 | 672449.646 | 574.046 | 5m at 3.08g/t Au | 0 | -90 | 0 | |
| Harmony LGSP | MXC0521 | 7161214.21 | 664334.712 | 550.143 | 6m at 1.65g/t Au | 0 | -90 | 0 |
| MXC0522 | 7161199.77 | 664320.276 | 550.585 | 6m at 1.7g/t Au | 0 | -90 | 0 | |
| incl | 2m at 3.34g/t Au | 3 | -90 | 0 | ||||
| MXC0524 | 7161187.7 | 664281.464 | 550.007 | 4m at 1.84g/t Au | 0 | -90 | 0 | |
| MXC0525 | 7161188.17 | 664261.111 | 549.75 | 4m at 2.01g/t Au | 0 | -90 | 0 | |
| MXC0528 | 7161228.88 | 664228.688 | 550.274 | 6m at 1.95g/t Au | 0 | -90 | 0 | |
| MXC0532 | 7161291.36 | 664237.208 | 551.232 | 7m at 1.83g/t Au | 0 | -90 | 0 | |
| incl | 3m at 2.16g/t Au | 3 | -90 | 0 | ||||
| MXC0533 | 7161291.12 | 664257.324 | 548.473 | 4m at 3.45g/t Au | 0 | -90 | 0 | |
| MXC0540 | 7161326.05 | 664203.11 | 553.931 | 9m at 1.39g/t Au | 0 | -90 | 0 | |
| incl | 4m at 2.16g/t Au | 1 | -90 | 0 | ||||
| MXC0541 | 7161311.73 | 664218.269 | 553.75 | 9m at 4.27g/t Au | 0 | -90 | 0 | |
| incl | 3m at 11.27g/t Au | 6 | -90 | 0 |
APPENDIX 5 – SIGNIFICANT EXPLORATION RESULTS FOR THE QUARTER 21
==> picture [505 x 27] intentionally omitted <==
----- Start of picture text -----
From
Lode Hole Collar N Collar E Collar RL Intercept (True Width) Dip Azi
(m)
----- End of picture text -----
| Lode | Hole | Collar N | Collar E | Collar RL | Intercept (True Width) | From (m) |
Dip | Azi |
|---|---|---|---|---|---|---|---|---|
| MXC0543 | 7161429.15 | 664231.651 | 550.275 | 5m at 1.6g/t Au | 0 | -90 | 0 | |
| MXC0544 | 7161438.15 | 664249.634 | 550.533 | 5m at 1.38g/t Au | 0 | -90 | 0 | |
| MXC0545 | 7161446.93 | 664268.026 | 551.17 | 6m at 1.23g/t Au | 0 | -90 | 0 | |
| MXC0546 | 7161455.72 | 664286.01 | 551.447 | 7m at 0.93g/t Au | 0 | -90 | 0 | |
| MXC0547 | 7161465.53 | 664303.584 | 550.917 | 6m at 2.19g/t Au | 0 | -90 | 0 | |
| incl | 3m at 3.97g/t Au | 2 | -90 | 0 | ||||
| MXC0548 | 7161474.73 | 664321.363 | 551.61 | 6m at 1.28g/t Au | 0 | -90 | 0 | |
| MXC0549 | 7161483.51 | 664339.755 | 551.218 | 6m at 1.73g/t Au | 0 | -90 | 0 | |
| MXC0550 | 7161466.14 | 664349.973 | 551.385 | 6m at 2.05g/t Au | 0 | -90 | 0 | |
| incl | 2m at 4.39g/t Au | 4 | -90 | 0 | ||||
| MXC0551 | 7161456.33 | 664331.581 | 551.956 | 7m at 3.29g/t Au | 0 | -90 | 0 | |
| MXC0552 | 7161448.16 | 664313.189 | 551.676 | 7m at 0.74g/t Au | 0 | -90 | 0 | |
| MXC0554 | 7161432.22 | 664276.814 | 550.991 | 6m at 2.17g/t Au | 0 | -90 | 0 | |
| incl | 2m at 4.16g/t Au | 4 | -90 | 0 | ||||
| MXC0555 | 7161423.43 | 664258.626 | 550.605 | 6m at 0.98g/t Au | 0 | -90 | 0 | |
| MXC0556 | 7161414.24 | 664240.438 | 550.816 | 6m at 0.89g/t Au | 0 | -90 | 0 | |
| MXC0557 | 7161405.45 | 664222.251 | 549.946 | 5m at 2.18g/t Au | 0 | -90 | 0 | |
| incl | 2m at 3.74g/t Au | 3 | -90 | 0 | ||||
| MXC0569 | 7205530 | 628180 | 489.026 | 4m at 1.37g/t Au | 0 | -90 | 0 | |
| MXC0571 | 7205510 | 628160 | 489.062 | 4m at 1.51g/t Au | 0 | -90 | 0 | |
| MXC0581 | 7205470 | 628200 | 488.861 | 4m at 2.06g/t Au | 0 | -90 | 0 | |
| MXC0583 | 7205470 | 628240 | 489.435 | 5m at 1.13g/t Au | 0 | -90 | 0 | |
| MXC0584 | 7205450 | 628240 | 489.383 | 5m at 1.05g/t Au | 0 | -90 | 0 | |
| MXC0594 | 7199812.5 | 631712.5 | 519 | 5m at 1g/t Au | 0 | -90 | 0 | |
| MXC0596 | 7199812.5 | 631762.5 | 519 | 5m at 1.34g/t Au | 0 | -90 | 0 | |
| Toms LGSP | MXC0614 | 7198684.5 | 637280.751 | 520.66 | 12m at 0.5g/t Au | 0 | -90 | 0 |
| MXC0616 | 7198704.22 | 637260.473 | 520.698 | 10m at 0.57g/t Au | 0 | -90 | 0 | |
| MXC0617 | 7198704.5 | 637280.468 | 520.883 | 14m at 0.54g/t Au | 0 | -90 | 0 | |
| MXC0618 | 7198704.78 | 637300.464 | 521.088 | 10m at 0.52g/t Au | 0 | -90 | 0 | |
| MXC0619 | 7198724.21 | 637260.191 | 520.655 | 11m at 0.7g/t Au | 0 | -90 | 0 | |
| MXC0621 | 7198724.78 | 637300.181 | 520.957 | 12m at 0.59g/t Au | 0 | -90 | 0 | |
| MXC0622 | 7198744.21 | 637259.908 | 519.585 | 12m at 0.63g/t Au | 0 | -90 | 0 | |
| MXC0623 | 7198744.49 | 637279.903 | 520.1 | 12m at 1.05g/t Au | 0 | -90 | 0 | |
| MXC0624 | 7198744.77 | 637299.899 | 520.795 | 12m at 0.46g/t Au | 0 | -90 | 0 | |
| MXC0625 | 7198764.77 | 637299.616 | 519.042 | 11m at 0.53g/t Au | 0 | -90 | 0 | |
| MXC0627 | 7198764.48 | 637279.621 | 518.741 | 11m at 0.73g/t Au | 0 | -90 | 0 | |
| MXC0629 | 7198764.2 | 637259.626 | 518.534 | 12m at 0.51g/t Au | 0 | -90 | 0 | |
| MXC0631 | 7198743.92 | 637239.913 | 515.701 | 10m at 0.53g/t Au | 0 | -90 | 0 |
APPENDIX 5 – SIGNIFICANT EXPLORATION RESULTS FOR THE QUARTER 22
APPENDIX 6 – JORC TABLE 1
Section 1 Sampling Techniques and Data (Criteria in this section apply to all succeeding sections.)
==> picture [772 x 27] intentionally omitted <==
----- Start of picture text -----
Criteria JORC Code explanation Commentary
Sampling techniques • Nature and quality of sampling (e.g. cut channels, random chips, or specific • Historic reverse circulation drilling was used to collect samples at 1m intervals with sample quality,
----- End of picture text -----
| Criteria | JORC Code explanation | Commentary |
|---|---|---|
| Sampling techniques | • Nature and quality of sampling (e.g. cut channels, random chips, or specifc |
• Historic reverse circulation drilling was used to collect samples at 1m intervals with sample quality, |
| specialised industry standard measurement tools appropriate to the minerals under investigation, such as down hole gamma sondes, or handheld XRF instruments, etc.). These examples should not be taken as limiting the broad meaning of sampling. • Include reference to measures taken to ensure sample representivity and the appropriate calibration of any measurement tools or systems used. • Aspects of the determination of mineralisation that are Material to the Public Report. • In cases where ‘industry standard’ work has been done this would be relatively simple (e.g. ‘reverse circulation drilling was used to obtain 1 m samples from which 3 kg was pulverised to produce a 30 g charge for fre assay’). In other cases more explanation may be required, such as where there is coarse gold that has inherent sampling problems. Unusual commodities or mineralisation types (e.g. submarine nodules) may warrant disclosure of detailed information. |
recovery and moisture recorded on logging sheets. Bulk samples were composited to 4-5m samples by PVC spear. These composites were dried, crushed and split to produce a 30g charge for aqua regia digest at the Fortnum site laboratory. • For Metals X (MLX) RC Drilling drill cuttings are extracted from the RC return via cyclone. The underfow from each interval is transferred via bucket to a four tiered rife splitter, delivering approximately three kilograms of the recovered material into calico bags for analysis. The residual material is retained on the ground near the hole. Composite samples are obtained from the residue material for initial analysis, with the split samples remaining with the individual residual piles until required for re-split analysis or eventual disposal. • In the case of grade control drilling, 1m intervals were split at the rig via a 3-tier splitter box below the cyclone and collected in calico bags with bulk samples collected into large plastic bags. These 1m splits were dried, pulverised and split to produce a 50g charge for fre assay at an ofsite laboratory. • Where composite intervals returned results >0.15g/t Au, the original bulk samples were split by 3-tier rife splitter to approximately 3-4kg. The whole sample was dried, pulverised and split to produce a 50g charge for fre assay at an ofsite laboratory. • Historic diamond drilling sampled according to mineralisation and lithology resulting in samples of 10cm to 1.5m. Half core pulverised and split to produce a 50g charge for fre assay at an ofsite laboratory. |
|
| Drilling techniques | • Drill type (e.g. core, reverse circulation, open-hole hammer, rotary air blast, auger, Bangka, sonic, etc.) and details (e.g. core diameter, triple or standard tube, depth of diamond tails, face-sampling bit or other type, whether core is oriented and if so, by what method, etc.). |
• All reverse circulation at nominal 5.5” diameter, utilising face sampling hammers to reduce the risk of sample contamination. • Diamond drilling utilised 10-40m RC pre-collars to penetrate transported cover then continued as NQ core. Core was oriented bydown-hole spear. |
| Drill sample recovery | • Method of recording and assessing core and chip sample recoveries and results assessed. • Measures taken to maximise sample recovery and ensure representative nature of the samples. • Whether a relationship exists between sample recovery and grade and whether sample bias may have occurred due topreferential loss/gain of fne/coarse material. |
• Reverse circulation recorded sample quality, recovery and moisture for 1m samples. The majority of samples were of good quality with ground water having minimal efect on sample quality or recovery. Statistical analysis of sample quality for samples over an Au bottom cut of 0.1ppm indicates negligible sample bias. • Diamond drilling recorded rock hardness, recovery and RQD. Core recovery was good. |
| Logging | • Whether core and chip samples have been geologically and geotechnically logged to a level of detail to support appropriate Mineral Resource estimation, mining studies and metallurgical studies. • Whether logging is qualitative or quantitative in nature. Core (or costean, channel, etc.) photography. • The total length andpercentage of the relevant intersections logged. |
• Reverse circulation chips were washed and stored in chip trays in 1m intervals. Chips were visually inspected, recording lithology, weathering, alteration, mineralisation, veining and structure. • Diamond core was visually inspected, recording data related to lithology, weathering, alteration, mineralisation, veining and structure. Photographs of each core tray were taken wet. • All mineralised intersections from both diamond core and reverse circulation were logged. |
APPENDIX 6 – JORC TABLE 1 23
==> picture [772 x 17] intentionally omitted <==
----- Start of picture text -----
Criteria JORC Code explanation Commentary
----- End of picture text -----
| Criteria | JORC Code explanation | Commentary |
|---|---|---|
| Sub-sampling techniques and sample preparation |
• If core, whether cut or sawn and whether quarter, half or all core taken. • If non-core, whether rifed, tube sampled, rotary split, etc. and whether sampled wet or dry. • For all sample types, the nature, quality and appropriateness of the sample preparation technique. • Quality control procedures adopted for all sub-sampling stages to maximise representivity of samples. • Measures taken to ensure that the sampling is representative of the in situ material collected, including for instance results for feld duplicate/second-half sampling. • Whether sample sizes are appropriate to thegrain size of the material being sampled. |
• Diamond core samples to be analysed were taken as half core. Sample mark-up was controlled by geological domaining represented by alteration, mineralisation and lithology. • Reverse circulation samples were split from dry, 1m bulk sample via a 3-tier rife splitter. Field duplicates were inserted at a ratio of 1:20, analysis of primary vs duplicate samples indicate sampling is representative of the insitu material. • Standard material was documented as being inserted at a ratio of 1:100 for both RC and diamond drilling. • Detailed discussion of sampling techniques and Quality Control are documented in publicly available exploration technical reports compiled by prior owners (Homestake, Perilya, Gleneagle, RNI). |
| Quality of assay data and laboratory tests |
• The nature, quality and appropriateness of the assaying and laboratory procedures used and whether the technique is considered partial or total. • For geophysical tools, spectrometers, handheld XRF instruments, etc., the parameters used in determining the analysis including instrument make and model, reading times, calibrations factors applied and their derivation, etc. • Nature of quality control procedures adopted (e.g. standards, blanks, duplicates, external laboratory checks) and whether acceptable levels of accuracy (ie lack of bias) and precision have been established. |
• Historic assaying of RC and core was done by 50g charge fre assay with Atomic Absorption Spectrometry fnish at Analabs. The method is standard for gold analysis and is considered appropriate in this case. No Laboratory Certifcates are available for historic assay results pre 2008 however, evaluation of the database identifed the following; Standards are inserted at a ratio of 1:100, Assay repeats inserted at a ratio of 1 in 20. • QA/QC analysis of this historic data indicates the levels of accuracy and precision are acceptable. • Assay of recent (post 2012) sampling was done by 40g charge fre assay with Inductively Coupled Plasma – Optical Emission Spectroscopy fnish at Bureau Veritas (Ultratrace), Perth. The method is standard for gold analysis and is considered appropriate in this case. Laboratory Certifcates are available for the assay results and the following QA/QC protocols used include; Laboratory Checks inserted 1 in 20 samples, CRM inserted 1 in 30 samples and Assay Repeats randomly selected 1 in 15 samples. • QA/QC analysis of this data indicates the levels of accuracy and precision are acceptable with no signifcant bias observed. • Detailed discussion of analytical QA/QC is documented in the individual resource reports. |
| Verifcation of sampling and assaying |
• The verifcation of signifcant intersections by either independent or alternative company personnel. • The use of twinned holes. • Documentation of primary data, data entry procedures, data verifcation, data storage (physical and electronic) protocols. • Discuss any adjustment to assay data. |
• No twinned holes drilled historically. • All sampling, geological logging, borehole location, laboratory analysis results and QA/QC data is retained in DataShed, a relational database which has thorough built-in triggers for validation of imported data. An experienced Database Administrator oversees quality control of input data. • Borehole, geological and sampling data is captured in specifcally designed spreadsheets with built in validation for data entry felds, using established procedures. • No adjustment toprimaryassaydata is made. |
APPENDIX 6 – JORC TABLE 1 24
==> picture [772 x 17] intentionally omitted <==
----- Start of picture text -----
Criteria JORC Code explanation Commentary
----- End of picture text -----
| Criteria | JORC Code explanation | Commentary |
|---|---|---|
| Location of data points | • Accuracy and quality of surveys used to locate drill holes (collar and down-hole surveys), trenches, mine workings and other locations used in Mineral Resource estimation. • Specifcation of the grid system used. • Quality and adequacy of topographic control. |
• The grid system used for historic Fortnum drilling is the established Fortnum Mine Grid. Control station locations and traverses have been verifed by eternal survey consultants (Ensurv). Collar locations of boreholes have been established by either total station or diferential GPS (DGPS). The Yarlarweelor, Callie’s and Eldorado open pits (currently abandoned) was picked up by DGPS at the conclusion of mining. The transformation between Mine Grid and MGA94 Zone 50 is documented and well established. • A LIDAR survey over the project area was undertaken in 2012 and results are in agreement with survey pickups of pits, low-grade stockpiles and waste dumps. • Historic drilling by Homestake was routinely surveyed at 25m, 50m and every 50m thereafter, using a single shot CAMTEQ survey tool. RC holes have a nominal setup azimuth applied. Perilya YLRC series holes had survey shots taken by gyro every 10m. Historic drilling in the area did not appear to have any signifcant problems with hole deviation. • Drilling by RNI / MLX was picked up by DGPS on MGA94. Downhole surveys were taken by digital single shot camera every50m or via agyro surveytool. |
| Data spacing and distribution |
• Data spacing for reporting of Exploration Results. • Whether the data spacing and distribution is sufcient to establish the degree of geological and grade continuity appropriate for the Mineral Resource and Ore Reserve estimation procedure(s) and classifcations applied. • Whether sample compositing has been applied. |
• Drillhole spacing is a nominal 40m x 40m that has been in-flled to a nominal 20m x 20m in the main zone of mineralisation at Yarlarweelor, Callie’s and Eldorado with 10m x10m RC grade control within the limits of the open pits. • The spacing is considered sufcient to establish geological and grade continuity for appropriate Mineral Resource classifcation. • During the historic exploration phase, samples were composited to 4m by spearing 1m bulk samples. Where the assays returned results greater than 0.15ppm Au, the original 1m bulk samples were split usinga 3-tier rife splitter and analysed as described above. |
| Orientation of data in relation to geological structure |
• Whether the orientation of sampling achieves unbiased sampling of possible structures and the extent to which this is known, considering the deposit type. • If the relationship between the drilling orientation and the orientation of key mineralised structures is considered to have introduced a sampling bias, this should be assessed and reported if material. |
• Multiple phases of drilling at diferent orientations: Homestake RC and diamond drilling oriented south east. Perilya RC drilling oriented east and vertical. • MLX drilling intersections are nominally designed to be normal to the orebody as far as underground infrastructure constraints / topography allows. • A report analysing the potential of bias between sampling types and drilling orientations was undertaken and determined no bias exists. |
| Sample security | • The measures taken to ensure sample security. |
• Sample bags tagged and logged, sealed in bulka bags. • Dispatch by third party contractor, recording consignment note for tracking. • In-companyreconciliation with laboratorysample reconciliation and assayreturns. |
| Audits or reviews | • The results of any audits or reviews of sampling techniques and data. |
• Database compilation into DataShed for data integrity. • Program review by external consultants. • QA/QC report on historic sampling and analysis is included in the individual resource reports, and verifed aspart of the QA/QC reviewprocess for 2016 Yarlarweelor Mineral Resource Estimate (MLX). |
APPENDIX 6 – JORC TABLE 1 25
Section 2 Reporting of Exploration Results
(Criteria listed in the preceding section also apply to this section.)
==> picture [772 x 17] intentionally omitted <==
----- Start of picture text -----
Criteria JORC Code explanation Commentary
----- End of picture text -----
| Criteria | JORC Code explanation | Commentary |
|---|---|---|
| Mineral tenement and land tenure status |
• Type, reference name/number, location and ownership including agreements or material issues with third parties such as joint ventures, partnerships, overriding royalties, native title interests, historical sites, wilderness or national park and environmental settings. • The security of the tenure held at the time of reporting along with any known impediments to obtaining a licence to operate in the area. |
• The Fortnum Gold Project tenure is 100% owned by Metals X through subsidiary company Aragon Resources Pty. Ltd. • Various Royalties apply to the package. The most pertinent being; o$10/oz after frst 50,000oz (capped at $2M)- Perilya oState Government – 2.5% NSR • The tenure is currentlyingood standing. |
| Exploration done by other parties |
• Acknowledgment and appraisal of exploration by other parties. |
• Drilled by RAB, AC, RC and diamond coring, assayed gold only. • Various parties not limited to RNI NL, Eagle Gold Ltd., Gleneagle Gold Ltd, Perilya Mines Ltd., Homestake Gold Mines Australia Ltd and Dominion MiningLtd. |
| Geology | • Deposit type, geological setting and style of mineralisation. |
• The Fortnum deposits are Paleoproterozoic shear-hosted gold deposits within the Fortnum Wedge, a localised thrust duplex of Narracoota Formation within the overlying Ravelstone Formation. Both stratigraphic formations comprise part of the Bryah Basin in the Capricorn Orogen, Western Australia. • The Horseshoe Cassidy deposits are hosted within the Ravelstone Formation (siltstone and argillite) and Narracoota Formation (highly-altered, moderate to strongly deformed mafc to ultramafc rocks). The main zone of mineralisation is developed within a horizon of highly altered magnesian basalt. Gold mineralisation is associated with strong vein stock works that are confned to the altered mafc. Alteration consists of two types; stockwork proximal silica- carbonate-fuchsite-haematite-pyrite and distal silica-haematite-carbonate+/- chlorite. • The Peak Hill district represents remnants of a Proterozoic fold belt comprising highly deformed trough and shelf sediments and mafc /ultramafc volcanics, which are generally moderately metamorphosed (except for the Peak Hill Metamorphic Suite). |
| Drill hole Information |
• A summary of all information material to the understanding of the exploration results including a tabulation of the following information for all Material drill holes: oeasting and northing of the drill hole collaroelevation or RL (Reduced Level – elevation above sea level in metres) of the drill hole collarodip and azimuth of the holeodown hole length and interception depthohole length.• If the exclusion of this information is justifed on the basis that the information is not Material and this exclusion does not detract from the understanding of the report, the Competent Person should clearly explain why this is the case. |
• No drillhole date being presented. |
APPENDIX 6 – JORC TABLE 1 26
==> picture [772 x 17] intentionally omitted <==
----- Start of picture text -----
Criteria JORC Code explanation Commentary
----- End of picture text -----
| Criteria | JORC Code explanation | Commentary |
|---|---|---|
| Data aggregation methods |
• In reporting Exploration Results, weighting averaging techniques, maximum and/or minimum grade truncations (e.g. cutting of high grades) and cut-of grades are usually Material and should be stated. • Where aggregate intercepts incorporate short lengths of high grade results and longer lengths of low grade results, the procedure used for such aggregation should be stated and some typical examples of such aggregations should be shown in detail. • The assumptions used for any reporting of metal equivalent values should be clearly stated. |
• No drillhole date being presented. |
| Relationship between mineralisation widths and intercept lengths |
• These relationships are particularly important in the reporting of Exploration Results. • If the geometry of the mineralisation with respect to the drill hole angle is known, its nature should be reported. • If it is not known and only the down hole lengths are reported, there should be a clear statement to this efect (e.g. ‘down hole length, true width not known’). |
• No drillhole date being presented. |
| Diagrams | • Appropriate maps and sections (with scales) and tabulations of intercepts should be included for any signifcant discovery being reported These should include, but not be limited to aplan view of drill hole collar locations and appropriate sectional views. |
• No drillhole date being presented. |
| Balanced reporting | • Where comprehensive reporting of all Exploration Results is not practicable, representative reporting of both low and high grades and/or widths should be practiced to avoid misleading reporting of Exploration Results. |
• No drillhole date being presented. |
| Other substantive exploration data |
• Other exploration data, if meaningful and material, should be reported including (but not limited to): geological observations; geophysical survey results; geochemical survey results; bulk samples – size and method of treatment; metallurgical test results; bulk density, groundwater, geotechnical and rock characteristics; potential deleterious or contaminating substances. |
• No drillhole date being presented. |
| Further work | • The nature and scale of planned further work (e.g. tests for lateral extensions or depth extensions or large-scale step-out drilling). • Diagrams clearly highlighting the areas of possible extensions, including the main geological interpretations and future drilling areas, provided this information is not commercially sensitive. |
• Ongoing surface exploration activities will be undertaken to support continuing feasibility works at the Fortnum Gold Project. |
APPENDIX 6 – JORC TABLE 1 27
Section 3 Estimation and Reporting of Mineral Resources
(Criteria listed in section 1, and where relevant in section 2, also apply to this section.)
==> picture [772 x 17] intentionally omitted <==
----- Start of picture text -----
Criteria JORC Code explanation Commentary
----- End of picture text -----
| Criteria | JORC Code explanation | Commentary |
|---|---|---|
| Database integrity | • Measures taken to ensure that data has not been corrupted by, for example, transcription or keying errors, between its initial collection and its use for Mineral Resource estimation purposes. • Data validation procedures used. |
• Geological logging, drillhole location, laboratory analysis results and QA/QC data is retained in a relational database. MLX uses DataShed as the relational database which has thorough built-in triggers for validation of imported data. An experienced Database Administrator oversees quality control of data. • Drillhole, geological and sampling data is captured in specifcally designed spreadsheets with built in validation for data entry felds, using established procedures. • Industry standard validation checks were conducted and included, but were not limited to: oNo overlapping intervals. oDownhole surveys at 0m depth and also at the end of hole. oConsistency of depths between diferent data tables. oCheck gaps in the data. oSample number matching between feld sample records and laboratory results. • Additional validation checks included comparison against historic databases (2014, 2011 and 2009) and the database stored on the DMP WAMEX database system (A035439). Approximately, 10% of the original collar, survey and assay (i.e. at least three intervalsper hole) information was validated against the original or scans of the original hard copies. |
| Site visits | • Comment on any site visits undertaken by the Competent Person and the outcome of those visits. • If no site visits have been undertaken indicate why this is the case. |
• Mr. Russell visits Metals X Gold Operations regularly. |
| Geological interpretation |
• Confdence in (or conversely, the uncertainty of) the geological interpretation of the mineral deposit. • Nature of the data used and of any assumptions made. • The efect, if any, of alternative interpretations on Mineral Resource estimation. • The use of geology in guiding and controlling Mineral Resource estimation. • The factors afecting continuity both of grade and geology. |
• Low-grade stockpiles are derived from previous mining of the mineralisation styles outlined above. • Geological matrixes were established to assist with interpretation and construction of the estimation domains. • Confdence in the interpretation is high as the geometry, geology, alteration and tenor of the mineralised zones was observed to be consistent along strike and down dip • The interpretations was based on 10m and 20m north-south spaced sections. • The information used in the construction and estimation of the respective resources mineralisation is based on Air Core (AC), Reverse Circulation (RC) and Diamond Drill (DDH) hole information. The AC was included in the poorly information estimation domains and this was considered during the classifcation of these domains. • Oxidation surfaces were constructed from the logged information on 20m north south sections. |
| • The extent and variability of the Mineral Resource expressed as length (along strike or otherwise), plan width, and depth below surface to the upper and lower limits of the Mineral Resource. |
• The Yarlarweelor mineral resource extends over 1,400m in strike length, 570m in lateral extent and 190m in depth. • The Tom’s and Sam’s mineral resource extends over 650m in strike length, 400m in lateral extent and 130m in depth. • The Eldorado mineral resource extends over 240m in strike length, 100m in lateral extent and 100m in depth. • Low-grade stockpiles are of various dimensions. |
APPENDIX 6 – JORC TABLE 1 28
==> picture [772 x 17] intentionally omitted <==
----- Start of picture text -----
Criteria JORC Code explanation Commentary
----- End of picture text -----
| Criteria | JORC Code explanation | Commentary |
|---|---|---|
| Estimation and modelling techniques |
• The nature and appropriateness of the estimation technique(s) applied and key assumptions, including treatment of extreme grade values, domaining, interpolation parameters and maximum distance of extrapolation from data points. If a computer assisted estimation method was chosen include a description of computer software and parameters used. • The availability of check estimates, previous estimates and/ or mine production records and whether the Mineral Resource estimate takes appropriate account of such data. • The assumptions made regarding recovery of by-products. • Estimation of deleterious elements or other non-grade variables of economic signifcance (e.g. sulphur for acid mine drainage characterisation). • In the case of block model interpolation, the block size in relation to the average sample spacing and the search employed. • Any assumptions behind modelling of selective mining units. • Any assumptions about correlation between variables. • Description of how the geological interpretation was used to control the resource estimates. • Discussion of basis for using or not using grade cutting or capping. • The process of validation, the checking process used, the comparison of model data to drill hole data, and use of reconciliation data if available. |
• All modelling and estimation work undertaken by Metals X is carried out in three dimensions with Surpac Vision, Snowden’s Supervisor v8.3 and or Isatis 2015. • Ordinary kriging (OK) and Localised Indicator Kriging (LIK) has been used. LIK was used for the estimation of all Jasperoid related estimation domains due to mosaic mineralisation style. Length weighting of assay values related to surveyed volumes was undertaken for low-grade stockpiles. • All estimates were validated where possible against historical production records and previous estimates. • After validating the drillhole data to be used in the estimation, interpretation of the orebody is undertaken in sectional and / or plan view to create the outline strings which form the basis of the three dimensional orebody wireframe. Wireframing was carried out using a combination of automated stitching algorithms and manual triangulation to create an accurate three dimensional representation of the sub-surface mineralised body. Domaining was constructed on 20m and 10m spaced sections and was based on logged lithologies, quartz percentage and gold value. • Drillhole intersections within the mineralised body are defned; these intersections are then used to fag the appropriate sections of the drillhole database tables for compositing purposes. Assay data was composited to 1m downhole using Surpac “best ft” algorithm. The “best ft” algorithm eliminates residual composites and the estimation domains boundaries defned the start and end position of the compositing routine. In all aspects of resource estimation; the factual and interpreted geology was used to guide the development of the interpretation. • Support analysis of the diference drill types (Air Core (AC), Reverse Circulation (RC) and Diamond Drill holes (DDH)) was performed and the mixing these deemed acceptable. The AC drill holes were used in the estimation of the poorly informed estimation domains. • Statistical analysis was carried out on the composited data to assist with determining estimation search parameters, top-cuts and spatial continuity. Data for some of the domains exhibit an increased degree of skewness and top-cuts were applied to reduce the skewness of distribution. The appropriateness of the top-cuts was assessed for each domain utilising log-probability plots, mean and variance plots, histograms and univariate statistics for the composite Au variable. • Variogram modelling was undertaken using Isatis™ software and defned the spatial continuity of gold within all domains and these parameters were used for the interpolation process. Indicator variograms were generated within the Jasperoid related estimation domains to the used in the LIK estimation process. • Volume models were generated in Surpac using topographic surfaces, oxidation surfaces and mineralised zone wireframes as constraints. • Quantitative Kriging Neighbourhood Analysis was used optimise the search parameters. • Search ellipses were aligned parallel to the maximum continuity defned during the variographic analysis. The search dimensions, generally, approximated the ranges of the interpreted variograms and ranged from 50 to 100m. The minimum and maximum number of samples range from 7 to 11 and 18 to 30, respectively. Second and third pass searches were implement to fll the un-estimated cells / blocks if they were not estimated during the frst search pass and these search parameters involved increasing in the search distances and reducing in the minimum number of samples used in the estimation process. • The extrapolation was control through the interpreted estimation domains, which was limited to half the drill hole spacing within section and half the section spacingbetween sections. |
APPENDIX 6 – JORC TABLE 1 29
==> picture [772 x 17] intentionally omitted <==
----- Start of picture text -----
Criteria JORC Code explanation Commentary
----- End of picture text -----
| Criteria | JORC Code explanation | Commentary |
|---|---|---|
| • Block estimation for gold was undertaken using Isatis™ and hard boundaries were used between domains for estimation of gold grade. • No assumptions were made about recovery during the OK and LIK estimation processes. • Grade estimation was undertaken, with the ordinary kriging (OK) estimation method for all non-jasperoid related estimation domains. • Check estimates were run using Localised Uniform Conditioning (LUC) for the LIK estimation domains, which produces a similar form of result to LIK. The LIK and LUC models were compared, with reasonable agreement at lower cut-ofs and diferences at higher cut-ofs refecting higher estimated gold variability in the LIK model. The LIK is believed to be better suited to the style of mineralisation for the Jasperoid related estimation domains. • The estimation is validated using the following: a visual interrogation, a comparison of the mean composite grade to the mean block grade for each domain, a comparison of the wireframe volume to the block volume for each domain, grade trend plots (moving window statistics), comparison to the previous resource estimate. • The only element of economic interest modelled is gold. The Isatis™ block models were transferred and imported to Surpac Mining Software. The transfer and importing process was validated against the Isatis™ block model. The resource was then depleted for mining voids and subsequently classifed in line with JORCguidelines utilisinga combination of various estimation derivedparameters andgeological / miningknowledge. |
||
| Moisture | • Whether the tonnages are estimated on a dry basis or with natural moisture, and the method of determination of the moisture content. |
• Tonnages are estimated as dry metric. |
| Cut-of parameters | • The basis of the adopted cut-of grade(s) or quality parameters applied. |
• Interpretation cut-of varies based upon boundary analysis. • Various top-cut values have been applied to the data dependent on domains used in the OK estimation process. No top-cutting was applied to the Jasperoid related estimation domains because of the LIK estimation methodology was implemented. • The reported ≥0.7 g/t Au cutof grade is based on surface mining techniques and was determined through interval engineering investigations. • Low-grade stocks are reportedglobally. |
| Mining factors or assumptions |
• Assumptions made regarding possible mining methods, minimum mining dimensions and internal (or, if applicable, external) mining dilution. It is always necessary as part of the process of determining reasonable prospects for eventual economic extraction to consider potential mining methods, but the assumptions made regarding mining methods and parameters when estimating Mineral Resources may not always be rigorous. Where this is the case, this should be reported with an explanation of the basis of the mining assumptions made. |
• Conventional open cut mining with 120t class hydraulic backhoe excavators and 90t rigid dump trucks. • 2m minimum mining width has been assumed. • No mining dilution or ore loss has been modelled in the resource model or applied to the reported Mineral Resource. |
| Metallurgical factors or assumptions |
• The basis for assumptions or predictions regarding metallurgical amenability. It is always necessary as part of the process of determining reasonable prospects for eventual economic extraction to consider potential metallurgical methods, but the assumptions regarding metallurgical treatment processes and parameters made when reporting Mineral Resources may not always be rigorous. Where this is the case, this should be reported with an explanation of the basis of the metallurgical assumptions made. |
• Horizons were modelled based on oxidation state of the host rocks, taken from the drilling information. These were: transported and lateritic residuum, oxidised, transitional and fresh. • Jasperoid was fagged in the model due to its hardness and difering heap leach characteristics as identifed in recent metallurgical scoping studies. |
APPENDIX 6 – JORC TABLE 1 30
==> picture [772 x 17] intentionally omitted <==
----- Start of picture text -----
Criteria JORC Code explanation Commentary
----- End of picture text -----
| Criteria | JORC Code explanation | Commentary |
|---|---|---|
| Environmental factors or assumptions |
• Assumptions made regarding possible waste and process residue disposal options. It is always necessary as part of the process of determining reasonable prospects for eventual economic extraction to consider the potential environmental impacts of the mining and processing operation. While at this stage the determination of potential environmental impacts, particularly for a greenfelds project, may not always be well advanced, the status of early consideration of these potential environmental impacts should be reported. Where these aspects have not been considered this should be reported with an explanation of the environmental assumptions made. |
• Metals X operates in accordance with all environmental conditions set down as conditions for grant of the respective mining leases. |
| Bulk density | • Whether assumed or determined. If assumed, the basis for the assumptions. If determined, the method used, whether wet or dry, the frequency of the measurements, the nature, size and representativeness of the samples. • The bulk density for bulk material must have been measured by methods that adequately account for void spaces (vugs, porosity, etc.), moisture and diferences between rock and alteration zones within the deposit. • Discuss assumptions for bulk density estimates used in the evaluationprocess of the diferent materials. |
• A large suite of bulk density determinations have been carried out across the project area. The bulk densities were separated into diferent weathering domains and lithological domains (i.e. jasperoid domains). Density determinations were made on diamond drill core representing mineralisation utilised the water immersion method (Archimedes Principle). |
| Classifcation | • The basis for the classifcation of the Mineral Resources into varying confdence categories. • Whether appropriate account has been taken of all relevant factors (i.e. relative confdence in tonnage/grade estimations, reliability of input data, confdence in continuity of geology and metal values, quality, quantity and distribution of the data). • Whether the result appropriately refects the Competent Person’s view of the deposit. |
• The continuity of geology and mineralisation is well understood, with most of the reported resource being covered by either 20 x2 0m resource drilling or 10 x1 0m grade control drilling. • Where employed, the non-linear, local estimation method used is considered appropriate for the style of mineralisation and assumed mining selectivity. • A combination of gold estimation quality parameters and drill spacing were ultimately used to defne resource confdence categories. • The Competent Person believes that the classifcation fairly represents the confdence in the resource estimates, as they are described in the JORC (2012) code. |
| Audits or reviews | • The results of any audits or reviews of Mineral Resource estimates. |
• Resource estimates are peer reviewed by the site technical team as well as Metals X’s Corporate technical team. |
APPENDIX 6 – JORC TABLE 1 31
==> picture [772 x 17] intentionally omitted <==
----- Start of picture text -----
Criteria JORC Code explanation Commentary
----- End of picture text -----
| Criteria | JORC Code explanation | Commentary |
|---|---|---|
| Discussion of relative accuracy/ confdence |
• Where appropriate a statement of the relative accuracy and confdence level in the Mineral Resource estimate using an approach or procedure deemed appropriate by the Competent Person. For example, the application of statistical or geostatistical procedures to quantify the relative accuracy of the resource within stated confdence limits, or, if such an approach is not deemed appropriate, a qualitative discussion of the factors that could afect the relative accuracy and confdence of the estimate. • The statement should specify whether it relates to global or local estimates, and, if local, state the relevant tonnages, which should be relevant to technical and economic evaluation. Documentation should include assumptions made and the procedures used. • These statements of relative accuracy and confdence of the estimate should be compared with production data, where available. |
• Mineral Resources have been reported in accordance with the guidelines of the 2012 edition of the Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves and refects the relative accuracy of the Mineral Resource estimates. • The current Mineral Resource model represents a robust estimate of the in-situ gold mineralisation for Fortnum resource reported. The method used is designed to provide an estimate of local mineable resources, based on current mining methods. |
APPENDIX 6 – JORC TABLE 1 32
Section 4 Estimation and Reporting of Ore Reserves
(Criteria listed in section 1, and where relevant in sections 2 and 3, also apply to this section.)
==> picture [772 x 17] intentionally omitted <==
----- Start of picture text -----
Criteria JORC Code explanation Commentary
----- End of picture text -----
| Criteria | JORC Code explanation | Commentary |
|---|---|---|
| Mineral Resource estimate for conversion to Ore Reserves |
• Description of the Mineral Resource estimate used as a basis for the conversion to an Ore Reserve. • Clear statement as to whether the Mineral Resources are reported additional to, or inclusive of, the Ore Reserves. |
• The total Reserve Statement of 338.5k Oz is a combination of the individual ‘Resource’ models with the appropriate mining, geotechnical, processing and hydrological modifying factors applied. • The total Resource for Measured and Indicated categories covered by the Reserve statement is 21,786k tonnes @ 1.8 g/t for 1,239k contained Ounces (based on cut-ofs specifc to the individual orebodies). Mineral Resources are inclusive of Ore Reserves. • All resources that have been converted to Reserve are classifed as either Indicated or Measured. Indicated Resources are only upgraded to Probable Reserves after adding appropriate modifying factors. Some Measured Resource may be classifed as Proven Reserves and some are classifed as Probable Reserve based on whether it is developed and /or has drill hole density/ historicalproduction. |
| Site visits | • Comment on any site visits undertaken by the Competent Person and the outcome of those visits. • If no site visits have been undertaken indicate why this is the case. |
• Mr Anthony Buckingham has been an employee of Metals X (and its subsidiaries) for the past 7 years and has over 15 years’ experience specifcally in the Western Australian mining industry. Mr Buckingham visits the Fortnum mine site on a regular fortnightly basis and is the primary engineer involved in mine planning, site infrastructure and project management. |
| Study status | • The type and level of study undertaken to enable Mineral Resources to be converted to Ore Reserves. • The Code requires that a study to at least Pre-Feasibility Study level has been undertaken to convert Mineral Resources to Ore Reserves. Such studies will have been carried out and will have determined a mine plan that is technically achievable and economically viable, and that material Modifying Factors have been considered. |
• The Fortnum Gold Mine Operation ceased production in May 2007 when owned by Gleneagle Gold. Previous to this the operation was operated by Perilya and Homestake, and frst began commercial mining operations in the late 1980’s. Extensive mining and processing records are therefore available in each of the deposits. • Various open pit styles and host domains have been mined since discovery of the area by Homestake in 1980’s. Mining during this time has ranged from open pit cut backs, virgin surface excavations to extensional underground developments. • The Fortnum Gold Mine Open Pit and Underground inventory had a Pre-feasibility study completed by MLX in early 2016. Additional cost details, operational constraints and a revision of the Resources (with classifcation) have continued since this initial fnancial evaluation. A Feasibility Study was completed on these revisions and therefore forms the basis for this Reserve Statement. The Fortnum Gold Mine is now at a budgetary level analysis with specifc details on processing components and reagent costs, specifc mining contractor cost profles, contractual haulage costs, power provider unit rates as well as site specifc G&A. |
APPENDIX 6 – JORC TABLE 1 33
==> picture [772 x 26] intentionally omitted <==
----- Start of picture text -----
Criteria JORC Code explanation Commentary
Cut-off parameters • The basis of the cut-off grade(s) or quality parameters applied. • The pit rim cut off grade (COG) was determined as part of the Open Pit Reserve estimation. The
----- End of picture text -----
| Criteria | JORC Code explanation | Commentary |
|---|---|---|
| Cut-of parameters | • The basis of the cut-of grade(s) or quality parameters applied. |
• The pit rim cut of grade (COG) was determined as part of the Open Pit Reserve estimation. The |
| pit rim COG determines which material will be processed by equating the operating cost of grade control, processing, surface haulage, G&A and selling cost to the value of the mining block in terms of recovered metal and the expected selling price. The COG is then used to determine whether or not a mining block should be delivered to the treatment plant for processing or taken to the waste dump as waste. • A range of COG’s were applied to the Open Pit Resources depending upon their location / distance to the ROM, oxide state, mill recoveries and density requirements for grade control drilling. Therefore COG’s varied between 0.9 g/t up to 1.2g/t. • Low grade piles local to the Plant had a 0.6g/t determinant and the regional low grade stocks of Horseshoe / Harmony were cut at 0.8 – 1.0g/t. Low Grade stockpiles incurred a low cost profle than open pits for processing, because of the predominantly oxide material, as well as G&A, as the operation would have limited fxed management when milling this inventory. • The Underground COG was determined by the applying Resource specifc mining method costs, operating development requirements, geology and fxed costs components, surface haulage (if applicable), royalties as well as processing requirements with mill recoveries incorporated. For the case of underground tunnel development, and in the situation where the drive is required to be excavated for production, a Low Grade COG is applied. This LG COG is calculated on only Processing and G&A costs. A subsequent, capital inputted, fnancial evaluation of each mine is completed to ensure the asset produces a positive NPV. The Starlight Underground had an applied 2.8 g/t COG to determine the HG category. |
APPENDIX 6 – JORC TABLE 1 34
==> picture [772 x 17] intentionally omitted <==
----- Start of picture text -----
Criteria JORC Code explanation Commentary
----- End of picture text -----
| Criteria | JORC Code explanation | Commentary |
|---|---|---|
| Mining factors or assumptions |
• The method and assumptions used as reported in the Pre-Feasibility or Feasibility Study to convert the Mineral Resource to an Ore Reserve (i.e. either by application of appropriate factors by optimisation or by preliminary or detailed design). • The choice, nature and appropriateness of the selected mining method(s) and other mining parameters including associated design issues such as pre-strip, access, etc. • The assumptions made regarding geotechnical parameters (e.g. pit slopes, stope sizes, etc.), grade control and pre-production drilling. • The major assumptions made and Mineral Resource model used for pit and stope optimisation (if appropriate). • The mining dilution factors used. • The mining recovery factors used. • Any minimum mining widths used. • The manner in which Inferred Mineral Resources are utilised in mining studies and the sensitivity of the outcome to their inclusion. • The infrastructure requirements of the selected mining methods. |
Open Pit Methodology. Following consideration of the various modifying factors the following rules were applied to the reserve estimation process for the conversion of measured and indicated resource to reserve for suitable evaluation. • The mining shape in the reserve estimation is generated by a wireframe (geology interpretation of the ore zone) which overlays the block model. Where the wire frame cuts the primary block, sub blocks fll out the remaining space to the wire frame boundary (efectively the mining shape). It is reasonable to assume that the mining method can selectively mine to the wire frame boundary with the additional dilution provision stated in point 4 below. • Ore Reserves are based on Pit shape designs – with appropriate modifcations to the original Whittle Shell outlines to ensure compliance with practical mining parameters. • Geotechnical parameters allied to the Open Pit Reserves are either based on observed existing pit shape specifcs or domain specifc expectations / assumptions. Various geotechnical reports and retrospective reconciliations were considered in the 2016 design parameters. A majority of the open pits have a fnal design wall angle of 38-420, which is seen as conservative. • Dilution of the ore through the mining process has been accounted for within the Reserve quoted inventory. Various dilution ratios are used to represent the style of mineralization. Where continuous, consistent ore boundaries and grade represent the mineralised system the following factors are applied: oxide 15%, transitional 17% and fresh 19%. In circumstances where the orebody is less homogenous above the COG then the following dilution factors are applied in order to model correctly the inherent variability of extracting discrete sections of the pit foor: oxide 17%, transitional 19% and fresh 21%. To ensure clarity, the following percentages are additional ore mined in relation to excavating the wire frame boundary as identifed in point 1 above, albeit at a grade of 0.0 g/t. The amount of dilution is considered appropriate based on orebody geometry, historical mining performance and the size of mining equipment to be used to extract ore. • Expected open pit mining recovery of the ore has been set at 93%. • Minimum mining widths have been accounted for in the designs, with the utilization of 40T & 90T trucking parameters. • No specifc ground support requirements are needed outside of suitable pit slope design criteria based on specifc geotechnical domains. • Mining sequence is included in the mine scheduling process for determining the economic evaluation and takes into account available operating time and mining equipment size and performance. • No Inferred material is included within the open pit statement, though in various pit shapes inferred material ispresent. In these situations this inferred material is classifed as waste. |
APPENDIX 6 – JORC TABLE 1 35
==> picture [772 x 17] intentionally omitted <==
----- Start of picture text -----
Criteria JORC Code explanation Commentary
----- End of picture text -----
| Criteria | JORC Code explanation | Commentary |
|---|---|---|
| Underground Methodology. • All Underground Reserves are based on 3D design strings and polygon derived stope shapes following the Measured and Indicated Resource (in areas above the COG). A complete mine schedule is then derived from this design to create a LOM plan and fnancial analysis. • Mining methodology is based on previous mining experience. All mining systems within the Reserve statement are standardized, mechanized Western Australian methods. • In large disseminated orebodies a sub level open stoping or single level bench stoping production methodology is used. • In narrow vein laminated quartz hosted domains a conservative narrow bench style mining method is used. • In narrow fat dipping deposits a Flat Long Hole process is adopted (with fllets in the footwall for rill angle) and or Jumbo stoping. • Stope shape parameters have been based on historical data (where possible) or expected stable hydraulic radius dimensions. • Stope inventories have been determined by cutting the geological wireframe at above the area specifc COG and applying mining dilution and ore loss factors. The ore loss ratio accounts for pillar locations between the stopes (not operational ore loss) whilst dilution allows for conversion of the geological wireframe into a minable shape as well as hangingwall relaxation. A 20% dilution factor and 10% loss ratio has been subsequently applied to the Starlight Reserve statement. • Minimum mining widths have been applied in the various mining methods. The only production style relevant to this constraint is ‘narrow stoping’ – where the minimum width is set at 1.5m in an 18.5m sub level interval. • Mining operational recovery for the underground mines is set at 100% due to the use of remote loading units. • Stope shape dimensions vary between the various methods. Default hydraulic radii are applied to each method, and are derived either from historical production or geotechnical reports / recommendations. Where no data or exposure is available conservative HR values are used based on the contact domain type. • Mining sequence is included in the mine scheduling process for determining the economic evaluation and takes into account available operating time and mining equipment size and performance. |
APPENDIX 6 – JORC TABLE 1 36
==> picture [772 x 17] intentionally omitted <==
----- Start of picture text -----
Criteria JORC Code explanation Commentary
----- End of picture text -----
| Criteria | JORC Code explanation | Commentary |
|---|---|---|
| Metallurgical factors or assumptions |
• The metallurgical process proposed and the appropriateness of that process to the style of mineralisation. • Whether the metallurgical process is well-tested technology or novel in nature. • The nature, amount and representativeness of metallurgical test work undertaken, the nature of the metallurgical domaining applied and the corresponding metallurgical recovery factors applied. • Any assumptions or allowances made for deleterious elements. • The existence of any bulk sample or pilot scale test work and the degree to which such samples are considered representative of the orebody as a whole. • For minerals that are defned by a specifcation, has the ore reserve estimation been based on the appropriate mineralogy to meet the specifcations? |
• Fortnum Gold Mine has an existing conventional CIL processing plant – which has been operational in various periods since the late 1980’s. The plant has a nameplate capacity of 1.0Mtpa though this can be varied between 0.8-1.2Mtpa pending rosters and material type. • Grind size for the sulphide material has historically been 130 µm. • An extensive database of historical CIL recoveries as well as detailed metallurgical test work is available for the various deposits and these have been incorporated into the COG analysis and fnancial models. • For the 2016 Reserve, Plant recoveries of 93-95% have been utilised. |
| Environmental | • The status of studies of potential environmental impacts of the mining and processing operation. Details of waste rock characterisation and the consideration of potential sites, status of design options considered and, where applicable, the status of approvals for process residue storage and waste dumps should be reported. |
• The Fortnum Gold Mine has normal Western Australian permitting requirements. |
| Infrastructure | • The existence of appropriate infrastructure: availability of land for plant development, power, water, transportation (particularly for bulk commodities), labour, accommodation; or the ease with which the infrastructure can beprovided, or accessed. |
• Fortnum Gold Mine, despite being under Care and Maintenance since 2007, has an existing operational infrastructure base with a 108 man camp facility, various water bores, existing TSF, a processing plant, airstrip, communications and main road access ways. |
| Costs | • The derivation of, or assumptions made, regarding projected capital costs in the study. • The methodology used to estimate operating costs. • Allowances made for the content of deleterious elements. • The source of exchange rates used in the study. • Derivation of transportation charges. • The basis for forecasting or source of treatment and refning charges, penalties for failure to meet specifcation, etc. • The allowances made for royalties payable, both Government and private. |
• Open Pit Mining costs have been sourced from MLX CMGP operations whereby several contracting companies are undertaking mining works. These costs include pit load and haul as well as drill and blast, dewatering and maintenance. The costs are based on recent tender submissions (early 2016) for the CMGP which is located 200km south of the Fortnum Gold Mine. • Underground mining costs used within the Reserve process are derived from existing operational UG mines within the Kalgoorlie and Meekatharra district. They are based on current contractual schedule of rates for all mining processes covered in this Reserve statement. • Additional to direct mining costs, surface haulage is based on recent 2016 request for quotation. Where specifc tkm rates are not available, a default value of $0.10-0.15 /tkm has been used. • Processing costs are based on the 2016 Feasibility profle. These costs are in line with previous operating conditions and are aligned to the cost profle seen in MLX’s neighbouring operation of CMGP. • Royalties applicable to the open pit, underground and stockpile inventory vary pending tenement, though a summary of these are: o$10/oz after frst 50,000oz (capped at $2M)- Perilya o1% NRS - Montezuma oState Government – 2.5% NSR |
APPENDIX 6 – JORC TABLE 1 37
==> picture [772 x 17] intentionally omitted <==
----- Start of picture text -----
Criteria JORC Code explanation Commentary
----- End of picture text -----
| Criteria | JORC Code explanation | Commentary |
|---|---|---|
| Revenue factors | • The derivation of, or assumptions made regarding revenue factors including head grade, metal or commodity price(s) exchange rates, transportation and treatment charges, penalties, net smelter returns, etc. • The derivation of assumptions made of metal or commodity price(s), for the principal metals, minerals and co-products. |
• Assessed at A$1,550 / Oz. |
| Market assessment | • The demand, supply and stock situation for the particular commodity, consumption trends and factors likely to afect supply and demand into the future. • A customer and competitor analysis along with the identifcation of likely market windows for the product. • Price and volume forecasts and the basis for these forecasts. • For industrial minerals the customer specifcation, testing and acceptance requirements prior to a supply contract. |
• Assessed at A$1,550 / Oz |
| Economic | • The inputs to the economic analysis to produce the net present value (NPV) in the study, the source and confdence of these economic inputs including estimated infation, discount rate, etc. • NPV ranges and sensitivity to variations in the signifcant assumptions and inputs. |
• A straight undiscounted Cash Flow Model has been used to analyse the Fortnum Gold Mine. The 5 years term does not warrant extensive Discount / Infationary modelling. |
| Social | • The status of agreements with key stakeholders and matters leading to social licence to operate. |
• No negative social impacts noted. • Local stakeholders have been consulted regarding MLX plan for the Fortnum Gold Mine. • MLX continues to work with local governments, business owners and residence around the Fortnum Gold Mine. |
APPENDIX 6 – JORC TABLE 1 38
==> picture [772 x 17] intentionally omitted <==
----- Start of picture text -----
Criteria JORC Code explanation Commentary
----- End of picture text -----
| Criteria | JORC Code explanation | Commentary |
|---|---|---|
| Other | • To the extent relevant, the impact of the following on the project and/or on the estimation and classifcation of the Ore Reserves: • Any identifed material naturally occurring risks. • The status of material legal agreements and marketing arrangements. • The status of governmental agreements and approvals critical to the viability of the project, such as mineral tenement status, and government and statutory approvals. There must be reasonable grounds to expect that all necessary Government approvals will be received within the timeframes anticipated in the Pre-Feasibility or Feasibility study. Highlight and discuss the materiality of any unresolved matter that is dependent on a third party on which extraction of the reserve is contingent. |
• A Mining Proposal for the localised 2016 Open Pit Reserves has been approved – Yarlarweelor, Callies, Toms. • A Project Management Plan for the re-start of the operations (processing, dewatering and open pit mining) has been approved. • Native Title Agreements are established in all Reserve areas. • Further work required on approvals for the underground and regional pits, and MLX will work through these requirements in late 2016. |
| Classifcation | • The basis for the classifcation of the Ore Reserves into varying confdence categories. • Whether the result appropriately refects the Competent Person’s view of the deposit. • The proportion of Probable Ore Reserves that have been derived from Measured Mineral Resources (if any). |
• Only a small vertical fitch within Tom’s Resources has been classifed as Measured (with fnal grade control density drilling completed in 2007) with all other Resources having an Indicated designation. • All Open Pit and Underground Reserves therefore have been classifed as Probable. • The LG stocks have been classifed as Probable to account for material type variations as well as any possible survey and density discrepancies. |
| Audits or reviews | • The results of any audits or reviews of Ore Reserve estimates. |
• Various technical mining and fnancial analysis reports have been undertaken on the operations since May 2007 as part of re-start programs. • These external independent reports and cost models have been used as a reference for the 2016 Reserve calculation / mining modifcation factors in order to validate MLX assumptions and or parameters. • A detailed internal MLX review of the Feasibility was completed in early July 2016. • MLX continues to utilise external consultants (experts in their feld) for geotechnical, geological, hydrological and metallurgical input. |
APPENDIX 6 – JORC TABLE 1 39
==> picture [772 x 27] intentionally omitted <==
----- Start of picture text -----
Criteria JORC Code explanation Commentary
Discussion of • Where appropriate a statement of the relative accuracy and confidence level in the Ore • Various sensitivity analyses have been undertaken on the 2016 Reserve models in order to understand
----- End of picture text -----
| Criteria | JORC Code explanation | Commentary |
|---|---|---|
| Discussion of | • Where appropriate a statement of the relative accuracy and confdence level in the Ore |
• Various sensitivity analyses have been undertaken on the 2016 Reserve models in order to understand |
| relative accuracy/ confdence |
Reserve estimate using an approach or procedure deemed appropriate by the Competent Person. For example, the application of statistical or geostatistical procedures to quantify the relative accuracy of the reserve within stated confdence limits, or, if such an approach is not deemed appropriate, a qualitative discussion of the factors which could afect the relative accuracy and confdence of the estimate. • The statement should specify whether it relates to global or local estimates, and, if local, state the relevant tonnages, which should be relevant to technical and economic evaluation. Documentation should include assumptions made and the procedures used. • Accuracy and confdence discussions should extend to specifc discussions of any applied Modifying Factors that may have a material impact on Ore Reserve viability, or for which there are remaining areas of uncertainty at the current study stage. • It is recognised that this may not be possible or appropriate in all circumstances. These statements of relative accuracy and confdence of the estimate should be compared with production data, where available. |
and subsequently control risk. |
APPENDIX 6 – JORC TABLE 1 40