AI assistant
LEGEND MINING LIMITED — Investor Presentation 2018
Oct 21, 2018
65223_rns_2018-10-21_c61f443e-a20c-4484-8354-24f1d99b68ce.pdf
Investor Presentation
Open in viewerOpens in your device viewer
ASX:LEG
==> picture [893 x 425] intentionally omitted <==
Paydirt Nickel Conference
1
23October 2018
DISCLOSURE
==> picture [119 x 43] intentionally omitted <==
This is not a disclosure document. Any material used in this presentation is a summary of selected data, and any investor in Legend Mining Limited should refer to all Legend Mining Limited ASX releases and statutory reports before considering to invest in the company.
Any forward looking information in this presentation has been prepared on the basis of a number of assumptions that may prove not to be correct. Neither Legend Mining Limited, nor its officers, employees and advisors make or give any representation, warranty or guarantee in relation to this presentation.
Legend Mining Limited reserves the right to update, amend or supplement the Information in this presentation at any time in its absolute discretion without incurring any obligation to do so.
The information in this presentation that relates to exploration results is based on information compiled by Mr Derek Waterfield who is a member of the Australian Institute of Geoscientists and is a full time employee of Legend Mining Limited.
Mr Derek Waterfield has sufficient experience which is relevant to the style of mineralisation and type of deposit under consideration and to the activity which he is undertaking to qualify as a Competent Person as defined in the 2012 Edition of the “Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves” (the JORC Code).
Mr Derek Waterfield consents to the inclusion in this presentation of the matters that relate to exploration results in the form and context in which it appears.
2
CONTENTS
==> picture [119 x 43] intentionally omitted <==
==> picture [433 x 355] intentionally omitted <==
1.
2.
3.
Nickel Market Commentary
About Legend
-
Investment Case
-
Rockford Project Location
-
Rockford Project Activities
Summary
“Prospective Fraser Range”
3
NICKEL MARKET COMMENTARY – ABOUT NICKEL
==> picture [119 x 43] intentionally omitted <==
==> picture [339 x 191] intentionally omitted <==
==> picture [350 x 184] intentionally omitted <==
Nickel Prices and Inventory
-
Balance in deficit since 2016, predicted to continue
-
Stockpiles diminishing from peak 900Kt (2015)*
-
• Price increase from US$3.80/lb to US$5.70/lb
($7.13 max 19/4/18)
- Tariff and trade-war talk uncertainty
– negative sentiment stronger than expected
-
Price stubbornly low
- defies fundamentals
-
Promising electric vehicle battery demand outlook
Source: BOCI Global Commodities, Reuters – Asia Nickel Conference, Jakarta, September 2018
*Glencore Nov 2017
“Nickel deficit - stockpiles diminishing – price rising”
4
ABOUT LEGEND
==> picture [119 x 43] intentionally omitted <==
ASX listed exploration company
Market capitalisation ~$70M (2B shares @ 3.5cps) Cash and liquids ~$6.5M as at 30 September 2018 (includes $3M receivable from Jindal) Fraser Range – Rockford Project
==> picture [87 x 123] intentionally omitted <==
Chairman Michael Atkins
==> picture [87 x 123] intentionally omitted <==
Managing Director Mark Wilson
==> picture [87 x 123] intentionally omitted <==
Exec. Director - Technical Derek Waterfield
==> picture [83 x 124] intentionally omitted <==
Company Secretary Tony Walsh
5
INVESTMENT CASE
==> picture [119 x 43] intentionally omitted <==
Fundamentals
-
Right People
-
Experienced corporate and technical team
-
JV Partner and major shareholder - Creasy Group (regional experience)
-
-
Biggest block on best street (2,621km[2] in Fraser Zone)
-
Main Commodity – Nickel
-
(stockpiles diminishing – price rising)
-
Cashed up (several years exploration funds)
==> picture [341 x 230] intentionally omitted <==
- Positive aircore drilling results (December 17 – June 18)
Legend share price graph twelve months to Oct 2018
- Systematic exploration approach ongoing
“Exploration success – price appreciation”
6
PROJECT LOCATION
==> picture [119 x 43] intentionally omitted <==
==> picture [321 x 446] intentionally omitted <==
Rockford Project
-
Located in northern Fraser Range district
-
120km NE of Nova / 100km S of Tropicana
-
100% within Fraser Zone (18% of total area)
-
Project potential for
-
−Nova style Nickel-Copper −Tropicana style Gold
-
Infrastructure access – transport, power
“Project potential for Nova style Nickel-Copper”
7
FRASER ZONE LAND HOLDERS
==> picture [346 x 430] intentionally omitted <==
==> picture [266 x 303] intentionally omitted <==
- Regional spend producing results – value add
==> picture [119 x 43] intentionally omitted <==
MAIN PLAYERS Legend Active & Funded Creasy Group Active & Private Independence (“IGO”) Active & ~$2.5B Mkt Cap Galileo Mining New IPO – Creasy backed
Leverage play is Legend
8
ROCKFORD PROJECT UPDATE – SYSTEMATIC APPROACH
==> picture [119 x 43] intentionally omitted <==
==> picture [499 x 381] intentionally omitted <==
----- Start of picture text -----
Area D
----- End of picture text -----
Summary to Date
-
25 Areas selected from aeromag and gravity
-
21 conductors identified by innovative MLTEM
-
Drilling: 4 diamond holes for 2,652m 10 RC holes for 2,266m 485 aircore holes for 33,455m
-
Exploration spend Sept 15 to Sept 18 - $10M (Tax refund $2.4M)
-
Area D aircore drilling success Nov 17 to Jun 18
-
Still early days
Area covered by MLTEM surveys - 200km[2] /2621km[2] = 7.6% of Project area
9
AREA D – RIGHT LOCATION
==> picture [119 x 43] intentionally omitted <==
==> picture [419 x 396] intentionally omitted <==
-
Within the Fraser Zone
-
Defined by 430km long gravity “trend”
-
Mapped as mafic / ultramafic intrusives
-
Analogies to Thompson Belt in Canada which contains clusters of orebodies
-
Contains three gravity “Hot Spots”
-
Area D lies on NE margin of central HS
-
Nova lies on NE margin of southern HS
10
“Fraser Zone considered highly prospective”
AREA D – AIRCORE DRILLING
==> picture [119 x 43] intentionally omitted <==
-
Multiple aeromag targets within 16km x 5km feature
-
RC/DD Drilling – July 2016 Positive petrology
-
Nov 2017 – June 2018 153 holes for 13,315m
-
Ultimate aim to generate areas of focus for innovative EM surveys
-
Identified four zones of anomalous Ni-Cu-Co mineralisation within three separate intrusive bodies
==> picture [597 x 381] intentionally omitted <==
==> picture [523 x 31] intentionally omitted <==
----- Start of picture text -----
Area D – Drillholes on Aeromagnetics
----- End of picture text -----
==> picture [11 x 7] intentionally omitted <==
----- Start of picture text -----
11
----- End of picture text -----
AREA D – RIGHT GEOLOGY
==> picture [119 x 43] intentionally omitted <==
-
Thick blanket of nickel-copper-cobalt enrichment
-
All holes ended in mineralisation
-
All holes ended in gabbronorite (Nova Host Rock)
-
Sulphides in hole RKAC183
==> picture [92 x 78] intentionally omitted <==
----- Start of picture text -----
Cpy
Po
----- End of picture text -----
==> picture [33 x 13] intentionally omitted <==
----- Start of picture text -----
Pent
----- End of picture text -----
==> picture [513 x 332] intentionally omitted <==
12
AREA D – RIGHT LITHOLOGY
==> picture [119 x 43] intentionally omitted <==
-
RKDD002 - Ultramafic with cumulate texture containing disseminated pyrrhotite and minor pentlandite-chalcopyrite
-
Sulphidic metasediments/granulite (sulphur source)
-
Identified basal contact – metased/gabbro – right position for mineralisation
| Legend’s RKDD002 – Simplified Drill Log Summary | Legend’s RKDD002 – Simplified Drill Log Summary | Nova-Bollinger Schematic Section (SIR 2014) |
|---|---|---|
| Interval | Description | |
| 0 – 80.6m | Regolith | |
| 80.6 – 207.0m | Gabbro | |
| 207.0 – 603.5m | Mafic-Felsic Metasediments / Granulite | |
| 459.3-472.9m | Sulphidic interval | |
| 503.0-514.4m | Sulphidic interval | |
| 526.4-583.9m | Sulphidic interval | |
| 603.5 – 690.6m | Gabbro | |
| 626.3-626.8m | Sulphidic interval | |
| 661.0-661.35m | Sulphidic interval | |
| 690.6 – 717.7m | Mafic Metasediments / Granulite |
13
CURRENT/FUTURE PROGRAMMES
==> picture [119 x 43] intentionally omitted <==
2018
Ongoing regional aircore programme – total to date 485 holes – 33,455m
-
Continued systematic approach MLTEM, FLTEM, LF EM surveys
-
Follow up RC/DD testing
Aircore Rig, Rockford Project
EM Surveying , Rockford Project
==> picture [925 x 87] intentionally omitted <==
14
SUMMARY
==> picture [119 x 43] intentionally omitted <==
-
Highly Prospective Rockford Project − Three years on ground <10% area first pass EM tested
-
Systematic/persistent/committed = going the distance!
-
Well Funded
-
Experienced Stable Team and JV Partner
Creasy says to Wilson: “This is what it looks like – go find it!”
- Grow Shareholder Value
“Highly leveraged to success”
15
==> picture [119 x 43] intentionally omitted <==
==> picture [931 x 488] intentionally omitted <==
----- Start of picture text -----
SIR Nov 2011 (Nova discovery July 2012)
16
THANK YOU LEG May 2018
----- End of picture text -----