ASX ANNOUNCEMENT
18 October 2017
==> picture [217 x 36] intentionally omitted <==
Maiden Ore Reserve for Miraflores
Metminco Limited (ASX: MNC, AIM: MNC) (“Metminco” or the “Company”) is pleased to announce a maiden NI 43-101 and JORC 2012-compliant Ore Reserve for its 100%owned Miraflores Gold Project in Colombia.
The Ore Reserve has been estimated using a gold price assumption of US$1200/oz and a cut-off grade of 1,53g/t Au. It is contained entirely within the Miraflores Deposit constrained Mineral Resource Estimate and is based entirely on the Measured and Indicated Resources.
The estimate represents a conversion rate of approximately 50% of Measured and Indicated Resources and has been based on information derived from the Feasibility Study (FS) for Miraflores, which will be released to the ASX today.
Miraflores Mineral Reserve Estimate as at October 2017
| Reserve Classification | Tonnes (t) | Gold (g/t) |
Silver (g/t) | Contained Metal (Koz Au) |
Contained Metal (Koz Ag) |
|---|---|---|---|---|---|
| Proven | 835,606 | 4.84 | 2.73 | 130 | 73 |
| Probable | 2,142,741 | 4.16 | 3.21 | 287 | 221 |
| Proven + Probable | 2,978,346 | 4.35 | 3.08 | 417 | 295 |
| Planned dilution | 1,347,867 | 0.91 | 1.42 | 39 | 62 |
Source: Ausenco, 2017
The Company’s Ore Reserve estimates for the Miraflores Gold Project have been independently reviewed and signed off by Mr Boris Caro who is a Member of Australasian Institute of Mining and Metallurgy and a Registered Member of the Chilean Mining Commission.
The information communicated in this announcement includes inside information for the purposes of Article 7 of Regulation 596/2014
Mr William Howe, Managing Director, said: “The release of the maiden Ore Reserve for the Miraflores Gold Project marks a significant step towards our goal of near-term production in South America and the culmination of many months of dedicated work by our team. It also cements our confidence in the projects location on the prolific Western Cordillera Andean Cauca trend. We look forward to releasing the results of the Feasibility Study later today which will demonstrate that this is an economically robust project.”
William Howe Managing Director
| William Howe Managing Director |
|
|---|---|
| Metminco Limited ABN 43 119 759 349 | Suite 401, 6 Help Street, Chatswood, NSW, 2067 |
| ASX Code: MNC.AX; AIM Code: MNC.L | Tel: +61 (0) 2 9460 1856; Fax: +61 (0) 2 9460 1857 |
| www.metminco.com.au |
==> picture [217 x 36] intentionally omitted <==
Miraflores Gold Project
Mineral Resources
The Miraflores Measured and Indicated Mineral Resources are reported at a gold cut-off grade of 1.20 g/t Au. The resources are based on 25,884 meters of drilling in 73 diamond drill holes and 236 meters of underground channel samples. This includes 3,624m in 10 holes carried out by AngloGold Ashanti and B2Gold in 2006-2007.
Statistical and visual checks were performed by Metal Mining Consultants of the estimated block model to ensure there were no discrepancies in the grade estimation routines and to ensure the geometry of mineralization meets the configuration that the geologists expected for estimated mineralization. The Mineral Resources are reported inclusive of the Ore Reserves.
Measured Mineral Resources; 2.958Mt @ 2.98g/t Au and 2.48g/t Ag
Indicated Mineral Resources; 6.311Mt @ 2.74g/t Au and 2.90g/t Ag
Measured and Indicated Mineral Resources; 9.269Mt @ 2.82g/t Au and 2.77g/t Ag
Inferred Mineral Resources; 0.487Mt @ 2.36g/t Au and 3.64g/t Ag
Competent Person
Mr Boris Caro visited the site in August 2017 for 3 days as part of the study team to review all aspects of the study including an investigation of the mine, plant and site layouts.
Type of Study Completed
A feasibility study has been completed for the Miraflores Project. Metminco engaged GR Engineering Services to complete the processing, infrastructure and feasibility study management aspects of the feasibility study. Ausenco Chile were engaged to complete all aspects of the mine design, mine scheduling, geotechnical analysis and ventilation system design to support the mine design, including capital and operating costs for the mine. Surface geotechnical design for the plant, infrastructure and tailings facility was undertaken by Dynami Geo Consulting (a Medellin based consulting company) and Grana y Montero Engineering, a Lima, Peru based engineering and contracting group assisted in the design of the Tailings Storage Facility. This study provided sufficient technical and economic support to back up the Ore Reserve estimate.
| Metminco Limited ABN 43 119 759 349 | Suite 401, 6 Help Street, Chatswood, NSW, 2067 |
|---|---|
| ASX Code: MNC.AX; AIM Code: MNC.L | Tel: +61 (0) 2 9460 1856; Fax: +61 (0) 2 9460 1857 |
| www.metminco.com.au |
==> picture [217 x 36] intentionally omitted <==
Further analysis and test work is recommended for the stope filling sequence and stability analysis prior to any decision to commence with the project construction.
- Cut off grade determination
An underground cut-off grade (CoG) of 1.53 g/t- for gold was applied to underground diluted resources constrained by the final underground design. This grade delineated the Ore Reserve estimate. The cut-off grade was utilized for the stope optimization and the mining schedule.
-
Reserves are based on a gold price of US$1,200/oz;
-
Reserves are defined within an underground mine plan generated from diluted Measured and Indicated Mineral Resources;
-
An underground CoG of 1.53 g/t-Au was applied to underground resources constrained by a final underground design;
-
Underground reserves assume a total dilution of 31%;
-
In-situ Au ounces disregard metallurgical recovery of 92%;
-
28% of the mined out stopes and drifts will use backfill including waste and filtered tailings material. Backfilling operations will commence in the 2nd year of operation;
-
Detailed ventilation designs were applied; and
-
Reserves are based on topography received from Metminco on January 26, 2017.
Ore Reserve Estimation Factors
For stope optimization, Stope Optimizer from Vulcan™ mine planning software was used. A post analysis of the optimisation confirms that for a life of mine of around 10 years, ore to plant of 1,300 tpd producing 4,000 oz Au per month, the cut-off grade would be 1.75 g/t Au. Therefore this cut-off grade was used in the optimization algorithm.
The mining method selected for the MIraflores deposit is the retreat longhole open stope method with partial backfill. The decision of which stopes require to be backfilled was made taking into consideration the geotechnical analysis and the mining sequence.
Only the underground resources contained within the mining stopes or underground development drives were included in the Ore Reserve estimate.
Underground reserves assume a total dilution of 31%.
Ore loss has been accounted for by removing areas that will not be mined as they are either too remote from other potential ore to pay for additional development, or the potential value has been diluted to a point where the material is eliminated from consideration. No other ore loss has been considered.
Metminco Limited ABN 43 119 759 349 Suite 401, 6 Help Street, Chatswood, NSW, 2067 ASX Code: MNC.AX; AIM Code: MNC.L Tel: +61 (0) 2 9460 1856; Fax: +61 (0) 2 9460 1857 www.metminco.com.au
==> picture [217 x 36] intentionally omitted <==
Mine development and stope production were scheduled using Vulcan Gantt Scheduler™. The scheduler package developed the schedule following a logic sequence of development drives with a maximum monthly rate of 270 meters per horizontal development drill jumbo.
Ramps; 4.5 x 4.5 meters Drifts and cross-cuts; 4 x 4 meters
Stoping minimum width; 2.5 meters Stoping average width; 7 meters
Production will start in year 1, focusing on high-grade areas and the early level development from the secondary ramps. The production will ramp up relatively quickly, allowing the processing of 1,300 tonnes per day during the first year of the mine schedule.
The mine operating and capital cost estimate was also constructed using first principles and an Excel™ cost model.
The geotechnical study included the data collection through drilling and mapping, rock mass classification, structural analysis, stability analysis and ground support recommendations.
The mine operation includes in-fill drilling activities for stope delineation and ore control purposes.
The planned dilution material will contain a small amount of Inferred Resources, However, this material contributes less than 1% of the total material above the cut-off grade.
The mining production schedule developed by Ausenco requires approximately 20% of the process tailings and all waste material mined for stope backfill purposes. Further backfill material (up to 50% of the total tailings), will be placed underground for cost and environmental benefit. Conceptually, Ausenco considers this strategy as adequate to improve either the stability of the stopes and for reducing the size of the tailing storage facility. However, it will be necessary to revisit the mining production schedule to achieve the proposed stope backfill targets prior to mining commencing.
Metallurgical Factors
The feasibility study metallurgical testwork program was conducted by Inspectorate Exploration and Mining Services (Inspectorate) of Vancouver, Canada, and ALS Laboratories (ALS) and was designed to evaluate a process flowsheet that included:
-
Three-stage crushing;
-
Grinding;
-
Gravity concentration of the coarse gold;
-
Gold flotation of the gravity tailing;
Metminco Limited ABN 43 119 759 349 Suite 401, 6 Help Street, Chatswood, NSW, 2067 ASX Code: MNC.AX; AIM Code: MNC.L Tel: +61 (0) 2 9460 1856; Fax: +61 (0) 2 9460 1857 www.metminco.com.au
==> picture [217 x 36] intentionally omitted <==
-
Cyanide leaching of the gold flotation concentrate;
-
Cyanide detoxification of the cyanidation residue; and
-
Tailing thickening and filtration.
This flow sheet as tested has resulted in a gold recovery of 92% and silver recovery of 60% being utilised in the process plant design.
The process facility is designed to treat 474,500 tonnes of ore per annum (1,300 tonnes per day). The wet plant is scheduled to operate seven days per week at a nominal treatment rate of 59 dry t/h.
Environmental Studies
Baseline environmental studies were initiated by the previous owner in order to advance the development and preparation of an Environmental Impact Assessment study needed for regulatory permitting in Colombia. Given the current revision to the mine plan, some additional studies may be required for the areas to which the mine facilities have been relocated. This will be determined once the final mine plan is developed and the aforementioned gap analysis has been completed but some of this information has already been gathered to date.
As of July 2017, Baseline Study and Environmental Impact Assessment programs have recommenced. The bulk of the Baseline activities previously completed will be used as background information, however, local regulations requires all environmental and social baseline data to be no older than 12 months since its collection, thus new monitoring programs are underway starting Q3 of 2017.
The monitoring and environmental inventories consist of:
-
Fauna and flora characterization;
-
Underground and surface water characterization;
-
Noise, vibration and air pollution; and
-
Potential contaminants from extracted minerals and stored tailings.
This data along with the mineralogical, geological, social and economic aspects of the new project will be used to complete the Environmental Impact Assessment, as per the Terms of Reference received by Miraflores from the local environmental agency Corporacion Autonoma Del Risaralda (CARDER) in July 2017.
The Environmental Management Plan (EMP) will be drafted once the environmental impacts are completed and finalized in late 2017.
Acid rock drainage characterization data obtained to date includes ABA, multi-element analyses, and mineralogical analyses. Column testing was conducted for waste rock and low-grade stockpile materials. Geochemical evaluation of flotation tailings and cyanide leach tailings was also conducted. Preliminary results indicate that the flotation tailings and the majority of waste rock are non-PAG (non-potentially acid generating); whereas the low-grade stockpiles and cyanide leach tailings are PAG (potentially acid generating).
| Metminco Limited ABN 43 119 759 349 | Suite 401, 6 Help Street, Chatswood, NSW, 2067 |
|---|---|
| ASX Code: MNC.AX; AIM Code: MNC.L | Tel: +61 (0) 2 9460 1856; Fax: +61 (0) 2 9460 1857 |
| www.metminco.com.au |
==> picture [217 x 36] intentionally omitted <==
Potential for metal leaching is indicated in the static test data, but further evaluation is in progress to acquire kinetic data for use in geochemical modelling.
The current mine plan does not include low grade stockpiling on surface. The cyanide leach tailings will be placed underground as part of the mine backfilling requirements.
The current mine plan includes the use of a large fraction of the expected tailings flow as underground backfill material. The remaining filtered tailings will be sent to the tailings management facility where they will be spread and mechanically compacted to achieve an unsaturated, dense and stable tailings deposit. No pond or water impoundment will exist so there is no potential for infiltration to native soils from the tailings materials.
Miraflores has received a mine development permit from the CARDER for the development of 2,000 meters of underground exploration development which includes 2 permanent waste dumps and water discharge licence (Resolution 1505 of 7 September 2017).
Infrastructure
The area is well serviced with respect to roads. The site is located approximately 7km from the Panamerican highway that runs along the Cauca River. The road connecting the Panamerican Highway with the town of Quinchia passes within a few kilometers of the site and is currently being upgraded with 4 of the 7km of road now newly sealed and with the remaining portion of the road expected to be completed prior to construction commencing. From the newly sealed road access to the site is via an unsealed road which will require upgrading to allow access for large bulk loads. The feasibility capital estimate allows for the upgrade to this access road, the mine haul roads and other proposed internal roads for the operation.
Sufficient labour is readily available throughout the region but specifically in Quinchia and in communities immediately surrounding the site. Professional and experience labour will be sourced from both within and outside of Colombia. The town of Quinchia and surrounding towns have an adequate supply of suitable accommodation for any labour brought into the area. It is Miraflores’s intention to employ labour locally and where labour is brought into the area from outside, the Company will require that labour to relocate to Quinchia.
Power Supply to the site will be via a new overhead power line from Quinchia. The incoming supply voltage will be 33 kV, with step-down transformers to the site distribution voltage of 13.8 kV. A medium voltage distribution board installed at the incoming HV switchyard will distribute power to the outgoing feeders. The new power line will be approximately 8km in length and will be a dedicated line.
Water supply needs for the Project (processing plant and camp) have been assessed and the water balance summary has been carried out. The processing plant will require a total of 500 m3/day of water to operate.
| Metminco Limited ABN 43 119 759 349 | Suite 401, 6 Help Street, Chatswood, NSW, 2067 |
|---|---|
| ASX Code: MNC.AX; AIM Code: MNC.L | Tel: +61 (0) 2 9460 1856; Fax: +61 (0) 2 9460 1857 |
| www.metminco.com.au |
==> picture [217 x 36] intentionally omitted <==
The accommodation camp will require 30 m3/day of freshwater which will be trucked to site from the local community water supply. The surplus water from mine dewatering operations will be used for construction works, dust suppression and drilling and/or will be sent to the water treatment plant.
Capital and Operating Costs
The capital and operating cost estimates produced for the establishment of the mine is considered to be an AACE class 3 estimate with a level of accuracy within -10% and +15%. Costs are presented in United States dollars (US$) and are based on prices in effect during the second quarter of 2017; no escalation factors have been applied.
The exchange rate applied for the operating and capital cost estimates are:
-
US$1.00 = A$0.80 (Australian Dollar);
-
US$1.00 = €0.86 (Euro); and
-
US$1.00 = 3,000 COP (Colombian Pesos).
The feasibility study delivered a total estimated Initial Capital cost of bringing the project into production of US$71.8 million excluding all contingency. This cost is based upon an EPCM approach whereby Miraflores assumes general risk. Contingencies of US$6.2 million was estimated for the project development. Contingencies have been estimated at 7.67% of initial capital.
Sustaining capital requirements associated with the mine and owner cost of US$18.5 million were included into the financial model.
The Operating cost was based on a high productivity operation, this will demand a high efficient environment for productivity and cost controls. No contingency was embedded into the operating cost.
The feasibility study delivered the following results for the operating costs:
-
Mining cost of US$27.94 /processed t;
-
Processing cost of 20.54/processed t;
-
Tailing cost of US$0.62 /processed t; and
-
G&A cost of US$4.36 / processed t;
The total site operating cost is US$53.46 /processed t
Government Royalty of US$52.18 / payable ounce.
Refining charges, transport and insurance of US$4.50 / payable ounce.
Total Cash Costs of US$599 / payable ounce
Metminco Limited ABN 43 119 759 349 Suite 401, 6 Help Street, Chatswood, NSW, 2067 ASX Code: MNC.AX; AIM Code: MNC.L Tel: +61 (0) 2 9460 1856; Fax: +61 (0) 2 9460 1857 www.metminco.com.au
==> picture [217 x 36] intentionally omitted <==
The operating cost estimate did not include Corporate overheads and exploration activities.
Revenue Factors
The revenue estimate was conducted as per industry standards taking into consideration the annual metal production, commercial terms and predicted metal prices.
The revenue estimate utilized the following assumptions:
-
A gold and silver prices of US$1,300/oz and US$18 /oz respectively (Within the range of industry expectations and Broker and Bank predictions. The gold price used is close to the moving 5 year average gold price);
-
The average processed head grade of 3.29 g/t and 2.56 g/t for gold and silver respectively (from the mine and processing schedules);
-
Metallurgical recoveries of 92 % and 60 % for gold and silver production respectively (determined from metallurgical testwork);
-
Metal payability factors of 96.6 % and 99.0 % for gold and silver respectively (from historical figures and discussions with refiners);
-
Refinery and transport and insurance charges of US$4.50/ payable ounce (based on previous study estimates); and
-
Royalty of 4 % of the net smelter return (based on the Miraflores licence and Existing Aporte contract expiry (2019) prior to commencement of production in late 2019 when the licence will revert to the normal system of concession contracts which are subject to a 4% royalty only).
Economic Analysis
Metminco developed a comprehensive financial model for the economic evaluation of the Miraflores Gold Project. The financial model incorporates the modifying factors delivered by the Miraflores Feasibility Study.
The key assumptions utilised in the financial model are listed as follows:
-
Gold and silver prices of US$1,300 /oz and US$18 /oz respectively;
-
Net smelter return as per the Revenue estimate;
-
Operating and capital costs as per industry standards;
-
Working capital and inventory management as per industry standards;
-
Debt and financing activities are excluded from the net present cost estimate;
-
All cash flows were treated in real terms, therefore, no inflation or escalation factors were applied;
-
Discount Rate of 8%;
-
Site operating cost of US$ 53,46 /processed t; and
-
Income tax of 33%.
The Miraflores Feasibility Study delivered a Net Present Value of US$72.3 million after tax and an Internal Rate of Return of 25%.
| Metminco Limited ABN 43 119 759 349 | Suite 401, 6 Help Street, Chatswood, NSW, 2067 |
|---|---|
| ASX Code: MNC.AX; AIM Code: MNC.L | Tel: +61 (0) 2 9460 1856; Fax: +61 (0) 2 9460 1857 |
| www.metminco.com.au |
==> picture [217 x 36] intentionally omitted <==
Social Licence
According to the social base line information for the project carried out in 2013, there were 289 families in the direct influence area, with a total population of 1,152 inhabitants. The village that has the largest number of inhabitants was Miraflores with 410 inhabitants.
Community base line studies, social impact assessments and community development plans will be complete by the end of 2017.
The Company has an existing agreement with the artisanal miners at Miraflores that will provide education, training and jobs for some of the certified miners while others will receive compensation when the project enters construction and artisanal mining ceases. The Company maintains excellent relations with the local community, municipality and government agencies.
Project Risks and Operating Licences
The main risks for the development of the Miraflores Gold Project identified by the feasibility study are described as follows:
-
Social disruptions or community unacceptance of the project;
-
Gold price;
-
Increase of the predicted capital or operating cost;
-
Not achieving the target production because of mining or processing issues. E.g. reduced ore grade, not achieving the design processing throughput or gold recovery, etc.
-
Existing Miraflores licence contract is not renewed or the licence does not revert to the normal system of concession contracts which are subject to a 4% royalty only);
-
Geotechnical instability; and
-
Unpredicted water levels in the underground mine.
Other than the Aporte contract for the Miraflores licence no other material agreement is in effect at this time.
The Miraflores Project Environmental Impact Assessment Study (2013) did not previously have an official Terms of Reference (ToR), instead, the baseline data collection and impact assessment development was progressed under a generic ToR for open pit mining. This generic ToR was issued by National Authority of Environmental Licenses (ANLA) in 2012. In July 2016, a new ToR was issued by ANLA. The Project submitted a request to Corporacion Autonoma Del Risaralda (CARDER) for an official ToR for the new underground Project concept. The new ToR was obtained in August 2017 and is being used as the basis for the ongoing environmental and social work.
The Environmental Impact Assessment Study is expected to be submitted in late Q4 of 2017 or early Q1 of 2018.
Metminco Limited ABN 43 119 759 349 Suite 401, 6 Help Street, Chatswood, NSW, 2067 ASX Code: MNC.AX; AIM Code: MNC.L Tel: +61 (0) 2 9460 1856; Fax: +61 (0) 2 9460 1857 www.metminco.com.au
==> picture [217 x 36] intentionally omitted <==
Plan de Trabajos y Obras or (PTO); The PTO licence is issued by the Ministry Of Mines and Energy and must comply with the Terms of Reference set out by the ministry for non seabed minerals and materials.
All projects must obtain an EIA and PTO prior to commencing development of the project. Approvals are expected to take between 4 and 6 months from submission depending on the requirement to provide further data requested by the authorities.
Ore Reserve Estimate
The Ore Reserve estimate of the Miraflores Project is reported as at the effective day of 18 October, 2017.
The Ore Reserves estimate is inclusive of Mineral Resources.
The reserve estimate is supported by the Miraflores Feasibility Study complying with the JORC Code standards.
The Ore Reserve estimate provided appropriately reflects the Competent Person’s view of the opportunity for Metminco to develop the Miraflores Gold Project based on the modifying factors derived from the Feasibility Study work and the updated Mineral Resource model.
The key modifying factors of the Ore Reserve estimate are described as follows:
-
Reserves are based on a gold price of US$1,200/oz and silver price of US$18/oz;
-
An underground cut-off grade (CoG) of 1.53 g/t-Au was applied to underground resources constrained by a final underground design;
-
Reserves are defined within an underground mine plan generated from diluted Mineral Resources;
-
Underground reserves assume a total dilution of 31%;
-
Mining and processing production schedules were developed for assessing the technical viability of the project;
-
Revenue estimates were developed as per industry standards;
-
Operating and capital cost estimates were executed as per industry standards; and
-
The construction and production schedules formed the basis for a financial model delivering a positive outcome for the economic evaluation.
Proven: 835,606 tonnes @ 4.84g/t Au and 2.73g/t Ag Probable: 2,142,741 tonnes @ 4.16g/t Au and 3.21g/t Ag Proven and Probable: 2.978,346 tonnes @ 4.35g/t Au and 3.08g/t Ag Planned Dilution: 1,347,867 tonnes @ 0.91g/t Au and 1.42g/t Ag
Metminco Limited ABN 43 119 759 349 Suite 401, 6 Help Street, Chatswood, NSW, 2067 ASX Code: MNC.AX; AIM Code: MNC.L Tel: +61 (0) 2 9460 1856; Fax: +61 (0) 2 9460 1857 www.metminco.com.au
==> picture [217 x 36] intentionally omitted <==
Statement of Accuracy
The Competent Person has recommended that further work be conducted prior to commencement of construction of the Miraflores Project on the following topics:
-
Geotechnical stability analysis for the underground mine, especially in the areas
-
containing non-backfilled stopes;
-
Stope Backfilling sequence;
-
Develop a detailed mining construction schedule;
-
Understand the predicted underground water levels;
-
Update the environmental and social costs as per the granted permit –still to be granted.
This further work may result in some changes to the modifying factors representing a high risk for the achievement of the technical and economic outcome of the Miraflores Gold Project delivered by the feasibility study.
Metminco Limited ABN 43 119 759 349 Suite 401, 6 Help Street, Chatswood, NSW, 2067 ASX Code: MNC.AX; AIM Code: MNC.L Tel: +61 (0) 2 9460 1856; Fax: +61 (0) 2 9460 1857 www.metminco.com.au
==> picture [217 x 36] intentionally omitted <==
For further information, please contact: METMINCO LIMITED
Brian Jones
Office: +61 (0) 2 9460 1856
NOMINATED ADVISOR AND BROKER RFC Ambrian
Australia Will Souter / Nathan Forsyth
Office: +61 (0) 2 9250 0000
United Kingdom Charlie Cryer
Office: +44 (0) 20 3440 6800
JOINT BROKER SP Angel Corporate Finance LLP (UK) Ewan Leggat
Office: +44 (0) 20 3470 0470
PUBLIC RELATIONS
Camarco
United Kingdom Gordon Poole / Nick Hennis Office: + 44 (0) 20 3757 4997 Media + Capital Partners Australia Luke Forrestal Office: +61 (0) 411 479 144
Forward Looking Statement
All statements other than statements of historical fact included in this announcement including, without limitation, statements regarding future plans and objectives of Metminco are forward-looking statements. When used in this announcement, forward-looking statements can be identified by words such as ‘’anticipate”, “believe”, “could”, “estimate”, “expect”, “future”, “intend”, “may”, “opportunity”, “plan”, “potential”, “project”, “seek”, “will” and other similar words that involve risks and uncertainties.
These statements are based on an assessment of present economic and operating conditions, and on a number of assumptions regarding future events and actions that, as at the date of this announcement, are expected to take place. Such forward-looking statements are not guarantees of future performance and involve known and unknown risks, uncertainties, assumptions and other important factors, many of which are beyond the control of the Company, its directors and management of Metminco that could cause Metminco’s actual results to differ materially from the results expressed or anticipated in these statements.
The Company cannot and does not give any assurance that the results, performance or achievements expressed or implied by the forward-looking statements contained in this announcement will actually occur and investors are cautioned not to place undue reliance on these forward-looking statements. Metminco does not undertake to update or revise forward-looking statements, or to publish prospective financial information in the future, regardless of whether new information, future events or any other factors affect the information contained in this announcement, except where required by applicable law and stock exchange listing
Metminco Limited ABN 43 119 759 349 Suite 401, 6 Help Street, Chatswood, NSW, 2067 ASX Code: MNC.AX; AIM Code: MNC.L Tel: +61 (0) 2 9460 1856; Fax: +61 (0) 2 9460 1857 www.metminco.com.au
==> picture [194 x 31] intentionally omitted <==
Section 4 Estimation and Reporting of Ore Reserves
(Criteria listed in section 1, and where relevant in sections 2 and 3, also apply to this section.)
| Criteria | JORC Code Explanation | Commentary | Responsible to Complete and/or Review the Comments |
|---|---|---|---|
| Mineral Resource estimate review for conversion to Ore Reserves |
Description of the Mineral Resource estimate used as a basis for the conversion to an Ore Reserve. Clear statement as to whether the Mineral Resources are reported additional to, or inclusive of, the Ore Reserves. |
The Mineral Resource estimate for the Miraflores deposit reported on 14 March 2017 was used as the basis for the conversion to an Ore Reserve. The Mineral Resource model was delivered to Ausenco through a data file The resource model for Miraflores was constructed with Vulcan software using a block model. All of the required information about the deposit is stored in each individual block. This includes estimated characteristics of gold and silver and statistical characteristics such as number of samples used in an estimate, distances to the nearest sample, number of drill holes used, etc., are stored in each individual block. Geologic triangulations were also used to identify the rock type of each block, and these structures also controlled the sub‐blocking in Vulcan along their boundaries. Geologic codes stored in the block model were also used to assign the density within specific geologic boundaries. . Final geologic codes were applied to the block model usingindicator kriging. Indicator kriging provides a very |
Metminco |
==> picture [194 x 31] intentionally omitted <==
good check against the implicit models derived with Leapfrog. This methodology estimates the probability that any block is a certain rock type based on the geologic information identified in drill hole logging. The volumes derived from the indicator kriging were nearly identical to the volumes identified with Leapfrog. So in keeping with generally accepted practices rock units were applied using indicator kriging.
Blocks identified as breccia, basalt and saprolite were estimated only using samples also identified as the same. Samples within the modelled veins were not used to estimate grade within the breccia, basalt or saprolite. Samples within the veins were limited to the vein the samples correlated with and only used to estimate grades within that specific vein. Samples within the breccia, basalt and saprolite but outside the veins were not used to estimate grade within the veins. For example: only samples flagged in vein 800 were used to estimate blocks within vein 800 and only samples flagged as breccia were used to estimate blocks within the breccia boundary.
Inverse distanced cubed grade estimation methodology was used to estimate gold and silver grades for Miraflores. For the breccia, basalt and saprolite variography was done to determined proper search ellipsoid orientation and search distances.
The Miraflores Measured and Indicated Mineral Resources are reported at a gold cut‐off grade of 1.20 g/t
==> picture [194 x 31] intentionally omitted <==
Au. The resources are based on 25,884 meters of drilling in 73 diamond drill holes and 236 meters of underground channel samples. This includes 3,624m in 10 holes carried out by AngloGold Ashanti and B2Gold in 2006‐ 2007.
Statistical and visual checks were performed by Metal Mining Consultants of the estimated block model to ensure there were no discrepancies in the grade estimation routines and to ensure the geometry of mineralization meets the configuration that the geologists expected for estimated mineralization.
Measured Mineral Resources; 2.958Mt @ 2.98g/t Au and 2.48g/t Ag Indicated Mineral Resources; 6.311Mt @ 2.74g/t Au and 2.90g/t Ag Measured and Indicated Mineral Resources; 9.269Mt @ 2.82g/t Au and 2.77g/t Ag Inferred Mineral Resources; 0.487Mt @ 2.36g/t Au and 3.64g/t Ag The Mineral Resources are reported inclusive of the Ore Reserves.
Artisanal miners have caused ore depletion within the Miraflores Project mining footprint. The Mineral Resource Estimate used as the base for the Ore Reserve estimate incorporates this ore depletion. The Ore Reserve estimate has relied on the accuracy of the Mineral Resource Estimate.
==> picture [194 x 31] intentionally omitted <==
| Site visits | Comment on any site visits undertaken by the Competent Person and the outcome of those visits. If no site visits have been undertaken indicate why this is the case. |
Mr Boris Caro visited the site in August 2017 for 3 days as part of the study team to review all aspects of the study including an investigation of the mine, plant and site layouts. The site visit involved field work on the project footprint area including an inspection of the underground tunnels and artisanal miners workings. Consultants involved in the mining study, metallurgical testwork, geotechnical and geological mapping, infrastructure study, social and environmental studies all visited the site during this time. |
CPs |
| Study status | The type and level of study undertaken to enable Mineral Resources to be converted to Ore Reserves. The Code requires that a study to at least Pre- Feasibility Study level has been undertaken to convert Mineral Resources to Ore Reserves. Such studies will have been carried out and will have determined a mine plan that is technically achievable and economically viable, and that material Modifying Factors have been considered. |
A feasibility study has been completed for the Miraflores Project. Metminco engaged GE Engineering Services to complete the processing, infrastructure and feasibility study management aspects of the feasibility study. Ausenco Chile were engaged to complete all aspects of the mine design, mine scheduling, geotechnical analysis and ventilation system design to support the mine design, including capital and operating costs for the mine. Surface geotechnical design for the plant, infrastructure and tailings facility was undertaken by Dynami Geo Consulting (a Medellin based consulting company) and Grana y Montero Engineering, a Lima, Peru based engineering and contracting group assisted in the design of the Tailings Storage Facility This study provided sufficient technical and economic support to back upthe Ore Reserve estimate. |
Metminco |
==> picture [194 x 31] intentionally omitted <==
| Further analysis and test work is recommended for the stope filling sequence and stability analysis prior to any decision to commence with the project construction. |
|||
|---|---|---|---|
| Cut‐off parameters | The basis of the cut-off grade(s) or quality parameters applied. |
An underground cut‐off grade (CoG) of 1.53 g/t‐ for gold was applied to underground diluted resources constrained by the final underground design. This grade delineated the Ore Reserve estimate. Reserves are based on a gold price of US$1,200/oz; Reserves are defined within an underground mine plan generated from diluted Measured and Indicated Mineral Resources; An underground CoG of 1.53 g/t‐Au was applied to underground resources constrained by a final underground design; Underground reserves assume 20% planned and 11% unplanned dilution; In‐situ Au ounces disregard metallurgical recovery of 92%; 28% of the mined out stopes and drifts will use backfill including waste and filtered tailings material. Backfilling operations will commence in the 2nd year of operation; Detailed ventilation designs were applied; and Reserves are based on topography received from Metminco on January 26, 2017. The cut‐offgrade was utilized for the stope optimization |
AUSENCO |
==> picture [194 x 31] intentionally omitted <==
| and the mining schedule. There are approximately 7,000 ounces of gold contained in material with a gold grade between 0.60 and 1.53 g/t. This material is not part of the Ore Reserve but it may deliver a positive economic value, therefore, it will be kept in a stock pile for potential feed to the processing plant. |
|||
|---|---|---|---|
| Mining factor or assumptions |
The method and assumptions used as reported in the Pre-Feasibility or Feasibility Study to convert the Mineral Resource to an Ore Reserve (i.e. either by application of appropriate factors by optimisation or by preliminary or detailed design). The choice, nature and appropriateness of the selected mining method(s) and other mining parameters including associated design issues such as pre-strip, access, etc. The assumptions made regarding geotechnical parameters (e.g. pit slopes, stope sizes, etc.), grade control and pre-production drilling. The major assumptions made and Mineral Resource model used for pit and stope optimisation (if appropriate). The mining dilution factors used. |
For stope optimization, Stope Optimizer from Vulcan™ mine planning software was used. A post analysis of the optimisation confirms that for a life of mine of around 10 years, ore to plant of 1,300 tpd producing 4,000 oz Au per month, the cut‐off grade would be 1.75 g/t Au. Therefore this cut‐off grade was used in the optimization algorithm. The mining method selected for the MIraflores deposit is the retreat longhole open stope method with partial backfill. The decision of which stopes require to be backfilled was made taking into consideration the geotechnical analysis and the mining sequence. The quantity and shape of the stopes were optimized with the Vulcan™ software. This process defined the total amount of Mineral Resources above the cut‐off grade. Subsequently, a manual check to eliminate the stopes isolated or difficult to mine reduced the material selected for the Ore Reserve estimate. For example the stopes located between surface and a vertical distance of |
AUSENCO |
==> picture [194 x 31] intentionally omitted <==
The mining recovery factors used. Any minimum mining widths used. The manner in which Inferred Mineral Resources are utilised in mining studies and the sensitivity of the outcome to their inclusion.
80 meters were eliminated from the Ore Reserve estimate due to geotechnical stability considerations. The Mineral Resource Model used was developed by Metal Mining Consultants of Denver, USA who provided the block model to Ausenco. Only the underground resources contained within the mining stopes or underground development drives were included in the Ore Reserve estimate. Underground reserves assume 20% planned and 11% unplanned dilution. Ore loss has been accounted for by removing areas that will not be mined as they are either too remote from other potential ore to pay for additional development, or the potential value has been diluted to a point where the material is eliminated from consideration. No other ore loss has been considered.
The mine layout was developed to obtain quick access to several mining areas by utilising three mine access portals. The ventilation circuit was designed to use the mine portals, ramps and three 3.1 meter diameter raise bored shafts for air intake and one large extraction raise (5m x 5m) was designed to extract the contaminated air. The stope design included an assessment of the crown pillar, sill pillars, dip pillars and rib pillars. The mine
==> picture [194 x 31] intentionally omitted <==
development design includes the main ramp and secondary ramps, drifts, cross cuts, passing bays, muck loading bays, refugee stations, dewatering bays, electrical substation bays and ventilation drifts. Details of the dimensions for the stope and mine development designs are listed below and described in the Miraflores Feasibility Study Report.
Mine development and stope production were scheduled using Vulcan Gantt Scheduler™. The scheduler package developed the schedule following a logic sequence of development drives with a maximum monthly rate of 270 meters per horizontal development drill jumbo. Ramps; 4.5 x 4.5 meters Drifts and cross‐cuts; 4 x 4 meters Stoping minimum width; 2.5 meters Stoping average width; 7 meters Production will start in year 1, focusing on high‐grade areas and the early level development from the secondary ramps. The production will ramp up relatively quickly, allowing the processing of 1,300 tonnes per day during the first year of the mine schedule. The mine development and production schedule included an estimate of the mine mobile equipment and workforce required to achieve the production targets. Ausenco created an Excel™ model for this purpose taking
Production will start in year 1, focusing on high‐grade areas and the early level development from the secondary ramps. The production will ramp up relatively quickly, allowing the processing of 1,300 tonnes per day during the first year of the mine schedule.
==> picture [194 x 31] intentionally omitted <==
into consideration productivity and maintenance factors.
The mine operating and capital cost estimate was also constructed using first principles and an Excel™ cost model.
The geotechnical study included the data collection through drilling and mapping, rock mass classification, structural analysis, stability analysis and ground support recommendations. An extensive section describing further details for these topics are detailed in of the Miraflores Feasibility Study Report.
The mine operation includes in‐fill drilling activities for stope delineation and ore control purposes.
The planned dilution material will contain a small amount of Inferred Resources, However, this material contributes less than 1% of the total material above the cut‐off grade.
The mining production schedule developed by Ausenco requires approximately 20% of the process tailings and all waste material mined for stope backfill purposes. Further backfill material (up to 50% of the total tailings), will be placed underground for cost and environmental benefit. Conceptually, Ausenco considers this strategy as adequate to improve either the stability of the stopes and for reducing the size of the tailing storage facility. However, it will be necessary to revisit the mining production schedule to achieve the proposed stope
==> picture [194 x 31] intentionally omitted <==
| backfill targets prior to mining commencing. | |||
|---|---|---|---|
| Metallurgical factors or assumptions |
The metallurgical process proposed and the appropriateness of that process to the style of mineralisation. Whether the metallurgical process is well-tested technology or novel in nature. The nature, amount and representativeness of metallurgical test work undertaken, the nature of the metallurgical domaining applied and the corresponding metallurgical recovery factors applied. Any assumptions or allowances made for deleterious elements. The existence of any bulk sample or pilot scale test work and the degree to which such samples are considered representative of the orebody as a whole. For minerals that are defined by a specification, has the ore reserve estimation been based on the appropriate mineralogy to meet the specifications? |
The Feasibility Study metallurgical testwork program was conducted by Inspectorate Exploration and Mining Services (Inspectorate) of Vancouver, Canada, and ALS Laboratories (ALS) and was designed to evaluate a process flowsheet that included: Three‐stage crushing; Ball mill grinding; Gravity concentration of the coarse gold; Gold flotation of the gravity tailing; Cyanide leaching of the gold flotation concentrate; Cyanide detoxification of the cyanidation residue; and Tailing thickening and filtration. This flow sheet as tested has resulted in a gold recovery of 92% and silver recovery of 60% being utilised in the process plant design. Three testwork programs using Miraflores diamond drill core have been completed by Miraflores, all using the services of Inspectorate Exploration and Mining Services (Inspectorate) based in Vancouver, Canada. Similar results have been achieved in all three programs. The metallurgical process is well tested and is utilised in the extraction of gold in many parts of the world and is wellproven for this type of mineralisation. Nopart of the |
GRES |
==> picture [194 x 31] intentionally omitted <==
process design is novel in nature. The metallurgical testwork has successfully demonstrated that recovery of gold at Miraflores by gravity and flotation concentrating is very effective with demonstrated recoveries for gold of 92%.
Although small amounts of base metals are evident, testwork has indicated that these are not concentrated to deliterous levels in the concentrate and have no effect in gold recovery at Miraflores.
Historical mining and processing by previous owners Asociación de Mineros de Miraflores (AMM) demonstrated the effectiveness of processing ore from the Miraflores breccia. Stoping over a vertical distance of 80 meters and strike of 200 meters demonstrated grade continuity and extraction of gold using cyanide processes. The mineralogy of the orebody at Miraflores is best presented by the investigation of three panned concentrates from Knelson concentrate test work that determined that the primary gold‐bearing mineral present is native gold with only minor amounts present as electrum. Minor amounts of Au/Ag telluride minerals were also observed being primarily composed of petzite, having a higher gold content, and subordinate amounts of hessite and stuetzite. These tellurides are often closely association with native gold, but not exclusively. Native gold was mainly liberated with finer grains
==> picture [194 x 31] intentionally omitted <==
| attached or included in sulphide minerals, which include pyrite, sphalerite and galena in minor amounts. Mineralogical work has shown that greater than 97% of gold at Miraflores occurs as free gold with the rest made up mostly of electrum. This fact supports the testwork which has demonstrated that gravity gold recovery using Knelson concentrators achieves high gold recoveries into a gravity concentrate. (>60%). At the completion of the feasibility study the only testwork remaining to be completed was filtration testwork on the flotation tailings and concentrate leach residue both of which are currently in progress. The process facility is designed to treat 474,500 tonnes of ore per annum (1,300 tonnes per day). The wet plant is scheduled to operate seven days per week at a nominal treatment rate of 59 dry t/h. |
|||
|---|---|---|---|
| Environmental | The status of studies of potential environmental impacts of the mining and processing operation. Details of waste rock characterisation and the consideration of potential sites, status of design options considered and, where applicable, the status of approvals for process residue storage and waste dumps should be reported. |
Baseline environmental studies were initiated by the previous owner in order to advance the development and preparation of an Environmental Impact Assessment study needed for regulatory permitting in Colombia. Given the current revision to the mine plan, some additional studies may be required for the areas to which the mine facilities have been relocated. This will be determined once the final mine plan is developed and the aforementioned gap analysis has been completed but some of this information has already been gathered to date. |
DYNAMI |
==> picture [194 x 31] intentionally omitted <==
As of July 2017, Baseline Study and Environmental Impact Assessment programs have recommenced. The bulk of the Baseline activities previously completed will be used as background information, however, local regulations requires all environmental and social baseline data to be no older than 12 months since its collection, thus new monitoring programs are underway starting Q3 of 2017.
-
The monitoring and environmental inventories consist of: Fauna and flora characterization; Underground and surface water characterization;
-
Noise, vibration and air pollution; and Potential contaminants from extracted minerals and stored tailings.
This data along with the mineralogical, geological, social and economic aspects of the new project will be used to complete the Environmental Impact Assessment, as per the Terms of Reference received by Miraflores from the local environmental agency Corporacion Autonoma Del Risaralda (CARDER) in July 2017.
The Environmental Management Plan (EMP) will be drafted once the environmental impacts are completed and finalized in late 2017.
Acid rock drainage characterization data obtained to date includes ABA, multi‐element analyses, and
==> picture [194 x 31] intentionally omitted <==
mineralogical analyses. Column testing was conducted for waste rock and low‐grade stockpile materials. Geochemical evaluation of flotation tailings and cyanide leach tailings was also conducted. Preliminary results indicate that the flotation tailings and the majority of waste rock are non‐PAG (non‐potentially acid generating); whereas the low‐grade stockpiles and cyanide leach tailings are PAG (potentially acid generating). Potential for metal leaching is indicated in the static test data, but further evaluation is in progress to acquire kinetic data for use in geochemical modelling. The current mine plan does not include low grade stockpiling on surface. The cyanide leach tailings will be placed underground as part of the mine backfilling requirements. The current mine plan includes the use of a large fraction of the expected tailings flow as underground backfill material. The remaining filtered tailings will be sent to the tailings management facility where they will be spread and mechanically compacted to achieve an unsaturated, dense and stable tailings deposit. No pond or water impoundment will exist so there is no potential for infiltration to native soils from the tailings materials. Laboratory testing completed by ACZ Laboratories in 2012 resulted in Acid Generation Potentials between 0 and 34 and Acid Neutralization Potential between 9 and 140. The potentially acid generating samples were identified as low grade ore and cyanide leach tailings.
==> picture [194 x 31] intentionally omitted <==
| Sulphur contents range from 0 to 1.4%. Paste pH ranges from 7.7 to 9.4 with an average of 8.6. It is Miraflore’s intention to place the cyanide leach tailings underground. Any low grade material mined will either be placed back underground or be processed depending on the grade of the material The proposed filtered stacked tailings storage facility will be permitted as part of the EIA application. Any waste dumps permitted in the EIA will be temporary dumps as the plan is to use all of the waste mined for planned backfilling operations in the mine. Miraflores has received a mine development permit from the CARDER for the development of 2,000 meters of underground exploration development which includes 2 permanent waste dumps and water discharge licence (Resolution 1505 of 7 September 2017). |
|||
|---|---|---|---|
| Infrastructure | The existence of appropriate infrastructure: availability of land for plant development, power, water, transportation (particularly for bulk commodities), labour, accommodation; or the ease with which the infrastructure can be provided, or accessed. |
The Project is a greenfield site, the facilities that will be required to be installed on site include: Construction accommodation facilities; Kitchen and messing facilities; Main office; First aid and ambulance post; Fuel Handling Facilities; Mine change house; Power supply (overhead power line); Stores and workshops; and Sewage treatment facilities. Access roads linkingthe tailingdam and |
DYNAMI GRES |
==> picture [194 x 31] intentionally omitted <==
construction camp with the process plant;
-
Mining haul roads;
-
Mining and maintenance workshops;
-
Warehouse and store;
-
Administration buildings;
-
Laboratory;
-
Reagents storage building;
-
Communications upgrade;
-
Security facilities;
-
Sewage and water treatment facilities;
-
Emergency response facilities including fire fighting building and equipment; and
-
Dedicated overhead power line.
A new overhead power line will be constructed for the process plant, mine, water supply, tailings area, administration and infrastructure. Power requirements will be as follows:
-
Process plant 4 x 2,250 kVA;
-
Mining 1 x 2,000 kVA;
-
Accommodation 1 x 300 kVA;
-
Tailings Area 1 x 50 kVA; and
-
Water Supply 1 x 50 kVA.
Each area will have a dedicated transformer and power supply motor control centre.
Power Supply to the site will be via a new overhead power line from Quinchia. The incoming supply voltage will be 33 kV, with step‐down transformers to the site
==> picture [194 x 31] intentionally omitted <==
distribution voltage of 13.8 kV. A medium voltage distribution board installed at the incoming HV switchyard will distribute power to the outgoing feeders. The new power line will be approximately 8km in length and will be a dedicated line. Water supply needs for the Project (processing plant and camp) have been assessed and the water balance summary has been carried out.
The processing plant will require a total of 500 m3/day of water to operate.
The accommodation camp will require 30 m3/day of freshwater which will be trucked to site from the local community water supply.
The surplus water from mine dewatering operations will be used for construction works, dust suppression and drilling and/or will be sent to the water treatment plant.
Miraflores have purchased 28 ha of land and intend to purchase a further 100ha as part of the development plan. Suitable sites for mine portals, haul roads, processing facilities and infrastructure to support those operations has been identified, geotechnical assessments of the ground conditions made and facility layouts completed as part of the feasibility study. The area is well serviced with respect to roads. The site is located approximately 7km from the Panamerican
==> picture [194 x 31] intentionally omitted <==
highway that runs along the Cauca River. The road connecting the Panamerican Highway with the town of Quinchia passes within a few kilometers of the site and is currently being upgraded with 4 of the 7km of road now newly sealed and with the remaining portion of the road expected to be completed prior to construction commencing. From the newly sealed road access to the site is via an unsealed road which will require upgrading to allow access for large bulk loads. The feasibility capital estimate allows for the upgrade to this access road, the mine haul roads and other proposed internal roads for the operation.
Sufficient labour is readily available throughout the region but specifically in Quinchia and in communities immediately surrounding the site. Professional and experience labour will be sourced from both within and outside of Colombia. The town of Quinchia and surrounding towns have an adequate supply of suitable accommodation for any labour brought into the area. It is Miraflores’s intention to employ labour locally and where labour is brought into the area from outside, the Company will require that labour to relocate to Quinchia.
Dynami Geo Consulting have completed preliminary basic engineering on the tailings storage facility (TSF). The dry stack tailings storage facility will receive filtered tailings for spreading and compaction. The final TSF configuration allows for 50% of final tailings to be used as backfill in the underground mine which includes 100% of the concentrate leach residue tailings.
==> picture [194 x 31] intentionally omitted <==
| Cost | The derivation of, or assumptions made, regarding projected capital costs in the study. The methodology used to estimate operating costs. Allowances made for the content of deleterious elements. The source of exchange rates used in the study. Derivation of transportation charges. The basis for forecasting or source of treatment and refining charges, penalties for failure to meet specification, etc. The allowances made for royalties payable, both Government and private |
Capital and operating cost estimates have been developed for a mining operation treating 466,628 tonne per annum of gold and silver bearing ore and includes: An underground operating mine; A gold / silver processing plant recovering these metals, utilising a flow sheet comprising crushing, grinding, gravity separation, conventional flotation, cyanide leach circuit for the concentrates, concentrate leach residue washing with Merrill Crowe for recovery of the precious metals, concentrate leach tailings detoxification and filtration for mine back fill, flotation tailings filtration for mine backfill and dry stack tailings storage and support infrastructure and utilities. The capital and operating cost estimates produced for the establishment of the mine is considered to be an AACE class 3 estimate with a level of accuracy within ‐ 10% and +15%. Costs are presented in United States dollars (US$) and are based on prices in effect during the second quarter of 2017; no escalation factors have been applied. The exchange rate applied for the operating and capital cost estimates are: US$1.00 = A$0.80 (Australian Dollar); US$1.00 = €0.85 (Euro); US$1.00 = 3,000 COP (Colombian Pesos). Exchange rates used include: |
AUSENCO GRES DYNAMI |
==> picture [194 x 31] intentionally omitted <==
| $US1 : COP3,000 |
|---|
| $US0.80 : $AUD1 |
| $US1 : 0.86 Euro |
| Transportation charges were derived from an |
| international freight forwarder allocating individual |
| equipment and fabricated transport charges included |
| overseas freight to port of Buenaventura where |
| applicable and in country freight from port/ fabrication |
| shop to site. |
| Refining charges; from discussions with potential refiners |
| and from previous studies by SRK; |
| Gold Payability – 99.6% |
| Silver Payability – 99% |
| Refining, transport and Insurance costs – US$4.50/ |
| payable ounce. |
| Miraflores will determine quality prior to completing an |
| offtake agreement. No deleterious elements are |
| expected based on the metallurgical testwork |
| completed. |
| The feasibility study delivered a total estimated Initial |
| Capital cost of bringing the project into production of |
| US$71.8 million excluding all contingency. This cost is |
| based upon an EPCM approach whereby Miraflores |
| assumes general risk. Contingencies of US$6.2 million |
| was estimated for the project development. |
| Contingencies have been estimated at 7.67% of initial |
==> picture [194 x 31] intentionally omitted <==
capital.
Sustaining capital requirements associated with the mine and owner cost of US$18.5 million were included into the financial model.
The Operating cost was based on a high productivity operation, this will demand a high efficient environment for productivity and cost controls. No contingency was embedded into the operating cost.
During the first year of operation, allowances for the employment of experienced ex‐patriate personnel were incorporated but it is expected that this personnel will be replaced progressively by local workforce.
The main consumables and labour wages were benchmarked against other similar operations.
The feasibility study delivered the following results for the operating costs:
Mining cost of US$27.94 /processed t; Processing cost of 20.54/processed t; Tailing cost of US$0.62 /processed t; and G&A cost of US$4.36 / processed t; The total site operating cost is US$53.46 /processed t Government Royalty of US$52.18 / payable ounce Refining charges, transport and insurance of US$4.50 / payable ounce
==> picture [194 x 31] intentionally omitted <==
| Total Cash Costs of US$599 / payable ounce The operating cost estimate did not include Corporate overheads and exploration activities. The Miraflores Feasibility Study assumed that the salvage value of the remaining assets at the end of the operating mine life will off‐set the closure and remediation cost. |
|||
|---|---|---|---|
| Revenue factors | The derivation of, or assumptions made regarding revenue factors including head grade, metal or commodity price(s) exchange rates, transportation and treatment charges, penalties, net smelter returns, etc. The derivation of assumptions made of metal or commodity price(s), for the principal metals, minerals and co-products. |
The revenue estimate was conducted as per industry standards taking into consideration the annual metal production, commercial terms and predicted metal prices. The revenue estimate utilized the following assumptions: A gold and silver prices of US$1,300/oz and US$18 /oz respectively (Within the range of industry expectations and Broker and Bank predictions. The gold price used is close to the moving 5 year average gold price); The average processed head grade of 3.29 g/t and 2.56 g/t for gold and silver respectively (from the mine and processing schedules); Metallurgical recoveries of 92 % and 60 % for gold and silver production respectively (determined from metallurgical testwork); Metal payability factors of 96.6 % and 99.0 % for gold and silver respectively (from historical figures and discussions with refiners); Refinery and transport and insurance charges of US$4.50/ payable ounce(based onprevious |
Metminco |
==> picture [194 x 31] intentionally omitted <==
| study estimates); and Royalty of 4 % of the net smelter return (based on the Miraflores licence and Existing Aporte contract expiry (2019) prior to commencement of production in late 2019 when the licence will revert to the normal system of concession contracts which are subject to a 4% royalty only). |
|||
|---|---|---|---|
| Market assessment | The demand, supply and stock situation for the particular commodity, consumption trends and factors likely to affect supply and demand into the future. A customer and competitor analysis along with the identification of likely market windows for the product. Price and volume forecasts and the basis for these forecasts. For industrial minerals the customer specification, testing and acceptance requirements prior to a supply contract. |
Metminco has been actively monitoring the market trends for the gold industry. Modifying factors such as gold price, payable metal factors, and transport and refining costs are within the ranges predicted by the industry analysts. Gold and silver are readily traded around the world. These markets are considered mature and with reputable smelters and refiners located throughout the world. |
Metminco |
| Economic | The inputs to the economic analysis to produce the net present value (NPV) in the study, the source and confidence of these economic inputs including estimated infation, discount rate, etc. NPV ranges and sensitivity to variations in the |
Metminco developed a comprehensive financial model for the economic evaluation of the Miraflores Gold Project. The financial model incorporates the modifying factors delivered by the Miraflores Feasibility Study. The keyassumptions utilised in the financial model are |
Metminco |
==> picture [194 x 31] intentionally omitted <==
| significant assumptions and inputs. | listed as follows: Gold and silver prices of US$1,300 /oz and US$18 /oz respectively; Net smelter return as per the Revenue estimate; Operating and capital costs as per industry standards; Working capital and inventory management as per industry standards; Debt and financing activities are excluded from the net present cost estimate; All cash flows were treated in real terms, therefore, no inflation or escalation factors were applied; Discount Rate of 8%; Site operating cost of US$ 53,46 /processed t; and Income tax of 33%. The Miraflores Feasibility Study delivered a Net Present Value of US$72.3 million after tax and an Internal Rate of Return of 25%. |
||
|---|---|---|---|
| Social | The status of agreements with key stakeholders and matters leading to social licence to operate. |
The Miraflores Gold Project is located in the municipality of Quinchía. The municipality obtained its name from the fortresses in Guadua that were called "Quinchos". In 1966, Quinchía became part of the Risaralda Department. The basic economy of the region can be divided in two activities: agricultural and mining activities. Quinchía is characterized bybeinga municipalitywith an agricultural |
PORTEX |
==> picture [194 x 31] intentionally omitted <==
| vocation, with small land divisions and with mining potential. However, there is a lack of attention to land uses and environmental regulations within the agricultural sector. For the primary information, the results of the surveys undertaken in 2013 were used. This information will be updated when the new social baseline study is completed at the end of 2017. For the study undertaken in 2013, the direct influence area of the project included the villages of Miraflores, Guerrero, Aguas Claras, Veracruz, Agua Salada, La Esmeralda and Los Medios. According to the social base line information for the project carried out in 2013, there were 289 families in the direct influence area, with a total population of 1,152 inhabitants. The village that has the largest number of inhabitants was MIraflores with 410 inhabitants. Community base line studies, social impact assessments and community development plans will be complete by the end of 2017. |
|||
|---|---|---|---|
| Other | To the extent relevant, the impact of the following on the project and/or on the estimation and classification of the Ore Reserves: Any identified material naturally occurring risks. The status of material legal agreements and marketing arrangements. |
The main risks for the development of the Miraflores Gold Project identified by the feasibility study are described as follows: Social disruptions or community unacceptance of the project; Gold price; Increase of thepredicted capital or operating |
Metminco CPs |
==> picture [194 x 31] intentionally omitted <==
cost;
The status of governmental agreements and approvals critical to the viability of the project, such as mineral tenement status, and government and statutory approvals. There must be reasonable grounds to expect that all necessary Government approvals will be received within the timeframes anticipated in the Pre-Feasibility or Feasibility study. Highlight and discuss the materiality of any unresolved matter that is dependent on a third party on which extraction of the reserve is contingent.
-
Not achieving the target production because of mining or processing issues. E.g. reduced ore grade, not achieving the design processing throughput or gold recovery, etc.
-
Existing Miraflores licence contract is not renewed or the licence does not revert to the normal system of concession contracts which are subject to a 4% royalty only);
-
Geotechnical instability;
-
Unpredicted water levels in the underground mine.
Other than the Aporte contract for the Miraflores licence no other material agreement is in effect at this time.
The Miraflores Project Environmental Impact Assessment Study (2013) did not previously have an official Terms of Reference (ToR), instead, the baseline data collection and impact assessment development was progressed under a generic ToR for open pit mining. This generic ToR was issued by National Authority of Environmental Licenses (ANLA) in 2012. In July 2016, a new ToR was issued by ANLA. The Project submitted a request to Corporacion Autonoma Del Risaralda (CARDER) for an official ToR for the new underground Project concept. The new ToR was obtained in August 2017 and is being used as the basis for the ongoing environmental and social work.
The Environmental Impact Assessment Study is expected
==> picture [194 x 31] intentionally omitted <==
| to be submitted in late Q4 of 2017 or early Q1 of 2018. Plan de Trabajos y Obras or (PTO); The PTO licence is issued by the Ministry Of Mines and Energy and must comply with the Terms of Reference set out by the ministry for non seabed minerals and materials. All projects must obtain an EIA and PTO prior to commencing development of the project. Approvals are expected to take between 4 and 6 months from submission depending on the requirement to provide further data requested by the authorities. |
|||
|---|---|---|---|
| Classification | The basis for the classification of the Ore Reserves into varying confidence categories. Whether the result appropriately refects the Competent Person’s view of the deposit. The proportion of Probable Ore Reserves that have been derived from Measured Mineral Resources (if any). |
The Measured and Indicated Mineral Resources were classified as Proven and Probable Ore Reserves respectively. The Ore Reserve estimate of the Miraflores Project is reported as at the effective day of 18 October 2017. The Ore Reserves estimate is inclusive of Mineral Resources. The reserve estimate is supported by the Miraflores Feasibility Study complying with the JORC Code standards. The Ore Reserve estimate provided appropriately reflects the Competent Person’s view of the opportunityfor |
AUSENCO |
==> picture [194 x 31] intentionally omitted <==
Metminco to develop the Miraflores Gold Project based on the modifying factors derived from the Feasibility Study work and the updated Mineral Resource model.
The key modifying factors of the Ore Reserve estimate are described as follows:
-
Reserves are based on a gold price of US$1,200/oz and silver price of US$18/oz;
-
An underground cut‐off grade (CoG) of 1.53 g/t‐ Au was applied to underground resources constrained by a final underground design;
-
Reserves are defined within an underground mine plan generated from diluted Mineral Resources;
-
Underground reserves assume 20% planned and 11% unplanned dilution;
-
Mining and processing production schedules were developed for assessing the technical viability of the project;
-
Revenue estimates were developed as per industry standards;
-
Operating and capital cost estimates were executed as per industry standards; and
-
The construction and production schedules formed the basis for a financial model delivering a positive outcome for the economic evaluation.
As can be appreciated from the information in Table 1, the Ore Reserve gold cut‐off grade utilized a gold price,
==> picture [194 x 31] intentionally omitted <==
| site operating costs and gold recovery values which have small differences from the figures used in the financial model. This is due to the Ore Reserve cut‐off grade being estimated for the stope optimization analysis prior to development of the financial model, being the first activity executed during the Miraflores Feasibility Study. The cut‐off grade delineated the material to be included in the Ore Reserve estimate but subsequent activities such as the metallurgical test work, mine and processing production schedule and operating cost estimate provided the final values for the modifying factors which have been included into the financial model. The Competent Person assessed these small discrepancies and concluded that no material impact on the final technical and economic outcome of the Miraflores Feasibility Study is evident. Ore Reserves Proven: 835,606 tonnes @ 4.84g/t Au and 2.73g/t Ag Probable: 2,142,741 tonnes @ 4.16g/t Au and 3.21g/t Ag Proven and Probable: 2.978,346 tonnes @ 4.35g/t Au and 3.08g/t Ag Planned Dilution: 1,347,867 tonnes @ 0.91g/t Au and 1.42g/t Ag |
|||
|---|---|---|---|
| Audit or reviews | The results of any audits or reviews of Ore Reserve estimates. |
No formal audits have been conducted on the Mineral Reserve estimate |
Metminco |
| Discussions of relative accuracy/confidence |
Where appropriate a statement of the relative accuracy and confidence level in the Ore Reserve estimate using an approach or |
The Competent Person has recommended that further work be conducted prior to commencement of construction of the Miraflores Project on the following |
Metminco CPs |
==> picture [194 x 31] intentionally omitted <==
procedure deemed appropriate by the Competent topics: Person. For example, the application of statistical or geostatistical procedures to Geotechnical stability analysis for the underground quantify the relative accuracy of the reserve mine, especially in the areas containing non‐backfilled within stated confidence limits, or, if such an stopes; approach is not deemed appropriate, a Stope Backfilling sequence; qualitative discussion of the factors which could Develop a detailed mining construction schedule; affect the relative accuracy and confidence of the Understand the predicted underground water levels; estimate. Update the environmental and social costs as per the granted permit –still to be granted‐.
The statement should specify whether it relates to global or local estimates, and, if local, state the relevant tonnages, which should be relevant to technical and economic evaluation. Documentation should include assumptions made and the procedures used.
This further work may result in some changes to the modifying factors representing a high risk for the achievement of the technical and economic outcome of the Miraflores Gold Project delivered by the feasibility study.
Accuracy and confidence discussions should extend to specific discussions of any applied Modifying Factors that may have a material impact on Ore Reserve viability, or for which there are remaining areas of uncertainty at the current study stage.
It is recognised that this may not be possible or appropriate in all circumstances. These statements of relative accuracy and confidence of the estimate should be compared with production data, where available.
==> picture [194 x 31] intentionally omitted <==