KNR Constructions Limited — Regulatory Filings 2021
Oct 6, 2021
61868_rns_2021-10-06_dfc3998f-42b9-4050-9419-95d747b10b5d.pdf
Regulatory Filings
Open in viewerOpens in your device viewer
==> picture [154 x 61] intentionally omitted <==
Date: 06[th] October 2021
Ref: KNRCL/SD/2021/337&338
To, To, The Manager The Manager, BSE Limited, National Stock Exchange of India Limited, P J Towers, Dalal Street, Exchange Plaza, Bandra Kurla Complex, Fort, Mumbai – 400001 Bandra (E), Mumbai – 400051. Scrip code: 532942 Scrip Code: KNRCON
Dear Sir/Madam,
Sub: Issuance of Provisional Certificate of Completion Ref: Regulation 30 of SEBI (LODR) Regulations, 2015
With reference to the above captioned subject, we herewith inform the Exchanges that Provisional Certificate of Completion for “Four laning of Trichy (KM 0.000) to Kallagam (KM 38.700) Section of NH-227 under Bharatmala Pariyojana (Residual projects under NHDP) in the State of Tamil Nadu” effective from 30[th] May 2021 was received by KNR Srirangam Infra Private Limited, a Wholly Owned Subsidiary of the Company and the Project was completed 89 days ahead of the Revised Scheduled Completion Date.
| Name of the Project | Bid Project Cost (Rs in crores) |
Appointed Date and Construction Period |
Scheduled Completion Date |
Revised Scheduled Completion Date |
Date of Provisional Completion |
|---|---|---|---|---|---|
| Four laning of Trichy (KM 0.000) to Kallagam (KM 38.700) Section of NH-227 under Bharatmala Pariyojana (Residual projects under NHDP) in the State of Tamil Nadu |
1020.60 | 01stMarch 2019 and 730 Days |
28thFebruary 2021 |
27thAugust 2021 |
30thMay 2021 |
This is for information and records of the Exchange, please. Thanking you,