KGL RESOURCES LIMITED — Investor Presentation 2011
May 15, 2011
65179_rns_2011-05-15_2dc56555-af7b-47f7-b4ae-256302b22099.pdf
Investor Presentation
Open in viewerOpens in your device viewer
Kentor Gold May 2011 Investor Presentation
ANDASH PROJECT
-
1.6mtpa to 3.2mtpa throughput
-
Simple and conventional open pit and flotation plant
-
3 stage crush, grind, float process
-
Average annual production:
-
70,000 oz Au and 7,400t Cu
-
High grade concentrate 24.5% Cu and 72 g/t Au
-
No deleterious elements
-
Initial mine life 6 years
==> picture [372 x 256] intentionally omitted <==
- Resource/reserve expansion likely to significantly increase mine life
2
ANDASH PROJECT
-
Cash cost US$29/oz Au (after Cu credits and royalty)
-
Capital Cost US$96m
-
Base Case NPV US$130m
-
US$1,000/oz Au & US$2.75/lb Cu
-
Base Case NPV increases by 56% by adding additional 6.0 mt of ore (2 years)
-
12 month construction programme
-
Awaiting final approvals
-
Corporate Income Tax 10%
-
Sales Tax 1.5%
-
Royalties – Gold 5%, Copper 3%
| Cost component (US$/t) |
Phase 1 (1.5mtpa) |
Phase 2 (3mtpa) |
|---|---|---|
| Mining | 3.46 | 3.46 |
| Processing | 8.62 | 7.09 |
| G&A | 3.38 | 1.69 |
| Total | 15.46 | 12.24 |
Project NPV (US$)
| Gold Price | Copper Price (US$/lb) |
Copper Price (US$/lb) |
Copper Price (US$/lb) |
Copper Price (US$/lb) |
Copper Price (US$/lb) |
|---|---|---|---|---|---|
| (US$/oz) | 2.25 | 2.75 | 3.25 | 3.75 | 4.25 |
| 800 | 56 | 83 | 110 | 138 | 165 |
| 1,000 | 103 | 130 | 157 | 185 | 212 |
| 1,200 | 150 | 177 | 204 | 231 | 258 |
| 1,400 | 197 | 223 | 251 | 278 | 305 |
| 1,600 | 243 | 271 | 298 | 325 | 352 |
3
ANDASH PROJECT
-
Project Capital Cost US$96m
-
Macquarie Bank to provide project debt of US$50m
-
No compulsory hedging
-
Cash in the bank US$71m (end of March 2011)
==> picture [358 x 251] intentionally omitted <==
==> picture [354 x 248] intentionally omitted <==
4
ANDASH PROJECT
==> picture [703 x 401] intentionally omitted <==
5
- Fully funded through to production
Developing one of the world’s lowest cost gold mines
-
Growing the resource base
-
Negotiations with local community
12 month construction programme
==> picture [726 x 222] intentionally omitted <==
6
- Kentor Gold has taken over 94% of Jinka Minerals
Near term development of Gold and Copper Resources
7
Location of Projects
Burnakura (100%) 50km south of Meekatharra Gabanintha (100%) 45km southeast of Meekatharra Jervois (100%) 280km northeast of Alice Springs
8
Key terms of offer
A$7.8m for all Jinka shares and options on issue
- Repayment of Jinka loans of A$4.95m
All cash offer to be funded from existing cash reserves
==> picture [725 x 270] intentionally omitted <==
9
Murchison Projects
==> picture [741 x 12] intentionally omitted <==
==> picture [329 x 440] intentionally omitted <==
Burnakura - Gabanintha
-
The Burnakura and Gananintha projects are within 20km of each other, approximately 750km NE of Perth and south of Meekatharra
-
Good access from Great Northern Hwy and Meekatharra-Sandstone Road
-
Planned work aimed at early conversion of mineralisation to resources to reserves
10
Burnakura Gold Project - Summary
==> picture [741 x 12] intentionally omitted <==
- 100% interest
• Located 50km south of Meekatharra, WA • 47.5 km2 gold prospective tenements of pre-1994 granted mining leases
Open pit historic production of 216,250 oz (1.8 million tonnes at 3.8 g/t)
Open pit production ceased in 1998 when the gold price fell below A$440 per oz Underground production of 50,637 oz (264,731 tonnes at 5.95 g/t) 160,000 tpa CIL gold plant
Refurbished ninety-person camp, offices and workshops
11
Burnakura Project
==> picture [231 x 174] intentionally omitted <==
==> picture [231 x 174] intentionally omitted <==
==> picture [231 x 174] intentionally omitted <==
==> picture [232 x 175] intentionally omitted <==
==> picture [231 x 174] intentionally omitted <==
==> picture [229 x 172] intentionally omitted <==
12
Burnakura Aerial View
==> picture [40 x 36] intentionally omitted <==
----- Start of picture text -----
13
----- End of picture text -----
==> picture [582 x 400] intentionally omitted <==
Burnakura NOA 7 and 8
==> picture [572 x 334] intentionally omitted <==
Burnakura Authaal
==> picture [709 x 381] intentionally omitted <==
==> picture [141 x 38] intentionally omitted <==
Gabanintha Copper-Gold Project
-
Key prospect - Yagahong
-
North Copper-Gold Deposit
-
Recent exploration success on adjacent tenements at Lady Alma and Copper Hills
==> picture [396 x 386] intentionally omitted <==
16
-
Yagahong North is located just north of the Yagahong open pit
-
Granted mining lease
-
Aim to delineate and quantify a JORC compliant resource.
-
Quality gold and copper drill results beneath and lateral to existing shallow pits
-
Trucking distance to Burnakura Plant for Ore
==> picture [348 x 432] intentionally omitted <==
17
18
==> picture [741 x 13] intentionally omitted <==
==> picture [577 x 437] intentionally omitted <==
19
==> picture [741 x 13] intentionally omitted <==
==> picture [629 x 440] intentionally omitted <==
==> picture [741 x 13] intentionally omitted <==
-
100% Interest
-
Land holding 38km[2 ]
-
12km strike of prospective
sequence
-
All tenements granted prior to introduction of Native Title legislation
-
Advanced multi-metal prospect with over $5 million incurred on past exploration
==> picture [327 x 394] intentionally omitted <==
20
Magnetics
==> picture [552 x 390] intentionally omitted <==
SAM Conductivity
==> picture [552 x 390] intentionally omitted <==
==> picture [741 x 13] intentionally omitted <==
==> picture [419 x 260] intentionally omitted <==
==> picture [311 x 289] intentionally omitted <==
==> picture [355 x 78] intentionally omitted <==
----- Start of picture text -----
Reward Longitudinal Section
----- End of picture text -----
==> picture [294 x 78] intentionally omitted <==
----- Start of picture text -----
Bellbird Longitudinal Section
----- End of picture text -----
23
Jervois
==> picture [652 x 386] intentionally omitted <==
Reward looking east
==> picture [524 x 390] intentionally omitted <==
Reward looking north
==> picture [524 x 390] intentionally omitted <==
Reward looking south
==> picture [691 x 418] intentionally omitted <==
Bellbird looking north
==> picture [724 x 418] intentionally omitted <==
Bellbird looking south
==> picture [724 x 424] intentionally omitted <==
-
Delineate and quantify a JORC compliant resource at Gabanintha and Burnakura
-
Complete feasibility studies at Burnakura and Gabanintha for Open Pit extensions
-
Recommission the Burnakura Plant and possible increase in capacity
-
Complete infill drilling program at Jervois for JORC resource calculation
-
Complete feasibility study at Jervois
==> picture [741 x 250] intentionally omitted <==
----- Start of picture text -----
30
----- End of picture text -----