KGL Announces Feasibility Study Update and
plans to progress to production in 2027
----- End of picture text -----
10 February 2025
The attached announcement contains:
-
Highlights of the Feasibility Study Update and next steps.
-
The Executive Summary of the Jervois Feasibility Study Update.
-
The Jervois Project Ore Reserve Statement prepared by Xenith Consultants.
This announcement is authorised by the KGL Resources Limited Board of Directors.
Cautionary Statement
The Feasibility Study referred to in this announcement has been undertaken to determine the potential viability of development of the Jervois Copper Project. The production target for the Jervois Copper Project is based on (Proved and Probable) Ore Reserves of 86.7% and 13.3% Inferred Mineral Resources.
There is a low level of geological confidence associated with Inferred Mineral Resources and there is no certainty that further exploration work will result in the determination of Indicated Mineral Resources or that the production target will be realised.
The Ore Reserve and Mineral Resource estimates underpinning the production targets were prepared by Competent Persons in accordance with the JORC Code 2012.
The production target and forecast financial information derived from the production target set out in this release (supported by the Feasibility Study Update) are based on the material assumptions outlined in Feasibility Executive Summary.
While KGL Resources considers all the material assumptions to be based on reasonable grounds, there is no certainty that they will prove to be correct or that the range of outcomes indicated by the studies will be achieved.
Given the uncertainties involved, investors should not make any investment decisions based solely on the results of these studies.
Page 1 of 9
==> picture [596 x 172] intentionally omitted <==
----- Start of picture text -----
KGL Announces Feasibility Study Update and
plans to progress to production in 2027
----- End of picture text -----
KGL Resources Limited today announced the results of the Feasibility Study Update (FSU25) and its intention to move ahead with Project financing plans and operational readiness works.
The findings of the Feasibility Study Update confirmed that the Jervois Copper Project is technically robust and financially viable. The project NPV is A$405 million with an attractive capital efficiency of ~A$12,000/t contained copper per annum., and a simple payback of around 3.4 years.
Executive Chairman, Jeff Gerard commented
“The release of the Feasibility Study Update is the foundation to deliver a new mining hub for critical and strategic minerals within the Northern Territory in the eastern Arunta region.
The Jervois Copper Project is a technically feasible, economically and environmentally sound mining operation leveraged to the global copper price. We have optimised the mine plan, updated the capital and operating costs estimates, and de-risked the project. The FSU25 contained copper resource has increased by 8.0% to 510,000[1] tonnes and the proportion of open cut ore increased from 25% to 41% of total ore mined. Proven ore reserves from the open pit are mined and processed through the plant over 4 years. During this time, the operations are able to transition to underground ore feed to the plant.
KGL is well positioned with all necessary approvals, to deliver its high-grade Jervois project into a copper market at a time of a projected chronic global supply shortfall bringing opportunities for jobs and economic development to the Northern Territory, ensuring sustainable operations and delivering long-term value to stakeholders.”
| Highlights | |
|---|---|
| Project Value | |
| • | Net Present Value (NPV8) A$405M (post-tax), NPV8of A$601M (pre-tax)2 |
| • | Internal Rate of Return (IRR) of 24%. |
| • | C1 cost US$1.95/lb (by-product basis, during 7 years of steady state). |
| • | Simple payback 3.4 years based on peak cash drawdown of A$497m (from 1st |
| concentrate). | |
| • | Average operating cashflow A$208 million per annum (steady state). |
| Scale and Opportunity | |
| • | Stage 1 (FSU 25) 10 year mine life lays the foundation for future low cost / accretive |
| growth opportunities based on substantial potential for Resource and Ore Reserve | |
| growth. | |
| Production | |
| • | Commissioning and ramp-up during H1 2027 with steady state throughput capacity from |
| mid-2027. | |
| • | Ore Reserves: Total Proven and Probable Reserves of 14.38 Mt @ 1.77% Cu, |
| containing 265 kt of copper, 9.4 Moz silver and 76.1 koz gold supporting average annual | |
| steady state production: Cu ~30kt pa, Ag ~1,016 koz pa and Au ~8.9 koz pa. | |
| Capital | |
| • | Construction Capital Cost estimate A$362 million. |
1 May 2024 Mineral Resource Estimate adjusted 2 8% Real Discount Rate, after tax
Page 2 of 9
==> picture [596 x 172] intentionally omitted <==
----- Start of picture text -----
KGL Announces Feasibility Study Update and
plans to progress to production in 2027
----- End of picture text -----
| Highlights (cont.) | |
|---|---|
| Contribution | |
| • | Peak employment by KGL and Contractors of up to 450 people during construction and |
| up to 500 people during operations supported by a 300-man camp. | |
| • | NT royalty contribution c.A$220M. |
| Concentrate | Offtake |
| • | An updated offtake contract for copper concentrate, including by-products, is being |
| finalised. | |
| Regulatory Approvals | |
| • | Key approvals in place to allow for the commencement of development and operation. |
| Next Steps | |
| • | Appointment of a financial advisor, assessment of the optimal financing structure of the |
| project and negotiations with potential equity and debt investors. | |
| • | Finalise Project Execution Plan in advance of key appointments and negotiation of |
| significant contracts with Tier 1 contractors. | |
| • | RPM Advisory Services Pty Ltd (RPM) is targeting completion of the Independent |
| Technical Engineers (ITE) Report and Independent Environmental and Social Report | |
| (IESR) acceptable for the purpose of project financing, during H1, 2025. |
Page 3 of 9
==> picture [596 x 172] intentionally omitted <==
----- Start of picture text -----
KGL Announces Feasibility Study Update and
plans to progress to production in 2027
----- End of picture text -----
FSU25: Project Overview
The Jervois Copper Project Feasibility Study Update 2025 (FSU 25) is the result of optimisation works and ongoing project derisking following the maiden Feasibility Study issued at the end of 2022.
The FSU 25 continues to define a robust project with a 10-year life of mine plan.
During the first seven years of the production schedule, post operational ramp up, the project delivers an average of 30 kt per annum of copper in concentrate at an average C1 cost of US$1.95/lb (after by-products) generating average EBITDA of approximately $229M per annum (steady state).
Overall, the Project’s after-tax net present value at a discount rate of 8% has increased from A$241M to A$405M (c.68%). The Project has an attractive capital efficiency of c.A$12,000 per tonne of contained copper per annum[3] , with a simple payback of c.3.4 years from first concentrate.
The Project is based on a high-grade Reserve, 1.77% copper, with silver and gold credits. The Project has an 18-month construction schedule followed by a 6-month plant commissioning and ramp up program to achieve forecast concentrate production during 2027 (subject to completing satisfactory financing arrangements). The Company currently has zero debt.
Initially all ore production will be from conventional contractor managed open cut operations delivering 2Mtpa (ore feed). This is followed by progressively developing underground mines to transition from open pit to full underground feed by mid-2030, as planned open pit ore finishes. The purpose-built, state of the art, concentrator, with a nameplate capacity of 2 million tonne ore feed per annum, is designed to produce 27% copper / byproducts concentrate, that is sold under a Free on Transport (FOT) / ex-site commercial offtake contract.
Detailed technical, environmental and commercial studies indicate the project can be built and operated with low operating costs, manageable technical risks, minimal environmental impact with positive economic and social outcomes.
Project Value & Sensitivity
Based on current market forecasts, the Project is expected to generate an after-tax net present value at a discount rate of 8% of A$405M. KGL believes the Jervois Project is timed to deliver copper into the potential supply deficit where increased commodity / incentive prices will prevail. The FSU 25 does not reflect supply deficit pricing however the upside economics facing the Project, once delivered, are significant.
3 Based on total initial capital cost of A$362M and annual copper production during steady state of 30ktpa.
Page 4 of 9
==> picture [596 x 172] intentionally omitted <==
----- Start of picture text -----
KGL Announces Feasibility Study Update and
plans to progress to production in 2027
----- End of picture text -----
Table 1: Project key sensitivities
| FS 2022 | FSU 25 | Incentive price assumption |
“Bullish price forecast” |
||
|---|---|---|---|---|---|
| Copper Price | US$/lb US$/t |
4.23 9,370 |
4.581 10,094 |
5.90 13,000 |
6.80 15,000 |
| Exchange Rate | A$:US$ | 0.70 | 0.64 | 0.70 | 0.70 |
| NPV 8% (real, before tax) | A$M | 372 | 601 | 992 | 1,413 |
| NPV 8% (real, after tax) | A$M | 241 | 405 | 682 | 978 |
| IRR (before tax) | % | 28% | 30% | 41% | 52% |
| IRR (post tax) | % | 21% | 24% | 33% | 42% |
| Simple Payback Period (1stConc.)2 | Years | 4.2 | 3.4 | 2.7 | 2.1 |
-
Bloomberg Brokers Consensus (avg.) and London Metals Exchange Forecast to 2027 - US$4.58/lb / US$10,100/t
-
1.5 years of construction period before 1[st] concentrate.
Study Outcomes
The key financial metrics for the FSU 2025 and FS 2022 are as follows:
Table 2 Project key financial metrics
| Metric | Unit | FS 2022 | FSU 25 |
|---|---|---|---|
| Life of Mine Net Revenue | A$ billion | $3.67 | $4.44 |
| Life of Mine EBITDA | A$ billion | $1.38 | $1.86 |
| Payable Copper | kt | 267.4 | 255.7 |
| Payable Gold | k oz | 59.1 | 68.5 |
| Payable Silver | M oz | 8,454.5 | 8,497.4 |
| Reserve | MT | 11.73MT @2.10% Cu, 0.29g/t Au & 29.8g/t Ag |
14.38MT @1.77% Cu, 0.26g/t Au & 26.27g/t Ag |
| CU concentrate (LOM) | kdmt | 1,028 | 983 |
| Cu recovery (Sulphide) | % | 92.2 | 92.0 |
| C1 Cost (US$/Ib Cu eq) (steady state) | US$/Ib | $2.22 | $1.95 |
| C1 Cost (US$/lb Cu eq) LOM | US$/lb | $2.35 | $2.19 |
| AISC (US$/lb) (steady state) | US$/lb | $3.13 | $2.86 |
| Average Cu in concentrate production (steady state) |
ktpa | 27 | 30 |
| Construction Capex | A$ million | 298 | 362* |
| Copper Price | US$/lb | 4.23 | 4.58 |
| Gold Price | US$/oz | 1,735 | 2,668 |
| Silver Price | US$/oz | 22.70 | 32.62 |
| FX AU$:US$ | US$ | 0.70 | 0.64 |
Page 5 of 9
==> picture [596 x 172] intentionally omitted <==
----- Start of picture text -----
KGL Announces Feasibility Study Update and
plans to progress to production in 2027
----- End of picture text -----
| Diesel (ex GST and Fuel Tax Credits) | A$/L | 1.30 | 1.30 |
|---|---|---|---|
| Electricity | c/kWh | 24.49 | 29.76 |
| Discount Rate (real) | % | 8% | 8% |
| Net Present Value (pre-tax) | A$ million | $372 | $601 |
| Net Present Value (post-tax) | A$ million | $241 | $405 |
| Internal Rate of Return (pre-tax) | % | 28.5 | 30.4 |
| Internal Rate of Return (post-tax) | % | 20.7 | 24.3 |
*Includes airstrip of $20m. FS2022 has provisions for Drive-In Drive-Out ex-Alice Springs.
On a gross revenue basis, copper contributes approximately 84%, whilst gold and silver by-products contribute circa 6% and 10%, respectively.
Following the ramp up of the plant to design throughput capacity (mid 2027), the average EBITDA is $229 million per annum.
Scale and Opportunity
The FSU 25 10-year mine life lays the foundation for low cost / accretive growth. Substantial potential exists for Resource and Ore Reserve growth, leading to increased utilisation of the installed plant capacity and mine life extension. The Jervois tenements remain under explored with recent drilling focused on infill drilling and extending the resource and knowledge, at depth, for the current lodes. This work has consistently demonstrated high grade copper intersects in these areas. Structural geology and geophysical interpretations of existing exploration information are providing key targets for future exploration programs.
Key improvements since FS November 22
In the period following the release of FS22, KGL has been able to embed numerous improvements including:
-
An updated 2024 Mineral Resource and Ore Reserve estimate.
-
Improved Resource confidence, for open cut mining, over the first 4 years of the project.
-
Increased open-cut mining tonnages in first 3 years.
-
Reduced proportion of Inferred Resources in the mine plan.
-
Increased the proportion of lower risk open cut mineable reserves.
-
Increased open cut productivity by the selection of larger capacity mining fleet and obtaining an approval for a shorter haul to Reward south dump.
-
Increased Concentrator plant nameplate capacity from 1.6Mtpa to 2.0Mtpa.
-
Updated the proportion of primary mined ore and stoped ore.
-
Increased Mineral Resource tonnages at depth.
-
Updated Infrastructure and civil works scopes including the addition of a dedicated airstrip.
Contribution
The Jervois Project (both KGL and Contractors) will provide peak employment of 450 people during - construction and up to 500 people employed during operations supported by a 300 man camp. The NT royalty contribution is c.A$220M.
Concentrate Offtake and Income Security
An updated contract for the offtake of up to 1Mt of copper concentrate is currently being re-negotiated. The payment terms of the concentrate will be Free on Transport (FOT). Provision for advance payments is included in the contract.
Page 6 of 9
==> picture [596 x 172] intentionally omitted <==
----- Start of picture text -----
KGL Announces Feasibility Study Update and
plans to progress to production in 2027
----- End of picture text -----
By-product credits for gold and silver represent approximately 16% of the gross revenue. The offtake contract also includes revenue adjustments for payable metals, TC/RC’s, contaminant penalties and freight charges.
The only penalty parameter triggered is for Bismuth which represents less than 1% of the gross revenue. There are no rejection criteria under the contract.
Regulatory Approvals
Mining tenements remain in good stead and key approvals are in place to allow for the commencement of development and operation. These include, but not limited to, Jervois Project ILUA and clearance, Authorisation 1061-1, Mining Management Plan and various water licenses and permits.
Sustainability and Environmental Plans
KGL is committed to sustainable mining practices, emphasising environmental stewardship and community engagement.
-
Renewable Energy: At least 60% of power needs are planned to be met by a dedicated hybrid power station that incorporates solar, wind and battery storage to reduce on site greenhouse gas emissions.
-
Tailings Management: Engineered HDPE-lined storage facility with staged embankments ensures longterm environmental containment.
-
Water Management: Water recycling is designed for process water to maximise reuse and minimise raw water consumption and cost.
-
Closure and Rehabilitation: Progressive reclamation plans align with NT Government requirements, ensuring minimal ecological disruption and restoration to the pre-existing or improved land use / capability.
Next Steps & Additional Project Optimisation Opportunities
A Phase 1 Independent Technical Review has been completed by RPM showing no red flag / critical issues. Lower-level risk issues (not Red Flags) have been included in the Company Risk Register with risk mitigations initiatives scheduled accordingly.
RPM have been engaged to complete Phase 2 that involves an Independent Technical Engineers (ITE) Report and Independent Environmental and Social Report (IESR) suitable for the purpose of project financing. This is targeted to be completed during H1, 2025.
KGL will appoint a financial advisor to assist with assessing the optimal capital structure for the Jervois project and negotiations with equity and debt investors.
Priority activities to advance the Project include:
-
Expand the owners / project delivery teams consistent with the Project Execution Plan.
-
Finalise water, power, and services agreements.
-
Finalise contracts for site preparation civil works, plant EPC and open pit operations.
-
Progress funding agreements.
Future optimisation opportunities, separate to Project delivery, include
- Capital reduction: Scope exists to further rationalise and reduce elements of the construction capital in the areas of civil works, village construction and the airstrip. This will be updated as part of the enabling / early works activities.
Page 7 of 9
==> picture [596 x 172] intentionally omitted <==
----- Start of picture text -----
KGL Announces Feasibility Study Update and
plans to progress to production in 2027
----- End of picture text -----
-
Construction schedule: Enabling / Early works, prior to a Financial Investment Decision (FID) is being considered to reduce the project delivery timeline risk for selected critical path activities which may also provide increased project time contingency.
-
Resource Expansion: Additional open pit resources have been identified that can be brought into the mining schedule to improve the open pit utilisation of equipment and improve the access and development cost of selected underground areas at Bellbird and Reward.
-
Polymetallic Recovery: Assessment of lead and zinc resources is a significant study that will be progressed during project construction and operation to further extend the life of the project and the incremental utilisation the installed capital and operating equipment to enhance project economics.
Timeline
Subject to finance, delivery of first concentrate is targeted H1 2027. Steady-state operations is expected H2 2027 delivering an average 30kt per annum of contained copper in a 27% saleable copper concentrate per annum.
==> picture [479 x 260] intentionally omitted <==
Page 8 of 9
==> picture [596 x 172] intentionally omitted <==
----- Start of picture text -----
KGL Announces Feasibility Study Update and
plans to progress to production in 2027
----- End of picture text -----
Market Timing
Wood Mackenzie reported in a recent article (August 2024) that “The world cannot decarbonise without copper, a key component of electrification. Amid efforts to secure minerals for the energy transition and achieve climate goals, demand is set to surge. We estimate that demand for copper will grow by 75% to 56 million tonnes (Mt) by 2050. Meeting this demand will require major investment.”
Ongoing decarbonisation via renewable generation, grid expansion, electric vehicles, technology advancement (AI and data centres) and military demand, support the demand growth whilst headwinds continue to impact the supply side that creates the expected supply / demand gap.
Macro-economic impact such as inflation and supply chain disruptions that were occurring, at the time the 2022 feasibility study was released, have abated.
A report titled Copper Price 2024-End Review (Dec 30, 2024), from Investing News Network concluded; “Copper demand is still constrained by weakness in the Chinese economy, particularly in its housing sector, which is an important driver of global demand for the metal. Ultimately, in the longer term, copper supply will be lacking from new projects and expanded production to meet demand. The base metal is expected enter a supply deficit over the next few years.”
In a recent interview at the Future Minerals Forum in Riyadh (FMF25), Codelco Chairman Maximo Pacheco expressed optimism about the future of copper, noting its critical role in the global energy transition. "If you believe that the world of the future will be more electrical, the best conductor of electricity is copper," he stated.
The increasing demand for copper will drive prices higher, he added. “The world needs more copper and it's obvious to me that if there is a strong demand of copper, that means that the world will pay for it.”
Page 9 of 9
Jervois Copper Project Feasibility Study Update
==> picture [64 x 43] intentionally omitted <==
1 EXECUTIVE SUMMARY
The Jervois Copper Project (the Project ) is in the Northern Territory ( NT ) of Australia approximately 380km by road, east-north-east of Alice Springs, within existing Mineral Leases, on the Jervois Pastoral Lease owned by Jervois Pastoral Company Pty Ltd (a non-KGL Resources Limited ( KGL ) related entity). The groundwater borefield related Mineral Lease is located around 20km from the project, on the approval of Lucy Creek Station owned by the Lucy Creek Pastoral Company, (also a non-KGL entity). The project is polymetallic (copper, silver, gold) that is primarily leveraged to the price of copper and AUD: USD exchange rate. Additional potential by-products including lead, zinc and other payable metals have not been considered in the project.
The Project Feasibility Study Update January 2025 ( FSU 2025 ) has been prepared by KGL with inputs and support of consultants, suppliers and contractors. RPM Advisory Services Pty Ltd has completed the Phase 1 Independent Technical Review with no critical / red flag issues identified. Phase 2 of the review will entail an Independent Technical Engineers report and Independent Environmental and Social Report for the purposes of financing arrangement. This is expected to be completed during H1 2025. The key financial metrics for the FSU 2025 are as follows:
Table 1-1: Project key financial metrics
| Metric | Unit | Value |
|---|---|---|
| Copper Price* | US$/lb | $4.58 |
| Gold Price* | US$/oz | $2,668 |
| Silver Price* | US$/oz | $32.62 |
| Exchange Rate | A$:US$ | $0.64 |
| Discount Rate (real) | % | 8% |
| Net Present Value (pre-tax) | A$ million | $601 |
| Net Present Value (post-tax) | A$ million | $405 |
| Internal Rate of Return (pre-tax) | % | 30.4% |
| Internal Rate of Return (post-tax) | % | 24.3% |
| Project Payback peak funding (from 1st concentrate) | Years | 3.4 |
| Life of Mine | Years | 10 |
| Life of Mine Ore | kt | 16,591 |
| Average Copper per annum (steady state) | ktpa | 30 |
| Process Plant nameplate capacity | Mtpa | 2.0 |
| Life of Mine Net Revenue | A$ billion | $4.437 |
| Life of Mine EBITDA | A$ billion | $1.858 |
| Life of mine free cashflow (pre-tax) | A$ billion | $1.183 |
| Life of mine free cashflow (post-tax) | A$ million | $873 |
| C1 Cost (US$/Ib Cu eq) (steady state) | US$/Ib | $1.95 |
| Construction Capital Cost estimate | A$ million | $362 |
| Peak Funding including Development Opex | A$ million | $497 |
Source: * Bloomberg Consensus – Oct/Dec 2024
Page 1
KGL RESOURCES LIMITED
Jervois Copper Project Feasibility Study Update
==> picture [64 x 43] intentionally omitted <==
On a gross revenue basis, copper contribute approximately 84%, whilst gold and silver by-products contribute circa 6% and 10%, respectively.
The Feasibility Study Update with an NPV of circa $405m demonstrated that the Jervois Copper Project is technically and financially viable, and a robust project notwithstanding the normal macroeconomic impacts from exchange rate, commodity price and inflation.
The feasibility study update has been estimated to a Class 4 estimate category (AusIMM guidelines) to a level of definition and accuracy in the range of +/-15% basis Q4 2024.
1.1 Project overview
Exploration in the Jervois Range first commenced in 1929 following discovery of base metals in the area. Since that time systematic exploration and small-scale mining has occurred; this included the construction of a concentrator treatment plant, mining facilities, substantial mining camp/township and associated services in the 1980s.
KGL acquired the project in 2011. The project leases are owned by Jinka Minerals Limited, a 100% owned subsidiary of KGL and the project will be operated by Jervois Operations Pty Ltd, also a 100% owned subsidiary of KGL. KGL completed a feasibility study (FS) for the project in November 2022, with exploration continuing throughout the subsequent development of the FSU 2025 during 2023 and 2024.
The objective of the FSU 2025 is to demonstrate viability of project operations. Development has been targeted for the second half of this decade, to coincide with an undersupply of copper later in the decade being forecast by independent market analysts.
KGL has prepared this FSU 2025 recognising and, where possible, mitigating the negative effects of external factors via a lower risk mine development sequence that reduces project delivery complexity, project capital and initial operating expenditure.
Project development is scheduled over two years, covering infrastructure and process plant development (18 months) followed by plant commissioning and production ramp-up during the final six months of the development schedule.
Open-cut operations are the primary ore source for the first three years of the project life. This reduces up front mine development and mining costs, simplifies operations during plant commissioning and reduces pre-production capital expenditure. Underground operations are progressively scheduled to deliver ore production to sustain process plant feed as open-cut operations decline. This mine development sequence delays higher grade copper in the underground reserves until later in the mine life but, more importantly, results in lower project execution complexity.
Page 2
KGL RESOURCES LIMITED
Jervois Copper Project Feasibility Study Update
==> picture [64 x 43] intentionally omitted <==
The KGL business model is based on a fully contracted operational model for both project development and ongoing operations. KGL will maintain a lean site based organisational structure with a contract management focus. KGL as the contract owner will maintain overall responsibility for safety and environmental compliance and will maintain control over budget planning and quality assurance of the copper concentrate.
KGL expects to produce the best project outcomes by engaging contractors with existing capability and capacity to deliver in a resource constrained and low unemployment market to reduce project execution risk.
All major operational components, such as mining, processing and camp management, will be contracted to proven service providers with demonstrated capability and capacity for safety and environmental management, operations and maintenance. These contracts will also include responsibility for maintenance related activities. The intent is to engage contractors and leverage their existing supplier relationships and draw on their internal skills capability. KGL will take an auditing and oversight role of the selected contractors.
1.2 Key project features
The project’s key features are as follows in Table 1-2.
Table 1-2: Jervois Copper Project key technical features
| Project Area | Project Element | Detail |
|---|---|---|
| Mining | Resource | 4.40 Mt Measured @ 1.90% Cu, 32.8 g/t Ag & 0.30 g/t Au 13.24 Mt Indicated @ 1.95% Cu, 29.4 g/t Ag & 0.28 g/t Au 11.31 Mt Inferred @ 1.48% Cu, 16.4g/t Ag& 0.14g/t Au |
| Mining Areas | Open-cuts – Reward & Bellbird Undergrounds – Rockface, Reward / Marshall, & Bellbird |
|
| Reserve | 4.19 Mt Proven @ 1.79% Cu, 31.03 g/t Ag & 0.29 g/t Au 10.19 Mt Probable @ 1.76% Cu, 26.27g/t Ag& 0.25g/t Au |
|
| Open-Cut Mining | Conventional open-cut drill and blast, load and haul StrippingRatio of 11.2 waste bcm / tonne of OP ore mined |
|
| Underground Mining | Underground decline access, longhole stope mining with selected cement rockfill, secondary access via ventilation rises for each underground mine 14 months of development prior to ore stope production Underground operations for 6.8years |
|
| Life of Mine(“LOM”) | 10years(Mining) | |
| Ore Mined (variance from reserves is inferred resource category) |
Bellbird OP (Transition & Oxide) 487kt, Cu 2.11% Bellbird OP (Fresh) 1,503kt, Cu 1.6% Reward OP (Transition & Oxide) 426kt, Cu 1.98% Reward OP (Fresh) 4,456kt, Cu 1.44% Bellbird UG 1,380kt, Cu 1.59% Reward UG 3,164kt, Cu 1.86% Rockface UG 3,346kt, Cu 2.53% Marshall UG 1,827kt, Cu 1.19% TOTAL 16,589kt, Cu 1.77%(average) |
Page 3
KGL RESOURCES LIMITED
Jervois Copper Project Feasibility Study Update
==> picture [64 x 43] intentionally omitted <==
| Project Area | Project Element | Detail |
|---|---|---|
| Processing | Flowsheet | Process plant nameplate capacity 2.0Mtpa ore feed Process elements include ore crushing, grinding to 120um, two stage froth flotation with secondary grind to 38um Concentrate and tailingdewateringand storage |
| Recoveries(LOM) | 92.0% Cu, 55.3% Au, 66.0% Ag (excludes transition & oxide) | |
| Metal Produced (LOM) | 983 kdmt Concentrate, Steady state 30kt Cu contained annually |
|
| Plant Operations | 10 years from first mill feed Q1 to Q2 2027: Plant commissioning / ramp up Q3 2027 to Q2 2035: Steady state mill feed @ 2.0Mtpa (OP) or 1.6Mtpa (UG) Q3 2035 to Q4 2036: Rampdown |
|
| Copper Production per annum (pa) |
Total production: 266 kt Cu, 9,442 Moz Ag, 76.1 koz Au Average steady state production: Cu ~29.4 kt pa, Ag~1,005 kozpa and Au ~8.4 kozpa |
|
| Average Concentrate Grade (dry concentrate basis) |
~27% copper in concentrate By-products: 299g/t Ag and 2.41g/t Au |
|
| Concentrate Production Steady State (12% moisture in wmt) |
Average production in 2028-2035: ~111,000 dmt | |
| Operations & Maintenance |
Mining & Processing | Contractors used for open-cut mining, underground mining andprocessplant operations |
| Tailings | Tailings Disposal | Conventional thickened tailings |
| Tailings Storage Facility |
Single cell facility with water recycling to process Staged design(wall raises)usingmine waste rock |
|
| Infrastructure | Site Access | Plenty Highway, Lucy Creek Station Road and Site Access Road |
| Power | 16MW Power Purchase Agreement basis Based on a hybrid power generation facility (solar PV, wind, batteryand dieselgeneration) |
|
| Water | 1,594MLpa of groundwater supply available from ML32277, ~20km north of the mine and ML30182, and 87MLpa from the Jervois Dam within ML30180. Supply exceeds requirements by~25%. |
|
| Camp | 300 room campbuilt & operated bycontractors | |
| Airstrip | New 100-seat-jet capable airstrip adjacent the accommodation facility. Owned and operated byKGL. |
|
| Product | Concentrate Transport & Refining |
Concentrate to be sold Free on Transport (FOT / ex site) to an offtake buyer |
Page 4
KGL RESOURCES LIMITED
Jervois Copper Project Feasibility Study Update
==> picture [64 x 43] intentionally omitted <==
1.3 Copper market forecasts
As the clean energy transition accelerates, cumulative demand for copper is expected to grow substantially. Most nations have committed to Net-Zero Emissions targets. CO2 emissions need to fall by about 45% from 2010 levels by 2030 to reach net zero by 2050
Wood Mackenzie analysts expect copper demand to grow by around 75% to 2050 from 30.4 Mt (2021) to 56 Mt a year by 2050.[1]
Global copper demand is expected to accelerate for the period 2021-2035 to grow at 2.6% annually or roughly 1 Mt copper demand growth per year compared with a 1.9% CAGR over the past 15 years.
Surging demand is being driven by the simultaneous adoption of copper-intensive technologies, such as electric vehicles (EVs), renewable energy systems, grid investments, and data centres, alongside continued economic development in emerging markets.
The FSU 2025 has adopted the December 2024 spot price of US$4.58/lb for a contemporaneous base line which is consistent with the London Metal Exchange (LME) range which has an average official copper contracts price of US$10,100 Mt (US$4.58/lb) to 2027 (1 October 2024). Gold and silver are also based on contemporaneous price and are below the Nymex forward pricing. Below are the adopted pricing.
Table 1-3: Payable metal prices
| Metal | Price |
|---|---|
| Copper | US$4.58/lb |
| Gold | US$2,668/oz |
| Silver | US$32.62/oz |
1.4 Revenue
The Jervois project will produce c.16.6Mt of ore from 4 mining areas, that have been further categorised into OC oxide/ transition, OC Fresh and UG, for the life of mine. They are as follows.
Table 1-4: Mining schedule
| Mine | Ore Kt | Average Grade % |
|---|---|---|
| Bellbird OP(Transition & Oxide) | 487 | 2.11% |
| Bellbird OP(Fresh) | 1,503 | 1.60% |
| Reward OP(Transition & Oxide) | 426 | 1.98% |
| Reward OP(Fresh) | 4,456 | 1.44% |
| Bellbird UG | 1,380 | 1.59% |
| Reward UG | 3,164 | 1.86% |
| Rockface UG | 3,346 | 2.53% |
| Marshall UG | 1,827 | 1.19% |
| Total | 16,589 | 1.77% |
1 Securing copper supply: no China, no energy transition. August 2024, Wood MacKenzie.
Page 5
KGL RESOURCES LIMITED
Jervois Copper Project Feasibility Study Update
==> picture [64 x 43] intentionally omitted <==
The mining profile and corresponding grade is depicted as follows.
==> picture [483 x 291] intentionally omitted <==
Figure 1-1: Monthly ore mined and Cu Grade
Processing onsite yields c.983 kdmt of copper concentrate at 27% grade.
Based on a production of 266kt Cu, 76.1koz Au and 9442Moz Ag, the gross metal payable is as follows.
Table 1-5: Project metal revenues
| Sales Revenue | Price(US$) | A$m |
|---|---|---|
| Copper | US$4.58/lb | $4,189 |
| Gold | US$2,668/oz | $317 |
| Silver | US$32.62/oz | $481 |
| Gross Metal Payable | $4,987 | |
| Net Revenue | $4,437 |
Net revenue after bismuth deductions of $44m at 0.12% threshold with maximum at 0.75% (no uranium or flourine penalties as they are below the threshold of 0.01% and 0.04% respectively and can be managed via blending), treatment charges and freight amounts to $4,437m with by-product credits of $713m.
Page 6
KGL RESOURCES LIMITED
Jervois Copper Project Feasibility Study Update
==> picture [64 x 43] intentionally omitted <==
The net revenue of $4,437m over the life of mine is depicted as follow.
==> picture [500 x 272] intentionally omitted <==
Figure 1-2: Net Revenue LOM
1.5 Capital and operating cost estimate
The capital cost in the FSU 2025 can be segregated into 3 categories.
Table 1-6: Project capital
| Category | $m |
|---|---|
| Construction Capex | $362 |
| Sustaining Capex | $38 |
| Underground Mining Capex | $272 |
Project construction capital of $362m together with pre-production/development mining opex, rehabilitation bond and working capital of c.$136m will be funded via a combination of term and working capital debt. Total funding requirement amounts to $498m peaking during Q1 2027.
The project will be self-contained for water supply and power generation. Consumables will be delivered to site via road and concentrate product will be despatched by road to Mt Isa.
Peak employment by KGL and Contractors of up to 450 people during construction and up to 500 people during operations is supported by a 300-man camp. Operational personnel will fly-in fly-out between the project and Brisbane commercial airport via direct jet service charter flights. Brisbane was identified as an appropriate source of personnel for the project by major contractors during discussions contributing to this FSU.
Page 7
KGL RESOURCES LIMITED
Jervois Copper Project Feasibility Study Update
==> picture [64 x 43] intentionally omitted <==
KGL has compiled the cost estimate using inputs from a range of engineering consultants, equipment providers and mining contractors. Significant portions of the study included mining related contributions from Xenith Consulting Pty Ltd ( Xenith ) and a tier one mining group. Sedgman Pty Ltd ( Sedgman ) provided process plant costs.
The FSU 2025 has been estimated to a level of definition to AusIMM Class 4 category estimate with an accuracy of +/-15% based on Q3 2024 costs.
Engineering design works and drawings undertaken to date for the process plant, infrastructure and tailings storage facility have provided sufficient detail to estimate material volumes, labour hours and EPC costs. All equipment and materials have been quoted for the project or estimated by Sedgman, and other contractors/consultants based on recently completed projects.
The contingency estimate considers and allows for, rising unit prices for materials and labour resulting from global and domestic inflation/escalation. The contingency was determined via a risk assessment to provide sufficient funding for risks that may eventuate during construction. An allowance of $32M (9%) has been provided for contingent events.
The project construction capital of $362m includes $330m of construction capital and $32m of contingency shown in Table 1-7.
Table 1-7: Project construction capital
| Construction Capital | $m |
|---|---|
| Site Preparation | $ 77 |
| Process Plant | $ 178 |
| Infrastructure(includes camp) | $ 42 |
| Other(includesproject team, flights, fuel, IT) | $ 33 |
| Contingency | $ 32 |
| Total | $ 362 |
The capital cost estimate for the project construction includes certain early works sunk costs of c.$35m up to 30 June 2025 and working capital. These costs up to 30 June 2025 have been included in the calculation of the project NPV (FID 1 July 2025 basis).
A significant portion of the construction cost can be attributed to process plant costs estimated at c.$178m (includes $3.7m capital spares). More than 90% of the process plant costs is denominated in AU$, with minimal FX exposure. Final negotiations for the process plant construction contract will be completed during H1 2025. The contractor has provided an indicative reduction in cost subject to the commercial model. The expected cost reduction, should it be realised, will be allocated to a cost overrun account and is therefore included in the FSU 2025.
The capital cost estimate for the process plant includes extensive engineering design works and drawings undertaken to date for the plant, infrastructure and tailings storage facility. These have provided sufficient detail for material volumes, labour hours and EPC costs.
Page 8
KGL RESOURCES LIMITED
Jervois Copper Project Feasibility Study Update
==> picture [64 x 43] intentionally omitted <==
The second largest segment of construction capital relates to site preparation cost of $77m. The details of the site preparation cost are as follows.
Table 1-8: Site preparation capital
| Site Preparation | $m |
|---|---|
| Tailing storage facility/drainage | $27 |
| Water management (pipeline, groundwater bores) | $18 |
| Airstrip | $20 |
| Haul road, creek diversion, earth platforms | $11 |
| Other | $1 |
| Total | $77 |
The third largest segment is the infrastructure capital of $42m which is mainly camp supply and installation costs of $34.4m with the balance mainly for the administration office and HV reticulation. Camp costs are based on an upfront capital purchase by KGL, with construction, ongoing maintenance and operations performed by specialist contractors.
A hybrid power generation facility is to be contracted via a Power Purchase Agreement (no capex allowance), where capital costs are recovered through an ‘installed capacity’ monthly fee and an electricity tariff on a $/kWh basis. Electricity reticulation across the project has been included in the infrastructure cost estimate.
Rehabilitation bond of c.$15m is included as operating cost in the FSU 2025.
The last main category is the mining capex which is comprised of the following.
Table 1-9: Mining capital
| Mining Capex | A$m |
|---|---|
| Open Pit development (per contractor’s estimate) | $40 |
| Underground development (per contractor’s estimate) | $217 |
| Vent fan | $12 |
| Underground portal & boxcut | $3 |
| Total | $272 |
The above does not include sustaining capex of $24m for expansion of the tailings storage facility capacity and $13m minor capital items. These have been included in the project financial model as sustaining capex.
For operating costs estimate, tier one mining contractors have been engaged to provide estimates on open pit mining, underground mining and processing. These cost estimates are based on the mining schedule prepared by Xenith. The cost estimates include the supply of mining equipment, operating labour, and maintenance. Owners’ cost estimates are built up from a combination of quotes and escalation of 2022 cost on first-principle basis.
Page 9
KGL RESOURCES LIMITED
Jervois Copper Project Feasibility Study Update
==> picture [64 x 43] intentionally omitted <==
The total operating cost based on the estimates are as follows.
Table 1-10 Project operating cost
| Operating Cost | A$m |
|---|---|
| Mining (OP) (per contractor’s estimate) | $357 |
| Mining (UG) (per contractor’s estimate) | $1,195 |
| Processing (per contractor’s estimate) | $495 |
| Camp (per contractor’s estimate) | $78 |
| Travel & charter (unit rates assessed against supplier’s estimate) | $48 |
| Site Admin | $94 |
| Head Office | $47 |
| Environmental | $15 |
| Total | $2,329 |
Page 10
KGL RESOURCES LIMITED
Jervois Copper Project Feasibility Study Update
==> picture [64 x 43] intentionally omitted <==
Total project capex and operating costs graph below shows the initial ramp up of costs primarily associated with open-cut mining and plant construction and throughput ramp up through FY2026 - FY2027. The open-cut mining is completed in 2029, with remaining stockpiled sulphide ore processed until January 2030. Stockpiled oxide ore from open-cut is then campaigned through the process plant until June 2030. From Q1 2030 all sulphide ore production is from higher unit cost underground operations.
==> picture [436 x 245] intentionally omitted <==
Figure 1-3: Total capex & site operating costs vs Ore mined
Operating cost inputs have been primarily sourced from external parties as at Q3 2024. Where costs have been provided prior to Q3 2024, KGL has applied appropriate escalation, for input into the financial model.
A diesel price of $1.30 per litre (ex-GST and rebates are applied) has been applied to diesel usage, with consumption rates estimated by third party contractors for mining and the process plant.
KGL has estimated site support services, owners’ team and head office costs based on current labour rates, corporate expenses adjusted for the project construction and operating requirements.
Operating cost estimate includes a bond for mine closure and final rehabilitation based on an agreement with the NT Government (approved project MMP, 2024), payment of a sequenced rehabilitation bond (confidential) is based on ground disturbance and related site activities.
Offsite costs include royalties and compensation payments. Royalties payable have been calculated as per the Minerals Royalty Act 2024 (MRA24) and compensation payable as per KGL’s ILUA obligations (commercial in confidence). The economic effects of any compensation agreements have been included; this comprises initial and annual payments, annual administrative costs and shut down payments. The terms of the compensation agreements remain confidential.
Tax payable has been calculated as per the Income Tax Assessment Act 1997 (Cth) at the rate of 30% of taxable income, and uses KGL’s estimated tax losses incurred up to the date of production.
Page 11
KGL RESOURCES LIMITED
Jervois Copper Project Feasibility Study Update
==> picture [64 x 43] intentionally omitted <==
Table 1-11 summarises the operating cost key metrics.
Table 1-11: Average operating costs over the life of mine
| LoM operating costs (Q3 2025- Q2 2034) |
A$ / tonne ore |
US$ / lb |
|---|---|---|
| payable Cu | ||
| Total operating cost | 89.95 | 2.65 |
| Smelting | 11.96 | 0.35 |
| By-product credit | (27.53) | (0.81) |
| Total C1 costs | 74.38 | 2.19 |
| Tax | 13.74 | 0.40 |
| Royalties | 9.72 | 0.29 |
| Depreciation and amortisation | 25.97 | 0.76 |
| Total C3 costs (AISC) | 123.81 | 3.64 |
Note: Steady state operating conditions (2.0Mtpa or 1.6Mtpa average plant feed) occur between Q3 2027 and Q2 2035. Outside this period the plant is either ramping to full capacity following commissioning or ramping down toward the end of the scheduled life.
1.6 Financial analysis
The economic analysis is based on a valuation date of 1 July 2025. Net Present Value ( NPV ) is calculated based on discounted cashflow (real, after tax) of 8% using flat real metal prices for copper, silver and gold, and A$:US$ exchange rate. Project capital payback is calculated from first concentrate production.
The project generates an NPV of $405m and EBITDA of c.$229m per annum (steady state). Average mining and sustaining capital over this same period is $30m per annum. Free cashflow averages $112m per annum.
Peak funding of A$497m occurs in Q1 2027 post plant commissioning, during ramp-up. Positive operating and free cashflows are delivered from Q2 2027.
==> picture [483 x 248] intentionally omitted <==
Figure 1-4: Free cashflow Vs project costs
Page 12
KGL RESOURCES LIMITED
Jervois Copper Project Feasibility Study Update
==> picture [64 x 43] intentionally omitted <==
The project is cashflow positive in the third month of mill feed.
==> picture [447 x 232] intentionally omitted <==
Figure 1-5: Project annual (financial year) free cash flow and revenue
Sensitivity analysis
==> picture [25 x 10] intentionally omitted <==
The sensitivity analyses in Figure 1-6 and Figure 1-7 show that the Project is most sensitive to copper price and the foreign exchange rate. A 5% strengthening of the US$ resulting in AU$ at c.0.60 (from 0.64) will increase the NPV by c.$100m (from $405m to $505m). Likewise, a 5% increase in copper price from US$4.58/lb to US$4.81/lb will result in an increase of NPV of c.$84m (from $405m to $489m). A 5% decrease of copper price to US$4.35/lb will result in a NPV of c.$319m (from $405m to $319m).
==> picture [447 x 234] intentionally omitted <==
Figure 1-6: Project NPV Sensitivity
Page 13
KGL RESOURCES LIMITED
Jervois Copper Project Feasibility Study Update
==> picture [64 x 43] intentionally omitted <==
==> picture [433 x 227] intentionally omitted <==
Figure 1-7: Project IRR sensitivity
The sensitivity of gold and silver by-product US$ price has a limited impact to the NPV and IRR than copper price although gold and silver contribute c.16% to gross revenue. Over the life of the project, total by-products equate to about 47 kt Cu equivalent for payable gold and silver combined. A 5% change in gold and silver price respectively results in an incremental NPV impact of $15 million.
Table 1-12: Precious metal prices - gold
| 2024 | 2025 | 2026 | 2027 | 2028 | |
|---|---|---|---|---|---|
| Gold(US$/oz) (Nymex Contracts) | $2,736 | $2,827 | $2,950 | $3,059 | $3,080 |
Source: Nymex Average Contracts 27 October 2024.
The financial model adopts a spot price in December 2024 of US$2,668/oz (more conservative compared to the Nymex forecast) as base case gold price. Nymex contracts prices as at 27 October 2024 are compared for sensitivity and indicates there is further upside in the gold price in the long term. Spot price as at 22[nd] January 2025 is US$2,758/oz.
Table 1-13: Precious metal prices – silver
| 2024 | 2025 | 2026 | 2027 | 2028 | |
|---|---|---|---|---|---|
| Silver(US$/oz) (Nymex Contracts) | $33.64 | $34.58 | $36.12 | $37.08 | $37.53 |
Source: Nymex Average Contracts 27 October 2024.
Similar to gold, the financial model adopts a silver spot price in December 2024 of US$32.62/oz (more conservative compared to the Nymex forward pricing).
Page 14
KGL RESOURCES LIMITED
Jervois Copper Project Feasibility Study Update
==> picture [64 x 43] intentionally omitted <==
Market demand supply commentators (see section 1.3 Copper Market Forecasts) are suggesting price expectations are being skewed in favour of higher US$ copper prices by between 40 – 60% above the consensus view.
The project is also more sensitive to operating costs than start-up capital costs. Less sensitive are the by-product US$ price assumptions.
1.7 Project location and access
The project is in the Northern Territory ( NT ) of Australia approximately 380km by road eastnorth-east of Alice Springs (see Figure 1-8). The project is on existing mineral leases located on the Jervois Station.
From the Project site, a 3.2km road will be upgraded to connect the project area to Lucy Creek Station Access Road (Road 194) which joins the Plenty Highway 16km to the south, see Figure 1-8. The Plenty Highway is mostly sealed toward the Stuart Highway 290km to the west of the project. The Stuart Highway extends between Adelaide, through Alice Springs to Darwin. Government funding to continue sealing the Outback Way, which includes the Plenty Highway near the project site, has been planned for 2025.
Major highways intersect the Stuart Highway giving access in and out of the NT via the Barkly Highway into Queensland and the Victoria Highway into Western Australia. These highways are all weather and have regularly spaced fuelling stations for commercial transport. Most materials imported to the project will come from Darwin via the Stuart and Plenty Highways.
The project area has a defined, brief wet season generally between November and April which can result in short delays to road access. The expected impact to site access is less than seven days a year based on historical knowledge.
Page 15
KGL RESOURCES LIMITED
Jervois Copper Project Feasibility Study Update
==> picture [64 x 43] intentionally omitted <==
==> picture [416 x 397] intentionally omitted <==
Figure 1-8: Project location
1.8 Project infrastructure
The project is modelled to be a remote stand-alone facility that will comprise all components required for operations producing copper concentrate. Major components include accommodation, power supply/reticulation, water supply, processing plant, tailings storage facility, warehousing, workshops, laboratory, fuel storage and explosives magazine. Access to the project is via NT public roads and the (newly) proposed Jervois airstrip, adjacent the accommodation village).
Infrastructure construction and mining will be undertaken within the existing Mineral Leases. Sustainable groundwater supplies have been identified from bores to be established as part of capital early works, on the granted bore field Mineral Lease 20km north of the process plant on the Lucy Creek Pastoral Station. Approval to install and operate a pipeline along Road 194 has been received from the NT Government.
Early construction works will consist of access road formation, accommodation village (Stage 1) upgrading communication facilities, establishment of pumps and a water pipeline from the Lucy Creek bore field. The mine infrastructure area (MIA) that includes the processing plant, power station, fuel storage and other supporting facilities are adjacent to the Reward pit. The solar array and camp accommodation are located to the south east of the MIA.
Page 16
KGL RESOURCES LIMITED
Jervois Copper Project Feasibility Study Update
==> picture [65 x 43] intentionally omitted <==
The proposed project layout is shown below.
==> picture [561 x 393] intentionally omitted <==
Figure 1-9: Project layout and infrastructure
Page 17
KGL RESOURCES LIMITED
Jervois Copper Project Feasibility Study Update
==> picture [64 x 43] intentionally omitted <==
1.9 Geology and mineralisation
The project lies within the eastern part of the Arunta Region, which forms part of the North Australian Craton. Copper mineralisation at the project is hosted by a lower-to-middle amphibolite grade metasedimentary sequence of the Bonya Metamorphics.
The project area lies on the south-eastern edge of the Jervois Range. The proposed mining activity is focused along the range of low hills and rises running approximately north to south through the middle of the project area, forming a J-shape.
This distinctive J-shape of the Bonya Schist outcrop has been interpreted as the result of re-folding of pre-existing folds, and as a drag feature to a regional Jervois fault that lies to the west. The more resistant lithologies feature as a series of hills that prominently define the J-structure on aerial photographs and satellite images.
The mineralisation style is generally stratabound and contained within steeply dipping lenticular bodies (lodes). The mineralised sequence has a strike length of some 12km and a stratigraphic thickness up to about 600m.
Copper-gold-silver mineralisation mostly occurs as massive to semi-massive layers of sulphides. Sulphides also occur in associated quartz veins and as thin interlayers in meta-mudstone and calcsilicates.
1.10 Mineral Resource
The Mineral Resources considered for development for the project comprise the Reward, Rockface and Bellbird deposits.
The total Mineral Resource estimate used in the Feasibility Study Update at:
-
28.95 million tonnes at 1.76% copper, 24.8 g/t silver and 0.23 g/t gold.
-
Containing 509,800 tonnes copper, 23.13 million ounces silver and 213,130 ounces of gold.
The mineral resource estimates (MRE) for Reward (ASX: KGL 23 May 2024), Rockface (ASX: KGL 07 March 2022) and Bellbird (ASX: KGL 14 September 2022) deposits were prepared by Mining Associates Pty Ltd (Mining Associates).
The MRE for the Reward, Rockface and Bellbird deposits has been re-reported at a lower break even cut-off reflective of the Feasibility Study Update, presented below in Table 1-14. An updated Mineral Resource Estimate was produced in November 2024 but has not been used as part of FSU 2025.
KGL RESOURCES LIMITED
Jervois Copper Project Feasibility Study Update
==> picture [64 x 43] intentionally omitted <==
Table 1-14: Revised project mineral resources, May 2024
| Resource | Grade (%) | Grade (%) | Grade (%) | Grade (%) | Metal | Metal | Metal | |
|---|---|---|---|---|---|---|---|---|
| Area | Category | Tonnes (Mt) |
Copper (%) |
Silver (g/t) |
Gold (g/t) |
Copper (kt) |
Silver (Moz) |
Gold (koz) |
| Open Cut Potential >0.35 % CuEq |
Measured | 4.40 | 1.90 | 32.8 | 0.30 | 83.5 | 4.63 | 42.3 |
| Indicated | 5.39 | 1.34 | 35.4 | 0.21 | 72.3 | 6.13 | 36.4 | |
| Inferred | 0.33 | 1.01 | 8.6 | 0.10 | 3.3 | 0.09 | 1.1 | |
| Subtotal | 10.12 | 1.57 | 33.4 | 0.25 | 159.1 | 10.85 | 79.7 | |
| Underground Potential > 0.8% CuEq |
Indicated | 7.85 | 2.37 | 25.4 | 0.33 | 186.1 | 6.4 | 82.3 |
| Inferred | 10.99 | 1.50 | 16.6 | 0.14 | 164.6 | 5.9 | 51.1 | |
| Subtotal | 18.84 | 1.86 | 20.3 | 0.22 | 350.7 | 12.28 | 133.4 | |
| Resource Categories Subtotal |
Measured | 4.40 | 1.90 | 32.8 | 0.30 | 83.5 | 4.63 | 42.3 |
| Indicated | 13.24 | 1.95 | 29.4 | 0.28 | 258.4 | 12.53 | 118.6 | |
| Inferred | 11.31 | 1.48 | 16.4 | 0.14 | 167.9 | 5.96 | 52.2 | |
| Total | 28.95 | 1.76 | 24.8 | 0.23 | 509.8 | 23.13 | 213.1 |
- Cut-off grades: 0.35% CuEq above an optimised pit shell (RF 1.15), 0.80% Cu below the pit shell;
Due to rounding to appropriate significant figures, minor discrepancies may occur, tonnages are dry metric tonnes. Does not include the Reward South resource estimate.
The formula for CuEq is Cu % + 0.478 x Au g/t +0.0068 x Ag g/t - 0.000074 x Bi ppm.
1.11 Mining & ore reserves
The MRE was used as the basis to design the open-cut pits and underground mines. Mine planning identified two open-cut and four underground mining areas in Table 1-15.
Key changes to the mine plan relative to the FS (November 2022) included:
-
Mineral resource updates adding more material, mainly to the underground mining areas,
-
Upgrade in mineral resource category levels (most notably the Reward open cut).
-
Open-cut optimisation processes were conducted on equivalent copper grades in the FS, instead of copper in isolation (as was conducted in the December 2020 PFS). The FSU 2025 equivalent copper grade method of optimisation includes the value of gold and silver credits.
Table 1-15: Mining areas
| Mineral resource | Open-Cut mining | Underground mining | Decline access |
|---|---|---|---|
| Rockface | n/a | Rockface Underground | Portal within Bellbird Open cut |
| Reward | Reward Open cut | Reward Underground | Dedicated Box cut |
| Marshall Underground | Portal within Reward Open cut | ||
| Bellbird | ` | Bellbird Underground | Decline from Rockface Decline |
KGL RESOURCES LIMITED
Jervois Copper Project Feasibility Study Update
==> picture [64 x 43] intentionally omitted <==
==> picture [465 x 675] intentionally omitted <==
Figure 1-10: Layout of operations
KGL RESOURCES LIMITED
Jervois Copper Project Feasibility Study Update
==> picture [64 x 43] intentionally omitted <==
Ore reserve estimation
==> picture [31 x 9] intentionally omitted <==
Consultant Xenith has determined the ore reserves based on the mineral resource classified as Measured and Indicated Resources. The ore reserves includes consideration of modifying factors (mining recovery and dilution) based primarily on mining method and ore width.
Further details on ore reserve process can be found in the ore reserve report provided by Xenith.
Table 1-16: Ore Reserves as of October 2024 (report dated 31[st] January 2025)
| Material | Material | Grade | Grade | Metal | ||||
|---|---|---|---|---|---|---|---|---|
| Source | Mt | CuEq (%) |
Cu (%) | Au (g/t) |
Ag (g/t) |
Cu (kt) |
Au (koz) |
Ag (Moz) |
| Reward Open Pit | ||||||||
| Proven | 2.68 | 2.19 | 1.71 | 0.39 | 41.96 | 45.7 | 33.6 | 3.6 |
| Probable | 2.2 | 1.54 | 1.19 | 0.22 | 36.3 | 26.1 | 15.6 | 2.6 |
| Sub-total | 4.88 | 1.9 | 1.47 | 0.31 | 39.41 | 71.8 | 49.2 | 6.2 |
| Bellbird Open Pit | ||||||||
| Proven | 1.51 | 2.07 | 1.94 | 0.11 | 11.59 | 29.2 | 5.3 | 0.6 |
| Probable | 0.48 | 1.1 | 1.04 | 0.06 | 5.55 | 5 | 0.9 | 0.1 |
| Sub-total | 1.99 | 1.84 | 1.72 | 0.1 | 10.13 | 34.2 | 6.2 | 0.6 |
| Rockface Underground | ||||||||
| Proven | - | - | - | - | - | - | - | - |
| Probable | 2.96 | 2.74 | 2.55 | 0.18 | 16.58 | 75.4 | 17.0 | 1.6 |
| Sub-total | 2.96 | 2.74 | 2.55 | 0.18 | 16.58 | 75.4 | 17.0 | 1.6 |
| Bellbird Underground | ||||||||
| Proven | - | - | - | - | - | - | - | - |
| Probable | 0.37 | 1.77 | 1.65 | 0.08 | 13.23 | 6.0 | 1.0 | 0.2 |
| Sub-total | 0.37 | 1.77 | 1.65 | 0.08 | 13.23 | 6.0 | 1.0 | 0.2 |
| Reward Underground | ||||||||
| Proven | - | - | - | - | - | - | - | - |
| Probable | 2.48 | 2.28 | 1.88 | 0.49 | 25.77 | 46.7 | 38.8 | 2.1 |
| Sub-total | 2.48 | 2.28 | 1.88 | 0.49 | 25.77 | 46.7 | 38.8 | 2.1 |
| Marshall Underground | ||||||||
| Proven | -- | -- | -- | -- | -- | -- | -- | -- |
| Probable | 1.71 | 1.51 | 1.16 | 0.19 | 39.52 | 19.8 | 10.2 | 2.2 |
| Sub-total | 1.71 | 1.51 | 1.16 | 0.19 | 39.52 | 19.8 | 10.2 | 2.2 |
| Total Proven | 4.19 | 2.15 | 1.79 | 0.29 | 31.03 | 74.9 | 39 | 4.2 |
| Total Probable | 10.19 | 2.05 | 1.76 | 0.25 | 26.27 | 179 | 83.4 | 8.6 |
| Total Reserve | 14.38 | 2.08 | 1.77 | 0.26 | 27.66 | 254 | 122.4 | 12.8 |
Quantities and grades in the above table may not add exactly due to rounding or weighting.
KGL RESOURCES LIMITED
Jervois Copper Project Feasibility Study Update
==> picture [64 x 43] intentionally omitted <==
Mining sequence
The FSU 2025 project mine schedule strategy is outlined as follows:
-
Reward Open Pit commences at the beginning of schedule year 1 and Bellbird Open Pit 3 months later. Both pits are mined concurrently until Bellbird Open Pit is completed.
-
The Rockface decline commences at the completion of the Bellbird Open Pit, at the end of year 2. First ore from Rockface commences at the end of year 3 with production from stopes commencing in year 4.
-
Reward underground is accessed via decline from a dedicated box cut that commences at the end of year 2. Upon the completion of the Reward Open Pit, a second decline from the pit will provide an access stub for Marshall before connecting to the Reward decline. The two declines will join approximately 220m below surface, providing a shorter haul to the RoM pad and second means of egress for the mine. Underground ore from Reward commences in the second half of year 3 with production from stopes commencing mid-year 4.
-
Development of the Bellbird Underground commences halfway through the Rockface Underground schedule in schedule year 5. Bellbird Underground production commences in schedule year 6.
-
Once development in Reward Underground is completed in schedule year eight, resources are allocated to Marshall Underground to recommence development to the Northern lode and to commence development to the Southern lode. Production from Marshall Underground starts in schedule year nine and continues until depletion of all remaining Reserves and stockpiles in schedule year eleven.
Mining schedule outcomes
==> picture [31 x 9] intentionally omitted <==
The combined project schedule (including development) produced the annual ore tonnage mined by source that is shown in Figure 1-11.
==> picture [464 x 193] intentionally omitted <==
Figure 1-11: FSU 2025 mining sequence (LOM schedule)
The mine development sequence provides fresh ore for plant commissioning and ramp-up, together with ore stocks to sustain operations through the transition from open-cut to underground ore production.
The FSU 2025 mine plan schedules processing a total of 16.6Mt of material which is sourced from open-cut (6.9Mt) and underground (9.7Mt). This processed material is sourced from Proven and Probable Reserves of 14.38Mt and 2.21Mt of resource conversion (13.3% of total).
KGL RESOURCES LIMITED
Jervois Copper Project Feasibility Study Update
==> picture [64 x 43] intentionally omitted <==
The majority of the resource conversion tonnage is processed in the later years of operation (see below diagram).
==> picture [296 x 178] intentionally omitted <==
Further drilling will continue to infill and progressively upgrade the Inferred Resource associated with these underground mining areas in advance of mining. However, there is a low level of geological confidence associated with the Inferred Resources and there is no certainty that further exploration work will result in the determination of Indicated Resources or that the production schedule using Inferred Resources will be realised.
Open-cut mining
==> picture [31 x 9] intentionally omitted <==
Open-cut operations will use conventional drill, blast, load and haul methods with all operations undertaken by a mining contractor. Open-cut equipment is sized to be suitable for both wide and thin vein mining as outlined in Table 1-17. The smaller 120 tonne class excavator will primarily focus on mining the thinner mineralised lodes, while the larger 360 tonne class excavator will primarily focus on waste mining and the wider mineralised lodes. It has been modelled that the mining contractor will supply, manage, operate and maintain all equipment required to drill, blast, load, haul and dump ore and waste.
Table 1-17: Open-cut mining equipment
| Type | Pit | Class | OEM | Model | Year 1 | Year 2 | Year 3 | Year 4 |
|---|---|---|---|---|---|---|---|---|
| Excavator | RE | 360 t | Hitachi | EX3600 | 1 | 1 | 2 | 1 |
| BB | 360 t | Hitachi | EX3600 | 1 | 1 | |||
| Excavator | 120 t | Komatsu | EX1200(6.0 m3) | 1 | 1 | 1 | 1 | |
| Truck | 185 t | Caterpillar | 789C | 9 | 12 | 9 | 5 | |
| Dozer | Caterpillar | D10T2 | 4 | 4 | 3 | 2 | ||
| Drill | Epiroc | SmartRoc D65 | 4 | 4 | 3 | 1 | ||
| Ancillary | Caterpillar | 18 Grader 777F Water Cart |
4 | 4 | 4 | 4 |
The open-cut plans showing waste dumps for both Bellbird and Reward are shown in the Mining and Ore Reserves Chapter. All open-cut haulage is conducted with 185 tonne class rear dump trucks.
KGL RESOURCES LIMITED
Jervois Copper Project Feasibility Study Update
==> picture [64 x 43] intentionally omitted <==
Underground mining
==> picture [31 x 9] intentionally omitted <==
Underground mining operations are based on a conventional approach that involves decline development and sub-level open stoping with or without fill (both rock and cemented rock fill).
30 metre level spacings are planned at Rockface, Reward and Marshall underground areas, whilst 20 metre spacings are planned for the Bellbird underground. This approach is well suited to the generally steeply dipping orebodies at the project.
A mining contractor will manage all aspects of the underground mining operations and will operate all underground equipment (Table 1-18). All haulage from the underground mines will be done with haul trucks.
Primary underground infrastructure for items such as primary ventilation, refuge chambers, power supply, water supply, and compressed air supply have been considered in the development of the FSU 2025. Each underground mine has a secondary egress ladderway via a raise-bored shaft.
Primary mining infrastructure, such as mains power and water, will be provided to the mining contractor, by other KGL contractors.
Production schedule
==> picture [31 x 10] intentionally omitted <==
The overall production schedule combines the open-cut and underground production schedules that are shown in Table 1-19 and Figure 1-12 respectively. These show ore production from the open-cut areas (Bellbird and Reward) during the first few years, with concurrent development of the underground (Rockface, Reward, Marshall and Bellbird), to prepare for subsequent underground production activities.
Table 1-18: Underground development and equipment
| Year of Mining | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 |
|---|---|---|---|---|---|---|---|---|---|---|---|
| Twin Boom Jumbo (Sandvik DD421) | - | 2 | 4 | 4 | 4 | 4 | 4 | 4 | 4 | 3 | - |
| Cable Bolter | - | 2 | 2 | 2 | 2 | 2 | 2 | 2 | 2 | 2 | 2 |
| Prod Drill Rig (Sandvik DL421) | - | - | 2 | 2 | 2 | 3 | 4 | 4 | 4 | 3 | 2 |
| Charge up Rig (Normet Charmec) | - | 2 | 2 | 2 | 2 | 4 | 4 | 4 | 4 | 3 | 2 |
| LRG Loader (CAT R2900) | - | 2 | 3 | 5 | 6 | 8 | 8 | 8 | 8 | 7 | 3 |
| Haul Truck 60t (CAT AD60) | - | 2 | 2 | 6 | 10 | 12 | 13 | 13 | 13 | 9 | 4 |
| Agitator Truck (10m³) | - | - | - | 2 | 2 | 2 | 2 | 2 | 2 | 2 | 1 |
KGL RESOURCES LIMITED
Jervois Copper Project Feasibility Study Update
==> picture [64 x 43] intentionally omitted <==
Table 1-19: Life of mine ore and waste mined by source - production schedules - annual (calendar year) basis
| Mine | Category | Unit | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | Total |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Reward OP |
Waste Tonnes | Mt | 16.89 | 23.26 | 18.24 | 0.81 | - | - | - | - | - | - | - | 59.20 |
| Ore Tonnes | Mt | 1.38 | 0.65 | 2.30 | 0.55 | - | - | - | - | - | - | - | 4.88 | |
| CuEq Grade | % | 1.93 | 2.51 | 1.69 | 2.17 | - | - | - | - | - | - | - | 1.92 | |
| Bellbird OP |
Waste Tonnes | Mt | 10.41 | 7.10 | - | - | - | - | - | - | - | - | - | 17.51 |
| Ore Tonnes | Mt | 0.80 | 1.19 | - | - | - | - | - | - | - | - | - | 1.99 | |
| CuEq Grade | % | 1.93 | 1.79 | - | - | - | - | - | - | - | - | - | 1.85 | |
| Reward UG |
Waste Tonnes | Mt | - | 0.03 | 0.22 | 0.22 | 0.22 | 0.20 | 0.21 | 0.00 | - | - | - | 1.10 |
| Ore Tonnes | Mt | - | - | 0.03 | 0.33 | 0.51 | 0.80 | 0.66 | 0.52 | 0.28 | 0.04 | - | 3.16 | |
| CuEq Grade | % | - | - | 2.05 | 2.04 | 1.87 | 2.38 | 2.55 | 2.17 | 2.34 | 2.89 | - | 2.27 | |
| Rockface UG |
Waste Tonnes | Mt | - | 0.03 | 0.22 | 0.30 | 0.21 | 0.18 | 0.21 | 0.03 | - | - | - | 1.18 |
| Ore Tonnes | Mt | - | - | 0.01 | 0.25 | 0.64 | 0.72 | 0.78 | 0.69 | 0.26 | - | - | 3.35 | |
| CuEq Grade | % | - | - | 2.08 | 1.59 | 2.71 | 2.74 | 3.25 | 2.64 | 2.55 | - | - | 2.73 | |
| Marshall UG |
Waste Tonnes | Mt | - | - | 0.05 | - | - | - | - | 0.35 | 0.18 | 0.01 | - | 0.58 |
| Ore Tonnes | Mt | - | - | - | - | - | - | - | 0.08 | 0.78 | 0.79 | 0.16 | 1.83 | |
| CuEq Grade | % | - | - | - | - | - | - | - | 1.37 | 1.48 | 1.64 | 1.65 | 1.56 | |
| Bellbird UG |
Waste Tonnes | Mt | - | - | - | - | - | 0.05 | 0.08 | 0.15 | 0.15 | 0.00 | - | 0.43 |
| Ore Tonnes | Mt | - | - | - | - | - | 0.01 | 0.06 | 0.36 | 0.56 | 0.32 | 0.09 | 1.39 | |
| CuEq Grade | % | - | - | - | - | - | 1.64 | 1.68 | 1.58 | 1.80 | 1.67 | 1.64 | 1.70 | |
| Total | Waste Tonnes | Mt | 27.30 | 30.43 | 18.72 | 1.33 | 0.44 | 0.43 | 0.50 | 0.53 | 0.33 | 0.01 | - | 80.01 |
| Ore Tonnes | Mt | 2.18 | 1.84 | 2.33 | 1.13 | 1.15 | 1.54 | 1.50 | 1.65 | 1.88 | 1.15 | 0.25 | 16.60 | |
| CuEq Grade | % | 1.93 | 2.04 | 1.70 | 2.01 | 2.34 | 2.54 | 2.88 | 2.20 | 1.85 | 1.69 | 1.65 | 2.08 |
Page 25
KGL RESOURCES LIMITED
Jervois Copper Project Feasibility Study Update
==> picture [64 x 43] intentionally omitted <==
==> picture [426 x 243] intentionally omitted <==
Figure 1-12:Ore tonnage mined by source – annual (calendar year) basis
Fresh sulphide ore mined will generally be direct feed from the mine to the crushing facility leaving sulphide ore and oxide ore from the open-cut, excess to plant capacity needs, to be stockpiled and rehandled to the crusher later.
There is a planned increase in ore stocks over the first three years of mining (see Figure 1-13). This planned outcome reduces the risk of ore supply gaps to the process plant in the first three years of operations and provides for the transition to full underground supply during year 4.
==> picture [437 x 234] intentionally omitted <==
----- Start of picture text -----
Jervois : Ore Stocks
1.8 140
1.6
120
1.4
100
1.2
1.0 80
0.8 60
0.6
40
0.4
20
0.2
- -
OP and UG Oxides Stock Valuation @ Lower of Cost or NRV
Mt Ore
A$m Real
----- End of picture text -----
Figure 1-13: Ore stocks balance at financial year end (30 June)
Page 26
KGL RESOURCES LIMITED
Jervois Copper Project Feasibility Study Update
==> picture [64 x 43] intentionally omitted <==
1.12 Metallurgical evaluation
Extensive metallurgical test work has been undertaken on the project since 2012. Samples have been tested by accredited providers. Sedgman oversaw the most recent laboratory test program undertaken by Core Resources to inform the process plant design.
Metallurgical testing of samples has included numerous individual samples representing three defined ore domains (sulphide, transition and oxide), blended domains and bulk composites. Each program phase followed a review of previous metallurgical test programs to focus on either confirmation and extension of knowledge, fine tuning process conditions, confirmation of the process flowsheet for the various ore domains and the development metallurgical algorithms.
Only sulphide and oxide domains are considered for this production schedule. The metallurgical test programs used samples and cores extracted during exploration drilling have supported the following testing and development work;
- Comminution test work
Comminution test work has been carried out in 2012, 2015 and 2021 at ALS Metallurgy in Perth. A comprehensive range of parameters were tested including Unconfined Compressive Strength (UCS), Crusher Work Index (CWi), Bond Ball Mill Work Index (BBWi), Bond Rod Mill Work Index (BRWi), SAG Mill Comminution (SMC) and Abrasion Work Index (Ai) tests.
- Process plant throughput & ramp-up rates
Processing rate for sulphide ore has targeted 2.0Mtpa. Sedgman assumed a ramp-up to full nameplate production within 12 months. This ramp-up rate was developed from a global database of ramp up rates for similar Copper Projects, Sedgman also mention another similar process facility ramping up in half that time.
The throughput rate of 2.0Mtpa is maintained until production month 39 when oxide copper ores start to be processed. The throughput rate targeted for treatment of oxide copper ore is set to a conservative of 2.2Mtpa for five months. Oxide copper ore is soft and can be treated at much higher throughput rates, but throughput will be constrained by the flotation circuit. The volumetric flow rate of the feed to the first rougher cell causes the recycle rate for the Jameson cell E4232/10 be too low at 2.63Mtpa throughput rate.
After 5 months of processing oxide copper ore, sulphide ore processing is resumed at a target throughput rate of 1.6Mtpa. This throughput rate commences in production month 44 and continues until production month 104. The reduced throughput rate is aligned with reduced production expected from underground mine production. In production month 104, a throughput rate target of 1.36Mtpa is targeted and maintained until the end of the project life.
- Primary grind optimisation
At the conclusion of the variability and bulk test work, further work was conducted to determine whether the primary grind size could be coarsened further. Primary grind P80 sizes of 120μm, 150μm and 180μm were tested using the Flowsheet Confirmation Composite. There appears to be scope to coarsen the primary grind size target, but design has considered 120μm P80 to be the baseline. Potential to coarsen the primary grind will be assessed more closely during processing operations.
Page 27
KGL RESOURCES LIMITED
Jervois Copper Project Feasibility Study Update
==> picture [64 x 43] intentionally omitted <==
• Regrind optimisation
Following the primary grind size optimisation, the coarser primary grind size was used in regrind optimisation test work. This test work was conducted to determine whether further uranium or bismuth rejection could be achieved.
Rougher concentrate from the bulk flotation tests was tested at the University of Queensland using the M4 IsaMill, and also dispatched to Metso Outotec for HIGmill and Jar mill testing.
- Flotation flowsheet development
Sulphide ore requires a simple copper sulphide flotation circuit with rougher and scavengers, scavenger tailing directed to final tailing and rougher + scavenger concentrates reground in a stirred mill to 35μm P80, and then three-stage cleaning (equivalent) and cleaner scavengers. The flotation circuit will need conditioning capacity installed post the primary grinding and regrind circuits to provide sufficient time for chemical reactions and stabilisation of chemical conditions.
Oxide ore requires a simple copper oxide flotation circuit with rougher and scavengers, scavenger tailing directed to final tailing and rougher + scavenger concentrates directed to a single-stage cleaning circuit. There is no regrind and prior to rougher and cleaner stage flotation there is need for additional conditioning capacity for sulphurdisation. Therefore, the oxide ore flowsheet requires two conditioning tanks prior to both rougher and cleaner stage flotation. The first conditioning tank is for sulphurdisation and the second for collector addition. The capacity of the conditioning tanks will provide sufficient time for chemical reactions and stabilisation of chemical conditions.
- Thickener and filtration test work
Wet solid samples of tailings and final concentrate from the bulk test work were sent to Metso Outotec for thickener testing. Concentrate filtration test work was conducted by both Metso Outotec and Matec. Metso Outotec tested both its Outotec Larox Pressure Filtration (PF) and the Outotec Larox Fast acting Filter Press (FFP) units.
Mineralogical assessment was performed using QEMScan PMA on a combined sample of final concentrate from the 2018 ALS programme, produced from the locked-cycle testing on the bulk composite.
- Contaminant reduction
A program was conducted to assess the deportment of contaminants such as uranium, fluorine and bismuth minerals and the options available for rejection.
- Site water and ore ageing evaluation
Flotation testwork was repeated on site water and showed no change in metallurgical performance. Testwork on aged samples stored at site in dry conditions to have no detectable effect on metallurgical performance.
- Bulk composites
Bulk composites were developed from blending sulphide domain samples to represent the most significant material in the production schedule, in order to:
-
Provide a rougher concentrate for IsaMill and HIG Mill signature plots and a Metso Jar test for tower mill sizing
-
Conduct a rougher scalper Jameson cell simulation
-
Conduct a rougher and cleaner Jameson cell simulation
Page 28
KGL RESOURCES LIMITED
Jervois Copper Project Feasibility Study Update
==> picture [64 x 43] intentionally omitted <==
-
Provide a final concentrate for thickener and filtration test work
-
Provide a final concentrate for transportable moisture limit, self-heating, corrosiveness and toxicology testing
-
Provide a final tailings for thickener, geochemical and geotechnical test work.
Sedgman was engaged in 2022 to collate all recent and historical results into a single comprehensive report. Metallurgical performance predictions were then developed by Sedgman taking into consideration all test work results since 2012. Data was sourced from over a dozen metallurgical programs.
2021/2022 focused on open circuit and locked-cycle testing to update and improve these metallurgical algorithms, with particular focus on low grade sulphide ore samples. The metal recovery algorithms developed by Sedgman (see Table 1-20) combined with the production schedule, forecast an average metal process recovery of 92.02% Cu, 55.28% Au, 66.02% Ag (excludes oxide) (see Figure 1-14 for metallurgical recoveries on an annual basis).
Table 1-20: Metal recovery algorithms
| Domain **type ** |
Metal performance | Prediction range | Predictive algorithm |
|---|---|---|---|
| Sulphide | |||
| Copper Recovery | <0.5% Cu | Cu Rec = 0.202 x LN(CuHG%) + 1.9601 | |
| ≥ 0.5% Cu | Cu Rec = 1.0485 x ((CuHG%)^0.0325) | ||
| Gold Recovery | Au Rec = 0.691 x ((Bi Rec)^0.723) | ||
| Silver Recovery | Ag Rec = (0.88 x Bi Rec) + 0.043 | ||
| Bismuth Recovery | Bi Rec = 0.2469 x (Ln(Pb Rec) + 0.8204 | ||
| Bismuth Recovery (secondary) |
Bi Rec = 0.093 x LN(BIHG ppm) + 0.0321 | ||
| Uranium Recovery | U Rec = 1E-08 x e^(17.484*(Cu Rec%)) | ||
| Fluorine Recovery | F Rec = 0.24% (Constant) | ||
| Lead Conc. Grade | Pb Concentrate Grade = (8.5 x Pb Feed Grade) - 0.0004 | ||
| Zinc Conc. Grade | Zn Concentrate Grade = (9 x Zn Feed Grade) - 0.0002 | ||
| Oxide | |||
| Oxide Copper Recovery | <0.2% Cu | Cu Rec = 0% | |
| 0.2% ≥ Cu ≤ 2.5% Cu |
Cu Rec = (34.675 x CuHG%) - 0.0646 | ||
| > 2.5% Cu | Cu Rec = 80% | ||
| Gold Recovery | Au Rec = (0.685 x Bi Rec) + 0.126 | ||
| Silver Recovery | Ag Rec = (1.326 x Bi Rec) - 0.0295 | ||
| Bismuth Recovery | Bi Rec = (0.873 x Cu Rec) - 0.174 | ||
| Uranium Recovery | U Rec = 1E-08 x e^(17.484*(Cu Rec%)) | ||
| Fluorine Recovery | F Rec = 2.52% (Constant) | ||
| Lead Conc. Grade | Pb Concentrate Grade = (8.5 x Pb Feed Grade) - 0.0004 | ||
| Zinc Conc. Grade | Zn Concentrate Grade = (9 x Zn Feed Grade) - 0.0002 |
Metal recovery algorithms developed for sulphide and oxide ore flotation testwork
Page 29
KGL RESOURCES LIMITED
Jervois Copper Project Feasibility Study Update
==> picture [64 x 43] intentionally omitted <==
==> picture [469 x 263] intentionally omitted <==
Figure 1-14: Metallurgical recoveries – annual basis
Metallurgical recoveries FY2027 to FY2029 are for fresh sulphide ore from the open cut mines
Metallurgical recoveries FY2030 (the dip in Cu recovery shown above in Figure 1-14) are from batch processing of sulphurdised oxide ore from the open cut mines and boxcut,
Metallurgical recoveries for the remainder of the processing period are from fresh ores sourced from the underground mines.
1.13 Process plant
The process plant design is a conventional concentrator for copper with gold and silver by-products. The design consists of consists of a ROM bin, jaw crushing, semi autogenous and ball mill comminution, rougher flotation, regrind and cleaner flotation followed by concentrate thickening and dewatering by filter press. Product concentrate is stockpiled within a purpose-built covered concentrate holding facility prior to being loaded into side tipping bulk carrier road trains for delivery to Mt Isa. The plant design is based on a 250t/hr throughput rate for 2.0Mtpa processing capacity.
The flowsheet developed for the plant is shown in Figure 1-15.
Page 30
KGL RESOURCES LIMITED
Jervois Copper Project Feasibility Study Update
==> picture [64 x 43] intentionally omitted <==
==> picture [679 x 422] intentionally omitted <==
Figure 1-15: Flowsheet for process plant
Page 31
KGL RESOURCES LIMITED
Jervois Copper Project Feasibility Study Update
==> picture [64 x 43] intentionally omitted <==
The process plant design, delivery schedule and cost estimate have been updated and refined based on independent peer review. Multiple iterations of the mine plan have been completed, with Sedgman honing the process plant design to provide incremental improvements in project value, guided by financial modelling.
The processing plant will be operated under an operating contract that includes providing the management, operating labour and plant maintenance. The operating contract will include key performance measures targeting plant throughput, metallurgical performance and concentrate quality and despatch performance.
Life of mine average Bismuth concentration, in concentrate, is forecast to average 289ppm (0.029%). Bismuth is the only element in the concentrate that is forecast to be penalised above a threshold limit contained in the draft offtake contract. The financial penalty applied equates to approximately 1% of the gross copper revenue.
A 3D view of the plant arrangement is provided in Figure 1-16.
==> picture [483 x 297] intentionally omitted <==
Figure 1-16: Process plant layout
1.14 Concentrate offtake and haulage
Copper concentrate (which includes recovered copper, gold and silver) will be sold via an offtake agreement. A high-level outline of the key aspects of the agreement is as follows:
-
The agreement is for the sale of all concentrate produced from the project for a minimum term of five full calendar years after commencement of commercial production. The sale agreement is evergreen and will continue beyond the minimum term until either party terminates it by giving two years’ prior notice.
-
The sale price for the copper concentrate is tonnage based and calculated by reference to the LME cash settlement price for copper, with silver and gold credits (subject to minimum ‘payable’ limits). The sale price includes adjustments for treatment, refining and treatment
Page 32
KGL RESOURCES LIMITED
Jervois Copper Project Feasibility Study Update
==> picture [64 x 43] intentionally omitted <==
charges, penalties associated with impurities above agreed threshold values, and other adjustments.
-
By-product credits for the gold and silver in the concentrate will be paid (within certain contractual limits) in addition to payable copper.
-
A number of penalty elements are identified in the agreement that include bismuth, fluorine and uranium. There are no rejection criteria included in the agreement. Bismuth is the only element foreseen to exceed defined threshold levels and be penalised.
-
The agreement is subject to other customary terms and conditions, including processes for assaying, weighing, sampling and moisture determination in relation to the concentrate, and contains relevant force majeure clauses.
Copper concentrate sold on an FOT basis is ex-site will be transported from the Jervois site in conventional, covered bulk haulage trailers in road train configuration (approximately 114 tonne payload). Annual concentrate haulage planned is around 90,000 – 135,000 (dry) tonnes, see Figure 1-17.
Truck haulage from site is currently approved for up to 150,000 tonnes per annum via the Plenty Highway. Concentrate transportation is to be undertaken by offtake buyer, including arrangement of vehicle and road specific approvals.
==> picture [433 x 235] intentionally omitted <==
----- Start of picture text -----
Concentrate sold - dmt
----- End of picture text -----
Note: FY 27 cover the Project completion and plant ramp up (6 months) FY37 is the final concentrate production and sales (5 months)
Figure 1-17: Concentrate offtake FOT (dry metric tonnes) - annual (financial year) basis
1.15 Tailings management and acid mine drainage
The tailings storage facility ( TSF ) will consist of one cell and will be constructed during the initial project development and then raised in stages as additional containment capacity is required. TSF embankment construction will utilise mine waste sourced from mining pre-strip, diversion drain excavation and locally borrowed soil materials. The TSF design is sufficient to contain all tailings for the life of the project. The TSF basin area will have a compacted base overlain by a high-density polyethylene (HDPE) liner to contain the tailings.
Page 33
KGL RESOURCES LIMITED
Jervois Copper Project Feasibility Study Update
==> picture [64 x 43] intentionally omitted <==
Tailings will be discharged into the cell onto an active ‘beach’ via spigots at regular intervals around the perimeter of the tailings embankment. As the tailings settles and a pond formed by the beach, water will be removed via a decant tower extraction system. It is estimated that 30% of water pumped to the TSF will be returned to the process water dam for re-use in processing.
The TSF has been designed in accordance with design criteria applicable to ‘High C’ category drawn from the Australian National Committee on Large Dams (ANCOLD) guidelines.
An Acid Mine Drainage (AMD) Management Plan has been developed for the project and includes strategies for the management of potential acidic forming waste rock. Potentially low pH water from the underground and open-cut dewatering operations will be contained on site in the process water dam or the TSF. It is not expected the open-cut derived water will be acidic, nor the majority of UG derived water. Peak flows of potentially acidic water from UG are projected to contribute 66% of plant site top up raw water requirements. The Acid Mine Drainage Management Plan will continue to be refined with additional sulfur block and geochemical modelling.
1.16 Power supply
A dedicated hybrid power supply will be delivered by an independent power producer ( IPP ) under a build, own, operate and maintain ( BOOM ) contract. The hybrid power station has been sized to provide sufficient capacity for underground, processing plant and support services. Peak power demand for the operating phase has been modelled to peak at about 14.5MW when all four underground mines are operating. The hybrid power generation facility includes:
-
A 20.8MW solar PV array
-
A 24.0MW wind farm
-
A 13.8 MW (27.6MWHr) battery energy storage system (BESS)
-
17 x 1MW containerised diesel-powered power plants
The BOOM contract with the IPP will include the requirement to deliver switch-rooms, control systems and transformers. Project-wide power distribution and step-down transformers will be delivered under a separate contract.
Engagement with IPP candidates has supported the assumption that power will be purchased via a Power Purchase Agreement arrangement under an agreed monthly capacity charge and usage charge tariff structure with no upfront capital charge to KGL (upfront capital costs are recovered by the IPP through the tariff). The IPP tariff will be inclusive of cost of diesel provided by KGL. The low marginal power cost (post installation) of the wind and solar generators encourages use of renewable power and as a result, both the IPP and KGL commercial drivers aim at minimising power generation carbon emissions.
It is projected that at least 60% of the project’s electricity consumption could be provided by the renewable wind and solar sources, minimising diesel consumption for power generation.
1.17 Water supply
Site water demands include those for the process plant, dust suppression, underground mining equipment demands, potable water and for general use. Process plant water will recycle through the Process Water Dam ( PWD ) which will also accept incoming water from mine dewatering and other water nodes such as sediment ponds. The 50ML PWD is located between the process facility and the TSF. Captured rainfall on the project area or water from dewatering pits and underground workings will be collected in sediment ponds and reused to supplement bore field supply.
Raw water requirements are to be sourced predominantly from the Lucy Creek bore field approximately 20km to the north of the main project site. The Lucy Creek bore field has regulatory
Page 34
KGL RESOURCES LIMITED
Jervois Copper Project Feasibility Study Update
==> picture [64 x 43] intentionally omitted <==
approvals in place up to a maximum extraction rate of 1,594 ML per annum. Raw water will also be sourced from the Jervois Dam to the west of the MIA when seasonal inflows allow.
Peak water demand on site is expected to be 3.5ML per day, while water approvals from the Lucy Creek bore field and the Jervois Dam equate to 4.6ML per day. This provides approximately 25% excess capacity.
1.18 Airstrip and camp
An asphalt airstrip is planned to be constructed on the eastern side of Lucy Creek Access Road, adjacent to the accommodation village at an estimated cost of $20m. Sized for 100 seat jet aircraft, the Jervois airstrip will be the primary means of transporting people to and from site. The aircraft will be capable of transfers from all Australian capital cities, with refuelling option at Jervois airstrip if required. Establishment of the airstrip is prioritised early in the project construction phase to support the ramp up of construction activities on site and timed to coincide with the accommodation village achieving second stage capacity.
The existing airstrip at the Bonya (Baikal) community located 17km from the Jervois project is currently used by the exploration team at Jervois. The Bonya airstrip will be suitable for early project construction requirements until the Jervois airstrip is completed.
The airstrip may also be constructed in stages to reduce capital, this will be verified closer to Project construction commencement. Potential to marshal personnel in Mt Isa and transfer people to site using a 40 seat turbo prop would allow a circa $12m cost deferment in capital. Constructing a gravel strip in the same position as the permanent strip would contribute to the final arrangement and enable a speedy upgrade as project cashflow allows.
Personnel numbers fluctuate through construction into operation. Accommodation requirements are based around the peak personnel requirements (approximately 300 personnel) during project development.
A contractor will be engaged for final detailed design, construction and installation of all site accommodation including the supporting infrastructure. Development of the Village is included in the project pre-production capital.
==> picture [374 x 241] intentionally omitted <==
----- Start of picture text -----
Site Personnel Histogram
350
300
250
200
150
100
50
0
Project Construction Open Pit Underground Others
Site Personnel
2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037
----- End of picture text -----
Figure 1-18: Monthly camp occupancy (number of people)
Page 35
KGL RESOURCES LIMITED
Jervois Copper Project Feasibility Study Update
==> picture [64 x 43] intentionally omitted <==
1.19 Value improvement opportunities
Value improvement opportunities have been identified by the project team that will continue to be progressed prior to and after FID. These value improvement opportunities, which are not included in the FSU 2025, have the potential to significantly improve the value of the project. These opportunities are summarised as follows:
-
Capital efficiency improvement via extending mineral resources – all mineral resources (Bellbird, Marshall, Reward and Rockface) included in the FSU 2025 remain open at depth, while Reward and Bellbird remains open along strike.
-
Competitive tendering of major contracts – The forward work plan leading to FID is to competitively tender the major service and supply contracts with an expectation of gains against the input assumptions for the FSU 2025.
-
Infrastructure rationalisation – there is an opportunity to rationalise various civil design and specification aspects for some landforms and infrastructure and align the scope with a contracting strategy to reduce the capital cost of the civil works packages.
-
Assay laboratory strategy – the project FSU 2025 includes the cost of establishing and operating an assay laboratory for mining and process grade control (GC). A cost per throughput-tonne of $2.74 was provided by Sedgman for this capacity.
-
Tailings storage – assess viability of dry stacking tailings or a centre spigot discharge against the current strategy of conventional tailings storage using a lined TSF.
-
Margin improvement via polymetallic recovery of lead and zinc – previous studies on the project have investigated the extraction of lead and zinc from ore bodies. Lead and Zinc mineralisation has continued to be identified in recent exploration analysis. Further work is planned to characterise the potential for economic polymetallic recovery.
-
Primary grind target reduction - comparison tests of primary grind size targets of 150 micron and 180 micronP80 may provide opportunity for increased mill throughput.
1.20 Forward Work Plan
The forward work plan covers activities from FSU 2025 completion through to FID. This interim phase provides certainty for FID by completing early works for rapid project development deployment and schedule risk reduction, finalising contracts ready for execution and preparing resources for implementation, inclusive of project team expansion.
The key objectives of this phase are summarised below:
-
Progress site works, enabling early-as-possible completion of critical path activities.
-
Review regulatory approvals ensuring construction starts as planned.
-
Complete engineering, specifications and scopes for all packages with an emphasis on critical path packages.
-
Complete procurement activities to:
-
Ensure a competitive bid process has been followed for packaged scopes key to the project’s success.
-
provide executable contracts for pre and post FID critical path packages.
-
provide accurate market pricing finalising project costs for pre-FID.
-
Complete project management implementation planning.
-
Project team recruiting for pre-FID scope and preparing onboarding for roles post FID.
-
Complete assessment of value improvement opportunities identified during FSU 2025.
Page 36
KGL RESOURCES LIMITED
Jervois Copper Project Feasibility Study Update
==> picture [64 x 43] intentionally omitted <==
Several critical path activities need to be completed or progressed during this interim phase to enable the project to maintain key milestones dates. These are summarised in Table 1-21:
Table 1-21: Critical path activities
Activities Early civil works –accommodation pad, contractor’s laydown pad, access roads Temporary accommodation – support early works prior to Village Stage 1 Borefield water supply – Stage 1 (procurement) Existing plant deconstruction Process plant – detail engineering and LLI Crushing and screening materials for airstrip and building platforms Accommodation Village – Stage 1 Accommodation Village – Stage 2 (procurement) Geotech – Airstrip, Village sewerage treatment plant (STP) Survey – Airstrip and new borefield alignment
Page 37
KGL RESOURCES LIMITED
Jervois Copper Project Feasibility Study Update
==> picture [65 x 43] intentionally omitted <==
Figure 1-19 shows the planned construction project timeline to first concentrate production.
==> picture [726 x 315] intentionally omitted <==
Page 38
KGL RESOURCES LIMITED
Jervois Copper Project Feasibility Study Update
==> picture [64 x 43] intentionally omitted <==
1.21 Project funding
The availability of funding to support the capital requirement for the development of the project has been assumed in the FSU 2025. The costs associated with project financing are not considered in the project base case model, which is ungeared.
The preliminary total financing requirements for the project based on the current FSU 2025 will be approximately $500 million (excluding interest and fees payable). This funding is to cover project construction capital; operating costs incurred during the construction and commissioning period and working capital requirements.
Financial advisor will be appointed to assist with assessing the optimal capital structure for the project and negotiations with equity and debt investors.
1.22 Risks
KGL has developed a comprehensive risk register for the project to identify and address reasonably foreseeable risk aspects (actual or potential) relevant to KGL’s corporate entities and the project’s development and ongoing operations.
This framework aligns with the requirements of AS ISO 31000:2018 and enables the integration of risk management into business activities and key decision-making processes.
The following key risks have been identified to deliver the project on time and within budget:
Financing not available. Although it has been assumed that project funding will be available to support project development, there is a chance that this will not eventuate. The robust project financial returns exhibited in this FSU 2025 are a key mitigation to the risk of not securing project finance, as are the tendering activities with the express intent of tailoring key contract terms to suit project financing requirements.
Adverse cost escalation. The current high inflation environment represents a risk to project cost escalation. Key mitigation activities include tendering key contracts prior to FID and providing sufficient pre-production capital contingency. Additionally, commencing operations with open-cut mining simplifies project development and reduces the risk of cost escalation through scope changes and/or project delays.
Skill shortage during construction. The low Australian unemployment rate and national skills shortage creates the risk of KGL’s contractors being unable to attract and retain skills to develop and operate the project. The key mitigation is the selection of suitable contractors with existing capability and capacity to develop and operate the project.
The following are business-wide risks have been identified as having the potential to affect delivery of the project:
Fluctuations in copper price and Australian dollar exchange rate. The copper mining industry is competitive. There can be no assurance that copper, silver and gold prices will be such that KGL can mine its deposits at a profit. Copper, silver and gold prices fluctuate due to a variety of factors including supply and demand fundamentals, international economic and political trends, expectations of inflation, currency exchange fluctuations, interest rates, global or regional consumption patterns and speculative activities. Similarly, demand and supply of capital and currencies, forward trading activities, relative interest rates and exchange rates and relative economic conditions can impact exchange rates.
Page 39
KGL RESOURCES LIMITED
Jervois Copper Project Feasibility Study Update
==> picture [64 x 43] intentionally omitted <==
Macro-economic risks. Inflationary pressures for appropriately skilled labour, oil and capital items are being seen across many industries, including the mining industry. The current conflict in the middle east and ongoing conflict between Ukraine and Russia may also continue to adversely affect capital markets and cause spikes in materials prices, particularly diesel prices, in the short term.
Regulatory risk. KGL’s operations are subject to various Commonwealth, State and local laws and plans, including those relating to mining, prospecting, development permit and licence requirements, industrial relations, environment, land use, royalties, water, native title and cultural heritage, mine safety and occupational health. Approvals, licences, and permits required to comply with such rules are subject to the discretion of the applicable government officials. No assurance can be given that KGL will be successful in obtaining or maintaining such approvals, licences and permits in full force and effect without modification or revocation. To the extent such approvals, licences and permits are required and not retained or obtained in a timely manner or at all, KGL may be curtailed or prohibited from continuing or proceeding with production and exploration. KGL’s business and results of operations could be adversely affected if applications lodged for exploration licences are not granted.
Mining and exploration tenements are subject to periodic renewal. The renewal of the term of a granted tenement is also subject to the discretion of the relevant Minister. Renewal conditions may include increased expenditure and work commitments or compulsory relinquishment of areas of the tenements comprising KGL’s projects. The imposition of new conditions or the inability to meet those conditions may adversely affect the operations, financial position and/or performance of KGL. It is also possible that, in relation to tenements which KGL has an interest in or will in the future acquire such an interest in, there may be areas over which legitimate common law native title rights of Aboriginal Australians exist. If native title rights do exist, the ability of KGL to gain access to tenements (through obtaining consent of any relevant landowner), or to progress from the exploration phase to the development and mining phases of operations, may be affected. KGL has a registered Indigenous Land Use Agreement with the traditional owners for its Jervois Copper Project.
A key mitigation strategy is the monitoring of compliance with these obligations that KGL has, to ensure it is across and complies with all its legal and moral obligations in regard to its licenses and agreements.
Environmental and climate change risk. The operations and activities of KGL are subject to the environmental laws and regulations of Australia. As with most exploration projects and mining operations, KGL’s operations and activities are expected to have an impact on the environment, particularly if advanced exploration or mine development proceeds. KGL attempts to conduct its operations and activities to the highest standard of environmental obligation, including compliance with all environmental laws and regulations. KGL is unable to predict the effect of additional environmental laws and regulations which may come into effect in the future, including whether any such laws or regulations would materially increase KGL’s cost of doing business or affect its operations in any area. However, there can be no assurances that new environmental laws, regulations, or stricter enforcement policies, once implemented, will not oblige KGL to incur significant expenses and undertake significant investments, which could have a material adverse effect on KGL’s business, financial condition and performance.
The operations and activities of KGL are subject to changes to local or international compliance regulations related to climate change mitigation efforts, specific taxation or penalties for carbon emissions or environmental damage, and other possible restraints on industry that may further impact KGL and its profitability. While KGL will endeavour to manage these risks and limit any consequential impacts, there can be no guarantee that KGL will not be impacted by these occurrences. Climate change may also cause certain physical and environmental risks that cannot be predicted by KGL, including events such as increased severity of weather patterns, incidence of
Page 40
KGL RESOURCES LIMITED
Jervois Copper Project Feasibility Study Update
==> picture [64 x 43] intentionally omitted <==
extreme weather events and longer-term physical risks such as shifting climate patterns. All these risks associated with climate change may significantly change the industry in which KGL operates.
Other material business risk exposures associated with holding an investment in KGL’s securities are disclosed in the 30 June 2024 Director’s Report, which forms part of KGL’s latest annual report for the period ended 30 June 2024.
1.23 Environmental, Social and Governance
KGL’s financial and operational success in developing the project will be underpinned by effective Environmental, Social and Governance ( ESG ) practices. Accordingly, KGL has continued to focus on putting in place management systems and governance processes throughout 2025 and 2026, continuing the work to-date including updating the 2023 KGL Sustainability Report (see www.kglresources.com.au).
KGL recognises that the United Nations’ Sustainable Development Goals ( SDGs ) provide a meaningful foundation upon which to strive towards sustainable development. KGL has identified which SDGs most closely align to the KGL values, strategic objectives and operational activities.
==> picture [412 x 197] intentionally omitted <==
Figure 1-20: SDGs most important to KGL and project stakeholders
By supplying responsibly produced copper, KGL will be a positive contributor to the world well beyond the operational boundaries of the project. Part of responsible production means purposefully and deliberately contributing to relevant SDGs within the host communities and across the value chains. This will be done while seeking to mitigate potential impediments to their realisation created by the development of the project.
1.24 Community
The traditional custodians of the land in the southern NT are represented by the Central Land Council ( CLC ). The CLC is one of four land councils in the NT. The project is in the Eastern Plenty subregion of the CLC jurisdiction. In August 2016, formalisation of cooperation with the CLC was achieved and documented in an Indigenous Land Use Agreement (ILUA) between Jinka Minerals Ltd, Kentor Minerals (NT) Pty Ltd (KGL’s operating company; the company name was subsequently changed to Jervois Operations Pty Ltd) and the CLC. This ILUA has been registered with the National Native Title Tribunal since May 2017.
Page 41
KGL RESOURCES LIMITED
Jervois Copper Project Feasibility Study Update
==> picture [64 x 43] intentionally omitted <==
The project is specifically located within the Jervois Pastoral Lease owned by Jervois Pastoral Company Pty Ltd. The Jervois homestead is located approximately 35 km south of the project, while the Lucy Creek property homestead is approximately 24 km north of the project.
There are two Aboriginal communities within 20 km of the project. The Bonya Community is approximately 17 km to the south-west and the Maperte Community is approximately 16 km to the north-east. Bonya currently has accommodation for approximately 80 people. The Maperte Community consists of only two currently unoccupied houses. Other regional community centres include the Atitjere Community, also known as Harts Range, which is located along the Plenty Highway approximately 160 km west of the project, and the Gemtree Caravan Park, which is located along the sealed section of the Plenty Highway.
Since acquiring the project in 2011, KGL has formed and maintained a good working relationship with the Bonya community through regular and open communication. KGL also keeps in regular contact with the pastoral leaseholders from Lucy Creek and Jervois Stations respectively.
The project will provide employment opportunities and increased business opportunities for local suppliers and service providers. Flow-on effects are expected to include the return of people to local communities, education and upskilling of local residents, improved community infrastructure and community benefits through distribution of sponsorship funds and royalties. Overall, feedback on the project from stakeholders has been mostly optimistic due to the positive benefits it could bring to central Australia.
KGL considers environmental stewardship an integral part of its business. It is committed to minimising potential environmental impacts and risks associated with its activities at every stage of the project, from planning through exploration, development, production and ultimately mine closure.
KGL recognises the strong cultural links of local communities to the surrounding environment and acknowledges the community role in KGL’s environmental responsibilities.
1.25 Regulatory approvals
The project has successfully progressed through numerous regulatory approvals and, most significantly, the authorisation under the Mining Management Act 2001 (NT).
As part of the project approvals process, KGL completed numerous environmental assessments and field surveys over several years on key aspects including flora and fauna, archaeology, surface water, groundwater, social impacts and geochemistry. These investigations were used to inform the draft Environmental Impact Statement and associated Supplement Report which ultimately led to the NT Environmental Protection Agency issuing its Assessment Report in September 2019. Subsequently, the NT Minister for Mining and Industry granted Authorisation 1061-01 for the approval of the project and associated Mining Management Plan ( MMP ) in January 2021.
The project was self-assessed and referred to the Federal Department of Environment in November 2013. In November 2014 the project was found not to be a controlled action and no Federal involvement was required in the assessment process.
In accordance with the conditions in Authorisation 1061-01, KGL must comply with, develop and operate the project in accordance with environmental commitments and safeguards identified and recommended in the project Environmental Impact Statement (EIS), the NT EPA Assessment Report 90 and approved project MMP.
The approved MMP for the project contains numerous strategies and environmental management plans which have been specifically designed to address and monitor all commitments and recommendations which form part of the project authorisation. The MMP will be updated and
Page 42
KGL RESOURCES LIMITED
Jervois Copper Project Feasibility Study Update
==> picture [64 x 43] intentionally omitted <==
amended as required to reflect changes in project activities which result in a change to the level of environmental impact or when environmental management strategies are revised. KGL has the personnel and systems in place to achieve commitments to ensure they are met within the required timeframes. Significant progress towards meeting pre-construction requirements has already been made.
During the early stage of project construction and prior to first ore processing, approvals for concentrate haulage eastward to Mt Isa will be required. It is not expected these would be withheld.
1.26 Reliance on independent experts
The project FSU2025 development relies upon numerous external consultants, Tier 1’s and experts for its outputs.
This announcement has been approved by the directors of KGL Resources Limited.
For further information:
-
Phone: (07) 3071 9003
-
Email: [email protected]
Page 43
KGL RESOURCES LIMITED
Jervois Copper Project Feasibility Study Update
==> picture [64 x 43] intentionally omitted <==
Competent Person Statement
The Jervois Resources information were first released to the market - Reward (ASX:KGL 23 May 2024), Rockface (ASX:KGL 07 March 2022) and Bellbird (ASX:KGL 14 September 2022) - and are compliant with JORC 2012. The company confirms that it is not aware of any new information or data that materially affects the information included in the original market announcement and that all material assumptions and technical parameters underpinning the estimates in the relevant market announcement continue to apply and have not materially changed. The company confirms that the form and context in which the Competent Person’s findings are presented have not been materially modified from the original market announcement.
The information in this announcement that relates to Mineral Resource Estimates is based on data compiled by Ian Taylor BSc (Hons), a Competent Person who is a Fellow of The Australasian Institute of Mining and Metallurgy. Mr Taylor is an independent consultant working for Mining Associates. Mr Taylor has sufficient experience, which is relevant to the style of mineralisation and type of deposit under consideration and to the activity, which is being undertaking to qualify as a Competent Person as defined in the 2012 Edition of ‘Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves’. Mr Taylor consents to the inclusion in the announcement of the matters based on his information in the form and context in which it appears.
The information in this announcement that relates to Ore Reserves Estimates is based on data compiled by Iain Ross BSc (Hons) Mining, a Competent Person who is a Member of The Australasian Institute of Mining and Metallurgy. Mr Ross is a consultant working for Xenith Consulting Pty Ltd who were engaged by the Company to carry out the ore reserve estimate. Mr Ross has sufficient experience, which is relevant to the style of mineralisation and type of deposit under consideration and to the activity which is being undertaken to qualify as a Competent Person as defined in the 2012 Edition of ‘Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves’. Mr Ross consents to the inclusion in the announcement of the matters based on his information in the form and context in which it appears.
Forward Looking statements
This release includes certain forward-looking statements. The words “forecast”, “estimate”, “like”, “anticipate”, “project”, “opinion”, “should”, “could”, “may”, “target” and other similar expressions are intended to identify forward looking statements. All statements, other than statements of historical fact, included herein, including without limitation, statements regarding forecast cash
Page 44
KGL RESOURCES LIMITED
Jervois Copper Project Feasibility Study Update
==> picture [64 x 43] intentionally omitted <==
Glossary
| Glossary | |
|---|---|
| Abi | Abrasion Work Index |
| AMD | Acid mine drainage |
| ANCOLD | Australian National Committee on Large Dams |
| AUD | Australian dollar(A$) |
| BBWi | Bond ball mill work index |
| BESS | Batteryenergystorage system |
| BOOM | Build, own, operate and maintain |
| BRWi | Bond Rod Mill Work Index |
| CAGR | Compound annualgrowth rate |
| CLC | Central Land Council |
| CO2 | Carbon dioxide |
| CoG | Cut offgrades |
| CuEq | Copper equivalent |
| CWi | Crusher work index |
| EBIDTA | Earnings before interest, taxes, depreciation and amortization |
| EIS | Environmental Impact Statement |
| EPA | Environmental Protection Authority |
| ESG | Environmental, Social and Governance |
| EV | Electric vehicle |
| FFP | Fast actingFilter Press |
| FS | FeasibilityStudy |
| FID | Financial Investment Decision |
| FSU 2025 | FeasibilityStudyUpdate announced January2025(this study) |
| GC | Grade control |
| HDPE | High density polyethylene |
| ILUA | Indigenous Land Use Agreement |
| IPP | Independentpowerproducer |
| IRR | Internal rate of return |
| Jinka Minerals Limited | 100% owned subsidiaryof KGL and owner ofproject leases |
| Jervois Pastoral Company PtyLtd |
A non-KGL Resources Limited (KGL) related entity |
| KGL | KGL Resources Limited |
| LME | London Metal Exchange |
| Macmahon | Macmahon Contractors PtyLtd |
| MMP | MiningManagement Plan |
| MRA | Minerals Royalty Act 2024 |
| MRE | Mineral resource estimates |
| NPV | Net Present Value |
| NT | Northern Territory |
Page 45
KGL RESOURCES LIMITED
Jervois Copper Project Feasibility Study Update
==> picture [64 x 43] intentionally omitted <==
| OP | Openpit |
|---|---|
| PF | Pressure filtration |
| PMA | Particle Mineral Analysis |
| PWD | Process water dam |
| The Project | Jervois Copper Project(the Project) |
| RF | Revenue factor |
| ROM | Run of Mine |
| SDG | Sustainable developmentgoals |
| SMC | SAG Mill Comminution |
| Sedgman | Sedgman PtyLtd |
| TSK | Tailings storage facility |
| UCS | Unconfined compressive strength |
| UG | Underground |
| USD | US dollar |
| Xenith | Xenith ConsultingPtyLtd |
Page 46
KGL RESOURCES LIMITED
==> picture [596 x 337] intentionally omitted <==
==> picture [137 x 101] intentionally omitted <==
2024 Ore Reserve Statement Jervois Project KGL Resources Limited January 2025
KGL Resources Limited 2024 Ore Reserve Statement
xenith.com.au
1
==> picture [195 x 147] intentionally omitted <==
Competent Person Consent Form
Pursuant to the requirements of ASX Listing Rules 5.6, 5.22 and 5.24 and
Clause 9 of the JORC Code 2012 Edition (Written Consent Statement)
Report name
Jervois Project – Ore Reserve Statement
(Insert name or heading of Report to be publicly released) (‘Report’)
KGL Resources
(Insert name of company releasing the Report)
Jervois Project
(Insert name of the deposit to which the Report refers)
31[st] January 2025 (Date of Report)
Statement
I, Iain Ross Insert Full Names(s)
confirm that I am the Competent Person for the Report and:
-
› I have read and understood the requirements of the 2012 Edition of the Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves (JORC Code, 2012 Edition).
-
› I am a Competent Person as defined by the JORC Code, 2012 Edition, having more than five years’ experience that is relevant to the style of mineralisation and type of deposit described in the Report, and to the activity for which I am accepting responsibility.
-
› I am a Member of The Australasian Institute of Mining and Metallurgy or the Australian Institute of Geoscientists or a ‘Recognised Professional Organisation’ (RPO) included in a list promulgated by ASX from time to time.
-
› I have reviewed the Report to which this Consent Statement applies.
KGL Resources Limited 2024 Ore Reserve Statement
xenith.com.au
2
I am a consultant working for: Xenith Consulting Pty Ltd
(Insert Company Name)
==> picture [195 x 147] intentionally omitted <==
and have been engaged by:
KGL Resources Ltd
(Insert Company Name)
to prepare the documentation for:
Jervois Project
(Insert Deposit Name)
on which the Report is based, for the period ended:
31[st] January 2025
(Insert date of Resource Estimate/Reserve Statement)
I confirm that I do not have any relationship with the reporting company that could be perceived by investors as a conflict of interest. I do not have any holdings in KGL Resources Ltd.
I verify that the Report is based on, and fairly and accurately reflects, in the form and context in which it appears, the information in my supporting documentation relating to Ore Reserves.
Signed: _____
KGL Resources Limited 2024 Ore Reserve Statement
xenith.com.au
3
Executive Summary
==> picture [195 x 147] intentionally omitted <==
2024 KGL Jervois Project Mineral Resource and Ore Reserves
The Revised May 2024 Mineral Resource for the KGL Jervois Project includes 28.95 Mt @ 1.76% Cu containing 509.8 kt Cu. The total October 2024 Ore Reserves for the Jervois Project are 14.38 Mt @ 1.77% Cu (with 0.26 g/t Au and 27.66 g/t Ag) containing 254.0 kt Cu. The stated Ore Reserves are based on the 2024 Feasibility Study Update (2024 FSU) Reserve Case Mine Plan.
Approximately 50% of the copper metal reported in the Mineral Resource is contained within the Proven and Probable Reserves. Approximately 50% of the total tonnage reported in the Mineral Resource is converted to Proven and Probable Ore Reserves.
2024 Feasibility Study Update
Xenith Consulting (Xenith) was engaged by KGL Resources in May 2024 to update the 2022 Feasibility Study (FS) for the Jervois Project (Project). The 2024 FSU is based on a recently revised geological model for the Reward deposit and 2022 models for Rockface and Bellbird deposits. All geological models were provided by Mr Ian Taylor of Mining Associates.
For the stated Ore Reserves, a Reserve Case mine design and schedule based on the 2024 FSU Life of Mine (LOM) plan was developed. For the Reserve Case, areas (lower levels) of the underground mines consisting of only or mostly (>90%) Inferred material were excluded, from the 2024 FSU LOM plan, along with the stopes at the extremities on the upper levels that contained a high proportion of Inferred material.
A total of 2.21 Mt of material has been excluded from the 2024 FSU LOM plan for the Reserve Case mine designs and schedule. The exclusions of these areas did not compromise the operability of the Reserve Case designs.
The 2024 FSU includes re-optimised open pits and underground mining inventories and revised open pit and underground designs. Life of Mine (LOM) mining and mill schedules were also updated to incorporate a larger processing plant with a 2.0 Mtpa throughput (an increase on the 1.6 Mtpa capacity specified in the 2022 FS).
The LOM schedule physicals were analysed in a financial model (developed by KGL Resources) to prove economic feasibility of the project. The LOM schedule and associated costings are integral components of the Jervois Project 2024 FSU.
The Jervois Project Ore Reserves as of October 2024 are shown below in Table 1.
KGL Resources Limited 2024 Ore Reserve Statement
xenith.com.au
4
==> picture [129 x 31] intentionally omitted <==
Table 1 – Jervois Project Ore Reserve Statement (31[st] October 2024)
| Material | Grade | Grade | Metal | |||||
|---|---|---|---|---|---|---|---|---|
| CuEq | Cu | Ag | ||||||
| Source | Mt | Cu (%) | Ag (g/t) | Au (g/t) | Au (Koz) | |||
| (%) | (kt) | (Moz) | ||||||
| Reward Open Pit | ||||||||
| Proven | 2.68 | 2.19 | 1.71 | 41.96 | 0.39 | 45.7 | 3.6 | 33.6 |
| Probable | 2.20 | 1.54 | 1.19 | 36.3 | 0.22 | 26.1 | 2.6 | 15.6 |
| Sub-total | 4.88 | 1.90 | 1.47 | 39.41 | 0.31 | 71.8 | 6.2 | 49.2 |
| Bellbird Open Pit | ||||||||
| Proven | 1.51 | 2.07 | 1.94 | 11.59 | 0.11 | 29.2 | 0.6 | 5.3 |
| Probable | 0.48 | 1.10 | 1.04 | 5.55 | 0.06 | 5.0 | 0.1 | 0.9 |
| Sub-total | 1.99 | 1.84 | 1.72 | 10.13 | 0.1 | 34.2 | 0.6 | 6.2 |
| Rockface Underground | ||||||||
| Proven | - | - | - | - | - | - | - | - |
| Probable | 2.96 | 2.74 | 2.55 | 16.58 | 0.18 | 75.4 | 1.6 | 17 |
| Sub-total | 2.96 | 2.74 | 2.55 | 16.58 | 0.18 | 75.4 | 1.6 | 17 |
| Bellbird Underground | ||||||||
| Proven | - | - | - | - | - | - | - | - |
| Probable | 0.37 | 1.77 | 1.65 | 13.23 | 0.08 | 6.0 | 0.2 | 1.0 |
| Sub-total | 0.37 | 1.77 | 1.65 | 13.23 | 0.08 | 6.0 | 0.2 | 1.0 |
| Reward Underground (including Marshall Underground) | ||||||||
| Proven | - | - | - | - | - | - | - | - |
| Probable | 4.19 | 1.97 | 1.59 | 31.38 | 0.37 | 66.5 | 4.3 | 49.0 |
| Sub-total | 4.19 | 1.97 | 1.59 | 31.38 | 0.37 | 66.5 | 4.3 | 49.0 |
| Total Proven | 4.19 | 2.15 | 1.79 | 31.03 | 0.29 | 74.9 | 4.2 | 39.0 |
| Total Probable | 10.19 | 2.05 | 1.76 | 26.27 | 0.25 | 179 | 8.6 | 83.4 |
| Total Reserve | 14.38 | 2.08 | 1.77 | 27.66 | 0.26 | 254 | 12.8 | 122.4 |
Notes:
- › The October 2024 Ore Reserves were estimated using the Jervois Base Metal Project Feasibility Study Mineral Resource Estimate - dated 23[rd] May 2024 by Mr Ian Taylor of Mining Associates at a revised cut off aligned to the reserves. There has been a subsequent update to the Resource models (for the Rockface and Reward deposits) but the engineering work to evaluate the full impact has not been completed.
KGL Resources Limited 2024 Ore Reserve Statement
xenith.com.au
5
==> picture [129 x 31] intentionally omitted <==
-
›
-
Quantities and grades in all tables may not add exactly due to rounding or weighting.
-
› The 2024 FSU Life of Mine open pit and underground designs and schedules include inferred tonnage. Areas (lower underground levels) of the Life of Mine Plan that are comprised of either all or large concentrations (>90%) of Inferred material have been excluded in development of a Reserve Case Mine Plan. Stopes at the extremities that contained a high proportion of Inferred material have also been excluded.
-
› The October 2024 stated Ore Reserves are based on the Reserve Case Mine Plan. Where Inferred material remains within the Reserve Case, zero grade has been assigned. The Inferred material contributes no revenue to the Reserve Case Mine Plan.
-
Inferred material is expected to be converted to Proven or Probable Ore Reserves as ongoing definition drilling is completed.
-
› The total of costs associated with the stated Ore Reserve with Inferred tonnes included was examined against the expected revenue from only the measured and indicated tonnages for all proposed open pit and underground mines. The inferred tonnage contained within the Reserve Case designs can be extracted profitably, even if no value is ascribed to the inferred material.
-
› Commodity price and exchange rate assumptions used for the Ore Reserves at the time of mine design / FSU (as provided by KGL Resources) are shown below in Table 2.
Table 2 – Ore Reserve Estimation Metal Price Assumptions
| USD | |
|---|---|
| Copper (lb) | 4.58 |
| Gold (Oz) | 2,400 |
| Silver (Oz) | 30.00 |
| Exchange Rate (US$/AU$) | 0.70 |
-
› All dollar figures in this report refer to Australian Dollars unless specifically indicated otherwise (e.g. USD).
-
› Commodity prices used in the estimation of the ore Reserves were provided by KGL Resources and are considered in line with reputable studies and consensus long term pricing. Further details are outlined in a later section of this report.
-
› The Marshall Underground mine is situated beneath the Reward Open Pit and is designed to extract a portion of the Reward Mineral Resource.
-
› The assumptions and data used to estimate the Jervois Project ore Reserves are outlined in this report. There is scope for further optimisation as the Project progresses to the execution phase and more data becomes available.
KGL Resources Limited 2024 Ore Reserve Statement
xenith.com.au
6
Table of Contents
==> picture [195 x 147] intentionally omitted <==
==> picture [455 x 585] intentionally omitted <==
----- Start of picture text -----
||||
|---|---|---|
|Competent Person Consent Form|2|
|Report name|2|
|Statement|2|
|Executive Summary|4|
|Table of Contents|7|
|List of Figures|10|
|List of Tables|12|
|List of Appendices|13|
|1.|Introduction|15|
|1.1|Project Description|15|
|1.2|Project Location|15|
|2.|Mining Limits|17|
|2.1|Project Tenements|17|
|2.2|Surface Feature Limits|19|
|2.3|Geological Depositional Limits|19|
|2.4|Practical Limits|19|
|2.5|Site Layout|19|
|3.|Geology|21|
|3.1|Geological Setting|22|
|3.2|Mineralisation|22|
|3.3|Geological Interpretation|22|
|4.|Metallurgy|23|
|5.|Geotechnical|26|
|5.1|Geotechnical Data|26|
|5.2|Geotechnical Design Criteria – Open Pit|27|
|5.3|Geotechnical Design Criteria – Underground|32|
|5.3.1|Stope Design Parameters and Guidelines|32|
|5.3.3|Backfill|34|
|5.3.4|Ground Support|34|
|6.|Optimisation Factors|37|
|6.1|Project Revenues|37|
|6.1.1|Commodity Prices|37|
----- End of picture text -----
KGL Resources Limited 2024 Ore Reserve Statement
xenith.com.au
7
| 6.1.2 Payables, Royalties and Penalty Elements |
37 | ||
|---|---|---|---|
| 6.1.3 Smelter Charges and Concentrate Transport Costs |
38 | ||
| 6.1.4 Metallurgical recoveries |
38 | ||
| 6.2 | Project Costs | 39 | |
| 6.3 | Metal Equivalent and Cut-off Grade | 40 | |
| 6.3.1 Metal Equivalent Calculation |
40 | ||
| 6.3.2 Mine Planning Cut-off Grades |
41 | ||
| 7. | Mineral Resources | 42 | |
| 7.1 | The Jervois Mineral Resource | 42 | |
| 7.2 | Mineral Resource Cut-off Grades | 43 | |
| 7.3 | Mineral Resource Estimate | 43 | |
| 7.4 | Mineral Resource Comparison | 45 | |
| 8. | Open | Pit Mining | 47 |
| 8.1 | Open Pit Optimisation | 47 | |
| 8.1.1 Pit Optimisation Process & Assumptions |
47 | ||
| 8.1.2 Reward Open Pit Optimisation Outcomes |
48 | ||
| 8.1.3 Bellbird Open Pit Optimisation |
50 | ||
| 8.2 | Open Pit Mine Design | 52 | |
| 8.2.1 Reward Open Pit |
52 | ||
| 8.2.2 Bellbird Open Pit |
54 | ||
| 8.2.3 Open Pit Design Quantities |
55 | ||
| 8.3 | Open Pit Mine Operations | 56 | |
| 8.3.1 Mining Equipment |
56 | ||
| 8.3.2 Drill & Blast Bench Heights |
58 | ||
| 8.3.3 Design Bench Heights |
58 | ||
| 8.3.4 Haul Road Parameters |
58 | ||
| 8.3.5 Minimum Operating Width |
59 | ||
| 8.3.6 Open Pit Dilution & Mining Recovery Assumptions |
59 | ||
| 8.4 | Jervois ROM and Waste Dump Design | 60 | |
| 8.4.1 Design Parameters |
60 | ||
| 8.4.2 Waste Haulage Routes |
61 | ||
| 8.4.3 Dump Capacities |
62 | ||
| 8.4.4 PAF and NAF Estimates |
62 | ||
| 8.4.5 Waste For Underground CRF Manufacture |
63 | ||
| 8.4.6 Water Management Considerations |
63 | ||
| 9. | Underground Mining | 64 |
KGL Resources Limited 2024 Ore Reserve Statement
xenith.com.au
8
| 9.1 | Stope Optimisation | 64 | |
|---|---|---|---|
| 9.1.1 Methodology and Optimisation Inputs |
64 | ||
| 9.1.2 Stope Orientation, Cut-off Grades and Pillars |
64 | ||
| 9.1.3 Stope Geometry and Dilution Assumptions |
65 | ||
| 9.2 | Stope Optimisation Results | 65 | |
| 9.2.1 Rockface Underground |
66 | ||
| 9.2.2 Bellbird Underground |
68 | ||
| 9.2.3 Reward Underground |
70 | ||
| 9.2.4 Marshall Underground |
72 | ||
| 9.3 | Underground Mine Design | 74 | |
| 9.3.1 Lateral Development |
74 | ||
| 9.3.2 Vertical Development |
78 | ||
| 9.3.3 Mine Design Schematics |
79 | ||
| 9.4 | Underground Mine Operations | 83 | |
| 9.4.1 Mining Equipment |
83 | ||
| 9.4.2 Development, Production and Backfill |
83 | ||
| 9.4.4 Mine Ventilation |
86 | ||
| 9.4.5 Mine Services |
89 | ||
| 10. | Mineral Processing | 92 | |
| 10.1 | Processing Plant Design | 92 | |
| 10.2 | Process Flow Sheet | 93 | |
| 10.3 | Sample Preparation Facility | 94 | |
| 10.4 | Tailings Storage Facility | 94 | |
| 10.5 | Concentrate Marketing & Transport | 95 | |
| 11. | Project Infrastructure | 97 | |
| 11.1 | Site Infrastructure Design | 97 | |
| 11.1.1 Warehouse |
97 | ||
| 11.1.2 Fuel Storage Facility |
97 | ||
| 11.1.3 Power Generation and Transmission |
97 | ||
| 11.1.4 Water Management |
98 | ||
| 11.1.5 Accommodation Camp |
98 | ||
| 11.1.6 Airstrip |
98 | ||
| 11.1.7 Ancillary Infrastructure |
99 | ||
| 12. | Regulatory Approvals | 100 | |
| 13. | Jervois Project Mine Plan | 100 | |
| 14. | Project Economics | 101 |
KGL Resources Limited 2024 Ore Reserve Statement
xenith.com.au
9
| 15. | Mineral Resources & Ore Reserves | Mineral Resources & Ore Reserves | Mineral Resources & Ore Reserves | 106 |
|---|---|---|---|---|
| 15.1 | Jervois | Mineral Resources and Ore Reserves | 106 | |
| 15.1.1 | Mineral Resources Summary (Revised May 2024) | 106 | ||
| 15.1.2 | Ore Reserves Summary (October 2024) | 107 | ||
| 15.2 | Open Pit Mineral Resources and Ore Reserves | 109 | ||
| 15.2.1 | Reward Open Pit | 109 | ||
| 15.2.2 | Bellbird Open Pit | 109 | ||
| 15.3 | Underground Mineral Resources and Ore Reserves | 110 | ||
| 15.3.1 | Rockface Underground | 110 | ||
| 15.3.2 | Bellbird Underground | 110 | ||
| 15.3.3 | Reward Underground | 110 | ||
| 15.3.4 | Marshall Underground | 111 | ||
| 15.4 | Financial Test of Reserve | 111 | ||
| 16. | Conclusions | 112 | ||
| Appendix A | JORC Table 1 | 113 | ||
| Appendix B | Jervois Project Geology | 136 |
List of Figures
Figure 1 – Jervois Project Location ................................................................................................ 16 Figure 2 – Jervois Project Current Tenements ................................................................................ 18 Figure 3 – General Layout of Site .................................................................................................. 20 Figure 4 – Jervois Project Geological Interpretation ........................................................................ 21 Figure 5 – 2024 FSU Mine Plan Predicted Annual Recoveries ........................................................... 24 Figure 6 – Pit Wall Terminology (after Read & Stacey) .................................................................... 28 Figure 7 – Reward Pit Geotechnical Domains .................................................................................. 30 Figure 8 – Bellbird Pit Geotechnical Domains .................................................................................. 30 Figure 9 – Decline and Capital Development Support Pattern .......................................................... 35 Figure 10 – Ore drive development support ................................................................................... 36 Figure 11 – Cable bolting Patterns for Intersections ........................................................................ 36 Figure 12 – Bellbird, Rockface and Reward Deposits ....................................................................... 42 Figure 13 – Reward Optimisation Margin vs Tonnage by Pit Shell .................................................... 48 Figure 14 – Reward Optimised Pit Shells E-W section ..................................................................... 49 Figure 15 – Reward Optimised Pit Shells N-S Section ...................................................................... 49 Figure 16 – Bellbird Optimisation Margin vs Tonnage by Pit Shell .................................................... 50 Figure 17 – Bellbird Optimised Pit Shells E-W Section ..................................................................... 51 Figure 18 – Bellbird Optimised Pit Shells N-S Section ...................................................................... 51
KGL Resources Limited 2024 Ore Reserve Statement
xenith.com.au
10
Figure 19 – Reward Open Pit N-S Section with Weathering Profile ................................................... 52 Figure 20 – Reward Open Pit Stage 1 ............................................................................................ 53 Figure 21 – Reward Open Pit Stage 2 ............................................................................................ 53 Figure 22 – Reward Pit Stages (Isometric) ..................................................................................... 54 Figure 23 – Bellbird Pit N-S Section with Weathering Profile ............................................................ 54 Figure 24 – Bellbird Open Pit ......................................................................................................... 55 Figure 25 – Typical Haul Road Schematic for a Dual Lane Ramp...................................................... 58 Figure 26 – Open Pit Haulage Routes ............................................................................................ 61 Figure 27 – Example Stope Orientation from the Rockface Mine. ..................................................... 64 Figure 28 – Rockface Stope Inventory by CuEq Grade. ................................................................... 66 Figure 29 – Rockface Scheduled Stopes by Fill Type ....................................................................... 67 Figure 30 – Bellbird Stope Inventory by CuEq Grade. ...................................................................... 68 Figure 31 – Bellbird Scheduled Stopes by Fill Type ......................................................................... 69 Figure 32 – Reward Stope Inventory by CuEq Grade. ..................................................................... 70 Figure 33 – Reward Scheduled Stopes by Fill Type ......................................................................... 71 Figure 34 – Marshall Stope Inventory by CuEq Grade. .................................................................... 72 Figure 35 – Marshall Scheduled Stopes by Fill Type ........................................................................ 73 Figure 36 – Decline Profile Section and Services Detail ................................................................... 76 Figure 37 – Ore Drive Profile Section and Services Detail ................................................................ 77 Figure 38 – Example Underground Level Layout for the Jervois Project ............................................ 77 Figure 39 – Rockface and Bellbird Underground – looking South ..................................................... 79 Figure 40 – Rockface and Bellbird Underground Mine Design – looking West ................................... 80 Figure 41 – Reward and Marshall Underground Mine Designs – looking West ................................... 81 Figure 42 – Reward and Marshall Underground Mine Designs – looking South .................................. 82 Figure 43 – Cemented Rock Fill Schematics .................................................................................... 84 Figure 44 – Example CRF 3% Mix and 5% Mix Mixing Bay (Sump) Designs ...................................... 84 Figure 45 – Jervois Primary Airflow Benchmarking .......................................................................... 88 Figure 46 – 2024 FSU Process Plant Arrangement .......................................................................... 92 Figure 47 – Flowsheet for Process Plant ......................................................................................... 93 Figure 48 – Tailing Storage Facility Location (looking Northeast) ..................................................... 95 Figure 49 – Concentrate Haulage Route ......................................................................................... 96 Figure 50 – Cumulative Ungeared Cashflows and Post Tax NPV ..................................................... 103 Figure 51 – Free Cashflow Present Value 8% ............................................................................... 103 Figure 52 – Sensitivity Chart (+/-20%) Relative to NPV ................................................................ 104 Figure 53 – Sensitivity Chart (+/-20%) Relative to IRR ................................................................. 104 Figure 54 – NPV Sensitivity to Metal Prices and Exchange Rates .................................................... 105
KGL Resources Limited 2024 Ore Reserve Statement
xenith.com.au
11
List of Tables Table 1 – Jervois Project Ore Reserve Statement (31[st] October 2024) ................................................5 Table 2 – Ore Reserve Estimation Metal Price Assumptions ...............................................................6 Table 3 – Details of the Jervois Project Tenure ............................................................................... 17 Table 4 – 2024 Metallurgical Recovery Formulae ............................................................................ 23 Table 5 – Reward Pit Slope Design Parameters .............................................................................. 29 Table 6 – Bellbird Pit Slope Design Parameters ............................................................................... 29 Table 7 – Underground Stope Design Parameters ........................................................................... 33 Table 8 – Commodity Price Assumptions ........................................................................................ 37 Table 9 – Payable Metal Percentages ............................................................................................. 37 Table 10 – Royalties Applicable to the Jervois Project ..................................................................... 38 Table 11 – Penalty elements ......................................................................................................... 38 Table 12 – Smelter Charges, Transportation Costs and Related Parameters ..................................... 38 Table 13 – Average Recoveries Used in Optimisation Revenue Calculations ...................................... 39 Table 14 – Project Costs Used in Optimisation Calculations ............................................................. 39 Table 15 – Mine Planning Cut-off Grades ....................................................................................... 41 Table 16 – Contributing Mineral Resources .................................................................................... 42 Table 17 – Jervois Project Resource Definition Drill Hole Summary .................................................. 43 Table 18 – Mineral Resource Estimate Cut-off Grades ..................................................................... 43 Table 19 – Revised May 2024 Jervois Mineral Resource Estimate ..................................................... 44 Table 20 – Change in Reward MRE due to Updated Cut-off Parameters ........................................... 45 Table 21 – Change in Bellbird MRE due to Updated Cut-off Parameters ........................................... 46 Table 22 – Change in Rockface MRE due to Updated Cut-off Parameters ......................................... 46 Table 23 – Pit Slope Design Parameters for Optimisation Process .................................................... 47 Table 24 – Open Pit Quantities - Volume........................................................................................ 55 Table 25 – Open Pit Quantities - Tonnes ........................................................................................ 56 Table 26 – Open Pit Production Rate ............................................................................................. 56 Table 27 – Open Pit Mining Equipment Schedule ............................................................................ 57 Table 28 – Bellbird Open Pit Ramp Width ....................................................................................... 59 Table 29 – Reward Open Pit Ramp Width ...................................................................................... 59 Table 30 – Open Pit Operating Width............................................................................................. 59 Table 31 – Open Pit Dilution & Recovery Assumptions .................................................................... 60 Table 32 – Waste Dump Design Parameters ................................................................................... 60 Table 33 – Waste Dump Capacities................................................................................................ 62 Table 34 – Waste PAF and NAF Designations ................................................................................. 63 Table 35 – Jervois Project Stope Optimisation Parameters .............................................................. 65 Table 36 – Rockface Underground Stope Optimiser Iterations ......................................................... 67 Table 37 – Bellbird Underground Stope Optimiser Iterations ........................................................... 69 Table 38 – Reward Underground Stope Optimiser Iterations ........................................................... 71 Table 39 – Marshall Underground Stope Optimiser Iterations .......................................................... 73 Table 40 – Development Design Profiles ........................................................................................ 74
KGL Resources Limited 2024 Ore Reserve Statement
xenith.com.au
12
Table 41 – Summary of Underground Lateral Development Metres .................................................. 74 Table 42 – Summary of Underground Lateral Development Metres .................................................. 78 Table 43 – Total Underground Mining Equipment by Year of Mining ................................................ 83 Table 44 – Airway Velocities .......................................................................................................... 86 Table 45 – Airway Dimensions and Airflow Quantities Based on Velocity Ranges .............................. 86 Table 46 – Friction Factors ............................................................................................................ 87 Table 47 – Forecast Annual Life of Underground Mine Working Inflows. .......................................... 90 Table 48 – Tailings Storage Facility Design Parameters ................................................................... 94 Table 49 – 2024 FSU Jervois Project Physicals Summary ............................................................... 101 Table 50 – 2024 FSU Jervois Project Costs Summary .................................................................... 102 Table 51 – 2024 FSU Jervois Project Economics Summary ............................................................ 102 Table 52 – Revised May 2024 Jervois Mineral Resource Summary ................................................. 106 Table 53 – Jervois Project Total Ore Reserves .............................................................................. 107 Table 54 – Jervois Proven Ore Reserves by Mine .......................................................................... 107 Table 55 – Jervois Probable Ore Reserves by Mine ....................................................................... 108 Table 56 – 2024 Reward Open Pit Ore Reserves ........................................................................... 109 Table 57 – Bellbird Open Pit Ore Reserves ................................................................................... 109 Table 58 – Rockface Underground Ore Reserves .......................................................................... 110 Table 59 – Bellbird Underground Ore Reserves ............................................................................ 110 Table 60 – Reward Underground Ore Reserves ............................................................................ 111 Table 61 – Marshall Underground Ore Reserves ........................................................................... 111
List of Appendices Appendix A JORC Table 1 .......................................................................................................... 113 Appendix B Jervois Project Geology ............................................................................................ 136
KGL Resources Limited 2024 Ore Reserve Statement
xenith.com.au
13
| Document issue approval | |||||||
| Title | 2024 Ore Reserve Statement | ||||||
| Project | Jervois Project | ||||||
| Client | KGL Resources Limited | ||||||
| Status | Final | Project/document no. | 3058KGLR | ||||
| Date | January 2025 | Revision no. | 1 | ||||
| Approvals | |||||||
| Name | Position | Signature | Date | ||||
| Prepared by | Phillip Cann | Senior Mining Engineer | 31/01/2025 | ||||
| Reviewed by | Mark Perquin | Technical Manager | 31/01/2025 | ||||
| Approved by | Iain Ross | Project Manager & CP | 31/01/2025 | ||||
| Distributions | |||||||
| Organisation | Attention | Hard copies | Electric copies | Actioned | |||
| KGL Resources Limited | Philip Condon | 0 | 1 | ||||
| KGL Resources Limited | Russell Dwyer | 0 | 1 | ||||
To be initialled and dated by the person who actions the issue of the documents.
DISCLAIMER
Xenith Consulting Pty Ltd makes no representation, undertakes no duty, and accepts no responsibility to any third party who may use or rely upon this document, or the drawings, information and data recorded in this document.
Any operating or capital cost estimation is current as at the date of estimation only.
The estimation assessed herein may change significantly and unexpectedly over a relatively short period (including as a result of general market movements and factors specific to the particular mine, project or deposit).
We do not accept responsibility or liability for losses arising from such subsequent changes in cost.
Without limiting the generality of the above comment, we do not assume responsibility or accept liability where the costing is relied upon after the expiration of 60 days from the date of the estimation or such earlier date if you become aware of any factors that affect the estimation.
KGL Resources Limited 2024 Ore Reserve Statement
xenith.com.au
14
1. Introduction
==> picture [195 x 147] intentionally omitted <==
1.1 Project Description
The Jervois Project (the Project) is in the south-eastern part of the Northern Territory (NT) of Australia, approximately 275 km linearly ENE of Alice Springs (Figure 1 below) which is approximately 380 km by road. The Project is approximately centred on 22.65°S and 136.27°E and located on the Jervois Pastoral Lease owned by the Jervois Pastoral Company Pty Ltd (JPC). JPC is not related to KGL.
The Project contains significant high‐grade copper Resources, as well as silver, and gold mineralisation across the various deposits proposed for mining. KGL Resources Ltd. (‘KGL’) will develop the Project to extract the existing and expanded base metal Resources, targeting copper ore within the Project area.
The Jervois Project will produce approximately 95 kt (dry tonnes) of copper concentrate per year for 10 years. The copper concentrate will be trucked 488 km from the mine site via the Plenty Highway, Urandangi North Road and the Bourke Developmental Road (National Road 83) to Mt Isa where it will be refined.
The Copper concentrate will contain silver and gold by-products that will be extracted during the refining process and credited to KGL under an existing contract with Glencore International AG.
1.2 Project Location
The main logistical service hubs relevant to the Project are Alice Springs, Adelaide, Darwin and Mt Isa. Major highways intersect with the Stuart Highway giving access in and out of the NT via the Barkly Highway into Queensland and the Victoria Highway into Western Australia. These highways are all weather and have regularly spaced fuelling stations for commercial transport.
A 3.2 km road connects the Project area to Lucy Creek Station Access Road (Road 194) which joins the Plenty Highway 16 km to the south. The Plenty Highway is mostly sealed toward the Stuart Highway 290 km to the west of the Project. The Stuart Highway extends between Adelaide, through Alice Springs to Darwin.
The Project area has a defined, brief wet season generally between November and April which can result in short delays to road and air access. The Project location is shown below in Figure 1.
KGL Resources Limited 2024 Ore Reserve Statement
xenith.com.au
15
==> picture [195 x 147] intentionally omitted <==
Figure 1 – Jervois Project Location
==> picture [423 x 634] intentionally omitted <==
KGL Resources Limited 2024 Ore Reserve Statement
xenith.com.au
16
2. Mining Limits
==> picture [195 x 147] intentionally omitted <==
2.1 Project Tenements
Three mineral leases (ML30180, ML30182 and ML30829) cover the area containing the current mineral Resources. A fourth mineral lease, ML32277, bounds the Project’s proposed groundwater borefield. The mineral leases cover the planned mining and processing infrastructure and the proposed location for the accommodation camp.
The exploration lease EL25429 allows potential for further drilling/discoveries close to the mineral leases. No issues with renewals of any of the required leases are evident. All tenements are 100% owned by KGL subsidiary Jinka Minerals Limited (JML).
The leases are listed below in Table 3 and Figure 2.
Table 3 – Details of the Jervois Project Tenure
| Area | Area | ||||||
|---|---|---|---|---|---|---|---|
| Title ID | Status | Granted | Expiry | Holder | Holding | ||
| Units | Measure | ||||||
| Granted | 02/02/2007 | 1/02/2025 | Jinka Minerals | 100% | 12 | Blocks | |
| EL 25429 | |||||||
| ML 30180 | Granted | 28/01/2014 |
27/01/2034 | Jinka Minerals | 100% | 33.21 | Hectares |
| Granted | 26/03/2014 | 25/03/2034 | Jinka Minerals | 100% | 481.7 | Hectares | |
| ML 30182 | |||||||
| ML 30829 | Granted | 18/08/2017 |
17/08/2032 | Jinka Minerals | 100% | 1438 | Hectares |
| Granted | 27/07/2021 | 17/08/2032 | Jinka Minerals | 100% | 124.1 | Hectares | |
| ML 32277 | |||||||
KGL Resources Limited 2024 Ore Reserve Statement
xenith.com.au
17
Figure 2 – Jervois Project Current Tenements
==> picture [194 x 147] intentionally omitted <==
==> picture [525 x 383] intentionally omitted <==
KGL Resources Limited 2024 Ore Reserve Statement
xenith.com.au
18
2.2 Surface Feature Limits
==> picture [195 x 147] intentionally omitted <==
The planned Unca Creek diversion is directly North of the Reward Open Pit and envelops the planned open pit crest in the 2024 FSU. This creek diversion is the key limit to the northern extent of the open pit. This is a change from the 2022 FS because of two key factors:
-
› The revision of the Reward mineral Resource geological model; and
-
› changes to the key economic assumptions used in the 2024 FSU open pit optimisation.
There are no other limiting delineations (such as waterways, dams, native title interests, heritage concerns or environmental concerns) for the open pit and underground optimisations and designs.
2.3 Geological Depositional Limits
The Mine Plan lies within the extents of the known geological deposits. Additional deposits are being investigated but currently do not have any impact on the 2024 FSU Mine Plan in respect of the delineated mine limits that are relevant to it.
2.4 Practical Limits
Both the open pit and underground designs that form the basis for the 2024 FSU are designed in accordance with industry standards and regulatory guidelines. The open pit designs are not overly large or elongated and as such pose no issue to practical haulage limits.
The extent of each underground mine conforms to mine design experience across Australia, and likewise, the mine designs do not present any practical limitations.
The Project ROM area is located adjacent to the processing plant near the Reward Open Pit. This is approximately 4 km from the Rockface and Bellbird deposits. Surface haulage of open pit ore from the Bellbird mine to the ROM is within haulage lengths seen at similar operations. Fleet numbers for open pit operations are based on haulage ex-pit to the ROM.
Haulage from the Bellbird and Rockface Underground mines to the ROM using the underground fleet is outside the practical limits for that type of equipment. Underground haulage modelling for Rockface and Bellbird is therefore based on haulage from underground to near Bellbird Open Pit for later rehandling to the ROM using larger surface equipment.
2.5 Site Layout
The Jervois Project is designed as a remote standalone facility and comprises all components for operations. A general site layout is shown below in Figure 3.
KGL Resources Limited 2024 Ore Reserve Statement
xenith.com.au
19
==> picture [195 x 147] intentionally omitted <==
Figure 3 – General Layout of Site
==> picture [435 x 627] intentionally omitted <==
KGL Resources Limited 2024 Ore Reserve Statement
xenith.com.au
20
==> picture [195 x 147] intentionally omitted <==
3. Geology
The major mineral deposits in the Jervois Project area – Reward, Bellbird and Rockface – are generally sub-vertical strata-bound lodes that form a distinctive, kilometre-scale, J-fold within the host rock. This J-fold is illustrated below in Figure 4.
Figure 4 – Jervois Project Geological Interpretation
==> picture [426 x 465] intentionally omitted <==
The geology, mineralisation and mineral Resources contained within the Mineral Resources Report and the 2024 FSU are focused on the copper-gold-silver (Cu-Au-Ag) Reward, Bellbird and Rockface deposits. Lead-zinc (Pb-Zn) mineralisation such as the Reward South deposit are not developed within the document.
At all three Cu-Au-Ag deposits, the mineralization is broadly similar, although each deposit differs in its detail, especially the local geological structures.
KGL Resources Limited 2024 Ore Reserve Statement
xenith.com.au
21
==> picture [195 x 147] intentionally omitted <==
3.1 Geological Setting
The geological setting and mineralisation are described by Mining Associates Pty Ltd in the “Mineral Resource Estimate, Reward, Bellbird and Rockface Deposits, Jervois Project, Northern Territory, Australia” (MA2218-2-2 Jervois Resource Report, dated 31 August 2022).
Geologically, the Project is located on the northern margin of the Paleoproterozoic Aileron Province and its faulted contact with late Neoproterozoic-Cambrian aged sedimentary rocks of the Georgina Basin.
The Aileron Province of the eastern Arunta region, forms part of the North Australian Craton. The base metal mineralization is hosted by metasedimentary rocks of the Bonya Metamorphics formation which is a unit of lower-middle amphibolite grade meta-sediments.
The Bonya formation is folded with the deformation giving rise to the characteristic J-shape associated with the Jervois ranges. Three main structural deformations are recognised in the area (Schmid, Schaubs & Otto, 2018):
-
› Layer-parallel foliation and rare isoclinal folds;
-
› Isoclinal folding of bedding and foliation producing dominant structures; and
-
› Folding of structures, late dextral transpression leading to a formation of map-scale J-fold as a drag fold.
3.2 Mineralisation
Mineralisation is hosted by various units of the Bonya Metamorphics, mostly occurring as massive to semi-massive layers of sulphides. Sulphides also occur as associated quartz veins and as thin interlayers in meta-mudstone and calc-silicates. The mineralisation typically consists of chalcopyrite and pyrite.
Alteration zones are associated with mineralisation and magnetite forms part of the alteration assemblage and is ubiquitous in the mineralized areas of Reward and Rockface, but less so at Bellbird. Sulphide textures vary from finely disseminated to stringers and veinlets to semi-massive.
The thickness of the mineralised zones vary extensively, from less than a meter to more than twenty meters.
Two main styles of mineralisation and alteration/metamorphic mineral assemblages are recognised as:
-
› Lower grade, primary syn-depositional or strata bound sulphides; and
-
› higher grade, structurally controlled shoots, representing both remobilised strata bound syngenetic mineralisation, and a possible late tectonic intrusion-related mineralising event.
Structurally controlled shoots are the result of reworked and remobilised primary strata-bound base metal mineralisation, during and after peak metamorphism, by granite intrusions. The shoots are observed as massive or semi-massive sulphide-magnetite veins and chalcopyrite-rich brecciated veins.
Oxidation due to surface weathering effects is relatively limited, with the oxidised zone being transitional from surface to base of oxidation (approximately 10-15 m below surface). No significant zone of complete oxidation can be delineated in the mineralisation.
3.3 Geological Interpretation
The full geological interpretation of the Jervois Project area is included in Appendix B.
KGL Resources Limited 2024 Ore Reserve Statement
xenith.com.au
22
==> picture [195 x 147] intentionally omitted <==
4. Metallurgy
Multiple phases of test work and analysis have been carried out by several consultants since 2012. In 2021 Core Metallurgy undertook test work to support the Jervois Project Feasibility Study. The work confirmed the primary grind, regrind size targets and the requirement for two stages of cleaner flotation.
In 2022 Sedgman oversaw the reassignment of new metallurgical domains, re-interpretation of results and collation of all recent and historical results into a comprehensive report with metallurgical performance and recovery predictions inclusive of new and preceding test work results for the 2022 Jervois Project Feasibility Study.
Formulae developed by Sedgman are used to estimate recovery for the minerals within the oxide and sulphide ore streams. The recovery formulae is the basis of the average recoveries that are used in the Project optimisation process.
Average recoveries have been provided by KGL Resources and are provided in Section 6. The full 2024 Jervois Project recovery formulae are shown below in Table 4.
Table 4 – 2024 Metallurgical Recovery Formulae
| Metal | |||
|---|---|---|---|
| Range | Predictive Formulae | R2 | |
| Performance | |||
| Sulphide | |||
| <0.5% Cu | Cu Rec = 0.202 x Ln(CuHG%) + 1.9601 | - | |
| Copper Recovery | |||
| ≥0.5% Cu | Cu Rec = 1.0485 x ((CuHG%)^0.0325) | 0.382 | |
| Gold Recovery | Au Rec = 0.691 x ((Bi Rec)^0.723) | 0.742 | |
| Silver Recovery | Ag Rec = (0.88 x Bi Rec) + 0.043 | 0.708 | |
| Bismuth Recovery | Bi Rec = 0.2469 x (Ln(Pb Rec) + 0.8204 | 0.492 | |
| Bismuth Recovery | Bi Rec = 0.093 x Ln(BIHG ppm) + 0.0321 | 0.311 | |
| (secondary) | |||
| Uranium Recovery | U Rec = 1E-08 x e^(17.484*(Cu Rec%)) | 0.596 | |
| Fluorine Recovery | F Rec = 0.24% (Constant) | - | |
| Lead Conc. Grade | Pb Concentrate Grade = (8.5 x Pb Feed Grade) - | 0.890 | |
| 0.0004 | |||
| Zinc Conc. Grade | Zn Concentrate Grade = (9 x Zn Feed Grade) - | 0.861 | |
| 0.0002 | |||
| Oxide | |||
| <0.2% Cu | Cu Rec = 0% | - | |
| Oxide Copper | 0.2% ≥ Cu | Cu Rec = (34.675 x CuHG%) - 0.0646 | 0.984 |
| Recovery | ≤ 2.5% Cu | ||
| >2.5% Cu | Cu Rec = 80% | - |
KGL Resources Limited 2024 Ore Reserve Statement
xenith.com.au
23
| Metal | ||
| Range | Predictive Formulae | |
| Performance | ||
| Gold Recovery | Au Rec = (0.685 x Bi Rec) + 0.126 | |
| Silver Recovery | Ag Rec = (1.326 x Bi Rec) - 0.0295 | |
| Bismuth Recovery | Bi Rec = (0.873 x Cu Rec) - 0.174 | |
| Oxide | ||
| Uranium Recovery | U Rec = 1E-08 x e^(17.484*(Cu Rec%)) | |
| Fluorine Recovery | F Rec = 2.52% (Constant) | |
| Lead Conc. Grade | Pb Concentrate Grade = (8.5 x Pb Feed Grade) - | |
| 0.0004 | ||
| Zinc Conc. Grade | Zn Concentrate Grade = (9 x Zn Feed Grade) - | |
| 0.0002 |
Key observations about the relationships and formulae are:
-
› Sulphide copper recoveries are consistently high for all copper feed grades and open pit and underground ores;
-
› Oxide copper recovery decreases rapidly at < 1.5% Cu feed grade. Oxide ore feed grades much below 1.5% Cu aren’t expected to be economically recoverable;
-
› Gold and silver recoveries are associated with bismuth recoveries;
-
› The copper, gold and silver metallurgical recoveries on an annual basis targeting a 27% copper concentrate grade are presented in Figure 5;
Figure 5 – 2024 FSU Mine Plan Predicted Annual Recoveries
==> picture [454 x 235] intentionally omitted <==
KGL Resources Limited 2024 Ore Reserve Statement
xenith.com.au
24
==> picture [129 x 31] intentionally omitted <==
-
› Sulphide bismuth recovery is associated with lead recovery due to high proportions of galenobismutite. The population of lead assays in the block model is not as substantial as that for bismuth so a secondary bismuth relationship was developed for bismuth recovery against bismuth feed grade relationship;
-
› Transition bismuth recovery appears to be more associated with copper recovery rather than lead;
-
› Sulphide fluorine recovery was determined to be very small and not related to any key elements defined. This result is consistent with fluorine present in non-sulphide gangue that should be readily rejected via an effective flotation flowsheet;
-
› Transition fluorine recovery was small at a constant recovery of 2.5% F. The increase in fluorine recovery with respect to sulphide ores is possibly a result of increased non-sulphide gangue recovery when processing this more difficult material;
-
› Lead and zinc feed grades in flotation feed need to be controlled to ≤ 0.5% Pb or Zn. If not controlled effectively (i.e., selective mining, or blending of ores or concentrates), lead and zinc grades > 3% in copper concentrate might make it difficult to achieve the target copper concentrate grade, which will result in valuable metal (Cu, Au and Ag) recovery losses; and
-
› Uranium recoveries are expected to be low (typically between 10% to 20% U).
KGL Resources Limited 2024 Ore Reserve Statement
xenith.com.au
25
5. Geotechnical
==> picture [195 x 147] intentionally omitted <==
Geotechnical recommendations cited and used within the 2024 FSU have been sourced from the three reports provided by Entech that cover the open pit and underground mining areas. These reports are listed below:
-
› Open Pit Mining Geotechnical Feasibility Study – June 2020 [ENT_0603];
-
› Geotechnical Open Pit Design Review – March 2022 [ENT_0831]; and
-
› Underground Mining Geotechnical Definitive Feasibility Study – October 2021 [ENT_0767_KGL].
The data collected is considered sufficient for the commencement of mining, but the location of the testing is biased towards the hanging wall side of the orebodies, and generally within the upper two thirds of the planned underground mines.
5.1 Geotechnical Data
The open pit report is based on a total of nine dedicated geotechnical diamond drill holes that are in the vicinity of the proposed Reward and Bellbird pit walls. The length of these drill holes totals approximately 1263 m.
The drill holes were used for the collection of detailed geotechnical data including rock mass and structure characterisation, and oriented structure data. Several samples were selected from diamond drill core from the geotechnical and Resource geology drill holes to perform material properties testing, including:
-
› Uniaxial compressive strength – 62 samples;
-
› Uniaxial tensile strength – 42 samples;
-
› Elastic properties (Young’s Modulus and Poisson’s Ratio) - 28 samples;
-
› Hoek triaxial – 26 samples; and
-
› Direct shear tests – 22 samples.
For the underground geotechnical assessment, a total of 1091 m of drill core was logged for geotechnical detail during July and August 2021. From this total 460 m was physically logged on site from existing exploration drilling and four dedicated geotechnical drill holes. The remaining core was logged from core photographs.
No structural measurements were able to be taken from the core logged on site in 2021, but a total of 560 structural measurements were measured across the three deposits during the pre-feasibility study (PFS) logging campaign.
The 2021 campaign complimented the 4404 m of logging undertaken for the PFS in 2020. The data from 2020 and 2021 was included in a comprehensive database of geotechnical information recorded for the three mining areas. The complete drill core dataset was analysed by Entech and forms the basis of the previously referenced underground geotechnical study.
This information has allowed a full characterisation of the rock mass, improved assessment of stable stoping span predictions, and ground support recommendations for the four underground mines. Entech did however state that limited diamond drilling was available to be geotechnically logged for the following areas:
-
› Reward Decline from the open pit and lower northern extent of the Reward orebody;
-
› Lower levels of Rockface and the lower Rockface Decline; and
-
› Bellbird orebody and lower capital development in Bellbird South.
The number and type of rock properties testing undertaken across the two underground programs consist of:
-
› Uniaxial compressive strength – 108 samples;
-
› Indirect Brazilian tensile strength – 129 samples;
-
› Elastic properties (Youngs Modulus & Poisson’s Ratio) – 80 samples;
KGL Resources Limited 2024 Ore Reserve Statement
xenith.com.au
26
-
› Direct Shear Strength/Cohesion of defects – 13 samples;
-
› Hoek Triaxial Single Stage – 24 samples; and
==> picture [195 x 147] intentionally omitted <==
- › Bulk density – 265 samples.
The data collected is considered sufficient for the commencement of mining, but the location of the testing is biased towards the hanging wall side of the orebodies, and generally within the upper two thirds of the planned underground mines.
5.2 Geotechnical Design Criteria – Open Pit
Pit wall slope design analysis was undertaken, including kinematic spill berm width and limit equilibrium slope stability analysis, to determine the slope design parameters for inter-ramp and overall slope angle stability.
The open pit geotechnical study concludes that based on the geotechnical data available, a slope stability assessment supports an inter-ramp angle in fresh rock of 58° for both the Reward and Bellbird Open Pits. Entech states that the revised slope design parameters for fresh rock are appropriate for feasibility level studies.
In addition, Entech have validated the previously recommended slope design parameters for oxide and transitional materials and that these are also considered appropriate for feasibility level optimisation and design.
The kinematic analysis indicated that the probability of any of the three bench-scale failure modes (planar, wedge and toppling) occurring on the major east and west pit walls at a bench face angle of up to 80° was generally low to moderate and within the acceptable limits of design.
Higher probability of planar, wedge and flexural toppling failure modes were apparent on the major pit walls in places. However, spill berm widths were designed to account for these higher probability failures. The limit equilibrium slope stability analysis indicated that slope instability at an inter-ramp or overall (pit) scale is unlikely within the slope design parameter recommendations.
It is expected that bench faces will break back to foliation cleanly. It is recommended that an observational design approach be undertaken, where regular review of bench-scale performance is undertaken, and the design adjusted as necessary.
A description and illustration of the terminology relating to the various slope parameters is presented below in Figure 6.
KGL Resources Limited 2024 Ore Reserve Statement
xenith.com.au
27
==> picture [128 x 31] intentionally omitted <==
Figure 6 – Pit Wall Terminology (after Read & Stacey)
==> picture [431 x 447] intentionally omitted <==
Based upon the analysis performed for 2024 FSU, the final slope design parameters are summarised for Reward in Table 5 and Bellbird in Table 6 below.
KGL Resources Limited 2024 Ore Reserve Statement
xenith.com.au
28
==> picture [195 x 147] intentionally omitted <==
Table 5 – Reward Pit Slope Design Parameters
| Bench height | Spill Berm | ||||
|---|---|---|---|---|---|
| Domain | Material | Batter BFA (°) | IRA (°) | ||
(m) |
Width (m) | ||||
| Transitional | 10 | 55 | 5 | 40 | |
| Reward | |||||
| North | Fresh | 20 | 80 | 9 | 58 |
| Transitional | 10 | 55 | 5 | 40 | |
| Reward | |||||
| East | Fresh | 20 | 80 | 9 | 58 |
| Transitional | 10 | 55 | 5 | 40 | |
| Reward | |||||
| South | Fresh | 20 | 80 | 9 | 58 |
| Transitional | 10 | 55 | 5 | 40 | |
| Reward | |||||
| West | Fresh | 20 | 80 | 9 | 58 |
Table 6 – Bellbird Pit Slope Design Parameters
| Bench height | Spill Berm | ||||
|---|---|---|---|---|---|
| Domain | Material | Batter BFA (°) | IRA (°) | ||
(m) |
Width (m) | ||||
| Transitional | 10 | 55 | 5 | 40 | |
| Bellbird | |||||
| North | Fresh | 20 | 80 | 9 | 58 |
| Transitional | 10 | 55 | 5 | 40 | |
| Bellbird | |||||
| East | Fresh | 20 | 80 | 9 | 58 |
| Transitional | 10 | 55 | 5 | 40 | |
| Bellbird | |||||
| South | Fresh | 20 | 80 | 9 | 58 |
| Transitional | 10 | 55 | 5 | 40 | |
| Bellbird | |||||
| West | Fresh | 20 | 80 | 9 | 58 |
The 2024 FSU pit designs illustrating the geotechnical domains referenced in Table 5 and Table 6 are shown in Figure 7 and Figure 8 below.
KGL Resources Limited 2024 Ore Reserve Statement
xenith.com.au
29
==> picture [195 x 147] intentionally omitted <==
Figure 7 – Reward Pit Geotechnical Domains
==> picture [313 x 308] intentionally omitted <==
Figure 8 – Bellbird Pit Geotechnical Domains
==> picture [313 x 252] intentionally omitted <==
KGL Resources Limited 2024 Ore Reserve Statement
xenith.com.au
30
==> picture [128 x 31] intentionally omitted <==
Further details and recommendations regarding the slope design parameters described by Entech in ENT_0831_KGL are outlined:
-
› Slope dewatering measures undertaken, including inflow monitoring and consideration for depressurisation holes;
-
› Good management of surface water, providing drainage away from the pit and prevention of ponding,
-
› Monitoring of ground water drawdown within pit wall limits;
-
› Implementation of thorough ground control management plan with provision for:
-
Good wall control blasting practices and achievement of spill berm widths, limited crest loss, and clean batters; and
-
Sound wall scaling practices.
-
› Ongoing routine monitoring of slopes and slope stability including:
-
Prism monitoring;
-
Visual inspections of wall conditions and the perimeter of the pit;
-
Crack monitoring using extensometers;
-
Routine geotechnical mapping and refinement of the geotechnical model;
-
Maintain a register of geotechnically significant events (i.e. rockfall, slips, cracking and unusual water occurrence); and
-
Periodic regular geotechnical review.
-
› The mining operation will perform a detailed risk assessment prior to implementation of the proposed design described in this report.
KGL Resources Limited 2024 Ore Reserve Statement
xenith.com.au
31
==> picture [195 x 147] intentionally omitted <==
5.3 Geotechnical Design Criteria – Underground
For the Jervois Underground mines, Entech states that the geotechnical sufficiency of data for the upper half of the Reward/Marshall, Rockface and Bellbird deposits meets feasibility level requirements. The lower portion of each deposit meets pre-feasibility levels of confidence. The report states that the rock masses at all three deposits shows very little variation spatially. This may indicate that rock mass conditions at depth may not vary greatly from what is expected and experienced in the early years of each mine.
Entech did note that the location of the Marshall, Reward, Rockface and Bellbird decline spirals as well as other permanent underground infrastructure such as ventilation shafts and mine services corridors, will require dedicated geotechnical drilling.
Analyses have been undertaken by Entech to define stoping parameters for the underground mining areas at the Project. These included stope stability analyses using the Mathews Potvin Stability Graph Method, overbreak/expected dilution estimation, pillar strength calculations, kinematic ground support analysis and numerical modelling.
Indications are that sub-level open stoping (SLOS) with backfill (both rock and cemented rock fill) using 30 m level spacings at Rockface, Reward (and Marshall), and 20 m spacings at Bellbird will be suitable for the narrow, generally steeply dipping orebodies at the Project. Extraction will also use a mix of bottom up and top down depending on the scheduling requirements.
Rock mass characteristics of the mining areas will determine if backfill with cemented rockfill (CRF) is used or rib pillars are left within the open stopes. Most SLOS will be extracted longitudinally with a mix of central and end access depending in their spatial location and lateral extent of the stopes. Some thicker portions of the orebody could be mined using a SLOS transverse layout.
5.3.1 Stope Design Parameters and Guidelines
The immediate hanging wall (HW) and footwall (FW) of the mineralization are comprised of the Bonya Schist units (Pelite, Psammite, and Psammopelite). Using the Q rock mass rating system the rock mass conditions in both the HW and FW can generally be characterised as good at Reward and Rockface, and poor to good at Bellbird.
Pervasive bedding/foliation throughout the rock units will dominate stope wall behaviour with the possibility of slabbing and sliding failure types occurring along foliation planes. To control this, stope spans should be restricted, undercutting of foliation should be avoided and drill and blast practices should be performed to a high standard. Prior to stoping occurring at any of the underground mines, detailed geotechnical mapping of ore drives must be undertaken for input into stope design and validation of rock mass parameters determined within the Entech study.
Continual review of stope performance will be undertaken throughout the life-of-mine. This will typically include, but is not limited to:
-
› Adjustments to stope spans if locally poorer ground conditions are encountered. If better than expected ground conditions are encountered, stope spans may be able to be increased;
-
› Geotechnical mapping of ore drives as input into stope design;
-
› Regular external geotechnical review;
-
› Periodic review of stope parameters and drill and blast designs based on practical results for dilution and span performance; and
-
› Periodic review of the placement and design of rib and sill pillars to optimise both extraction and geotechnical performance based on the ground conditions and performance of surrounding stopes.
The recommended stope parameters and dilution estimates for each of the underground deposits are outlined below in Table 7. The stope parameters referenced for Reward include both the Reward and Marshall lodes which are mined separately as individual underground mines.
KGL Resources Limited 2024 Ore Reserve Statement
xenith.com.au
32
==> picture [195 x 147] intentionally omitted <==
Table 7 – Underground Stope Design Parameters
| Orebody | Parameters | Hanging Wall | Ore Zone |
|---|---|---|---|
| Reward / Marshall | |||
| Allowable Strike Length | 25 – 30 m | 25 – 30 m | |
| Reward North Upper | |||
| Dilution/ELOS | 0.0 – 0.5 m | 0.0 – 0.5 m | |
| Allowable Strike Length | 20 m | 20 m | |
| Reward North Lower | |||
| Dilution | 0.0 – 0.5 m | 0.0 – 0.5 m | |
| Allowable Strike Length | 20 - 25 m | 35 m | |
| Reward North Footwall Stopes | |||
| Dilution | 0.0 – 0.5 m | 0.0 – 0.5 m | |
| Allowable Strike Length | 20 - 25 m | 25 – 30 m | |
| Reward South | |||
| Dilution/ELOS | 0.0 – 0.5 m | 0.0 – 0.5 m | |
| Rockface | |||
| Allowable Strike Length | 25 – 30 m | 20 – 30 m | |
| Rockface North | |||
| Dilution | 0.0 – 0.5 m | 0.0 – 0.5 m | |
| Allowable Strike Length | 30 – 35 m | 30 – 35 m | |
| Rockface South Upper | |||
| Dilution | 0.0 – 0.5 m | 0.0 – 0.5 m | |
| Allowable Strike Length | 25 – 30 m | 25 – 30 m | |
| Rockface South Lower | |||
| Dilution | 0.0 – 0.5 m | 0.0 – 0.5 m | |
| Bellbird | |||
| Allowable Strike Length | 30 m | 20 – 25 m | |
| Bellbird South Combined | |||
| Dilution | 0.0 – 0.5 m | 0.0 – 0.5 m | |
| Allowable Strike Length | 35 m | 35 m | |
| Bellbird South Upper | |||
| Dilution | 0.0 – 0.5 m | 0.0 – 0.5 m | |
| Allowable Strike Length | 10 m | 15 m | |
| Bellbird South Lower | |||
| Dilution | 0.0 – 0.5 m | 0.0 – 0.5 m | |
| Allowable Strike Length | 20 m | 20 m | |
| Bellbird North | |||
| Dilution | 0.0 – 0.5 m | 0.0 – 0.5 m | |
KGL Resources Limited 2024 Ore Reserve Statement
xenith.com.au
33
==> picture [195 x 147] intentionally omitted <==
5.3.3 Backfill
Cemented rock fill (CRF) is planned to be used in higher grade zones within the underground mines. The use of CRF will allow bottom up mining and as close to 100% recovery while maintaining global stability as extraction continues level by level.
In lower grade zones, where geotechnically feasible, open stoping with rib and sill pillars will be used; no backfill will be required in these zones.
CRF manufacturing is planned to preference waste rock from the underground mines but where required surface stockpiles. The waste rock will be mixed with cement slurry of various binder (general purpose cement) content to create the required bond strength between the rock fragments. Local groundwater will also be used. No issues with the groundwater or waste rock are expected.
Backfill requirements and strengths vary across the mining areas, controlled mainly by stope width and mining sequence and schedule. Most production will occur from narrow stopes the width of the ore drive or less (<6 m) with sub level intervals of 30 m. In some areas stopes with widths of up to 25 m maybe necessary.
For narrow stopes, CRF unconfined compressive strengths (UCS) of 275 kPa is expected, while wider stopes may require fill strengths of approximately 450 kPa.
Based on the 2024 FSU LOM schedules, a peak volume of approximately 370,000 m[3 ] per year of CRF will be required. Where backfill is used fill rates average between 435 and 700 t (~200 – 325 m[3] ) per loader per day which is within normal ranges for this method of fill.
5.3.4 Ground Support
Ground support standards are based on the rock mass characterisation from detailed geotechnical logging of drill core from the Project. Due to the similar nature of the rock types in the underground mines, the support and reinforcement is currently consistent between each mine.
Review of the ground support standards will be required after development mining has commenced with any gathered geotechnical data incorporated to improve and validate the recommended standards.
For increased life and serviceability, it is recommended that fully encapsulated resin-grouted rebar type rock bolts are used as the primary support in capital development. Galvanised split-set bolts are at this stage appropriated for ore drive and other temporary development.
Geotechnical analysis indicates that there is no requirement for the use of shotcrete as a surface support. Small, isolated faults and poorer ground were infrequently observed, and mesh is recommended as the primary surface support.
5.3.4.1 Ground Support Standards
The recommended ground support standards for the various development profile types are based on kinematic analysis.
5.3.4.1.1 Decline and Capital Development
Development ground support for decline and access development will be in-cycle pattern bolting using:
-
› Galvanised 2.4 m long, resin grouted (gewi) bolts or other long-life bolt of similar performance in the backs and shoulders;
-
› Galvanised 2.4 m friction bolts on the walls; and
-
› Galvanised 5.6 mm gauge 100 x 100 mm aperture weld mesh to within 2.0 m of the floor.
KGL Resources Limited 2024 Ore Reserve Statement
xenith.com.au
34
==> picture [128 x 31] intentionally omitted <==
Figure 9 – Decline and Capital Development Support Pattern
==> picture [297 x 284] intentionally omitted <==
The bolting pattern shown above in Figure 9 is described:
-
› Bolts to be spaced on a 1.2 m maximum inter-ring spacing;
-
› 1.4 m maximum distance between rings; and
-
› 11 bolts per ring.
5.3.4.1.2 Ore Drive Development
Development ground support for ore drive development will be in-cycle pattern bolting using:
-
› Galvanised 2.4 m long, 46 mm friction bolts in the backs, shoulders and walls; and
-
› Galvanised 5.6 mm gauge 100 x 100 mm aperture weld mesh to within 2.2 m of the floor.
KGL Resources Limited 2024 Ore Reserve Statement
xenith.com.au
35
==> picture [195 x 147] intentionally omitted <==
Figure 10 – Ore drive development support
==> picture [276 x 254] intentionally omitted <==
The bolting pattern shown above in Figure 10 is described:
-
› Bolts to be spaced on a 1.2m maximum inter-ring spacing;
-
› 1.4m maximum distance between rings; and
-
› 9 bolts per ring installed.
5.3.4.1.3 Cable Bolting of Intersections
Two cable bolting patterns will be employed for different intersection designs:
-
› For 5.0 m wide drives – minimum of 8 x single strand 6m cable bolts;
-
› For 5.5 m wide drives – minimum of 10 x single strand 6m cable bolts; and
-
› All cable bolts to be fully grouted and plated.
The cable bolt patterns described above are shown below in Figure 11. It is recommended that four way intersections be avoided and as such cable bolting patterns for these intersections are not provided.
Figure 11 – Cable bolting Patterns for Intersections
==> picture [483 x 148] intentionally omitted <==
KGL Resources Limited 2024 Ore Reserve Statement
xenith.com.au
36
6. Optimisation Factors
==> picture [195 x 147] intentionally omitted <==
6.1 Project Revenues
6.1.1 Commodity Prices
The commodity prices provided below in Table 8 were used for:
-
› Mine Optimisation (Xenith)
-
› Mine Design and Scheduling (Xenith)
Table 8 – Commodity Price Assumptions
| USD | Data source | |
|---|---|---|
| Copper (lb) | 4.90 | KGL supplied |
| Gold (Oz) | 2,400 | KGL supplied |
| Silver (Oz) | 32.00 | KGL supplied |
| Exchange Rate (US$/AU$) | 0.70 | KGL supplied |
KGL has undertaken additional economic analysis (described in Section 14 and 15) on the Project based on updated market consensus pricing. The updated pricing is discussed in further detail in Section 14. Additional analysis where updated pricing is used includes:
-
› 2024 FSU Project economic analysis (KGL)
-
› 2024 Ore Reserve case validation (Xenith)
6.1.2 Payables, Royalties and Penalty Elements
The payable metal percentages are provided below in Table 9 and were used for the optimisation, mine design, mine scheduling and Ore Reserve Validation.
Table 9 – Payable Metal Percentages
| Item | Payable (%) | Data source |
|---|---|---|
| Copper | 96.5 | KGL supplied |
| Gold | 90 | KGL supplied |
| Silver | 90 | KGL supplied |
The government royalties relevant to the Project are provided below in Table 10. On 1 July 2024, the Minerals Royalty Act 2024 (MRA24) imposed an ad valorem royalty scheme in the Northern Territory for new mines. As the Project will commence production after 1 July 2024, the MRA24 royalty arrangements will apply to the Project.
Under MRA24, royalties for minerals are calculated based on the value of a mineral and by applying a royalty rate based on the level of processing performed on the mineral. A deduction is allowed from the value of the mineral for shipping costs incurred in the Territory.
KGL Resources Limited 2024 Ore Reserve Statement
xenith.com.au
37
==> picture [128 x 31] intentionally omitted <==
Table 10 – Royalties Applicable to the Jervois Project
| Condition | |
|---|---|
| The formula to determine the net value is: | |
| Royalty = RR*(V – SC) | |
| Where: | |
| RRis the royalty rate of a mineral | |
| Mineral Royalty | Copper (concentrate) royalty rate is 5.0% |
| Gold (gravity recovery) royalty rate of 5.0% has been used. There is no concentrate | |
| Act 2024 | |
rate for Gold in Schedule 1 of MRA24, only Gold (nuggets) 7.5%, Gold (gravity |
|
recovery) 5.0% and Gold (Doré) 3.5%. |
|
| Silver (concentrate) royalty rate is 5.0% | |
| Vis the value of the mineral extracted from a mining operation | |
| SCis the amount allowed to be deducted for shipping costs within the Territory. |
The penalty elements relevant to the Project are provided below in Table 11.
Table 11 – Penalty Elements
| Condition | Data source | |
|---|---|---|
| US$1.50 per DMT of concentrate for each 0.01% greater than | KGL supplied | |
| Bismuth | ||
| 0.12% concentration. | ||
6.1.3 Smelter Charges and Concentrate Transport Costs
The smelter charges, transportation and related items are provided below in Table 12.
Table 12 – Smelter Charges, Transportation Costs and Related Parameters
| Rate | Unit | Data source | |
|---|---|---|---|
| Treatment charge | 92.86 | AU$/conc. DMT | KGL supplied |
| Cu refining charge | 0.09 | AU$/lb Cu | KGL supplied |
| Au refining charge | 5.71 | AU$/oz troy Au | KGL supplied |
| Ag refining charge | 0.57 | AU$/oz troy Ag | KGL supplied |
| Transport charge | 205 | AU$/conc. WMT | KGL supplied |
| Moisture content | 12 | % increase to DMT | KGL supplied |
| Concentrate specification | 25 | % Cu concentration | KGL supplied |
6.1.4 Metallurgical recoveries
The calculation of revenues for project optimisation used average metallurgical recoveries for commodity metals and penalty elements. The recovery percentage varies by weathering type. Where partially oxidised material existing within the block models, the recovery percentage for fully oxidised material is applied.
Further information regarding metallurgical recoveries is provided in Section 4. Average recoveries are provided below in Table 13.
KGL Resources Limited 2024 Ore Reserve Statement
xenith.com.au
38
==> picture [128 x 31] intentionally omitted <==
Table 13 – Average Recoveries Used in Optimisation Revenue Calculations
| Recovery Fresh (%) | Recovery Oxide (%) | Data source | |
|---|---|---|---|
| Copper | 92.7 | 50.0 | KGL supplied |
| Gold | 60.0 | 45.0 | KGL supplied |
| Silver | 65.0 | 45.0 | KGL supplied |
| Bismuth | 65.0 | 50.0 | KGL supplied |
6.2 Project Costs
The costs included in the calculation of cut-off grades and Deswik Pseudoflow open pit optimisation and underground stope optimiser processes are provided below in Table 14. These costs are based on the previous 2022 FS financial results.
Table 14 – Project Costs Used in Optimisation Calculations
| Cost | Units | Data source | |
|---|---|---|---|
| General and common | |||
| General and administrative | |||
| Camp / Accommodation | 12.50 | AU$/feed tonne | KGL Supplied |
| FIFO (admin / mine / mill) | |||
| Ore processing cost | 31.00 | AU$/feed tonne | KGL Supplied |
| Surface mining | |||
| Clear and grub | |||
| ROM management | |||
| Drill and blast | |||
| Mine and haul (ore) | 3.75 | AU$/tonne | KGL Supplied |
| Mine and haul (waste) | |||
| Ancillary (Grader, dozer, water cart) | |||
| Open pit operations cost above 340rL | |||
| Geology and grade control | 0.40 | AU$/Ore tonne | KGL Supplied |
| AU$/tonne/m | |||
| Vertical haulage increment below 340rL | 0.008 | KGL Supplied | |
| below 340rL | |||
| Ore mining premium | 0.10 | AU$/tonne ore | KGL Supplied |
| AU$/ROM | KGL Supplied | ||
| Ore transport to ROM (Bellbird UG only) | 2.00 | ||
| tonne/km | |||
KGL Resources Limited 2024 Ore Reserve Statement
xenith.com.au
39
| Cost | Units | Data source | |
| Underground mining | |||
| Mining cost including CRF backfill | 80.00 | AU$/tonne | KGL Supplied |
| Mining cost excluding CRF backfill | 60.00 | AU$/tonne | KGL Supplied |
| Development cost | 5800 | AU$/m | KGL Supplied |
6.3 Metal Equivalent and Cut-off Grade
6.3.1 Metal Equivalent Calculation
The Project consists of several polymetallic deposits. Copper, gold and silver can be recovered and will contribute to revenue. As copper is the dominant metal, a copper equivalent (CuEq) calculation was considered appropriate for the Project and is in line with the mineral Resource estimate. The CuEq percentage is calculated using parameters outlined in this section.
The CuEq equation is given:
==> picture [368 x 24] intentionally omitted <==
The general equation for Cu metal value is given:
𝑀𝑒𝑡𝑎𝑙 𝑉𝑎𝑙𝑢𝑒= 𝐺𝑟𝑎𝑑𝑒 × 𝐶 × (𝑃𝑟𝑖𝑐𝑒−𝑇𝐶𝑅𝐶) × 𝑅 × 𝑃
Where:
-
› Grade – The grade of the metal (e.g. Au grade in g/t)
-
› C – Constant to convert grade to the metal price unit (e.g. 1/31.1035 to convert g/t to ounces)
-
› Price – The price of the commodity metal per unit (e.g. $/oz Au)
-
› TCRC – Treatment charges and refining costs (i.e. $/oz Au)
-
› R – Average metallurgical recovery percentage for the metal (e.g. 60% Fresh Au recovery)
-
› P – Payable metal percentage for each metal (e.g. 90% Au payable metal percentage)
-
› T – Concentrate transport costs (i.e. $/concentrate WMT)
The Bismuth penalty is applied where the concentration of Bismuth in the copper concentrate product is above the threshold limit; where the concentration of Bismuth in concentrate is below the threshold limit, zero penalty applies. The equation for the Bismuth penalty when above the threshold limit is given:
(𝐵𝑖 𝑔𝑟𝑎𝑑𝑒 𝑖𝑛 𝑐𝑜𝑛𝑐. −𝐵𝑖 𝑝𝑒𝑛 𝑡ℎ𝑟𝑒𝑠𝑜𝑙𝑑) 𝐵𝑖𝑠𝑚𝑢𝑡ℎ 𝑝𝑒𝑛𝑎𝑙𝑡𝑦= × 𝐵𝑖 𝑝𝑒𝑛 × 𝐶𝑜𝑛𝑐. 𝑇𝑜𝑛𝑛𝑒𝑠 𝐷𝑀𝑇 100
Where:
-
› Bi grade in conc. – Is the Bismuth grade in concentrate as ppm
-
› Bi pen threshold – Is the Bismuth penalty threshold as ppm
-
› Bi pen – is the Bismuth penalty in AU$
KGL Resources Limited 2024 Ore Reserve Statement
xenith.com.au
40
==> picture [195 x 147] intentionally omitted <==
6.3.2 Mine Planning Cut-off Grades
The assumptions detailed in this section were used to determine the Mine Planning cut-off grades for the Project. The cut-off grade varies by weathering type and mining method. The cut-off grades are provided below in Table 15.
Table 15 – Mine Planning Cut-off Grades
| Oxide (CuEq%) | Fresh (CuEq%) | |
|---|---|---|
| Surface mining | 0.71 | 0.35 |
| Underground mining with backfill | n/a | 1.00 |
| Underground mining without backfill | n/a | 0.83 |
| Underground development | n/a | 0.50 |
KGL Resources Limited 2024 Ore Reserve Statement
xenith.com.au
41
7. Mineral Resources
==> picture [195 x 147] intentionally omitted <==
7.1 The Jervois Mineral Resource
The May 2024 Jervois Project Mineral Resource Estimate (MRE) was completed by Mining Associates Pty Ltd ( Mining Associates or MA ). The Mineral Resource estimate encompasses the copper, gold and silver resources considered for extraction by the KGL Jervois Project.
The Resource estimates for the Reward, Rockface and Bellbird deposits have been re-reported at a lower break-even cut-off reflective of the current Feasibility Study. The Resources for the Jervois Project as described in the May 2024 Resource Estimate are listed below in Table 16 and shown in Figure 12.
Table 16 – Contributing Mineral Resources
| Deposit | Open Pit Mining | Underground Mining |
|---|---|---|
| Marshall Underground | ||
| Reward | Reward Pit | |
| Reward Underground | ||
| Bellbird | Bellbird Pit | Bellbird Underground |
| Rockface | n/a | Rockface Underground |
Figure 12 – Bellbird, Rockface and Reward Deposits
==> picture [483 x 270] intentionally omitted <==
The May 2024 Mineral Resource estimate is based on 975 drill holes for 257,903 m of drilling between 2011 and 15[th] May 2024. Drilling is on a nominal 25 m spacing near the surface, widening to 50 m spacing at depth, and further widening to 100 m spacing on the periphery of the mineralisation.
Collar and down holes surveys have been completed for many of the KGL and historic drill holes. Where the location of historic holes is in doubt, these were excluded from the Resource estimate.
KGL Resources Limited 2024 Ore Reserve Statement
xenith.com.au
42
==> picture [128 x 31] intentionally omitted <==
There are no sample recovery issues that would cause sampling bias (although no recovery records for core drilling are available for holes drilled prior to 2013). A summary of the drill used to define the Jervois Mineral Resource is shown below in Table 17.
Table 17 – Jervois Project Resource Definition Drill Hole Summary
| Previous Lease Holders | Previous Lease Holders | |||||
|---|---|---|---|---|---|---|
| Total | Holes | KGL holes | ||||
| Holes | ||||||
| Deposit | #Holes | Total (m) | #Holes | Total (m) | #Holes | Total (m) |
| Bellbird | 331 | 53,044 | 271 | 48,202 | 56 | 6,789 |
| Reward | 635 | 151,964 | 563 | 138,537 | 72 | 13,427 |
| Rockface | 147 | 61,396 | 141 | 60,618 | 6 | 778 |
7.2 Mineral Resource Cut-off Grades
For the purposes of the Revised May 2024 MRE, an open pit and underground cut-off grade (CoG) was applied. The 2024 FSU revenue factor (RF) 1.15 optimisation shell Bellbird and Reward has been used to delineate the potential for open pit or underground extraction when applying the CoG.
Deswik Pseudoflow was used to produce the optimised pit shells for the Project (the optimisation is outlined in Section 8.1 of this report). The Mineral Resource cut-off grades and related criteria are shown below in Table 18.
Table 18 – Mineral Resource Estimate Cut-off Grades
| Mine Area | Cut-off Grade | Criteria |
|---|---|---|
| Open Pit Extraction Potential | >0.35% CuEq | Above an RF 1.15 optimised pit shell |
| Underground Extraction | ||
| >0.8% CuEq | Below an RF 1.15 optimised pit shell | |
Potential |
||
The assumptions and formulas used to derive the MRE cut-off grades, and the copper equivalent calculation are shown in Section 6.
The 0.35% CuEq cut-off has been shown to cover direct open pit mining and processing unit costs (allowing for metallurgical recovery). The 0.8% CuEq cut-off has been shown to compensate for the higher unit mining costs incurred, applying basic underground methods.
7.3 Mineral Resource Estimate
The Jervois MRE dated 23[rd] May 2024 has been prepared by Mr Ian Taylor of Mining Associates at a revised cut off aligned to the reserves for the Reward, Rockface and Bellbird deposits.
The total Resource estimates stand at:
-
› 28.95 million tonnes at 1.76% copper, 24.8 g/t silver and 0.23 g/t gold;
-
› containing 509,800 tonnes copper, 23.13 million ounces silver and 213,130 ounces of gold.
The Resource estimates for the Reward, Rockface and Bellbird deposits have been re-reported at a lower break-even cut-off reflective of the current Feasibility Study and are presented below in Table 19.
KGL Resources Limited 2024 Ore Reserve Statement
xenith.com.au
43
==> picture [195 x 147] intentionally omitted <==
Table 19 – Revised May 2024 Jervois Mineral Resource Estimate
| Resource | Material | Material | Grade | Metal | ||||
|---|---|---|---|---|---|---|---|---|
| Area | Cu | Ag | Au | Cu | Ag | Au | ||
| Category | Mt | |||||||
| (%) | (g/t) | (g/t) | (kt) | (Moz) | (koz) | |||
| Measured | 4.40 | 1.90 | 32.8 | 0.30 | 83.5 | 4.63 | 42.3 | |
| Open Cut | ||||||||
| Indicated | 5.39 | 1.34 | 35.4 | 0.21 | 72.3 | 6.13 | 36.4 | |
| Potential >0.35% |
||||||||
| CuEq | Inferred | 0.33 | 1.01 | 8.6 | 0.10 | 3.3 | 0.09 | 1.1 |
| Subtotal | 10.12 | 1.57 | 33.4 | 0.25 | 159.1 | 10.85 | 79.7 | |
| Indicated | 7.85 | 2.37 | 25.4 | 0.33 | 186.1 | 6.4 | 82.3 | |
| Underground | ||||||||
Potential >0.8% CuEq |
Inferred | 10.99 | 1.50 | 16.6 | 0.14 | 164.6 | 5.9 | 51.1 |
| Subtotal | 18.84 | 1.86 | 20.3 | 0.22 | 350.7 | 12.28 | 133.4 | |
| Measured | 4.40 | 1.90 | 32.8 | 0.30 | 83.5 | 4.63 | 42.3 | |
| Resource Categories | ||||||||
| Indicated | 13.24 | 1.95 | 29.4 | 0.28 | 258.4 | 12.53 | 118.6 | |
Subtotal |
||||||||
| Inferred | 11.31 | 1.48 | 16.4 | 0.14 | 167.9 | 5.96 | 52.2 | |
| Total | 28.95 | 1.76 | 24.8 | 0.23 | 509.8 | 23.13 | 213.1 |
Mineral Resources Notes as provided by Mining Associates Pty Ltd:
-
› Cut-off grades: 0.35% CuEq above an optimised pit shell (RF 1.15), 0.8% CuEq below the pit shell;
-
› Due to rounding to appropriate significant figures, minor discrepancies may occur, tonnages are dry metric tonnes. Does not include the Reward South Resource estimate;
-
› Mineral Resources are not ore Reserves and do not have demonstrated economic viability;
-
› Inferred Resources have less geological confidence than measured or indicated Resources and should not have modifying factors applied to them. It is reasonable to expect that with further exploration most of the inferred Resources could be upgraded to indicated Resources; and
-
› Copper Equivalent uses a copper price of USD $4.90/lb, silver price of USD $32/oz and a gold price of USD $2400/oz, and a Bi penalty of US$1.5/dmt for every 100ppm over 1200ppm in the concentrate. Fresh recoveries; Copper 92.7%, silver 65%, gold 65%, and bismuth 65%. Oxide recoveries; Copper 50%, silver 45%, gold 45%, and bismuth 50%. E.g. Cu 0.5%, Ag 20 g/t, Au 0.2 g/t and 100ppm Bi, the formula is Cu % + 0.478 x Au g/t +0.0068 x Ag g/t - 0.000074 x Bi ppm.
KGL Resources Limited 2024 Ore Reserve Statement
xenith.com.au
44
==> picture [195 x 147] intentionally omitted <==
7.4 Mineral Resource Comparison
Since the 23[rd] May 2024 resource the reported the cut-off parameters have been updated to include silver and gold for the Revised May 2024 Jervois MRE.
-
› The largest impact is in the contained Resource within the reward optimised pit where there is a 32% increase in tonnes;
-
› Bellbird adds 16% more tonnes and Rockface adds 7% more tonnes;
-
› Across the deposits the average copper grade drops between 5% and 14%, silver between 5 and 7% and gold grades drop between 4 and 13%;
-
› The contained metal reported has increased most notably at Reward, (copper and gold increased 13% and silver by 23%);
-
› Bellbird shows contained metal increasing 5% for copper, 8% for silver and 6% for gold; and
-
› Rockface shows the least impact, mainly due to the strong copper grades, all contained metals increased by 2%.
The tabularised comparison of the impact the change in cut-off grade methodology and relevant assumptions on the MRE for each of the Jervois deposits is shown below in Table 20, Table 21, and Table 22.
Table 20 – Change in Reward MRE due to Updated Cut-off Parameters
| Reward | Material | Material | Grade | Metal | ||||
|---|---|---|---|---|---|---|---|---|
| Deposit | Ag | Au | Ag | Au | ||||
| Category | Mt | Cu (%) | Cu (kt) | |||||
| (g/t) | (g/t) | (Moz) | (koz) | |||||
| May 2024 | Measured | 2.63 | 1.91 | 46.2 | 0.43 | 50.3 | 3.91 | 36.0 |
| Reported | ||||||||
| Indicated | 6.22 | 1.94 | 41.2 | 0.38 | 122.1 | 8.18 | 78.5 | |
| Using Cu | ||||||||
| 0.5% and | ||||||||
| 1.0% | Inferred | 4.38 | 1.41 | 17.4 | 0.18 | 62.5 | 2.43 | 25.3 |
| Revised May | ||||||||
| Measured | 2.67 | 1.89 | 46.4 | 0.42 | 50.4 | 3.98 | 36.2 | |
| 2024 | ||||||||
| Reported | Indicated | 8.56 | 1.59 | 36.3 | 0.32 | 136.4 | 9.98 | 88.6 |
| using CuEq | ||||||||
0.35% and |
||||||||
| Inferred | 6.18 | 1.25 | 19.6 | 0.17 | 77.5 | 3.89 | 33.3 | |
| 0.8% | ||||||||
| Measured | 1.4% | -1.0% | 0.4% | -1.9% | 0.3% | 1.8% | 0.6% | |
| Indicated | 37.5% | -17.9% | -11.9% | -15.1% | 11.7% | 22.0% | 12.9% | |
| Change (%) | ||||||||
| Inferred | 41.1% | -11.3% | 12.6% | -6.7% | 23.9% | 60.0% | 31.8% | |
KGL Resources Limited 2024 Ore Reserve Statement
xenith.com.au
45
==> picture [128 x 31] intentionally omitted <==
Table 21 – Change in Bellbird MRE due to Updated Cut-off Parameters
| Bellbird | Material | Material | Grade | Metal | ||||
|---|---|---|---|---|---|---|---|---|
| Ag | Au | Ag | Au | |||||
| Deposit | Category | Mt | Cu (%) | Cu (kt) | ||||
(g/t) |
(g/t) | (Moz) |
(koz) | |||||
| May 2024 | Measured | 1.23 | 2.53 | 15.1 | 0.14 | 31.18 | 0.60 | 5.6 |
| Reported | ||||||||
| Indicated | 1.59 | 1.63 | 11.3 | 0.16 | 26.01 | 0.58 | 8.3 | |
| Using Cu | ||||||||
| 0.5% and | ||||||||
| 1.0% | Inferred | 3.86 | 1.87 | 11.9 | 0.11 | 71.82 | 1.47 | 13.7 |
| Revised May | ||||||||
| Measured | 1.73 | 1.91 | 11.7 | 0.11 | 33.05 | 0.65 | 6.1 | |
| 2024 | ||||||||
| Reported | Indicated | 1.78 | 1.50 | 10.4 | 0.15 | 26.72 | 0.60 | 8.7 |
| using CuEq | ||||||||
0.35% and |
||||||||
| Inferred | 4.25 | 1.77 | 11.8 | 0.11 | 75.16 | 1.61 | 14.4 | |
| 0.8% | ||||||||
| Measured | 40.5% | -24.4% | -22.5% | -21.4% | 6.0% | 8.4% | 9.1% | |
| Change (%) | Indicated | 11.8% | -7.9% | -7.8% | -7.2% | 2.7% | 2.9% | 4.7% |
| Inferred | 10.1% | -5.2% | -0.6% | -6.6% | 4.7% | 9.5% | 4.9% | |
Table 22 – Change in Rockface MRE due to Updated Cut-off Parameters
| Rockface | Material | Material | Grade | Metal | ||||
|---|---|---|---|---|---|---|---|---|
| Ag | Au | Ag | Au | |||||
| Deposit | Category | Mt | Cu (%) | Cu (kt) | ||||
(g/t) |
(g/t) | (Moz) |
(koz) | |||||
| May 2024 | ||||||||
| Indicated | 2.80 | 3.37 | 21.4 | 0.23 | 94.31 | 1.93 | 21.1 | |
| Reported |
||||||||
| Using Cu | ||||||||
| 0.5% and | Inferred | 0.73 | 1.92 | 19.0 | 0.18 | 13.97 | 0.45 | 4.2 |
| 1.0% | ||||||||
| Revised May | ||||||||
| Indicated | 2.91 | 3.27 | 20.9 | 0.23 | 95.24 | 1.96 | 21.3 | |
| 2024 |
||||||||
| Reported | ||||||||
| using CuEq | ||||||||
| Inferred | 0.88 | 1.73 | 16.4 | 0.16 | 15.32 | 0.46 | 4.5 | |
0.35% and |
||||||||
| 0.8% | ||||||||
| Indicated | 3.9% | -2.8% | -2.2% | -0.8% | 1.0% | 1.4% | 1.1% | |
| Change (%) | ||||||||
| Inferred | 21.1% | -9.7% | -14.0% | -12.4% | 9.7% | 3.2% | 6.7% | |
KGL Resources Limited 2024 Ore Reserve Statement
xenith.com.au
46
8. Open Pit Mining
==> picture [195 x 147] intentionally omitted <==
8.1 Open Pit Optimisation
8.1.1 Pit Optimisation Process & Assumptions
Open pit optimisation was completed using Deswik Pseudoflow Mine Planning software. The pit optimisation process is outlined below:
-
› The original block model for Reward and Bellbird was regularised to several selective mining units (SMUs). The impact that the different SMUs sizes had on volumes and grades was evaluated with consideration given to the mining equipment. This ensured that the regularisation process was providing an appropriate estimate for ore dilution:
-
The Reward SMU size selected (X = 2.5 m, Y = 5.0 m, Z = 5.0 m) approximated 12.4% dilution compared to the unregularized model. This compared well to the 10% dilution previously modelled and included in the 2022 FS Reward schedule;
-
The Bellbird SMU size selected (X = 2.5 m, Y = 5.0 m, Z = 5.0 m) approximated 27% dilution compared to the unregularized model. This was conservative when compared to the 15% dilution previously modelled and included in the 2022 FS schedule; and
-
The dilution estimates for the Reward and Bellbird 2022 FS schedules (referenced above) are based on the minimum mining thicknesses and the use of stope optimiser to deliver an estimate of dilution. This is in line with the actual equipment capabilities when considered against the geometry of the orebodies.
-
› The Project geotechnical, geological, metallurgical, cost and revenue assumptions were incorporated into the Pseudoflow modelling for the purposes of pit optimisation;
-
› The Pseudoflow model and regularised block model were used to produce pit optimisation shells for each of the mineral assets;
-
› The process was used to produce optimiser shells for the Reward and Bellbird deposits from revenue factor 0.5 to 1.15 stepping in 0.05 increments; and
-
› Each of the Bellbird and Reward optimiser shells were assessed against the Project economic goals and operational constraints. The final shell formed the basis of the open pit design and schedule for each mine.
The global revenue and cost assumptions used in the pit optimisation are provided in Section 6.
The Reward and Bellbird Open Pit slope design criteria used in the optimisation are shown below in Table 23.
Table 23 – Pit Slope Design Parameters for Optimisation Process
| Weathering Profile | Overall Slope Angle (°) |
|---|---|
| Oxide | 45 |
| Transition | 45 |
| Fresh | 45 |
KGL Resources Limited 2024 Ore Reserve Statement
xenith.com.au
47
==> picture [195 x 147] intentionally omitted <==
8.1.2 Reward Open Pit Optimisation Outcomes
Deswik Pseudoflow Optimisation for Reward produced the cumulative margin versus incremental pit shell size chart shown below in Figure 13. The pit shells and detailed pit design are shown in Figure 14 and Figure 15 below.
The Unca creek diversion becomes a limiting factor for the Northern extent of the open pit from the revenue factor 0.8 shell. The updated Reward Mineral Resource geological model was the primary reason for the Unca Creek diversion becoming a limitation on the northern extent of the open pit design.
Increase in cumulative margin were minimal above a 0.6 revenue factor. This is illustrated in Figure 13 below by the slight upward trend in the cumulative margin curve beyond 0.6 revenue factor.
The cumulative margin does accelerate at the 0.8 revenue factor but adopting this pit shell would require a larger cutback and result in changes to the design of the Unca Creek Diversion and associated approvals.
Accordingly, the 0.6 revenue factor shell was selected for the detailed design.
Figure 13 – Reward Optimisation Margin vs Tonnage by Pit Shell
==> picture [485 x 283] intentionally omitted <==
KGL Resources Limited 2024 Ore Reserve Statement
xenith.com.au
48
==> picture [501 x 425] intentionally omitted <==
----- Start of picture text -----
Figure 14 – Reward Optimised Pit Shells E-W section
----- End of picture text -----
Figure 15 – Reward Optimised Pit Shells N-S Section
==> picture [412 x 290] intentionally omitted <==
KGL Resources Limited 2024 Ore Reserve Statement
xenith.com.au
49
==> picture [195 x 147] intentionally omitted <==
8.1.3 Bellbird Open Pit Optimisation
Deswik Pseudoflow Optimisation for Bellbird produced the cumulative margin versus incremental pit shell size chart shown below in Figure 16. The pit shells and detailed pit design are shown in Figure 17 and Figure 18 below.
The existing pit design completed during the 2022 FS (albeit with a wider ramp), aligned well with the 2024 FSU revenue factor 0.7 pit shell. Above a 0.7 revenue factor the incremental margins were minimal for substantial increases in pit size and stripping requirements.
The 2022 FS pit design was therefore adopted as the 2024 FSU Bellbird pit.
Figure 16 – Bellbird Optimisation Margin vs Tonnage by Pit Shell
==> picture [483 x 276] intentionally omitted <==
KGL Resources Limited 2024 Ore Reserve Statement
xenith.com.au
50
==> picture [128 x 31] intentionally omitted <==
Figure 17 – Bellbird Optimised Pit Shells E-W Section
==> picture [412 x 292] intentionally omitted <==
Figure 18 – Bellbird Optimised Pit Shells N-S Section
==> picture [412 x 291] intentionally omitted <==
KGL Resources Limited 2024 Ore Reserve Statement
xenith.com.au
51
8.2 Open Pit Mine Design
==> picture [195 x 147] intentionally omitted <==
8.2.1 Reward Open Pit
The Reward Open Pit design follows the optimiser shell selected. The design also considers site infrastructure and the Unca Creek diversion.
The Reward Open Pit was designed with two stages. Stage one removes most of the oxide material and establishes the upper benches of the southern end of the pit as shown below in Figure 19. Stage one is also planned to build a buffer of fresh ore in a stockpile to supply to the mill.
The transition of stage one to stage two in the Reward Open Pit does not disrupt supply of fresh ore to the processing plant as ore is supplied from the Bellbird Open Pit.
Section, plan and isometric views of the Reward pit design stages are shown below in Figure 19 to Figure 22. Figure 19 shows the transition from oxidised (Ox) and partially oxidised (Po) material to fresh (remaining material within the stage 1 and 2 open pit designs).
Figure 19 – Reward Open Pit N-S Section with Weathering Profile
==> picture [484 x 340] intentionally omitted <==
KGL Resources Limited 2024 Ore Reserve Statement
xenith.com.au
52
==> picture [195 x 147] intentionally omitted <==
Figure 20 – Reward Open Pit Stage 1
==> picture [426 x 299] intentionally omitted <==
Figure 21 – Reward Open Pit Stage 2
==> picture [426 x 301] intentionally omitted <==
KGL Resources Limited 2024 Ore Reserve Statement
xenith.com.au
53
==> picture [195 x 147] intentionally omitted <==
Figure 22 – Reward Pit Stages (Isometric)
==> picture [412 x 231] intentionally omitted <==
8.2.2 Bellbird Open Pit
The Bellbird Open Pit has been designed with a single stage. Section and plan views of the Bellbird pit design is shown below in Figure 23 and Figure 24. Figure 23 shows the transition from oxidised (Ox) and partially oxidised (Po) material to fresh (remaining material within the stage 1 and 2 open pit designs).
Figure 23 – Bellbird Pit N-S Section with Weathering Profile
==> picture [429 x 301] intentionally omitted <==
KGL Resources Limited 2024 Ore Reserve Statement
xenith.com.au
54
==> picture [195 x 147] intentionally omitted <==
Figure 24 – Bellbird Open Pit
==> picture [488 x 345] intentionally omitted <==
8.2.3 Open Pit Design Quantities
The final design quantities for the open pits as scheduled are shown below in Table 24 and Table 25. This represents the total planned mining from each of the open pits over the life of mine.
Table 24 – Open Pit Quantities - Volume
| Total | Waste | Ore | Cu Grade | Strip Ratio | |
|---|---|---|---|---|---|
| Mine | |||||
| (MBCM) | (MBCM) | (MBCM) | (%) | (Waste/Ore) | |
| Bellbird | 6.95 | 6.25 | 0.69 | 1.73 | 9.00 |
| Reward | 22.03 | 20.48 | 1.55 | 1.49 | 13.25 |
| Total | 28.97 | 26.73 | 2.24 | 1.56 | 11.93 |
KGL Resources Limited 2024 Ore Reserve Statement
xenith.com.au
55
| Table 25 – Open Pit Quantities - Tonnes | Table 25 – Open Pit Quantities - Tonnes | Table 25 – Open Pit Quantities - Tonnes | Table 25 – Open Pit Quantities - Tonnes | Table 25 – Open Pit Quantities - Tonnes | |
|---|---|---|---|---|---|
| Total | Waste | Ore | Cu Grade | Strip Ratio | |
| Mine | |||||
| (Mt) | (Mt) | (Mt) | (%) | (Waste/Ore) | |
| Bellbird | 19.5 | 17.51 | 1.99 | 1.73 | 8.8 |
| Reward | 64.08 | 59.19 | 4.88 | 1.49 | 12.12 |
| Total | 83.58 | 76.71 | 6.87 | 1.56 | 11.16 |
8.3 Open Pit Mine Operations
8.3.1 Mining Equipment
Open pit operations are planned to utilise conventional drill and blast, load and haul methods with all operations undertaken by a mining contractor. The mining contractor will supply, manage, operate, and maintain all required open pit mining equipment. Open pit mining equipment is sized so that it is suitable for mining of thin veins.
The selected excavators and haul trucks are in line with current industry standards. The auxiliary and supplementary fleet are appropriate to support the capabilities of the nominated excavators and haul trucks.
Open pit excavation is based on a combination of 120 tonne class and 360 tonne class excavators.
The smaller 120 tonne class excavator will focus on selective mining around the boundaries of the thinner mineralised lodes. The larger 360 tonne class excavators will focus on bulk waste mining and excavation of the wider mineralised lodes.
The haulage fleet consists of 185 tonne payload dump trucks and are suited to the combination of open pit and surface haulage duties across the two open pits.
The production rates provided by the preferred contractor in the open pits are summarised below in Table 26. The mining rate of ore is reduced in comparison to bulk waste movement to account for the selective mining process around the boundaries of the mineralised lodes.
The production rates are assumed to include all activities and delays related to production drill and blast, shift change and meetings, meal breaks, breakdowns and maintenance.
Table 26 – Open Pit Production Rate
| Mine | Waste Mining Rate (t / day) | Ore Mining Rate (t / day) |
|---|---|---|
| Bellbird | ||
| EX3600 | 41,500 | 32,200 |
| EX1200 | 17,900 | 14,800 |
| Reward | ||
| EX3600 | 51,400 | 45,300 |
The final make and model of the equipment deployed will depend on the mining contractor engaged and the contract specifications. The nominated fleet used in project costing is shown below in Table 27.
KGL Resources Limited 2024 Ore Reserve Statement
xenith.com.au
56
==> picture [194 x 147] intentionally omitted <==
Table 27 – Open Pit Mining Equipment Schedule
| Y1 | Y1 | Y2 | Y2 | Y3 | Y3 | Y4 | Y4 | |||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Type | ||||||||||||||||||||
| Pit | Class | Manufacturer | Model | Q1 | Q2 | Q3 | Q4 | Q1 | Q2 | Q3 | Q4 | Q1 | Q2 | Q3 | Q4 | Q1 | Q2 | Q3 | Q4 | |
| RE | 360 t | Hitachi | EX3600 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 2 | 2 | 2 | 2 | 2 | 1 | ||||
| Excavator | ||||||||||||||||||||
| BB | 360 t | Hitachi | EX3600 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | ||||||||||
| Excavator | 120 t | Komatsu | EX1200 (6.0 m3) | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | ||||
| Truck | 185 t | Caterpillar | 789C | 9 | 9 | 9 | 9 | 12 | 12 | 12 | 12 | 9 | 9 | 9 | 9 | 5 | ||||
| Dozer | Caterpillar | D10T2 | 4 | 4 | 4 | 4 | 4 | 4 | 4 | 4 | 3 | 3 | 3 | 3 | 2 | |||||
| Drill | Epiroc | SmartRoc D65 | 4 | 4 | 4 | 4 | 4 | 4 | 4 | 4 | 3 | 3 | 3 | 3 | 1 | |||||
| 18 Grader | ||||||||||||||||||||
| Ancillary | Caterpillar | 4 | 4 | 4 | 4 | 4 | 4 | 4 | 4 | 4 | 4 | 4 | 4 | 4 | ||||||
| 777F Water Cart | ||||||||||||||||||||
KGL Resources Limited 2024 Ore Reserve Statement
xenith.com.au
57
8.3.2 Drill & Blast Bench Heights
==> picture [195 x 147] intentionally omitted <==
Bench height is an important design factor and is selected considering the deposit attributes, dilution and ore loss, and the impact on mining productivity. The contractor pricing estimate is based on a blast hole burden between 3.5 m and 4.8 m utilising 165 mm blast holes and a 10 m mining bench height. Smaller diameter blast holes are preferred to control lateral boundary dilution.
As the dip of the Jervois orebodies is generally steep, vertical dilution is not considered to be as significant. Blasted 10 m benches may heave to 12 m height and will therefore be excavated as three 4.0 m flitches.
8.3.3 Design Bench Heights
Reward and Bellbird pit designs follow the geotechnical recommendations outlined in Section 5. The recommendations allow for 10 m benches with 5 m catch berms in oxide/transitional material and 20 m benches with 9 m catch berms in fresh material. Mining in fresh material will require each design bench to be mined in two 10 m drilled and blasted benches.
8.3.4 Haul Road Parameters
Haul road width will conform to industry standards and legislation. This will ensure safe operation of the haul roads. Dual lane ramps are designed to where floor widths allow normal truck and excavator operations. Single lane ramps are employed for smaller or narrower areas of the pit where operations are restricted at depth.
The selection of depth to employ single lanes directly impacts the overall pit strip ratio.
Figure 25 – Typical Haul Road Schematic for a Dual Lane Ramp
==> picture [483 x 171] intentionally omitted <==
Haul road width is based on the largest truck used. For the Project this is a 185 tonne rigid body dump truck. The Caterpillar 789C haul truck (on which project costing is based) is approximately 7.7 m wide. Additional width allowance for a 1.0 m wide drain, clearance for trucks running in each lane (an additional truck width), and a 4.8 m wide safety bund constructed to axle height.
Using the measurements provided above in Figure 25 and the width allowances described, final haul road widths are calculated below in Table 28 and Table 29. These widths have been used for all in-pit, ROM and waste dump haul road designs.
Dual lane ramps are used for all upper benches in both pit designs. Single lane ramps are used in the lowest three design benches in both open pits. All pit ramps are designed with a maximum 11% grade (1 in 9 gradient).
KGL Resources Limited 2024 Ore Reserve Statement
xenith.com.au
58
==> picture [195 x 147] intentionally omitted <==
Table 28 – Bellbird Open Pit Ramp Width
| A | B | C | D | F | |
|---|---|---|---|---|---|
| Ramp Type | |||||
| Truck (m) | Clearance (m) | Bund (m) | Drain (m) | Total Ramp (m) | |
| Dual Lane | 15.4 | 8.8 | 4.8 | 1.0 | 30 |
| Single Lane | 7.7 | 4.5 | 4.8 | 1.0 | 18 |
Table 29 – Reward Open Pit Ramp Width
| A | B | C | D | F | |
|---|---|---|---|---|---|
| Ramp Type | |||||
| Truck (m) | Clearance (m) | Bund (m) | Drain (m) | Total Ramp (m) | |
| Dual Lane | 15.4 | 9.8 | 4.8 | 1.0 | 31 |
| Single Lane | 7.7 | 5.5 | 4.8 | 1.0 | 19 |
8.3.5 Minimum Operating Width
As the pits deepen, the area that is available for the equipment to operate will reduce. Typically, there will be enough room for a truck to complete a 360 ° turn. When the available space is less than 30 m wide, the truck will reverse into position to be loaded.
In these areas, a minimum 20 m mining width will be maintained and is considered the smallest operating width to conduct operations. The described operating widths are shown below in Table 30.
Table 30 – Open Pit Operating Width
| Full Turn (m) | Minimum (m) | |
|---|---|---|
| Operating Width | 30 | 20 |
8.3.6 Open Pit Dilution & Mining Recovery Assumptions
Bellbird Open Pit often has multiple and up to 4 thin lenses across a flitch for which the dilution of each lens needs to be accounted for when mining using a 120-tonne class excavator. To appropriately account for dilution at Bellbird, Deswik Stope Optimiser was used to simulate linear dilution along the footwall and hanging wall of the copper ore veins.
This allowed dilution on each of the individual copper veins to be calculated and built into a global average dilution factor. The analysis assumed a minimum mining width (MMW) of 2.5 m along with 0.25 m of dilution along the footwall and hanging wall. The analysis described provided a dilution factor of 15% for the Bellbird Open Pit.
The Reward orebody geometry differs from Bellbird in that it consists mostly of one large lens. This geometry supports use of a larger 360 tonne class excavator in the Reward Open Pit. Deswik Stope Optimiser was again used to determine a global average dilution for Reward. A minimum mining width (MMW) of 3.0 m along with 0.5 m of dilution along the footwall and hanging wall were used for the Reward dilution calculation.
These parameters account for the larger bucket size and lower digging selectivity of the 360-class excavator. The analysis described provided a dilution factor of 10% for the Reward Open Pit.
The described ore dilution and the mining recovery assumptions are shown below in Table 31.
KGL Resources Limited 2024 Ore Reserve Statement
xenith.com.au
59
==> picture [128 x 31] intentionally omitted <==
Table 31 – Open Pit Dilution & Recovery Assumptions
| Pit | Recovery Factor (%) | Dilution (%) |
|---|---|---|
| Bellbird Open Pit | 95 | 15 |
| Reward Open Pit | 95 | 10 |
8.4 Jervois ROM and Waste Dump Design
All open pit waste will be moved to waste dumps designed for the Reward Open Pit, Bellbird Open Pit and underground operations. The dump footprints will be created through the first years of open pit operations with underground waste deposition and associated stockpiling located on the upper dump lifts.
Importantly, for schedule years where open pit and underground mines will operate concurrently, the Jervois open pit and underground haulage fleet will be required to operate in proximity. At an operational level, risk assessments and identified controls (such as traffic management plans and haul road designs) will need to be completed/implemented to reduce any risk.
The following considerations were incorporated into the waste dump designs:
-
› Priority given to existing and planned infrastructure (including roadways);
-
› Dumps are positioned within the mineral lease boundaries relevant to the Project; and
-
› To reduce haul lengths, dumps are positioned as close to the respective pit crest as allowable (100 m minimum offset required).
The dump locations designed for the Project include:
- › Reward Dump North › ROM Pad › Reward Dump South › Bellbird Dump
The Bellbird Dump is located immediately west of the Bellbird Open Pit. The footprint is approximately 1300 m x 470 m. The Reward Dump North is located immediately north-west of the Reward Open Pit, and north of the plant and related infrastructure. The Reward Dump North footprint is approximately 1600 m x 850 m.
The Reward Dump South is located south of the Reward Open Pit, adjacent to the ROM pad. The Reward Dump South footprint is approximately 1000 m x 1000 m. The described dump and ROM locations are shown below in Figure 26.
8.4.1 Design Parameters
Waste dumps have been designed as construction waste emplacements. Final waste dump shaping will be required as part of the Project rehabilitation at the end of the mine life. Construction design parameters are shown below in Table 32.
Table 32 – Waste Dump Design Parameters
| Slope | Berm | Ramp | Ramp | ||
|---|---|---|---|---|---|
| Waste Dump | Bench | ||||
| Angle | Width | Width | Gradient | ||
| Design Parameters | Height (m) | ||||
| (°) | (m) | (m) | (m) | ||
| Reward Waste Dump | 10 | 37 | 10 | 25 | 10 |
| Bellbird Waste Dump | 10 | 37 | 10 | 27 | 10 |
KGL Resources Limited 2024 Ore Reserve Statement
xenith.com.au
60
==> picture [195 x 147] intentionally omitted <==
8.4.2 Waste Haulage Routes
The optimum waste haulage routes are calculated for each 50 m x 50 m x 10 m open pit block to each 50m x 50m x 10m waste dump block available. Waste haulage follows the haulage paths shown below in Figure 26.
Figure 26 – Open Pit Haulage Routes
==> picture [398 x 564] intentionally omitted <==
KGL Resources Limited 2024 Ore Reserve Statement
xenith.com.au
61
==> picture [195 x 147] intentionally omitted <==
8.4.3 Dump Capacities
Dump capacities are referenced in units Loose Cubic Metre (LCM). Waste deposition is compacted only by the normal operation of dozers, trucks and loaders on and about the waste dump. Capacity figures assume all waste is deposited in the respective waste dumps. Significant volumes of waste will be used in pit bunding, CRF manufacture, infrastructure construction, tailings dam construction and roadway construction and maintenance.
All waste dumps include a 6.0 m high first lift with subsequent lifts measuring 10.0 m. Dump volumes are based on a 25% swell factor. The number of 10.0 m lifts specified for each of the Jervois waste dumps is outlined:
-
› Reward Dump North – 5 x 10 m lifts;
-
› Reward Dump South – 3 x 10 m lifts; and
-
› Bellbird Dump – 3 x 10 m lifts.
The Reward Dump North specifications allow surplus capacity (should it be required). The height of this dump was limited to five lifts to minimise elevation and truck haulage distance.
Dump waste capacities and estimated total waste volumes are detailed below in Table 33.
Table 33 – Waste Dump Capacities
| Waste Dump | OP Waste | UG Waste | Total Waste | Total Capacity | Utilisation |
|---|---|---|---|---|---|
| (MLCM) | (MLCM) | (MLCM) | (MLCM) | (%) | |
| Reward Dump North | 20.35 | - | 20.35 | 27.70 | 73% |
| Reward Dump South | 4.92 | 1.69 | 6.60 | 45.04 | 15% |
| Bellbird Dump | 7.82 | 1.61 | 9.43 | 13.79 | 68% |
| Total Waste Volumes | 33.08 | 3.30 | 36.38 | 86.53 | 42% |
The dump capacities outlined in Table 33 do not include topsoil storage. Storage areas for topsoil have not been identified as part of the 2024 FSU. Topsoil dumps should be placed in free draining areas with topsoil stockpiled no greater than 3 m in height.
8.4.4 PAF and NAF Estimates
Waste from open pit mining will account for most of the Potentially Acid Forming (PAF) material generated by the Project. The mechanics of PAF storage (dump design, waste haulage scheduling) have not been considered in the 2024 FSU. The ratio of PAF to Non-Acid Forming (NAF) material means PAF storage and isolation within the confines of the waste dumps is achievable as there is surplus dump capacity included in dump designs.
Hence, there is only a minor risk that the PAF storage requirements of the Project will impact the 2024 FSU dump footprints. Notwithstanding, it is recommended that detailed PAF management strategies be incorporated into the life of mine schedule during operational readiness phases and prior to execution.
PAF and NAF estimates completed as part of the 2024 FSU are based on waste material having a concentration of sulphur greater than 0.4%. Further geochemical analysis will be required to confirm the exact ratio of PAF to NAF. PAF and NAF estimates for the Project are shown below in Table 34.
KGL Resources Limited 2024 Ore Reserve Statement
xenith.com.au
62
==> picture [195 x 147] intentionally omitted <==
Table 34 – Waste PAF and NAF Designations
| Waste Designation | NAF Tonnes | PAF* Tonnes | PAF* Component |
|---|---|---|---|
| (Mt) | (Mt) | (%) | |
| Reward Open Pit | 50.74 | 8.46 | 14 |
| Bellbird Open Pit | 11.66 | 5.85 | 33 |
| Marshall Underground | 0.5 | 0.08 | 14 |
| Reward Underground | 0.93 | 0.17 | 15 |
| Rockface Underground | 1.06 | 0.13 | 11 |
| Bellbird Underground | 0.28 | 0.15 | 35 |
| Waste Total | 65.17 | 14.84 | 19 |
- Estimate only
8.4.5 Waste For Underground CRF Manufacture
Underground development waste would be the preferred source of waste material for CRF. However, at the volumes required, supplementary open pit waste will be required. This should be allowed for during open pit operations. Fresh waste suitable for underground CRF and/or stope void backfill will need to be stockpiled separately.
To limit potential impacts to backfill productivity, oversize should be screened from the CRF material. Whether any fines will need to be removed should be assessed and documented prior to execution; a reasonable concentration of fines will ensure suitable compressive strength for CRF emplacement.
8.4.6 Water Management Considerations
All waste dump run-off and drainage will be directed away from the pit boundaries back to settling and collection ponds and ultimately back to the raw water dams for re-use in mining operations and processing plant operations.
KGL Resources Limited 2024 Ore Reserve Statement
xenith.com.au
63
9. Underground Mining
==> picture [195 x 147] intentionally omitted <==
9.1 Stope Optimisation
9.1.1 Methodology and Optimisation Inputs
The underground stope shapes for the Project were created using Deswik Stope Optimiser Mine Planning software. The economic and geotechnical assumptions in Section 4 and 6 that are relevant to the underground mining were used in the stope optimisation.
9.1.2 Stope Orientation, Cut-off Grades and Pillars
Several stope optimisation scenarios were run. The scenarios incorporated different stope orientations, cut-off grades and rib pillars. The economic viability of backfill and open stoping with rib pillars was also tested. This process was completed to determine the mineable inventory for the underground mines.
The most economic stope inventory proved a combination of backfilled and open stoping. An example stope orientation produced during the optimisation process in relation to the local mine design is shown below in Figure 27.
Figure 27 – Example Stope Orientation from the Rockface Mine.
==> picture [481 x 338] intentionally omitted <==
KGL Resources Limited 2024 Ore Reserve Statement
xenith.com.au
64
==> picture [195 x 147] intentionally omitted <==
9.1.3 Stope Geometry and Dilution Assumptions
The stope geometry for the Project considers the geotechnical requirements outlined in Section 4.
Due to the orebody geometry, Reward and Marshall both tend to have wider stopes. Consequently, a 3.0 m minimum mining width (MMW) has been applied. Reward and Marshall stopes also include 0.5 m of hanging wall (HW) and footwall (FW) dilution, resulting in a total dilution of 1.0 m. The Rockface and Bellbird deposits include thinner sections (as splays) and therefore a 2.0 m MMW was selected. Rockface and Bellbird stopes include 0.5 m dilution on both the HW and FW.
The final stope geometry and dilution assumptions used in the stope optimiser process for each mine are shown below in Table 35.
Table 35 – Jervois Project Stope Optimisation Parameters
| Stope Optimiser Geometry and Parameters | Stope Optimiser Geometry and Parameters |
|---|---|
| Common Parameters | |
| 0.5 m HW | |
| Stope Dilution | |
| 0.5 m FW | |
| Mining Recovery | 90% |
| Rockface Underground | |
| Level Interval | 30 m |
| Stope Strike Length | 25 m |
| Bellbird Underground | |
| Level Interval | 20 m |
| Stope Strike Length | 15 - 35 m |
| Reward Underground | |
| Level Interval | 30 m |
| Stope Strike Length | 25 m |
| Marshall Underground | |
| Level Interval | 30 m |
| Stope Strike Length | 25 m |
9.2 Stope Optimisation Results
Multiple stope optimisation iterations were computed to assess the optimal stoping methods for each mine. The analysis focused on the variable cut-off grade of 0.83% CuEq (open stoping), 1.00% CuEq (base case) and 1.16% CuEq (sensitivity) to determine the impact on the stope inventory for each mine.
The analysis considers the cost of cemented rock fill against the value of sacrificial pillars that are required when leaving stopes unfilled.
KGL Resources Limited 2024 Ore Reserve Statement
xenith.com.au
65
9.2.1 Rockface Underground
Mining methods applied include:
==> picture [195 x 147] intentionally omitted <==
-
› Bottom up long-hole stoping with cemented rock fill and rock fill (CRF_RF);
-
› Bottom up long-hole stoping of sill pillars with cemented rock fill (CRF); and
-
› Bottom up open stoping with rib pillars under filled sill pillars.
The Rockface lodes consist of high grade ore and most of the scheduled stopes are backfilled to maximise metal recovery. Sill pillars are introduced in the mine design to allow early access to the upper production levels and to increase the number of stoping fronts. Sill levels are filled with cemented rock fill with high cement content to enable the undercutting of the fill mass under the sill pillars towards end of the mine life.
With the longitudinal stoping retreat method, some stopes on the periphery were excluded due to either scheduling resourcing constraints, Inferred resource confidence, or low-grade ore content; this decreased ore drive development to access the stopes. The optimisation 1.0% CuEq base case scenario identified 246 stopes.
From the 246 stopes identified in the analysis, 211 stopes were included in 2024 FSU Rockface Underground schedule.
The Rockface stope inventory is shown below in Figure 28. The 2024 FSU Rockface scheduled inventory with fill type is shown below in Figure 29.
Figure 28 – Rockface Stope Inventory by CuEq Grade.
==> picture [475 x 334] intentionally omitted <==
KGL Resources Limited 2024 Ore Reserve Statement
xenith.com.au
66
==> picture [128 x 31] intentionally omitted <==
Figure 29 – Rockface Scheduled Stopes by Fill Type
==> picture [439 x 310] intentionally omitted <==
For the Rockface stopes, the pillar margin is greater than the CRF cost. The results of CRF versus open stoping with pillars analysis for the Rockface stopes is shown below in Table 36.
Table 36 – Rockface Underground Stope Optimiser Iterations
| CuEq Cut-off Grade | 0.83% | 1.00% | 1.16% |
|---|---|---|---|
| Stope Tonnes (Mt) | 3.63 | 3.21 | 3.1 |
| Cu Grade (%) | 2.31 | 2.51 | 2.61 |
| Stope NSR (A$M) | $1,128 | $1,082 | $1,071 |
| Pillar Tonnes (Mt) | 0.76 | 0.68 | 0.65 |
| Cu Grade (%) | 2.37 | 2.54 | 2.67 |
| Pillar NSR (A$M) | $241 | $233 | $227 |
| Pillar Cost (A$M) | $75 | $68 | $63 |
| Pillar Margin (A$M) | $165 | $165 | $164 |
| CRF (Mt) | 2.82 | 2.49 | 2.34 |
| CRF Cost (A$M) | -$112 | -$99 | -$93 |
KGL Resources Limited 2024 Ore Reserve Statement
xenith.com.au
67
9.2.2 Bellbird Underground
Mining methods applied include:
==> picture [195 x 147] intentionally omitted <==
-
› Top down, long-hole stoping with open stopes; and
-
› Bottom up, long-hole stoping with cemented rock fill and rock fill (CRF_RF).
The stope optimisation process identified 400 stopes for the Bellbird deposit. These stopes are situated directly below the Bellbird Open Pit. Due to the low grade nature of the Bellbird lodes, rib pillars left in place between stopes are cost-effective as they offset the backfill costs while maintaining the stability of the open voids. The top down mining eliminates any need for access to the stopes once mined.
There are 180 stopes in 2024 FSU Bellbird Underground schedule. More than 50% of the stopes at depth were excluded from the original inventory due to either scheduling resourcing constraints, Inferred resource confidence, or low-grade ore content.
Where high CuEq grades allow, Bellbird stopes are backfilled with a blend of cemented rock fill and rock fill to recover the metal content in the rib pillars. Some of these areas are mined top down adjacent to unfilled stops. A fill drive located in the footwall has been included in the mine design so these voids can be backfilled.
The Bellbird stope inventory is shown below in Figure 30. The 2024 FSU Bellbird scheduled inventory with fill type is shown below in Figure 31.
Figure 30 – Bellbird Stope Inventory by CuEq Grade.
==> picture [480 x 337] intentionally omitted <==
KGL Resources Limited 2024 Ore Reserve Statement
xenith.com.au
68
==> picture [195 x 147] intentionally omitted <==
Figure 31 – Bellbird Scheduled Stopes by Fill Type
==> picture [461 x 324] intentionally omitted <==
For the Bellbird stopes, in most areas, the CRF cost is greater than the pillar margin. The results of CRF versus open stoping with pillars for the Bellbird stopes is shown below in Table 37.
Table 37 – Bellbird Underground Stope Optimiser Iterations
| CuEq Cut-off Grade | 0.83% | 1.00% | 1.16% |
|---|---|---|---|
| Stope Tonnes (Mt) | 2.43 | 1.82 | 1.46 |
| Cu Grade (%) | 1.52 | 1.69 | 1.83 |
| Stope NSR (A$M) | $491 | $407 | $354 |
| Pillar Tonnes (Mt) | 0.52 | 0.4 | 0.3 |
| Cu Grade (%) | 1.55 | 1.68 | 1.86 |
| Pillar NSR (A$M) | $107 | $90 | $74 |
| Pillar Cost (A$M) | $52 | $40 | $30 |
| Pillar Margin (A$M) | $55 | $49 | $44 |
| CRF (Mt) | 2.25 | 1.69 | 1.34 |
| CRF Cost (A$M) | -$89 | -$67 | -$53 |
KGL Resources Limited 2024 Ore Reserve Statement
xenith.com.au
69
9.2.3 Reward Underground
Mining methods applied include:
==> picture [195 x 147] intentionally omitted <==
-
› Bottom up, long-hole stoping with cemented rock fill and rock fill (CRF_RF);
-
› Bottom up, long-hole stoping of sill pillars with cemented rock fill (CRF); and
-
› Bottom up open stoping with rib pillars under filled sill pillars.
The stope optimisation process identified 272 stopes for the Reward deposit. The stope inventory comprises of a high grade lode in the hanging wall and a lower grade lode in the footwall. Both lodes lie North of the Reward Open Pit. The hanging wall lode extends to -500RL depth, the deepest stopes scheduled out of the four underground mines.
There are 214 stopes in the 2024 FSU Reward Underground schedule. Similarly to Rockface Underground, five sill levels are incorporated in the mine design. The sill levels enable early access to the upper levels and increase production mining fronts in the schedule. Most of stopes in the hanging wall lode are designed to be filled with cemented rock fill or with blended rockfill.
As backfill removes the need for rib pillars, metal recovery is increased. The footwall lode is accessed directly from the main decline. Low grade stopes in the footwall will be extracted by top down mining with rib pillars.
The Reward stope inventory is shown in Figure 32. The 2024 FSU Reward scheduled inventory with fill type is shown below in Figure 33.
Figure 32 – Reward Stope Inventory by CuEq Grade.
==> picture [485 x 342] intentionally omitted <==
KGL Resources Limited 2024 Ore Reserve Statement
xenith.com.au
70
==> picture [195 x 147] intentionally omitted <==
Figure 33 – Reward Scheduled Stopes by Fill Type
==> picture [453 x 319] intentionally omitted <==
For the Reward stopes, in most areas, the pillar margin is greater the CRF cost. The results of CRF versus open stoping with pillars for the Reward stopes is shown below in Table 38.
Table 38 – Reward Underground Stope Optimiser Iterations
| CuEq Cut-off Grade | 0.83% | 1.00% | 1.16% |
|---|---|---|---|
| Stope Tonnes (Mt) | 4.08 | 3.42 | 2.78 |
| Cu Grade (%) | 1.6 | 1.78 | 1.96 |
| Stope NSR (A$M) | $985 | $913 | $819 |
| Pillar Tonnes (Mt) | 0.85 | 0.71 | 0.55 |
| Cu Grade (%) | 1.7 | 1.88 | 2.14 |
| Pillar NSR (A$M) | $217 | $201 | $176 |
| Pillar Cost (A$M) | $85 | $71 | $54 |
| Pillar Margin (A$M) | $132 | $129 | $121 |
| CRF (Mt) | 3.5 | 2.93 | 2.35 |
| CRF Cost (A$M) | -$139 | -$116 | -$93 |
KGL Resources Limited 2024 Ore Reserve Statement
xenith.com.au
71
9.2.4 Marshall Underground
Mining methods selected for Marshall include:
==> picture [195 x 147] intentionally omitted <==
-
› Bottom up long-hole stoping with cemented rock fill (CRF); and
-
› Top down long-hole stoping with cemented rock fill (CRF).
The stope optimisation process generated 162 stopes for the Marshall deposit. The stopes are located directly below the Reward Open Pit and extend North and South following the strike of the orebody. Most of the stopes include rib pillars and are mined top down due the CuEq grade relative to the backfill costs. High grade zones are scheduled with a bottom up sequence to maximise the recovery of metal that would otherwise be left in rib pillars.
From the full Marshall stope inventory, 109 stopes are included in the 2024 FSU Marshall schedule. The schedule inventory comprises open stoping with rib pillars and open stoping with backfill. Stopes below 0RL were excluded from the schedule due to either scheduling resourcing constraints, Inferred resource confidence, or low-grade ore content.
The crown pillar stopes located directly beneath the Reward pit floor are planned to be mined near the end of the mine life.
The Marshall stope inventory is shown below in Figure 34. The 2024 FSU Marshall schedule inventory with fill type is shown in Figure 35 below.
Figure 34 – Marshall Stope Inventory by CuEq Grade.
==> picture [486 x 340] intentionally omitted <==
KGL Resources Limited 2024 Ore Reserve Statement
xenith.com.au
72
==> picture [530 x 462] intentionally omitted <==
----- Start of picture text -----
Figure 35 – Marshall Scheduled Stopes by Fill Type
----- End of picture text -----
For the Marshall stopes, in most areas, the CRF cost is greater than the pillar margin. The results of CRF versus open stoping with pillars for the Marshall stopes is shown below in Table 39.
Table 39 – Marshall Underground Stope Optimiser Iterations
| CuEq Cut-off Grade | 0.83% | 1.00% | 1.16% |
|---|---|---|---|
| Stope Tonnes (Mt) | 3.55 | 2.63 | 1.91 |
| Cu Grade (%) | 1.1 | 1.19 | 1.27 |
| Stope NSR (A$M) | $610 | $497 | $395 |
| Pillar Tonnes (Mt) | 0.37 | 0.28 | 0.2 |
| Cu Grade (%) | 1.17 | 1.27 | 1.35 |
| Pillar NSR (A$M) | $70 | $57 | $45 |
| Pillar Cost (A$M) | $37 | $28 | $20 |
| Pillar Margin (A$M) | $32 | $29 | $25 |
| CRF (Mt) | 2.75 | 2.02 | 1.46 |
| CRF Cost (A$M) | -$109 | -$80 | -$58 |
KGL Resources Limited 2024 Ore Reserve Statement
xenith.com.au
73
==> picture [195 x 147] intentionally omitted <==
9.3 Underground Mine Design
The mine design comprises the capital and operating development that supports stope extraction. Mine designs were completed in Deswik CAD software. Design parameters follow industry best practices.
9.3.1 Lateral Development
Lateral development is mined using conventional drill and blast techniques. Underground design parameters relevant to the Project are shown below in Table 40.
Table 40 – Development Design Profiles
| Parameter | Development Design |
|---|---|
| 5.5mW x 5.8mH arched | |
| Drive Profile – Decline | |
| 5.5mW x 6.0mH arched | |
| Drive Profile – Level Access | 5.5mW x 5.8mH arched |
| Drive Profile – Extraction/ Ore Drives | 5.0mW x 5.0mH arched |
| 5.0mW x 5.0mH arched | |
| Ventilation Lateral | |
| 6.0mW x 6.0mH arched | |
| Decline Gradient | 1 in 7 Down |
| Ore Drive Gradient | 1 in 50 Up |
| Decline X-Cut Stand-off Distance | ~65m |
The total quantity of lateral development metres in each underground mine is tabulated below in Table 41.
Table 41 – Summary of Underground Lateral Development Metres
| Drive Type | Marshall (m) | Reward (m) | Bellbird (m) | Rockface (m) | Total |
|---|---|---|---|---|---|
| Decline | 3,251 | 6,080 | 1,945 | 5,403 | 16,680 |
| Level Access | 2,216 | 2,215 | 739 | 3,852 | 9,022 |
| Stockpile | 399 | 1,974 | 507 | 951 | 3,830 |
| Mixing Bay | 61 | 491 | 222 | 429 | 1,204 |
| Sump | 3,762 | 5,181 | 7,369 | 5,777 | 22,089 |
| Ventilation | |||||
| 953 | 2,003 | 841 | 1,727 | 5,524 | |
| Drives | |||||
| Ore Drive | 99 | 230 | 102 | 202 | 633 |
| Row Total | 10,742 | 18,175 | 11,725 | 18,340 | 58,982 |
KGL Resources Limited 2024 Ore Reserve Statement
xenith.com.au
74
9.3.1.1 Mine Access and Design Overview
==> picture [195 x 147] intentionally omitted <==
9.3.1.1.1 Rockface and Bellbird
The Bellbird and Rockface Underground mines are planned to be accessed via a single portal developed from within the Bellbird Open Pit (after completion of the pit). The decline gradient is 1 in 7 (14.3%).
The Rockface mine is accessed from the Bellbird Open Pit via a 1100 m decline; 200 m of which is shared access with the Bellbird Underground mine. Due to the extensive length of the decline until the return air raise is established, the main decline to the Rockface lodes uses a profile 5.5mW x 6.0mH. The increased drive height accommodates two 1600mm diameter ducts while maintaining adequate clearance to haul trucks.
Once the access decline reaches the Rockface orebody and the primary circuit is established with a 290 m return air raise, the decline profile reverts to 5.5mW x 5.8mH (as a smaller 1400 mm diameter duct can be used).
The Bellbird mine primary ventilation circuit utilises the main decline to deliver fresh air to production levels. The upper portion of this decline is shared access for Bellbird and Rockface mines.
9.3.1.1.2 Reward and Marshall
Access to the Reward decline is via a dedicated box cut (located North of the Reward Open Pit). The main Reward decline from the mine box cut employs profile 5.0mW x 5.8mH and is designed at 1 in 7 gradient. The establishment of a dedicated portal from a box cut allows development of the Reward Underground mine to occur concurrent to production from the Reward Open Pit. The Marshall North Decline is also planned to connect into the Reward mine to reduce the truck haulage route from Reward to the ROM.
The declines accessing Marshall North and South will be established from separate portals within the Reward pit once it is completed. The Marshall North and South declines employ the 5.0mW x 5.8mH profile and are designed at 1 in 7 gradient.
For these mines, production levels situated directly below the Reward Open Pit are linked by short drill and blast exhaust raises with the uppermost level of each connected to separate exhaust portals via raisebored airways. The Marshall North and South declines are both used to deliver fresh air to production levels.
9.3.1.2 Decline Design
Two tunnel section profiles are used for the Project declines; 5.5mW x 5.8mH and 5.5mW x 6.0mH with semiarched shoulder radii of 1.0 m. The larger decline profile is used where a 1600 mm diameter ventilation duct is required. Both profiles are suitable for 60 tonne articulated dump trucks, smaller diameter ventilation ducting, electrical and communications cabling, and service piping (110 mm poly).
The declines will serve as fresh air intakes for each mine. The Decline profile is shown below in Figure 36.
KGL Resources Limited 2024 Ore Reserve Statement
xenith.com.au
75
==> picture [128 x 31] intentionally omitted <==
Figure 36 – Decline Profile Section and Services Detail
==> picture [348 x 261] intentionally omitted <==
The maximum allowable decline gradient for the Project is 1 in 7 or 14.3%. A minimum decline corner radius of 25 m has been used in the designs. Stockpiles occur every 120 m along the decline, which is sufficient for a high-speed development cycle. Once a stockpile is no longer used for rock storage, it will house infrastructure such as electrical substations and refuge chambers (where required).
Stockpiles may also be used for diamond drilling to define the orebody at depth. Stockpiles are generally 17.5 m in length but those designated for infrastructure may be lengthened to allow bunding and provision for vehicle usage.
Should the stockpiles be used as waste material storage for CRF production, additional stripping of the backs may be required to enable truck tipping in the stockpiles.
The decline to ore body stand-off distance to stopes is approximately 65 m. This distance will minimise potential damage to the decline from production activities.
9.3.1.3 Level Design
The Jervois underground mines’ level access and level stockpile drive profiles are 5.5mW x 5.8mH. As each level access will house similar service infrastructure and 60 tonne trucks, the decline section area is maintained on to the production level.
Production ore drives, sumps and ventilation drives are mostly designed at 5.0mW x 5.0mH at gradients 1 in 50 or 2.0%. This section area is appropriate for a Caterpillar R2900 Load Haul Dump (LHD) or similar. The ore drive profile is designed with semi-arched shoulder radii of 1.0 m.
The profile provides clearance for 1220 mm diameter secondary ventilation duct, electrical and communications cabling, and service piping (63 mm poly). The ore drive profile is shown below in Figure 37.
KGL Resources Limited 2024 Ore Reserve Statement
xenith.com.au
76
==> picture [128 x 31] intentionally omitted <==
Figure 37 – Ore Drive Profile Section and Services Detail
==> picture [276 x 214] intentionally omitted <==
Production of CRF backfill requires waste rock to be mixed with cement slurry in underground mixing bays. LHD units then tram and tip the CRF into the stope void. The required mixing bays must be located within close tramming distance to the stopes being filled. Mixing bays have been included as part of each of the Jervois mine designs where required. Further details regarding mixing bay design are included in Section 9.4.2. A typical underground level layout is shown below in Figure 38.
Figure 38 – Example Underground Level Layout for the Jervois Project
==> picture [319 x 290] intentionally omitted <==
KGL Resources Limited 2024 Ore Reserve Statement
xenith.com.au
77
==> picture [195 x 147] intentionally omitted <==
9.3.2 Vertical Development
Vertical development will be established by raisebores or drill and blast. Raises of different section areas are required to support each mine’s ventilation strategy.
The total quantity of vertical development metres in each underground mine is tabulated below in Table 42.
Table 42 – Summary of Underground Lateral Development Metres
| Type | Marshall | Reward | Bellbird | Rockface | Total |
|---|---|---|---|---|---|
| 1.1m Dia. Raisebore | 572 | 763 | 312 | 726 | 2,373 |
| 3.1m Dia. Raisebore | - | - | - | - | 0 |
| 3.5m Dia. Raisebore | - | - | 321 | - | 321 |
| 4.0m Dia. Raisebore | - | 313 | - | - | 313 |
| 4.5m Dia. Raisebore | 69 | 1,070 | 71 | 1,229 | 2,439 |
| 5.5m Dia. Raisebore | 220 | 146 | - | 278 | 644 |
| Ventilation D&B Raise | 221 | 602 | 162 | 506 | 1,491 |
| Row Total | 1,083 | 2,894 | 867 | 2,738 | 7,582 |
KGL Resources Limited 2024 Ore Reserve Statement
xenith.com.au
78
==> picture [195 x 147] intentionally omitted <==
9.3.3 Mine Design Schematics
An overview of the Jervois Project underground mine designs are provided below in Figure 39 to Figure 42.
Figure 39 – Rockface and Bellbird Underground – looking South
==> picture [808 x 567] intentionally omitted <==
KGL Resources Limited 2024 Ore Reserve Statement
xenith.com.au
79
Figure 40 – Rockface and Bellbird Underground Mine Design – looking West
==> picture [195 x 147] intentionally omitted <==
==> picture [808 x 565] intentionally omitted <==
KGL Resources Limited 2024 Ore Reserve Statement
xenith.com.au
80
Figure 41 – Reward and Marshall Underground Mine Designs – looking West
==> picture [195 x 147] intentionally omitted <==
==> picture [808 x 567] intentionally omitted <==
KGL Resources Limited 2024 Ore Reserve Statement
xenith.com.au
81
Figure 42 – Reward and Marshall Underground Mine Designs – looking South
==> picture [195 x 147] intentionally omitted <==
==> picture [808 x 569] intentionally omitted <==
KGL Resources Limited 2024 Ore Reserve Statement
xenith.com.au
82
==> picture [195 x 147] intentionally omitted <==
9.4 Underground Mine Operations
9.4.1 Mining Equipment
Equipment deployed will depend on the preferences of the contractor engaged, the contract specifications and any relevant legislated standards. The total equipment for the underground mines is based on the current mine schedules and has been provided by a third party mining contractor for the purposes of project costing. The current underground mining fleet list provided by the contractor is summarised below in Table 43.
Table 43 – Total Underground Mining Equipment by Year of Mining
| Year of Mining | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 |
|---|---|---|---|---|---|---|---|---|---|---|---|
| Twin Boom Jumbo | |||||||||||
| - | 2 | 4 | 4 | 4 | 4 | 4 | 4 | 4 | 3 | - | |
| (Sandvik DD421) | |||||||||||
| Cable Bolter | - | 2 | 2 | 2 | 2 | 2 | 2 | 2 | 2 | 2 | 2 |
| Prod Drill Rig | |||||||||||
| - | - | 2 | 2 | 2 | 3 | 4 | 4 | 4 | 3 | 2 | |
| (Sandvik DL421) | |||||||||||
| Charge Up Rig | |||||||||||
| - | 2 | 2 | 2 | 2 | 4 | 4 | 4 | 4 | 3 | 2 | |
(Normet Charmec) |
|||||||||||
| LRG Loader | |||||||||||
| - | 2 | 3 | 5 | 6 | 8 | 8 | 8 | 8 | 7 | 3 | |
| (CAT R2900) | |||||||||||
| Haul Truck 60t | |||||||||||
| - | 2 | 2 | 6 | 10 | 12 | 13 | 13 | 13 | 9 | 4 | |
| (CAT AD60) | |||||||||||
| Agitator Truck | |||||||||||
| - | - | - | 2 | 2 | 2 | 2 | 2 | 2 | 2 | 1 | |
(10m³) |
|||||||||||
9.4.2 Development, Production and Backfill
9.4.2.1 Mine Backfill
Backfilling of stopes will utilise mostly cemented rock fill (CRF). To produce CRF, waste rock is mixed with cement slurry in underground mixing bays. Loaders backfill the CRF into each stope void. Sump mixing with a loader offers a low cost form of exposable backfill for mines with small, narrow stopes.
Most stopes will be backfilled as single exposure stopes, requiring 60% CRF emplacement. A small number of key stopes will require 100% CRF emplacement. Some stopes will be backfilled with available clean waste rockfill. A schematic for CRF backfilling is shown below in Figure 43.
Notably the variable nature of run-of-mine waste and limited control over sump mixing generally means CRF is not suitable for undercut exposure (working directly beneath the CRF fill). Study work indicates higher strength CRF results when the waste rock used contains fines and has been screened of oversize above 400 mm; CRF can attain compressive strengths of between 2-3 MPa.
CRF Backfill has been scheduled to occur at a rate of 435 – 700 t/day for the Jervois underground mines. This rate is provided by the mining contractor for the specified Caterpillar R2900 loader. The lower backfill rate is reflective of an increased tramming distance. Rates are reliant on continuous supply of cement binder to the CRF mixing bays. Binder will be delivered by agitator trucks from a surface batch plant.
KGL Resources Limited 2024 Ore Reserve Statement
xenith.com.au
83
==> picture [195 x 147] intentionally omitted <==
To reduce tramming distances, mixing bays should be placed as close to stopes as practical. For the Jervois underground, development designs include a single mixing bay on each level where CRF is required. Mixing bays will require two-pass benching of a 20 m long drive.
This is to provide suitable height for the loader to dig, drop and mix. In addition, if no ejector trucks are included in the Jervois mining fleet, the waste rock stockpile on each level (or stockpiles on the decline), will need to be stripped to 7.5 – 8.0 m high to allow dump truck tipping of waste for CRF mixing.
Figure 43 – Cemented Rock Fill Schematics
==> picture [438 x 279] intentionally omitted <==
Example mixing bay designs with indicative mix ratios for 3% and 5% cement CRF are shown below in Figure 44. The schematics in Figure 44 are illustrative only as they are based on a set bucket volume. Specific CRF batch recipes will need to be developed for the Jervois Project at execution.
Figure 44 – Example CRF 3% Mix and 5% Mix Mixing Bay (Sump) Designs
==> picture [480 x 142] intentionally omitted <==
KGL Resources Limited 2024 Ore Reserve Statement
xenith.com.au
84
9.4.2.2 Production Mining
==> picture [195 x 147] intentionally omitted <==
9.4.2.2.1 Production Drilling
A drilling rate of 270 m/day and stope tonne per drill metre factor of 7 t/metre were applied to the Jervois schedules. These factors are based on typical benchmark drilling rates for hole diameters of 76 - 89 mm and typical stope drilling yields.
The drilling rates are assumed to include all activities and delays related to production drilling, including drill rig up, drill rig down, slot drilling, production drilling, shift change and meetings, meal breaks, breakdowns, maintenance, services installation, and geology/survey/engineering control delays.
9.4.2.2.2 Production Bogging
A total instantaneous stoping rate of 1,200 t/day has been applied to the stopes in the schedule based on stope size in addition to typical bogging distance. This includes all conventional and remote stope loading activities. This rate does not include charging time, as a one-day delay has already been allowed for in scheduling between production drilling and bogging activities.
All development was assumed to be loaded conventionally. Stope bogging rates include activities and delays associated with bogging, including mine firings, re-entry, remotes set-up and testing, bogging, truck loading, shift change and meetings, meal breaks, breakdowns, maintenance, services installation, and geology, survey and engineering inspection intervals.
9.4.2.3 Development Mining
9.4.2.3.1 Lateral Development
Twin boom jumbos are used to mine lateral development. These drill rigs drill 45 mm blastholes for development rounds and are also used to installation in-cycle ground support and rehab as required. Drill rigs specifically designed to install cable bolts are also included in the Jervois fleet.
A lateral development advance rate of 250 m/month was applied to the schedule. The maximum advance rate in a single heading decline was set at 160 m/month, reducing to 100 m/month when additional development headings are available. All other headings were set at 50 m/month.
These advance rates are assumed to include all activities and delays related to the development cycle, including drill rig up, drill rig down, face drilling, charging and firing, re-entry, bogging, ground support installation, services installation, shift change and meetings, meal breaks, breakdowns, maintenance, face markup and geology/survey control delays.
The peak monthly development rate in the Jervois schedule is approximately 1000 m per month equating to an advance rate of 250 m/month across four jumbos.
9.4.2.3.2 Vertical Development
Vertical development for the Jervois underground mines is mined by either raisebore or long hole drill and blast methods.
KGL Resources Limited 2024 Ore Reserve Statement
xenith.com.au
85
9.4.4 Mine Ventilation
==> picture [195 x 147] intentionally omitted <==
The following section presents the key elements of the 2024 FSU ventilation design. The ventilation assessment that supports the 2024 FSU underground mine designs and schedules is documented within the supporting report: XEN_3058KGL_Jervois Ventilation Report_20241028.pdf
9.4.4.1 Ventilation Modelling
The ventilation model has been constructed in Ventsim™ using the parameters detailed below in Table 44 and Table 45. Due to differing production profiles of each underground mine, several airway section areas are shown for the same drive type.
Table 44 – Airway Velocities
| Parameter | Value | Comments |
|---|---|---|
| Raises or shafts (bored) – | Considering economic assessment. Outside | |
| 15-20 m/s | ||
| intake or exhaust (dedicated) | water blanketing range. |
|
| Raises or shafts (D&B) – intake | ||
| max. 12 m/s | Considering economic assessment. | |
| or exhaust (dedicated) | ||
| Raises or shafts – ladderway | <6 m/s | Safe access for personnel |
| Lateral airway – intake or | ||
return (personnel or vehicle |
<6 m/s | Reduce risk of dust entrainment |
| access) | ||
| Lateral airway – intake or | ||
| Access approval system to be administered at | ||
return (infrequent personnel or |
10-12 m/s | |
| operational level. | ||
| vehicle access) | ||
| Routine work area – no | Worker comfort, reduced risk of dust | |
| 0.3-4 m/s | ||
| contaminants | entrainment. | |
| Routine work area – wet bulb | ||
| (WB) temperature greater than | min. 0.5 m/s | Western Australian guidelines. Best practice. |
| 27°C or dust or gas |
Table 45 – Airway Dimensions and Airflow Quantities Based on Velocity Ranges
| Airway | Dimensions | **Area (m2) ** | Max. Quantity (m3/s) |
|---|---|---|---|
| 5.5mW x 5.8mH arched | 30.9 | 185 | |
| Declines | |||
| 5.5mW x 6.0mH arched | 35.0 | 210 | |
| Extraction / other | 5.0mW x 5.0mH arched | 24.0 | 96 |
| lateral | |||
| Level access lateral | 5.5mW x 5.8mH arched | 30.9 | 124 |
| 5.0mW x 5.0mH arched | 24.0 | 288 | |
| Ventilation lateral | |||
| 6.0mW x 6.0mH arched | 35.0 | 420 | |
KGL Resources Limited 2024 Ore Reserve Statement
xenith.com.au
86
==> picture [195 x 147] intentionally omitted <==
| Airway | Dimensions | **Area (m2) ** | Max. Quantity (m3/s) |
|---|---|---|---|
| 2.4 m dia. round | 4.5 | 90 | |
| Intake raise | 3.0 m dia. round | 7.1 | 141 |
| (bored) | 3.5 m dia. round | 9.6 | 192 |
| 4.5 m dia. round | 15.9 | 318 | |
| 3.5 m dia. round | 9.6 | 192 | |
| Exhaust raise | 4.0 m dia. round | 12.6 | 251 |
| (bored) | 4.5 m dia. round | 15.9 | 318 |
| 5.5 m dia. round | 23.8 | 476 | |
| Exhaust raise | 4.0mW x 4.0mW square | 16.0 | 192 |
| (D&B) | 5.0mW x 5.0mW square | 25.0 | 300 |
Table 46 – Friction Factors
| Parameter | **Value (kg/m3) ** |
|---|---|
| Lateral | 0.012 |
| Decline | 0.014 |
| Raise (D&B) | 0.020 |
| Raise (Bored) | 0.005 |
| Conveyor | 0.014 |
| Duct Flexible | 0.004 |
9.4.4.2 Primary Ventilation Design
The primary circuit for each mine uses the decline as the primary intake path. The decline access is developed under forced ventilation until a vertical airway establishes a primary ventilation loop for each mine. Drill and blast ventilation raises then extend the primary circuit between sub-levels. Where required, the Jervois underground mines have a supplementary parallel intake and exhaust raisebore system. All mines include an escapeway network that is established as a fresh air intake.
Ventsim modelling was used to assess the underground mine design and ensure that the current design specifications allow sufficient air quantities for anticipated peak fleet requirements.
Key milestones for the underground that will require further modelling include:
-
› The depth and timing of exhaust and intake airway duplications relative to the required mine primary airflow;
-
› Interaction of Marshall North and Reward, and Rockface and Bellbird primary circuits relative to the required mine primary airflow for each mine (to ensure airflow velocities in the shared declines are not exceeded but to also assess the impact on each mine); and
-
› The circuit resistance at different mine schedule stages to determine a range of required primary fan duties.
KGL Resources Limited 2024 Ore Reserve Statement
xenith.com.au
87
==> picture [195 x 147] intentionally omitted <==
The primary airflow requirements for the Jervois Project are estimated from the probable mining fleet for each of the underground mines. The airflow requirement is derived from the maximum rated power (kW) of the estimated mining fleet, multiplied by the Western Australian airflow factor for ventilation of diesel units of 0.05 m[3] /s/kW (Section 656C of the Western Australian Work Health and Safety (Mines) Regulation 2022).
The fleet airflow estimate was then cross checked against benchmark data for Australian stoping operations. The result of the benchmarking exercise is shown below in Figure 45. The analysis indicates close alignment between the diesel fleet airflow estimate and the benchmark data for Bellbird, Reward and Rockface.
Figure 45 – Jervois Primary Airflow Benchmarking
==> picture [483 x 236] intentionally omitted <==
For the Marshall North and South mines airflow estimates deviate from benchmarking. The deviation is due to the following factors:
-
› The Marshall North and South mines have small mine footprints with independent ventilation systems;
-
› The combined maximum annual production of the Marshall North and South mines is 0.99 Mtpa for total primary airflow of 370 m[3] /s. This is consistent with benchmarking;
-
› The small mine footprints means additional heavy equipment (trucks, graders, agitators, services trucks) can remain outside of the ventilation circuit in the Reward pit;
-
› The reduced depth of mining and small mine footprints of the Marshall North and South mines enable use of a lower leakage, density and maldistribution allowance (5%); and
-
› Marshall North contains two levels that are connected to the Reward mine primary circuit. These levels are scheduled after development mining at Reward has ceased and hence, will be ventilated using the Reward primary fans.
9.4.4.3 Ventilation Design Recommendations
-
› From 1 December 2026, Safe Work Australia (SWA) will include an allowable concentration for diesel particulate matter (DPM) in the workplace exposure limits (WEL). Diesel emissions modelling was beyond the scope of work for the ventilation study. To ensure compliance with future legislation diesel emissions modelling of the finalised fleet should be completed prior to project execution;
-
› The fleet estimates for each mine were derived from the 2024 FSU mining schedule. The fleet estimates were checked against the fleet supplied by the proposed contractor; the fleet estimate was within an
KGL Resources Limited 2024 Ore Reserve Statement
xenith.com.au
88
==> picture [195 x 147] intentionally omitted <==
allowable margin of error for electrical power consumption estimates. The finalised fleet from the selected mining contractor must be considered when producing the final primary fan duties;
-
› The Jervois primary airflow estimates were benchmarked against other mining operations with similar materials handling systems. The analysis indicates close alignment between the diesel fleet estimate and benchmark data for Bellbird, Reward and Rockface; and
-
› The lateral and vertical development profiles (section areas) assigned are suitable for the derived airflow estimates. All proposed mine designs are suitable for peak production.
9.4.5 Mine Services
The selected underground mining contractor will be responsible for providing all secondary power cabling, pumping and sump management, mine services reticulation, communications installations and cabling and underground roadway maintenance. Installation and maintenance have been included in the rates and costings that form the fixed and variable pricing for underground mining.
9.4.5.1 Electrical Power
Power supply for use underground will be supplied by KGL and will include electrical sub-stations which are nominally located every 300 m vertically for each mine. High voltage reticulation will be supplied to the network of sub-stations. Substations will be placed in disused decline stockpiles at the interval provided. The mining contractor will then be responsible for distribution of power to other underground locations as required.
9.4.5.2 Compressed Air
The mining contractor will supply air compressors and be responsible for the distribution of compressed air to underground work areas. Compressors will be located on the surface adjacent to each of the underground portals.
9.4.5.3 Raw Water
KGL will supply raw water. It will be the responsibility of the mining contractor to connect to, distribute, and discharge water back to the designated storage facilities for settling, storage and re-use.
9.4.5.4 Communications
The contractor will supply and maintain the underground communications network. This will be a leaky feeder radio system and repeater. Future requirements may see the addition of alternate communications networks (such as ethernet or Wi-Fi systems).
9.4.5.5 Remote Systems and Firing Lines
The contractor will supply and maintain the required systems for remote operation of loaders for stope production. The contractor will also install and maintain the system to initiate blasts throughout each of the mines.
9.4.5.6 Road base
KGL will maintain a stockpile of suitable road base to which the underground contractor will have access to. The underground contractor will be responsible for distributing road base to each of the underground mines and for maintaining road and travel ways to an appropriate standard. This will include grading and utilisation of a water cart and/or spray systems.
KGL Resources Limited 2024 Ore Reserve Statement
xenith.com.au
89
9.4.5.7 Dewatering
==> picture [195 x 147] intentionally omitted <==
Groundwater information used within this report is sourced from the report provided by CloudGMS for the Jervois Project Feasibility Study, the report is:
› GX6 A7 Groundwater Management Plan Rev V4 (27/01/2022)
Groundwater levels at Jervois are generally greater than 20 m metres below ground level. Two sites drilled in 1972 reported groundwater levels less than 5 m below ground level, but these were interpreted to be associated with Unca Creek. Both bores were completed to less than 15 metres and this suggests that this feature may be overlying less permeable rocks and as such is disconnected from the regional groundwater system.
The primary fractured rock unit through which groundwater flow occurs in the Project area is the Bonya Metamorphics. Drilling has identified that faults cross-cutting the “J-fold” units of the Bonya Schist can result in increased local permeability along the features.
The pits and underground workings are in these low permeability metasediments, hence, based on analytical estimates of pit inflows, there is expected to be limited groundwater recharge or discharge through the walls of the mine excavations.
Mine water sources will be mainly from groundwater seepage and process water used in mining operations for development drilling, washing, backfill, production drilling and bogging.
The forecast of groundwater inflows in underground mine is summarised below in Table 47.
Table 47 – Forecast Annual Life of Underground Mine Working Inflows.
| Bellbird | Reward | Rockface | Bellbird | Reward | Rockface | |||
|---|---|---|---|---|---|---|---|---|
| Year | Total | Total | ||||||
| UG | UG | UG | UG | UG | UG | |||
| L/s | L/s | L/s | L/s | ML/d | ML/d | ML/d | ML/d | |
| 1 | 17.3 | 0 | 0 | 17.3 | 1.49 | 0 | 0 | 1.49 |
| 2 | 44.8 | 0 | 0 | 44.8 | 3.87 | 0 | 0 | 3.87 |
| 3 | 36.5 | 0 | 0 | 36.5 | 3.15 | 0 | 0 | 3.15 |
| 4 | 32.7 | 0 | 0 | 32.7 | 2.82 | 0 | 0 | 2.82 |
| 5 | 41.2 | 0 | 10.7 | 30.5 | 3.56 | 0 | 0.92 | 2.64 |
| 6 | 49.3 | 0 | 49.3 | 0 | 4.26 | 0 | 4.26 | 0 |
| 7 | 42.7 | 0 | 42.7 | 0 | 3.69 | 0 | 3.69 | 0 |
| 8 | 64.6 | 29.1 | 35.5 | 0 | 5.58 | 2.52 | 3.07 | 0 |
| 9 | 53.7 | 21.2 | 32.5 | 0 | 4.64 | 1.83 | 2.81 | 0 |
| 10 | 50.6 | 19.8 | 30.9 | 0 | 4.37 | 1.71 | 2.67 | 0 |
The Life of Mine schedule shows the extent of mining depth which is indicative of the total head that the dewatering system should overcome to remove water from underground mine workings. The dewatering system consists of a staged primary pumping system with pump installations installed approximately 150 m vertically apart.
KGL Resources Limited 2024 Ore Reserve Statement
xenith.com.au
90
==> picture [195 x 147] intentionally omitted <==
The water produced from groundwater and mining activities will be collected in a dedicated sump on each level. Water will report from active work areas to these sumps due to either the gradient of the tunnel or by mechanical means such as submersible “flygt” style pump. The water is then pumped to the closest primary pumping installation to be removed from the mine.
The proposed dewatering system for the underground mines is as follows:
-
› Marshall Underground – 3 single WTX3;
-
› Reward Underground – 5 twin WTX3;
-
› Rockface Underground – 1 single WTX3 at the bottom level, 4 twin WTX3; and
-
› Bellbird Underground – 1 single WTX3.
KGL Resources Limited 2024 Ore Reserve Statement
xenith.com.au
91
10. Mineral Processing
==> picture [195 x 147] intentionally omitted <==
10.1 Processing Plant Design
The process plant design is a conventional concentrator for copper with gold and silver by-products. The design consists of semi-fixed jaw crushing, semi autogenous and ball mill grinding, Jameson cell rougher flotation, regrinding and Jameson cell cleaner flotation followed by concentrate thickening and dewatering by filter press. Product concentrate is stockpiled within a purpose-built covered concentrate holding facility prior to being transported to the Glencore Mt Isa smelter.
Sedgman have refined the process plant design and flowsheet to provide incremental improvements in Project value with the 2024 FSU process plant design, delivery schedule and cost estimate having also been subject to peer review.
The current design now differs from the previous designs via inclusion of additional Jameson cells and a larger regrind mill and larger SAG mill and is based on a 250 t/hr throughput rate for a nameplate 2.0 Mtpa processing capacity. The plant will produce copper-gold-silver concentrate only. The capital cost estimate for the processing plant is $177.9 million.
A three-dimensional view of the plant arrangement is shown below in Figure 46.
Figure 46 – 2024 FSU Process Plant Arrangement
==> picture [487 x 300] intentionally omitted <==
The processing plant will be operated under an operating contract that includes provision of management, operating labour and plant maintenance. The operating contract is expected to include key performance measures targeting plant throughput, metallurgical performance and concentrate quality and despatch performance.
KGL Resources Limited 2024 Ore Reserve Statement
xenith.com.au
92
==> picture [195 x 147] intentionally omitted <==
10.2 Process Flow Sheet
The 2024 FSU summary flowsheet developed for the plant is shown below in Figure 47.
Figure 47 – Flowsheet for Process Plant
==> picture [914 x 568] intentionally omitted <==
KGL Resources Limited 2024 Ore Reserve Statement
xenith.com.au
93
==> picture [195 x 147] intentionally omitted <==
10.3 Sample Preparation Facility
A sample preparation/XRF scanning facility will be established adjacent to the processing facility. Sampling from underground locations and throughout the processing plant will be transported at least daily to the ALS Laboratory in Mt Isa for testing. Samples will be transported using the concentrate haulage trucks.
During open pit mining operations, the time between grade control sampling and mining allows some flexibility in sample turnaround. As mining moves underground and grade control becomes more hand-to-mouth within the mining activities, an assay laboratory is planned to be operating at site. The cost of the onsite laboratory is included within the sustaining capital cost in year three of operations.
10.4 Tailings Storage Facility
The tailings storage facility (TSF) will consist of one cell and will be constructed (raised) in stages using mine waste sourced from mining pre-strip, diversion drain excavation and locally borrowed soil materials.
The design objectives for the TSF included:
-
› Permanent and secure containment of tailings material;
-
› Maximisation of tailings densities through sub-aerial deposition;
-
› Removal and re-use of water through constant dewatering;
-
› Seepage minimisation and control;
-
› Storage capacity to retain a 1 in 100-year recurrence interval, 72-hour duration storm event throughout the life of the Project;
-
› Ease of operation; and
-
› Rapid and effective rehabilitation.
The TSF has been designed in accordance with design criteria applicable to the ‘High C’ category drawn from the Australian National Committee on Large Dams (ANCOLD) guidelines. ANCOLD guideline design levels for earthquake, consequential population at risk and potential environmental and economic impacts were considered during design. The resulting peak ground acceleration levels are considered low.
The TSF is included in the 2024 FSU financial model at an initial cost of $22.2M. Any future lifts will be covered
in Sustaining Capital.
The design capacity adopted for the TSF are detailed below in the Table 48 with the location of the TSF relative to surrounding infrastructure shown in Figure 48.
Table 48 – Tailings Storage Facility Design Parameters
| Design Parameters | Design Value | Units |
|---|---|---|
| Mill Feed | 1.6 – 2.0 | Mtpa |
| Copper Concentrate Production | Up to 130 | Ktpa |
| Mine Life | 10.4 | Years |
| TSF Capacity | >16 | Mt |
| Tailings Density | 1.30 - 1.45 | t/m3 |
| Tailings Beach Slope | 2.5 | % |
KGL Resources Limited 2024 Ore Reserve Statement
xenith.com.au
94
==> picture [195 x 147] intentionally omitted <==
Figure 48 – Tailing Storage Facility Location (looking Northeast)
==> picture [483 x 220] intentionally omitted <==
*Note – Process Plant is located to the east of the TSF, Reward Pit and Northern Dump are in the background.
10.5 Concentrate Marketing & Transport
Copper concentrate (which includes recovered copper, gold and silver) will be sold to the Glencore International AG (Glencore) smelter in Mt Isa. A high-level outline of the key aspects of the agreement is as follows:
-
› The agreement is for the sale of all concentrate produced from the Project for a minimum term of five full calendar years after commencement of commercial production. The sale agreement is evergreen and will continue beyond the minimum term until either party terminates it by giving two years’ prior notice;
-
› The sale price for the copper concentrate is tonnage based and calculated by reference to the LME cash settlement price for copper, with silver and gold credits (subject to minimum ‘payable’ limits). The sale price includes adjustments for treatment, refining and treatment charges, penalties associated with impurities above agreed threshold values, and other adjustments;
-
› By-product credits for the gold and silver in the concentrate will be paid (within certain contractual limits) in addition to payable copper;
-
› Penalty elements are identified in the agreement including bismuth, fluorine and uranium. There are no rejection criteria included in the agreement. Bismuth is the only element foreseen to exceed defined threshold levels and be penalised;
-
› The agreement is subject to other customary terms and conditions, including processes for assaying, weighing, sampling and moisture determination in relation to the concentrate, and contains relevant force majeure clauses; and
-
› The details of the Glencore agreement are commercially confidential.
Copper concentrate will be transported from the Project to Mt Isa in conventional, covered bulk haulage trailers in road train configuration (approximately 100 tonne payload). Annual concentrate haulage is up to 150 kt (wet).
Truck haulage from site is currently approved for up to 150,000 tonnes per annum via the Plenty Highway. Modification to this approval to haul east is to be finalised. Haulage from the Northern Territory / Queensland
KGL Resources Limited 2024 Ore Reserve Statement
xenith.com.au
95
==> picture [195 x 147] intentionally omitted <==
border to Mt Isa is to be progressed in consultation with Glencore, affected parties and the Queensland Government.
The concentrate haulage route between the Project and Mt Isa is 488 km in total. The Plenty Highway makes up 213 km of the route. There is a further 187 km of unsealed road between the Plenty Highway and National Road 83.
The remaining 88 km portion of National Road 83 (Bourke Developmental Road) is already sealed to Mt Isa. The concentrate haulage route in full is shown below in Figure 49.
Figure 49 – Concentrate Haulage Route
==> picture [483 x 371] intentionally omitted <==
KGL Resources Limited 2024 Ore Reserve Statement
xenith.com.au
96
11. Project Infrastructure
==> picture [195 x 147] intentionally omitted <==
11.1 Site Infrastructure Design
All key items of infrastructure required have been considered as part of the 2024 FSU. The Project is designed as a remote standalone facility and comprises all components for operations. Significant project infrastructure will include:
-
› Site buildings including:
-
Administration & first aid building;
-
Emergency response facility;
-
Warehouse;
-
Crib rooms & ablutions;
-
Reagent storage area; and
-
Process plant workshop.
-
› On-site LV and HV roads;
-
› Fuel storage tanks;
-
› Hybrid wind/solar/diesel/battery - battery energy storage system (BESS) power station;
-
› High voltage (HV) power reticulation and step-down transformers;
-
› Water borefield (including local power generation);
-
› Communications infrastructure;
-
› Jervois Airstrip;
-
› Site gate/site fencing; and
-
› 300-room accommodation camp (build, own and operate contract) including:
-
Sewage treatment facilities;
-
Water treatment plant and potable water reticulation; and
-
Camp roads, landscaping and fencing.
11.1.1 Warehouse
Stores and logistic areas total around 33,000 m[2] and will support inventory storage, laydown, receivals and issue for all logistic activities at site. The stores area is located as a permanent facility adjacent to the process plant.
11.1.2 Fuel Storage Facility
The Project’s proposed main fuel storage facility will be located east of the power station and south of the processing facility. The fuel storage facility will consist of 10 equally sized self-bunded tanks of 110,000 litres each. The total site fuel storage is 1.1 million litres.
11.1.3 Power Generation and Transmission
Power to the Project will be supplied by a Build, Own, Operate and Manage (BOOM) hybrid power generation facility consisting of a wind farm, large solar photovoltaic (PV) arrays, a diesel-powered power plant and battery energy storage system (BESS).
The remote nature of the Project requires the construction of a power station to suit the projected 16 MW maximum power demand. The power station will satisfy the requirements of the mining operations, process
KGL Resources Limited 2024 Ore Reserve Statement
xenith.com.au
97
==> picture [195 x 147] intentionally omitted <==
plant, camp, contractor’s area and other powered areas of site. The power station is modular and like many other remote site power stations. The power generation facilities will have flexibility for adding or subtracting generation capability as the mine evolves over time.
The following main items are included in this footprint:
-
› 24 MW wind farm;
-
› 21 MW solar power station;
-
› 14 MW battery energy storage system (5 MWhr capacity);
-
› 17 x 1 MW diesel generator sets;
-
› Self-bunded diesel day tank;
-
› Switch room;
-
› Transformers and inverters;
-
› Control system;
-
› Control room; and
-
› Containerised office/workshop/store.
Power reticulation for the Project will utilise a high voltage site-wide power distribution network. This network will be installed between key electrical nodes, with distances between power take off nodes warranting a voltage of 11 kV to reduce resistance related power losses through power transmission.
The above power station arrangement is expected to provide a unit cost of $0.29 per kWh.
11.1.4 Water Management
Water is sourced predominantly from groundwater bores and from dewatering of pits and underground workings as mining activities progress. Any water captured in sediment ponds, within mine pits and underground mines will be reused in processing or dust control – as water quality allows.
The Lucy Creek borefield system is located 20 km north-north-west of the mine site and approximately 40 km from the processing facility. A mineral lease (ML32277) over this area was approved in July 2020. The peak water demand is expected to be 3.5 ML per day, while water approvals for the Lucy Creek borefield and additional supply from the Jervois Dam equates to 4.6 ML per day.
Potable water will be provided through two reverse osmosis plants. A plant will be installed at each of the processing and accommodation facilities.
11.1.5 Accommodation Camp
Accommodation camp size is based on the estimates of total personnel required to support the mining operation. A permanent 300 room camp will be constructed in three phases. The accommodation camp is planned to be located approximately 2.5 km from the processing plant. The existing exploration camp is expected to remain occupied for the Project duration.
The total operating cost for the camp is estimated at $77.8M for the life of the Project. The capital cost for construction of the camp is expected to be $29.9M.
11.1.6 Airstrip
An asphalt airstrip will be constructed adjacent to the accommodation village on the eastern side of Lucy Creek Access Road. The airstrip will be sized for 100 seat jet aircraft and is the primary means of transporting people to and from site. Transfers from all Australian capital cities to the site will be supported with the option to refuel at the Jervois airstrip if required.
KGL Resources Limited 2024 Ore Reserve Statement
xenith.com.au
98
==> picture [195 x 147] intentionally omitted <==
Establishment of the airstrip is prioritised early in the Project construction phase to support the ramp up of activities on site and is also timed to coincide with the accommodation village achieving second stage capacity. The cost of construction for the airstrip is estimated at $22.4M.
The existing Bonya aerodrome at the Bonya (Baikal) community is currently used by the exploration team at Jervois. The Bonya airstrip will be suitable for early project construction requirements until the Jervois airstrip is completed.
11.1.7 Ancillary Infrastructure
Additional project infrastructure included in the capital estimate for the 2024 FSU includes:
-
› Site buildings including:
-
Health Clinic / First Aid building;
-
Emergency Response building;
-
Administration building;
-
Security building;
-
Shift Change / Meeting rooms; and
-
Core Shed building.
-
› Communications infrastructure;
-
› Process plant mobile equipment;
-
› Site gate / security fencing;
-
› CCTV system for site access points, accommodation camp, breathalysers, stores, kitchen/mess hall as a recorded but not monitored system;
-
› Sewage treatment facility;
-
› On-site roads (separated from heavy haulage roads/routes);
-
› Vehicle washdown; and
-
› Unca Creek diversion.
KGL Resources Limited 2024 Ore Reserve Statement
xenith.com.au
99
12. Regulatory Approvals
==> picture [195 x 147] intentionally omitted <==
The Project has achieved several regulatory approvals. Most significantly, the Project is authorised under the Mining Management Act 2001 (NT). As part of the approvals process, during different study phases, KGL have completed several environmental assessments and field surveys. These assessments and surveys encompass key aspects including flora and fauna, archaeology, surface water, groundwater, social impacts and geochemistry.
These investigations were used to inform the draft Environmental Impact Statement (EIS) and associated Supplement Report. The completion of these studies resulted in the NT Environmental Protection Agency (NT EPA) issuing its Assessment Report in September 2019. Subsequently, the NT Minister for Mining and Industry granted Authorisation 1061-01 for the approval of the Project and associated Mining Management Plan (MMP) in January 2021.
The Project was self-assessed and referred to the Federal Department of Environment in November 2013. In November 2014 the Project was found not to be a controlled action and no Federal involvement was required in the assessment process.
In accordance with the conditions in Authorisation 1061-01, KGL must comply with, develop and operate the Project in accordance with environmental commitments and safeguards identified and recommended in the Project EIS, the NT EPA Assessment Report 90 and the approved MMP for the Project.
The approved MMP for the Project contains numerous strategies and environmental management plans which have been specifically designed to address and monitor all commitments and recommendations which form part of the Project authorisation. The MMP will be updated and amended as required to reflect changes in Project activities which result in a change to the level of environmental impact or when environmental management strategies are revised.
KGL has approval from the NT Department of Infrastructure, Planning and Logistics for water infrastructure to be installed within existing state gazetted roadways. During the early stage of Project construction and prior to first ore processing, approvals for concentrate haulage eastward to Mt Isa will be required.
The traditional custodians of the land in the Southern NT are represented by the Central Land Council (CLC). The CLC is one of four land councils in the NT. The Project is in the Eastern Plenty sub-region of the CLC. In August 2016, formalisation of cooperation with the CLC was achieved and documented in an Indigenous Land Use Agreement (ILUA).
The ILUA is between Jinka Minerals Ltd, Kentor Minerals (NT) Pty Ltd (KGL’s operating company; which was later revised to Jervois Operations Pty Ltd) and the CLC. The ILUA has been registered with the National Native Title Tribunal since May 2017.
13. Jervois Project Mine Plan
As outlined previously, for the Reserve Case, areas (lower levels) of the underground mines consisting of only or mostly (>90%) Inferred material were excluded from the 2024 FSU full LOM Plan along with the stopes at the extremities on the upper levels that contained a high proportion of Inferred material.
The exclusion of these areas did not compromise the operability of the Reserve Case designs.
Inferred material is included in the 2024 FSU Reserve Case mine designs and schedule. The included Inferred material has been assigned zero grade and contributes no metal.
Inferred material is expected to be converted to Proven or Probable Ore Reserves as ongoing definition drilling is completed.
KGL Resources Limited 2024 Ore Reserve Statement
xenith.com.au
100
==> picture [195 x 147] intentionally omitted <==
14. Project Economics
The physicals and project economics are related to the full feasibility mine designs and schedules (as described in the feasibility study update).
A summary of the 2024 FSU project physicals are included below in Table 49.
Table 49 – 2024 FSU Jervois Project Physicals Summary
| Physicals Summary | Units | Value | ||
|---|---|---|---|---|
| Mining Physicals | ||||
| Ore Tonnage | Mt | 16.6 | ||
| Grade Copper | % Cu | 1.77 | ||
| Grade Gold | g/t Au | 0.26 | ||
| Grade Silver | g/t Ag | 27.17 | ||
| Run-of-Mine Ore | Mtpa | 1.5 - 2.0 | ||
| Life of Mine (“LOM”) | Years | 10.4 | ||
| Contained Metal | ||||
| Copper Metal | kt | 294 | ||
| Gold Metal | koz | 139 | ||
| Silver Metal | Moz | 14.5 | ||
| Metallurgical Recoveries | Cu | Au | Ag | |
| Oxide Ore | % | 64.6% | 43.2% | 53.6% |
| Fresh Ore | % | 92.0% | 55.3% | 66.0% |
| Copper in Concentrate | ||||
| Total | Kt | 265.5 | ||
| Average Annual | Ktpa | 25.5 |
Operating costs have been based on contractor pricing developed for the 2024 FSU open pit and underground mines.
Treatment costs and refining charges have been applied in the financial model as per the agreement with Glencore International AG.
A summary of the 2024 FSU project costs is included below in Table 50.
KGL Resources Limited 2024 Ore Reserve Statement
xenith.com.au
101
==> picture [195 x 147] intentionally omitted <==
Table 50 – 2024 FSU Jervois Project Costs Summary
| Cost Summary | Units | Value |
|---|---|---|
| Operating | ||
| Mining – Open Pit | $/t ore | 52.02 |
| Mining – Underground | $/t ore | 123.01 |
| Mining – Combined | $/t ore | 93.60 |
| Processing | $/t ore | 29.83 |
| Other | $/t ore | 17.03 |
| Total Operating Cost | $/t ore | 140.55 |
| Capital | ||
| Upfront Capital Costs | $M | 362 |
KGL Resources Limited modelled the Project economics using a bespoke financial model. The key assumption for, and outcomes from the financial model are listed below in Table 51.
Table 51 – 2024 FSU Jervois Project Economics Summary
| Project Economics | Units | Value |
|---|---|---|
| Key Assumptions | ||
| Copper Price | US$/lb | 4.58 |
| Gold Price | US$/Oz | 2,668 |
| Silver Price | US$/Oz | 32.62 |
| Exchange Rate | A$:US$ | 0.64 |
| Discount Rate | % | 8 |
| Financials* | ||
| Operating Cost (C1) | US$/lb | 2.19 |
| Net cash flow (undiscounted, post-tax) | $M | 873 |
| NPV8% (post-tax) | $M | 405 |
| IRR (post-tax) | % | 24.3 |
*Financials taken from the KGL 2024 FSU financial model using US$4.58/lb Cu, US$2,668/oz Au and US$32.62/oz Ag.
KGL Resources Limited 2024 Ore Reserve Statement
xenith.com.au
102
==> picture [195 x 147] intentionally omitted <==
The Life of Mine schedule and financial model has projected net cashflows of $873M and a post-tax NPV of $405M using an 8% discount rate. Cumulative cashflows and post-tax NPV, and free cashflow by project year are shown below in Figure 50 and Figure 51, respectively.
Figure 50 – Cumulative Ungeared Cashflows and Post Tax NPV
==> picture [484 x 259] intentionally omitted <==
Figure 51 – Free Cashflow Present Value 8%
==> picture [478 x 230] intentionally omitted <==
KGL Resources Limited 2024 Ore Reserve Statement
xenith.com.au
103
==> picture [195 x 147] intentionally omitted <==
A range of project sensitivities are provided. The impact to the Project NPV and IRR of a 20% increase/decrease in several parameters (Commodity Prices, Exchange Rate, Opex and Capex) are shown below in Figure 52 and Figure 53, respectively.
Figure 52 – Sensitivity Chart (+/-20%) Relative to NPV
==> picture [437 x 201] intentionally omitted <==
Figure 53 – Sensitivity Chart (+/-20%) Relative to IRR
==> picture [443 x 205] intentionally omitted <==
Exchange rate has the biggest potential to impact on project value and is beyond the control of the Project team. As copper metal in concentrate is the biggest single revenue for the Project it is logical to expect that the Project value would be sensitive to the copper price.
The three major sensitivities are:
-
› Exchange Rate;
-
› Copper Price; and
-
› Total Opex.
KGL Resources Limited 2024 Ore Reserve Statement
xenith.com.au
104
==> picture [195 x 147] intentionally omitted <==
The major sensitivities (exchange rate and copper price) are shown for a greater range of sensitivities below in Figure 54.
Figure 54 – NPV Sensitivity to Metal Prices and Exchange Rates
==> picture [489 x 244] intentionally omitted <==
KGL Resources Limited 2024 Ore Reserve Statement
xenith.com.au
105
15. Mineral Resources & Ore Reserves
==> picture [195 x 147] intentionally omitted <==
The Revised May 2024 Jervois Mineral Resources for the Project are inclusive of Ore Reserves. Mineral Resources include Measured, Indicated and Inferred material. Indicated material includes unclassified dilution.
For the October 2024 stated Reserves, portions (lower levels) of the Jervois 2024 FSU underground mine designs that include only Inferred or high concentration of Inferred (>90%) material have been excluded for the Reserve Case Mine Plan. This is also the case for stopes at the extremities on the upper levels that contained a high proportion of Inferred material.
The Open Pit designs remain unchanged between the 2024 FSU LOM plan and Reserve Case. Where Inferred material remains within the Open Pit and Underground mine designs (partial stope inclusion etc.), it has been assigned zero grade and contributes no metal. The Probable Ore Reserves include unclassified dilution.
15.1 Jervois Mineral Resources and Ore Reserves
15.1.1 Mineral Resources Summary (Revised May 2024)
The Revised May 2024 Jervois Mineral Resources estimate is summarised in Table 52 below.
Table 52 – Revised May 2024 Jervois Mineral Resource Summary
| Resource | Material | Material | Grade | Metal | ||||
|---|---|---|---|---|---|---|---|---|
| Mine | Category | Ag | Au | Ag | Au | |||
| Mt | Cu (%) | Cu (kt) | ||||||
| (g/t) | (g/t) | (Moz) | (koz) | |||||
| Measured | 2.67 | 1.89 | 46.4 | 0.42 | 50.4 | 3.98 | 36.2 | |
| Reward OP | Indicated | 4.01 | 1.31 | 44.4 | 0.23 | 52.6 | 5.73 | 30.2 |
| Inferred | 0.05 | 1.08 | 15.4 | 0.14 | 0.6 | 0.03 | 0.2 | |
| Measured | 1.73 | 1.91 | 11.7 | 0.11 | 33.1 | 0.65 | 6.1 | |
| Bellbird OP | Indicated | 1.38 | 1.43 | 9.0 | 0.14 | 19.7 | 0.40 | 6.2 |
| Inferred | 0.27 | 1.00 | 7.2 | 0.09 | 2.7 | 0.06 | 0.8 | |
| Subtotal | 10.12 | 1.57 | 33.4 | 0.25 | 159.1 | 10.85 | 79.7 | |
| Indicated | 4.54 | 1.85 | 29.1 | 0.40 | 83.8 | 4.25 | 58.4 | |
| Reward UG | ||||||||
| Inferred | 6.13 | 1.25 | 19.6 | 0.17 | 76.9 | 3.86 | 33.1 | |
| Indicated | 0.40 | 1.76 | 15.4 | 0.20 | 7.0 | 0.20 | 2.5 | |
| Bellbird UG | ||||||||
| Inferred | 3.98 | 1.82 | 12.1 | 0.11 | 72.4 | 1.55 | 13.6 | |
| Indicated | 2.91 | 3.27 | 20.9 | 0.23 | 95.2 | 1.96 | 21.3 | |
| Rockface UG | ||||||||
| Inferred | 0.88 | 1.73 | 16.3 | 0.16 | 15.3 | 0.46 | 4.5 | |
| Subtotal | 18.84 | 1.86 | 20.3 | 0.22 | 350.7 | 12.28 | 133.4 | |
| Total Resources | 28.95 | 1.76 | 24.8 | 0.23 | 509.8 | 23.13 | 213.1 |
KGL Resources Limited 2024 Ore Reserve Statement
xenith.com.au
106
15.1.2 Ore Reserves Summary (October 2024)
==> picture [195 x 147] intentionally omitted <==
The total Proven and Probable Ore Reserves are shown below in Table 53.
Table 53 – Jervois Project Total Ore Reserves
| Material | Material | Grade | Grade | Metal | ||||
|---|---|---|---|---|---|---|---|---|
| CuEq | Cu | Ag | Au | Cu | Ag | Au | ||
| Source | Mt | |||||||
| (%) | (%) | (g/t) | (g/t) | (kt) | (Moz) | (koz) | ||
| Proven | 4.19 | 2.15 | 1.79 | 31.03 | 0.29 | 74.9 | 4.2 | 39 |
| Probable | 10.19 | 2.05 | 1.76 | 26.27 | 0.25 | 179 | 8.6 | 83.4 |
| Total Reserves | 14.38 | 2.08 | 1.77 | 27.66 | 0.26 | 254 | 12.8 | 122.4 |
The Proven Ore Reserves by Source are shown below in Table 54.
Table 54 – Jervois Proven Ore Reserves by Mine
| Material | Material | Grade | Grade | Metal | ||||
|---|---|---|---|---|---|---|---|---|
| CuEq | Cu | Ag | Au | Cu | Ag | Au | ||
| Source | Mt | |||||||
| (%) | (%) | (g/t) | (g/t) | (kt) | (Moz) | (koz) | ||
| Open Pit | ||||||||
| Reward OP | 2.68 | 2.19 | 1.71 | 41.96 | 0.39 | 45.7 | 3.6 | 33.6 |
| Bellbird OP | 1.51 | 2.07 | 1.94 | 11.59 | 0.11 | 29.2 | 0.6 | 5.3 |
| Sub-total | 4.19 | 2.15 | 1.79 | 31.03 | 0.29 | 74.9 | 4.2 | 39 |
| Underground | ||||||||
| Rockface UG | - | - | - | - | - | - | - | - |
| Bellbird UG | - | - | - | - | - | - | - | - |
| Reward UG | - | - | - | - | - | - | - | - |
| Marshall UG | - | - | - | - | - | - | - | - |
| Sub-total | - | - | - | - | - | - | - | - |
| Total Proven | 4.19 | 2.15 | 1.79 | 31.03 | 0.29 | 74.9 | 4.2 | 39 |
KGL Resources Limited 2024 Ore Reserve Statement
xenith.com.au
107
The Probable Ore Reserves by Source are shown below in Table 55.
==> picture [195 x 147] intentionally omitted <==
Table 55 – Jervois Probable Ore Reserves by Mine
| Material | Material | Grade | Grade | Metal | ||||
|---|---|---|---|---|---|---|---|---|
| CuEq | Cu | Ag | Au | Cu | Ag | Au | ||
| Source | Mt | |||||||
| (%) | (%) | (g/t) | (g/t) | (kt) | (Moz) | (koz) | ||
| Open Pit | ||||||||
| Reward OP | 2.20 | 1.54 | 1.19 | 36.3 | 0.22 | 26.1 | 2.6 | 15.6 |
| Bellbird OP | 0.48 | 1.10 | 1.04 | 5.55 | 0.06 | 5 | 0.1 | 0.9 |
| Sub-total | 2.68 | 1.46 | 1.16 | 30.77 | 0.19 | 31.1 | 2.7 | 16.5 |
| Underground | ||||||||
| Rockface UG | 2.96 | 2.74 | 2.55 | 16.58 | 0.18 | 75.4 | 1.6 | 17 |
| Bellbird UG | 0.37 | 1.77 | 1.65 | 13.23 | 0.08 | 6 | 0.2 | 1 |
| Reward UG | 2.48 | 2.28 | 1.88 | 25.77 | 0.49 | 46.7 | 2.1 | 38.8 |
| Marshall UG | 1.71 | 1.51 | 1.16 | 39.52 | 0.19 | 19.8 | 2.2 | 10.2 |
| Sub-total | 7.51 | 2.26 | 1.97 | 24.66 | 0.28 | 147.9 | 6.0 | 67.0 |
| Total Probable | 10.19 | 2.05 | 1.76 | 26.27 | 0.25 | 179 | 8.6 | 83.4 |
KGL Resources Limited 2024 Ore Reserve Statement
xenith.com.au
108
==> picture [195 x 147] intentionally omitted <==
15.2 Open Pit Mineral Resources and Ore Reserves
15.2.1 Reward Open Pit
The Reward Open Pit Resource is a significant part of the mineralisation identified at the Project. The October 2024 Reward Open Pit Ore Reserves are shown below in Table 56.
Table 56 – 2024 Reward Open Pit Ore Reserves
| Material | Material | Grade | Grade | Metal | ||||
|---|---|---|---|---|---|---|---|---|
| CuEq | Cu | Ag | Au | Cu | Ag | Au | ||
| Category | Mt | |||||||
| (%) | (%) | (g/t) | (g/t) | (kt) | (Moz) | (koz) | ||
| Proven | 2.68 | 2.19 | 1.71 | 41.96 | 0.39 | 45.7 | 3.6 | 33.6 |
| Probable | 2.20 | 1.54 | 1.19 | 36.3 | 0.22 | 26.1 | 2.6 | 15.6 |
| Total Reserve | 4.88 | 1.90 | 1.47 | 39.41 | 0.31 | 71.8 | 6.2 | 49.2 |
15.2.2 Bellbird Open Pit
The October 2024 Bellbird Open Pit Ore Reserve is shown below in Table 57.
Table 57 – Bellbird Open Pit Ore Reserves
| Material | Material | Grade | Grade | Metal | ||||
|---|---|---|---|---|---|---|---|---|
| CuEq | Cu | Ag | Au | Cu | Ag | Au | ||
| Category | Mt | |||||||
| (%) | (%) | (g/t) | (g/t) | (kt) | (Moz) | (koz) | ||
| Proven | 1.51 | 2.07 | 1.94 | 11.59 | 0.11 | 29.2 | 0.6 | 5.3 |
| Probable | 0.48 | 1.10 | 1.04 | 5.55 | 0.06 | 5 | 0.1 | 0.9 |
| Total Reserve | 1.99 | 1.84 | 1.72 | 10.13 | 0.1 | 34.2 | 0.6 | 6.2 |
KGL Resources Limited 2024 Ore Reserve Statement
xenith.com.au
109
==> picture [195 x 147] intentionally omitted <==
15.3 Underground Mineral Resources and Ore Reserves
15.3.1 Rockface Underground
The October 2024 Rockface Underground Ore Reserve is shown below in Table 58.
Table 58 – Rockface Underground Ore Reserves
| Material | Material | Grade | Grade | Metal | ||||
|---|---|---|---|---|---|---|---|---|
| CuEq | Cu | Ag | Au | Cu | Ag | Au | ||
| Category | Mt | |||||||
| (%) | (%) | (g/t) | (g/t) | (kt) | (Moz) | (koz) | ||
| Proven | - | - | - | - | - | - | - | - |
| Probable | 2.96 | 2.74 | 2.55 | 16.58 | 0.18 | 75.4 | 1.6 | 17.0 |
| Total Reserve | 2.96 | 2.74 | 2.55 | 16.58 | 0.18 | 75.4 | 1.6 | 17.0 |
15.3.2 Bellbird Underground
As much of the Bellbird deposit at depth consists of Inferred material, a significant portion of the 2024 FSU design has been excluded for the October 2024 Reserve Case. Hence, there is a significant reduction in tonnage between the 2024 FSU case and the Reverse Case for the Bellbird Underground Mine.
Less than 10 kt of Measured Resources has been included in the Bellbird Underground Probable Ore Reserve. The October 2024 Bellbird Underground Ore Reserves are shown below in Table 59.
Table 59 – Bellbird Underground Ore Reserves
| Material | Material | Grade | Grade | Metal | ||||
|---|---|---|---|---|---|---|---|---|
| CuEq | Cu | Ag | Au | Cu | Ag | Au | ||
| Category | Mt | |||||||
| (%) | (%) | (g/t) | (g/t) | (kt) | (Moz) | (koz) | ||
| Proven | - | - | - | - | - | - | - | - |
| Probable | 0.37 | 1.77 | 1.65 | 13.23 | 0.08 | 6.0 | 0.2 | 1.0 |
| Total Reserve | 0.37 | 1.77 | 1.65 | 13.23 | 0.08 | 6.0 | 0.2 | 1.0 |
15.3.3 Reward Underground
The October 2024 Bellbird Underground Ore Reserve is shown below in Table 60.
KGL Resources Limited 2024 Ore Reserve Statement
xenith.com.au
110
==> picture [195 x 147] intentionally omitted <==
Table 60 – Reward Underground Ore Reserves
| Material | Material | Grade | Grade | Metal | ||||
|---|---|---|---|---|---|---|---|---|
| CuEq | Cu | Ag | Au | Cu | Ag | Au | ||
| Category | Mt | |||||||
| (%) | (%) | (g/t) | (g/t) | (kt) | (Moz) | (koz) | ||
| Proven | - | - | - | - | - | - | - | - |
| Probable | 2.48 | 2.28 | 1.88 | 25.77 | 0.49 | 46.7 | 2.1 | 38.8 |
| Total Reserve | 2.48 | 2.28 | 1.88 | 25.77 | 0.49 | 46.7 | 2.1 | 38.8 |
15.3.4 Marshall Underground
The Marshall Underground mine is situated beneath the Reward Open Pit and is designed to extract a portion of the Reward Mineral Resource; strictly, there is no Marshall Mineral Resource as it is part of the Reward Mineral Resource as defined by the May 2024 Jervois Mineral Resources statement issued by Iain Taylor of Mining Associates (Section 7 of this report). To maintain consistency to previous studies and for the purposes of stating the October 2024 Jervois Ore Reserves, the portion of the Reward Mineral Resource designed to be extracted by the Marshall Underground design will be titled the Marshall Resources and Reserves.
For the Marshall Underground mine the 2024 FSU design and Reserve case use the same mine design and schedule. The Marshall design contains significant Indicated tonnage on all levels.
The Marshall Underground Probable Ore Reserve contains 0.02 Mt of Measured Resource. The October 2024 Marshall Underground Ore Reserves are shown below in Table 61.
Table 61 – Marshall Underground Ore Reserves
| Material | Material | Grade | Grade | Metal | ||||
|---|---|---|---|---|---|---|---|---|
| CuEq | Cu | Ag | Au | Cu | Ag | Au | ||
| Category | Mt | |||||||
| (%) | (%) | (g/t) | (g/t) | (kt) | (Moz) | (koz) | ||
| Proven | - | - | - | - | - | - | - | - |
| Probable | 1.71 | 1.51 | 1.16 | 39.52 | 0.19 | 19.8 | 2.2 | 10.2 |
| Total Reserve | 1.71 | 1.51 | 1.16 | 39.52 | 0.19 | 19.8 | 2.2 | 10.2 |
15.4 Financial Test of Reserve
To determine the economic viability of the stated October 2024 Jervois Ore Reserves, a financial test of the Reserve Case design and schedule was completed. The total of costs associated with the stated Ore Reserve with inferred tonnes included was examined against the expected revenue from only the measured and indicated tonnages for all proposed open pit and underground mines. The KGL Reserve Case returned a positive NPV.
An additional set of Reserves test cases, on a mine by mine basis, was completed for all the current designs above Level 20 in the underground mines. The operating unit costs, for mining, milling and “other”, were applied to all tonnage (including inferred) and compared to the value of the contained metal in the stope designs. The value was adjusted downwards to reflect recoveries and payable metal limits. In all cases, the value exceeded the costs, although Bellbird was marginal. The combined underground mines produced sufficient operating cash to more than offset all mining capital by over $500M.
KGL Resources Limited 2024 Ore Reserve Statement
xenith.com.au
111
16. Conclusions
==> picture [195 x 147] intentionally omitted <==
The 2024 Feasibility Study Update (FSU) Life of Mine Plan is based on the Revised May 2024 stated Mineral Resources for the Project. Analysis indicates that the 2024 FSU Life of Mine Plan is technically and economically feasible. Financial analysis is based on an all contractor mining model.
The Life of Mine Plan forms the basis of the Reserve Case Mine Plan used for the declaration of the October 2024 Ore Reserves. Both the 2024 FSU Life of Mine Plan and the Reserve Case Mine Plan provide a positive return.
The 2024 FSU Reserve Case mine design and schedule converts approximately 50% of the copper metal reported in the Revised May 2024 Mineral Resources to Proven and Probable Ore Reserves. The October 2024 stated Ore Reserves total 14.38 Mt @ 1.77% Cu and is suitable to support the proposed open pit and underground mining operation.
Inferred material remaining in the Life of Mine Plan and the Reserve Case Mine Plan is expected to be converted to Reserve prior to extraction.
KGL Resources Limited 2024 Ore Reserve Statement
xenith.com.au
112
==> picture [596 x 483] intentionally omitted <==
Appendix A 0B JORC Table 1 Jervois Mineral Resource and Reserves Estimate
KGL Resources Limited 2024 Ore Reserve Statement
xenith.com.au
113
For the 2024 KGL Jervois Resources and Reserves:
==> picture [195 x 147] intentionally omitted <==
-
› JORC Table 1 Sections 1, 2 and 3 have been reproduced from the Mineral Resource Estimate, Reward, Bellbird and Rockface Deposits – Jervois Project, Northern Territory, Australia completed by Mr Ian Taylor Mining Associates Pty Ltd dated 23[rd] May 2024.
-
› JORC Table 1 Section 4 has been compiled by Mr Iain Ross of Xenith.
Table A.1 – Section 1 Sampling Techniques and Data: Jervois Project
| Criteria | JORC Code explanation | Section 1: Commentary |
|---|---|---|
| Sampling | Nature and quality of sampling | › At the Jervois Project, diamond drilling and reverse |
techniques |
(e.g. cut channels, random |
circulation (RC) drilling were used to obtain |
| chips, or specific specialised | samples for geological logging and assaying. The | |
industry standard |
core samples comprised a mixture of sawn HQ |
|
measurement tools |
quarter core, sawn NQ half core and possibly BQ |
|
| appropriate to the minerals | half core (historical drilling only). Sample lengths |
|
under investigation, such as |
are generally 1 m, with adjustments made were |
|
down hole gamma sondes, or |
necessary to consider geological variations. RC |
|
handheld XRF instruments, |
sample intervals are predominantly 1 m, with some |
|
| etc). These examples should | 2 m and 4 m compositing (historical holes only). |
|
| not be taken as limiting the | › RC samples are routinely scanned by KGL |
|
| broad meaning of sampling. | Resources with a Niton XRF. Samples assaying |
|
| Include reference to measures | greater than 0.1% Cu, Pb or Zn are submitted for | |
| taken to ensure sample | chemical analysis at a commercial laboratory. |
|
| representivity and the | › Documentation of the historical drilling (pre-2011) |
|
| appropriate calibration of any | for Jervois Project is variable. |
|
measurement tools or |
||
| systems used. | ||
| Aspects of the determination of | ||
mineralisation that are |
||
| Material to the Public Report. | ||
| In cases where ‘industry | ||
standard’ work has been done |
||
| this would be relatively simple | ||
(e.g. ‘reverse circulation |
||
drilling was used to obtain 1 |
||
m samples from which 3 kg |
||
was pulverised to produce a |
||
30 g charge for fire assay’). |
||
In other cases more |
||
| explanation may be required, | ||
such as where there is coarse |
||
| gold that has inherent | ||
sampling problems. Unusual |
||
commodities or mineralisation |
||
| types (e.g. submarine | ||
nodules) may warrant |
||
disclosure of detailed |
||
| information. | ||
| Drilling techniques | Drill type (e.g. core, reverse | › The KGL and previous Jinka Minerals RC drilling |
| circulation, open-hole | was conducted using a reverse circulation rig with a | |
hammer, rotary air blast, |
5.25-inch face-sampling bit. Diamond drilling was |
|
auger, Bangka, sonic, etc) |
either in NQ2 or HQ3 drill diameters. Metallurgical |
|
and details (e.g. core |
diamond drilling (JMET holes) were PQ core. |
|
| diameter, triple or standard | ||
tube, depth of diamond tails, |
KGL Resources Limited 2024 Ore Reserve Statement
xenith.com.au
114
==> picture [195 x 147] intentionally omitted <==
| Criteria | JORC Code explanation | Section 1: Commentary |
|---|---|---|
| face-sampling bit or other | › There is no documentation for the historic drilling |
|
type, whether core is oriented |
techniques, drill type is recorded as UNK. |
|
| and if so, by what method, | › Diamond drilling was generally cored from surface |
|
| etc). | with some of the deeper holes at Rockface utilising |
|
| RC pre-collars. | ||
| › Oriented core has been measured for the recent |
||
| 2020-2021 KGL drill program. | ||
| Drill sample | Method of recording and | › The KGL RC samples were not weighed on a |
recovery |
assessing core and chip |
regular basis. KGL report no sample recovery issues |
| sample recoveries and results | were encountered during the drilling program. | |
| assessed. | › Jinka Minerals and KGL split the rare overweight |
|
| Measures taken to maximise | samples (>3kg) for assay. Since overweight | |
| sample recovery and ensure | samples were rarely reported no sample bias was |
|
representative nature of the |
established between sample recovery and grade. |
|
| samples. | › Drilling muds are used to improve drilling recovery, |
|
| Whether a relationship exists | and in broken ground triple tube barrels are | |
between sample recovery and |
employed. Core recovery for recent drilling is >95% |
|
grade and whether sample |
with the mineral zones having virtually 100% |
|
bias may have occurred due |
recovery. |
|
| to preferential loss/gain of | › No evidence has been found for any relationship |
|
| fine/coarse material. | between sample recovery and copper grade and |
|
| there are no biases in the sampling with respect to | ||
copper grade and recovery. |
||
| Logging | Whether core and chip samples | › All KGL RC and diamond core samples are |
| have been geologically and | geologically logged. Logging in conjunction with | |
geotechnically logged to a |
multi-element assays is appropriate for Mineral |
|
level of detail to support |
Resource estimation. |
|
| appropriate Mineral Resource | › Core samples are orientated and logged for |
|
| estimation, mining studies | geotechnical information suitable for mining |
|
| and metallurgical studies. | studies. |
|
| Whether logging is qualitative or | › All logging has been converted to quantitative and |
|
| quantitative in nature. Core | qualitative codes in the KGL Access database. |
|
(or costean, channel, etc) |
||
| › All relevant intersections are logged. |
||
photography. |
||
| › Paper logs existed for the historical drilling. There is |
||
| The total length and percentage | ||
very little historical core available for inspection. |
||
of the relevant intersections |
||
| logged. | ||
| Sub-sampling | If core, whether cut or sawn and | › The following describes the recent KGL sampling |
techniques and |
whether quarter, half or all | and assaying process: |
| sample | core taken. | › RC drill holes are sampled at 1 m intervals and split |
| preparation | If non-core, whether riffled, tube | using a cone splitter attached to the cyclone to |
| sampled, rotary split, etc and | generate a split of ~3 kg. |
|
| whether sampled wet or dry. | › RC sample splits (~3 kg) are pulverised to 85% |
|
| For all sample types, the nature, | passing 75 microns. |
|
| quality and appropriateness | › Diamond core was quartered with a diamond saw |
|
| of the sample preparation | and generally sampled at 1 m intervals, with |
|
| technique. | sample lengths adjusted at geological contacts. |
|
| Quality control procedures | › Diamond core samples are crushed to 70% passing |
|
| adopted for all sub-sampling | 2 mm and then pulverised to 85% passing 75 |
|
| stages to maximise | microns. |
|
representivity of samples. |
||
KGL Resources Limited 2024 Ore Reserve Statement
xenith.com.au
115
==> picture [195 x 147] intentionally omitted <==
| Criteria | JORC Code explanation | Section 1: Commentary |
|---|---|---|
| Measures taken to ensure that | › Two quarter core field duplicates were taken for |
|
| the sampling is representative | every 20 m of sampling by Jinka Minerals and KGL |
|
of the in-situ material |
Resources. |
|
| collected, including for | › All sampling methods and sample sizes are deemed |
|
| instance results for field | appropriate for Mineral Resource estimation. |
|
| duplicate/second-half | ||
| › Details for the historical sampling are not available. |
||
sampling. |
||
| Whether sample sizes are | ||
appropriate to the grain size |
||
of the material being |
||
sampled. |
||
| Quality of assay | The nature, quality and | › The KGL drilling has QAQC data that includes |
data and |
appropriateness of the |
standards, duplicates and laboratory checks. |
| laboratory tests | assaying and laboratory |
Within mineralisation, standards are added at a |
| procedures used and whether | ratio of 1:10 and duplicates and blanks 1:20. | |
| the technique is considered | › Base metal samples are assayed using a four-acid |
|
| partial or total. | digest with an ICP AES finish. Gold samples are |
|
| For geophysical tools, | assayed by Aqua Regia with an ICP MS finish. | |
spectrometers, handheld XRF |
Samples over 1 ppm Au are re-assayed by Fire |
|
instruments, etc, the |
Assay with an AAS finish. |
|
| parameters used in | › Fluorine is determined with carbonate infusion |
|
determining the analysis |
||
| › There are no details of the historic drill sample |
||
including instrument make |
||
assaying or any QAQC. |
||
and model, reading times, |
||
calibrations factors applied |
› All assay methods were deemed appropriate at the |
|
and their derivation, etc. |
time of undertaking. | |
| Nature of quality control | ||
procedures adopted (e.g. |
||
standards, blanks, duplicates, |
||
external laboratory checks) |
||
and whether acceptable levels |
||
of accuracy (i.e. lack of bias) |
||
and precision have been |
||
established. |
||
| Verification of | The verification of significant | › Data is validated on entry into the MS Access |
| sampling and | intersections by either |
database, using database check queries within |
assaying |
independent or alternative |
Maxwell’s DataShed. |
| company personnel. | › Further validation is conducted when data is |
|
| The use of twinned holes. | imported into Micromine and Leapfrog Geo | |
| Documentation of primary data, | software. | |
| data entry procedures, data | › Hole twinning was occasionally conducted at |
|
verification, data storage |
Reward and Bellbird with mixed results. This may |
|
(physical and electronic) |
be due to inaccuracies with historic hole locations |
|
protocols. |
rather than mineral continuity issues. | |
| Discuss any adjustment to assay | › No twin holes have been drilled at Rockface. |
|
| data. | › For the Resource estimation, below detection |
|
| values were converted to half the lower detection | ||
| limit. | ||
| Location of data | Accuracy and quality of surveys | › Surface collar surveys for the KGL drilling were |
| points | used to locate drill holes |
picked up using a Trimble DGPS, with accuracy to |
| (collar and down-hole | 1 cm or better. | |
| surveys), trenches, mine |
KGL Resources Limited 2024 Ore Reserve Statement
xenith.com.au
116
==> picture [195 x 147] intentionally omitted <==
| Criteria | JORC Code explanation | Section 1: Commentary |
|---|---|---|
| workings and other locations | › Historical holes commonly only have a collar and |
|
used in Mineral Resource |
identical end of hole survey record. Recent (post |
|
| estimation. | 2011) downhole surveys were taken during drilling |
|
| Specification of the grid system | with an Eastman style tool at 30 m intervals. | |
used. |
Recent (post 2018) drilling uses a Ranger or Reflex | |
survey tool at intervals of between 5 and 15 m |
||
| Quality and adequacy of | ||
downhole. |
||
topographic control. |
||
| › All drilling by Jinka Minerals and KGL is referenced |
||
on the GDA 94, MGA Zone 53. All downhole |
||
| magnetic surveys were converted to MGA azimuth. | ||
| › There are concerns about the accuracy of some of |
||
the historic drill hole collars at the Jervois Project, |
||
but there are virtually no Reserved historic collars |
||
for checking. Several spurious holes from each |
||
deposit were excluded. Historic holes with complete |
||
assay data and logging, and confirmed by newer |
||
drilling, were used in the Resource estimate. |
||
| › There is no documentation for the downhole survey |
||
method for the historic drilling. |
||
| › Topography was mapped using Trimble DGPS and |
||
merged with the LIDAR. |
||
| Data spacing and | Data spacing for reporting of | › Drilling at Reward and Bellbird was on 25 m spaced |
distribution |
Exploration Results. |
sections in the upper part of the mineralisation |
| Whether the data spacing and | extending to 50 m centres with depth and | |
distribution is sufficient to |
ultimately reaching 100 m spacing on the periphery | |
| establish the degree of | of mineralisation. Several sections are drilled with | |
geological and grade |
tight (~10-15m) spaced shallow drillholes | |
| continuity appropriate for the | › Drilling at Rockface was on 50 m spaced sections |
|
Mineral Resource and Ore |
(50 m x 50 m grid), with significant areas infilled to |
|
| Reserve estimation | 25 m centres by drilling on intermediate sections or |
|
| procedure(s) and | with child holes. |
|
| classifications applied. | › The drill spacing for all areas is appropriate for |
|
| Whether sample compositing has | Resource estimation and the relevant classifications | |
been applied. |
applied. | |
| › A small amount of sample compositing has been |
||
applied to some of the near surface historic drilling. |
||
| Orientation of data | Whether the orientation of | › Reward and Rockface Holes were drilled |
| in relation to | sampling achieves unbiased | perpendicular to the strike of the mineralization; |
| geological | sampling of possible |
the default angle is -60 degrees, but holes vary |
structure |
structures and the extent to |
from -45 to -80. |
| which this is known, | › Rockface Holes were drilled perpendicular to the |
|
| considering the deposit type. | strike of the mineralisation; the default angle is - |
|
| If the relationship between the | 60°, but holes vary from -20° to -90° (navi holes). |
|
| drilling orientation and the | › A small amount of sample compositing has been |
|
| orientation of key mineralised | undertaken on some of the near surface historic |
|
| structures is considered to | drilling, this data was excluded from the Resource | |
| have introduced a sampling | estimate. |
|
bias, this should be assessed |
||
| › Drilling orientations are considered appropriate, and |
||
| and reported if material. | ||
no obvious sampling bias was detected. |
||
KGL Resources Limited 2024 Ore Reserve Statement
xenith.com.au
117
==> picture [195 x 147] intentionally omitted <==
| Criteria | JORC Code explanation | Section 1: Commentary |
|---|---|---|
| Sample security | The measures taken to ensure | › Samples were stored in sealed polyweave bags on |
| sample security. | site and transported to the laboratory at regular | |
| intervals by KGL staff or a transport contractor. | ||
| Audits or reviews | The results of any audits or | › The sampling techniques are regularly reviewed |
| reviews of sampling | internally and by external consultants. | |
| techniques and data. |
Table A.2 – Section 2 Reporting of Exploration Results: Jervois Project
| Criteria | JORC Code explanation | Section 2 Commentary |
|---|---|---|
| Mineral tenement | Type, reference name/number, | › The Jervois Project is within EL25429 and EL28082, |
| and land tenure | location and ownership |
100% owned by Jinka Minerals and operated by |
| status | including agreements or |
Jervois Operations Pty Ltd, both wholly owned |
| material issues with third | subsidiaries of KGL Resources Limited. | |
| parties such as joint ventures, | › Excised from the Exploration Licences are four |
|
| partnerships, overriding | Mining claims (ML 30180, ML 30182, ML 30829 & |
|
| royalties, native title interests, | ML 32277) owned by Jinka Minerals. Rockface lies |
|
| historical sites, wilderness or | within ML30182. |
|
| national park and | ||
| › The tenements are all in good standing. |
||
environmental settings. |
||
| › An Indigenous Land Use Agreement (ILUA) was |
||
| The security of the tenure held at | ||
registered in 2017. |
||
the time of reporting along with |
||
any known impediments to |
› Royalties will be payable as per the NT Minerals |
|
obtaining a licence to operate in |
Royalty Act (1982) on production of saleable | |
the area. |
mineral commodities. | |
| Exploration done | Acknowledgment and appraisal of | › Previous exploration has primarily been conducted |
by other parties |
exploration by other parties. |
by Reward Minerals, MIM and Plenty River. |
| › This report references a Mineral Resource Estimate, |
||
and this item is not applicable. |
||
| Geology | Deposit type, geological setting and | › EL25429 and EL28082 lie on the Huckitta 1: 250 |
| style of mineralisation. | 000 map sheet (SF 53-11). The tenement is located | |
| mainly within the Palaeo-Proterozoic Bonya Schist | ||
on the north-eastern boundary of the Arunta |
||
| Orogenic Domain. The Arunta Orogenic Domain in | ||
the north western part of the tenement is overlain |
||
unconformably by Neo-Proterozoic sediments of the |
||
Georgina Basin. |
||
| › The stratabound mineralisation for the Project |
||
consists of a series of complex, narrow, structurally |
||
controlled, sub-vertical sulphide/magnetite-rich |
||
deposits hosted by Proterozoic-aged, amphibolite |
||
grade metamorphosed sediments of the Arunta |
||
Inlier. |
||
| › Mineralisation is characterised by veinlets and |
||
disseminations of chalcopyrite in association with |
||
magnetite. In the oxide zone, which is vertically |
||
limited, malachite, azurite and chalcocite are the |
||
| main Cu-minerals. |
KGL Resources Limited 2024 Ore Reserve Statement
xenith.com.au
118
==> picture [195 x 147] intentionally omitted <==
| Criteria | JORC Code explanation | Section 2 Commentary |
|---|---|---|
| Drill hole | A summary of all information | › This report references a Mineral Resource Estimate, |
| Information | material to the understanding |
and this item is not applicable. |
| of the exploration results | › All drill holes are stored in the drill hole database, |
|
| including a tabulation of the | detailing drill hole collar location including elevation |
|
| following information for all | or RL (Reduced Level – elevation above sea level in |
|
| Material drill holes: | metres), dip and azimuth of the hole at consistent |
|
| easting and northing of the drill | points down hole, and hole length. |
|
hole collar |
||
| elevation or RL (Reduced Level – | ||
elevation above sea level in |
||
| metres) of the drill hole collar | ||
| dip and azimuth of the hole | ||
| down hole length and interception | ||
depth |
||
| hole length. | ||
| If the exclusion of this information | ||
| is justified on the basis that the | ||
information is not Material and |
||
| this exclusion does not detract | ||
| from the understanding of the | ||
report, the Competent Person |
||
should clearly explain why this |
||
is the case. |
||
| Data aggregation | In reporting Exploration Results, | › This report references a Mineral Resource Estimate, |
methods |
weighting averaging |
and this item is not applicable. |
| techniques, maximum and/or | › No metal equivalents are used. |
|
minimum grade truncations (eg |
||
cutting of high grades) and cut- |
||
off grades are usually Material |
||
and should be stated. |
||
| Where aggregate intercepts | ||
incorporate short lengths of |
||
high grade results and longer |
||
lengths of low grade results, |
||
the procedure used for such |
||
aggregation should be stated |
||
and some typical examples of |
||
such aggregations should be |
||
shown in detail. |
||
| The assumptions used for any | ||
reporting of metal equivalent |
||
values should be clearly stated. |
||
| Relationship | These relationships are particularly | › This report references a Mineral Resource Estimate, |
between |
important in the reporting of |
and this item is not applicable. |
| mineralisation | Exploration Results. | |
| widths and | If the geometry of the | |
| intercept lengths | mineralisation with respect to |
|
| the drill hole angle is known, its | ||
nature should be reported. |
||
| If it is not known and only the | ||
down hole lengths are reported, |
||
there should be a clear |
KGL Resources Limited 2024 Ore Reserve Statement
xenith.com.au
119
==> picture [195 x 147] intentionally omitted <==
| Criteria | JORC Code explanation | Section 2 Commentary |
|---|---|---|
| statement to this effect (eg | ||
‘down hole length, true width |
||
not known’). |
||
| Diagrams | Appropriate maps and sections | › Appropriate scaled maps and sections are provided |
| (with scales) and tabulations of | in the body of the report. | |
| intercepts should be included | ||
for any significant discovery |
||
being reported These should |
||
include, but not be limited to a |
||
| plan view of drill hole collar | ||
locations and appropriate |
||
sectional views. |
||
| Balanced | Where comprehensive reporting of | › This report references a Mineral Resource Estimate, |
| reporting | all Exploration Results is not |
and this item is not directly applicable. The Mineral |
| practicable, representative | Resource considers all drilling within the Rockface | |
reporting of both low and high |
deposit area. |
|
| grades and/or widths should be | ||
practiced to avoid misleading |
||
reporting of Exploration |
||
Results. |
||
| Other | Other exploration data, if | › Outcrop mapping of exploration targets using Real- |
| substantive | meaningful and material, |
time DGPS. |
| exploration data | should be reported including | › IP, Magnetics, Gravity, Downhole EM are all used |
| (but not limited to): geological | for targeting. |
|
observations; geophysical |
||
| › Metallurgical studies are well advanced, including |
||
survey results; geochemical |
||
recovery of the payable metals including Cu, Ag and |
||
survey results; bulk samples – |
||
Au. |
||
size and method of treatment; |
||
metallurgical test results; bulk |
› Deleterious elements such as Pb, Zn, Bi, U and F |
|
density, groundwater, |
are modelled. Pb and Zn may have future economic | |
geotechnical and rock |
value, at present KGL do not intend to recover Pb | |
characteristics; potential |
and Zn as economically beneficial metals. | |
| deleterious or contaminating | ||
substances. |
||
| Further work | The nature and scale of planned | › The current report relates to an updated Mineral |
further work (eg tests for |
Resource as a result of ongoing confirmatory |
|
lateral extensions or depth |
drilling. |
|
| extensions or large-scale step- | ||
out drilling). |
||
| Diagrams clearly highlighting the | ||
areas of possible extensions, |
||
including the main geological |
||
interpretations and future |
||
drilling areas, provided this |
||
information is not commercially |
||
sensitive. |
KGL Resources Limited 2024 Ore Reserve Statement
xenith.com.au
120
==> picture [195 x 147] intentionally omitted <==
Table A.3 – Section 3 Estimation and Reporting of Mineral Resources: Jervois Project
| Criteria | JORC Code explanation | Section 3: Commentary |
|---|---|---|
| Database | Measures taken to ensure that | › MA has undertaken limited independent first principal |
| integrity | data has not been corrupted | checks of the database. |
| by, for example, | › Historical ITRs accept the integrity of the database with |
|
| transcription or keying | the exception of the rejected holes. |
|
errors, between its initial |
||
| › The geological database is managed and updated by |
||
| collection and its use for | ||
KGL Staff. |
||
| Mineral Resource estimation | ||
| purposes. | › Basic database validation checks were run, including |
|
checks for missing intervals, overlapping intervals, |
||
| Data validation procedures | ||
down hole deviation checks and hole depth |
||
used. |
||
mismatches. |
||
| › Holes at Reward up to KJD614 were used in the MRE. |
||
| › At Bellbird MA identified three drill collars as spurious, |
||
KGL staff corrected the errors |
||
| › At Rockface MA identified two drill collars as spurious, |
||
KGL staff corrected the errors. |
||
| Site visits | Comment on any site visits | › The CP (Mr I Taylor) visited site from the 1stto 3rd |
| undertaken by the | November 2020 to review the geology, drill core and | |
Competent Person and the |
field practices as part of the 2020 DFS and Mineral |
|
outcome of those visits. |
Resource Estimate Update. |
|
| If no site visits have been | ||
| undertaken indicate why | ||
this is the case. |
||
| Geological | Confidence in (or conversely, | › The geological model is well understood at a deposit |
interpretation |
the uncertainty of) the |
scale. Reward is interpreted as an original syn- |
| geological interpretation of | depositional copper rich polymetallic massive sulphide | |
the mineral deposit. |
deposit that has undergone deformation, |
|
| Nature of the data used and of | metamorphism and some degree of structural | |
| any assumptions made. | remobilisation. | |
| The effect, if any, of alternative | › Geological logging, structural mapping and drill hole |
|
interpretations on Mineral |
assays have been used in the establishment of a | |
Resource estimation. |
Resource estimate. Validation has been carried out by | |
KGL and MA competent persons. |
||
| The use of geology in guiding | ||
and controlling Mineral |
› No alternative interpretations have been presented. |
|
Resource estimation. |
Alternative estimation methods applied to density | |
estimation had little effect on overall tonnes and grade. |
||
| The factors affecting continuity | ||
both of grade and geology. |
› Alternate estimation methods (ID2and NN) were run |
|
and performed as expected. |
||
| › Geological and grade continuity within defined domains |
||
appears well understood. Lithology and weathering |
||
were considered during the mineralisation domain |
||
interpretations |
||
| › Ongoing Infill drilling by KGL has increased the |
||
confidence in grade and geology interpretations which |
||
is the basis for the mineral Resource estimation. |
||
| Dimensions | The extent and variability of the | › The Reward deposits strike over 1.5 km. Within the |
| Mineral Resource expressed | structural corridor lie five high grade shoots each | |
as length (along strike or |
approximately 200m in length and plunge steeply south |
|
otherwise), plan width, and |
||
depth below surface to the |
KGL Resources Limited 2024 Ore Reserve Statement
xenith.com.au
121
==> picture [195 x 147] intentionally omitted <==
| Criteria | JORC Code explanation | Section 3: Commentary |
|---|---|---|
| upper and lower limits of | up to 800 m below the surface. Two lodes lie to the | |
the Mineral Resource. |
east in the footwall of the reward structure. |
|
| › The Rockface deposits strike over 0.4 km. Within the |
||
hook of “J” structure, there are four defined lodes |
||
| which range from 100 m to 300 m in length and plunge | ||
900 m steeply to East. |
||
| › The Bellbird deposits strike over 1.3 km. Within the |
||
structural corridor lie three defined lodes ranging from |
||
approximately 200 m to 500 m in length, and plunge |
||
moderately North. Three mineralised structures lie in |
||
the hanging wall position of the main structure and two |
||
oblique lodes lie to the east of the Bellbird structure. |
||
| Estimation and | The nature and appropriateness | › Ordinary Kriging has been used as the interpolation |
| modelling | of the estimation |
technique to estimate the Mineral Resource. This |
techniques |
technique(s) applied and | method considered appropriate given the nature of |
| key assumptions, including | mineralisation. All elements were estimated using | |
treatment of extreme grade |
ordinary kriging. |
|
| values, domaining, | › Estimation was undertaken in Surpac Geological |
|
| interpolation parameters | Software |
|
and maximum distance of |
||
| › Drill hole intercepts were flagged manually within |
||
| extrapolation from data | ||
Surpac with individual domain codes. The flagged drill |
||
points. If a computer |
||
hole intercepts were imported into LeapFrog, and |
||
assisted estimation method |
||
three-dimensional mineralisation wireframes created. |
||
| was chosen include a | ||
| Intervals were checked for inconsistences, split | ||
| description of computer | ||
samples, edge dilution and mineralisation outside the |
||
software and parameters |
||
interpretation. A separate table was created to store |
||
used. |
||
drill hole intercepts greater than 0.5% S, these |
||
| The availability of check | intercepts were domained as stratabound |
|
| estimates, previous | mineralisation. |
|
estimates and/or mine |
||
| › The domain codes (for Cu and S) have then been used |
||
| production records and | ||
to extract a raw assay file from MS Access for grade |
||
whether the Mineral |
||
population analysis (multi-element), as well as analysis |
||
| Resource estimate takes | ||
of the most appropriate composite length to be used |
||
| appropriate account of such | ||
for the estimation. |
||
data. |
||
| › Analysis of the raw samples within the Cu |
||
| The assumptions made | ||
mineralisation domains indicates that the majority of |
||
regarding recovery of by- |
||
sample lengths are at 1 m. Samples were composited |
||
products. |
||
to one metre honouring geological boundaries. |
||
| Estimation of deleterious | ||
| › Grade continuity analysis within Cu domains to define |
||
| elements or other non- | ||
the mineralisation has been undertaken. Where |
||
| grade variables of economic | ||
| variograms could not be generated for a particular | ||
significance (eg sulphur for |
||
element, variograms were considered from adjacent |
||
acid mine drainage |
||
domains. |
||
characterisation). |
||
| › 3D experimental variogram modelling used a nugget |
||
| In the case of block model | ||
(C0) and two spherical models (C1, C2), occasionally |
||
| interpolation, the block size | ||
one spherical model was sufficient. |
||
in relation to the average |
||
sample spacing and the |
› Reward: The stratabound mineralisation included a |
|
search employed. |
third long range structure (C3). Nuggets ranged from | |
reasonably low to moderate, between 0.14 and 0.44, |
||
| Any assumptions behind | ||
and variogram ranges varied between 60 and 133m for |
||
modelling of selective |
||
Cu. Nuggets for additional elements ranged from 0.12 |
||
mining units. |
||
to 0.4 and variogram ranges varied between 80 and |
||
180m. |
KGL Resources Limited 2024 Ore Reserve Statement
xenith.com.au
122
==> picture [195 x 147] intentionally omitted <==
| Criteria | JORC Code explanation | Section 3: Commentary |
|---|---|---|
| Any assumptions about | › Rockface: Nuggets ranged from reasonably low to high, |
|
correlation between |
between 0.11 and 0.23, and variogram ranges varied |
|
| variables. | between 120 m and 150 m for Cu |
|
| Description of how the | › Bellbird: Nuggets ranged from reasonably low to high, |
|
geological interpretation |
between 0.19 and 0.48, and variogram ranges varied |
|
was used to control the |
between 112 and 230 m for Cu |
|
| Resource estimates. | › Anisotropic ellipses based on the resulting bearing, |
|
| Discussion of basis for using or | plunge, dip, defined ranges and anisotropic ratios were | |
not using grade cutting or |
graphically plotted in Surpac and displayed against the |
|
capping. |
extracted assay composites to ensure modelled |
|
| The process of validation, the | parameters were reasonably orientated. Estimation | |
checking process used, the |
utilised dynamic anisotropy based on local variations of | |
comparison of model data to |
the domain centre plane | |
| drill hole data, and use of | › The interpolations have been constrained within the |
|
| reconciliation data if | mineralisation wireframes and undertaken in three |
|
| available. | passes with the mineralisation wireframes utilised as | |
| hard boundaries during the estimation. | ||
| › The first pass at Reward utilised a search distance of |
||
70 m and a minimum number of informing samples of |
||
8, and a maximum number of informing samples of 20. |
||
The second pass utilised a minimum of 6 and maximum |
||
of 16 samples, the search distance was doubled to 140 |
||
m. Both passes restricted the maximum number of |
||
samples per hole to 4. The third pass dropped the |
||
minimum to 2 and maximum to 10 samples and the |
||
restriction of samples per hole was lifted. Third pass |
||
maximum distance was 210 m. 56% of estimated metal |
||
| (> 0.5 % Cu) is estimated in pass 1. | ||
| › The first pass at Rockface utilised a search distance of |
||
60 m, a minimum number of informing samples of 6, |
||
and a maximum number of informing samples of 16. |
||
The second pass utilised a minimum of 4 and maximum |
||
of 14 samples, while the search distance was doubled |
||
to 120 m. Both passes restricted the maximum number |
||
of samples per hole to 4. The third pass dropped the |
||
minimum to 3 and maximum to 8 samples, and the |
||
restriction of samples per hole was lifted. Third pass |
||
maximum distance was 180 m. 80% of estimated metal |
||
| (> 0.5 % Cu) is estimated in pass 1 | ||
| › The first pass at Bellbird utilised a search distance of 70 |
||
m and a minimum number of informing samples of 8, |
||
and a maximum number of informing samples of 16. |
||
The second pass utilised a minimum of 6 and maximum |
||
of 13 samples, the search distance was doubled to 140 |
||
m. The third pass dropped the minimum to 4 and |
||
maximum to 8 samples and the restriction of samples |
||
per hole was lifted. Third pass maximum distance was |
||
210 m. 44% of estimated metal (> 0.5 % Cu) is |
||
estimated in pass 1. |
||
| › The company is not intending to recover Pb, Zn at this |
||
stage of the Project. Ag and Au will report to the |
||
copper concentrate. |
||
| › The model includes an estimation of deleterious |
||
| elements Bi, W, U and F, these elements can attract a |
KGL Resources Limited 2024 Ore Reserve Statement
xenith.com.au
123
==> picture [195 x 147] intentionally omitted <==
| Criteria | JORC Code explanation | Section 3: Commentary |
|---|---|---|
| penalty and rejection limits in the concentrate may | ||
apply. S for potential acid mine drainage |
||
characterisation is included in the block model. |
||
| › No specific assumptions have been made regarding |
||
selective mining units. However, the sub-blocks are of a |
||
suitable selective mining unit size for either an open pit |
||
operation or underground mining scenario. |
||
| › Two 3D models were created for Reward and Bellbird |
||
| with a parent block size of 2.5 m (X) by 10 m (Y) by 5 | ||
m (Z) was used. The drill hole spacing in the deposit |
||
ranges from 25 m by 25 m in the better drilled parts of |
||
the deposit to the dominant 50 m by 50 m drill pattern. |
||
In order for effective boundary definition, a sub-block |
||
size of 1.25 m (X) by 5 m (Y) by 2.5 m (Z) has been |
||
used; the sub-blocks are estimated at the parent block |
||
scale. |
||
| › The Rockface 3D model has a parent block size of 15 m |
||
by 2 m by 15 m (XYZ). The drill hole spacing ranges |
||
from 25 m to 50 m throughout the deposit. In order for |
||
effective boundary definition, a sub-block size of 3.75 |
||
m by 0.5 m by 3.75 m (XYZ) has been used; the sub- |
||
blocks are estimated at the parent block scale. |
||
| › The Reward lodes show moderate to good correlation |
||
between Pb and Ag and weak correlation between Bi |
||
and Ag. There is a moderate (> 0.5) correlation |
||
between Cu, Pb, Zn, Ag Au and S. Fe is associated with |
||
magnetite and shows a weak correlation (~0.3) with S |
||
and Cu There is no correlation between F, U and W and |
||
| the other elements. | ||
| › The Rockface and Bellbird deposits show a moderate |
||
(> 0.5) correlation between Cu, Au, Ag and S. Pb and |
||
Zn also have a moderate correlation (0.56). Fe is |
||
associated with magnetite and pyrite and has a low |
||
correlation (~0.24) with S. There is no correlation |
||
between F, U and W and the other elements. |
||
| › The geological model (grade domains and faults |
||
interpretations) was used to control grade estimation. |
||
| › High grade outliers (Cu, Pb, Zn, Ag, Au, Bi, F, U and W) |
||
within the composite data were capped. No capping |
||
was applied to Fe and S. Domains were individually |
||
assessed for outliers using histograms, log probability |
||
plots and changes in average metal content; grade |
||
caps were applied as appropriate. Generally, the |
||
domains defined a well distributed population with low |
||
CV’s and only minimal grade-capping was required. |
||
| › The Resource has been validated visually in section and |
||
level plan along with a statistical comparison of the |
||
block model grades against the composite grades to |
||
ensure that the block model is a realistic representation |
||
of the input grades. No issues material to the reported |
||
Mineral Resource have been identified in the validation |
||
| process | ||
| Moisture | Whether the tonnages are | › Tonnages are based on dry tonnes. |
| estimated on a dry basis or |
KGL Resources Limited 2024 Ore Reserve Statement
xenith.com.au
124
==> picture [195 x 147] intentionally omitted <==
| Criteria | JORC Code explanation | Section 3: Commentary |
|---|---|---|
| with natural moisture, and | ||
| the method of | ||
| determination of the | ||
| moisture content. | ||
| Cut-off | The basis of the adopted cut-off | › The Resource is reported above an optimised pit shell |
| parameters | grade(s) or quality |
at 0.35 % CuEq lower cut-off representing open pit |
| parameters applied. | potential mineralisation. Below the optimised pit shell | |
| the Resource is reported at a 0.8 % CuEq Cut-off | ||
reflecting an underground mining scenario. Assumed |
||
Copper price is AU $ 15,428/t ($US 4.90/lb), silver price |
||
of US $ 32/t and gold price of US $ 2400/oz. Recoveries |
||
are 92.7% for copper, 65% for silver and 60% for gold. |
||
Payables are 95.5% Cu, 90% Ag > 30g/t and 90% Au |
||
> 1.0 g/t in concentrate. |
||
| › The metal equivalent formula is: |
||
| ▪ CuEq = (Cu Metal Value + Ag Metal Value + Au |
||
metal Value- bi penalty-T)/Cu metal value per |
||
percent Cu -T |
||
| › The general metal value is defined as: |
||
| ▪ Metal Value = grade x C x (Price-TCRC) x R x P |
||
| › Where: |
||
| ▪ Grade – The grade of the metal (e.g Au g/t) |
||
| ▪ C – Constant to convert grade to the metal price |
||
unit (e.g. 1/31.1035 to convert g/t to ounces) |
||
| ▪ Price – The price of the commodity metal per unit |
||
(e.g. $/oz Au) |
||
| ▪ TCRC – Treatment charges and refining costs (i.e. |
||
$/oz Au) |
||
| ▪ R – Average metallurgical recovery percentage for |
||
the metal (e.g. 60% Fresh Au recovery) |
||
| ▪ P – Payable metal percentage for each metal (e.g. |
||
90% Au payable metal percentage) |
||
| ▪ T – Concentrate transport costs (i.e. |
||
$/concentrate WMT) |
||
| ▪ Bi penalty = US$1.50 x (Bi grade in concentrate – |
||
1200ppm)x 100ppm x concentrate tonnes(dmt) |
||
| Mining factors or | Assumptions made regarding | › The mineralisation above an optimised pit shell with a |
assumptions |
possible mining methods, |
revenue factor of 1.15 has been deemed to be |
| minimum mining dimensions | potentially accessible by open cut mining methods at | |
and internal (or, if |
Reward and Bellbird. The near surface deposits are |
|
applicable, external) mining |
extensive steeply dipping syn-depositional copper |
|
dilution. It is always |
deposits likely resulting in a moderate to high strip |
|
necessary as part of the |
ratio, |
|
| process of determining | › Mineralisation below the optimised pit shells (RF 1.15) |
|
| reasonable prospects for | is considered to have underground potential above a |
|
| eventual economic | 0.8 % CuEq cut-off. Due to topography and short strike |
|
| extraction to consider | of Rockface only underground potential is considered. |
|
| potential mining methods, | ||
| › No other mining assumptions have been used in the |
||
but the assumptions made |
||
estimation of the Mineral Resource. |
||
regarding mining methods |
||
and parameters when |
||
estimating Mineral |
||
Resources may not always |
KGL Resources Limited 2024 Ore Reserve Statement
xenith.com.au
125
==> picture [195 x 147] intentionally omitted <==
| Criteria | JORC Code explanation | Section 3: Commentary |
|---|---|---|
| be rigorous. Where this is | ||
the case, this should be |
||
| reported with an | ||
explanation of the basis of |
||
the mining assumptions |
||
made. |
||
| Metallurgical | The basis for assumptions or | › No metallurgical factors have been applied to the in- |
factors or |
predictions regarding |
situ grade estimates. |
| assumptions | metallurgical amenability. It | › Metallurgical Recoveries for copper, silver and gold are |
| is always necessary as part | determined as 92.7% for copper, 65% for silver and |
|
| of the process of | 60% for gold. 60% of Bismuth is also expected to be |
|
| determining reasonable | recovered. |
|
prospects for eventual |
||
economic extraction to |
||
| consider potential | ||
metallurgical methods, but |
||
the assumptions regarding |
||
metallurgical treatment |
||
processes and parameters |
||
made when reporting |
||
Mineral Resources may not |
||
always be rigorous. Where |
||
this is the case, this should |
||
| be reported with an | ||
explanation of the basis of |
||
the metallurgical |
||
assumptions made. |
||
| Environmental | Assumptions made regarding | › Samples from the Project representing different waste |
| factors or | possible waste and process |
rock, ore, and tailings materials underwent laboratory |
| assumptions | residue disposal options. It |
scale column leach testing for durations between 64 |
| is always necessary as part | and 132 weeks. The tests confirmed most of the waste | |
of the process of |
material recoverable by mining will have low potential | |
determining reasonable |
to become acidic. The volume of material with potential |
|
prospects for eventual |
to become acidic can be encapsulated within the non- |
|
economic extraction to |
acid forming waste rock. |
|
| consider the potential | › Sulphur has been estimated throughout the block |
|
| environmental impacts of | model. Fe and S have been estimated within the |
|
| the mining and processing | sulphur domain and outside the sulphur domain (waste | |
| operation. Where these | rock). |
|
aspects have not been |
||
| › It is assumed that surface waste dumps will be used to |
||
considered this should be |
||
store waste material and conventional storage facilities |
||
| reported with an | ||
will be used for the process plant tailings. |
||
explanation of the |
||
environmental assumptions |
||
made. |
||
| Bulk density | Whether assumed or | › Onsite measurements by water immersion method are |
| determined. If assumed, the | only conducted on competent transitional and fresh | |
| basis for the assumptions. If | core. Limited oxide samples have been taken. |
|
| determined, the method | › Dry bulk density has been varied according to the |
|
| used, whether wet or dry, | weathering profile. Within Fresh material bulk density |
|
| the frequency of the | was estimated (OK) directly from density readings. A |
|
| measurements, the nature, | minimum of 5 samples and a maximum of 12 samples |
|
| size and representativeness | was used. In areas not filled with estimated density |
|
| of the samples. | values, a linear regression of iron assays was |
KGL Resources Limited 2024 Ore Reserve Statement
xenith.com.au
126
==> picture [195 x 147] intentionally omitted <==
| Criteria | JORC Code explanation | Section 3: Commentary |
|---|---|---|
| The bulk density for bulk | employed; the calculated density data was then used in | |
material must have been |
a second pass. |
|
| measured by methods that | › All models have an average assigned density of 2.60 |
|
| adequately account for void | t/m3for mineralised oxide material and 2.80 t/m3 |
|
| spaces (vugs, porosity, etc), | transitional material. |
|
moisture and differences |
||
| › Reward - areas of high sulphide content average |
||
| between rock and alteration | ||
3.12 t/m3and mineralised fresh material averages |
||
| zones within the deposit. | ||
3.13 t/m3. |
||
| Discuss assumptions for bulk | ||
| › Rockface – areas of high sulphide content average |
||
density estimates used in |
||
3.24 t/m3and mineralised fresh material averages |
||
the evaluation process of |
||
3.46 t/m3. The total Rockface Resource averages |
||
the different materials. |
||
3.44 t/m3 |
||
| › Bellbird - the high sulphide material averages 2.91 t/m3 |
||
and mineralised fresh material averages 2.88 t/m3 |
||
| Classification | The basis for the classification | › Blocks have been classified as Measured, Indicated, |
| of the Mineral Resources | Inferred or Unclassified based on geological continuity | |
| into varying confidence | and estimation quality parameters, dominantly |
|
categories. |
influenced by drill spacing. |
|
| Whether appropriate account | › The above criteria were used to determine areas of |
|
has been taken of all |
implied, assumed and confirmed geological and grade | |
| relevant factors (ie relative | continuity. Only small areas have confirmed geological |
|
confidence in tonnage/grade |
and grade continuity and have been classified as |
|
estimations, reliability of |
measured. Classification was assessed on a per domain |
|
input data, confidence in |
basis and Resource categories were stamped onto the |
|
continuity of geology and |
individual domains. |
|
| metal values, quality, | › Unclassified mineralisation has not been included in this |
|
| quantity and distribution of | Mineral Resource. Unclassified material is either | |
| the data). | contained in isolated blocks above cut-off within the | |
| Whether the result | strata-bound domain or in deeper portions of the | |
| appropriately reflects the | deposit with sparse drill intercepts. |
|
| Competent Person’s view of | › The classification reflects the competent person’s view |
|
| the deposit. | of the Reward deposit. |
|
| Audits or reviews | The results of any audits or | › There has been a limited independent audit of the data |
| reviews of Mineral Resource | performed by MA, there has been no independent | |
| estimates. | review of the mineral Resource. |
|
| Discussion of | Where appropriate a statement | › With further drilling it is expected that there will be |
| relative | of the relative accuracy and |
minimal variances to the tonnage, grade and contained |
| accuracy/ | confidence level in the |
metal within the deposits. The competent person does |
confidence |
Mineral Resource estimate | not expect that these variances will impact the |
| using an approach or | economic extraction of the deposit. | |
| procedure deemed | › The mineral Resource estimate appropriately reflects |
|
| appropriate by the | the competent person’s view of the deposit. |
|
Competent Person. For |
||
| › No geostatistical confidence limits have been estimated. |
||
example, the application of |
||
Geostatistical procedures (kriging statistics) were used |
||
statistical or geostatistical |
||
to quantify the relative accuracy of the estimate. |
||
procedures to quantify the |
||
Consideration has been given to all relevant factors in |
||
relative accuracy of the |
||
the classification of the mineral Resource. |
||
Resource within stated |
||
| confidence limits, or, if such | › The ordinary kriging result, due to the level of |
|
an approach is not deemed |
smoothing, should only be regarded as a global | |
appropriate,aqualitative |
estimate, and is suitable as a life of Mine Planning tool. |
KGL Resources Limited 2024 Ore Reserve Statement
xenith.com.au
127
==> picture [195 x 147] intentionally omitted <==
| Criteria | JORC Code explanation | Section 3: Commentary |
|---|---|---|
| discussion of the factors |
› Should local estimates be required for detailed mine |
|
| that could affect the relative | scheduling, techniques such as uniform conditioning or |
|
| accuracy and confidence of | conditional simulation could be considered. Ultimately |
|
the estimate. |
grade control drilling will be required. |
|
| The statement should specify |
› Limited mining records exist (40 kt of oxide extracted |
|
whether it relates to global |
from Green Parrot – south of Reward Deposit). Some |
|
or local estimates, and, if |
historic mining has occurred on the Marshall – Reward |
|
| local, state the relevant | structure. Minor historic mining has occurred on the |
|
| tonnages, which should be | Main Bellbird structure, records are insufficient to |
|
relevant to technical and |
reconcile. Records are insufficient to reconcile | |
| economic evaluation. | ||
| Documentation should | ||
| include assumptions made | ||
and the procedures used. |
||
| These statements of relative | ||
| accuracy and confidence of | ||
the estimate should be |
||
| compared with production | ||
data, where available. |
Note: Regarding Section 3, criteria listed in Section 1, and where relevant in Section 2, also apply to this section.
Table A.4 – Section 4 Estimation and Reporting of Mineral Resources and Ore Reserves: Jervois Project
| Criteria | JORC Code explanation | Section 4 Commentary |
|---|---|---|
| Mineral Resource | Description of the Mineral | › This Ore Reserve Statement is based on the revised May |
| estimate for | Resource estimate used as a |
2024 Mineral Resource Estimate compiled by Ian Taylor |
| conversion to Ore | basis for the conversion to | of Mining Associates. |
| Reserves | an Ore Reserve. | › Mineral Resources are reported inclusive of Ore |
| Clear statement as to whether | Reserves. |
|
| the Mineral Resources are | ||
| reported additional to, or | ||
inclusive of, the Ore |
||
| Reserves. | ||
| Site visits | Comment on any site visits | › A site visit was conducted by Mr Iain Ross, accompanied |
| undertaken by the | by the Resource CP, Mr Ian Taylor of Mining Associates, | |
Competent Person and the |
from 1st to 3rd November 2020. |
|
| outcome of those visits. | › During that visit, all deposits (outcrops) were inspected |
|
| If no site visits have been | along with the proposed sites for proposed | |
| undertaken indicate why this | infrastructure. Exploration drill cores were examined |
|
is the case. |
and some spot checks on randomly selected holes |
|
| (collars seen during the visit) were performed. | ||
| Study status | The type and level of study | › The optimisation process is deemed to be at a Feasibility |
| undertaken to enable | Study level and was completed as part of open pit and | |
| Mineral Resources to be | underground studies documented by Xenith Consulting |
|
| converted to Ore Reserves. | in the 2024 Feasibility Study Update (2024 FSU) |
|
| The Code requires that a study | compiled by KGL. | |
| to at least Pre-Feasibility | › Proven and Probable Reserves have been declared for |
|
Study level has been |
both the Bellbird and Reward open pits and only | |
undertakento convert |
ProbableReserveshave beendeclaredforthefour |
KGL Resources Limited 2024 Ore Reserve Statement
xenith.com.au
128
==> picture [195 x 147] intentionally omitted <==
| Criteria | JORC Code explanation | Section 4 Commentary |
|---|---|---|
| Mineral Resources to Ore | proposed underground mines. Modifying Factors in | |
| Reserves. Such studies will | respect of dilution and mining recoveries, are noted |
|
| have been carried out and | herein and documented within the 2024 FSU. |
|
| will have determined a Mine | › A Life of Mine plan has been prepared which has been |
|
| Plan that is technically | financially modelled. The assumptions in the plan |
|
| achievable and economically | appear reasonable and the costs have been sourced |
|
| viable, and that material | from suppliers, contractors, consultants or agents. This |
|
| Modifying Factors have been | information is documented in the 2024 FSU. |
|
considered. |
||
| › The mining sequence has been established and follows |
||
reasonable assumptions regarding mining rates and |
||
durations, as documented in the 2024 FSU. |
||
| › Sufficient metallurgical test-work has been undertaken |
||
to identify likely recovery rates for different grades |
||
(including composites). The recovery formulae have |
||
been built into the optimisation models. |
||
| › Other modifying factors including tailings disposal, |
||
environmental considerations, leasing, accommodation, |
||
power supply and logistics have all been considered and |
||
costs have been appropriately applied in the financial |
||
model. |
||
| The basis of the cut-off grade(s) | › The resource is reported above an optimised pit shell at |
|
or quality parameters |
0.35 %CuEq lower cut-off representing open pit |
|
applied. |
potential mineralisation. Below the optimised pit shell |
|
| the resource is reported at a 0.8 %CuEq Cut-off | ||
reflecting an underground mining scenario. |
||
| › Using the price assumptions for Ore Reserves and |
||
| Cut-off | Mineral Resources, anticipated recovery factors, the | |
material above cut-off of 0.35 %CuEq would cover Open |
||
| parameters | ||
pit mining and processing costs and contribute |
||
towards overheads.Similarly, material above the |
||
0.8%CuEq cut-off would cover typical underground |
||
mining and processing costs. |
||
| › The cut-off grades applied are appropriate, however |
||
there is a lower margin than there was in 2022 due to |
||
moving to a %CuEq |
||
| Mining factors or | The method and assumptions | › The assumptions used in the 2024 FSU optimisations |
assumptions |
used as reported in the Pre- |
appear valid for both the open pits and the underground |
| Feasibility or Feasibility | mines. | |
| Study to convert the Mineral | The Reward pit SMU selection approximated 12.4% | |
| Resource to an Ore Reserve | dilution (compared to the 2022 assumption of 10%) |
|
| (i.e. either by application of | when compared to the unregularized model. Similarly, |
|
| appropriate factors by | the SMU selected for the Bellbird pit approximated 27% |
|
| optimisation or by | dilution compared to the 2022 assumption of 15%. |
|
preliminary or detailed |
||
| The dilution and recovery assumptions for the | ||
design). |
||
underground mines are detailed below and these were |
||
| The choice, nature and | used during the stope optimisation and design process. |
|
| appropriateness of the | ||
| › All deposits have been optimised though a valid process |
||
selected mining method(s) |
||
and the preliminary designs tested against updated |
||
and other mining parameters |
||
costs and metal prices. |
||
including associated design |
||
issues such as pre-strip, |
› The mine designs, assumptions, mining fleets and |
|
access, etc. |
methods, recovery factors and assumed dilution | |
parameters are all stated in the 2024 FSU chapters |
||
KGL Resources Limited 2024 Ore Reserve Statement
xenith.com.au
129
==> picture [195 x 147] intentionally omitted <==
| Criteria | JORC Code explanation | Section 4 Commentary |
|---|---|---|
| The assumptions made | relating to the individual deposits and represent a | |
regarding geotechnical |
pragmatic approach to mining engineering and |
|
parameters (e.g. pit slopes, |
incorporates industry standards with respect to fleet |
|
stope sizes, etc), grade |
selection for open pit and underground mining of similar |
|
control and pre-production |
sized deposits similar to the Jervois Project. |
|
| drilling. | › Geotechnical recommendations from Entech regarding |
|
| The major assumptions made, | both pit wall slopes and stope dimensions were sourced |
|
| and Mineral Resource model | as part of the PFS. These are detailed in the 2024 FSU. |
|
| used for pit and stope | › Minimum mining widths underground are 3m and |
|
| optimisation (if appropriate). | maximum stope height is 30 m. 2 m widths are |
|
| The mining dilution factors | considered but are expanded to an effective mining |
|
| used. | width of 3.0 m including dilution in the narrower |
|
| The mining recovery factors | sections of the deposits. | |
| used. | › Due to the geometry of the ore deposits in the Open |
|
| Any minimum mining widths | Pits, different dilution factors are applied. Dilution of | |
used. |
10% for Reward open pit has been applied where wider | |
ore lenses are to be mined, and 15% for Bellbird where |
||
| The manner in which Inferred | ||
| narrower ore lenses are to be mined. Underground | ||
| Mineral Resources are | ||
stope optimisations include 0.5 m dilution for both the |
||
| utilised in mining studies and | ||
hangingwall and footwall of proposed underground |
||
the sensitivity of the |
||
stopes. |
||
outcome to their inclusion. |
||
| › Mining recoveries of 95% have been applied for the |
||
| The infrastructure requirements | ||
open pits. |
||
of the selected mining |
||
methods. |
› The mining recoveries applied in the underground |
|
mines are considered conservative and in line with |
||
| averages seen in similar style operations and are given | ||
as 90% of diluted stope shapes, 80% for the mining of |
||
sill pillars between mining panels. Crown pillars between |
||
open pit and underground are designated as 66%. |
||
Further work will be required prior to finalizing designs |
||
for stoping. |
||
| › Any grade from Inferred material contained in |
||
underground mine designs was excluded from the Ore |
||
Reserve statement, although the tonnage is included. A |
||
check was made to ensure that the Indicated material |
||
| (probable Reserve) still contained sufficient value to | ||
carry the costs of mining the inferred material (at zero |
||
value). The Inferred tonnages and grades remain in the |
||
LoM forecast for both open pit and underground mines. |
||
| › Inferred Resources in the LoM forecast do not drive the |
||
| mining plan. The bulk of mill feed in the first four years | ||
is from the open pits which contain very little Inferred |
||
material (<3%). After year 8, there are significant |
||
quantities of Inferred material (~50%) which are |
||
expected to be converted to Indicated or better prior to |
||
being mined. |
||
| Metallurgical | The metallurgical process | › The mill flotation process planned for concentrate |
factors or |
proposed and the |
recovery is a standard approach widely used in industry. |
| assumptions | appropriateness of that | › Test-work has been completed and predictive |
| process to the style of | algorithms developed and verified. The CP considers the |
|
| mineralisation. | metallurgical test work appropriate, considering the |
|
| Whether the metallurgical | work to date is at FS level. |
|
| process is well-tested |
KGL Resources Limited 2024 Ore Reserve Statement
xenith.com.au
130
==> picture [195 x 147] intentionally omitted <==
| Criteria | JORC Code explanation | Section 4 Commentary |
|---|---|---|
| technology or novel in | › The presence of deleterious elements (including |
|
nature. |
Bismuth) has been modelled. The only element that is |
|
| The nature, amount and | likely to incur penalties is Bismuth and this has been | |
representativeness of |
appropriately applied in the financial modelling by KGL. | |
metallurgical test work |
Note that there are no rejection limits under their | |
undertaken, the nature of |
contract. | |
| the metallurgical domaining | › Composite samples (to represent potential head-feed |
|
| applied and the | blends over the first 3 years of operation) have been |
|
| corresponding metallurgical | tested and validate modelled recoveries. |
|
recovery factors applied. |
||
| Any assumptions or allowances | ||
made for deleterious |
||
| elements. | ||
| The existence of any bulk | ||
sample or pilot scale test |
||
work and the degree to |
||
which such samples are |
||
considered representative of |
||
the ore body as a whole. |
||
| For minerals that are defined by | ||
a specification, has the ore |
||
Reserve estimation been |
||
| based on the appropriate | ||
mineralogy to meet the |
||
specifications? |
||
| Environmental | The status of studies of | › The EIS process was acknowledged as completed in |
| potential environmental | 2019 by the EIA following a number of studies and | |
impacts of the mining and |
submissions up until 2019. Requirements have been |
|
processing operation. Details |
included in the MMP for the Jervois Project. |
|
| of waste rock | ||
| characterisation and the | ||
| consideration of potential | ||
sites, status of design |
||
options considered and, |
||
where applicable, the status |
||
of approvals for process |
||
residue storage and waste |
||
dumps should be reported. |
||
| Infrastructure | The existence of appropriate | › Infrastructure is planned and contractor built/owner- |
| infrastructure: availability of | operator systems for both the accommodation camp and | |
land for plant development, |
power station have been included in the infrastructure |
|
power, water, transportation |
requirements. |
|
| (particularly for bulk | ||
commodities), labour, |
||
accommodation; or the ease |
||
| with which the infrastructure | ||
| can be provided or accessed. | ||
| Costs | The derivation of, or | › A reputable mining contractor has provided indicative |
| assumptions made, | rates for the designs, methods and mining rates | |
regarding projected capital |
proposed. The process plant has been designed and |
|
costs in the study. |
costed by Sedgman -see 2024 FSU. |
KGL Resources Limited 2024 Ore Reserve Statement
xenith.com.au
131
==> picture [195 x 147] intentionally omitted <==
| Criteria | JORC Code explanation | Section 4 Commentary |
|---|---|---|
| The methodology used to | › Transport charges have been based on the selected |
|
estimate operating costs. |
route to the (Glencore) Mt Isa treatment facility. |
|
| Allowances made for the | › Presence of Bi, Pb, Zn, S, F and U has been assessed as |
|
| content of deleterious | they can impact on Concentrate quality or recovery. | |
| elements. | Where levels of penalty elements (Bi, F and U) are likely |
|
| The derivation of assumptions | to incur penalties, these have been accounted for in the | |
made of metal or commodity |
financial model. | |
price(s), for the principal |
› Costs are documented in the 2024 FSU. |
|
| minerals and co- products. | ||
| The source of exchange rates | ||
used in the study. |
||
| Derivation of transportation | ||
charges. |
||
| The basis for forecasting or | ||
source of treatment and |
||
| refining charges, penalties | ||
for failure to meet |
||
| specification, etc. | ||
| The allowances made for | ||
| royalties payable, both | ||
Government and private. |
||
| Revenue factors | The derivation of, or | › Commodity prices are taken from recent reputable |
| assumptions made regarding | studies and consensus pricing (Bloomberg – 9th October | |
revenue factors including |
2024). |
|
| head grade, metal or | › Copper Price US$4.58/lb, Gold US$2,400/Oz, Silver |
|
| commodity price(s) | US$30.00/Oz and an Exchange Rate of 0.70 $US/AU$ |
|
| exchange rates, | was used in contribution tests. |
|
transportation and treatment |
||
charges, penalties, net |
||
smelter returns, etc. |
||
| The derivation of assumptions | ||
made of metal or commodity |
||
price(s), for the principal |
||
metals, minerals and co- |
||
| products. | ||
| Market | The demand, supply and stock | › Analysts reports and price forecasts from Goodman |
| assessment | situation for the particular |
Sachs and others have indicated that Copper demand |
| commodity, consumption | will remain relatively strong. There appears to be | |
trends and factors likely to |
potential constraints on supply so prices should remain |
|
affect supply and demand |
stable or even increase over the medium to long term. |
|
| into the future. | ||
| A customer and competitor | ||
analysis along with the |
||
identification of likely market |
||
windows for the product. |
||
| Price and volume forecasts and | ||
| the basis for these forecasts. | ||
| For industrial minerals the | ||
| customer specification, | ||
testing and acceptance |
||
requirements prior to a |
||
supply contract. |
KGL Resources Limited 2024 Ore Reserve Statement
xenith.com.au
132
==> picture [195 x 147] intentionally omitted <==
| Criteria | JORC Code explanation | Section 4 Commentary |
|---|---|---|
| Economic | The inputs to the economic | › Sensitivity to changes in exchange rate, commodity |
| analysis to produce the net | prices, Opex and Capex has been examined. | |
| present value (NPV) in the | › The project is sensitive to copper price changes (as |
|
| study, the source and | expected) and to a lesser extent, Opex. |
|
confidence of these |
||
| › Changes in other commodity prices (Au and Ag) do not |
||
| economic inputs including | ||
have much impact as they are minor compared to the |
||
estimated inflation, discount |
||
value generated by Cu. |
||
| rate, etc. | ||
| › NPV variations are indicated in the 2024 FSU and follow |
||
| NPV ranges and sensitivity to | ||
| the KGL financial model outcomes. | ||
variations in the significant |
||
assumptions and inputs. |
||
| Social | The status of agreements with | › There are ongoing consultations with local landowners |
| key stakeholders and | and relationships appear sound. | |
| matters leading to social | › Discussion with NT authorities are on a sound footing. |
|
licence to operate. |
||
| › Status of agreements: An ILUA (between the Central |
||
Land Council and Jervois Operations) has been |
||
formalised and registered with the National Native Title |
||
Tribunal since 2017. |
||
| Other | To the extent relevant, the | › No issues are apparent with any of the Leases or |
| impact of the following on | permits required. | |
| the Project and/or on the | › An offtake agreement has been signed with Glencore |
|
| estimation and classification | and the relevant costs, charges and conditions have |
|
| of the Ore Reserves: | been appropriately applied in the financial model. |
|
| Any identified material naturally | › All approvals are in place in line with completion of the |
|
| occurring risks. | FS and progression to the Execution Phase for the |
|
| The status of material legal | Project. |
|
| agreements and marketing | › The NT Minister for Mining and Industry granted |
|
| arrangements. | Authorisation 1061-01 for the approval of the Project |
|
| The status of governmental | and associated Mining Management Plan (MMP) in |
|
| agreements and approvals | January 2021. |
|
critical to the viability of the |
||
Project, such as mineral |
||
tenement status, and |
||
| government and statutory | ||
approvals. There must be |
||
| reasonable grounds to | ||
expect that all necessary |
||
Government approvals will |
||
be received within the |
||
| timeframes anticipated in | ||
the Pre-Feasibility or |
||
Feasibility study. Highlight |
||
and discuss the materiality |
||
of any unresolved matter |
||
that is dependent on a third |
||
party on which extraction of |
||
the Reserve is contingent. |
||
| Classification | The basis for the classification | › Bellbird and Reward open pits have Proven and Probable |
| of the Ore Reserves into | Reserves (with ~60% being Proven). All other Reserves | |
| varying confidence | are classified as Probable Reserves only. The Probable |
|
categories. |
reserve for the Marshall Underground includes a small |
|
| quantity of Measured Resources. |
KGL Resources Limited 2024 Ore Reserve Statement
xenith.com.au
133
==> picture [195 x 147] intentionally omitted <==
| Criteria | JORC Code explanation | Section 4 Commentary |
|---|---|---|
| Whether the result appropriately | › This is considered satisfactory for the FS stage of the |
|
reflects the Competent |
project with the first 3 years of mining dominated by |
|
Person’s view of the deposit. |
Measured material and the following 4 years mostly |
|
| The proportion of Probable Ore | mining Indicated material. The first 5 years of operation | |
Reserves that have been |
are based on ~93% of mill feed being Proven and | |
| derived from Measured | Probable ore reserves. | |
| Mineral Resources (if any). | › It is unlikely that Measured Resources will be declared |
|
| for the underground mines until stope definition drilling | ||
is carried out. This may be only one to three months |
||
ahead of stoping operations. |
||
| Audits or reviews | The results of any audits or | › The 2024 Ore Reserve statement has been audited for |
| reviews of Ore Reserve | veracity by Mr Mark Perquin who is a full-time employee | |
| estimates. | of Xenith Consulting and a member of the AusIMM and |
|
| is in agreement with the assumptions used and the | ||
resultant Ore Reserve Estimate included in this report. |
||
| Discussion of | Where appropriate a statement | › The FS study estimates accuracy to be within +/-10- |
| relative | of the relative accuracy and |
15%. |
| accuracy/ | confidence level in the Ore | › The level of confidence associated with the 2024 Ore |
| confidence | Reserve estimate using an | Reserve statement is high given the cost basis has been |
| approach or procedure | determined from a Feasibility Level study into the |
|
| deemed appropriate by the | Jervois Project. |
|
| Competent Person. For | ||
| › The resource block models from which the Ore Reserve |
||
example, the application of |
||
| has been derived was based on a geostatistical | ||
statistical or geostatistical |
||
estimation completed by Mr Ian Taylor of Mineral |
||
procedures to quantify the |
||
Associates. Within the Ore Reserve estimation process |
||
relative accuracy of the |
||
the effects of included dilution have been accounted for |
||
Reserve within stated |
||
| to produce an anticipated selective mining unit grade. | ||
| confidence limits, or, if such | ||
an approach is not deemed |
› Modifying factors that could potentially impact the Ore |
|
appropriate, a qualitative |
Reserve estimate include: | |
| discussion of the factors | ▪ Mining loss & dilution |
|
| which could affect the | ▪ Geotechnical issues associated with pit wall and |
|
| relative accuracy and | ramp stability. |
|
| confidence of the estimate. | ▪ Geotechnical issues associated with ground |
|
| The statement should specify | stability, stope stability and pillar stability. |
|
| whether it relates to global | ▪ Metallurgical recoveries. |
|
| or local estimates, and, if | › Presence and levels of deleterious elements within the |
|
| local, state the relevant | ||
| transported concentrate. | ||
| tonnages, which should be | ||
relevant to technical and |
||
| economic evaluation. | ||
| Documentation should | ||
| include assumptions made | ||
and the procedures used. |
||
| Accuracy and confidence | ||
discussions should extend to |
||
| specific discussions of any | ||
applied Modifying Factors |
||
that may have a material |
||
impact on Ore Reserve |
||
viability, or for which there |
||
are remaining areas of |
||
uncertainty at the current |
||
study stage. |
KGL Resources Limited 2024 Ore Reserve Statement
xenith.com.au
134
==> picture [195 x 147] intentionally omitted <==
| Criteria | JORC Code explanation | Section 4 Commentary |
|---|---|---|
| It is recognised that this may | ||
not be possible or |
||
appropriate in all |
||
circumstances. These |
||
| statements of relative | ||
| accuracy and confidence of | ||
the estimate should be |
||
| compared with production | ||
data, where available. |
Note: Regarding Section 4, criteria listed in Section 1, and where relevant in Section 2 and 3, also apply to this section.
KGL Resources Limited 2024 Ore Reserve Statement
xenith.com.au
135
==> picture [596 x 483] intentionally omitted <==
Appendix B 2B Jervois Project Geology Geological Interpretation
KGL Resources Limited 2024 Ore Reserve Statement
xenith.com.au
136
==> picture [194 x 147] intentionally omitted <==
Figure C.1 – Jervois Project Geology Interpretation
==> picture [599 x 885] intentionally omitted <==
KGL Resources Limited 2024 Ore Reserve Statement
xenith.com.au
137
==> picture [128 x 31] intentionally omitted <==
==> picture [125 x 93] intentionally omitted <==
Brisbane Office Level 31/10 Eagle Street Brisbane City QLD 4000 P +61 7 3835 3900
xenith.com.au
KGL Resources Limited 2024 Ore Reserve Statement
xenith.com.au
1