J. Kumar Infraprojects Limited Capital/Financing Update 2023

Aug 1, 2023

61720_rns_2023-08-01_7dcc40f9-d698-453f-9312-5d548bb7658a.pdf

Capital/Financing Update

Open in viewer

Opens in your device viewer

==> picture [68 x 59] intentionally omitted <==

J. KUMAR INFRAPROJECTS LIMITED Regd Off: J. Kumar House, CTS No. 448, 448/1, 449, Subhash Road, Vile Parle (East), Mumbai 400 057, Maharashtra, India

Phone: +91 22 67743555. Fax: +91 22 26730814, Email: [email protected],

[email protected]

Website: www.jkumar.com , CIN: L74210MH1999PLC122886

August 01, 2023

To,

The General Manager The Listing Department Department of Corporate Services National Stock Exchange of India Ltd BSE Ltd Exchange Plaza, Plot No. C/1, G- Block Mumbai Samachar Marg Bandra- Kurla Complex, Bandra East Mumbai - 400 001 Mumbai - 400 051

Scrip Symbol/Code: JKIL/532940 and ISIN: INE576I01022

Sub: Disclosure under Regulation 30 of SEBI (Listing Obligations and Disclosure Requirements) Regulations, 2015 and SEBI Circular No: CIR/CFD/CMD/4/2015 dated September 09, 2015

  • Ref: Receipt of 04 (Four) ‘Letter of Acceptance’ from M/s. National Highway Authority (NHAI) of India.

Dear Sir,

We are pleased to inform you that M/s. J. Kumar Infraprojects Limited (the Company) is in receipt of 04 (four) Letter of Acceptance (LOA) dated July 31, 2023, from M/s. National Highway Authority of India, out of which 02 (two) LOA is received in the name of the Company (sole bidder) and 02 (two) LOA is received in the name of M/s. J. KUMAR-AZVIRT (JV), where the share of the Company is 90% of the total contract cost.

Project Name and
Max. cumulative
award value (INR
*inCr.) **
Mode Duration /
Validity of Rate
Contract
Commencement
of the work
Construction of New Double Tier 4-
lane
Elevated
Corridor
from
Chennai Port to Maduravoyal in
Chennai District from Km -0+342 to
Km20+593on EPC mode under
Bharatmala Pariyojana in the State
of Tamil Nadu Package 1 (Km -
0+342 to Km 4+604
M/s.
J.
KUMAR-
AZVIRT (JV)
Rs. 915 Cr, whereas
the share of JKIL is
90% amounting to
Rs. 823.50 Cr.
EPC 30 months July 31, 2023
Construction of New Double Tier 4-
lane
Elevated
Corridor
from
Chennai Port to Maduravoyal in
Chennai District from Km -0+342 to
Km20+593on EPC mode under
Bharatmala Pariyojana in the State
of Tamil Nadu Package- II (Km
4+604toKm9+700).
M/s.
J.
KUMAR
INFRAPROJECTS
LTD
Rs. 1,015 Cr
EPC 30 months July 31, 2023

==> picture [68 x 59] intentionally omitted <==

J. KUMAR INFRAPROJECTS LIMITED

Regd Off: J. Kumar House, CTS No. 448, 448/1, 449, Subhash Road, Vile Parle (East), Mumbai 400 057, Maharashtra, India

Phone: +91 22 67743555. Fax: +91 22 26730814, Email: [email protected],

[email protected]

Website: www.jkumar.com , CIN: L74210MH1999PLC122886

Construction of New Double Tier 4-
lane
Elevated
Corridor
from
Chennai Port to Maduravoyal in
Chennai District from Km -0+342 to
Km20+593on EPC mode under
Bharatmala Pariyojana in the State
of Tamil Nadu - Package- III (Km
9+700 to Km 14+185)
M/s.
J.
KUMAR
INFRAPROJECTS
LTD
Rs. 865 Cr
EPC 30 months July 31, 2023
Construction of New Double Tier 4-
lane
Elevated
Corridor
from
Chennai Port to Maduravoyal in
Chennai District from Km -0+342 to
Km20+593 onEPC mode under
Bharatmala Pariyojana in the State
of Tamil NaduPackage 4 (Km
14+185 to Km 20+593).
M/s.
J.
KUMAR-
AZVIRT (JV)
Rs. 775 Cr,whereas
the share of JKIL is
90% amounting to
Rs. 697.50 Cr
EPC 30 months July 31, 2023

*exclusive of Goods and Service Tax

The details for 04 (four) LOA as received from NHAI to the Company and details pursuant to SEBI Circular No: CIR/CFD/CMD/4/2015 dated September 09, 2015 is mentioned in Annexure A, B, C and D respectively.

We request you to take this on record.

for J. Kumar Infraprojects Limited

POORNIMA Digitally signed by POORNIMA CHINTAKINDI CHINTAKINDI Date: 2023.08.01 14:36:24 +05'30' Poornima Company Secretary

==> picture [68 x 59] intentionally omitted <==

J. KUMAR INFRAPROJECTS LIMITED

Regd Off: J. Kumar House, CTS No. 448, 448/1, 449, Subhash Road, Vile Parle (East), Mumbai 400 057, Maharashtra, India

Phone: +91 22 67743555. Fax: +91 22 26730814, Email: [email protected],

[email protected]

Website: www.jkumar.com , CIN: L74210MH1999PLC122886

Annexure - A

Sr No. Particulars Details
1 Significant terms and conditions of the Order /
Contract
NHAI has issued Letter of Acceptance to J. KUMAR-
AZVIRT (JV) for Construction of New Double Tier 4-lane
Elevated Corridor from Chennai Port to Maduravoyal in
Chennai District from Km -0+342 to Km20+593on EPC
mode under Bharatmala Pariyojana in the State of Tamil
Nadu Package 1 (Km -0+342 to Km 4+604. Awarded Cost
Rs. 915 Cr (Excl GST)whereas the share of JKIL is 90%
amounting to Rs. 823.50 Cr.,TimePeriodis 30months
2 Whether order(s) / contract(s) have been
awarded by domestic/ international entity
Domestic
3 Nature of Order / Contracts Service
4 Whether Domestic /International Domestic
5 Time Period by which the order/s / contract/s
is to be executed
30 months
6 Broad consideration or size of the
order(s)/contract(s);
Rs. 915 Cr, whereas the share of JKIL is 90% amounting
to Rs. 823.50 Cr.
7 Whether the promoter/ promoter group/group
companies have any interest in the entity that
awarded the order(s)/contract(s)?
Ifyes,nature of interestland details thereof;
NA
8 Whether the order(s)/contract(s) would fall
within related party transactions?
If yes, whether the same is done at “arm’s
length”.
NA

POORNIMA CHINTAKINDI

Digitally signed by POORNIMA CHINTAKINDI Date: 2023.08.01 14:36:57 +05'30'

==> picture [68 x 59] intentionally omitted <==

J. KUMAR INFRAPROJECTS LIMITED Regd Off: J. Kumar House, CTS No. 448, 448/1, 449, Subhash Road, Vile Parle (East), Mumbai 400 057, Maharashtra, India

Phone: +91 22 67743555. Fax: +91 22 26730814, Email: [email protected],

[email protected]

Website: www.jkumar.com , CIN: L74210MH1999PLC122886

Annexure – B

Sr No. Particulars Details
1 Significant terms and conditions of the Order /
Contract
NHAI has issued Letter of Acceptance to the Company
for the Construction of New Double Tier 4 - lane
Elevated Corridor from Chennai Port to Maduravoyal
in Chennai District from Km -0+342 to Km20+593on
EPC mode under Bharatmala Pariyojana in the State of
Tamil Nadu Package- II (Km 4+604 to Km 9+700).
Awarded Cost Rs. 1015 Cr (Excl GST), Time Period
is 30 months
2 Whether order(s) / contract(s) have been awarded
by domestic/ international entity
Domestic
3 Nature of Order / Contracts Service
4 Whether Domestic /International Domestic
5 Time Period by which the order/s / contract/s is to
be executed
3 Years
6 Broad consideration or size of the
order(s)/contract(s);
Rs. 1015 Cr
7 Whether the promoter/ promoter group/group
companies have any interest in the entity that
awarded the order(s)/contract(s)?
If yes, nature of interest land details thereof;
NA
8 Whether the order(s)/contract(s) would fall within
related party transactions?
Ifyes, whetherthe sameis done at“arm’slength”.
NA

POORNIMA Digitally signed by POORNIMA CHINTAKINDI CHINTAKINDI Date: 2023.08.01 14:37:11 +05'30'

==> picture [68 x 59] intentionally omitted <==

J. KUMAR INFRAPROJECTS LIMITED Regd Off: J. Kumar House, CTS No. 448, 448/1, 449, Subhash Road, Vile Parle (East), Mumbai 400 057, Maharashtra, India

Phone: +91 22 67743555. Fax: +91 22 26730814, Email: [email protected],

[email protected]

Website: www.jkumar.com , CIN: L74210MH1999PLC122886

Annexure – C Annexure – C
Sr No. Particulars Details
1 Significant terms and conditions of the Order /
Contract
NHAI has issued Letter of Acceptance to the
Company for the Construction of New Double Tier
4-lane Elevated Corridor from Chennai Port to
Maduravoyal in Chennai District from Km -0+342
to Km20+593on EPC mode under Bharatmala
Pariyojana in the State of Tamil Nadu_- Package-
III (Km 9+700 to Km 14+185) Awarded Cost Rs.
865 Cr (Excl GST), Time Period is 30 months
2 Whether order(s) / contract(s) have been awarded
by domestic/ international entity
Domestic
3 Nature of Order / Contracts Service
4 Whether Domestic / International Domestic
5 Time Period by which the order/s / contract/s is to
be executed
30 months
6 Broad
consideration
or
size
of
the
order(s)/contract(s);
Rs. 865 Cr
7 Whether the promoter/ promoter group/group
companies have any interest in the entity that
awarded the order(s)/contract(s)?
If yes, nature of interest land details thereof;
NA
8 Whether the order(s)/contract(s) would fall within
related party transactions?
If yes, whether the same is done at“arm’s length”.
NA

POORNIMA CHINTAKINDI

Digitally signed by POORNIMA CHINTAKINDI Date: 2023.08.01 14:37:25 +05'30'

==> picture [68 x 59] intentionally omitted <==

J. KUMAR INFRAPROJECTS LIMITED Regd Off: J. Kumar House, CTS No. 448, 448/1, 449, Subhash Road, Vile Parle (East), Mumbai 400 057, Maharashtra, India

Phone: +91 22 67743555. Fax: +91 22 26730814, Email: [email protected], [email protected]

Website: www.jkumar.com , CIN: L74210MH1999PLC122886

Annexure- D

Sr
No.
Particulars Details
1 Significant terms and conditions of the
Order / Contract
NHAI has issued Letter of Acceptance to J. KUMAR-
AZVIRT (JV) for Construction of New Double Tier 4
- lane Elevated Corridor from Chennai Port to
Maduravoyal in Chennai District from Km -0+342 to
Km20+593 onEPC mode under Bharatmala
Pariyojana in the State of Tamil NaduPackage 4 (Km
14+185 to Km 20+593).Awarded Cost Rs. 775 Cr
(Excl GST),whereas the share of JKIL is 90%
amounting to Rs. 697.50 Crand the time Period is 30
months
2 Whether order(s) / contract(s) have been
awarded by domestic/ international
entity
Domestic
3 Nature of Order / Contracts Service
4 Whether Domestic / International Domestic
5 Time Period by which the order/s /
contract/s is to be executed
30 months
6 Broad consideration or size of the
order(s)/contract(s);
Rs. 775 Cr,whereas the share of JKIL is 90%
amounting to Rs. 697.50 Cr
7 Whether the promoter/ promoter
group/group companies have any
interest in the entity that awarded the
order(s)/contract(s)?
If yes, nature of interest land details
thereof;
NA
8 Whether the order(s)/contract(s) would
fall within related party transactions?
If yes, whether the same is done at
“arm’s length”.
NA