IRB Infrastructure Developers Limited Capital/Financing Update 2020

Jul 29, 2020

62323_rns_2020-07-29_1ea7b1f8-ccf7-495b-96ce-b9a0fe321ade.pdf

Capital/Financing Update

Open in viewer

Opens in your device viewer

July 29, 2020

Corporate Relationship Department, National Stock Exchange of India Limited The Bombay Stock Exchange Ltd Exchange Plaza, BKC Complex, Bandra (East) Dalal Street, Mumbai - 400 023 Mumbai – 400 051

Dear Sir,

Re: Update

We are pleased to inform you that the Company has emerged as a preferred bidder for the following Hybrid Annuity Project. Key highlights of the Project are as under:

Project NHAI
Bid
Project
Cost
(Rs. In
Crores)
Compan
y’s Bid
Project
Cost
(Rs. In
Crores)
1st
Year
O&M
quote
(Rs.
In
Crore)
Company’s
Bid Price
(NPV
of
Company’s
Bid
Project
Cost & O&M
Cost over the
Concession
Period
(Rs. In Crores)
Construction
and
Operation
Period
Length
(Km)
Construction of Eight
lane access controlled
Expressway from Km
190.000 to Km 217.500
of Vadodara Mumbai
Expressway (Gandeva to
Ena Section) in the State
of Gujarat on Hybrid
Annuity Mode under
Bharatmala Pariyojana
(Phase I-PackageVII)
1241.79 1,755 8.10 1723.97 730 days
Construction
Period; 15
years
Operation
Period
27.50

With addition of this Project, the Company’s construction orderbook stands to Rs. 13,755 Crore to be executed in 2 years.

For IRB INFRASTRUCTURE DEVELOPERS LIMITED

MEHULKUMA Digitally signed by MEHULKUMAR NATWARLAL PATEL DN: c=IN, o=Personal, cn=MEHULKUMAR NATWARLAL PATEL, serialNumber=4a1816113b59302c922bb55f82b11 R NATWARLAL efd9325486d58d16564a6d1458dd0a6a0fe, postalCode=400607, 2.5.4.20=94a78f064dab4ff39b7861edcf64efc24591 PATEL 00e5464ea6f9ea45f7ffdd0e48dc, st=Maharashtra Date: 2020.07.29 14:04:45 +05'30'

Mehul Patel Company Secretary

==> picture [98 x 43] intentionally omitted <==

Media Release:

IRB Infra emerges as a preferred bidder for Gandeva – Ena Eight Lane Hybrid Annuity (HAM) project in Gujarat

  • Second HAM project for the Company

  • Project involves construction of eight lanes on 27.500 Kms stretch as part of Vadodara – Mumbai Expressway

  • Project cost is Rs. 1,755 Crores

Mumbai, July 29, 2020: IRB Infrastructure Developers Ltd (IRB), India’s leading and the largest highways infrastructure developers has emerged as a preferred bidder for construction of eight lanes of Vadodara – Mumbai Expressway in Gujarat, on the Gandeva – Ena stretch having length 27.500 Kms with the project cost of Rs.1,755 Crores.

Commenting on the development, Mr. Virendra D. Mhaiskar, Chairman & Managing Director, IRB Infrastructure Developers Ltd. said, “We are happy to see the Company being awarded another section of prestigious Vadodara – Mumbai Expressway in Gujarat. Winning this project once again validates our domain expertise, rich experience and execution capabilities demonstrated over last two decades.”

Key highlights of the Projects are as under:

  • The subject project (Package-VII) is part of India’s ambitious ‘Bharatmala Pariyojana’ of the NHAI under Phase-I.

  • It is a green-field project of eight laning of Gandeva – Ena stretch of 27.500 Kms on upcoming Vadodara – Mumbai Expressway.

  • The concession will comprise 730 days for construction and 15 years Operations & Maintenance rights thereafter

  • Upon award of this project, Company’s Order Book will stand at Rs. 13,755 Crores

To recollect, the Company is also constructing another stretch on this prestigious Expressway project between Padra and Vadodara having length of 23.740 Kms with cost outlay of Rs.2,043 Crores.

About IRB Infrastructure Developers Ltd:

1

IRB Infrastructure Developers Ltd (IRB) is the largest private roads and highways infrastructure developer in India, with an asset base of over Rs. 45,000 Crs. across the parent company and two InvITs.

The Company has strong track record of constructing over 12,300 lane Kms pan India in 2 decades and has an ability to construct over 500 Kms in a year. It has approx. 20% share in India’s prestigious Golden Quadrilateral project, which is the largest by any private infrastructure developer in India.

IRB Group’s portfolio comprises of 21 projects including 19 BOT, 1 TOT and 1 HAM projects. BOT segment includes 9 projects under Private InvIT with O & M contracts; 3 projects under Tolling & 7 projects under O & M contracts as a Project Manager for IRB InvIT.

For further details, please contact: