20 March 2023

MAKUUTU STAGE 1 DFS CONFIRMS TECHNICAL AND FINANCIAL VIABILITY FOR SUSTAINABLE, LONG-LIFE SUPPLY OF MAGNET AND HEAVY RARE EARTHS, MAIDEN ORE RESERVE ESTIMATE

STAGE 1 KEY DEFINITIVE FEASIBILITY STUDY (DFS) HIGHLIGHTS

  • The Mining Licence Application (MLA) focuses on the Stage 1 DFS and provides for a 35-Year mine life based on the Indicated Mineral Resource over Retention Licence 1693 (Application TN03834);

  • Stage 1 DFS delivers an EBITDA of A$2.29 billion (US$1.60 billion[1] ), Post Tax Free Cash Flow total ~ A$1.46 billion (US$1.02 billion), Net Present Value (NPV8) (Pre-tax) of A$580 million (US$406 million) and an Internal Rate of Return (IRR) of 32.7%;

  • Stage 1 production of a value-added product, mixed rare earth carbonate (MREC) (including Scandium), via a modular heap desorption processing plant, amounts to a total Capital Expenditure (CAPEX) of US$120.8 million;

  • Stage 1 plant capacity is 5.0 million tonne per annum (Mtpa) Run of Mine (ROM) throughput;

  • Stage 1 TREO production of 40,090 tonnes (t) REO equivalent product, with 71% magnet plus heavy REO content;

  • Stage 1 Rare Earth Oxide (REO) anticipated production capacity is ~ 1,300 tpa REO over first 10 years, averaging ~1,160 tpa over 35-years of production;

  • Maiden Ore Reserve for the Makuutu Stage 1 over RL 1693 of 172.9 Mt at 848 ppm TREO, or 584 ppm TREO – CeO2, and 30 ppm Sc2O3;

  • Uniquely positioned to be a long-term sustainable magnet and heavy REO producer, with first MREC production targeted for Q4 2024; and

  • Further staged development and expansion options will consider the total mineral resource at Makuutu.

Strong Financial Metrics

  • Stage 1 Pretax NPV8 of ~US$406 million (~A$580 million);

  • Stage 1 Posttax NPV8 of ~US$278 million (~A$397 million);

  • 1 USD to AUD FX = 0.70

Ionic Rare Earths Limited, Level 1, 34 Colin Street, West Perth WA 6005 Australia T+61 3 9776 3434 E [email protected]

  • Stage 1 Post-tax IRR of ~32.7%;

  • Stage 1 Post-tax capital payback of ~3 years from first MREC production;

  • Stage 1 Net Revenue totalling ~US$3.98 billion (~A$5.69 billion);

  • Stage 1 Revenue forecast of ~US$92/kg REO equivalent produced (excluding Sc2O3), payable;

  • Stage 1 EBITDA totalling ~US$1.60 billion (~A$2.29 billion); and

  • Post Tax Free Cash Flow totalling ~ US$1.02 billion (~A$1.46 billion).

Physical Parameters

  • Stage 1, over MLA TN03834, provides an initial 35-year Probable Ore Reserve Estimate of 172.9 Mt @ 848 ppm Total Rare Earths Oxide (TREO) for 146,654 of contained TREO;

  • Stage 1 strip ratio of 0.57; and

  • Scandium Oxide by-product credit (~511 t Sc2O3) is included as Base Case.

Capital and Operating Costs

  • Pre-production CAPEX (including 10% contingency) of ~US$120.8 million, including mining fleet;

  • All In Sustaining Cost (AISC) for the operation is ~US$12.40/t ROM feed;

  • AISC for the operation is ~US$53/kg REO equivalent produced;

  • AISC for the operation is ~US$46/kg REO equivalent produced (including Sc2O3 by-product credit); and

  • Power for the Project is to be delivered from low-cost hydroelectric power accessible from 132 kV power transmission corridor running immediately through the Project tenements.

The Board of Ionic Rare Earths Limited (“IonicRE” or “The Company”) (ASX: IXR) is pleased to advise the results of the Definitive Feasibility Study (DFS or Study) for the Stage 1 development of the Makuutu Rare Earths Project (“Makuutu” or “the Project”) which has been conducted and signed off by a series of independent competent persons. Much of the hydrometallurgical flowsheet for the Project has been developed by expert competent persons specifically for Makuutu, being a large near surface ionic adsorption clay deposit. This bespoke Intellectual Property (IP) will remain a valuable asset in optimising financial returns from Makuutu as further activity, including a Demonstration Plant, progresses to unlock further value through providing scale up data to adopt more informed information on grade control, material handling and heap desorption conditions including heap stack height.

Makuutu is being developed by Rwenzori Rare Metals Limited (RRM), a Ugandan private company which owns 100% of the Makuutu Rare Earths Project. IonicRE is a 51% owner of RRM and moving to 60% with the completion of the DFS. IonicRE also maintains a first right over the remaining 40% of the Project.

Ionic Rare Earths Limited, Level 1, 34 Colin Street, West Perth WA 6005 Australia T+61 3 9776 3434 E [email protected]

The Makuutu Stage 1 Study has been prepared to support the application for the granting of the Mining Licence over RL 1693, via Mining Licence Application (MLA) TN03834 which RRM initiated in September 2022, and as such covered only the central area of the greater Makuutu resource area. It is anticipated that following the DFS, the Mining Licence over RL 1693 will be granted in Q2 2023. A further staged development approach, including additional MLAs over the other five (5) tenements at Makuutu will progressively be considered which will cover the total Mineral Resource at Makuutu.

IonicRE’s Managing Director Mr Tim Harrison stated;

“The outcome of this study, which focuses solely on the central Makuutu zone, provides the required inputs for Rwenzori Rare Metals Limited to now finalise the Mining Licence Application for RL 1693. These Stage 1 results support what we think is a unique, geopolitically strategic asset to supply magnet and heavy rare earths into western supply chains. Evidence currently shows that countries are motivated to secure sustainable, traceable supplies of these critical raw materials to support their domestic manufacturing ambitions and to support both the energy transition, and increasingly, military and defence requirements to provide sovereign capability and global security.

“Furthermore, this Stage 1 study provides a path to production at Makuutu, which has the potential for significant growth into the future through the conversion of the other tenements at Makuutu towards additional MLAs over the coming decade. The intent is to significantly increase production from the Stage 1 initial focus at Makuutu, and expand into the forecast increase in demand that will far exceed supply for the most readily sought after rare earths, being Dysprosium and Terbium. These rare earths, are critical for the production of the magnets required to drive electric vehicles, offshore wind turbines and support a number of specialised defence applications.

“Makuutu is now advancing towards a Final Investment Decision with the capability to provide more heavy rare earths per annum from our initial Stage 1 Project than existing western light rare earth hard rock mines in production today.

“The next phase of work at Makuutu, is to build the Demonstration Plant to further drive value by proving the potential to achieve high desorption heap stack heights to improve capital efficiency with a view to further increasing production capacity, whilst optimising desorption conditions to explore improved extractions and minimising the dissolution of impurities, to further optimise economics.”

Makuutu Rare Earth Project – Stage 1 Overview

Rwenzori Rare Metals Limited (RRM), a Uganda registered private limited company, is investigating the development of the Makuutu Rare Earths Project located 120 kilometres (km) east of Kampala, Uganda, illustrated in Figure 1. RRM owns 100% of the Makuutu Rare Earths Project.

This DFS has been completed in conjunction with RRM’s major shareholder, Ionic Rare Earths Limited (IonicRE) (51% of RRM moving to 60% upon approval of the DFS as per RRM earn in agreement announced 5 July 2019). IonicRE has collaborated with the other shareholders of RRM plus independent consultants to complete this DFS.

Ionic Rare Earths Limited, Level 1, 34 Colin Street, West Perth WA 6005 Australia T+61 3 9776 3434 E [email protected]

The Project has been explored since 2012. RRM, and shareholders have completed all exploration works on the Project, which includes Retention Licenses RL 1693, RL 00007, RL00234 and Exploration Licenses EL 00147, EL 00148 and EL 00257.

Since August 2019, IonicRE has funded exploration and project development activities which includes nearly 12,953 completed meters of core drilling across the three licenses, initial metallurgical variability and optimisation test work, mine planning and process design estimation.

This DFS, which focuses on the Makuutu central tenement, Retention Licence 1693, is the first of RRM’s six (6) tenements to progress to the MLA stage, driven by the timeline controlled under the Ugandan Mining Act to progress from Exploration Licence to Retention Licence, and ultimately to Mining Licence Application within an 11-year period.

==> picture [483 x 261] intentionally omitted <==

Figure 1: Makuutu Rare Earths Project location with major existing infrastructure.

The Stage 1 DFS contemplates a proposed open pit mining operation, and evaluation of an annualised mining rate of 5 Mtpa of mineralisation from the Project. Several scenarios were run to determine the optimal mine plan design. The revised Mineral Resource Estimate (MRE) in May 2022 was used as the basis for the preliminary mine plans and mining optimisation studies.

The economic analysis of the Makuutu Stage 1 development was completed by IonicRE, indicating the potential for an economic project, however several assumptions will require substantiation via additional work programs to be completed in the next phase of the Project.

The Stage 1 Project NPV, with Scandium production assumed, using a discount rate of 8%, was pretax, US$406 million, and post-tax US$278 million, and an IRR of 32.7%. The payback period was determined at three (3) years from first production.

Ionic Rare Earths Limited, Level 1, 34 Colin Street, West Perth WA 6005 Australia T+61 3 9776 3434 E [email protected]

The Makuutu Stage 1 development will also be a significant contributor to Uganda, with estimated gross royalty payments of US$199 million plus corporate tax contributions of US$438 million over the Stage 1 development of the Project, based upon only RL1693 at this stage.

All capital, operating and revenue inputs used in the DFS are on a US dollar basis.

A summary of the Makuutu Stage 1 DFS results are provided in Table 1. The financial modelling of the DFS has been carried out on a 100% ownership basis to determine Project value.

Table 1: Makuutu Stage 1 DFS Financial and Technical Summary.

Table 1: Makuutu Stage 1 DFS Financial and Technical Summary.
Parameter Unit DFS Results
Stage 1 Duration
Stage 1 Feed, dry
Stage 1 Waste, dry
Stage 1 StripRatio
Years
Mt
Mt
Mt
35
172.9
98.8
0.57
Stage 1 TREO Head Grade
Stage 1 TREO-CeO2Head Grade
Total REO Feed
Total REO Production
Average REO Production
ppm
ppm
Kt
Kt
t/a
848
584
146.7
40.1
1,156
Stage 1 Sc2O3Head Grade
Total Sc2O3Feed
Total Sc2O3Production
Annual Average Sc2O3Production
ppm
t
t
t/a
30
5,112
511
15
Recoveries – TREE-Ce
Yield – TREO-CeO2
MREC Payability
%
ppm
%
35%
208
70%
Total Stage 1 Revenue
REO Revenue, Stage 1
Sc2O3Revenue, Stage 1
REO Revenue (excl Sc2O3),per t Ore
REO Revenue(excl Sc2O3), per kgREO
USD, M
USD, M
USD, M
USD/t
USD/kg
3,984
3,707
277
21.44
91.64
Total Stage 1 OPEX
Mining OPEX
Processing OPEX
G&A OPEX
USD, M
USD, M
USD, M
USD,M
2,143
757
1,309
260
OPEX, annual average
OPEX, per t Ore (dry)
OPEX, per kg REO
OPEX, per kgREO(less Sc2O3credit)
USD, M
USD/t
USD/kg
USD/kg
61.24
12.40
52.99
46.13
Govt Royalties
Social Fund Package – CSR
USD, M
USD,M
199
40
CAPEX, upfront
CAPEX, sustaining
Tax
Total Free Cash Flow
EBITDA
USD, M
USD, M
USD, M
USD, M
USD,M
120.81
19.28
438
1,023
1,602
Pre-Tax NPV8(01-Jul-23)
Post-Tax NPV8(01-Jul-23)
IRR
Payback from First Production
USD, M
USD, M
%
Years
406
278
32.7%
3

Ionic Rare Earths Limited, Level 1, 34 Colin Street, West Perth WA 6005 Australia T+61 3 9776 3434 E [email protected]

The forecast REO production over the Stage 1 development, for a mine life of 35 years indicated a total of 40,448 tonnes of REO equivalent product, as a MREC, a value-added product, with approximately 71% magnet and heavy REO content within.

The average head grade over the first ten years is 928 ppm TREO (652 ppm TREO-CeO2) generating an average production of 1,303 tonnes per annum of REO equivalent MREC product. After that, given the reduction in TREO head grade from years 11 to 35, to 814 ppm TREO (554 ppm TREO-CeO2), the average REO production over the last 25 years of operation is 1,097 tonnes per annum.

RRM will continue to implement the highest levels of Environmental, Social and Corporate Governance (ESG) compliance and standards in developing and operating the Project. RRM aims to establish a long life, sustainable mining operation with a dominant Ugandan workforce composition that can ultimately be the template for successful mining projects within Uganda, and Eastern Africa.

Definitive Feasibility Study

The DFS report has been prepared by IonicRE based upon a review of project specific information including geological reports, maps, assessment files, retention and exploration licenses, technical papers and spreadsheets, publicly available reports and data generated by RRM and IonicRE over the past four (4) years.

IonicRE has coordinated a group of leading industry consultants during 2021 and 2022 to complete technical and commercial studies into the Project in support of the DFS, in addition to initiating environmental and social impact assessment studies.

Contributing consultants include:

  • Geological Management and Studies: Geoff Chapman, GJ Exploration Pty Ltd (Australia).

  • • Technical Field Services: Benzu Minerals Ltd (South Africa);

  • Environmental and Social Impact: Environmental Plus Pty Ltd (Australia), JBN Consults & Planners Ltd and Atacama Consultants Ltd (UG);

  • Metallurgical Testwork: ALS Metallurgy (Australia), Australian Nuclear Science and Technology Organisation (ANSTO) (Australia), Bureau Veritas Minerals (Australia), SGS Lakefield (Canada) and HydroGeoSense (USA);

  • Metallurgical Testwork: Harley Davies, Ultramet Ltd (Australia);

  • Metallurgical Simulation Modelling and Process Design: Dr Will Goodall, MinAssist Pty Ltd (Australia);

  • Mineral Resource Estimation: Daniel Saunders, Cube Consulting Pty Ltd (Australia);

  • Mine Planning: Lee White, Kalem Group Pty Ltd (Australia);

  • Mine Operating Estimation: ADT Africa, Kampala (Uganda);

  • Process Plant Design, Capital Estimation and Operations Estimation: Mincore Pty Ltd (Australia);

  • Membrane Technology Plant Design: Eco Technol (Pty) Ltd (Australia);

  • Financial Modelling: Lee Platek, Platek Analytics Pty Ltd (Australia); and

  • Rare Earth Marketing Study, Adamas Intelligence (Canada).

Ionic Rare Earths Limited, Level 1, 34 Colin Street, West Perth WA 6005 Australia T+61 3 9776 3434 E [email protected]

Project Design Philosophy

The Makuutu Rare Earths Project hosts an ionic adsorption clay hosted rare earth deposit. As a result, the weathered mineralisation can be processed using an ionic desorption process, akin to chemical ion exchange process.

Under the Project design, the near surface mineralisation, under approximately three (3) metres (m) of cover, is to be mined using free dig bulk mining methods, with a low strip ratio, to feed to a processing facility, which chemically washes the ore with a salt-based solution, using ammonium sulfate (NH2SO4), at mild acidic conditions, using sulfuric acid (H2SO4) at an approximate pH of 2, which extracts the rare earth elements into a value added intermediate chemical precipitate known as MREC. The MREC product produced is a high payability value product (~70%), free of radionuclides, suitable for export for further processing via solvent extraction refining to high purity oxides.

Post processing, the residue is washed to recover residual reagents and process liquors, and neutralised prior to reclamation, and redeposition in the mining pit voids prior to rehabilitation of the mined areas. Subsequent new organised agri-industry will be established to align with Uganda’s National Development Plan, NDP-III. As such there will be no tailings facility or permanent spoil heaps anywhere on the property.

The DFS considers only the initial RL 1693 for the purposes of the study, to support the MLA of the first of six (6) tenements that make up the greater Makuutu Project. It is envisaged that the Stage 1 development at Makuutu will be supported with further growth expected to be derived from other tenements at the Project which will progress to MLA with further exploration over the next decade. A full list of the tenements at Makuutu is provided in Table 2, showing that the MLA for RL 1693 was initiated in early September 2022. A map of the overall tenements and RL 1693 (MLA TN03834) is illustrated in Figure 2.

Table 2: Makutu Rare Earths Project Tenement Status and Details

Licence ID Licence Type Application
Date
Granted Date Expiry /
Renewal Date
Area (km2)
RL00007 Retention 12/12/2022 20/12/2022 26/11/2024 43.38
RL 1693 /
TN03834
Retention 01/09/2022 Pending Pending 43.78
RL00234 Retention 26/06/2021 06/07/2021 05/07/2024 47.03
EL00257 Exploration 15/07/2021 21/10/2021 20/10/2024 55.51
EL00147 Exploration 19/10/2020 28/12/2020 27/12/2023 60.30
EL00148 Exploration 21/10/2020 28/12/2020 27/12/2023 48.15

Highlighted row showing tenement supporting Stage 1 development for RL 1693 only, supporting the MLA application.

Ionic Rare Earths Limited, Level 1, 34 Colin Street, West Perth WA 6005 Australia T+61 3 9776 3434 E [email protected]

==> picture [483 x 266] intentionally omitted <==

Figure 2: Makuutu Project resource map showing resources and exploration target areas, and the Stage 1 Mining Licence Application TN03834, which is the focus of the Feasibility Study.

Mining modelling has indicated that dilution and mining losses will be at a minimum.

Heap desorption leach processing has been chosen for the extraction methodology of the deposit. This process type lends itself to low-cost, large-scale operations as they are relatively simple in nature and robust in performance.

As a result of these criteria, the scale of operation chosen is a five (5) Mtpa mining and processing facility.

The relatively large operational scale is intended to take advantage of the uniform geometry and grade distribution throughout the large orebody. Given the scale of the Project, material handling logistics underpin the operability of the mining and processing with a centralised large heap desorption leach facility being located within central proximity to ore mined from several satellite, concurrently operating pits. The management of in-situ and ambient water is a key element to achieving operational targets.

The contracting philosophy that will be adopted is in line with other African mining projects with a strong focus on localisation. The Company believes that local stakeholders must enjoy the first opportunity to benefit from local value creation and the employment of foreign or non-local persons or contractors will be kept to a minimum.

The development philosophy is underpinned by the large scale of the deposit and the fact that the processing option selected will enable additional processing modules to be added in time across the full 37-km-long mineralisation trend at Makuutu.

Ionic Rare Earths Limited, Level 1, 34 Colin Street, West Perth WA 6005 Australia T+61 3 9776 3434 E [email protected]

Mineral Resource Estimate

The local geology interpretation of the Makuutu area has been compiled by RRM using the country wide airborne radiometric and magnetic survey imaging, ground gravity survey data, geological field observations, pitting and drilling. The Makuutu deposit is interpreted to be an ion-adsorption claytype (IAC) rare earth element (REE) deposit similar to those in South China, Myanmar, Madagascar, Chile and Brazil. Ionic adsorption clay (IAC) REE mineralisation can be summarised as REEs that are mainly adsorbed onto the surfaces of clay minerals in the form of hydrated ions or hydroxyl-hydrated ions. These REE deposits are hosted within the regolith (laterite profile).

Three types of drilling have been conducted on the Project area. Initial drilling focused on open hole Rotary Air Blast (RAB) drilling with subsequent programs principally using diamond core drilling. Resource definition core drilling commenced in October 2019 initially on a 400-metre x 400-metre pattern over the Makuutu Central Zone (RL 1693) where previously RAB drilling identified the thickest and highest-grade clay hosted REE mineralisation. Since then, drilling has been completed across both the Makuutu Eastern Zone (RL00234) and Makuutu Western Zone (RL 00007).

Drilling completed by RRM since October 2019 has totalled 711 holes for 12,953m HQ triple tube (HQ3) sized vertical holes designed to provide high quality samples at an appropriate drill spacing to estimate a JORC compliant MRE, announced 3 May 2022, and for detailed metallurgical extraction test work.

Cube Consulting Pty Ltd (Cube) were engaged by RRM through IonicRE to provide a JORC 2012 Mineral Resource Estimate as outlined in Table 3. Figure 2 and Figure 3 illustrate the resource areas at Makuutu that support the Feasibility Study and the focus of the MLA over RL 1693. The MLA focused on the central Retention Licence (RL) 1693 and will provide the basis for initial mining at Makuutu. This area contains an Indicated Resource of 259 million tonnes at 740 ppm TREO (Table 2 and ASX: 3 May 2002), refer to Table 4. This is the basis for the Stage 1 DFS at Makuutu.

Table 3: Makuutu Rare Earth Project Resource Tabulation of REO Reporting Groups at 200ppm TREOCeO2 Cut-off Grade (ASX: 3 May 2022).

TREO-
Resource Tonnes TREO LREO HREO CREO Sc2O3
CeO2
Classification (millions) (ppm) (ppm) (ppm) (ppm) (ppm)
(ppm)
Indicated 404 670 450 500 170 230 30
Inferred 127 540 360 400 140 180 30
Total 532 640 430 480 160 220 30

Notes; Tonnes are dry tonnes rounded to the nearest 1.0Mt. All ppm rounded from original estimate to the nearest 10 ppm which may lead to differences in averages. TREO = Total Rare Earth Oxide

Ionic Rare Earths Limited, Level 1, 34 Colin Street, West Perth WA 6005 Australia T+61 3 9776 3434 E [email protected]

==> picture [483 x 262] intentionally omitted <==

Figure 3: Makuutu Project resource map showing RL 1693 Mineral Resource Estimate areas which supports the Mining Licence Application TN03834, along with other tenement resource areas estimated to date, and additional exploration tenements across the 37 km mineralisation trend.

Table 4: Mineral Resources by Area (ASX: 3 May 2022), RL 1693 Resource Areas shaded blue to comprise basis for Stage 1 DFS.

Classification Indicated Resource Indicated Resource Indicated Resource Inferred Resource Inferred Resource Inferred Resource Total Resource Total Resource Total Resource
Area Tonnes
(millions)
TREO
(ppm)
TREO-
CeO2
(ppm)
Tonnes
(millions)
TREO
(ppm)
TREO-
CeO2
(ppm)
Tonnes
(millions)
TREO
(ppm)
TREO-
CeO2
(ppm)
A 13 580 390 13 580 390
B 26 410 290 26 410 290
C 31 580 400 3 490 350 35 570 400
D 6 560 400 6 560 400
E 18 430 280 18 430 280
Central Zone 151 780 540 12 670 460 163 770 530
Central Zone East 59 750 490 12 650 430 72 730 480
F 18 630 420 7 590 400 25 620 410
G 9 750 500 5 710 450 14 730 480
H 6 800 550 7 680 480 13 740 510
I 129 540 350 19 530 350 148 540 350
Total Resource 404 670 450 127 540 360 532 640 430

Rounding has been applied to 1Mt and 10ppm which may influence averaging calculations. Highlighted rows providing Indicated Resource Estimate for RL 1693 only, supporting the MLA.

Ionic Rare Earths Limited, Level 1, 34 Colin Street, West Perth WA 6005 Australia T+61 3 9776 3434 E [email protected]

Maiden Ore Reserve Estimate

A Maiden Ore Reserve Estimate has also now been completed for the Makuutu Stage 1 Project across RL 1693, based on the Indicated Mineral Resource (based on a 200ppm TREO-CeO2 cut-off grade) tabled above. The Mineral Resources reported are inclusive of the Ore Reserves for the Stage 1 Project.

As shown in Table 5 below, total current Ore Reserves for the Makuutu Stage 1 over RL 1693 are 172.9 Mt at 848 ppm TREO, or 584 ppm TREO – CeO2, and 30 ppm Sc2O3.

Table 5: Maiden Makuutu Stage 1 Ore Reserve Estimate.

Classificati
on
Tonnage
(Mt)
TREO Grade
(ppm)
TREO-CeO2
Grade (ppm)
LREO
(ppm)
HREO
(ppm)
CREO
(ppm)
Sc2O3
(ppm)
Proven - - - - - - -
Probable 172.9 848 584 629 219 296 30
Total 172.9 848 584 629 219 296 30

Mining and Material Handling

After a review of several scenarios, a 5 Mtpa throughput represented the Base Case (defined below) and also the optimal case, based on return on investment. It is estimated that the development approach enabled the Company to place the product into western supply chains, with expected timing to receive the product from late 2024. Additionally, the staged development of the Project limits initial capital investment to enable the downstream supply chain, ex-China, to mature to take the additional product from Makuutu at higher anticipated REO pricing.

An opportunity to scale up production in 2.5 Mtpa modules has also been identified but does not form part of this economic assessment at this time given the lack of maturity in existing western rare earth supply chains, and the fact that expected downstream refining capacity is:

  1. Suitable for processing a basket product such as that from Makuutu, i.e. medium Yttrium (Y), high Europium (Eu); and

  2. Only expected to be operational by late 2024 at the earliest.

The mine plan was developed using only Indicated Resources into the mining and processing schedule. Over the first 35 years of mining and processing operations at Makuutu, a Mineral Resource inventory of 172.9 Mt is proposed to be mined and processed. This constitutes the maiden Ore Reserve Estimate at Makuutu.

Figure 4 illustrates the annual total mining rate that has been used in the Study, which has been smoothed to ensure the fleet requirements are best optimised.

For the Stage 1 scenario adopted for the DFS, the nominated production case resulted in a higher plant feed grade, at 928 ppm TREO (652 ppm TREO-CeO2), using a 500ppm TREO-CeO2 cut-off during the first 10 years of mining followed by a relaxation of the cut-off and also processing lower grade material stockpiled (Base Case). TREO head grade is also illustrated in Figure 4.

Ionic Rare Earths Limited, Level 1, 34 Colin Street, West Perth WA 6005 Australia T+61 3 9776 3434 E [email protected]

Stage 1 Mine Plan and Head Grade

==> picture [455 x 244] intentionally omitted <==

----- Start of picture text -----

14 1,200
12
1,000
10
800
8
600
6
400
4
200
2
0 0
ROM to Processing Ore to Stockpile Ore Reclaimed Waste Head Grade
ROM Head Grade (ppm TREO)
Annual Material Movement by Type (Mtpa)
2024 2026 2028 2030 2032 2034 2036 2038 2040 2042 2044 2046 2048 2050 2052 2054 2056 2058
----- End of picture text -----

Figure 4: Makuutu Stage 1 DFS annual material movement mine plan, by type, and ROM TREO Head Grade processed.

Mining costs were estimated based on the physical mining movements and estimated US$1.80/tonne (wet) mined for mining optimisations assuming mining equipment and personnel provided by a local Ugandan operator, allowances for operational/technical personnel and grade control drilling costs each year.

The pit inventory, limiting the orebody to that contained within RL1693, includes 172.9 Mt of ROM @ 848 ppm TREO over a 35-year mine-life. This includes 67.8 Mt of ROM for the first 10 years at 928 ppm (500 ppm TREO-CeO2 cut-off). The total pit tonnage mined over the LOM is approximately 272 Mt including 98.8 Mt of waste and mineralised rock material with a very low strip ratio (waste : ROM) of 0.57.

A specific processing cut-off grade of 500 ppm TREO-CeO2 cut-off was utilised for Base case pit scenario for the first 10 years, with the optimisations all run on a cash flow basis for Rare Earth Oxide equivalent revenue only. Beyond the initial 10 years a processing cut-off grade of 200ppm TREOCeO2 was applied. IonicRE completed numerous metallurgical studies on composite samples of mineralisation at Makuutu as previously announced to the ASX on 18 February 2020, 26 May 2020, and most recently 4 August 2020. These results together with indicative mining and processing costs and other cost inputs support the application of a marginal cut-off grade of 200 ppm TREO (excluding CeO2). This cut-off is comparable to peer projects with similar mineralisation types and processing assumptions.

Metallurgical factors were applied to the block model.

Revenue factors were applied to the block model at a 70% MREC payability factor.

Ionic Rare Earths Limited, Level 1, 34 Colin Street, West Perth WA 6005 Australia T+61 3 9776 3434 E [email protected]

Metallurgical Test Work and Processing by Heap Desorption

Metallurgical test work has been completed upon Makuutu samples dating back to 2014. Given the nature of the mineralisation, metallurgical recovery will have a substantive impact on project viability. A complete review of historical test work results coupled with a baseline variability program for Makuutu (2019), and subsequent optimisation test work in 2020 has indicated substantial potential for improved metallurgical extraction at Makuutu using a slightly more acidic desorption / leach arrangement.

Further metallurgical test work conducted in 2021 and 2022 to support the DFS, including extensive variability test work to better define the metallurgical extraction parameters and extent of weathering, was completed to apply across the mineralisation within RL 1693. The breadth of the variability and heap desorption columns tested included the following;

  • 527 variability interval desorption bottle rolls;

  • 88 variability desorption column composite bottle rolls;

  • Selection of targeted desorption bottle rolls and tests on validation composites completed at independent laboratories to validate results;

  • 22 variability composite desorption columns (3m);

  • 15 validation composite desorption columns (3m);

  • Scale up heap desorption columns including 1m, 2m, 3m, 4m and 5m columns (see Figure 5); and

  • Scale up columns at 6m underway at present.

The Stage 1 DFS assumes a dynamic heap desorption with a 3m stack height. Whilst data exists to suggest a stack height of 6m, or higher, is possible, the Project will look to validate this through the Demonstration Plant prior to adopting this as the Stage 1 Base Case. Agglomerates and 5m heap desorption column completed at ANSTO is shown in Figure 6.

Subsequent to the work defining metallurgical extraction parameters applied to desorb REE from the clay mineralisation, additional test work has been completed to quantify the downstream impacts, most notably the impact of more aggressive leach conditions at lower pH (higher acidity), resulting in excessive dissolution of impurity elements, notably aluminium (Al) and iron (Fe). As a result, pH conditions applied in the heap desorption was targeted at pH 2, reducing REE extractions, but importantly substantially reducing the dissolution of Al and Fe, and thereby reducing the reagent consumption required to precipitate out impurity elements to reach the target MREC composition (> 40% REE content).

Elevated Al presence in the desorption liquor also results in increased potential for REE precipitation losses in the impurity precipitation circuit. As a result of this, test work has defined that operating the heap desorption at pH 2 provides a fair trade off to maximise REE extraction while managing the impurity load reporting the pregnant leach solution (PLS).

The metallurgical test work consisting of bottle rolls, columns, plus nano-filtration (NF) and reverse osmosis (RO) testing, impurity precipitation, MREC precipitation and materials handling characterisation lead to the development of a Makuutu Project unique SysCAD® simulation model,

Ionic Rare Earths Limited, Level 1, 34 Colin Street, West Perth WA 6005 Australia T+61 3 9776 3434 E [email protected]

which has been used to define the overall metallurgical recoveries applied to the Project. Validation test work and procedures to verify the model outputs that were produced from the simulation model combined together to form the basis for the process design and the Process Design Criteria (PDC). The process design is represented in Figure 7.

==> picture [483 x 256] intentionally omitted <==

----- Start of picture text -----

45
40
35
30
25
20
15
10
5
0
0.0 0.2 0.4 0.6 0.8 1.0 1.2 1.4 1.6
Liquor output (m3/t)
C8 (1 m rpt) C2 (2 m) C7 (3 m) C12 (5 m)
TREE-Ce extraction (%)
----- End of picture text -----

Figure 5: Heap desorption column scale up from 1m to 5m completed on a composite tested from RL 1693.

==> picture [313 x 209] intentionally omitted <==

==> picture [168 x 209] intentionally omitted <==

Figure 6: Agglomerates, post-curing, on the left, and a 5m heap desorption column under irrigation at ANSTO.

Ionic Rare Earths Limited, Level 1, 34 Colin Street, West Perth WA 6005 Australia T+61 3 9776 3434 E [email protected]

==> picture [483 x 273] intentionally omitted <==

Figure 7: Makuutu Rare Earths Project Stage 1 DFS Process Flowsheet.

==> picture [483 x 301] intentionally omitted <==

Figure 8: 3D model representation of the Stage 1 development at Makuutu.

Ionic Rare Earths Limited, Level 1, 34 Colin Street, West Perth WA 6005 Australia T+61 3 9776 3434 E [email protected]

==> picture [483 x 178] intentionally omitted <==

Figure 9: Ore Surge and agglomeration to feed Heap Desorption pads.

==> picture [483 x 230] intentionally omitted <==

Figure 10: 3D model representation of the Heap Desorption pad stacking in the foreground, and precipitation circuit in the background.

Ionic Rare Earths Limited, Level 1, 34 Colin Street, West Perth WA 6005 Australia T+61 3 9776 3434 E [email protected]

==> picture [483 x 233] intentionally omitted <==

Figure 11: 3D model representation of the solution handling circuit, showing NF circuits in the foreground, and precipitation circuits and product handling in the background.

Based upon the results of the various test work programs, the overall recovery of ore to MREC product has been revised with a recovery trend provided in Figure 12. Also shown in Figure 12 is the total Stage 1 estimated production for each respective rare earth in oxide form.

==> picture [483 x 284] intentionally omitted <==

----- Start of picture text -----

Makuutu Stage 1 REOs Recovered (t)
12,000 60%
10,000 50%
8,000 40%
6,000 30%
4,000 20%
2,000 10%
- 0%
La2O3 CeO2 Pr6O11 Nd2O3 Sm2O3 Eu2O3 Gd2O3 Tb4O7 Dy2O3 Ho2O3 Er2O3 Tm2O3 Yb2O3 Lu2O3 Y2O3
Recovered (t) Recovery %
REE Recovery (%) to MREC Product
REO equivalent Product by Element (t)
----- End of picture text -----

Figure 12: Makuutu elemental recovery and Stage 1 production to MREC (as REO equivalent) estimates.

Ionic Rare Earths Limited, Level 1, 34 Colin Street, West Perth WA 6005 Australia T+61 3 9776 3434 E [email protected]

A further breakdown is provided in Figure 13 on a year by year basis over the proposed Stage 1 development, and a revised Makuutu MREC product basket provided in Figure 14.

Stage 1 Annual REO Production by REO

==> picture [457 x 244] intentionally omitted <==

----- Start of picture text -----

1,600
1,400
1,200
1,000
800
600
400
200
-
La2O3 CeO2 Pr6O11 Nd2O3 Sm2O3 Eu2O3 Gd2O3 Tb4O7
Dy2O3 Ho2O3 Er2O3 Tm2O3 Yb2O3 Lu2O3 Y2O3
Production by REO (t)
2023 2025 2027 2029 2031 2033 2035 2037 2039 2041 2043 2045 2047 2049 2051 2053 2055 2057 2059
----- End of picture text -----

Figure 13: Makuutu Stage 1 DFS Production plan by REO for Years 1 to 35.

Makuutu Stage 1 Product Basket, by composition

==> picture [338 x 251] intentionally omitted <==

----- Start of picture text -----

La2O3
Y2O3
17.8%
26.5%
Lu2O3
0.25%
CeO2
Yb2O3
11.3%
1.63%
Tm2O3
0.27%
Er2O3
2.23% Pr6O11
Ho2O3 5.0%
0.76%
Dy2O3
3.82%
Tb4O7
0.62% Gd2O3 Eu2O3 Sm2O3 Nd2O3
4.22% 0.75% 3.69% 21.2%
----- End of picture text -----

Figure 14: Makuutu Stage 1 REO product basket, excluding Sc2O3 (note rounding applied).

Ionic Rare Earths Limited, Level 1, 34 Colin Street, West Perth WA 6005 Australia T+61 3 9776 3434 E [email protected]

The updated Stage 1 basket has a 71% magnet plus heavy REO content, and breaking this down further;

  • Magnet REO fraction (Nd, Pr, Dy and Tb) of approximately 31%;

  • Additional magnetic fraction of approximately 9 % (Sm, Gd and Ho); and

  • Heavy REO fraction of approximately 45%.

Basis for Product Revenue Assumptions

Pricing has been calculated based upon the data reported by independent research and advisory services group, Adamas Intelligence (Adamas) in September 2022. The individual REO pricing has been applied to the Makuutu basket composition to determine the annual basket pricing.

Table 6: Indicative Makuutu Rare Earth Oxide pricing forecast applied (Adamas Intelligence, September 2022).

REO REO 2025 2027 2029 2031 2033 2035
Base Case US$/kg $112.77 $109.41 $110.68 $122.36 $131.08 $138.53

Going forward, from 2022 through 2035 Adamas forecasts that global demand for NdFeB magnets will increase at a compound annual growth rate (CAGR) of 8.6%, bolstered by double-digit growth from electric vehicle and wind power sectors, translating to comparable demand growth for the rare earths elements, i.e., Neodymium (Nd), Praseodymium (Pr), Dysprosium (Dy) and Terbium (Tb), these magnets contain.

Over the same period, Adamas forecast that global production of Nd, Pr, Dy and Tb will collectively increase at a slower CAGR of just 5.4% as the supply side of the market increasingly struggles to keep up with rapidly growing demand.

From 2023 through 2035, Adamas forecasts that the global rare earth industry will consistently underproduce Nd, Pr, Dy and Tb oxides (or oxide equivalents), resulting in the depletion of historically accumulated inventories and, ultimately, shortages of these critical magnet materials if supply is not increased beyond levels currently anticipated.

The Makuutu Rare Earths Project offers broad economic exposure to the rare earth permanent magnet sector, which is the fastest-growing end-use category and most in need of additional rare earth supplies, according to Adamas.

From a marketing, logistics and economic standpoint, the high proportion of valuable magnet- related rare earth elements in the Makuutu Project’s prospective TREO production means that a future mine (with separation) could generate approximately 83% of its rare earths revenues from just 31% of its production volume (NdPr, Dy and Tb oxide).

Looking forward, Adamas believes that the current strong pricing environment for rare earth materials is here to stay, notwithstanding the market’s usual ebbs and flows on the back of seasonality and other transient factors.

Ionic Rare Earths Limited, Level 1, 34 Colin Street, West Perth WA 6005 Australia T+61 3 9776 3434 E [email protected]

In its base case scenario (excluding Sc2O3), Adamas forecasts that the basket value of Makuutu TREO production will total US$106.83 per kg in 2024 and will increase to US$138.53 per kg in 2035. In its upside scenario (excluding Sc2O3), Adamas forecasts the basket value will total US$114.98 per kg in 2024 and will increase to US$154.27 per kg in 2035. In its downside scenario (excluding Sc2O3), Adamas forecasts the basket value will total US$98.94 per kg in 2024 and will increase to US$122.80 per kg in 2035. Refer to Figure 15 for the base case, upside case and downside case forecast from Adamas in September 2022.

==> picture [483 x 205] intentionally omitted <==

Figure 15: Makuutu REO indicative basket pricing forecasts, excluding Sc2O3, using individual REO pricing forecasts for Base Case, Upside Case and Downside Case, provided by Adamas Intelligence (Sept 2022).

A scandium oxide (Sc2O3) price of US$775 per kg has been used for the study as forecasted by Adamas for production of less than 25 tpa.

Capital and Operating Costs

The capital cost estimate (CAPEX) has been developed to meet the requirements of an Association for the Advancement of Cost Engineering (AACE Class 3) estimate, targeting an accuracy of ±15%. The CAPEX estimate is broken down into the main areas of mining and processing plant. The mining capital cost estimate was developed by IonicRE with input from contract mining service providers in Uganda. The process plant capital cost estimate was developed by Mincore Pty Ltd (Mincore), located in Melbourne, Victoria, Australia.

To maintain high environmental standards at Makuutu, the process plant CAPEX includes a series (3) of nano-filtration (NF) circuits, each with a separate duty, and required to concentrate the REE and salt solutions enabling the recycling of water and ultimately the discharge of high-quality water from the site. The inclusion of NF technology is seen as a significant step change from historical IAC processing flowsheets operating in southern China, where illegal and unregulated mining of such deposits has resulted in considerable environmental damage.

Infrastructure costs include provision for access roads, haul roads, and water collection and management, which would need to be developed.

Ionic Rare Earths Limited, Level 1, 34 Colin Street, West Perth WA 6005 Australia T+61 3 9776 3434 E [email protected]

The CAPEX includes a provision for Owner’s Costs, which includes more specific project related in country costs including an allocation for land acquisition and community programs.

Plant construction is expected to be 12 months.

The capital development profile for Makuutu reflects an initial project development with no planned expansion. Initial capital requirements of US$120.8 million in pre-production CAPEX including 10% contingency. The Capital Expenditure (CAPEX) estimate was developed from a bottom-up approach with majority of pricing received from the carrying out of procurement (check-price) packages and historical details of not more than 12 months from previous similar projects.

A breakdown of the CAPEX is provided in Table 7. A sustaining CAPEX allocation of US$19.3 million was estimated for the remaining operation of the Stage 1 development.

Table 7: Makuutu Stage 1 Development CAPEX.

Initial CAPEX
Breakdown
(US$, Million)
Mining $5.86
Process Plant $67.4
Infrastructure $10.7
Owners Cost $24.7
Contingency $12.1
Total, US$M $120.8

The mining operating costs estimate (OPEX) was developed by IonicRE in consultation with a Ugandan based mining contractor and utilises their in-country knowledge on operational costs and servicing requirements for similar equipment to that nominated by RRM.

The operating model for the open pit mining is owner procured contract operated. RRM will provide management, technical services and other support services. RRM will provide the mechanical equipment and it is assumed that the contractor will be responsible for mobile equipment operation and service.

Process operating costs have been estimated with inputs provided by Mincore in collaboration with IonicRE. The estimated process operating costs were derived based upon an interim mass balance used for the study to estimate reagent consumption and consumables.

The general and administration (G&A) costs were determined by IonicRE.

The operating cost estimate was developed from a bottom-up approach. Makuutu Stage 1 OPEX (Mining, Process and G&A) is US$12.40 per t Ore (dry), US$52.99 per kg of REO.

A breakdown of Stage 1 OPEX is provided in Figure 16.

Ionic Rare Earths Limited, Level 1, 34 Colin Street, West Perth WA 6005 Australia T+61 3 9776 3434 E [email protected]

Makuutu OPEX Breakdown

==> picture [299 x 187] intentionally omitted <==

----- Start of picture text -----

G&A Costs
12%
Mining Costs
27%
Processing &
Environmental Costs
26%
Reagent Costs
35%
----- End of picture text -----

Figure 16: OPEX breakdown for Makuutu Stage 1.

Financial Modelling and Metrics

As part of the Makuutu Stage 1 DFS a Financial Model was developed, this contained many scenarios in an attempt to determine the sensitivities of the project. The economic analysis of the Makuutu Stage 1 development was completed by IonicRE, indicating the potential for an economic project, however several assumptions will require substantiation via additional work programs to be completed in the next phase of the Project. The Project NPV, with Scandium production assumed, using a discount rate of 8%, was pre-tax, US$406 million, and post-tax US$278 million, and an IRR of 32.7%. The payback period was determined at three (3) years from first production.

The Makuutu Stage 1 development will also be a significant contributor to Uganda’s fiscus, with estimated gross royalty payments of US$199 million plus corporate tax contributions of US$438 million over the Stage 1 development of the Project, based upon RL1693 only at this stage.

All capital, operating and revenue inputs used in the DFS are on a US dollar basis.

A full breakdown of economic metrics is provided in Table 1.

The Project is most sensitive to mine grade, metallurgical recovery and REO pricing, with increases in these having substantial increments in the post-tax NPV of the Project. Operating cost has a larger effect on NPV compared to capital cost. The response of sensitivities tested is illustrated in Figure 17 and Figure 18.

Ionic Rare Earths Limited, Level 1, 34 Colin Street, West Perth WA 6005 Australia T+61 3 9776 3434 E [email protected]

Sensitivities (+/- 20%) – NPV8 Post-Tax

==> picture [465 x 165] intentionally omitted <==

----- Start of picture text -----

Grade
G&A
Capital Expenditure
Process Recovery
Opex - Processing
Opex - Mining
Price
- 50 100 150 200 250 300 350 400 450 500
US$m
----- End of picture text -----

Figure 17: Makuutu Stage 1 DFS sensitivity analysis ±20%, post-tax NPV.

==> picture [483 x 213] intentionally omitted <==

----- Start of picture text -----

Sensitivities (+/- 10%) – NPV8 (Post-Tax)
Grade
G&A
Capital Expenditure
Process Recovery
Opex - Processing
Opex - Mining
Price
- 50 100 150 200 250 300 350 400 450 500
US$m
----- End of picture text -----

Figure 18: Makuutu Stage 1 DFS sensitivity analysis ±10%, post-tax NPV.

ESG and Land Ownership

The Project’s ESG programs are documented in the Environmental and Social Impact Assessment (ESIA) which was approved by the Ugandan National Environmental Management Authority (NEMA), and with the permit awarded in October 2022 (see Figure 19).

The submitted development approach, which was approved by NEMA provides for a continuous rehabilitation of mined areas to ensure no footprint is left behind due to the mining operations, and the resulting rehabilitated agricultural land is more productive. The commitment to the local community, documented and approved by NEMA in the ESIA, outlined a prioritisation of employment for local stakeholders and engagement of local service providers, where available. This will form the

Ionic Rare Earths Limited, Level 1, 34 Colin Street, West Perth WA 6005 Australia T+61 3 9776 3434 E [email protected]

basis of a long partnership with the local residents, Busoga Kingdom, and Ugandan Government. Makuutu aligns with Uganda’s commitment to National Development Plan III (NDP-III).

Land Ownership is established through in the Land Access Agreements. RRM will partner with the Community, the Local Council, Kingdom and National Government to ensure the success of these agreements.

==> picture [483 x 272] intentionally omitted <==

Figure 19: NEMA Executive presenting the Certificate of Approval for the Makuutu Rare Earth Project ESIA to the Rwenzori team in Uganda.

Next Steps

The positive outcomes generated by the DFS confirm the technical and economic viability of the Project. Next steps are to progress the Project towards the Final Investment Decision (FID) by the Board in late 2023, which will be supported by a positive outcome from the demonstration plant at Makuutu. Construction of the commercial plant is expected to commence in Q1 2024.

To achieve FID within the above timeframe, there are several key workstreams which need to be completed.

Demonstration Plant and Process Validation

The immediate next phase of the Project is to develop a Demonstration Plant at Makuutu to evaluate the scale up of mining, material handling and larger scale processing works onsite at Makuutu in Uganda. This has the benefits of further developing knowledge of the orebody, grade control optimisation processes, optimisation of desorption process conditions and control, evaluating logistics and material handling at larger scale, plus verifying the potential to increase the heap desorption stack height beyond 3m to unlock potential for greater capital efficiency.

Ionic Rare Earths Limited, Level 1, 34 Colin Street, West Perth WA 6005 Australia T+61 3 9776 3434 E [email protected]

Whilst heap desorption columns have demonstrated successful scale up to 5m and additional test work infers the potential to increase to 6m, and beyond, a larger program of variability columns, cribs and heap desorption test modules of approximately 5,000t will be required to confirm this as viable.

The Demonstration Plant will also be critical in producing substantial quantities of MREC product that will be required to progress potential supply chain partnerships, plus providing samples to support the next phase of development for IonicRE’s potential downstream activities.

The Demonstration Plant and associated facility will also assist the Company in de-risking the Project through further capacity building in Uganda, training the geologists, metallurgists, mining specialists, project management and support staff – safety and environmental to ensure the ramp up of the Project in 2024 can be achieved.

Planning and works are well underway, with some initial equipment orders placed. Activity is set to increase during Q2 of 2023, with the construction of the facility shed, and delivery of the first 6m heap desorption columns.

Project Ownership

A key requirement on the financing of Makuutu Stage 1 will be to agree terms and finalise a transaction for IonicRE to secure a significant increase in the ownership of Makuutu beyond the earnin target of 60% post DFS completion. Discussions have progressed well with partners within RRM, and the Company expects that a suitable transaction can be agreed in the near term to achieve this target now the Stage 1 DFS has been completed.

Product Offtake and Supply Chain Development

IonicRE has been actively engaging with potential supply chain partners, marketing to end users and intermediaries in the development of western supply chains over the past 18 months. These discussions have progressed well, and with the Makuutu Stage 1 DFS now complete, the Company expects to further progress engagement over the coming months with a view to also advancing potential refinery processing options suitable for receiving the Makuutu product in early 2025.

Several groups have indicated strong interest in working with IonicRE to bring the Makuutu basket into key western markets across the US, EU and UK, however the maturity of the downstream supply chain still requires significant investment, limiting the capacity for Makuutu to scale up at this time. IonicRE is continuing to work with these potential partners on a number of initiatives, which, at a smaller scale, are aligned to the Makuutu Stage 1 production profile.

To support the engagement and natural progression of several strategic partner discussions, now that the Stage 1 DFS has been completed and the award of the ML at Makuutu is pending, the Company will be appointing a Corporate Advisor to drive a formalised competitive process to progress strategic partnership and generate a positive outcome for the Company.

Project Financing

The Company has been in discussions with financiers regarding the potential funding of Makuutu Stage 1. Whilst a number of western government initiatives may be suitable to support favourable

Ionic Rare Earths Limited, Level 1, 34 Colin Street, West Perth WA 6005 Australia T+61 3 9776 3434 E [email protected]

financing terms for Makuutu, greater clarity on supply chain partnerships will be crucial to secure the necessary milestones to secure Project debt finance.

To help facilitate the process, the Company will be looking to appoint an independent technical expert to review the outcomes of the DFS with a view to supporting the debt financing package for Makuutu. It is expected that this will occur post award of the ML for the Stage 1 development.

In addition, the Company is assessing other opportunities to raise the remaining equity required to build the Project, including involving a potential offtake/supply chain counterparty, streaming/royalty transactions or other strategic investors at corporate and Project level. To the extent the Company decides to undertake a capital raise to fund the Project this will dilute the interests of existing Shareholders.

The Company estimates that a total of US$48 million equity will be needed to finance the Project.

Land Access Agreements

The Company, via RRM, has initiated the next phase of land access agreements over the MLA at RL 1693, to agree a staged development at Makuutu with local landowners. Discussions and engagement with landowners are progressing well and we will update the market accordingly.

Detailed Front-End-Engineering and Design

While a substantial volume of work has been completed as part of the DFS, there is a further body of work required to finalise the overall plant design, including produce the final designs and detailed engineering to enable construction to commence as early as possible post FID. This work will be informed through initial workstreams from the Demonstration Plant and is expected to commence in Q3 2023.

Additionally, a number of opportunities have been flagged to value engineer the Study further, plus as well as exploring longer-term opportunities to reduce operational costs through development of local reagent capacity, which can support the staged development at Makuutu.

Mining Licence Application over RL 1693 (TN03834)

With the finalisation of the Makuutu Stage 1 DFS, IonicRE can now confirm all necessary documentation has been provided to the DGSM and Ugandan Mining Cadastre portal to support the MLA, which was initiated on 1 September 2022.

RRM are in regular contact with the DGSM, and the Company will update the market on progress of the MLA, now expected to be grant in the second quarter. This will not delay construction of the Demonstration Plant which is progressing.

Ionic Rare Earths Limited, Level 1, 34 Colin Street, West Perth WA 6005 Australia T+61 3 9776 3434 E [email protected]

Authorised for release by the Board.

For enquiries, contact :

Tim Harrison Peter Taylor Managing Director NWR Communications Ionic Rare Earths Limited [email protected] [email protected] +61 (0) 412 036 231

Competent Persons Statements

The information in this report that relates to Mineral Resources for the Makuutu Rare Earths deposit was first released to the ASX on 3 May 2022 and is available to view on www.asx.com.au. Ionic Rare Earths Limited confirms that it is not aware of any new information or data that materially affects information included in the relevant market announcement, and that all material assumptions and technical parameters underpinning the estimates in the announcement continue to apply and have not materially changed.

The information in this announcement that relates to mine design, planning and optimisation is based on information reviewed by Mr Lee White who is the Principal Engineer of Ionic Rare Earths Limited, engaged through a service contract with Kalem Group Pty Ltd and a shareholder of the Company. Mr White is also a Member of the AusIMM. Mr White has sufficient experience relevant to the style of mineralisation and type of deposit under consideration and to the activity being undertaken to qualify as a Competent Person as defined by the JORC Code 2012. Mr. White visited the Makuutu Site, Uganda on 23-31 August 2022. Mr White consents to the inclusion in this announcement of the matters based on their information in the form and context in which it appears.

The information in this document that relates to metallurgy test work and metallurgy simulation modelling is based on information reviewed by Dr Will Goodall who is the Principal Metallurgist (test work) and metallurgy simulation modelling, is based on information reviewed by Dr Will Goodall who is Principal Metallurgist (Simulation Modelling) and engaged through a service contract with Minassist Pty Ltd. Dr Goodall is a Member of the Australasian Institute of Mining and Metallurgy (AusIMM). Dr Goodall has sufficient experience relevant to the style of mineralisation and type of deposit under consideration and to the activity being undertaken to qualify as a Competent Person as defined by the JORC Code 2012. Dr Goodall is due to visit the Makuutu Site, Uganda, in the first half of 2023. Dr Goodall did visit the metallurgy test work laboratories during the test work phase of the Project in 2022. Dr Goodall consents to the inclusion in this announcement of the matters based on their information in the form and context in which it appears.

The information in this announcement and that relates to Capital Expenditure (CAPEX) is based on information reviewed by Mr Stephen McEwen who is Principal Mechanical Engineer of Ionic Rare Earths Limited, engaged through a service contract with SMC Pty Ltd and is a shareholder of the Company. Mr McEwen is a Member of the AusIMM. Mr McEwen has sufficient experience relevant to the style of mineralisation and type of deposit under consideration and to the activity being undertaken to qualify as a Competent Person as defined by the JORC Code 2012. Mr. McEwen last visited the Makuutu Site, Uganda, 23-31 August 2022. Mr McEwen consents to the inclusion in this announcement of the matters based on their information in the form and context in which it appears.

Ionic Rare Earths Limited, Level 1, 34 Colin Street, West Perth WA 6005 Australia T+61 3 9776 3434 E [email protected]

Forward Looking Statements

This announcement has been prepared by Ionic Rare Earths Limited and may include forward-looking statements. Forward-looking statements are only predictions and are subject to risks, uncertainties and assumptions which are outside the control of Ionic Rare Earths Limited. Actual values, results or events may be materially different to those expressed or implied in this document. Given these uncertainties, recipients are cautioned not to place reliance on forward looking statements. Any forward-looking statements in this document speak only at the date of issue of this document. Subject to any continuing obligations under applicable law and the ASX Listing Rules, Ionic Rare Earths Limited does not undertake any obligation to update or revise any information or any of the forward-looking statements in this document or any changes in events, conditions or circumstances on which any such forward looking statement is based.

Ionic Rare Earths Limited, Level 1, 34 Colin Street, West Perth WA 6005 Australia T+61 3 9776 3434 E [email protected]

Appendix 1: Makuutu Rare Earths Project 3 May 2022 Mineral Resource Estimate Tabulations

Table 8: Makuutu Rare Earth Resource Tabulation at 200ppm TREO- CeO2 Cut-off Grade.

Resource
Classification
Tonnes
(millions)
La2O3
(ppm)
CeO2
(ppm)
Pr6O11
(ppm)
Nd2O3
(ppm)
Sm2O3
(ppm)
Eu2O3
(ppm)
Gd2O3
(ppm)
Tb4O7
(ppm)
Dy2O3
(ppm)
Ho2O3
(ppm)
Er2O3
(ppm)
Tm2O3
(ppm)
Yb2O3
(ppm)
Lu2O3
(ppm)
Y2O3
(ppm)
Indicated 404 130 220 30 110 20 4 20 3 10 3 10 1 10 1 100
Inferred 127 110 180 30 90 20 3 10 2 10 2 10 1 10 1 80
Total 532 130 210 30 110 20 4 20 2 10 3 10 1 10 1 90

Notes: Tonnes are dry tonnes rounded to the nearest 1Mt.

All material REO grades are rounded to the nearest 10 ppm except Eu2O3, Tb4O7, Ho2O3, Tm2O3, Lu2O3 which are immaterial to overall resource grade.

Table 9: Makuutu Rare Earth Project Resource Tabulation of REO Reporting Groups at 200ppm TREO- CeO2 Cut-off Grade.

Resource
Classification
Tonnes
(millions)
TREO
(ppm)
TREO- CeO2
(ppm)
CREO
(ppm)
HREO
(ppm)
LREO
(ppm)
NdPr
(ppm)
Sc2O3
(ppm)
U3O8
(ppm)
ThO2
(ppm)
Indicated 404 670 450 230 170 500 150 30 10 30
Inferred 127 540 360 180 140 400 120 30 10 30
Total 532 640 430 220 160 480 140 30 10 30

Notes: All ppm rounded from original estimate to the nearest 10 ppm which may lead to differences in averages from Table 8.

Y2O3 is included in the TREO, HREO and CREO calculation.

TREO (Total Rare Earth Oxide) = La2O3 + CeO2 + Pr6O11 + Nd2O3 + Sm2O3 + Eu2O3 + Gd2O3 + Tb4O7 + Dy2O3 + Ho2O3 + Er2O3 + Tm2O3 + Yb2O3 + Y2O3 + Lu2O3. CREO[2] (Critical Rare Earth Oxide) = Nd2O3 + Eu2O3 + Tb4O7 + Dy2O3 + Y2O3

HREO (Heavy Rare Earth Oxide) = Sm2O3 + Eu2O3 + Gd2O3 + Tb4O7 + Dy2O3 + Ho2O3 + Er2O3 + Tm2O3 + Yb2O3, + Y2O3 + Lu2O3 LREO (Light Rare Earth Oxide) = La2O3 + CeO2 + Pr6O11 + Nd2O3

NdPr = Nd2O3 + Pr6O11

U3O8 and ThO2 are deleterious elements being reported in accordance with JORC (2012) Guidelines.

  • 2 U.S. Department of Energy, Critical Materials Strategy, December 2011

29

Appendix 2: Makuutu Rare Earths Project Stage 1 Ore Reserve Estimate Tabulations – Areas C, Central Zone, Central Zone East and F Only.

Table 10: Makuutu Stage 1 Ore Reserve Estimate Tabulation.

Classification Tonnes
(millions)
La2O3
(ppm)
CeO2
(ppm)
Pr6O11
(ppm)
Nd2O3
(ppm)
Sm2O3
(ppm)
Eu2O3
(ppm)
Gd2O3
(ppm)
Tb4O7
(ppm)
Dy2O3
(ppm)
Ho2O3
(ppm)
Er2O3
(ppm)
Tm2O3
(ppm)
Yb2O3
(ppm)
Lu2O3
(ppm)
Y2O3
(ppm)
Proven - - - - - - - - - - - - - - - -
Probable 172.9 173 264 42 150 26 5 22 3 18 4 10 1 9 1 119
Total 172.9 173 264 42 150 26 5 22 3 18 4 10 1 9 1 119

Table 11: Maiden Makuutu Stage 1 Ore Reserve Estimate.

Classification Tonnage
(Mt)
TREO Grade
(ppm)
TREO-CeO2
Grade (ppm)
NdPr
(ppm)
DyTb
(ppm)
LREO
(ppm)
HREO
(ppm)
CREO
(ppm)
Sc2O3
(ppm)
U3O8
(ppm)
ThO2
(ppm)
Proven - - - - - - - - - - -
Probable 172.9 848 584 192 21 629 219 295 30 16 31
Total 172.9 848 584 192 21 629 219 295 30 16 31

Notes: All ppm rounded from original estimate to the nearest 10 ppm which may lead to differences in averages from Table 8. Y2O3 is included in the TREO, HREO and CREO calculation.

TREO (Total Rare Earth Oxide) = La2O3 + CeO2 + Pr6O11 + Nd2O3 + Sm2O3 + Eu2O3 + Gd2O3 + Tb4O7 + Dy2O3 + Ho2O3 + Er2O3 + Tm2O3 + Yb2O3 + Y2O3 + Lu2O3. CREO[3] (Critical Rare Earth Oxide) = Nd2O3 + Eu2O3 + Tb4O7 + Dy2O3 + Y2O3

HREO (Heavy Rare Earth Oxide) = Sm2O3 + Eu2O3 + Gd2O3 + Tb4O7 + Dy2O3 + Ho2O3 + Er2O3 + Tm2O3 + Yb2O3, + Y2O3 + Lu2O3

LREO (Light Rare Earth Oxide) = La2O3 + CeO2 + Pr6O11 + Nd2O3

NdPr = Nd2O3 + Pr6O11

DyTb = Dy2O3 + Tb4O7

U3O8 and ThO2 are deleterious elements being reported in accordance with JORC (2012) Guidelines.

  • 3 U.S. Department of Energy, Critical Materials Strategy, December 2011

30

Appendix 3: Makuutu Rare Earths Project Stage 1 JORC Code, 2012 Edition – Table 1 Report.

Section 1 Sampling Techniques and Data

(Criteria in this section apply to all succeeding sections.)

Criteria JORC Code explanation Commentary
Sampling
techniques

Nature and quality of sampling (eg cut channels, random chips, or
specific specialised industry standard measurement tools
appropriate to the minerals under investigation, such as down
hole gamma sondes, or handheld XRF instruments, etc). These
examples should not be taken as limiting the broad meaning of
sampling.

Include reference to measures taken to ensure sample
representivity and the appropriate calibration of any measurement
tools or systems used.

Aspects of the determination of mineralisation that are Material to
the Public Report.

In cases where ‘industry standard’ work has been done this would
be relatively simple (eg ‘reverse circulation drilling was used to
obtain 1 m samples from which 3 kg was pulverised to produce a
30 g charge for fire assay’). In other cases more explanation may
be required, such as where there is coarse gold that has inherent
sampling problems. Unusual commodities or mineralisation types
(eg submarine nodules) may warrant disclosure of detailed
information.
Diamond Core Drilling
Drill core was collected from a core barrel and placed in appropriately marked core trays. Down hole
core run depths were measured and marked with core blocks. Core was measured for core loss and
core photography and geological logging completed.
Sample lengths were determined by geological boundaries with a maximum sample length of 1 metre
applied in clay zones and up to 2 metres in laterite zones where core recovery was occasionally low.
Where the core contained continuous lengths of soft clay a carving knife was used to cut the core.
When the core was too hard to knife cut it was cut using an electric core saw.
Using either method core was initial cut in half then one half was further cut in half to give quarter core.
Quarter core was submitted to ALS for chemical analysis using industry standard sample preparation
and analytical techniques.
Half core was collected for metallurgical test work.
Drilling
techniques

Drill type (eg core, reverse circulation, open-hole hammer, rotary
air blast, auger, Bangka, sonic, etc) and details (eg core diameter,
triple or standard tube, depth of diamond tails, face-sampling bit
or other type, whether core is oriented and if so, by what method,
_etc). _
Diamond Core Drilling
Core size was HQ triple tube with a nominal diameter of 61.1mm.
The core was not oriented (vertical holes)
Drill sample
recovery

Method of recording and assessing core and chip sample
recoveries and results assessed.

Measures taken to maximise sample recovery and ensure
representative nature of the samples.

Whether a relationship exists between sample recovery and grade
and whether sample bias may have occurred due to preferential
loss/gainof fine/coarse material.
Diamond Drilling
Core recovery was calculated by measuring actual core length versus drillers core run lengths. Core
recovery ranged from 70% to 100% and averaged 97%.
No relationship exists between core recovery and grade.
Logging
Whether core and chip samples have been geologically and
geotechnically logged to a level of detail to support appropriate
Mineral Resource estimation, mining studies and metallurgical
_studies. _
All (100%) drill core has been geologically logged and core photographs taken.
Logging is qualitative with description of colour, weathering status, alteration, regolith zone, major and
minor rock types, texture, grain size and comments added where further observation is made.

31

Criteria JORC Code explanation Commentary

Whether logging is qualitative or quantitative in nature. Core (or
costean, channel, etc) photography.

The total length and percentage of the relevant intersections
_logged. _
Additional non-geological qualitative logging includes comments for sample recovery, humidity, and
hardness for each logged interval.
Sub-sampling
techniques
and sample
preparation

If core, whether cut or sawn and whether quarter, half or all core
taken.

If non-core, whether riffled, tube sampled, rotary split, etc and
whether sampled wet or dry.

For all sample types, the nature, quality and appropriateness of
the sample preparation technique.

Quality control procedures adopted for all sub-sampling stages to
maximise representivity of samples.

Measures taken to ensure that the sampling is representative of
the in situ material collected, including for instance results for field
duplicate/second-half sampling.

Whether sample sizes are appropriate to the grain size of the
_material being sampled. _
Diamond Drill Core
Where the core contained continuous lengths of soft clay a carving knife was used to cut the core.
When the core was too hard to knife cut it was cut using an electric core saw.
Sample lengths were determined by geological boundaries with a maximum sample length of 1 metre
applied in clay zones and up to 2 metres in laterite zones where core recovery was occasionally low.
Samples were collected from core trays by hand and placed in individually numbered bags. These bags
were dispatched to ALS for analysis with no further field preparation.
Sample weights were recorded prior to sample dispatch. Sample mass is considered appropriate for the
grain size of the material being sampled that is generally very fine grained and uniform.
Field duplicate sampling was conducted at a ratio of 1:25 samples. Duplicates were created by
lengthways halving the ¼ core primary sample into 2 identical portions. Duplicate samples were
allocated separate sample numbers and submitted with the same analytical batch as the primary
sample.
Quality of
assay data
and laboratory
tests

The nature, quality and appropriateness of the assaying and
laboratory procedures used and whether the technique is
considered partial or total.

For geophysical tools, spectrometers, handheld XRF instruments,
etc, the parameters used in determining the analysis including
instrument make and model, reading times, calibrations factors
applied and their derivation, etc.

Nature of quality control procedures adopted (eg standards,
blanks, duplicates, external laboratory checks) and whether
acceptable levels of accuracy (ie lack of bias) and precision have
been established.
Assay and Laboratory Procedures – All Samples
Samples were dispatched by air freight direct to ALS laboratory Perth Australia. The preparation and
analysis protocol used is as follows:
ALS Code
Description
WEI-21
Received sample weight
LOG-22
Sample Login w/o Barcode
DRY-21
High temperature drying
CRU-21
Crush entire sample
CRU-31
Fine crushing–70%<2mm
SPL-22Y
Split sample–Boyd Rotary Splitter
PUL-31h
Pulverise 750g to 85% passing 75 micron
CRU-QC
Crushing QC Test
PUL-QC
Pulverising QC test
The assay technique used for REE was Lithium Borate Fusion ICP-MS (ALS code ME-MS81). This is a
recognised industry standard analysis technique for REE suite and associated elements. Elements
analysed at ppm levels:
Ba
Ce
Cr
Cs
Dy
Er
Eu
Ga
Gd
Hf
Ho
La
Lu
Nb
Nd
Pr
Rb
Sm
Sn
Sr
Ta
Tb
Th
Tm
U
V
W
Y
Yb
Zr
Criteria JORC Code explanation Commentary
Analysis for scandium (Sc) was by Lithium Borate Fusion ICP-AES (ALS code Sc-ICP06).
The sample preparation and assay techniques used are industry standard and provide a total analysis.
All laboratories used are ISO 17025 accredited.
QAQC
Diamond Drill Core Samples

Analytical Standards
CRM AMIS0275 and AMIS0276 and a specific Makuutu CRM MUIACREI01 were included in sample
batches at a ratio of 1:25 to drill samples submitted. This is an acceptable ratio.
The assay results for the standards were consistent with the certified levels of accuracy and precision
and no bias is evident.

Blanks
CRM blanks AMIS0681 and OREAS22e were included in sample batches at a ratio of 1:25 to drill
samples submitted for analysis. This is an acceptable ratio.
Both CRM blanks contain some REE, with elements critical elements Ce, Nd, Dy and Y present in small
quantities. The analysis results were consistent with the certified values for the blanks. No laboratory
contamination or bias is evident from these results.

Duplicates
Field duplicate sampling was conducted at a ratio of 1:25 samples. Duplicates were created by
lengthways halving the ¼ core primary sample into 2 identical portions. Duplicate samples were
allocated separate sample numbers and submitted with the same analytical batch as the primary
sample. Variability between duplicate results is considered acceptable and no sampling bias is evident.

Alternative Analysis Technique
A selection of sample pulps was re-analysed at Bureau Veritas Minerals laboratory Perth W.A. using
Laser Ablation MS technique.
There is no evidence of systematic analytical bias or errors from these results.
Verification of
sampling and
assaying

The verification of significant intersections by either independent
or alternative company personnel.

The use of twinned holes.

Documentation of primary data, data entry procedures, data
verification, data storage (physical and electronic) protocols.

Discuss any adjustment to assay data.
No independent verification of significant intersection undertaken.
No twinning of diamond core drill holes was undertaken.
Sampling protocols for diamond core sampling and QAQC were documented and held on site by the
responsible geologist. No procedures for data storage and management have been compiled as yet.
Data were collected in the field by hand and entered into Excel spreadsheet. Data was compiled with
assay results compiled and stored in Access database. Data verification is conducted on data entry
including hole depths, sample intervals and sample numbers. Sample numbers from assay data are
verified by algorithm in spreadsheet prior to entry into the database.
Assay data was received in digital format from the laboratory and merged with the sampling data into an
Excel spreadsheet format for QAQC analysis and reviewed against field data. Once finalised and
validated data is stored in a protected Access database.
Data validation of assay data and sampling data have been conducted to ensure data entry is correct.
All assay data is received from the laboratory in element form is unadjusted for data entry.
Criteria JORC Code explanation Commentary
Conversion of elemental analysis (REE) to stoichiometric oxide (REO) was undertaken by spreadsheet
using defined conversion factors.(Source:https://www.jcu.edu.au/advanced-analytical-centre/services-
and-resources/resources-and-extras/element-to-stoichiometric-oxide-conversion-factors)
Element ppm
Conversion Factor
Oxide Form
Ce
1.2284
CeO2
Dy
1.1477
Dy2O3
Er
1.1435
Er2O3
Eu
1.1579
Eu2O3
Gd
1.1526
Gd2O3
Ho
1.1455
Ho2O3
La
1.1728
La2O3
Lu
1.1371
Lu2O3
Nd
1.1664
Nd2O3
Pr
1.2082
Pr6O11
Sm
1.1596
Sm2O3
Tb
1.1762
Tb4O7
Tm
1.1421
Tm2O3
Y
1.2699
Y2O3
Yb
1.1387
Yb2O3
Sc
1.5338
Sc2O3
Rare earth oxide is the industry accepted form for reporting rare earths. The following calculations are
used for compiling REO into their reporting and evaluation groups:
Note that Y2O3is included in the TREO, HREO and CREO calculation.
TREO (Total Rare Earth Oxide) = La2O3+ CeO2+ Pr6O11+ Nd2O3+ Sm2O3+ Eu2O3+ Gd2O3+ Tb4O7+
Dy2O3+ Ho2O3+ Er2O3+ Tm2O3+ Yb2O3+ Y2O3+ Lu2O3.
HREO (Heavy Rare Earth Oxide) = Sm2O3+ Eu2O3+ Gd2O3+ Tb4O7+ Dy2O3+ Ho2O3+ Er2O3+ Tm2O3+
Yb2O3, + Y2O3+ Lu2O3
CREO (Critical Rare Earth Oxide) = Nd2O3 +Eu2O3 +Tb4O7 +Dy2O3 +Y2O3
(From U.S. Department of Energy, Critical Materials Strategy, December 2011)
LREO (Light Rare Earth Oxide) = La2O3+ CeO2 + Pr6O11+ Nd2O3
NdPr = Nd2O3+ Pr6O11
DyTb = Dy2O3+ Tb4O7
HREO% of TREO= HREO/TREO x 100
In elemental form the classifications are:
Note that Y is included in the TREE, HREE and CREE calculation.
TREE: La+Ce+Pr+Nd+Sm+Eu+Gd+Tb+Dy+Ho+Er+Tm+Yb+Lu+Y
HREE: Sm+Eu+Gd+Tb+Dy+Ho+Er+Tm+Yb+Y+Lu
CREE: Nd+Eu+Tb+Dy+Y
LREE: La+Ce+Pr+Nd
Criteria JORC Code explanation Commentary
Location of
data points

Accuracy and quality of surveys used to locate drill holes (collar
and down-hole surveys), trenches, mine workings and other
locations used in Mineral Resource estimation.

Specification of the grid system used.

Quality and adequacy of topographic control.
Drill hole collar locations for holes RRMDD001 to RRMDD711 were surveyed using a relational DGPS
system. The general accuracy for x,y and z is+0.2m.
Datum WGS84 Zone 36 North was used for location data collection and storage. This is the appropriate
datum for the project area. No grid transformations were applied to the data.
No downhole surveys were conducted. As all holes were vertical and shallow, the rig setup was checked
using a spirit level for horizontal and vertical orientation Any deviation will be insignificant given the short
lengths of the holes.
Topography has been defined by creating a wireframe from drill hole collar locations
Data spacing
and
distribution

Data spacing for reporting of Exploration Results.

Whether the data spacing and distribution is sufficient to establish
the degree of geological and grade continuity appropriate for the
Mineral Resource and Ore Reserve estimation procedure(s) and
classifications applied.

_Whether sample compositing has been applied. _
Drill spacing was optimised to suite grade estimation ranges as determined from variogram analysis of
data distribution.
162 drill holes were spaced on a nominal 100m x 100m spacing within the MCZ.
517 holes in Areas C, E MCZ, MCZE, F, G, H and I were drilled on a 200m spacing.
32 drill holes in Areas A, B and D were drilled on a 400m spacing.
Orientation of
data in relation
to geological
structure

Whether the orientation of sampling achieves unbiased sampling
of possible structures and the extent to which this is known,
considering the deposit type.

If the relationship between the drilling orientation and the
orientation of key mineralised structures is considered to have
introduced a sampling bias, this should be assessed and reported
if material.
The Makuutu mineralisation is interpreted to be in a flat lying weathered profile including cover soil,
lateritic caprock, clays transitioning to saprolite and saprock. Below the saprock are fresh shales,
siltstones and mudstones. Pit mapping and diamond drilling indicate the mineralised regolith to be
generally horizontal.
All drill holes are vertical which is appropriate for horizontal bedding and regolith profile.
Sample
security

The measures taken to ensure sample security.
After collection, the samples were transported by Company representatives to Entebbe airport and
dispatched via airfreight to Perth Australia. Samples were received by Australian customs authorities in
Perth within 48 hours of dispatch and were still contained in the sealed shipment bags.
Samples were subsequently transported from Australian customs to ALS Perth via road freight and
inspected on arrival by a Company representative.
Audits or
reviews

The results of any audits or reviews of sampling techniques and
_data. _
No audits or reviews have been undertaken.

Section 2 Reporting of Exploration Results

(Criteria listed in the preceding section also apply to this section.)

Criteria JORC Code explanation Commentary
Mineral
tenement and
land tenure
status

Type, reference name/number, location and ownership including
agreements or material issues with third parties such as joint
ventures, partnerships, overriding royalties, native title interests,
historical sites, wilderness or national park and environmental
_settings. _
The Makuutu Rare Earths Project is 100% owned by Rwenzori Rare Metals Limited (“RRM”), a Ugandan
registered company. IonicRE currently has earned a 51% shareholding in RRM and may increase its
shareholding to 60% by meeting further commitments as follows:
1.
IonicRE to fund to completion of a Definitive Feasibility Study (DFS) to earn an additional 9%
interest for a cumulative 60% interest in RRM.

35

Criteria JORC Code explanation Commentary

The security of the tenure held at the time of reporting along with
any known impediments to obtaining a licence to operate in the
area.
2.
Milestone payments, payable in cash or IonicRE shares at the election of the Vendor, as
follows:
a.
US$375,000 on production of 10 kg of mixed rare-earth product from pilot or
demonstration plant activities; and
b.
US$375,000 on conversion of existing licences to mining licences.
At any time should IonicRE not continue to invest in the project and project development ceases for at
least two months RRM has the right to return the capital sunk by IonicRE and reclaim all interest earnt by
IonicRE.
Exploration
done by other
parties

Acknowledgment and appraisal of exploration by other parties.
Previous exploration includes:
1980: Country wide airborne geophysical survey identifying uranium anomalies in the Project area.
1990s: French BRGM and Ugandan DGSM undertook geochemical and geological survey over South-
Eastern Uganda including the Project area. Anomalous Au, Zn, Cu, Sn, Nb and V identified.
2006-2009: Country wide high resolution airborne magnetic and radiometric survey identified U
anomalism in the Project area.
2009: Finland GTK reprocessed radiometric data and refined the Project anomalies.
2011: Kweri Ltd undertook field verification of radiometric anomalies including scout sampling of existing
community pits. Samples showed an enrichment of REE and Sc.
2011: The GTK conducted a ground gravity traverse which indicated a gravity low in the area.
2011: Kweri Ltd conducted ground radiometric survey and evaluated historic groundwater borehole
logs.
2012: Kweri Ltd and Berkley Reef Ltd conducted prospect wide pit excavation and sampling of 48 pits
and a ground gravity traverse. Pit samples showed enrichment of REE weathered profile.
2012 Kweri Ltd. Sent Five (5) samples to Toronto Aqueous Research Laboratory for REE leach test
work.
2016 – 2017: Rwenzori Rare Metals conducted the excavation of 11 pits, ground gravity survey, RAB
drilling (109 drill holes) and one (1) diamond drill hole.
The historic exploration has been conducted to a professional standard and is appropriate for the
exploration stage of the prospect.
Geology
Deposit type, geological setting and style of mineralisation.
The Makuutu deposit is interpreted to be an ionic adsorption REE clay-type deposits similar to those in
South China, Chile, Madagascar and Brazil.
The mineralisation is contained within the tropical lateritic weathering profile of a basin filled with
sedimentary rocks including shales, mudstones and sandstones potentially derived from the
surrounding granitic and mafic rocks. These rocks are considered the original source of the REE which
were then accumulated in the sediments (via ionic bonds with the clays) of the basin as the surrounding
rocks have degraded. These sediments then form the protolith that was subjected to prolonged tropical
weathering.
The weathering developed a lateritic regolith with a surface indurated hardcap, followed downward by
clay rich zones that grade down through saprolite and saprock to unweathered sediments. The
thickness of the regolith is between 10 and 20 metres from surface.
The REE mineralisation is concentrated in the weathered profile where it has dissolved from its primary
mineral form, such as monazite and xenotime, then ionically bonded (adsorbed) or colloidally bonded on
Criteria JORC Code explanation Commentary
to fine particles of aluminosilicate clays (e.g. kaolinite, illite, smectite). The adsorbed and colloidal REE is
the target for extraction and production of REO at Makuutu.
Drill hole
Information

A summary of all information material to the understanding of the
exploration results including a tabulation of the following
information for all Material drill holes:
o easting and northing of the drill hole collar
o elevation or RL (Reduced Level – elevation above sea level in
metres) of the drill hole collar
o dip and azimuth of the hole
o down hole length and interception depth
o hole length.

If the exclusion of this information is justified on the basis that the
information is not Material and this exclusion does not detract from
the understanding of the report, the Competent Person should
_clearly explain why this is the case. _
The material information for drill holes relating to this announcement are contained in Appendix 2.
Data
aggregation
methods

In reporting Exploration Results, weighting averaging techniques,
maximum and/or minimum grade truncations (eg cutting of high
grades) and cut-off grades are usually Material and should be
stated.

Where aggregate intercepts incorporate short lengths of high-
grade results and longer lengths of low-grade results, the
procedure used for such aggregation should be stated and some
typical examples of such aggregations should be shown in detail.

The assumptions used for any reporting of metal equivalent values
_should be clearly stated. _
No metal equivalents values are used.
Relationship
between
mineralisation
widths and
intercept
lengths

These relationships are particularly important in the reporting of
Exploration Results.

If the geometry of the mineralisation with respect to the drill hole
angle is known, its nature should be reported.

If it is not known and only the down hole lengths are reported,
there should be a clear statement to this effect (eg ‘down hole
_length, true width not known’). _
Down hole lengths, true widths are not known.
The mineralisation is interpreted to be horizontal, flat lying sediments and weathering profile, with the
vertical drilling perpendicular to mineralisation. Any internal variations to REE distribution within the
horizontal layering was not defined, therefore the true width is considered not known.
Diagrams
Appropriate maps and sections (with scales) and tabulations of
intercepts should be included for any significant discovery being
reported These should include, but not be limited to a plan view
_of drill hole collar locations and appropriate sectional views. _
Refer to diagrams in body of text.
Balanced
reporting

Where comprehensive reporting of all Exploration Results is not
practicable, representative reporting of both low and high grades
and/or widths should be practiced to avoid misleading reporting
_of Exploration Results. _
This report contains all drilling results that are consistent with the JORC guidelines. Where data may
have been excluded, it is considered not material.
Criteria JORC Code explanation Commentary
Other
substantive
exploration
data

Other exploration data, if meaningful and material, should be
reported including (but not limited to): geological observations;
geophysical survey results; geochemical survey results; bulk
samples – size and method of treatment; metallurgical test results;
bulk density, groundwater, geotechnical and rock characteristics;
potential deleterious or contaminating substances.
Metallurgical leach testing was previously conducted on samples derived from exploration pits, RAB
drilling, and one 8.5 tonne bulk pit sample.
In 2012, 5 pit samples were sent to the Toronto Aqueous Research Laboratory at the University of
Toronto for leachability tests.
In 2017, 2 pit samples were sent to SGS Laboratory Toronto for leachability tests.
2017/18, 29 samples were collected from 7 RAB drill holes. 20 of these were consigned to SGS Canada
and 4 to Aqueous Process Research (APR) in Ontario Canada. The remaining 5 samples were
consigned to Bio Lantanidos in Chile.
2018/19, 8.5 tonne bulk sample was consigned to Mintek, South Africa, to evaluate using Resin-in-leach
(RIL) technology for the recovery of REE.
2019: 118 samples from 31 holes from the 2019 diamond drilling program had preliminary variation test
work conducted TREE-Ce extraction ranged from 3% to 75%.
2020: Testing of composite samples with lower extractions from the 2019 variation testing using
increasing rates of acid addition and leach time. Significant increases in extractions were achieved.
2020: Testing of composited samples from two exploration holes east of the Makuutu Central Zone
provided an average extraction of TREE-Ce recovery of 41% @ pH1
Testing of samples from the project is ongoing.
Further work
The nature and scale of planned further work (eg tests for lateral
extensions or depth extensions or large-scale step-out drilling).

Diagrams clearly highlighting the areas of possible extensions,
including the main geological interpretations and future drilling
_areas, provided this information is not commercially sensitive. _
Future work programs to be determined.

Section 3 Estimation and Reporting of Mineral Resources

(Criteria listed in section 1, and where relevant in section 2, also apply to this section.)

Criteria JORC Code explanation Commentary
Database
integrity

Measures taken to ensure that data has not been corrupted by,
for example, transcription or keying errors, between its initial
collection and its use for Mineral Resource estimation purposes.

Data validation procedures used.
Data collected in the field has been validated against core photography and original data collection files.
Analytical data is received in digital format from the laboratory and merged with the sampling data into
an Excel spreadsheet format for QAQC analysis and review against field data. Once finalised and
validated data is stored in a protected Access database.
Data validation of original sampling and assay data have been conducted on the database on a 1:10
entries spot check basis. Data has also been correlated against interval lengths and EOH details.
Any data entry errors identified have been corrected in the database.
Site visits
Comment on any site visits undertaken by the Competent
Person and the outcome of those visits.

If no site visits have been undertaken indicate why this is the
_case. _
The project site has been visited by the Competent Person for Exploration Results who has observed
drilling operations, reviewed drill core, and reviewed sampling and QAQC procedures. The project has
been visited by the Competent Person responsible for the reporting of Mineral Resources who reviewed
the fieldproject area,drill core,samplingand bulk density procedures.

38

Criteria JORC Code explanation Commentary
Geological
interpretation

Confidence in (or conversely, the uncertainty of ) the geological
interpretation of the mineral deposit.

Nature of the data used and of any assumptions made.

The effect, if any, of alternative interpretations on Mineral
Resource estimation.

The use of geology in guiding and controlling Mineral Resource
estimation.

The factors affecting continuity both of grade and geology.
The mineral deposit is hosted in a tropical laterite regolith profile derived from generally flat lying
sediments. The regolith commences from surface to an average depth of approximately 18 metres. All
drilling was geologically logged in the field including rock type and degree of weathering. Following field
data collection and receipt of analytical data the deposit has been categorised on a Regolith Zone basis
based on visual observation from drill core and multi-element ratio analysis.
There is a moderate to high degree of confidence in the interpretation of the regolith units given the flat
lying and reasonably consistent nature of the regolith.
There is unlikely to be any significant structural disruption to the mineralisation through the resource
area.
Estimation domains were based on grouping of the regolith domains into five zones as defined by
regolith rheology, and by comparison of regolith statistics:

Domain 1,2,3 – Cover zone

Domain 4 – Mottled zone

Domain 5 – Clay zone

Domain 6 – Upper Saprolite zone

Domain 7 – Lower Saprolite zone

Domain8,9– Basementzone
Dimensions
The extent and variability of the Mineral Resource expressed as
length (along strike or otherwise), plan width, and depth below
surface to the upper and lower limits of the Mineral Resource.
The overall defined mineralised zone extends across 11 discrete prospect areas defined by radiometric
and topographical features. The overall strike for the eastern-most to western-most prospects is
approximately 37 kilometres, with an across strike extent of ~3,000m and an average vertical thickness
of 18m.
The top of the mineralised zone is defined by a thin surficial soil / hardcap zone that averages 3.5m in
thickness. The base of the mineralised zone is defined by the top of the saprock/fresh rock boundary
which extends to an average vertical depth of 17m.
Estimation and
modelling
techniques

The nature and appropriateness of the estimation technique(s)
applied and key assumptions, including treatment of extreme
grade values, domaining, interpolation parameters and maximum
distance of extrapolation from data points. If a computer assisted
estimation method was chosen include a description of
computer software and parameters used.

The availability of check estimates, previous estimates and/or
mine production records and whether the Mineral Resource
estimate takes appropriate account of such data.

The assumptions made regarding recovery of by-products.

Estimation of deleterious elements or other non-grade variables
of economic significance (eg sulphur for acid mine drainage
characterisation).

In the case of block model interpolation, the block size in relation
to the average sample spacing and the search employed.

Any assumptions behind modelling of selective mining units.
A total of 15 rare earth element (REE) grade attributes (Y, La, Ce, Pr, Nd, Sm, Eu, Gd, Tb, Dy, Ho, Er,
Tm, Yb, and Lu) and Sc, and 2 deleterious elements (U, and Th) were estimated. Additionally, bulk
density was estimated for those domains with sufficient numbers of measurements. Final estimated
values are converted to stoichiometric oxide values by calculation using published ratios to support
reporting of rare earth oxides (REO).
The grade estimation used the Ordinary Kriging (“OK”) technique together with dynamic anisotropy to
guide the grade interpolation parallel to the regolith boundaries.
Grade interpolation used 1m composited samples constrained by the estimation domain boundaries
which were either treated as hard or soft boundaries based on statistical boundary analysis.
An appropriate top cutting strategy (generally above the 99thgrade percentile) was used to minimise the
influence of isolated high-grade outliers.
Interpolation parameters were derived using standard exploratory data analysis techniques of statistical
and continuity analysis. Appropriate interpolation strategies were developed on a domain basis using
kriging neighbourhood analysis (“KNA”), which included:

Oriented ellipsoidal search radii ranged from 600m to 1500m depending on the estimation
domain;
Criteria JORC Code explanation Commentary

Any assumptions about correlation between variables.

Description of how the geological interpretation was used to
control the resource estimates.

Discussion of basis for using or not using grade cutting or
capping.

The process of validation, the checking process used, the
comparison of model data to drill hole data, and use of
reconciliation data if available.

Minimum number of samples = 8;

Maximum number of samples = 20, and

Octant search with a maximum of 5 samples per octant.
The maximum extrapolation distance from the last data points was no more than 200m.
Computer software used for the modelling and estimation were:

Leapfrog Geo v2021 was used for geological domain modelling.

Supervisor v8.14 was used for geostatistical analysis.

Maptek Vulcan 2022 was used for grade estimation, block modelling and reporting.
The estimation block model definitions are:

Non-rotated block model with an azimuth of 000ºGN;

OK panel size was set at 100m x 100m x 2m (XYZ):
o
A smaller parent cell size of 50m x 50m x 2m (XYZ) was used in the Central Main
prospect where drilling was completed to 100m x 100m on average.

Sub-block size of 25m x 25m x 1m (XYZ);

The bulk of the drilling data is on 200m by 200m grid spacings with a portion of the Central
Main prospect infilled to 100m spacing, and

Appropriate search ellipses were derived from KNA with an average search radii of 600m to
1500m and average anisotropy of 30:20:1 (major/semi/minor).
Selection of the block size was based on the geometry of the mineralisation, data density, and the likely
degree to which selective mining can be successfully applied to the geologically based domain
boundaries.
Estimations of U and Th elements were completed for the Mineral Resource estimate. Estimates of Sc
were also completed. No other deleterious elements or other non-grade variables of economic
significance are reported.
Correlations between the elements were determined from statistical analysis of the REE and
demonstrated strong positive correlations between the majority of REE variables, particularly for the
heavy rare earth elements in the primary mineralised domains (domains 4, 5, 6 and 7).
The estimation model was validated using the following techniques:

Visual 3D checking and comparison of informing samples and estimated values;

Global statistical comparisons of raw sample and composite grades to the block grades;

Comparison of correlation coefficients between composite and block data;

Validation ‘swath’ plots by northing, easting and elevation for each domain, and

Analysis of the grade tonnage distribution.
No by-product recoveries were considered.
No mining production has taken place at the deposit.
Moisture
Whether the tonnages are estimated on a dry basis or with
natural moisture, and the method of determination of the
_moisture content. _
Tonnes are estimated on an In situ Dry Bulk Density basis. No moisture content has been determined by
test work or used in estimation.
Cut-off
parameters

The basis of the adopted cut-off grade(s) or quality parameters
_applied. _
Ionic Rare Earths Ltd have completed numerous metallurgical studies on composite samples of
mineralisation at Makuutu aspreviouslyannounced to the ASX on 18 February2020,26 May2020,and
Criteria JORC Code explanation Commentary
most recently 4 August 2020. These results together with indicative mining and processing costs and
other cost inputs supports application of a marginal cut-off grade of 200 ppm TREO (excluding CeO2).
This cut-off is comparable to peer projects with similar mineralisation types and processing
assumptions.
Mining factors
or
assumptions

Assumptions made regarding possible mining methods,
minimum mining dimensions and internal (or, if applicable,
external) mining dilution. It is always necessary as part of the
process of determining reasonable prospects for eventual
economic extraction to consider potential mining methods, but
the assumptions made regarding mining methods and
parameters when estimating Mineral Resources may not always
be rigorous. Where this is the case, this should be reported with
_an explanation of the basis of the mining assumptions made. _
Mineralisation is near surface, broadly flat lying, and of grades amenable to conventional open pit mining
methods.
The assumed mining method would be ‘free dig’ using truck and shovel.
Metallurgical
factors or
assumptions

The basis for assumptions or predictions regarding metallurgical
amenability. It is always necessary as part of the process of
determining reasonable prospects for eventual economic
extraction to consider potential metallurgical methods, but the
assumptions regarding metallurgical treatment processes and
parameters made when reporting Mineral Resources may not
always be rigorous. Where this is the case, this should be
reported with an explanation of the basis of the metallurgical
_assumptions made. _
Processing of the REE mineralisation is considered relatively simple, with the clay undergoing a
desorption process in which the REE are desorbed from the mineralisation into a salt solution,
concentrated, and precipitated to create a mixed rare earth product.
Preliminary metallurgical test work has been completed on core samples from the project area (ASX
Releases 18 February 2020, 26 May 2020, 4 August 2020). This reports metallurgical recoveries up to
75% TREE minus Cerium using simple extraction techniques. These recoveries compare favourably to
other known ionic clay hosted rare earth projects.
Environmental
factors or
assumptions

Assumptions made regarding possible waste and process
residue disposal options. It is always necessary as part of the
process of determining reasonable prospects for eventual
economic extraction to consider the potential environmental
impacts of the mining and processing operation. While at this
stage the determination of potential environmental impacts,
particularly for a greenfields project, may not always be well
advanced, the status of early consideration of these potential
environmental impacts should be reported. Where these aspects
have not been considered this should be reported with an
_explanation of the environmental assumptions made. _
Tailings (the processed clay) are expected to be returned to the mined open pits and areas
progressively rehabilitated.
Bulk density
Whether assumed or determined. If assumed, the basis for the
assumptions. If determined, the method used, whether wet or
dry, the frequency of the measurements, the nature, size and
representativeness of the samples.

The bulk density for bulk material must have been measured by
methods that adequately account for void spaces (vugs, porosity,
etc), moisture and differences between rock and alteration zones
within the deposit.
Bulk density has been determined from 1,223 individual drill core measurements using Archimedes
method. Samples were oven dried, weighed, coated with wax then weighed dry and in water using an
appropriate analytical balance.
Bulk densities for the primary mineralised domains (domain 4, 5, 6 and 7) were estimated using an
omnidirectional variogram with soft boundaries following boundary analysis. Densities for the remaining
regolith zones were by direct assignment based on reported measurements.
Criteria JORC Code explanation Commentary

Discuss assumptions for bulk density estimates used in the
_evaluation process of the different materials. _
Classification
The basis for the classification of the Mineral Resources into
varying confidence categories.

Whether appropriate account has been taken of all relevant
factors (ie relative confidence in tonnage/grade estimations,
reliability of input data, confidence in continuity of geology and
metal values, quality, quantity and distribution of the data).

Whether the result appropriately reflects the Competent
_Person’s view of the deposit. _
Classification of the mineral resource considered the interpretation confidence, drilling density,
demonstrated continuity, estimation statistics (conditional bias, kriging efficiency) and block model
validation results.
The Makuutu Mineral Resource has been classified into Indicated (76%) and Inferred (24%) categories.
The assigned Mineral Resource classification reflects the Competent Person’s view of the deposit.
Audits or
reviews

The results of any audits or reviews of Mineral Resource
_estimates. _
No audits or review have been completed for the Mineral Resource Estimate.
Discussion of
relative
accuracy/
confidence

Where appropriate a statement of the relative accuracy and
confidence level in the Mineral Resource estimate using an
approach or procedure deemed appropriate by the Competent
Person. For example, the application of statistical or
geostatistical procedures to quantify the relative accuracy of the
resource within stated confidence limits, or, if such an approach
is not deemed appropriate, a qualitative discussion of the factors
that could affect the relative accuracy and confidence of the
estimate.

The statement should specify whether it relates to global or local
estimates, and, if local, state the relevant tonnages, which should
be relevant to technical and economic evaluation.
Documentation should include assumptions made and the
procedures used.

These statements of relative accuracy and confidence of the
estimate should be compared with production data, where
_available. _
The relative accuracy of the Mineral Resource estimate is reflected in the reporting of the Mineral
Resource as per the guidelines of the 2012 JORC Code.
The statement relates to the global estimates of tonnes and grades.
No production data is available.

Section 4 Estimation and Reporting of Ore Reserves

(Criteria listed in section 1, and where relevant in sections 2 and 3, also apply to this section.)

Criteria JORC Code explanation Commentary
Mineral
Resource
estimate for

Description of the Mineral Resource estimate used as a basis
for the conversion to an Ore Reserve.

Clear statement as to whether the Mineral Resources are
reported additional to, or inclusive of, the Ore Reserves.

The Mineral Resource estimate methodology is described in Sections 2 of this JORC Table 1The
Mineral Resource for the Ionic Rare Earths Makuutu
Project was completed in April 2022 and released by Ionic Rare Earths Ltd on the ASX 3 May 2022
“Substantial Increase To Makuutu Resource To Over 500 Million Tonnes”.

42

Criteria JORC Code explanation Commentary
conversion to
Ore Reserves

The Mineral Resource contains Indicated and Inferred classifications but only the Indicated Mineral
Resource was used to generate the Ore Reserves.

The Mineral Resource was reported using a cut-off grade of 200 parts per million (ppm) TREO
minus CeO2(TREO-CeO2) was used to generate the 2023 Ore Reserves.

The Mineral Resources reported are inclusive of the Ore Reserves for the Project.
Site visits
Comment on any site visits undertaken by the Competent
Person and the outcome of those visits.

If no site visits have been undertaken indicate why this is the
case.

The Competent Persons for the estimation and reporting of Ore Reserves are: Stephen McEwen
(Study Manager), Dr Will Goodall (Principal Metallurgist) and Mr Lee White (Principal Mining
Engineer). The information in this report relating to metallurgical test work results, metallurgical
modelling and metallurgical recoveries applied for calculation of Ore Reserves is based on
information compiled by Dr Goodall. The information in this report relating to Capital and Operating
Cost Estimations and Engineering Study is based on information compiled by Mr McEwen. Mr.
McEwen is engaged as an internal consultant to Ionic Rare Earths Limited and is a Member of the
Australian Institute of Mining and Metallurgy (AusIMM).

Mr White is an employee of Kalem Group Pty Ltd, a Member of the Australian Institute of Mining and
Metallurgy (AusIMM) and engaged as an internal consultant to Ionic Rare Earths Limited. Mr White
conducted a site visit in August 2022.

Dr Goodall is an employee of MinAssist Pty Ltd, a Member of the Australian Institute of Mining and
Metallurgy (AusIMM) and engaged as a consultant to Ionic Rare Earths Limited. Dr Goodall has not
yet visited site but has attended the ANSTO heap column desorption test works and reviewed other
metallurgical test work programmes.

Mr McEwen hasmadenumerous extendedvisits to site during2022.
Study status
The type and level of study undertaken to enable Mineral
Resources to be converted to Ore Reserves.

The Code requires that a study to at least Pre-Feasibility
Study level has been undertaken to convert Mineral
Resources to Ore Reserves. Such studies will have been
carried out and will have determined a mine plan that is
technically achievable and economically viable, and that
material Modifying Factors have been considered.

In March 2023, Ionic Rare Earths completed a Definitive Feasibility Study (DFS) prepared by
Mincore Pty Ltd, Ionic Rare Earths Ltd employees and other internal and external consultants.

The project consists of mining and processing of 5 Mtpa of rare earth ore containing ionic
adsorption clay (IAC) deposits in Uganda. The mineralisation is processed via simple heap leach
desorption of the IAC ore using a salt desorption to produce a mixed rare earth carbonate (MREC)
intermediate product that is the filtered, dried and bagged for sale to downstream REE separation
and refining. The product will be a MREC, a chemical precipitate with a nominal REO content
exceeding 90% REO grade. The leach residues will be reclaimed from spent heap leach stockpiles
and rehabilitated back into open cut pit voids.

The project development consists of an open cut operation, hydrometallurgical processing plant
and associated infrastructure, including:
o
Haul Truck Site Roads
o
Agglomerator.
o
Materials Handling.
o
Heap Desorption Leach pads and ponds.
o
Impurity Removal, thickener, filter, materials handling, rehabilitation.
o
MREC Precipitation, thickener, filter, drying and bagging of product for transport.
o
Membrane (Nano-filtration) water treatments circuits.
o
Reagent storage and mixing facilities.
o
Services:
Criteria JORC Code explanation Commentary

Potable water; (pumping and piping only);

Process water (pumping and piping only);

Fire water (stand-alone system, pumping and piping);

Air (compressed process and instrument air, low pressure blower air); and

Sewage (system, reticulation and collection).
o
Plant facilities.
o
Central control room and ablutions
o
Plant buildings:

Process offices, first aid and emergency services building;

Laboratory; and

Warehouse and laydown facilities (including Chemical storage area).
o
Access road intersection to the site.
o
Electricity transmission to the project site.
o
Electrical reticulation within the project area to the facilities within scope including reticulation
to the Mining Infrastructure Area.
o
External communications to site and internal communications across site (including data
access and distribution).
o
Reticulation of services (electricity, potable water, fire water, sewage) within the scope.
o
Surface water diversion.
o
Raw water collection and reticulation.
o
Water treatment, sewage treatment and disposal.
o
Putrescible waste, industrial waste and hydrocarbon waste disposal facility and systems.

A detailed and practical mine plan was developed following Multimine optimisation using CAE
NPVS software to determine an economic block models for Makuutu deposits. The Makuutu
deposits were scheduled to meet quality targets and processing constraints. Conventional open pit
miningis planned to usehydraulic excavators and articulated dump trucks.
Cut-off
parameters

The basis of the cut-off grade(s) or quality parameters
applied.

For the 2023 Ore Reserves, a cut-off grade of 200 parts per million (ppm) TREO minus CeO2
(TREO-CeO2) was used to generate the Ore Reserves

Ionic Rare Earths Ltd have completed numerous metallurgical studies on composite samples of
mineralisation at Makuutu as previously announced to the ASX on 18 February 2020, 26 May 2020,
and most recently 4 August 2020. These results together with indicative mining and processing
costs and other cost inputs supports application of a marginal cut-off grade of 200 ppm TREO
(excluding CeO2). This cut-off is comparable to peer projects with similar mineralisation types and
processing assumptions.

Domain 1,2,3 – Cover zone, and Domain 8,9 – Basement zone are all classified as waste prior to pit
optimisation.
Mining factors or
assumptions

The method and assumptions used as reported in the Pre-
Feasibility or Feasibility Study to convert the Mineral
Resource to an Ore Reserve (i.e. either by application of
appropriate factors by optimisation or by preliminary or
_detailed design). _

The economic portions of the Mineral Resources were converted to Ore Reserves from pit
optimisation, mine scheduling and pit design studies.

Ionic Rare Earths proposes to mine the Makuutu Deposits by conventional open pit mining methods
using a selective mining approach.

Miningof Ore isplanned to be undertaken on 2 m benches.
Criteria JORC Code explanation Commentary

The choice, nature and appropriateness of the selected
mining method(s) and other mining parameters including
associated design issues such as pre-strip, access, etc.

The assumptions made regarding geotechnical parameters
(eg pit slopes, stope sizes, etc), grade control and pre-
production drilling.

The major assumptions made and Mineral Resource model
used for pit and stope optimisation (if appropriate).

The mining dilution factors used.

The mining recovery factors used.

Any minimum mining widths used.

The manner in which Inferred Mineral Resources are utilised
in mining studies and the sensitivity of the outcome to their
inclusion.

The infrastructure requirements of the selected mining
methods.

The mine designs include pits, haul roads, dump and stockpile designs and water management
bunds and dams.

An allowance for grade control and pre-production drilling was included in the mining cost.

A regularised mining block model, as distinct from the sub-blocked resource model, was developed
from the resource model by the application of a regular block size and estimation of the Mineral
Resource model to a Standard Mining Unit (SMU) mining block model;

An SMU of 10.0 m (X) by 10.0m (Y) by 2.0 m (Z) was used for the Makuutu Deposits. Grades were
re-estimated into the SMU but no other dilution is applied other than the inherent dilution built
within the geological modelling as precursor to the Resource Modelling and Estimation. Appropriate
factors have been added to the regularised mining block model, which has been optimised using
Datamine NPVS Optimisation software. The resultant optimal shell was then used as the basis for
the detailed design to include pit wall angles and access ramps.

The Ore Reserve model is a recoverable reserve estimate that considers estimation of dilution and
ore losses in the estimation based on a SMU.

The Makuutu Feasibility Study considered infrastructure requirements associated with the
conventional excavator and truck mining operations.
including: heap leach and conveying systems, dump & stockpile locations, plant and maintenance
facilities, access routes, fuel, water and power, etc

Mining will involve a pre-strip of 1m of topsoil which will be stockpiled adjacent to the pit. ROM
mining will be selective with lower recovered rare earth grade open pit material stockpiled adjacent
to the pit, whilst waste will be mined and paddock dumped adjacent to the pit. Open pit material will
be hauled to the process plant. Once areas are completely mined out, the mined waste and heap
desorption leach residue will be reclaimed and the mining void will be backfilled (progressive
rehabilitation), priorto the topsoilspread backonthe area disturbed.
Metallurgical
factors or
assumptions

The metallurgical process proposed and the appropriateness
of that process to the style of mineralisation.

Whether the metallurgical process is well-tested technology
or novel in nature.

The nature, amount and representativeness of metallurgical
test work undertaken, the nature of the metallurgical
domaining applied and the corresponding metallurgical
recovery factors applied.

Any assumptions or allowances made for deleterious
elements.

The existence of any bulk sample or pilot scale test work and
the degree to which such samples are considered
representative of the orebody as a whole.

For minerals that are defined by a specification, has the ore
reserve estimation been based on the appropriate
mineralogy to meet the specifications?

The proposed metallurgical process for the Makuutu ore will apply heap desorption leach extraction
with membrane solution purification and staged carbonate precipitation. This process has been
demonstrated in the laboratory to be appropriate for the ionic adsorption clay style deposit present
at Makuutu.

Heap desorption leach extraction and staged carbonate precipitation are both mature processing
technologies that have been used extensively at commercial scale on ionic adsorption clay style
deposits in China as an appropriate method of extracting rare earth elements from this type of ore.
Membrane liquid separation is a mature processing technology that is used extensively on a
commercial scale in many industrial applications, but is considered novel for the concentration and
purification of rare earth elements leached from ionic adsorption clay style deposits.

Significant metallurgical test work has been undertaken on Makuutu samples to support the
selected recovery factors. These include:
o
Head characterisation (ALS Metallurgy, ANSTO Minerals, BV Minerals, SGS Lakefield)
o
Bottle roll desorption leaches (712 tests at ALS Metallurgy and 330 tests at BV Minerals)
o
Column desorption leaches, mostly at 3 m height, but up to 5 m height (39 tests at BV
Minerals and 20 tests at ANSTO Minerals)
o
Agglomerationtesting (16 tests atBV Minerals,10 tests atANSTOMinerals, and18 tests
Criteria JORC Code explanation Commentary
at HydroGeoSense)
o
Nanofiltration testing (Ecotechnol)
o
Precipitation testing (124 tests at ALS Metallurgy)
o
Material handling testing (Jenike and Johanson)

A variability bottle roll program was performed incorporating 528 drill intervals from various
locations across RL1693. TREE-Ce extraction values ranged from 2%-83%.

A variability column desorption leach program was performed using 3 m columns and incorporating
22 composite samples from RL1693. Composites were prepared based on geographical domains
and regolith types. TREE-Ce extraction values ranged from 24%-53%.

Two separate bulk samples were tested at two separate laboratories (ANSTO Minerals and BV
Minerals) to confirm the suitability of heap desorption leaching for the Makuutu Ore. The samples
constituting the composites were prepared from a range of intervals sourced from RL 1693, and
were selected based on a wide spatial location and targeted proportions of regolith types
approximately equal to the Resource tonnages. The samples were prepared, agglomerated, and
loaded into 5 m columns, with test masses being 65-67 kg on a dry basis. Successful irrigation of
these bulk samples and extraction of rare earth elements provided assurance that the processes
are suitable for the Makuutu Ore. Pregnant desorption liquor solution recovered from these bulk
tests was used for nanofiltration testing and precipitation testing.

The reagent consumption values for sulfuric acid, ammonium sulfate, and ammonium carbonate
were derived from SysCAD simulation of the process. Inputs to the SysCAD model were taken from
Makuutu test work results and thermodynamic data included with the software.

Based on the results of the metallurgical testing and process modelling, average overall recovery
estimates for each rare earth oxide are given in the table below:
La2O3
24%
Dy2O3
49%
CeO2
10%
Ho2O3
49%
Pr6O11
28%
Er2O3
51%
Nd2O3
33%
Tm2O3
45%
Sm2O3
33%
Yb2O3
43%
Eu2O3
38%
Lu2O3
46%
Gd2O3
45%
Y2O3
52%
Tb4O7
45%
Sc2O3
10%

Deleterious elements for the Makuutu Project are present in the form of semi-soluble gangue
minerals that cannot be easily separated, or constitute, the minerals of interest. These deleterious
elements include aluminium, calcium, iron, silicon, thorium, uranium, and zinc, all of which are
presentinthe pregnantliquorsolutionto some extent. These deleteriousminerals arerejected

46

Criteria JORC Code explanation Commentary
using membrane solution purification and staged carbonate precipitation, which allow production of
amarketablemixedrare earthcarbonate product.
Environmental
The status of studies of potential environmental impacts of
the mining and processing operation. Details of waste rock
characterisation and the consideration of potential sites,
status of design options considered and, where applicable,
the status of approvals for process residue storage and waste
dumps should be reported.

All required environmental approvals from the Ugandan Government were received in October
2022 for the Makuutu deposits following the approval of the Environment Impact Study Analysis
(ESIA) for the development of mining and processing infrastructure in Uganda.

Mining will involve a pre-strip of 1m of topsoil which will be stockpiled adjacent to the pit. ROM
mining will be selective with lower recovered rare earth grade open pit material stockpiled adjacent
to the pit, whilst waste will be mined and paddock dumped adjacent to the pit. Open pit material will
be hauled to the Run-of-Mine (ROM) pad and either stockpiled or direct fed into the process plant.
Once areas are completely mined out, the mined waste and heap leach residue will be reclaimed
and the slot will be backfilled (progressive rehabilitation), prior to the topsoil spread back on the
area disturbed.
Infrastructure
The existence of appropriate infrastructure: availability of
land for plant development, power, water, transportation
(particularly for bulk commodities), labour, accommodation;
or the ease with which the infrastructure can be provided, or
accessed.

Mining of the Makuutu deposits is dependent on new development of the following infrastructure:
o
Open cut operations, haul roads, hydrometallurgical processing plant and associated
infrastructure, reagent storage, and
o
Power reticulation to the mine site from Iganga-Busesa towns.

The capital costs for this infrastructure were estimated within the DFS.

Transport of all bulk commodities and reagents to site are via road delivered into Mombasa, Kenya
and to site, with the main transport routes identified. Acid is proposed to be supplied from an
existing sulphuric acid producerontheKenya-Ugandanborder.
Costs
The derivation of, or assumptions made, regarding projected
capital costs in the study.

The methodology used to estimate operating costs.

Allowances made for the content of deleterious elements.

The source of exchange rates used in the study.

Derivation of transportation charges.

The basis for forecasting or source of treatment and refining
charges, penalties for failure to meet specification, etc.

The allowances made for royalties payable, both Government
and private.

Ionic Rare Earths developed a detailed project financial capital and operating model for the Project.

The capital costs were estimated within the DFS by Mincore Pty Ltd and Ionic Rare Earths with
expected accuracy of -10% to +15%.

Operating costs were estimated within the DFS and included allowances for mining, administration,
reagent costs, transport to Mombasa and shipping to rare earth refineries; a nominated east coast of
the USA.

Freight prices are derived from an independent logistic consultant for the DFS and include port costs
and charges, road and sea transportation.

A range of forecast long-term rare earth prices were provided by leading external economic
forecasters (Adamas Intelligence) were used in the financial modelling.

Exchange rates are derived from external economic forecasters.

The DFS assumes that a Mixed Rare Earth Carbonate (MREC) containing scandium will be produced
on site and sent to a refinery for processing. No allowances were made for penalties for failure to
meet specification.

Financial commitments are outlined in the Mining Act by the Ugandan Government. These have
been incorporated in the detailed project financial model including production royalties at the rate of
5% of mine-gate grossrevenueforUganda.
Revenue factors
The derivation of, or assumptions made regarding revenue
factors including head grade, metal or commodity price(s)
exchange rates, transportation and treatment charges,
penalties, net smelter returns, etc.

Financial assumptions used in cost modelling include: - A range of forecast long-term rare earth
prices provided by leading external economic forecasters was considered. Ionic used US$120.81/kg
as its’ long-term rare earth basket price, excluding Sc2O3.

A longterm Sc2O3 price of$775/kghas been applied based on leadingexternal economic
Criteria JORC Code explanation Commentary

The derivation of assumptions made of metal or commodity
price(s), for the principal metals, minerals and co-products.
forecasters. Assumption is that the Sc2O3is purity 99.9%.

A payability factor of 70 per cent of the forecast rare earth and scandium prices has been applied for
calculating revenue.

As IonicRE is targeting selling MREC ex-China prices should be taken at face value.

No impurity penalties have been applied. Assuming all elements contained in the MREC attract the
highest prices in the market – that is high purity carbonate/oxides.

Rare Earth and Scandium production and product quality are derived from the Life of Mine (LOM)
schedule.
Market
assessment

The demand, supply and stock situation for the particular
commodity, consumption trends and factors likely to affect
supply and demand into the future.

A customer and competitor analysis along with the
identification of likely market windows for the product.

Price and volume forecasts and the basis for these forecasts.

For industrial minerals the customer specification, testing and
acceptance requirements prior to a supply contract.

From 2022 through 2035, global demand for neodymium magnet (NdFeB magnets) is anticipated to
increase bolstered by double-digit growth from electric vehicle and wind power sectors, translating
to comparable demand growth for the rare earths elements (i.e., neodymium, praseodymium,
dysprosium, and terbium) these magnets contain.

Over the same period, global production of neodymium, praseodymium, dysprosium, and terbium
will collectively increase as the supply side of the market increasingly struggles to keep up with
rapidly growing demand.

From 2023 through 2035, the global rare earth industry is anticipated to consistently underproduce
neodymium, praseodymium, dysprosium and terbium oxides (or oxide equivalents), resulting in the
depletion of historically accumulated inventories and, ultimately, shortages of these critical magnet
materials if supply is not increased beyond levels currently anticipated.

The Makuutu project offers broad economic exposure to the rare earth permanent magnet sector,
which is the fastest-growing end-use category and most in need of additional rare earth supplies.

From a marketing, logistics and economic standpoint, the high proportion of valuable magnet-
related rare earth elements in the Makuutu Project's prospective TREO production means that a
future mine (with separation) could generate approximately 83% of its rare earths revenues from just
31% of its production volume (NdPr, Dy and Tb oxide).

Financial modelling in real terms, including sensitivity analysis, was also completed. This shows that
Makuuturemains economicallyviable at US$53.37/kgrare earthbasket price.
Economic
The inputs to the economic analysis to produce the net
present value (NPV) in the study, the source and confidence
of these economic inputs including estimated inflation,
discount rate, etc.

NPV ranges and sensitivity to variations in the significant
_assumptions and inputs. _

LOM financial model demonstrates that, based on the assumptions set out above, the Makuutu Rare
Earths Project will generate significant Net Present Value (NPV) after tax using a discount rate of 8%.

The NPV is most sensitive to Rare Earth and scandium prices, metallurgical recoveries, operating
cost and capital costs.
Social
The status of agreements with key stakeholders and matters
leading to social licence to operate.

Ionic Rare Earths, through Rwenzori Rare Metals Ltd, has been exploring and undertaking project
development activities in the Republic of Uganda since 2019 respectively and has a good
relationship with the local community and key stakeholders.

Rwenzori Rare Metals Ltd, has been operational in Uganda and working on the Makuutu Rare Earths
Project since 2016, and has a significant Ugandan workforce.

The Company, via RRM, has initiated the next phase of land access agreements over the MLA at RL
1693, to agree a staged development at Makuutu with local landowners. Discussions and
engagementwith landowners are progressingwelland the Companywillupdate themarket
Criteria JORC Code explanation Commentary
accordingly
Other
To the extent relevant, the impact of the following on the
project and/or on the estimation and classification of the Ore
Reserves:

Any identified material naturally occurring risks.

The status of material legal agreements and marketing
arrangements.

The status of governmental agreements and approvals
critical to the viability of the project, such as mineral
tenement status, and government and statutory approvals.
There must be reasonable grounds to expect that all
necessary Government approvals will be received within the
timeframes anticipated in the Pre-Feasibility or Feasibility
study. Highlight and discuss the materiality of any unresolved
matter that is dependent on a third party on which extraction
of the reserve is contingent.

Major risks are Rare Earth price variation, failure of the western Rare Earth supply chain to mature
due to a lack of investment in downstream capacity, delays in construction and ramp up of
operations, foreign exchange rates, capital cost of the project, foreign jurisdiction and political,
production and operational risks.

The main Makuutu Deposits (Central Makuutu and Central Makuutu East) containing majority of the
Mineral Resources and Ore Reserves are located in Uganda on Retention Licence 1693. This permit
was granted to Rwenzori Rare Metals (a Ugandan subsidiary) on 2 November 2017 for an initial
period of 3 years and was renewed (2 November 2020) for another 2 years. On 1stSeptember 2022,
Rwenzori Rare Metals Ltd applied for a Mining licence (MLA TN03834) over RL1693, itis anticipated
that this will be granted during Q2 2023.

The other Makuutu deposits containing the remaining Mineral Resources are contained in retention
licences (RL00234 and RL00007) and are in good standing.

Land Ownership is developed established through Land Access Agreements. The Company, via
RRM, has initiated the next phase of land access agreements over the MLA at RL 1693, to agree a
staged development at Makuutu with local landowners. Discussions and engagement with
landowners are progressingwelland the Companywillupdate themarket accordingly
Classification
The basis for the classification of the Ore Reserves into
varying confidence categories.

Whether the result appropriately reflects the Competent
Person’s view of the deposit.

The proportion of Probable Ore Reserves that have been
derived from Measured Mineral Resources (if any).

A total of 172.9 million tonnes of Ore Reserves, with a TREO grade of 848 ppm, have been classified
as Probable. The Ore Reserves were based on the current RL 1693 inventory of Indicated Mineral
Resources only (comprising 259 million tonnes grading 740 ppm TREO).

Mr Lee White, Mr Stephen McEwen and Mr Will Goodall are satisfied that the stated Probable Ore
Reserves accurately reflect the outcome of mine planning and the input of economic parameters and
metallurgical recoveries into pit optimisation studies.

TherewerenoMeasuredMineral Resources.
Audits or reviews
The results of any audits or reviews of Ore Reserve
_estimates. _

No audit or review has been undertaken.
Discussion of
relative
accuracy/
confidence

Where appropriate a statement of the relative accuracy and
confidence level in the Ore Reserve estimate using an
approach or procedure deemed appropriate by the
Competent Person. For example, the application of statistical
or geostatistical procedures to quantify the relative accuracy
of the reserve within stated confidence limits, or, if such an
approach is not deemed appropriate, a qualitative discussion
of the factors which could affect the relative accuracy and
confidence of the estimate.

The statement should specify whether it relates to global or
local estimates, and, if local, state the relevant tonnages,
which should be relevant to technical and economic
evaluation. Documentation should include assumptions made
and the procedures used.

Accuracy and confidence discussions should extend to

The Ore Reserve estimate is the outcome of a study undertaken to a Feasibility Study level with
geological, metallurgical, geotechnical, engineering and mining engineering considerations. It has a
nominal accuracy of ± 15% and applies to global estimates.

Certain statements concerning the economic outlook for the Rare Earths mining industry, financing a
large capital project, expectations regarding Rare Earths, production, cash costs and to the
operating results, growth prospects and the outlook of IonicRE’s operations including the likely
financing and commencement of commercial operations of the Makuutu Rare Earths Project and its
liquidity and capital sources and expenditure, contain or comprise certain forward-looking
statements regarding IonicRE’s operations, economic performance and financial condition. No
assurance can be given that such expectations will prove to have been correct. Accordingly, results
could differ materially from those set out as a result of, among other factors: changes in economic
and market conditions, deterioration in the rare earth market, deterioration in debt and equity
markets that lead to the Project not being able to be financed, success of business and operating
initiatives, changes in the regulatory environment and other government action, fluctuations.
Criteria JORC Code explanation Commentary
specific discussions of any applied Modifying Factors that
may have a material impact on Ore Reserve viability, or for
which there are remaining areas of uncertainty at the current
study stage.
It is recognised that this may not be possible or appropriate
in all circumstances. These statements of relative accuracy
and confidence of the estimate should be compared with
_production data, where available. _
50