IMAGE RESOURCES NL Investor Presentation 2007

Aug 6, 2007

65117_rns_2007-08-06_53a0dcd3-c989-41d2-b90e-a25ca66c92a3.pdf

Investor Presentation

Open in viewer

Opens in your device viewer

DIGGERS & DEALERS AUGUST 2007 GEORGE SAKALIDIS MANAGING DIRECTOR

FORWARD LOOKING STATEMENTS

This presentation contains forecasts and forward looking statements which are made in good faith and are believed to have reasonable basis.

However, such forward looking statements are subject to risks, uncertainties and other factors which could cause the actual results to differ materially from the future results expressed, projected or implied by forward looking statements.

HISTORY

¾ Aeromagnetic database second only to Rio Tinto ¾ Discoveries ¾ Magnetic Minerals listed 2000

  • ¾ Image Resources listed July 2002
  • ¾ Meteoric Resources listed July 2004
  • ¾ Magnetic Resources listed April 2007
  • ¾ Potential Nickel float late 2007

  • Quality Heavy Mineral and Ni projects
  • New HM discoveries at Cooljarloo and Cooljarloo North with major resources being defined
  • Expanding HM ground position (1850sq km) in North Perth Basin
  • Emu Lake high grade nickel sulphide project potential float
  • Experienced management with discovery track record

DIRECTORS

  • George Sakalidis: Managing Director, Geophysicist, 29 yrs exp.
  • Roger Thomson: Executive Director, Geologist, 40 yrs exp.
  • Peter Thomas: Chairman, Mining Lawyer, 27 yrs exp.

MINERAL SANDS NORTH PERTH BASIN

  • Image represents a new opportunity for new mineral sands resource development in the province
  • Magnetic mapping has not been used widely. Southern end of North Perth Basin still poorly mapped.
  • Over 20% of annual world production of zircon
  • Excellent Infrastructure
  • New acquisition opportunities
  • Image with 1850 sq km is the largest tenement holder. Cooljarloo area represents only 6% of Images ground position

COOLJARLOO HISTORICAL

  • Strategic location close to established infrastructure and world class operating mines
  • 3 strands with historical resources of 2.4 Mt of concentrate (pre 1990) which cover over 12km of strike length
Deposit Resource
Tonnes
Grade
(%)
HM
Tonnes
Ilmenite
Tonnes
Rutile
Tonnes
Leucoxene
Tonnes
Zircon
Tonnes
28,000 850,000 8.6
73,000
25,000 8,000 6,700 9,800
Mid-level 49,000,000 2.3 1,127,000 531,000 96,000 60,500 91,000
35 AHD 30,860,000 4.0 1,234,000 na na na na
Total 80,710,000 3.0 2,434,000

MAGNETIC MAPPING PROGRESS

Project Aeromagnetic
Target Length
Groundmag
Completed
Groundmag
Target Length
Bidaminna 80 % 42 km
Bootine 87 km 25 % In progress
Cataby West 20 km 80% In progress
Gingin 30 km 10 % In progress
Quinns Hill 10 % In progress
McKinley 40 % 12 km

IMAGE PROJECTS RESOURCE POTENTIAL

Project Resource(M
t)
Zircon +
Rutile
Grade HMC
(Mt)
Cut-of
Grade
Cash Flow Cap Ex
(M)
NPV
(M)
IRR
(%)
Market
Cap
Dongara (MGE) 182 23-41% 5.0% 9.1 2.0% 273M/12
years
\$71 \$63 76 25M
Other Projects
(IMA)*
50-200 4-6% 5-20
Cooljarloo
Cooljarloo North
(IMA)*
200-400 5% 10-20 160M

*targeted tonnage and grade

  • Image's market cap has factored in the potential of the Cooljarloo 28000,35AHD, channel and of the Cooljarloo North Target 1
  • Further channels and high grade shallow strands are expected after further drilling of the 42 km of targets and of Image's other extensive projects

EUCLA BASIN

  • Zircon rich discovery on Image's tenement boundary
  • 28km paleocoastline
  • 2.3km mineralised coastline discovered by Diatreme on tenement boundary
  • Prospective shoreline thickens to 9km in width on Image ground
  • Access agreements in progress
  • Ground magnetics/aircore drilling planned

EMU LAKE Ni PROJECT
GOSSAN ZONE DRILL INTERSECTIONS
Hole No From
(m)
To
(m)
Interval
(m)
Ni
%
Cu
%
Pt
ppb
Pd
ppb
Pt+Pd g/t
ELD 5 256.40 256.70 0.3 7.55 0.35 1015 1726 2.74
258.22 258.35 0.13 0.34 21.3 1355 1659 3.01
258.60 259.90 1.3 1.11 0.18 125 351 0.48
277.06 277.23 0.17 7.08 6.46 1092 2315 3.41
ELRC 10 192.0 193.0 1.0 2.28 0.20 350 718 1.07
ELD 11 364.05 364.10 0.05 3.55 0.01 205 745 0.95
ELD 15 336.0 338.0 2.0 6.20 1.78 749 1424 2.17
343.5 345.5 2.0 2.63 1.05 237 3953 4.19
ELD 16 377.07 377.35 0.28 6.66 0.24 423 226 0.65
ELD 17 269.50 269.81 0.31 1.11 0.14 104 197 0.30
ELD 18 302.57 303.65 1.08 1.52 0.20 166 291 0.46
302.57 302.68 0.11 3.95 0.18 632 723 1.35
ELD 21 366.50 366.65 0.15 7.54 0.11 928 1310 2.24
ELD 25 346.60 346.70 0.10 10.9 757 4.17
ELD 26 414.10 414.21 0.11 1.94 830 0.20
414.53 414.58 0.05 2.42 668 0.52

TIMETABLE

Project Activity Date
Cooljarloo Air Core Drilling/Pre Feasibility Aug-Sept 2007
Cooljarloo North Air Core Drilling/Pre Feasibility Aug- Sept 2007
Gingin, Bootine, Quinns Ground Mag Aug-Sept 2007
Bidaminna Air Core Drilling Sept 2007
Emu Lake Deep Drilling and potential IPO Late 2007
My Hays Auger Drilling Aug 2007
Lookout Well RAB Drilling Aug 2007

SUMMARY

  • Increasing focus on Mineral Sands
  • Potential major high grade discovery at Cooljarloo and Cooljarloo North
  • Largest HM land holder North Perth Basin
  • Potential Nickel float, generous benefits to existing Image shareholders
  • Tightly held stock: Top 5 hold 50% (long term investors)
  • Planned Resource Studies and Exploration over extensive HM ground in North Perth Basin