Tropicana Gold Mine Analysts Visit – 5 August, 2012
==> picture [211 x 91] intentionally omitted <==
AngloGold Ashanti Australia Ltd ABN 42 008 737 424
==> picture [135 x 74] intentionally omitted <==
Independence Group NL ABN 46 092 786 304
Tropicana Gold Project - summary
Location: 330 km east-north east of Kalgoorlie in Western Australia
Ownership: AngloGold Ashanti Australia Ltd 70% and manager; Independence Group NL 30%
Discovered: 2005
Approved: November 2010
First Gold Production: December Quarter 2013
Mine Life (approved project): 10+ years
Employment: 550 construction workers and 450 during operations. FIFO operations out of Perth & Kalgoorlie, mostly on an 8-and-6 roster for operations employees
==> picture [387 x 436] intentionally omitted <==
1
Tropicana Gold Project – approved project* parameters
Capital Cost: A$690-A$740 million (real)
Annual Production first three years: 470,000490,000 ounces
LOM Production: 3.45 million ounces
Cash Costs first three years: A$580/oz-A$600/oz
LOM Cash Costs : A$710/oz-730/oz
Ore Reserves (as at December 31, 2011): 3.91 Moz
Mineral Resource (as at December 31, 2011): 6.41 Moz
Mining Methods: Conventional open cut with potential for future underground mining
Plant Throughput: 5.8 million tonnes per annum (5.5 Mtpa on fresh material)
==> picture [358 x 506] intentionally omitted <==
2
* 100% project
Tropicana Gold Project – construction safety
==> picture [814 x 393] intentionally omitted <==
3
* 100% project
Tropicana Gold Project – major contracts
EPCM
- Lycopodium
Construction Contracts
-
Mine access road – Lucas (complete)
-
Airstrip and bulk earthworks – Watpac (complete)
-
Village, airport and plant buildings installation – Freo
-
Concrete supply – Holcim
-
Concrete installation – S&N Concrete
-
Structural Mechanical & Piping; Tankage – Pacific Industries Company (PIC)
-
Steel frame buildings – WABG
-
Process water supply pipeline - DSA
-
Tailings Storage Facility – to be awarded
-
Electrical and Instrumentation – to be awarded
Operational Contracts
-
Mining – Macmahon
-
Power Generation – Pacific Energy Ltd
-
Village & Administration – ESS
-
Aviation – Network Aviation, Goldfields Air Services
-
Dayworks Services - Bundarra
-
Tavern and retail services – SMC
-
Cross-cultural inductions – Triodia
-
Light Vehicle Workshop – to be awarded
==> picture [260 x 509] intentionally omitted <==
4
Tropicana Gold Project – organisation structure operations
==> picture [800 x 250] intentionally omitted <==
Operational recruitment status
-
Management team in place – critical roles filled early to establish systems and processes
-
First phase of recruitment focused on mining, geology, sustainability and business support roles
-
Second phase will focus on processing and maintenance
-
Transfer of some personnel from AngloGold Ashanti Australia’s Sunrise Dam mine
-
Sunrise Dam used to train processing personnel
5
Tropicana Gold Project – infrastructure status
-
220 km road from Pinjin to Tropicana completed
-
Microwave communications installed
-
Airstrip work almost complete and CASA approval for landing of 100 seat jets expected in the September quarter
-
350 permanent village rooms complete; dry mess and wet mess operational; village complete in September quarter
-
Waste water plant commissioned
-
First wing of administration buildings commissioned; second wing installed
-
Medical clinic operational
-
Process water supply borefield pipeline commenced
-
Powerhouse construction commenced
==> picture [242 x 174] intentionally omitted <==
==> picture [241 x 162] intentionally omitted <==
==> picture [241 x 191] intentionally omitted <==
6
Tropicana Gold Project – plant construction status
-
Process plant engineering design and drafting complete
-
Plant bulk earthworks complete
-
Concrete installation for primary crusher, crusher reclaim, ball mill and HPGR in progress
-
CIL tank concrete foundations in place and all eight base plates installed, tankage installation in progress
-
Off-site tankage fabrication nearing completion
-
Structural, mechanical & piping work scheduled to begin in September quarter
-
Steel-framed workshop/warehouse building erection underway
==> picture [283 x 174] intentionally omitted <==
==> picture [280 x 147] intentionally omitted <==
==> picture [282 x 213] intentionally omitted <==
7
Tropicana Gold Project – mining status
-
Macmahon fleet mobilised and operational
-
Construction of Mining Services Area facilities continuing with steelworks underway for boilermaker, light vehicle and heavy vehicle workshops
-
Clearing and grubbing of open pit, haul roads, ROM and TFS underway
-
Mining in Havana starter pit has commenced
-
Mining waste utilised for ROM pad and TSF construction
-
MineStar Fleet Management System implementation commissioning nearing completion
• Subcontractors
-
Carey Mining - ancillary equipment and personnel
-
Dyno Nobel – Explosive supply
-
Wallis Drilling – Grade Control
==> picture [300 x 275] intentionally omitted <==
==> picture [300 x 230] intentionally omitted <==
8
Tropicana Gold Project - mining fleet
-
5 x Cat 793 dump trucks
-
3 x Cat 785C dump trucks
-
1 x Cat 6040 excavator
-
2 x Cat D10T dozer
-
1 x Cat D6T dozer
-
1 x Cat 992G loader
-
1 x Cat 966H loader
-
•1 x Cat 773 service truck
-
1 x Cat 777F water cart
-
1 x Cat 988 tyre handler
-
1 x Cat16H grader
-
1 x Cat 16M grader
-
1 x Cat CH74 roller
-
1 x Cat 854 wheel dozer
-
1 x Cat 24M grader mobilising in Sept
-
1 x Cat MD6240 drill
-
(SKFX) mobilising in Sept
==> picture [346 x 260] intentionally omitted <==
9
Tropicana Gold Project - processing plant
==> picture [715 x 505] intentionally omitted <==
----- Start of picture text -----
Mining Area
ROM
HV Workshop Primary Crusher
Offices
Secondary Crusher
Ball Mill
HPGR
PowerStation
Emergency
Stockpile
----- End of picture text -----
Tropicana-Havana resource growth
==> picture [440 x 527] intentionally omitted <==
----- Start of picture text -----
Open Pit Reserve &
Resource (Dec 2010)
----- End of picture text -----
Bankable Feasibility Study Reserve & Resource
Open Pit Proved and Probable Ore Reserve (Dec 2010): 48 Mt @ 2.2 g/t for 3.4 Moz*
Mineral Resource (Dec 2010): 76.5 Mt at 2.15 g/t for 5.28 Moz**
- *Cut off grade of 0.6 g/t for Oxide and Sap-Rock materials and
0.7 g/t for Fresh materials at a nominated gold price of US$880/oz and an AUD:USD exchange rate of 0.80 (equiv to A$1,100/oz at the time)
- ** At a gold price of US$1,600/oz and an AUD:USD exchange rate of 1.14
Tropicana-Havana resource growth
June 2011 Reserve & Resource Update
Open Pit Proved & Probable Ore Reserve (June 2011): 56.4 Mt at 2.16 g/t for 3.91 Moz
Open Pit Mineral Resource (June 2011): 73.3 Mt at 2.01 g/t for 4.73 Moz
Underground Mineral Resource (June 2011): 5.3 Mt at 3.65 g/t for 0.63 Moz
Total Mineral Resource: 78.6 Mt at 2.12 g/t for 5.36 Moz
Open Pit Reserve & Resource (June 2011 & Dec 2011)
==> picture [32 x 37] intentionally omitted <==
Underground Resource (June 2011 & Dec 2011)
December 2011 Reserve & Resource Update
Open Pit Reserve (June 2011): 3.91 Moz
Open Pit Mineral Resource (Dec 2011): 74.5 Mt at 1.99 g/t for 4.78 Moz
Underground Resource (Dec 2011): 13.8 Mt at 3.67 g/t for 1.63 Moz
Total Mineral Resource: 88.3 Mt at 2.26 g/t for 6.41 Moz
Tropicana-Havana resource growth
==> picture [490 x 528] intentionally omitted <==
----- Start of picture text -----
OPEN
Potential expanded open
pit resource
Underground outside expanded
open pit resource
Potential additional
underground resource
----- End of picture text -----
Havana Deeps
-
Completion of Havana Deeps drilling in Sept quarter
-
Resource model update to be completed at year end
-
Completion of Havana Deeps PFS mid2013
Exploration
-
Drill testing north of Boston Shaker
-
Follow up drilling of intercepts at Springbok
Havana Deeps Pre-feasibility Study drilling
==> picture [713 x 509] intentionally omitted <==
14
Near-mine exploration – phase one RC drilling traverses