TROPICANA JV COMMITS TO LONG ISLAND AND INCREASED MILLING CAPACITY

Independence Group NL (IGO or the Company) (ASX:IGO) is pleased to announce that the Tropicana Joint Venture (TJV) has committed to both the Long Island mining strategy and a process plant improvement project to further increase processing plant capacity and improve metallurgical recovery. The TJV is an unincorporated partnership between AngloGold Ashanti Australia (AGAA)(ASX: AGG) (Manager and 70% interest) and IGO (30% interest).

Key Highlights

  • Long Island mining strategy will proceed resulting in the extension of the operation life through to CY27.

  • Process plant improvements will increase throughput to 8.1Mtpa and improve metallurgical recovery by up to 3%.

  • Ore Reserves have increased to 4.08Moz (100% basis) as at 31 December 2017.

  • Drilling underway at Boston Shaker confirms the deeper continuity of high-grade ore-shoots which will form the basis of underground mining studies.

  • Regional exploration around Tropicana and within the broader Fraser Range region continues to be a key focus.

IGO’s Managing Director, Peter Bradford, commented: “We continue to optimise our operations and maximise the business by delivering both increased production rates and extending the mine life at Tropicana through the multiple work programs underway over the last few years.

“The accelerated mining strategy deployed in the 2017 calendar year should deliver elevated gold production rates for the next two years, commencing this 2018 financial year and resulting in higher free cash flow to IGO.

“The Long Island mining strategy, which is now approved as part of the Joint Venture 2018 Business Plan, has delivered an Ore Reserve of 4.08Moz and extended the life-of-mine through to the 2027 calendar year.

“Capital costs associated with Long Island are estimated at A$18M on a 100% basis, limited to the expansion of site infrastructure, including accommodation and workshops. Costs for the expansion of the mining fleet to increase annual mining capacity will be borne by the mining contractor, Macmahon. Mining capacity will increase from an estimated 90Mt this year to a peak of 107Mtpa in the 2019 calendar year, and continue at that rate for about four years and then gradually reduce.

“Coupled with Long Island, the Joint Venture has also approved the addition of a new ball mill which will deliver an increase in mill throughput capacity to 8.1Mtpa along with improved metallurgical recoveries. The total capital costs are estimated at A$28M on a 100% basis and are expected to

PAGE 1

==> picture [595 x 82] intentionally omitted <==

have a pay-back of less than twelve months. The expansion work is scheduled to be completed in the upcoming 2018 calendar year.

“This is a great result for our business and for the Joint Venture, with Tropicana continuing to deliver strong results that bolster IGO’s portfolio of operations reflecting high-quality, long life assets. We congratulate AngloGold Ashanti and the entire team at Tropicana for their continued hard work and focus on value creation.”

Focus on Unlocking Value

At Tropicana, the Joint Venture partners have pursued multiple work programs that have demonstrated significant additional value to date, with the underground studies and regional exploration expected to unlock additional value going forward.

These work programs have included:

  • Debottlenecking process plant capacity through to end-CY17 from 5.8Mtpa to 7.6Mtpa;

  • Accelerated mining in CY17 to bring value forward and deliver a period of elevated gold production during FY18 to FY20;

  • Long Island mining strategy to extend mine life by understanding the resource potential beneath the pits;

  • Additional ball mill will further debottleneck the processing plant capacity by the end of CY18 to 8.1Mtpa and increase metallurgical recovery by up to 3%;

  • Underground studies to better understand and unlock further potential beneath the pits within this major mineralised system; and

  • Regional exploration to understand the potential for further discoveries.

Accelerated Mining and Grade Streaming

The Tropicana mining fleet was optimised in late-CY16 with the addition of a 600t face shovel, which resulted in a step change to the mining rate during CY17.

This increased mining rate in CY17 has delivered two outcomes:

  • Accelerated access to ore, resulting in more ore being mined over the next two to three years than required for the process plant. This allows higher grade ore to be preferentially fed to the process plant while stockpiling lower grade ore. As a result, gold production during the period FY18 to FY20 is expected to be at an elevated level; and

  • De-risked the mining volumes required for the Long Island strategy as set out under the “Long Island Mining Strategy” section below.

PAGE 2

==> picture [595 x 82] intentionally omitted <==

==> picture [382 x 196] intentionally omitted <==

----- Start of picture text -----

koz A$/oz
750 1,500
600 1,200
450 900
300 600
150 300
- -
FY17A FY18E FY19E FY20E
Gold produced Gold production forecast range AISC forecast
----- End of picture text -----

Figure 1: LoM Profile for the next three years

Long Island Mining Strategy

Background and Concept

The Long Island mining strategy was conceived in CY15 to unlock the open-pit potential of the extensive Tropicana Mineralised System consisting of multiple mineralised zones offset by post mineralisation faulting. The Tropicana Mineralised System has a strike extent over 5km.

The Long Island mining strategy utilises a strip mining approach designed to significantly reduce waste mining costs through the introduction of short, horizontal hauls to backfill a void in-pit. Initially, a starter pit at Havana was considered to act as a void for waste. However, as planning progressed it became apparent from drilling that there was limited potential beneath the Tropicana pit and that the completed pit under conventional mining practices would provide significant value as a backfill location to commence the Long Island development.

To progress the Long Island strategy, an extensive Mineral Resource definition drill program was completed through CY15 to CY17 to provide a framework for the understanding of the Tropicana Mineralised System. In total, 193,554m of drilling was completed on a 100 × 100m spacing with 50 × 50m, and later 50 × 25m, drilling on the known plunge of higher-grade ore-shoots.

In CY17, technical and financial studies, including risk assessments, were completed to demonstrate the technical feasibility and economic viability of the Long Island mining strategy.

For further background information, refer to the following IGO ASX Releases:

  • 25 July 2017 titled Tropicana Gold Mine – Delineation of new high-grade shoot.

  • 15 December 2016 titled Tropicana Gold Mine – Value Enhancement Update.

  • 6 August 2017 titled Tropicana Gold Mine – Update.

PAGE 3

==> picture [595 x 82] intentionally omitted <==

==> picture [482 x 223] intentionally omitted <==

Figure 2: Tropicana Gold Mine showing mineralisation and pits over a 5km strike with current Mineral Resource and Ore Reserve open pits.

Long Island Mining Implementation

The Long Island concept provides optionality and flexibility, with eight mining stages and three decision points (see Figures 3 and 4 ) giving the opportunity to adjust to changing economic conditions.

Long Island Phase One, which has been approved as part of the CY18 Business Plan, requires mining of Havana South Pit and a cutback of the Boston Shaker Pit. The next decision points occur in CY20 with the commencement of mining of the Havana Main Pit strip and in CY22 with the final stages of Havana Main Pit.

Mining rates at Tropicana have risen over the past year to more than 90Mtpa with the addition in late CY16 of a 600-tonne face shovel. The higher mining rate in CY17 has de-risked the increase in mining rate of between 95 -107Mtpa required for the Long Island mining strategy.

Mining rates will peak at 107Mtpa in CY19 and will continue at that rate for four years until the bulk of the Havana Pit is mined.

To achieve the additional material movement increase, a second 600t face shovel with up to five additional Caterpillar 793 trucks and supporting ancillary equipment will be added to the mining fleet. This additional fleet will be provided by Macmahon Holdings as part of the existing mining contract at the site.

The capital expenditure to the owners related to the implementation of the Long Island strategy will be approximately A$18M (on a 100% basis), primarily for expansions to the accommodation camp and heavy vehicle workshop infrastructure.

Productivity improvements through AGAA’s Operational Excellence program have resulted in a reduction in mining costs at Tropicana over the past two years to A$3.07/t mined using conventional mining methods. It is anticipated that ongoing mining efficiencies will further reduce mining costs by 5-10% during Phase One.

PAGE 4

==> picture [595 x 82] intentionally omitted <==

==> picture [356 x 400] intentionally omitted <==

Figure 3: Image showing; A) current mining; B) the Long Island pit shapes, and C) the Long Island commitment decision points.

Risk Mitigation and Phasing of Decisions

Given the time horizon over which the Long Island pits will be mined, three decision points have been built into the mining plan so that final pit designs at each decision point stage can be optimised to reflect any change to revenue and cost assumptions. The three phases of the implementation of the Long Island mining strategy are depicted in Figure 4.

PAGE 5

==> picture [595 x 82] intentionally omitted <==

==> picture [449 x 182] intentionally omitted <==

Figure 4: Forecast planning calendar reflecting the three implementation phases of the Long Island mining strategy.

Process Plant Optimisation

Background

The Tropicana process plant was designed with a nameplate capacity of 5.8Mtpa on a blend of soft and hard rock (5.5Mtpa on hard rock only). Since then, the process plant throughput rate has been increased by approximately 31% to 7.6Mtpa through a number of debottlenecking projects including:

  • upgrading of conveyors;

  • installation of additional carbon-in-leach tanks;

  • installation of additional raw materials infrastructure and capacity;

  • improved processing plant reliability; and

  • commissioning of a fines pulping facility in November 2017 to deliver improved efficiency and throughput by minimising downtime during maintenance shutdowns.

Additional Ball Mill Installation

In CY18, a 6MW ball mill will be installed in the Tropicana processing plant grinding circuit to supplement the existing 14MW ball mill. The additional ball mill is designed to increase process plant throughput to 8.1Mtpa. In addition, the increased grinding capacity will enable an improvement in the baseline metallurgical recovery by up to 3% to approximately 92%.

Total capital expenditure is expected to be A$28M (100% basis) including equipment, construction cost and spares and the new mill is scheduled to be commissioned in the December 2018 quarter. The site has adequate power generation capacity to cater for the additional mill and no further infrastructure is required.

The increased throughput will efficiently match processing capacity to the Long Island mining rate, and effectively bring forward gold production delivering the best production profile for the operation. The improved recovery rate will add approximately 160,000oz to recovered gold over the life-ofmine.

Based on mill throughput of 8.1Mtpa and a recovery improvement of 2.7% in the first year, the payback period will be less than twelve months.

PAGE 6

==> picture [595 x 82] intentionally omitted <==

Mineral Resource and Ore Reserve

Mineral Resource

The total Tropicana Mineral Resource (100% basis) as at 31 December 2017 is estimated to contain 143.2Mt grading 1.62g/t Au for 7.45Moz of contained gold compared to 148.1Mt grading 1.68g/t for 8.02Moz as at 31 December 2016.

Table 1: Tropicana Mineral Resource (100% Project) as at 31 December 2017

Area Resource
Classification
Dec-16 Dec-17 **Change **
Mt
g/t
Moz
Mt
g/t
Moz
Mt
g/t
Moz
Open Pit Measured 8.8
1.90
0.54
10.3
1.40
0.46
1.5
-0.50
-0.08
Indicated 81.1
1.61
4.19
86.8
1.58
4.41
5.7
-0.03
0.22
Inferred 22.3
1.32
0.94
9.2
1.17
0.35
-13.1
-0.14
-0.60
Total 112.3
1.57
5.68
106.4
1.53
5.22
-5.9
-0.05
-0.45
Stockpiles Measured 17.2
0.73
0.40
21.1
0.72
0.49
3.9
-0.01
0.09
Underground Measured -
-
-
-
-
-
-
-
-
Indicated 6.8
3.38
0.73
10.1
3.57
1.16
3.3
0.20
0.42
Inferred 11.9
3.15
1.20
5.7
3.20
0.58
-6.2
0.05
-0.62
Total 18.6
3.23
1.94
15.7
3.44
1.74
-2.9
0.21
-0.20
Total Measured 26.1
1.13
0.94
31.5
0.94
0.96
5.4
-0.18
0.01
Indicated 87.9
1.74
4.93
96.9
1.79
5.57
9.0
0.04
0.64
Inferred 34.2
1.95
2.15
14.9
1.95
0.93
-19.3
-0.01
-1.21
Total 148.1
1.68
8.02
143.2
1.62
7.45
-4.9
-0.06
-0.56

Notes:

  1. The Open Pit Mineral Resource using a marginal (break-even) block cut-off grade of ≥ 0.3g/t Au cut-off for oxide material, and a ≥0.4g/t Au cut-off for transitional and fresh material. Cut-off grades for Mineral Resources have been based on an A$1,817/oz (US$1,400/oz) gold price.

  2. The Open Pit Mineral Resource is reported within a combination of pit designs and optimisation shells, reflecting the current Long Island mining strategy including; a) Havana South is reported within a A$1,817/oz (US$1,400/oz) gold price optimised shell, at Long Island study costs; b) Havana is reported within a pit design, based on Long Island Study costs at an A$1,370/oz (US$1,055/oz) gold price optimised shell; c) Tropicana is reported within the current life of mine design, and; d) Boston Shaker is reported within current life of mine design based on an A$1,350 (US$1,040/oz) gold price and Long Island Study costs.

  3. All figures are rounded to reflect appropriate levels of confidence. Apparent differences may occur due to rounding.

  4. Mineral Resources are inclusive of Ore Reserves.

  5. All Mineral Resources are reported in accordance with requirements and guidelines to the 2012 JORC Code.

  6. JORC Code (2012) Table 1check-lists for Mineral Resource estimates are contained within Appendix B of this ASX release.

Ore Reserve

The total Tropicana Ore Reserve (100% basis) as at 31 December 2017 is estimated to contain 66.6Mt grading 1.91g/t Au for 4.08Moz of contained gold compared to 60.1Mt at 1.97g/t for 3.80Moz as at 31 December 2016. This represents an increase in the Ore Reserve of 820,000oz net of depletion since 31 December 2016 as a result of the incorporation of the expanded Boston Shaker and Havana South pits.

PAGE 7

==> picture [595 x 82] intentionally omitted <==

Table 2: Tropicana Ore Reserves (100% Project) as at 31 December 2017*

Area Reserves
Category
Dec-16 Dec-17 **Change **
Mt
g/t
Moz
Mt
g/t
Moz
Mt
g/t
Moz
Open Pit Proved 15.7
1.48
0.75
17.4
1.29
0.72
1.7
-0.18
-0.02
Probable 44.4
2.14
3.05
49.2
2.12
3.36
4.8
-0.02
0.30
Total 60.1
1.97
3.80
66.6
1.91
4.08
6.5
-0.06
0.28

*Including depletion of 7.15 Mt at 2.38 g/t for 0.55 Moz.

Notes:

  1. The Proved and Probable Ore Reserve are reported above economic break-even gold cut-off grades for each material type at a gold price of A$1,491/oz (US$1,100/oz).

  2. The Ore Reserve estimate is based on depletion through to the 31 December 2017, using the Resource model from June 2017.

  3. The block cut-off grades used for reported are 0.6g/t Au for oxide material and 0.7g/t Au for transitional and fresh.

  4. All figures are rounded to reflect appropriate levels of confidence. Apparent differences may occur due to rounding.

  5. Mineral Resources are inclusive of Ore Reserves.

  6. All Mineral Resources are compiled in accordance with the 2012 JORC Code.

  7. JORC Code (2012) Table 1 check lists for Ore Reserve estimates, are contained within Appendix B of this ASX release

During CY16 the conversion of Mineral Resource to Ore Reserve for the Open Pit improved from 40% at 30 June 2016 to 62% at 31 December 2016. This improvement continued in CY17 with conversion of Mineral Resource to Ore Reserve improving from 62% at 31 December 2016 to 78% at 31 December 2017.

Underground Potential

Background

Down-plunge mineralisation at Havana was previously drilled and a feasibility study was completed in 2013. At the time the gold price and resource tonnage per vertical metre resulted in the project not meeting required investment hurdles.

As part of the framework drilling for the Long Island mining strategy, a greater understanding of the down-plunge potential through the whole of the Tropicana Mineralised System has emerged with additional higher-grade shoots identified at Boston Shaker and Havana South.

At Boston Shaker, the thickness, grade and plunge of the shoots have the potential to be amenable to conventional underground mining.

An initial 3,000m of diamond drilling was completed in the September 2017 quarter which returned significant intersections and resulted in the commitment to a 20,000m diamond drilling resource definition drill program. The Mineral Resource definition drill program based on 100 x 100m spaced drilling will be 60% complete at 31 December 2017.

Boston Shaker drilling and underground studies

Diamond drilling beneath the Boston Shaker pit in the second half of CY17 pit has returned significant intercepts including:

  • 18m at 6.58 g/t Au from 587m depth ( BSD087W1 );

  • 37m at 6.49 g/t Au from 509m ( BSD088 ); and

  • 20m at 5.82 g/t Au from 609m ( BSD089AW2 ).

Refer to Figures 5,6 and detailed table of intercepts in appendix A.

PAGE 8

==> picture [595 x 82] intentionally omitted <==

A scoping study has commenced and will be followed by a Pre-Feasibility Study in CY18 to investigate the potential for underground mining at Boston Shaker with the aim of defining an underground Ore Reserve by the end of CY18.

Successful development of an underground mine at Boston Shaker has the potential to contribute high-grade ore to the processing plant from CY21 onwards.

==> picture [412 x 352] intentionally omitted <==

Figure 5: Image showing recent drilling beneath the Boston Shaker pit.

PAGE 9

==> picture [595 x 82] intentionally omitted <==

==> picture [483 x 298] intentionally omitted <==

Figure 6: Boston Shaker cross-section showing recent drilling

Regional Exploration

Regional exploration at Tropicana in CY17 has been guided by new thinking and work completed through CY16.

Palinspastic reconstruction and a geological review have provided an updated understanding and revised interpretation of the regional geology and prospectivity in the belt. The evolution of this work continues, with inputs from current exploration drilling and further specialist and academic work.

Over the past year, a balanced strategy was adopted, comprising resource development at Tropicana, and early-to-advanced stage exploration regionally.

Advanced exploration continued to evaluate existing prospects (Madras, Voodoo Child, Angel Eyes, Springbok) and test the New Zebra anomaly identified through aircore drilling in late CY16. Early stage aircore drilling was carried out at Chocalatini, Iceburg, Caprioska and Watchtower.

Following exceptional results at Boston Shaker in CY17, priority was given to resource development drilling to evaluate the underground potential. This focus will continue in CY18 along with regional exploration to test new targets identified as a result of the palinspastic reconstruction.

FY18 Guidance

FY18 guidance for Tropicana (IGO 30% basis) is substantially unchanged with the exception of an increase to sustaining and improvement capex for IGO’s share of the capital expenditure that will be incurred in FY18 for (i) the implementation of the Long Island mining strategy and (ii) the installation of the additional ball mill.

PAGE 10

==> picture [595 x 82] intentionally omitted <==

Table 3: Updated FY18 Guidance – substantially unchanged

Metric UOM Guidance Changed Guidance
Gold produced (100% basis) oz 440,000 – 490,000 No change
Gold Sold (30% basis) oz 132,000 – 147,000 No change
Cash Cost A$/oz 680 – 750 No change
All-In-Sustaining-Cost A$/oz 1,060 – 1,170 No change
Sustaining and Capex A$M 3 – 5 4 – 6
Improvement capex1 A$M 6 – 7 16 – 18
Capitalised Waste Stripping A$M 44 – 55 No change
Exploration Expenditure A$M 4 - 5 No change

Notes:

  1. Improvement capex includes the Long Island camp expansion and heavy vehicle workshop infrastructure, and installation of additional ball mill. For the avoidance of doubt, the Improvement capex is not included in All-In-SustainingCosts.

JORC Code (2012) Competent Persons Statements

The information in this report that relates to Exploration Results is based on information compiled by Mr. Damon Elder who is a full-time employee of AGAA and is a member of The Australasian Institute of Mining and Metallurgy. Mr Elder has sufficient experience which is relevant to the style of mineralisation and type of deposit under consideration and to the activity being undertaken to qualify as a Competent Person as defined in the 2012 Edition of the ‘Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves’. Mr. Elder consents to the inclusion in the report of the matters based on his information in the form and context in which it appears.

The information that relates to the Tropicana Mineral Resources is based on, and fairly represents information and supporting documentation compiled by Mr Mark Kent, a full-time employee and security holder of AGAA, who is a member of The Australasian Institute of Mining and Metallurgy. Mr Kent has sufficient experience relevant to the type and style of mineral deposits under consideration, and to the activity which has been undertaken, to qualify as a Competent Person as defined in the 2012 edition of the JORC Code. Mr Kent consented to the inclusion in this report of the Tropicana Mineral Resource estimate, based on the information in the form and context in which it appears.

The information that relates to the Tropicana Ore Reserves is based on, and fairly represents information and supporting documentation compiled by Mr Leonardo Vilela Couto, a full-time employee and security holder of AGAA, who is a member of The Australasian Institute of Mining and Metallurgy. Mr Vilela Couto has sufficient experience relevant to the type and style of mineral deposit under consideration, and to the activity which has been undertaken, to qualify as a Competent Person as defined in the 2012 edition of the JORC Code. Mr Vilela Couto consented to the inclusion in this report of the Tropicana Ore Reserve estimate, based on the information, in the form and context in which it appears.

FORWARD LOOKING STATEMENTS

This announcement contains forward-looking statements regarding future events, conditions and circumstances including but not limited to statements regarding plans, strategies and objectives of management, anticipated construction timelines and expected costs and levels of production. Often, but not

PAGE 11

==> picture [595 x 82] intentionally omitted <==

always, forward-looking statements can be identified by the use of forward-looking words such as "may", "will", "expect", "intend", "plan", "estimate", "anticipate", "continue" and "guidance", or other similar words.

These forward-looking statements are not a guarantee of future performance and involve unknown risks and uncertainties, many of which are beyond IGO’s control, which may cause actual results and developments to differ materially from those expressed or implied. These risks include but are not limited to economic conditions, stock market fluctuations, commodity demand and price movements, access to infrastructure, timing of approvals, regulatory risks, operational risks, reliance on key personnel, reserve and resource estimations, native title and title risks, foreign currency fluctuations, exploration risk and mining development, construction and commissioning risk.

The production guidance in this announcement is subject to the risks referred to above and should be read in conjunction with the further information regarding the Mineral Resources and Ore Reserves, as well as the Competent Persons' Statements, included in this announcement and with IGO’s other announcements lodged with the ASX.

Forward-looking statements in this announcement apply only at the date of issue. Subject to any continuing obligations under applicable law or regulations, IGO does not undertake to publically update or revise any of the forward-looking statements in this announcement or to advise of any change in events, conditions or circumstances on which any such statement is based. Readers are cautioned not to place undue reliance on any forward-looking statements contained in this announcement.

Investor and Media Inquiries:

Andrew Eddowes Business Development Manager Independence Group NL +61 8 9238 8300 [email protected]

Jill Thomas Communications Manager Independence Group NL +61 8 9238 8300

PAGE 12

==> picture [595 x 82] intentionally omitted <==

APPENDIX A

Table of significant CY17 drill intersections

Tropicana Resource Drilling - Boston Shaker Intercepts Tropicana Resource Drilling - Boston Shaker Intercepts Tropicana Resource Drilling - Boston Shaker Intercepts Tropicana Resource Drilling - Boston Shaker Intercepts Tropicana Resource Drilling - Boston Shaker Intercepts Tropicana Resource Drilling - Boston Shaker Intercepts Tropicana Resource Drilling - Boston Shaker Intercepts Tropicana Resource Drilling - Boston Shaker Intercepts Tropicana Resource Drilling - Boston Shaker Intercepts Tropicana Resource Drilling - Boston Shaker Intercepts Tropicana Resource Drilling - Boston Shaker Intercepts Tropicana Resource Drilling - Boston Shaker Intercepts Tropicana Resource Drilling - Boston Shaker Intercepts Tropicana Resource Drilling - Boston Shaker Intercepts
Hole Total Depth Depth Intercept Gram
Hole ID East North RL Dip Azi Drill Date Grade
Type Depth From To Width Metres
BSD087W1 DDH 652394.8 6763263.8 345.9 -63.3 319.4 6/08/2017 669.4 587 605 18 6.58 118.44
BSD087W2 DDH 652394.8 6763263.8 345.9 -63.3 319.4 6/08/2017 648.4 588 606 18 3.79 68.22
BSD088 DDH 652320.2 6763540.5 356.0 -83.2 319.0 16/08/2017 600.0 509 546 37 6.49 240.13
BSD088W2 DDH 652320.2 6763540.5 356.0 -83.2 319.0 18/08/2017 579.6 514 531.9 17.8 5.59 99.50
BSD089AW1
DDH
652804.4 6763482.6 350.2 -63.4 317.3 5/09/2017 716.5 661 674 13 3.95 51.35
BSD089AW2
DDH
652804.4 6763482.6 350.2 -63.4 317.3 5/09/2017 702.1 609 629 20 5.78 115.60
BSD098 DDH 652213.3 6763391.4 344.6 -63.9 317.7 16/10/2017 507.7 458 484 26 3.33 86.49
BSD101 DDH 652423.7 6763178.0 346.3 -67.3 318.5 14/10/2017 636.3 562 590 28 3.55 99.48
Intercept Note:
Intercepts calculated based on minimum intercept 2m @ 0.5 g/t, lower cut·off grade 0.5 g/t, maximum consecutive waste 2m, minimum
intercept grade 1 g/t, calculation based on downhole length, true thickness/width not stated or calculated.

PAGE 13

==> picture [595 x 82] intentionally omitted <==

APPENDIX B

Tropicana Gold Mine Mineral Resource and Ore Reserve as at 31 December 2017

JORC Code, 2012 Edition – Table 1

Section 1 Sampling Techniques and Data

Criteria Commentary
Sampling techniques -AngloGold Ashanti Australia (AGAA) has used drilling and sub-sampling of the cuttings or cores
as the data basis for the Mineral Resource estimates of the Tropicana deposit. Details are given
in the following subsection.
-Drill hole spacing ranges from 25m×25m grids to 100m×100m grids, with most of the drilling of
the Open Pit Mineral Resources on a 50m×50m spacing with 25m×25m testing the starter pits
of the Tropicana and Havana initial pits, and the southern end of the Boston Shaker deposit.
-A 100m×100m area of Havana was drilled out on a 10m×10m grid to validate the Mineral
Resource estimate model and optimise the grade control sample spacing.
-The Underground Mineral Resource down-plunge extensions of Havana Deeps is tested using
a 100m×100m grid. Deep +800m deep step-out holes have been drilled on nominal
≈200m×100m to test the high-grade mineralisation of Havana Deeps.
-All holes are drilled plunging towards the west to intersect the east dipping mineralised zones.
Drilling techniques -Reverse circulation (RC) percussion drilling using face-sampling bits (5¼ inch or 133mm
diameter) has been used to collect samples from the shallower (up-dip) part of the deposits with
a nominal maximum RC depth of 150m.
-Diamond core drilling has been used for deeper holes, with diamond tails drilled from RC pre-
collars. To control the deviation of deep DD holes drilled since 2011, many of these holes
were drilled from short≈60m RC pre-collars or using 63.5mm (HQ) diameter core from
surface.
-Diamond core drilling for Mineral Resource definition is predominantly 47.6mm (NQ) diameter
core, with a lesser number of holes drilled for collection of metallurgical and/or geotechnical
data using 63.5mm (HQ2, HQ3) or 85mm (PQ) core diameters.
-In fresh rock, cores are oriented wherever possible for collection of structural data. Prior to
2009, core orientations are made using the EzyMark tool with the Reflex Ace Tool replacing
the system in later drilling programs.
Drill sample recovery -RC recovery
oPrior to 2008 semi-quantitative assessment was made regarding RC sample recovery
with recovery visually estimated as 25%, 50%, 75% of 100% of the expected mass
volume of a 1m drilling interval.
oSince 2008, AGAA has implemented quantitative measure on every 25thinterval where
the masses of the sample splits are recorded and compared to the theoretical mass of
the sampling interval for the rock type being drilled.
oAGAA found that overall recovery in the regolith was >80% and total recovery in fresh
rock.
-DD Recovery
oDD recovery has been measured as percentage of the total length of core recovered
compared to the drill interval.
oCore recovery is consistently high in fresh rock with minor losses occurring in heavily
fractured ground or for DD drilling in the regolith.
-The main methods to maximise recovery have been recovery monitoring as described above
and diamond core drilling below≈150m depth.
-No relationships have been noted between sample recovery and grade and sample biases
that may have occurred due to the preferential loss or gain of fine or course material are
considered unlikely.

PAGE 14

==> picture [595 x 82] intentionally omitted <==

Criteria Commentary
Logging -RC cuttings and DD cores have been logged recording geological and geotechnical
characteristics with reference to AGAA’s logging standard library, to levels of detail that
support Mineral Resource estimation, Ore Reserve estimation and metallurgical studies.
-Qualitative logging includes codes for lithology, regolith, and mineralisation for both RC and
DD, with sample quality data recorded for RC such as moisture, recovery, and sub-sampling
methods.
-DD cores are photographed, qualitatively structurally logged with reference to orientation
measurements where available.
-Geotechnical quantitative logging includes QSI, RQD, and matrix and fracture
characterisation.
-The total lengths of all drill holes have been logged.
Sub-sampling
techniques and
sample preparation
-RC – Primary splitting
oPrior to 2007 RC samples were collected from the cyclone stream using a tiered riffle
splitter. From 2007 a static cone splitter was introduced and replaced riffle splitters on all
rigs.
oThe RC sampling interval is generally 1m but from CY16 2m intervals were introduced
for RC pre-collars.
oThe splitters collected a≈12% split from the primary lot with two 12% splits collected –
the first for laboratory submission and second as a reference or replicate. Most samples
were collected dry with <2% of samples recorded as being split in moist or wet state.
oThe main protocol to ensure the RC samples were representative of the material being
collected was monitoring of sample recovery and collection and assay of replicate
samples.
-DD – Primary sample
oDD cores are collected of intervals determined by geological boundaries but generally
targeting a 1m length
oAll NQ cores have been half-core sampled with the core cut longitudinally with a wet
diamond blade.
oA small amount of DD whole cores have been sampled from HQ3 cores drilled to twin
RC holes in the regolith or for geotechnical or metallurgical testing.
oIn 2005, some 1,150m of cores drilled in the oxide zone were chisel split rather than wet
cut but this poorer sub-sampling represents <0.01% of the core drilled.
-Laboratory preparation
oSample preparation has taken place at three laboratories since commencement of
Mineral Resource definition drilling including SGS Perth (pre- 2006), Genalysis Perth
(CY06 to April 2016) and Tropicana site laboratory (2015 Boston Shaker samples and
post-April 2016 samples)
oRC samples were over dried then pulped in a mixer mill to a PSD of 90% passing 75
microns before sub-sampling for fire assay.
oSGS prepared DD half-core samples by jaw-crushing then pulverisation of the whole
crushed lot to a particle size distribution (PSD) of 90% passing 75 microns. A 50g
subsample of the pulp was then collected for fire assay.
oGenalysis prepared the samples in a Boyd crusher rotary splitter combo with nominally
2.5kg half-core lots crushed to <3 mm then rotary split to≈1 kg before pulverisation and
sub-sampling for fire assay.
oSamples less with mass <800g submitted to Tropicana laboratory are pulped in a LM2
mill to a PSD of 75 microns before sub-sampling for fire assay. Samples with larger
masses are crushed in a Boyd crusher to a PSD of 90% passing 2mm then subsampled
using a linear sample divider.
oFrom May 2016, a jaw crusher has been used to crush half-core samples to a PSD of
100% passing 6 mm.
-Quality controls for representative sampling:
oSGS inserted blanks and standards at a 1:20 frequency in every batch with a duplicate
pulp collected for assay every 20thsample. Further repeats were also completed at a

PAGE 15

==> picture [595 x 82] intentionally omitted <==

Criteria Commentary
1:20 frequency in a random manner. Sieve checks were completed on 5% of samples to
monitor PSD compliance.
oGenalysis inserted blanks and standards in every batch and a duplicate pulp was
collected for assay on every 25thsample and 6% of each batch was randomly selected
for replicate analysis. Sieve checks were completed on 5% of samples to monitor PSD
compliance.
oTropicana laboratory used barren basalt and quartz to clean equipment between routine
samples
-Sample size versus grain size
oNo specific heterogeneity tests have been carried out but the sample sizes collected are
consistent with industry standards for the style of mineralisation under consideration.
oA 2008 sampling variability study found that 72% of the gold in the samples tested was in
size fraction <300 microns, and that repeated sampling of the same lot have very low
variance between replicates.
Quality of assay data
and laboratory tests
-No geophysical tools were used to determine any element concentrations material to the Mineral

Resource estimate.
-All Mineral Resource prepared pulps have undergone 50g fire assay which is considered a
total assay for gold
-As discussed above all laboratories have used industry standard quality control procedures
with standards used to monitor accuracy, replicate assay to monitor precision, blanks to
monitor potential cross contamination and sieve tests to monitor PSD compliance.
-AGAA has also used other ‘umpire’ laboratories to monitor accuracy including Genalysis Perth
(prior to November 2006), SGS (from November 2006 to August 2007) and ALS Perth (since
August 2007), with these check assaying campaigns coinciding with each Mineral Resource
update.
-AGAA has reviewed the quality sample results on a batch by batch and monthly basis and
has found that the overall performance of the laboratories used for Mineral Resource
estimation samples is satisfactory.
Verification of
sampling and
assaying
-Significant intersections of mineralisation are routinely verified by AGAA senior geological
staff and have also been inspected by several independent auditors as describe further below.
-Twin holes have been drilled to compare results from RC and DD drilling with the DD results
confirming that there is no material down-hole smearing of grades in the nearby RC drilling
and sampling.
-All logging and sample number data is captured digitally in the field using Field Marshall
Software (upgrade to Micromine Geobank in 2016). Data is downloaded daily to the
Tropicana exploration server and checked for accuracy, completeness and structure by the
field personnel.
-Assay data is merged electronically from the laboratories into a central Datashed database,
with information verified spatially in Vulcan software. AGAA maintains standard work
procedures for all data management steps.
-An assay importing protocol has been set up to ensure quality samples are checked and
accepted before data can be loaded into the assay database
-All electronic data is routine backed up to AGAA’s server in Perth and provided to IGO via
FTP transfer.
-There have been no adjustments or scaling of assay data other than setting below detection
limit values to half detection for Mineral Resource estimation work.
Location of data
points
-All early drill hole collar locations of surface holes have been surveyed using RTK GPS

equipment, which was connected to the state survey mark (SSM) network.
-The grid system is GDA94 Zone 51 using AHD elevation datum.
-Prior to 2007, drill hole path surveys have been completed on all holes using Eastman single
shot camera tools, with down-hole gyro tools used for all drilling post 2007

PAGE 16

==> picture [595 x 82] intentionally omitted <==

Criteria Commentary
-A digital terrain model was prepared Whelan’s Surveyors from aerial photography flown in 2007,
which has been supplemented with collar data surveyed using RTK GPS. This model is
considered to have centimetre-scale accuracy.
Data spacing and
distribution
-The drill hole spacing nominally ranges from 25mN×25mE to 100mN×100mE (local grid) over
most of the Mineral Resource area with a small area of 10mN×10mE used for grade control
calibration work.
-Most of the Open Pit Mineral Resources has been tested on a 50mN×50mE grid with closer
spaced 25mN×25mE patterns in the upper parts of the deposit within initial open pit designs.
-The Havana Deeps area has been drilled on a 100mN×100mE pattern.
-Down-hole sample intervals are typically 1m with 2m compositing applied for Mineral Resource
estimation work.
-The Competent Person considers that data spacing is sufficient to establish the degree of
geological and grade continuity appropriate for the Mineral Resource and Ore Reserve
estimation procedures applied, and the JORC Code classification applied.
Orientation of data in
relation to geological
structure
-Most drill hole are oriented to intersect the shallowly east dipping mineralisation at a high
angle and as such, a grade bias introduced by the orientation of data in relation to geological
structure is highly unlikely.
Sample security -The chain-of-sample custody is managed by AGAA.
-Samples were collected in pre-numbered calico bags, which are then accumulated into calico
bags for transport from the collection site. The accumulated samples are then loaded into
wooden crates and road hauled to the respective laboratories (Perth or Tropicana).
-Sample dispatches are prepared by the field personnel using a database system linked to the
drillhole data.
-Sample dispatch sheet are verified against samples received at the laboratory and any
missing issued such as missing samples and so on are resolved before sample preparation
commences.
-The Competent Person considers that the likelihood of deliberate or accidental loss, mix-up or
contamination of samples is considered very low.
Audits or reviews -Field quality control data and assurance procedures are reviewed on a daily, monthly and
quarterly basis by AGAA field personnel and senior geological staff.
-The field quality control and assurance of the sampling was audited by external consultants,
Optiro, during CY17. Optiro rated the standard of the work as “good”. The conclusion of the
audit was that the data was suitable for Mineral Resource estimation work.

PAGE 17

==> picture [595 x 82] intentionally omitted <==

Section 2 Reporting of Exploration Results

Criteria Explanation
Mineral tenement and
land tenure status
-The Tropical Gold Mine Mineral Resources are located wholly within WA mining lease
M39/1096, which commenced on 11 Mar 2015 and has a term of 21 years (expiry 10 Mar 2036).
-Tropicana Gold Mine in a joint venture between AGAA (70%) and IGO (30%) with AGAA as
manager.
-Gold production is subject to WA State royalties of 2.5% of the value of gold value.
-There are no material issues relating to native title or heritage, historical sites, wilderness or
national parks, or environmental settings
-The tenure is secure at the time of reporting and there are no known impediments to
exploitation of the Mineral Resource and Ore Reserve and on-going exploration of the mining
lease.
Exploration done by
other parties
-AGAA entered in to a JV with IGO in early 2002 with the main target of interest being a WMC

gold soil anomaly of 31ppb, which was reporting in a WA government open file report. Prior to
the JV, the WMC soil sampling program was the only known exploration activity and the only
dataset available were WA government regional magnetic and gravity data.
Geology -The Tropicana Gold Mine is on the western margin of a 700km long magnetic feature that is
interpreted to the collision suture zone between the Archean age Yilgarn Craton to the west
and the Proterozoic age Albany-Fraser Origan to the east of this feature. The gold deposits
are hosted by a package of Archean age high metamorphic grade gneissic rocks.
-Four distinct structural domains have been identified – Boston Shaker, Tropicana, Havana
and Havana South, which represent the same mineral deposit offset by NE striking faults that
post-date the mineralisation.
-The gold mineralisation is hosted by a shallowly SW dipping sequence of quartz-feldspar
gneiss, amphibolite, granulite and meta-sedimentary chert.
-The gold mineralisation is concentrated in a ‘favourable horizon’ of quartz-feldspar gneisses,
with a footwall of garnet gneiss, amphibolite or granulite.
-Mineralisation is characterised by pyrite disseminations, bands and crackle veins within
altered quartz-feldspar gneiss. Higher grades are associated with close-spaced veins and
sericite alteration
-Mineralisation presents as stacked higher grade lenses within a low-grade alteration
envelope. Geological studies suggest the mineralisation is related to shear planes that post-
date the development of the main gneissic fabric and metamorphic thermal maximum.
Drill hole Information -A summary of the all drillholes used to prepare the Mineral Resource estimate is not practical
for this public report. The Mineral Resource estimate gives the best-balanced view of all the
drillhole information available as at June 2017.
Data aggregation
methods
-No metal equivalent values are considered in the Mineral Resource estimate.
Relationship between
mineralisation widths
and intercept lengths
-Exploration results included in this report are for extensional drilling at Boston Shaker
(underground resource extension).
-All Mineral Resource drilling interests the mineralisation at a high angle and as such
approximate true thicknesses in most cases.
Diagrams -A representative 3D oblique view for Boston Shaker results is included in the body of this report.
Balanced reporting -The Mineral Resource is based on all available data and as such provides the best-balanced
view of the Tropicana gold deposits as at June 2017. The Exploration results reported are not
included in the Mineral Resource Estimate reported.

PAGE 18

==> picture [595 x 82] intentionally omitted <==

Criteria Explanation
Other substantive
exploration data
-Information relating to other exploration data, such as density, metallurgical assumptions are
detailed in Section 3 further below
Further work -Exploration drilling is continuing at Boston Shaker (Underground resource extension drilling)
and will be included in the next Mineral Resource update, planned for the March 2018 quarter.

PAGE 19

==> picture [595 x 82] intentionally omitted <==

Section 3 Estimation and Reporting of Mineral Resources

Criteria Commentary
Database integrity -AGAA captures field data and drill hole logging directly in to handheld devices or laptop
computers using Field Marshall and Geobank software.
-The drillhole data is managed in DataShed software, which is an industry recognised system
for management of geoscientific drillhole information. Logging, assays and survey
information is loaded directly into Datashed using data import routines, with loading
procedures incorporating quality control checking.
-Data is validated following loading through visual inspection of results on-screen both spatially
and using database queries and cross section plots. Typical checks carried out against
original records to ensure data accuracy include items such as overlapping records, duplicate
records, missing intervals, end of drillhole checks and so on.
Site visits -The Competent Person makes regular site visits to Tropicana to review the data collection
procedures and discuss the geology and mineralisation of the deposit prior to any Mineral
Resource update.
Geological
interpretation
-To control the Mineral Resource estimation process, three dimensional digital solids were
prepared in LeapFrog software for the mineralised zones, dykes, shears and garnet (mostly
hanging wall) gneiss.
-Mineralised solids were prepared using a nominal 0.3g/t AU drill hole cut-off grade to
encompass the gold mineralisation targeted for Mineral Resource estimation. The dykes,
shears and garnet gneiss solids were prepared from geological logging codes. Regolith units
were prepared as digital surfaces below topography based on the geological logging.
-The resulting models encompass the mineralisation, the post-mineralisation barren dykes,
and the shears controlling higher grade mineralisation and the main waste rock units that are
the footwall and hanging wall to the mineralisation.
Dimensions -The Open Pit Mineral Resource is reported within a combination of life-of-mine pit designs
and an open pit Lerchs-Grossman-Analysis (LGA) pit optimisation ‘shell’ based on a gold
price of A$1,817/oz (US$1,400/oz).
-This reporting shell has dimensions of approximately 4.7km along strike, up to 1km wide and
up to 450m deep, spanning all the major deposits.
-The Underground Mineral Resource extends from the base of the Open Pit Resource below
the Havana Open Pit with plan extents in long dimension down dip to the SE by up to 900m
and up to≈200m wide. Additional underground Mineral Resource is down dip from Boston
Shaker open pit. A smaller lode extends from the Havana South pit with down dip extents of≈
200m and up to 200m wide. Other parts of the Underground Resource are below the other
pits.

PAGE 20

==> picture [595 x 82] intentionally omitted <==

Criteria Commentary
Estimation
and
modelling techniques

-The Open Pit Mineral Resource:
oHas been estimated from the drillhole data available to 16 January 2017, which included
3,666 drill holes for a total of 702,961m of drilling of which, 1,011 holes were DD for
387,191m and 2,421 holes were RC for 278,683m. A further 144 holes of RC with DD
holes totalled 37,087 of drilling.
oThe December 2017 update included 279 new holes (170 RC and 109 DD) for an
additional 54,753m of drilling compared to the prior estimate.
oThe drillhole data was composited to 2m lengths within geological estimation domains
using Vulcan software.
oNo grade top-cut or caps were applied to the composites, but high-grade estimation
limits were applied to limit the spatial spread of high grades.
oThe composite data was declustered in each estimation domain using cell declustering
commensurate with the drill spacing (25mE×25mN or 50mE×50mN and planned kriging
panel height (10m for Havana and Tropicana, 7.5m for Boston Shaker)
oGold continuity was interpreted for each estimation domain and grades for large panels
were estimated using ordinary block kriging in Isatis, with estimation panel dimension
15mE×45mN×10mElv used for Havana and Tropicana, and panels of
15mE×30mN×7.5mElv for Boston Shaker.
oSample searches were oriented down dip with a 160mX×160mY×30mZ search used for
mineralised domains and 120mX×120mY×30mZ search in waste domains. A minimum
of 8 (or 4 for Boston Shaker) and maximum of 32 samples were required for a panel
grade to be estimated. A second pass search was then applied to address blocks with
>1% negative kriging weights with the maximum number of samples reduced to 12.
oSelective Mining Unit (SMU) grades were then estimated for each panel using the Local
Uniform Conditioning method, where the SMU grade distribution within each panel is
estimated through a change of support then the SMUs are localised using kriging so the
distribution within the panel reflects the local grade trends in nearby data. The
information effect of 12mE×12mN grade control information was accommodated in the
change of support from panels to SMUs
oThe SMU dimensions were set to prepare 36 SMUs per panel with SMU dimensions of
10mE×15mN×3.33mElv for Havana and Tropicana and 5mE×7.5mN×2.5mElv for Boston
Shaker. The elevation heights nominally match the mining flitch heights applied at each
area.
oThe estimate model was validated by comparing (input) data declustered means for each
domain to the respective (output) block estimated grades both globally within each
domain and locally using moving window ‘swath-plot’. On screen visual inspections were
also completed in plan and section to ensure that the grade trends observed in the data
were acceptably reproduced in the estimates without over extrapolation in areas of
sparse drilling.
oComparison of the Open Pit estimate forecasts to mine production indicates acceptable
forecasting performance for monthly, quarterly and annual recompilation periods.
-The Underground Mineral Resource:
oIs estimated in a separate model from the Open Pit with the model oriented to follow the
30°east dip of mineralisation.
oThe estimate has been prepared using Ordinary Block Kriging in Isatis software into
block dimensions 10mX×10mY×2mZ in the rotated coordinates.
oA higher-grade zone (>2 g/t) was defined by implicit modelling, with grades estimated
into the higher and lower grade zones separately. Search ranges were consistent with
the Open Pit estimate, with an additional longer-range search used.
oDrill hole data were composited to 2m prior to estimation with no-top cuts applied
oThe model was validated in an equivalent manner to the Open Pit estimates.
oThere has been no mining of the Underground Resource to compare to the estimate
-There are no assumptions relating to deleterious elements of non-grade variables of
economic significance. Gold and density are the only relevant variables.

PAGE 21

==> picture [595 x 82] intentionally omitted <==

Criteria Commentary
Moisture -The tonnages are estimated on a dry basis.
Cut-off parameters -Open Pit
oThe Open Pit estimate is reported within a combination of life-of-mine pit designs and a
pit optimisation run with an assumed gold prices of US$1,400/oz (A$1,817/oz) and cost
assuming back-filling of pits (‘Long Island Study’).
oOn the basis described above, and assuming lower processing costs and higher
metallurgical oxide ore, the cut-off are≥0.3g/t Au for oxide Mineral Resources and
≥0.4g/t Au for transitional and fresh Mineral Resources.
-Underground
oThe Underground estimate cut-off grade is based on assumptions of a pre-feasibility
study completed in 2013 which used a gold price of US$1,400 US$/oz (A$1,817/oz) and
underground mining and process cost assumptions for fresh Mineral Resource.
oThe cut-off grade for reporting the Underground Mineral Resource on this basis is≥2.0g/t
Au.
Mining factors or
assumptions
-The mining factors and assumption for the Open Pit Mineral Resource is the current mining

method of conventional truck and shovel mining with blasting of 10m benches in Tropicana and
Havana and blasting of 7.5m benches in Boston Shaker.
-Open Pit ore is mined in three 1/3 blast height flitches, with ore predefined by 12mE×12mN RC
grade control drilling and 1m downhole sampling.
-The assumed Open Pit mining selectivity are the SMU dimensions assumed for the LUC
estimates.
-The assumption for the Underground Mineral Resource is long-hole open stoping between 20m
levels.
-No Mineral Resource margin (external) dilution has been modelled in either estimate.
-Eventual prospects of economic extraction for the Open Pit resource have been assessed
through pit optimisation studies and reporting the Mineral Resource within pit designs and an
optimisation shell.
-Eventual prospects of economic extraction for the Underground Resource have been
demonstrated in the 2013 study, albeit the project development is not currently economical
attractive at current metal prices and costs.
Metallurgical factors
or assumptions
-The ore processing method at Tropicana is well-established with conventional, crushing,
grinding then carbon-in-leach extraction of gold followed by electrowinning to produce gold bars.
-An average metallurgical recovery of 90.3% has been assumed for both the Open Pit and
Underground Mineral Resources based on metallurgical testing completed as part of the
Feasibility Study for the Havana Open Pit.
Environmental factors
or assumptions
-Tropicana Gold mine operates under an environmental management plant that meets or

exceeds all statutory and legislative requirements.
-Mined waste rock is disposed in waste dumps which are progressively rehabilitated as mining
progresses with any potentially acid generating waste encapsulated in non-acid generating
material.
-A tailing storage facility is used to contain and capture process residues.
-The mine produces rehabilitation plans for ongoing rehabilitation and mine closure plans, and
the costs are included in the financial model.
Bulk density -AGAA routinely collects_in situ_bulk density measurements on≈10cm long core segments using
the Archimedes principle method of dry weight versus weight in water. There are≈138,000
density measurements in the estimation database with 131,000 from fresh rock and the
remainder in the regolith or cover.

PAGE 22

==> picture [595 x 82] intentionally omitted <==

Criteria Commentary
-Measurements are collected over 1m to 5m intervals targeting intervals that are deemed
representative of key lithology in fresh rock. Density has been collected on core within the
regolith from ‘core-from-surface’ drill holes, with the measurement method accounting for voids.
-Depending on rock type density ranges of 1.89 t/m3to 2.18 t/m3in the saprolite and ranges
from 2.56 t/m3to 2.96 t/m3in the transitional and fresh rock domains.
-Density is estimated by ordinary block kriging in the Mineral Resource estimates apart from a
few minor domains with sparse data (such as the regolith), where density is assigned as a
mean of the data.
Classification -The basis of classification of the Tropicana estimates into different JORC Code confidence
categories is drill hole spacing as follows:
oMeasured Mineral Resources: average 25mE×25mN collar spacing.
oIndicated Mineral Resources: average50mE×50mN collar spacing.
oInferred Mineral Resources: average 100mE×100mN collar spacing (or less) when
evidence of geological or grade continuity is sufficient to support grade estimation.
-AGAA considers that the Measured Resource supports mine planning with a 90% confidence
interval of ±15% on tonnage or grade on a quarterly production basis, with Indicated Resources
have the same confidence but applicable on an annual production basis.
-The Competent Person considers this classification takes in to account all relevant factors such
as data reliability, confidence in the continuity of geology and grades, and the quality, quantity
and distribution of the data.
-The classification reflects the view of the Competent Person reporting the estimate with the
same methodology applied to both the Open Pit and Underground estimates.
Audits or reviews -The Open Pit estimate methodology was audited by consultant QG in 2007, 2009 and 2011.
-Consultants Golder Associates audited the 2015 estimate in 2015 with recommendations that
have been adopted in the current estimate.
-Optiro consultants reviewed the current Mineral Resource and endorsed the estimate.
-AGAA conducts internal peer review prior to the release of any Mineral Resource update.
Relative
Accuracy/Confidence
-AGAA has carried out some non-conditional simulation studies to confirm the relationship

between drill spacing and 90% confidence interval assumptions and found the study results in
agreement with the drill spacing classification criteria described above.
-The trial grade 10mE×10mN control pattern drilled within an 100m×100m area during the
project Feasibility Study has also confirmed the precision assumptions and confidence the
Mineral Resource estimate in that area
-Mine reconciliation for the life-of-mine to date is satisfactory.

PAGE 23

==> picture [595 x 82] intentionally omitted <==

Section 4 Estimation and Reporting of Ore Reserves

Criteria Commentary
Mineral Resource
estimate for
conversion to Ore
Reserves
-The estimate used for the Ore Reserve study is the Open Pit estimate described in the
preceding sections of this JORC table 1.
-The Tropicana Open Pit Mineral Resource is reported inclusive of the Ore Reserve.
-No Ore Reserve has been estimated from the Underground Mineral Resource estimate.
Site visits -The Competent Person for the Ore Reserve is the Senior LoM Planning Engineer and as
such has intimate knowledge of the operation and is in daily contact when on site with
personnel providing key inputs to the estimate.
Study status -The level of study for the Ore Reserve estimate is commensurate with industry
expectations of a Feasibility Study as described in the JORC Code, with all material
Modifying Factors considered in the Ore Reserve estimate.
-Current mining and processing operations confirming that the mine plans are technically
feasible and economically viable
Cut-off parameters -The Ore Reserve reporting cut-offs are determined based on the net return of gold
produced at the processing plant for each ore type.
-The specific cut-offs for reporting the Ore Reserve are;≥0.6g/t Au for oxide and≥0.7 g/t
Au for transitional and fresh rock.
Mining factors or
assumptions
-The mining method for the Ore Reserve is open pit mining with conventional excavators
and trucks with blasting on 10m benches in Tropicana and Havana and 7.5m in Boston
Shaker. Ore is mined in three 1/3 bench height flitches.
-Inter-ramp pit slope angles are assumed to be 35°on the footwall and 67°on the
hangingwall in both oxide and fresh rock, modified depending on lithology and alteration
type.
-The Ore Reserve is reported within operation designs that have been prepared using the
Mineral Resource model described above, geotechnical inputs and financial assumptions
discussed below.
-Grade control RC drilling is completed on a 12mE×12mN pattern prior to ore mining.
-No mining dilution has been applied as the LUC model incorporates internal dilution.
-Mining recovery of ore is assumed to be 100%
-Mine designs assume a minimum working face of 50m to 80m at the base of pits.
-Inferred Mineral Resources are excluded from the Ore Reserve with the total in-pit
Inferred Resource being <0.001% of the Ore reserve and as such, is no material to the
mine viability.
-No new infrastructure is required to support the operating mine methods.
Metallurgical factors
or assumptions
-The metallurgical process for Tropicana ores is already established and is a process flow
of crushing (grinding rolls), grinding the recovery of gold through carbon-in-leach and
electrowinning to produce gold bars.
-Gold recovery factors are based on extensive metallurgical testing and range from 92.5%
recovery in mineralised transported material down to 89.9% recovery in fresh rock.
-No deleterious elements are present in the ore.
-In the project Feasibility Study Pilot scale test work was carried out on large diameter
(PQ) core collected in a spatially representative manner form the deposit. To date
metallurgical recoveries have been consistent with the forecasts from these studies.
-As a gold mine, the gold doré bars produced are not subject to any specification
requirements.
Environmental -Tropicana Gold mine operates under an environmental manage plant that meets or
exceeds all statutory and legislative requirements.
-Miner rock wastes are disposed in waste dumps which are progressively rehabilitated as
mining progresses with any potentially acid generating waste encapsulated in non-acid
generating material.

PAGE 24

==> picture [595 x 82] intentionally omitted <==

Criteria Commentary
-A tailing storage facility is used to contain and capture process residues.
-The mine produces rehabilitation plans for ongoing rehabilitation and mine closure plans,
and the costs are included in the financial model.
Infrastructure -All major infrastructure required for the mining and processing is in place.
-The owner and contractor staffing is fully complete, with personnel sourced on a fly-in-
out basis from Perth or Kalgoorlie.
-No other significant infrastructure is anticipated and sustaining capital cost for
infrastructure are included in the financial model.
Costs -The capital cost of removing waste overburden are included in the evaluation of the
applicable pit designs.
-Mining operating costs are provided by the mining contractor and other costs are sourced
from in the mine operating budget.
-As discussed there are no deleterious elements and as such related costs are not
relevantThe source of AU$:US$ exchange rates is AGAA/IGO corporate guidance
-Transpiration charges for gold doré bars is relatively minor and are charged on a contract
basis with the refinery.
-Treatment and refining charges are included in the refining contract and there are no
specification ore penalties associated with treatment and refining.
-WA State royalties are levied at 2.5% of the value of gold produced.
Revenue factors -The assumption for gold prices for the Ore Reserve is US$1,100/oz based on corporate
guidance and assessment of historical prices
-The A$:US$ exchange rate is 0.74, also based on corporate guidance and assessment
of historical exchange rates.
Market assessment -No specific market assessment has been completed for this Ore Reserve update.
Economic -The inputs into the economic analysis for the Ore Reserve update have already been
described above under previous subsections.
-The economic evaluation has been carried out on a real basis (adjusted for inflation) with
rates provided by AGAA corporate.
-The confidence in majority of the economic inputs is high as Tropicana is an operating
mine and as such, costs (opex and capex) are well understood.
-The confidence in metal prices and exchange rates is consistent with routine industry
practices with the data derived from reputable forecasters.
-The discount rate used for NPV calculations is derived from the weighted average cost
of capital in Australia.
-Sensitivity studies have been completed on inputs such a mining and processing costs,
gold price and discount rate. NPV has the greatest sensitivity to gold price with an
estimated 30,000oz lost from the Ore Reserve for a 10% reduction in gold price.
Social -Tropicana Gold Mine has all necessary agreements in place with key stakeholders and
matters leading to social licence to operate.
Other -There are no material naturally occurring risks associated with the Tropicana operation.
-There are no material legal agreements or marketing arrangements not already
discussed in prior sub sections.
-All necessary government and statutory approvals are in place.
-There are no unresolved third-party matters hindering the extraction of the Ore Reserve.
Classification -The Ore Reserve has been classified into Proved and Probable Ore Reserve JORC Code
classes based on the underlying MRE classification in the MRE model, with Measured
Mineral Resources converted to Proven Ore Reserves, and Indicated Mineral Resources
converted to Probable Ore Reserves.
-The classifications applied to the estimate are consistent with the opinion of the
Competent Person reporting the Ore Reserve.

PAGE 25

==> picture [595 x 82] intentionally omitted <==

Criteria Commentary
-There is no portion of Probable Ore Reserves derived from Measured Mineral Resources
Audits or reviews -A Mineral Resource and Ore Reserve audit was completed in CY17 and no material
recommendation came from the audit
-The current Ore Reserve estimate has been reviewed internally by AGAA personnel
Discussion of
relative accuracy/
confidence
-AGAA has carried out simulation to quantify the confidence in the Ore reserve – refer to
the commentary at the end of Section 3 above.
-The main driver of accuracy and confidence is the spacing of the pre-production drilling,
which is captured in the Mineral Resource JORC Code classifications underpinning the
Ore Reserve estimates.
-Confidence in Ore Reserve inputs is generally high given the mine is operation and costs,
prices, recoveries and so on are well understood.
-The Ore Reserve estimates are considerate to have sufficient local accuracy to support
mine planning and production schedules with Proved Ore Reserves considered a reliable
basis for quarterly production targeting and Probable Ore Reserves reliable for annual
production targets.
-Confidence in the mine design and schedule are high as mining rates and modifying
factors are based on actual site performance. Mine designs are consistent with what has
been effective previously.
-The mine to mill reconciliation data to date indicates the forecast precision of the
estimates is good with the Ore Reserve estimate slightly conservative.

PAGE 26