ANNUAL MINERAL RESOURCE AND ORE RESERVE STATEMENT

Independence Group NL (IGO or the Company) (ASX: IGO) is pleased to provide its annual Mineral Resource and Ore Reserves estimates, as at 30 June 2016.

Highlights

  • Total Mineral Resource for the Tropicana Gold Mine (100% basis) is 7.5Moz and Ore Reserve is 2.4Moz, under the existing mining costs structure. An updated Mineral Resource and Ore Reserve is expected to be released in the December 2016 quarter as part of the Long Island study.

  • Nova Project Mineral Resource and Ore Reserves remain unchanged although the resource is currently being de-risked with the current grade control program. Results to-date are encouraging.

  • Successful completion of the Flying Spur and Arnage resource definition drilling at Bentley has resulted in a significant Ore Reserve increase with extension of the life of mine to greater than 3 years.

  • IGO actively drilling both highly prospective brownfields and greenfields projects with the aim of delivering further resource and reserve growth in the future.

Commenting on the update IGO’s Managing Director and CEO, Peter Bradford, said:

“We have significantly strengthened our growth platform during FY16 as we transform the business in FY17.

A key element of the Tropicana Long Island study has been completed with development of the mineral resource model, which captures the resource drilling completed as part of this study. The model will form the framework for the completion of the prefeasibility study. The current Mineral Resource stands at 7.5Moz of gold using the current cost structure to constrain the resource, with the Ore Reserve at 2.4Moz of gold. A change in the mining costs delivered by the strip mining approach and optimisation of waste haulage being investigated as part of our Long Island Study will unlock the resource to reserve conversion. An updated Mineral Resource and Ore Reserve will be issued as part of the study expected in the December quarter”

At Nova there has been no change to our Mineral Resource or Ore Reserve statement, however the resource continues to be de-risked with the current grade control drilling program. At present, we have three underground diamond drill rigs executing this program. Results to date, although only representative of a small proportion of the total resource have been encouraging with positive nickel equivalent metal reconciliations when compared to the resource model.

IGO has consistently extended the Jaguar and Long Operations life of mines through brownfields exploration. We have again demonstrated this during FY16 with Ore Reserve growth at Jaguar from the drilling program targeting the Flying Spur and Arnage lenses at Bentley underground with zinc contained metal, net of depletion increasing approximately 56%. Exploration has recommenced at Long with the aim of again extending the life of mine for FY17, as has been the historic trend of this operation.

==> picture [596 x 83] intentionally omitted <==

There are numerous exciting exploration programs planned for FY17 across our extensive and highly prospective brownfields and greenfields portfolio. It is these programs which will continue to deliver resource and reserve growth for IGO in the future.”

An overview of each of the assets in the Company’s portfolio is provided within this release .

Table 1: IGO Group – 100% basis - 30 June 2016 Total Mineral Resources

Project Tonnes
Grade
Contained Metal
Ore
(Mt)
Ni
(%)
Cu
(%)
Zn
( %)
Ag
(g/t)
Au
(g/t)
Ni
(kt)
Cu
(kt)
Zn
(kt)
Ag
(Moz)
Au
(Moz)
Nova 14.3
2.3
0.9



325
134


Long 1.3
4.7




60



Tropicana 37.4




1.9




2.2
Jaguar 3.7

1.4
7.0
111
0.6

51
256
13.1
0.1
Stockman 14.0

2.1
4.3
38
1.0

294
598
17.1
0.4
Total 70.6

Notes:

  1. Detailed tables setting out each of the Measured, Indicated and Inferred Mineral Resource categories are set out on tables 3 to 12 on each of the relevant sections.

  2. All figures are rounded to reflect appropriate levels of confidence. Apparent differences may occur due to rounding. 3. Tropicana Gold Mine - IGO share (30%) shown.

  3. Long Operation, Jaguar Operation, Nova Project and Stockman Project are 100% IGO owned.

  4. Metal quantities are contained metal.

  5. Mineral Resources are inclusive of Ore Reserves.

Table 2: IGO Group – 100% basis - 30 June 2016 Total Ore Reserves

Project Tonnes
Grade
Contained Metal
Mt
Ni
(%)
Cu
(%)
Zn
(%)
Ag
(g/t)
Au
(g/t)
Ni
(kt)
Cu
(kt)
Zn
(kt)
Ag
(Moz)
Au
(Moz)
Nova 13.6
2.0
0.8



275
112


Long 0.4
3.9




14



Tropicana 12.3




1.8




0.7
Jaguar 1.4

1.1
9.5
145
0.8

16
137
6.7
0.0
Stockman 9.0

2.1
4.5
39
1.1

189
408
11.3
0.3
Total 36.7

Notes:

  1. Detailed tables setting out each of the Proven and Probable Ore Reserves are set out on tables 3 to 12 on each of the relevant sections.

  2. All figures are rounded to reflect appropriate levels of confidence. Apparent differences may occur due to rounding. 3. Metal quantities are contained metal

  3. Tropicana Gold Mine - IGO (30%) share shown.

  4. Long Operation, Jaguar Operation, Nova Project and Stockman Project are 100% IGO owned.

Nova Project

The world-class Nova Project is located 160km by road, east of Norseman. The Nova discovery hole was drilled in July 2012 and a maiden resource was released twelve months later, in May 2013. The Definitive Feasibility Study was completed in July 2014. As at 30 June 2016, the overall Project construction and

PAGE 2

==> picture [596 x 83] intentionally omitted <==

development was 93% complete. The Project is on schedule and on budget to produce first nickel and copper concentrates by December 2016.

Geology

The Nova–Bollinger magmatic nickel-copper-sulphide deposits are located in the Fraser Zone of the ~1.3 billion year (Ga) old Albany–Fraser Orogenic belt, on the south-eastern margin of the Archaean aged Yilgarn Craton, in Western Australia. The mineralisation is hosted by meta-gabbro to meta-picrite cumulates that were originally emplaced as a series of sills in an extensional sedimentary basin during the late stages of continental breakup.

The deposit is located on the north-western side of an ovoid structural feature measuring approximately 3km by 1.5km, which is best seen in regional and ground magnetics. The deposits are analogous to many mafichosted nickel-copper deposits worldwide.

The Nova and Bollinger deposits are generally tabular in geometry, with clear boundaries that define the various mineralised domains. The Nova and Bollinger deposits are joined by a feeder zone.

Mineralisation at Nova and Bollinger occurs as massive, breccia, matrix or net-textured and disseminated sulphides. Massive sulphides within Nova typically grade 6.0 to 7.0% nickel, and disseminated sulphide mineralisation contains in the order of 0.5 to 1.5% nickel. The massive sulphide at Bollinger is lower grade, typically containing 4.5 to 5.5% nickel. The primary ore mineralogy is pyrrhotite (~80-85%), pentlandite (~1510%) and chalcopyrite (5-10%), irrespective of the ore type.

Mineral Resource

The Mineral Resource estimate for the Nova Project as at 30 June 2016, which covers both the Nova and Bollinger deposits is estimated at 14.3Mt at 2.3% Ni, 0.9% Cu and 0.08% Co with no change to the 30 June 2015 Mineral Resource.

An extensive grade control diamond drilling program commenced in May 2016. As of the end of September 2016 there were three underground diamond drill rigs executing the work program which is expected to take 14 months, to complete an estimate of 139km of drilling. The nominal drill spacing is 12.5m by 12.5m.

Grade control drilling and interpretation has been completed between the 2080mRL level and the 2030mRL level and updated into the Nova grade control model. The grade control model provides a more robust local estimate given the improved geological understanding and higher resolution of data. Reconciliation between the grade control model and resource model has been encouraging. To-date, although over a small volume compared to the total resource, the reconciliation is showing a slight decrease in tonnes and increase in nickel equivalent grades for an approximate 5% increase in contained nickel equivalent metal.

Ore Reserve

The Ore Reserve for the Nova Project was updated as part of the Nova Optimisation Study (ASX 14 December 2015 – Optimisation Study Significantly Enhances Nova Project Value). The Probable Ore Reserve estimate as at 30 June 2016 is 13.6Mt @ 2.0% Ni, 0.8% Cu and 0.07% Co for contained metal of 275kt of nickel, 112kt of copper and 9kt of cobalt metal. This underpins an initial mine life of 10 years.

Exploration

IGO has approximately 3,200km[2] of tenements in the Fraser Range region with an additional 450km[2] of tenements added to the portfolio with the joint venture entered into with Buxton Resources. IGO’s strategy is to pursue further consolidation to strengthen its brownfields exploration portfolio proximal to the Nova Project.

Some key exploration activities planned for FY17 include:

  • Resource extension at Nova including the drill testing of the Conductor 5 from the Bollinger Decline;

  • Establishing an underground Electromagnetic Loop (EM) with deeper framework drilling to be completed beneath the Nova and Bollinger orebodies as a geophysical platform;

  • 3D seismic to provide the geological and structural architecture for the Nova-Bollinger deposits;

PAGE 3

==> picture [596 x 83] intentionally omitted <==

  • Commencement of an embedded postdoctoral research program with the Commonwealth Scientific and Industrial Research Organisation (CSIRO) and University of Western Australian (UWA) on the lithostratigraphy, magmatic evolution and control on emplacement and mineralisation associated with the Nova-Bollinger orebodies;

  • Systematic ground EM over key prospects;

  • Extensive aircore, reverse-circulation (RC) and diamond drill testing of the highly ranked prospects.

Table 3: Nova Project – 30 June 2016 Mineral Resources (and 2015 comparison)

Mineral Resources ‐ June Mineral Resources ‐ June Mineral Resources ‐ June Mineral Resources ‐ June 2015 Mineral Resources ‐ 30 June Mineral Resources ‐ 30 June Mineral Resources ‐ 30 June Mineral Resources ‐ 30 June 2016
Tonnes Grade Contained Metal Tonnes Grade Contained Metal
Ni Cu Co Ni
Cu
Co Ni Cu Co Ni Cu Co
Deposit Classification (Mt) (%) (%) (%) (kt) (kt) (kt) (Mt) (%) (%) (%) (kt) (kt) (kt)
Nova Measured
Indicated 9.1 2.5 1.0 0.08 230 94 7.3 9.1 2.5 1.0 0.08 230 94 7.3
Inferred 1.0 1.4 0.6 0.05 14 6 0.5 1.0 1.4 0.6 0.05 14 6 0.5
Sub‐total 10.1 2.4 1.0 0.08 244 100 7.7 10.1 2.4 1.0 0.08 244 100 7.7
Bollinger Measured
Indicated 2.4 2.7 1.1 0.11 64 26 2.6 2.4 2.7 1.1 0.11 64 26 2.6
Inferred 1.8 1.0 0.4 0.04 17 8 0.7 1.8 1.0 0.4 0.04 17 8 0.7
Sub‐total 4.2 2.0 0.8 0.08 82 34 3.3 4.2 2.0 0.8 0.08 82 34 3.3
Stockpile
GRAND TOTAL 14.3 2.3 0.9 0.08 325 134 11.0 14.3 2.3 0.9 0.08 325 134 11.0

Notes:

  1. Mineral Resources are reported above a 0.6% nickel equivalent cut-off grade which is calculated as NiEq% = ((Cu % x 0.95) x ($7,655/$16,408)) + (Ni % x 0.89).

  2. As at 30 June 2016 the resource broken stocks was not material to the Mineral Resource with an estimated 11.8kt at 0.88% Ni, 0.55% Cu and 0.03% Co stockpile.

  3. There is no change to the Mineral Resources from June 2015 to June 2016, with no drilling completed nor changes to the understanding of the geological controls.

  4. Mineral Resources are inclusive of Ore Reserves.

  5. No depletion has occurred during the period.

  6. Ore tonnes have been rounded to the nearest hundred thousand tonnes.

  7. All figures are rounded to reflect appropriate levels of confidence. Apparent differences may occur due to rounding.

  8. JORC Code (2012) Table 1 Parameters are contained within Appendix A of this release

Table 4: Nova Project – 30 June 2016 Ore Reserves (and 2015 comparison)

Ore Reserves ‐ December 2015 Ore Reserves ‐ 30 June 2016
Tonnes
Grade
Contained Metal
Tonnes
Grade
Contained Metal
Deposit
Classification
(Mt)
Ni
(%)
Cu
(%)
Co
(%)
Ni
(kt)
Cu
(kt)
Co
(kt)
(Mt)
Ni
Cu
Co
Ni
Cu
Co
(%)
(%)
(%)
(kt)
(kt)
(kt)
Bollinger
Proven
2.7
Probable
2.7
2.2
0.9
0.09
59
24
2
2.2
0.9
0.09
59
24
2
Sub‐Total
2.7
2.2
0.9
0.09
59
24
2
2.7
2.2
0.9
0.09
59
24
2
Nova
Proven
10.9
Probable
10.9
2.0
0.8
0.06
216
89
7
2.0
0.8
0.06
216
89
7
Sub‐Total
10.9
2.0
0.8
0.06
216
89
7
10.9
2.0
0.8
0.06
216
89
7
Stockpile












GRAND TOTAL
13.6
2.0
0.8
0.07
275
112
9
13.6
2.0
0.8
0.07
275
112
9

Notes

  1. All figures are rounded to reflect appropriate levels of confidence. Apparent differences may occur due to rounding.

PAGE 4

==> picture [596 x 83] intentionally omitted <==

  1. As at 30 June 2016 the Ore Reserves broken stocks was not material to the Ore Reserve with an estimated 9.3kt at 0.99% Ni, 0.62% Cu and 0.03% Co stockpile.

  2. A Net Smelter Return (NSR) cut-off value of $64/t of stope ore has been used in the evaluation of the Ore Reserve, which includes mining and G&A operating costs. Processing costs are captured as a variable to the NSR block value.

  3. There is no change to the December 2015 Ore Reserve as the project is still under construction and no new significant information is available as of 30 June 2016.

  4. Minor Ore Reserves are now broken stocks on the ROM pad but as yet have not been reconciled through processing and sampling.

  5. Sub-level open-stoping with paste backfill is the primary method of mining to be used at Nova.

  6. The Ore Reserve has been estimated as part of the Optimisation Study completed by IGO in December 2015. 8. JORC Code (2012) Table 1 Parameters are contained within Appendix A of this release

Tropicana Gold Mine (IGO 30%, AngloGold Ashanti 70%)

The Tropicana Gold Mine, a joint venture between IGO and AngloGold Ashanti Australia (AGAA) is located 330km east-northeast of Kalgoorlie. Tropicana is a greenfields exploration discovery, with open pit mining commencing in 2012 and first gold production occurring during September 2013. The Tropicana Joint Venture partners hold a dominant land position covering the geological host sequence to the exploited mineralisation and consequently the Joint Venture partners have a competitive advantage in understanding its mineralised system. The land position covers approximately 2,900km[2] of tenements along a strike length of approximately 200km.

A significant framework drilling program was executed during FY16 as part of the Long Island study. The Long Island study is an internal name given to a work program designed to unlock the future potential of the Tropicana Gold Mine. The goals of the Long Island study are to provide an economically robust method of accessing the substantial mineralisation identified below the current Ore Reserve pit design via open pit mining methods. Current studies are quantifying alternative lower cost mining methods to enable mining of ore below the current planned pits, which would extend the life of mine and improve the mining cost structure.

Due to the unique geometry and continuity of mineralisation at Tropicana, the JV partners are considering a strip mining approach, which has the effect delivering a step change reduction in mining costs as a result of reducing haulage of waste which is predominantly hauled and dumped in pit. The current concept involves using the Tropicana pit as a void for waste dumping once it has been mined to the end of its current Ore Reserve limit. Once the Ore Reserves are depleted at the Tropicana pit, it will be backfilled with waste from the strip mining of the Havana, Havana South, and Boston Shaker ore zones. The approach reduces waste removal mining costs as a result of shorter haul distances which would, in turn, facilitate economically viable extensions to the life of mine.

The resource model which forms part of the Mineral Resource statement captures the framework drilling completed as part of the Long Island study. However, no changes to mining cost assumptions from the Long Island study have been captured to constrain the 2016 Mineral Resource. Completion of the Long Island study to pre-feasibility level is expected to be completed during the December 2016 quarter, which will also include an update to the Mineral Resource and Ore Reserve statements.

Geology

The Tropicana Gold Mine lies to the west of a major tectonic suture between the Yilgarn Craton and the Proterzoic Albany-Fraser Belt that stretches over 550km northeast-southwest. The regional geology is dominated by granitoid rocks, felsic to mafic paragneiss and orthogneiss, and felsic to ultramafic intrusive and volcano-sedimentary rocks.

The Tropicana, Havana, Havana South and Boston Shaker deposits define a north-east trending mineralised corridor approximately 1.2km wide and 5km long, that has been tested to a vertical depth of more than 1,200m below the Havana pit. Mineralisation is up to 50m thick, which is hosted predominantly in quartzofeldspathic gneiss, bounded by a garnet-gneiss hangingwall sequence. The mineralisation is accompanied by pyrite (2% to 8%) with accessory pyrrhotite, chalcopyrite and other minor sulphides and tellurides.

Mineralisation remains open down-dip from the Havana, Havana South and Boston Shaker deposits.

PAGE 5

==> picture [596 x 83] intentionally omitted <==

Mineral Resource

The total Tropicana Mineral Resource (100% basis) for as at 30 June 2016 is estimated at 124.8Mt @ 1.86g/t Au for 7.48Moz of contained gold compared to 115.7Mt at 1.89g/t Au for 7.04Moz.

The Mineral Resource as reported captures the Long Island exploration drilling through to the end of June 2016. The Mineral Resource has been reported internal to an optimised shell based on an assumed gold price of US$1,400/oz (A$1,817/oz), depleted through to 30 June 2016. The optimised pit shell is based on current mining costs and does not capture expected mining cost reductions as part of the Long Island study. In comparison to the Mineral Resource as at 30 June 2015, the break-down of the year-on-year changes to the Mineral Resource include:

  • Depletion of ~-480koz of gold

  • Stockpile adjustments of ~-10koz of gold

  • Long Island exploration success internal to the open pit resource shell of ~300koz of gold

  • Changes to the underground mining shapes of ~110koz of gold

  • Long Island exploration success external to the open pit resource shell captured as an underground increase of 840koz of gold

  • Changes to the gold price and cost modifying parameters resulting in a decrease of ~-320koz of gold

An update on the Mineral Resource and Long Island study based on expected changes to the mining cost structure is expected to be completed in the December 2016 quarter.

Ore Reserve

During the FY16, 7.3Mt of ore at 2.13g/t Au were mined from the Havana, Tropicana and Boston Shaker pits (>0.6g/t Au) on a 100% basis. IGO attributable gold production was 134koz of gold produced for this period.

The Total Tropicana Ore Reserves (100% basis) as at 30 June 2016 was 41Mt at 1.83g/t Au for 2.41Moz of contained gold. The Ore Reserve has been restated based on mining depletion as at 30 June 2016 using the 30 June 2015 Mineral Resource model.

It is important to note that neither the exploration drilling nor the expected changes to the mining costs as part of the Long Island study have been captured as part of this Ore Reserves Statement. Release of an updated Ore Reserve for Tropicana is expected to be provided in the December quarter 2016. A change in the mining cost structure will likely deliver a favourable resource to reserve conversion.

Exploration

The framework drilling associated with the Long Island study was substantially completed in FY16. The drill hole spacing ranges from 50m by 50m down plunge of known higher-grade ore shoots to 100m by 100m or greater, elsewhere along strike. Current resource extensional exploration drilling programs will focus on improved definition of high-grade ore shoots on a 50m by 50m spacing at Havana South, Havana and Boston Shaker. Results to date have been encouraging, extending the high-grade ore shoots.

Regional exploration on the extensive ground position has been the priority at the completion of the current stage of the Long Island study. The joint venture has developed an improved understanding on the geological host sequence and structural controls which has resulted in enhanced targeting and prioritisation of prospects. The tenements host a portfolio of numerous exploration prospects including, Tumbleweed, Voodoo Child, Zebra, Beetlejuice, Sanpan, Monsoon, Panama and Angel Eyes. These prospects are planned to be systematically tested during FY17.

PAGE 6

==> picture [596 x 83] intentionally omitted <==

Table 5: Tropicana Gold Mine – 100% basis (IGO 30%) - 30 June 2016 Mineral Resources (and 2015 comparison)

omparison)
Mineral Resources ‐ 30 June 2015 Mineral Resources ‐ 30 June 2016
Contained Contained
Tonnes Grade Metal Tonnes Grade Metal
Au Au Au Au
Classification (Mt) (g/t) (Moz) (Mt) (g/t) (Moz)
Open Pit Measured 12.8 2.09 0.86 10.9 1.91 0.67
Indicated 75.3 1.85 4.47 78.3 1.71 4.32
Inferred 5.8 2.54 0.48 4.4 2.23 0.32
Sub‐Total 93.9 1.92 5.80 93.7 1.76 5.30
Underground Measured
Indicated 2.4 3.58 0.27 5.4 3.36 0.59
Inferred 5.8 3.14 0.59 12.1 3.13 1.22
Sub‐Total 8.2 3.26 0.86 17.6 3.20 1.81
Stockpiles Measured 13.6 0.87 0.38 13.6 0.85 0.37
Total Tropicana Measured 26.4 1.46 1.24 24.5 1.32 1.04
Indicated 77.7 1.90 4.74 83.8 1.82 4.90
Inferred 11.7 2.84 1.06 16.6 2.89 1.54
GRAND TOTAL 115.7 1.89 7.04 124.8 1.86 7.48

Notes:

  1. The open pit Mineral Resource is reported at a 0.3g/t Au cut-off for oxide material and a 0.4g/t Au cut-off for transitional and fresh material, constrained within an a US$1,400/oz Au (A$1,817/oz Au) optimised pit shell based on actual mining and processing costs.

  2. The underground Mineral Resource is reported outside the US$1,400/oz Au pit optimisation based on underground mineable shapes at a cut-off grade of 2.0g/t Au.

  3. All figures are rounded to reflect appropriate levels of confidence. Apparent differences may occur due to rounding. 4. Mineral Resources are inclusive of Ore Reserves.

  4. All Mineral Resources are completed in accordance with the 2012 JORC Code.

  5. JORC Code (2012) Table 1 Parameters are contained within Appendix B of this release

Table 6: Tropicana Gold Mine – 100% basis (IGO 30%) - 30 June 2016 Ore Reserves (and 2015 comparison)

omparison)
Ore Reserves ‐ 30 June 2015 Ore Reserves ‐ 30 June 2016
Contained Contained
Tonnes Grade Metal Tonnes Grade Metal
Au Au Au Au
Classification (Mt) (g/t) (Moz) (Mt) (g/t) (Moz)
Open Pit Proved 11.1 2.27 0.81 7.6 2.33 0.57
Probable 29.0 2.05 1.91 24.2 2.01 1.56
Sub‐Total 40.1 2.11 2.72 31.8 2.07 2.12
Stockpiles Proved 8.4 1.09 0.29 9.2 0.98 0.29
GRAND TOTAL 48.5 1.93 3.01 41.0 1.83 2.41

Notes

  1. The Proven and Probable Ore Reserves is reported above economic break-even gold cut-off grade for each material type at nominated gold price of US$1,100/oz (A$1,436/oz).

  2. The Ore Reserve estimate is update based on depletion as at 30th June 2016, using the Resource model from July 2015.

  3. The cut-off grades reported were 0.6/g Au for oxide material and 0.7g/t Au for transitional and fresh.

  4. All figures are rounded to reflect appropriate levels of confidence. Apparent differences may occur due to rounding.

  5. JORC Code (2012) Table 1 Parameters are contained within Appendix B of this release

PAGE 7

==> picture [596 x 83] intentionally omitted <==

Long Operation

The Long Operation is located 60km south of Kalgoorlie and forms part of the world-class Kambalda Dome nickel sulphide mineralised complex. The Long Operation has been in continuous production since 1979, except for a short hiatus in 2002 between transition of ownership from BHP Billiton Nickel West Pty Ltd (formerly WMC Resources Ltd (WMC)) and IGO.

Since the acquisition, IGO has produced over 3.2Mt of nickel ore, containing approximately 125kt of nickel metal from the Long Operation. This is in addition to the 5.4Mt of nickel ore with contained nickel metal of 203kt previously produced from the operation. The Long Operation has a history of continued exploration success including, extensions to known mineralisation defined by WMC and discovery of new mineralisation by IGO at the Long, Victor, Gibb, Gibb South, Victor South, Long North, Moran, McLeay, Moran South and McLeay South orebodies. This discovery record has enabled the operation to maintain an Ore Reserve base to support a two to three year mine life over the previous 13 years of IGO operation. The current life of mine plan extends for the next 18 months based on current Ore Reserves.

Geology

The Long Operation occurs along the eastern flank of the Kambalda Dome in the South Central portion of the Archaean aged Norseman-Wiluna Greenstone belt of the Yilgarn Craton in Western Australia. The Kambalda Dome is a double-plunging antiform with a core of granodiorite flanked by meta-tholeiitic basalt that is overlain by komatiite and intercalated sediments. The host rocks and associated contacts have been subjected to lower amphibolite metamorphism, structural modification, and intrusion by multiple felsic to intermediate igneous dykes that are mostly barren.

The Kambalda style nickel-sulphide orebodies are associated with Archaean aged ultramafic lava channels where molten liquid nickel-sulphides pooled at topographic lows along the komatiite channel. Subsequent folding has rotated the channels from 30° to vertical dip to the east, 10° plunge to the south as well as resulting in the remobilisation of some of the original sulphides into new, structurally imposed positions. The nickel sulphide orebodies are narrow, ribbon-like accumulations of massive to semi-massive sulphides to disseminated sulphides up to 12m thick.

The Long Operation consists of four main deposits in two parallel lava channels: Long and Moran in one channel (the Long Channel), McLeay and Victor South in another (the Victor Channel). Victor South contains the only disseminated sulphides of economic value whereas the other three are massive to semimassive or matrix ore nickel-sulphide deposits. The Victor Channel was also host to the Gibb, Gibb South and Victor deposits, which are now mined out.

Mineral Resource

The Mineral Resource estimate for FY16, as at 30 June 2016 has been reduced in both tonnes and grade from 30 June 2015, attributed dominantly by mining depletion of the Moran orebody. As at 30 June 2016 the Mineral Resource estimate was 1,259kt at 4.7% Ni for 59,700t of contained nickel metal . This compares with 1,379kt at 4.8% Ni for 66,400t of contained nickel metal as at 30 June 2015.

Ore Reserve

During FY16, 215kt at an average grade of 3.9% Ni for 8,500t of contained nickel metal were mined, predominantly from the Moran deposit.

The Ore Reserve as at 30 June 2016 was 351kt at 3.9% Ni for 13,600t of contained nickel metal. This compares with 608kt at 3.6% Ni for 22,000t of contained nickel metal as at 30 June 2015.

Exploration and Resource Extension

In response to low nickel prices, the Long business plan was reviewed in late 2015 and a new business plan implemented, designed to ensure the profitability and sustainability for the current operation at lower nickel prices. As part of the plan all exploration activities where suspended.

PAGE 8

==> picture [596 x 83] intentionally omitted <==

Exploration has recommenced in July 2016 with the prioritisation of testing prospective targets that could be easily accessed from the current mine development without significant capital investment. The exploration program planned for FY17 is designed to extend the Long Operation life of mine back to a two to three year window, as has been the case historically.

The first of the targets to be tested which has commenced in July 2016 is directly west of the Victor orebody which has the potential to host a Kambalda style flow channel. Historic drilling by WMC has intersected lower contact mineralisation (eg. KD6165 0.71m @ 5.11%Ni including 0.12m @ 19.20%Ni). The target is approximately 250m west of the current Victor decline mine development.

Table 7: Long Operation - 30 June 2016 Mineral Resources (and 2015 comparison)

Mineral Resources ‐ 30 June 2015 Resources ‐ 30 June 2015 Mineral Resources ‐ 30 June 2016
Contained Contained
Tonnes Grade Metal Tonnes Grade Metal
Ni Ni Ni Ni
Classification (t) (%) (t) (t) (%) (t)
Long Measured 65,000 5.4 3,500 62,000 5.3 3,300
Indicated 287,000 5.1 14,600 287,000 5.1 14,600
Inferred 355,000 4.7 16,700 355,000 4.7 16,700
Sub‐Total 707,000 4.9 34,800 704,000 4.9 34,600
Victor South Measured
Indicated 147,000 2.1 3,100 147,000 2.1 3,100
Inferred 33,000 1.5 500 33,000 1.5 500
Sub‐Total 180,000 2.0 3,600 180,000 2.0 3,600
McLeay Measured 63,000 6.3 4,000 61,000 6.4 3,900
Indicated 71,000 4.9 3,500 71,000 4.9 3,500
Inferred 21,000 6.7 1,400 21,000 6.7 1,400
Sub‐Total 155,000 5.7 8,900 153,000 5.8 8,800
Moran Measured 234,000 6.6 15,500 126,000 7.2 9,100
Indicated 51,000 3.3 1,700 44,000 3.9 1,700
Inferred 52,000 3.7 1,900 52,000 3.7 1,900
Sub‐Total 337,000 5.7 19,100 222,000 5.7 12,700
Stockpiles Measured
GRAND TOTAL 1,379,000 4.8 66,400 1,259,000 4.7 59,700

Notes:

  1. Mineral Resources are reported using a 1% Ni cut-off grade except for the Victor South disseminated Mineral Resource, which is reported using a cut-off grade of 0.6% Ni.

  2. Block modelling used the ordinary-kriging grade-interpolation method on 1m composites within wireframes for all elements and density for the Victor South, McLeay and Moran deposits. For the Long mineralisation, ordinarykriging was used to estimate metal accumulation and horizontal width variables for each drill hole intercept into a two-dimensional block model. The final block grades were back-calculated and the block model was converted to a conventional three-dimensional block model using nearest neighbour assignment.

  3. Mining as at 30 June 2016 has been removed from the 2016 Mineral Resource estimate.

  4. Mineral Resources are inclusive of Ore Reserves.

  5. All figures are rounded to reflect appropriate levels of confidence. Apparent difference may occur due to rounding.

  6. JORC Code (2012) Table 1 Parameters are contained within Appendix C of this release.

PAGE 9

==> picture [596 x 83] intentionally omitted <==

Table 8: Long Operation – June 2016 Ore Reserves (and 2015 comparison)

Table 8: Long Operation – June 2016 Ore Reserves (and 2015 comparison) Table 8: Long Operation – June 2016 Ore Reserves (and 2015 comparison)
Ore Reserves ‐ 30 June 2015
Ore Reserves ‐ 30 June 2016
Tonnes
Grad
Contained
Metal
Tonnes
Contained
Grad
Metal
Classification
(t)
Ni
(%)
Ni
(t)
(t)
Ni
Ni
(%)
(t)
Long
Proved
28,000
3.6
1,000
23,000
Probable
94,000
2.8
2,600
45,000
3.5
800
3.1
1,400
Sub‐Total
122,000
3.0
3,600
68,000
3.2
2,200
Victor South
Proved
7,000
3.0
200
4,000
Probable
15,000
2.2
300
6,000
5.0
200
1.7
100
Sub‐Total
22,000
2.5
500
10,000
3.0
300
McLeay
Proved
22,000
3.5
800
18,000
Probable
24,000
3.1
700
19,000
3.9
700
3.2
600
Sub‐Total
46,000
3.3
1,500
37,000
3.5
1,300
Moran
Proved
380,000
4.0
15,200
224,000
Probable
38,000
3.0
1,200
12,000
4.2
9,400
3.3
400
Sub‐Total
418,000
3.9
16,400
236,000
4.2
9,800
Stockpiles
Proved




GRAND TOTAL
608,000
3.6
22,000
351,000
3.9
13,600

Notes:

  1. Ore Reserves are reported above an economic Ni Cut-off value as at 30 June 2016.

  2. A NSR value of $176/t has been used in the evaluation of the 2016 Ore Reserve.

  3. Mining as at 30 June 2016 has been depleted from the 2016 Ore Reserves estimate.

  4. All figures are rounded to reflect appropriate levels of confidence. Apparent difference may occur due to rounding. 5. Revenue factor inputs (US$): Ni $11,766/t, Cu $5,173/t. Exchange rate A$1.00 : US$0.74.

  5. JORC Code (2012) Table 1 Parameters are contained within Appendix C of this release.

Jaguar Operation

The Jaguar Operation is located 300km north of Kalgoorlie and 60km north of Leonora. Ore is currently sourced from the Bentley underground mine and processed through the Jaguar concentrator to produce a high grade zinc and copper concentrates with silver and gold credits.

A total of 498kt of ore at 8.9% Zn, 1.8% Cu, 131g/t Ag and 0.77g/t Au was mined from predominantly the Arnage and Comet lenses at Bentley during FY16. Metal production was 39kt Zn, 7.4kt Cu, 1.6Moz Ag, and 4.9koz Au.

Geology

The Jaguar Operation is a cluster of Volcanic Massive Sulphides (VMS) deposits located within the Gindalbie Terrane, a part of the late Archaean Eastern Goldfields Superterrane of the Yilgarn Craton of Western Australia. The area is dominated by volcanic and lesser sedimentary and intrusive rocks that have undergone tilting to sub-vertical positions. Regional metamorphism is lower greenschist facies.

The three principal deposits forming the known VMS cluster are Bentley, Jaguar and Teutonic Bore. The deposits have formed by sub-seafloor replacement, principally of shales and volcanoclastic sediments with mineralisation located in a similar stratigraphic position near a transition from calc-alkaline to tholeiitic volcanism.

The Bentley mineralisation occurs at the contact of a thick basal rhyolitic sequence with an overlying andesite. The rhyolitic sequence is overlain by a sediment unit comprising carbonaceous mudstones and siltstones.

PAGE 10

==> picture [596 x 83] intentionally omitted <==

The Bentley massive sulphide mineralisation is banded and consists of pyrite, sphalerite, chalcopyrite, galena and minor pyrrhotite. The upper contact of the massive sulphide is typically sharp. The footwall to massive sulphide consists typically of stringer and disseminated sulphide mineralisation comprising pyrite, chalcopyrite and minor sphalerite.

A dolerite sill at low angle to the Bentley massive sulphide mineralisation and steeper in dip intrudes the orebody, cutting it into five main segments (Arnage, Mulsanne, Brooklands, Comet and Flying Spur lenses).

Mineral Resource

The Mineral Resource estimate for the Jaguar Project as at 30 June 2016 is 3.7Mt at 7.0% Zn, 1.4% Cu, 111g/t Ag and 0.6g/t Au which is inclusive of both the Teutonic Bore remnant massive sulphide and stringer mineralisation (1.6Mt @ 2.5% Zn, 1.6% Cu, and 49 g/t Ag) and the Bentley Mineral Resource (2.1Mt @ 10.3% Zn, 1.2% Cu, 157g/t Ag and 1.0g/t Au).

Work programs at the Bentley mine completed during FY16 aimed at defining potential life of mine extensions. This entailed an extensive underground drilling program at Bentley from the hanging wall drill drive established in FY15. The drilling program was designed for the conversion of Inferred Mineral Resource to Indicated Mineral Resource category and to drill test mineralisation extensions at depth. As a result, the conversion of Arnage and Flying Spur lenses from Inferred Mineral Resources to Indicated Mineral Resource category extended from 3820mRL in FY15 to 3625mRL in FY16. In addition, the Arnage lens is extended 270m down dip from the FY15 resource boundary. This confirms the Arnage mineralisation is continuous to Bentley Deeps mineralisation identified from FY15 drilling to a depth of 1,000m below surface.

Ore Reserve

Jaguar Operation Ore Reserve as at 30 June 2016 was 1.4Mt at 9.5% Zn, 1.1% Cu, 145g/t Ag and 0.8g/t Au compared to the 30 June 2015 Ore Reserve of 1.2Mt at 7.6% Zn, 1.7% Cu, 126g/t Ag and 0.7g/t Au.

The resource to reserve drilling programme executed during FY16 has resulted in a 155%, 143% and 142% increase in zinc, silver and gold metals. Copper metal has reduced by 20% inclusive of FY16 mining depletions. This has resulted in the extension of mine life to 3.5 years from June 30 2016.

Exploration and Resource Definition

Planned exploration and resource definition drill programs at the Jaguar Operation during FY17 will focus on:

  • Down-dip extensions of the Arnage and Flying Spur lens at Bentley including testing several off hole geophysical electromagnetic conductors.

  • Improved definition of the Triumph mineralised system, located 5 km north of the Jaguar processing facility will be completed based on conceptual studies supporting the economic viability of the highgrade core (Stag lens) as incremental ore feed to the Jaguar Operation. Drilling to-date has intersected zinc-copper-silver-gold mineralisation from a vertical depth of 200m extending over a strike length of approximately 400m, with a steep-dip and a shallow southerly-plunge. Mineralisation is in a broad, low to moderate grade envelope around a linear high-grade core of variable thickness (2m to 30m) and dip extent (40m to 100m). Triumph mineralisation has not been included in the Mineral Resource statement as at 30 June 2016.

  • Continuation of systematic exploration on a number of prospects in the extensive land package containing over 50km long prospective corridor on a 350km[2] land package. Work programs will focus on Lagonda, Daimler, Bentley North, and Bentley South for potential VMS systems similar in style to the Bentley and Jaguar deposits. Exploration will also be completed on a number of early stage gold prospects including Charlie Chicks, Garden Well #1, Halloween and JunHill.

PAGE 11

==> picture [596 x 83] intentionally omitted <==

Table 9: Jaguar Operation – 30 June 2016 Mineral Resources (and 2015 comparison)

Mineral Resources ‐ 30 June 2015 Resources ‐ 30 June 2015 Resources ‐ 30 June 2015 Mineral Resources ‐ Mineral Resources ‐ Mineral Resources ‐ 30 June 2016 30 June 2016
Tonnes Grade Tonnes Grade
Cu Zn Ag Au Cu Zn Ag Au
Classification (t) (%) (%)
(g/t)
(g/t) (t) (%) (%) (g/t) (g/t)
Bentley Measured 529,000 2.1 11.5 159 0.8 402,000 1.8 11.5 177 0.9
Indicated 1,252,000 1.6 7.3 118 0.8 1,418,000 1.0 11.0 161 1.0
Inferred 1,113,000 1.0 8.8 149 1.1 282,000 0.7 5.3 107 1.0
Stockpiles 13,000 1.1 9.2 121 0.6 5,000 2.0 8.9 131 0.8
Sub‐Total 2,907,000 1.5 8.6 138 0.9 2,107,000 1.2 10.3 157 1.0
Mineral Resources – 30 August 2009 Mineral Resources – 30 August 2009
Teutonic Bore Measured
Indicated 946,000 1.7 3.6 65 946,000 1.7 3.6 65
Inferred 608,000 1.4 0.7 25 608,000 1.4 0.7 25
Sub‐Total 1,554,000 1.6 2.5 49 1,554,000 1.6 2.5 49
GRAND TOTAL 4,461,000 1.5 6.5 107 3,661,000 1.4 7.0 111 0.6

Notes:

  1. FY15 Mineral Resources include massive sulphide and stringer sulphide mineralisation. Massive sulphide resources are geologically defined; stringer sulphide resources for FY15 are reported above a cut-off grade of 0.7% copper. No economic mining constraints were applied to the FY15 Mineral Resource.

  2. FY16 massive sulphide Mineral Resource is reported above a cut-off of $96/t NSR. Stringer sulphide (incremental resources) reported above a cut-off of $60/t NSR. Economic mining constraints have been applied to the FY16 Mineral Resource. The change in methodology has resulted in a reduction in the reported tonnages and the associated contained metal between FY15 and FY16. On a like for like basis the FY16 Mineral Resource would have delivered an additional 15% zinc, 31% copper, 14% silver, and 28% gold contained metal.

  3. Block modelling mainly used ordinary-kriging grade-interpolation methods within wireframes for all elements and density.

  4. All Mineral Resources are depleted for mining

  5. All figures are rounded to reflect appropriate levels of confidence. Apparent differences may occur due to rounding. 6. Mineral Resources are inclusive of Ore Reserves.

  6. The Teutonic Bore Resource estimate is reported in accordance with JORC Code 2012 reporting guidelines. The model is unchanged from the 2009 model.

  7. JORC Code (2012) Table 1 Parameters are contained within Appendix D of this release.

Table 10: Jaguar Operation – 30 June 2016 Ore Reserves (and 2015 comparison)

Ore Reserves ‐ 30 June Reserves ‐ 30 June 2015 Ore Reserves ‐ 30 June 2016 Ore Reserves ‐ 30 June 2016 Ore Reserves ‐ 30 June 2016
Tonnes Grade Tonnes Grade
Cu Zn Ag Au Cu Zn
Ag
Au
Classification (t) (%) (%) (g/t) (g/t) (t) (%) (%) (g/t) (g/t)
Bentley Proved 323,000 2.0 10.8 155 0.8 277,000 1.8 9.7 157 0.8
Probable 821,000 1.6 6.3 115 0.7 1,157,000 1.0 9.5 142 0.7
Sub‐Total 1,144,000 1.7 7.6 126 0.7 1,434,000 1.1 9.5 145 0.8
Stockpiles Proved 13,000 1.1 9.2 121 0.6 4,000 1.7 9.3 138 0.7
GRAND TOTAL 1,157,000 1.7 7.6 126 0.7 1,438,000 1.1 9.5 145 0.8

Notes:

  1. Cut-off values were based on NSR values of $134/t ore or direct mill feed and $80/t ore for marginal feed.

  2. Revenue factor inputs (US$): copper price $5,540/t, zinc price $2,020/t, silver price $17.00/oz, gold price $1,200/oz and foreign exchange rate of A$1.00 : US$0.75.

PAGE 12

==> picture [596 x 83] intentionally omitted <==

  1. The following metallurgical recovery factors have been used: 85.0% copper recovery into copper concentrate, 45.0% silver recovery into copper concentrate, 32.0% gold recovery into copper concentrate, 86.0% zinc recovery into zinc concentrate and 16.0% silver recovery into the zinc concentrate.

  2. Longitudinal sub-level long hole stoping with unconsolidated rock fill is the primary method of mining.

  3. All Measured Resources and associated dilution was classified as Proved Reserves. All Indicated Resources and associated dilution was classified as Probable Reserves. No Inferred Resources has been converted into Reserves.

  4. All figures are rounded to reflect appropriate levels of confidence. Apparent differences may occur due to rounding.

  5. JORC Code (2012) Table 1 Parameters are contained within Appendix D of this release.

Stockman Project

The Stockman Project is located in the East Gippsland region of eastern Victoria, 460km by road from Melbourne and approximately 19km east-south-east of Benambra. The Stockman Project was acquired as part of IGO’s acquisition of Jabiru Metals Ltd in 2011.

The Stockman Project encompasses two copper-zinc-lead-silver-gold VMS deposits, Wilga and Currawong, and various exploration prospects and targets. The larger Currawong deposit is intact, whilst a core of copper-rich ore from the Wilga deposit was mined and processed onsite between 1992 and 1996.

Feasibility level studies have been completed on the Stockman Project with design studies based on a 1.0Mtpa differential flotation concentrator to produce approximately 150ktpa of copper and zinc concentrates over a Project life of approximately ten years.

The Environment Effects Statement (EES) for the Stockman Project, the overarching permitting instrument for the project under the Victorian Environmental Effects Act 1978, received a positive assessment from the Victorian Government, and Project approval from the Federal Government, subject to conditions, in November 2014. This allowed the Stockman Project to proceed to the licensing phase, which is currently being advanced.

As the project approval process progresses, IGO continues to evaluate the Project’s economics and strategic fit. A final investment decision will likely only occur once approvals are finalised.

Geology

The Wilga and Currawong deposits are hosted within a Silurian age sedimentary basin that forms part of the Lachlan Fold Belt. Both deposits are hosted by fine-grained sediments and intermediate to felsic volcanics of the Gibson’s Folly Formation. Mineralisation occurs as stratiform massive sulphide lenses. Both deposits are approximately 350m in strike and dip extent, dip shallowly to the north and are located some 100m below the surface. The Currawong deposit comprises five massive-sulphide lenses and associated stringer-style mineralisation, stacked by a series of post-mineralisation faults. Located approximately 4km to the south, the Wilga deposit comprises a single massive sulphide lens with an extensive zone of stringer-style mineralisation situated down-dip and along-strike to the west of the massive sulphide mineralisation. The sulphide mineralogy in both deposits is predominantly pyrite, sphalerite, chalcopyrite and minor galena.

Mineral Resource

The Mineral Resource estimate is unchanged since 2012, consisting of 14.0Mt at 2.1% Cu, 4.3% Zn, 38g/t Ag and 1.0g/t Au.

Ore Reserve

The Ore Reserve for the Stockman Project remains unchanged from 30 June 2015 at 9.0Mt at 2.1% Cu, 4.5% Zn, 39g/t Ag and 1.1g/t Au.

Exploration

There remains significant exploration potential on the Stockman Project for repetition of the VMS styles of mineralisation as observed at Wilga and Currawong. Limited exploration programs are planned for FY17 on a number of the prospects.

PAGE 13

==> picture [596 x 83] intentionally omitted <==

Table 11: Stockman Project – 30 June 2016 Mineral Resources (and 2015 comparison)

Mineral Resources ‐ 30 Resources ‐ 30 June 2015 Mineral Resources ‐ 30 June 2016 Mineral Resources ‐ 30 June 2016 Mineral Resources ‐ 30 June 2016 Mineral Resources ‐ 30 June 2016
Tonnes Grade Tonnes Grade
Cu Zn Ag Au Cu Zn Ag Au
Classification (Mt) (%) (%) (g/t) (g/t) (Mt) (%) (%) (g/t) (g/t)
Currawong Measured
Indicated 9.5 2.0 4.2 42 1.2 9.5 2.0 4.2 42 1.2
Inferred 0.8 1.4 2.2 23 0.5 0.8 1.4 2.2 23 0.5
Sub‐Total 10.3 2.0 4.0 40 1.1 10.3 2.0 4.0 40 1.1
Wilga Measured
Indicated 3.0 2.0 4.8 31 0.54 3.0 2.0 4.8 31 0.54
Inferred 0.7 3.7 5.5 34 0.4 0.7 3.7 5.5 34 0.4
Sub‐Total 3.7 2.3 4.9 32 0.54 3.7 2.3 4.9 32 0.54
GRAND TOTAL 14.0 2.1 4.3 38 1.04 14.0 2.1 4.3 38 1.04

Notes:

  1. All figures are rounded to reflect appropriate levels of confidence. Apparent differences may occur due to rounding.

  2. The Mineral Resource estimate is unchanged since 2012.

  3. Mineral Resources include massive sulphide and stringer sulphide mineralisation. Massive sulphide resources are geologically defined; stringer sulphide resources are reported above cut-off grades of 0.5% Cu.

  4. Au grades for Wilga are all Inferred due to paucity of Au data in historic drilling.

  5. Block modelling used ordinary-kriging grade-interpolation methods within wireframes for all elements and density.

  6. Mining as at end of historic mine life (1996) has been removed from the Mineral Resource estimate for Wilga.

  7. Mineral Resources are inclusive of Ore Reserves.

  8. JORC Code (2012) Table 1 Parameters are contained within Appendix E of this release.

Table 12: Stockman Project – 30 June 2016 Ore Reserves (and 2015 comparison)

Ore Reserves ‐ 30 June 2015 Ore Reserves ‐ 30 Ore Reserves ‐ 30 June 2016
Tonnes Grade Tonnes Grade
Cu Zn
Ag
Au Cu Zn Ag Au
Classification (Mt) (%) (%) (g/t) (g/t) (Mt) (%) (%) (g/t) (g/t)
Currawong Proved
Probable 7.4 2.1 4.3 40 1.2 7.4 2.1 4.3 40 1.2
Sub‐Total 7.4 2.1 4.3 40 1.2 7.4 2.1 4.3 40 1.2
Wilga Proved
Probable 1.6 2.1 5.6 31 0.52 1.6 2.1 5.6 31 0.52
Sub‐Total 1.6 2.1 5.6 0.52 1.6 2.1 5.6 0.52
GRAND TOTAL 9.0 2.1 4.5 39 1.12 9.0 2.1 4.5 39 1.12

Notes

  1. All figures are rounded to reflect appropriate levels of confidence. Apparent differences may occur due to rounding. 2. Gold (Au) grades are Inferred at Wilga due to a paucity of gold assays in historic drilling. Revenue from gold in the Wilga ore was included in the estimation of the Ore Reserve. The contribution to revenue of this gold was estimated to be $8.65/g of gold in situ. This inclusion was not material to the value of the mining envelopes considered and did not warrant downgrading of any portion of the Ore Reserve attributable to Wilga. The contribution from Wilga represents 18% of the Total Ore Reserve.

  2. The Ore Reserve was estimated using the NSR method. The NSR value represents unit revenue per tonne net of all off-site costs. These off-site costs included road transport, sea transport, treatment charges, refining costs and state royalties. The NSR value did not include site costs such as mining, geology, processing and site administration. These site costs were applied in the form of an NSR cut-off, used to guide the limits of a practical and economic mining envelope. The Currawong NSR cut-off was $97/t and for Wilga it was $105/t.

PAGE 14

==> picture [596 x 83] intentionally omitted <==

  1. Revenue factor inputs (US$): Cu $6,591/t, Zn $2,979/t, Ag $20.17/oz, Au $1,146/oz. Exchange rate A$1.00 : US$0.84.

  2. Metallurgical recoveries – 81.5% Cu, 40.7% Ag, and 20.4% Au in Cu concentrate; 76.4% Zn and 18.5% Ag in Zn concentrate.

  3. Long hole open stoping with cemented paste backfill is the primary method of mining proposed at Stockman.

  4. Historic mining at Wilga has been removed from the Ore Reserve estimate.

  5. The Ore Reserve estimate includes Inferred and unclassified material in the form of mining dilution estimated to be approximately 780,000t at 0.31 Cu%, 1.0 Zn%, 5.2g/t Ag and 0.1g/t Au.

  6. JORC Code (2012) Table 1 Parameters are contained within Appendix E of this release.

JORC Code (2012) Competent Persons Statement

Nova Project Resources and Reserves

The information that relates to the Nova Project Mineral Resources is based on, and fairly represents information and supporting documentation compiled by Mr Mark Drabble and Mr David Hammond. Mr Hammond is an employee of IGO and Mr Drabble is Principal Consultant-Geology of consultancy group Optiro Pty Ltd. Both are members of The Australasian Institute of Mining and Metallurgy and both have sufficient experience relevant to the type and style of mineral deposit under consideration, and to the activity which has been undertaken, to qualify as Competent Persons as defined in the 2012 edition of the ‘Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves’ (the JORC Code). Mr Drabble and Mr Hammond consent to the inclusion in this report of the Nova Bollinger Mineral Resource estimate, based on their information in the form and context in which it appears.

The information that relates to the Nova Project Ore Reserves is based on, and fairly represents information and supporting documentation compiled by Mr Brett Hartmann who is a Member of The Australasian Institute of Mining and Metallurgy. Mr Hartmann is a full-time employee of IGO. Mr Hartmann has sufficient experience which is relevant to the style of mineralisation and type of deposit under consideration, and to the activity which has been undertaken, to qualify as a Competent Person as defined in the 2012 edition of the JORC Code. Mr Hartmann consented to the inclusion in this report of the Nova Bollinger Ore Reserve estimate, based on his information, in the form and context in which it appears.

Tropicana Gold Mine Resources and Reserves

The information that relates to the Tropicana Mineral Resources is based on, and fairly represents information and supporting documentation compiled by Mr Mark Kent, a full-time employee and security holder of AngloGold Ashanti Australia Limited, who is a member of The Australasian Institute of Mining and Metallurgy. Mr Kent has sufficient experience relevant to the type and style of mineral deposits under consideration, and to the activity which has been undertaken, to qualify as a Competent Person as defined in the 2012 edition of the JORC Code. Mr Kent consented to the inclusion in this report of the Tropicana Mineral Resource estimate, based on the information in the form and context in which it appears.

The information that relates to the Tropicana Ore Reserves is based on, and fairly represents information and supporting documentation compiled by Mr Jason Vos, a full-time employee and security holder of AngloGold Ashanti Australia Limited, who is a member of The Australasian Institute of Mining and Metallurgy. Mr Vos has sufficient experience relevant to the type and style of mineral deposit under consideration, and to the activity which has been undertaken, to qualify as a Competent Person as defined in the 2012 edition of the JORC Code. Mr Vos consented to the inclusion in this report of the Tropicana Ore Reserve estimate, based on the information, in the form and context in which it appears.

Long Operation Resources and Reserves

The information in this report that relates to the Long Operation’s Mineral Resources is based on, and fairly represents information and supporting documentation compiled by Ms Somealy Sheppard. The information in this report that relates to the Long Operation’s Ore Reserves is based on information compiled by Mr Brett Hartmann. Ms Sheppard is a fulltime employee of IGO and is a member of the Australian Institute of Geoscientists. Mr Hartmann is a full-time employee of IGO and is a member of The Australasian Institute of Mining and Metallurgy. Ms Sheppard and Mr Hartmann have sufficient experience which is relevant to the style of mineralisation and type of deposit under consideration and to the activity which they are undertaking to qualify as Competent Persons as defined in the 2012 edition of the JORC Code. Ms Sheppard and Mr Hartmann consent to the inclusion in the report of the matters based on their information in the form and context in which it appears.

Jaguar Operation Bentley / Teutonic Bore Resources and Reserves

The information in this report that relates to the Bentley Mineral Resources is based on, and fairly represents information and supporting documentation compiled by Mr William Stewart. The information in this report that relates to the Teutonic

PAGE 15

==> picture [596 x 83] intentionally omitted <==

Bore Mineral Resources is based on information compiled by Mr Stewart. Mr Stewart is a full-time employee of IGO and member of The Australasian Institute of Mining and Metallurgy and member of Australian Institute of Geoscientists.

The information in this report that relates to the Bentley Ore Reserves is based on information compiled by Mr Shane McLeay who is a Fellow of The Australasian Institute of Mining and Metallurgy. Mr McLeay is a full-time employee of Entech Pty Ltd. Mr Stewart and Mr McLeay have sufficient experience relevant to the style of mineralisation and type of deposit under consideration and to the activity which they have undertaken to qualify as Competent Persons as defined in the 2012 edition of the JORC Code. Mr Stewart and Mr McLeay consent to the inclusion in the report of the matters based on their information in the form and context in which it appears.

Stockman Project Currawong and Wilga Resources and Reserves

The information in this report that relates to the Stockman Mineral Resources is based on, and fairly represents information and supporting documentation compiled by Mr Matthew Dusci. Mr Dusci is a full-time employee of IGO and is a member of the Australian Institute of Geoscientists. Mr Dusci has sufficient experience which is relevant to the style of mineralisation and type of deposit under consideration, and the activity which he is undertaking, to qualify as a Competent Person as defined in the 2012 edition of the JORC Code. Mr Dusci consents to the inclusion in the report of the matters based on his information in the form and context in which it appears.

The information in this report that relates to the Stockman Ore Reserves is based on, and fairly represents information and supporting documentation compiled by Mr Geoff Davidson who is a Fellow of The Australasian Institute of Mining and Metallurgy. Mr Davidson is a consultant working for Mining and Cost Engineering Pty Ltd. Mr Davidson has sufficient experience which is relevant to the style of mineralisation and type of deposit under consideration, and the activity which he is undertaking, to qualify as a Competent Person as defined in the 2012 edition of the JORC Code. Mr Davidson consents to the inclusion in the report of the matters based on his information in the form and context in which it appears.

Annual Report Mineral Resource and Ore Reserve Statement

The information in this report that relates to the Independence Group Annual Report Mineral Resources and Ore Reserves Statement as a whole is based on information compiled by Mr. Dusci who is a member of Australian Institute of Geoscientists and is a full-time employee of IGO. The Annual Report Mineral Resources and Ore Reserves Statement is based on, and fairly represents, information and supporting documentation prepared by the above-named Competent Persons. The Annual Report Mineral Resources and Ore Reserves Statement has been issued with the prior written consent of Mr. Dusci, in the form and context in which it appears in the Annual Report.

Mineral Resource and Ore Reserve Governance

In estimating Mineral Resources and Ore Reserves the Competent Person(s) for each estimate is (are) responsible for:

  • Adopting annual Board approved metal prices and foreign exchange assumptions for use in estimates

  • Monitoring the planning, progress, estimation and reporting of Mineral Resources and Ore Reserves to meet IGO standards and timelines

  • JORC Code compliant reporting

  • Periodic internal review of process, data, estimates and reports

  • Periodic external review of data, Estimates and reports for new or materially changed estimates.

Independence Group NL reports its Mineral Resources and Ore Reserves on an annual basis, in accordance with the ‘Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves’ (the JORC Code) 2012 Edition. Mineral Resources are quoted inclusive of Ore Reserves.

Competent Persons named by Independence Group NL are Members or Fellows of the AusIMM and/or the Australian Institute of Geoscientists, and qualify as Competent Persons as defined in the JORC Code.

For further information contact:

Peter Bradford Joanne McDonald Managing Director Company Secretary Independence Group NL Independence Group NL Telephone: 08 9238 8300 Telephone: 08 9238 8300

PAGE 16

==> picture [596 x 83] intentionally omitted <==

APPENDIX A

Nova Bollinger Mineral Resource and Ore Reserve 2016

JORC Code, 2012 Edition – Table 1

Section 1 Sampling Techniques and Data

Criteria Commentary
Sampling techniques
Note: Due to the similarity
of the deposit setting,
procedures and estimation
these tables present the
combined Nova-Bollinger
tabulation. All references to
the Bollinger deposit are in
bold font, and Nova is in
normal font.
The Bollinger deposit was sampled using diamond drill holes (DD) on a nominal 25m x 25m
to 50m x 50m grid spacing. A total of 72 DD holes were drilled for 35,935m. Holes were
generally angled towards grid west between -60
0 and -90
0 to optimally intersect the
mineralised zones.
The Nova deposit was sampled using Reverse Circulation (RC) and diamond drill holes (DD) on
nominal 25m x 25m grid spacing. A total of 15 RC and 163 DD holes were drilled for 2,910m and
63,099m respectively. Holes were generally angled towards grid west at varying angles to
optimallyintersect the mineralised zones.
Bollinger is defined by diamond drilling only, and uses the same measures employed at
Nova for controls and sample representivity.
The drill hole locations were picked up and downhole surveyed by survey contractors. Initial RC
drilling identified the Nova target and diamond core was used to delineate the resource. The RC
samples were collected by cone or riffle splitter. Diamond core was used to obtain high quality
samples that were logged for lithological, structural, geotechnical, density and other attributes.
Sampling was carried out under Sirius protocols and QAQC procedures as per industry best
practice.
Diamond core is HQ and NQ2 size, sampled on geological intervals (0.2m to 1.2m), cut into
half (NQ2) or quarter (HQ) core to give sample weights under 3kg. Samples were crushed,
dried and pulverised (total prep) to produce a sub-sample for analysis by four acid digest
with an ICP/OES or ICP/MS finish and fire assay (Au, Pt, Pd) with MS finish.
Diamond core is HQ (metallurgical holes) or NQ2 size, sampled on geological intervals (0.2m to
1.3m), cut into half (NQ2) or quarter (HQ met) core to give sample weights under 3kg. Samples
were crushed, dried and pulverised (total prep) to produce a sub-sample for analysis by four acid
digest with an ICP/OES or ICP/MS finish and fire assay (Au, Pt, Pd) with MS finish. Reverse
circulation drilling was used to obtain 1m samples from which 3kg was pulverised (total prep) to
produce a sub-sample for assayingas above.
Drilling techniques Diamond drilling accounts for 100% of the current drilling at Bollinger and comprises NQ2
or HQ sized core. Pre-collar depths range from 20m to 84m and hole depths range from
450m to 667m. The core was oriented using a Camtech orientation tool.
Diamond drilling accounts for 96% of the drilling in the resource area and comprises NQ2 or HQ
sized core. Pre-collar depths range from 6m to 150m and hole depths range from 144m to 667m.
The core was oriented using a Camtech orientation tool with 71% of orientations rated as “good”.
RC drilling accounts for 4% of the total drilling and comprises 140mm diameter face sampling
hammer drilling. Hole depths range from 90m to 280m.
Drill sample recovery Diamond core and RC recoveries are logged and recorded in the drill hole database. Overall
recoveries are >95% for Nova andBollingerand there are no core loss issues or significant
sample recovery problems.
Diamond core at Nova andBollingeris reconstructed into continuous runs on an angle iron cradle
for orientation marking. Depths are checked against the depth given on the core blocks and rod
counts are routinely carried out by the drillers. RC samples were visually checked for recovery,
moisture and contamination.
The Bollinger mineralisation is defined by diamond core drilling, which has high recoveries.
The bulk of the Nova resource is defined by diamond core drilling, which has high recoveries. The
massive sulphide style of mineralisation and the consistency of the mineralised intervals are
considered topreclude anyissue of sample bias due to material loss orgain.
Logging Geotechnical logging at Nova andBollingerwas carried out on all diamond drillholes for recovery,
RQD and number of defects (per interval). Information on structure type, dip, dip direction, alpha
angle, beta angle, texture, shape, roughness and fill material is stored in the structure table of the
database.
Logging of diamond core and RC samples at Nova andBollingerrecorded lithology, mineralogy,
mineralisation, structural (DD only), weathering, colour and other features of the samples. Core
wasphotographed in both dryand wet form.

PAGE 17

==> picture [596 x 83] intentionally omitted <==

Criteria Commentary
All drillholes were logged in full, apart from rock roller diamond hole pre-collar intervals of between
20m to 60m depth(Bollinger)and 20m to 60m(Nova).
Sub-sampling
techniques
and sample preparation
Core for Nova andBollingerwere cut in half (NQ2) and quarter core (HQ) onsite using an
automatic core saw. All samples were collected from the same side of the core.
RC samples were collected on the rig using cone splitters. All samples in mineralised zones were
dry.
The sample preparation of diamond core for Nova andBollingerfollows industry best practice in
sample preparation involving oven drying, coarse crushing of the half core sample down to ~10mm
followed by pulverisation of the entire sample (total prep) using Essa LM5 grinding mills to a grind
size of 85% passing 75µm.
The samplepreparation for RC samples is identical,without the coarse crush stage.
Field QC procedures involve the use of certified reference material as assay standards, along with
blanks, duplicates and barren washes. The insertion rate averaged 1:15for both projects, with an
increased rate in mineralised zones.
No field duplicates were taken for Bollinger. Samples were selected to weigh less than 3kg
to ensure total preparation at the pulverisation stage.
Field duplicates were taken on 1m composites for RC, using a riffle splitter. One twinned diamond
hole was drilled at Nova. This hole supported the location of the geological intervals intersected in
the first drillhole(no assays were taken as this is a metallurgical hole).
The sample sizes are considered appropriate to correctly represent the sulphide
mineralisation at Bollinger based on: the style of mineralisation (massive sulphides), the
thickness and consistency of the intersections, the sampling methodology and percent
value assay ranges for the primary elements.
The sample sizes are considered appropriate to correctly represent the sulphide mineralisation at
Nova based on: the style of mineralisation (massive sulphides), the thickness and consistency of
the intersections, the sampling methodology and percent value assay ranges for the primary
elements.
Quality of assay data and
laboratory tests
The analytical techniques used a four acid digest multi element suite with ICP/OES or
ICP/MS finish (25 gram FA/MS for precious metals).
The analytical techniques used a four acid digest multi element suite with ICP/OES or ICP/MS
finish (25 gram or 50 gram FA/MS for precious metals). The acids used are hydrofluoric, nitric,
perchloric and hydrochloric acids, suitable for silica based samples. The method approaches total
dissolution of most minerals. Total sulphur is assayed bycombustion furnace.
No geophysical tools were used to determine any element concentrations used in either resource
estimate.
Sample preparation checks for fineness were carried out by the laboratory as part of their internal
procedures to ensure the grind size of 85% passing 75µm was being attained. One diamond hole
had duplicates taken from the half core after coarse crushing and the results were within 3% of the
original sample values. Laboratory QAQC involves the use of internal lab standards using certified
reference material, blanks, splits and replicates as part of the in-house procedures. Umpire
laboratory campaigns with two other laboratories have been carried out as independent checks of
the assay results using201 pulp samples and standards sent to ALS,(Nova 2,590 samples) and
these show good precision.
Certified reference materials, having a range of values, were inserted blindly and randomly.
Results highlight that sample assay values are accurate and that contamination has been
contained. The diamond drilled core pulp duplicates had more than 90% of its pairs with
differences (half absolute relative differences or HARD values) below 10% (Ni, Cu, Co), which
concurs with industry best practice results. Repeat or duplicate analysis for samples reveals that
precision of samples is within acceptable limits.
Verification of sampling and
assaying
Both the Managing and the Technical Director of Sirius have visually verified significant
intersections in diamond core from Bollinger in 2013. Optiro has viewed the intersections of
metallurgical core and checked core photos against the assay and geology logs.
Optiro has visually verified significant intersections in diamond core as part of the resource
estimationprocess.
No twin holes were drilled at Bollinger to date.
Two PQ and one HQ metallurgical holes have been drilled at Nova since March 2013 and the
logging supports the interpreted geological and mineralisation domains.
One hole at Nova was twinned (SFRD0117 and SFRD0117W1M). The results confirmed the initial
intersectiongeology. The twin(suffixed W1M)was used as a metallurgical hole.
Primary data were collected forboth projectsusing a set of standard Excel templates on
Toughbook laptop computers using lookup codes. The information was sent to ioGlobal for
validation and compilation into a SQL database server.
No adjustments or calibrations were made to anyassaydata used ineitherestimate.

PAGE 18

==> picture [596 x 83] intentionally omitted <==

Criteria Commentary
Location of data points Hole collar locations forall holeswere surveyed by Whelans Surveyors of Kalgoorlie using RTK
GPS connected to the state survey mark (SSM) network. Elevation values were in AHD RL and a
value of +2,000m was added to the AHD RL for local co-ordinate use. Expected accuracy is +/–
30mm for easting, northing and elevation coordinates.
Downhole surveys used single shot readings during drilling (at 18m, then every 30m) and Gyro
Australia carried out gyroscopic surveys using a Keeper high speed gyroscopic survey tool with
readings every 5m, after completion of the drill hole. Stated accuracy is +/-0.25
oin azimuth and +/-
0.05
oin inclination. QC involved field calibration using a test stand. Only gyro data are used in the
resource estimate.
The grid system forNova-Bollingeris MGA_GDA94, zone 51 (local RL has 2,000m added to
value). Local eastingand northingare in MGA.
Topographic surface forNova-Bollingeruses 2012 Lidar 50cm contours.
Data spacing and
distribution
The nominal drill hole spacing is 25m (northing) by 25m (easting) in the core of the deposit,
and is up to 50m by 50m on the margins.
The nominal drill hole spacingis 25m(northing)by25m(easting)for Nova.
The mineralised domains forNova-Bollingerhave demonstrated sufficient continuity in both
geological and grade continuity to support the definition of Mineral Resources and Reserves, and
the classifications applied under the 2012 JORC Code.
Samples have been composited to one metre lengths forboth projects, and adjusted where
necessaryto ensure that no residual sample lengths have been excluded(best fit).
Orientation of data in
relation to geological
structure
The deposit is drilled towards grid west at angles varying from -60
~~0~~and -90
~~0~~to intersect the
mineralised zones at a close to perpendicular relationship for the bulk of the deposit.
The deposit is drilled to grid west, which is slightly oblique to the orientation of the mineralised
trend; however the intersection angles for the bulk of the drilling are nearly perpendicular to the
mineralised domains. Structural logging based on oriented core indicates that main sulphide
controls are largely perpendicular to drill direction.
No orientation based samplingbias has been identified atNova-Bollingerin the data.
Sample security Chain of custody was managed by the company. Samples forNova-Bollingerwere stored on site
and were either delivered by company staff to Perth and then to the assay laboratory, or collected
from site by Centurion transport and delivered to Perth, then to the assay laboratory. Whilst in
storage, samples were stored in a locked yard. “Tracking sheets” track the progress of batches of
samples.
Audits or reviews A review of the sampling techniques and data was carried out by Optiro as part of each resource
estimate and the database is considered to be of sufficient quality to carry out resource estimation.
An internal system audit was undertaken bySirius in November 2012.

Section 2 Reporting of Exploration Results

Criteria Commentary
Mineral tenement and land
tenure status
Nova and Bollingerare located wholly within M28/376. IGO has a 100% interest in the ML
following acquisition of Sirius effective 22 September 2015. The tenement is located within the
Ngadju Native Title Determination Area.
The tenement is in good standing and no known impediments exist.
Exploration done by other
parties
No previous systematic exploration has been undertaken at the Nova-BollingerProject prior to the
work by Sirius.
Geology The global geological setting is a Proterozoic aged gabbroic intrusion(s) within metasediments
situated in the Albany Fraser mobile belt. It is a high grade metamorphic terrane. The sulphide
mineralisation is related to, and is part of the intrusive event. The deposits are analogous to other
mafic-hosted nickel-copper deposits which occur worldwide.
Drill hole Information No new exploration data are announced within this report.
Data aggregation methods No new exploration data are announced within this report.
Relationship between
mineralisation widths and
intercept lengths
The Nova deposit is moderately east dipping in the west, flattening to shallow dipping in the east.
The fans of drillholes are inclined between -54
0and -90
0to the west to allow intersection angles
with the mineralised zones to approximate the true width.
The Bollinger deposit is dominantly flat lying and is drilled to grid west with drill holes
inclined between -60
0 and -90
0. The intersection angles for the drilling appear to be close to
perpendicular to the mineralised zones, therefore reported downhole intersections
approximate true width.
Diagrams No new exploration data are announced within this report.

PAGE 19

==> picture [596 x 83] intentionally omitted <==

Criteria Commentary
Balanced reporting No new exploration data are announced within this report.
Other substantive
exploration data
All samples are measured for their bulk density which in the Nova-Bollingerdeposit range from
2.90 g/cm
3to 4.66g/cm
3.
Multi element assaying is conducted routinely on all samples for a suite of potentially deleterious
elements including Arsenic, Sulphur, Zinc and Magnesium.
Geotechnical logging was carried out on all diamond drillholes for recovery, RQD and number of
defects (per interval). Information on structure type, dip, dip direction, alpha angle, beta angle,
texture, shape, roughness and fill material is stored in the structure table of the database.
Further work Underground mapping in decline development confirms geotechnical assumptions. Mapping of ore
development commenced in early 2016 in parallel with diamond grade control drilling conducted
from a service drives above the Nova andBollingerorebodies to a nominal 12.5m x 12.5m
spacing. This work will start in early 2016 and will be an ongoing process to allow the geological
model to be refined for final underground detailed design. The Mineral Resource will be updated
with this new data in late 2016.
Section 3 Estimation and Reporting of Mineral Resources
Criteria Commentary
Database integrity Data templates with lookup tables and fixed formatting are used for logging, spatial and sampling
data atNova-Bollinger. Data transfer is electronic via e-mail. Sample numbers are unique and
pre-numbered bags are used. These methods all minimise the potential for errors.
Data validation checks are run by database management consultancy “ioGlobal” using their
proprietary software (“ioHub”). ioGlobal have their own database model with a production and
quarantine database for each client. Data are validated from quarantine to upload using a set of
validation rules developed by Sirius and ioGlobal.Data for Nova-Bollinger are stored in a
single database.
Site visits Mark Drabble (Principal Consultant - Optiro), who is acting as Competent Person, viewed
the metallurgical drill core at AMMTEC on 28
th June 2013.
Optiro carried out a site visit to the Nova deposit on the 21
stof February 2013. Mark Drabble
inspected the deposit area, the core logging and sampling facility and density measurement area.
During this time, notes and photos were taken along with discussions were held with site personnel
regarding the available drill core and procedures. Diamond core was also viewed in the Sirius
offices in Perth on three occasions. A number of minor recommendations were made on
procedures but no major issues were encountered.
In addition, Mr Drabble viewed drill core in the Sirius offices in Balcatta on a number of occasions
in 2013.
Geological interpretation The confidence in the geological interpretation of Nova andBollingeris considered good. The
global geological setting is a gabbroic intrusion(s) within metasediments within a high grade
metamorphic terrane. The sulphide mineralisation is related to, and part of, the intrusive event.
The Bollinger deposit appears to be intimately related to the Nova deposit and represents
part of a number of intrusive events that transgress sedimentary layers to the immediate
east of Nova. TheNova-Bollingerdeposit appears similar in style to many mafic-hosted nickel-
copper deposits.
Petrography and litho-geochemistry have been used to assist identification of the rock type
subdivisions applied in the interpretation process.
TheNova-Bollingerdeposit is generally tabular in geometry, with clear boundaries which define
the mineralised domains. Infill drilling has supported and refined the model and the current
interpretation is thus considered to be robust.
Geological controls and relationships were used to define sub-domains. Key features are sulphide
content, form and multi-element geochemistry relationships.
The Bollinger disseminated zone has small intervals of massive sulphide that required sub-
domaining to constrain the estimation of metal around these samples.
The Nova lower breccia zone has mixed grade populations due to variable clast versus massive
sulphide content. This can be seen in the MgO and nickel grade relationships and influences the
local rather than the global grade estimate. These factors have been addressed via the resource
estimation process applied.
Dimensions The Bollinger Mineral Resource area abutsthe Nova areaand has dimensions of 300m

PAGE 20

==> picture [596 x 83] intentionally omitted <==

Criteria Commentary
(north) by 400m (east) and 125m (elevation). The Bollinger resource has a maximum depth
of 450m below surface. The Nova and Bollinger deposits are conjoined by a feeder zone.
The two resources areas are arbitrarily split along a North-South line defined by the
518,600mE MGA grid line.
The Nova Mineral Resource starts at a depth of 40m below surface. The Resource area has
dimensions of 450m (north) by 550m (east) and 400m (elevation).
Estimation and modelling
techniques
Grade estimation using Ordinary Kriging (OK) was completed for Nova andBollinger. CAE Studio
3 software was used to estimate six elements; Ni%, Cu%, Co%, Fe%, Mg (ppm) and S%, as well
as bulk density. Drill grid spacing ranges from 25m to 50m. Drillhole sample data were flagged
using domain codes generated from three dimensional mineralisation domains and oxidation
surfaces. Sample data were composited per element to a one metre downhole length using a best
fit-method. There were consequently no residuals. Intervals with no assays were excluded from
the compositing routine.
The influence of extreme sample distribution outliers was reduced by top-cutting where required.
The top-cut levels were determined using a combination of top-cut analysis tools (grade
histograms, log probability plots and CVs). Top-cuts were reviewed and applied on a domain
basis.
Due to the folded nature of the Lower Massive domain at Novaand the Massive domain at
Bollinger,an industry accepted unfolding routine was carried out using CAE Studio 3 software.
Variography and grade estimation of these domains were completed in unfolded space.
It was noted that the Lower Massive domain at Novaand the Massive and the Carapace domain
at Bollingershowed evidence of sub-populations within the domains which were not able to be
wireframed separately at the available grid spacing. A categorical indicator approach using three
grade bins at Novaand two grade bins within the Bollinger domains was considered
appropriate to sub-domain these populations.It was interpreted that these sub-domains
represented massive, breccia and/or low-grade mineralisation.
Several domains which demonstrated a moderate degree of folding at Bollinger were
estimated using flattening routines or Dynamic Anisotropy in order to optimise the grade
estimation. Variography of these domains was completed in 2D space.
For all domains, directional variograms were modelled using traditional variograms or normal
scores transformations. Nugget values are moderate to high (Nova <0.5, Bollinger <0.3).Grade
continuity was variable in either resource depending on mineralisation styles and ranged from 50m
to 170m in the major direction. Small or poorly sampled domains where robust variography could
not be generated used the variography of a geologically similar domain. Estimation searches for
all elements were set to the ranges of the nickel variogram for each domain.
No previous mining activity has taken place in this area. Check estimates have been complted
during the development drilling of the deposit and have produced very similar global estimates for
the Nova-Bollinger deposit.
The main by-product of the resource is cobalt and recovery will be as a by-product with the
pentlandite. This is dependent on any off-take agreement and may realise a credit.
The non-grade elements estimated are Fe%, Mg% and S%.
A single block model for Nova-Bollingerwas constructed using an 8mE by 12mN by 4mRL parent
block size with subcelling to 1mE by 1mN by 0.25mRL for domain volume resolution. All
estimation was completed at the parent cell scale. Kriging neighbourhood analysis was carried out
for Nova in order to optimise the block size, search distances and sample numbers used.
Discretisation was set to 4 by 6 by 2 for all domains.
The size of the search ellipse per domain was based on the nickel variography, due to the
moderate-strong correlation of nickel with the other elements. Three search passes were used for
each domain. In general, the first pass used the ranges of the nickel variogram and a minimum of
8 and maximum of 30 samples. In the second pass the search ranges were changed to double the
ranges of the nickel variogram, maintaining a minimum of 8 samples. The third pass ellipse was
extended to3 times the range of the variograms for Bollingerand 5 times for Nova. A
minimum of 4 and a maximum of 30 samples were applied. A maximum of 5 samples per hole
were used.
In the majority of domains, most blocks were estimated in the first pass (particularly for the main
domains); however, some more sparsely-sampled domains were predominantly estimated on the
second or third pass. Non-estimated blocks, i.e. those outside the range of the third pass, were
assigned the estimated domain mean and lower resource confidence classification.
Hard boundaries were applied between all estimation domains,excludingthe alteration envelope

PAGE 21

==> picture [596 x 83] intentionally omitted <==

Criteria Commentary
at Nova where a soft boundary with the disseminated domain was used.
No selective mining units were assumed in this estimate.
Neural networking (3D spatial analysis) was used to determine relationships between the variables
at Nova in the initial estimate. These were then incorporated into the domain interpretation
process. Strong positive correlation exists between nickel and all other elements estimated, with
the exception of copper. The correlation between nickel and copper is variable; based on domain
and mineralisation style. All elements within a domain used the same sample selection routine for
block grade estimation.
The geological interpretation correlated the sulphide mineralisation to geological and structural
elements at Nova-Bollinger. The structural framework and understanding of primary magmatic
and remobilised mineralisation was used to refine the mineralisation domains. These domains
were used as hard boundaries to select sample populations for variography and estimation.
Statistical analysis showed the populations in each domain at Nova andBollingerto generally
have a low coefficient of variation but it was noted that a very small number of estimation domains
included outlier values that required top-cut values to be applied.
Validation of the block model included a volumetric comparison of the resource wireframes to the
block model volumes. Validating the estimate compared block model grades to the input data
using tables of values, and swath plots showing northing, easting and elevation comparisons.
Visual validation of grade trends and metal distributions was carried out. Minor mining has taken
place but broken stocks remain unprocessed.
Moisture The tonnages are estimated on a dry basis.
Cut-off parameters A nominal grade cut-off of 0.4% Ni appears to be a natural grade boundary between disseminated
and trace sulphides for the Nova-Bollingermineralised system. This cut-off grade was used to
define the mineralised envelope within which the higher grade sub-domains were interpreted.
Mineral Resources are reported above a 0.6% NiEq Cut-off grade. NiEq% = ((Cu % x 0.95) x
($7,655/$16,408))+(Ni % x 0.89).
Mining factors or
assumptions
Mining of the Nova-Bollingerdeposit will be dominantly by underground mining methods involving
mechanised mining techniques. The geometry of the deposit will make it amenable to mining
methods currently employed in many underground operations in similar deposits around the world.
No assumptions on mining methodology have been made.
Metallurgical factors or
assumptions
Mineralogy shows the main sulphide minerals as chalcopyrite, pentlandite and pyrrhotite.
Chalcopyrite is largely liberated, however some fine pentlandite is associated with the pyrrhotite.
Gangue minerals include olivine/pyroxene, amphibole, feldspars, garnets, quartz which are un-
altered.
The Concentrator is designed for a nominal 1.5Mtpa capacity. Processing will comprise
conventional crushing, milling and classification circuits followed by dual flotation circuits to
produce separate nickel (+cobalt) and copper (+silver) concentrates.
Detailed testwork in 2013/2014 has developed a split concentrate flowsheet that has achieved
separation between copper and nickel for production of separate concentrates with acceptable
recoveries. The results to date show a robust processing flowsheet than can consistently achieve a
copper concentrate grading 27 – 31% Cu for 95% overall recovery and a nickel concentrate
grading 13 - 17% Ni for 89% overall recovery.
Environmental factors or
assumptions
No assumptions have been made.
Bulk density Bulk density has been estimated from density measurements carried out on7,950 (Bollinger)and
12,429 (Nova) full length core samples using the Archimedes method of dry weight versus weight
in water. The use of wax to seal the core was trialled but was shown to make less than 1%
difference. Density standards were used for QAQC using an aluminium billet, and pieces of core
with known values.
The density ranges for the mineralised units are listed below:
Massive sulphides 2.0 to 4.7g/cm
3(average: 3.9g/cm
3), net textured sulphides 3.0 to 4.4g/cm
3
(average: 3.6g/cm
3) and disseminated sulphides 2.5 to 4.6g/cm
3(average: 3.5g/cm
3).
The host geology comprises high grade metamorphic rocks that have undergone granulite facies
deformation. The rocks have been extensively recrystallised and are very hard and competent.
Vugs or large fracture zones are generally annealed with quartz or carbonate in breccia zones.
Porosity in the mineralised zone is low. Sensitivity to these issues is thus low.
The bulk densityvalues were estimated usingthe nickel searchparameters and7,950plus 12,429

PAGE 22

==> picture [596 x 83] intentionally omitted <==

Criteria Commentary
density samples taken within the geological domains.
Classification The Mineral Resource classification at Bollinger is based on good confidence in the
geological and grade continuity, along with 25m by 25m spaced drill hole density in the
core and bulk of the deposit, and 50m x 50m on the margins.
The Mineral Resource classification at Nova is based on good confidence in the geological and
grade continuity, along with 25m by 25m spaced drill hole density throughout. Estimation
parameters including Kriging efficiency have been utilised during the classification process.
The input data are comprehensive in coverage of the mineralisation and do not favour or
misrepresent_in situ_mineralisation. Geological control at Nova-Bollingerconsists of a primary
mineralisation event modified by metamorphism and structural events. The definition of
mineralised zones is based on a high level of geological understanding producing a robust model
of mineralised domains. This model has been confirmed by infill drilling which supported the initial
interpretation.
The validation of the block model shows good correlation of the input data to the estimated grades.
The Mineral Resource estimate appropriately reflects the view of the Competent Person.
Audits or reviews This is the maidenBollingerMineral Resource estimate and an update of the Nova March 2013
Mineral Resource estimate. The Nova resource was reviewed by Optiro and some improvements
made to the geological domains as a result of the new information at Bollinger.
Discussion of relative
accuracy/confidence
The relative accuracy of the Mineral Resource estimate is reflected in the reporting of the Mineral
Resource as per the guidelines of the 2012 JORC Code.
The statement relates to global estimates of tonnes and grade.
No production data are available for comparison and reconciliation. The boxcut has been
completed and decline access to the orebody is underway.

Section 4 Estimation and Reporting of Ore Reserves

Criteria Commentary
Mineral Resource estimate
for conversion to Ore
Reserves
The Underground Ore Reserve estimate is based on the Mineral Resource estimate carried out by
Optiro Pty Ltd._ASX announcement 15 July_2013 “Maiden Bollinger Resource and Scoping Study
Update”.
The June 2016 Ore Reserves are December 2015 with minor broken stocks
The Mineral Resources reported are inclusive of the Ore Reserve.
Site visits The Competent Person is employed by IGO on the Nova site.
Study status Feasibility level studies have been completed for all areas of the Nova Nickel Project and the
project is under construction.
The current Ore Reserve estimates are based around the assumptions completed for the Nova
Nickel Project Feasibility Study and enhanced in the IGO Optimisation Study.
Cut-off parameters In order to determine the economically mineable part of the resource, the total value of the
mineralised material was calculated, including recognition of the value of nickel, copper and cobalt
in the ore. This value, commonly referred to as a Net Smelter Return (NSR) is calculated in
Australian dollars per ore tonne and represents the value of the products produced from one tonne
of ore if sold at the mill gate. It is calculated from the revenue received from the payable metal (mill
recovered) contained in the products less all costs and charges downstream of the site including
transportation, smelting, refining and metal loss throughout these stages.
The NSR cut-off calculations were conducted by prior to designing the underground mine, and
again following completion of the design, scheduling and cost modelling. The initial estimation that
was used for Feasibility Study mine design purposes was based on processing, treatment, refining,
mining, administration and operating cost estimates from the Sirius Scoping Study. The operating
cost generated from the Nova Underground financial model is $105/tonne of ore comprising:

Mining cost of $55/t

Processing cost of $38/t

Admin cost of $12/t.
Metal prices are based on 12 month averages (not volume-weighted) of spot prices from the
London Metal Exchange between June 2012 and July2013 and wereprovided bySirius, prices are

PAGE 23

==> picture [596 x 83] intentionally omitted <==

Criteria Commentary
as follows:

Nickel – US$7.44/lb

Copper – US3.47/lb

Cobalt – US$12.00/lb

Exchange rate - $A 1: $US 0.90
Mining factors or
assumptions
The Ore Reserve estimate has been calculated by generating detailed mining shapes for each
stoping block as well as development. Designed stope shapes include planned dilution, being
waste material that is located within the mineable stope shape. Additional unplanned dilution is also
generally incurred from the walls of stopes due to re-distribution of stress within the rock mass as
voids are created in the mine, blast damage, poor mining practice (such as poor blasthole drilling
setup). This additional material is also included in Ore Reserve Estimate.
A 7% unplanned dilution factor has been calculated by Entech in consultation with SRK based on
kinematic and empirical methods.
The selected mining methods for the Nova Project is long-hole sub-level open-stoping which is
widely used in many underground mines in Western Australia and is deemed appropriate
considering the nature of the ore body, and the desire to extract the maximum value from the
deposit.
Stope sizes are generally 25mW by 25mH by the orebody width and have been created to suit the
Mineral Resource model. As the resource changes in width and dip the mining method changes
from large multi-lift stopes to echelon retreat single access stopes. Geotechnical assessment of
the mineralised zone is also favourable for the selected mining method. In consultation with SRK
geotechnical parameters have been set out for the size of the stoping blocks as well as support
standards and development stand-off distances. All mining shapes included in the Ore Reserve
estimate abide by the recommendations supplied by SRK.
A mining recovery factor of 95% has been applied post geological interrogation to generate the final
diluted and recovered Ore Reserve estimate. This mining recovery is applied to allow for any ore
loss due to mining related issues such as; underbreak due to poor drilling and blasting techniques,
stope bridging or freezing or material being left in stopes due to inaccessibility.
Minimum mining width for stoping is 4m.
Grade control drilling is underway from UG drill platforms on a nominal 12.5m x 12.5m pattern on
the footwall.
No Inferred Mineral Resources have been included in the Ore Reserve Estimate. Any Inferred
Mineral Resource contained within a mining block (stope or development) is classified as waste
and is used to dilute the overall Ore Reserve.
Infrastructure build for Nova is still underway, with the remaining been accounted for and included
in all work leading to the generation of the Ore Reserve estimate. The Nova Nickel Project
infrastructure includes:

All site surface infrastructure, including:
o
Processing facilities, including crushing, grinding, flotation and dewatering
o
Tailings storage facility
o
Offices, workshops, warehouses and associated facilities
o
Borefield and pipeline
o
Camp
o
Airstrip
o
Access Road
o
Power Station

Paste filling infrastructure. The backfilling of the production stopes is an integral
component of the mining method at Nova for all stope sizes and configurations. Paste fill
utilising classified live tailings is the nominated fill type. A Paste Plant will be located
above the orebody on the surface and will comprise: tailings storage tank(s); filter; binder
storage; mixer and associated facilities. Paste will be delivered underground by gravity
through a reticulation system consisting of boreholes and horizontal piping.

All power and pumping reticulation will be fed through decline development, ventilation
rises and service holes drilled in close proximity to the decline to minimise cable and
pipe runs along the decline path.

Ventilation fans will be installed underground at the base of a raisebored shaft to supply
fresh air to underground workings. Return air ventilation system to be located on
opposite side of the deposit to the decline to allow for flow through ventilation. Caged
ladderways will be installed in fresh air ventilation rises to establish a second means of
egress from undergroundproject.
Metallurgical factors or Mineralogyshows main sulphide minerals as chalcopyrite, pentlandite andpyrrhotite. Chalcopyrite

PAGE 24

==> picture [596 x 83] intentionally omitted <==

Criteria Commentary Commentary Commentary
assumptions



is largely liberated, however some fine pentlandite is associated with the pyrrhotite. Gangue
minerals include olivine/pyroxene, amphibole, feldspars, garnets, quartz which are un-altered.
The nameplate of the processing facility is 1.5Mtpa capacity plant. Processing will comprise
conventional crushing, milling and classification circuits followed by dual flotation circuits to produce
separate nickel (+cobalt) and copper (+silver) concentrates.




The Nova-Bollinger deposit is different from other local nickel deposits of Norlisk – Lake Johnston,
Western Areas – Forrestonia, Panoramic – Lanfranchi and Mincor - Widgemooltha which are near
Norseman to the West and North.
The nearest analogous deposits are in Canada such as Thompson (owned by Vale), Raglan
(owned by Xstrata) and Voisey’s Bay (owned by Vale) who are using fresh water in the processing.






















The split concentrate flowsheet has achieved separation between copper and nickel for production
of separate concentrates with acceptable recoveries. The results to date show a robust processing
flowsheet than can consistently achieve a copper concentrate grading 27 – 31% Cu for 95%
overall recovery and a nickel concentrate grading 13 - 17% Ni for 89% overall recovery.
The copper concentrate is low in nickel (<0.5%) and represents <0.5% nickel recovery. It should be
noted that the grades and recoveries reported cannot be paired as there are middling streams in
the batch flowsheet that are yet to be allocated to either concentrate or tails. That is, recoveries are
rougher recoveries, whilst grades are cleaner grades. The final copper and nickel flotation recovery
for this flowsheet will be determined from planned locked cycle testwork.
The testing is investigating two potential reagent regimes for split flotation, one using TETA (tri-
ethylene-tetra-amine) with sodium sulphite and Cytec Industries polymeric depressant (7261A).
These are all used in commercial flotation processes, more commonly in North America, less
commonly in Australia. Selective sulphide flotation is considered a well-tested technology.
Flotation testing has shown the ability to produce a combined bulk concentrate or a separate split
concentrate in hyper-saline site water.
Economic evaluations concluded that a split concentrate option will achieve a higher revenue than
a combined concentrate, due to the increased pay-ability of the copper. Split concentrate offers
flexibility, marketing options and was adopted as the preferred flowsheet for the Feasibility Study.
Composite A was formulated as the main testing composite to be used in further development
testwork. Composite A is based on the following criteria:

Year 1-3 stoping material

All MET holes below 2005 RL

Including mining dilution as advised by Entech, and agreed by Sirius, nominally 2.5m HW
and 0.5m FW.

Every second metre from 9 holes.
Composites B - P includes all major material types of Disseminated in Gabbro, Stringer in
Sediment, Upper Massive, Lower massive/breccia and Net-textured, including dilution coming from
HW Waste, FW Waste and HW Gabbro Disseminated. All metallurgical composites represent 83%
of the known ore resource. Detailed modelling of the metallurgical recoveries by ore type and ore
zones has been applied to the mining schedule to determine the overall recoveries used in the
financial modelling. These are as follows:
Metallurgical
Recoveries
Copper
Concentrate
Nickel
Concentrate
Ni
1%
89%
Cu
95%
3%
Co
1%
85%
Note: Nickel Recoveries are based on Mill Feed Grades.
Metallurgical
Recoveries
Copper
Concentrate
Nickel
Concentrate
Ni 1% 89%
Cu 95% 3%
Co 1% 85%
Note: Nickel Recoveries are based o

No deleterious elements were observed in the concentrates, with the exception of chloride from the
process water. Concentrate washing has been investigated to determine the required amount.
Copper Concentrate specification– Cu 27-31%, S 29-33%, Fe 29-30%, MgO <1%, SiO2<2.5%,
As 0.005%, Sb 0.001%, Bi 0.003%, Cd <0.002%, Pb 0.016%, Zn 0.046%, Ni 0.64%, Co 0.02 %, Cl
+ F <300 ppm, Hg <1 ppm, Al2O30.56%.
Nickel Concentrate specification– Ni 13-17%, Cu 0.20-0.6%, Co 0.43-0.49%, Au 0.05g/t, Ag
4.8g/t,S 31-34%,Fe 41-44%,MgO <1.5%,SiO2<3.0%,As 0.002%,Pb 0.005%,Zn 0.020%,Cl + F

No deleterious elements were observed in the concentrates, with the exception of chloride from the process water. Concentrate washing has been investigated to determine the required amount. Copper Concentrate specification – Cu 27-31%, S 29-33%, Fe 29-30%, MgO <1%, SiO2 <2.5%, As 0.005%, Sb 0.001%, Bi 0.003%, Cd <0.002%, Pb 0.016%, Zn 0.046%, Ni 0.64%, Co 0.02 %, Cl + F <300 ppm, Hg <1 ppm, Al2O3 0.56%.

Nickel Concentrate specification – Ni 13-17%, Cu 0.20-0.6%, Co 0.43-0.49%, Au 0.05g/t, Ag 4.8g/t, S 31-34%, Fe 41-44%, MgO <1.5%, SiO2 <3.0%, As 0.002%, Pb 0.005%, Zn 0.020%, Cl + F

PAGE 25

==> picture [596 x 83] intentionally omitted <==

Criteria Commentary
<300 ppm, Al2O30.9%.
The main minerals of chalcopyrite, pentlandite and pyrrhotite can be defined by Cu, Ni, Fe and S
grades. The deposit has been modelled with Ni, Cu, Co, Fe, S and MgO for all major material
domains.
Environmental All environmental approvals for the proposed mining activities have been secured.
Waste rock and tailings characterisation studies have been completed. Negligible waste rock will
be disposed of on surface. Tailings are highly acid-forming and the costs of appropriate
impoundments have been allowed. Construction of the Tailings Storage Facility (TSF) has been
completed to full Life of Mine capacity.
Infrastructure The majority of the significant surface infrastructure for the Nova Nickel Project has been
constructed, or is currently under construction. The concentrator is planned to be commissioned in
late 2016. Decline access to the orebody is well advanced, having commenced in May 2015 and
will begin supplying ore to the concentrator in line with the commissioning schedule.
The proposed infrastructure lies partly on Fraser Range Station (a pastoral lease administered by
Pastoral Lands Board) and unallocated crown land. Some infrastructure (access road, borefield,
pipeline) is located on mining tenure held by other companies, and appropriate access agreements
have been entered into.
It has been modelled that there will be sufficient water available to develop the Nova Nickel
Project. Dewatering of a confined aquifer overlaying the ore zone (the Botryoidal Aquifer) is well
advanced and this water is being stored in the TSF for use in the initial years of processing.
Further exploration for Life of Mine (LOM) water supply is continuing.
Costs Capital costs used in the production of the Ore Reserve estimate have been gathered from budget
pricing or from a cost database. In the case where database costs have been used, contingencies
have been applied. Major capital items are based on estimates prepared by experienced
independent engineers, including:

Processing Plant – Ausenco

TSF, Access Road, Aerodrome – GHD Australia Pty Ltd

Borefields – MSP Engineering Pty Ltd

Underground (Fixed Plant) – Entech Ltd
As firm contracts have been let during the implementation phase, costs have generally being seen
to be in line with,or less than those used in the FeasibilityStudyand the Ore Reserve estimate.
Operating costs for the underground operation are based on a budget estimate from a leading
underground mining contractor. Major operating costs are based on estimates by Sirius and
experienced independent engineers, including:

Underground Contract Mining – Barminco

Processing Costs (based on Sirius reagent consumption) – Ausenco
A capital and operating cost model has been developed in Excel and has been used to complete a
life of mine cash flow estimate.
Smelter terms have been determined from typical contracts and include:

Nickel payability and TC.

Copper payability (Ni Concentrate)

Copper concentrate copper payability and TC/RC

The presence of deleterious elements has been assessed and it has been determined
that no penalties will be applied

Estimates ofsmeltertermshave beendeterminedin-house.
Product inland transport costs have been estimated by an experienced contractor, Qube Logistics.
Shipping costs from the Port of Esperance have been estimated by an experienced shipping
broker, Braemar Seascope.
Royalty allowances are in accordance with Division 5 of the WA Mining Act (Ni and Co = 2.5% of
gross FOB metal value in $A; Cu = 5% of nett FOB metal value in A$). In addition a 0.5% of gross
Ni FOB value in A$ is payable under Native Title agreements.
Revenue factors Head grade of the project is dependent on the material scheduled to be mined from underground.
Treatment and transportation charges applied in the economic evaluation as outlined previously.
Revenue has been based on the commodity price and exchange rates commented on above.
Metal prices are based on 12 month averages (not volume-weighted) of spot prices from the
London Metal Exchange between June 2012 and July 2013 and were provided by Sirius. Prices
are as follows:

PAGE 26

==> picture [596 x 83] intentionally omitted <==

Criteria Commentary

Nickel – US$7.44/lb

Copper – US3.47/lb

Cobalt – US$12.00/lb
Exchange rate - $A 1: $US 0.90
Market assessment Demand for concentrate has been derived from international metals market analysts – Wood
Mackenzie, who prepared a commissioned nickel & copper market study, dated 18 June, 2014.
Customer and competitor analysis is based on research provided by Wood Mackenzie, plus input
from Wood Mackenzie Nickel Industry Cost Service. Also, a commissioned research report into
Nickel West furnished by Vector Solutions Pty Ltd, entitled “Value-in-Use Assessment of Nova
Concentrate to Nickel West”.
The price and volumes forecast are based on information provided by Wood Mackenzie’s Long
Term Outlook Reports for Nickel and Copper, June 2014 editions, the commissioned research by
Wood Mackenzie, and pricing forecasts by Consensus Economics Inc.
Potential customers have received and approved representative samples, and received detailed
specifications.
Economic The Ore Reserve estimate is based on a financial model that has been prepared at a “Feasibility
Study” level of accuracy. All inputs from underground operations, processing, transportation and
sustaining capital as well as contingencies have been scheduled and evaluated to generate a full
life-of-mine cost model.
Economic inputs have been sourced from suppliers or generated from database information
relating to the relevant area of discipline.
A discount rate of 8% has been applied.
The NPV of the project is strongly positive at the assumed commodity prices.
Social IGO has engaged in discussions with key project stakeholders including:

The Fraser Range Pastoral Lessees,

Southern Hills Pastoral Lessees,

The Esperance Ports Sea and Land; and

Shires of Esperance and Dundas.
None has expressed material concerns with the proposed development.
Apart from the Fraser Range homestead and caravan park, there are no permanent residences
within the Project Area or its environs.
All agreements with key stakeholders including traditional owner claimants have either been
issued, or are expected to be issued in due course. Those not yet finalised will not affect the Ore
Reserve estimate.
Other Groundwater model simulations indicate that the Nova Project shall have excess water for the first
12 months during construction and development. However, as the aquifers are successfully
dewatered and mineral processing commences, the Project is likely to fall into a water deficit
scenario. Three additional water supply bores have been identified and these shall need to be
drilled, constructed and equipped. Additional bores may be required within a further 2 years, but
this can be re-assessed once dewatering and other pumping data becomes available.
Although it is not expected, if further groundwater resources are necessary later in the Project’s life,
there are multiple options for further groundwater resource development within a 50km radius of the
Project. These include:

additional discrete fractures that could be identified within the Nova lease

off-lease palaeochannel aquifers

off-lease fractured rock aquifers.
A Reverse Osmosis (RO) plant will be required to produce all potable water requirements including
concentrate washing. This plant will be designed to treat water quality expected from the borefield.
The RO plant will produce the Project’s potable water requirement which is then distributed across
the site and to the accommodation village.
Nova and Bollinger are located wholly within Mining Lease M28/376. IGO has a 100% interest in
the tenements. The tenements sit within the Ngadju Native Title Determination.
Classification The Ore Reserve is based on Probable Ore Reserves, no Proved Ore Reserves are reported.
Indicated Mineral Resources have been converted to a Probable Ore Reserve.
No Measured category Mineral resources have been estimated to date.

PAGE 27

==> picture [596 x 83] intentionally omitted <==

Criteria Commentary
The Competent Person is satisfied with the classification of the Underground Mineral Resource
and hence the conversion to Ore Reserve is appropriate.
Audits or reviews The Ore Reserve has been peer reviewed internally and is in line with current industry standards.
Discussion
of
relative
accuracy/confidence
The Ore Reserve has been completed to a Definitive Feasibility standard; hence confidence in the
resulting figures is high.
Confidence in the mine design and schedule are high.
All modifying factors have been applied to designed mining shapes on a global scale as there are
limited local data.

PAGE 28

==> picture [596 x 83] intentionally omitted <==

APPENDIX B

Tropicana Mineral Resources and Ore Reserves 2016

JORC Code, 2012 Edition – Table 1

Section 1 Sampling Techniques and Data

Criteria Commentary
Sampling techniques AngloGold Ashanti Australia (AGA) has carried out all the drilling within the Tropicana deposit, with
sampling from Reverse Circulation (RC) and diamond drilling predominantly from one metre
sample intervals, for 50g gold fire assay. The sampling methodology with RC drilling has changed
over time. Sample collection prior to 2007 was via a cyclone, dust collection system and multi-
stage riffle splitter attached to the drill rig. From the beginning of 2007 sample collection was via a
cyclone, dust collection system and cone splitter attached to the drill rig.
RC samples are collected from one metre intervals for resource definition drill holes, with two metre
sample intervals from RC pre-collar drilling introduced in 2016.
All NQ2 and HQ diamond holes have been half-core sampled over prospective mineralised intervals
determined by the geologist, where sample intervals are generally one metre samples. In 2016 two
metre samples were processed from un-mineralised core to collect additional geometallurgical data
(hyperspectral and XRF) for waste rock characterisation.
Within fresh rock, core is oriented for structural/geotechnical logging wherever possible. In oriented
core, one half of the core was sampled over one metre intervals and submitted for fire assay. The
other half of the core, including the bottom-of-hole orientation line, was retained for geological
reference and potential further sampling such as metallurgical test work. In intervals of un-oriented
core, the same half of the core has been sampled where possible, by extending a cut line from
oriented intervals through into the un-oriented intervals. The lack of a consistent geological
reference plane, (such as bedding or a foliation), precludes using geological features to orient the
core.
Drilling techniques Reverse Circulation drilling has been utilised to an average depth of 150m in the shallower, up-dip,
western portions of the Resource and as pre-collars to diamond holes. All Reverse Circulation
drilling has been via face sampling hammer.
Diamond drilling has predominantly been NQ2 with limited HQ2, HQ3 and PQ in the upper saprolite
and for holes drilled for geotechnical and metallurgical purposes. The majority of diamond holes
have been drilled as tails to RC drilling. From 2011 many deeper holes were drilled with shorter RC
pre-collars (~60m), or HQ from surface to minimise deviation.
Drill sample recovery The sample recovery is currently recorded on selected intervals to assess that the sample is being
adequately recovered during RC drilling. Prior to April 2008, no systematic assessment of sample
recovery data was made for RC drilling. A subjective visual estimate was used where weights were
recorded as 25, 50, 75 or 100%. Since April 2008 a systematic sample recovery program has been
implemented where for 1:25 intervals, the Primary (lab weight), Secondary (archive weight) and
Reject splits are weighed and recorded in the database. These weights are combined and then
compared to a theoretical recovery of the interval based on the regolith and rock type of the interval
being analysed.
For diamond drilling recovered core for each drill run is recorded and measured against the
expected core from that run. Core recovery is consistently very high, with minor loss occurring in
regolith and heavily fractured ground.
Logging All RC chips and diamond drill cores have been geologically logged for lithology, regolith,
mineralisation and alteration utilising AGA’s standard logging code library. RC Sample quality data
recorded includes recovery, sample moisture (i.e. whether dry, moist wet or water injected) and
sampling methodology.
Diamond core has also been logged for geological structure and geotechnical properties. Diamond
drill holes are routinely orientated, photographed and structurally logged with the confidence in the
orientation recorded. Geotechnical data recorded includes QSI, RQD, matrix, and fracture
categorisation.
Bulk density determinations have been routinely collected for diamond drill core over one to five
meter intervals using water immersion methods. A coherent segment of core (>10cm length),
representative of the meter interval is selected. Laboratory bulk density determination is completed
on selected ‘core from surface’ diamond holes to collect bulk density data for oxide and transitional
rock types, and from fresh rock types to ensure water immersion methods used onsite is accurate.

PAGE 29

==> picture [596 x 83] intentionally omitted <==

Criteria Commentary
All logging data are digitally captured via Field Marshall Software (upgraded to Micromine Geobank
platform 2016) and the data are validated in Vulcan prior to being uploaded to an SQL database.
DataShed has been utilised for the majority of the data management of the SQL database. The
SQL database utilises referential integrity to ensure data in different tables are consistent and
restricted to defined logging codes.
Sub-sampling techniques
and sample preparation
Since the commencement of exploration activities at Tropicana, sample preparation and analysis
has been carried out by three laboratories, as detailed below:
Prior to November 2006 - SGS (formerly Analabs) Welshpool performed all gold and multi-element
analysis. SGS routinely prepared half-core diamond samples by crushing in a jaw crusher followed
by pulping in an LM5 to 90% passing 75µm. One metre RC samples are pulped in an LM5 to 90%
passing 75µm. 50-gram samples are then assayed by fire assay. Sieve tests are carried out on 5%
of samples.
November 2006 to 2014 – Genalysis Perth has performed all gold and multi-element analyses and
hyperspectral scans.
The 2015 Boston Shaker infill drilling was analysed at the Tropicana onsite lab, with sample
preparation conducted by AGAA staff operating an automated circuit, and SGS conducting the
fire assay and analysis.
June 2016 to current, infill drilling has been analysed at the Tropicana onsite lab, with sample
preparation conducted by AGAA staff operating an automated circuit, and SGS conducting the
fire assay and analysis.
At Genalysis, half core samples weighing approximately 2.5kg are prepared via a robot.
The samples are then crushed to <3mm in a Boyd crusher and automatically split, down to a
sample of ~1kg for pulping and analysis. The remainder of the material was retained as a
coarse split for metallurgical test-work. One metre RC samples were pulped in a mixer mill to
90% passing 75µm. Wet sieve tests were carried out on 5% of the samples.
The Tropicana laboratory uses a linear automated process to prepare the samples. Samples, from
RC and diamond drilling, are loaded onto racks at the lab. Each sample bag has a unique bar-code
attached to the bag. Samples are dried and weighed. Small samples (<800g) are manually
pulverised in an LM2 mill to 90% passing 75µm. Acceptable weight samples (>800g) are
loaded into tubs and the samples passed under a Terraspec Hyperspectral camera. Samples are
then passed through a Boyd crusher, reducing the particle size to 90% passing 2mm before being
split via a Linear Sample Divider. Coarse duplicates are assayed at a rate on 1 in 20 within the
assaying of the batch. Primary samples then get pulverised to 90% passing 75µm and the resultant
product split into a 50g sample or fire assay and a 500g sample. The 500g sample passes under a
portable XRF scanner for analysis of secondary elements (that are not used in the Mineral Resource
estimate). The 500g sample is retained for check assay work. Routinely, coarse blank samples are
inserted as the first sample in each laboratory job. The purpose of this sample is to check that
laboratory crushing and grinding equipment is kept clean. Coarse blanks samples are also inserted
into the sequence of samples before each zone of mineralisation. Standards are inserted into
batches of samples at a frequency of three standards in every 100. Sieve tests are carried out on
5% of samples. Coarse duplicates are completed on 20% of the samples.
Quality of assay data and
laboratory tests
At SGS 50-gram samples were assayed by fire assay. SGS inserted blanks and standards (one in
20 samples) in every batch. Every 20th sample was selected as a duplicate from the original pulp
packet and then analysed. Repeat assays were completed at a frequency of one in 20 and were
selected at random throughout the batch. In addition, further repeat assays were selected at
random by the quality control officer, the frequency of which was batch dependent. Analysis was by
fire assay with similar quality assurance (QA) for RC and half core samples.
Genalysis inserted internal standards and blanks randomly through each batch. Every 25th sample
was selected as a duplicate from the original pulp packet and then analysed at the end of the batch.
Finally, 6% of the batch was selected for re-analysis.
Internal laboratory checks and internal and external check assays such as repeats and check
assays enable assessment of precision. Contamination between samples is checked for by the use
of blank samples. Assessment of accuracy is carried out by the use of certified Standards (CRM).
Check assay campaigns generally coincide with each Resource update.
QAQC results are reviewed on a batch-by-batch and monthly basis. Any deviations from acceptable
precision or indications of bias are acted on with repeat and check assays. Overall performance of
both laboratories has been satisfactory.

PAGE 30

==> picture [596 x 83] intentionally omitted <==

Criteria Commentary
Verification of sampling
and assaying
On receipt of assay results from the laboratory the results are verified by the Data Manager and by
geologists who compare results with geological logging.
Analysis of twinned drill holes showed that no significant down-hole smearing was occurring in RC
holes when compared to the twinned diamond holes in Tropicana and Havana.
Location of data points All hole locations within the resource area to date have been pegged with a standard GPS, or by
RTK GPS. Once the holes are drilled the collar location is then surveyed with an RTK GPS.
A regional Digital Terrain Model was then created to cover the Tropicana JV tenement area from
Shuttle Radar Topography Mission (SRTM) data. The data were sampled at 3 arc-seconds, which
is 1/1200th of a degree of latitude and longitude, or about 90 metres.
Eastman single shot instruments were used routinely for down-hole surveys prior to 2007.
From 2007, gyro surveying instruments have been used to complete downhole surveying.
Data spacing and
distribution
Drill hole spacing on sections, and between sections, typically range from 25 x 25m to 100 x 100m.
The majority of the Open Pit Resource area has been drill tested at a nominal density of 50 x 50m
with the spacing closed up to 25m x 25m within the upper levels of the deposit.
The down-plunge extension of the Havana Deeps area is drilled at 100m x 100m or 100 x 50m
closer to the pit area.
1m samples are composited to 2m prior to Resource Estimation.
Orientation of data in
relation to geological
structure
The majority of drilling is orientated to intersect normal to mineralisation. The chance of bias
introduced by sample orientation is thus considered minimal.
Sample security Samples are sealed in calico bags, which are in turn placed in large poly-weave bulka-bags for
transport. Filled poly-weave bulk-bags are secured on wooden crates and transported directly via
road freight to the laboratory with a corresponding submission form and consignment note.
Genalysis checks the samples received against the submission form and notifies AGA of any
missing or additional samples. Once Genalysis has completed the assaying, the pulp packets, pulp
residues and coarse rejects are held in their secure warehouse. On request, the pulp packets are
returned to the AGA warehouse on secure pallets where they are documented for long term storage
and retrieval.
Audits or reviews Field quality control and assurance has been assessed on a daily, monthly and quarterly basis.
Field QA/QC was assessed by Quantitative Group (QG) as part of their audits of the Tropicana and
Havana Resource between 2007 and 2009.

Section 2 Reporting of Exploration Results

Criteria Commentary
Mineral tenement and land
tenure status
Tropicana is a joint venture between AngloGold Ashanti Australia Limited (AGA) and Independence
Group NL (IGO) (AGA:IGO, 70:30) AGA is the manager of the JV.
There is no known heritage or environmental impediments over the leases where significant
results were received.
The tenure is secure at the time of reporting. No known impediments exist to operate in the area.
Exploration done by other
parties
AGA has carried out all the drilling within the Tropicana deposit.
Geology The Tropicana and Havana gold deposit host rocks are predominantly gneisses.
Drill hole Information No new exploration data are announced within this report.
Data aggregation methods No new exploration data are announced within this report.
Relationship between
mineralisation widths and
intercept lengths
No new exploration data are announced within this report.
Diagrams No new exploration data are announced within this report.
Balanced reporting No new exploration data are announced within this report.
Other substantive
exploration data
No new exploration data are announced within this report.

PAGE 31

==> picture [596 x 83] intentionally omitted <==

Criteria Commentary
Further work No new exploration data are announced within this report.

Section 3 Estimation and Reporting of Mineral Resources

Criteria Commentary
Database integrity AGA uses various software programs to collect the different forms of drilling data obtained during
exploration. The main packages are from Microsoft (SQL Server and Access) an, Maptek Pty Ltd.
(Vulcan), Micromine Pty Limited (Micromine, Field Marshall and Geobank), Aranz Geo Limited
(Leapfrog), Maxwell Services Limited (DataShed) and Karjeni Pty Limited (dPipe).
The database is managed with Microsoft’s SQL Server and Maxwell’s DataShed. DataShed was
developed as a front end interface to MS Access or SQL Server. DataShed was specifically created
for the exploration and mining community and contains queries and data management utilities
unique to the mining industry. Many of these or additional processes have been modified or added
to by AGA.
Drilling data are captured in the field directly into handheld, for example Husky, LXE, Toughbook or
laptop computers with Field Marshall and Geobank software. Daily drilling forms (Plods) are
completed by the driller in hard copy and signed off by the geologist and entered into DataShed.
ampling, bulk densities, Hardness and Magnetic Susceptibility (MagSus) readings are also recorded
digitally into handheld devices. Up to end of 2015, the merging of logging data into the database
was semi- automated via a file transfer program called dPipe. Karjeni Pty Limited developed dPipe
to facilitate the transfer of data from one format into another into SQL databases. This program has
the ability to read a file to split, composite and append data into the desired format.
From 2016, logging data is synchronised from Geobank directly into Datashed, and field data, such
as RTK collar coordinates and downhole surveys are loaded via DataShed importers. Assay
results received from the laboratories are emailed to geologists and stored on the server.
An invoice is mailed to AGA along with a hard copy or digital PDFs of the results. The hard
copies are filed in folders and PDFs stored on the network for future auditing purposes.
Assay data files are loaded via DataShed importers, and loading procedures include
QA/QC checks to ensure standards and blanks have returned acceptable results.
Rigorous data validation procedures are in place to identify data issues.
Site visits Mining activities are ongoing and the site is visited regularly by the Competent Persons.
Geological interpretation 3D solids are created or mineralised zones, dykes, shears and garnet gneiss using
Leapfrog. The mineralised domains are created by flagging intervals at a 0.3g/t gold rade
cut-off with internal lower grades included in the model. The Dykes, Shears an Garnet
Gneiss units are selected by flagging intervals based on logged lithology, as they are the
most visually distinctive units, are the least subjective when being logged and therefore
are considered to have a high level of confidence in interpretation. The dykes are locally
important as they post-date mineralisation and are generally barren of mineralisation.
Modelling of the shears is critical to understanding geotechnical aspects and assessing
the spatial controls on the mineralisation. The Garnet Gneiss units are important because
they are generally found in the hanging wall and as a precursor to mineralisation, as well
as being the dominantwasterockunit.
Dimensions The Open Pit Mineral Resource is reported within an A$1817 optimisation shell that is 4.7km long,
up to 1km wide, and up to 450m deep.
The Underground Mineral Resource extends to a depth of approximately 1km below surface.

PAGE 32

==> picture [596 x 83] intentionally omitted <==

Criteria Commentary
Estimation and modelling
techniques
The Mineral Resource is reported from open pit and underground Mineral Resource models,
estimated with differing estimation techniques and with different cut-off grades applied to each
model. The Open Pit Mineral Resources have been estimated using the geostatistical technique of
Localised Uniform Conditioning using average drill hole intercepts and is reported above a marginal
(break-even) cut-off grade of 0.3g/t for oxide material and 0.4g/t for transitional and fresh
material. The Havana Deeps Underground Mineral Resource has been estimated at a cut-off grade
of 2.0g/t using the geostatistical technique of Ordinary Kriging using average drill hole intercepts.
The Underground cut-off grade calculation is based on an underground Pre-Feasibility study
completed in late 2013, and a gold price of US$1400 (A$1704).
2m down-hole composites are used for both estimates.
Gold is the only element modelled, as no other significant element has been detected in sampling to
date which would be deleterious to mine and mill performance.
The Open Pit estimate uses block sizes of 15m (X) by 30m (Y) by 10m (Z) with an SMU of 5m (X)
by 7.5m (Y) by 3.33m (Z).
The Underground estimate uses a block size of 10m (X) by 10m (Y) by 2m (Z), with blocks dipping
30° to the (grid) east, parallel to the majority dip of the orebody, with the resulting estimate filtered to
remove isolated blocks that cannot be mined individually.
Both Resource Estimates are compared to the input data using swath plots to check for bias in the
estimation, no bias was noted in the plots.
Mining has been ongoing since 2012 and reconciliations to date indicate that the Mineral Resource
model has reconciled well with grade control.
Moisture Tonnage estimates are on a dry tonne basis.
Cut-off parameters The Open Pit Mineral Resources use a cut-off grade of 0.3g/t for oxide material and 0.4g/t for
transitional and fresh material, based on contract mining costs, budgeted processing and
administration costs, and a gold price of US$1400 (A$1817).
The Underground Mineral Resource has been estimated at a cut-off grade of 2.0g/t.
The cut-off grade calculation is based on an underground Pre-Feasibility study completed in late
2013, and a gold price of US$1400 (A$1704).
Mining factors or
assumptions
Open Pit mining assumes selectivity of SMU’s of 5m (X) by 7.5m (Y) by 3.33m (Z) for Havana and
Tropicana. Boston Shaker uses an SMU of 5m (X) by 7.5m (Y) by 2.5m (Z).
No external dilution accounted for in the Mineral Resource.
Underground mining is based on a modified Long-Hole Open Stope method, with 20m vertical
intervals between ore drives. The Mineral Resource is filtered based on the average grade of
surrounding blocks to remove isolated blocks from the Mineral Resource total.
No external dilution is included in the Mineral Resource Estimate.
Metallurgical factors or
assumptions
Metallurgical recovery is taken into account in the optimisation of both Open Pit and Underground
Resource optimisations, with an average project recovery of 90.3% assumed, based on extensive
metallurgical test work completed as part of the Feasibility Study for the Havana Open Pit.
Environmental factors or
assumptions
Tropicana Gold Mine (TGM) operates under an environmental management plan that meets or
exceeds all environmental and legislative requirements. TGM holds the license to operate and it is
valid for the life of the Ore Reserve. Environmental rehabilitation plans are produced and cost of the
rehabilitation work is accounted for in the financial evaluation model.
Bulk density Dry Bulk Density (DBD) determinations have been routinely collected on the mineralised zones in all
DDH core at one-metre intervals using water immersion methods. A coherent segment of core
(>10cm length), representative of the metre interval, is selected. The weight is measured dry, in air,
then measured submerged in water. Core was left to dry naturally on the core racks.
Dry Bulk Density has been estimated using Ordinary Block Kriging, with areas with
insufficient data to generate a kriged estimate being assigned the average measured value
for that lithology and regolith type. Density values within units show little variation.
Classification The estimates of the Mineral Resources presented in this Report have been carried out in
accordance with the principles and guidelines of the Australasian Code for Reporting of Exploration
Results, Mineral Resources and Ore Reserves (JORC Code, 2012).
Mineral Resources have been classified based on the 15% rule whereby a Measured Resource
should reconcile within plus or minus 15% over quarterly production volumes, 90% of the time, and
an Indicated Resource should reconcile within plus or minus 15% over yearly volumes, 90% of the
time, as per internal AGA guidelines. This criterion defines a drill spacing of approximately 25 x 25
m to define a Measured Resource,and 50m x 50 m to define an Indicated Resource. Inferred
PAGE 33

==> picture [596 x 83] intentionally omitted <==

Criteria Commentary
Resources are defined when evidence of geological and grade continuity exists sufficient to
generate an estimated grade. The average data spacing for Inferred Resources varies, but is
generally 100m x 100m or less.
The Resource classification is consistent between the Open Pit and Underground estimates, given
that the underground mining will focus on large tonnage, low cost methods and the Resource is
mined at a relatively low cut-off grade. Material defined by relatively few drill-holes was manually
recoded out of Resource classifications, and not reported as part of the Tropicana Mineral
Resource.
Audits or reviews The Open Pit Mineral Resource has been audited previously as part of the BFS by Quantitative
Group (QG) between 2007 and 2009. An additional external review of the Mineral Resource was
also completed in 2011. Golder Associates audited the 2015 Mineral Resource estimate, and
supported the estimate with some recommendations which have been adopted for the current
update.
Discussion
of
relative
accuracy/confidence
The relative accuracy of the Mineral Resource Estimates is reflected in the Resource Classification.
A trial grade control pattern of ~100m by 100m was drilled during the BFS which provided
confidence that the Mineral Resource Estimate was accurate in that volume. Reconciliations of the
Resource model to date indicate no significant flaws in the grade estimate, with some additional
lower grade material being mined than was predicted from the Resource.

Section 4 Estimation and Reporting of Ore Reserves

Criteria Commentary
Mineral Resource estimate
for conversion to Ore
Reserves
All Ore Reserves estimated for Tropicana Gold Mine are based on the Mineral Resource model. No
Ore Reserve exists outside of the Mineral Resource base.
Mineral Resources are reported inclusive of Ore Reserves.
Site visits The Competent Person is based on site and it is part of his daily activities to inspect the
mining areas.
Study status A Feasibility Study was completed in 2010, which determined a technically achievable and
financially economic mine plan. The Ore Reserves are designed based on the current operational
practices of the mine. All Ore Reserves are estimated by reporting physicals (volumes, tonnes,
grades, material types, etc.) against the Resource model within detailed staged pit designs. Ore
Reserve physicals are then put through a financial model for economic evaluation.
Performance of the on-going mining activities has demonstrated that current mine plans are
technically achievable and economically viable considering the material modifying factors.
Cut-off parameters The cut-off grades are determined based on the net return from the gold produced at the processing
plant for each material type. Only the ore that has a grade above the cut-off grades are included in
the Ore Reserves.
Mining factors or
assumptions
The Ore Reserves are reported within detailed operational designs that are developed based on the
geological Resource model, geotechnical studies and financial information.
Open pit mining method is based on using excavator and truck fleet system. The staged pit designs
used for Ore Reserves are generated as three dimensional designs considering operational
requirements such as equipment access. Mining operations at Tropicana Gold Mine started in July
2012 and the operation has proven that the designs and plans are technically achievable; no issue
preventing access or pre-strip is experienced or envisaged for the Ore Reserves.
Overall pit slope angles for oxide and fresh rock types are assumed to be 36° and 60°, respectively.
External and internal Geotechnical studies carried out to evaluate the operational designs have
confirmed that the pit designs do not violate the geotechnical guidelines developed during Feasibility
study. Grade control drilling is completed prior to ore mining on a 12 x 12m pattern using reverse
circulation drill rigs.
The Mineral Resource model used to develop the Ore Reserves uses blocks in 15m x 30m
horizontal dimensions and 10m (7.5m for Boston Shaker) vertical bench height that are mined in 3
flitches (3.3m in average height and Boston Shaker 2.5m in average height), with a minimum SMU
5m x 7.5m x 3.33m (Boston Shaker 5m x 7.5m x 2.5m). The grades within the resource model have
been diluted to reflect the average grade of this mineable block size. Therefore, no other mining
dilution is applied.
Mining recovery factor used is 1.0.
In the designs, a minimum of 50m width is implemented for a pit base or some location with only
one bench height,where it is technically possible to access. In the design work,a minimum of 80m

PAGE 34

==> picture [596 x 83] intentionally omitted <==

Criteria Commentary
mining width is implemented as a generic rule.
Inferred material is excluded from the Ore Reserves and treated as waste material, which incurs a
mining cost but is not processed and hence does not generate any revenue. The total quantity of the
Inferred material is less than 0.3% the Ore Reserve. Hence the reported Ore Reserve's financial
outcome is not sensitive to the Inferred material within the pit designs.
There is no infrastructure to be completed.
Metallurgical factors or
assumptions
The metallurgical process, which was proposed and is currently in operation, was developed
through a comprehensive series of test programs at Scoping, Pre-Feasibility and Feasibility study
levels. Test work was mostly at batch scale but, where considered advisable, at pilot and
demonstration plant scale.
The majority of the process uses highly mature technology. The sole exception is the use of High
Pressure Grinding Rolls to prepare ball mill feed. The equipment used for this technology itself
dates back over twenty years, and is mature. Developments for the hard rock industry are more
recent, but have now been successfully used in a number of plants worldwide and this is the part of
the process that was extensively tested in a range of machines from pilot up to demonstration scale.
Metallurgical test work consisted of comprehensive testing of a number of composite samples to
develop the process design basis, and supplementary testing of a much larger number of samples
to establish variability. These variability samples were taken on a grid pattern to ensure even
coverage of the entire deposit. No metallurgical domains have been recognised to date other than
by regolith type and some minor variation in one northern section of the deposit.
The ore is exceptionally free of deleterious elements and base metals. No allowances have been
made or are considered necessary.
Pilot scale test work utilised PQ diameter core. Whilst only a relatively small number of PQ holes
were drilled, their position was selected based on the prior variability test work to provide samples
considered to be adequately representative of the orebody as a whole. The samples were also
characterised by standard batch scale and geometallurgical style tests so that results could be
related to the wider orebody.
As a gold mine, the product is not defined by specification. No problems are envisaged, or have
been encountered, in producing gold bars of saleable quality.
Environmental Tropicana Gold Mine (TGM) operates under an environmental management plan that meets or
exceeds all environmental and legislative requirements. TGM holds the license to operate and it is
valid for the life of the Ore Reserve. Environmental rehabilitation plans are produced and cost of the
rehabilitation work is accounted for in the financial evaluation model.
Infrastructure Adequate infrastructure has been completed and sustaining cost of the infrastructure (maintenance
and replacement) is accounted for in the financial model.
Costs Capital costs of removing waste over ore are included in the evaluations for the applicable pits.
Mining operating costs are provided by the contractor Macmahon as rates (from an annual rate
review conducted between AGAA and Macmahon). Processing operating costs have been derived
from variety of sources including first principle estimates, metallurgical test work results, budget
quotations for consumables and vendors, consultant advice on wear rates/component replacement
frequency, baseline input parameters such as exchange rates, power cost, labour numbers etc.,
AGA Australia Ltd advice, Lycopodium and sub-consultants data and experienced based on similar
sized operations.
No allowances have been made or are considered necessary for the content of deleterious
elements.
Transportation cost for the produced gold doré is relatively small and charged on a contract base
with the refinery.
The source of the treatment and refinery charges is the contract with refinery and there is no
specification and no penalty is considered for not meeting specifications.
Total royalty cost allowance is 2.5% of the total revenue.
Revenue factors The assumption made for the gold price is US$1,100/oz, A$1,436/oz and the exchange rate is
US$0.77 per Au$1.0.
The assumptions are derived after reviewing historic commodity prices and exchange rates.
Market assessment Long term market assessments are provided by a number of independent companies. AGA does
not provide advice or endorsement for using a specific forecasting company.

PAGE 35

==> picture [596 x 83] intentionally omitted <==

Criteria Commentary
Economic Tropicana Gold Mine (TGM) is now operating with mining costs based on contractor mining rates.
Processing costs have been derived via comprehensive test work and studies. TGM is therefore not
highly exposed to uncertainty in, or to inaccuracy in estimation of, mining or processing costs. The
inflation rates assumed are based on prior AGAA Treasury guidance provided, whilst discount rate
utilised at AGA is derived from the weighted average cost of capital for Australia.
Sensitivity studies are carried out on various parameters including mining cost, processing cost,
gold price and discount rate. Gold price is the most sensitive input for NPV and a 10% reduction
would eliminate about 30,000 ounces (~0.80%) from the Reserves.
Social Tenement status is in good standing.
Other There is no foreseeable TGM specific risk. There are typical risks of an open pit mining operation
such as heavy rain events and geotechnical risks. These risks are managed through implementation
of various risk management mechanisms as much as practical.
Classification Exploration drill-hole spacing is the basis of the classification. Proved material is defined for the
areas drilled with 25m spacing and Probable is defined on 50m drill spacing.
The methodology of classification is appropriate for the deposit.
Proportion of the Proved Ore Reserves is a sub-set of Measured Mineral Resources. Probable Ore
Reserves are derived from Indicated Mineral Resources.
Audits or reviews A Mineral Resource and Ore Reserve audit was completed in 2011. No unexpected results came
from the audit.
Discussion of relative
accuracy/confidence
As part of the Ore Reserve estimation process, a review is performed for the actual reconciled
extraction against previous year’s Reserve estimation.
Reconciliation of the Ore Reserves to actual mined during the 2014 year showed that Ore Reserve
estimation is slightly conservative.

PAGE 36

==> picture [596 x 83] intentionally omitted <==

APPENDIX C

Long Operation Mineral Resources and Ore Reserves 2016

JORC Code, 2012 Edition – Table 1

Section 1 Sampling Techniques and Data

Criteria Commentary
Sampling techniques Conventional Diamond drilling is used to test Long, Victor South, McLeay and Moran ore bodies.
Recent diamond drill core consisted of four different sizes. HQ, NQ2, LTK-60 and BQTK.
Downhole electromagnetic (EM) and in-drive EM geophysical surveys have been undertaken to
assist in targeting of massive sulphide horizons.
Sampling was undertaken by half coring to logged geological intervals using an automatic core saw.
Maximum sample length was 1.1m and minimum sample length was 0.1m for all core sizes.
Sample lengths did not cross geological intervals. Core was cut into half core to give sample weight
of approximately 3kg.
All geological contacts between the footwall basalt and hanging wall ultramafics, with or without the
presence of sulphides, were sampled. Sample intervals extend at least 5m beyond the sulphide
zone (greater than 1% nickel grade) within the footwall and hanging wall geological contact
positions.
Samples were crushed and pulverised (total prep) to produce sub-samples of 400mg for analysis
by mixed four acid digest, followed by ICP-OES analysis.
Densities were determined using Archimedes water immersion technique.
Drilling techniques Historical surface drill holes were drilled with percussion RC pre-collars and NQ diamond tails.
Recent diamond drill core consisted of four different sizes. HQ (core diameter 63.5mm) holes are
drilled where bad ground is expected, and the hole is often completed with a smaller NQ2 core
diameter core (core diameter 50.6mm). Drilling also consisted of LTK-60 (core diameter 43.9mm)
and BQTK core sizes (core diameter 40.7mm).
Drill sample recovery Diamond core was logged and recorded in the database. Intervals of core loss are logged as
geological units with a code of ‘CLOSS’. Intervals of partial core recovery are rare, but are noted in
the comments for both the sample and geology logs. Overall recoveries are >95% and there are no
core loss issues or significant sample recovery problems. Intervals of core loss were not included in
the sample intervals. All recent drilling is completed using underground diamond drill holes with high
(>95%) core recovery.
Diamond core was reconstructed into continuous runs where possible and each interval identified on
the core and the depths checked against the depth given on the core blocks. Rod counts are
marked on additional core blocks routinely completed by the drill crew. Core losses are marked on
additional core blocks marking the start of core loss and end of core loss intervals, by the contract
drillers.
HQ core was used in areas of bad ground to assist in core recovery.
No relationship between sample recovery and grade has been established for the Long, Victor
South, McLeay and Moran mineralisation. They are all located in very competent fresh material so
any loss of fine material would be negligible.
Logging Geotechnical logging was carried out on all recent diamond drill holes for recovery, RQD, and
number of fractures (per interval). The information is captured in the main drill hole database.
Logging of drill samples recorded lithology, mineralogy, mineralisation, veins, alteration minerals,
contact type. Recent core samples were photographed wet and the images stored in the main drill
hole database.
The drill samples were logged qualitatively in full for all samples.
Sub-sampling
techniques
and sample preparation
All samples were cut in half using an automatic core saw. All core samples were collected from the
same side of the core. Extremely broken core is sampled by visually selecting a representative
sample consisting of half of the rock fragments. It is unknown how historical RC samples were
collected. No RC samples were collected in recent drilling data and no RC data is used for grade
interpolation.
The core samples were totally crushed in a jaw crusher to a nominal particle size of 6mm then fine
crushed in a Boyd crusher to a nominal size of 2mm. A sub-sample of approximately 750g is split
out via a rotarydivider(the rotarydivider is adjustable so that consistent-sized splits can be taken

PAGE 37

==> picture [596 x 83] intentionally omitted <==

Criteria Commentary
for pulverising, regardless of original sample weights). The sample is then pulverised in a ring mill. A
sub-sample of 100g is taken from the pulverised, homogenised sub-sample; this sub-sample is
retained as the ‘pulp’. An assay sample of 400mg is taken from the pulp for mixed four acid digest
and then ICP-AES analysis.
Sample preparation checks for grain size were carried out by the contract laboratories as part of its
internal checks to ensure the grind size of 90% passing 75µm. Greater than 90% of all sizing tests
met acceptable limits.
Field QC is through the use of certified reference material as assay standards inserted at irregular
intervals and blank core samples inserted after massive sulphide mineralisation and at irregular
intervals. The insertion rate is 1in 10 blank samples and 1 in 20 standard samples.
The performance of the blank returned 97% of results within acceptable limits as opposed to 88%
reported for the last estimation period. Results of standards and blanks from each batch are
scrutinised at the time they are received, and compared with expected values. Variation outside two
standard deviations from the expected result is reported to the lab for checking, and re-assaying if
required. In-house QAQC reports are produced quarterly and annually to examine variability in
standard and blanks performance and reliability.
Quality of assay data and
laboratory tests
The analytical techniques used a 400mg sub sample digested in mixed four acid digest (Nitric,
Perchloric, Hydrochloric and Hydrofluoric Acid). The digest commences with the samples at room
temperature and after thirty minutes the beakers are transferred to a hotplate which heats the digest
solution to 200°C. The digest solution is reduced until the solution is reduced to a dry, solid state.
This process takes approximately four hours. The dry, powdery material which remains is soluble in
Hydrochloric Acid and is ready for the next stage.
The beaker is removed from the hot plate and Hydrochloric Acid is added. The beaker is returned to
a hotplate, this time operating at 100°C. This “leach back” stage ensures all solids are dissolved
back into solution. The beaker is again removed from the hotplate and allowed to cool. De-iodised
water is added to the beaker to bring the volume of the solution up to a standard 18ml and the
solution is transferred to a test tube, where the volume is checked again and if necessary, adjusted.
This solution is vigorously agitated, so that solution is fully homogenised. This “Primary Digest
Liquor solution” is diluted on a 1:1 basis. Included in the diluent are two rare elements, which are
used as “internal standards” - Yttrium (Y) and Ytterbium (Yb).
The ICP-OES analysis is run for either four (production drilling) or nine elements (exploration
drilling). The four element suite with detection limits is: Ni (10ppm), Cu (10ppm), As (10ppm), S
(100ppm). The nine element suite is: As (10ppm), Co (10ppm), Cr (20ppm plus the possibility of
incomplete digestion), S (100ppm), Cu (5ppm), Fe (100ppm), Mg (100ppm), Ni (10ppm), Zn
(10ppm).
No geophysical or XRF tool was used to determine element concentrations used in the Resource
estimate.
Sample preparation checks for grain size were carried out by the contract laboratory as part of its
internal checks to ensure the grind size of 90% passing 75µm. Greater than 90% of all sizing tests
were within acceptable limits.
Blank samples returned results of 88% of the samples within acceptable limits. Work is ongoing with
the current laboratory to reduce contamination through the crushing and pulverising stages.
Diamond core samples are taken for field duplicates and submitted to the laboratory as separate
batches with overall 22% returned results outside acceptable limits. 52% of the field duplicates
were from diamond quarter core samples. These returned with 53% results outside acceptable
limits. The remaining 48% field duplicates were from diamond half core samples. These returned
with 14% results outside acceptable limits. The majority of the results reported outside acceptable
limits were below 1% Ni, where the lab accuracy is decreased. This is considered to be due to
heterogeneous core samples and accuracy of analysis decreasing as the value approaches the
detection limit. The half core, sampled at 0.1m to 1.1m intervals is considered to be appropriate to
correctly represent the sulphide mineralisation based on the style of dominantly massive and matrix
sulphides, the thickness and consistency of the intersections, the sample methodology and percent
value assay range for the primary elements.
No umpire labs were used. Noprecision checks have been implemented.
Verification
of
sampling
and assaying
Due to the high visibility of mineralisation, significant intersections in diamond core were visually
verified following lithological logging of core samples and after laboratory analysis, by IGO
geologists. Core photos and visual checks from remaining half core samples were randomly
checked.
No drill holes were twinned.
Primarydata were collected usinglaptopcomputers and acQuire database loggingtemplates. The

PAGE 38

==> picture [596 x 83] intentionally omitted <==

Criteria Commentary
data were transferred into main drill database (acQuire Database version 4.5.0.1) with SQL2008
database server backend.
There was no adjustment to assay data. Assay results are received from the laboratory via email in
CSV and PDF files. Original Assay files are archived digitally in the company computer network.
CSV files are imported into the main drill hole database through a database importer protocol.
Location of data points Planned drill collars for underground diamond drill holes are laid out by marking fore-sight pins
drilled in the walls of the mine development by the Company Surveyor using a Viva TS15 Total
Station Theodolite considered to be accurate to 0.002m. The collar dip and azimuth set up is
carried out by the drill contractor using “Azimuth Aligner” North Seeking Gyro with drill rig alignment
accuracy of < 0°Lat RMS True North, and dip accuracy of <0.01°.
The collar position is later surveyed by the Company Surveyor using a Viva TS15 Total Station
Theodolite, locating the exact position of the drill hole collar. The collar coordinates are stored in the
main drill hole database.
Historical downhole surveys were completed using Eastman and Reflex cameras and recent down
hole surveys were taken using an Electronic Reflex Ez-Trac down hole survey tool by the Diamond
drilling contractors. Holes were down hole surveyed with multi-shot surveys (6m intervals) at the
completion of the hole. Single-shot surveys were progressively taken as the hole was drilled to
maintain planned drill direction at 15m, and 30m intervals. Stated accuracy of the Electronic Reflex
Ez-Trac down hole survey tool is 0.35 degrees on azimuth and 0.25 degrees on Dip. All down hole
surveys were stored in the database and de-surveyed as curvilinear projections down the drill hole
trace.
No gyroscopic validation of down hole surveys was undertaken in the drilling from January 2014 to
December 2014, but validation of the surveys with the SMART TEM geophysical probe was
completed. No significant survey problems were identified.
Recent underground drill holes are within mine development with established survey wall stations
located a minimum of 10m to a maximum of 30m intervals along the mine development.
The Resource is estimated in Local Grid (KNO-Grid). It is a non-linear projection of MGA_GDA94,
Zone52 co-ordinates. All collars are captured in Local Grid. North-South Local Grid is -1 degrees
off Magnetic North declination. MGA co-ordinates are generated by automated scripts within the
main drill hole database.
The deposits are located at least 300m below surface. No topographic data are used in the
Resource estimation.
Data spacing and
distribution
Diamond drill spacing at Long, Victor South and McLeay deposits are on a nominal 20m northing
with 10m easting drill spacing with 5m by 5m closer-spaced drilling. Moran is on a nominal 20m
northing with 10m easting drill spacing with some up to 10m by 10m closer-spaced drilling.
The data spacing and distribution are considered to be sufficient to establish the degree of
geological and grade continuity to support the Mineral Resource estimation and classification
applied.
Orientation of data in
relation to geological
structure
Drill holes are generally angled near perpendicular to the Long, Victor South McLeay and Moran ore
bodies.
Underground diamond drill holes collars are generally fanned off sections but kept to near true width
as much as possible.
In Long, Victor South and McLeay ore bodies grade control holes (holes drilled within the ore bodies
and within the ore drives) which were drilled up dip or down dip of the ore bodies were utilised to
determine footwall or hanging wall geometry only and the assay results were not used for 2D
Resource estimation for the Long orebody as they do not represent the entire mineralised width.
Some grade control drill holes (holes drilled within the ore bodies and within the ore drives) were
used to determine footwall or hanging wall geometry and the assay results were used in the 3D
Resource estimation for Victor South, McLeay and Moran ore bodies.
Sample security Core samples are stored on site and delivered by IGO personnel to ALS in Kalgoorlie. Whilst in
storage the samples are kept in a fenced and locked yard on site. ALS has a batch tracking system
that allows IGO staff to track progress of batches of samples from delivery to reporting of results.
Half core is kept for reference and is stored in a fenced and locked yard on site. The location and
photographs of the core samples are stored on a regular basis in the main drill hole database.
Audits or reviews The sampling data are collected and managed by IGO geologists familiar with the local rock-types
and data collection process established by IGO and previously through WMC Resources. The
major rock-types of the area are visually distinct from each other in drill core. There are no major
inconsistencies or errors in the logging of lithology or mineralised zones. The database is audited
annuallybyIGOgeologist and is considered to be of sufficientqualityto carryout Resource

PAGE 39

==> picture [596 x 83] intentionally omitted <==

Criteria Commentary
estimation.
Section 2 Reporting of Exploration Results
Criteria Commentary
Mineral tenement and land
tenure status
All Resources lie within mining tenements own by Independence Group NL, except for M15/1515
which forms a part of a Joint Venture Agreement with St Ives Gold Mining Co. Pty Ltd (SIGM).
The agreement allows Independence Group NL (IGO) to mine and explore for nickel on the leases.
SIGM is paid a royalty based on Ore Recovered under an “Ore Tolling and Concentrate Agreement”
between IGO and BHP Billiton.
Listed below are tenement numbers and expiry dates.
M15/1761 – 05/10/2025
M15/1762 – 05/10/2025
M15/1763 – 05/10/2025
M15/1515 – 23/12/2025
Location 48 - Non Crown Lease
There are no Native Title Claims registered over the leases and no other known impediments.
Exploration done by other
parties
Exploration was initially undertaken by WMC who eventually commissioned the Long Shaft and
Victor decline mine development. The data are of high quality with most of the historic drilling
concentrated in areas that have been mined out.
Geology The Long, McLeay, Moran and Victor South deposits are typical Kambalda-style nickel deposits,
consisting of narrow, steeply-dipping, shallowly south-plunging, ribbon-like accumulations of
massive and semi-massive (with minor disseminated) sulphides. The mineralisation is located at
the base of Archaean komatiitic ultramafic flows at the contact with an underlying tholeiitic basalt
unit. The massive sulphide is overlain by matrix then disseminated mineralisation, with the bulk of
the nickel mineralisation being massive and matrix in nature. The host rocks and associated
contacts have been subjected to lower amphibolite facies metamorphism, structural modification,
and intrusion by multiple felsic to intermediate igneous dykes and sills.
Drill hole Information Drill hole data have been collected from this area since 1978 with over 2,800 drill holes completed.
Reproduction of this number of drill holes, the majority of which have been mined out, is not feasible
for this report. Material drill holes have been reported to the ASX in previous public releases.
Data aggregation methods Exploration results are calculated as the length and density-weighted average to 1% nickel cut-off
grade. Maximum internal waste of 2m may be included however the total nickel composite average
grade must be >1% nickel.
Intercepts are length and density-weighted across the entire width of the mineralised unit.
No metal equivalents have been used.
Relationship between
mineralisation widths and
intercept lengths
All mineralisation intervals are reported as down hole lengths as well as true widths. The plunge and
dip of the mineralisation is generally well understood so estimated likely true widths are calculated
and reported.
Diagrams No new exploration data are announced within this report.
Balanced reporting No new exploration data are announced within this report.
Other substantive
exploration data
Geophysical plates generated from down hole EM or in-drive EM surveys are used for targeting
additional drilling. EM targets are generated as 3D surfaces in a geological modelling program to
target exploration testing.
EM targets are displayed as rectangular shapes on plans to identify the proximal location of
potential nickel mineralisation targets.
Further work Further drilling will test for potential new ore channel positions.

Section 3 Estimation and Reporting of Mineral Resources

Criteria Commentary
Database integrity Primary data were collected using laptop computers and acQuire drill hole database logging
templates. The data were transferred into acQuire Database version 4.5.0.1 with SQL2008

PAGE 40

==> picture [596 x 83] intentionally omitted <==

Criteria Commentary
database server backend.
All validation is completed by IGO geologists on site. Lab assay results are printed out and results
for site blanks and standards are visually checked for acceptable values before the assay data are
loaded from the digital lab files directly into the primary database.
Drill hole collar coordinates, geology and assay data are visually checked by printing out a drill log
with the combined information. The drill hole geology and assay results are also validated using a
3D geological modelling package.
Core photos and visual checks from remaining half core samples were randomly carried out.
Site visits The Competent Person employed by IGO. Reviews on QAQC and sampling procedures are
undertaken quarterly.
Competent Persons from external consultants have not visited site for over 12 months but have
reviewed the estimation process.
Geological interpretation Geological interpretation has a high to moderate confidence as up/down dip and plunge continuity is
well established. Barren porphyry dykes are irregularly spaced and orientated so geological
interpretation is considered to be moderate in confidence. Data used for geological interpretation
consists of diamond drill holes, lithology logging, assay grades and underground mapping of
mineralisation and lithology units. Unmineralised porphyry dykes cutting across the ore bodies are
mapped, logged and modelled into 3D wireframes. These are stamped in the block model as being
waste. No alternative interpretations were investigated.
Lithological control is used to determine the footwall and hanging wall contacts of the ore bodies and
the unmineralised porphyry intrusions.
The ore bodies are off-set by porphyry intrusion and faults. The mineralised komatiite volcanic flows
continue past the off-sets.
Dimensions Long deposit consists of 26 mineralised surfaces and is approximately 2.2km down plunge, 3m thick
and 500m down dip in extent. The surfaces are narrow and ribbon-like accumulates of massive and
semi-massive sulphides and start from approximately 300 metres below surface topography.
McLeay deposit consists of 7 mineralised surfaces and is approximately 600m down plunge, 3m
thick and 160m down dip in extent and starts from approximately 700 metres below surface
topography.
Victor South deposit consists of 3 mineralised surfaces and is approximately 180m down plunge, 4m
thick and 130m down dip in extent and starts from approximately 700 metres below surface
topography.
Moran deposit consists of 3 mineralised surfaces and is approximately 650m down plunge, 5m thick
and 120m down dip in extent and starts from approximately 900 metres below surface topography.
Estimation and modelling
techniques
Surpac v6.3 and v6.6 modelling software was used for the variography and block modelling.
Wireframes for all mineralised domains are interpreted as strings in section or plan orientation to
honour geological contacts and to 1% nickel cut-off grade. Victor South disseminated zone cut-off
grade was 0.6% nickel. The string interpretations are used to generate digital terrain wireframes
(DTMs) which are finally validated using Surpac 3D modelling software and set as solids.
The Long ore body was estimated using a 2D metal accumulation. Due to the narrow nature of most
of the lodes, selectivity of ore is not possible and the entire ore surface will be mined with no internal
selectivity. Therefore the 2D longitudinal modelling approach is based on an accumulation variable
incorporating mineralised domain horizontal width, intercept grade and density. Each sample within
a mineralised domain was assigned a unique code. This coding was used to control compositing
and mineralised domain grades were composited across the entire coded interval resulting in a
single intercept composite. The 2D modelling approach uses Ordinary Kriging to estimate
accumulation and horizontal width variables and the final grade is back calculated.
The Long 2D block estimates were based on a parent block size of 10mYx8mX in the longitudinal
plane. The minimum number of samples used in the estimate was 6 and the maximum was 24. The
search ellipse radius used was 200m. The final Long 3D block model parent cell size was
10mYx4mXx8mZ sub-celling to 1.25mYx0.25mXx0.25mZ. The 2D grade variables were imported
into the 3D “real world’ block model using nearest neighbour assignment. The orientation, block
size and sub-celling regime of the real world block model was designed to provide sufficient volume
resolution for accurate surface geometry representation, mine design, depletion and porphyry
flagging.
Victor South, McLeay and Moran ore bodies were estimated using Ordinary Kriging of 1m downhole
composites. During estimation, a local rotation was applied to both the variogram model and search
ellipsoid. The orientation of this local rotation was controlled by the trend of individual DTM surfaces
modelled to reflect thegeneral trend of each domain. The rotations were interpolated into the
PAGE 41

==> picture [596 x 83] intentionally omitted <==

Criteria Commentary
volume intermediate to and beyond the controlling surfaces for use in the grade interpolation. The
local rotations were used to orient both the variogram model and search neighbourhood. Domain
surfaces which were believed to be similar in nature in regards to mineralisation controls were
combined for the purpose of grade estimation.
The McLeay, Victor South and Moran block 3D models parent cell size was 10mYx4mXx4mZ sub-
celling to 5mYx0.5mXx0.5mZm. The minimum number of samples used in the estimate was 4 and
the maximum was 12. The search ellipse radius used was between 60 and 100m.
Diamond drill spacing at Long, Victor South and McLeay deposits are on a nominal 20m northing
with 10m easting drill spacing with 5m by 5m closer-spaced drilling. Moran is on a nominal 20m
northing with 10m easting drill spacing with some up to 10m by 10m closer-spaced drilling. Block
sizes are considered appropriate for the data spacing and search employed.
Porphyry wireframes were generated as 3D solid models (3DMs). The porphyry wireframes were
used to flag a porphyry code of 999 into the 3D block model. Block nickel grade (ni) was reset to
0.01% Ni and density (density) was reset to 2.7 g/cm
3within the flagged blocks. Fields ni_orig and
density_orig retain the original estimated values prior to porphyry flagging and resetting.
Comparisons with previous estimates show that the grade estimation is robust and does not vary
significantly with new drilling data or depletion. Reconciliations show a positive result with more
metal being produced when compared to the Mineral Resource block models and attributed to
conservative Resource estimation.
Reconciliation is completed monthly using 3D wireframes of surveyed mine development. The
wireframes are imported to the original Resource model and volume and metal calculated using the
Surpac modelling package. The volume and metal are compiled in an Excel spreadsheet and
compared with reconciled volume and metal produced.
No assumptions have been made regarding the recovery of by-products.
No deleterious elements are estimated.
Most samples had measured densities determined using the Archimedes water immersion
technique. Historical samples without measured densities were assigned calculated densities using
the regression curve formula from measured data. Recent samples from ownership by IGO all have
measured bulk density values.
Top-cutting was not applied to the nickel assays as the data do not present any apparent outliers.
Densities were checked against density vs grade regression curves and outliers were replaced with
calculated densities.
Block model validation was undertaken by comparing the volume of the modelled ore and the block
model volume for each ore body. Comparisons were also undertaken on the average grade and
density of the block model and the drill data for each model estimated using the 3D estimation
technique or the accumulated metal variables where the 2D accumulation estimation technique has
been used. The comparisons were undertaken for each ore body in total and also as SWATH plots
for comparing sectional divisions along the length of each ore body.
Monthly mine reconciliation is completed and updated each time the Resource estimate is updated.
Other than for comparative purposes, the reconciliation data are not used in the block model.
Moisture The natural moisture of nickel sulphides is typically very low (<1%) due to the deposit being in fresh
rock. Moisture is not factored into the estimation process.
Cut-off parameters All grade interpolation was constrained within geological contacts and to 1% nickel cut-off grade.
Victor South disseminated zone cut-off grade was 0.6% nickel. This is based on a natural grade
boundary that exists for the two areas and also relates to an economic grade boundary.
Mining factors or
assumptions
The mining method used will be underground mechanised cut and fill, long hole stoping and airleg
stoping. Minimum mining width is in the order of 1.2m to greater than 4.5 metres depending on the
ore body and mining method used in extraction of the ore. Long hole stopes range from 5m to 15m
high stopes. No internal mining dilution assumptions have been made.
Metallurgical factors or
assumptions
All intersections are in fresh rock.
The ore treatment processes are undertaken using the BHP Billiton (BHP_B) nickel concentrator
located within 5km of the mine. This process plant has been in use for over 30 years and is
appropriate for nickel ore sourced from this area.
Environmental factors or
assumptions
Waste is trucked to the surface or used for backfill old stopes.
See Section 4.
Bulk density All recent samples have measured densities determined using the Archimedes water immersion
technique. Historical samples without measured densities were assigned calculated densities using
aregressioncurveformula.

PAGE 42

==> picture [596 x 83] intentionally omitted <==

Criteria Commentary
This water immersion technique accounts for vugs and porosity as it is undertaken on drill core
before crushing and pulverising. As the drill core material is fresh the impact of contained moisture
is very low. The core is sampled based on lithology and different mineralisation zones so bulk
density values will not cross different rock types and mineralisation styles.
Bulk density is estimated into the block model using ordinary kriging. Porphyry intrusions are
assigned a bulk density value of 2.7g/cm
3as this represents the average value of porphyry bulk
density measurements.
Classification Mineralisation classification is conducted primarily on drill data density and mine development
proximity, in conjunction with a review of the understanding of footwall geology and fault controls on
the mineralisation.
Classification of Measured material is only used where ore drives are developed at the top and base
of the ore block. Classification of Indicated material is generally because of closely spaced drilling
and a production history, as well as good confidence in the geological model. Close-spaced drilling
is on a 20mY x 10mX grid for all Long, Victor South and McLeay deposits and 40mY x10mX for
Moran. Mineralisation modelled with a drilling density up to 40m x 40m is classified as Inferred
Resource provided there is a reasonable assumption of grade continuity.
The classification scheme takes into account all of the relevant factors when assigning the Resource
category.
This result appropriately reflects the Competent Person’s view of the deposit.
Audits or reviews No review of the previous Resource estimate was conducted as all only depletion was calculated
in 2016. The variography and estimation parameters used in the estimation for all the deposits have
been generated and validated by Cube Consulting prior to estimation.
Discussion of relative
accuracy/confidence
The block model has block sizes set at approximately half the drill hole spacing to enable robust
volume and grade estimation that is not overly smoothed. The parameters chosen for the estimate
are selected to best represent the drilling data taking into account any declustering effect.
The block model estimate is a global Resource estimate.
Confidence in the Mineral Resource estimate is moderate to high in the mine development areas
and/or drilling with a 20m x 20m pattern or greater. Confidence is moderate to poor in areas with
broader drill spacing. Reconciliation with production data is completed monthly and updated each
time a Mineral Resource estimate is completed.

Section 4 Estimation and Reporting of Ore Reserves

Criteria Commentary
Mineral Resource estimate
for conversion to Ore
Reserves
All Ore Reserves estimated for the Long Operation are a sub-set of the Long Operation Mineral
Resources. No Reserves exist outside of the Mineral Resource base.
Mineral Resources are inclusive of Ore Reserves.
Site visits Rob Dennis as the General Manager of Operations frequently visits the operation and inspects
working areas within the mine.
Study status The Long Operation has a history of being mined by Lightning Nickel since October 2002. The mine
Reserves have been designed based on the current operational practices of the mine. All Ore
Reserves are estimated by constructing three dimensional mine designs and reporting against
updated Mineral Resource block models. After modifying factors are applied, all physicals (tonnes,
grade, metal, development and stoping requirements etc.) are input to a Reserve Evaluation model
for an economical evaluation on a stope-by-stope basis.
Previous mine performance has demonstrated that the current mining methods are technically
achievable and economically viable. Material Modifying Factors have been considered and
compare well to reconciled performance.
Cut-off parameters Cut off values are calculated on the basis of the NSR (Net Smelter Return) calculation. The
Resource model is evaluated against the NSR cut off value and mining areas (stopes and
development) are designed for those areas above the NSR cut off value.
Once designed, the entire mining area / stope is evaluated again, against the NSR cut off value.
Mining factors or
assumptions
Three dimensional mine designs are designed based on known information about orebodies
physical characteristics and the geotechnical environment. Modifying factors such as unplanned
dilution (25% for Long hole stoping and 5% for all other methods) and Reserve recovery (90% for
Jumbo stoping and 95% for all other methods) are applied based on the chosen mining method. In
some cases geotechnical losses are applied where appropriate.

PAGE 43

==> picture [596 x 83] intentionally omitted <==

Criteria Commentary
In certain cases where a mined stope contains both Indicated and Inferred Mineral Resources, the
stope was only designed around the Indicated Resources, however in some cases a small quantity
of Inferred Resources have been captured. Only in cases where the Inferred mineralisation had to
be mined to access Measured or Indicated Resources has it been included in the Reserve
calculation. Any Inferred material mined was converted to a Probable Reserve and had no bearing
on the economic outcome of the Reserves.
No additional infrastructure was required for the mining of the current Reserves.
Metallurgical factors or
assumptions
Independence Group is contractually required to supply all ore to the BHP_B Ni_West Kambalda
Concentrator. All metallurgical recoveries are well defined within this contract and are built into the
above mentioned Reserve Evaluation model.
Environmental Independence Group operates under an environmental management plan, which meets or exceeds
all environmental legislative requirements. Independence Group’s license to operate is in good
standing.
Environmental rehabilitation plans are constructed and progressively acted upon. The costing of the
rehabilitation works is accounted for in the operations Life of Mine model.
Infrastructure The current infrastructure at the Long Operation is adequate for the Ore Reserves statement.
Maintenance costs for current equipment were included in the Reserve economic model.
Costs Capital costs for decline development were included where applicable.
An allowance per ore tonne is also made for ongoing exploration costs.
Operating costs were updated against the previous twelve months actual costs.
Nil allowances were made for the content of deleterious elements as none have been previously
encountered.
A fixed processing charge from BHP_B Nickel West Kambalda Concentrator was applied to all ore
tonnes mined; this includes all transport and shipping from their facilities.
All unit costs are updated from the most recent financial year’s actual costs.
Revenue factors The assumptions made for commodity prices are: Nickel price US$11,766 per tonne, Copper price
US$ 5,173 per tonne and Foreign exchange rate of AUD$1.00 : US$0.74.
These values were selected after reviewing a number of industry recognised price forecasting
leaders, which included Bloomberg and Brook Hunt.
Metal prices were assumed fixed for the life of the project.
Market assessment Longer term market assessments are provided by a number of independent companies such as
Brook Hunt and Bloomberg. Market conditions are considered in part of the long term cost
evaluation.
Economic NPV was not taken into account in the economic review. The estimated life of mine is currently
under five years and so fixed cost and prices were used.
Sensitivity analysis work has been undertaken on variables such as head grade, tonnages, foreign
exchange rate and metal price.
The project is highly sensitivity to the foreign exchange rate (AUD:USD) and nickel metal price.
Social Tenement status is currently in good standing.
Other The Long Operation is a historically seismically active mine. This risk is managed as far as
practically possible through the operations Ground Control Management Plan and the allocation of
appropriate resources.
There are no other foreseeable risks associated with the Long Operation on a sociological or
political assessment.
Classification Ore Reserves are based on geological and mining confidence and categorised as either Proved or
Probable.
This result appropriately reflects the Competent Person’s view of the deposit.
The proportion of Proved Ore Reserves is a subset of the Measured Mineral Resources. All
Probable Ore Reserves have been derived from Indicated or from a small proportion of Inferred
Mineral Resources.

PAGE 44

==> picture [596 x 83] intentionally omitted <==

Criteria Commentary
Audits or reviews An independent audit is periodically undertaken on both the Mineral Resource and Reserve
process. No external audit was undertaken this year.
Discussion of relative
accuracy/confidence
As part of the Ore Reserve estimation process a comparison is undertaken reviewing actual
reconciled extraction versus previous years Ore Estimation and Resource Estimation.
A review of last year’s performance by the Competent Person found that both the Resource and
Reserve estimation processes are conservative estimates.

PAGE 45

==> picture [596 x 83] intentionally omitted <==

APPENDIX D

Jaguar Operation (Bentley) Mineral Resource and Ore Reserve 2016 JORC Code, 2012 Edition – Table 1

Section 1 Sampling Techniques and Data

Criteria Commentary
Sampling techniques Almost all sampling has been core sampling, with the surface resource drilling programs being
mostly ½ NQ core or ¼ HQ core. In these drill programs, the minimum sample length was set at
0.3m, while the maximum sample length was 1.5m. In the underground drilling, NQ2 ½ core
samples were minimum length 0.3m and maximum length 1m. BQ core was submitted as whole
core samples. Only 11 holes were drilled BQ.
Core was cut with an automated core cutter after orientation and mark-up.
Drillhole spacing is described in the sub-section “Data spacing and distribution”.
Zinc and copper mineralisation is visible and zones containing sphalerite and chalcopyrite, whether
in massive sulphide or stringer form, are sampled, along with a 5m buffer zone either side of the
mineralised interval.
Core was cut with an automated core saw after orientation, mark-up, logging and photography. The
same side of the core is always selected for sampling. Analytical techniques are described in the
sub-section “Quality of assay data and laboratory tests”.
Drilling techniques Principally diamond drilling with the exception of several RC precollars. Surface holes were drilled
by Titeline Drilling Pty Ltd and Boart Longyear Pty Ltd. The surface diamond drilling is a mixture of
HQ and NQ core sizes. Core was oriented using an Ace tool or spear. Underground drilling from
2011 was by Sanderson Drilling, Kalgoorlie (now First Drilling) and holes were NQ2 core size. In
2013 BQ core size was tested but later discontinued. Core was oriented using a Reflex ACT II tool
and the orientation line was drawn on core prior to mark-up for cutting and sampling.
Drill sample recovery Core is measured and marked up on angle iron in continuous runs. Core recovery was good to
excellent, being consistently >90%. Measured core lengths and core losses are compared with
driller’s blocks and recorded in the database. The measured lengths are compared with expected
lengths to calculate recovery.
Core was cut with an automated core saw after orientation, mark-up, logging and photography. The
same side of the core is always selected for sampling. Core samples and core duplicate masses
are compared to monitor core cutting bias. Action is taken to stop bias when bias is noted.
Most core is competent and cuts well with minimal loss of fines. No sample bias from core drilling or
core recovery is suspected.
Logging Core was photographed both dry and wet and copies of the digital images stored on the site server.
All core holes are logged via laptop into an acquire database. Geological logging included rocktype,
deformation, structure, alteration, mineralisation, veining and RQD measurements. Logging of
underground core occurs digitally straight into acQuire data entry objects and is loaded into the
acQuire database. Surface drilled holes were logged on paper and subsequently data entered and
loaded into the acQuire database. Underground faces and backs are also mapped and used with
the drilling data to guide geological interpretation. Geological logging is adequate for resource
estimation.
Logging is qualitative and semi-quantitative in nature.
All mineralised zones are logged in detail and the remainder of the hole is logged in slightly less
detail (at distances >30m from economic ore zones, detailed structural alpha and beta angles are
not collected).
Sub-sampling
techniques and
sample preparation
Core was cut with an automated core cutter after orientation and mark-up. Core sample sizes are
discussed in the Sampling Techniques sub-section.
Samples were sent to Genalysis (now Intertek) in Maddington, WA. The sample preparation
method was to dry the core in ovens for at least 2 hrs (105°C), then jaw crush the samples to a
nominal minus 10mm size then Boyd crushed to a nominal minus 2mm. After crushing, the surface
drillhole samples were pulverised in a mixer mill in a single stage mix and grind process (SSMG) to
a nominal 85% passing 75 micron. Any samples that exceeded the 3kg mill limit were rotary split
prior to the pulverising stage. For the underground holes, total sample pulverisation has occurred
for the majority of samples. These techniques are appropriate for base metals samples.

PAGE 46

==> picture [596 x 83] intentionally omitted <==

Criteria Commentary
Coarse crush washes at the crusher stage and quartz washes at the pulverising stage have been
implemented between every sample to combat sample carryover (contamination) during the sample
preparation process. Sieve tests on 10% of the samples are used to measure and monitor the
fraction of pulp passing the 75 micron threshold. Samples through mineralised zones that fail the
sieve test, plus samples either side of the failed test, are recombined with residues and pulverised
again.
Field duplicates in the form of second half- sampling are inserted at a rate of 2 per 100 samples or
better in the underground drilling. The sampling is representative of the material drilled. Precision
is lower this year, with 72% of the field duplicate samples in the 2014-2015 drilling being within +/-
20% relative difference for Zn, 77% for Ag and 66% for Cu. More stringer duplicates were
submitted this year, showing greater variability as expected, with core cutting issues identified and
rectified during the year potentially contributing to some of the poorer precision. Stringer
mineralisation, by nature, is also expected to be less precise in core duplicates.
Sample sizes are appropriate for the material sampled.
Quality of assay data
and laboratory tests
At the exploration stage (surface drilling), assaying for Cu, Pb, Zn, Ag and Fe was by four-acid
digest involving hydrofluoric, nitric, perchloric and hydrochloric acids and analysis by Flame Atomic
Absorption Spectrometry (AAS), while Au was analysed by fire assay with AAS finish. Assay
techniques in the original resource definition program consisted of four-acid digest with AAS finish
for base metals to 0.01% detection limits, while Ag used four-acid digest with an MS finish to 0.2-
1ppm detection limit. The 2014 surface drilling samples were subjected to a four acid digest and
ICP-MS or OES finish. Gold was originally analysed by 50g fire assay to 0.01ppm detection limit,
but in 2014 a 25g fire assay with solvent extraction and AAS finish was used. For the underground
drill samples similar digest methods were used but in Feb 2012 the 50g fire assay was reduced to a
25g charge (or less) due to high sulphide/copper content samples. In Nov 2012 the underground
samples were changed to a finish by ICP-OES method for Cu, Zn, Pb, Ag and Fe, so that As, Sb
and S could also be analysed. Gold analysis remained as AAS. The assay techniques used are
considered appropriate for this type of mineralisation, both are total extraction methods.
No geophysical or XRF results are used in the resource estimate.
Quality control procedures included the insertion of standards, blanks, field duplicates, cross-lab
checks and same laboratory checks. Umpire check-assay samples identified poor precision for Au
(78% within +/-20% RD), due to the need to reduce the catchweight in high sulphide samples,
sometimes to 5g (from 25g) at the primary laboratory, which impacts the repeatability of the Au
assays. The Ag, Cu, Zn and Pb analyses were shown to be reasonably precise (>90% within +/-
20% RD for Ag, Cu, Pb and Zn; 73% within +/-10% RD for Ag, 80% for Cu, 82% for Pb, 91% for Zn)
and only low bias (<5% for Ag, Cu, Pb; and <1% for Zn) was observed for these elements in the
2015-16 drilling. Bias is monitored and addressed throughout the year with re-assaying of samples
when required. IGO is satisfied that the base metal analyses are suitable for resource estimation.
IGO will continue to work with the laboratory to further reduce bias and improve precision.
Verification of
sampling and
assaying
Significant intersections are checked by company personnel to see they meet the known geological
and mineralisation models.
Twin holes were drilled as wedge holes in surface drilling for resource delineation, in 2009. Holes
are fan drilled in the underground and twin holes are not drilled.
Primary data are collected in Excel spreadsheets or using off-line acQuire data entry objects on
Toughbooks. Data are imported directly to the database with importers and have built in validation
rules. Assay data are imported directly from digital assay files and are merged in the database with
sample information. All holes have a hard copy summary with geological and assay information
plotted for review.
From time to time assays will be repeated if they fail company QAQC protocols, however no
adjustments are made to assay data once accepted into the database.
Location of data
points
Surface holes were collar surveyed by independent surveyors and later drill holes by on-site
surveyors. Drillhole collar positions were surveyed using RTK GPS equipment. Dip and Azimuth
readings – good quality surveys using downhole camera shots at about 30m intervals for the initial
exploration program, whilst a gyro survey tool was used for the follow-up resource definition
programs (surface drilling). Underground drilling used a DeviFlex 8377 non-magnetic multi-shot tool
(referencing non-gyro tool) with surveys at 4m intervals, accuracy to +/-0.01° Azimuth (per station)
and +/-0.2° Dip, or more recently a Reflex MEMS referencing gyro with surveys at 3m intervals,
accuracy to +/-0.1° Azimuth (per 100m) and +/-0.2° Dip. Mine workings and underground hole
collars are surveyed by the on-site surveyors using a Leica TCRP1203 instrument to an accuracy of
+/- 3mm, or from November 2013 a Leica TS15P instrument to an accuracy of +/-2mm. A CMS
(Cavity Monitoring System) tool is used for surveying stope voids.
Collar and downhole surveys are considered accurate,which is supported bylocation of mine

PAGE 47

==> picture [596 x 83] intentionally omitted <==

Criteria Commentary
workings in the modelled mineralisation.
All resource work has been conducted on the local mine grid co-ordinate system.
All mineralisation is mined by underground methods so no surface topographic control is required.
Data spacing and
distribution
Surface diamond hole drill coverage at Bentley is on a nominal 50m x 50m pattern with fan drilled
patterns from underground to intersect the mineralisation at a nominal spacing of 20m (northing) x
20m (RL). Minimum hole spacing of ~10m where wedge holes have been drilled, while the
maximum hole spacing does not exceed 110m (Inferred Resource) for the Arnage lens. Indicated
drill spacing is generally less than 40m (northing) x 40m (RL).
The data spacing and distribution are sufficient to establish the geological and grade continuity for
the classifications applied. The wide spaced drilling below 3625mRL, with low intersection angles,
has resulted in a resource classification of Inferred, until greater confidence through drilling at
appropriate spacing and intersection angles can be demonstrated.
Samples were composited to 1m downhole composites with length and density weighting, for grade
estimation.
Orientation of data in
relation to geological
structure
Surface drilling intersects the massive sulphide lenses almost perpendicular to the lens orientation
at Bentley, and at a mean angle of 45-50° to the sulphide veins in the stringer sulphide domain.
09BTDD015, 09BTDD017, 10BTDD017 and 10BTDD018 were drilled down dip and along strike of
mineralisation to test for dolerite bodies and faults that might not have been intersected by drilling
perpendicular to the orebody. (Underground drilling has been undertaken from footwall and
hangingwall positions to enable appropriate drill intercept angles to the mineralisation.
No orientation biased sampling is suspected or has been identified in the data above the 3625mRL.
Below that level, drilling is at very low angles to the mineralisation and is classified as inferred or
unclassified.
Sample security All samples are securely contained and sealed during transport to and from the laboratory in Perth
and site. All transportation is direct with corresponding sample submission forms and consignment
notes travelling with the samples, and which are also recorded on site. The laboratory receives
samples and checks them against dispatch documents. IGO staff are advised of any missing or
additional samples. All storage is secure on site, at the laboratory, and when the samples return to
site after assay.
Audits or reviews Sampling techniques and data collection processes are reviewed regularly by IGO staff. A data
audit was completed by an independent consultancy in January 2015 for all Bentley surface and
underground drillholes, in preparation for the resource estimate. Improvements in data collection
processes as a result of that audit are being introduced. Data validation commenced with the
resource relevant data verified first and other drillhole data to follow.

Section 2 Reporting of Exploration Results

Criteria Commentary
Mineral tenement and
land tenure status
The Bentley deposit is within mining lease M37/1290 (expiry date is 2 February 2031) held 100% by
Independence Jaguar Limited, a wholly owned subsidiary of Independence Group NL (IGO). There
is no native title claim over the area.
The tenure is secure and no known impediments exist. The Bentley mine has been operating since
2011.
Exploration done by
other parties
The Bentley mineralisation was discovered by Jabiru Metals Limited (JML) in 2008. JML was taken
over by IGO in 2011. No exploration is being conducted by other parties in or around the Bentley
mine.
Geology Bentley is a V(H)MS style deposit, occurring as polymetallic (pyrite-sphalerite-chalcopyrite-galena)
massive sulphide mineralisation within a volcano-sedimentary succession. Intrusion by tholeiitic
dolerite has led to disruption of the original massive sulphide lenses into six discrete lenses
(Arnage, Mulsanne, Brooklands, Comet, Flying Spur and Zagato). The footwall to the Arnage
massive sulphide lens consists typically of stringer and disseminated sulphide mineralisation
comprising pyrite, chalcopyrite and minor sphalerite in a rhyolitic unit.
The mineralisation dips steeply (75-80°) to the west (local grid). The largest lens (the Arnage lens)
has a strong southerly plunge.

PAGE 48

==> picture [596 x 83] intentionally omitted <==

Criteria Commentary
Drill hole Information Holes drilled into the Bentley deposit are described in Section 1. Current drilling is from
underground and involves infill grade control drilling known mineralised zones within the resource
envelope to a nominal 20m x 20m hole spacing. Resource conversion drilling is drilled at 40m x
40m hole spacing with resource addition drilling on 80m x 80m hole spacing.
Data
aggregation
methods
There are no exploration results reported for the immediate Bentley mine area.For the resource
drilling, top-cuts applied are described in the “_Estimation and modelling techniques”_in Section 3.
Samples are composited to 1m downhole length using the best fit compositing method. Composite
grades are length and density-weighted prior to grade interpolation.
No metal equivalent values are used.
Relationship between
mineralisation widths
and intercept lengths
There are no exploration results reported for the immediate Bentley mine area. Orientation of
mineralisation with drilling angles has been covered in Section 1.
Diagrams There are no exploration results reported for the immediate Bentley mine area.
Balanced reporting There are no exploration results reported for the immediate Bentley mine area.
Other
substantive
exploration data
There are no exploration results reported for the immediate Bentley mine area.
Further work Drilling will continue to focus on delineating additional resources at depth following the main plunge
of the mineralised system. Exploration drilling will continue in FY2017.

Section 3 Estimation and Reporting of Mineral Resources

Criteria Commentary
Database integrity The parent database for all collar, survey, geology and assay data is a SQL database with the
acQuire software as the front end. This acQuire database has a number of built in fields and
reports to ensure data are entered correctly and obey certain validation rules. Assay data are
imported directly from laboratory files and merged with sampling data. Most other data are
captured digitally and imported directly to the database with few opportunities for keying errors. All
data with the parent Jaguar or OP-Bentley project code are exported to a Microsoft Access
database which is frozen in time as a permanent record of the database used for that resource
estimate.
Data are visually and graphically checked to ensure that there are no outlying errors. Any errors
noted are corrected on an ongoing basis. The database is again checked and corrected for errors
and missing data prior to resource estimation work.
Site visits The competent person, William Stewart, is the Geology Manager at Jaguar operations and is
based on-site on a 9 and 5 FIFO roster. He regularly checks procedures and processes used to
collect data used for Resource estimation.
Geological
interpretation
Confidence in the geological interpretation for Bentley is high, with the mineralisation and
geological setting being simple and well understood, and the drilling and face mapping confirming
the interpretation.
Good geological logging was available to guide modelling of the mineralisation. Face and backs
mapping, face sampling, as well as geological interpretation on section from drilling information,
were used to refine the interpretation for this estimate.
Face and backs mapping in the underground workings has confirmed the interpretation originally
based on drilling data. There is no alternative interpretation.
The mineralisation was domained into massive and stringer domains. Geology was used to define
the massive sulphide domain whereas both geology and cut-off grades were used to define the
stringer domain. Grades for each domain were interpolated independently.
The main factors controlling continuity at Bentley are a series of post-mineralisation dolerite
intrusives which are interpreted to be disrupting the lenses, and a minor east-west fault displacing
the Arnage and Mulsanne lenses by 8m to the east.
Dimensions The Arnage massive sulphide lens, which is the largest of the mineralised lenses at the Bentley
deposit, has a length of 400m along strike (north-south) with a steep, southerly down-plunge length
of 890m and a maximum thickness of 30m. It sits 160m below the surface and extends a vertical

PAGE 49

==> picture [596 x 83] intentionally omitted <==

Criteria Commentary
depth of 1000m. Mulsanne is about 220m along strike, 160m vertical extent, and approximately 3m
thick. Brooklands is about 100m along strike, 230m vertical extent, and approximately 4m thick.
The Comet lens is about 200m along strike, 160m vertical extent and approximately 5m thick. The
Flying Spur lens is about 370m along strike, 300m vertical and averages 2m in thickness. The
Arnage Deeps zone sits adjacent to the Arnage lens, approximately 1000m below surface.
Estimation and
modelling techniques
Statistics and variography were completed using Supervisor v6.5 software. Ordinary Kriging was
used for grade estimation utilising Surpac v6.3.2 software. Block modelling was also completed in
Surpac. Kriging and search parameters were derived from variogram models for each element and
Kriging Neighbourhood Analysis (KNA). Grade estimation was constrained to each of the massive
sulphide and stringer sulphide lens wireframes. Mild top-cuts were used to reduce the impact of
extremely high grades. Search distances were up to 230m for Pass 1 and up to 382m for Pass3.
The minimum number of samples was reduced to 5 for the majority of lenses in Pass 2.
This estimate compares well with previous estimates for the Bentley deposit. Reconciliation of the
undiluted resource model with mine production shows the model tends to underestimate ore
tonnes (-20%) and overestimate grades (between 16-22%). The tonnage and grade difference is
due to dilution during mining.
No assumptions have been made regarding the recovery of by-products.
Zn, Cu, Ag, Au, Fe, Pb, As, Sb, and S have been estimated
Drill intercept spacing is nominally 20m x 20m in the developed portion of the mine and nominally
40m x 40m in deeper portions of the mineralised envelope (below current development). Kriging
Neighbourhood Analysis was used to determine modelling parameters. The parent block size was
set at 15m Y x 5mX x 15mZ and grades were interpolated into these blocks. Parent block grades
are assigned to sub-blocks within the parent block and the constraining wireframe. Sub-celling is
used for better volume resolution. Search dimensions and orientations were set from variography.
No modelling of selective mining units has taken place.
No correlation between variables has been assumed in the grade interpolation stage. Each
variable has been interpolated independently.
The block model cells were coded according to which style of mineralisation and which wireframe
they were within. Corresponding composite sample files for each wireframe were used for grade
interpolation into block model cells inside each of the wireframe domains. Each wireframe was
used as a hard boundary during estimation.
Top-cut grades were determined from a review of the composite sample data statistics, histograms
and log-probability plots. Massive sulphide domain top-cuts are applied to Cu (14%), Pb (10%), Ag
(1200ppm), Au (12ppm), As (2500ppm). Stringer sulphide domain top-cuts Pb (1.7%), Zn (13%),
Ag (400ppm), Au (2.5ppm), As (14000ppm), Sb (300ppm). Azure lens top-cuts are applied for Cu
(15%), Zn (18%), Ag (130ppm), Au (0.75ppm).
The block model is checked visually first, in Surpac graphics, and compared with drilling data, then
checked on a section, bench and lens basis by comparing composite sample grades with block
model grades in swath plots. Life of mine reconciliation is completed each time the resource
estimate is updated. No reconciliation factors are applied to the resource estimate.
Moisture No samples were tested for moisture content. All sampled core was from well below the oxidised
rock profile. The samples were considered impermeable and moisture content is expected to be
well below 1%. On this basis the tonnage estimate is considered to have been estimated with
natural moisture.
Cut-off parameters Resource block cut-off grade for massive sulphide domain of $96/t Net Smelter Return (NSR) was
employed. Stringer sulphide domain employed a resource cut-off grade of $60/t NSR. Both cut-
offs are derived from estimated future mining and processing costs applied to fully costed massive
sulphide domain and incremental stringer domains.
Mining factors or
assumptions
Economic grade and mineralisation continuity were taken into account with some areas on the
periphery of the ore body excluded from the resource estimate.
Metallurgical factors or
assumptions
No metallurgical factors or assumptions have been made; the mill on site is a flotation plant which
generates two concentrate types, and has treated the ore proficiently and successfully for over 5
years.
Environmental factors
or assumptions
No environmental factors or assumptions have been made; the waste dump and tailings storage
facilities are well established with approval from the Department of Mines and Petroleum (DMP).
Bulk density JML/IGO performed density test work on almost all core samples that were submitted to the
laboratoryfor assay. All densitymeasurements have been determined usingthe simple water

PAGE 50

==> picture [596 x 83] intentionally omitted <==

Criteria Commentary
immersion technique, on uncoated core and for the entire sample interval. Core was uncoated
because it was impervious. The assays for Cu, Pb, Zn and Fe were combined and compared with
the measured densities and regression curves determined for massive sulphide and stringer
domains. Outliers (outside a nominal +/-10% from the regression curves) were removed from the
dataset. A calculated density, using the appropriate regression formula, was assigned to those
samples without their own correct density measurement. Density was interpolated into the block
model using Ordinary Kriging. Density was also used to weight each of the sample composite
grades used in grade estimation.
Classification Kriging efficiency (KE), slope of regression (RS), drill hole spacing, geological continuity, and mine
development was used for 2016 classification.

Measured resources: KE >0.6, RS >0.75, drill spacing < 20m along strike and down dip,
high confidence of geological continuity, areas with lateral mine development.

Indicated resources: KE >0.3, RS >0.5, drill spacing < 40m along strike and down dip,
high to moderate confidence of geological continuity.

Inferred resources: KE <0.3, RS <0.5, drill spacing > 40m along strike and down dip,
moderate to low confidence of geological continuity
Unclassified resources: one or few drill intercepts with very low confidence of geological continuity.
Audits or reviews No audits were conducted for 2016 resource estimate. Optiro Pty Ltd assisted and mentored the
2016 resource estimate for Bentley with supporting documentation complied in the 2016 Mineral
Resource report.
Discussion of relative
accuracy/confidence
Confidence of the Mineral Resource estimate is high within the measured resource envelope. High
to moderate confidence of the Mineral Resource within the Indicated Resource envelope. Moderate
to low confidence within the Inferred Resource envelope.
Factors considered in classifying the resource estimate were estimators KE, RS, development
exposures, drill spacing, quantity of numbers of drillholes and samples for good grade estimation,
and mineralisation intersection angles. Sample quality was excellent and did not factor into the
classification.
The estimate is a local estimate and is suitable for mine planning within areas classified as
measured and indicated resources.
Reconciliation with production data takes place each time a new Mineral Resource estimate is
completed. Reconciliation for the life of mine to 29 February 2016 was carried out in March 2016
and commented on in the sub-section on “Estimation and Modelling Techniques”, above.
Resource
Model
number
BT_RSC_2016_06

PAGE 51

==> picture [596 x 83] intentionally omitted <==

Jaguar Operation (Teutonic Bore) Mineral Resources and Ore Reserves 2016 Section 1 Sampling Techniques and Data

Criteria Commentary
Sampling techniques Almost all sampling used in this estimate has been core sampling. Mostly sawn half-core samples
of NQ or quarter-core samples of HQ core, varying in length up to 1m and adjusted to geological
boundaries, for the JML drilling. Historic surface holes were filleted with about 1/3 core diameter
used as the sample, up to 2m sample lengths but usually 1.5m. Poorly mineralised zones were chip
sampled at about 15cm intervals bulked over 1.5-3m lengths. Sample quality in the JML holes is
considered very good and is considered moderate in the historic holes. Underground holes were
sampled as sawn half-core BQ core in strong mineralisation and not sampled in weak
mineralisation. Drillhole spacing is described in the sub-section “Data spacing and distribution”.
Zinc and copper mineralisation is visible and zones containing sphalerite and chalcopyrite, whether
in massive sulphide or stringer form, are sampled by JML, along with a 5m buffer zone either side of
the mineralised interval.
Core was cut with an automated core saw or a diamond core saw after orientation, mark-up, logging
and photography. The same side of the core is always selected for sampling. Analytical techniques
are described in the sub-section “Quality of assay data and laboratory tests”.
Drilling techniques Percussion drilling, diamond drilling - some with percussion pre-collars. The surface diamond holes
are HQ and NQ core sizes. The underground holes are BQ core size. Core from Jabiru Metals
Limited (JML) work was oriented using a Reflex Ace Core Orientation tool. Few percussion drilling
holes were used in the 2009 estimate.
Drill sample recovery Core is measured and marked up on angle iron in continuous runs. For JML holes, core recovery
was good to excellent, except where drillholes intersected old underground workings. Measured
core lengths and core losses are compared with driller’s blocks and recorded in the database. The
measured lengths are compared with expected lengths to calculate recovery.
JML core was cut with an automated core saw after orientation, mark-up, logging and photography.
The same side of the core was always selected for sampling. Core was saw cut but no information
was available for the measures taken to maximise sample recovery and ensure representative
nature of the samples in the historic drilling.
Most core is competent and cuts well with minimal loss of fines. No sample bias is suspected.
Logging JML core was photographed both dry and wet and copies of the digital images stored on the Jaguar
minesite server. All core holes are logged. Geological logging included rocktype, deformation,
structure, alteration, mineralisation, veining and RQD measurements. Surface drilled holes were
logged on paper and subsequently data entered and loaded into the acQuire database.
Underground holes were logged but not photographed by Australian Selection. Geological logging
is adequate for Resource estimation.
Logging is qualitative and semi-quantitative in nature.
All mineralised zones are logged in detail and the remainder of the hole is logged in slightly less
detail.
Sub-sampling
techniques
and sample preparation
JML core was cut with a diamond core saw or Almonte automated core saw after orientation and
mark-up. Core sample sizes are discussed in the_Sampling Techniques_sub-section of Section 1.
All samples were oven dried, crushed and pulverised. Sample preparation techniques at Genalysis
for the JML samples were industry standard. Sample preparation for the historic holes was industry
standard for those days but would be considered of moderate quality today.
Quartz washes at the pulverising stage were implemented between every sample to combat sample
carryover (contamination) during the sample preparation process.
Field duplicates in the form of second quarter-core samples were submitted from the JML drilling.
The results showed there is a significant difference in assays between the two quarters. Cu, Zn and
Ag show poor reproducibility with numerous samples outside the 20% relative difference lines (32%
of Cu analyses, 50% of Zn analyses, and 55% of Ag analyses). These results are indicating that
either there is a large sampling error or there is a large inherent nugget effect. The dataset was
small (40) and further data are needed.
Sample sizes are appropriate for the material sampled.

PAGE 52

==> picture [596 x 83] intentionally omitted <==

Criteria Commentary
Quality of assay data and
laboratory tests
All JML samples were crushed and pulverised, then a subsample digested using a four-acid digest
(digest A or AX) with an AAS finish, at Genalysis. Detection limits for the A digest were 1ppm for
Cu, Zn, Ag, and 5ppm for Pb. Detection limits for the AX digest were 0.01% for Cu, Zn, Pb and
5ppm for Ag. Historic sampling (surface holes) was assayed by Australian Selection in house using
a 3 acid digest with AAS finish (Cu, Pb. Zn to 0.01% and Ag to 0.2, 2 or 10ppm.). Underground
samples were prepared on site and assayed by Analabs in Kalgoorlie using an_aqua regia_digest.
The majority of the assay techniques are for total digestion of the sulphides and are considered
appropriate for this type of mineralisation. The_aqua regia_digest is a partial digest and those
assays (underground drilling) may underestimate true grades of the samples.
No geophysical or XRF results are used in the Resource estimate.
Quality control procedures included the insertion of standards, blanks, field duplicates, cross-lab
checks and same laboratory checks for the JML work. Standards and blanks were inserted into the
sample sequence in the 2005-2007 campaigns at the rate of about 1 in 40, increasing to 1 in 20 for
standards and decreasing to 1 in 50 for blanks in 2008. Check assays on pulps were also carried
out, both using the primary lab Genalysis and another lab Ultra Trace. Standards and check assays
showed reasonable levels of accuracy and precision in the JML samples. Blanks showed some
contamination was occurring and procedures were changed to include barren flushes between
samples. Duplicate sampling showed large variation of grades between the two quarter-core
samples for the same interval, up to 40% relative difference for Cu and Zn. The analytical technique
for Ag in 2008 was not appropriate for the stringer mineralisation grade range and samples were re-
analysed using a more suitable technique.
Australian Selection assayed 10% of samples in duplicate and if the assays varied by more than 5%
the entire batch was re-assayed. Quality control procedures were adequate for the different eras
but new work will need to have improved QC applied.
Verification of sampling
and assaying
Significant intersections are checked by company personnel to see they meet the known geological
and mineralisation models.
No twin holes were drilled for any of the drilling programs.
Primary data for JML were collected in Excel spreadsheets or using off-line acQuire data entry
objects on Toughbooks. Data were imported directly to the database with importers and have built
in validation rules. Assay data were imported directly from digital assay files and were merged in
the database with sample information. All holes had a hard copy summary plotted for review with
geological and assay information.
Historic data were collected on paper logs and hard copy printouts. In 2006 the historic data were
compiled by JML, validated and imported to the acQuire database.
No adjustments are made to assay data once accepted into the database.
Location of data points All recent drillhole collar positions were surveyed by licensed or company surveyors using either
GPS or dGPS. Original Australian Selection surface holes were measured by tape from the nearest
grid peg and are considered to have +/-3m level of accuracy. Underground holes have been
measured from plans and sections and are considered to be to a +/-5m level of accuracy. Dip and
Azimuth readings – generally good quality surveys using Eastman down hole camera shots at 40m
intervals down the historic surface holes, and gyro surveys for the recent surface holes to 2007.
JML holes in 2008 were downhole surveyed at 20m intervals using a Reflex EZ-Trac digital
downhole camera. Underground holes have been measured from plans and sections and only have
collar azimuth and dip.
Collar and downhole surveys are considered good to moderate accuracy.
Mined volume at Teutonic Bore has been removed from the Resource estimate using void
wireframes based on historical plans and sections and the surface topography from
photogrammetry. Void wireframes are considered accurate to about +/-3m and have been
confirmed by intersections during JML’s drilling.
All Resource work has been conducted on the local mine grid.
Topographic control was from photogrammetry following aerial photography flown in October 2008.
Five co-ordinates were used to transform photo centres and observations to the ground co-ordinate
system (GDA94/51). The registered photography was then transformed to the Teutonic Bore local
grid for use in modelling.
Data spacing and
distribution
Diamond drill coverage at Teutonic Bore is on a nominal 20 x 20m (massive) to 40 x 40m (stringer)
pattern with stringer mineralisation closer to the massive sulphide having closer spaced drilling.
Twin holes have not been drilled.

PAGE 53

==> picture [596 x 83] intentionally omitted <==

Criteria Commentary
The data spacing and distribution is sufficient to establish geological and grade continuity
appropriate for the Mineral Resource estimation procedure and classification applied (Indicated) in
the massive sulphide and Indicated or Inferred classification in the stringer mineralisation.
Samples were composited to 1m length with an acceptable minimum of 0.6m, using length and
density-weighting for Cu, Zn, Pb and length-weighting for Ag and density.
Orientation
of
data
in
relation
to
geological
structure
Surface drilling intersects the massive sulphide lenses almost perpendicular to the lens orientation.
Holes drilled in 2008 for the stringer zone were drilled from the east side of the pit to avoid the
underground workings. The stringer zone is intersected at moderate to low angles to the
mineralisation. The underground fan drilling mostly intersects the massive sulphide zone at a
variety of angles. Two of the underground holes were removed prior to the estimate due to
inappropriate dip orientations.
No orientation biased sampling was used in the Resource estimate.
Sample security All JML samples are securely contained and sealed during transport to and from the laboratory in
Perth and site. All transportation is direct with corresponding sample submission forms and
consignment notes travelling with the samples which are also recorded at site. The laboratory
receives samples and checks them against dispatch documents. JML staff are advised of any
missing or additional samples. All storage is secure on site, at the laboratory, and when the
samples return to site after assay.
No information on sample security is available for the historic drilling.
Audits or reviews Sampling techniques and data collection processes are reviewed regularly by IGO staff. No
external review has been conducted.
A program of data compilation and validation was completed in 2006 for all historic drillholes in
preparation for Resource estimation.
Section 2 Reporting of Exploration Results
Criteria Commentary
Mineral tenement and land
tenure status
Teutonic Bore is located within mining lease M37/44. There are no Native Title Claims registered
over the lease and no other known impediments. Heritage sites registered at the Department of
Aboriginal Affairs (DAA) surround the area but the immediate pit area does not encroach on these.
The tenure is secure and expires on 17 December 2026. Other than the heritage sites mentioned
above there are no known impediments to obtaining a licence to operate in the area.
Exploration done by other
parties
JML acquired the Teutonic Bore mining leases from Mount Isa Mines (MIM) in August 1997. No
exploration is being conducted by other parties in or around the Teutonic Bore deposit.
Geology Teutonic Bore is a V(H)MS style deposit, occurring as a polymetallic (pyrite-sphalerite-chalcopyrite)
massive sulphide lens within a volcano-sedimentary succession. An extensive feeder zone below
the massive sulphide lens (in the footwall) has produced a large sulphide stringer zone.
The mineralisation dips steeply (70-80°) to the west (local grid) and plunges gently (20°) to the
north.
Drill hole Information Holes drilled into the Teutonic Bore deposit are described in Section 1. No new drilling is being
reported here.
A summary of drillholes is not considered applicable in this instance as no new drilling is being
reported.
Data aggregation methods There are no exploration results reported for the immediate Teutonic Bore mine area.
Relationship
between
mineralisation widths and
intercept lengths
There are no exploration results reported for the immediate Teutonic Bore mine area. Orientation of
mineralisation with drilling angles has been covered in Section 1.
Diagrams There are no exploration results reported for the immediate Teutonic Bore mine area.
Balanced reporting There are no exploration results reported for the immediate Teutonic Bore mine area.
Other
substantive
exploration data
There are no exploration results reported for the immediate Teutonic Bore mine area.
Further work Further drilling to better define the stringer mineralisation may follow if preliminary mine planning
studies show positive results.

PAGE 54

==> picture [596 x 83] intentionally omitted <==

Section 3 Estimation and Reporting of Mineral Resources

Criteria Commentary
Database integrity The parent database for all collar, survey, geology and assay data is a SQL database with the
acQuire software as the front end. This acQuire database has a number of built in fields and reports
to ensure data are entered correctly and obey certain validation rules. Assay data are imported
directly from laboratory files and merged with sampling data. Most other data are captured digitally
and imported directly to the database with few opportunities for keying errors. All data with the
parent Jaguar project code are exported to a Microsoft Access database which is frozen in time as a
permanent record of the database used for that Resource estimate.
Data are visually and graphically checked to ensure that there are no outlying errors. Any errors
noted are corrected on an ongoing basis. The database is again checked and corrected for errors
and missing data prior to Resource estimation work.
Site visits The competent person, Will Stewart, is the Geology Manager at Jaguar operations and is based on-
site on a 9 and 5 FIFO roster. He regularly checks procedures and processes used to collect data
used for Resource estimation.
Geological interpretation Confidence is high for the geological interpretation of the massive sulphide and is moderate for the
stringer zone. Vein orientation is not well understood in the stringer zone and drilling density
sparser, with mineralisation boundaries defined by cut-off grade rather than geologically defined
units. As the cut-off grade increases, continuity of mineralised stringer zones reduces.
Good geological cross-sectional interpretations were available to guide modelling of the
mineralisation. No underground mapping was available to aid interpretation.
There have been no alternative interpretations of the mineralisation model, with the Teutonic Bore
massive sulphide deposit being well regarded as a V(H)MS style orebody. It is relatively planar and
simple in geometry.
The stringer interpretation is based on assay cut-offs and could be interpreted slightly differently;
however this is not expected to have a major impact on the stringer Resource estimate.
Should additional sampling be added to the database for the historic drilling, then this could impact
on the stringer Resource estimate.
The mineralisation was domained into massive and stringer domains. Geology was used to define
the massive sulphide domain whereas both geology and cut-off grades were used to define the
stringer domain. Grades for each domain were interpolated independently.
See above. There are no known intrusives or significant faults disrupting the mineralisation at
Teutonic Bore.
Dimensions The massive sulphide (pre-mining) is a tabular body about 250m long and 17m thick (true width),
extending down dip for about 190m. The remnant mineralisation is located 240m below surface,
below the previously stoped mineralisation, as well as in fingers to the south and north ends of the
open pit and stoped areas. The stringer mineralisation occurs in the footwall to the massive
sulphide zone over a strike length of about 245m. It is up to 50m thick and extends down dip about
200m.
Estimation and modelling
techniques
GeoAccess software was used for statistical analysis of the composites. Surpac software v6.1 was
used for the variography and block modelling. Ordinary kriging (with top-cuts) was used for grade
interpolation, based on the variography and validation of the search orientations in Surpac. Block
cells had been coded with the wireframe name and only composite samples from that zone were
used to interpolate grades into that zone. All grade interpolation was constrained to within the
massive and stringer sulphide wireframes. The massive sulphide was domained into a fresh rock
and a transitional rock domain for statistics and variography. Both these domains were further
subdivided for search ellipse orientation changes due to changes in their geometry in the south end.
The largest of the stringer zones was used to establish kriging parameters and these were applied
to the other stringer zones with an appropriate search ellipse orientation change. Search distances
were generally 150m along the major axis, up to 140m in the semi-major direction and up to 40m in
the minor direction (18m in the massive zone).
Ordinary kriging is considered an appropriate estimation technique for this style of deposit.
Both the massive and stringer estimates compare well with previous estimates. The Mineral
Resource estimate is undiluted. It does not take into account any historic production data, other
than to have the previous workings model used to deplete the Resource estimate. Block model
cells were coded as mined if within the open pit or void wireframes and were excluded from the
estimate. The void wireframes were expanded slightly to remove any skins of mineralisation that
might be left behind through the coding of the cells within the wireframes.

PAGE 55

==> picture [596 x 83] intentionally omitted <==

Criteria Commentary
No assumptions have been made regarding the recovery of by-products.
Economic minerals estimated are Zn, Cu, Ag and Pb (sub-economic). Density was also estimated.
Insufficient assay data for Au, Fe and S were available for grade interpolation.
There are no known deleterious elements in the Teutonic Bore mineralisation.
The block model had extents of 700m in Y, 500m in X and 410m in the Z direction. The parent cell
size was 5 x 5 x 5m sub-celling to 1.25 x 1.25 x 1.25m. The parent cell size was a compromise
between close-spaced drilling in the massive sulphide and wider-spaced drilling in the stringer zone.
Sub-cell size was determined more for an open-cut mining scenario rather than underground, and
could be reduced further for better resolution in an underground mining scenario.
No modelling of selective mining units has taken place.
No correlation between variables has been assumed in the grade interpolation stage. Each variable
has been interpolated with its own kriging parameters based on variography.
The block model cells were coded according to which style of mineralisation and which wireframe
they were within. Corresponding composite sample files for each wireframe were used for grade
interpolation into block model cells inside each of the wireframe domains. Each wireframe was used
as a hard boundary during estimation.
Top-cut grades for massive and stringer mineralisation were defined using log-probability plots and
identifying the inflexion point indicating deviation from log-normality. Top-cut grades applied were:
Massive sulphide fresh rock 18% Cu, 3.8% Pb, 880ppm for Ag and no top-cut for Zn; massive
sulphide transitional rock 17% Cu, 33% Zn, 3.6% Pb and 440ppm Ag; Stringer sulphide 7% Cu,
12% Zn, 2% Pb and 350ppm Ag.
The block model is checked visually first, in Surpac graphics, and compared with drilling data, then
checked on a section, bench and lens basis by comparing composite sample grades with block
model grades in swath plots. For the massive sulphide the grade comparison is adequate and for
the stringer the grade comparison is very close.
Moisture Tonnages have been estimated using densities that contained natural moisture. The natural
moisture of the Teutonic Bore massive sulphides is typically very low (<1%).
Cut-off parameters No cut-off grade was applied to the massive sulphide as the mineralisation was defined geologically.
A modelling cut-off grade of 0.5% Cu was applied to the stringer mineralisation. A block cut-off
grade of 0.7% Cu was applied to the stringer zone for Resource estimation and was based on
marginal mining and processing costs and recoveries for the Jaguar Operation, plus some
allowance for changes in metal price and NSR assumptions in the Ore Reserve estimation stages.
Mining factors or
assumptions
No mining method, minimum mining width, dilution or other mining factors have been assumed in
the Mineral Resource estimate. The mine was in production from 1980-1984 with a conventional
flotation processing plant, where mostly massive sulphide ore was processed.
The stringer mineralisation would be amenable to open cut mining methods or underground sub-
level caving.
Metallurgical factors or
assumptions
No metallurgical factors or assumptions have been made; the Jaguar mill on site is a flotation plant
which generates two concentrate types, and has treated Jaguar and Bentley massive sulphide and
stringer ore proficiently over numerous years. There is no known reason why Teutonic Bore ore
could not be successfully treated on site, given the production history of the old Teutonic Bore mine.
Environmental factors or
assumptions
No environmental factors or assumptions have been made. The waste dump and tailings storage
facilities for the nearby Bentley mine are well established with approval from the Department of
Mines and Petroleum (DMP). There are however, areas surrounding the old open pit that have
been rehabilitated and signed off by the Department of Mining and Petroleum (DMP), and if
IGO/JML were to re-start mining there could be significant environmental liability issues to deal with
for past disturbances and dumping.
Any renewed mining activities would require a new mining proposal and works approval which
require DMP and Department of Environment Regulation (DER) approvals respectively.
Bulk density JML performed density testwork on almost all core samples that were submitted to the laboratory for
assay. Historic density data were restored during the 2006 data compilation stage. Most samples
had measured densities determined using the simple water immersion technique. Densities were
checked against density vs grade regression curves and outliers were replaced with calculated
densities or in the case of the stringer mineralisation, a nominal density of 2.95g/cm
3. The density
dataset is quite large and in good condition. Densities were used for compositing Cu, Zn and Pb
grades and were interpolated into the block model in the same way as a grade.

PAGE 56

==> picture [596 x 83] intentionally omitted <==

Criteria Commentary
Classification The massive sulphide mineralisation was classified as Indicated because it has closely spaced
drilling and a production history, as well as good confidence in the geological model. The stringer
mineralisation was classified as Indicated where drill spacing was about 20x20m and Inferred where
drill spacing was about 40x40m. Stringer mineralisation also had some historic holes drilled through
it that were not sampled and these areas, if not sampled with JML drilling, were classified as
Inferred. Mineralisation modelled but with drilling density sparser than 40x40m was not classified as
Resource.
Input data are partly historic (of reasonable quality) and more recent data are of excellent quality.
There is high confidence in the massive sulphide mineralisation interpretation and moderate
confidence in the stringer interpretation. Confidence in grade and tonnage estimates where the
drilling is at a >40m spacing is low, and is reflected in the classification. More drilling into the
stringer zone along with sampling of previously unsampled intervals in the historic drilling will
improve the interpretation, confidence and Resource estimate for the stringer zone.
The classification of the Mineral Resource reflects the Competent Person’s view of the confidence in
the estimate.
Audits or reviews A review of the Resource estimate was conducted by Runge Limited in 2009 which identified no
significant issues other than some aspects of the variography, derivation of kriging parameters and
search neighbourhoods. Subsequent review (by Wildfire Resources Pty Ltd and JML staff) of these
aspects concluded that there was no material issue that required action.
Discussion of relative
accuracy/confidence
Confidence in the Mineral Resource estimate for massive sulphide is high in the areas with mine
development and/or drilling with a 20m x 20m pattern. Confidence is moderate to low in the stringer
mineralisation. Factors considered in classifying the Resource estimate were drill spacing,
confidence in defining mineralisation boundaries along strike and down plunge, sufficient (or not)
numbers of drillholes and samples for good grade estimation, sampling and assaying quality, and
mineralisation intersection angles. Assay quality was varied with recent JML sampling and assaying
considered more reliable than historic sampling and assaying. The main factors that could affect the
accuracy of the estimate, in particular the stringer Resource estimate, is the historic assaying
methods, the selective sampling of intervals with some of the low grade intervals not sampled, and
drillhole spacing.
The estimate is a global estimate and is suitable for long term mine planning.
The Resource estimate is a remnant Resource estimate and as such has no production data
available for comparison.
Further work Historic core that has not been sampled and is in suitable condition may be sampled to improve the
detail of the Resource estimate prior to mining. Similarly JML core that was not sampled but lies
within the mineralised envelope may be sent for assaying. Core trays for historic drilling have been
rehabilitated and are in a suitable condition for longer term storage.
Preliminary mine planning studies into the viability of the Teutonic Bore project is the next step.
Other testwork would be completed as part of a Pre-feasibility study if the preliminary mine planning
studies meet the company’s expectations.
Resource Model number TB_RSC_2009_03

Section 4 Estimation and Reporting of Ore Reserves

Criteria Commentary
Mineral Resource estimate
for conversion to Ore
Reserves
All Ore Reserves estimated for the Jaguar Operation are a sub-set of the Bentley Mineral
Resources. No reserves exist outside of the Mineral Resource base.
Mineral Resources are inclusive of Ore Reserves.
Site visits The competent person has not visited the site. The competent person is comfortable relying on
reports from other independent consultants, and other Entech staff, who have visited site and other
operations in the area respectively.
Study status The mine Reserves have been designed based on the current operational practices of the mine. All
Ore Reserves are estimated by construction of three dimensional mine designs and reported
against updated Mineral Resource block models. After modifying factors are applied, all physicals
(tonnes, grade, metal, development and stoping requirements etc.) are input to a cost model where
each stope is economically evaluated and the total reserve is evaluated to assess its economic
viability.

PAGE 57

==> picture [596 x 83] intentionally omitted <==

Criteria Commentary
Previous mine performance has demonstrated that the current mining methods are technically
achievable and economically viable. The modifying factors are based on historical data utilising a
similar mining method.
Cut-off parameters Cut off values are calculated on the basis of the NSR (Net Smelter Return) calculation. The
Resource model is evaluated against the NSR cut off value and mining areas (stopes and
development) are designed for those areas above the NSR cut off value. All designed stopes and
development are then assessed individually to verify that they are above the NSR cut-off and can be
economically mined. For longhole stoping, the mill feed NSR cut-off used is $134/t with a marginal
cut-off NSR value of $80 /t. For development a $57/t cut-off NSR value has been used. Airleg
stoping is an incremental mining method and a $161/t cut-off NSR value has been used.
Mining factors or
assumptions
Three dimensional mine designs are designed based on known information about the orebodies
physical characteristics and the geotechnical environment. The designs are consistent with what
has been in practice on site. Modifying factors such as unplanned dilution (10-20% for Long hole
stoping depending on stope size) and mining recovery (90-95% for stoping, depending on mining
method and stope size) are applied based on the chosen mining method. In some cases, additional
recovery losses have been applied where pillars are required. These modifying factors are based
on recent historical data. Minimum mining widths 1.5 m and 1 m were used for longhole stopes and
airleg stopes respectively. Current infrastructure supports mining of the Reserve. Any additional
capital required has been included in the cost model.
In cases where Inferred Mineral Resources are present in a design, this material has been assigned
as waste and re-evaluated to ensure it is economically viable.
Metallurgical factors or
assumptions
Ore from Bentley is processed at the Jaguar processing facilities. The process and recovery of
contained metal is well understood and reasonably consistent in performance. The following
metallurgical recovery factors have been used: 85.0% Cu recovery into Cu concentrate, 45.0% Ag
recovery into Cu concentrate, 32.0% Au recovery into Cu concentrate, 86.0% Zn recovery into Zn
concentrate and 16.0% Ag recovery into the Zn concentrate.
Environmental Independence Group operates under an environmental management plan, which meets or exceeds
all environmental legislative requirements. Independence Group’s license to operate is in good
standing. Environmental rehabilitation plans are constructed and progressively acted upon. The
costing of the rehabilitation works is accounted for in the operations Reserve model at a value of
$11,000,000 AUD.
Infrastructure The current infrastructure at the Jaguar Operation is adequate for the extraction of the Bentley
underground Reserves. Maintenance costs for current equipment were included in the Reserve
economic model.
Costs Capital costs for decline development and accesses were included in the financial evaluation. An
allowance per ore tonne is also made for ongoing exploration costs. Operating costs were modelled
on recent actual mining costs from site. Concentrate payables, which includes accounting for any
deleterious elements, has been calculated and used within the NSR evaluation process.
Revenue factors The assumptions made for commodity prices are: Copper price US$ 5,540 per tonne, Zinc price
US$2,020 per tonne, Silver price US$17.00 per troy ounce, Gold price US$1,200 per troy ounce and
Foreign exchange rate of AU$1.00 : US$0.75.
These prices are based on the 50
thpercentile of the Consensus Economics commodity price
assumptions as well as the 50
thpercentile of Bloomberg foreign exchange rates (US$ to AU$).
During the calculation of Reserves, the Metal prices and exchange rates were assumed fixed for the
life of the project.
Market assessment The volume and high quality of concentrate produced is expected to continue to attract a ready
market domestically and internationally.
Economic The reserve shows a robust NPV. The confidence in the inputs is consistent with the assigned
Proved and Probable classifications of the Ore Reserve.
Sensitivity analysis work has been undertaken on variables such as mining costs, processing costs,
foreign exchange rate and metal price, with the NPV proving particularly sensitive to changes in the
exchange rate.
Social Tenement status is currently in good standing.
Other There are no other foreseeable risks associated with the Jaguar Operation on a sociological or
political assessment.
Classification Ore Reserves are based on geological and mining confidence and categorised as either Proved or
Probable.

PAGE 58

==> picture [596 x 83] intentionally omitted <==

Criteria Commentary
This result appropriately reflects the Competent Person’s view of the deposit.
The proportion of Proved Ore Reserves is a subset of the Measured Mineral Resources. All
Probable Ore Reserves have been derived from Indicated Mineral Resources.
Audits or reviews The Ore Reserve has been peer reviewed internally and is in line with current industry standards.
Discussion of relative
accuracy/confidence
The Ore Reserve is based on recent operational performance and costs at the mine; hence
confidence in the resulting figures is high.
Confidence in the mine design and schedule are high as mining rates and modifying factors are
based on actual site performance. Mine design is consistent with what has been effective
previously.

PAGE 59

==> picture [596 x 83] intentionally omitted <==

APPENDIX E

Stockman Mineral Resources and Ore Reserves 2016

JORC Code, 2012 Edition – Table 1

Section 1 Sampling Techniques and Data

Criteria Commentary
Sampling techniques A total of 37 additional diamond drill holes drilled at Currawong since the previous Resource
estimate in 2011. An additional 34 diamond drill holes were drilled into Wilga, from both surface and
underground. A total of 13,803.8m of additional drilling has been completed at Currawong and
Wilga as part of the 2011/2012 drilling program. All new holes at Wilga were infill holes. New holes
at Currawong were a mixture of infill and extension drilling with a maximum drill spacing of 25m X
25m. Only diamond drilling has been utilised for Resource estimation at Stockman. Sampling of
mineralised zones waspredominantlyhalf core with a nominal 1m sample length.
Diamond drilling is solely used at Stockman to ensure a high quality of sampling. All sampling and
check sampling is conducted to industry best practice in accordance with IGO QAQC protocols.
The 2010-2012 drilling campaigns included a combination of sawn half-core NQ or quarter-core HQ,
with a typical sample length of 1m. A minimum sample length of 0.15m and maximum sample
length 1.5m in mineralised domains were adjusted to geological boundaries. All massive sulphide
intercepts have been sampled and sampling generally extends 10m into waste rock. All drill core to
be sampled from the Jabiru Metals Ltd (Jabiru) and Independence Group NL (IGO) holes, was
marked up by the geologist. The sampling book was filled out detailing the from and to depths for
each sample, the corresponding sample numbers as well as which standard to insert at which point
and where to insert blank samples. Field technicians cut the core using an Almonte automated core
cutting machine. The core was systematically cut 1cm off the orientation line to allow the orientation
line to remain in the core tray.
JML and IGO samples were cut, dried and pulverised for analysis by 4 acid digest, ICP/OES (Cu,
Pb, Zn, Ag, Fe, S) and fire assay FA/AAS (Au) at and independent laboratory.
Historic sampling involved crushing, with a sub-sample pulverised, followed by three or four acid
digest with AAS or ICP determination. All samples apart from the WMC samples were prepared and
analysed at independent laboratories. WMC and Denehurst did not routinelyanalyse for Au.
Drilling techniques All JML and IGO holes were diamond drilled for the entire hole using a combination of HQ and NQ
core sizes. Historical holes were principally diamond drilling with the exception of several RC
precollars drilled by Denehurst and Austminex. None of the RC samples have been used in the
Resource estimates. The surface diamond drilling is a mixture of HQ, NQ and BQ core sizes, with
BQ occurring only in the older WMC holes. The historic underground holes at Wilga were drilled
LTK46 (Ø=35.6mm).
Drill sample recovery Drill sample recovery is logged and recorded by field technicians and subsequently entered into the
acQuire database. Core sample recovery was good to excellent. Some lost core intervals have
been recorded, particularly where structures such as faults or underground workings (Wilga) were
intersected by the drilling. Theseintervals donot affect theResource estimate.
The diamond drill core is reconstructed in the core yard as part of the orientation process and metre
marks are checked against driller’s depthblocks.
One small area of poor sample recovery at Wilga has been identified and isolated. This area
corresponds with the presence of chalcocite and its classification has been downgraded to Inferred.
Recent core recoveries are reviewed annually to ensure there are no new areas of poor sample
recovery. There is no evidence of bias or preferential loss or gain of material in samples except for
the chalcocite zone mentioned above.
Logging Entire holes were logged and photographed by the various companies completing the drilling
programs. Geological and geotechnical logging is very thorough and more than adequate for
Resource estimation. Logging has previously been on paper logs, which were data entered and
then loaded into the Acquire database. Paper logs were scanned and stored on the IGO Perth
server. Starting In 2011, drillholes have been logged straight into a digital format via AcQuire data
entry objects which were then uploaded directly into the database. AcQuire data entry objects have
built-in rules that allow for validationofdata asitislogged.
Detailed logging routinely consisted of lithology, alteration, mineralisation, veining, structure,
deformation and oxidation state and was recorded using the JML logging codes. JML/IGO core has
been photographed both wet and dry. Historical geological codes were converted to JML codes in
2008.
All drill holes were logged in full.
Sub-sampling
techniques
and sample preparation
Mostly cut half-core samples of NQ, BQ and LTK46, or quarter-core samples of HQ varying in length
up to 1.3m in the massive sulphide and adjusted to geological boundaries. Some quarter-core NQ
samples byAustminex where corewasneededfor metallurgicaltestwork. The JML/IGO drilling
PAGE 60

==> picture [596 x 83] intentionally omitted <==

Criteria Commentary
campaigns included a combination of cut half-core NQ or quarter-core HQ, with a typical sample
length of 1m. A minimum sample length of 0.3m and maximum sample length 1.5m in mineralised
domains were adjusted to geological boundaries. All massive sulphide intercepts have been
sampled and JML/IGO sampling generally extends 10m into waste rock. The samples were routinely
taken fromthe same side ofthe corein relationto the orientation lines.
No non-core samples were taken in the 2010-2012 JML/IGO drilling.
Samples from the 2010-2012 JML/IGO diamond drillholes were sent to Genalysis Adelaide for
sample preparation and analysis. Sample preparation consisted of drying the core for 8 hours at
121°C then jaw crushing to a nominal minus 10mm size. Pulverising then occurred in a LM5
pulverising machine for 5 minutes to 85% passing 75µm. The entire sample undergoes pulverising
in the LM5 machines, resulting in no coarse rejects, only bulk pulp rejects. The sample preparation
technique is normal industry practice and is considered suitable for Stockman samples.
Quality control procedures during JML/IGO sampling included the insertion of certified reference
standards and blanks (1 in 20 samples) as well as the inclusion of barren quartz washes between
every sample.
Historic drilling containedverylittle QAQCwork.
Apart from 62 duplicate samples collected by Macquarie Resources there were no field duplicates
collected prior to the JML/IGO programs. JML/IGO field duplicates were taken during the 2010-
2012 drilling campaigns. In addition, pulp repeats, bulk pulp repeats and cross lab pulp checks
were completed on ~5% of the samples. All these quality control measures confirmed that sampling
and sub-sampling techniques used were appropriate for the style of mineralisation and that samples
were representative of the in situ material.
The sample sizeis considered appropriatefor massive sulphidemineralisation.
Quality of assay data and
laboratory tests
All samples were crushed and a sub-sample pulverised followed by three or four acid digest with
AAS or ICP determination. All samples apart from the WMC samples were prepared and analysed
at independent laboratories. The assay techniques by JML/IGO are for total digestion of the
sulphides and are considered appropriate for this type of mineralisation. For the JML/IGO drill
programs, all samples were assayed at Genalysis Adelaide Laboratory using a 4 acid ore grade
digest with an ICP-OES finish. Au was assayed using a fire assay 50g charge. Lower detection
limits were to 50ppm for Cu,Pb,Zn,1ppm/5ppm for Agand 0.005ppm for Au.
No geophysicalor handheldXRF instrument datawere usedinthisResource estimate.
In comparison with modern requirements, minimal quality control procedures were adopted by
companies completing the drilling programs before JML (eg. inclusion of only 17 field standards, 62
duplicates, 84 external laboratory checks in total). This shortfall was recognised by JML and more
rigorous check sampling programs were implemented. For the JML/IGO drill programs,
comprehensive QAQC programs were completed following company QAQC guidelines, which
include the insertion of standards, blanks, duplicates and cross-lab checks. Results indicate that
sample contamination is kept at a minimum and that assay values are within acceptable accuracy.
In 2011, IGO also implemented particle sizing checks to be completed at the laboratory on 10% of
the samples submitted for assay. These tests were to determine the pulverising quality of the
samples.
Verification of sampling
and assaying
All significant intersections were verified by alternative company personnel. No independent
personnel verified anyintersections.
A total of 10 holes were drilled as twin holes by JML/IGO (4 at Wilga and 6 at Currawong). These
showed that there was no bias between the twin and original holes but they did indicate that the
degree of sulphide development is quite variable even over short distances. Consequently metal
grades are quite variable also.
An acQuire database was used by JML/IGO which includes all drilling information. Data are entered
into the database mainly through acQuire data entry objects which have the required filters and
validation rules built in. Data entry objects with built in validation tables are used to capture collar
information, survey information (single shot), sampling information, geotech, and all geological
logging information. Excel spreadsheets are used to capture downhole survey (multi-shot) data,
surveyed collars and density information. All data entry objects and Excel spreadsheets were sent
to the Database Administrator in Perth for uploading into acQuire. Assays received from
laboratories were imported by the Database Administrator using customised acQuire importers thus
alleviating any data entrymistakes.
No adjustmentsweremade to any assay data usedinthis estimate.
Location of data points Most historic drillhole collar positions were surveyed by licensed or company surveyors. The
JML/IGO (2008-2012) drillhole collar positions were located using RTK GPS equipment with a
horizontal accuracy of +/-10mm and a vertical accuracy of +/-20mm.
Historical drilling includes generally good quality surveys using downhole camera shots at about
30m intervals. Initial JML/IGO downhole surveys were taken by the drillers every 30m using the
ORI-Shot digital camera. The results from the downhole camera were checked at the end of every
hole and prior to uploading into the acQuire database. In addition, at the end of hole, a multi-shot
survey was taken which recorded a reading every 6m. These multi-shot surveys were transferred to
the site geologists digitally at the end ofeveryhole, and thenuploadedinto the acQuire database.
Since2008, alldrillinginformation has beenconvertedinto Stockman RegionalGrid (SRG). This

PAGE 61

==> picture [596 x 83] intentionally omitted <==

Criteria Commentary
grid was created by JML in 2008 and extends over the Currawong and Wilga deposits. All holes
were collarsurveyedin MGA94grid and transformed to SRGin MapInfo using transformationties.
Topographic surface is a DTM created from height measurements collected during an aeromagnetic
survey during 2008. All historical drillhole collars were surveyed by a surveyor and all JML/IGO
drillhole collarswere surveyed upwithan RTKGPSwithanominal height accuracy of +/-20mm.
Data spacing and
distribution
No exploration results areincludedinthisreport.
Diamond drill coverage in the massive sulphide at Wilga and Currawong is on a nominal 25x25m
pattern. In the stringer sulphide lenses of both deposits, drillhole spacing ranges from 25x25m to
50x50m. Minimum hole spacing ~10m and maximum hole spacing ~70m. In general, drillhole
spacing of less than 50x50m is classed as Indicated whereas drillhole spacing greater than this is
classed as Inferred. No part of the Resource at Currawong is classified Measured due to the
nominal required drillhole spacing of 25x25m in the massive sulphide, as well as existence of
multiple generations of drilling. The data spacing and distribution is more than sufficient to establish
geological and grade continuity appropriate for the Mineral Resource estimation procedure and
classificationapplied.
Drillholes were composited to 1m downhole with length and density weighting. Face sampling at
Wilga and recent probe drillholes at Wilga were not used for grade interpolation nor were the down
plungeholes at Currawong.
Orientation of data in
relation to geological
structure
Surface drilling intersects the massive sulphide lenses almost perpendicular to the lens orientation
at both Currawong and Wilga. The underground fan drilling at Wilga has some intercepts that are
almost dip parallel. Some sample bias will occur in the Wilga deposit due to this fan drilling
orientation but most of the affected area has already been mined and is excluded from the Resource
estimate. Two down-plunge or down-dip holes were drilled at Currawong however these were
excluded from the estimate. They were drilled to detect offsetting faults, cross-cutting intrusions and
test the grade continuity along strike. In the Resource estimate they were used solely for geometry
purposes. No down-plunge ordown-dipholeswere drilled atWilga.
Three of the 2012 stringer drillholes at Wilga were drilled at low angles to the mineralisation due to
the lack of more appropriate drilling locations. These holes also do not represent a large volume of
theResource estimate and arenot consideredmaterial.
Sample security Drill core was transported from the drilling site to the Stockman core yard by staff personnel on a
daily basis. All samples are stored in the Stockman core yard which is either manned or locked at
all times. They are then transported to the assay laboratory in Adelaide using Toll IPEC. All
deliveries are tracked using consignment numbers. Once they are received at the laboratory, the
samples arereconciled against the sample despatch.
Audits or reviews The Stockman database was rigorously checked during a data compilation and validation stage in
2008. Since then, routine validation of the database has been conducted in-house.
M Wild (IGO Principal Resource Geologist) completed an onsite review of drilling and sampling
techniques in February, 2012. The procedures in place were considered to be of a suitable
standard for the drilling data to be included in this Resource estimate.
In addition, laboratory audits were completed for the Genalysis Adelaide Laboratory by B Kendall
(IGO Principal Geologist – Advanced Projects) in February 2010, and by M Wild (IGO Principal
Resource Geologist) and K Kitchen (Stockman Senior Project Geologist) on the 29th February,
2012. No major issues were identified during these visits.

Section 2 Reporting of Exploration Results

Criteria Commentary
Mineral tenement and land
tenure status
The Currawong and Wilga deposits are both within MIN5523 held by Stockman Project Pty Ltd, a
wholly owned subsidiary of IGO. There are no native title claims registered over the lease, but an
agreement is in place with a previous claimant group that makes provision for both the previous
claimants and/or other indigenous groups who may assert an interest in the future. The tenement is
located on crown land administered by the Department of Sustainability & Environment. The area is
rugged and heavily forested with no significant heritage sites identified.
The tenure was secure at the time of this report. No significant impediments are believed to exist.
Exploration done by other
parties
Exploration at the Stockman Project was initially carried out by WMC in the early 1970s, WMC
discovered both Currawong and Wilga deposits. Subsequent exploration has been completed by
MacquarieResources,Denehurst,Austminex, JMLandIGO.
Geology Currawong and Wilga are V(H)MS style deposits, occurring as polymetallic (pyrite-sphalerite-
chalcopyrite) massive sulphide lenses with stringer feeder zones within a volcano-sedimentary
succession. Wilga is a single stratabound lens whereas Currawong comprises multiple stratabound
lenses with a series of faults offsetting and stacking the lenses.
Drill hole Information There are no exploration results reported for the immediate Currawong and Wilga areas.
Data aggregation methods There are no exploration results reported for the immediate Currawong and Wilga areas.

PAGE 62

==> picture [596 x 83] intentionally omitted <==

Criteria Commentary
Relationship between
mineralisation widths and
intercept lengths
There are no exploration results reported for the immediate Currawong and Wilga areas.
Diagrams There are no exploration results reported for the immediate Currawong and Wilga areas.
Balanced reporting There are no exploration results reported for the immediate Currawong and Wilga areas.
Other substantive
exploration data
There are no exploration results reported for the immediate Currawong and Wilga areas.
Further work No further work is planned.

Section 3 Estimation and Reporting of Mineral Resources

Criteria Commentary
Database integrity An acQuire database is used by IGO which includes all drilling information. Data are entered into
the database mainly through acQuire data entry objects which have the required filters and
validation rules built in. Data entry objects are used to capture collar information, survey information
(single shot), sampling information, geotech, and all geological logging information.
Excel spreadsheets are used to capture downhole survey (multi-shot) data, surveyed collars and
density information.
All data entry objects and Excel spreadsheets were sent to the JML/IGO Database Administrator in
Perth for uploading into acQuire. Assays received from laboratories were imported by the Database
Administrator using customised acQuire importers thus alleviating any data entry mistakes.
The acQuire database for the Stockman Project is exported to an Access database for Resource
estimation work.
Ongoing data validation checks include visual checks in Surpac of collar, downhole surveys as well
as checks between logging and assays received. Most of the data validations occur during the
importing process and are built in to the acQuire database.
Site visits The competent person for this report, Bruce Kendall (IGO Principal Geologist - Advanced Projects)
was employed at the Stockman Project as Project Manager until January 2012. Whilst at the
Stockman Project, he was closely involved in the planning and management of the drilling
programs. Another site visit by Bruce Kendall was conducted in August 2012, where the Resource
estimate was reviewed. There has been no further drillingsince that date.
Geological interpretation Confidence in the geological interpretation for Wilga is high, with the mineralisation and geological
setting being simple and the availability of underground drilling, mapping and plans confirming the
interpretation. Currawong is more structurally complex and whilst confidence in the geological
interpretation is good, additional drilling and further data review may result in modifications to the
detail of thegeological model,but this is unlikelyto have an impact on the estimate.
Thorough geological logging of all drill holes formed the basis of the geological interpretations.
East-West sections were used to create mineralisation wireframes of both deposits. Several of the
mineralisation wireframes were also constrained by shear planes, particularly at Currawong. At
Wilga, historic backs mapping of development drives has been used to confirm mineralisation
boundaries.
The confidence in the geological interpretation, in particular of the mineralisation domain, is high. All
infill drilling completed has supported the current geological interpretation. It is thought that any
alternative interpretations will not have an impact on this estimate.
Both deposits have been modelled using the massive sulphide as the main geological constraint.
The main factors controlling continuity at Currawong are a series of post-mineralisation faults which
are interpreted as disrupting the lenses. Controls on stringer mineralisation are essentially
independent of the host sequences and lithology was not used to constrain the Resource estimation
for the stringer mineralisation.
At Wilga, minor structures within the massive sulphide have been mapped which affect the
distribution of the high grade copper massive sulphide, otherwise this is a continuous lens. At
Currawong, faulting has controlled the geometry of the Currawong mineralisation. Some stacking
may be the result of early growth faults during the formation of the massive sulphide lenses.
Observed D2 shearing has dislocated many lenses and appears to be responsible for the
termination of some. The extent of the D3 faulting is less certain but is thought to terminate the
down dip portion of some lenses.
Dimensions Currawong (Main Lens) is approximately 300m long, 240m wide (down-dip), up to 35m thick and
located 100-300m below surface. Wilga is about 400m long, 220m wide (down-dip), up to 35m thick
and located 50-150m below surface.

PAGE 63

==> picture [596 x 83] intentionally omitted <==

Criteria Commentary
Estimation and modelling
techniques
Ordinary kriging was used for grade estimation utilising Surpac software (v6.2) for Cu%, Pb%, Zn%,
Fe%, Ag ppm, Au ppm and As ppm. Bulk density values were interpolated as for the other
elements. Search parameters were based on variogram models for each element and density
(variography also completed using Surpac v6.2 software). The various mineralisation wireframes
were intersected with the drillholes in the database and the resulting intervals were written to tables
in the Access database. Density weighted 1m composites were created using the lens coding as the
control with a minimum passing of 50%. Grade estimation was constrained to the massive sulphide
lens and stringer sulphide lens wireframes. At Wilga and Currawong, additional, internal
subdomains of high grade Cu and Zn (Cu>1.2%, Zn>3%) were included in the massive sulphide
lenses. No dilution was included in the Resource models for Wilga or Currawong. Grade
estimation for Au at Wilga may not be reliable due to a paucity of Au assays in the historic sample
data and so Au is classified as Inferred at Wilga. Mild top-cut grades have been used for some
elements where required.
For Currawong, variography was performed on the M Lens massive sulphide (the largest of the
massive sulphide lenses) and the kriging parameters obtained from M Lens variography were
applied to the other massive sulphide and all the subordinate sulphide lenses. This approach was
used as all the massive sulphide lenses are interpreted to be originally part of the same massive
sulphide horizon which has subsequently been structurally disturbed into the different lenses.
Variography for the stringer domain was conducted on the main stringer zone.
For Wilga, variography was conducted on the main massive sulphide lens (most massive sulphide
mineralisation is within the one lens) and the main stringer zone.
Variography was conducted on Cu, Pb, Zn, Ag, Au, As and Fe as well as density.
There is a 10% increase in global tonnage compared with the previous 2011 estimate due to
additional drilling at both deposits. The grades remained consistent with the previous estimate.
No assumptions were made regarding the recovery of by-products.
As part of this estimate, the deleterious element As was estimated along with the economic
elements. Fe was also estimated as it is important from a metallurgical perspective.
Currawong 10mX, 10mY, 10mZ parent cell size as this is approximately ½ the average drill hole
spacing. At Wilga 10mX, 10mY, 5mZ parent cell size was used as this is approximately ½ the
average drill hole spacing. For both deposits, subcelling to 1.25m in all directions was used to
ensure adequate delineation of mineralisation boundaries. The size of the search ellipses was
determined from the variography for each element.
No selective mining units were assumed in this estimate.
Correlation matrices were produced for each separate mineralisation domain. In general, As, Ag,
Au and Pb display good positive correlations in all mineralisation styles. Grades were interpolated
independently into the block model, assuming no correlation with each other, and based on
variography for each element.
The individual massive sulphide and stringer sulphide wireframes were used to code the block
model with a unique identifier. The composite files for each domain were then used to estimate only
the blocks which were attributed the same zone coding.
No cut-off grades have been applied to the massive sulphide outer boundary but cut-off grades were
applied to help delineate the high grade Cu mineralisation (1.2%Cu) and the high grade Zn
mineralisation (3%) within the massive sulphide zones for both deposits. Cut-off grades were also
used to delineate the stringer mineralisation at both Wilga and Currawong. These cut-off grades
were 0.5% Cu or 2% Zn.
Mild top-cut grades have been used for elements where the Co-efficient of Variation was > 1.0. The
top-cut grades were determined from disintegration points on log probability plots. (Currawong
massive sulphide 8% Pb, 10g/t Au, no top-cut for Zn, Ag or Cu; Currawong stringer sulphide 3% Pb,
13.9% Zn, 106g/t Ag, 10g/t Au, no top-cut for Cu; Wilga massive sulphide 26% Cu, 4% Pb, 31% Zn,
110g/t Ag, 2.6g/t Au; Wilga stringer sulphide 15% Cu, 1% Pb, 11% Zn, 120g/t Ag, 0.95g/t Au). A
geological constraint (the massive sulphide zone) has been used as it is stable and will not vary
over time, unlike cut-off grades. Mineralisation within both the massive sulphide and stringer lenses
has been reported.
Initial visual validation was completed by comparing drillhole assays with modelled values. A
comparison was also completed to ensure the volumes of the wireframes closely resembled the
block modelled volumes. The interpolated block grades were compared to the composited sample
data and the declustered sample data(obtained via a nearest neighbour model created in Surpac)

PAGE 64

==> picture [596 x 83] intentionally omitted <==

Criteria Commentary
for each of the lenses by easting and by elevation to check if any model bias has been introduced.
Moisture Tonnages have been estimated using densities some of which were dry (those analysed at external
laboratories) and others that contained natural moisture. The natural moisture of the Stockman
massive sulphides is typically low (<0.5%).
Cut-off parameters No cut-off grades have been applied to the massive sulphide outer boundary but cut-off grades were
applied to help delineate the high grade Cu mineralisation (1.2% Cu) and the high grade Zn
mineralisation (3% Zn) within the massive sulphide zones for both deposits. Cut-off grades were
also used to delineate the stringer mineralisation at both Wilga and Currawong. These cut-off
grades were 0.5% Cu or 2% Zn.
Mining factors or
assumptions
Mining of the Currawong and Wilga deposits is planned to occur using underground mechanised
mining techniques.
No assumptions regarding minimum mining width or dilution have been made. The Resource
estimate is undiluted.
Metallurgical factors or
assumptions
A detailed metallurgical testwork program has been completed using samples from drill holes drilled
during the period 2008-2011. Results indicate all styles of mineralisation are amenable to being
recovered by flotation with no issues apparent due to deleterious elements.
Environmental factors or
assumptions
Investigations are ongoing into suitable waste and tailings disposal options for the Stockman
Project. A preferred option for both tailings and waste was selected as part of the Feasibility Study.
Although these are yet to be approved by the regulating authorities, they have been fully informed of
the preferred option.
Bulk density Many samples had measured densities using either water immersion or air pycnometer techniques.
All JML/IGO samples were measured for density using water immersion techniques. For those
samples with no density measurement, a calculated density was applied to the sample. The assays
for Cu, Pb, Zn and Fe were compared with the measured densities and a second power regression
curve developed for each deposit and for each mineralisation style. Densities were used in the
sample compositing. Tonnages have been estimated using densities some of which were dry
(those analysed at external laboratories) and others that contained natural moisture, expected to be
<1%.
No samples were sealed prior to bulk density determination due to low porosity in the mineralised
zones.
Density was kriged into the block model in a similar method as was used for all other elements.
However, a density regression formula was required in order to assign densities to historical
samples which did not already have a density measurement. This was achieved in excel by
ascertaining a multi element regression formula based on the existing assays and their
corresponding measured densities.
Classification Classification was based on sample density and confidence in the geometry of the lenses. All of the
major massive sulphide lenses in both deposits were classified as Indicated. Stringer sulphide was
classified as Indicated or Inferred or sometimes left as Unclassified if there is limited repeatability
across sections. Generally, where the sample density was 50x50m or less the Resource was
classified as Indicated, where the spacing was greater than 50x50m the Resource was classified as
Inferred. The Au grades at Wilga are considered Inferred due to a paucity of gold assays in the
historic drilling data.
The classification has taken into account the quality, quantity and distribution of the input data. In
addition, the high confidence in the geological interpretation and modelling parameters were taken
into account.
The Mineral Resource estimate reflects the Competent Person’s view of the Currawong and Wilga
deposits.
Audits or reviews No audits or reviews have been completed on this particular Mineral Resource Estimate. The
previous estimate (2011) was reviewed by Cube Consulting Pty Ltd and several recommendations
were implemented in this update. No significant issues were identified.
Discussion of relative
accuracy/confidence
The 2009 and 2011 Resource estimates were independently reviewed and the classification and
Resource estimation method of Ordinary Kriging were deemed to be appropriate. The same
estimation methods including recommendations made during previous reviews were implemented in
this Resource estimation. The 2012 Mineral Resource estimate correlates well with previous
Resource estimates.
There are no known significant factors that might impact the accuracy and confidence of the
estimate. Mineralisation has been classified as Indicated and Inferred. No mineralisation has been
classified as Measured.
PAGE 65

==> picture [596 x 83] intentionally omitted <==

Criteria Commentary
The statement relates to global estimates of tonnes and grade.
No production data are available for Currawong as it has not been mined previously.
There is a slight discrepancy between the historic total reported tonnes mined at Wilga (956kt) and
the calculated tonnes mined using the volumes of underground void models (802kt), with the
reported tonnes being greater. During 2012, Wilga was re-opened and all voids above the current
water table checked to see if the wireframes were accurate. Below the water table several holes
were drilled to test for the presence of voids which were not indicated by the void wireframes, in
areas of high grade. Although some discrepancies were identified they do not entirely account for
the difference. The difference, since revision of the void model after probe drilling and access to the
underground workings down to the water table, is 154kt, only 4.2% of the Wilga Resource tonnage.
This Mineral Resource estimate assumes the void model as being correct and the Resource model
was depleted accordingly.
Resource Model Numbers CU_RSC_2012_07 and WG_RSC_2012_07

Section 4 Estimation and Reporting of Ore Reserves

Criteria Commentary
Mineral Resource estimate
for conversion to Ore
Reserves
Mineral Resource estimates were created using Ordinary Kriging. Variography was completed on
Cu, Pb, Zn, Fe, Ag, As, Au and density.
The Mineral Resource estimate was completed in June 2012 and covers both Wilga and Currawong
deposits and has remained unchanged.
This Ore Reserve was derived from Resource block model currawong_2012.mdl and Resource
block model wilga_2012.mdl.
The Mineral Resources reported are inclusive of the Ore Reserves.
Site visits The site was visited by Mr Geoff Davidson in August 2008. During the site visit diamond drill core for
Currawong was inspected, visits were made to the existing Tailings Storage Facility (TSF) of Lake
St Barbara, the old plant site at Waxlip spur, existing Wilga portal and site of the proposed
Currawong portal.
Study status This Ore Reserve was based on designs and estimates consistent with a detailed Feasibility Study.
The costs were derived from Vendor estimates specific to the project and are considered to be
within +/- 15% order of accuracy.
A detailed mine plan was developed from which a practical mining schedule was determined.
Standard modifying factors associated with the selected mining method have been applied. The
mining method will use long hole stoping techniques to recover economic mineralisation. Amongst
others, the study included geotechnical analysis of the mine openings and detailed analysis and
design of the paste backfill and its application in the mining method.
Cut-off parameters The Net Smelter Return (NSR) method was used to determine the economic cut-off for the
mineralisation. The NSR values were calculated on a ‘mine gate’ sale basis and incorporate metal
pricing current at the time. The NSR value was adjusted for transport costs, port handling charges
and TC/RC on all payable metals. Payable metals are copper, zinc, gold and silver.
The cut-off NSR value was determined from the site operating costs including mining, processing
and site administration and overhead costs. The cut-off was estimated to be between $97 and $105
per tonne processed. An incremental cut-off of $60 per tonne was also estimated as a subset of
these costs and represented the minimum value of material economic to process once delivered to
the surface stockpile. The incremental NSR cut-off was applied to ore drive development to
determine its inclusion in the Ore Reserve estimate.
Mining factors or
assumptions
The Ore Reserve was determined by digitising practical stope wireframes around contiguous blocks
of Indicated material above the NSR cut-off value. The wireframes include a nominal 0.5 m of
unplanned mining dilution from over-break. An additional 2% dilution was included for all stopes due
to fall off from paste walls. A further 2% dilution allowance was applied to secondary stopes which
will have more than one exposed wall of paste backfill during mining. A nominal 5% ore loss was
applied to account for losses such as under-break, unrecovered bridges and toe, ore lost due to
excessive dilution from fall dirt. In addition, any development, such as ore drives, outside the stope
wireframes, which reported an average value above an incremental NSR cut-off of $60 per tonne,
were also included in the Reserve.
The Ore Reserves for both Currawong and Wilga were determined on the basis of long hole open
stoping using cemented paste backfill. This mining method and associated parameters used to
estimate the Ore Reserve were deemed to be appropriate for the nature andgeometryof the

PAGE 66

==> picture [596 x 83] intentionally omitted <==

Criteria Commentary
deposits at Currawong and Wilga.
Stope spans and other ground support requirements were based on analysis conducted by
geotechnical consultants Mining One Pty Ltd. Grade control methods would entail methods used by
Independence Group NL (IGO) at their existing operations in WA and will include stope definition
diamond drilling, face and stockpile sampling.
The Mineral Resource model was originally prepared and reported by IGO geologists in accordance
with the JORC Code (2004), and the report was recently updated to comply with the JORC Code
(2012) reporting requirements. Ordinary Kriging was used to estimate the grade of key elements
such as Cu, Zn, Au, Ag, Pb and Fe within wireframe constraints.
Sufficient detailed analysis was carried out to provide confidence in key assumptions such as
stability of stope spans and mining rate. Recent testwork of the paste backfill using cycloned tailings
to remove the ultrafine fraction of the tailings stream has demonstrated over time (260 days) that a
number of 4% binder mixes can achieve acceptable early strengths, good long terms strengths with
no signs to date of fill degradation. The final tests were at 365 days and were due in February 2015.
The total dilution (planned plus unplanned) included in the stope wireframes was estimated to be
14% at grades reported from the Mineral Resource model and within the diluted stope wireframe
envelopes. The mining method requires total extraction within the stoping envelope; therefore, no
losses will occur from sterilisation of ore in pillars. A nominal 5% ore loss was applied for reasons as
described above. An approximate minimum mining width of 3 m (true width) was used when
creating the stope wireframes.
The underground capital infrastructure will include decline access and primary ventilation shafts and
tunnels as well as services infrastructure such as electrical distribution, air and water reticulation,
dewatering facilities, communications, and workforce refuge chambers. In addition, a backfill paste
plant will need to be constructed and paste reticulated throughout the stoping areas of the
Currawong mine. At Wilga, tailings filter cake will be trucked to from Currawong to a surface
stockpile adjacent to the Wilga portal where it will be used to produce paste on surface, then
pumped into the mine and reticulated throughout the workings.
The Ore Reserve estimate includes Inferred and unclassified material in the form of mining dilution
estimated to be approximately 780,000 t at 0.31 Cu%, 1.0 Zn%, 5.2 g/t Ag and 0.1 g/t Au.
The Wilga Ore Reserve was derived from the Indicated Mineral Resource. The Indicated
classification was based on the confidence in copper, zinc and silver grades; however, gold grades
within these blocks were considered to be Inferred due to a paucity of gold assays in historic drilling.
Revenue from gold in the Wilga ore was included in the estimation of the Ore Reserve. The
contribution to Revenue of this gold was estimated to be $8.65 per gram of gold in situ and within
the mining envelope. This was not material to the value of the mining envelopes considered and did
not warrant downgrading of any portion of the Ore Reserve attributable to Wilga. The tonnage
contribution from Wilga represents 18% of the total Ore Reserve tonnage.
Metallurgical factors or
assumptions
The metallurgical process will use differential flotation to produce separate concentrates of copper
and zinc minerals.
The method is commonly used throughout the world for the style of mineralisation that exists at
Stockman and is currently being used at IGO’s Jaguar operations.
Numerous composite samples have undergone batch testing. The samples tested were selected
from different geological domains from both Currawong and Wilga deposits. Geo-metallurgical
algorithms were developed for the mineralisation at Stockman; therefore, recoveries vary depending
on the combination of minerals present in the feed at any increment in time.
The life of mine average recoveries for copper concentrate were as follows:

Copper = 81.5%

Silver = 40.7%

Gold = 20.4%
The life of mine average recoveries for zinc concentrate were as follows:

Zinc = 76.4 %

Silver = 18.5%
Metallurgical test work demonstrated that marketable concentrates of both copper and zinc can be
produced from both deposits. Marketable electrolytic grade zinc concentrates are produced from
both deposits when treating lower lead grade feeds (<1% Pb). Arsenic is low (<0.25%), iron is
acceptable (8-10%), lead relatively low (<2%) and silica is also acceptable (<1.5%).

PAGE 67

==> picture [596 x 83] intentionally omitted <==

Criteria Commentary
The penalty element assays were generally low, but where slightly elevated, remained in the
negotiable range for settlement. Deductions for penalty elements were applied in the cash flow
model in the periods where threshold values were exceeded. The life of mine estimated cost of
penalties represents < 1% of the project operating cost.
Locked cycle tests, which are designed to simulate a continuous and stable condition of the
proposed flotation process, were conducted on a range of composited samples considered to be
representative of the various types of mineralisation, including a blend representative of the first 5
years production. Locked cycle test results by previous owners observed similar results to those
conducted by IGO.
Bulk flotation testwork was carried out on ten 50 kg samples as part of the 2014 Optimisation Study.
The testwork demonstrated the geo-metallurgical algorithms to be reliable.
Economic concentrations of minerals were defined by their intrinsic value derived through
beneficiation to produce concentrates within marketable specifications. The commercial value was
determined through the application of an economic cut-off, as described above. No other
mineralogical specifications were applied in determining the Ore Reserve however charges were
applied to the concentrate product where the estimated level of penalty elements exceeded
threshold levels. These penalty elements included zinc and lead for copper concentrate and iron for
zinc concentrate.
Environmental No permanent waste rock landforms will be created during operations. All material determined to be
potential acid forming (PAF) or containing soluble metals will be either returned underground as
backfill for workings or disposed of sub-aqueously in the tailings storage facility (TSF).
Tailings produced from on-site processing will be either returned to the underground workings as
backfill or disposed of in an approved TSF. The existing decommissioned TSF will be reinstated to
accept the tailings from operations. The proposed TSF has been designed in accordance with the
Australian National Committee on Large Dams (ANCOLD) guidelines. Detailed geotechnical and
hydrogeological assessment of the proposed TSF impoundment is still to be carried out to validate
the design parameters. No material changes to the design parameters are anticipated.
Water produced from dewatering the underground workings will be treated and recycled for use in
the mining or processing operations. Surplus water will be discharged into the TSF.
An Environment Effects Statement (EES) was compiled as a requirement of the Victorian state
government project approval process. The project also triggers Commonwealth assessment which
utilises the Victorian EES via a State-Federal bilateral agreement. The EES prepared for the
Stockman base metals project provides a comprehensive and integrated assessment of the
potential environmental, social and economic impacts of project implementation. Technical studies
conducted for the project provided confidence that the project can be implemented in a way that is
consistent with relevant Victorian and Commonwealth government environmental and social policy
objectives.
Project licensing and approval, including permitting of the TSF is subject to a favourable
assessment by the Victorian Minister for Planning of the EES and approval by the federal
Environment Minister under the EPBC Act. The Victorian Minister for Planning has provided a
positive assessment of the EES and associated Inquiry Panel report. The approval process by the
federal Environment Minister is still in progress.
There are no known impediments to the outstanding portions of the approval process; however, the
review and approval process is still in progress and project development will be subject to the
conditions placed on the project by respective regulators.
Infrastructure The project will be supported by limited existing infrastructure. The project is currently serviced by
an existing access road which will be upgraded to accommodate increased traffic and concentrate
transport. Telecommunications are available within the wider area which will need to be upgraded to
bring these services to the site. Power will be generated on site using natural gas sourced from the
Victorian natural gas infrastructure. Water balance modelling has indicated the project will have a
near neutral requirement for supplementary water; however, contingent sources of groundwater
have been identified beneath the Benambra plains and various locations adjacent to the site access
road. The availability of labour is limited in the immediate area and an accommodation village will be
constructed to house a drive-in drive-out workforce with most personnel expected to commute from
regional population centres.
IGO currently holds the mining lease on which the Stockman project is located (MIN5523). Land
access to other support infrastructure is the subject of various draft agreements and Memoranda of
Understanding (MOU’s) with respective land holders. The site for the TSF is currently located within
an Exploration Exemption area and application to have this lifted will be subject to approval of the
proposed facility by state and federal regulators. Any new tenement covering the current Exploration
Exemption area,ifgranted,would be as a separate tenement to MIN5523. There are no known

PAGE 68

==> picture [596 x 83] intentionally omitted <==

Criteria Commentary
impediments to the granting of this license.
Costs Capital costs for the project were based on 2014 budget quotations provided by potential vendors
based on design and scope specific to the project. Where vendor quotations were not available, cost
estimates were provided by consultants with expertise in their specific field or were built-up from first
principals based on IGO operational experience or sourced internally from the IGO existing
operations.
Mining capital and operating costs were estimated from first principals using vendor quotations for
materials and equipment running costs. Productivities were based on internal industry experience.
Labour costs were based on an assessment of similar mining projects within Victoria.
Provision was made within the cash flow analysis for the penalties applied to deleterious elements in
excess of the limits proposed by independent metal traders.
Road transport costs and port handling charges were based on vendor quotations specifically for the
project scope of work. A number of export port options are available; however, the costs used
contemplated export via Port Anthony. Sea freight charges were based on market assessment by
logistics consultants with expertise in this industry.
Treatment charges, refining costs and element penalties were based on forecasts provided by
recognised market analysts.
Victorian government standard state royalties were applied to Copper, Zinc and Silver. No royalty
was applied to Gold. Under Part 2, Section 7 of the Mineral Resources Development Regulations
2002, State royalties do not apply to gold.
No third party royalties are applicable to this project.
Revenue factors The project head grade was determined on a month by month basis from a detailed schedule of
mining of the Ore Reserve. The schedule incorporated a logical development and extraction
sequence of the Ore Reserve and utilised productivity rates considered to be typical of the
Australian mining industry.
Provision was made within the cash flow analysis for the penalties applied to deleterious elements in
excess of the limits proposed by independent metal traders.
Transport costs, port handling charges and sea freight charges have been discussed in the section
on Costs.
Smelter recoveries, treatment charges, refining costs and element penalties were based on budget
quotations provided by recognised metal traders and were in line with standard contracts for copper
and zinc concentrates. Consideration was also given to existing contracts in place at the IGO’s
Jaguar operations.
The commodity prices and exchange rates used for the cash flow model were applied as real pricing
and were based on forecast pricing provided by recognised market analysts. The project is therefore
leveraged to the rising future zinc price forecast by most industry analysts.
The average Life of Mine metal prices and foreign exchange rate used in the cash flow model
included the following:

Copper $US 6,591 per tonne of copper metal

Zinc $US 2,979 per tonne of zinc metal

Gold $US 1,146 per ounce troy of gold

Silver $US 20.17 per ounce troy of silver

Exchangerate of$0.84$AU per$US
The cash flow was modelled in real terms and no price or cost escalation was applied.
Market assessment In its September 2014 “Q3 2014 Global copper long-term outlook”, Wood Mackenzie forecast the
need for a long-term incentive price of US$3.50/lb Cu (in 2014 dollars) to encourage sufficient
investment in mine capacity to ensure the market does not slip into structural deficit. This equates to
a tonnage price of US$7,700/t Cu (in 2014 dollars).
In its September 2014 “Q3 2014 Global zinc long-term outlook”, Wood Mackenzie forecast the need
for a long-term incentive price to encourage mine development to address market deficits. For the
period between 2013 to 2035 Wood Mackenzie have forecast the price to average
US$2997/t (in 2014 dollars).

PAGE 69

==> picture [596 x 83] intentionally omitted <==

Criteria Commentary
Economic A detailed cash flow model was created using the design case commodity pricing described above.
The cash flow included detailed schedule of Capital and Operating cost expenditures for each of the
project cost centres. Revenue from product sales were modelled by shipment with 90% payable in
the month of loading and the balance paid the following month. Typical off take contracts were
incorporated in the cash flow and were based on input parameters determined by recognised
market analysts. The cash flow was modelled in real terms, hence no price or cost escalation was
applied. A discount rate of 10% was applied to determine a Net Present Value (NPV) from the
project cash flow.
The cash flow analysis demonstrated a positive return for the project with a pre-tax internal rate of
return of 25%.
Input costs were considered to be accurate to within +/- 15%. Costs were taken either directly from
vendor quotes or consultant estimates for specific scopes of work. Mining costs were developed
from first principals on an owner operator basis.
Various sensitivity analyses were carried out on the cash flow model. Key parameters were varied
by +/- 15%. These parameters included process plant feed grade, capital and operating costs,
metal prices, foreign exchange rate. The results were evaluated on the basis of pre-tax NPV. All
parameters tested returned a positive NPV over the range.
Social There are currently no Native Title claims or determinations over the Stockman project area. A
license for the mining lease has been granted.
A program of community engagement has been undertaken and will continue through the life cycle
of the project. This has included the establishment of a “shop front” to facilitate two-way
communications with the public. No material objections to the project have been received
throughout the community engagement process and the general consensus is one of positive
economic benefit to the local community.
An MOU has been executed between IGO and the East Gippsland Shire Council. The MOU
commits both parties to working in collaboration to identify and progress opportunities that will
deliver social and economic development benefits for the region whilst, through endeavouring to
maximise the efficiency and robustness of the project’s operations, not compromising or placing an
unnecessary financial burden on IGO as a company with obligations to its shareholders.
Other IGO currently holds the mining lease on which the Stockman project is located. Land access to
other support infrastructure is the subject of various draft agreements and MOU’s with respective
land holders.
The site for the proposed TSF is currently located in an Exploration Exemption area. An agreement
to access the area for the purposes of confirmatory site investigation works is currently being sought
from the state government. The state government has acknowledged the need to access the site
without transferring liability of the facility; however, details are still to be finalised. The project
sanction will be contingent on confirming the site conditions and the proposed tailings management
strategy. An application for an Infrastructure Mining License will be made following project sanction
by IGO. There are no known impediments to the granting of this license.
The project is located in state forest and prone to bushfires. Analysis of the risk has been
undertaken by independent consultants WSP and mitigation measures recommended including the
establishment of fire protection zones and fire-resistant construction materials. In addition,
procedures and training for bushfire events will be implemented as part of the project Work Plan and
procedures.
Land access agreements and MOU’s for required external infrastructure have been tabled in draft
form to the following stakeholders:

Local pastoralist for land access to the Stockman Village site and a potential borefield
site.

East Gippsland Shire Council for road improvements and maintenance, land (road verge)
accessfora potentialborefield pipeline andhigh voltage underground powercable.
The project will require vegetation offsets for ground required to be disturbed for construction and
mining. These offsets have largely been identified and secured in part or subject to a draft heads of
agreement with existing land holders. There are no known impediments to securing the final
calculated offsets required for the project.
The Victorian Minister for Planning’s positive assessment of the Stockman Environmental Effects
Statement (EES) and Inquiry Panel report was released on 30 October 2014. The Minister’s
Assessment contains no unexpected conditions that are material to the project. The specific detail of
the various licenses that are required for project operations will now be scoped and agreed with
Government agencies. It is expected that detailed licensing will take approximately 12 months.
The Victorian Minister for Planning’s assessment report was alsoprovided at the same time to the
PAGE 70

==> picture [596 x 83] intentionally omitted <==

Criteria Commentary
Commonwealth Minister for Environment for his consideration under the Environment Protection
and Biodiversity Conservation (EPBC) Act. The Federal decision is expected to be announced by
early 2015, and no significant issues are foreseen.
There are currently no unresolved matters with third parties.
Classification The Ore Reserve was classified in accordance with the guidelines in the JORC Code (2012).
Standard modifying factors and conversions were applied as described above. The Currawong
portion of the Ore Reserve comprised approximately 95% Indicated Mineral Resource with the
balance comprising dilution from Inferred and unclassified material. The Wilga portion of the Ore
Reserve comprised approximately 85% Indicated Mineral Resource with the balance comprising
dilution from Inferred and unclassified material. The Ore Reserve estimate includes Inferred and
unclassified material in the form of mining dilution estimated to be approximately 780,000 t at 0.31
Cu%, 1.0 Zn%, 5.2 g/t Ag and 0.1 g/t Au. Given these proportions and the manner in which the
modifying factors were applied, the entire estimate was classified at Probable Ore Reserve. No
known conditions or issues existed that warranted downgrading of this classification.
Gold (Au) grades are Inferred at Wilga due to a paucity of gold assays in historic drilling.
The Ore Reserve estimation and classification methods used were considered by the Competent
Person to be appropriate for the style and nature of the deposit.
Audits or reviews The Ore Reserve estimate has been subject to internal peer review.
Discussion
of
relative
accuracy/confidence
The Ore Reserve is a global estimate derived from the global Stockman Mineral Resource.
The Stockman Ore Reserve was classified as Probable only and includes Mineral Resources largely
classified as Indicated with the balance comprising either Inferred or unclassified material
incorporated as mining dilution. No downgrading was applied to economic material within the mining
envelope. The accuracy of the Ore Reserve is reflected in the classification of the Ore Reserve and
the classification of the underlying Mineral Resources upon which it is based.
A sensitivity analysis was conducted on the cash flow model over a +/-20% range of variability of
key parameters including copper and zinc grade, capital and operating cost, copper and zinc price
and exchange rate. The results were evaluated on the basis of pre-tax cash flow. All parameters
tested returned a positive pre-tax cash flow over the range.
The nature of the deposit is such that the economic mining envelope is dependent on metal price
and foreign exchange assumptions. Material changes in price assumptions could alter the outcome
of the Ore Reserve estimate.
Discrepancy exists between the historical tonnes reported as mined at Wilga (about 956 kt) and
those accounted for in current digital wireframe of the workings (about 802 kt).The reason for the
discrepancy remains unclear and reconciliation between the digital model and the actual mined
areas is ongoing, subject to further drilling or access to areas of the workings that are currently
flooded. This discrepancy represents <2% of the Ore Reserve and was not considered material to
the viability of the project.
Gold (Au) grades are classified as Inferred at Wilga due to a paucity of gold assays in historic
drilling.
Vendor quotation used in the cost estimates were requested on the basis of +/-10% to 15%
accuracy.
Revenue assumptions were based on real forward-pricing calculated by combining Consensus
forecasts (sourced from eight separate banks &/or research firms) and Wood Mackenzie forecasts.
Forecast periods varied across the sources, ranging from two years to eight years. Where the
project life exceeded a reasonable number of available forecasts, the last period price was held
constant (or “flat-lined”) in the cash flow model to the end of the project.
The Life of Mine (LoM) average forward copper pricing (US$6,591/t) is 11% below the September
2014 long term forecast copper pricing by Wood Mackenzie which covers the mine production
period (US$7,446/t).
The LoM average forward zinc pricing (US$2,979/t) is 1% below the September 2014 long term
forecast zinc pricing by Wood Mackenzie which covers the mine production period (US$3,020/t).
The foreign exchange rate used the IGO-derived consensus rate calculated by combining forecasts
from three separate bank &/or research firm’s forecasts. As with the copper and zinc pricing, the
foreign exchange rate was flat-lined from the last period forecast to the end of the project.
Reserve Model Number SM_OS_RSV_2014_11

PAGE 71